Professional Documents
Culture Documents
Brian Cooke
M
MACMILLAN
EDUCATION
© B. Cooke 1988
All rights reserved. No reproduction, copy or transmission
of this publication may be made without written permission.
Published by
MACMILLAN EDUCATION LTD
Houndmills, Basingstoke, Hampshire RG21 2XS
and London
Companies and representatives
throughout the world
v
Chapter 4. Case Studies relating to bar-charts, precedence diagrams
Network Techniques 89 and networks. 157
4.6- Sequence study network for precast 5.3- Precedence diagram for industrial
concrete retaining wall and process building. 171
associated drainage work. 112
5.4- Precedence diagram for factory
4.7 - Concrete tank sequence - project. 175
development of cost envelopes
based on earliest and latest starts. 116 5.5- Precedence diagram for garage
project. 178
4.8 - Ladder diagram for foundations
project - development of labour 5.6- Precedence diagram for earthworks
resource diagrams from bar-chart. 123 and bridge project. 182
vi
Preface
Contract Planning Case Studies provides students in both Building and Civil Engineering with a range of
practical situations relating to pre-contract and contract planning procedures. The case studies enable the
reader to follow the planning situations relative to the preparation of valuation forecasts and cash flow
forecasting. Methods of construction in relation to resources and sequences of construction are considered
for the construction of a reinforced concrete retaining wall and multi-storey concrete frame. It is essential for
managers and planning staff to appreciate the relationships between resources and sequences of
construction.
All the case study material relates specifically to a range of contracts on which the author has been
directly involved during the past two years. The data was collected while undertaking the role of
engineer/surveyor working for the contractor. The case study material has been reduced in complexity to
enable it to be used in the text.
The contents are divided into six chapters, each highlighting a specific planning technique:
• the planning process, planning policy, the role of planning within construction firms
• development of bar-charts for contract budgets, sequence studies and short-term planning
• principles and application of line of balance techniques to a range of building and civil engineering
situations
• network analysis including time scaled networks, lead and lag relationships, time-cost optimisation
• precedence diagram relationships with bar-charts and network arrow diagrams; precedence start and
finish relationships in practical planning situations
• project planning by computer; a review of software packages available; the development of a software
training package
The case study material will prove of direct interest to building management personnel and students
undertaking HND and Building Degree courses. Students involved in the preparation of the Project
Evaluation and Design project of the Chartered Institute of Building will also find the planning case studies of
direct interest.
vii
Acknowledgements
I wish to acknowledge the support and encouragement afforded by Professor I. H. Seeley in his role as
Series editor. His meticulous eye for detail can only enhance the quality of his fellow writers.
The work undertaken in editing the script into a readable textbook was ably carried out by Mr W. Perry.
I wish once again to thank my students atStockport College of Technology and Liverpool Polytechnic for
participating in the case studies. Lastly, I wish to acknowledge the building contractors who have allowed
me to participate in the organisation, planning and management of the contracts on which the case studies
are based.
viii
List of Figures
Chapter 2
2.1 - Factory project plan and section 13
2.2 - Factory project pre-tender programme 14
2.3 -Contract budget- valuation forecast 15
2.4 -Cost-value graphical display 16
2.5 -Value-time, cost-time, income-time relationships 18
2.6 -Factory project- tabular analysis of project cash flow 19
2.7 -Saw tooth cash flow diagram 20
2.8 -Model spreadsheet format- project cash flow 21
2. 9 -Calculated data format- project cash flow 22
2.10- Valuation forecast based on {- j rule 24
2.11 -Valuation forecast based on conversion chart 25
2.12 - Principles of cost-value reconciliation procedures 26
2.13 -Cost-value reconciliation statement 27
2.14- Factory project value-time, cost-time relationships 28
2.15- Cost-value reconciliation- end of month 3 29
2.16- Canal project general arrangement 32
2.17- Plan of existing lock- showing proposed works 33
2.18- Sections through existing lock 34
2.19- Pre-tender programme- canal project 35
2.20- Method statement format 36
2. 21 - Method statement - sheet 1 37
2.22- Method statement- sheet 2 37
2.23- Method statement- sheet 3 38
2.24- Formwork proposals for retaining wall 41
2.25 - Retaining wall pouring sequence 42
2.26- Sequence study bar-chart 44
2.27- Elevation and plan of frame 46
2.28- Diagrammatic construction sequence 47
2.29- Diagrammatic construction sequence 48
2.30- Column construction sequence 50
2.31 -Bar-chart for column sequence 50
2.32 - Sequence study bar-chart 53
2.33- Method statement for basement project 55
2.34- Plan and elevation of reinforced concrete framed tower 56
2.35- Precedence diagram for construction sequence 57
Chapter 3
3.1 -Logic diagram for sequence 60
3. 2 - Line of balance diagram - non-parallel working 60
3.3 -Line of balance- ideal relationship 60
3.4 -Logic diagram for sequence 61
3.5 - Line of balance diagram- operations Band C commencing together 61
ix
3.6 -Line of balance diagram- operations B and C finishing together 61
3.7 -Logic diagrams 63
3.8 -Line of balance schedule- site strip and foundations 65
3.9 -Line of balance schedule- foundations project 67
3.10- Labour resources for refurbishment project 69
3.11 - Resource assessment from balance lines 69
3.12 - Histogram of labour- refurbishment project 70
3.13 - Labour assessment based on four gangs 70
3.14- Plan and section- reinforced concrete platform 72
3.15 - Line of balance schedule- reinforced concrete platform 72
3.16 - Labour resources - reinforced concrete platform 73
3.17- Revised line of balance schedule 75
3.18- Revised labour resources 75
3.19- Logic diagram - housing finishes sequence 76
3.20- Line of balance- calculation sheet 77
3.21 -Line of balance schedule- housing finishes sequence 78
3.22- Line of balance schedule- valuation stages 80
3.23 -Valuation forecast based on line of balance schedule 81
3.24- Valuation time curve- housing sequence 82
3.25- Line of balance- progress position, Day 60 83
3.26- Logic diagram- 10 houses 84
3.27- Manhours per operation for 10 houses 84
3.28- Line of balance diagram 86
3.29- Plan and section- residential flats 87
3.30- Logic diagram and manhour allocation 88
Chapter 4
4.1 - Network principles 91
4.2 - Network relationships 92
4.3 -Network diagrams 93
4.4 - Network ladder diagram 94
4.5 -Procedure when analysing a network diagram 95
4.6 - Bar-chart-network relationships 96
4.7 -Network diagram- base and column sequence 98
4.8 -Time scale bar-chart presentation 99
4. 9 - Time scale bar-chart- labour balanced 99
4.10- Network diagram - internal finishes 101
4.11 - Analysed network diagram - internal finishes 102
4.12 - Bar-chart presentation - internal finishes 103
4.13 - Time scaled bar-chart presentation - internal finishes 104
4.14 - Network diagram - ladder diagram for drainage work 106
4.15 - Network diagram - lead and lag relationship 107
4.16 - Bar-chart presentation - drainage ladder diagram 108
4.17 - Bar-chart presentation - lead and lag relationship 109
4.18- Network diagram- railway modernisation project 111
4.19 - Network diagram - retaining wall sequence 113
4.20- Network diagram- 4 week contract period 114
4.21 -Bar-chart presentation- 4 week contract period 115
4.22- Network diagram- pumphouse and tank project 117
4.23- Analysed network- pumphouse and tank project 118
4.24 - Earliest start bar-chart- pumphouse and tank project 119
4.25 - Latest start bar-chart- pumphouse and tank project 120
4.26- Cost envelope- valuation forecast 121
4.27- Cost envelope- labour cost forecast 122
X
4.28- Network ladder diagram- foundations project 124
4.29- Analysed network- foundation project 125
4.30- Bar-chart presentation -earliest start labour resources 126
4.31 -Time scaled bar-chart- balanced labour resources 127
4.32 - Labour resources histogram 128
4.33- Normal time-cost. Crash time-cost relationships 131
4.34- Normal time-normal cost network 133
4.35- Crash time-crash cost network 133
4.36- Tabular data- cost slope assessment 134
4.37- Network diagram showing rank order 135
4.38- Least cost assessment for 20 day duration 135
4.39- Tabular data- least cost assessment 136
4.40 - Project cost relationship 137
4.41 - Normal time-cost network 139
4.42- Crash time-cost network 139
4.43- Tabular data- cost slope assessment 140
4.44- Normal time-cost network analysed 140
4.45 - Crash time-cost network analysed 140
4.46- Least cost assessment at Day 70 141
4.47- Least cost assessment at Day 74 142
4.48 - Network diagram for finishes sequence 145
4.49 - Network diagram for building extension 145
4.50- Network diagram for time-cost optimisation project 146
Chapter 5
5.1 -Piling and foundation sequence 159
5.2 -Steelwork and cladding sequence 160
5.3 -Floor beam sequence with data entry 161
5.4 -Floor beam sequence analysed 162
5.5 -Bar-chart display floor beam sequence 163
5.6 -Factory project sequence with data entry 164
5.7 - Factory project sequence analysed 165
5.8 -Bar-chart display for factory project 166
5. 9 - Reinforced concrete frame with data entry 167
5.10 - Blank bar-chart for reinforced concrete frame 168
5.11 -Reinforced concrete frame analysed 169
5.12 - Bar-chart display for reinforced concrete frame 170
5. 13 - Industrial process building precedence diagram 172
5.14- Industrial process building analysed 173
5.15 - Bar-chart display industrial process building 174
5.16- Factory project precedence diagram 176
5.17- Bar-chart display factory project 177
5.18- Network diagram for garage project 179
5.19- Garage project precedence diagram 180
5.20- Bar-chart display garage project 181
5.21 -Earthworks and bridge project precedence diagram 183
5.22- Earthworks and bridge project analysed precedence diagram 185
5.23- Bar-chart display for earthworks and bridge project 187
5.24- Precedence network exercise 189
Chapter 6
6. 1 - Critical path analysis routines 194
6.2 -Network diagram foundations for housing project 195
6.3 - Data input sheet 196
xi
Screen Display 1 - Critical path analysis - main menu 198
Screen Display 2 - CPA- sub-menu option 1, key-in data 198
Screen Display 3 - Data input procedure 199
Screen Display 4 - Output summary of input data 200
Screen Display 5 -Sort routine menu options 201
Screen Display 6 - Standard report - critical activities first 203
Screen Display 7 - Standard report - earliest start order 204
Screen Display 8 - Standard report - latest start order 205
Screen Display 9 - Bar-chart display - critical path first 206
Screen Display 10 - Bar-chart display - earliest start order 207
Screen Display 11 - Bar-chart display- latest start order 208
Screen Display 12 - Labour resources - all labour at earliest start 209
Screen Display 13 - Labour resources - all labour at latest start 210
Screen Display 14 - Labour resources - single trade at earliest start 211
Screen Display 15 - Labour resources - single trade at latest start 212
Screen Display 16 - Labour cost at earliest start 213
Screen Display 17 - Labour cost at latest start 214
xii
List of Abbreviations
xiii
Chapter 1
The Planning Process and the Role of the
Planning Department within a Large
Construction Firm
1.1 THE PLANNING PROCESS tender stage and during the contract. The pro-
gramme assessment on which the tender is based
forms the basis of the master contract programme.
The planning process has been developed around The master programme lays down a broad outline
the construction stages of pre-tender, pre-contract of the construction sequence, which will later be
and contract planning. This follows the sequence developed into a series of short-term programmes
involved in the planning of a contract from tender as further information becomes available to the
to completion in order to aid contract control. contractor. The planning policy laid down by the
Control is defined as: to check, verify or regulate board of directors establishes planning routines
- planning enables management to establish aimed at providing control procedures. Contracts
realistic standards against which performance can managers, site managers and planners should be
be matched during a contract. Planning proce- encouraged to work as a team in order to achieve
dures enable overall control to be maintained by the objectives of the company.
careful monitoring of the contract position. Plann-
ing enables decisions taken at tender stage to be
monitored throughout the pre-contract and post- 1.2 THE ROLE OF PLANNING WITHIN A
contract period. CONSTRUCTION ORGANISATION
Within the construction industry, companies RELATIVE TO COMPANY SIZE AND
both large and small follow a similar pre-tender NATURE OF WORK UNDERTAKEN
process during the production of an estimate and
its conversion into a tender. Similar tendering
decisions have to be considered by the principal of On contracts undertaken using the Standard Form
a small building firm as those of an estimating of Contract (1980 Edition) Clause 5.3.1.2, it is a
director in a larger company. The extent to which contract requirement that the contractor provides
procedures are formal and involve the production a contract programme. The ICE Conditions of
of a plan depend upon the size of the company, Contract- Clause 14.1 and 14.3- relate to the
the nature and complexity of work undertaken and approval of a programme of works and the pro-
the policy of the firm. Planning decisions at tender duction of information pertaining to methods of
stage revolve around the production of a realistic construction. In certain cases the contract pre-
contract period, often based on good luck rather liminaries may specify the form of presentation -
than good management. The assessment of the for example, network analysis or bar-chart pro-
contract period influences the monetary allow- gramme. Small building contracting organisations,
ances for preliminaries and plant, and hence employing up to twenty five staff and operatives,
reflects in the competitiveness of the contractor's usually base the overall contract period on ex-
bid. Likewise, consideration of methods of con- perience. In such cases a simple bar-chart pro-
struction has a similar effect on tender success. gramme format usually meets their requirements.
Tenders based on a careful analysis of construction Jobbing work, house extensions and specialist
methods relating to key operations have been sub-contract work rarely involve the contractor in
shown to improve the tender success rate. The using sophisticated planning techniques.
seventh edition of the Standard Method of Measure- Medium-sized Contractors employing between
ment for Building Works and CESMM 2 place 26 and 300 staff and operatives do not often have
considerable emphasis on the contractor to pro- an organisation structure which incorporates a
duce statements of construction method, both at planning department. The planning function is
2
usually undertaken by the contracts director or Planning - preparation of
contracts manager. Here again, the bar-chart form contract programme when
of presentation is widely adopted as it is readily applicable
understood at site management level and accept- Co-ordination of sub-
able to the client. Housing modernisation work, contractors and suppliers
industrial developments and one-off office type Principal/Owner Direct labour control
developments can readily be planned, again usin_g Preparation and submission of
bar-charts. The master contract programme 1s accounts
rarely completely redrafted unless major design Overall company control
decisions affect the construction sequence. The As expansion takes place,
monitoring of progress usually becomes the res- responsibility for various
ponsibility of the site construction manager. A facets of the organisation
good client/contractor relationship is often a more may be delegated for the
relevant factor than the contractor's ability to pro- surveying and estimating
duce fanciful programmes when the contract falls function
behind schedule. The company often considers
that the engagement of 'expert' planning staff
1.2.2 Case 8 - Planning function in a
rarely warrants the expense and simply creates
medium-sized firm
additional overheads which it cannot afford. Major
contracts up to a value of two to three million
The planning function will be the responsibility
pounds may be successfully undertaken and com-
of the construction director. It is assumed that
pleted without the need to utilise sophistica~ed
responsibility for each facet of the organisation is
planning techniques. Within the more progress1ve
under the control of a director. The company
medium-sized firms, where contracts of a more
turnover is between ten to twelve million pounds
complex nature are undertaken and a planning
per annum. The range of work undertaken in-
policy prevails, a more organised approach to
cludes factory developments, housing moderni~a
planning may be evident.
tion schemes and housing association new budd
The responsibility for the planning function is
works. The company have a small works division
illustrated by using a range of company situations
and an active speculative housing section.
relative to small, medium and large contracting
One-half of the company turnover is obtained
firms. The cases are based on procedures com-
by competitive tendering. The balance is obtain_ed
monly adopted by construction firms in the North-
by negotiated contracts and from speculative
west of England. They may, however, not be
housing developments.
typical of the way in which other firms of a similar
The responsibility for the preparation of the
size organise their planning function.
master contract programme for each contract lies
with the contracts director and individual contracts
manager. No planning engineers are employed
1.2.1 Case A - Planning function in a
within the company and the direct responsibility
small firm
for short-term planning lies with the site construc-
tion managers. The company buying section is
All decisions within the company are made by the
responsible for the preparation of material call off
principal/owner. The type of work undertaken an?
schedules based on the requirements of the con-
rate of company expansion is directly under h1s
tract bar-chart. The site manager is responsible for
control. Control is achieved by a concentration of
liaising with the buying section and calling material
management effort on major contracts influenc!ng
and sub-contractors to site as required.
company profitability. As company expans1on
The structure of the organisation and responsi-
takes place, delegation of responsibility by the
bility for the planning aspects is outlined as shown:
principal is necessary in order that efficient control
may be maintained.
1.2.3. Case C- Planning function in a
I
Responsible for: large firm
Obtaining work- developing
contacts with new clients No two large companies organise the planning
Preparation of estimates function in exactly the same way. This is due to
2
1"1£0/IJI"' St'Z.£0 Fl~,._,
CHA.IIf.MA A./
lt..E:sou«.eu j :suat:.ooiTJCAcrocs
Olt..GAHISATIOH
1../JiojSOH f,oltTH SuVR • MAT£.C.IIILS
the nature of work undertaken and the emphasis less complex projects may be planned using bar-
different companies place on the planning role. charts. It may be considered a foolish decision
The planning technique adopted by the company perhaps to enforce the use of network analysis
depends upon the type, size and complexity of techniques for all new projects undertaken. The
work undertaken. The company should adopt the senior management should ensure that site manage-
technique which best suits its planning needs. A ment personnel are kept informed of planning
contractor undertaking work involving speculative policy. Adequate provision should be made for
and local authority housing projects may adopt the in-service training courses to keep site manage-
line of balance techniques for use throughout the ment aware of planning developments. The intro-
company. Network planning techniques may be duction of computers as a planning aid speeds up
adopted for complex one-off type projects while the analysis process for networks and precedence
3
CHA/1/.MAN
Olt..GAHISATIOH
I "'IIUC TO (l.
I
Olt..GAHISATIOH
I
ACCOUNTS SUI.VEYitoiG CONT~IICTS PLANT MIHOil. WOit.ICS SPEC. HOcJrllfl6
OE'PT. 0£17.. OEPT. DEPT. OEPT. D£PT.
I
I
I In the above case the planning department forms
an integrated part of the contracts department and
I is controlled by the contracts director. The rela-
I tionship between the contracts and planning staff is
shown.
CottJTtLACTS
DILICTOR..
Olt..GAHISATIOH SEZVICE
4
diagrams. Bar-charts can be readily produced from On site, the planner will be directly responsible
the networks which enable critical operations to be to the construction site manager; movement be-
highlighted. Computers make network techniques tween contracts will be the direct responsibility of
a more viable planning proposition both as a head the contracts manager in liaison with the senior
office and site planning tool. planning engineer.
Within the large contracting organisations more
emphasis is placed on short-term planning pro-
cedures. The planning engineer should become 1.4 ROLE OF THE PLANNING
the 'right arm' of the site manager and the develop- DEPARTMENT IN A LARGE
ment of teamwork between site and planning staff CONSTRUCTION FIRM
should be encouraged. Site planners of today often
Case study particulars
become the key site management of the future.
The following case study relates to the planning
Refer to the case study relating to the organisation procedures adopted within a large building
of a planning department. firm - employing over 1200 staff and operatives.
The senior contract planner, and contracts The case study will be developed under the
manager, aided by the site manager, are respon- following headings:
sible for the preparation of the contract master
programme. The planning engineer provides a site Planning policy as laid down at director level
based planning service to the site manager on all The planning function within the company
major contracts.
Organisation structure of the planning
department
Duties of planning personnel
Objectives of pre-tender planning
1.3 DUTIES OF THE PLANNING
Objectives of contract planning
ENGINEER
The case study has been based on planning
procedures adopted by a national building con-
The site planning engineer's duties include:
tractor based in North-west England and has been
subject to my own interpretation of the planning
1. Liaison with site manager regarding the prepa-
role within the construction firm.
ration of stage programmes covering a four to
From observations in the industry no two firms
six week period.
control the planning function in exactly the same
2. Attendance at weekly site planning meetings to
way, therefore it is difficult to establish a model
liaise with trades foreman and sub-contractors'
planning procedure which would satisfy the require-
representatives. Preparation of the weekly plan
ments of all large companies.
of work.
3. Liaison with sub-contractors and suppliers to
ensure adequate resources are available to 1.4.1 Planning policy statement
meet the requirements of the short-term plan.
4. Progress recording - updating of master pro- It is important that the planning procedures to be
gramme and short-term programmes at weekly used within a company have the full backing of
intervals. Liaison with head office regarding the senior management. Planning policy should be
progress situation. laid down by the board of directors and may be
5. Preparation of weekly progress report aided by communicated to the staff by means of a policy
site manager. statement. This may take the following form:
6. Recording receipt of contract drawings - dis-
tribution of revised drawings and maintaining POLICY STATEMENT
drawing register on site.
7. Collection of planning output data on site "The company policy for the planning function in
operations specifically requested by the senior B and C Construction which has been laid down
contract planner/contracts manager. by the Chairman and accepted by the board of
8. Preparation of method statements in liaison directors reads as follows:
with the site manager for future stages of work. 1. To establish a strong and lively planning depart-
9. Attendance at monthly site meetings. ment under the control of the planning director.
5
2. To provide a comprehensive tender programm- chief contract planner and the chief tender
ing service to each production director, the planner.
production director being ultimately respon- The duties of these two functions include:
sible to the managing director for the final
tender programme. Chief contract planner
3. To provide a comprehensive planning service
to the production director for contracts 1. To meet the needs of the company's contract
awarded. planning requirements at head office and on
4. To produce progress reports at not greater than contract sites, including short-term planning
fortnightly intervals with copies to all those and liaison with site management
directly concerned with the contracts including 2. Receiving and co-ordinating all progress re-
the production and surveying director. ports.
5. Programmes and the adherence thereto are the 3. Preparation and maintenance of all records.
direct responsibility of the production director.
6. The production of monthly reports for con- Chief tender planner
sideration by the board of directors is the joint
responsibility of the surveying and production 1. Preparation of all tenders including the
directors. establishing of tender documents and the pre-
7. Accurate progress reporting is the direct res- paration of tender programmes.
ponsibility of the planning director. 2. Liaison with the estimating team in the prepara-
8. The system of planning to be used must be tion of the tender plan.
appropriate to the form of construction. The 3. Liaison with senior management in the prepara-
planning director is directly responsible for tion of tenders. To seek advice from contracts
planning development and the arranging of management as and when required.
training courses to keep planners and site
management informed of changes in planning Senior planners
techniques and policy.
B.C. These will be affiliated to a construction unit as far
September 1988 Chairman" as is practicable. In certain instances this may be a
major contract site. The senior planner will be
The planning function is, and must remain the responsible for liaison with the site manager and
ultimate responsibility of contract management. supervising the planning staff allocated to that
The purpose of the planning department is to project. His responsibility will be to advise on
provide a planning, programming and monitoring techniques, methods of planning and the presenta-
service to management both on site and within tion of planning data.
head office.
Management must always be aware of the role Assistant site planners
each service department plays and one should not
allow 'empire building' within individual depart- These, in the main, will be management trainees
ments to be encouraged. having some qualifications in building, or currently
studying for them. Their experience and
background will be varied and many will be
1.4.2 Organisation of the planning undertaking work in the planning department as
department part of their management training programme.
Additionally some will be management trainees
The planning department organisation structure is receiving planning experience for a period of up to
indicated in Figure 1.1. The department is under three years.
the control of the planning director who has the
authority, after consultation with the production
director involved, to move planning staff to con- 1.4.3. Pre-tender planning procedures
tracts to which they are allocated. On site, the
planner is directly responsible to the site construc- The objective is to provide for the managing
tion manager. The planning department provides director, after discussion with the tendering team,
two separate but related functions headed by the as accurate an assessment as possible of the time
6
PLANNti<JG O~PA~T!Vt£NT ST~IJCTU/t.£
( L Alt.Gi F t~M)
PLANI>IIN G
l>tlt..ECTOL
C.HIEF CHIEF
T£Hl>~ll.. PLANH£1t.. (t) CONTC.AC.T PLANNE'Jt. (•)
PLAI>IHCX.S PLA~>~~>~n
r~---------JA~------------~,
08.TECTIVE- "T"O />ll.OVIOE
ASStSTAAIT ~)
PL.AHNIHG AAVIC£ AT SITE PLANNIAIG
"TFto.lbCit.. STAGE A .S Pllll.T EN&ti>I..._S
OF Plt.l.- 7£Nl>CJIL PLAHHtfoiG
o&JEcTt'IIE- To PltoVtDE A
PLAHNifoiG SEit.'IIICE. AT SIT£
MAAIAGEMEHT LE.VCL. PLANNING
AND PltOGI£ESS COAintOL
Figure 1.1
and resources required relative to the contractual Control of tendering procedures
risk and conditions of contract.
