ID Task Task Name Duration Start Finish April 2019 May 2019

Mode 30 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 01 03 05 07 09 11 13 15 17
1 Construction of Field Office for
the Engineer
2 Project Billboard
3 Occupational Safety and Health
Program
4 Traffic Management
5 Mobilization/Demobilization
6 Temporary Diversion of 4 days Tue Fri 19/04/19
Waterways 16/04/19
7 Removal of Existing Structures 3 days Mon Wed
(Existing Line Canal) 22/04/19 24/04/19
8 Removal of Actual 4 days Mon Thu
Structures/Obstruction, (0.20m 06/05/19 09/05/19
thk) PCCP (Unreinforced)
9 Structure Excavation (Common
Soil)
10 Embankment from Excavation
(Common Soil)
11 Embankment from Borrow
(Common Soil)
12 Subgrade Preparation (Common 12 days Tue Wed
Material) 23/04/19 08/05/19
13 Aggregate Base Course 13 days Mon 22/04/19Wed 08/05/19
14 Portland Cement Concrete 15 days Wed Tue
Pavement (Unreinforced) - 3500 24/04/19 14/05/19
PSIO, 20mm thk
15 Reinforcing Steel (Grade 40) 9 days Tue 16/04/19Fri 26/04/19
16 Structure Concrete (7days, 7 days Wed Thu
4000psi) Class A 24/04/19 02/05/19
17 Metal Frame and Covers
18 Metal Frames and Grating
19 Lean Concrete
20 Stone Masonry, (Grouted Riprap - 11 days Mon Mon
Class A) 01/04/19 15/04/19
21 Lean Concrete
22 Solar LED Street Light (Single 3 days Mon Wed
Arm) 13/05/19 15/05/19
23 Painting Works, Masonry Painting 3 days Fri 10/05/19 Tue
14/05/19

Task Project Summary Manual Task Start-only Deadline

Project: Sto. Nino Work Schedu Split Inactive Task Duration-only Finish-only Progress
Date: Mon 15/04/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone