[Contract No.

DJT/RJP

INTERIM PAYMENT CERTIFICATE ( IPC ) NO. 42


PERIOD ENDING March 27, 2014

Contractor: M/S Nishan Engineers (Pvt) Ltd Consultants

1 Date of Award 13-May-11


2 Start Date 27-May-11
3 Original Contract Price including Provisional Sums 430,680,
4 Amount of Approved Variation Orders -7697696.28931
5 Amount/No. of VOs under process
6 Revised Contract Price (3+4) 422,982,
7 Completion Period (Days) 480
8 Original Contract Completion Date (2+7) 18-Sep-12
9 Extension granted (Days) 559
10 Revised Completion Date (8+9) 31-Mar-14

Amount
Sr. Upto Previous
Description Up to Date
No. Certificate
Rs.
Rs.
1 Value of Executed Permanent works @ B.O.Q. rates 409,499,348.20 409,499,348.20
2 Value of Executed work as per Approved Variation Orders - -
3 Price Variation of Specified Materials. 71,447,443.90 68,950,827.48
4 Sub-total (1+2+3) 480,946,792.10 478,450,175.68
5 13.116% Bid Discount on Sr. No.1 53,709,934.49 53,709,934.49
6 Sub-total after bid discount (4-5) 427,236,857.61 424,740,241.19
7 With-held amount as per clause 47-A - -
7(a) Other amount(s) with-held
8 Sub-Total (6-7-7a) 427,236,857.61 424,740,241.19
ADVANCE PAYMENTS
9 Mobilization Advance 59,217,696.00 59,217,696.00
Secured Advance on Materials brought at site.
10 - -
(working attached)
DEDUCTIONS:-
11 Security Deposits/Retention Money (See Attachment-I) 18,039,470.69 18,039,470.69
12 Repayment of Mobilization Advance. 59,217,696.00 59,217,696.00
13 Recovery of Secured Advance. - -
14 Income Tax @ 6% 26,167,170.73 25,844,490.60
Deductions on account of compensation for delay in LD
15 - -
(if any)
Total Amount Certified 383,030,216.20 380,856,279.91
Deduction against Performance Security @ 05 %
16 11,463,866.45 11,463,866.45
of the due amount (Refer. GCC Clause 7)
NET CERTIFIED AMOUNT 371,566,349.75 369,392,413.46
Verified & Certified by:-

Seal/Stamp
Resident Engineer - PISIP
file:///conversion/tmp/scratch/422266737.xlsx
IPC Form-2
Date: ----------------------------------------------------

file:///conversion/tmp/scratch/422266737.xlsx
IPC Form-2
[Contract No. DJT/RJP-01]

AYMENT CERTIFICATE ( IPC ) NO. 42


ERIOD ENDING March 27, 2014

Consultants: PISIP

13-May-11
27-May-11
430,680,365
-7697696.28931414

422,982,669

18-Sep-12

31-Mar-14

Amount
Due this
Certificate
Rs.
-
-
2,496,616.42
2,496,616.42
-
2,496,616.42
-

2,496,616.42

-
-
-
322,680.13

2,173,936.29

2,173,936.29

file:///conversion/tmp/scratch/422266737.xlsx
IPC Form-2
Date: ----------------------------------------------------

file:///conversion/tmp/scratch/422266737.xlsx
IPC Form-2
PUNJAB IRRIGATION SYSTEM IMPROVEMENT PROJECT (PISIP)
CONTRACT PACKAGE: DJT/RJP-01
SUMMARY IPC WISE
Variation in Prices of Specified Materials
(Ref: GCC Clause 55 Escalation)

