You are on page 1of 34

www.civil.eng.usm.

my
To introduce the mechanism of transfer 1. Able to explain the mechanism by
of prestress in PSC member and which prestressing force is
determine the bursting force. transferred to concrete in pre-
tensioned beams;
2. Able to explain the stress
trajectories in an end block of a
post-tensioned concrete beam with
a single anchorage.
3. Able to determine the bursting
force in post-tensioned member.
 Prestressed concrete contains  In pre-tensioned concrete, the force
tendons which are typically stressed is transferred by bond between the
to about 1000 MPa. tendon and the concrete (steel-
concrete bond).
 These tendons need to be anchored
at their ends in order to transfer  For a pre-tensioned member, usually
prestressing force to the concrete. there is no anchorage device at the
ends.
 In post-tensioned concrete, relatively
small anchorage plates transfer the
force from the tendon to the
concrete immediately behind the
anchorage by bearing at each end of
the tendon.

End of pre-tensioned End of post-tensioned


member member
 Therefore, a finite length of the
member is required for the
concentrated forces to redistribute
(disperse) the stress occurs behind
the anchorage plate to form the
linear compressive stress
distribution, (according to St.
Venant's Principle).
Anchoring device  The distance over which this
redistribution occurs is called
 In either case, the prestressing force anchorage zone (disturbed region).
is transferred in a relatively
concentrated fashion, usually at the  The length of member over which the
ends of the member, and involved redistribution of stress takes place is
high local pressures and forces. called the transmission length (in pre-
tensioned), and the anchorage length
(in post-tensioned).
 In the anchorage zone (within the  When the pretressing force is
transmission/anchorage length), the transferred to the concrete,
stress trajectories are the main transverse stresses (compressive and
tensile) developed together with the
concern of Engineers. shear stress within the anchorage
 Stress trajectories are complex in zone.
nature.  Usually, the stress concentrations
 Therefore, it is in the Engineer's within the anchorage zone in a pre-
tensioned member are not as severe
interest to ensure two things in this as a post-tensioned anchorage zone.
zone:
 A more gradual transfer of
 The zone must not crack at the prestressing force occur in pre-
serviceability limit state, and tensioning system.
 The zone must not fail at the  Meanwhile, the high concrete bearing
ultimate limit state. stresses behind the anchorage plates
in post-tensioned members.
The mechanism of prestressing force is
transferred to pre-tensioned beams

 The transmission of prestressing


force from steel (wires) to concrete
is generally through a steel-concrete
bond.
 The transfer of prestressing force
usually occurs only at the end of the
member, with the steel stress varying
from zero at the end of the wires to
the prescribed amount (Pm0) at some
distance.
 That distance is known as
transmission length.
The mechanism of prestressing force is
transferred to pre-tensioned beams

 Over the transmission length the


bond stresses are high.
 The figure shows the distribution of
bond stresses – stress in steel and
concrete in the transmission zone.
 The maximum bond stress is reached
in the zone of transverse
compression.
 When the bond stress is zero, the
stress in steel and concrete reach
their maximum values, and uniform
stress distribution is prevalent from
this section.
The mechanism of prestressing force is
transferred to pre-tensioned beams
 When the wires are released from its
anchorage within the casting bed and
 The main mechanisms that contribute the force is transferred to the
to the strength of the steel-concrete concrete, there is a small amount of
bond are: wires (tendon) slip at the end of the
member.
(1) chemical adhesion of steel to
concrete,  This slippage destroys the bond for a
(2) friction at the steel-concrete short distance into the member at
interface, and the released end, after which
adhesion, friction and mechanical
(3) mechanical interlocking of interlock combine to transfer the
concrete and steel. wires force to concrete.
Hoyer effect (Wedge action)

 When the wires are released from its


temporary anchorage on the
prestressing bed, the end of the
wires swell as a result of the recovery
of the lateral contraction.
 During the stressing operation, there
is a reduction in the diameter of the
wires (tendon) due to Poisson’s ratio
effect.
 The concrete is then cast around the
highly tensioned wires (tendon).
Hoyer effect (Wedge action)

