INSTALLATION MANUAL
CONTENT:
2.1 INSPECTION 1
2.2 DOCUMENTS 1
3.1 PEDESTAL 2
3.1.1 Erection of the pedestal 2
3.1.2 Dimensional control and tolerances before welding 4
3.1.3 Installation of slip-ring collector 5
3.1.4 Installation of circumferential platform 6
3.1.5 Installation of pedestal on foundation 6
3.1.6 Welding 8
3.3 A-FRAME 14
3.3.1 Installation of mounting crane frame 14
3.3.2 Mounting of compression bar 15
3.3.3 Installation of mounting crane 17
3.3.4 Installation of tilting-back support 17
3.3.5 Installation of platforms and walkways 18
3.3.6 Mounting of A-Frame on slewing column 19
3.4 BOOM 22
No copying or duplication of this document without the permission of Liebherr.
This document has been issued electronically and is valid without signature.
1/2
Item code: 10598372
- Installation Manual Edition: 00
LEGEND
Up, Hoisting
Slowly
Down, Lowering
Attention, Danger!
Attention!
GENERAL
In case of any trouble during crane assembly preparation or assembly itself, please
do not hesitate to contact LIEBHERR-Nenzing, AUSTRIA / EUROPE.
IMPORTANT:
For start-up please apply for engineer at least three weeks in advance.
GENERAL DISCLAIMER
HOWEVER, LIEBHERR SHALL NOT BE RESPONSIBLE AND / OR LIABLE FOR ANY AND
ALL DAMAGES, LOSSES (INCLUDING LIQUIDATED DAMAGES / LOSSES AS WELL AS
CONSEQUENTIAL DAMAGES / LOSSES), CLAIMS, LIABILITIES, DEMANDS, COSTS,
FEES AND EXPENSES WHATSOEVER ARISING OUT OF PERSONAL INJURY,
INCLUDING FATAL INJURY AND DISEASE, TO ANY PERSON AS WELL AS LOSS OF,
LOSS OF USE OR DAMAGE TO ANYONE´S PROPERTY TO THE EXTENT THAT THE
SAME IS CAUSED DUE TO AN IMPROPER PERFORMANCE OF THE ABOVE
MENTIONED PROCEDURE / WORK.
INSTALLATION MANUAL
SECTION 1 :
Unpacking – Lifting –
Handling – Storage
For transport, safety and protection reasons, attachment parts (walkways, mounting cranes,
all type of electrical and electronic equipment) are removed and dismantled from the
primary crane parts and are delivered in separate packages.
In the shipping document, the following information is given for item identification:
All shipping items are grouped in sections and marked in the “Packing List”, with
their position given in the drawing “Delivered Items”.
Steel made items such as walkways, platforms, railings etc. are grouped and palletised for
easy handling.
All electrical, electronic and other sensitive equipment are packed in suitable boxes
according to working instruction “Preservation for Storage and Shipping”, included in
Section 5 of this manual.
If not otherwise specified and agreed in a contract specification, every package is clearly
marked for easy identification. In each package, one fully complete packing list is included
in a waterproofed envelope.
1.2 UNPACKING
Attention shall be paid to package markings, package weight, warning marks and other
standard international signs on the packages. Unpacking is to be done in the storage area
which suits the package size and item nature or in open air according to the environment
atmospherically and weather conditions.
The safe and careful handling, especially during lifting up of the delivered packages, must
be observed.
The crane main component lifting points, (pad eyes) weight of the main items and
SWL of main equipment (required for safe lifting and handling) is shown in the
drawing “Delivered Items”.
Lifting must proceed with equipment (hooks, slings, shackles, turnbuckles etc.) of
corresponding safe working load and using pad eyes as shown in the above
mentioned drawing.
The operator is fully responsible for complete lifting preparation and co-ordination
during lifting operation and handling as well as for supervising and during
operation.
Important:
For any further information, required before or during preparation, do not hesitate
to contact LIEBHERR.
