Quality Management
Quality Management System Integration
The Quality Department is monitoring the Audit Programme of the Supervision Consultants
(SC) and Construction Contractors (CC). The summary of CARs and Observations raised /
The Quality Department has completed all activities as part of the 100 Days activity
closed during the audits by SCs and CCs are given below.
plan for integration of QMS functions on the HPD Projects. The activities included
training on Performance KPIs, QC KPIs, Asphalt Quality Tracker and other QA oversight Audit By Audits CARs Raised CARs Closed OBS Raised OBS Closed
activities to the Supervision Consultants and Contractors. Also, to create an awareness
on the HPD QMS and Blueworks Processes, specific in house training has been Supervision Consultant 14 11 7 38 20
conducted. More than 125 HPD staff attended these sessions conducted in 10 sessions Construction Contractor 12 11 6 21 8
during the 1st week of December 2018.
The Performance KPI portal in SharePoint is now functional and performance
evaluations of the Supervision Consultants and Contractors on all the HPD Projects will
commence from January 2019 onwards.
Status of QSD/ANAS Audit Reports and Responses
Audits No. of Projects Response Provided
In Progress
Waiting Response Audit in Progress
Audited to QSD from SC by ANAS
The Quality Department has carried out a total of 6 Audits on the Expressway 15 9 1 4 1
Programme out of the 7 planned for the month of December 2018. There were 7 CARs
and 31 Observations raised during the audits. There were 2 CARs and 9 Observations P 029-C1
closed during the Follow-up Audits. P 012
P 023-C2 P 17-C2
The Compliance / system and Follow up Audits were conducted on the following P 07-C1
Projects: P 015
The evidence for close out for the audit findings were reviewed by HPD Pavement team and
Project Audited Audit Scope Supervision Consultants.
P007-C5-P1 Parsons International System Audit Key Quality issues Actions to address the key issues
P007-C7-P2 Parsons International Follow-up Audit
International Roughness Index (IRI) Action plan to resolve the IRI non compliant
P008-C3 Parsons International System Audit Non-Conformances on the EXW. sections of road pavement to be implemented
Supervision Consultant’s RAG (Red, Amber, Green) Graph 5 P023-C1 AECOM 7.3 4 P003 CDM 7.4
Average Overall Score
100% 6 P007-C2 Egis 7.2 5 P023-C1 AECOM 7.3
10
75% 6 P023-C4 AECOM 7.2 6 P007-C2 Egis 7.0
8 7.4 7.2 7.2
6.8 6.8 6.8
% RAG
2
Expressway Programme Monthly Programme Report - Document Number EXW-GENL-0000-PM-KBR-RM-80119
monthly programme report Quality expressway programme
Leighton – Al Leighton – Al
0.0 3 P023-C3
Jaber
6.6 3 P023-C3
Jaber
6.7
QD-SBG
CHEC
L&T
Hyundai
SIX-BOOM
P023 C1
P010
Al Jaber T&GC
P015
J&P
P011
QDVC-BOTC
LEIGHTON-AJE
DOGUS-ONUR
P005
P007 C1
J&P
P003
P023 C2
P023 C3
P007C2
P012
4 P007-C2 Dogus - Onur 6.5 4 P007-C2 Dogus - Onur 6.5
Construction Contractor’s Average Overall Score RAG (Red, Amber, Green) Graph 6 P007-C1 Six - Boom 6.2 5 P011 CHEC 6.3
2.0 0% 10 P023-C1 J&P - J&P Avax 4.5 10 P023-C1 J&P - J&P Avax 4.9
Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Red 1 1 1 3 2 1 Average Score 6.0 Average Score 6.0
0.0
Amber 7 9 8 5 8 9
Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18
Green 4 2 3 3 1 0
P007-C1
P007-C2
P008-C2
P008-C3
P017-C2
P023-C1
P023-C2
P023-C3
P029-C1
P003
P005
P017-C1-IN
P060
P007-C7-P2
P007-C5-P1
Length
Balance Road Lane Length
(Includes WC Laid to be tested, Test Results 470 14%
awaited and WC to be placed) Internal Projects External Projects
HPD Quality Department is monitoring the status of testing frequency compliance on the
Expressway Programme. In order to ensure that the Construction Contractors are achieving
The Supervision Consultants should provide an action plan to resolve and rectify the non the required Material Sampling and Testing Frequencies, as stipulated in the Project
compliant road pavement sections of the road pavements and submit to HPD Pavement Specifications and QCS, each project Supervision Consultants are required to provide a
Team for approval. monthly summary to the PMC.
