You are on page 1of 6

5 The Revay Report 6

documents, most contracts require 3. If a problem arises and the consul- 3. Be mindful of contract clauses These schedules can then be used 8. On-site monitoring of actual prog- 1
McLachlin, Beverley M. and Wilfred J.
the consultant to perform the first tant is not able to provide a solu- requiring the contractor to investi- to explain delays and determine ress is becoming more common as it Wallace, The Canadian Law of Architecture
adjudication of an issue. When the tion, consultation with the team, in gate existing or hidden conditions causation of the additional costs. provides a better case for presenting and Engineering, Butterworth-Heinemann,
claim results from design errors particular the affected trade con- promptly and issue a claim for loss of productivity claims to arbitra- 1987,p.97
and omissions in the contract docu– tractor, may result in the most cost- additional compensation within the 4. Many contracts contain change order tors and courts as well as owner’s
2
Judgments of the Supreme Court of Canada,
procedures and pricing guidelines Canadian National Railway Co. vs Royal and
ments, the consultant is in a con- effective solution without neces- allowed time as per the notice pro- claims consultants. More important-
Sun alliance Insurance Co. of Canada, 2008
flict of interest position and has no sarily sacrificing performance of visions of the contract. Ensure that that provide for a complete and exclu- ly, monitoring actual progress of the SCC66, 20081121 Docket 32062 Project Management and Published by Revay and Associates Limited
incentive to be fair to the contrac- the project for the owner. the timeframe is reasonable and sive remedy for the contractor in the various trades working on site can 3
Revay, Stephen G., Can Construction Claims
achievable. event of changes, including those for Construction Claims Services Volume 29 Number 1 March 2010
tor and award it proper compensa- provide an early warning of prob- be Avoided?, CIB UMIST Conference 1992,
tion in view of its relationship with 4. To protect themselves in case of incomplete or inaccurate design docu– lems12. Both owners and contractors Manchester, England, Building Research and
potential litigation, architects and After a contractor is awarded a con- ments. At the start of a project, the can mitigate damages or losses if Information, Vol. 21, Number 1, 1993
its own insurance carrier. The result 4
Ibid
is a dispute between the contractor engineers are adding more exculpa- tract and finds that the construction contractor should explain to the owner problems are identified early. 5
The Alberta Report – COAA Major Project
and the owner with possible litiga- tory clauses to contract documents documents are incomplete, it should how it will meet the contract require- Benchmarking Summary, Construction
tion costs. A better approach may to make up for incomplete design document, communicate and record ments for changes and agree on what Conclusion Owners Association of Alberta, February
be for the owner to use a third party documents. Statements in supple- problems. The contractor needs to cost items will or will not be included 2009.
mentary conditions to supply and implement proper procedures outlined in the pricing. In 1992, the founder of Revay and 6
Kumaraswamy Mohan M. and Kumaru
neutral who has both knowledge
install contracts (such as CCDC 2) in the contract, or at a minimum do the Associates Limited stated at a confer- Vogeswaran, Significant Sources of
and experience in the construction Construction Claims, The International
that require the contractor to build a following: 5. Be aware of constructive changes ence that “the only way to avoid dis-
environment to provide an inde- Construction Law Review, Vol. 15, January
facility in accordance with all design i.e. changes caused by the owner or putes and/or claims is either to elimi-
pendent opinion on issues that 1998
codes irrespective of what is shown 1. If a contractor discovers that spe- its consultant, which are not acknow– nate or at least reduce significantly the Impact Costs – The Validity and Calculation
arise during construction10. 7

on the drawings and specifications cific owners and/or designers are ledged as changes. For example, opportunities for cost overruns, such of Costs Related to Reduced Productivity,
suggests an insecurity about the less capable of providing complete changes made through revisions to can be achieved only with better pre- The Revay Report, December 1985, Vol. 4,
14. The use of “exemption”, “exculpa-
design. Moreover, this practice is contract documents, or buildable the shop drawings which have cost pared and more comprehensive bid Number 2
tory”, “exclusion” or “limitation of The Effect of Change Orders on Productivity, In 1970 Stephen G. Revay founded a small consulting company in Montreal. Initially the firm provided typical project manage-
not guaranteed to protect the drawings and specifications, it implications which could have or documents.”13
liability” clauses to prevent a con- The Revay Report, August 1987, Vol. 6, No. 2 ment services. Their contractor clients had other ideas; and soon Revay and Associates Limited was also filling the new niche
designer in litigation. should prepare for above-average should have been included in the
tractor from recovering costs due to The Cumulative Effects of Change Orders on market of preparing construction claims. Over the last forty years the company has become a leader in the construction claims
impacts on labour productivity and contract design documents. There are no revolutionary suggested Labour Productivity – The Leonard Study
incomplete contract documents industry and has blazed trails in offering project management, risk management and claims avoidance services; all provided by
5. When consultants have been asked the resulting need to issue and practices in this report, simply some “Reloaded”. The Revay Report, May 2007,
may not be considered as being fair logical fundamentals for achieving the fifty construction professionals in five offices across Canada and one in the United States. This growth would not be possible
why incomplete documents are defend claims. 6. When the number of changes begins Vol. 26, No, 1
by the courts, and may therefore be schedule and cost objectives of a pro– Coping with Extras, The Revay Report, without the loyalty and support of our clients. Thank you for your continued patronage. All of us at Revay and Associates
issued for contracts, the usual to affect productivity, the contractor
either unenforceable or interpreted 2. As soon as a problem is perceived, ject. The most critical of the require- September 2002, Vol. 21, No. 2 Limited look forward to continuing to build business relationships with past, present and future clientele.
response has been that the fees may want to attempt to include in its
to the benefit of the contractor. This provide written notice to the owner ments is having drawings, specifica-
8
Ibbs, William, Impact of Change’s Timing on
are not adequate to do a complete pricing any anticipated impact or loss
should be taken into consideration Labour Productivity, Journal of Construction
or its representative. Some jurisdic-
The Pitfalls of Incomplete Contract Documents
job. Designers should be cautious of productivity costs resulting from tions and other parts of the contract Engineering and Management, November
when drafting a contract11. tions have held that recovery cannot the changes. When impact costs are documents as close to 100% complete
that commercialism does not 2005, pp. 1219 – 1223
replace professionalism. be made without written notice when excluded by the consultant, the con- as possible at the time of executing an 9
Changes in Design / Build Contracts, The
Best Practices for Designer it is a requirement of the contract. tractor should issue a letter of objec- agreement or a contract. If 100% is not Revay Report, April 1997, Vol. 16 No. 2 By Bob Keen, P.Eng., MBA
Consultants Best Practices for Contractors Contractors need to appreciate that tion as soon as possible. Failing to achievable for one reason or another,
10
Facilitating the Construction Dispute Senior Consultant
giving notice to an owner is not only Resolution Process, The Revay Report, Revay and Associates Limited – Toronto
include such costs, failing to issue a then budget contingencies must be
1. Consultants need to define the proj- Prior to signing a contract, the follow- a contractual obligation but it also
March 2004, Vol. 23, No. 1
letter of objection or failing to provide adjusted, an alternative type of con- 11
Mackay, Michael, The Enforceability of
ect in clear and easily interpreted ing is recommended for contactors. provides the owner an opportunity to notice may preclude any remedy at tract should be considered, and the Exclusion Clauses in Cases of Fundamental The signing of a contract with incomplete drawings and specifications is a source of significant risk for
terminology. Generally, when ambi- assist in resolving the cause of an the end of the project. contract documents must make provi- Breach of Contract, Construction Law Letter, owners, general contractors and trade contractors. For all parties to a construction contract, incomplete
guities exist in the contract docu- 1. At the time of tender, if the contract excusable delay or to take steps to sion for fair and equitable adjustments Vol. 26, No.1, September/October 2009 contract documents at the time of awarding a contract substantially increase the risk of major cost over-
ments, the courts have ruled against language or contract requirements minimize any further losses and 7. The contractor should be open to to the time and price in the contract as
12
Monitoring Job-Site Productivity, The Revay runs and project delays.
the author of the documents. are not clear or are conflicting, ask future claims. In addition, our experi- working collaboratively with the changes are issued. Otherwise, the Report, May 2000, Vol. 19, No. 2
13
Revay , Stephen G., Can Construction Claims
for clarification. Differing interpreta- ence has been that contractors owner’s team to develop solutions spectre of claims and potential litiga- Incomplete contract documents invariably lead to claims from contractors for extension of time and
2. Some consultants are reluctant to be Avoided?, CIB UMIST Conference 1992,
tions of the contract documents obtain better results if they commu- that avoid claims or mitigate dam- tion loom on the horizon to the peril of Manchester, England, Building Research and additional compensation. When owners have tight budgets or are reluctant to pay more for a project, a
recommend change orders, approve during construction will simply lead nicate and negotiate during the dispute results. The dispute leads to further increased costs, as senior management of the various par-
ages incurred. all parties involved in the contract. Information, Vol. 21, Number 1, 1993
shop drawings, or respond to to disputes. course of construction rather than ties get involved attempting to resolve issues, frequently with associated legal costs.
requests for information because it waiting until the end of the project. The Revay Report is published by Revay and REVAY OFFICES: Bob Keen
can be interpreted as recognizing 2. Contracts with unfair clauses will Associates Limited, a national firm of Construction This Revay Report addresses the subject of incomplete contract documents, the causes, impacts and recom-
that the contract documents were OTTAWA VANCOUVER
ultimately lead to financial losses 3. Prepare a proper Critical Path and Claims Specialists, assisting owners and MONTREAL
39 Robertson Road 1755 W. Broadway
mended best practices for reducing or eliminating the consequences of inadequate contract documents.
