Professional Documents
Culture Documents
1. Regarding management and leadership all of the following are true except
1. The first project is a process optimization which would result in a cost reduction of
$120,000 per year. This benefit would be achieved immediately after the end of
the project.
2. The second project would be the development of a new product which could
produce the following net profits after the end of the project:
1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000
Assumed is a discount rate of 5 % per year. Looking at the net present values of these
projects' revenues in the first 3 years, what is true?
Both projects are equally attractive.
The measurements made at the end of the process yielded the following results:
20.033 cm, 19.982 cm, 19,995 cm, 20.006 cm, 19.970 cm, 19.968 cm, 19.963
cm, 19.958 cm, 19.962 cm, 19.979 cm, 19.959 cm.
5. During a software project Earned Value Analysis is performed and gives the following
results:
EV: 523,000; PV: 623,000; AC: 643,000.
7. Which process is applied to break down the project into smaller, more manageable
elements?
Scope Planning.
Scope Definition.
Scope Verification.
8. Which of the following Tools and Techniques are part of Risk Management Planning?
Diagramming techniques.
9. All of the following statements concerning project stakeholders are true except
Project stakeholders may influence the course of the project and its results.
Proposals.
Evaluation criteria.
Contract negotiation.
Contract.
Standards often begin as guidelines that are not mandatory. With later widespread
adoption, they can become de facto regulations.
12. Which type of leadership is best suited for optimizing team performance in projects?
Democratic leadership.
Participative leadership.
Autocratic leadership.
13. Where is the result node (outcome) shown on a typical Ishikawa diagram?
Top.
Bottom.
Center.
Marked for review
14. A project management team has subcontracted work to a service company. The process
of ensuring that this service company's performance meets contractual requirements is
called
Contract Administration.
Staff Acquisition.
Contract Closeout.
Contract Negotiation.
Unachievable deliverables.
Accomplished objectives.
Decisions made earlier which limit the options for decision making.
17. During execution of a project which is performed for a customer on a T&M (Time and
Material) contract base a new project manager is taking over the assignment.
He discovers that two members assigned to the project have charged time without
performing any work. Upon further investigation, he determines that this occurred
because there were no other project assignments available for these people. The
customer is unaware of these facts.
Try to find a responsible person for the over-assignment who can be made
accountable.
Take the two people off the team immediately and arrange for the refund of the
excess charges to the customer.
18. In the following network logic diagram start dates are defined as early morning, finish
dates are evening.
If tasks are scheduled to begin at early start date, what is true?
19. Which of the following is not considered to be part of Project Resource Management?
Working staff.
Materials.
Equipment.
Time and money.
The ability to communicate using drawings and pictograms which are understood all
over the world.
22. A project manager performs Earned Value Analysis and finds the following values:
23. During a project the scope of product purchased on a cost reimbursable contract has
increased. In the contract the contractor‘s indirect costs are calculated as 20 % of the
direct costs. What is most likely to be true?
The contractor‘s indirect costs will increase and the customer‘s payment for them
will increase, too.
The contractor‘s indirect costs will increase but the customer‘s payment for them
not.
Neither the indirect costs nor the customer‘s payment for indirect costs will
increase.
The contractor‘s indirect costs will not increase but the customer‘s payment for them
will.
Special causes are easier to predict and handle than random causes.
25. You are performing a project management audit in your company and find that most of
the project plans are neither consistent nor up-to-date.
A great deal of effort is required to develop and update a project plan, but the
benefits include less pressure on all stakeholders and a resulting product that will
satisfy the requirements.
Poor planning is one of the major reasons for cost and time overruns.
CPI < 1.
CPI < 0.
SPI = 1.
Only those who realize that cultural differences are a resource to be fully utilized will
survive.
There is a common ground for people from different cultures on which they can
interact without unsolvable conflicts.
Improve team communication and availability of high quality data on risks. Use this
information to enable you to make well-founded decisions earlier.