The control at tendering stage is achieved by three
formal meetings:
1.4.4 Involvement with pre-tender activities
1. Preliminary method meeting.
2. Final method meeting.
Tender planning will normally be undertaken by a 3. Tender meeting.
senior planner; if possible the planner will be one
affiliated to the construction team selected to carry The chief tender planner will attend all the above
out the project. The planner's first responsibility is meetings. Once the final tender meeting has final-
to initiate and promote the necessary liaison with ised the content of the company's offer, no depar-
the estimator and contracts manager. Details of ture from this may be made without reconvening a
all decisions made during discussions must be further tender meeting. Standard forms used in the
recorded. pre-tender planning process include:
The planner is responsible for the preparation of
the tender programme and the associated method Planning calculation sheet
statements and presenting the data in a standard Tender planning report
form to the tender meetings. The pre-tender report Typical pre-tender programme
is designed to ensure that no aspect of the tender Sub-contractor's requirement questionnaire
planning is omitted. Method statement proforma
7
1.4.5 Contract procedures Programme decision Responsibility Agree
stage for
The main objective is to assist the contract manage- preparation
ment team by providing a contract planning ser- 1. Improve or accept
vice. Initially this would involve supplying all tender programme and SM P CM
relevant data and details of the contractual com- method
mitments and the preparation of an agreed con- 2. Advise on any variations CM
tract programme - for example, contract master in information
programme. This may be followed by a monitoring 3. Prepare draft contract
and progressing service and the preparation of programme including
periodic short-term programmes and other such sub-contractor's
activities, highlighting
planning services that may be required by contract
critical items of work
management. and examining the most
economic means of
reducing critical time p SM CM
1.4.6 Responsibility for preparation of the 4. Prepare schedule of
contract master programme temporary works SM ENG C. ENG
5. Prepare site layout plan SM p CM
The determining of the contract master programme 6. Prepare final contract
is the responsibility of the contracts manager programme, highlighting
contract start and finish
for agreement with the production director. The
dates, date of
site manager's commitment to the programme is waterproofing building
obtained by discussion between the contracts and holiday periods p SM CM
manager and site manager. 7. Define latest dates for
The planner allocated to the contract will liaise receipt of contract
with the contracts manager and site manager in information regarding
order to improve, expand or accept the tender design data and
material and prepare the contract programme and nominations p SM CM
other related documents as the basis of the com- 8. Define latest dates for
pany's commitment. Tender programmes are not delivery of key materials
and plant p SM CM
to be altered to serve as the contract master
9. Prepare resource
programme; the latter must be redrawn based on
schedules for labour,
the current information available and a re- plant, scaffolding and
assessment of the contract requirements. site staffing p SM CM
The detailed responsibility for the contents of the
build up of the master programme are summarised Liaison between planner, site manager and contracts
in tabular form in Figure 1.2. This indicates the manager during preparation of contract master pro-
close liaison necessary between the planner and gramme of the initial information assessment.
the site management team.
Abbreviations: SM -Site Manager
CM - Contracts Manager
1.4.7 Schedules of information P -Planner
ENG - Engineer
requirements C.Eng- Chief Engineer
At the beginning of a contract, a schedule of Figure 1.2
information required must be forwarded to the
architect and the planner is responsible for the
preparation. In determining the dates for the receipt of informa-
Separate schedules are to be prepared covering: tion, account must be taken of the time required
for processing design information. Ideally the sche-
1. Architectural information. dules should be based on information obtained
2. Structural details. from the architect of all drawings and information
3. Services requirements. he intends to issue to cover the contract. The
4. Details of prime cost sums and nominations. schedule of information relating to key dates
8
should be requested from the architect before the 1.4. 9 Responsibility of planning staff for
contract programme is finalised. short-term planning
The provisional contract programme should be
issued to the architect for approval in order that (1) Short-term programmes are to be prepared by
key dates may be agreed prior to the issue of the the planner to cover periods of 8 weeks. The
final contract programme. programme is to be reviewed every 6th week
Information schedules should be prepared to and the programme for the next 8 week period
cover information relating to: prepared. The procedures continue in 6 week
cycles until contract completion. Programme
1. Drawings - dates for the release of data rele- reviews are to take account of the progress
vant to setting out, boundary information, con- actually achieved, the effect of the latest infor-
struction detail. This may also include for such mation and any acceleration or other require-
items as services layout drawings and details of ment dictated by the contracts manager and
service pockets. site manager.
2. Schedules of manholes, doors, windows, iron- (2) Short-term programmes are to be sufficiently
mongery, colours and furnishings. detailed to permit economic construction and
3. Nominations, including estimated dates by should indicate labour, plant and sub-contract
which site work must start and the duration resources required.
periods allowed in the programme. (3) Standard programme sheets are to be used and
4. Dates by which the instructions for expending the programme must be cross-referenced to
provisional sums must be given. the contract master programme.
9
1 . Progress reports for contract management to be 3. Short-term progress reports are to be submitted
prepared monthly to co-incide with site meet- every two weeks for consideration by the site
ings. This must reflect the planner's own assess- construction manager.
ment of progress after discussion with the site
construction manager. The procedures outlined in the case study may not
be representative of planning procedures under-
2. Progress report to be submitted to the directors taken in other large companies. They may however
at two monthly intervals. This will normally be be used as a guide to establishing more formal
in the form of a summarised and edited version planning procedures in both medium and large
of the monthly report. sized contracting organisations.
10
Chapter 2
Case Studies relating to Bar-charts
11
Bar-chart Programme Case Study 2.1
Factory Project Project Valuation Forecast
12
Bar-chart Programme Case Study 2.1
Factory Project Project Valuation Forecast
Bo ...
- - - - - - - - - - - - - - - - - --
I I
I I
-- - ,..,. -
I
I_--------
I
- - - - _ _I
,,, "
,
P.C.oPosl:b
,'
CA.C. PA<It.~ '
, ,
,,
I=ACToR.Y PR.o3"ECT
~ ..... .....
..... ..... .....
.... .....
.....
STn1.
Po.C.TAL
F<lt.AMI
.2.00 SLA8
.2!SO
Ac:cES.r ~oAD
S EC:T lOki
13
"T'' =
AI AI
I") ';'
- I")
5;
"<
=-
AI
"'C :s.
"'C
~
-·a ... Q
I") QQ
- ...
AI
~ACTOR.Y Pf/I.OJEC.T OA.A FT ""'-"' S TEA PII.OGI!I.A MM£ 3
3
~
0 Pl:'ltATION But>Gt:T I I I I I I I I T T I I I I I I
112131415'1 ,;I 7 Is I ~ I /0 I II I /2. I I~ I I+ I IS I I c I
I
SIT6. I I
I SI.T UP I
~ I
I I
:a f.XCAVATION cz:z:z:::z:r I
I I
I
I I
3 PILING IZZZZZZZZJ
I I
I
12 2 ? 2 t 2 I 2 2 2 2 2 2 2 2 2 2 2 II I
,I
4 ,.,,_,C,.,.:I' B611NIS 01
j:l
s ~lt.ICT .STal.I..IOI!I.IC a:zzzzt
I ~I
,,
4::..
6 .I!I.ICICI..IOI!I.IC TO b,. C ll
JZZZZ2I 01
7 GllouAIC> FLOOR. IZZZZZZZZ?Z??~ZZZI
u
I
I .. I
8 /l.OOT SHE£TIIItlti ???? 2 zzzza I ul
~I
I
I
~I
q t..IAI.L SHiiFTING IZZZZ2222j ~I
IJI
I I
/o l>ltAIIIIA G E 1?222 2?2 ZZZI fZZZZZZZZ) I
I
I
I
II £V r. IIIII. I CIC wolr.IC 12?2?2222?2222222?~ ..."'C
I
..2.
~
I")
I I
I I I
I <
I I AI
i : I 1 ("')
-c
AI AI
fl>
5" ~
:I
-
"T''
Ill
c
Q
...
- c.
~ "<
I")
~ !'-1
Figure 2.2 Factory project pre-tender programme
- ...
Dol
.,Dol =
t"l ...
-
Q I
t"l
... ::r
-< AI
""C:C :::1
""C:C
FACTofl.Y P fl. OJ EC T Cor..~Tit.ACT 8UOG£T - V.AL.LJATION FOII££CA.ST ~
-·a ... Q
t"l (JQ
- ...
AI
3
I 3
~
0/>E~ATIOH I I I I I I I I 1 I J I I I
8u1,;" 1 l21314ls l ~ I 7 I 8 I e I 1o I " I 1:2. I 13 1 14 1 1s 1 Ho
I
I I
I
I SAT Uf> SIT£ lo ooo ~ I I
~ I I
c:::::::J I
.. EXCAVATION 2. ooo I
I
s 5 I
3 PILING 10 ooo I
2. 12. 2. 2.. I
4. PILE CAl'S, BE.AAof S 8 000 201
6 E/t.ECT STRU.JOIUC. 2.0 000
~3
&R.ICI(WOU To bPC 3 000 ~
" I s s; 5 5
V1 ~oooo I I I I
7 G Roui'Jb FL.DO/t. I
I 10 10
8 RooF SHEETJWG 2.0 000 I I
•
I
I B a
WlfLL SH aTII<IG IIi 000 I I
I
" 3 ~ I 2.. 2.
/Q ll/U.I/1114 '*£ Cf 000 I I I I
I I
I
I 4 4- 4- 4-
II E'J:r. &R.Icxwolt.X IG ooo
I I
- - - - - - - -
I -
I
""C:C
I I I I I I I I I I I I I I
PIUUMS R.ECc:NEit.V /(; 00 0 I t I I I I I I I I I I I I I I I
~
-·a
t"l
:II & 8 8 r3 3 3 %1-j 1¥ /~ 1&1~~ 12. 7 5 s :
IV££kl.'{ auoG•T I I I
1
cu,..u&.ATI\11 auotUT /5o ooo : II 17 2.5 .33 : 3.0 3'9 ~2. ~3: "77 Cf3 1o1 /:ZI: 133 t¥o t'l-5 1so:
-
~
cAI n
I 1 I I AI
Cll
VAL. VAL.NII. cs· ~
VAL.IJ/1. I VAL. N/1.2--l>i N•~l of-;>: :I
-
VALUATION 0ATL5 -1> ~ tn
I .,
0 c
... - c.
~ -<
Figure 2.3 Contract budget- valuation forecast t"l
AI N
Cll :...
-
Bar-chart Programme Case Study 2.1
Factory Project Project Valuation Forecast
ISO
VALU£- T/11£
IAI-o R.'U.TIONSHI
ISO
1'2.0
110
100
qo
""':I.J
< 8o
>
...
u 70
<
~
~
0 GOO
0
so
40
30
:lO
VALUATION FORECAST
lo
0
0 2.0
8 I~
COI>JTR.ACT OUR..ATIOI>J
16
Bar-chart Programme Case Study 2.2
Factory Project Project Cash Flow
ANALYSIS OF THE PROJECT CASH FLOW come being paid to the contractor 4 weeks after
REQUIREMENTS TO BE PROVIDED BY the valuation submission date.
THE CONTRACTOR The value, cost and income are represented
graphically in Figure 2.5. The graphical presenta-
tion clearly shows the relationship between valua-
In order to prepare a forecast of the cash flow
tion forecast, cost and income. By moving the cost
requirements, the following information is required
commitment forward 4 weeks in order to create a
from the contract documentation- and analysis of
payment delay, the effect on the cash flow is
the tender:
clearly demonstrated.
The cash finding to be provided by the con-
1. Contract value - £150,000 tractor may be read directly from the graphical
2. Contract period - 16 weeks presentation or presented in a tabular form of
3. Payment interval -Monthly analysis as Figure 2.6.
4. Retention applicable - 3% Summary of project cash flow requirements:
5. Profit included in the estimate- 15%
6. Delay in meeting the cost: Month Net cash flow Cross cash flow
average payment delay - 4 weeks
7. Interest payable in financing 1 - 14,350 - 14,350
the contract - 20% 2 + 3,310 -28,700
3 + 6,310 - 22,790
The cash flow requirement is the difference at 4 + 12,170 - 44,090
any point in time between the MONEY IN (monies 5 + 17,350 - 13,030
received from valuations) and the MONEY OUT
(the expenditure or cost).
The assessment of the cash flow will be devel-
oped from first principles based on graphical ASSESSMENT OF THE INTEREST CHARGE
presentation of the value-time, cost-time and ON CAPITAL LOCK UP
income-time relationships. The cash flow will also
be developed by computer using spreadsheet
techniques based on the APPLE II microcomputer The cash flow diagram for the project is shown in
and VISICALC. Figure 2.7. In order to calculate the interest on the
The cumulative monthly valuation forecast on capital locked up in financing the project it will be
which the cash flow is to be based is summarised necessary to assess the average monetary sum tied
as follows: up each month. This may be calculated from the
cash flow diagram as the area below the zero base
line. By considering the monetary requirements at
Valuation Cumulative Cumulative Cumulative the beginning and end of each month the average
value cost income may be assessed. In months 1 and 2 the contract
requires full funding while in months 3, 4 and 5
1 33,000 28,700
funding is only required for part of the month. By
2 63,000 54,800 32,010
observation of the cash flow diagram this may be
3 121,000 105,200 61,110
assessed as a 3 week period in months 3 and 4 and
4 150,000 130,400 117,370
a 2 week period in month 5.
5 147,750
17
Bar-chart Programme Case Study 2.2
Factory Project Project Cash Flow
RETEI>ITION 3°/o
PR.OFIT 15%
PIIY MEI>IT P£~100 - 4 WEfilt::s
O£LAY IN MEETII>IG - 4 WfiEI<S
COST COMMtTM/iN T
140
12.0 I
I
,
I
I 117 ,570
I
110 I
I ,
I
~
100 I
I'
I
I
VAL.UI£ • TI""E
"'::J
.J
qo A.ELATIO,.,SH IP.
I
I
COST-
TIM I£ 4 f,.J££1<. 0£1.AY
'(
I I
IN M££111/G
I
)
8o I
COST
,.. I
I
I
I
u I
'< "'70 I
,..ct I
I
2 v I I c; 1110
0 Go I
u I
so
* ,
4o
I
I INCoME- TIME
II>JC.OME i=«OM VA LUIITION!O
32010
~0
c
2.o
R.ELATION.SHIP
8 12. ,.
CONTA.ACT OUR..ATI0"-1
18
Bar-chart Programme Case Study 2.2
Factory Project Project Cash Flow
provided each month. This has been abstracted TOTAL INTEREST CHARGE
from Figure 2.7 as follows: £877.48
ON CAPITAL LOCK UP
Minimum cash requirement is termed the Net Cash Flow, maximum cash requirement is termed the Gross Cash Flow and the
contractor will require loan facilities to take account of the above sums during the contract.
19
~
"'" = ~
l"l ...
0- I
l"l
... :r
'< ~
~ ::l
S!.......~
MO>.I"TH 3 4 s ~ <i
Factory Project
...
~
-1'+3SO - t'+.3So +3310 -Z.2.7ool+ G310
3o
- 3
3
CASH I'll
Bar-chart Programme
.2.o
CASH
SHOit.TFAU.3 0
+o
N
a 50
FUNDING R.EG.UIR.£0
s 0 13 03 0 t; Sl S 2. WEEI<:S
~
...
S!.
I'll
l"l
~
Bar-chart Programme Case Study 2.2
Factory Project Project Cash Flow
A B c D E F G H
1
2CONTRACT PROFIT
3
4DURATION <MONTHS) RETENTION
5
6
7MONTH DATE CUM VALUE CUM CUM DELAY lN NET CASH MONTHLY GROSS
8 COST INCOME COST 1M REQUIRED INCOME CASH
9
10---------------------------------------------------- ---------------------------
lll 0 0 0 0
12 2 0 0 0 0
13 3 0 0 0 0
14 4 0 0 0 0
15 5 0 0 0 0
16 6 0 0 0 0
17 '( 0 0 0 0
18 8 0 0 0 0
19 9 0 0 0 0
20 10 0 0 0 0
21 11 0 0 0 C)
22 12 () 0 0 0
23---------------------------------------------------- ---------------------------
24
25
SPREADSHEET IKJDiiL
21
Bar-chart Programme Case Study 2.2
Factory Project Project Cash Flow
A B c: D E F G H
1
2CONTRACT FACTORY PROFIT 15%
3
4DURATION CMONTHS) FOUR RETENTION 3%
5
6
?MONTH DATE CUM VALUE CUM CUM DELAY IN NET CASH MONTHLY GROSS
8 COST INCOME COST 1M REQUIRED INCOME CASH
9
10---------------------------------------------------- ---------------------------
11 l 29/1187 33000 28696 14346 -14345 -14345
12 2 2!5/ 2 I 87 63000 54763 32010 28696 3314 32010 -28690
13 3 28/3/87 121000 106317 61110 54363 6321 29100 -22424
14 4 30/4/87 150000 1:30435 1170~'0 105217 12153 56260 -44793
15 5 0 145500 13005 1506~ -28130 -13065
16 6 0 0 0 0
17 1/ 0 0 () 0
18 8 l) (j 0 0
1') 9 0 0 0 I)
20 10 0 0 0 0
21 l l 0 0 () ()
.:.....:. 12 0 0
.-),j
I) ()
23------
24
CALCULATED DATA
22
Bar-chart Programme Case Study 2.3
Factory Project Budgetary Control
23
'- U 1\11 U L.A T I 'II E. VA L.U E FO~ECA.ST
'7"
2 10 0 0 0 75ooo
3 2Soo o qoooo
4 1#-2.000 8 <tBooo
q /00 ooo
100 ~00.!..!!0-
- - ---- -- -
~s~ - - - - - - - -
..... ·I
....
2.0
10
OUit.ATION
EMPIRICAL S CURV£
Figure 2.10 Valuation forecast based on { - ~ rule
24
"T'' =
~ ~
0- I
t"l
... ::r
-< Dl
.,... .,;:::.
.52.
0
~ a
QQ
VALU£ FORECAST 5ASEO ON Dl
CO .... VER.SrON CHAR.T
- 3
3
tD
2o
THE APPitOXIMATION GIVES A H IGHE"'R.
3o- C.UMULATIVI: VALUE IN THE E"AitLY
STAG£ oF A PA.Ql£GT TliE GII.APH
4-o-
ASSIMILATES A ST«.AIC:OHT LINE
"'::> so
..I C.OWTitACT 1/A LUE .f 100 ooo
< Go_,
> Dl.lflATION !:) "-10..,-HS
1o
~
0
8o
qo
N
v,
roo
OUitATION
MOo.aTH 0 /o COMPLETF. 0
VALUE MoloiTH /o COMPLETf: VAUJE ~
r:z.
J
·~000 ~ ~8 t:;;Booo
2. .14 .:lAooo 7 ao Boooo
3 34 ~4ooo 8 91 .91 OoO
4 41iP 4loooo 9 IOO roo ooo
5 58 5Sooo
cQ..
=n
Figure 2.11 Valuation forecast based on conversion chart a,§ Dl
Dl "'tD
-< Vl
c
n Q..
0
-... -
:I -<
... N
2.. 1..1
-
Bar-chart Programme Case Study 2.3
Factory Project Budgetary Control
COST-VALU£ R.£CONCILIATION
VALUE COST
/UCONCIL£0 CUMULATIV£
CUMU LAT/11~ COST ANb
Af>/0 MONTHLY MONTHLY COST
VA .LUI
ANALYSIS
CU114UV.T1'1£ 1"/tOFIT
MoNTHLY PllOFIT
'Yo AHIIL'ISI.S
COMMIUS'... 0, A
AIID I'&.AII.,D lrlo#IT
AHALVSIS Of VA&IA,C£
IN VI ST I.ATI 11.110
DIT£/lllfiOIIE AC.TIO,.,
OUTPUT
26
Bar-chart Programme Case Study 2.3
Factory Project Budgetary Control
OAT£ ~U.R.ATtOI-J
VALUATION NR..
MONTHLY
bAT£ VAL. VALUE IUCotJCU.EIJ CUM. CVM •/o
Wll. CER.11FIED VALUE COST Ftl.ol'11 P/loFIT VAWE CDsT PlloFfT o/o
PR.oFIT /o
0 MONTH
II 21 31 41 S_l G_l '7_1
~ : : : I : :
+N ----'--·-'·---:-- ·- -~!C~T-~~~~-·lL·-··-
: I
0
-14&
27
Bar-chart Programme Case Study 2.3
Factory Project Budgetary Control
I 'SO
VALUATioN/TIM£
l'lo
FOIC.I£CAST
130
I:Z.O
VALUE VAll-lANCE
r-
110
TIME VAll-lANCE ro7.ooo
(,~
~
)
So P..E C.OI>ICI LE'D VALUE
1- CUMULATIVIE coST
u P..t; LEAS El)
I
< I
Ill 70
1- 1 I
//
1
);/
0
\J c;o
v C:03000
I
I S20oo
5o
,/4" c 47000
,
1/
/
~0
30 v.~~-/
/
2.7SOO
,,
%.GIOOO
2.0 VALU £-TIM£
~/ COST- TIM£
IO
I'
.,
, I'
8 /2. 1(0
bUR..AT/OkJ ( r.JU~<s)
28
C O.ST VALUE ~£CONCILIATION
VALUATIO..., NR. - 3
Mo,.,THL"I
OAT~ VAL. VALUE A,ECDNCIL£1. CuM. C.UM. O/o
N/2. C!Eit'nFIED VALUE CoST PltOfiT PlloFtT VALUE COST PlloFn •/o
J J /. I J I i
.l.W 3A.. NAI 2..8200 27500 2~000 ISOO 5·77 2.7Soo 2'ooo 1500 5·1 7
2~ FE& N,c..2. 54200 S2000 47ooo Sooo 10·64 2.¥$00 21ooo 3Soo 16·& 6
30-'fM. NA.. a 108700 to7 ooo Cl~ooo IJooo 11·11-S 55ooo 4'9000 ~ 12·2
MOAJTH
1 I .:Z.6 F~a. :~1 ao Mlftt.. 3 I '+I
I
~' I
.a.o 1 I FOR.E.CAsr
I ~-.- I : Mllltt;ll</ IS%
IS ------' - - -....&-- o:-_..._~_l---- -1----- I
I ""'•""' -'" • 'Z"-
10-~1
..... •
I....
"r
I I
5- 1 I :
I I I
29
Bar-chart
Budgetary Programme
BudgetaryControl
Control Case Study 2.3
Factory Project Budgetary Control
COST-VALUE RECONCILIATION £11,000 below forecast and the contract is still one
ANALYSIS week behind programme.
Progress and profit released to end of month 2
Month 1 must be maintained throughout the forthcoming
Cumulative position Comment monthly period.
£
Budget forecast 33,000 Contract's progress 1 week
Actual cum. value 27,500 behind programme based on Month 3
Variance (total) -5,500 site progress reports. Delay
due to late start of foundation Cumulative position Comment
works.
£
Budget forecast 121 ,000 Contract progress still 1 week
Actual cum. value 27,500 Profit release to date £1,500. Actual cum. value 107,000 behind programme based on
Cumulative cost 26,000 Profit expressed as % of Total variance 14,000 site progress reports.
Cost variance 1,500 cumulative cost.
(Profit)
Actual cum. value 107,000 Profit release to date £11,000
Cumulative cost 96,000
Profit forecast % 15 1 500 Cost variance 11,000
Actual profit % 5.77 Profit%--- = 5.77 (Profit)
Profit variance % -9.23 26 000
Profit forecast % 15.0 Cumulative profit position to
The current profit release of 5.77% is well below Actual profit % 11.45 date 11.45%. Increase of 1%
the 15% profit margin forecast. The need is to Profit variance % -3.55 in position during past month.
investigate the cost and value of individual opera-
tions undertaken during month 1 - for this reason Monthly position
it is important that cost-value comparisons are £
Budget forecast 58,000 Increase in value of work
made as close as possible to the valuation data (say Actual monthly value 55,000 during month 3 is due to
within 5-7 days). Monthly variance 3,000 early commencement of
finishing trades on services.