4333 Ste. Catherine St. West
unclear. The carriers of errors and which will not be fully recoverable, Method (CPM) schedule that is fea- contractors in achieving profitable and trouble-
Suite 500 Suite 230 Suite 401
omissions insurance often advise even if addressed by the courts. Be sible, update it monthly and ensure free construction projects. MONTRÉAL, Québec H3Z 1P9 NEPEAN, Ontario K2H 8R2 VANCOUVER, B.C. V6J 4S5 Role of Consultants
Tel.: (514) 932-2188 Tel.: (613) 721-6801 Tel.: (604) 737-2005
consultants to not admit to any errors on guard for disclaimers about site personnel are in agreement with Fax: (514) 939-0776 Fax: (613) 596-8172 Fax: (604) 737-2008
or omissions. Consultants need to Contents may be reproduced, with a credit as The role of architects and engineers to the role defined in the contract, expected of a person of ordinary com-
incomplete plans, incomplete site the sequencing of the work. Actual montreal@revay.com ottawa@revay.com vancouver@revay.com
be reminded that as licensed profes- and soil reports as well as other progress must be monitored. Not
to source appreciated. Your comments and (often referred to as the “consultant” or architects and engineers are also petence, measured by the professional
suggestions for future articles are most welcome. TORONTO CALGARY Revay & Associates Inc.
sionals, they have a duty to act data furnished about the site, or adhering to a planned schedule can 2255 Sheppard Avenue East­­­ 10655 Southport Road, S.W. 1105 N Market Street “design consultant” in construction required to abide by a professional standard of the time1.
impartially and delaying decisions requirements to install as per the result in labour and equipment pro- Edition française disponible sur demande.
Suite 402 ­ Suite 540 Suite 1300 contracts) is determined by the con- standard of care. In all the work done
TORONTO, Ontario M2J 4Y1 CALGARY, Alberta T2W 4Y1 WILMINGTON, DE 19801
and information will result in addi- drawings and specifications as well ductivity losses. In addition, make Tel.: (416) 498-1303 Tel.: (403) 777-4900 Tel.: (302) 427-9340 tract between the owner and the archi- for the client, the architect or engineer Owners and contractors must realize
tional costs to the owner and possi- as meeting specific performance sure a detailed as-built schedule is Please advise the Montreal office of any Fax: (416) 491-0578 Fax: (403) 777-4903 Fax: (302) 651-8426 tect or engineer in traditional design- owes a duty to exercise the skill, care that the consultant’s duty to the owner
toronto@revay.com calgary@revay.com
bly delay the project completion. criteria. prepared as the project progresses. change of address. http://www.revay.com bid-build delivery systems. In addition and diligence which may reasonably be does not mean that drawings, specifi-
Publications #40042162
The Revay Report 2 3 4 Published by Revay and Associates Limited

cations or other contract documents state of engineering art and omni- to determine the common causes of complete their design with the required design of a building facilitates ease of designers simply allocate general Ibbs, the author of several studies on design-bid-build delivery system, tract is awarded than to have them
issued by them will be free of errors science, a standard of perfection in significant claims on contracts. The rigour. construction. The benefits of a con- areas for architectural, mechanical changes, not only reaffirmed that pro– consider using the construction treated as changes later.
and omissions. A consultant is required relation to all foreseeable risks is too results seem to be consistent from structability or buildability review can and electrical components ject change is disruptive and detrimen- management at risk and partnering
to exercise reasonable skill, care and high”2. study to study. In 2003 the Construction Owner’s include: reduced construction cost, tal to labour productivity, but also that approach. With the construction 8. If the project is large, request a con-
diligence as currently practiced in the Association of Alberta (COAA) in part- less interferences, shorter construction 2. Have an outside construction if changes are necessary, they should manager being part of the owner’s structability review to ensure the
profession. The question is at what Expectations of Design Revay’s study encompassed 175 nership with the Government of Alberta times and fewer claims. expert review the drawings at the be recognized and incorporated as team, he can issue tender packa– work can be built in the sequence
point do the number of changes to the Consultants industrial, commercial, institutional undertook a benchmarking initiative with time they are issued for tender to early as possible8. ges and trade contracts as portions and manner portrayed by the
contract resulting from design errors and heavy engineering construction the Construction Industry Institute (CII). Constructability reviews are most effec- discover constructability issues of the design are completed, result- designer. Recognize that this is not
and omissions become unacceptable? Design consultants expect that the projects which, on average, had claims In analyzing thirty-seven mega projects5 tive when performed prior to completion Owners should not expect to obtain ing in fewer changes and delays. normally an expertise developed in
owners know what they want and can amounting to 30% of the construction it was found that the percent of engi- of the design. Owners must realize that 3. Prepare CAD drawings in three changes to a project at the same price Partnering can improve communi- house by design consultants.
The typical method of allowing for communicate all of their needs to the value3. neering completed prior to the start of decisions or changes made after con- dimensions that show the relation- as if those items were included in the cation and provides for a shortened
errors and omissions is to include a consulting teams. However, most own- construction was the common factor struction begins are more difficult and ships and interferences of struc- original contract. Not only may the process of decision making, there- 9. Owners should require a review of
design contingency in the owner’s bud- ers do not have extensive design and Four of the major causes for claims that impacted project cost, project more costly to implement. tural, architectural, mechanical and labour cost be higher, but materials by reducing the probability of the drawings and specifications prior
get. An allowance of 2% to 5% may be construction experience in-house and were: schedule and construction productivity. electrical components purchased in smaller quantities may delays and disruptions. This pro- to the tender stage by their operating
appropriate for new construction rely on the expertise of the consultants While the benefits of constructability cost more, equipment may have to be cess results in a higher probability and maintenance personnel to
whereas a contingency of 10% to 15% to assist them in defining the perfor- • Inadequate site and/or subsurface In a study published in the International reviews are recognized, they are sel- 4. Have a group of senior trade super- returned to the site for a shorter period of completion in the required time ensure there is sufficient space to
may be required for renovation pro– mance requirements of the project and investigation prior to starting the Construction Law Review, authors dom employed. The reasons are the intendents and general foremen of time, and the project may have to be frame, however, it may not elimi- service equipment and that the new
jects. Additional design and construc- their implementation. design Kumaraswamy and Yogeswaran6, lack of construction experience in the from the general contractor/con- extended with its associated indirect facility will achieve its intended pur-
nate or even reduce claims, partic-
tion contingencies may be required for found that the source of the most fre- design team, the absence of guidelines struction manager and each of its costs. The most cost effective solution ularly if the construction documents pose. Note that not all operating and
Design consultants also expect owners • Starting design efforts too late and quent claims and those of greatest subcontractors meet on a regular
a renovation, especially where the abi– to assist designers in evaluating con- is to minimize the number of changes, are faulty or incomplete. maintenance personnel are familiar
to make quick decisions. When owners /or unduly limiting the cost of engi- magnitude are: basis to resolve the interferences
lity to investigate existing conditions is structability, the inability to obtain con- and ensure contract documents are with engineering drawings and speci–
lack the required expertise, they are neering and design and inadequacies of the design?
limited or prevented by the owner for tractor input at the design stage due to complete when a contract is signed. 5. Where parts of a facility cannot be fications. As such, detailed explana-
operational reasons. often slower in making decisions and • Unclear documentation bidding practices, the lack of a cham- included in the contract due to delay tions and/or three dimensional CAD
• Calling for bids with an incomplete
the designers are then squeezed for pion of the constructability process on Impact of Inadequate Contract Best Practices for Owners of part of the financing, the tender sketches from the consultants should
set of drawings
In recent years, owners and contrac- time to finalize and issue the design • Inadequate documentation the part of the owner and the consul- Documents document should be divided into be made available.
tors have become less accepting of documents. 1. Owners need to recognize there is alternatives to establish a base price
• Endeavouring to complete the tant, the objective of minimizing costs
errors and omissions by consultants. • Inadequate site investigation If the contract documents are inade- an implied warranty that the draw- 10. Owners should demand that con-
design through shop drawing at the design stage and the desire to and the pricing of future alternatives
Owners recognize that they may not
Expectations of Contractors quate or incomplete, the most serious ings and specifications that they when financing permits. This advises sultants provide 100% complete
review. put a shovel into the ground as soon as
• Late or inadequate instructions impact is an abundance of changes to
recover the full cost of a change result- possible (fast track). provide to the contractors as part the contractor and sets into the con- contract documents at the time a
In providing a price, contractors expect the work. Changes come about as a
ing from an error or omission by the The common feature of all these pro– • Changes initiated by the owner and of a contract are accurate, com- tract the exact circumstances under contract is tendered. If necessary,
that the contract documents are com- result of:
consultants and contractors recognize
plete and reflect the project require- jects was hurriedly and incompletely consultant. Design Coordination plete and buildable and that the which portions of the project will pro- cash allowances should be well
that errors and omissions can lead to prepared bid documents, giving rise to contractor is not responsible for ceed, and maintains the competitive defined.
ments, and that any changes, errors or • Additional requests from the owner
significant delays and disruptions to design changes, extra work, and quan- As shown in the above studies, the To avoid confusion, design coordination the consequences of defects in the pricing for additional work without it
omissions from the documents will lead by way of added / changed scope
the planned schedule of work. tity fluctuation during the project. seeds for most construction claims have responsibility should be spelled out in plans and specifications. having to be priced as a change to 11. Value engineering can be a mixed
to a change order with commensurate
been sown prior to awarding a con- the contract documents. However, this the contract. blessing. Generally, the intent is for
adjustment to both the contract price • Errors and omissions on the drawings
Expectations of Owners and duration. Many owners would argue that even struction contract, primarily as a result is rarely done satisfactorily which cre- and specifications leading to revi- 2. In the context of a traditional the contractors to provide sugges-
such a high premium can be justified of incomplete contract documents. ates an atmosphere of uncertainty and sions design-bid-build delivery, the owner 6. Include in the consultant’s contract tions to reduce the cost of a project.
