ID Task Name Duration Start Finish Qtr 2, 2012 Qtr 3, 2012

Apr May Jun Jul Aug Sep


1 PROYECTO PTAS POTABLE 246 days Mon 08/04/13 Wed 08/01/14
2 DESARROLLO INGENIERIA 74 days Mon 08/04/13 Sat 29/06/13
3 REUNIÓN DE INICIO Y REVISIÓN DE ANTECEDENTES 5 days Mon 08/04/13 Fri 12/04/13
4 VISITA A TERRENO 7 days Mon 08/04/13 Mon 15/04/13
5 CRITERIOS DE DISEÑO 7 days Sat 13/04/13 Sun 21/04/13
6 DIMENSIONAMIENTOS OBRAS Y EQUIPOS A NIVEL CONCEPTUAL 7 days Thu 18/04/13 Fri 26/04/13
7 Hito 1: Proyecto "Toma de Agua de Mar" 0 days Thu 02/05/13 Thu 02/05/13
8 INFORME TÉCNICO PRELIMINAR 14 days Wed 24/04/13 Thu 09/05/13
9 PLANOS CONCEPTUALES 14 days Wed 24/04/13 Thu 09/05/13
10 CAPEX Y OPEX CONCEPTUAL 7 days Wed 24/04/13 Thu 02/05/13
11 Hito 2: Ingreso SFI 0 days Thu 02/05/13 Thu 02/05/13
12 INFORME DE CIERRE INGENIERIA CONCEPTUAL 14 days Tue 30/04/13 Wed 15/05/13
13 DISEÑO INGENIERIA BÁSICA 40 days Wed 15/05/13 Sat 29/06/13
14 CUBICACIONES Y LISTADOS 14 days Thu 13/06/13 Sat 29/06/13
15 ESTIMACIÓN DE OPEX Y CAPEX 7 days Fri 21/06/13 Sat 29/06/13
16 EMISIÓN PAQUETES TÉCNICOS 14 days Thu 13/06/13 Sat 29/06/13
17 LICITACION CONTRATO CONSTRUCCION 98 days Fri 10/05/13 Tue 27/08/13
18 CONFECCION ANTECEDENTES LICITACION 7 days Fri 10/05/13 Fri 17/05/13
19 Hito 3: Ingreso solicitud SINCO Licitacion Construccion 0 days Fri 17/05/13 Fri 17/05/13
20 LICITACION CONTRATO CONSTRUCCION 90 days Sun 19/05/13 Tue 27/08/13
21 Hito 4: Adjudicacion Contrato Construccion 0 days Tue 27/08/13 Tue 27/08/13
22 ADQUISICIONES 118 days Sat 29/06/13 Fri 08/11/13
23 CONFECCION DE PAQUETE DE COMPRAS 7 days Sat 29/06/13 Sun 07/07/13
24 PRE SELECCION PROVEEDORES 7 days Sun 07/07/13 Mon 15/07/13
25 Hito 5: Ingreso RQ Compra Planta RO 0 days Mon 15/07/13 Mon 15/07/13
26 EMISION ORDEN COMPRA PLANTA RO 14 days Mon 15/07/13 Tue 30/07/13
27 SUMINISTRO DE PLANTA RO 90 days Wed 31/07/13 Fri 08/11/13
28 CONSTRUCCION Y ADQUISICIONES 119 days Wed 28/08/13 Wed 08/01/14
29 MOVILIZACION CONTRATO CONSTRUCCION 14 days Wed 28/08/13 Thu 12/09/13
30 Hito 6: Inicio Construccion Obras Civiles 0 days Thu 12/09/13 Thu 12/09/13
31 CONSTRUCCION OBRAS CIVILES 70 days Thu 12/09/13 Fri 29/11/13
32 MONTAJE PLANTA RO 15 days Fri 29/11/13 Mon 16/12/13
33 PUESTA EN MARCHA Y COMISIONAMIENTO 20 days Tue 17/12/13 Wed 08/01/14

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Planificacion diseño y constru
Progress Rolled Up Milestone Group By Summary
Date: Fri 12/04/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 1
Qtr 4, 2012 Qtr 1, 2013 Qtr 2, 2013 Qtr 3, 2013 Qtr 4, 2013 Qtr 1, 2014
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
PROYECTO PTAS POTABLE 08/01
DESARROLLO INGENIERIA 29/06
REUNIÓN DE INICIO Y REVISIÓN DE ANTECEDENTES 12/04
VISITA A TERRENO 15/04
CRITERIOS DE DISEÑO 21/04
DIMENSIONAMIENTOS OBRAS Y EQUIPOS A NIVEL CONCEPTUAL 26/04
Hito 1: Proyecto "Toma de Agua de Mar" 02/05
INFORME TÉCNICO PRELIMINAR 09/05
PLANOS CONCEPTUALES 09/05
CAPEX Y OPEX CONCEPTUAL 02/05
Hito 2: Ingreso SFI 02/05
INFORME DE CIERRE INGENIERIA CONCEPTUAL 15/05
DISEÑO INGENIERIA BÁSICA 29/06
CUBICACIONES Y LISTADOS 29/06
ESTIMACIÓN DE OPEX Y CAPEX 29/06
EMISIÓN PAQUETES TÉCNICOS 29/06
LICITACION CONTRATO CONSTRUCCION 27/08
CONFECCION ANTECEDENTES LICITACION 17/05
Hito 3: Ingreso solicitud SINCO Licitacion Construccion 17/05
LICITACION CONTRATO CONSTRUCCION 27/08
Hito 4: Adjudicacion Contrato Construccion 27/08
ADQUISICIONES 08/11
CONFECCION DE PAQUETE DE COMPRAS 07/07
PRE SELECCION PROVEEDORES 15/07
Hito 5: Ingreso RQ Compra Planta RO 15/07
EMISION ORDEN COMPRA PLANTA RO 30/07
SUMINISTRO DE PLANTA RO 08/11
CONSTRUCCION Y ADQUISICIONES 08/01
MOVILIZACION CONTRATO CONSTRUCCION 12/09
Hito 6: Inicio Construccion Obras Civiles 12/09
CONSTRUCCION OBRAS CIVILES 29/11
MONTAJE PLANTA RO 16/12
PUESTA EN MARCHA Y COMISIONAMIENTO 08/01

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Planificacion diseño y constru
Progress Rolled Up Milestone Group By Summary
Date: Fri 12/04/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 2
Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Planificacion diseño y constru
Progress Rolled Up Milestone Group By Summary
Date: Fri 12/04/13
Milestone Rolled Up Progress Deadline
Summary Split