CALCULATED PRICE REVISED BALANCED PRICE


Sr. No. IPC No PAID ESCALATION
ESCALATION ESCALATION ESCALATION

1 IPC-03 743,981.38
2 IPC-04 671,166.34
3 IPC-05 661,247.73
4 IPC-07 879,032.37
5 IPC-09 846,086.59
6 IPC-11 959,840.32
7 IPC-13 1,087,129.94
8 IPC-15 4,705,946.35
9 IPC-17 3,178,086.98
10 IPC-19 2,818,694.29
11 IPC-21 4,515,780.11
12 IPC-23 3,414,955.00
13 IPC-25 2,632,998.81
14 IPC-27 3,198,844.91
15 IPC-29 3,208,330.38
16 IPC-31 6,070,805.83
17 IPC-33 5,839,735.72
18 IPC-35 6,337,308.78
19 IPC-37 5,817,009.41
20 IPC-39 8,482,460.57
21 IPC-41 2,881,385.67
22 Final Bill 2,496,616.42 2,496,616.42
Total Payable 2,496,616.42 68,950,827.48 2,496,616.42
Total Payable upto Date (Previous+Balance) Rs. 71,447,443.90
Contractor Executive Engineer Resident Engineer
M/S Nishan Engineers Rajanpur Canal Division Rajanpur PISIP Rajanpur
MONTHWISE STATEMENT OF QUANTITIES AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Material Disty/Minors Item Mar-14 Total Mar-14 Total

Cement Kousar Disty 1.5" thick Plaster 1:6 -21.002 -21.002 -19.953 -19.953

1L Kousar Minor 1.5" thick Plaster 1:6 132.105 132.105 205.395 205.395

Noushera Disty 1.5" thick Plaster 1:6 2.774 2.774 4.666 4.666

1R Noushera Minor 1.5" thick Plaster 1:6 -3.922 -3.922 -7.130 -7.130

1L Noushera Minor 1.5" thick Plaster 1:6 -9.951 -9.951 -18.667 -18.667

Zam Zam Disty 1.5" thick Plaster 1:6 0.000 0.000 -0.098 -0.098

Patwali Minor 1.5" thick Plaster 1:6 -13.595 -13.595 -24.213 -24.213

1L Zam Zam Minor 1.5" thick Plaster 1:6 29.751 29.751 50.783 50.783

1R Zam Zam Minor 1.5" thick Plaster 1:6 0.956 0.956 1.678 1.678

Islampur Disty 1.5" thick Plaster 1:6 59.729 59.729 64.170 64.170

Malkani Minor 1.5" thick Plaster 1:6 -8.213 -8.213 -13.166 -13.166

Abe Hayat Disty 1.5" thick Plaster 1:6 64.553 64.553 -8.850 -8.850

Hajipur Disty 1.5" thick Plaster 1:6 0.000 0.000 -0.150 -0.150

1R Hajipur Minor 1.5" thick Plaster 1:6 -4.120 -4.120 -7.286 -7.286

2R Hajipur Minor 1.5" thick Plaster 1:6 1.932 1.932 4.403 4.403

Kousar Disty 1/2" thick Plaster 1:5 1.640 1.640 0.000

1L Kousar Minor 3/4" thick Plaster 1:3 0.690 0.690 0.000

1R Zam Zam Minor 3/4" thick Plaster 1:3 1.240 1.240 0.000

Islampur Disty 3/4" thick Plaster 1:3 1.240 1.240 0.000

Abe Hayat Disty 3/4" thick Plaster 1:3 1.240 1.240 0.000

1R Hajipur Minor 3/4" thick Plaster 1:3 0.690 0.690 0.000

2R Hajipur Minor 3/4" thick Plaster 1:3 1.240 1.240 0.000

Kousar Disty 1/2" thick Plaster 1:4 3.600 3.600 0.000

Islampur Disty 1/2" thick Plaster 1:4 3.600 3.600 0.000

Abe Hayat Disty 1/2" thick Plaster 1:4 3.600 3.600 0.000

Hajipur Disty 1/2" thick Plaster 1:4 3.600 3.600 0.000

Kousar Disty Pointing 1:2 12.460 12.460 0.000

Islampur Disty Pointing 1:2 12.460 12.460 0.000

Abe Hayat Disty Pointing 1:2 12.460 12.460 0.000

Hajipur Disty Pointing 1:2 12.460 12.460 0.000

Kousar Disty C/S Mortor 1:3 4.100 4.100 0.000

Kousar Disty 1.5" Toping of C/C 1:2:4 5.475 5.475 0.000


MONTHWISE STATEMENT OF QUANTITIES AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Material Disty/Minors Item Mar-14 Total Mar-14 Total