1.4 STORAGE
Storage of the main components of crane and package crates delivered, are to be treated
in different ways:
Sandblasting equipment
Welding or flame-cutting equipment
Burners, open flame equipment
Exhaust gases
Adverse chemicals
The storage area must have an AC current source to enable operation or heating
system. The heating system complies from:
Attention:
If the storage period will exceed 3 month (including time for shipment) there must
be taken specific action regarding the crane system (start of power unit, winches,
motors etc) required. For details contact Liebherr Service Department.
If this measurement will not be taken, this can result in major damages of
components or systems. The complete operation has to be recorded properly.
Check the physical protection (plastic covers, timber covers) and corrosion protection on
weather exposed items and repair or renew it if necessary.
Crates – Packages
All other equipment packed in crates or card-boxes are to be stored in dry, enclosed, fully
sheltered stores/warehouses. Inside the crates/boxes the items are treated by VCI
compounds providing the corrosion protection for a shipping and storage period up to
maximum 12 month.
INSTALLATION MANUAL
SECTION 2 :
Inspection of
“As Delivered Conditions”
2.1 INSPECTION
Notice:
If any parts are missing or damaged, please contact LIEBHERR – Werk Nenzing under
consideration of the following reference data:
customer name
crane type
series number
package and LIEBHERR item number
a short description of the damage occurred if possible documented by help of photos
2.2 DOCUMENTS
INSTALLATION MANUAL
SECTION 3 :
Crane Installation
Instructions
Important:
For all bolted flange connections the following steps must be done prior the installation and
the bolt fastening:
1. Clean both contact surfaces of the flange connection. The connections must be free of
moisture, grease, oil, painting or any dirt.
2. Install the bolt into the hole, install the washer plates and thread the nuts.
3. Bolts must be properly fastened/pre-tensioned by using torque wrench with torque-wrench
tightening moment.
For data and values regarding required pre-tensioning torque refer always to the
mentioned drawings only. Any other value found in other documents or sketches
may not be valid. In case of doubt revert to LIEBHERR.
If not otherwise mentioned in the contract, torque wrench may be, on client request,
supplied by LIEBHERR for extra cost.
If torque wrench is supplied by a client, it must be of an approved and calibrated
type, equipped with an indication scale.
3.1 PEDESTAL
Image 01:
Drawing No.:
2278 995 69 01 000 00X
Image 02:
Image 03:
of adequate capacity!
Image 04:
Image 05:
Image 06:
Image 07:
Image 08:
Image 09:
Drawing No.:
2278 060 17 00 000 00X
2278 061 17 00 000 00X
Image 10:
Image 11:
Image 12:
Image 13:
Image 14:
Image 15:
Image 16:
Image 17:
Image 18:
3.1.6 Welding
Image 19:
Image 20:
For the required hooking arrangements as well as required site crane capacities refer to the
following technical documents:
Image 21:
Image 22:
Image 23:
Image 24:
Image 25:
Image 26:
Image 27:
Image 28:
Image 29:
Image 30:
Image 31:
3.3 A-FRAME
Image 32:
Image 33:
Image 34:
Image 35:
Image 36:
Image 37:
Image 38:
Image 39:
Image 40:
Image 41:
Image 42:
Image 43:
Image 44:
Image 45:
Image 46:
Image 47:
Image 48:
Image 49:
Mounting of A-Frame
according to Drawing No.:
2278 125 01 00 000 00X
Image 50:
Image 51:
3.4 BOOM
The boom as a whole is completely assembled (inclusive walkway, platforms, winches etc),
before it is connected to the slewing platform.
For the completion of the boom assembly also refer to the drawings:
Image 52:
Image 53:
Image 54:
Image 55:
Image 56:
Image 57:
Image 58:
Image 59:
Image 60:
Image 61:
Image 62:
Installation remark:
Pins, bushings and bores
must be cleaned,
dried and shall not be
greased or oiled before
installation !
