Professional Documents
Culture Documents
Go r d o n M. Pu g h
Da v i d G. Ra s m u s s e n
not handle this size equipment. The most desirable
means of access enables equipment to be driven into the
INTRODUCTION stoping areas. Ramps can enter the stope by being
driven upward in the vein walls or by being developed in
the vein on top of the fill as the stope advances. This
The two unit operations in cut-and-fill stoping that ramp system not only permits the use of rubber-tired
would benefit most from increased mechanization are equipment in multiple working places but also enables
drilling blastholes and moving broken ore to the ore- its removal for repairs without component breakdown.
passes. Drilling in current practice is done with hand-
held jackleg and stoper drills. Broken ore is commonly
moved from the face to the orepass by a small slusher.
This type of equipment can be easily moved through the
raises.
The orepasses are spaced about 61 m (200 ft) Haulage Drifts and Raises
In the proposed method, as in conventional cut-and- The first development step will be to drive the
fill stoping, sand fill will replace the mined-out ore. By 3 x 3-m (10 x 10-ft) haulage drifts above and below
610
612 UNDERGROUND MINING METHODS HANDBOOK
the stope blocks. The boreholes can be made from short in between these distances depending on ground condi-
footwall crosscuts while the drifts progress. The ore- tions or other factors. In this chapter, the longer length
passes can also be driven from the lower drift through was used for all calculations.
the planned sill pillar. Initial Cuts
Sill Pillar Up Ramps The initial stope cut is advanced in the vein above
The up ramps can be started as their locations are the sill pillar, and because it involves drift-type break-
passed by the haulage drifts. They will crosscut into the ing and mucking, the cut is considered to be develop-
footwall at angles from 2.09 to 2.35 rad (120 to 135°) ment. The orepass raises will be broken into as the cut
with the haulage drift direction. The ramp will curve is advanced to provide short tramming distances. A
back toward the vein at an average gradient of about grizzly will be installed at the raise collar. The raise at
0.2 rad (10%), then steepen to 0.3 rad (17%) on the the end line will be used for ventilation access.
straight segment. In Fig. 4, two plans are shown; one
ramp is 57 m (188 ft) in length and the other 88 m
STOPING
(290 ft). The difference in lengths is due to the curve One of three stoping systems will be used depending
lengths and gradients. Actual design lengths could fall on the individual block’s position within the vein length.
O 5 IO 20 SAND FILL IN FIRST BLOCK
I-------- 1 1------------------I
Fig. 3. Back stoping operations. Metric equivalents: in. X 25.4 — mm; ft X 0.3048 = m; yd X 0.914 4 — m.
613
CUT-AND-FILL STOPING
The ramp is developed on the fill, through to the upper tion this tunnel intersects the drift. The last stope cut
drift by the first stope. The subsequent stope operations can then be filled tight to the crown pillar.
then back fill the former ramps and develop new ones First sand fill is essential to the success of this
along their endlines. The final stope is then worked method. Sand that is as free of slimes as possible should
upward by filling the last ramp without developing a be used for rapid draining and quick setup. To ensure a
new one at its endline. hard traveling surface it may be necessary to add port-
land cement to the upper few inches of fill.
3
First Block
area above the projected ramp line to form a 2.4-m While the first stope is still producing, the up ramp
(3-in.) thick planks is then nailed to the caps. Burlap Fill will be added in much the same manner as it was
covers the underside of this ramp chinked into any open- in the first stope. The portion of the up ramp for the
ings. Fill can then be run into the stope for its full preceding stope below the stope level must be filled
length with care to be taken to see that it fills tightly along with the stope. As the stope progresses upward,
under the ramp decking (Fig. 2). A ramp 14.6 m (48 the utility lines can be removed from the ramp to be
ft) in length is constructed for each 2.4 m (8 ft) of fill filled and added to extend the lines up the near ramp.
The remaining stope cuts will proceed in a similar The final block will not develop a new ramp as did
manner until the crown pillar is reached. The ramp is the former blocks. Because there will be no new ramp,
then turned into the footwall again and driven to the breasting rounds will probably again be used to avoid
elevation of the upper haulage drift. At the sill eleva- trapping the jumbo behind a muck pile. Filling of this
614 UNDERGROUND MINING METHODS HANDBOOK
Minable*
Cost, $
Tonnage
•Excluding sill and crown pillars to give a recovery of 89.4% of reserves in place.