There is a growing trend for owners to as long as the facility starts earning mistrust. While it is often expected that should not skimp on the front 10% that a representative of the consul- If it is performed after a contract is
As the bidding is done in a competitive
stipulate that a construction project is environment, contractors and their sub- revenue on the scheduled date. The above can be mitigated by a more the designer will provide direction to the • Unforeseen or hidden conditions on of the project costs (architectural tant be available (preferably located awarded, it could delay the “issued
to be built on a “fast track” basis; in contractors are reluctant to add various Unfortunately, experience does not thorough design prior to construction. various trades through the design docu- site which should have been identi- and engineering) at the expense of on site) to respond to requests for for construction drawings” and the
other words, starting construction prior contingencies and allowances to their support such an argument. The analy- Additionally, constructability reviews ments, in reality, trade contractors are fied through earlier investigations the latter 90% of the project (cons– information, resolve issues and project as the consultants will have
to the design being 100% complete. tendered price, fearing that they will not sis of 145 projects out of the total 175 and design coordination are two more frequently instructed through the design truction). recommend or approve changes to verify that the proposed solution
On the surface, this is understandable be successful as low bidder. While the (i.e. the projects for which appropriate ways that the impact of incomplete documents to produce trade coordina- • Lack of essential coordination to iden- quickly. The ability of a contractor will work and is indeed cost effec-
from a financial perspective; the sooner design may have taken several months information was available) revealed contract documents can be minimized. tion drawings showing locations of major tify and eliminate design conflicts. 3. Consider design-build as a means to achieve the contracted schedule tive. A subsequent claim for delays
a project starts generating revenue, the to complete, the contractor is often that nearly all of them suffered signifi- pieces of equipment and services to of project delivery where the owner is facilitated by the owner and its could outstrip any cost savings.
greater the return on investment. At the unfairly expected to verify the consul- cant delays, notwithstanding any Constructibility reviews reveal interferences between various While a few changes may have a negli- feels that close control of the design representatives providing timely
same time, owners expect the project tants” drawings and specifications for attempted acceleration. The average pieces of equipment. The question gible impact on labour productivity, a is not essential. As the designer and responses to submittals, requests 12. There is a movement by large own-
will be built within budget and on time deficiencies or completeness during a delay was 5.69 months, representing Constructability reviews that could mini- becomes who is responsible for coordi- large number of changes can have a the contractor are on the same for information and change orders. ers, particularly in the USA, to
and have high expectations of their much shorter bidding period. To remain nearly a 50% overrun in the average mize construction problems are not usu- nating the various design disciplines? major impact on labour productivity as team, external decision making is require the use of Building
consultants. Owners expect that the competitive, a contractor should be planned duration. Had the owners ally performed after the design is com- well as creating significant delays to minimized resulting in fewer delays 7. If the project is large (say greater Information Modelling (BIM). These
consultants will commit their needs to able to rely entirely on the contract spent four to five months more in pleted as the pressure to get the tender The answer is based on economics and the project. These losses in labour pro- and disruptions. However if the than $100 million), request a peer systems have been able to identify
paper and issue contract documents documents, and its price reflect the investigating, planning and designing documents out for bid is intense. it needs to be addressed early in the ductivity and the resultant extended owner cannot clearly and complete- review of the design for errors and weaknesses in design documents
with minimal errors and omissions, not scope of work outlined in the docu- these projects than they actually did, design process. Is it more cost effec- duration of the project usually lead to ly communicate its requirement to omissions. Owners have to recog- and provide methodologies to track
always recognizing that to expect per- ments alone, even if the contract is they would have saved at least 20% of The Construction Industry Institute tive to: claims for additional compensation. the design-builder, then this process nize that the design of a facility is the resulting changes. While this
fection from a consultant is not reason- loaded with exculpatory clauses. the actual cost even had they paid defines constructability as “the use of will be fraught with changes, delays not an exact science, and simply may be costly at the outset, 3D
able. In the decision of the Canadian approximately 50% more to their construction knowledge and experi- 1. Have the design team review areas In previous Revay Reports we have and also result in claims9. allowing a contingency for design models could prevent costly chan–
National Railway Co. vs Royal and Sun Causes of Claims designers4. It is safe to state that the ence in planning, design, procurement of potential interference and pre– outlined some of the studies that have errors and omissions may not be ges and delays during construction.
Alliance Insurance Co. of Canada, ultimate cost of the project would be and field operations to achieve overall sent additional details on the draw- been used to calculate the damages 4. If the design is less than 80% com- the most cost-effective approach.
Judge Binnie states that “as there is Revay and Associates and other significantly lower if owners allowed project objectives”. Similarly “buildabili- ings showing appropriate dimen- resulting from a large number of plete at the time of tender, rather It is more cost-effective to find 13. In resolving claims and disputes
inevitably a gap between the current researchers have conducted studies more time to the design consultants to ty” is defined as the extent to which the sioning as opposed to having changes7. than proceeding with the traditional errors and omissions before a con- resulting from incomplete contract
The Revay Report 2 3 4 Published by Revay and Associates Limited

cations or other contract documents state of engineering art and omni- to determine the common causes of complete their design with the required design of a building facilitates ease of designers simply allocate general Ibbs, the author of several studies on design-bid-build delivery system, tract is awarded than to have them
issued by them will be free of errors science, a standard of perfection in significant claims on contracts. The rigour. construction. The benefits of a con- areas for architectural, mechanical changes, not only reaffirmed that pro– consider using the construction treated as changes later.
and omissions. A consultant is required relation to all foreseeable risks is too results seem to be consistent from structability or buildability review can and electrical components ject change is disruptive and detrimen- management at risk and partnering
to exercise reasonable skill, care and high”2. study to study. In 2003 the Construction Owner’s include: reduced construction cost, tal to labour productivity, but also that approach. With the construction 8. If the project is large, request a con-
diligence as currently practiced in the Association of Alberta (COAA) in part- less interferences, shorter construction 2. Have an outside construction if changes are necessary, they should manager being part of the owner’s structability review to ensure the
profession. The question is at what Expectations of Design Revay’s study encompassed 175 nership with the Government of Alberta times and fewer claims. expert review the drawings at the be recognized and incorporated as team, he can issue tender packa– work can be built in the sequence
point do the number of changes to the Consultants industrial, commercial, institutional undertook a benchmarking initiative with time they are issued for tender to early as possible8. ges and trade contracts as portions and manner portrayed by the
contract resulting from design errors and heavy engineering construction the Construction Industry Institute (CII). Constructability reviews are most effec- discover constructability issues of the design are completed, result- designer. Recognize that this is not
and omissions become unacceptable? Design consultants expect that the projects which, on average, had claims In analyzing thirty-seven mega projects5 tive when performed prior to completion Owners should not expect to obtain ing in fewer changes and delays. normally an expertise developed in
owners know what they want and can amounting to 30% of the construction it was found that the percent of engi- of the design. Owners must realize that 3. Prepare CAD drawings in three changes to a project at the same price Partnering can improve communi- house by design consultants.
The typical method of allowing for communicate all of their needs to the value3. neering completed prior to the start of decisions or changes made after con- dimensions that show the relation- as if those items were included in the cation and provides for a shortened
errors and omissions is to include a consulting teams. However, most own- construction was the common factor struction begins are more difficult and ships and interferences of struc- original contract. Not only may the process of decision making, there- 9. Owners should require a review of
design contingency in the owner’s bud- ers do not have extensive design and Four of the major causes for claims that impacted project cost, project more costly to implement. tural, architectural, mechanical and labour cost be higher, but materials by reducing the probability of the drawings and specifications prior
get. An allowance of 2% to 5% may be construction experience in-house and were: schedule and construction productivity. electrical components purchased in smaller quantities may delays and disruptions. This pro- to the tender stage by their operating
appropriate for new construction rely on the expertise of the consultants While the benefits of constructability cost more, equipment may have to be cess results in a higher probability and maintenance personnel to
whereas a contingency of 10% to 15% to assist them in defining the perfor- • Inadequate site and/or subsurface In a study published in the International reviews are recognized, they are sel- 4. Have a group of senior trade super- returned to the site for a shorter period of completion in the required time ensure there is sufficient space to
may be required for renovation pro– mance requirements of the project and investigation prior to starting the Construction Law Review, authors dom employed. The reasons are the intendents and general foremen of time, and the project may have to be frame, however, it may not elimi- service equipment and that the new
jects. Additional design and construc- their implementation. design Kumaraswamy and Yogeswaran6, lack of construction experience in the from the general contractor/con- extended with its associated indirect facility will achieve its intended pur-
nate or even reduce claims, partic-
tion contingencies may be required for found that the source of the most fre- design team, the absence of guidelines struction manager and each of its costs. The most cost effective solution ularly if the construction documents pose. Note that not all operating and
Design consultants also expect owners • Starting design efforts too late and quent claims and those of greatest subcontractors meet on a regular
a renovation, especially where the abi– to assist designers in evaluating con- is to minimize the number of changes, are faulty or incomplete. maintenance personnel are familiar
to make quick decisions. When owners /or unduly limiting the cost of engi- magnitude are: basis to resolve the interferences
lity to investigate existing conditions is structability, the inability to obtain con- and ensure contract documents are with engineering drawings and speci–
lack the required expertise, they are neering and design and inadequacies of the design?
limited or prevented by the owner for tractor input at the design stage due to complete when a contract is signed. 5. Where parts of a facility cannot be fications. As such, detailed explana-
operational reasons. often slower in making decisions and • Unclear documentation bidding practices, the lack of a cham- included in the contract due to delay tions and/or three dimensional CAD
• Calling for bids with an incomplete
the designers are then squeezed for pion of the constructability process on Impact of Inadequate Contract Best Practices for Owners of part of the financing, the tender sketches from the consultants should
set of drawings
In recent years, owners and contrac- time to finalize and issue the design • Inadequate documentation the part of the owner and the consul- Documents document should be divided into be made available.
tors have become less accepting of documents. 1. Owners need to recognize there is alternatives to establish a base price
• Endeavouring to complete the tant, the objective of minimizing costs
errors and omissions by consultants. • Inadequate site investigation If the contract documents are inade- an implied warranty that the draw- 10. Owners should demand that con-
design through shop drawing at the design stage and the desire to and the pricing of future alternatives
Owners recognize that they may not
Expectations of Contractors quate or incomplete, the most serious ings and specifications that they when financing permits. This advises sultants provide 100% complete
review. put a shovel into the ground as soon as
• Late or inadequate instructions impact is an abundance of changes to
recover the full cost of a change result- possible (fast track). provide to the contractors as part the contractor and sets into the con- contract documents at the time a
In providing a price, contractors expect the work. Changes come about as a
ing from an error or omission by the The common feature of all these pro– • Changes initiated by the owner and of a contract are accurate, com- tract the exact circumstances under contract is tendered. If necessary,
that the contract documents are com- result of:
consultants and contractors recognize
plete and reflect the project require- jects was hurriedly and incompletely consultant. Design Coordination plete and buildable and that the which portions of the project will pro- cash allowances should be well
that errors and omissions can lead to prepared bid documents, giving rise to contractor is not responsible for ceed, and maintains the competitive defined.
ments, and that any changes, errors or • Additional requests from the owner
significant delays and disruptions to design changes, extra work, and quan- As shown in the above studies, the To avoid confusion, design coordination the consequences of defects in the pricing for additional work without it
omissions from the documents will lead by way of added / changed scope
the planned schedule of work. tity fluctuation during the project. seeds for most construction claims have responsibility should be spelled out in plans and specifications. having to be priced as a change to 11. Value engineering can be a mixed
to a change order with commensurate
been sown prior to awarding a con- the contract documents. However, this the contract. blessing. Generally, the intent is for
adjustment to both the contract price • Errors and omissions on the drawings
Expectations of Owners and duration. Many owners would argue that even struction contract, primarily as a result is rarely done satisfactorily which cre- and specifications leading to revi- 2. In the context of a traditional the contractors to provide sugges-
such a high premium can be justified of incomplete contract documents. ates an atmosphere of uncertainty and sions design-bid-build delivery, the owner 6. Include in the consultant’s contract tions to reduce the cost of a project.
There is a growing trend for owners to as long as the facility starts earning mistrust. While it is often expected that should not skimp on the front 10% that a representative of the consul- If it is performed after a contract is
As the bidding is done in a competitive
stipulate that a construction project is environment, contractors and their sub- revenue on the scheduled date. The above can be mitigated by a more the designer will provide direction to the • Unforeseen or hidden conditions on of the project costs (architectural tant be available (preferably located awarded, it could delay the “issued
to be built on a “fast track” basis; in contractors are reluctant to add various Unfortunately, experience does not thorough design prior to construction. various trades through the design docu- site which should have been identi- and engineering) at the expense of on site) to respond to requests for for construction drawings” and the
other words, starting construction prior contingencies and allowances to their support such an argument. The analy- Additionally, constructability reviews ments, in reality, trade contractors are fied through earlier investigations the latter 90% of the project (cons– information, resolve issues and project as the consultants will have
to the design being 100% complete. tendered price, fearing that they will not sis of 145 projects out of the total 175 and design coordination are two more frequently instructed through the design truction). recommend or approve changes to verify that the proposed solution
On the surface, this is understandable be successful as low bidder. While the (i.e. the projects for which appropriate ways that the impact of incomplete documents to produce trade coordina- • Lack of essential coordination to iden- quickly. The ability of a contractor will work and is indeed cost effec-
from a financial perspective; the sooner design may have taken several months information was available) revealed contract documents can be minimized. tion drawings showing locations of major tify and eliminate design conflicts. 3. Consider design-build as a means to achieve the contracted schedule tive. A subsequent claim for delays
a project starts generating revenue, the to complete, the contractor is often that nearly all of them suffered signifi- pieces of equipment and services to of project delivery where the owner is facilitated by the owner and its could outstrip any cost savings.
greater the return on investment. At the unfairly expected to verify the consul- cant delays, notwithstanding any Constructibility reviews reveal interferences between various While a few changes may have a negli- feels that close control of the design representatives providing timely
same time, owners expect the project tants” drawings and specifications for attempted acceleration. The average pieces of equipment. The question gible impact on labour productivity, a is not essential. As the designer and responses to submittals, requests 12. There is a movement by large own-
will be built within budget and on time deficiencies or completeness during a delay was 5.69 months, representing Constructability reviews that could mini- becomes who is responsible for coordi- large number of changes can have a the contractor are on the same for information and change orders. ers, particularly in the USA, to
and have high expectations of their much shorter bidding period. To remain nearly a 50% overrun in the average mize construction problems are not usu- nating the various design disciplines? major impact on labour productivity as team, external decision making is require the use of Building
consultants. Owners expect that the competitive, a contractor should be planned duration. Had the owners ally performed after the design is com- well as creating significant delays to minimized resulting in fewer delays 7. If the project is large (say greater Information Modelling (BIM). These
consultants will commit their needs to able to rely entirely on the contract spent four to five months more in pleted as the pressure to get the tender The answer is based on economics and the project. These losses in labour pro- and disruptions. However if the than $100 million), request a peer systems have been able to identify
paper and issue contract documents documents, and its price reflect the investigating, planning and designing documents out for bid is intense. it needs to be addressed early in the ductivity and the resultant extended owner cannot clearly and complete- review of the design for errors and weaknesses in design documents
with minimal errors and omissions, not scope of work outlined in the docu- these projects than they actually did, design process. Is it more cost effec- duration of the project usually lead to ly communicate its requirement to omissions. Owners have to recog- and provide methodologies to track
always recognizing that to expect per- ments alone, even if the contract is they would have saved at least 20% of The Construction Industry Institute tive to: claims for additional compensation. the design-builder, then this process nize that the design of a facility is the resulting changes. While this
fection from a consultant is not reason- loaded with exculpatory clauses. the actual cost even had they paid defines constructability as “the use of will be fraught with changes, delays not an exact science, and simply may be costly at the outset, 3D
able. In the decision of the Canadian approximately 50% more to their construction knowledge and experi- 1. Have the design team review areas In previous Revay Reports we have and also result in claims9. allowing a contingency for design models could prevent costly chan–
National Railway Co. vs Royal and Sun Causes of Claims designers4. It is safe to state that the ence in planning, design, procurement of potential interference and pre– outlined some of the studies that have errors and omissions may not be ges and delays during construction.
Alliance Insurance Co. of Canada, ultimate cost of the project would be and field operations to achieve overall sent additional details on the draw- been used to calculate the damages 4. If the design is less than 80% com- the most cost-effective approach.