Month 2
Actual value 55,000 Monthly profit margin still
Monthly cost 49,000 below forecast but
Cumulative position Comment
Cost variance 6,000 improvement during month 2
£
Monthly profit 12.24% maintained.
Budget forecast 63,000 Contract's progress 1 week
Actual cum. value 52,000 behind programme based on
Total variance
Profit release to date 11.45%. Necessary to
-11 ,000 site progress reports.
analyse profit release on remaining work to be
Actual cum. value 52,000 Profit release to date £5,000. undertaken in order to complete the project. (Con-
Cumulative cost 47,000 tract sum £150,000- work completed to date
Cost variance 5,000 £1 07,000.)
(Profit)
A forecast of the finish profit from the contract
Profit forecast % 15.0 Profit release to date 10.64%. may then be obtained; if possible additional quota-
Actual profit % 10.64 Increase in cumulative profit tions may be obtained for siteworks/landscaping in
Profit variance % -4.36 from previous month order to boost the profit position. However, at this
(5.77%).
late stage the profitability position may not be able
Monthly position to be greatly influenced by management decisions.
£ The example is intended to illustrate the need for
Budget forecast 30,000 Forecast value per month still management to analyse closely the cost-value
Actual monthly value 24,500 not being maintained. Increase performance during a contract. A wide range of
Monthly variance -5,500 in profit release from 5.77% to
16.66% for monthly period.
building and civil engineering companies utilise
Actual value 24,500 cost-value control techniques as their only method
Montly cost 21,000 of cost control. It is not unusual for specialist civil
Cost variance 3,500 engineering contractors to allow three months to
Monthlv orofit 16.66%
elapse prior to preparing an accurate cost-value
Cumulative profit position improved from 5.77% comparison only to find the contract position
to 10.64%. The total variance is still however irrecoverable.
30
Bar-chart Programme Case Study 2.4
Canal Project Pre-tender Programme/Method Statement
A number of contracting firms rely on weekly The sequence study is simply a detailed study of
labour control procedures for short-term cost con- the operational sequence presented in bar-chart
trol and hence less emphasis is placed on monthly form.
cost-value procedures.
METHOD STATEMENT- PURPOSE
DESCRIPTION OF PROJECT
Method statements are prepared at the tender
The project consists of a canal renovation project stage in order to provide an assessment of the
in order to provide a marina facility for pleasure methods of construction for inclusion in the
boats and yachts. estimate. The method statement is normally pre-
Work involves cleaning out the existing disused pared by an experienced construction manager in
canal and lock. A precast concrete retaining wall order to provide advice to the estimator.
300 metres in length is to be constructed adjacent The contractor may also be required to furnish
to the existing railway. the engineer/architect with a statement of con-
The existing lock fronts onto an adjacent tidal struction methods to be used during a particular
river and temporary works are required across the stage of the contract.
lock entrance. The lock is to be emptied of silt The method statement may be presented in the
approximately 4 metres deep and a new in-situ form of a descriptive statement covering each
concrete retaining wall constructed to one side of operation relating to plant or construction methods.
the lock. The sequence of construction should be clearly
Figure 2. 16 indicates a plan of the overall pro- expressed in the statement and alternative methods
ject. Figure 2.17 indicates a section through the should be outlined in order to aid estimating
existing lock showing the extent of the new retain- decisions. Estimates based on practical construc-
ing wall. Figure 2.18 illustrates a layout of the new tion methods lead to more realistic and competit-
retaining wall base indicating the sequence of ive tendering and clearly reflect an increase in
pours. tender success.
The method statement may alternatively be pre-
sented in schedule format as shown in Figure 2.20.
The information to be included on the method
CONTRACT INFORMATION statement includes:
Contract value £267,000. Contract period 24 Operation description
weeks. Figure 2.19 indicates a draft pre-tender Approximate quantities
programme for the overall contract. Method to be used
The contract tender includes a monetary sum for Plant requirements or summary
piling to the lock mouth in order to provide safety Labour strength required - gang size
for the operations during the construction of the Output for labour or plant
retaining wall to the lockmouth. The construction Duration - assessment of operational time
of the temporary works is considered essential to Further information may include relationships be-
the overall success of the contract. At the tender tween the sequence of operations. The plant items
stage it was a requirement of the contract tender indicated on the method statement may be abs-
submission to submit a method statement. tracted for inclusion in the build up of preliminaries
With reference to the project information the or may later be used as the basis of the plant
following tasks will be undertaken: requirements schedule.
31
f}(. .RA IUJI'I'(
1111111111111111111111111111111111111
-· ·-·-·
· - · - · TOWPATH ·-·-· ·-·-·-·- CONS TRUC TIOI'I
- - - rII I I
N£'-J P. C. R..ETAiolltlt!t II
I . .. ------
, ... . CAI>IAL WALL I I CAI>IAI.
ISoo,.,• I I
1· ,' OF I
"'
t! ,'/ :S POl&.
' qoo ,._l o~ SPOIL. :I
I I
\r
falii/IIIT" TO LOC"
WAu. .&ua.I'Ac&
w
w \
AVERAGE OEPTI-4 01=
S IL7 IN LOCJr;.ltiiOI.JTH S&GUENC£ OF POURS
\
4 METR.ES. TO BAS£ ANO KIC.ICER.
R.IVER.
\
MER.SEY
\
\ WOR.K TO £X/STING LOCK
\ - Nf.W Rf.TAINING WALL
\
\
Figure 2.17 Plan of existing lock- showing proposed works
~ =
1:11 1:11
= ...I
e!.. ::r l"l
1:11
...""1:1 ...
1'1)
..S!. ""1:1-
4.,.., PoU#I.. l"l ...
r: ::-·. . ~ --
I :.. r.-·.-,._\., 0
OQ
CI'I~~IIIG
- ...
1:11
I.;_ • 3
3
1'1)
3•<~ PouR.
SII..T To BE R.E:MOV/£0 (."l-ISTING
SToooll, WALLS
'I>I.PTH
,4 PPilO'll
4-.
w
-!>.
Ol:t'TH
tii-1 .... ""1:1
{VAI&IIS) ~I
ii
=
c..
1'1)
I w-r I'OU/l. ...
.4NO
...""1:1
~
3
£.XT£NT OF RECONSTRUCTION WORK
I
::2. ~
:r 1:11
0 "'
c.. 1'1)
Vl Vl
~ETA IN lNG WALL D£TA IL ....
e:. §..
1'1)
3
-
-<
1-.J
Figure 2.18 Sections through existing lock ~.... ~
CANAL PR.OJ"£CT PR£-TENOER. PROGRAMME DAT£ -.TAHUARY 1!3815
AND LOCKMOUTH WO~~S Cl.IEAIT IJ W WB
FIG It/A- 2. I#J
No 0 Pa IVtTION ~
1J2.J3J+ •JGJ7JS ~ )1o J 11 )12. IS Jll~ )1• )145 17 )18)1~ Jao 2.1 Jz:z Iu 12.• uJ
I S&T UP SITE ~
,..a
2. CL.UN OUT CA...,AL. ~000 ~ooo -•/uee~ . I
w 7 PUI/IIfPUousE UOIUC.. I
Vl
8 SWI"'Ii<.IOG!' FHIHI#
I
=1
I
Figure 2.19 Pre-tender programme - canal project
Bar-chart Programme Case Study 2.4
Canal Project Pre-tender Programme/Method Statement
1. Removal of silt from existing canal basin contracts manager and be familiar with modern
2. Precast concrete retaining wall construction methods. When preparing a method
statement for drainage work one should be familiar
Excavation
with the use of modern trench support systems
Base construction
involving the use of patent box and hydraulic
Backfill to retaining wa!l
support methods.
3. Temporary piling work to lockmouth An extract from the method statement is outlined
4. Excavation to lockmouth in Figures 2.21 to 2.23.
5. Lockmouth in-situ concrete retaining wall
Base construction
Reinforcement and formwork to wall NOTES FOR ITEMS TO BE INCLUDED ON
Concrete to retaining wall METHOD STATEMENTS
6. Embankments and landscape works
7. Outfall drain from canal to lockmouth Excavation work
lt/EF.
OPI:It.ATJOiol GLUA,.,TITY MI:THOO I*LAUT LA&OI.J/1. OU!V.
Ntc
36
Canal renovation Method statement Date- 2 Feb. 1986
Sheet NR- 1
37
Bar-chart Programme Case Study 2.4
Canal Project Pre-tender Programme/Method Statement
38
Bar-chart Programme Case Study 2.4
Canal Project Pre-tender Programme/Method Statement
the use of concrete pumps. Cost studies may be gang - sufficient steel-
undertaken as part of the method statement assess- fixers to be employed in
ment especially where the estimate rate build up order to maintain rate of
directly affects the overall success of the tender. formwork fixing. Ratio be-
tween carpenters and
steelfixers approx. 3 to 1.
form work
39
Bar-chart Programme Case Study 2.5
Retaining Wall Project Sequence Study
SEQUENCE STUDY FOR THE IN-SITU Sufficient alternative work is available on site for
CONCRETE RETAINING WALL TO THE labour gangs between concreting operations.
LOCKMOUTH The sequence of operations will involve cons-
tructing bay numbers 1 to 10 as shown on the
lockmouth plan as the wall is straight between
PURPOSE OF SEQUENCE STUDIES these sections. Bay numbers 11 to 14 are to be
formed to a curve and this will necessitate altera-
A sequence study is a detailed analysis of a con- tions to the kicker and wall formwork on comple-
struction task. It is an in-depth study of the tion of the straight length of wall - refer to the
sequence of construction depicting time periods in overall plan in figure 2.18.
days. The study is intended to cover sufficient of It is important for the planning engineer/
the operation to enable labour and key resources construction manager preparing the sequence stu-
to be assessed. dy to have a thorough knowledge of the construc-
Sequence studies may be undertaken in order to tion process. He should be fully aware of the types
assess the economic utilisation of formwork as in of patent formwork systems available and be able
the case of a column sequence or retaining wall. to call readily on specialists for temporary works
The programme format may be likened to a design facilities. Cost information must be available
short-term programme but it does not need to relating to the hire rates of the various formwork
cover any specific period of time. systems proposed. Supplies of patent systems will
readily provide scheme drawings and a design
service.
PROJECT INFORMATION Figure 2.25 indicates a plan and elevation of the
pouring sequence. The fourth pour to the wall
The work involves the construction of an in-situ
capping is to be considered as a make up pour to
concrete retaining wall 500 mm thick and 6 to 7
the overall height of the wall and has therefore not
metres in height. Figure 2.18 indicates a plan of the
been shown on the wall elevation.
lockmouth indicating the sequence of pours to the
base and kicker.
SEQUENCE OF OPERATIONS
Assumptions on methods of construction
1 . Lock excavation work has been completed It is first necessary to consider the sequence of
together with the temporary works sheet piling work from the contract drawings.
to the lockmouth.
2. The base and kicker is to be cast in fourteen Duration
bays. The base reinforcement is to be prefabri- Base and kicker - 10 bays per bay
cated in three metre bays adjacent to the works Fix reinforcement - pre-
and lowered into position by crane. fabricated sections 1 day
3. The retaining wall is to be poured in four Fix formwork to base and kicker
sections consisting of the base and kicker and (1st bay) 1-j days
three wall pours per panel (14 panels on plan). Concrete base j day
4. Patent formwork is to be used for the wall face Strip formwork and refix (remain-
consisting of aluminium soldiers incorporating a ing bays) 1-j days
plywood faced shutter. Figure 2.24 indicates Wall pours - 20 bays
the formwork detail. Fix reinforcement to wall 1 day
Two sets of wall shutters are to be made Fix formwork to wall face 1-j days
initially available - further shutters will be Concrete wall panel j day
available if required. Strip formwork and refix 1-j days
5. Concrete and formwork handling is to be un-
dertaken by a mobile crane located at ground The durations are based on a practical assessment
level adjacent to the works. The crane is also to based on the experience of the construction
be used for the handling of steel reinforcement. manager.
40
Bar-chart Programme Case Study 2.5
Retaining Wall Project Sequence Study
FOR.MINOR.I< DETAILS TO
RETAINING WALL
C.At..JTIL£\1 £RE"D
F OA.M WOIU<..
..S TR.O#JG 8.1\C~
2ND WALL LIFT a..JA.LIHG.S
" , . Tl~$ TO
PR.~"IOfJS
._
, C 0 NCR.6 T£.
LII'T
j#
.,
~.
,
I>AT£#./T
. 0
A LUMIOo/IUM
"'.-...
ANl> hi.I\1-IA/6$
J
..:1 ·~
"
....
...
<
l -4----
.."'
-
I<.ICI<ER.. AI>ID lsr LIFT
TO WALL
0 "0 ·... 0
•I'
• 0
..
Figure 2.24 Formwork proposals for retaining wall
41
R.E'TAINING WALL BAY LAYOUT
!JAY LAYOUT
PLAN OF BAS£ POUltS.
I./AU.
Poue
II IGO 12. 17 I :!I 18 ,,. I~ IS 2.0
WALL
POUR. I G 2 7 3 8 4 !:) 5 10
8A$£
8AY 2. ..., 8 5 10
SEQU£NCE OF POUR.S
HEIGI-lT OF LIFT
2.·G ... To 3•2.""
WALL Poua.
42
Bar-chart Programme Case Study 2.5
Retaining Wall Project Sequence Study
43
R.£7AININ G WALL /eESOURC:E S- I SET OF 8A:S£ .SHUTTI&R.S
CASE I - S£GUENC E STUDY 1 sn- OF WAL.L. SHurr£/lt.S
OPER.ATION /:)Uti.. I I J I I I I I I I I I I I I T -r
bAYS 'I2I:5J+ :. 1 10 1 , 1 12 13 IS It; 17
5I'"I7IB II¥- I I I Ill I 19 I -zo I I
/3.4$£ ANO I< I C: 1<.£R.
I 2. 3 4 s ~
.., 6 9 IO
F IY. R.E.IIJFOII.CE/IIIEIJT I 0
,
~IX FOA./IIIWOIU< /0 c:::::J
I .., , 10
CoNC/l.ETE BAS~ IIJ I::::J ~ 6 6 c!::J 6 ~ 6 'c:::J c:::J
IO
STII.IP ANO R.E.FIX 10 6 c:!:3 ~ 6 ~ ~ 6 6 c:::::J
FOIC.IIItWOitl(
Poull.. uuM&d:S
/I>IOICATS"D
I./ALL POUR.. S SE.eouo FA"'G
-1:::..
-1:::..
OF STii~LJ IX
F~ REINFOR.CEM CN1
I
Fl'-1. ~011./IIIWOIUC. H.o I I
R.ESOU~CES
.., t ~ 2. '1 2. 2. 2. % :l'" sJF
STEELF/Y.E"RS Gl- BASE
"'I I ,2. I I I I I I I' LA&
sJ,:- ., 1 I I I I I I I I I I I I I I 1.,.
Ci2- WALL I I
LAe ' I I I I I I I I I I I I I I
CAR.PE.HTE:R.. Gl- BAS£ ~----~ ----~---- -~ ---~---
I I I I~ ---~---
I I I I~ ---~
I ---~-
I --
~2. 2 ~ 'Z. z 2. ~ 2. 2. 2. 2. 2. 2. 2.
G2- WALL ... ,.....
~~-
45
Bar-chart Programme Case Study 2.6
Reinforced Concrete Frame Sequence of Construction
JL
II
£L.E VATio N
*
POUR.. PouR.. 2. PouR. 3
3 5 .., 9 II 13 15 17 19
4 12. 16 18 2.0
·~
10
46
FLO Oil. CONSTRUCTION SEGUENC£ FOR.
CASE I
SuFFICIENT 8£A"'' SoFFITS FoL A
C. OM Pl..fiT£. FL.OOR.
(0; C 0 L.UM AI S
Poult 3 ~
K
*
F-LOoR. POUlt. FLOOR. POUlt.. 2.
I j I
I I 1
I I
S UFfiCI£/>JT ~LOO/t.. ~Oit.MWOR..Jt:. ~Of! A COM PL.I&TE.
j'
l_., I:>ENOTr .5 MOVEM£/>JT Of. 1!0/t.MWOR.It!.
• I
l......, l
'-' ~~
~-
l ,"
t
..........
1/'
'-1 "-J
~'
47
CASE 2 S Uf!FICI£NT i=ORMWOR.IC. FoR. %•..tr ANI> '/3 --.1
o,: A F L.OOR..
SEGUJEtJCE 3- 8£AMS A
t=LooR..
n ...
------ ----- ----
~-----1·--r--] ,,
II
••fl••
••••,,
..
II II
•• ••
"
I
SEQUENCE 3- BEAMS
AND FLOO~
,,11 ~
at
••I •'••
,I
k
* >k
~.a ~0 f!LOOR. ~R.O FLooR. ~3R.O FLo oil...
48
Bar-chart Programme Case Study 2.6
Reinforced Concrete Frame Sequence of Construction
Figure 2. 30 illustrates the sequence of construc- The manhour allocation for formwork is based
tion during the erection of twenty seven columns on fixing and striking formwork - it is assumed
using six column shutters. The movement of the that patent standard formwork is to be used and
formwork is shown. A bar-chart sequence for the the making element can be included with the
movement of the column shutters is shown in fixing.
Figure 2. 31 together with a labour resource assess-
ment. The planner is encouraged to develop se-
quence patterns illustrating the movement of the
Allocation time for columns
formwork and labour gangs.
The introduction of additional column shutters
will not always speed up the overall floor construc- REINFORCEMENT- Steel delivered to site cut
tion sequence - it may simply result in columns and bent only.
standing awaiting the construction of the floor slab
to the floor above. 80 mh
With column shutters, a degree of remaking of
Time allocation for 6 columns = -- X 6 = 24
20 Nr
formwork will have to be allowed after say 6 to 8
uses unless patent aluminium forms are being Total manhours for 6 columns = 24
used.
24.0 mh _ d Gang size 2
Continuity of work for the concrete gang can - 3 man ays. If"
never in practice be economically achieved - the 8.0 hours/day stee rxers
key factor is to obtain balance between the steel-
fixers and carpenters in relation to the amount of 3 mh _ 1 1gangdays
formwork being used. 2 men in gang - duration
The ratio of carpenters to steelfixers is normally
in the order of 3-4 to 1 but this is dependent upon FABRICATE AND FIX REINFORCEMENT- 1 1DAYS
the complexity of construction and the amount of
prefabrication. Reinforcement to column and floor FORMWORK - Time allocated is for fixing and
beams can be readily fabricated adjacent to the striking column formwork. Allow
works and simply lifted into position by crane. 66% fixing- 33% striking
Larger floor pours can be considered where shutters.
concrete pumping is to be used. The introduction
of concrete pumping enables the crane to be more FORMWORK TO COLUMNS
readily available for formwork and reinforcement Time allocation for 6 columns
handling. - Fix shutters 66% X 160 mh = 106 mh
The form of construction being used directly Strip shutters 33% x 160 mh = 54 mh
affects the choice of formwork system and is of Total manhours for fixing 6 columns
particular importance in flat slab construction whe-
re table forms may be introduced.
106 mh
- - - x 6 = 32 mh
20 Nr
32.0 mh
SHORT-TERM PROGRAMME FOR - - - - = 4 mandays. Gang size 4 carpenters
REINFORCED CONCRETE FRAME 8 hours/day
4 md gangday's
From the analysis of the manhour allocation for 4 men in gang duration
one floor of the building, it is first necessary to
abstract data relating to the sequence of opera- FIX FORMWORK - 1 DAy I
tions. The manhour allocation must be broken
down into the exact number of shutters to be CONCRETE TO COLUMNS
used - for example, the column sequence involv- Concrete supplied ready mixed. Placing of con-
es using six shutters therefore the manhour alloca- crete by crane and skips.
tion must be related to this pouring sequence. Number of men in concrete gang = 4 labourers.
49
Bar-chart Programme Case Study 2.6
Reinforced Concrete Frame Sequence of Construction
COLUMN SE.O.UENC£ US IlliG
SHUTTER-S
C:YCI-' I CYc&.£ 2.
~
ra ~ o o (] 0 tl D Cl
~
m ~ o o D 0 0 [] D
~
fa ~ [] tJ [] 0 D D 0
G COL.UMN CYCLE.
LA&oull.
•o "L
0 P£R.ATIO"'
I I 2. I 3 I • I s '" 1 7 1s 1 ~ 1
Fl~ .STf:EL
ll.£ lfol FOR.CE.MEI>IT .2. •/F ·- ~ STftLF/~R. CO"'TINUQ ....
FIX FOitii!WOR.II: 2-c:.ARP. w.zzzz~ .¥Z2ZZZ~ c:::J
CAif.'EioiTOs
b.: ~: ~
I "':'
.zl+l7l'fiY. '1lii-l~l7l.tf I
Figure 2.31 Bar-chart for column sequence
50
Bar-chart Programme Case Study 2.6
Reinforced Concrete Frame Sequence of Construction
51
Bar-chart Programme Case Study 2.6
Reinforced Concrete Frame Sequence of Construction
52
Sl-loR.T T£/l..M fteOGil..AMM£ Co\IER.JAJG R.Eii'Jt=OI!..Ct:.I:J COWC/l.GTE'
~Ill. ST .2.o .bAY~ OF P/i!oJ EC.T ~A!AAAE - FLOOIC SE.G.UENCE
(a) Discuss the use of construction programmes as The data given in the table shows the sequence of
a basis of project control. work for the construction of twelve ground-floor
concrete columns. Assume that an adequate
(b) Draw up a bar-chart programme for the fol- supply of mechanical plant is available for the
lowing work: work.
Programme the work to demonstrate clearly the
Foundation work to a new office block. efficient use of formwork based on the following
Excavate oversite - commence start of week resources:
1 and complete end of
week 7. (a) two sets of column formwork are available
Concrete to- commence start of week 3 and (b) four sets of column formwork are available
foundations complete end of week 9.
lndiccte the gang size of carpenters required in
Brickwork to damp-proof course - com- each of the above cases.
mence start of week Note- scaffolding is not to be included in the
4 complete end of programme.
week 11.
Hardcore and backfill - commence start of
week 5 and com- Operation Duration for ONE
plete end of week 300 x 300 x 3000 mm
12. high column
Site concrete - commence start of week 7 1. Excavate base including 0.5 man/machine days
and complete end of week blinding
14. 2. Reinforcement to base 0.5 mandays
3. Concrete to base 0.5 man/machine days
4. Reinforcement to column 1.0 manday
(c) At the beginning of week 10 the progress was 5. Formwork to column 1.5 mandays
as follows: 6. Concrete to column 0.5 man/machine days
7. Strike formwork, clean 0.5 mandays
Excavation oversite commenced at the end of and repair
week 1 and was completed by week 5. Con-
crete to foundations commenced beginning of
week 2 and is 75% complete. Brickwork to (CIOB. Direct Membership Examination - Build-
damp-proof course commenced at the ing Production and Management Paper- 1985)
beginning of week 3 and is 50% complete.
Hardcore and backfill commenced halfway
through week 5 and is 15% complete.
(i) Plot the progress against the programme EXERCISE 2.3 - METHOD STATEMENT
produced in part (b).
(ii) Prepare an outline report for the next Figure 2.33 shows the plan of the site of a four-
weekly production site meeting with pro- storey reinforced concrete framed building to be
posals for achieving the original pro- built adjacent to an existing single-storey shop built
gramme. in 1834. The shop is 36 m long with a 255 m brick
(CIOB. Direct Membership Examina- wall built directly off the clay subsoil. The shop
tion - Building Production and Management wall adjoining the proposed building is to be
Paper- 1986) underpinned by means of a 475 m thick reinforced
54
Bar-chart Programme Exercises
E.XISTio.IG
SI.,GI.l
STOIU'/
SHoP
'2 f 5 &A.ICIC
Willi.&.
f>r.OI'OSlD
E'XISTING SECTION I -1
II OOWirLS
I
Ll""lt OF' NlW ---j
I!.ASlM&NT A.E.TAINU4G I
WALL
I MASS CONCillT&
WALL
-1~15
I
&AS.LHlNT SLA& "'50 TloliCI( I 0
--- _}_j
---------------------If
£ltiSTI""Clii SI .. CIL(
STOAE'/ SHOP
...
50"" J ..