’Operating costs only. Does not include amortization of capital, etc.
block will be simplified as no new ramp deck will need are carried in fill at 63-m (208-ft) intervals; haulage
the footwall at 183-m (600-ft) intervals; the maximum edge of both the productivity and cycle time elements,
ramp gradient is 0.3 rad (17%); the cribbed orepasses for each of the mining methods being considered. Costs
3
Table 2. Summary of First Block Mining Costs
Install chutes
Breast stoping
Stope Ore, $
Build timber ramp
72,827 195,176 2.68
Timber operations
21,865 0.30
Temporary ground
Miscellaneous —
13,650 0.20
(engineering,
68,493 —
Total production
Metric equivalents: ft x 0.3048 = m; st x 0.907 184 7 = t.
UNDERGROUND MINING METHODS HANDBOOK
616
Backstop! ng
200 st per shift per stope is achievable on a continuous basis
1 miner
1 LHD operator
3 per shift
Assume 2 stopes each being worked on 2 shifts per day to give 800 stpd
12 men per day + 4 utility crew (stope preparation, salvage, piping, etc.)
16 men
Breast Stoping
Assume 2 men per stope per shift will produce 100 st (2 rounds per shift) so that 4 stopes worked on 2 shifts per
day basis produce 800 st.
1 LHD operator
24 men
for equipment, fuel, tires, and other expendables are plan. Total costs calculated from dollar-per-foot fig-
-
1976 figures, and equipment hourly operating costs for
each piece of equipment are included at the end of the ures were then expensed over the ore block directly as-
sociated with the development. The development costs
entire cost section. The labor cost used has been fixed do not include shafts, slopes, or other major support
at $10.50 per hr, based on average rates at underground systems, but only the costs incurred for the development
mines in the United States and including 35% markup of the specific tonnage block.
for fringe benefits and 25% for an incentive payment Stoping costs were calculated, using derived unit
The total mining cost, based on these assumptions, preparation, and ground support installation when re-
consists of two parts: development costs, and stoping quired. Selection of proper unit operations was made
costs. Development costs are determined by first creat- for specific stoping cases and their related costs compiled
ing a development plan of drifting, raising, and chutes to give a stoping cost.
or mill holes. Several specific development plans are It should be reemphasized that costs given include
considered for each stoping method. Prior to this, ap- labor, direct operating costs of equipment, and expend-
propriate unit costs were applied to the development ables. These costs have been allocated to the assigned
sl LL P1LLAR -
CUT-AND-FILL STOPING 617
tonnage for the example stoping block. Equipment capi- ried in the fill. Bored or driven raises can be located in
talization and depreciation have not been included. the footwall near the switchback stations to serve as ore-
The stope productivity measured in tons per miner passes. Other convenient locations for these orepasses
shift will depend on the blasting technique employed. could be intersected by short crosscuts.
The first and the final blocks require breast stoping and Irregular endlines and raking ore shoots can be
for this method 30.2 t (33.3 st) per miner shift was es- worked by locating the switchback stations to conform
timated to be the productivity. The intermediate or sub- with the endlines. The orepasses would be the limiting
sequent blocks are back stoped to produce about 45 t factor.
This ramp method of cut-and-fill stoping will be best Any innovation or change in a stoping system will
suited for very long ore shoots in veins or continuous affect the total mine system. There will be improvements
beds. Any number of the subsequent blocks may be to certain facets but there are also some limitations
This highly mechanized ramp system will show sig- Safety: Safer working conditions with less manual
nificant improvements over conventional practices in labor will result from the following; jumbo drill opera-
productivity, operating costs, and safety. tors will be back from the face under supported ground
or possibly under a canopy; danger from slusher cables
will be removed; material handling will be with LHD
Productivity: This will be increased in the following units or underground trucks in place of man handling;
operations: mucking of broken ore, drilling blastholes personnel access will be by the ramp instead of the
in stopes, handling stoping supplies, installing utility raises; and ventilation through the stope will be superior
lines, ventilating stopes, and hauling ore from stopes. as all dust and gases should exhaust away from the
working area.