Judge Binnie states that “as there is Revay and Associates and other significantly lower if owners allowed project objectives”. Similarly “buildabili- ings showing appropriate dimen- resulting from a large number of plete at the time of tender, rather It is more cost-effective to find 13. In resolving claims and disputes
inevitably a gap between the current researchers have conducted studies more time to the design consultants to ty” is defined as the extent to which the sioning as opposed to having changes7. than proceeding with the traditional errors and omissions before a con- resulting from incomplete contract
The Revay Report 2 3 4 Published by Revay and Associates Limited

cations or other contract documents state of engineering art and omni- to determine the common causes of complete their design with the required design of a building facilitates ease of designers simply allocate general Ibbs, the author of several studies on design-bid-build delivery system, tract is awarded than to have them
issued by them will be free of errors science, a standard of perfection in significant claims on contracts. The rigour. construction. The benefits of a con- areas for architectural, mechanical changes, not only reaffirmed that pro– consider using the construction treated as changes later.
and omissions. A consultant is required relation to all foreseeable risks is too results seem to be consistent from structability or buildability review can and electrical components ject change is disruptive and detrimen- management at risk and partnering
to exercise reasonable skill, care and high”2. study to study. In 2003 the Construction Owner’s include: reduced construction cost, tal to labour productivity, but also that approach. With the construction 8. If the project is large, request a con-
diligence as currently practiced in the Association of Alberta (COAA) in part- less interferences, shorter construction 2. Have an outside construction if changes are necessary, they should manager being part of the owner’s structability review to ensure the
profession. The question is at what Expectations of Design Revay’s study encompassed 175 nership with the Government of Alberta times and fewer claims. expert review the drawings at the be recognized and incorporated as team, he can issue tender packa– work can be built in the sequence
point do the number of changes to the Consultants industrial, commercial, institutional undertook a benchmarking initiative with time they are issued for tender to early as possible8. ges and trade contracts as portions and manner portrayed by the
contract resulting from design errors and heavy engineering construction the Construction Industry Institute (CII). Constructability reviews are most effec- discover constructability issues of the design are completed, result- designer. Recognize that this is not
and omissions become unacceptable? Design consultants expect that the projects which, on average, had claims In analyzing thirty-seven mega projects5 tive when performed prior to completion Owners should not expect to obtain ing in fewer changes and delays. normally an expertise developed in
owners know what they want and can amounting to 30% of the construction it was found that the percent of engi- of the design. Owners must realize that 3. Prepare CAD drawings in three changes to a project at the same price Partnering can improve communi- house by design consultants.
The typical method of allowing for communicate all of their needs to the value3. neering completed prior to the start of decisions or changes made after con- dimensions that show the relation- as if those items were included in the cation and provides for a shortened
errors and omissions is to include a consulting teams. However, most own- construction was the common factor struction begins are more difficult and ships and interferences of struc- original contract. Not only may the process of decision making, there- 9. Owners should require a review of
design contingency in the owner’s bud- ers do not have extensive design and Four of the major causes for claims that impacted project cost, project more costly to implement. tural, architectural, mechanical and labour cost be higher, but materials by reducing the probability of the drawings and specifications prior
get. An allowance of 2% to 5% may be construction experience in-house and were: schedule and construction productivity. electrical components purchased in smaller quantities may delays and disruptions. This pro- to the tender stage by their operating
appropriate for new construction rely on the expertise of the consultants While the benefits of constructability cost more, equipment may have to be cess results in a higher probability and maintenance personnel to
whereas a contingency of 10% to 15% to assist them in defining the perfor- • Inadequate site and/or subsurface In a study published in the International reviews are recognized, they are sel- 4. Have a group of senior trade super- returned to the site for a shorter period of completion in the required time ensure there is sufficient space to
may be required for renovation pro– mance requirements of the project and investigation prior to starting the Construction Law Review, authors dom employed. The reasons are the intendents and general foremen of time, and the project may have to be frame, however, it may not elimi- service equipment and that the new
jects. Additional design and construc- their implementation. design Kumaraswamy and Yogeswaran6, lack of construction experience in the from the general contractor/con- extended with its associated indirect facility will achieve its intended pur-
nate or even reduce claims, partic-
tion contingencies may be required for found that the source of the most fre- design team, the absence of guidelines struction manager and each of its costs. The most cost effective solution ularly if the construction documents pose. Note that not all operating and
Design consultants also expect owners • Starting design efforts too late and quent claims and those of greatest subcontractors meet on a regular
a renovation, especially where the abi– to assist designers in evaluating con- is to minimize the number of changes, are faulty or incomplete. maintenance personnel are familiar
to make quick decisions. When owners /or unduly limiting the cost of engi- magnitude are: basis to resolve the interferences
lity to investigate existing conditions is structability, the inability to obtain con- and ensure contract documents are with engineering drawings and speci–
lack the required expertise, they are neering and design and inadequacies of the design?
limited or prevented by the owner for tractor input at the design stage due to complete when a contract is signed. 5. Where parts of a facility cannot be fications. As such, detailed explana-
operational reasons. often slower in making decisions and • Unclear documentation bidding practices, the lack of a cham- included in the contract due to delay tions and/or three dimensional CAD
• Calling for bids with an incomplete
the designers are then squeezed for pion of the constructability process on Impact of Inadequate Contract Best Practices for Owners of part of the financing, the tender sketches from the consultants should
set of drawings
In recent years, owners and contrac- time to finalize and issue the design • Inadequate documentation the part of the owner and the consul- Documents document should be divided into be made available.
tors have become less accepting of documents. 1. Owners need to recognize there is alternatives to establish a base price
• Endeavouring to complete the tant, the objective of minimizing costs
errors and omissions by consultants. • Inadequate site investigation If the contract documents are inade- an implied warranty that the draw- 10. Owners should demand that con-
design through shop drawing at the design stage and the desire to and the pricing of future alternatives
Owners recognize that they may not
Expectations of Contractors quate or incomplete, the most serious ings and specifications that they when financing permits. This advises sultants provide 100% complete
review. put a shovel into the ground as soon as
• Late or inadequate instructions impact is an abundance of changes to
recover the full cost of a change result- possible (fast track). provide to the contractors as part the contractor and sets into the con- contract documents at the time a
In providing a price, contractors expect the work. Changes come about as a
ing from an error or omission by the The common feature of all these pro– • Changes initiated by the owner and of a contract are accurate, com- tract the exact circumstances under contract is tendered. If necessary,
that the contract documents are com- result of:
consultants and contractors recognize
plete and reflect the project require- jects was hurriedly and incompletely consultant. Design Coordination plete and buildable and that the which portions of the project will pro- cash allowances should be well
that errors and omissions can lead to prepared bid documents, giving rise to contractor is not responsible for ceed, and maintains the competitive defined.
ments, and that any changes, errors or • Additional requests from the owner
significant delays and disruptions to design changes, extra work, and quan- As shown in the above studies, the To avoid confusion, design coordination the consequences of defects in the pricing for additional work without it
omissions from the documents will lead by way of added / changed scope
the planned schedule of work. tity fluctuation during the project. seeds for most construction claims have responsibility should be spelled out in plans and specifications. having to be priced as a change to 11. Value engineering can be a mixed
to a change order with commensurate
been sown prior to awarding a con- the contract documents. However, this the contract. blessing. Generally, the intent is for
adjustment to both the contract price • Errors and omissions on the drawings
Expectations of Owners and duration. Many owners would argue that even struction contract, primarily as a result is rarely done satisfactorily which cre- and specifications leading to revi- 2. In the context of a traditional the contractors to provide sugges-
such a high premium can be justified of incomplete contract documents. ates an atmosphere of uncertainty and sions design-bid-build delivery, the owner 6. Include in the consultant’s contract tions to reduce the cost of a project.
There is a growing trend for owners to as long as the facility starts earning mistrust. While it is often expected that should not skimp on the front 10% that a representative of the consul- If it is performed after a contract is
As the bidding is done in a competitive
stipulate that a construction project is environment, contractors and their sub- revenue on the scheduled date. The above can be mitigated by a more the designer will provide direction to the • Unforeseen or hidden conditions on of the project costs (architectural tant be available (preferably located awarded, it could delay the “issued
to be built on a “fast track” basis; in contractors are reluctant to add various Unfortunately, experience does not thorough design prior to construction. various trades through the design docu- site which should have been identi- and engineering) at the expense of on site) to respond to requests for for construction drawings” and the
other words, starting construction prior contingencies and allowances to their support such an argument. The analy- Additionally, constructability reviews ments, in reality, trade contractors are fied through earlier investigations the latter 90% of the project (cons– information, resolve issues and project as the consultants will have
to the design being 100% complete. tendered price, fearing that they will not sis of 145 projects out of the total 175 and design coordination are two more frequently instructed through the design truction). recommend or approve changes to verify that the proposed solution
On the surface, this is understandable be successful as low bidder. While the (i.e. the projects for which appropriate ways that the impact of incomplete documents to produce trade coordina- • Lack of essential coordination to iden- quickly. The ability of a contractor will work and is indeed cost effec-
from a financial perspective; the sooner design may have taken several months information was available) revealed contract documents can be minimized. tion drawings showing locations of major tify and eliminate design conflicts. 3. Consider design-build as a means to achieve the contracted schedule tive. A subsequent claim for delays
a project starts generating revenue, the to complete, the contractor is often that nearly all of them suffered signifi- pieces of equipment and services to of project delivery where the owner is facilitated by the owner and its could outstrip any cost savings.