.. +s·SOO
0
0
-(
fll
~
E 1
b._
' ...
f
2 ft) SITII Foil. .... STOUY PRO PO S£0 SEc·not.J
~ FRAMU> SUII.tUo.IG
~ WITH 8ASKM&II4T
Sla.VICl !tOAD
S/Tii. Pl-At./
55
Bar-chart Programme Exercises
56
Bar-chart Programme Exercises
it is executed. The gross profit margin is 5% of the EXERCISE 2.6- CASH FLOW
certified value. APPLICAliONS
A I '2.0
B 2 cao
c 4- 240
D 4 ao
E 3 1'2.0
F 4- 240
G 2.0
f100
57
Chapter 3
Case Studies relating to Line of Balance
Techniques (Elemental Trend Analysis)
3.1 - Line of Balance Principles 3.4 - Housing Project: Finishes Sequence
Principles and format of presentation m Development of line of balance for the
relation to a foundations project finishing sequence for 10 houses
Information available from line of balance
charts
3.5 - Housing Project
3.2 - Refurbishment Project Preparation of valuation forecast based on
Assessment of labour requirements based line of balance chart for housing project
on line of balance chart Progress recording on the line of balance
chart
3.3 - Reinforced Concrete Deck Platform
Development of line of balance chart and
labour requirements based on differing Chapter exercises based on line of balance tech-
manning levels niques Exercises 1 to 3
58
Line of Balance Planning Techniques Case Study 3.1
Line of Balance Principles Foundations Project
The line of balance planning technique was deve- for different rates of working from one operation to
loped by the National Building Agency in 1965. the other. The 'ideal' line of balance relationship is
The technique was developed for repetitive hous- shown in Figure 3.3 where each balance line lies
ing projects but the principles may be readily parallel. The objective of the planning technique is
applied to any repetitive construction sequence. to keep the balance lines parallel for each related
Application areas include sequences involving the activity and maintain minimum buffer periods for
erection of reinforced concrete columns and each unit or sequence. This can be achieved by
beams, piling and related foundation operations. balancing the gang sizes on each operation in
The technique may equally be applied to refurbish- order to maintain the planned rate of construction.
ment works and finishing operations on housing Figure 3.4 illustrates a logic diagram where
projects. activities start at the same time. Activity B and C
The format for presenting line of balance sche- may commence at the same time but they must
dules will first be illustrated together with the both be completed prior to activity D commenc-
sequence of preparing a schedule from first ing. Figure 3.5 and Figure 3.6 indicate alternative
principles. line of balance schedules based on different rates
of construction for activities Band C. Figure 3.5 is
based on B and C commencing together, with
activity C proceeding at a slower rate than B.
Figure 3.6 is based on activity Band C finishing at
FORMAT OF PRESENTATION the same time but with activity B proceeding at a
slower rate than C.
In order to reduce the overall project period,
B and C should ideally proceed at the same
Figure 3.1 illustrates a logic diagram for three rate - this is rarely achieved in practice because
operations A, Band C which proceed in sequence. of varying manhour allocations and difficulties
Figure 3.2 indicates the line of balance schedule encountered in balancing the labour gangs.
59
LOGIC DIAGRAM
A~ I
TO
B
OIFP:.ILit:NT ~AT&S OF
WoiLIC.ING. G
~VE'~U.
NIJM&E'R.
OF
Ut.IITS
I~ DUIUTioN
ACTIVITY A PltOCI'U>I..,Cii
AT A FA.STE'It. R.ATII
THA .... ACTIVITY B
ACTIVITY C. P~OC.I!EDI..,G
AT A SLOWER. R.ATI!
THAt.l ACTIVITY 8
0 U~ATION __.
Mlo.IIMU M &UFFI'It.
Figure 3.2 Line of balance diagram - non-parallel working
A 8 c
OVI'~LL
NUM&ER.
DUR.ATION
OF
UNITS
ACTIVITIES A, 8 A..,D C
ALL PlltOCET'DI"'G AT
THE' .SAMI'. R.ATE OF
C.O .... STILUCTI0"-1
DURATION ~
60
LOGIC DIAGRAM
A c
NUMBER.
OF
U ... ITS
ACTI"ITY S AND C
STAR.T ToGETHER.,
C. Pll.OGEEbS AT A
S LOWE'R. R.ATI! THA..a &
DU~TIOt-1 >
Figure 3.5 Line of balance diagram - operations B and C commencing together
A 13.C D
NUI'1&£"R.
OF
U fiiiT.S
Ac.TtVITY a A..ao c.
I=I...,ISH TOGoi'THE~,
& Pl'lOC.E'E:DS AT A
SLOWER. RATE THA~ C
DU~A'TION >
Figure 3.6 Line of balance diagram - operations B and C finishing together
61
Line of Balance Planning Techniques Case Study 3.1
Line of Balance Principles Foundations Project
62
Line of Balance Planning Techniques Case Study 3.1
Line of Balance Principles Foundations Project
A - FOU...,DATION SEGlUE...,CE
c- C 0 LUM..., SEG.U£NCE
FA&lliCAT£
FAI!.Itii:.AT£ FW!c::
63
Line of Balance Planning Techniques Case Study 3.1
Line of Balance Principles Foundations Project
Manhours required for 2 units = 2 X 120 hours For the first house unit - site strip operations
= 240 manhours Commencement of first unit = Day 0
Planned number of men to 240 Completion of first unit = Day 0 + Duration
achieve 2 units/week 0 + 2 days
40 hours/week
=Day 2
= 6.0
Optimum number of men in (Nr of unit - 1) X duration
Start of last unit = - - - - - - - - - - -
gang = 3 nr Nr of gangs
Number of gangs to be used = 2 nr (10 - 1) X 2 18
-----=-=18
actual nr of men 21 21
Actual rate of construction = - - - - - - -
planned nr of men Start of last unit = Day 18
x reqd rate of construction Finish of last unit = Day 18 + Duration
Day 18 +2
Actual nr of men to be used on foundations =Day 20
Two gangs consisting of 3 men = 6 men
Planned nr of men to achieve forecast rate of Summary: Site strip
construction of 2 units/week = 6 men House unit 1 - Starts Day 0, Finishes Day 2
House unit 10- Starts Day 18, Finishes Day 20
6.0
Actual construction rate = - x 2.0 = 2.0 The balance line for the site strip has been
6.0 plotted as shown in Figure 3.8. The dotted line
Rate of construction requireJ = 2.0 hours/week indicates the movement of the gang from unit to
unit.
Using the labour resources as shown, the rate of FOUNDATIONS- OPERATION 2
construction on foundations will be at the required
rate. Commencement of first unit. As the rate of cons-
The duration of the foundations work for each truction for the foundations is slower than the site
unit will be: strip operation, the balance line for the founda-
tions construction will be at a lower gradient. The
120 manhours/unit 120 foundations works can therefore proceed relative
------- = _ = 5 days
3 men X 8 hours 24 to the completion of the site strip works to the first
house unit.
Commencement of first unit = Unit 1
The rate of construction for the site strip (2.66
units/week) is faster than the rate of construction Completion of site strip to Unit 1
for the foundations (2.0 units/week). The balance = Day 2 + 2 day buffer
line for the site strip will therefore be at a greater =Day 4
slope than that of the foundations.
Completion of foundations to Unit 1
= Day 4 + 5 day duration
=Day 9
5. Assessment of start and finish times for first and
last unit (Nr of units - 1) x duration
Start of last unit = - - - - - - - - - - -
Nr of gangs
In order to develop the balance lines for each
operation, the start and finish time of the first and (10 - 1) X 5 9 X 5
last unit must be calculated. Assume that a mini- Day4 + ---
mum buffer time of 2 days is to be allowed
2 2
between the site strip and foundation works. Day 4 + Day 22~ = Day 26~
64
0
.:t
<J)
,...
~ c
0 ,....... .Q
~ -:t
~
a
'2
.
0
<
Q
\J
c
:::l
..2
ai
6 o-
...
,.
\J
~ \....., c
;;_ 1&.
IIi
II
0 ~
~ 0.
·s
"'
~
..C
2
<J)
-~
0
...Ill
..<
<J)
2 Ill
0 , ~ i
0 "t :J ...£:!
,"'
:)
j:
- rJ. :::l
15 '( \J
.."• ""'
0 J QJ
'( l ..c
::, u
"
~ <J)
~
0 '( QJ
"
l'(ll u
15 0 c
rl ~
~
..0
.....0
QJ
c
...J
~
M
...::I
~
...,-a. =t)
u:::
=~
If\ II)
-~
, '-~
0
Ill
"'( !::
:a \II
-'t
l!llll
-f'l
-o
Ill ~ lfl ti
65
Line of Balance Planning Techniques Case Study 3.1
Line of Balance Principles Foundations Project
= 6.7 days
say 7 days
INFORMATION OBTAINABLE FROM LINE
OF BALANCE CHARTS
As the rate of construction for the external brick-
work is faster than the foundations operation, the
balance line will be at a steeper gradient. The 1. The line of balance chart indicates the rates of
external brickwork balance line must therefore working from one operation to the other. The
relate to the completion of the last house unit on objective should be to keep all balance lines
foundations in order to prevent operations over- parallel and as close as possible to the required
lapping. rate of construction. Out of balance manning
levels can be readily observed by comparing
Commencement of last house unit- unit 10 the slopes of balance lines.
66
r- r-
:r s·
~ ~
S, S,
Ql
= = Ql
10 ~0 3o 40 so jj;' jj;'
:I :I
1"'1 1"'1
~ ~
4D~ .,... .,
10-1-- -I
L.J ~ - - - l:u.·~ I,.,:_ =:3·,... jj;'
- - -- - E'IIT. B.Wic:
s·
1"'1
:I
:I
-a·
;;'
s· IJQ
<I>
-!
~-1 I / / I / / 1/ / I I ~
1"'1
::T
:I
rIll si I I I v / / I / I I ~~·
cd
7
s:
:I
'2
,.
~I !:
'2
J 5
Ul
.
:l
()
• """
~
3.
I ~::/ /J"Ou..DAiJ" /EXT. aw~l/ I30 "T'I
I I I I I I I I 0
d c
:I
0 2.
I
.....
I
!)
I
12.'/-.
I
lct'/:a. DU~ATio"-1 ( oAvs)
1- c.
~
~
Ql
s· :;
:I Ill
Figure 3.9 Line of balance schedule - foundations project .,"' c.c
-9.
~
-
-<
w
1"'1 •
- ....
Line of Balance Planning Techniques Case Study 3.1
Line of Balance Principles Foundations Project
2. The start and finish date for each operation Operation- FOUNDATIONS GANG DATES
relative to each unit may be abstracted and
summarised in schedule format. Scheduled
dates presented in this form aid the planning of Gang Commencement dates
work and the control of sub-contractors.
Labour Gang 1 (4) 19/6/87 Unit 1
Labour Gang 2 (9) 26/6/87 Unit 2
House Commencement date Completion date
unit
Gang Completion dates
1 (0) 15/6/87 (1) 16/6/87
2 (2) 17/6/87 (3) 18/6/87 Labour Gang 1 (29) 24/7/87 Unit 9
3 (4) 19/6/87 (5) 22/6/87 Labour Gang 2 (31j) 27/7/87 Unit 10
4 (6) 23/6/87 (7) 24/6/87
5 (8) 25/6/87 (9) 26/6/87
4. Handover dates relating to the completion of
a particular stage of work or unit completion
Note. Dates relate to the beginning or end of the may be abstracted and presented in schedule
calendar date. format.
This procedure may prove useful where sub-
contractors require occupation dates for specific
3. The start and finish date relating to each trade house units.
gang may be abstracted from the balance line. 5. A cut off line may be drawn vertically at the
From this data a labour histogram may be forecast valuation dates for the purpose of
produced. The dates for the commencement of assessing the number of units completed for
each gang may be alternatively shown in sche- each operation. This data may then be deve-
dule format. loped to form a monetary valuation forecast.
68
Line of Balance Planning Techniques Case Study 3.2
Refurbishment Project Labour Requirements
Figure 3.10 illustrates a line of balance chart for A histogram depicting the various trade gangs is
three operations relating to a refurbishment con- presented in Figure 3.12 showing full continuity of
tract. The balance lines are based on two gangs of work for each trade engaged on the project.
labourers engaged on foundations, one gang of An assessment of the labour resources for the
carpenters working on the ground floor and two foundations operation involving the utilisation of 4
gangs of bricklayers on external walls. gangs is shown in Figure 3.13. The histogram is
The labour line relating to the start and finish of produced from the balance lines by considering
each trade gang has been transferred from the line the start and finish date of each gang engaged on
of balance diagram onto the bar-chart shown in the operation.
Figure 3. 11.
Figure 3.10 Labour resources for refurbishment project
LABOU/t. R.£SOIJRCE A SSESSMf: H T
GROUN b
FOU~DA"TIOIIIS FLOOR. &RICk:WORI<.
8
...,
5
II.
0 4
I LA&OUR
I GA.,G I I
I I I
12 ";I 2 2 12 2 2 2 2 21 LABOUR I I
I I I I I I I I I I I GAII6 2 I I
I I I
I
~~~£~ \ ~1"2? I '2.12121\21212121 \2121212 121 '2/.121
I I
&RICIC.LA'I'f"R. 12 1 2 2 2 2 2 2. 2.
I I I I I I I I
2-z.l
I II 1
GAtiG I
I
<iCir.LAYifll
GAIIG "2.
\2·2·1·% ,2 1'2. ,z ,z ,z ,21,
LA SOUR. BAR-CHART
69
Line of Balance Planning Techniques Case Study 3.2
Refurbishment Project Labour Requirements
8
I I..LU.STitATIOtol TO R..ESOUR.CE
~
4 GANGS ow FO U 1>1 OA TIONS
a
......
II)
l 7 G AI>/ G I- UNIT I. S. 9
'::J
G
GA"'G 2- UNIT :z.. G. to
....
0 GAUG .3 - UNIT 3.7
5
Ql GAI>IG .... - U~>~ rr 4. 8
:z 4-
:J
t .
..
7 GA""G 4 OAV t.IUIII &£ R. AT THE
5
GA""G 3
• Fo C. EACI-I
Tit A ""SFE.RICEI>
GAIIIG
FR.OM Llt.IE
0~ BAI..AHC~ C.HA#t.T TO
LA /10UL R.&SOUICCE
GA""G 2.
OIA G lt.A lVI
2.
GA""G
• 2.
bUR..ATIOI<J (OAVS)
Figure 3.13 Labour assessment based on four gangs
70
Line of Balance Planning Techniques Case Study 3.3
Access Deck Project Manning levels
71
Line of Balance Planning Techniques Case Study 3.3
Access Deck Project Manning Levels
ACCESS OECI<. Pll.O.JECT
0 0 0 0 0 0
.-----~~---- -~~-----·11___ - -i .------, ~--~-
1 1I 1I 1I 1I I I I
I 8AV 1 I I 2. I I 3 I I 4 1 I 5 I I r,;,l PLA 1\J
1 I I I 1 I I 1 1 I I I
L ____ !I L
I
____ !I 1_ _ _ _ _ J 1 1 I
t_ ____ J L ___ _.
1 I I I
~-!
I
0 0 0 0 0 0
L 0 G I C 0 I A G R.A r-1
'2.3
INSITU Pf£CA.ST
&EA~ DECK
CoMPL£Tio"'
DAY 2.q
>-
<
cQ
72
Line of Balance Planning Techniques Case Study 3.3
Access Deck Project Manning Levels
lo 12. '23>
PILIIoJ~ ~ SEAMS~
I I
1 PILI ... G -a LA& I I
( I )! I
C::Aa.f\EIITE~~
I< PIL( CAP.Sj BEAMS 4
I .
I 0EC."'2. L.Ae..
I< >I
7 - . .
6 - PIL£ CAPs/
8EAI"IS DEC.K
-
PILl ... CO PILE CA P.S I &EAMS
- DEC."
73
Line of Balance Planning Techniques Case Study 3.3
Access Deck Project Manning Levels
OPERATION - BEAMS
The revised line of balance chart indicates an
Start of Bay 1 = Day 2 + 1 day buffer overall reduction in the duration of 10 days (from
=Day 3 Day 29 to Day 19).
74
Line of Balance Planning Techniques Case Study 3.3
Access Deck Project Manning Levels
I
5
~y 2,q
I
IN TIM£
Jo DAYS
I I
I I
4
G I 8 IO
I
1:1.1 I I& 18 2o 2:2.
DAY
24 u oz.a 3o
NUW18Eitl..
%3 7 ·~ ....
II
,.... C.APS AND
~
BEAMS E
~ GA'IG 2. c
6-
..._.._
IC
7
LAI!>OUR. R..ES OUR.CES
II! ~ CAP~ AWD
:J BEAMS
H/STOGR.A~
0 .s GAWG I
l!l
<
.,J
4 -
3
2 PILING-
I DECK
75
Line of Balance Planning Techniques Case Study 3.4
Housing Project Finishing Sequence
A line of balance chart is to be prepared for the 1. Total manhours to construct 2 houses.
finishing operations on 10 houses from completion 2. Planned number of men required to complete
of external brickwork to the plastering stage. The the required houses per week.
logic diagram is shown in figure 3.19. 3. Establish gang size and number of gangs to be
The rate of construction is to be based on two used.
houses per week and the manhours allocated to 4. Assess the rate of building and match with the
each operation are indicated. joinery 1st fix may required rate of construction.
commence immediately the roof tiling is com- 5. Calculate duration for one house.
pleted using a minimum buffer of 2 days. 6. Calculate earliest start and finish date for the
The electrical work and plumbing may be operation (Unit 1).
planned to commence after the joinery work has 7. Calculate the start and finish date for the last
started, but must be complete prior to plastering. house (Unit house 10).
8. Plot the balance lines on the chart.
Operation Manhours!house Nr of men 9. Establish the position of the buffer and continue
in gang with next operation.
Roof carpentry 140 3 joiners The calculation of the earliest start and finish
Roof tiling 60 2 tilers dates for the first and last house is presented in
1st fix joiner 180 3 joiners tabular form in Figure 3.20.
1st fix electrician 70 2 electricians The line of balance chart relating to the first five
1st fix plumber 110 2 plumbers operations is illustrated in Figure 3.21. The balance
Plastering 110 3 plasterers line for the plastering operation is to be based on
the completion date of the first fix plumber and
Rate of building- 2 per week electrician to the first house unit. The presentation
of the calculated data in tabular form simplifies the
The procedure to be adopted in analysing the calculation procedures. The balance line should
problem is as follows. For each operation the be developed for each operation as the calcula-
following data is to be calculated.: tions are undertaken.
fS"f:l~ :TOIHtR..
fST FIX
EL£C71LICIAN
76
Line of Balance Planning Techniques Case Study 3.4
Housing Project Finishing Sequence
77
Line of Balance Planning Techniques Case Study 3.4
Housing Project Finishing Sequence
L 0 GIC
/Sr FIX
ELECT/l.IC IAN
~I ~II I
IO
2.
I ' ' I I I
ol ~' g! it! ~I
bLJ R.ATION ( OAVS)
78
Line of Balance Planning Techniques Case Study 3.5
Housing Project Valuation Assessment
79
::1: ~
0 ::I
c ~
"'
:r
CJCI
s.
22. =
""C
.., ll.l
QT
..2. ::I
VALUATio"-1 DATES ~ I")
il ~
lq-1 v I I 'I I I I I I I I I VAL 11/'L I - DAY 30 ""C
ill
VAL. NIL 2 - DAY 60 ::I
::I
VAL. Nl. 3 - DAY 85 :r
I CJCI
lcD-1 I I I I I I I I y I I I VAL. NA. 4 - bAY 115
-l
~
I")
:::r
::I
13-, I II I ~ L I !t ,~·
If)
I f I:> I
1-
-
'Z 10
:J
t--
~
O:l -J 7 _,
a I ~ I ... ~
' ' .. ' ' . ' -- ' ' . ' ' LIN£ OF 13ALANC£
CHAR.T 2.2. FLATS
VALUATlo~
lilA. I VJ I
VALUATio..,__r-j
NA. 2. ~ VALUA~
VALUATIOt.l - I
N«.3 ~ II/A.4 ~
LOGIC DIAGRAM ~
cll.l
fouNOATIO"'S SuPIItSTl.UC:T ltOOF II\IT. PAR.TlTIOII £UCTR.ICAL PLASTP.Eft
n
ll.l
() >() >0 >0 >() £) >() 6·::I
> "'~
~ Ill
Figure 3.22 Line of balance schedule - valuation stages ~
"' c -
"'
3 -<c.
~ w
::I •
- t.n
:I: r-
0 :r
c ~
Ill
V ALUATI0"-1 FOR.£ CAST BASED ON Ll 1-.1£ Of BALANCE :r 0
lXI
Cl:l
Q,l
::I
:r
lXI
f:OUr.J OATIOIJS
-l
~
t"'
:r
::I
I S U P[R.STRUCTUieE 15"
c
1\.. VAL. I ~
I Ill
R.ooF
"VAL. 2
VALUATION 4 INT. PARTITIOIJ
O:l
ELEC'TR.I C1AIJ
VAL. 3
PLASTER Eli:.
VAL.4
VAL._,R Fb"T.S S IJPE R.STRUaURE ROOF INT. PTI'IS ELECTiliCIAfol PUS. TOTALVAWE f>AV NL
--- 13- fsoo
-- 30 <
Q,l
4 .... 000 60 c
2
3
22.-1800
12.- tsoo
·~-t 12.00 4Co-f coo
r400 c;7GOO ss
Q,l
15" ("")
:2.2-fl:r.oo 22-fGoo •o-feoo 4-f6oo Q,l
::I
4 u-( soo 22-f120o 22-/Goo 22-rsoo :zz-.('coo r'5..fisoo .fto7,5oo 115
-
;:;...
Ill
~
Ill ..,.,
Ill
~
Ill
cQ.
Figure 3.23 Valuation forecast based on line of balance schedule Ill
3 -<
~
-w
::I
Case Study 2.2
Project Cash Flow
1.n
-
Line of Balance Planning Techniques Case Study 3.5
Housing Project Valuation Assessment
·~
110
100
CUMULATIVE :.\
VAUJE FOilECAST \,\.
So
7o
_______ ..,.
,.......
0
0
0
~
5o
\J
,4400
10
DUe.ATION ( l>AVS)
Figure 3.24 Valuation time curve - housing sequence
82
Line of Balance Planning Techniques Case Study 3.5
Housing Project Valuation Assessment
2.2
I
1'1 -
I
I
., I
'"
I
1- I
7
:I
Ill
Ill
::J
·~
0
::t
IO
u.
0
Qr!
"'
10
1
~
'Z:
I+
83
Line of Balance Planning Techniques Exercises
EXERCISE 3.1 - LINE OF BALANCE: handover rate is 2 houses per week and a 40
HOUSING PROJECT hour week is to be worked.
(b) Prepare a Line of Balance programme for the (CIOB. Direct Membership Examination - Build-
construction of 10 houses. The proposed ing Production and Management Paper - 1986)
I
PLUM & I#>#G
EL~CTILICS
PLIUTIULIIIG
, S Ll &STLUCTUII..E loo 4
2 S U Pi: lt.STil.I.ICTUIII./£ 000 8
3 t= IIII.:ST F/'tCING 2.00 6
If Pt...I.IN16ti#G I ElSCTitiC.S tOO 3
s PL.I'!:ST&Je.tNG So I
6 F/~ING .2.00 2.
t= '"'"' L.
84
Line of Balance Planning Techniques Exercises
85
....
:r
tD
s.
=
s::w
D7'"
:I
I")
tD
OVERALL PR..oJ I<CT "'CC
D7'"
PER.IO D 1.50 DAV.S :I
:I
~ :r
CJQ
12.
~
:::r
II . . :I
- ... . - ... . . A· PuJH&ING JST FJ)(- 6 I)AVS .s·
c
tD
10 -1 I II I l l /IIIII I I B- ELECTRICAL I'" FIX- 4 DAYS "'
9 C.- CAR.Pii toiT"R. I'" FIX - 3 DAYS
b- PLASTU.It.JG- .5 OAVS
8
.,.. £- PLUto! I!> IN 6 2•o FlY.· 4 I)Avs
O::l Ill 7
0\ I :1 f- li:LfC:TRICAL 2"• FIX- 2. DAYS
0
:J:
6 G· CAR.PEtHn. 2"• FJ)( - t; DAYS
...0
at 5
:&
X
::J 4
2
.,
t-
I
I
........
