Professional Documents
Culture Documents
Optimize
Heat Exchanger
Cleaning Schedules
Brendan R. O’Donnell
and Bruce A. Barna,
Michigan Technological University
Chris D. Gosling,
UOP LLC
The theory
Consider a single bank of process exchang-
ers, as shown in Figure 1. Assume that the tar-
rate of return (DCFROR). However, this get temperatures for both the hot and cold
method is not applicable in all situations. streams are such that any degradation in ex-
For example, when determining an opti- changer performance results in incremental
mum cleaning schedule for heat exchangers, utility consumption on trim heaters and cool-
one must factor in that a one-time expendi- ers elsewhere in the plant.
ture can lead to both a reduction in expenses The equations associated with this system are:
and a change in the life of the project. This is
also a good example of an optimization where QE–100 = mcCpc(t2 – t1) (1)
expenses vary with time (unsteady state). In
this case, incremental analysis is still re- QE–100 = mhCph(T2 – T1) (2)
quired, but the discounted cash flow analyses
will require the use of the equivalent uniform QE–100 = UA∆Tlm (3)
annual worth (EUAW) technique. This arti-
70
Every 5 yr
or: 60
50
U = U0e–kt (9)
40 Every 10 yr
By fitting a limited amount of operating data to this 30
equation, the required time vs. cost information can be 20
0 1 2 3 4 5 6 7 8 9 10
calculated. This approach can also be used to integrate
the performance over the year to more correctly deter- Time, yr
mine annual costs. In addition to heat-transfer informa-
tion, the following cost data are also needed: ■ Figure 2. U vs. time for various cleaning schedules.
Cold Fluid:
mc = 40,000 lb/h
Cpc = 0.5 Btu/lb•˚F
t1 = 50˚F
t2(Clean) = 550˚F 10
0 1 2 3 4 5 6 7 8 9 10
Exchanger:
UClean = 100 Btu/ft2•h•˚F Time, yr
A = 1,098 ft2
Economics:
MAR = 20% DCF
Tax Rate = 34%
Hot utility cost = $5.00/MMBtu Table 2. Incremental utility increase for k = 0.1 yr–1.
Cold utility cost = $0.50/MMBtu
Operation time = 8,760 stream•h/yr Process Duty, Trim Duty, Incremental Incremental
(100% service factor) QE–100, QE–101, QE–102 Hot Utility, Cold Utility,
Year MM Btu/h MM Btu/h $/yr $/yr
0 10.00 0.00 0 0
Cleaning changes the project life, or 1 9.93 0.07 3,269 327
analysis period, to the number of 2 9.76 0.24 10,415 1,042
years between cleanings. A cash 3 9.59 0.41 18,156 1,816
flow analysis is used to find incre- 4 9.40 0.60 26,489 2,649
mental increases in operating ex- 5 9.19 0.81 35,408 3,541
penses until the year of cleaning. 6 8.97 1.03 44,902 4,490
Cleaning is treated as a year zero 7 8.75 1.25 54,951 5,495
cost for a new analysis period. Dis- 8 8.50 1.50 65,532 6,553
counted cash flow is used to calcu- 9 8.25 1.75 76,615 7,661
late a net present value for the 10 7.99 2.01 88,161 8,816
cleaning and subsequent incremen-
tal operating costs. From the net
present value, an EUAW can be calculated based upon Using this model, we can readily find discrete U val-
the life of the project between cleanings. ues at the end of each year. The degradation of U is con-
Using EUAW allows a direct comparison of results tinuous over time, and the first-order model could be in-
between projects with varying life spans. Plotting EUAW tegrated to determine incremental trim duties and costs
vs. cleaning schedule reveals the maximum annual worth for each year. However, the slow change in U in this ex-
or optimum cleaning schedule. ample indicates that linearizing the curve over a one-year
period is reasonable and that the average value can be
Using the technique used to represent each year. Table 2 presents the solution
We can illustrate the application of this technique by of Eqs. 1–3 and the resulting required duties and energy
looking at a model heat exchanger system. Table 1 summa- costs for a degradation constant of k equal to 0.1 yr–1.
rizes the initial conditions and requirements for this system. To evaluate different cleaning options, we assume that
A sensitivity analysis was conducted to investigate the a cleaning occurs in year zero for all cases and starts a
effect of the fouling rate, represented by the degradation new project life for the analysis. For example, a two-year
constant (k), and the effect of the total cleaning cost over cleaning schedule would have the following cash flows:
the following ranges: k = 0.01, 0.05, 0.1, 0.2; total clean- • Year 0 expenses = 0 + cleaning cost.
ing costs = $5,000, $10,000, $15,000, $20,000. • Year 1 expenses = hot utility + cold utility for aver-
The fouling rate constant is easily calculated from U age decrease in U from Year 0 to Year 1.
vs. time historical operating data (Figure 3). The first- • Year 2 expenses = hot utility + cold utility for aver-
order fouling model fits the data with a slope, which is age decrease in U from Year 1 to Year 2.
the value of k, equal to 0.1 yr–1. A cash flow table, incorporating the marginal tax rate,
-10
EUAW, $1,000
$10,000
-8
$10,000 -15 $15,000
0 1 2 3 4 5 6 7 8 9 10 -30
0 1 2 3 4 5 6 7 8 9 10
Cleaning Interval, yr Cleaning Interval, yr
■ Figure 4. EUAW vs. cleaning interval for k = 0.01 yr–1. ■ Figure 6. EUAW vs. cleaning interval for k = 0.1 yr–1.
