Km 121+380 - Km 121+490

Enrocado Excavacion Geotextil


Ubicación Distanc
Area Volumen Area Volumen Perimetro Area
Km ia m
m2 m3 m2 m3 m m2
121+380 0 30.38 0.00 11.22 0.00 18.78 0.00
121+440 60 44.54 2,247.63 19.80 930.60 20.54 1,179.45
121+490 50 46.10 2,265.95 20.80 1,015.00 20.87 1,035.25
Totales= 4,513.58 1,945.60 2,214.70

Km 126+440 - Km 126+560

Enrocado Excavacion Geotextil


Ubicación Distanc
Km ia m Area Volumen Area Volumen Perimetro Area
m2 m3 m2 m3 m m2
126+440 0 13.65 0.00 10.12 0.00 10.75 0.00
126+450 10 14.05 138.50 9.56 98.40 10.40 105.75
126+460 10 13.30 136.75 8.71 91.35 10.20 103.00
126+480 20 12.52 258.20 8.68 173.90 10.00 202.00
126+500 20 13.57 260.90 9.30 179.80 10.27 202.70
126+510 10 14.67 141.20 9.80 95.50 10.54 104.05
126+520 10 14.20 144.35 9.80 98.00 10.37 104.55
126+530 10 12.87 135.35 9.03 94.15 9.92 101.45
126+540 10 16.21 145.40 9.73 93.80 10.21 100.65
126+560 20 17.00 332.10 9.62 193.50 12.31 225.20
Totales= 1,692.75 1,118.40 1,249.35
S
ESTUDIO DEFINITIVO PARA LA CONSTRUCCIÓN Y MEJORAMIENTO DE LA
CARRETERA CUSCO - QUILLABAMBA TRAMO: ALFAMAYO - CHAULLAY -
PROYECTO QUILLABAMBA

CONSULTOR CONSORCIO LAGESA - INGEDISA

METRADO CAMA DE ARENA ESPESOR: 0.20m

Defensa ribereña margen derecha Rio vilcanota Km 121+380 - Km 121+490

Distancia Perimetro Espesor Excavacion


Ubicación Km Area m2
m m m m
121+380 0 18.776 0 0.2 0
121+440 60 20.539 1179.45 0.2 235.89
121+490 50 20.871 1035.25 0.2 207.05
Totales= 110 442.94

Defensa ribereña Rio vilcanota sector Ayunay Km 126+440 - Km 126+560

Distancia Perimetro Espesor Excavacion


Ubicación Km Area m2
m m m m
126+440 0 10.75 0.00 0.20 0.00
126+450 10 10.40 105.75 0.20 21.15
126+460 10 10.20 103.00 0.20 20.60
126+480 20 10.00 202.00 0.20 40.40
126+500 20 10.27 202.70 0.20 40.54
126+510 10 10.54 104.05 0.20 20.81
126+520 10 10.37 104.55 0.20 20.91
126+530 10 9.92 101.45 0.20 20.29
126+540 10 10.21 100.65 0.20 20.13
126+560 20 12.31 225.20 0.20 45.04
Totales= 120 249.87
ESTUDIO DEFINITIVO PARA LA CONSTRUCCIÓN Y MEJORAMIENTO DE LA
CARRETERA CUSCO - QUILLABAMBA TRAMO: ALFAMAYO - CHAULLAY -
PROYECTO QUILLABAMBA

CONSULTOR CONSORCIO LAGESA - INGEDISA

Revestimiento del canal de tierra

Km 116+200

Longitud 7.00
Area seccion = 0.245
0.95 0.10 0.10
0.75 0.10 0.08
0.75 0.10 0.08

Volumen de concreto: f´c 175 kg/cm2 1.715


Vc(m3) = 0.245X7.00
0.245 7.000

Area encofrado: 7.490


Ae(m2) = 0.245x2.00 + 1.00x7.00
0.245 2 0.49
1.000 7.00 7

Excavacion: 6.720
Ve(m3) = 1.60x0.60x7.00
1.60 0.60 7.00
ESTUDIO DEFINITIVO PARA LA CONSTRUCCIÓN Y MEJORAMIENTO DE LA
CARRETERA CUSCO - QUILLABAMBA TRAMO: ALFAMAYO - CHAULLAY -
PROYECTO QUILLABAMBA

CONSULTOR CONSORCIO LAGESA - INGEDISA

Metrado de Gaviones

Calculos de areas:

Lados Areas Cantidad Total


Tipo
mxm m2 Unid m2
A 1.00 x 1.00 1.00 5.00 5.00
B 1.50 x 1.00 1.50 2.00 3.00
Total= 8.00

Calculos de volumenes:

Ubicación Longitud Area Volumen Excavacion


Km m m2 m3 m3
095+290 095+320 30.00 8.00 240.00 240.00
100+800 100+840 40.00 8.00 320.00 320.00
107+070 107+140 70.00 8.00 560.00 560.00
127+020 127+060 40.00 8.00 320.00 320.00
Total= 1,440.00 1,440.00
ESTUDIO DEFINITIVO PARA LA CONSTRUCCIÓN Y MEJORAMIENTO DE
LA CARRETERA CUSCO - QUILLABAMBA TRAMO: ALFAMAYO -
PROYECTO CHAULLAY - QUILLABAMBA