Cl:
I
0/. 0/.
0
Ill
0
...
0/.
0
o.l
0 Q
""0
Ill --ct-- -~mr-
--- - --
.......
0 0 'Z
0 ..... 0
...0 <
0
9
I I
...J
u.. u.. L&. ..... ':1
0 0..
II! 1 1 Jl ~
0
1.\l
~
10 ~ 10 N "" 171
I
I ;;
<Jl
<:;:::
I
I
'Z
:5
-;a
""§
Q)
a.. ""0
·;:;;
I
=
~
"'-<_,
t- eli
-9 --=~]]]~
0 c:
u. 0 .Q
...0 ....
-J
uQ)
I
I <Jl
~
<
Q. I
I I
""0
c:
~
c:
I I
~
0::
Q'l
CO'!
M
~
I ...
~
<t ~
1)1)
'Z
0
., i.i:
....
1.,)
t-
...
~
u.
~
Vl v--- ~ --v
lf 0
~
tl
~
a.
87
Line of Balance Planning Techniques Exercises
/
/
88
Chapter 4
Case Studies relating to Network
Techniques
4.1 - Network Analysis Principles 4.7- Concrete Tank and Pumphouse Building
Network principles and format of presenta- Development of cost envelopes based on a
tion network sequence
Network/bar-chart relationships Presentation of cost envelope based on
earliest and latest start times
4.2 - Bases and Column Sequence
Network analysis and the relationship to
4.8 - Foundations Project
time scaled diagrams
Labour resource allocation for the construc-
tion of the foundations to six blocks of flats
4.3 - Internal Finishes to a House
Labour resourced on bar-chart in order to
Analysis of network sequence and presen-
assess minimum number of site visits for
tation of analysis in bar-chart form and time
labour
scaled format
89
Network Analysis Case Study 4.1
Principles Presentation and Relationships
The network principles outlined in the exercises the sequence by the end of Day 12. Bar-charts
are based on the format shown in Figure 4.1 A. It is are also displayed for the networks illustrated in
not intended to explain the principles of preparing Figures 4.6B and 4.6C.
network logic diagrams, as it is expected that the The bar-chart format is more readily acceptable
reader will already be familiar with the principles at site management level as it indicates clearly the
involved. critical activities in order to complete the sequence
in the shortest time. Management by exception
In the exercises and case studies the float calcu-
thus becomes possible.
lations are all based on the total float assessment. A
The use of computers to undertake the numerical
series of analysed network diagrams illustrating a
analysis of the network is gaining favour within the
variety of relationships is shown in Figures 4.1,
larger organisations. The computer is being used as
4.2, 4.3 and 4.4. It is suggested that the reader
a head office tool to produce bar-chart displays
follows through the analysis process on these
based on the network; these are then utilised on
examples before continuing with the case study
site as the master contract programme. The com-
examples. Figure 4.5 illustrates the float relation-
puter may also produce labour resource forecasts
ships together with the procedure for preparing
based on the earliest or latest start together with
and analysing a network.
resource levelling procedures. The bar-chart may
The relationships between activities may be be progress recorded using colour codings or be
more readily understood by presenting the net- re-run through the computer to produce updated
work in the form of a bar-chart. This enables the reports.
float relationship to be more clearly expressed. Management must be aware of the problem of
Critical activities may be linked on the bar-chart by producing too many computer updates which
an arrow or dotted line enabling the chart to be completely confuse the site manager. Paper chase
clearly interpreted. The bar-chart or calendar for- management systems usually result in chaos.
mat may be readily prepared by abstracting data A number of case studies are presented in order
from the network relative to the event number, to expand the relationships outlined. Each case
earliest start, duration and float. Figure 4.6A shows study is intended to extend the application areas in
the relationship for activities A, B and C which run order to demonstrate a wide range of ideas of
end on in the form of finish to start relationships. practical interest to planning staff and site manage-
All the activities are critical in order to complete ment personnel.
90
Network Analysis Case Study 4.1
Principles Presentation and Relationships
Figure 4.1A
Figure 4.18
Acccu~
4
Figure 4.1C
91
Network Analysis Case Study 4.1
Principles Presentation and Relationships
ACT. 0 ACT. E
II+
C>AV 35
FL.oAT
92
R.E:LA TION SHIPS
xk)
I.V£#JT N/1.
Figure 4.3A
93
Network Analysis Case Study 4.1
Principles Presentation and Relationships
LAl:>D£R.. 0/AGR..AM
94
:::'
-· z~
PR.OCEOUR.£ INH EN PR.E PAR.ING A NETWOR.I<. DIAGRAM !:!. -
::I :;:
'tl
- 0...
~ ~
frorv~ Hu. drowo;,..!JS pr•torfL Q /iS'I: <ll >
o{ e. S' 1: alol,·~ I. tke. lol:esl: fi"".~h t:.i-e. for ::I
Ill
o. c.l:.v; t:.es IT. e. S'e,ut."c:e o{ c.o... .rl:r<~c:t:oo"". e. oc.k ~d; ivi~. At: node. tif'o~errc.cl:oons
-<
'" <ll
;;;·
1. Assess the. duro 1: u:s ... for e.oc:k Doc: I: 1\J ;t:J• t-he. lowc.cl: ""'..,. ber &n C.Cllr r I it d bo cJc •
3. Drofl: OCJ~ N..e. n el:worlc. b::J c.arefc.l C.h&c.k H-e. "u_e.,.•c. 0" ,.,,,.,1'.
~- C ar•fc.dl)
c:.o "'ro'J&r-.1: oo... of f1..e. c:.o"'rtruc.t to;,. re' ue.l\c&. jO. C. o.l c: u I A+' f-h-. Col:ol floo.~ for ALil~J..
1-2 ACT. A 0 4- 0
2-3 ACT,8 4 3 0
Figure 4.6A
0
3-1,< ACT. C 7 5'
~
E b F ... c; , a q lo II 12 I~ ,.,_ IS
I :l 3
" s
I - Z. ACT. A 0 5 0
2·11 AcT. C s 2 0
1..0
'01 3-S ACT. 0 3 3 t;
~ I Figure 4.68
1- 61 ACT. 6 0 <:. 0
4-S ACT. E t; 4 0
1
5-t; AcT.G 10 5 15
1- 2 ACT. A 0 ... 3
2·5 A CT. I) 4 3 3
,_ 3 ACT. C 0 2. 4-
2-t; ACT. F 2 8 s
Figure 4.6C
Figure 4. 7 illustrates a network diagram for Vertical lines have been introduced to link related
a base and column sequence. Analysis of the operations in order to denote continuity of gangs.
network indicates an overall duration of 20 days. The site strip and excavation to trench 1 and 2 are
The network has been connected to a bar-chart or to be undertaken by the same gang. A similar
calendar format as shown in Figure 4.8. This has relationship is shown between the carpenter gang
been achieved by first considering the operations making and fixing the column shutters to trench 1
on the critical path and presenting them to a time and trench 2. In order to accommodate the rein-
scale. The activity descriptions have been entered forcement fixing, it will necessitate increasing the
over the bar lines. Figure 4.8 illustrates the earliest gang size on the fixing of the column reinforce-
start situation and in no way takes account of ment. Shading has been introduced in Figure 4. 9
continuity of labour gangs. By considering float in order that the gangs may be related to the
times on non-critical operations, the time scaled operations they are undertaking.
presentation has been redrafted in Figure 4. 9.
97
=z
~ ~
"'Dol 0~...
:I ~
Q..>
n :I
0 e!..
--<
3c "' iii'
:I
BAS£ A/tJO COLUM~ SE.Q.UE.NC£
tl'l
.ac
~
l"l
~
~
Oo
Concrete
Silc. $!,., . trc .. ch trcfte.l• I Sl-tul:l:er
:=:::J
::3
1..0
1..0
I :z 3> .,.. I s ,;1'7181:!' I '• II IZ. I 13 I Ill- IS I~ I I., I I~ I I!) I Zo 2. I I 2~ 'Z:J 2.4 I "ZS I
3" 4" s• (,;. 1-,• to• ,•1/z,.l/3" It-+" 17"
I ts•l 1"!>.. zo" 21 ..
1 2.....125"12G.1 21"l ztf' 31•1 I •• 2"" 3 "" I ,. .. I
T,.e,.cl. I 2.
.,.J F• COI'Icrct-4
Coftcrct•
S il:e sl:r•Jt i"«c t:rc"'" I trc .. cl. I C.ol. rc,;,forcc ...., t C.o . sltutter • C.olv-"s
. . . .. I
I
I
I coL ......
~-k~
+I
I
--- -1-
s:k~ ...,. -~
I
-1- -1
I
- -- --
I I
il.l .SOu LCCD ·= I
I
LAaouo~~. I c.o" c. : F•v c.ol, I
_.,£vc .~r. 2
----- •r.2.--~--
·= ---- ... -- - ====I
- - - - - - - - - - - - - - - - - - - - - - .. - - - --- -
Figure 4.9 Time scale bar-chart- labour balanced
Network Analysis Case Study 4.3
Internal Finishes Bar-chartffime Scaled Formats
Figure 4.10 indicates the network diagram for the been entered over the bar lines to clarify the
internal finishes to a house. Earliest start times for sequence of operations. Non-critical activities with
each activity have been entered on the network shared float times have been linked together and
diagram. The calculation of the latest event times again represented as a single line of the bar-chart.
and float may be entered by the reader. This can be seen by considering the services
Figure 4.11 shows the analysed network indicat- activities on the network diagram linking events 1,
ing the critical path as those activities with zero 6, 10 and 15. Each of the activities has a 19 day
float. Part of the network sequence is presented in float. The float, however, is shared by the three
bar-chart format in Figure 4.12; this covers the first activities. In the event of activities 1-6 being
4-5 days of the contract period. In this case the delayed 19 days, then the remaining activities on
critical activities have been grouped together and the loop become critical.
entered as the first operations on the bar-chart. The relationship can be more readily expressed
Figure 4.13 illustrates a time scaled network in bar-chart format in the form of a time scaled
produced from the network diagram. Critical acti- diagram as shown in Figure 4.13. The activity
vities have been devoted as a single line on durations for the three services activities have been
the time scaled diagram by simply linking them linked together end on and the 19 days shared
together end on. Operational descriptions have float time dotted in after the last operation.
100
SEi..lltC£ Tll.EIJCH £x.c.AVItTION 1-RY SEICIItC(;S
3 2.
NTE/t.I<IIIL.
7.
I
~
PLASHit.IGS
2
_ _j
I
r
RAI...,WitTEL GooOS' Ex. TEL1<114L. Pl"f '"'''"' G
2. ~
a
Ex.TEI!.wAL PRit.ITtN(3
Ci
Figure 4.10 Network diagram- internal finishes
SER.VtC/& "Tif.EIVCH Exc.
3 ,,.
I
I
LAS/.ItA/GS I
% ,,.,.
I
__ j
R.Ath/1./ATER. PA IA/T/toiG
.2. ~
a
N
E'KTE.IUIRI. PAtiJTti>IG
6 12.5
IVa1fT
A CTI'IIIT"/ £ .S I Oul.l PL
N ..,..,,
sj ,•I t.sl 2~ 2.5_1 3o I .J.sj ""'oTl
I I
,_ 2. I &1.11< To trr FLooit.l 0 I e I 0 I c 112 2 2 ) z 'I I :
~ - II I PA ._TITIO#<& G. F. I 2~ I 2 Io Ic ~
I
11-12. I P/KTITIOJJS IIT'FL.I 251 2. I 0 I c
0 ~
w
12- It; I PW~~~t61i:Jt I 2.11 G I o Ic I t2 I 2 2
I I 1
I '-·1'11 twr. PUtrrEJt. I 131 4 I o I c I I~
I I --r-f
I I I I
lf-/91 2..,b !=1~ :TOieJd 1371 ~ I o I c I I I )'z 21 2 21
~ I I
1- <D 1/loNESTIGAT£ su"sJ o 1 1 I'"
I I I
6-lol Tit.rEio/CH E'ICC. 7 I 3 I Itt I I I
I I I
c:::JI
1 I
t::::::: 1 I I I I
/o-1~ L.A"/ ~U.Vtc~s I 10 I 2. 11q
I I I I I
~ -14 ISW" ~flo/A L. L.IFT I 'it I 3 I 3 r=p al I I I
I I I I
5-15 I GLA21NG 17 12. I 1¥ I I c:::J 1 I I '
I I I I I I
Figure 4.12 Bar-chart presentation - internal finishes
;-
:; I'Dz
.. i'
TIM~ - SCAL£ SAR:CHA/1.7 1'-IT&R.N.AL. FINISH£ S
-~ .Q
"TT :II('"
:r >
2. ~ 4 5 jeiO- 7 8 f!»---/o(-11--la I'S 1,_ ISJ IC 17 IW l'f 2.of 2.1 U 'Z.~ Z¥ z.sJ ZG '1.7 OZ .. Z.'t 3ol 3.1 3Z 33 -· =
"' 1:11
i'-<
"' iii'
"'
I I I I I I
,:~7z·•z 71't•; z 1 I~oo; 7 , z ,,.J._:tG'I ~~!'" :~~~v z ,'t~rt'Pt·l ';'-';.L~.,"z z1 7
S••clo•k l 1 I I 1 : :
11
ILT! :
II Itl~i ~ t~L.\~IoiG I ~
I I I ; I I
1 7._jn z ""jnry~"z" z l•jj('~ f!.OAT I i ~ :
0
""" I I I '
I
1 £XCAVAn
II LAY 1I II I'
I z-·r·t"', ·~·"j•""j II'..;·z I j"'if I fLOAT , ... I DI!Vs) i
I I I I I 1:11
I
.=
I")
1 :r
I I I I 1:11
§
I I I I I 3
I'D
V'l l""l
I")
1:11
Figure 4.13 Time scaled bar-chart presentation - internal finishes e!.
"'I'D
a. V'l
"TTc
Q Q..
. -
-<
3 ~
0<1
"' w
-
Network Analysis Case Study 4.4
Drainage Work Ladder Sequence
This example is intended to illustrate the applica- be introduced as illustrated in Figure 4.15. This
tion of ladder diagrams to repetitive operations. In situation more clearly reflects the practical con-
this way the movement of gangs between success- struction sequence on site. The pipelaying opera-
ive acitvities may be shown for such sequences as tions are shown to start 1 day after the commence-
foundations, drainage work and internal finishes. ment of the excavation work.
The technique is used in order to show the move- Lead times enable overlaps to be established
ment of labour from one unit to another. Figure between the start of related activities and lag times
4.14 illustrates a ladder diagram for a drainage relate to the difference in time between their
sequence involving the excavation of trenches, finishes. The logic of the construction sequence
laying pipes and constructing manholes. Each must be maintained as the laying of pipes cannot
operation is to be undertaken by a separate gang commence until the trench has been excavated in
moving from trench to trench as the work pro- part.
ceeds. The relationship shown on the network Figures 4.16 and 4.17 illustrate the bar-charts
illustrates finish to start relationships in all cases, produced from the network analysis. The introduc-
that is, the excavation of trench 1 must be com- tion of lead and lag relationships provides a means
pleted before pipelaying commences. In order to of reducing the overall duration of a construction
introduce the overlapping of activities between sequence by taking maximum advantage of over-
related operations, lead and lag relationships may laps between related activities.
105
c... t'Dz
Dol
Dol
:r Q:e-
(JQ ...
t'D ~
~
Q
>
:I
... ~
~-<
.,;·
"'
OR.. A 11>1 A G £ WOit.IC. 1- A 0 0 £R N . T W 0 lt. 1<. t> I A G .CJII M
.......
0
0\
SSCTIOM
A
r-
Dol
Figure 4.14 Network diagram -ladder diagram for drainage work Cl.. n
Cl.. elt'D
...t'D
la
c
.a
c -<Cl..
t'D
:I ~
n
t'D ~
0
...
z
I'D
AI -
:r ~
AI 0
OQ ...
I'D :II:"
>
L..-A~ 0
:E =
OA.AINA G£ WO/t..IC. 1.. A OOCR.. N £TW 0 ~UC: WITH ... e!.
:11:"'-:i
ANO LAG f.l.£LATIONSHIPS iii'
l'tocl 1 La_,
I
I I
0
'J
1L&acl ' /
I
I v•'!>/
/
/
,., ACTIVITY
No E.S .Dwt FL
1 I .2. I 15 I4 I s I 4i I ..., I t1 I .s I 1o I "I 12 I 1a 1 1¥1 1s J ,,.J 17 JlfiJ/9 I zo I 21 I u I u)
SECTio,., A I I I I
Eve.. trend, 0 '3 0 c. I I I I
La!l pipe.s '3 2. I 6:::z:h I I I
I
5 4 I I I I z z I
8ac.kf•ll I
ZH I
M a .. koles 3 2 3 I I z I I I
I
I I I
I
•
SECTION 6 I I I I I
....
0
OJ E'Vc. f:t•enc" 3 4 0 c. lz 'I z I
'\ I I
La!l pipes ..., 3 0 c TI z 7,
I ., I I
8Qclc..f•11 IO 4 0 c. 7 I
l 7 '\
I I
I I
Ma.-llole.s 14 2. I
I I ~ I
SECTION C. I
I I I
I
I I
f.'ICc. l:nt.-ch , 3 I I I 7 I 1---t
I
I I I I I
La!j , iJ-eS IO 3 I IZZZJ--1
I I I
BQc.lc.f•ll Ill 3 0 c tz I 'I 7
11 7 0
I I I
?I
M"""ol~s c z I7
'? I
I I I I
LAG I I I
£"'t C 114 Hs I- J1. 5 4 0 G I I I .t ..
3-+ tl I
I I I I I
LaAD
) I
~-1 L.AY PI,.U 1- 4 '3 ,, I '---1 I I
' LAG
10 _, UAD ~
MHs 1- .,_ 4- 0 IE I 2 I I I Ia Jll
-
8 c I I
I
I I
0
\.0 I I I I
I I
I LIA6 I
I ,,LACJ I
4 -s ave. MHsS•IO '!) 4- I I# JJ
I
I L•Aol I lt..tc I
~
8 -CJ L.AY PtP£5 5-10 10 3 2. , ,,
I "' I I I
LaAO lI
.·13 MHs S•IO 12. 4 0 c. /I
I t• z z zI I I
H¥ /!l.£11.1 STAT£ /{;. (0 0 c i 2 z z z 2 Zl
I I I I
I I I I
I I I I
I I I I
Figure 4.18 illustrates a network diagram for the the temporary works to the subway tunnel.
initial stages of a railway modernisation project. The network diagram is to be analysed by the
After the site has been set up, work is due to reader and the critical path established.
commence on the demolitions, subway bases and
110
MAt.IU~ACTUit£ P. c. BEAMS
,.
COH.ITA:VCT"
/NT". w.-&.&.S
2.
The project involves the construction of a precast Figure 4.21 indicates a bar-chart produced from
concrete retaining wall and in-situ concrete foun- the network diagram showing the operations relat-
dation. The work is to be undertaken in 15 m ing to the utilisation of plant linked together with a
sections in order to accommodate 20 precast dotted line.
concrete panels. Figure 4.19 indicates a plan of The network sequence incorporates a ladder
four wall sections together with a cross-section diagram relationship between the drainage activi-
showing the foundation and precast wall. A net- ties. The case study clearly indicates the advan-
work diagram for the construction of the founda- tages of using network analysis techniques for
tion and erection of the precast concrete wall is short-term planning procedures. The bar-chart dis-
shown for wall sections A, B and C. An extract play may be updated by colour coding using the
from the bar-chart produced from the network normal bar-chart progressing procedures. In order
is depicted showing continuity of work for the to relate the network diagram to a calendar time
excavation and formwork gang. format, highlight flags may be used to convert
Figure 4.20 indicates a network diagram for the contract day numbers readily to a calendar date.
first 20 days of the project in order to form the basis A number of calendar dates have been included
of the short-term planning. The planned operations on the network diagram shown in Figure 4.20
include four sections of precast retaining wall, based on a contract commencement date of
excavation to the lock mouth and the drainage August 5th.
works up to manhole 2.
112
.,. z
~ ~
1"1
~ =;;:
R.ETA.ii>JII>JG W-"LL PLAN 0
"'
t"'l ~
0
- >.
:I
1"1
:I
~
~
. -< ~.
SUOR.T TER.M PLANNING ~
;:lei
SEG.UENC£ STUDY
-~
"'
e!.
:I
-s·
CICI
~
3 ... .5'£1'1
DAY He 7
I3"'AIIG.
-..
-!::..
bAY No I
S"'"AII&
CoNCR!i:T£ .!.AS£ b
Fl\6/t.ICATE FI.IK. -----
------
FI"K t=Oif.MWOif..Jc:
A cost envelope may be developed from a network 4.24 illustrates the earliest start bar-chart with the
sequence by analysing the rate of income or forecast value allocated to each operation on a
expenditure based on the earliest and latest start proportional time basis. An assessment of the
situation. This may be achieved by producing weekly and cumulative budget has been entered
bar-charts based on the latest or earliest start and along the lower section of the bar-chart display.
entering on the bar lines the forecast value or cost Figure 4.25 shows a bar-chart of the latest start
relative to each operation. The rate of working or situation together with the cumulative value.
release of monies may be assumed directly propor- The cumulative value forecast for the earliest
tional to time or allocated on a disproportionate and latest starts has been presented graphically to
basis. form the cost envelope shown in Figure 4.26. Data
The cost envelope may be used as a basis for relating to the cumulative value forecast at four
providing a valuation forecast based on the earliest weekly intervals, based on the earliest start situa-
start situation or as an aid for site cost control. In tion, is shown in tabular form alongside the cast
this way a labour cost envelope may be developed envelope.
against which the cumulative labour cost may be A cost envelope based on the forecast labour
plotted as work proceeds on site. The cumulative cost of the contractor's own work is shown in
labour expenditure should fall between the enve- Figure 4.27. This has been developed from an
lope lines produced. anlysis of the labour contract for each operation
In order to illustrate the principles of preparing a being undertaken by the contractor and is to form
cost envelope, the network diagram for the tank the basis of the labour cost control procedures.
and pumphouse building as shown in Figure 4.22 The cumulative labour cost to the end of week 4
will be used. Activity durations are shown in weeks has been indicated on the envelope diagram.
and the budget value for each activity is also When comparing the actual labour cost with the
indicated. forecast cost, the progress position must be care-
Analysis of the network is shown in Figure 4.23 fully reviewed. The reason for the cost being less
indicating an overall contract period of 18 weeks than forecast could simply be related to the fact
based on a contract value of £153,000. Figure that the contract is behind programme.
116
~ z
0 I'D
l"l
:I -
:IE
.., 0
I'D ..,
;;' ~
-1 >
~ :I
:I ~
:II:"-
-<
~ ~.
:I
Q.. "'
"J 0
I'D
<
I'D
0
'C
:r
ao
~
0
"'I'TI
-
::I
PIIMPHOUS£ <
I'D
Foui<II:MT•ool 0
2w 3w 'C
I'D
{llooo {12ooo ..,
0
-
3
Figure 4.22 Network diagram - pumphouse and tank project z
I'D
~
:IE ~
0
-...
:II:" "'I'D
V'l
0 c
iti' c..-
ao -<
...
~ ~
3
"
~ z
0 I'D
:I
f')
-~
.. 0
I'D ..
;- ~
-1 >
llol :I
:I llol
~-<
llol l!).
:I Ill
Q..
~
C 0 1-J C tU. Tli: TANK AfoJll PUMPI-40US£ BUI 1-b IN G c
3
"CC
6c
~
.....
Q:)
0
I'D
<
I'D
0
"CC
:r
(JQ
~
0
Ill
I TI
:I
-<
I'D
0
~
.....
0
3
Figure 4.23 Analysed network - pumphouse and tank project z
I'D
~
~ llol
0 Ill
I'D
-.
~
{I)
0 c
Ai. Q..
-
(JQ '<
.j:o,
.
llol
3 :.....
l'"l z
0 I'D
:I
l"l -
:IE
CON CltETE TANK. I'I.NO PUMP HOUSE. &UIL.OING ... 0
I'D ...
it ~
E A R.L.tE ST STAR. T 8A/Z.•CHA R. T. -1 >
E.Jl,.. ACTIVITY E..S. but_ FIIJIIff &IOCIT llol :I
:I llol
l{ooo I .2 3 .... 5 c: 7 8 !) 10 II 12. /3 I¥ . IS I C. 17 tt :11:"-
-<
0
llol
:I ~-
II>
1-~ .SITE STIC.IP I 0 3
~ Q..
11·5 ACCESS' ~oAD I 3 0 12. '+ '+ '+ .,c
:s-~
8 8 8
ltiVEIL biii£ASIOI>I + 3 0 :J.I/o 3
"C
,_ 2 OIJTAII>I GIUOT£S 0 :2. 2
:r
- 0
~ 10 c
2·3 FA61tiCAT£ TAIIIICS 2. :z. :2. 12. ~
3·" TAHK /..II>III>IG 4 I :2. s s
c;.-, 0 ll;, 9 8
E.IUCT TANK.S 7 2.
4 4 4
7-8 WALL f'.OUI>IOATIOol :} 3 0 1'2..
I
11-13 PAINT TANKS 12. I 3 I
~ !> ~ :a
8-llf IL. C. 6Ufl0 lolA L.L 12. '+ 0 12.
'2. '2. 2. 2.
+-'l OUTFAU. MANHOU I '+ 3 8
<.0 '5 '3
,.10 OUTFALL SEioiEil. 5 :z.. 3 & 0
I'D
/O-Il 4 ... <
PUAAI'HOUStl F.HDI>I 7 'l. 3 8 I'D
q 3 1:1.
.... .... ..... 0
I 1·12. P.H. 8LJILD/I>IG 3 "C
3 ~
Network Analysis Case Study 4.7
Concrete Tank and Pumphouse Developing Cost Envelope from Network Diagram
I
I
,~
CO/>JCR.£T£ TA.NIC A NO
I
I PUMPHOUS£ BUIL.OIIv G
12.0
/
I
118 000
I
I
EAR.LIE~T
CUMULATIWi
.STAR.T
I
I
VALue
I
I
/00 i VALUitTION FOIZ.£Cit.ST
I BltS£0 ON
/
~Ail.LIE.$T
STI'f/l.T.S:
JC IJEEI<. Nit
I CUMULitTIV£
VALUE
4 33. ooo
8 sz.ooo
12. 118, ooo
I
/G. /51. ooo
liO I
I
I CUMVLATIV£
.Ill VAl. US
I
40
'"'
B /2 I(D
121
Network Analysis Case Study 4.7
Concrete Tank and Pumphouse Developing Cost Envelope from Network Diagram
PUMPHOUSE f!UII.OING
EAR.LIE:ST
CoST
,_ 32
Ill
0
u 28
AT j.J££1(. 8 PltOG~1414&
I WI!DC. AEHI-.J.D
SCI-4Et>UI.£
c:t.
::J 24-
0
cQ
"':
-J 2.o
LA&olJR. COST
12.
8 12. I~
D U R.A T I o r-J ( W i U:: S)
122
Network Analysis Case Study 4.8
Foundations Project Labour Resource Allocation
The objective of resource allocation is to obtain joiners. Figure 4.29 indicates the analysed network
maximum continuity of work for each labour gang diagram with the critical path following the foun-
engaged on the project. This may be achieved by dations activity for blocks one to six. Figure 4.30
using float times on non-critical activities in order indicates a bar-chart produced from the network
to ensure maximum continuity of work. By careful showing the earliest start situation. The labour
planning, a gang may be moved from critical to requirements for the three trade gangs are shown
non-critical activities in order to maintain continu- on the bar-chart.
ity. This process aids labour smoothing and ensures Full continuity of work can only be achieved for
maximum use of a gang once they are on site. the foundations gang with the brickwork and join-
Consideration should be given to bringing sub- ery trades visiting the site intermittently on six
contract gangs onto the site for a minimum occasions.
number of visits. It may be more convenient to By considering the float times on the non-critical
prepare four roofs for tiling prior to calling the tiling activities for the bricklayers and joiners, the
sub-contractor to site. This will result in better number of visits to site may be reduced. The
continuity of work for the tiling contractor and the network has been presented in the form of a time
trade gangs following the tiling work. It may prove scaled display in Figure 4. 31 and the float times
more beneficial to delay commencing a particular utilised to obtain better continuity of work for the
trade in order to achieve continuity of work once brickwork and ground floor operations.
the sub-contractor is on site. Figure 4.32 illustrates a labour resource diagram
Figure 4.28 illustrates a ladder network for the based on the earliest start situation and the opti-
construction of foundations to six blocks of flats. mum labour requirements are shown in Figure
The sequence involves the utilisation of three trade 4.31.
gangs - for example, labourers, bricklayers and
123
8LOCI< I
FNONS BLOCK 2.
5
F NOIJS
BLOCk: 3
5
..... ~NIIIJS
N
..,. BLOC.#c: 4
5
FoUI>IbATIOI>I s PR.OJECT
'FNONS
8LOC#c: S'
- G FLATS 5
B Lo c.K. 2.
BLock: 3
s
N
l.n
BLo c.Jr:. 4
FOUIIDATIONS Pll.03ECT
BLoc.c S
- G FLATS
BLock:. t:.
E.- 1<1.
~CTI\IITY ESIO-I~Ltr-------~-------i---------f---------+--------+-------~--------L-JL
i.j 1 z 3 4 s I~ 7 8 ~ to I 11 12 13 ,,. 15 I •• 17 •• 19 zoJ 2.1 u 21 1¥ zst 2& &.7 II' aud 311& 3J3¥-.!S" )3~
1-2 I BLOCIC 1-~0Uitll:MTIO#II 0 Is I0
-4-1
I ...._.
2.-.3 BIUCICWOIU(. Is I FLoAT
3-1+ Gao~.~.,, F~ q '.Z. IJ. I
•l2.13l..o.ls (; h Is I~ l,o "I •2,,3,t¥ls 1£,1"7,181'' lz.. lzz.jujz.,.ju 'lJ 1 4;1-z.7 18 1 lz'l3o 3•lnlni:~~Ss ~ 137~,P, 11101
/JLOGic. I 81.ocJ< 2. Sl.OCk ::5 8LOC:.IC 4 BLOCkS /.3 LOCA:: <0
FouNDA.T ONS
3L ~L 3L. 3L 3L 3L 3L 3L 3L 3L 3L 3L 3L 3L 3&. 3 .. 3&. 3.. 3L 3L '3 L 3L 34_ 3L 3L 34 3&. 34 3&. ~ I
I
I
~A60UIC. AN AI..VSIS
3 I..AIJOUIC.£ R.S
,"'
'" LltVEitS .... 2 8/C. CACL/t YIE.It.S, _, 2 811./C ICLAY£1tS'"
/ 2. /J R.ICIC /
81tiCICLitV£1l.$ I'IHb .... / ,- 7" ,
'
:Toii•IEU 1'1 TrtEIIblolli ,2 ;ro .... s .... _,2:101~~
-
SITIE. ON 3 OCC,..sl ID...s' ....,2 .:To ....s '-
, .... ,. ·~
,
'
-To eo ....,un .z 64 OCA:S
PElt. VISIT
r -- -- - 5" lo IS 2o 2$ ao 3S
N
~ to-- ~ - r--
:lT z:r a:r z:r
...'2 --- --- ...
I
~
::L •/1. 12J'I 2.8/L
I I
12TI 2 B/1-
: I
12TI
-- 28/L 12J1
: I
2. 8/1- :u
I I I I I
0 I : : : I : i I lu
~ 3 L.A A 01.1 ll.~ ll.S
:.--
I
I
I 2 •/'-
l a;T
I :
5 10 IS 2.0 2.5 30 35
bAY I I I 1 o~y r.JR.. I I I I
LA&ouR.. R.ESOUII.CE ALLOCATION- EAR.LIEST STAR.T.S.
129
Network Analysis Case Study 4. 9
Time-Cost Optimisation Principles
days. The relationship between normal time, crash path. Reduce the duration of each
time, normal cost and crash cost is shown graphi- activity in rank order and assess the
cally in Figure 4.33. Indirect costs of fx per day are revised project duration and direct
depicted along the bottom axis of the chart. cost. This process may have to be
repeated a number of times in order to
arrive at the optimum duration and
least cost situation.
PROCEDURE IN PREPARING A
It must be noted that when reducing
COST-TIME OPTIMISATION ASSESSMENT
activity durations on the critical path,
other non-critical activities may be-
The following procedure may be adopted at each come critical as their float times are
stage of the network optimisation: reduced. The cost slopes of these acti-
vities will also require to be considered
Stage I - Draw the network diagram. Enter and in the least cost assessment.
assess the normal time, normal cost, Stage IV- Assess the indirect costs relative to the
crash time and crash cost for each overall project duration.
activity. Stage V - Assess the total project costs which
Analyse the network and establish is the summation of the indirect and
the critical path based on the normal direct costs attributable to the project.
time-normal cost basis.
Stage II - Calculate the cost slope for each activ- The direct and indirect cost relationship may
ity on the network. be represented graphically in order to assess the
Stage Ill -Apply the ranking to establish the cost optimum duration and least cost situations more
slope of each activity on the critical readily.
130
Network Analysis Case Study 4.9
Time-Cost Optimisation Principles
J. DIRECT COST
CR.-'SH TIMI!.
J(; C~ASH COST
l(iooo
ToTAL.
..
l
Ptt.O.JECT
.,
...
Ej
CO.ST
,;
loa
~
l>£C/l..EASE IN TIM£
lo 12 l't
IN DII!.ECT COST
looo
qSo
...
'2
~1
q-
lrSO
.,
loa
~
..,u
~
Boo
q l>.£C.lllEASA! lr.l TI"''E.
7So ~
7001~---T--~--~~--~----------~--~------~--~--~--~--~--~
to 12 14 16 IS 2.o 22. 2.11- u; '2.8 3o 32. 34 3t; 38
.DiJlilATIOH {bAYs)
Figure 4.33 Normal time-cost. Crash time--cost relationships
131
Network Analysis Case Study 4.1 0
Cost Optimisation Examples
132
Figure 4.34 Normal time-normal cost network n
0
z
~
<ll -
-0 0:e
NoR.MAL TIME I='
/.loll.MAL TINt£ "C
26; DAYS
NO/l.M AL CoST 4- l!r >
<ll Ql
J.Iooo NOll. MAL CoST {1 0 2.o o
--· *=
Ql -
--<
~.
<ll
s·=
a
8
j1zoo
Dlll.ECT COST -, G 0 0
INOI/t.~CT COST
G 2GOifVS.Aoo 2.4»oo
ItO AT .J..: ,
Soo
!. -+ 7/o:Z.oo
w
w
Cll.ASH TIM£
t:
Clt.ASH TIME 18 DAYS
CR..ASH COST Cll.ASH COST {12.800
/ AIC:HUCT COST
G- 18 oAvsftoo /Boo n
AT :J.' ~
~
2.
I I
/12.800
Jqoo I'TI
ALL ACTIVITIES Cll.ASHED ><
"C •
Figure 4.35 Crash time-crash cost network -3 ...
~ Q
n
0
z
I'D
"'- -
0 0:!;
"5!.
3" > *
-· :I
"'-
Dol Dol
--<
0
-· "'-·
:I "'
Normal Crash
Et·ent Duration Cost Duration Cost Reduction Additional Cost Float Ranking
nr (days) (£) (days) (£) in time cost(£) slope
1-2 A 4 800 2 1,000 2 days 200 100 0 1st ranking
2-3 E 8 1,000 6 1,600 2 days 600 300 0 3rd ranking
2-4 B 8 1,200 4 2,000 4 days 800 200 4
2-5 G 4 500 2 900 2 days 400 200 10
3-4 I 4 500 3 700 1 day 200 200 0 2nd ranking
3-6 F 4 1,000 2 1,600 2 days 600 300 4
4-6 c 4 1,200 3 1,600 1 day 400 400 0 4th ranking
w 5-'6 H 2 400 2 400 - - - 8
-1::>. 6-7 D 6 1,000 4 1,200 2 days 200 100 0 1st ranking
Direct Direct
normal crash
cost 7,600 cost 11,000
n
~
til
1'1'1 c
>< -c.
Dol -<
"CC.
3 ""'
- ...
~ Q
Figure 4.37 Network diagram showing rank order
I=
R.AN K/~G OR..O£R.. 4
...<'o,">-.f~./'
~"'<co.~
.,.'t-~
a ..... '
8 f2 '1-
CO.ST SLOP£ , Oo
= F Itt ST ll.AN 1<111 G
G
4 IS
w
\.n
F OPT/HUM T/M£ 2o OAYS
L.EAST CoST !=oR.
11- LEAST CoST Jtosoo
20 lMY DURATION J.tooo
~
f.ll
1"1"1-
>< cQ.
~
3 -<
'C ~
ii":...
<ll =
Network Analysis Case Study 4.1 0
Cost Optimisation Examples
OPTIMU"'' OU/l.ATION
L.6AST COST AT
DAY :2.2. (102.00
.,
10 8
0 "7'loo
c..
,
,800 "J"'Ioa
"'-t0
.Ooo
DIR.ECT COST
n G
0
"'.... 5
..
I foiOIIt[CT CoST 24000
2
18oo ~,.....----~----~f:•~o~o~J~~~y--~----~----~t~·~--~~4~---~~
U )I
ll tt
/NOI/UCT CoST
Du R.ATION (oAY-3)
Figure 4.40 Project cost relationship
137
Network Analysis Case Study 4.1 0
Cost Optimisation Examples
138
Network Analysis Case Study 4.1 0
Cost Optimisation Examples
A
I jtoo
N£TWOIU<.. INOICATING
NOAMAI. TIMES AND NOR.MAI.
COSTS
Nf.T"''OR.I<. II<JDICATING
CR.A3H TIMES ltNO CR.ASH
COST.s
139
Normal Crash
Event Duration Cost Duration Cost Reduction Additional Cost Float Ranking
nr (days) (£) (days) (£) in time cost(£) slope
10-11 1 100 1 100 - - - 0
11-12 8 420 6 560 2 140 70 0 2nd ranking
11-13 16 800 12 1,160 4 360 90 4
12-13 12 1,000 8 1,200 4 200 50 0 1st ranking
12-15 18 1,080 14 1,200 4 120 30 4
13-15 10 300 8 480 2 180 90 0 3rd ranking
13-14 8 1,000 2 2,200 6 1,200 200 12
14-16 6 300 6 300 - - 0 12
15-16 14 1,200 12 1,500 2 300 150 0 4th ranking
Direct cost 6,200 8,700 Direct cost
Indirect cost Indirect cost
80 days at £40 3,200 2,800 70 days at £40
Project normal Project crash
cost i£9,400 £11,500 cost
140
n z
0 II)
~ i"
0 0
"CC ...
- ~
L£.AST COST FoA. A 70 I>AY ~: ~
<ll s:w
OUR.ATIOAJ !::, -<"'
-· <ll
0
:I -·
<ll
- ~
-4 NOI!l..M.AL. CIILASH
'<.Y '<.Y
P.•l>UCTION A 00 ITIO AIIU..
E.llliiiT ll~a /:>UII..ATto'-1 DULATto'-1 FL.OAT IJOTES
cosrJ. cosrJ. IN Ttl"'&: COST J..
/0 - ,, I /00 I 100 - 0 L ,;..,.~ eo sl: / ft,;.c
-
I I - 12 'l-2..0 c;; s~o 2. I~ 0 u..t-.1: •
.:..1"+ - ·cJ.
8
IG Boo /If CfiO :2. /tJO 0 t!o~T /!!:lo .,. Z J111!j•
II- /3
looo 12.00 0
12..- 13 12.. 8 ~ 2.00
Plto:T£cT
J'1t;Bo
COST
N
NOA.MAL CIUfSH
"""'
R.~I>CIC7ION A b~ITIO.,L
~V6.fi7N,t I> UR.ATioN cosT}. DUll-AT ION f:LOAT NOTES
cosrJ COST
/D -II I /OD I 10 0
'"" ''""· (:>
- -
II- 12 8 4:.Zo 6 560 2. 111-0 0 2 ..J ~ .. k;"j
EXERCISE 4.1- NETWORK ANALYSIS (a) Draw the network diagram for the stage of the
contract, analyse the diagram and establish
the critical path.
The schedule lists the activities involved in the
construction of a new bank vault from possession
(b) Convert the network to a bar-chart presenta-
of the site to the fixing of ground floor beams over
tion and highlight the critical path.
the vault.
(c) During the progress of the contract the follow-
ing durations are recorded:
143
Network Analysis Exercises
Figure 4.48 shows a network sequence based on the following tabulated data.
(b) Describe and illustrate the procedure for level- (a) Write a formal report to a Contracts Manager
ling resources. recommending the adoption of the time--cost
(CIOB. Direct Membership Examination - Build- optimisation technique to select the optimum
ing Production and Management Paper- 1983) duration of a construction project.
(b) Figure 4.50 shows the network for part of a
project. The latest progress report indicates
EXERCISE 4.4- NETWORK ANALYSIS that, because of delivery problems, the earliest
starting time for operations 12-13 and 12-14
will be day 51. Careful study of the master
A network showing actual durations for an exten- programme and the inter-relationships between
sion to a small building is shown in Figure 4.49. trades shows that it is important for operation
(a) Analyse the diagram and show by tabulation 19-20 to be completed no later than Day 81 .
the critical activities and the earliest and latest
event times. (i) Using the following information calculate
the cost slopes for activities 14-16 and
(b) From the information draw a bar-chart pro- 16-19 and insert these on the network
gramme and explain its use. diagram.
Activity Activity
(c) The following delays occur: 14-16 16-19
(i) Delivery of kitchen fittings now takes 38
days. Normal duration 10 days 6 days
(ii) Electrical finishing now takes 8 days. Normal cost £520 £300
Determine the effect on the critical path and Crash duration 8 days 4 days
related activities. Crash cost £570 £352
(d) Compare network and bar-chart methods of (ii) Advise the Contracts Manager on the cost
planning. implication of completing operation 19-20
on or before Day 81 .
(CIOB Direct Membership Examination - 1984
Building Production and Management Paper- (CIOB. Membership Examination - Building Pro-
1984) duction and Management Paper- 1983)
144
Network Analysis Exercises
NETWOR.K DIAGR.Afo'l
FoR. S£R.VIcE.s sus~coNTIUICTOR...
NT - o./0/I.UA&. TIM~
lo WT
CT- C/l.A~H TIMii. S CT
5WT
4 CT
/
/
/
/ 0/l.IGI..,AL
/ E.AALIC'.ST .STAAT
DAY IS~
Fl>l Gtcou~o~O F'U>aoW'::::-..
/l.A DIATOIC:S
8NT
$ cr
~ LECTR.ICA&.
R.AIJIWAT~R. GoeOS
10
145
Network Analysis Exercises
KEY
146
Chapter 5
Case Studies relating to Precedence
Diagrams
5.1 - Precedence Relationships 5.4- Factory Project
Relationships between network analysis, Analysis of precedence diagram for a fac-
precedence diagrams and bar-charts de- tory project
picted for a range of construction situations
5.5 - Garage Project
5.2 - Precedence Sequences Analysis of network diagram and prece-
A series of case studies relating to a range of dence diagram for a garage project
practical planning situations aimed at illus-
trating precedence relationships: 5.6 - Earthworks and Bridge Project
Analysis of precedence diagram for civil
Piling and foundation sequence
engineering project
Steelwork and cladding sequence
Development of sub-networks for the pre-
In-situ concrete floor beam sequence
cedence diagram
Factory project sequence
Presentation in bar-chart format
Reinforced concrete frame sequence
147
Precedence Diagrams General Principles
148
Precedence Diagrams General Principles
PR.~CEOE.NC£ R..ELATIONSHIP.S
WUMAiiiC.
SU&NETWOI/l.l<.
Fote. TI-llS
149
Precedence Diagrams General Principles
PRECEO'£NCE R..ELATIONSI- /1 PS
O.-.TES.
., 51
SPECIFIE:b DATE - USC/!> TO SHo.._, SPECIFIC:.
S UUT PIUI<IG
ACThiiT"'. /foJDICAT0/1..
-0---
1
R.: INOICATE:S Ti-l liT TU£ ACT,.IITY /VIAV SC
A'FFECT£"0 8'1 M--.WAGEMENT DECISIONS TO
150
Precedence Diagrams General Principles
2. l-----:-D-A-Y-S-~)~0
()1----..;..:..;.._D_""_~-S-___;0W
0 1.1- ll- q
UNTil..
I
A
I
HAS
ACTIVIT'/
A
~
, ACTIVITY
15
4 5
A CTniiT'f 8
...:
A CThiiT"i 0
:Z. OAYS
I b. CA~~OT .STALT
'C.'
UNTIL
HAS
4 O.AY.S AI'T£R..
Fli>IUHEO.
IO
·~
., Jq
N4
MAV 86 USCb TO
ACTIVIT'f
c. '.I ACTIVIT"'
t:>
O•~OTIE CUif.ING
3 2.
T/MiiS Fo~ COA/c.ll.rr£
ACTIIIJT""/ II 1•11 l!o I ... ,.s '' J '"' I•• 1' 1 1-z.• 11 I U j z:Jl "Zotl2S'
ACTIVITY c.
I
I
4DII YS
I
.J
I
ACT HilT'/ 0
'I I
151
Precedence Diagrams General Principles
16 .20
,#.C.Til/IT'/ A CT,../ITV F AI>IO
~ F G C.AI>I .STA.C.T
q. AT THE 5AM£'
TINt ..
II; 2..
s ..... ,l.cTniiT'/
/ 6
8
(STAG£ 1)
ACTIVITY 0
S &>AY$
2.2. 30
ACTIVIrY
p C.AI>/I>IOT $TA&T
0
LJI>ITIL. fa DAYS AFTER.
8 0 HA5 STA._T~D
27 35
s 5 AcT,./rry
p
6
152
Precedence Diagrams General Principles
~ ...
ACTIVITY p
3o 3B
ACTIVITY F
~ )(
J1
"~
y 3'1- 38
CAH..,OT FII<IISH
ACTIVITY
U NTU.. lC HA$ y
FIN ISH£0 ~
ACTIVITY y -.~
153
Precedence Diagrams General Principles
2.1 2.7
Ac.TIVITY F6
~ y
t;
FINISH
A FTalt.
UNTIL
ACTIVITY
Q OAYS
y
23 ""
33
ACTIVITY
z ,...
IO
ACTIVITY 2.1l zzl ulz¥Jzs -z~ 111 I u In lao -.1 I.u Iu I s¥1 u
ACTIVITY '/ I
I 4iD !AY.S I
I :
A CTI'IIITY z
154
Precedence Diagrams General Principles
lo 18
F6
'
/
.AC.Tn/JTY
R.
B
Ill- 24 ""
S/.1-
,
~ ACTI..,ITY
s
,\.
10
I I
A CTI\IITY s
I
~ OAYS
I
,_
PILING To FOTS
I I
STAAT I D,.VS .J
ll.&I.ATI....,~HtP I I
PI'-£ C-"P
C 0 AI S Tit CJ CT 10,.,
- 41>AYS
.... ,,
I
155
Precedence Diagrams General Principles
LS LF
#.S EF
ACTIVITY
bult. jltE,.
0 4 + • t,i
,,.
S£T UP
SITir
~
~
S~T
OUT
,... f:t>TS r--
4- PI 2. Sl 8 Fl
TI-lE
, FL.OAT TIIVI E I FoL EACH A CTI\IITY IS THE
OISPL.AY So)C
0 ,,.
0
S'ET uP
4 4- 6 c; ,,.
SIT f. , S&T
our , FOTS"
r--
4- PI 2. 51 8 Fl
156
Network Analysis Case Study 5.1
Relationships and Presentation Principles
METHOD OF ANALYSING THE earliest start and earliest finish times, taking
PRECEDENCE NETWORK account of the relationships.
157
Precedence Diagrams Case Study 5.2
Precedence Networks Relationship Examples
A number of examples are presented based on 5.2.3 In-situ concrete floor beam sequence
practical situations. These are intended to demon-
strate clearly the relationships between the start Figure 5.3 illustrates the relationship between
and finish of operations when applied to a range of formwork and reinforcement operations during the
site situations. construction of an in-situ concrete floor. Durations
and start and finish relationships have been indi-
cated in order that the reader may analyse the
precedence network. The analysed network is
shown in Figure 5.4. The bar-chart display and
5.2.1 Piling and foundation work sequence
allocation of labour are shown in Figure 5.5.