 When the wires (tendon) are


released, the unstressed portion of
the wires (tendon) at the end of the
member returns to its original
diameter, whilst at some distance into
the member, where the tensile stress
in the wires (tendon) are still high,
the wires (tendon) remains at its
reduced diameter.
 Within the transmission length, the
diameter of wires varies and there is
radial pressure exerted on the
surrounding concrete.
Hoyer effect (Wedge action)

 This pressure produces a frictional


component which assists in the
transferring of force from the steel
to the concrete.
 The wedging action due to this radial
strain is known as the Hoyer effect.
Transmission Length

 The length required at the end of a  The force transfer is not linear, with
pre-tensioned member for a build-up about 50% of the force transferred
of stress in concrete is of great in the 1st quarter of the transfer
importance. length and about 80% within the 1st
 The transmission length depends half of the length.
mainly on the diameter and surface  For design purpose, however, it is
characteristics of the wire, the reasonable and generally conservative
elastic properties of steel and to assume a linear variation of steel
concrete, and the coefficient of stress over the entire transmission
friction between steel and concrete. length.
 Observed values of transmission
length for most common condition are
ranged from 50 – 150 times the
diameter of the tendon.
Transmission Length

 Based on the wedge action, Hoyer has  Marshall and Krishna Murthy’s semi-
developed an expression for empirical relations for determination
computing the transmission length, of transmission length which
which is given by: applicable for plain smooth wires and
strands is given by:
𝜙 𝛼e 𝑓pi 𝑓pe
𝑙pt = 1 + 𝜐c −
2𝜇 𝜐s 𝐸c 2𝑓pi − 𝑓pe 𝑓cu × 103
𝑙pt =
𝛽
Example 5.1 Solution:
Calculate the transmission length at the end
of the pre-tensioned simply supported beam 𝜙 𝛼e 𝑓pi 𝑓pe
as per Hoyer’s method using the following 𝑙pt = 1 + 𝜐c −
2𝜇 𝜐s 𝐸 c 2𝑓pi − 𝑓pe
data:
Span of the beam = 50 m 𝐸𝑠 210
ϕ wire = 7 mm 𝛼e = = =7
𝐸𝑐 30
m = 0.1
nc = 0.15 𝑓pi = 0.7𝑓pu = 0.7 ∗ 1500 = 1050 N mm2

ns = 0.30
𝑓pe = 0.6𝑓pu = 0.6 ∗ 1500 = 900 N mm2
Es = 210 kN/mm2 and Ec= 30 kN/mm2
Ultimate tensile strength of steel wire, fpu =
1500 N/mm2 7 7
𝑙pt = 1 + 0.15
2 ∗ 0.1 0.30
Initial stress in steel, fpi = 0.7fpu 1050 900
− = 𝟕𝟎𝟑 𝐦𝐦
Effective stress in steel, fpe = 0.6fpu 30000 2 ∗ 1050 − 900
Example 5.2 Solution:

Estimate the transmission length of the ends 𝑓cu × 103


of a pre-tensioned beam prestressed by 7 mm 𝑙pt =
𝛽
ϕ wires. Assume the cube strength of
concrete at transfer as 42 N/mm2. Adopt
Marshall and Krishna Murthy’s empirical From Table 5.1: β = 0.0174
relation.

42 × 103
𝑙pt = = 𝟔𝟏𝟎 𝐦𝐦
0.0174
Bond stress
 The magnitude of bond stresses
developed between concrete and steel
and its variation in the anchorage
zone of a pre-tensioned beam is
depicted in the following figure.
 The bond stress is zero at the ends
but build up rapidly to a maximum
over a very short length.
 This value decreases as the stress in
the wire builds up.
 At a distance equal to the
transmission length, the bond stress
is almost zero while the stress in
steel and concrete reach their
maximum values.
Bond stress
If:
 (tbp)max = the max. value of bond  Based on tests conducted at the
stress University of Leeds, the following
relations have been proposed by
 (tbp)x = bond stress at a distance x
from the free end Marshall:

 ϕ = diameter of the wire


𝜏bp = 𝜏bp 𝑒−4𝜓𝑥 𝜙
 fs = stress in steel a distance x from x max
the free end
 fsc = effective stress in steel at the 𝑓s = 𝑓sc 1 − 𝑒−4𝜓𝑥 𝜙

end of the anchorage zone  The stress in a steel wire gradually


increases from zero at the end of the
beam to 100% of the effective stress
at the end of the transmission length.
Example 5.3 Solution:

A pre-tensioned beam is prestressed using 5 (a) Calculate the transmission length;


mm diameter wires with an initial stress 80%
Use Marshall and Krishna Murthy’s equation:
of the ultimate tensile strength of steel. The
cube strength of concrete at transfer is 30 From Table 5.1: β = 0.0235
N/mm2. Given the ultimate tensile strength of
steel is 1600 N/mm2, (tbp )max = 7.42 N⁄mm2 30 × 103
𝑙pt = = 𝟒𝟖𝟑 𝐦𝐦
and ψ=0.00725. 0.0235

a) Calculate the transmission length;


b) Compute the bond stress at ¼ and ½ the (b) Compute the bond stress at ¼ and ½ the
transmission length from the end; transmission length from the end;
c) Calculate the overall average bond stress.
𝜏bp = 𝜏bp 𝑒−4𝜓𝑥 𝜙 = 7.42𝑒−4∗0.00725𝑥 𝜙
x max
Solution: Solution:

(b) Compute the bond stress at ¼ and ½ the (b) Compute the bond stress at ¼ and ½ the
transmission length from the end; transmission length from the end;

𝜏bp = 𝜏bp 𝑒 −4𝜓𝑥 𝜙


= 7.42𝑒 −4∗0.00725𝑥 𝜙
𝜏bp = 𝜏bp 𝑒 −4𝜓𝑥 𝜙
= 7.42𝑒 −4∗0.00725𝑥 𝜙
x max x max

¼ the transmission length from the end = ½ the transmission length from the end = ½
¼*483 = 120.75 mm *483 = 241.5 mm
𝜙 = 5mm 𝜙 = 5mm
Therefore, the bond stress: Therefore, the bond stress:

𝜏bp = 7.42𝑒−4∗0.00725∗120.75 5
𝜏bp = 7.42𝑒 −4∗0.00725∗241.5 5
120.75mm 120.75mm
= 𝟑. 𝟔𝟖 𝐍 𝐦𝐦𝟐 = 𝟏. 𝟖𝟑 𝐍 𝐦𝐦𝟐
Solution:

(c) Calculate the overall average bond


stress;

0.8 ∗ 1600 ∗ 𝜋 ∗ 2.52


𝜏bp =
average 2 ∗ 𝜋 ∗ 2.5 ∗ 483
= 𝟑. 𝟑 𝐍 𝐦𝐦𝟐
Introduction

 In the anchorage zone of a post-  The transverse stresses developed in


tensioned member, the state of the anchorage zone are tensile in
stress-distribution is complex and 3D nature over a large length.
in nature.  The effect of transverse tensile
 In most post-tensioned members, the stress is the development of a zone
prestressing tendons are introduced of bursting tension in a direction
in a duct, then stressed and anchored perpendicular to the anchorage force,
at the end faces. resulting in horizontal cracking.
 The large forces will be concentrated  Since concrete is weak in tension,
over relatively small areas and applied suitable reinforcement are generally
on the end blocks and hence, develop provided in the transverse direction
transverse and shear stresses. to resist the bursting tension.
Stress distribution (trajectories) in the
anchorage zone

 High bearing stresses at the


anchorage plate disperse throughout
the anchorage zone, creating high
transverse stresses (compressive and
tensile), until at a distance la from the
anchorage plate.
 The idealised stress trajectories
(distribution) in the anchorage zone
(end block) with the compressive and (a) A single square anchorage plate centrally
tensile stress paths are shown in fig. positioned at the end of a prismatic member depth
(b). h and width b. (b) Stress trajectories for a
centrally placed anchorage plate
Stress distribution (trajectories) in the
anchorage zone
 The stress trajectories are convex to
the centre line of the member, and
produce transverse paths of
compressive stress normal to the
member axis.
 Further from the anchorage, the
compressive stress trajectories
become concave to the member axis
and, produce transverse tensile
stress paths. (a) A single square anchorage plate centrally
 At the same time, transverse tensile positioned at the end of a prismatic member depth
stresses develop in the nearby h and width b. (b) Stress trajectories for a
concrete. centrally placed anchorage plate
Stress distribution (trajectories) in the
anchorage zone