0
0 Total Cleaning Costs
Total Cleaning Costs -10 $5,000 $10,000
-4 $5,000
-20 $20,000
EUAW, $1,000
EUAW, $1,000
-8 $10,000 $15,000
-30
$15,000 -40
-12
$20,000 -50
-16
-60
0 1 2 3 4 5 6 7 8 9 10 0 1 2 3 4 5 6 7 8 9 10
■ Figure 5. EUAW vs. cleaning interval for k = 0.05 yr–1. ■ Figure 7. EUAW vs. cleaning interval for k = 0.2 yr–1.
is developed for each cleaning case, and the NPV and The plots in Figures 4–7 can also be used to estimate
EUAW are calculated. This is repeated for cleaning inter- the incremental cost of using a nonoptimal cleaning
vals of one to ten years and all combinations of the two cycle. This is done by comparing annual worth at the op-
sensitivity variables (total cleaning cost and degradation timum cleaning cycle to annual worth at the actual clean-
constant). The results are presented in Figures 4–7. (The ing cycle. For example, consider a process where the
EUAW results are all negative, as expected for a cash degradation constant is k = 0.05 yr–1, incremental utility
flow analysis that has only costs and taxes involved.) costs are similar to the model system, and total cost of
The optimum occurs at the maximum EUAW (mini- cleaning is $5,000 (the upper cleaning cost curve in Fig-
mum cost). As we would anticipate, higher fouling rates ure 5). If the exchanger is cleaned every eight years, the
(degradation constant) lead to shorter optimum cleaning incremental losses due to not cleaning at the optimum
cycles, and higher total cleaning costs (direct cost plus are approximately $5,000/yr.
downtime) lead to longer optimum cleaning cycles.
It is interesting that the optimum cleaning schedules Example
are all relatively short for the range of parameters used in This example illustrates the application of this opti-
this model system. For example, only at the very low k mization technique to a commercial problem where the
values or high cleaning costs are the optimum cleaning solution lies outside the boundaries of the previous
cycles three or more years. This may suggest that current model system. The data (Table 3) are representative of
practices deserve review. actual performance results for a combined feed exchang-
EUMW, $1,000
T1 = 700˚F yr–1 and total
T2(Clean) = 312˚F cleaning costs =
-8
$22,000).
Cold Fluid:
mc = 160,000 lb/h
Cpc = 0.53 Btu/lb•˚F -12
t1 = 250˚F
t2(Clean) = 660˚F
-16
0 5 10 15 20
Exchanger:
UClean = 45 Btu/ft2•h•˚F
Month
U1 = 38 Btu/ft2•h•˚F (6 mo)
U2 = 32 Btu/ft2•h•˚F (12 mo)
U3 = 27 Btu/ft2•h•˚F (18 mo)
U4 = 22 Btu/ft2•h•˚F (24 mo)
A = 15,412 ft2 (4 shells)
Economics:
MAR = 10%
Hot utility cost = $4.25/MMBtu
Cold utility cost = $0.40/MMBtu Closing thoughts
Cleaning costs = $22,000 The optimization techniques illustrated here permit
(labor and materials)
Operation time = 8,760 stream•h/yr
prediction of the optimum cleaning schedule from the
(100% service factor) fouling rate data, incremental utility costs, and cleaning
costs for a given situation. The same optimization tech-
niques could also be applied to a wide variety of opti-
mization problems dealing with expense trade-offs, such
er in a gas-oil hydrotreater. The unit is a 12 million bbl/d as those often found in optimization related to mainte-
hydrotreater processing a 30º API gas-oil. As in the nance and repairs. CEP
yearly basis used previously), so the input parameters, B. A. BARNA is a professor of chemical engineering at Michigan
operation time, MAR, and k are adjusted to reflect a Technological Univ., Houghton, MI (Phone: (906) 487-2569; Fax: (906)
monthly analysis. 487-3213; E-mail: bbarna@mtu.edu). He holds BS and MS degrees in
Equations 1–3 are solved and cash flow tables gener- chemical engineering from Michigan Tech and a PhD in chemical
engineering from New Mexico State Univ. Prior to joining the faculty at
ated for cleaning intervals of 1 to 24 months. The results MTU, he worked as a process engineer for Reynold’s Metals and Exxon,
are presented graphically in Figure 8. The optimum and as a plant engineer and plant manager for Kalsec, Inc. He is a
cleaning schedule is found to be 10 months. registered professional engineer in Michigan. He is a member of AIChE.
As before, we can use the results to examine the im-
C. D. GOSLING is the alkylation, oxygenates, and treating technologies
pact of cleaning at a less-than-the optimum point. Stan- manager in UOP’s FCC, Alkylation, Oxygenates, and Treating Business
dard practice in this service is to clean in conjunction Group, Des Plains, IL (Phone: (847) 375-7759; Fax: (847) 391-2253;
with normal turnarounds at 24 months. The incremental E-mail: cdgoslin@uop.com). He joined UOP after graduating from
cost for a 24-month cleaning interval over the 10-month Michigan Technological Univ. in 1980 with a BS and MS in chemical
engineering. He has had assignments in UOP’s technical service and
optimum is (from Figure 8) approximately $15,000/yr. R&D departments, involving development and commercialization of a
No downtime has been built into the cleaning cost. If number of new technologies and products. Since 1996, he has been
downtime were a component, then the incremental cost responsible for new alkylation technology developments. He is a
for cleaning at a turnaround would have to be corrected registered professional engineer in Michigan.