Figure 5.2 illustrates the relationship between the Figure 5. 9 shows the sequence, duration and
erection of steelwork, roof cladding, perimeter interdependencies of eight activities which consti-
brickwork and wall cladding. The erection of the tute part of a reinforced concrete framed project. A
steelwork and its relationship with the roof cladd- blank bar-chart is shown in Figure 5.10 in order
ing are critical to the earliest completion of the that the reader may prepare an assessment of the
project. The commencement of the brickwork on bar-chart sequence.
Day 15 will ensure the start of the wall cladding on The earliest and latest times for each activity
Day 18 and hence the completion of the overall have been indicated in the activity boxes as shown
sequence by Day 23. in Figure 5. 11 . The float for each operation is the
The relationships used on precedence diagrams difference between the earliest and latest start; and
allow the start of an operation to form part of a the earliest and latest finish. Figure 5.12 illustrates
critical sequence. In this example the earliest and the bar-chart format produced from the prece-
latest start of the external brickwork falls on Day dence sequence.
15. The start of the brickwork directly affects the
earliest commencement date of the wall cladding Note - this example has been adapted from the
as this cannot start until 3 days after the commence- 1985 Final Part II Building Production Paper of the
ment of the brickwork. Chartered Institute of Building.
158
Precedence Diagrams Case Study 5.2
Precedence Networks Relationship Examples
0 4 4 I~
~
0 4 4 14
EXCAVATE F&
TO PILUIG
I+A.. L. El 10 PI
q ICf",
q 17
F3
55 .,.... Pn.a CAPS
8 P2
I!> 22.,
/e
IS 22.
S4 ... GRouoiD
'\
w
6£AMS
:> E2.
OPER.ATIOt.l •I ~fsf ... fs 5 l"~l•lq l•o 11 f•z f•s l••(•s ·~I 17 I' 8 ~•La. a~(ujuJ~~zs
I
-' .J. _.
IAtl.l[~
I
f.l· E.lCC.AYATt: To ILL I
I I
I
I I
J, I
Pt- PIL1"4 G
•
I I
I I
P2.· PIL£ CAPS I
I I
I I
J, J
E 2.· GROUiolb 6£AMS
159
Precedence Diagrams Case Study 5.2
Precedence Networks Relationship Examples
4 Jf
0 s s IS Ill u,v
0 5 s IS S3 ~
,,
WjiiiU.
23
II IB_y
II 18
Ft..oo'
SG .... c:.LAOOioHI
7 3
OPEit.ATtOfJ '12.1314-ls col "lief I9 Ito ultzl t3l t¥ Its 1~1 1 1~'1"1*' Zl Ju Jz.s Jz.o Iu ala7tz'J
I· ~OUt>JllATIOHS
~
2· E~rcr :srmLJoc.~c:
I
I
I
..,
I
3· /l.OO~ CLAbDti/G I
I
I
I
• liXT. 5/t.ICIC.I.JOIU<
:I
,:,
5• /.JAI.L CLADDIIlG
160
Precedence Diagrams Case Study 5.2
Precedence Networks Relationship Examples
S"5 F2.
', 1'-&a"FT
To alAMS
G MY%
,
\.
•
SEAM
So,.r!'S
...,
'",
... .. ..,.
SIDI'S , .. ...
\. Coli! CUll'
~
..,.
'
aAf% 3 &Af2 &AY'2
...
0
B£Aio4 &lAM
1-- CON&&ftt
8 5 I
lr"
S'S \.
u ... ,r F2
I To UAJU
fii
~·
161
Precedence Diagrams Case Study 5.2
Precedence Networks Relationship Examples
SEGU6NCE
ss ,
"
"a.aueFr
,,
17
FZ
To ad~U
G ·~y.z
.. '" IG ,q :z.o
.. •
1'\
16 ICI Zo
~· 14
,.,..,.. ,\. &lAM
~
a rAM ,
~
CoNCUI'I
r
SID•S
,..
B~AM•
0
0
..
a
II
s
IG
,,
II
II
14
\2.
t-
~
&lAIII
Soi'FITS
&IrA .. __., c:o..c..,.
SIDIS ,. Sir AN• t-
8 .,..,. 'I 81WI I 8AYI
II'
8 l&f
3 Cf
s:a
'""''r
,' To aUMJ
F2.
162
8 A /t:"C ,_, IHt T PP..E.S£N TATtoiJ /ltiSITU COtoiCIC.ET£ FLOOR.. SEAM SEGl.f.JENCE
I!.A'i I
SEAM SOFFIT.S z ON
~ - CAR.PE!ol~ 6A"'G '2
§I R£111( fOR.CEMEtoiT &!rAM s4FFIT.S A ... D SID&:S
ON &AY Z.
e,EAI'I\ SIDES
Ll ', :I : ; :I :1 I
CONCfUT£
LA~uR (<AAu-r•~u) I ~ I
CAR.PU~1l.ll GAe.&G t < 4- C.AA.PE T£R. S ~
~ ~ CAR.PI!~TEICS ..I
c:.AR.PUI"Td. 6At66 ~
) 1/ 2. STEJi'Z..Fir'I<ERS "
7J
ST£n.fl'lttltS I< .2. STiilil.riiCOtS '
71
GO...,C.IItliTE
"
GAtoiG
~ A
Figure 5.5 Bar-chart display floor beam sequence
FACToAY PA.o.J6C.T .5£BUEitiCE
(PAA.T 0~ P&ac•o•~t~C6 OIA&It.AM)
S7 llooF F2.
~
......... ,... C. LA DO
__; ~r
wr- f--
lor-
SS' PIL£
,... C.APS f-
12.r=
71'
0 '
3n UP PILI .. G F5 '--i G«ouMb ss
Sl'n
...; ,.... WA&.&.
a-, SLA& - C:UU).
..j::,.
51 ~ ~
•or- sr- 7r-
.;~
•sr- ; 5 r-
~~L
4 DllAJJIA8£
tor-
Figure 5.6 Factory project sequence with data entry
FACTOR.'/ PR.OJ ECT SEG.UENC£
10 ~1
~ cofsa 10 reT
IO u
ss PILE CAPS
, ~
~
12.. fP'i"
/I'
~~
I ~;;. ~~
~~ ~~
0 5 ,q 22. 2..8 31
0 5
' 5 15 22. '28 ss '3q
4"
44i
~n UP PILI"'G F3 ~ Gt.ouoU) , Wf'lLL
// 1-
SITE ,,I I ,,. SLA6 CLADG
---:)
\.n
"' lorPJ ~ "7 (C"i'"
5~ ~w
I['
1 2.2. 34 3Cf
s ~0 34 3CI
I..T&R.NI\L 1- E'ICTEt.NI\ L
,'- DIL\lo.IA6t 4 Blt•c.-
1---
15fOT , SIST
2q '3CI
20 30
ilCTII.IIAL
DEIIIOTf.S ,.lt.CC.EDENCE
~ baA~t~NiE
I 'f PATH
10~
'"' I
c.
c;
~
ERECT STE'nWORK. 2.8
I
c. I
J.,
RooF CLAODI"'6 34 10
I
c I
I
EXi. B~IC"WOIU:. 34- 5 I
I
c I
ISO
IIC.OND F8 RooF
I'Looa SLA& -
SI.A&
) sa _ ... -
~ r
2om 2o_ffi
..... / I'
c;r,
"'-~
I
~
~'
COI.UM""S F2..
~ COLUMt.lll-
Sl2. ~ WALL,&tA14 ,
, ~
!IEAMSTc
SICoolt> FL , RooF
liD@ 32. [4i
II'
~2.0
•
;:11:1
WINDOWS RooF ~
_L _ Awb F 12. jij'
,.... C!ILI ... G
SC:If.I!El>~
sa ' s·
-
... t'"l
,' :::r
"' llol
-4-o [:40" , s m ~ =-· "0 "'~
rn V"l
><
llol c
Figure 5.9 Reinforced concrete frame with data entry Q.
-
3 -<
"0
1f :n ~
BAR.- CHART DISPLAY R.. C. F~AME SEG.UENCE
OPERATION
E-S. DU.
ISO 155 160 165 no 175 lBO ISS 1qo l'fS 2- 2QS '210 2'2.0
215
S£c.oND FLOOJl
SL.A&
CoL, WALL,BEAMS
2Mo FLooA..
ROOF SLA&
O:l
"' WINDows AtUl
CEILING
COLUMNS A .. D
&AIIIIS '1l) RooF
RooF Ll QHT TO
STAIR.:S
RooF scum
~~
1~2. IS~# ISO .212' /
1402. 178 178 222.
CoLUMOIS 1 F2.
Co\..UMol
WALL 1 BQII 7
512. '
, BE:AMS
!l..... " 7' To ltooF
~~
IGtrJ 3~ Kz
52.0
.:::~ 170 .210 21lf 2Hi.
170 210 llf8 2Z4 ;'
WIIIOolooiS
~
Ft2. R-oof
7 A"' I> ,,, SC.Uii.D.S
as·
CEILitiG
~8 -~
'" ~ t"'l
l ... ::r AI
~ 7
~ -· <I>
' I
4-o J4; 5 r-43
~ "C I'D
I'TI ""
><
AI -
C
3 Q.
Figure 5.11 Reinforced concrete frame analysed "C -<
-
I'D •1.11
"' N
8AR:CHAR.7 PltESEH7ATION R.E.II<JFOR.CED COIJCR.ETE FR.AME
OPEA.ATI0"-1
~.s. out
I 'SO 155 I COo lc;5 17o 175 I So 185 I<to 1qs 200 2os 210 '215 ).tO
$12.
.j,
COL, WALL 1 &lAI4~ lei "'
''2 I
~010 FLOoa. c . I
I
I
I ov ll,AL..&..
'-J p 1'2.
0 1 _,
WU•t)OW.S: AND ,,0 4-o -- ---
CEILitoiG c I
I I
I
I
COWM"'S AND ,,8 32 I
8'AMS TO lt.OOF Fa. I
I
l
RooF LIGHT 'TO aqo 4 - :F2 1
STAI._S F-aa I
I
I
Figure 5.12 Bar-chart display for reinforced concrete frame
Precedence Diagrams Case Study 5.3
Industrial Process Building Analysis
The precedence network for an industrial process facility allows the user to relate the network to a
building is illustrated in Figure 5.13. Procurement real time situation when following through the
boxes have been incorporated relating to key construction sequence.
material resources. Calendar flags have also been The analysed precedence network is shown in
introduced in order to relate the earliest and latest Figure 5.14 and the bar-chart display in Figure
start days of key activities to a time scale. This 5.15.
171
5" .""0
c. ~
LF c 1"1
LS ~
NoTE • DLJ/L.A.TroHS SHoo.Jol "' c.
~
CA.S£ .STUDY 5.3
I >I j.JEF:'IC.S et ~
~ - 1"1
/>IJII.. ""0 ~
-..
Q 0
1"1
~o:r
I<.EY (JQ
PIU CI\,..S L~
.
"'"' Ill
32. J J ~~a-:;_-·- =5. Ill3
Precedence Diagrams
s:::
(JQ
:r
Industrial Process Building
S2.
'J
N
s:z.
H"J
0 - OA.OEltS
;;;· w
:I ""C:C
Q. ~
c l"l
LS Lf ~ !_
13 .21 :::!. ~
CAS£ 5TUOY S. :3 f'.... f~0. ___ 10\ !:!., ~
""C:C ~
buR.. a 0
l"l
~ -·
Ill
/O ~!I :zs I<.E:Y ~ ~
i01 13 /$'1 =3
52. .. _I PILE C.I\P.S 1 r,n
I
y
. !_.CI~~oob: 5.
c:::
:r
(IQ
S2.
, -- r,..,,
....
"w
S2. 48 loUU:.S
M1
slslo Ill
..... G. f • SLA6 IO 3 0 c:=
52. STrtU<:T. STIEU. :r
Industrial Process Building
OQ
MA CoNe. CASr>JG
151 ... 10
11 3 0
sa 1•r FL.oolt. SLA6 2.0 :z. 0
..... Co.,c. CASrOIG 1•••1,1221 S I 0
S4 :2.NJ> FLOO"- SLA6 l25l :Z. I0
,..,, CONC. CA:SI#IG 2-::J.11 131 0
ss /t.OOF SLA6 ·-,3. 2. 0 ~
I.YT. IJrubow s t1 I I I I i I
S7
0 I
R.ooF .SS
SG FI.,ISH
32.1':z."1 I
~
,..,c; _j
INT. Fl>~r"ISHI!S I3Sitol o ..
I
"-.! I
. - - - - - - · - - - --f-- -----· ---- --·--- - r-
""" 3 5
02.
.. ,.....0 It Mil.
·-~j·
, .. .., ....
0 IO
s Ill 'I
0.1 0.C..D1'1t ~c. ST-'tt.S 0 IZ If)
------ ,_- ---- - - - -- - ·-- - - - - - I- - - -
_L
MJliOITr:&riAL l>lltAIOIA•t:l S 2 3
I
I
M5 8/C&.I. To G&DIIrii>F 13 :Z. 10
(")
AI
lfl
(I)
> S'
:I Cl.
Figure 5.15 Bar-chart display industrial process building e!..-<
~ 1.11
Case Study 5.3
Analysis
iii" IN
Precedence Diagrams Case Study 5.4
Factory Project Analysis
Figure 5.16 indicates a precedence network for a such as the boiler house and chimney construc-
factory project. Start and finish relationships be- tion. Boxes prefixed by the letter F relate to
tween the steelwork, roofing and wall cladding foundation operations. The introduction of a simple
operations are illustrated. Analysis of the network coding system aids presentation when collecting
indicates the path of precedence following the together related activities for the bar-chart format.
drainage work, ground beams and external brick- Figure 5.17 illustrates the bar-chart format pro-
work activity boxes. Reference codes have been duced from the precedence network.
introduced relating to particular work locations
175
""C:C
~
S' ~
CAS( STJJO"/ S. 4 .
-< a.t'D
""C:C =
;o 75 trS ,
... too /10 /10 /25
.
5 /o IS
"" 15
"" 2.5 :z.s 35 ss so ..2. ~
BotUAIIocJSS IJ OILECH041$a
'" .OIUICHOU.J6 ~LIIIHOfiSI INSTALl.. ~ 0
r--4 ~0 6/HbA.TIOit/ ~ ~00, .OI~EJf.S
f-- Ai.
~ F~o"~rn ~t..U ru CJQ
5 f"il 10 m IS IIi' - ~
3
,s 15 'IS 11S 125 /Jo
"'
10 ;:1.0 20 <:o .... GS
CHJMNW'f EllEC.T TI<ST
~ FouWOATioW CJ.41"-4NN Bo1LCJlS
10 40 s
-
fCI ICz ~
0 s II 31 311 41 7'1
0 5
¥•
1- s :z.s ;;zs 35 35 cos
SITU,.
PILIN(J PILC £111<CT
SIT. C:.AP.S .ST.-TLL-10~
s !Pi .2o Vr" to _jFi - 3o St
FS
Sto
'L '11 IS oro 'to loo loo IS.
'..J '1-S 7o 75 "'15 lr5 /IS
•• •s
teooFING SUJI'WNDCll Ett.•cr CAT HHJN uvn
"' SCAFFO.L.D ~ I-../14LIIC::·m SQVIC'I"S
!Z.o TiT 5 liz lo IU 30 m
~ F8
ss
S'O /00 Go "70 qc>
70
So <;o Co 7o 70
GAoullib a.C.ICI(W_,I(
L W~L&..
<ro
~ SE~M.S'rFJ Exr. I.JAU.S ., CLADOIHG
to Fl
f-+-l 10 _IFf .:zo @
-
~
4-S IS [FS 5 40 IO
ro. IFi E ~
n
Qj
Figure 5.16 Factory project precedence diagram "'t'D
Vl
:I
> cQ.
Qj
~
-
-<
V1
;;;· ~
C::AS£ .STUDY s. 4 BAR:CHAR.T DISPLAY
O~£AA.Tto,.J IU 11>~1 ~~
lo I Zo I 3o l 4o So l ..... l .,_ I eo I l!lo 1 1oo
1 I
SIT UP SIT£ 0 s
Doll.AI.,A&E 5 45
oh
0
G"oU""O 8EAMS So 10 0
COMMISSIO~o/ ISO lo 0
Bo•LCR.Houst
Foui>JOATioi!J.S 5 5 GS
l&.ooA. /0 5 75
1../At.LS
~ I
15 lo 75
/too, I
zs 10 751
INSTALL 80IUAS 35 /5 7~
T~ST &otLC'._.S 4io s 6:
'-J r----- I
'-J I-- - - - - - I- - - - - 1---- - I - - - - - I -
CHIMN&Y
FOUI>JDATIOI>J
t:AIC.T CH 1"'1N•Y
i
------- I I ~-- ---
FA.A...,,
PILU•I~ 5 '2.0 13
P u.r cA ~.s
,:,
2.5 10 u
E~IC.T ST81LU~ liS :so 15
ltoo~,.,G 11-S ::to 12.
..i,
.1C'CAVAT6 8AJitJI 50 /5 20
Co..,c-.rr• •AJitS t<S 5 20 ......._
.SU$,11>10rD SCA ... 7o s IS
A network diagram for the construction of a pre- the same project in order that a comparison may
cast concrete framed garage is illustrated in Figure be made between the two formats. Figure 5.20
5.18. Analysis of the network indicates the critical illustrates the bar chart presentation based on an
activities connecting the path of zero float. analysis of the precedence diagram.
Figure 5.19 indicates a precedence network for
178
C'l .,
Cl iil
;:: t"l
()Q ~
~ Q.
~
?l
~
CASE STUOY 5.5 GAR.AGE P~O..JECT
0
~·
.
~
3
"'
CONT~CT
COM ~UTIO ol
OA_, 7 :!t
'.J
1.0
I
I
OR.DI:R CLAD.DJtol6 I
II+ 12.7 I
I
_ _J
I
L.A"nST
O/I.DC1l.
bAY+
2.1 u al ,.
0 18 ~., ~+Z S1 S7
l 39
0 181 _r~., ~71 I"f., s?i ls7
Oo I
~·-~
18 Ill 13
a
11 LtN£ oF
II P~£ C£lH'61JC£
E'l/i#fT
0 PFR.ATIOo.l .:;~ Out. FL
NA tc 2o 3o 4-0 5o 60 7o 76
I FOUN[)ATIOioJS 0 18 0 I
I
2. Efl.ECT Fll.AM£ /8 3 0 b: I
I
02 OIU>taA. R.oOF UNITS 0 18 3 ---t
I
~
3 A.ooF ST~UC.TUU 2.1 I'Z. 0 I
I
I
/3 Fl '-Nl>OV£7l. 7/ 2 0 'b
Precedence networks are widely used for planning the analysed diagram covering an overall construc-
works of a civil engineering nature. Operational tion period of 100 days. Sub-networks have been
sequences on civil projects tend to be of a less incorporated for activity boxes 204 and 205 in
complex nature and the relationships between order to analyse the activities in more detail.
them can be readily presented in precedence Figure 5.23 illustrates a bar-chart presentation
format. analysed from the precedence diagram showing
Figure 5.21 shows the layout of a precedence earliest start times.
network for a bridge project. Figure 5.22 illustrates
182
~------~---------------------12%5
~~
Cl:l
w
~ l:u.7
C.£1./Til.AoL. PIE7l
s....
I'D
l"l
SU/!JI.JET"--oll.IC- ACTIVITY 2.oS
F3 -
0:>
-1::>.
Nolfl.TH A BvTMENT
,ILl C-4~
I 'll ~~ ~~~-~~~~ I >I
~ >I Sn'D NoUM 6
SIT
2.
~
Ql
"'I'D
Figure 5.21 B Earthworks and bridge project precedence diagram fJ)
>
::I
c
Ql
c..
-
-<
-< (J1
;;;·
"' =--
1"1"1
~to~
.,...
~
~ l"l
'10 'I~ :r ~
~ ~ c.
2~ )( S.tlb Woi.T>I 1------.. CA!I£ STUDY s.G 0 ~
l.M&.A•IIC.Ml..rf
~
... l"l=
4 (laS ~
"'
~to~
J+ J7 4-~ 4-B 4-B 54- 0
•+ =
c. s;·
m I~·,:~~ J:~NeAr~~ J~~. . . .,., l_r:;::-] CIQ
"I =
... ... ~to~
~
V1
NOR.TH A &UTME:NT
2.
("')
~
~
Figure 5.22A Earthworks and bridge project analysed precedence diagram fll
>
~to~
= -<c.c
-<'VI
~· a,
I'T'I "'CC
~ ...
:::1. I'D
t"'
:r
77
llSI
NS ~
!8
~... :t
t"'
Ill I'D
~
::r 0
Q. ;s;·
CIQ
CASE STUDY S.c; =
... ... ~
" 5:. 3
CIQ Ill
I'D
"'CC
...
.2.
I'D
t"'
15
I N3 )4CC -
s
q
..
co
0'\
0
.G
3 55
.. ''
~u
Accrss8 ~_ ~
::;
3 Z•
lo
n
~
~
r.n
Figure 5.228 Earthworks and bridge project analysed precedence diagram > cQ.
::r -
~ -<
-<
Ill VI
c;;·
""
I'T'I
l:ol
.,...
~
::I. 1"1
::r ~
CASE: STUOY s. 6 lJA.It<HAR.T 0/SPLAY ~ Q.
0 ~
... :I
~ 1"1
<ll ~
OP£1lATIO,.., l:ol
£s 1"""1 FL' 1 loj I 3ol I -4ol I Sol I 6oj Sol 100
1 ~ol I 7oj I I Sol I I :I 0
Q. s;·
UP SI'TT
OCI
2ol SiT 0 6 ...
2d SUL.Irt £XCAVA.TIOPol 18 5
ofz=l• =
::::!. l:ol
. Q. 3
2oJ OAA.INS "' .. A&UTM, IS 0 OCI <ll
~
2 .... 1-/0II.TH r' 6UTI'•U.NT " 0
2."' 3o
2.11 IJO/f.TH SPAI>I 81AM6 0
S'-4- 12.
.,...
lf_
:tl<q SOUT,., S~AN &lAMS 15 0 s.
cc ~
:zu Fl"'t I'IIMI'tT WAI.L.S .. , 10 1"1
U3 .SUA.~Ael &OAD/&&J liS 3 0
'2.110 !.C.IOGa" L.ICI411"'G 8W IS 0
218 CL.A.C. $nE 'f¥ . 0 ~=
-
:Zo7
--------
S 11£ a PC6CAST CAw• 0 :zo 2.<q
2.10 OAOt.C. PAIUt f'tT 0 35 3W
-=1- 0 ADEll. LAM,. a'TAWD 0 3o sa
~oG
--------
01V61tT Aec.•l$ 0 3 ...
2.08 H• ..TH A ,,IL,II.AMP I 'I ... ....,
7.1¥ Satrrl4 A ,,It, ._A""~ 2.'1 5 SIJ
2.1& /t.OA.b 6'rC-J &o,c. :13 IO 2.7
Co
'J 2.1 .. SouTH A8UT"'4Et>#T :u lo 33
I ao, 4AC.tcjl:l&.&. H.A..,.,.,..r 54 J ....
:no To,.so•L 1>1 •• ,.. ...... S"J J 17
1U AIO~TN AHt. lf..OAb :n 11 IC
11 .. a Ae.tc FILL Soc.rTN AkJr, cs :1 ..,
2.17 'Tor.lol&. $o"TH «NA, 3 IC
.__...
2.18 SouTH A 1¥LoAQl ..,
....""' 12.
2.12. D-.Atltll $. A6UT"t&N7' 2.¥ 'I 3
2.oS C&lloiTAAL I' I~ 2.• :.s s
:>.osf/ £1CCAVAT& Pl<. 2.'1 s s I===:!
2osf2. P•«A FOVIJOATIOtol 2.'f 3 5
2.osf3 Fo-.Mwo-.tc/ «.~cs 3:& s
:Z.osJ¥ CoNc.A.•T& PtE. 41 ":z. s
:z.osjS ST~Uc.C l=o&HWOLI<. ..., . s ~ ~~~ __ _I_ L_
---- - I
-·--- -
_I_----'·
:l:l.S
SUI> HOI.TH £ .. a I sol+ I 5o r---'
22.7 S£f'l) sovm .,..a L.
"" ~ ...
~
~
~
Figure 5.23 Bar-chart display for earthworks and bridge project fJl
> c
:I Q.