Image 63:
Image 64:
Image 65:
Image 66:
All adjustments of the limit switches and potentiometers shall be carried out or
checked by a LIEBHERR Engineer.
The crane is usually delivered with dry tanks and piping systems and with equipment
temporary protected for transport.
A) Electrical System
Connect electrical cables from platform/ship main supply to the junction box, located in
the pedestal adapter. Refer to the drawing:
Electric motor
In general, electric motors are ready for the start when the main power is connected. Before
you run the power pack or start-up the crane, the following steps are necessary for electrical
system start-up:
Remove all transport protection from the equipment (the power pack frame is fastened to
the supporting structure by means of bolts as transport safety).
Before the initial start-up of the electric-motor or in case that the electric-motor was out of
service for a longer period, the insulation resistance of motor is to be checked in order to
prevent short circuit damage of rotor and stator due to residual humidity, moisture, oil or
dirt between rotor and stator please contact LIEBHERR Service Department.
When you fill the storage tanks with fuel, observe the appropriate safety
instructions. Fire or explosion may be dangerous and can kill.
To minimise system faults, make sure the fuel system is clean. Use the necessary
filters to prevent ingress of dirt and moisture into the system.
clean the fuel storage tank and fuel filters if necessary. Moisture is not allowed in the
fuel tank or in the pipes.
fill the fuel tank according to “Utility Requirements” included in Section 5 of this
manual.
fill the engine (oil pan and oil filters) according to “Utility Requirements” and “Table of
Lubricants” included in Section 5 of this manual.
fill the cooling system with coolant containing the recommended additives for summer
or winter seasons according to “Utility Requirements” and “Table of Lubricants”
included in Section 5 of this manual. Use a strainer to remove dirt.
C) Hydraulic drive
check and clean hydraulic oil tank if necessary. The tank must be dry and free of
moisture.
fill hydraulic oil tank with hydraulic oil provided. Use a strainer to keep oil free from dirt.
For oil quantities and for oil-types refer to “Utility Requirements” and “Table of Lubricants”
included in Section 5 of this manual.
remove blind plugs at hydraulic gears, check oil level and replace blind plugs with vent
plugs.
D) Lubrication
For information about oil types and quantities please refer to “Utility Requirements” and
“Table of Lubricants” included in Section 5 of this manual.
For start up of the Power Pack please contact LIEBHERR service department.
In order to avoid torsion / twisting of the rope during handling and spooling,
please refer to the attached “Instruction for handling of crane ropes” (see Section
5 of this manual).
Read the instructions prior to the rope reeving carefully!
Image 67:
The reeving of the wire rope shall be carried out according to Drawing No.
2278 700 35 00 000 00X
Image 68:
After completion of the installation the crane shall be checked according to the requirements
specified in the handing over report. The service engineer is responsible for completion of
this document. If not otherwise specified the tests have to be witnessed by the client and
surveyor of the nominated Certifying Authority. The scope of crane test has also to meet the
requirements of the Certifying Authorities rules for lifting appliances.