 The stress trajectories are closely


spaced directly behind the bearing
plate where compressive stress is
high, and become more widely spaces
as the distance from the anchorage
plate increases.
 St. Venant’s principle suggests that
the length of the disturbed region, la,
for the single centrally located (a) A single square anchorage plate centrally
anchorage is approximately equal to positioned at the end of a prismatic member depth
the depth of the member h. h and width b. (b) Stress trajectories for a
centrally placed anchorage plate
Stress distribution (trajectories) in the
anchorage zone

 The variation of the transverse


stresses along the centre line of the
member, and normal to it, is presented
in the following figure.
 The degree of curvature of the stress
trajectories is dependent on the size of
the bearing plate. The smaller the
bearing plate, the larger are both the
curvature and concentration of the
stress trajectories, hence the larger Distribution of transverse stress behind a
are the transverse tensile and single central anchorage
compressive forces in the anchorage
zone.
Stress distribution (trajectories) in the
anchorage zone

 The transverse tensile forces, often


called bursting or splitting forces, need
to be estimated accurately so that
transverse reinforcement within the
anchorage zone can be designed to
resist them.
 Elastic analysis can be used to analyse
anchorage zone prior to the
commencement of cracking.
Distribution of transverse stress behind a
single central anchorage
Investigation on anchorage zone stress Investigation on anchorage zone stress
through Guyon’s method for forces through Guyon’s method for forces
evenly distributed evenly distributed
 Guyon has developed design tables for Where:
the computation of bursting tension in P = anchorage force
end blocks which are based on his
earlier mathematical investigations ypo yo = distribution ratio (refer design
concerning the distribution of table of Guyon’s method)
stresses in end blocks subjected to 2ypo = depth of the anchorage plate
concentrated loads.
2yo = depth of the anchorage prism (for
 According to Guyon’s method, the
bursting tension is expressed as: this case is equal to the depth of the end
block)
0.58
𝐹bst = 0.3𝑃 1 − 𝑦po 𝑦𝑜
Investigation on anchorage zone stress
through Guyon’s method for forces
evenly distributed
 In Guyon’s method, the position of
zero stress, maximum transverse
stress and its magnitude for the
forces which are evenly distributed
are computed by using the coefficient
given in design table of Guyon’s
method.
Example 5.4 Solution:
Calculate the position and magnitude of the
The end block of a prestressed concrete maximum tensile stress
beam, rectangular in section, is 100 mm 2𝑦po = 50 mm
wide and 200 mm deep. The prestressing
2𝑦o = 200 mm
force of 100 kN is transmitted to
concrete by a distribution plate, 100 mm ∴ 𝑦po 𝑦o = 50 200 = 0.25
wide and 50 mm deep, concentrically
located at the ends. Refer design table of Guyon’s method:
a) Calculate the position and magnitude Position of zero stress from the end face =
of the maximum tensile stress; 0.15 2𝑦o = 0.15 × 200 = 30 mm
b) Compute the bursting tension. Position of max. stress from the end face =
0.33 2𝑦o = 0.33 × 200 = 66 mm
Ratio of max. tensile stress to average
stress = 0.345
Solution: Solution:

Max. tensile stress = 0.345 𝑃 𝐴


100 × 103 Compute the bursting tension:
= 0.345 = 1.725 N mm2 0.58
200 × 100 𝐹bst = 0.3𝑃 1 − 𝑦po 𝑦𝑜
Therefore, the max. tensile stress is given by 𝐹bst = 0.3 × 100 103 1 − 0.25 0.58
= 16.575 kN
1.725N mm2 at the position of 66 mm from
the end face.
If the yield stress in mild steel is 260N mm2 ,
66 mm then:
𝐹bst 16.575
Area of steel required = =
0.87𝑓𝑦𝑘 0.87 ∗ 260
30 mm = 73mm2
Hence, provide 3M6 for the tensile
reinforcement in the anchorage zone.
End Zone Reinforcement

The forms are closed stirrups, mats or Confining the concrete with spiral
links with loops. reinforcement.
End Zone Reinforcement

Fabrication of end zone reinforcement: End zone reinforcement with guide and
duct:

You might also like