-
l:ol -<
-<
<ll
V1
iii" a-
Precedence Diagrams Exercises
188
PllocuiU. Sl 1
AlfAT6R..IALS
..::........,) 0 1'£/UtTION /til
OPE RATIO,., £
8 PI 2. I CIJ
F2
Oo
'-0 I OPE/CATION 1<.
~ :P£A;;,:H oP£RAn~~ a N2
I f~~T•oN c
1
6 C/ 4- C2.. 7 C3 2.
~
~ OP£/CATIM G- I OPERATIOII/ H
)I ~
rl3[C2" 1~ 1 ce
/'ll.OC U/U
MAT£~1ALS
0~/t.ATIO,., G
~ '
6 P2. 1 Fl
~ OPEitATtoN .J"
""t--------'
8 !c.9
6.1 PROJECT PLANNING BY COMPUTER neglected, resulting in ineffective action and a lack
of control reports. As the construction market
During the early sixties and seventies, network becomes more competitive, the contractor offering
analysis by computer was undertaken on main- the shortest contract period often places himself in
frame computers using head office based machines a more advantageous position. A reduction in the
or computer service bureaus. These were well- contract duration reflects savings in preliminaries
tried procedures but were found wanting because and hence a more competitive bid.
of the cumbersome input routines using punched The introduction of the desktop microcomputer,
tape. Difficulties were also experienced owing to with memory capacities up to 640K, has now
the time lapse between the entry of data and the brought computerised planning to the site. Many
production of a report at site management level. clients now specify that the contractor must pro-
Critical path analysis applications to construc- vide site based computing facilities as part of the
tion planning have rarely been used in the past contract requirements. A site based micro costing
because of the lack of expertise in the industry and under £5,000 can be provided complete with a
because of the effort involved in analysis of all but software planning package capable of handling up
trivial cases. Planners have tended to work directly to 2,000 activities. Packages of this type are cap-
on time scaled bar-charts. For master programmes able of satisfying the majority of planning situa-
and short-term planning with no more than 50 tions. A microcomputer with good software and a
activities, a hand-drawn bar-chart is easily pro- dot matrix printer can produce excellent screen
duced and readily understood at all management displays and a wide array of printed reports for
levels. Because of a lack of detailed information at reproduction at site and head office level. The use
the pre-contract planning stage, long-term plann- of graphical displays assists in enhancing the pres-
ing has generally involved a broad brush approach entation of output data. Integrated packages allow
covering the main phasing or major operations. the transfer of text, tabulated data and planning
These have later been developed into more de- displays to other software such as word processors
tailed short-term programmes as additional infor- and spreadsheets.
mation became available during the progress of The site based computer enables the current
site works. Adequate time contingencies are nor- progress position to be instantly reviewed. The
mally built into the programming to allow for effect of changing resources on future operations
unforeseen circumstances. in the short-term period can be simulated and
The production of bar-charts is time-consuming alternative bar-charts produced for discussion
and often diverts key staff away from their main and future action. In this respect the computer
technical responsibilities. The recording of accurate becomes the vehicle for management decision
progress and updating of the programme is often making.
190
6.2 RANGE OF PROJECT PLANNING Pacs High Point Business Systems
PACKAGES AVAILABLE Ltd
*Pertmaster Abtex Software Ltd
Construction Computing, Spring and Summer edi- Plankit II Amazon Computers Ltd
tion 1986 (computer applications journal published *Piantrac Computerline Ltd
by the Chartered Institute of Building), provides a PPMS Planet Systems
review of project planning packages currently *Project 2 PSDI (UK) Ltd
available for use in the construction industry. The Project Cost Project Software Ltd
review covers some 41 packages offering a wide Model
variety of options depending upon the selected *Project Manager Hoskyns Group Ltd
package and requirements of the contractor. Workbench
Primavera LA Computer Services
Package Supplier *Superproject Plus Computer Associates
*The Planner Micro Planning Software Ltd
Artemis Metier Management Systems Target Task Carefree Software and
Ltd Services
*Artemis PC Metier Management Systems Track T and B Computing Ltd
Ltd Vision/Elan Euro-log Ltd
Apecs/8000 Automatic Data Processing Quickplan Mitchell Management
Ltd Services
CBACS- Pert Conquerer Business and *Quikret PSDI
Computer Services Ltd
Cogniplan Cognisoft Other software packages are also available
Cresta K and H Project Systems Ltd which have not been included in the above sur-
Diagonal Planning Partnership Ltd vey.
Network Analysis The packages marked with an asterisk have each
Easytrack Planning Control sold in excess of 1000 packages since their intro-
International (UK) Ltd duction.
G/c Cue Gilbert Associates (Europe)
Ltd Features available from planning packages
Kernel UIS
Korkus K and H Computer Systems The following features are available from software
Ltd packages; the various features include combina-
Havard TPM W.H. Smith Business tions of:
Computer Centres
*Hornet Claremont Controls Ltd 1. Logic format
Internet 805 Computer Research and
Development Ltd The majority of systems require the user to first
*Logistix Grafox Ltd draw the network diagram, check the logic and
Mapps Mitchell Management prepare the data for entry using a data input sheet.
Systems (UK) Ltd This process simplifies the input data process.
Microplanner Micro Planning Software Ltd Many packages offer either the arrow notation or
Microsoft Project Microsoft precedence notation (activity or the node). Certain
*Milestone Raven Computers packages enable overlaps to be built in and utilise
Mentor The Consulting Centre (UK) precedence with lag facilities.
Ltd A range of software packages allow the network
Monitor Origin Computer Software arrow diagram or precedence boxes to be directly
Ltd displayed on the screen. Using the Apple Macintosh
N 100 Nichols Associates Macproject package, the user is enabled to set up
N 5500 Nichols Associates his own precedence boxes on the screen using the
Open plan Welcome Software mouse facility. The boxes can be altered in size,
Technology International moved around the screen and linked together to
PC-Mapps Mitchell Management show the relationship between activity boxes. It is
Systems (UK) Ltd possible to view and print bar-charts, and sort
191
activities by time order or resources used. The cost critical path sequence may be highlighted through-
of resources and fixed costs may be entered to- out the display and the relationship between all
gether with the forecast income and a cash flow activities, durations and floats may be observed.
forecast produced. Separate plotter programmes Display formats between packages vary widely
are also available for linking to the packages. and preferences lie with the individual users.
Period bar-charts allow the user to select a
2. Calendar facilities display for a partial section of the project. This may
be used to provide a weekly update during the
The user may define the format of the calendar to progress of the contract. Bar-charts may also be
be used - this enables a five, six or seven day output between specified calendar periods.
calendar reference to be incorporated. Switching
between one calendar format and another is avail- 5. Resource allocation of labour facilities
able. The calendar may be printed out in order to
differentiate between working days, weekends and The software packages allow resources of labour
holiday periods. and cost to be entered at the input data stage.
Resource reports can be output in histogram form
3. Standard report format for all labour based on the earliest or latest starts.
Site managements may review the period over
Report facilities enable the network to be listed in which peak requirements occur in order that con-
different orders - 'Earliest starts,' 'Latest starts,' sideration may be given to labour smoothing.
'Critical activities first', 'Order of entry', and 'Alpha- Resource reports for individual gangs or trades
betical sequence'. may also be displayed.
A wide variety of sort routines can be incorpor- A number of packages enable resource levelling
ated in order to group related activities together by to be undertaken in order to assess economic
reference to resources or phases of work. Although labour utilisation. This facility is often used to show
the information presented in each report is the the time and cost effect of undermanning on
same, the fact that it is sorted into different orders selected operations or trades.
allows the user to abstract the relevant facts. A
manager can check on the start and finish dates of 6. Resourcing cost data
critical activities or view the order of work relative
to earliest starts using the various sort routines. Entry of the activity cost or value data at the input
Milestone reports are available in order that data stage enables a number of cost reports to be
management may review the most critical activities displayed. Formats include a cumulative cost curve
relevant to the success of the project. Standard based on the earliest and latest start for all activities
l
report formats display the following headings on or selected trade gangs. This may be used to form
the screen or print out. the basis of a cost envelope. Analysis of the value
data enables cumulative valuation forecasts to be
Activity description prepared based on earliest or latest starts. The
Earliest start cumulative valuation forecast may be extended to
Earliest finish provide a forecast of the project cash flow require-
Latest start ments.
All dates relate to
Latest finish
calendar format
Durations
Float
6.3 CASE STUDY: PRESENTATION OF A
CRITICAL PATH ANALYSIS PACKAGE
4. Bar-chart displays DEVELOPED AS A TRAINING AID
The most readily understood format at site mana-
gement level is the bar-chart (or Gantt Chart). PACKAGE NAME- CPA
Analysis in bar-chart format enables the user
to view the complete project using any of the This is a training package developed for both the
required sort routines. This type of display may be BBC and IBM computers. It enables the user to
used for the purpose of displaying the overall gain hands on experience in following screen
master programme in earliest start format. The prompts prior to moving onto a more sophisticated
192
commercial package. The basic functional net- Prior to the entry of data into the computer it is
work routines are illustrated in Figure 6.1. This necessary to prepare a data input sheet as shown
enables the user to work through the program in Figure 6.3 This simplifies the input data proce-
routine in a logical manner in order to become dure and involves transferring each loop of the
familiar with the system. network in a logical order to the data input sheet.
Figure 6.2 indicates a network diagram prepared Dummies are entered with a zero duration. The
for part of a timber-framed housing project. The user must check that the number of entries
example will be developed to illustrate the applica- matches the number of arrows on the network
tion of the CPA software package. Screen displays diagram.
relating to each stage of the output data will be
illustrated.
193
LOA/:) P/l.OGIItAM OISIC£TT£
194
I= OU#ol OAT ION INOR.IC.S T/M8ER. Fll.A M£ 0 HoUSING
R1MOVI'
2
2L
J.2A»
UN~OI'IP
1.0
\.n Flt.AIJI~S
2.
3L
j J.»o
8wiC Ul
:I - :TOIN£R.S
.5
L - I-A &ou .C..£ R..S .2. .,,
0/t. - Dlt.AINLA'YE R..:S J.•o-
8/L - & It I CI<.&.A VI! It .S
-~----
I,_.PUT bATA SHEET
--.__ -
I'NTII.'i PltEb. sue. bUR.. LAI!.OUR. N• Of C.OST DESCR.IPTIOo.l
ME..,
J
I I :1. 4 :TOI'IE1t. 2. Goo SET UP SITE.
2. 2 ~ ~ LA60UR.E"R. I ISO Sa,. STILIP
.,
w I 8 3 3 Soo FDT U"'IT 2.
,
LA6outtt
12 s II 0 - - - DUMMY
Ill- q 12 0 - - - DUMM'r'
2.o
21
J; IS 0 - -
3
-
eoo
bUM MY
2.fl.
""I 9 '+ !)ll.A '" LA'fE:It 2. +co ,._,HI - MH '2.
25 10 IS - - - OP.DER l'ltAMr:S
196
Critical path routines
Load program disk and boot up using the program
instructions. The main menu options as shown in
Screen Display 1 will be displayed.
Predecessor
Successor
Duration - in days
Type of labour (enter in capitals)
Number of men
Activity description
197
MAIN MENU
~· EXIl PROGRAM
ENTriR CHUICt,
ENTER CHOICE ?
198
KEY IN DATA
ACTIVITY 1
PREDECESSOR - 1
SUCCESSOR - 2
DURATION 4
NR OF MEN - 2
COST ·- 600
ACTIVITY 2
PREDCESSOR 2
SUCCESSOR 3
DURATION 3
NR MEN 1
COST 150
199
/
"""'
ENTRY ND-PRED-SltC-DESCRIPT!Ctl -DUR-NO.IIEN-TYPE OF LABOUR-COST
----------------------------------
1 1 2 Set up site 4 2 Joiner 61!10
2 2 3 Site Strip 3 1 labourer 150
3 1 3 Remove Trees 2 2 labourer 200
4 3 4 R.L.Excavation 4 1 labourer 200
5 4 7 FDT lilit 1 3 3 labourer 51!11!1
b 7 a FDT Unit 2 3 3 labourer 5BV
7 B 9 FDT Unit 3 3 3 labourer 500
B 9 10 Hardstanding 2 3 labourer 31!11!1
9 11!1 1b Unload Fraa~es 2 3 labourer 300
10 lb 17 Erect Frames 5 4 Joiner 12Bil
11 7 11 Bwk Unit 1 5 2 Bricklayer 11!11!10
12 a 11 Dullllly 0 il il
13 11 12 Bilk Unit 2 5 2 Bricklayer 1001!
14 9 12 llullllly il 1!1 1!1
15 12 13 Bwk lili t 3 5 2 Bricklayer 101110
lb Iii 13 llullmy 111 lil il
17 11 14 Srd Slab Unit I 2 5 labourer bOO
ta 12 14 Dllll•y il 0 il
19 14 15 Srd 51 ab lili t 2 2 3 labourer b111il
2il 13 15 Dullllly il il il
21 15 1b Srd Slab Unit 3 2 3 labourer bil0
22 3 5 Draw Connection 2 2 Drainlayer 200
23 5 b Draw Ex-IIHI 4 2 Drainlayer 41110
24 b 9 IIHHIH2 4 2 Drainlayer 400
25 I til Order Frames 15 il il
--------------------------------------
\.. ~
200
SORT ROUTINE MENU
ENTER CHOICE ?
201
Sort by latest starts
Sort by order of entry
Retain sort order
202
S!JlT ORDER : Float 1 Order of entry
203
r
SffiT ORDER : Earliest start, Float
"'
-ACT-PRD-SUC-DESCRJPTION -NO.I'IEN-TYPE OF LAB-DlR I E. ST-L. ST-E. FN-L. FN-FLOAT-
------------------------------------------------------
1 1 2 Set up site 2 Joiner 4 I 0 0 4 4 II
3 1 3 Remove Trees 2 Laboorer 2 I 0 5 2 7 5
25 1 Ill Order Frames ll 15 Ill 14 15 'l1 14
2 2 3 Site Strip 1 Labourer 3 I 4 4 7 7 ll
4 3 4 R. L. Excavation I Labourer 4 7 7 11 11 ll
22 3 5 Draw Connection 2 Drainlayer 2 7 14 9 16 7
23 5 6 Draw Ex-I'IHI 2 Drainlayer 4 9 16 13 20 7
5 4 7 FDT Lnit 1 3 Laboorer 3 11 11 14 14 ll
24 6 9 I'IHH'IH2 2 Drainlayer 4 13 20 17 24 7
II 7 11 Bwk Unit 1 2 Bricklayer 5 14 14 19 19 0
6 7 8 FDT Unit 2 3 Labourer 3 14 16 17 19 2
12 8 11 Dummy ll il 17 19 17 19 D
7 8 9 FDT Unit 3 3 Labourer 3 17 21 20 24 4
13 11 12 Bwk Unit 2 2 Bricklayer 5 I 19 19 24 24 ll
17 11 14 Srd Slab Unit I 5 Labourer 2 19 25 21 27 6
14 9 12 lltuMiy ll 0 21l 24 20 24 D
8 9 Ill Hardstandi ng 3 Labourer 2 20 27 22 'l1 7
9 Ill 16 Lnload Fra11es 3 Labourer 2 22 'l1 24 31 7
16 Ill 13 Dummy 0 8 22 29 22 'l1 D
15 12 13 Bwk Lnit 3 2 Bricklayer 5 24 24 'l1 29 ll
18 12 14 lluawny 0 0 24 27 24 27 D
19 14 15 Srd Slab Lnit 2 3 Laboorer 2 24 27 26 29 3
20 13 15 Dummy 0 ll 'l1 29 29 29 D
21 15 16 Srd Slab Unit 3 3 Laboorer 2 ,'}!1 29 31 31 0
Ill 16 17 Erect Frames 4 Joiner 5 I 31 31 36 36 8
-------------------------------------------------
"
..j
204
r ""'
SORT ORDER : Latest start, Ear 1i est start
205
All activities asSUIII!d to begin at earliest start The start day is : 0
S(J(T ORDER : Float 1 Latest start
206
All activities assumed to begin at earliest start The start day is : 0
SORT ORDER : Earliest start, Earliest start
207
All activities assumed to begin at latest start The start day is : 0
SORT ORDER : Earliest start, Latest start
-EVENT-:DESCRlPTION :WK 1 :tl< 2 :WK 3 :WK 4 :WK 5 :WK b :WK 7 :WK B :WK 9 :
--------------------------------------------- ----------
1-2 :set up Site :•*** :
1-3 :Re110ve Trees :FFFFF:DD
1-10 :Order Fraliii!S :FFFFF:FFFFF:FFFFD:DDDDD:DDDDD:DDDD
2-3 :site Strip t:tt
3-4 :R. L Excavation : Ht: t
3-5 :Draw Connection : FFF :FFFFD :D
5--b :Draw Ex-MH1 F:FFFFF:FDDDD:
4-7 :FDT Unit 1 : Ht :
b-9 :MH1-MH2 FF:FFFFF:DDDD
7-11 :Bwk Unit 1 t:tttt :
7-B :FDT Unit 2 F:FDDD :
B-9 :FDT Unit 3 FFF:FDDD
11-12 :Bwk Unit 2 t:ttft
11-14 :Brd Slab Unit 1o F:FFFFF ,DD
9-10 :Hardstanding :FFFFF: FFDD :
10-16 :Unload Frames : FFF:FFFFD:D
12-13 :Bwk Unit 3 tltfff :
14-15 :Grd Slab Unit 2: F:FFDD :
1s-1o :Grd Slab Unit 3: •:•
16-17 :Erect Frames : ****:*
----------------------------------------------- -
208
All activities assumed to begin at earliest start The start day is : Ill
B=Bricklayer ; D=Drainlayer ; J=Joiner ; L=Labourer ;
X SCALE : 2 days per line Y SCALE : 1 11AN DAYS per column
:11AN DAYS 2 3 4 5 6
Day: Total : 1234567890123456789012345678901234567890123456789012345678911112345
Ill :a :JJJJllll
2 :4 :JJJJ
4 :2 :LL
6 :4 :ddLL
8 :6 :ddddLL
10 :a :ddddLLLL
12 :1111 :ddddLLLLLL
14 :14 :BBBBddddllllll
16 :12 :BBBBdd 111111
1a :15 :BBBB11111111111
20 :ts :BBBB11 Jll Jlll11
22 :till :BBBB111111
24 :10 :BBBBllllll
26 :4 :BBBB
2a :s :BBLLL
30 :7 :JJJJLLL
32 :a :JJJJJJJJ
34 :a :JJJJJJJJ
TOTAL 150
209
All activities asslllll!d to begin at latest start The start day is : ll
B=Bricklayer ; D=Drainlayer ; J=Joiner ; L=labourer ;
X SCALE : 2 days per 1i ne Y SCALE : 1 !'IAN DAYS per col Wllf1
li1AN DAYS 2 3 4 5 6
Day: Total : 1234567891l12345b78901234567891l1234567B901234567891l1234567891l12345
0 :4 :JJJJ
2 :4 :JJJJ
4 :4 ILL! I
6 :4 lllll
B 12 ILL
10 :4 ILLLL
12 :6 ILLLLLL
14 :a lBBBBdddd
16 :14 :BBBBdddd llllll
18 :tt : BBBBddddlll
211:11 :SBBBddddlll
22 114 :BBBBddddllllll
24 :9 iBBBBlllll
26 :1s :BBBBlllllllllll
28 :14 iBBLLLlllllllll
30 :10 :JJJJLLLlll
32 :a :JJJJJJJJ
34 :a IJJJJJJJJ
TOTAL 151l
210
All activities assumed to begin at latest start The start day is : I!
B=Bricklayer ; D=Drainlayer ; J=Joiner ; L=labourer ;
X SCALE : 2 days per line Y SCALE : 1 I'IAN DAYS per col u111
itiAN DAYS 2 3 4 5 6
Day: Total : 12345b78901234567B'I012345b78901234567B91111234567891l123456789012345
0 :4 :1111
2 ill
4 :2 iLL
6 :2 iLL
a :2 iLL
10 :4 iLLLL
12 :6 iLLLLLL
14 :6 illl111
16 16 :111111
18 :11 :11111111111
21l :11 :11111111111
22 :6 illllll
24 :6 :111111
26 ill
28 :3 iLLL
30 :3 iLLL
32 :111
34 10
TOTAL 72
211
All activities assumed to begin at latest start The start day is : I!
B=Bricklayer ; D=Drainlayer ; J=Joiner ; L=labourer ;
X SCALE : 2 days per line Y SCALE : 1 I'IAN DAYS per col u111
:11AN DAYS 2 3 4 5 6
Day: Total : 12345678901234567890123456789012345678901234567891!123456789012345
----------
lil :0
2 :0
4 :4 :Llll
6 :4 :Llll
8 :2 :LL
11! :4 :LLLL
12 :6 :LLLLLL
14 :0
16 :6 :111111
18 :3 :m
21! :3 :m
22 :6 :mm
24 :5 :mn
26 :u :lllllllllll
28:12 :Llllllllllll
3lil :6 :LLLlll
32 :lil
34 :lil
TOTAL 72
212
All activities assumed to begin at earliest start The start day is : 0
X SCALE : 2 days per line Y SCALE : 200 POUNDS per col um
lf'OUNDS
1.2345678911123
l24b8111246802468024680246802468024b8111246802468024680246802468024680
:00000000~~
Day: Total l1!01Bl0001!01'l000~~000000~0000
0 :500 I
2 :800 I
4 :900 I
6
a
:1100
:1400
*I
10 :1817 f
12 :2350 I
14 :3283 f
16 :4117 t
18 :51511 I
20 :6150 t
22 :6850 t
24 :7B50 I
26 lB250 f
28 :8750 I
30 :mil t
32 :9771! t
34 :10250 t
HlTAL 10250
213
All activities assu11ed to begin at latest start The start day is : 1!1
X SCALE : 2 days per line Y SCALE : 201!1 ~DS per column
IPOUNDS
1234Sb7891!1123
124b81!124b81!124b8024b81!124b81!124b8024b81!124b8024b8024b8024b81!124b8024b80
lil00011111!1!1001110000110001!1~091!11!11!1~1!11!10001!10000001!11!1
Day: Total :l!ll!lil0000000000001!11!11!11!11!11!11!11!11!11!11!11!101!1!1001!101!100001!11!1000001!1
1!1 1301!1 :*
2 1600
4 I 81!10
*
b 11000
*
*
8 : 111!11!1
*
!Ill :1317
*
12 llbse
*
14 122Sill
16 13183
*
18 139Sill
*
21!1 14717
*
22 :Sbse
*
24 lb3SI!I
*
26 17Silllll
*
28 :Bbl!ll!l
*
31!1 19291!1
*
32 19771!1
*
34 : 11!1251!1
*
--------------------
TOTAL 11!12Sill
214
DISK COPIES OF THE CPA PROGRAM DISK REF. CPA (BBC)
OR
DISK REF. CPA (IBM)
Disk copies of the CPA network program for the Details available from Probuild Software, 82
BBC micro or the IBM/PC computers. Details on Tarkington Road, Hazel Grove, Stockport, SK7
how to obtain the disk copies is given below. 4RL, England.
215
Bibliography: Contract planning studies
Armstrong, B. (1981 ). Programming Building Con- Lumsden, P. (1968). The Line of Balance Method,
tracts, Northwood Books, London. Pergamon Press, Oxford.
Barton, P. (1985). Information Systems in Con- Martin, W. R. (1969). Network Planning for Build-
struction, Batsford, London. ing Construction, Heinemann, London.
Brech, E. F. L. (1975). Construction Management National Building Agency (1970). Programming
in Principle and Practice, Longmans, London. House Building by Line of Balance, NBA, Lon-
Cooke, B. (Ed) (1984). Contract Planning and don.
Contractual Procedures, Macmillan, London. Oxley, R. and Poskitt, j. (1986). Management
Cooke, B. and Jepson, W. B. (1979). Cost and Techniques Applied to the Construction Indus-
Financial Control for Construction Firms, Mac- try, 4th edn, Granada, London.
millan, London. Peters, G. (1984). Construction Project Manage-
Chartered Institute of Building (1980). Programmes ment using Small Computers, Architectural Press,
in Construction- a guide to good practice, London
CIOB Publications, London. Pilcher, R. (1976). Principles of Construction
Cormican, D. (1985) Construction Management: Management, McGraw-Hill (UK), Maidenhead.
Planning and Finance, Longmans, London.
216