greater the return on investment. At the unfairly expected to verify the consul- cant delays, notwithstanding any Constructibility reviews reveal interferences between various While a few changes may have a negli- feels that close control of the design representatives providing timely
same time, owners expect the project tants” drawings and specifications for attempted acceleration. The average pieces of equipment. The question gible impact on labour productivity, a is not essential. As the designer and responses to submittals, requests 12. There is a movement by large own-
will be built within budget and on time deficiencies or completeness during a delay was 5.69 months, representing Constructability reviews that could mini- becomes who is responsible for coordi- large number of changes can have a the contractor are on the same for information and change orders. ers, particularly in the USA, to
and have high expectations of their much shorter bidding period. To remain nearly a 50% overrun in the average mize construction problems are not usu- nating the various design disciplines? major impact on labour productivity as team, external decision making is require the use of Building
consultants. Owners expect that the competitive, a contractor should be planned duration. Had the owners ally performed after the design is com- well as creating significant delays to minimized resulting in fewer delays 7. If the project is large (say greater Information Modelling (BIM). These
consultants will commit their needs to able to rely entirely on the contract spent four to five months more in pleted as the pressure to get the tender The answer is based on economics and the project. These losses in labour pro- and disruptions. However if the than $100 million), request a peer systems have been able to identify
paper and issue contract documents documents, and its price reflect the investigating, planning and designing documents out for bid is intense. it needs to be addressed early in the ductivity and the resultant extended owner cannot clearly and complete- review of the design for errors and weaknesses in design documents
with minimal errors and omissions, not scope of work outlined in the docu- these projects than they actually did, design process. Is it more cost effec- duration of the project usually lead to ly communicate its requirement to omissions. Owners have to recog- and provide methodologies to track
always recognizing that to expect per- ments alone, even if the contract is they would have saved at least 20% of The Construction Industry Institute tive to: claims for additional compensation. the design-builder, then this process nize that the design of a facility is the resulting changes. While this
fection from a consultant is not reason- loaded with exculpatory clauses. the actual cost even had they paid defines constructability as “the use of will be fraught with changes, delays not an exact science, and simply may be costly at the outset, 3D
able. In the decision of the Canadian approximately 50% more to their construction knowledge and experi- 1. Have the design team review areas In previous Revay Reports we have and also result in claims9. allowing a contingency for design models could prevent costly chan–
National Railway Co. vs Royal and Sun Causes of Claims designers4. It is safe to state that the ence in planning, design, procurement of potential interference and pre– outlined some of the studies that have errors and omissions may not be ges and delays during construction.
Alliance Insurance Co. of Canada, ultimate cost of the project would be and field operations to achieve overall sent additional details on the draw- been used to calculate the damages 4. If the design is less than 80% com- the most cost-effective approach.
Judge Binnie states that “as there is Revay and Associates and other significantly lower if owners allowed project objectives”. Similarly “buildabili- ings showing appropriate dimen- resulting from a large number of plete at the time of tender, rather It is more cost-effective to find 13. In resolving claims and disputes
inevitably a gap between the current researchers have conducted studies more time to the design consultants to ty” is defined as the extent to which the sioning as opposed to having changes7. than proceeding with the traditional errors and omissions before a con- resulting from incomplete contract
5 The Revay Report 6

documents, most contracts require 3. If a problem arises and the consul- 3. Be mindful of contract clauses These schedules can then be used 8. On-site monitoring of actual prog- 1
McLachlin, Beverley M. and Wilfred J.
the consultant to perform the first tant is not able to provide a solu- requiring the contractor to investi- to explain delays and determine ress is becoming more common as it Wallace, The Canadian Law of Architecture
adjudication of an issue. When the tion, consultation with the team, in gate existing or hidden conditions causation of the additional costs. provides a better case for presenting and Engineering, Butterworth-Heinemann,
claim results from design errors particular the affected trade con- promptly and issue a claim for loss of productivity claims to arbitra- 1987,p.97
and omissions in the contract docu– tractor, may result in the most cost- additional compensation within the 4. Many contracts contain change order tors and courts as well as owner’s
2
Judgments of the Supreme Court of Canada,
procedures and pricing guidelines Canadian National Railway Co. vs Royal and
ments, the consultant is in a con- effective solution without neces- allowed time as per the notice pro- claims consultants. More important-
Sun alliance Insurance Co. of Canada, 2008
flict of interest position and has no sarily sacrificing performance of visions of the contract. Ensure that that provide for a complete and exclu- ly, monitoring actual progress of the SCC66, 20081121 Docket 32062 Project Management and Published by Revay and Associates Limited
incentive to be fair to the contrac- the project for the owner. the timeframe is reasonable and sive remedy for the contractor in the various trades working on site can 3
Revay, Stephen G., Can Construction Claims
achievable. event of changes, including those for Construction Claims Services Volume 29 Number 1 March 2010
tor and award it proper compensa- provide an early warning of prob- be Avoided?, CIB UMIST Conference 1992,
tion in view of its relationship with 4. To protect themselves in case of incomplete or inaccurate design docu– lems12. Both owners and contractors Manchester, England, Building Research and
potential litigation, architects and After a contractor is awarded a con- ments. At the start of a project, the can mitigate damages or losses if Information, Vol. 21, Number 1, 1993
its own insurance carrier. The result 4
Ibid
is a dispute between the contractor engineers are adding more exculpa- tract and finds that the construction contractor should explain to the owner problems are identified early. 5
The Alberta Report – COAA Major Project
and the owner with possible litiga- tory clauses to contract documents documents are incomplete, it should how it will meet the contract require- Benchmarking Summary, Construction
tion costs. A better approach may to make up for incomplete design document, communicate and record ments for changes and agree on what Conclusion Owners Association of Alberta, February
be for the owner to use a third party documents. Statements in supple- problems. The contractor needs to cost items will or will not be included 2009.
mentary conditions to supply and implement proper procedures outlined in the pricing. In 1992, the founder of Revay and 6
Kumaraswamy Mohan M. and Kumaru
neutral who has both knowledge
install contracts (such as CCDC 2) in the contract, or at a minimum do the Associates Limited stated at a confer- Vogeswaran, Significant Sources of
and experience in the construction Construction Claims, The International
that require the contractor to build a following: 5. Be aware of constructive changes ence that “the only way to avoid dis-
environment to provide an inde- Construction Law Review, Vol. 15, January
facility in accordance with all design i.e. changes caused by the owner or putes and/or claims is either to elimi-
pendent opinion on issues that 1998
codes irrespective of what is shown 1. If a contractor discovers that spe- its consultant, which are not acknow– nate or at least reduce significantly the Impact Costs – The Validity and Calculation
arise during construction10. 7

on the drawings and specifications cific owners and/or designers are ledged as changes. For example, opportunities for cost overruns, such of Costs Related to Reduced Productivity,
suggests an insecurity about the less capable of providing complete changes made through revisions to can be achieved only with better pre- The Revay Report, December 1985, Vol. 4,
14. The use of “exemption”, “exculpa-
design. Moreover, this practice is contract documents, or buildable the shop drawings which have cost pared and more comprehensive bid Number 2
tory”, “exclusion” or “limitation of The Effect of Change Orders on Productivity, In 1970 Stephen G. Revay founded a small consulting company in Montreal. Initially the firm provided typical project manage-
not guaranteed to protect the drawings and specifications, it implications which could have or documents.”13
liability” clauses to prevent a con- The Revay Report, August 1987, Vol. 6, No. 2 ment services. Their contractor clients had other ideas; and soon Revay and Associates Limited was also filling the new niche
designer in litigation. should prepare for above-average should have been included in the
tractor from recovering costs due to The Cumulative Effects of Change Orders on market of preparing construction claims. Over the last forty years the company has become a leader in the construction claims
impacts on labour productivity and contract design documents. There are no revolutionary suggested Labour Productivity – The Leonard Study
incomplete contract documents industry and has blazed trails in offering project management, risk management and claims avoidance services; all provided by
5. When consultants have been asked the resulting need to issue and practices in this report, simply some “Reloaded”. The Revay Report, May 2007,
may not be considered as being fair logical fundamentals for achieving the fifty construction professionals in five offices across Canada and one in the United States. This growth would not be possible
why incomplete documents are defend claims. 6. When the number of changes begins Vol. 26, No, 1
by the courts, and may therefore be schedule and cost objectives of a pro– Coping with Extras, The Revay Report, without the loyalty and support of our clients. Thank you for your continued patronage. All of us at Revay and Associates
issued for contracts, the usual to affect productivity, the contractor
either unenforceable or interpreted 2. As soon as a problem is perceived, ject. The most critical of the require- September 2002, Vol. 21, No. 2 Limited look forward to continuing to build business relationships with past, present and future clientele.