The rideability compliance levels achieved on the Projects and status of IRI resolution plans An overview indicating the compliance level on the Expressway Programme for the month
are presented in Appendix 3. of December 2018 is attached to this report.
Project P008-C3 Construction Contractor did not submit the Testing Frequency Compliance
details.
2 1
5 3 7
4 3 3 3 2 2 2 1 1 1 27
NCRs OBS
Thickness
Tack Coat
Temperature
In-Place Av
IRI
Fuel Spillage
Gradation
Surface Defects
Operations
Compaction
Compaction
Settlement
Level Control
In-Place Av
Asphalt
Paving
Control
1.1
0.9
1.0 0.8 0.7
6 0.5
3 0.3
1 1 1 1 0.5 0.2
01 - Geotechnical Investigation N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
02 - Earthworks / Subgrade / Backfill / Pipe Bedding /
Trenching / Fluidised Thermal Backfill N/A
03 - Kerbstone N/A N/A N/A N/A
04 - Subbase (Class A, B, C etc) N/A
05 - Geotextiles N/A N/A N/A N/A N/A N/A N/A
06 - Aggregates (Coarse & Fine - Used for Asphalt,
Concrete, Masonry, Landscaping) N/A
07 - Cement N/A N/A N/A
08 - Concrete / Admixture N/A N/A
09 - Steel, Sheathing etc (Rebar, Structural Steel, & Pre &
Post Tensioning Steel / Strand) N/A N/A N/A N/A N/A
10 - Asphalt Works N/A
11 - Tack Coat / Prime Coat N/A
12 - Concrete & Clay Blocks / Bricks N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
13 - Masonry / Mortar for Tiles, Plaster etc N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
14 - Interlocking Blocks (or Paving Blocks) N/A N/A N/A N/A N/A N/A N/A N/A N/A
16 - Waterproofing / Protective Coating N/A N/A N/A N/A N/A N/A N/A N/A N/A
17 - Pipes / Sprinklers N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
18 - PRC Pipes / GRP Lined RC Pipes / Precast Pipes /
GRP (Long, Short Pieces) N/A N/A N/A N/A N/A N/A N/A N/A
19 - Functionality Tests for Piping Systems N/A N/A N/A N/A N/A N/A
20 - Road Furniture Markings / Thermoplastic /
Accessories etc N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
21 – Microsilica (or Silica Fume), GGBS, PFA (or Fly Ash)
etc N/A N/A N/A N/A N/A N/A N/A
22 - Commissioning / Activation Tests N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
23 - Manhole Covers, Road Gullies / Gratings etc N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
25 - Ground Water (Dewatering), Water for Concrete /
Curing, TSE, Storm Water, Foul Sewer N/A N/A N/A N/A N/A N/A
27 - Others (Specify) - Rockfill N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
28 - Others (Specify) - CBM N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A
Full Compliance with Frequency Partial Compliance with Frequency Not Complying with Frequency
Improvement noted from the previous Deficiencies noted from the previous
report report
To reduce the additional “Testing Frequency Compliance Report”, HPD Quality Department and QSD have revised the Ashghal QA/QC Questionnaire to cover the cumulative testing frequency compliance
reporting on the new Projects. In above overview, Projects P003, P005, P007-C1, P007-C2, P023-C1 and P023-C3 monthly testing frequency compliance levels, whereas the rest of the Projects reported
frequency compliance using the revised Ashghal QA/QC Questionnaire.
Project P003 P005 P007-C1 P007-C2 P010 P011 P012 P015 P023-C1 P023-C2 P023-C3 P023-C4
Testing Laboratory ACES DTL FUGRO QEL FUGRO QEL ACES QEL FUGRO QEL ACES ACES
Lane Length of Road applicable for IRI in Scope 79 62 23 96 205 215 91 255 373 660 690 608
Balance WC To be Placed (IRI) 0 31 0 53 0 0 0 0 61 87 1 0
Total WC Laid 79 30 23 43 205 215 91 255 313 573 689 608
Laid To be Tested 0 0 5 3 14 0 54 0 70 17 1 0
Length of Road Lanes Tested 79 30 18 40 191 215 36 255 243 557 688 608
IRI Compliant 42 24 18 31 112 147 27 156 103 456 687 608
IRI Out of Tolerance 18 0 1 4 66 68 5 63 130 39 0 0
IRI Significantly Out of Tolerance 10 6 0 4 14 0 0 36 10 4 0 0
Tested Results Awaited 8 0 0 0 0 0 5 0 0 58 1 0
% IRI Out of Specification limits 40% 20% 3% 22% 42% 32% 14% 39% 58% 9% 0% 0%