The problem might be the customer disturbing project rhythm. Keep him on
distance from the team.
Apply fast tracking to shorten project duration without additional work.
31. Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and
Activity 4 of 6 days. What is the minimum total duration between the Milestones A and B?
36 days.
37 days.
39 days.
42 days.
Marked for review
The Activity List is a principle output used for resource allocation and is an input to
network diagramming.
The Work Breakdown Structure is a principle output and should be broken down to a
level which allows sufficient accuracy in planning.
33. All the following statements regarding "whistleblowing" are true except
It is the term used to define an employee’s decision to disclose information on
unethical, immoral or illegal actions at work to an authority figure.
An employee should always discuss the matter with people external to the company
before following the "chain of command" and discuss it with the immediate superior.
The consequences of whistleblowing are often extreme and include possible being
branded as having bad judgment, firing, civil action and imprisonment.
Assumptions limit the project management team's options for decision making.
It is axiomatic of the quality management discipline that the benefits outweigh the
costs.
Quality should be tested and inspected into work results on a regular base.
The primary cost of meeting quality requirements is the expense associated with
project quality management activities.
The primary benefit of meeting quality requirements is less rework, which means
higher productivity, lower costs, and increased stakeholder satisfaction.
37. Which of the following statements about diagramming methods is not true?
38. A project is managed by a project coordinator. Which of the following statements is most
likely to be true?
Cultural dilemmas should be denied to not allow them to disrupt project work.
Communicating across cultures should only be done using language. The nonverbal
dimension bears too many risks.
Activities in PDM which are not necessary and can be dropped if time is running out.
Arrows in ADM which represent dependencies between nodes without real activities.
Activities, which can be passed to the team members with the lowest IQ.
Prevention costs.
Failure costs.
Transportation costs.
Appraisal costs.
43. According to the project plan, a contractor is scheduled to deliver some software
components at the end of the day. A regular payment is due to be made to this
contractor tomorrow.
The project team received a note this morning informing them that the software delivery
will be delayed by 2 weeks.
This morning, the project team received a note that the software will be delayed by 2
weeks.
The project management team should conduct a meeting with the contractor to
resolve the delivery issues before making the payment.
The project management team should make the payment and reschedule the project
plan.
44. In a software company a large number of simultaneously performed projects utilize the
same groups of human and other resources.
Resource over-allocation.
Resource pooling.
Program management.
45. What does the acronym RAM commonly stand for in project management?
Limits of authorization.
Team preferences.
Physical constraints.
47. A precontract agreement that establishes the intent of a party to buy products or services
is called a
Letter of intent.
Letter of credit.
Individual risks.
Marked for review
49. A project manager performs Earned Value Analysis and finds the following results:
BAC is 500,000.
What is right?
EAC = 400,000.
EAC = 550,000.
BTC = 400,000.
ETC = 75,000.
50. The construction of a residential home will cost a certain amount per square foot of living
space. This is an example of what type of estimating?
Analogous estimating.
Bottom-up estimating.
Top-down estimating.
Parametric modeling.
51. Which of the following should not be reason for “rebaselining” in a project?
Scope changes.
Cost variances.
New information indicating that the basis for the original project cost estimates was
incorrect.
Marked for review
52. When a change control system‘s provision for changes without formal review in case of
emergency is being utilized
Changes can be simply applied without further managerial activities if they help
solving the problem.
Changes must still be documented and captured so that they do not cause problems
later in the project.
53. Which of the following is generally not regarded to be a motivator according to Frederick
Herzberg?
55. You are the project manager and have contracted with a service provider to develop a
complicated software solution This software is necessary to control the machinery
equipment which your project team will develop. It is a lump-sum contract with additional
incentives for meeting predefined schedule targets. The payment schedule and incentives
are as follows:
Yesterday the company submitted the prototype to your project team. This was 2 weeks
after the scheduled delivery date and 3 weeks after the date necessary to qualify for the
incentive payment.
This morning, the manager of the contractor approached you to ask for changes to the
payment schedule. They found that their initial work and costs were much higher than
originally expected and they now wish to increase the second payment to 30% and
reduce the final payment to 10%.
During the discussion you got the impression that the company is in serious financial
trouble.
Point out that the contractor is not in a position to demand a change to the contract.
Audit.
Inspection.
Screening.
It allows one to easily identify the breakdown level of the item in the resource
structure.
It defines ethical behavior in the project and the responsibilities to the customer and
the profession.
58. You are a member of your company's project office. The company is running many
concurrent projects; most of them share a resource pool. Understanding how resources
are utilized across projects is seen as being essential to cost effectiveness and
profitability.
You recently received an inquiry to assess the benefits of using project management
software to manage the company's project portfolio.
59.
Objectives specified with far more detail than necessary for a successful project.
60. You have been assigned to a new project and have finished the scope statement. You and
your team are now going to create a Work Breakdown Structure. You are spending a lot
of time discussing how to create a completely decomposed Work Breakdown Structure.
61. A project manager performs Earned Value Analysis and finds the following results:
CV = 30,000.
CV = -30,000.
CV = 1.
62. During a company event, you had the opportunity to talk to a colleague project manager.
He told you that in his current project actual costs are 15% under cumulated costs
scheduled for today.
The project will probably be completed with total costs remaining under budget.
A significant cost increase during the further course of the project will probably bring
the costs back to baseline level.
Original cost planning must have been poor to allow this variance.
Marked for review
64. Which of the following statements describes the relationship between project phases and
the project life cycle?
The project lifecycle contains the iterative incremental elements inside a project
phase.
Collectively, the project phases are known as the project life cycle.
The project lifecycle is regarded as a sequence of project activities while phases are
defined to control the overlapping of activities.
The project lifecycle contains the repetitive elements inside a project phase
A metaphoric description of the short term uncertainties that are present in every
project.
The graph that describes the typical growth of earned value during the course of the
project.
67. The output of the resource planning process is a document "resource requirements". This
a description of what types of resources are required in what quantities...
It includes investment, direct and indirect costs and may include allowances for
capital cost, depreciation, risk of loss, and/or inflation.
71. Regarding Delphi Technique all of the following statements are true except
The responses are submitted and are then circulated to the experts for further
comment.
72. Regarding quality and grade all of the following statements are true except
Grade is a category or rank given to entities having the same functional use but
different requirements for quality.
Quality is the totality of characteristics of an entity that bear on its ability to satisfy
stated or implied needs.
Quality can simply be improved through intelligent testing and examining, upgrading
requires additional expenses.
Marked for review
73. Network templates which contain only portions of a network are often referred to as
Subnets or fragnets.
Subprojects.
Programs.
WBS items.
74. In making an investment in a project, investors require compensation for which of the
following?
The risk-free rate of return plus a risk premium plus a premium for inflation.
Hammock.
Dangler.
Milestone.
Subtask.
19 25.3
Result: of 75, %
I am...
...generally interested in PMI and in the PMP certification.
Please note: The Solve Sample Test function and some other functions in this page use dynamic HTML which is not
supported by all browsers.If you have difficulties you can find the answers here.
Finished? We love to see results and are interested in any comments. Click here, if you want to
send us yours.
If you would like to receive our free 25 Tips and Tricks for Exam Success please click here.
Of course there is no obligation.
We have a big body of additional support material: More sample questions in our test
simulator, exercises, helpful URLs and literature. And of course we do training and qualify for
success.
More information about professional training and support on your way to the PMP exam can be
found in our website. To visit our homepage please click here.
"PMI", "PMP", "PMBoK" are marks of the Project Management Institute which are registered in the United States of
America and in other nations.
This test is for self assessment only and no guaranty is given for passing the PMP exam.© 2003 Dr. Voight, Lehmann &
Partners, PMPs, Ismaning. Germany. All rights reserved.