Islampur Disty 1.5" Toping of C/C 1:2:4 1.687 1.687 0.000

Abe Hayat Disty 1.5" Toping of C/C 1:2:4 1.687 1.687 0.000

Hajipur Disty 1.5" Toping of C/C 1:2:4 1.687 1.687 0.000

Kousar Disty 1.5" DPC 1:2:4 0.126 0.126 0.000

Islampur Disty 1.5" DPC 1:2:4 0.450 0.450 0.000

Abe Hayat Disty 1.5" DPC 1:2:4 0.450 0.450 0.000

Kousar Disty P.C.C 1:2:4 10.930 10.930 -5.730 -5.730

1L Kousar Minor P.C.C 1:2:4 36.061 36.061 56.054 56.054

Noushera Disty P.C.C 1:2:4 8.313 8.313 0.598 0.598

1R Noushera Minor P.C.C 1:2:4 -0.447 -0.447 -2.068 -2.068

1L Noushera Minor P.C.C 1:2:4 -2.379 -2.379 -5.326 -5.326

Zam Zam Disty P.C.C 1:2:4 21.475 21.475 -0.901 -0.901

Patwali Minor P.C.C 1:2:4 -3.229 -3.229 -6.974 -6.974

1L Zam Zam Minor P.C.C 1:2:4 10.908 10.908 13.521 13.521

1R Zam Zam Minor P.C.C 1:2:4 3.947 3.947 -0.130 -0.130

Islampur Disty P.C.C 1:2:4 16.930 16.930 16.826 16.826

Malkani Minor P.C.C 1:2:4 2.221 2.221 -4.135 -4.135

Abe Hayat Disty P.C.C 1:2:4 43.519 43.519 -3.496 -3.496

Hajipur Disty P.C.C 1:2:4 20.244 20.244 -1.271 -1.271

1R Hajipur Minor P.C.C 1:2:4 -1.473 -1.473 -2.816 -2.816

1L Hajipur Minor P.C.C 1:2:4 0.460 0.460 0.000 0.000

2R Hajipur Minor P.C.C 1:2:4 5.599 5.599 0.444 0.444

Kousar Disty P.C.C 1:4:8 1.520 1.520 0.000

1L Kousar Minor P.C.C 1:4:8 1.520 1.520 0.000

Noushera Disty P.C.C 1:4:8 1.916 1.916 0.000

1R Noushera Minor P.C.C 1:4:8 2.280 2.280 0.000

1L Noushera Minor P.C.C 1:4:8 1.520 1.520 0.000

Patwali Minor P.C.C 1:4:8 2.280 2.280 0.000

1L Zam Zam Minor P.C.C 1:4:8 1.520 1.520 0.000

1R Zam Zam Minor P.C.C 1:4:8 1.520 1.520 0.000

Islampur Disty P.C.C 1:4:8 1.520 1.520 0.000

Malkani Minor P.C.C 1:4:8 0.760 0.760 0.000

Abe Hayat Disty P.C.C 1:4:8 0.760 0.760 0.000


MONTHWISE STATEMENT OF QUANTITIES AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Material Disty/Minors Item Mar-14 Total Mar-14 Total