CONSULTOR CONSORCIO LAGESA - INGEDISA

Ensanche de Cuneta y Metrado de excavacion Km 85+240 - Km 85+420

Area Volumen
Ubicación Distancia Corte Relleno Corte Relleno
m2 m3 m2 m3
085+240 0 4.30 0.00 0.00 0.00
085+250 10 4.30 0.00 43.00 0.00
085+260 10 5.35 0.00 48.25 0.00
085+270 10 4.79 0.00 50.70 0.00
085+280 10 3.45 0.00 41.20 0.00
085+290 10 2.57 0.00 30.10 0.00
085+300 10 1.15 0.76 18.60 1.90
085+320 20 1.34 0.00 24.90 3.80
085+330 10 10.48 0.00 59.10 0.00
085+340 10 13.20 0.00 9.62 0.00
085+350 10 11.90 0.00 125.50 0.00
085+360 10 10.49 0.00 111.95 0.00
085+370 10 12.34 0.00 114.15 0.00
085+380 10 13.19 0.00 127.65 0.00
085+400 20 7.85 0.00 210.40 0.00
085+410 10 4.32 0.00 60.85 0.00
085+420 10 1.49 0.00 29.05 0.00
Totales= 1,105.02 5.70
ESTUDIO DEFINITIVO PARA LA CONSTRUCCIÓN Y MEJORAMIENTO DE LA CARRETERA CUSCO -
PROYECTO QUILLABAMBA TRAMO: ALFAMAYO - CHAULLAY - QUILLABAMBA

CONSULTOR CONSORCIO LAGESA - INGEDISA

Canal de Pase para Riego Alcantarilla Km, 115+200

Canal de pase para riego Km 115+200 Longitud: 6.31 m

Volumen de concreto: f´c 175 kg/cm2 Longitud:


As (m2)= 2x0.10x0.60 + 1.00x0.10 L(m)= 4.93
As (m2)= 0.22
Vol (m3)= 1.08 SECCION 01

As (m2)= 0.10X0.60 L(m)= 1.56


Vol (m3)= 0.09

As (m2)= 0.90X1.56 e(m)= 0.10


Vol (m3)= 0.07

Vt(m3)= 1.41 SECCION 02

Encofrado:
A1 (m2)= 0.70x(4.49+8.12) Caras 1 y 4
A2 (m2)= 0.60x(4.49+8.12) Caras 2 y 3
A3 (m2)= 2(2x0.10x0.60 + 1.00x0.10) Cara frontal
At (m2)= 16.83

Excavacion: Longitud:
As (m2)= (1.20+1.09)X0.95/2 L(m)= 6.31 Zona a encofrar
As (m2)= 1.09
Vol (m3)= 6.88
Resumen de metrados

Enrocados:

Enrocado Excavacion Geotextil


Sector
m3 m3 m2
Sector Ayunay 1692.75 1118.40 1249.35
Rio Chaullay 4513.58 1945.60 2214.70
Puentes 1582.08 2665.52 1466.52
Total= 7788.41 5729.52 4930.57

Cama de arena: espesor 0.20m

Sector Distancia Volumen


m m3
Sector Ayunay 120.00 249.87
Rio Chaullay 110.00 442.94
Puentes 81.00 293.34
Total= 311.00 986.15

Demolicion de Alcantarillas: 0.8x0.8 MCA

Longitud Volumen
m m3
45.40 29.06

Gaviones:

Longitud Volumen Excavacion


m m3 m3
180.00 1440.00 1440.00
Revestimiento de canal de tierra Km 116+200 - Long: 7.00m

Concreto Encofrado Excavacion


m3 m2 m3
1.72 7.49 6.72

Ensanche de cuneta para desagüe de canal Km 85+240 - Km 85+420

Concreto Encofrado Excavacion


m3 m2 m3
121.29 323.00 1105.02

Cunetas de coronacion - Long: 660 m

Concreto Encofrado Excavacion


m3 m2 m3
99.00 9.00 193.05

Encauzamiento de puentes:

Longitud
Ancho promedio Altura Volumen
Ubicación Aguas arriba Aguas abajo
m m m m m3
Alfamayo 18 25.00 0.40 180.00
084+665 16 25.00 0.40 160.00
Huamanmarca 16 30.00 0.40 192.00
098+652 22 25.00 0.40 220.00
Amaybamba 21 30.00 0.40 252.00
103+552 20 30.00 0.40 240.00
Sicre 16 25.00 0.40 160.00
105+019 16 20.00 0.40 128.00
Ipal 18 30.00 0.40 216.00
105+728 16 25.00 0.40 160.00
Huyro 26 25.00 0.40 260.00
108+341 26 20.00 0.40 208.00
Incatambo 15 30.00 0.40 180.00
090+888 15 25.00 0.40 150.00
Chontamayo 20 30.00 0.40 240.00
111+994 20 25.00 0.40 200.00
Huayopata 16 30.00 0.40 192.00
114+012 16 20.00 0.40 128.00
Totales= 255.00 215.00 3466.00