HOKCHI ONSHORE EPCI HOK-ON-24-H-DS-0102


HOKCHI ENERGY S.A. DE C.V. Hokchi Document Reference:
(-)
Date: 10/29/2018

DATA SHEET

EXPORT OIL PIPELINE PIG LAUNCHER V-


2601

DOCUMENT No HOK-ON-24-H-DS-0102

AVANZIA
REV. DATE DESCRIPTION
BY CHECKED APPROVED

1 10/29/2018 FOR PURCHASE SCR JMV RMR

0 09/26/2018 FOR PURCHASE SCR JMV RMR

Information contained in this document is the work product of Avanzia and embodies confidential and proprietary information of Avanzia and / or its client. This document and
all information herein are confidential, and may not be used, reproduced or distributed without prior authorization of Avanzia or Hokchi Energy S. A. de C.V. Avanzia
disclaims any and all liabilities for any changes or modifications to this document.
1

SHEET: 2 OF 3
EXPORT OIL PIPELINE PIG LAUNCHER V-2601
CLIENT: HOKCHI ENERGY S.A. DE C.V. LOCATION.: PARAISO, TABASCO, MÉXICO DATA SHEET No. HOK-ON-24-H-DS-0102
EXPORT OIL PIPELINE PIG LAUNCHER
1 Manufacturer's name:
2 Description: EXPORT OIL PIPELINE PIG LAUNCHER Identification: V-2601 Type:Horizontal (Note 9) Size: 8" X 12" 600# * 0

3 OPERATING CONDITIONS INSTRUMENTS (NOTE13) 0

4 Pressure (kg / cm²): Normal 70.0 Maximum 85.0 Security valve: 26-PSV-236, Size 1''Ø-600# RF x 2''Ø-150# RF (Note 11) 0
5 Temperature (° C): Min 59 Maximum 85 Pressure Indicators and transmite: 26-PI-225 , 26-PI-227 and 26-PZT-226

6 Managed fluid: crude oil Pig Pass Indicator: 26-XI-228


CP(corrosion probe), CC(corrosion coupon), CS3(sample testing with ball valve
Others 3/4"),flow trasmiter 2".
One Nozzle , 8"Ø-600# RF with blinde flage

7 DESIGN DATA (NOTE 2) VALVES(NOTE 6,13)

8 Pressure man. (kg / cm² man): 85.0 Barrel blocking: (two)/(one) Full step ball,8"Ø - 600# RF / and ball valve 1" (NOTE 5) 0
Pressure indicator and
Temperature (° C): 85 NOTE 13 0
9 transmiter:
10 Code: ASME B31.4 / ASME B31.3 ASME Sec. VIII, Div. 1 Before: psv (two)/(two) Full step ball,2"Ø- 600# RF and ball valve 3/4" 0
11 Permissible corrosion: 3 (mm) After: psv (one) Full step ball,2"Ø- 600# RF

12 MAIN CHARACTERISTICS (NOTES 9 AND 13) Barrel vent: (one)/(one) Full step ball,2"Ø and globe valve 2''Ø- 600# RF

13 Ø pipeline: 8" kicking/receiver Line Valve (two)/(one) Full step ball 3",Ø-600# RF and ball valve 1" 0
14 Nominal Diameter (BARREL) (in.): 12" (one)/(one) Bypass, full step valve ball 2"Ø- 600# RFØ and globe valve 2''Ø 0
15 Class: 600# RF Barrel drainage: (two) Full step ball, 2"Ø 600RF

Material: ISO 3183L360 (X52) Blocking process flow line: (one)/(one)/(one) Globe 8"Ø- 600# RF / ball valve 2"/ globe valve2" (NOTE 5) 0
16

Pig Station: Igualation line: (two)/(one) Ball ,2"Ø- 600# RF and globe valve 2"
17

Drain before the barrel: (one)/(one) Ball ,1"Ø- 600# RF and globe valve 2"
18

19 Orientation: Purge conection: (one)/(one) Globe ,2"Ø- 600# RF and check valve 2"

20 Type of cover: Note 4 ACCESSORIES 0

21 Rings and Insulation Supports: Yes, for process line

22 Dimensions of the trap: * (Note 2) Isolation: Yes, for Heat Conservation

23 Barrel D.E .: 12" Basket for the Pig: No 0


24 Barrel Wall Thickness (in.): SCH 40, 0.406" MIN. Special Tee with Slots: Yes 0
25 Barrel reduction (in.): 12" X 8" * 90 ° elbows (long radius) Yes 0
26 Thickness of barrel reduction (in.): SCH 40, 0.406" MIN. Skid Drain Tray: Yes (Note 10) 0
27 Barrel Length: * Operation and Maintenance Platforms: Yes (if necessary)

