Required action to eliminate or control the hazard Personel name involved on the job
N/A Alan Legaspi
Ensure that the roto-z is sealed and secure
Archie Flores
container label for used oil.
Follow the procedure of filter installation and put
Erwin Reveche
mark/tagging
Follow the procedure of filter installation and put
mark/tagging
Ensure that theres no leak before test run
N/A
Signature Steps in completing the job
Conduct 8k PM of compressor unit (VSD)
Change oil
Test run
Erwin Reveche
Steps in completing the job Potential hazard
Contact facilities operations to inform them that we
N/A
are starting the activities.
Incident commander order to shutdown Air Dryer 1 Wrong equipment to be shut
to Facilities Technician down
Remove existing orifice installed and install new bump to adjacent or nearby
orifice component
N/A
N/A
N/A N/A
Slip, bump, and Use proper PPE: Safety hard hat, safety shoes,
stumble and safety glass.
N/A N/A
Slip, bump, and Use proper PPE: Safety hard hat, safety shoes,
stumble and safety glass.
N/A N/A
Slip, trip, Use proper PPE: Safety hard hat, safety shoes,
fall,bump,stumble and safety glass and find a proper position replacing
lectricution the orifice.
Personel name involved on the job Signature
Steps in completing the job Potential hazard
Contact facilities operations to inform them that we
N/A
are starting the activities.
Incident commander order to shutdown Air Dryer 1 Wrong equipment to be shut
to Facilities Technician down
Then close air cooler valve (CC1) (valve tag # 4) Wrong valve manifulation
Close air cooler valve (CC2) (valve tag # 5) Wrong valve manifulation
Close cooling water supply valve (valve tag # 2) Wrong valve manifulation
Close cooling water return valve (valve tag # 3) Wrong valve manifulation
Switch off main panel breaker at EE Room
Wrong breaker should be off
Mechanical Area (BM1-LVSG16-08-ckt # 1)
N/A
N/A
N/A
Signature Steps in completing the job
Contact facilities operations to inform them that we
are starting the activities.
Incident commander order to shutdown Air Dryer 1
to Facilities Technician
N/A N/A
Slip, bump, and Use proper PPE: Safety hard hat, safety shoes,
stumble and safety glass.
N/A N/A
N/A N/A
Personel name involved on the job Signature
Steps in completing the job Potential hazard
Coordinate with operations to transfer operation of Vaccuum
pump to other unit if back-up is available N/A
Put barricade and caution sign on the affected area. Bump other equipment
Shut off PVAC 3 - Quincy Wrong equipment manifulation