be filled as mining progresses upward. Because one Several factors may limit the application of this cut-
ramp will be above the other, orepasses cannot be car- and-fill stoping system: the long stope lengths must be
applied to the same conditions. The typical application
capable of standing open without extensive ground sup-
port; stope fills will require more time and larger ca- model as described previously was used for evaluation
pacity equipment than the smaller pours of the conven- of both the new and the old methods. This model is
tional method; capital investment in equipment will be similar to many narrow vein mining operations now or
50% higher than for the current method (see Table 9); formerly in production.
the method cannot be as selective in mining discontin-
uous veins as can timbered methods; and highly faulted
or irregular veins would be difficult to follow. Comparisons were made in the subjects of devel-
opment, stoping, equipment and manpower require-
ments, and an economic evaluation analysis known as
COMPARISONS BETWEEN PROPOSED AND ECONEVAL was made by computer for each case.
A full evaluation of a new mining method can be The mine development periods, to gain full stope
made by comparing it with contemporary method production, are of the same duration. It is assumed that
= 92,029 st $297,848
@ $71.52 per ft Short tons *ore
= $20,169
4-compartment raise
= $7,902 developed
Chute fronts 2 @$3,200
7 x 7-ft bald raise 191 ft
= $6,400 = 86,262 st $161,664
Subsequent Block
@ $82.45 per ft
= $15,752
Short tons ore
Total development cost
developed
= 68,493 st $6,185
= $71,691
Short tons ore developed in
block 300 x 200 x 10 ft x Final Block
162
= 48,600 st
Short tons ore
2000
developed
Total development
Cost per short ton ore $465,697
developed = $1.48
cost
$1.89
Cost per short ton
ore developed
Total Total
$137,400 188,880
2,800 87,240
3rd Year 3rd Year
systems start stope development by driving three 3 x 3-m the ramp method to be 28.6% higher than conventional.
(10 x 10-ft) haulage drifts in ore. EQUIPMENT AND MANPOWER REQUIREMENTS
Stoping
Major equipment prices are tabulated in Table 7 to
give a comparison. This equipment would cost approxi-
Stoping in the conventional system will begin at mately $593,000 over three years for the conventional
45 t/d (50 stpd) about the fifth month after the start method. The equipment for the highly mechanized
of the third year (months begin at the start of the third method would cost approximately $900,000 over a two-
year). Production will then increase by 45 t/d (50 stpd) year period. To start up the highly mechanized system
per month until the 24th month when 20 stopes will be would, therefore, cost approximately 50% more than
available to give continuous production of 725 t/d (800 the conventional method. This is to be expected as ex-
stpd). Twenty-five percent of the stopes are assumed pensive, but more efficient, equipment would be used in
to be out of production for fill or development at all place of cheaper but less efficient equipment.
times (Fig. 6). Development ore could bring total mine
production up to 725 t/d (800 stpd) as early as the
eighth month, but this production would not be main- Manpower requirements for both the conventional
tained. and highly mechanized methods are estimated and com-
pared in Tables 8, 9, and 10. Table 8 shows 29 salaried
employees for the conventional and 22 for the highly
Stoping in the highly mechanized cut-and-fill method mechanized method. Fewer shift foremen will be re-
would begin about the eighth month after the start of quired to supervise stoping, as well as fewer support
the third year and continue at 363 t/d (400 stpd) to the personnel. Table 9 shows 136 hourly employees for the
26th month when it would increase to the full 725 t/d conventional and 85 for the highly mechanized method.
(800 stpd). Four stopes in full production will actually The greatest reduction in labor is in the stope mining.
produce sufficiently more than 725 t/d (800 stpd) so as Total personnel are compared in Table 10. Labor cost
to make up for any downtime for sand fills. Develop- per ton is $18.01 for the conventional method and
ment ore, again, could bring total mine production up to $11.82 for the highly mechanized method for a reduc-
725 t/d (800 stpd) in the eighth or ninth month. Ore tion of 34.4%. Productivity is 4.4 t (4.85 st) per man-
from the haulage drifts would be intermittent after the shift for the conventional method and 6.78 t (7.48 st)
12th month (see Fig. 7). for the highly mechanized. Tons per total manshift will
therefore be increased by 54.2% if the highly mecha-
nized method is used.
The conventional stoping system could come into
production earlier than the new ramp method; however,
considerably more miners would be required. These ECONOMIC EVALUATION ANALYSIS
miners would need to be highly skilled to accomplish
the development work required.
