You are on page 1of 8

Nestle Waters RE-LOCATING FIRE PUMPS

Project
RE-LOCATION OF FIRE PUMP ASSEMBLY
NESTLE WATERS, EGYPT ABU-RAWASH
WAREHOUSE ABU-RAWASH, EGYPT

BILL OF QUANTITIES

FOR CIVIL & MECHANICAL WORKS

Prepared by
GRAPHCO ENGINEERING DESIGN

RV-00
MAY 2019

Price in L.E.
Item Description Unit Qty.
Unit Total

GRAPHCO Engineering Design Page-1-


Nestle Waters RE-LOCATING FIRE PUMPS

1 Prepare the underground tank compartment for acceptance of existing fire pump system. It will be made ready through the following:
Empty water from two compartments and dispose of site to authorized dump location. This will
1-a be done by tankers equipped with pumps for sucking water from underground tanks. Tank two No. 1
compartment capacity 300m3.
Close existing 3 openings in concrete wall between two compartments. This will be done by
casting a reinforced concrete wall in the other compartment. New wall height shall extend 40cm
above the openings and width shall be such that it extends by 50cm on either side of the
openings. Thickness of wall is 25cm with double reinforcement mesh of 5phi12/m’. Steel
dowels of phi12 (every 30cm) shall be placed to fix new wall to tank floor and wall. This in
2-a addition to closure of the three openings by a special Sika fast setting grout (or equivalent). No. 1
Opening closure has to be tested by filling one compartment with water for 1-2days and fixing
any leaks that will appear. The item includes the water proofing of the new wall with a strong
water proof from sika or equivalent.

Close existing 2 openings in ceiling of pump room compartment using galvanized steel wavy
3-a wire mesh. The mesh shall be placed over a galvanized steel frame fixed to the existing opening. No. 1
Frame shall be set so that it protects pedestrian from topping over of falling in tank.
Supply and place reinforced concrete base for pumps (fire, diesel and jockey) in the new room,
with mixing ratios of 0.4 cubic meter sand, 0.8 cubic meter gravel, and at least 250 kg ordinary
Portland cement (fcu=250kg/cm2). The footings shall be placed in correct locations similar to
4-a design drawings and according to final approved shop drawings of pump assembly layout. No. 1
Approximate dimensions of footings shall be 6.2m in length, 1m in width and 0.4m in thickness.
Upper double mesh of 6phi12/m shall be used in new bases.

Supply and place 40x40x1.2cm white ceramic tiles for flooring of the new pump room. The tiles
shall be laid and fixed to the ground using cement mortar. Approximate area is 55m2. The item
5-a includes placement of imported clean coarse sand (35cm) and compaction. Tiles are Cleopatra No. 1
or Rocca or equivalent.

Item Description Unit Qty. Price in L.E.

GRAPHCO Engineering Design Page-2-


Nestle Waters RE-LOCATING FIRE PUMPS

Unit Total
Supply and place drainage trench on one side of the new pump room beside the dividing existing
6-a wall. The item includes supply and placement of 10inch PVC half pipe fixed in a box of plain No. 1
concrete. Approximate length of 6m.
Supply and place new drainage sump at the corner of the new pump room. Dimensions of sump
are 1mx1mx0.6m. Side walls are reinforced concrete walls, 20cm 5phi12. Inside of sump to be
7-a painted with water proofing coating. The item includes the supply of small submersible pump No. 1
5lit/s, 20m and connection of pump discharge pipe to nearest manhole.
Supply and place steel ladder for access of the new pump room. Steel is prim-prepared and
8-a painted with 3 coats of anti-rust paint and fixed to new pump room floor. No. 1

8-a-
Option Paint existing steel ladder with 3 coats of anti-rust paint. No. 1
Make new openings (two 8 inch openings for supply of water to header, one 6inch for test drain,
one 6inch for the drain line) in the reinforced concrete divider wall. The item includes using the
core machine for making openings at correct location –depending on the approved shop drawing
of the fire assembly. The item includes the placement of black steel 8inch and 6inch puddle
9-a No. 1
pieces in the opening and the proper sealing around it by specialized sealants from sika or
equivalent. Opening closure has to be tested by filling one compartment with water for 1-2days
and fixing any leaks that will appear with proper procedure.

Make new opening in concrete ceiling for muffler of diesel engine. This item includes using the
core machine for making openings at correct location –depending on the approved shop drawing
10-a of the fire assembly. The item includes proper sealing around muffler pipe by specialized No. 1
sealants from sika or equivalent. Opening closure has to be tested by water hose on the ceiling
and fixing any leaks that will appear with proper procedure.

Make new opening (one 8 inch openings for discharge of pump to fire loop). In ceiling of new
11-a pump room. This item includes using the core machine for making openings at correct location No. 1
–depending on the approved shop drawing of the fire assembly. The item includes proper

GRAPHCO Engineering Design Page-3-


Nestle Waters RE-LOCATING FIRE PUMPS

Price in L.E.
Item Description Unit Qty.
Unit Total
sealing around pipe by specialized sealants from sika or equivalent. Opening closure has to be
tested by water hose on the ceiling and fixing any leaks that will appear with proper procedure.
2 Relocate fire pump assembly from top of tank to new pump room, commission and test. The item includes the following:
Dismantle all fire assembly, including: pumps, valves, pipes, fittings etc. in a good condition so
that they can be used in new pump room. The item includes repairing rusted pipes or accessories
2-a by sand plastering, prime painting with one coat, and paint with red color plastic paint for three No. 1
coats. The item includes the re-location of all fire assembly to the new pump room using suitable
crane.

Assemble all piping, fittings, accessories, pumps, and valves in the new pump room according
to final approved shop drawings. The item includes all required piping and mechanical
connections for operation of new fire pump assembly. Any needed accessories (not available on
site or from old assembly) such as: piped header, piping, elbows, reducers etc. are included in
this item. Pipes are Russian or Ukraine made. Valves are English of US made. No Chinese
2-b components shall be approved. The item includes required steel supports for valves and bends No. 1
(prime and 3 coat painted); all required connections for the fuel tank and batteries to the diesel
engine. The item includes the supply and installation of the muffler hood from the diesel engine
to the atmosphere. The item includes all required fittings such as elbows and vortex shedding
pieces inside the water tank

Supply and connect all required electrical connections between pumps and their electric panel
2-c inside pump room. All cables are installed on galvanized cable tray fixed on the walls of the No. 1
new pump room.
Supply and connect main feeding cable to pump control panel in new pump room. All cables are
2-d installed on galvanized cable tray fixed on the walls of the new pump room. No. 1

2- Re-connect existing main feeding cable to pump control panel in new pump room. All cables are
doption installed on galvanized cable tray fixed on the walls of the new pump room. No. 1

GRAPHCO Engineering Design Page-4-


Nestle Waters RE-LOCATING FIRE PUMPS

2-e Supply, install and commission analogue pressure gauges on various locations of new No. 4

Price in L.E.
Item Description Unit Qty.
Unit Total
assembly.

Total
Proposed time for completion of project in days

GRAPHCO Engineering Design Page-5-


Nestle Waters RE-LOCATING FIRE PUMPS

1- Openings in tank wall:

2- Openings in tank ceiling:

GRAPHCO Engineering Design Page-6-


Nestle Waters RE-LOCATING FIRE PUMPS

3- Assembly of fire pumps:

GRAPHCO Engineering Design Page-7-


Nestle Waters RE-LOCATING FIRE PUMPS

GRAPHCO Engineering Design Page-8-

You might also like