response has been that the fees may want to attempt to include in its
to the benefit of the contractor. This provide written notice to the owner ments is having drawings, specifica-
8
Ibbs, William, Impact of Change’s Timing on
are not adequate to do a complete pricing any anticipated impact or loss
should be taken into consideration Labour Productivity, Journal of Construction
or its representative. Some jurisdic-
The Pitfalls of Incomplete Contract Documents
job. Designers should be cautious of productivity costs resulting from tions and other parts of the contract Engineering and Management, November
when drafting a contract11. tions have held that recovery cannot the changes. When impact costs are documents as close to 100% complete
that commercialism does not 2005, pp. 1219 – 1223
replace professionalism. be made without written notice when excluded by the consultant, the con- as possible at the time of executing an 9
Changes in Design / Build Contracts, The
Best Practices for Designer it is a requirement of the contract. tractor should issue a letter of objec- agreement or a contract. If 100% is not Revay Report, April 1997, Vol. 16 No. 2 By Bob Keen, P.Eng., MBA
Consultants Best Practices for Contractors Contractors need to appreciate that tion as soon as possible. Failing to achievable for one reason or another,
10
Facilitating the Construction Dispute Senior Consultant
giving notice to an owner is not only Resolution Process, The Revay Report, Revay and Associates Limited – Toronto
include such costs, failing to issue a then budget contingencies must be
1. Consultants need to define the proj- Prior to signing a contract, the follow- a contractual obligation but it also
March 2004, Vol. 23, No. 1
letter of objection or failing to provide adjusted, an alternative type of con- 11
Mackay, Michael, The Enforceability of
ect in clear and easily interpreted ing is recommended for contactors. provides the owner an opportunity to notice may preclude any remedy at tract should be considered, and the Exclusion Clauses in Cases of Fundamental The signing of a contract with incomplete drawings and specifications is a source of significant risk for
terminology. Generally, when ambi- assist in resolving the cause of an the end of the project. contract documents must make provi- Breach of Contract, Construction Law Letter, owners, general contractors and trade contractors. For all parties to a construction contract, incomplete
guities exist in the contract docu- 1. At the time of tender, if the contract excusable delay or to take steps to sion for fair and equitable adjustments Vol. 26, No.1, September/October 2009 contract documents at the time of awarding a contract substantially increase the risk of major cost over-
ments, the courts have ruled against language or contract requirements minimize any further losses and 7. The contractor should be open to to the time and price in the contract as
12
Monitoring Job-Site Productivity, The Revay runs and project delays.
the author of the documents. are not clear or are conflicting, ask future claims. In addition, our experi- working collaboratively with the changes are issued. Otherwise, the Report, May 2000, Vol. 19, No. 2
13
Revay , Stephen G., Can Construction Claims
for clarification. Differing interpreta- ence has been that contractors owner’s team to develop solutions spectre of claims and potential litiga- Incomplete contract documents invariably lead to claims from contractors for extension of time and
2. Some consultants are reluctant to be Avoided?, CIB UMIST Conference 1992,
tions of the contract documents obtain better results if they commu- that avoid claims or mitigate dam- tion loom on the horizon to the peril of Manchester, England, Building Research and additional compensation. When owners have tight budgets or are reluctant to pay more for a project, a
recommend change orders, approve during construction will simply lead nicate and negotiate during the dispute results. The dispute leads to further increased costs, as senior management of the various par-
ages incurred. all parties involved in the contract. Information, Vol. 21, Number 1, 1993
shop drawings, or respond to to disputes. course of construction rather than ties get involved attempting to resolve issues, frequently with associated legal costs.
requests for information because it waiting until the end of the project. The Revay Report is published by Revay and REVAY OFFICES: Bob Keen
can be interpreted as recognizing 2. Contracts with unfair clauses will Associates Limited, a national firm of Construction This Revay Report addresses the subject of incomplete contract documents, the causes, impacts and recom-
that the contract documents were OTTAWA VANCOUVER
ultimately lead to financial losses 3. Prepare a proper Critical Path and Claims Specialists, assisting owners and MONTREAL
39 Robertson Road 1755 W. Broadway
mended best practices for reducing or eliminating the consequences of inadequate contract documents.
4333 Ste. Catherine St. West
unclear. The carriers of errors and which will not be fully recoverable, Method (CPM) schedule that is fea- contractors in achieving profitable and trouble-
Suite 500 Suite 230 Suite 401
omissions insurance often advise even if addressed by the courts. Be sible, update it monthly and ensure free construction projects. MONTRÉAL, Québec H3Z 1P9 NEPEAN, Ontario K2H 8R2 VANCOUVER, B.C. V6J 4S5 Role of Consultants
Tel.: (514) 932-2188 Tel.: (613) 721-6801 Tel.: (604) 737-2005
consultants to not admit to any errors on guard for disclaimers about site personnel are in agreement with Fax: (514) 939-0776 Fax: (613) 596-8172 Fax: (604) 737-2008
or omissions. Consultants need to Contents may be reproduced, with a credit as The role of architects and engineers to the role defined in the contract, expected of a person of ordinary com-
incomplete plans, incomplete site the sequencing of the work. Actual montreal@revay.com ottawa@revay.com vancouver@revay.com
be reminded that as licensed profes- and soil reports as well as other progress must be monitored. Not
to source appreciated. Your comments and (often referred to as the “consultant” or architects and engineers are also petence, measured by the professional
suggestions for future articles are most welcome. TORONTO CALGARY Revay & Associates Inc.
sionals, they have a duty to act data furnished about the site, or adhering to a planned schedule can 2255 Sheppard Avenue East­­­ 10655 Southport Road, S.W. 1105 N Market Street “design consultant” in construction required to abide by a professional standard of the time1.
impartially and delaying decisions requirements to install as per the result in labour and equipment pro- Edition française disponible sur demande.
Suite 402 ­ Suite 540 Suite 1300 contracts) is determined by the con- standard of care. In all the work done
TORONTO, Ontario M2J 4Y1 CALGARY, Alberta T2W 4Y1 WILMINGTON, DE 19801
and information will result in addi- drawings and specifications as well ductivity losses. In addition, make Tel.: (416) 498-1303 Tel.: (403) 777-4900 Tel.: (302) 427-9340 tract between the owner and the archi- for the client, the architect or engineer Owners and contractors must realize
tional costs to the owner and possi- as meeting specific performance sure a detailed as-built schedule is Please advise the Montreal office of any Fax: (416) 491-0578 Fax: (403) 777-4903 Fax: (302) 651-8426 tect or engineer in traditional design- owes a duty to exercise the skill, care that the consultant’s duty to the owner
toronto@revay.com calgary@revay.com
bly delay the project completion. criteria. prepared as the project progresses. change of address. http://www.revay.com bid-build delivery systems. In addition and diligence which may reasonably be does not mean that drawings, specifi-
Publications #40042162
5 The Revay Report 6

documents, most contracts require 3. If a problem arises and the consul- 3. Be mindful of contract clauses These schedules can then be used 8. On-site monitoring of actual prog- 1
McLachlin, Beverley M. and Wilfred J.
the consultant to perform the first tant is not able to provide a solu- requiring the contractor to investi- to explain delays and determine ress is becoming more common as it Wallace, The Canadian Law of Architecture
adjudication of an issue. When the tion, consultation with the team, in gate existing or hidden conditions causation of the additional costs. provides a better case for presenting and Engineering, Butterworth-Heinemann,
claim results from design errors particular the affected trade con- promptly and issue a claim for loss of productivity claims to arbitra- 1987,p.97
and omissions in the contract docu– tractor, may result in the most cost- additional compensation within the 4. Many contracts contain change order tors and courts as well as owner’s
2
Judgments of the Supreme Court of Canada,
procedures and pricing guidelines Canadian National Railway Co. vs Royal and
ments, the consultant is in a con- effective solution without neces- allowed time as per the notice pro- claims consultants. More important-
Sun alliance Insurance Co. of Canada, 2008
flict of interest position and has no sarily sacrificing performance of visions of the contract. Ensure that that provide for a complete and exclu- ly, monitoring actual progress of the SCC66, 20081121 Docket 32062 Project Management and Published by Revay and Associates Limited
incentive to be fair to the contrac- the project for the owner. the timeframe is reasonable and sive remedy for the contractor in the various trades working on site can 3
Revay, Stephen G., Can Construction Claims
achievable. event of changes, including those for Construction Claims Services Volume 29 Number 1 March 2010
tor and award it proper compensa- provide an early warning of prob- be Avoided?, CIB UMIST Conference 1992,
tion in view of its relationship with 4. To protect themselves in case of incomplete or inaccurate design docu– lems12. Both owners and contractors Manchester, England, Building Research and
potential litigation, architects and After a contractor is awarded a con- ments. At the start of a project, the can mitigate damages or losses if Information, Vol. 21, Number 1, 1993
its own insurance carrier. The result 4
Ibid
is a dispute between the contractor engineers are adding more exculpa- tract and finds that the construction contractor should explain to the owner problems are identified early. 5
The Alberta Report – COAA Major Project
and the owner with possible litiga- tory clauses to contract documents documents are incomplete, it should how it will meet the contract require- Benchmarking Summary, Construction
tion costs. A better approach may to make up for incomplete design document, communicate and record ments for changes and agree on what Conclusion Owners Association of Alberta, February
be for the owner to use a third party documents. Statements in supple- problems. The contractor needs to cost items will or will not be included 2009.