The comparison of the two cut-and-fill methods was
carried further by applying the costs and productivities
In the highly mechanized system, the miners that to the computerized evaluation program, ECONEVAL.
drove the three haulage drifts could phase into the stope This program was developed by the Office of Coal Re-
development work and then into the actual stoping. The
net effect would be reduced personnel requirements.
620 UNDERGROUND MINING METHODS HANDBOOK
Salaried Personnel
Highly
Conventional
Mechanized
Method
Method
1
Maintenance superintendent 25,000 1 25,000 1 25,000
Hourly Personnel
S Total cost
t
Job Classification o @ $10.50 per hr* x
p 1920 hr per year
e
Electrician m
i
n
Welder e
r
s
Warehouseman
F
Lampman i
l
l
Janitor
c
r
Laborer e
w
Total surface T
o
t
Surface shaftmen a
l
Hoistmen d
e
Underground shaftmen v
e
l
Grizzly tender o
p
m
e
Motorman n
t
Track maintenance m
i
n
Utility men e
r
Laborers s
Conventional* Highly
Mechanized*
Method
Method
4
4
3
3
3 2
2 2
1 1
4 4
17 16
4 4
4 4
6 6
2 2
8 8
3
3
4
4
4
4
35
35
8
8
8
2
16
10
64
18
4
6
68
24
136
85
$2,741,760
‘ Based on 2 shifts per day, 2 operating levels, 8 stopes per level, and 2 miners per stope crew.
r Based on 2 shifts per day, 3 stoping areas, and 3 men per stoping area.
♦Includes burden.
CUT-AND-FILL STOPING 621
search to provide a reliable standardized estimate of the Table 11. It is shown that the average operating cost for
rate of return on investment. It is this figure that will the conventional method is $19.63 per ton, whereas for
be of paramount interest to any investor or loan the highly mechanized method it is $13.72 per ton. The
operating cost for the mechanized method will
then be
institution.
Input data used in the analysis was specified in the 70% of that for the conventional method. This saving
application model described earlier in the chapter. Other of 30% in operating cost is very significant when one
costs were assumed to be similar to costs obtained from realizes that it comes totally from the increase in stoping
working mines. These assumed costs are equal for both efficiency. The other unit operations and costs are held
and depreciation rates were applied equally. The commodity value of $40.00 per ton of ore pro-
Estimates of operating costs for each year were duced was first applied to the ECONEVAL program.
needed as input data. These costs were developed in The results were that the conventional method of stoping
Total Personnel
Method Method
Salaried
Hourly 29 $716,850 22 $556,200
2,741,760 85 1,713.600
136
Total
$3,458,610 107 $2,269,800
165
s Short tons
h per
Manshifts per year o manshift
r
t
Annual production
t •Metric
o equivalent: st x
n 0.907 184 7 = t.
Labor cost per
39,600 25,680
$18.01 $11.82
4.85 7.48
Table 11. Operating Costs Per Year for Conventional Cut-and-Fill vs Mechanized Cut-and-FIII
Year 1,$ Year 2, $ Year 3, $ Year 4, $ Year 5-17, $ Year 1, $ Year 2, $ Year 3, $ Years 4-17, $
Pumping 0 0 0 0
(0.60) (0.60) (0.60) (0.60) (0.60)
Miscellaneous
surface equipment 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000 12,000
0 0)
Surface lagoon 0 0 84,288 (0.60) 99,912 ( .
6 115,200
(0.60) 0 0 93,660 115,20
0
(0.60)
(0.60
)
Miscellaneous
20,000 20,000 35,000 35,000 50,000 20,000 20,000 35,000 50,000
operating expense
(0.25) (0.21) (0.26) (0.22) (0.26)
-10.00
would not only yield no profit but would never return creasing production and decreasing costs. The key to its
the equity in investment. Because there can be no nega- success is the use of the efficient mobile equipment sug-
tive value for a rate of return, the program was rerun gested. To use less productive equipment even for this
for the two methods using a commodity value of $50.00 unique stoping system would fail to produce the results
per ton. For conventional cut-and-fill stoping, the equity derived in this study.
