INDEX
1. DIFFERENT SCENARIOS
2. OBJECTIVES FVSM
3. CURRENT VSM
4. MAIN PROBLEMS
5. WORKLOAD vs CAPACITY
6. NEXT STEPS
1. DIFFERENT SCENARIOS
2. OBJECTIVES FVSM
3. CURRENT VSM
4. MAIN PROBLEMS
PROBLEMS RELATED TO DPM (Planning of DPM vs CAs, Quality of DPM, Lead Time,
Delays)
5. WORKLOAD vs CAPACITY
WORKLOAD Hours/Year per person Yearly working days
1 AC/year 2 AC/year 4 AC/year 6 AC/year 1.920 240
STATION STD REAL STD REAL STD REAL STD REAL Hours (- Abs.)
ST1 7.873 15.299 15.746 30.598 31.492 61.196 47.238 91.794 1.862
ST2 2.651 10.113 5.302 20.226 10.604 40.452 15.906 60.678 Hours (- Abs.-Loss Eff.) Daily effective hours
ST3 890 7.174 1.780 14.348 3.560 28.696 5.340 43.044 1.490 6,21
TOTAL 11.414 32.586 22.828 65.172 45.656 130.344 68.484 195.516 Takt Time 1 AC/Year # Shifts
240 1 for Std. or Real
DAILY HOURS ACCORDING TO TAKT TIME Takt Time 2 AC/Year # Shifts
1 AC/year 2 AC/year 4 AC/year 6 AC/year 120 1 for Std - 2 for Real
STATION STD REAL STD REAL STD REAL STD REAL Takt Time 4 AC/Year # Shifts
ST1 33 64 131 255 525 1.020 1.181 2.295 60 2 for Std - 3 for Real
ST2 11 42 44 169 177 674 398 1.517 Takt Time 6 AC/Year # Shifts
ST3 4 30 15 120 59 478 134 1.076 40 3 for Std - 4 for Real
TOTAL 48 136 190 543 761 2.172 1.712 4.888
PEOPLE NEEDED
1 AC/year 2 AC/year 4 AC/year 6 AC/year
STATION STD REAL STD REAL STD REAL STD REAL
ST1 5 10 11 21 21 41 32 62
ST2 2 7 4 14 7 27 11 41
ST3 1 5 1 10 2 19 4 29
TOTAL 8 22 15 44 31 87 46 131
SAVING = $ 111,162. 06
14 2019/2/27 Preparation FVSM RF Rev.1
TIP FOR HANDBOOK
Create guidance, to get standard perspective between Quality PT.DI (Quality Sealant,
quality painting, quality part) and Quality ADS. The Objective is to reduce recurrent
cost and leadtime production
A lot of Pickup and Sealant and Painting
Rejection Tag about Ship set 2 Rear Fuselage = 160 Insert Operation /
Sealant and = 846 Man Hours /
Painting. = $ 21,996
Target :
Reduce 70% Rejection Tag and Pickup
Different perspective
Saving Cost = $21,996 x 70% = $15,397. 20
with one operator
Cost = Book/ Paper/ Socialization = $ 200
and others about
“what is good Part”
SAVING = $ 15,197. 20
15 2019/2/27 Preparation FVSM RF Rev.1
TIP FOR INDUSTRIAL MEANS
Make Some Systems and Analysis Tools to Maintain Handtools in shopfloor, the
method will be buy or improve the tools. The objective is to reduce leadtime
production.
Improvement Hand Reamer
A lot of Handtools PT.DI has 3 Hand Reamer = 149.04 Hours / $ 3,875. 04
not good to use or Rivet Gun = 497 Hours / $ 12,922.00
lack of quantity in Hand Drill = 200 Hours/ $ 5,200. 00
Rear Fuselage Area Clamp C = 100 Hours / $ 2,600
Kaneho Type A = 298 Hours / $7,750. 08
Ex. Target :
1.Hand Reamer Reduce 50% Man Hours and Leadtime
2.Rivet Gun Saving Cost = $32,347. 12 x 50% = $ 16,173. 56
3.Clamp C Cost = $ 8,628.21 / 3 Years = $ 2,876. 07
4.Kaneho Type A
16 2019/2/27 Preparation FVSM RF Rev.1 SAVING = $ 13,297. 49
TIP FOR INTEGRATED PLANNING
Make communication system (Weekly discussion) between Production Control
Assembly to inform Production Control DPM about priority part. The objective reduce
lead time production and reduce waste waiting process
WORKLOAD
1 AC/year 2 AC/year 4 AC/year 6 AC/year
STATION IMPROVEMENT IMPROVEMENT IMPROVEMENT IMPROVEMENT
ST1 10120.16 20240.32 40480.63 60720.95
ST2 6689.66 13379.33 26758.65 40137.98
ST3 4745.54 9491.08 18982.16 28473.24
PEOPLE NEEDED
1 AC/year 2 AC/year 4 AC/year 6 AC/year
STATION IMPROVEMENT IMPROVEMENT IMPROVEMENT IMPROVEMENT
ST1 7 14 27 41
ST2 4 9 18 27
ST3 3 6 13 19
TOTAL 14 29 58 87
6. NEXT STEPS