1L Hajipur Minor P.C.C 1:4:8 1.520 1.520 0.000

2R Hajipur Minor P.C.C 1:4:8 0.760 0.760 0.000

Kousar Disty P.C.C 1:6:18 0.101 0.101 0.000

Islampur Disty P.C.C 1:6:18 0.101 0.101 0.000

Abe Hayat Disty P.C.C 1:6:18 0.101 0.101 0.000

Hajipur Disty P.C.C 1:6:18 0.101 0.101 0.000

Kousar Disty P.C.C 1:7:20 0.126 0.126 0.000

Islampur Disty P.C.C 1:7:20 0.450 0.450 0.000

Abe Hayat Disty P.C.C 1:7:20 0.450 0.450 0.000

Bitumen Kousar Disty Expansion Joint -50.557 -50.557

1L Kousar Minor Expansion Joint 1007.085 1007.085

Noushera Disty Expansion Joint 16.155 16.155

1R Noushera Minor Expansion Joint 0.001 0.001

1L Noushera Minor Expansion Joint -36.089 -36.089

Patwali Minor Expansion Joint -41.644 -41.644

1L Zam Zam Minor Expansion Joint 88.390 88.390

Islampur Disty Expansion Joint 1718.148 1718.148

Malkani Minor Expansion Joint -22.189 -22.189

Abe Hayat Disty Expansion Joint 1389.592 1389.592

1R Hajipur Minor Expansion Joint 279.454 279.454

1L Hajipur Minor Expansion Joint -10.402 -10.402

2R Hajipur Minor Expansion Joint 1306.464 1306.464

Kousar Disty Joint Sealent -387.606 -387.606

1L Kousar Minor Joint Sealent 9218.301 9218.301

Noushera Disty Joint Sealent 84.118 84.118

1R Noushera Minor Joint Sealent -84.533 -84.533

1L Noushera Minor Joint Sealent -231.029 -231.029

Patwali Minor Joint Sealent -327.897 -327.897

1L Zam Zam Minor Joint Sealent 843.462 843.462

1R Zam Zam Minor Joint Sealent 36.561 36.561

Islampur Disty Joint Sealent 15374.421 15374.421

Malkani Minor Joint Sealent -198.796 -198.796


MONTHWISE STATEMENT OF QUANTITIES AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Material Disty/Minors Item Mar-14 Total Mar-14 Total

Abe Hayat Disty Joint Sealent 12507.779 12507.779

1R Hajipur Minor Joint Sealent 2821.119 2821.119

1L Hajipur Minor Joint Sealent -41.209 -41.209

2R Hajipur Minor Joint Sealent 11875.440 11875.440

Kousar Disty Bitumen Coating 4.100 4.100

1L Kousar Minor Bitumen Coating 17.719 17.719

Noushera Disty Bitumen Coating 6.059 6.059

1R Noushera Minor Bitumen Coating 2.801 2.801

1L Noushera Minor Bitumen Coating 4.052 4.052

Zam Zam Disty Bitumen Coating 7.994 7.994

Patwali Minor Bitumen Coating 4.842 4.842

1L Zam Zam Minor Bitumen Coating 4.217 4.217

1R Zam Zam Minor Bitumen Coating 0.183 0.183

Islampur Disty Bitumen Coating 6.216 6.216

Malkani Minor Bitumen Coating -0.994 -0.994

Abe Hayat Disty Bitumen Coating 6.456 6.456

Hajipur Disty Bitumen Coating 22.572 22.572

1R Hajipur Minor Bitumen Coating 6.706 6.706

2R Hajipur Minor Bitumen Coating 14.291 14.291

Bricks Kousar Disty B/W in 1:3 c/s 4.680 4.680

1L Kousar Minor B/W in 1:3 c/s 5.220 5.220

Noushera Disty B/W in 1:3 c/s 12.626 12.626

1R Noushera Minor B/W in 1:3 c/s 7.020 7.020

1L Noushera Minor B/W in 1:3 c/s 4.680 4.680

Zam Zam Disty B/W in 1:3 c/s 36.849 36.849

Patwali Minor B/W in 1:3 c/s 7.020 7.020

1L Zam Zam Minor B/W in 1:3 c/s 7.709 7.709

1R Zam Zam Minor B/W in 1:3 c/s 10.215 10.215

Islampur Disty B/W in 1:3 c/s 5.960 5.960

Malkani Minor B/W in 1:3 c/s 8.439 8.439

Abe Hayat Disty B/W in 1:3 c/s 45.901 45.901

Hajipur Disty B/W in 1:3 c/s 33.110 33.110

1R Hajipur Minor B/W in 1:3 c/s 0.540 0.540


MONTHWISE STATEMENT OF QUANTITIES AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Material Disty/Minors Item Mar-14 Total Mar-14 Total

1L Hajipur Minor B/W in 1:3 c/s 4.680 4.680

2R Hajipur Minor B/W in 1:3 c/s 10.881 10.881

Kousar Disty B/W in 1:6 c/s 0.514 0.514

Islampur Disty B/W in 1:6 c/s 2.294 2.294

Abe Hayat Disty B/W in 1:6 c/s 2.294 2.294

Hajipur Disty B/W in 1:6 c/s 0.000 0.000

Steel Kousar Disty Steel G-40 0.265 0.265

Noushera Disty Steel G-40 22.617 22.617

Islampur Disty Steel G-40 0.265 0.265

Abe Hayat Disty Steel G-40 0.265 0.265

Hajipur Disty Steel G-40 0.265 0.265

Executed Amount
Month
(Rs.)
Mar-14 8,080,865.61
`
Total 8,080,865.61
It is certified that claimed quantities in final bill for
price escalation for above said work as per measurement book (M.B)