Service Engineer
Client representative
Surveyor of the Certifying Authority (if applicable)
INSTALLATION MANUAL
SECTION 4 :
Referenced Drawings
PEDESTAL ADAPTER
BS Weld. Constr. 2278 061 17 00 000 00X 993598914
BC Top Section Weld. Constr. Cpl. 2278 060 17 00 000 00X 993598814
Slip Ring Carrier Installation 2278 541 05 00 000 00X 10550150
BS Add-On 2278 551 02 00 000 00X 991421314
All-Around Platform RFK 2276 006 34 00 000 00X 10545380
SLEWING COLUMN
Standard Constr. Unit Instal. 2278 516 04 00 000 00X 10524546
Mounting Material - Standard Constr. Unit 2278 517 04 01 000 00X 10524547
Luffing Winch Cpl. 2276 304 05 01 000 00X 10533414
Drivers Cabin Install. Cpl. 2267 491 12 01 000 00X 10521415
MACHINARY HOUSE
Drive Unit 2267 410 06 00 000 00X 10598437
Central Power Unit Cpl. 1 2267 412 04 00 000 00X 10579451
Central Power Unit Cpl. 2 not in this crane not in this crane
Machinery House Add-On 2276 440 01 02 000 00X 990277514
Railing Cpl 2277 440 01 01 000 00X 10519998
Mounting Material – Machinary House 2277 440 01 02 000 00X 10520082
A-FRAME
Pressure Profile Weld. Constr. Cpl. 2278 126 01 00 000 00X 990288014
Mounting Material A-Frame 2278 125 01 00 000 00X 990288514
Standard Constr. Unit Instal. 2278 516 03 00 000 00X 10520968
Mounting Material Standard Constr. Unit 2278 125 02 00 000 00X 10521682
Mounting Crane Installation – 5 to 2278 543 01 00 000 00X 990289014
Mounting Crane Installation – 0.5 to 2276 543 02 00 000 00X 990817614
BOOM
Gangway Pivot Piece – left 2277 544 05 17 000 00X 10516104
Mounting Material – Pivot Piece - left 2278 544 33 01 000 00X 10576067
Gangway Intermediate Section – 12m 2277 544 05 15 000 00X 10517042
Mounting Material – Interm. Section 12m 2278 544 33 04 000 00X 10594251
Gangway Head Section 2278 544 02 03 000 00X 10516549
Mounting Material – Head Section 2278 544 33 05 000 00X 10594252
Gangway Head Section 2267 544 10 02 000 00X 992935914
Mounting Material – Head Section 2278 544 25 02 000 00X 10595930
Gangway Pivot Piece – right 2277 544 05 18 000 00X 10516105
Mounting Material – Pivot Piece - right 2278 544 33 07 000 00X 10594261
Bolting Pivot 2276 514 01 00 000 00X 990274414
Mounting Material – Pivot Piece 2277 215 01 00 000 00X 990284214
Mounting Material – Boom Sections 2272 235 01 00 000 00X 919933614
ELECTRIC
Outline Power Supply 2278 600 69 00 031 00X 10597929
Search Light Installation – Cabin Platform 2276 528 04 00 000 00X 992032814
Search Light Installation – A-Frame 2278 530 02 00 000 00X 919648014
Search Light Installation – A-Frame 2276 531 10 00 000 00X 10533543
Search Light Installation – Boom Head 2276 529 08 00 000 00X 992937214
Search Light Installation – Boom 2276 531 07 00 000 00X 993820314
Helicopter Lamp Instal. – Aux. Hoist Boom 2276 537 01 01 000 00X 990695314
Helicopter Lamp Instal. – Boom 2276 537 02 01 200 00X 990844514
Helicopter Lamp Instal. – A-Frame 2276 537 01 02 000 00X 990695414
Helicopter Lamp Instal. – A-Frame add. 2276 537 02 02 200 00X 990844714
Wind Transmitter Installation 2265 526 01 00 000 00X 919332214
Camera Equipment – Boom Head 2289 552 03 02 000 00X 994546214
Camera Equipment – Luffing Winch not in this crane not in this crane
Wind Sock Installation not in this crane not in this crane
Fire Extinguisher System not in this crane not in this crane
HYDRAULIC
Diagram Hydraulic 2278 970 28 00 001 00X 11216463
ROPES
Ropes 2278 700 35 00 000 00X 10598584
BALLAST
Ballast RFK not in this crane not in this crane
Notice:
Item numbers i.e. positions in the Packing List corresponding with the positions
indicated in the drawing: Delivered Items 2278 995 69 01 000 00X. The Packing List
can be found in Section 6 of this manual.
INSTALLATION MANUAL
SECTION 5 :
Document Content:
Welding 10225362
INSTALLATION MANUAL
SECTION 6 :
Packing List
6. PACKING LIST
Document Content: