Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


REGIONAL OFFICE XIII
J. Rosales Avenue, Butuan City

EXECUTIVE SUMMARY
(Proposed Variation Order No. 3)

FOR : DANILO E. VERSOLA, CESO III


Regional Director
THRU : POL M. DELOS SANTOS
OIC-Assistant Regional Director
===============================================
1. Subject : Proposed Variation Order No. 3 for the project 14NO0049: Concreting
/Improvement of Socorro Port –Jct. Songkoy –Sohoton Cove K2+838 –
K5+422, Socorro, Bucas Grande Island, Surigao del Norte
2. Implementing Office : Construction Division, DPWH – XIII Regional Office
3. Reviewee Office : Construction Division, DPWH – XIII Regional Office
4. Reasons for this request : This Variation Order No. 3 is proposed due to increase and decrease in
quantities and introduction of new item of work to suit actual field requirement
per approved As-Built Plan
The Items of Work involved in this proposed Variation Order No. 3 covers:
a. Increase in quantities of Item 102-3 – Surplus Rock Excavation, Item 103-1 – Structure
Excavation, Item 103-3 – Foundation Fill, Item 103-6 – Pipe Culvert and Drain Excavation, Item
104-1a – Embankment from Roadway Excavation, Item 300 – Aggregate Surface Course, Item
500-1b – Pipe Culverts, 1220mm dia., Item 505-5 – Grouted Riprap, Class “A”

b. Decrease in quantities of Item 200 – Aggregate Sub Base Course, Item 311-1a – PCCP, 0.28m
Thick, Item 311-1b – PCCP, 0.15m Thick, Item 404 –Reinforcing Steel Bar, Grade 40, Item 405
-Structural Concrete, Class “A”, Item 500-1a –Pipe Culverts, 910mm dia., and Item 506 –Stone
Masonry
5. CONTRACTOR : Socor Construction Corporation
SUSPENSION
CONTRACT
6. CONTRACTUAL DATA AMOUNT ORDER/TIME REMARKS
TIME
EXTENSION
6.1 Original Contract ₱ 79,696,098.80 210 CD
Previously Approved Variation
6.2
Order(s):
Due to approved As-
 Variation Order No. 1 ₱ 79,696,097.00 270 CD 60 CD
Stake Plan

Due to additional line


 Variation Order No. 2 ₱ 79,696,089.00 - - of 910mm. dia. RCPC
needed to suit actual
field condition
Previously Approved
Suspension Order/ Resume
6.3 Order / Time Extension: -
Due to unavailability
300 CD 30 CD of barge
 Time Extension No. 1
Due to unfavorable
 Time Extension No. 3 - 330 CD 30 CD
weather condition
6.4 Time Extension if Approved - - -
Revised Contract Cost/Time If this Variation Order
6.5 due to this Change (if ₱ 79,696,081.80 No. 3 is approved
approved)
Estimated Cost of Change
6.6 (-) 0.000009034% -
(% equivalent)

7. Physical Accomplishment as of May 31, 2017:


Schedule Accomplishment : 100.000%
Actual Accomplishment : 93.140%
Slippage : (-) 6.860%
8. Remarks
a. The request for Prior Clearance to Issue Variation Order No. 3 was duly approved
by the Regional Director.
b. The unit cost of items of work involved in this proposed Variation Order No. 3 were
based on the original contract, as indicated/reflected in the proposed Itemized Cost of Revision.
c. The subject Variation Order is in accordance with Clause No. 13 of the Conditions
of the Contract.
d. The authority to approve this proposed Variation Order No. 3 is in accordance with
the provision and guidelines of D.O. 54 series of 2011.
In view of the foregoing, this proposed Variation Order No. 3 is respectfully recommended for your
consideration and approval.
MARIBETH D. BURGOS
Chief, Construction Division