Exeuctive Engineer
Rajanpur Canal Division Rajanpur
PRICE VARIATION STATEMENT AGAINST FINAL BILL
ABSTRACT OF COST

Name of work :- Concrete Lining of DJT/RJP-01

Sr. No. Disty/Minor Amount

1 H.P. Diesel (Item No. 01-003) 237,560.94

2 Labour (Item No. LB - 015) 688,710.14

3 Cement (Item No. 6.008) 969,721.28

4 Bitumen 88,809.86

5 Bricks 483,401.80

6 Steel 28,412.40

TOTAL :- 2,496,616.42

Contractor Executive Engineer Resident Engineer


M/S Nishan Engineers Rajanpur Canal Division Rajanpur PISIP Rajapur
PRICE VARIATION STATEMENT FOR DIESEL AGAINST FINAL BILL
Name of work :- Concrete Lining DJT/RJP-01
Amount Rate at
time of Current
Inc/Dec
tender Rate of Factor Amount of variation
Sr. # Description. Month Amount of rate
Amount March- Month (α) =α x VOW x (CPD-BPD)/BPD
(VOW) after Rebate in %
2011 (CPD)
(13.116%) (BPD)
Work done during the month of Mar-2014
1 Mar-14 9300752.30 8080865.61 82.22 116.75 41.997 0.07 237560.94
Against Final Bill

9,300,752.30 8,080,865.61 Total (Rs.) :- 237,560.94

Contractor Sub Divisional Officer Junior Engineer


M/S Nishan Engineers Hajipur Sub Division Fazilpur PISIP Rajanpur
PRICE VARIATION STATEMENT FOR LABOUR AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Rate at time Rate


Inc/Dec Amount of variation
of tender During the Factor
Sr. # Description. Month Amount of rate =β x VOW x (CLR-
Amount March-2011 month (β)
(VOW) after Rebate in % BLR)/BLR
(BLR) (CLR)
(13.116%)

Work done during the month of Mar-


1 Mar-14 9300752.30 8080865.61 220 345 56.818 0.15 688710.14
2014 Against Final Bill

9,300,752.30 8,080,865.61 Total (Rs.) :- 688,710.14

Contractor Sub Divisional Officer Junior Engineer


M/S Nishan Engineers Hajipur Sub Division Fazilpur PISIP Rajanpur
PRICE VARIATION STATEMENT FOR CEMENT AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Cement Rate at time of Inc/Dec


Sr. Bags per Difference of Amount of variation
Description. Month Quantity Unit consumed tender Current Rate of Rate
No. %Cft / Sft rate. BagsxDiff. Of Rate
(Bags) March-2011 in %

1 Cement plaster 1.5" thick Mar-14 462.579 %Sft 1.56 721.62 346 501 155 44.798 111851.65

2 Concrete lining 1:2:4 Mar-14 227.674 %Cft 17.6 4007.07 346 501 155 44.798 621095.49

P/L DPC with cement


concrete (ratio 1:2:4) 1½ "
3 Mar-14 1.026 %Cft 2.25 2.31 346 501 155 44.798 357.82
thick with two coat of hot
bitumen
Providing and laying 1.5"
toping of cement concrete
4 1:2:4 including surfice Mar-14 10.536 %Cft 2.2 23.18 346 501 155 44.798 3592.78
finishing and dividing in
panals

5 P.C.C 1:4:8 Mar-14 19.396 %Cft 9.6 186.20 346 501 155 44.798 28861.25

6 P.C.C 1:6:18 Mar-14 0.404 %Cft 5 2.02 346 501 155 44.798 313.10

7 P.C.C 1:7:20 Mar-14 1.026 %Cft 4.4 4.51 346 501 155 44.798 699.73
1/2'' thick cement plaster
8 upto 20ft height ratio 1:5 Mar-14 1.640 %Cft 0.6 0.98 346 501 155 44.798 152.52
cement sand mortar
Cement plaster ratio 1:3
9 upto 20' (6.00 m) height:- Mar-14 6.340 %Cft 1.32 8.37 346 501 155 44.798 1297.16
3/4'' (20mm) thick
1/2'' thick cement concrete
10 plaster ratio 1:4 upto 20' Mar-14 14.400 %Cft 0.73 10.51 346 501 155 44.798 1629.36
height
Cement pointing deep
11 struck joints with ratio 1:2 Mar-14 49.840 %Cft 0.72 35.88 346 501 155 44.798 5562.14
with redoxide pigment
PRICE VARIATION STATEMENT FOR CEMENT AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Cement Rate at time of Inc/Dec