mentary conditions to supply and implement proper procedures outlined in the pricing. In 1992, the founder of Revay and 6
Kumaraswamy Mohan M. and Kumaru
neutral who has both knowledge
install contracts (such as CCDC 2) in the contract, or at a minimum do the Associates Limited stated at a confer- Vogeswaran, Significant Sources of
and experience in the construction Construction Claims, The International
that require the contractor to build a following: 5. Be aware of constructive changes ence that “the only way to avoid dis-
environment to provide an inde- Construction Law Review, Vol. 15, January
facility in accordance with all design i.e. changes caused by the owner or putes and/or claims is either to elimi-
pendent opinion on issues that 1998
codes irrespective of what is shown 1. If a contractor discovers that spe- its consultant, which are not acknow– nate or at least reduce significantly the Impact Costs – The Validity and Calculation
arise during construction10. 7

on the drawings and specifications cific owners and/or designers are ledged as changes. For example, opportunities for cost overruns, such of Costs Related to Reduced Productivity,
suggests an insecurity about the less capable of providing complete changes made through revisions to can be achieved only with better pre- The Revay Report, December 1985, Vol. 4,
14. The use of “exemption”, “exculpa-
design. Moreover, this practice is contract documents, or buildable the shop drawings which have cost pared and more comprehensive bid Number 2
tory”, “exclusion” or “limitation of The Effect of Change Orders on Productivity, In 1970 Stephen G. Revay founded a small consulting company in Montreal. Initially the firm provided typical project manage-
not guaranteed to protect the drawings and specifications, it implications which could have or documents.”13
liability” clauses to prevent a con- The Revay Report, August 1987, Vol. 6, No. 2 ment services. Their contractor clients had other ideas; and soon Revay and Associates Limited was also filling the new niche
designer in litigation. should prepare for above-average should have been included in the
tractor from recovering costs due to The Cumulative Effects of Change Orders on market of preparing construction claims. Over the last forty years the company has become a leader in the construction claims
impacts on labour productivity and contract design documents. There are no revolutionary suggested Labour Productivity – The Leonard Study
incomplete contract documents industry and has blazed trails in offering project management, risk management and claims avoidance services; all provided by
5. When consultants have been asked the resulting need to issue and practices in this report, simply some “Reloaded”. The Revay Report, May 2007,
may not be considered as being fair logical fundamentals for achieving the fifty construction professionals in five offices across Canada and one in the United States. This growth would not be possible
why incomplete documents are defend claims. 6. When the number of changes begins Vol. 26, No, 1
by the courts, and may therefore be schedule and cost objectives of a pro– Coping with Extras, The Revay Report, without the loyalty and support of our clients. Thank you for your continued patronage. All of us at Revay and Associates
issued for contracts, the usual to affect productivity, the contractor
either unenforceable or interpreted 2. As soon as a problem is perceived, ject. The most critical of the require- September 2002, Vol. 21, No. 2 Limited look forward to continuing to build business relationships with past, present and future clientele.
response has been that the fees may want to attempt to include in its
to the benefit of the contractor. This provide written notice to the owner ments is having drawings, specifica-
8
Ibbs, William, Impact of Change’s Timing on
are not adequate to do a complete pricing any anticipated impact or loss
should be taken into consideration Labour Productivity, Journal of Construction
or its representative. Some jurisdic-
The Pitfalls of Incomplete Contract Documents
job. Designers should be cautious of productivity costs resulting from tions and other parts of the contract Engineering and Management, November
when drafting a contract11. tions have held that recovery cannot the changes. When impact costs are documents as close to 100% complete
that commercialism does not 2005, pp. 1219 – 1223
replace professionalism. be made without written notice when excluded by the consultant, the con- as possible at the time of executing an 9
Changes in Design / Build Contracts, The
Best Practices for Designer it is a requirement of the contract. tractor should issue a letter of objec- agreement or a contract. If 100% is not Revay Report, April 1997, Vol. 16 No. 2 By Bob Keen, P.Eng., MBA
Consultants Best Practices for Contractors Contractors need to appreciate that tion as soon as possible. Failing to achievable for one reason or another,
10
Facilitating the Construction Dispute Senior Consultant
giving notice to an owner is not only Resolution Process, The Revay Report, Revay and Associates Limited – Toronto
include such costs, failing to issue a then budget contingencies must be
1. Consultants need to define the proj- Prior to signing a contract, the follow- a contractual obligation but it also
March 2004, Vol. 23, No. 1
letter of objection or failing to provide adjusted, an alternative type of con- 11
Mackay, Michael, The Enforceability of
ect in clear and easily interpreted ing is recommended for contactors. provides the owner an opportunity to notice may preclude any remedy at tract should be considered, and the Exclusion Clauses in Cases of Fundamental The signing of a contract with incomplete drawings and specifications is a source of significant risk for
terminology. Generally, when ambi- assist in resolving the cause of an the end of the project. contract documents must make provi- Breach of Contract, Construction Law Letter, owners, general contractors and trade contractors. For all parties to a construction contract, incomplete
guities exist in the contract docu- 1. At the time of tender, if the contract excusable delay or to take steps to sion for fair and equitable adjustments Vol. 26, No.1, September/October 2009 contract documents at the time of awarding a contract substantially increase the risk of major cost over-
ments, the courts have ruled against language or contract requirements minimize any further losses and 7. The contractor should be open to to the time and price in the contract as
12
Monitoring Job-Site Productivity, The Revay runs and project delays.
the author of the documents. are not clear or are conflicting, ask future claims. In addition, our experi- working collaboratively with the changes are issued. Otherwise, the Report, May 2000, Vol. 19, No. 2
13
Revay , Stephen G., Can Construction Claims
for clarification. Differing interpreta- ence has been that contractors owner’s team to develop solutions spectre of claims and potential litiga- Incomplete contract documents invariably lead to claims from contractors for extension of time and
2. Some consultants are reluctant to be Avoided?, CIB UMIST Conference 1992,
tions of the contract documents obtain better results if they commu- that avoid claims or mitigate dam- tion loom on the horizon to the peril of Manchester, England, Building Research and additional compensation. When owners have tight budgets or are reluctant to pay more for a project, a
recommend change orders, approve during construction will simply lead nicate and negotiate during the dispute results. The dispute leads to further increased costs, as senior management of the various par-
ages incurred. all parties involved in the contract. Information, Vol. 21, Number 1, 1993
shop drawings, or respond to to disputes. course of construction rather than ties get involved attempting to resolve issues, frequently with associated legal costs.
requests for information because it waiting until the end of the project. The Revay Report is published by Revay and REVAY OFFICES: Bob Keen
can be interpreted as recognizing 2. Contracts with unfair clauses will Associates Limited, a national firm of Construction This Revay Report addresses the subject of incomplete contract documents, the causes, impacts and recom-
that the contract documents were OTTAWA VANCOUVER
ultimately lead to financial losses 3. Prepare a proper Critical Path and Claims Specialists, assisting owners and MONTREAL
39 Robertson Road 1755 W. Broadway
mended best practices for reducing or eliminating the consequences of inadequate contract documents.
4333 Ste. Catherine St. West
unclear. The carriers of errors and which will not be fully recoverable, Method (CPM) schedule that is fea- contractors in achieving profitable and trouble-
Suite 500 Suite 230 Suite 401
omissions insurance often advise even if addressed by the courts. Be sible, update it monthly and ensure free construction projects. MONTRÉAL, Québec H3Z 1P9 NEPEAN, Ontario K2H 8R2 VANCOUVER, B.C. V6J 4S5 Role of Consultants
Tel.: (514) 932-2188 Tel.: (613) 721-6801 Tel.: (604) 737-2005
consultants to not admit to any errors on guard for disclaimers about site personnel are in agreement with Fax: (514) 939-0776 Fax: (613) 596-8172 Fax: (604) 737-2008
or omissions. Consultants need to Contents may be reproduced, with a credit as The role of architects and engineers to the role defined in the contract, expected of a person of ordinary com-
incomplete plans, incomplete site the sequencing of the work. Actual montreal@revay.com ottawa@revay.com vancouver@revay.com
be reminded that as licensed profes- and soil reports as well as other progress must be monitored. Not
to source appreciated. Your comments and (often referred to as the “consultant” or architects and engineers are also petence, measured by the professional
suggestions for future articles are most welcome. TORONTO CALGARY Revay & Associates Inc.
sionals, they have a duty to act data furnished about the site, or adhering to a planned schedule can 2255 Sheppard Avenue East­­­ 10655 Southport Road, S.W. 1105 N Market Street “design consultant” in construction required to abide by a professional standard of the time1.
impartially and delaying decisions requirements to install as per the result in labour and equipment pro- Edition française disponible sur demande.
Suite 402 ­ Suite 540 Suite 1300 contracts) is determined by the con- standard of care. In all the work done
TORONTO, Ontario M2J 4Y1 CALGARY, Alberta T2W 4Y1 WILMINGTON, DE 19801
and information will result in addi- drawings and specifications as well ductivity losses. In addition, make Tel.: (416) 498-1303 Tel.: (403) 777-4900 Tel.: (302) 427-9340 tract between the owner and the archi- for the client, the architect or engineer Owners and contractors must realize
tional costs to the owner and possi- as meeting specific performance sure a detailed as-built schedule is Please advise the Montreal office of any Fax: (416) 491-0578 Fax: (403) 777-4903 Fax: (302) 651-8426 tect or engineer in traditional design- owes a duty to exercise the skill, care that the consultant’s duty to the owner
toronto@revay.com calgary@revay.com
bly delay the project completion. criteria. prepared as the project progresses. change of address. http://www.revay.com bid-build delivery systems. In addition and diligence which may reasonably be does not mean that drawings, specifi-
Publications #40042162

You might also like