28 Maximum dimensions of the package (m): * Structural skid (with lifting ears) Yes

29 CONSTRUCTION MATERIALS

30 Pig Characteristics Barrel Body: ISO 3183L360 (X52) 0

31 Type: Cleaning Pigs / Instrumented Pig Quick Openening SA-350-LF2/A694-F52 0


32 Largo: * Nozzle neck: ISO 3183L360 (X52) (ASME B31.4) 0
33 Nozzle Flanges: 694 GR.F52/A-105 (ASME B31.3) 0

34 FINISH Valves: A216 GR. WCB / A 105 (NOTE 5,12) 0

35 Paint Specification: Note 8 Auxiliary Pipes ISO 3183L360 (X52) (ASME B31.4) 0
36 Specification Insulation / barriers: - Reinforcement: ISO 3183L360 (X52)

37 Skid and Supports ASTM A36

38 Packaging: Spirometalic SS-316 filled with graphite 0


39 Screws/nuts: ASTM A193 Gr B7 / ASTM A194 Gr 2H (Note 14) 0
40 Skid floors and platforms: ASTM A36

41 NOTES:
42 1.(*) Asterisk Means information to be confirmed or provided by the SUPPLIER.

2.The design and construction of the barrel body will be in accordance with the ASME B31.8 and ASME Section VIII DIV.1 with stamping for quick opening closure.The piping to be desinged according ASME B31.8 and ASME B31.3 0
43

44 3.The dimensions must be those neessary to run the pig instrumented 0


45 4.Launcher quick opening closure to be provided with safety latch to avoid door opening until the pressure has been depleted. 0
46 5.The valves for sectioning the trap (barrel and process) must be full pass. 0
47 6.They must comply with the API 6D latest edition. 0
48 7.Intrussive type pig signaller 0
49 8.Paint specification according to 0769SIC-100-SP-3600-004 0
50 9.Pig Launcher should be mounted horizontally on a structural skid designed to withstand loads by lifting and own weight. It must have accesses and platforms 0
51 for operation and maitenance of valves and with spill colector tray. 0
52 10.The skid and tray of the trap should prevent spilling products due to the opening of the lid of the barrel. 0
53 11.The size of the PSV must be ratified by the contractor in its Technical Proposal. 0
54 12.The provider must offer the letter or guarantee. 0
13.See reference drawing 076951C-200-PID-0026-003-C. Quote the package with the intrumentation shown within the limits. The instrumentation must be comply with the document 076951C-000 SP-1514-001 General Instrument Specification
55 for Package Equuipment 0

0
56 14.Stud bolts, screws, nuts and washers used in piping and mechanical systems shall be hot spun zinc galvanized. The hot spun zinc galvanizing shall be done in accordance ASTM A153 and ASTM F2329.

57 15.The supplier must indicate area for mantenence and operation 0


1

SHEET: 3 OF 3
EXPORT OIL PIPELINE PIG LAUNCHER V-2601
CLIENT: HOKCHI ENERGY S.A. DE C.V. LOCATION.: PARAISO, TABASCO, MÉXICO DATA SHEET No. HOK-ON-24-H-DS-0102
EXPORT OIL PIPELINE PIG LAUNCHER
1 Brand No. Size Cedula Rating Type Proj. Service

2 N1 1 8" * 600# BISEL * Crude oil inlet 0


3 N2 1 8" * 600# RF * Crude oil outlet 0
4 N3 1 2" * 150# RF * Exhaust outlet

5 N4 2 2" * 150# RF * Drain of barrel 0

6 N5 1 2" * 150# RF * Drain of skid

9
ATTACHED P&ID 076951C-200-PID-0026-003 Rev C 0
10

11

12

13

14

15

16

17

18

19

20

21

23

24
25

26

27

28

29
30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45
46

47 NOTES:

48 1.- Drawing for information only

49 2.- Launcher quick opening closure to be provided wih safety latch to avoid door opening until the pressure has been depleted

50 3.- Purge connection

51 4.- Cp orientation to be at 12 o'clock orientation on horizontal pipe-run. minimum clearance of 2m above the pipe is required for retrieving

52 of probe during maintenance.


53 5.- NA

54 6.- NA

55 7.- Valve I.D. to be at least equal to pipe I.D.

56 8.- Emergency stop system. This system is not part of package scope

57 9.- The following site conditions will be considered; corrosive marine environment:
58 - Minimum Temperature: 14 °C - Maximum Relative Wet: 96% 0
59 - Average Temperature: 27.1 °C - Minimum Relative Wet: 44% 0
60 - Maximum Temperature: 40.2 °C - Atmosphere pressure: 1.013 kg/cm2 abs 0
61 10.- Quote the package with the intrumentation shown within the limits (Pig receiver V-2602)
- Atmosphere pressure:
62 11.- Consider preparation for three injection nipples