INVESTMENT
RETURN ON
For highly mechanized cut-and-fill stoping, the equity
RATE OF
rate of return is 18.48%, the total investment rate of
*
return is 18.48%, and the equity payback period is
6.26 years.
x
then for the conventional method, the value of the com- VARIANCE COMMOOiTY VALUE
APPENDIX
Cost of trackless 10 x 10-ft* drift at 7.6 ft advance per round = $71.36 per ft
Track installation
$101.13 per ft
Ventilation Raises
97,763.20
ANFO,
4.8 lb x
Tonnage produced = 8748 st* 7.4 cu yd
x $0.15 x
2
Development tonnage cost = $11.18 per st
support
brow, 2
Cost per short ton prorated over block tonnage = $1.06 men for 1
•Metric equivalents: ft x 0.3048 = m; st x 0.907 184 7 = t. shift @
$10.50
per hr
supplies,
4 mats @
$2.70
each and
Table 15. Estimated Conditions and Costs for Driving a
15 bolts
5 x 5 ft Raise for 14-ft Height @ $2.64
each
Conditions stoper,
bits and
steel, 650
ft @
Drill and blast two 8-ft* rounds to break 14 ft total $0.15 per
ft
Costs
Mucking
costs
Drilling and blasting costs
7.4 cu yd
drill and blast 2 men, 2 shifts @ $10.50 per hr x2=
14.8 cu
yd x 1.2
blasting supplies, 60 caps @ $1.21 each swell
factor =
3
17.76;
10.80
39.60
97.50
$735.16
$336.00
72.60
10.66
168.00
use 18 loose cu yd
= 10 scooptram loads
with a 2-cu yd bucket at 90% fill factor
$53.02
Total Costs
Mucking 53.02
$788.18
Raise cost = 6 x $788.18 each = $4,729.08 or $0.05 per st of stope block tonnage
Chutes
5 x $3,200 = $16,000 = $0.17 per st
Total raise cost prorated over stope block tonnage = $0.22 per st
CUT-AND-FILL STOPING
Using computerized simulated drilling program it was found that one 8-ft* breast
round could be taken by 2 men in 32.4 + 42 min * 75 min, and would cost $1.31
per st *
Temporary support
$21.12
13.00
drilling material and supply costs,
50 ft @ $0.26 per ft
$34.12
$0.64 per st
60 min
2 men could
3.5 cu yd x 90% fill factor x 1,2 swell factor x 75% availability take 2
= 1.97 cu yd per cycle, or 4.41 st per cycle rounds per
6yrhr shift
men x v/2 hr x
3.0 min haul (maximum 200 ft, 150 fpm * average speed)
$10.50 per hr
cost per
4.0 min total haul cycle short ton =
$2.68
at 50 min per hr = 12.5 cycles = 55.13 stph capacity
•Metric
Assume 1 hr mucking time equivalents: ft x
0.3048 = m; fpm x
0.005 08 - m/s; cu
yd x 0.764 554 9 =
m;
Totals 1
T
able 17. Costs to Build Timber Ramp
Timber Requirements
12 10 x 10 in. by 10 ft =1000bdft*
2400 bd ft
= $0.30 per st
Other Supplies
Time Analysis
2 hr drill
2 hr hang 10 x 10's
Totals
Total cost of ramp floor = 1051.17 x $20.80 = $21,865 = $0.30 per st*
•Metric equivalents: in. x 25.4 = mm; ft x 0.3048 = m; bd ft x 0.002 359 737 = m - st x
0.907 1 84 7 = t.
626 UNDERGROUND MINING METHODS HANDBOOK
Labor Costs
Consider 2 men
1.00 hr
Material Costs
Cost per short
6 x 6-in. * cribbing by 5 ft * long x 4 sides =120 bdft * per ft of height ton prorated
6 cribs x 8 ft high = 48 ft of crib or 5760 bdft over stoped
tonnage =
3 $0.27
Use $200 per 1000 bd ft to allow for cutting = $1,152
Cost of fill has
Add 10% for nails, etc. = 115 been
calculated
previously at
Use 3 rolls of brattice cloth @ $60.00 each = 180 $1.25 per st’
$1,447 •Metric
equivalents: in. x
25.4 = mm; ft x
0.3048 = m; bd ft
x 0.002 359 737 =
Supplies Transport m ; st x 0.907 184
7 = t.
