Professional Documents
Culture Documents
Methodology
Dead Load and Live Load
Before any other computations, dead load and live load are first assumed or computed.
For this design project, live load is computed with the use of tables from ASCE 7-98. Formula and
computation is shown below.
There are two components of dead load in this design: dead load of the slab and
self-weight of the beam. For the dead load of the slab, its type must be identified, whether
it is one-way or two-way slab. Since two slabs are connected in this beam, these two
slabs contribute to the total dead load that is carried by the beam.
For slab 1,
𝐿𝑦 5200 𝑚𝑚
= = 1.118 < 2 ∴ 𝑆𝑙𝑎𝑏 1 𝑖𝑠 𝑡𝑤𝑜 − 𝑤𝑎𝑦.
𝐿𝑥 4650 𝑚𝑚
And from the distribution of loads for two-way slab, the load is distributed in a trapezoidal
shape. Hence,
𝐿𝑥 1 𝐿𝑦 5200 𝑚𝑚
𝐷𝐿𝑠𝑙𝑎𝑏 1 = 𝛾𝑐𝑜𝑛𝑐 (𝑡𝑠𝑙𝑎𝑏 ) ( ) (1 − ) 𝑤ℎ𝑒𝑟𝑒 𝛽 = = = 1.118
2 2𝛽 𝐿𝑥 4650 𝑚𝑚
4.65 𝑚 1
𝑫𝑳𝒔𝒍𝒂𝒃 𝟏 = 23.6 𝑘𝑁⁄𝑚3 (0.125 𝑚) ( ) (1 − ) = 𝟑. 𝟕𝟗𝟐 𝒌𝑵⁄𝒎
2 2(1.118)
For slab 2,
𝐿𝑦 9200 𝑚𝑚
= = 1.769 < 2 ∴ 𝑆𝑙𝑎𝑏 1 𝑖𝑠 𝑡𝑤𝑜 − 𝑤𝑎𝑦
𝐿𝑥 5200 𝑚𝑚
In the figure shown, the load is distributed in a triangular shape, unlike in slab 1.
Therefore,
𝐿𝑥 5.20 𝑚
𝑫𝑳𝒔𝒍𝒂𝒃 𝟐 = 𝛾𝑐𝑜𝑛𝑐 (𝑡𝑠𝑙𝑎𝑏 ) ( ) = 23.6 𝑘𝑁⁄𝑚3 (0.125 𝑚) ( ) = 𝟓. 𝟏𝟏𝟑 𝒌𝑵⁄𝒎
3 3
Combining the loads from slabs 1 and 2, the total unfactored dead load of the slab will be
8.905 𝑘𝑁⁄𝑚.
𝑙𝑛 4400
𝑏𝑓 = 𝑏𝑤 + 2 ( ) = 250 𝑚𝑚 + 2 ( ) = 1350 𝑚𝑚
8 8
𝑠𝑤 3600
𝑏𝑓 = 𝑏𝑤 + 2 ( ) = 250 𝑚𝑚 + 2 ( ) = 4100 𝑚𝑚
2 2
∴ 𝒃𝑓 = 𝟏𝟑𝟓𝟎 𝒎𝒎
Section 406.3.2.2 of NSCP 2015 states additional provisions and limitations for isolated
non-prestressed T-beams. The flange thickness must be greater than or equal to 0.5bw and
flange width should also be less than or equal to 4bw.
ℎ𝑓 ≥ 0.5𝑏𝑤
𝑏𝑓 ≤ 4𝑏𝑤
Normal Density concrete will be used in the design but since there is no maximum
compressive strength of concrete at 28 days or f’c, the maximum f’c for lightweight
concrete with special moment frames and special structural walls will be used with design
strength 35 MPa. Table 419.2.1.1 as shown below was used as basis for the f’c.
Table 419.2.1.1 Limits for f’c
(Page 4-128 , NSCP Vol.I, 7TH Edition, 2016)
Minimum f’c Maximum f’c,
Application Concrete
,MPa MPa
Normal-weight
General 17 None
and lightweight
Special moment Normal-weight
21 None
frames and
special
structural walls Lightweight 21 35*
*The limit is permitted to be exceeded where demonstrated by experimental evidence that members
made with lightweight concrete provide strength and toughness equal to or exceeding those of
comparable members made with normal weight concrete of the same strength.
In addition to that, the table below stated that at the time of transfer, the maximum
permissible tensile stresses in prestressed reinforcement immediately after force transfer
at post-tensioning anchorage devices and couplers is 70 percent of ultimate tensile
strength. Hence, the compressive strength of concrete at time of initial prestresss is also
assumed to have attained 70% of compressive strength of concrete at 28 days or f’c
which is equal to 24.50 MPa.
Table 420.3.2.5.1
Maximum Permissible Tensile Stresses in Prestressed Reinforcement
(Page 4-135, NSCP Vol.I, 7TH Edition, 2016)
Stage Location Maximum tensile stress
0.94fpy
0.80fpu
Maximum jacking
During stressing At jacking end Least of:
force recommended
by the supplier of
anchorage device
Immediately At post-tensioning
after force anchorage devices 0.70fpu
transfer and couplers
NOTE: Figure and initial assumptions na lang para sa prestressed concrete kulang