Sr. Bags per Difference of Amount of variation
Description. Month Quantity Unit consumed tender Current Rate of Rate
No. %Cft / Sft rate. BagsxDiff. Of Rate
(Bags) March-2011 in %

Single layer of tiles


9''x4½'x1½
(225x113x40mm) grouted
with cement sand mortor
12 1:3 laid over 4'' thick earth Mar-14 4.100 %Cft 0.75 3.08 346 501 155 44.798 476.63
i/c mud plaster over
polythene sheet 500 guage a
layer of bitumen 34 lbs
%Sft complete

13 B/w in 1:3 c/s mortor Mar-14 205.530 %Cft 6 1233.18 346 501 155 44.798 191142.90

14 B/w in 1:6 c/s mortor Mar-14 5.102 %Cft 3.4 17.35 346 501 155 44.798 2688.75

Total (Rs.) 969,721.28

Note: Current Rates are freezed up to December 2013.

Contractor Sub Divisional Officer Junior Engineer


M/S Nishan Engineers Hajipur Sub Division Fazilpur PISIP Rajanpur
PRICE VARIATION STATEMENT FOR BITUMEN AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Bitumen Rate at time of Inc/Dec


Sr. Kg per Difference of Amount of variation
Description. Month Quantity Unit consumed tender Current Rate of Rate
No. Rft / %Sft rate. KgxDiff. Of Rate
(Kg) March-2011 in %

Expansion joints with bitumen. sand &


1 Mar-14 5644.407 Rft 0.04094 231.08 59.5 79.15 19.65 33.025 4540.76
saw dust in ratio 1:2:2.
joint sealent ratio 1:2:3, 1/2" wide and
2 Mar-14 51490.131 Rft 0.05118 2635.26 59.5 79.15 19.65 33.025 51782.96
1" thick.
Bitumen coating
3 Mar-14 107.214 %Sft 15.42 1653.24 59.5 79.15 19.65 33.025 32486.14
34 lbs per 100 Sft ( 1.72 kg per Sq. m.)

Total (Rs.) 88,809.86

Contractor Sub Divisional Officer Junior Engineer


M/S Nishan Engineers Hajipur Sub Division Fazilpur PISIP Rajanpur
PRICE VARIATION STATEMENT FOR BRICKS AGAINST FINAL BILL
Name of work :- Concrete Lining of DJT/RJP-01

Bricks Rate at time of Inc/Dec Amount of variation


Sr. Bricks per Difference of
Description. Month Quantity Unit consumed tender Current Rate of Rate Bricks (1000
No. %Cft / Sft rate.
(1000 No) Mar-2011 in % No)xDiff. Of Rate

1 B/W in 1:3 c/s Mortor Mar-14 205.530 %Cft 1350 277.466 4200 5900 1700 40.476 471692.20

2 B/W in 1:6 c/s Mortor Mar-14 5.102 %Cft 1350 6.888 4200 5900 1700 40.476 11709.60

Total (Rs.) 483,401.80

Contractor Sub Divisional Officer Junior Engineer


M/S Nishan Engineers Hajipur Sub Division Fazilpur PISIP Rajanpur
PRICE VARIATION STATEMENT FOR STEEL AGAINST FINAL BILL
Name of work :- Concrete Lining & Rehabilitation of DJT/RJP-01

Steel Inc/Dec Amount of variation


Sr. Rate at time of tender
Description. Month Quantity Unit Consumed Current Rate Difference of rate. of Rate Steel Consumed in
No. Mar-2011
M.Ton in % M.TonxDiff. Of Rate

1 Steel Reinforcement G-40 Mar-14 23.677 %Kg 2.3677 67448 79448 12000 17.79 28412.40

Total (Rs.) 28,412.40

Note: Current Rates are freezed up to December 2013.

Contractor Sub Divisional Officer Junior Engineer


M/S Nishan Engineers Hajipur Sub Division Rajanpur PISIP Rajanpur