Professional Documents
Culture Documents
Abstract – The converter in a large variable- that fault-tolerance is introduced into these
speed wind turbine has amongst the highest turbines.
failure rate of any component, but in an onshore Generally the converter set up within any fully
setting it has not received much attention as rated wind turbine will include a series of parallel
repairs can be carried out quickly and with switching modules which will house the converter
minimal equipment. In an offshore wind farm, components such as the IGBTs, gate drives and
access is by boat or helicopter, which is capacitors. This will typically be connected to a
significantly more expensive and may be general system controller and cooled via an air or
restricted by high winds or wave heights. This liquid cooling system, which will depend on the
means that converter failures offshore will cost turbine manufacturer and the location of the
more to fix, and potentially also lead to a greater turbine.
downtime, leading to loss of revenue. Converters To include fault-tolerance a local controller
can be designed to be modular and to feature will be implemented alongside the converter
fault-tolerance, where the turbine can continue switching modules; this will allow the turbine to
running at reduced power after a fault in one operate under certain faults at a lower rating. Fault-
converter module, or fully redundant, in which tolerance will come with a cost however this paper
the turbine can continue at full power. The investigates the costs and benefits associated with
purpose of this project is to investigate the implementing fault tolerance in several offshore
effects of using such converters on the turbine wind turbines of different ratings.
downtime, maintenance cost and lost revenue. Another method to reduce downtimes, which
has already been implemented in wind turbines, is
Index Terms - Converters, Cost benefit analysis, the concept of converter redundancy [2]. In a
Fault tolerance, Redundancy, Reliability redundant set up there will be one or more
analysis additional converters which are not operating and
will only begin to operate should one of the already
I. INTRODUCTION operational converters fail.
model was built using the configuration of the 0.7 Series System
Siemens equivalent and altered slightly to introduce System with 2 parallel branches
System with 3 parallel branches
fault tolerance. As with the 3.6MW turbine, the 0.6
System with 4 parallel branches
Reliability (Failures/Turbine)
50,000 € 15
Number of Parallel Branches
Overall Cost Benefit
40,000 € 12
30,000 € 9
20,000 € 6
10,000 € 3
0€ 0
Fault-Tolerance Fault-Tolerance with Redundancy
Considering the reliability of any given converter [1] Forewind Annual Review. June 2014 Accessed
set up within a wind turbine it is evident that as the on: 24/07/2014 Accessed from:
number of parallel branches is increased the http://www.forewind.co.uk/uploads/FOR_final%20
observed increase in system reliability is
Annual%20Review_2014.pdf
diminishing, for example, after 4 or 5 branches are
reached in the case of the 1.5MW model. This is
[2] F. Blaabjerg, M. Liserre, K. Ma: “Power
interesting as a 1.5MW turbine would typically
require at least 3 branches to operate at rated Electronics Converters for Wind Turbine Systems”,
power, and could not operate with any less than 2 IEEE Transactions on industry applications. Vol.
branches. Hence it can be deduced that in any wind 48, No. 2 March/April 2012
turbine configuration there will be a point at which
there will be a greater cost than benefit. From the [3] R.-D. Klug, A. Mertens: “Reliability of
results of the reliability calculations and cost Megawatt Drive Concepts”, IEEE 2003
benefit analysis it is the maximum number of
redundant branches appears to be 4/3 of the number [4] K. Fischer, T. Stalin, H. Ramsberg, T. Tjiringer,
of branches required for rated operation. As with J. Wenske, R. Karlsson: “Investigation of converter
any more branches there would be a cost incurred failure in wind turbines”, Nov 2012, pg. 29
whislt any fewer branches would be somehwat
illogical, including one branch of redundancy in a
[5] R. Billinton, A. N. Allan: “Reliability
6MW wind turbine which has 12 branches either
side would incur a much smaller cost but would Evaluation of Engineering Systems”, 2nd Ed, 1993
lead to larger downtimes in the event of a failure of
more than one converter branch. However it is [6] H. Polinder, F. van der Pijl, G.-J. de Vilder, &
important to note that these results rely heavily Tavner, P. J.: “Comparison of Direct-Drive and
upon the assumptions made during the calculations. Geared Generator Concepts for Wind Turbines.”,
The assumptions made, which have been listed IEEE Transactions on Energy Conversion, 21(3),
previously, could have been vastly improved. The pp. 725-733. 2006
capacity factor and ability to access the turbine
could have been improved by altering the data to [7] Capacity factors at Danish offshore wind farms.
include seasonal variatons in weather conditions. Accessed on: 04/07/14. Accessed from:
Given that the wind speed will be higher and more
http://energynumbers.info/capacity-factors-at-
constant during the winter months, the capacity
factor during this time would have been danish-offshore-wind-farms
significantly higher however the failures may have
been more frequent due to increased loading on the [8] European Commission. Energy prices and costs
converters and due to the weather conditions this in Europe. March 2014
would have lead to much greater downtimes for
each of the turbines. [9] Department of Energy and Climate Change,
New Renewables Obligation Certificates (ROCs)
VI. CONCLUSIONS table. September 2012.