Mode 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17
1 Construction of Field Office for
the Engineer
2 Project Billboard
3 Occupational Safety and Health
Program
4 Traffic Management
5 Mobilization/Demobilization
6 Temporary Diversion of 4 days Tue Fri 19/04/19
Waterways 16/04/19
7 Removal of Existing Structures 3 days Mon Wed
(Existing Line Canal) 22/04/19 24/04/19
8 Removal of Actual 4 days Mon Thu
Structures/Obstruction, (0.20m 06/05/19 09/05/19
thk) PCCP (Unreinforced)
9 Structure Excavation (Common
Soil)
10 Embankment from Excavation
(Common Soil)
11 Embankment from Borrow
(Common Soil)
12 Subgrade Preparation (Common 12 days Tue Wed
Material) 23/04/19 08/05/19
13 Aggregate Base Course 13 days Mon 22/04/19Wed 08/05/19
14 Portland Cement Concrete 15 days Wed Tue
Pavement (Unreinforced) - 3500 24/04/19 14/05/19
PSIO, 20mm thk
15 Reinforcing Steel (Grade 40) 9 days Tue 16/04/19Fri 26/04/19
16 Structure Concrete (7days, 7 days Wed Thu
4000psi) Class A 24/04/19 02/05/19
17 Metal Frame and Covers
18 Metal Frames and Grating
19 Lean Concrete
20 Stone Masonry, (Grouted Riprap - 11 days Mon Mon
Class A) 01/04/19 15/04/19
21 Lean Concrete
22 Solar LED Street Light (Single 3 days Mon Wed
Arm) 13/05/19 15/05/19
23 Painting Works, Masonry Painting 3 days Fri 10/05/19 Tue
14/05/19
Project: Sto. Nino Work Schedu Split Inactive Task Duration-only Finish-only Progress
Date: Mon 15/04/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1