1 trip per crib + 30 min per trip = 3 hr. Allow 4 hr for contingencies
4 hr x $28.10 (ownership and operating costs of LHD) = $112.40
T
a
b
Total Cost l
e
Haulage Drift
Orepass Raises
Vent Raise
$30.50 per st
$0.03 per st
$0.13 per st
(290-ft ramp and 515 ft initial stoping cut) x $71.36 per ft = $57,444.80
Orepass Chutes
$0.24 per st
627
CUT-AND-FILL STOPING
st x 0.907 184 7 = t.
Use a 3V2-cu yd* LHD. Use the same time cycle as in first
block which produces 32.75 cu yd per 60 min hour =
77.22 stph
3
Because 200 st per shift is required, muck can be removed
in 2.59-50 min hour at a machine availability of 86%
Assume 3 shift hr are used to muck out 200 st, 3V2-cu yd
LHD @ $23.03 operating cost for 3 hr ($60.09) = $0.35
per st
Temporary Support
Cribbed Raises
Fill
Assume 10-ft* thick vein and 12.35 cu ft* per short ton *
Miscellaneous Costs
1090 ft- -4
Stope Tonnage
162
Ramp Around Crown Pillar
Raises = 5x5x12ftx6x = 146St
235 ft* @ $71.36 per ft = $16,769 2000
Development = 19,202 st
72,827 st = $0.23 per st
588 ft----------
X
■586 ft
Stope Tonnage
3
Volume of stoped block 588 x 162 10 ft* = 952,560 cu ft* or 77,157 st*
Development Tonnage
Stope Tonnage
1040 x 162
Volume of ore in block
------ - -------x 10
—----------------------KMOfT
= 842,400 cu ft*
Stoping
= 68,243 st*
Development Tonnage
Volume of development ore
= 259 st
Development
= 68,501 st
Total tonnage
previous block
CUT-AND-FILL STOPING
APPENDIX B.
Cost Summary
This
Yards
shows
broken
a per
representative
blast run for13.95 yd
breasting using
jacklegs to develop drilling and blasting times and costs Underground Percussive
Totals
for a particular run. Blasting Drilling
2.67 Per ton
1.24
1.42
Performance Summary
3.89 Per cu yd
2.07 1.81
Footage advanced per blast 5.98 ft 4.84 4.23 9.07 Per ft of advance
Working Variables
(Input + Calculated)
1.25
1.00
2. Weight of solid rock, lb per cu ft
1.38
Drilling Equipment Description
Mine Design p
e
r
1. Number of drills drilling per face b
i
t
2. Number of drillers working per face
4
3. Number of driller helpers working per face .
J
a
4. Average number of headings c
k
l
5. Percent of foreman’s time allocated to each face e
g
d
6. Number of powder loaders r
i
l
7. Actual, or measured drilling rate over an 8-hr shift, ipm l
c
Cost Variables o
s
t
1. Labor rate—driller, incl. fringe, $ per hr c
o
m
2. Labor rate—driller’s helper, incl. fringe, $ per hr p
l
e
t
e, $
1.75
5. Jumbo cost complete, $
2.00
6. Drifter drill cost, $
0.95
7. Foreman’s wage rate, incl. fringe, $ per hr
61.25
8. Labor rate—blaster, incl. fringe, $ per hr
0.0
9. ANFO cost, $ per lb
1.00
0.0
1.00
0.0
1.00
12.00
10.50
10.50
7.50
0.00
0.00
0.00
0.00
10.50
0.00
1.25
UNDERGROUND MINING METHODS HANDBOOK
630
Output Variables
. Penetration rate further modified for the effect of bit diameter 0.0
4. “Direct” drill (or jumbo) write-off cost per foot drilled, $ per ft 0.0
“Direct” drill maintenance cost per foot drilled, $ per ft 0.04
“Direct” drilling supervision per foot drilled, $ per ft s 0.0
5. a
6.
1.
R
Blasting Results and Costs es
ul
tant powder factor, in lb of explosive per tons actually broken 2.
Resultant per cubic yard powder factor, in lb of explosive per
2.44
cu yd of material broken
3. Blasting labor (i.e., powdering the holes) cost per blast 3.56
before % pull)
5. Footage drilled per shift per face, in ft per shift per heading
9. Actual (or resultant) depth of drift advance per blast, in ft per blast
0.17 rir,rt
1.00
42.00
-J tMn
78.00
20.
!7l K w IQ
273.00
13.
78.00
0.
60.00
6.50
5.08
Ui
00 -
J