You are on page 1of 90

CHAPTER : R-1 ROAD MATERIAL AND THEIR CARRIAGE

PART-A
CARRIAGE OF MATERIALS
NOTE: Part of Km beyond 1Km will be treated as under :
1.499=1.00 Km; 1.500 Km = 2.00 Km.

S. No. Description Unit Rates


Up to Add for For for 1 Add for For 5 Add for For 10 Add for For 20 Add for
50 M each 50 500 M Km each 1 Km each Km each 1 Km each 1
M (up to Km 1Km Km Km
500 M) beyond beyon beyond beyond
1 Km d 5 Km 11 Km 20 Km
up to 5 up to up to 20
Km 10 Km Km

1 Carriage of Earth, Sand, Lime, Cum 14.7 2.4 36.3 43 2.7 53.8 2.3 65.3 2.1 86.3 1.9
Morrum, Manure or Sludge etc.
including loading and unloading
complete with a lead of
2 Carriage of Building Rubbish Cum 16 2.7 40.3 48.3 2.7 59.1 2.4 71.1 2.1 92.1 1.9
Stone Metal, Grit and Ballast etc.
including loading and unloading
complete with a lead of

3 Stone for masonry work and Cum 16.8 3 43.8 54.6 3.4 68.2 2.75 81.95 2.7 108.95 2.1
soiling
4 Excavated work Cum 19 3.3 48.7 58.8 3.7 73.6 3 88.6 3 118.6 2.4

5 Bricks 1000 30.5 6.1 85.4 91.3 6.1 115.7 6.1 146.2 4.8 194.2 3.95
Nos.
6 Brick Tiles 1000 24.2 4.2 62 67.2 4.8 86.4 4.8 110.4 4.2 152.4 2.75
Nos.
7 Cement, Stone Blocks, Pipes and MT 19 1.5 32.5 38.9 2.1 47.3 2.4 59.3 1.9 78.3 1.5
other heavy materials
8 Steal, Tar, Bitumen and Steam MT 22 2.1 40.9 48.3 2.7 59.1 2.75 72.85 2.1 93.85 1.5
Coal
9 Empty Bitumen Drums 10 8.4 1.2 19.2 24.2 1 28.2 1.2 34.2 1 44.2 1
Nos.
10 carriage with care PreCast cement concrete blocks like Dand & kerbs etc. weighting

10.1 Up to 50 Kg. Each - - - 3.3 0.25 4.3 0.25 5.55 0.1 6.5 0.1

10.2 51 to 70 Kg. Each - - - 4.9 0.3 6.1 0.25 7.35 0.1 8.35 0.1

10.3 71 to 100 Kg. Each - - - 6 0.4 7.6 0.25 8.85 0.1 9.85 0.1

11 RCC Hume Pipe with Collar

11.1 Dia 300 mm Meter - - 14.7 17.6 0.4 19.2 0.25 20.45 0.1 21.45 0.1

11.2 Dia 600 mm Meter - - 38.8 40.9 1 44.9 0.9 49.4 0.65 55.9 0.4

11.3 Dia 900 mm Meter - - 96.6 102.9 1.9 110.5 1.6 118.5 1.3 131.5 0.9

11.4 Dia 1200 mm Meter - - 120 133.4 2.4 143 1.9 152.5 1.3 165.5 1
CHAPTER : ROAD MATERIALS & THEIR CARRIAGE
R-1
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATION
PART - A CARRIAGE OF MATERIALS
12 Carriage of Bitumen mixed material from Hot Mix Plant
in Tipper to Paver Finisher
12.1 For the first km. (rate is included in the respective item).

12.2 Add for each subsequent Km. Lead


12.2.1 2nd Km. Up to 10 Km. Cum/K 2.70 2.70 0.00
M.
12.2.2 11th Km. Up to 20 Km Cum/K 2.30 2.30 0.00
M.
12.2.3 Beyond 20 Km Cum/K 2.10 2.10 0.00
M.
13 Loading in or unloading cement of the railway wagons at M.T. 24.00 24.00 0.00
siding and carrying the same from or into god owns
adjacent to the viding including stacking the same
properly in rows up to any height as per direction of
Engineer in-charge sweeping the wagons and screening
the swept cement and filling in bags complete

14 Loading in or unloading from the railway wagons and


stacking as per the direction of Engineer in-charge
14.1 Steel M.T. 30.50 30.50 0.00
14.2 G.I., C.I., R.C.C. or C.C. Pipes Up to 500 mm Dia and M.T. 24.10 24.10 0.00
similar heavy materials
14.3 Full bitumen drums Each 4.20 4.20 0.00
14.4 Heavy materials where each piece or bundle, crate or M.T. 36.80 36.80 0.00
case weight more than 1 tonne and R.C.C., C.I. And
concrete pipes above 500 mm dia.
CHAPTER : ROAD MATERIALS & THEIR CARRIAGE
R-1
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATION
1 Collection of graded broken hard stone aggregates free
from katcha stuff, deleterious and organic matters as per
IRC/MORTH specifications including stacking as per the
standard specifications of sizes:
1.1 63mm to 45mm hand broken Cum 140.00 140.00 0.00
1.2 53mm to 22.4mm hand broken Cum 150.00 150.00 0.00
1.3 63mm to 45mm crusher broken Cum 350.00 350.00 0.00
1.4 53mm to 22.4mm crusher broken Cum 410.00 410.00 0.00
1.5 13.2mm/11.2mm crusher broken Cum 410.00 410.00 0.00
1.6 6.7mm crusher broken Cum 300.00 300.00 0.00
2 Collection of graded gravel/unscreened kankar for 0.00
granular sub base (PI less than 6) grading as per
MORTH specifications table 400-1, 400-2 with CBR
value not less than 30 Cum 200.00 200.00
3 Collection of quarry rubbish (P.I. less than 6) grading as 0.00
per MORTH specifications table 400-1 including stacking
as per the standard specifications Cum 160.00 160.00
4 Collection of Coarse, Clean sharp river sand (Bajri) 0.00
passing IS sieve 2.36mm and retained on 180 micron
sieve (Mashi, Banas ) including stacking as per the
standard specifications : Cum 350.00 350.00
5 Collection of crusher dust Cum 160.00 160.00 0.00
6 Supply of bitumen of following grades:
6.1 Straight run bitumen (60/70 grade) MT 31679 34987.00 -9.45
6.2 CRMB-60 MT 34538 36492.00 -5.35
6.3 PMB-40 MT 37468 42965.00 -12.79
6.4 Emulsion MT 28023 32331.00 -13.32
8

CHAPTER SITE CLEARANCE & DISMANTLING


: R-2
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON

1 Cutting of trees, including cutting of trunks, branches


and removal of stumps, roots stacking of serviceable
material with all lifts and up to a lead of 1000 m and
earth filling in the depression/ pit as per MoRTH
specification clause 201.
1.1 (i) Girth from 300 mm to 600 mm Each 94.00 78.00 20.51
1.2 (ii) Girth from 600 mm to 900 mm Each 171.00 158.00 8.23
1.3 (iii) Girth from 900 mm to 1800 mm Each 329.00 301.00 9.30
1.4 (iv) Girth above 1800 mm Each 622.00 566.00 9.89
2 Clearing grass and removal of rubbish maximum Hectare 6413.00 5711.00 12.29
150mm up to a distance of 100 Meter outside the
periphery of the area by manual means.
Note : where only grass is met with , the area clear
shall be measured & paid for under this item
(MoRTH clause 201 )
3 Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, saplings and
trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials
and stacking of serviceable material up to a lead of
1000m including removal and disposal of top organic
soil not exceeding in 150 mm thickness as per
MoRTH specification clause 201

3.1 By Manual Means.


3.1.1 In area of light jungle Hectare 19421 17315.00 12.16
3.1.2 In area of thorny jungle Hectare 26015 23208.00 12.09
3.2 By mechanical Means.
3.2.1 In area of light jungle Hectare 24895 24838.00 0.23
3.2.2 B. In area of thorny jungle Hectare 30082 29998.00 0.28
4 Dismantling up to 1.5m in foundation and/or 1.5m
above ground level including T&P and scaffolding
wherever necessary, sorting the dismantled material,
disposal of unserviceable material, and stacking
serviceable material with in a lead of 1000m. [MoRTH
Specification clause 202]
4.1 Concrete
4.1.1 By Manual Means.
4.1.1.1 Lime concrete, cement concrete grade M-10 and Cum 142.00 131.00 8.40
below
4.1.1.2 Cement concrete grade M-15 & M-20. Cum 167.00 153.00 9.15
4.1.1.3 Pre-stressed/ reinforced cement concrete grade M-20 Cum 436.00 396.00 10.10
& above
4.1.2 By mechanical Means
4.1.2.1 Cement concrete grade M-15 & M-20 Cum 193.00 185.00 4.32
9

CHAPTER SITE CLEARANCE & DISMANTLING


: R-2
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON

4.1.2.2 Pre-stressed/ reinforced cement concrete grade M-20 Cum 329.00 312.00 5.45
& above
4.2 Brick/ tile work
4.2.1 In lime mortar Cum 91.00 85.00 7.06
4.2.2 In cement mortar Cum 116.00 108.00 7.41
4.2.3 In mud mortar Cum 80.00 76.00 5.26
4.3 Stone masonry
4.3.1 Rubble stone masonry in lime mortar Cum 94.00 94.00 0.00
4.3.2 Rubble stone masonry in cement mortar Cum 116.00 108.00 7.41
4.3.3 Rubble stone masonry in mud mortar Cum 91.00 85.00 7.06
4.3.4 Dry rubble masonry Cum 85.00 80.00 6.25
4.4 Stone pitching/ dry stone spells. Cum 80.00 76.00 5.26
4.5 Dry brick pitching or brick soling Cum 80.00 73.00 9.59
4.6 Wood work wrought framed and fixed in frames of Cum 217.00 205.00 5.85
Trusses up to a height of 5 m above plinth level.
4.7 Steel work in all types of sections up to a height of 5
m above plinth level excluding cutting of rivet.
4.7.1 Including dismembering Tonne 553.00 515.00 7.38
4.7.2 Excluding dismembering Tonne 413.00 377.00 9.55
4.7.3 Extra over item No. 4.7.1 and 4.7.2 for cutting rivets Each 4.00 4.00 0.00

4.8 Scraping of bricks dismantled from brick work


including stacking.
4.8.1 In lime / cement mortar 1000 449.00 400.00 12.25
Nos.
4.8.2 In mud mortar 1000 160.00 143.00 11.89
Nos.
4.9 Scraping of stone from dismantled stone masonry
4.9.1 In lime / cement mortar Cum 180.00 160.00 12.50
4.9.2 In mud mortar Cum 38.00 34.00 11.76
4.1 Scraping plaster in lime or cement mortar from Brick/ Sqm 6.00 5.00 20.00
stone masonry.
4.11 Removing all types of Hume pipes and stacking
within a lead of 1000 Meters including earthwork and
dismantling of masonry works.
4.11.1 Up to 600 mm dia Meter 67.00 59.00 13.56
4.11.2 Above 600 mm to 900 mm dia Meter 90.00 80.00 12.50
4.11.3 Above 900 mm Meter 154.00 137.00 12.41
5 Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 meters,
stacking serviceable and unserviceable materials
separately as per MoRTH specification clause 202.

5.1 By Manual Means :


5.1.1 Bituminous courses Cum 261.00 240.00 8.75
5.1.2 Granular courses Cum 188.00 174.00 8.05
5.2 By Mechanical Means :
10

CHAPTER SITE CLEARANCE & DISMANTLING


: R-2
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON

5.2.1 Bituminous courses Cum 111.00 118.00 -5.93


6 Dismantling of cement concrete pavement by Cum 574.00 555.00 3.42
mechanical means using pneumatic tools, breaking to
pieces not exceeding 0.02 cum in volume and stock
piling at designated locations and disposal of
dismantled materials up to a lead of 1000 meters,
stacking serviceable and unserviceable materials
separately as per MoRTH specification clause 202.

7 Dismantling guard rails by manual means and Meter 28.00 26.00 7.69
disposal of dismantled material with all lifts and up to
a lead of 1000 meters, stacking serviceable materials
and unserviceable materials separately as per
MoRTH specification clause 202.
8 Dismantling kerb stone by manual means and Meter 6.00 6.00 0.00
disposal of dismantled material with all lift and up to a
lead of 1000 meter as per MoRTH specification
clause 202.
9 Dismantling Kerb stone channel by manual means Meter 9.00 9.00 0.00
and disposal of dismantled material with all lifts and
up to a lead of 1000 meter as per MoRTH
specification clause 202.
10 Dismantling of Kilometer stone including cutting of
earth, foundation and disposal of dismantled material
with all lifts and lead up to 1000 m and back filling of
pit as per MoRTH specification clause 202.

10.1 5th Km stone Each 142.00 126.00 12.70


10.2 Ordinary Km Stone Each 82.00 75.00 9.33
10.3 Hectometer stone Each 16.00 15.00 6.67
11 Dismantling of barbed wire fencing/ wire mesh Meter 18.00 17.00 5.88
fencing including posts, foundation concrete, back
filling of pit by manual means including disposal of
dismantled material with all lifts and up to a lead of
1000 meters, stacking serviceable material and
unserviceable material separately as per MoRTH
specification clause 202.

12 Dismantling of CI water pipe line 600 mm dia Meter 50.00 47.00 6.38
including disposal with all lift and lead up to 1000
meters and stacking of serviceable material and
unserviceable material separately under supervision
of concerned department but excluding earth
excavation and dismantling of masonry works as per
MoRTH specification clause 202.
11

CHAPTER SITE CLEARANCE & DISMANTLING


: R-2
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON

13 Removal of cement concrete pipe of sewer gutter Meter 64.00 60.00 6.67
1500 mm dia under the supervision of concerned
department including disposal with all lifts and up to a
lead of 1000 meters and stacking of serviceable and
unserviceable material separately but excluding earth
excavation and dismantling of masonry works as per
MoRTH specification clause 202.

14 Removal of telephone / electric poles including P.Pole 64.00 60.00 6.67


excavation and dismantling of foundation concrete
and lines under the supervision of concerned
department, disposal with all lifts and up to a lead of
1000 meters and stacking the serviceable and
unserviceable material separately.
15 Scarifying the existing granular road surface to a Sqm 9.00 9.00 0.00
depth of 50 mm by manual means and disposal of
scarified material within all lifts and leads up to 1000
meters as per MoRTH specification Clause No.
305.4.3.
16 Scarifying the existing bituminous road surface to a Sqm 3.50 3.50 0.00
depth of 50 mm by mechanical means and disposal
of scarified material within all lifts and lead up to 1000
meters as per MoRTH specification Clause No.
305.4.3.
12

CHAPTER EARTH WORK FOR ROADS


: R-3
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
1 Earth work in excavation, including stacking/disposal
of surplus material with all lifts and lead up to 1000
meters, exclusive of compensation of earth [MoRTH
specification : Clause 301 to 305]

1.1 In ordinary Soil


1.1.1 Kassi work, undressed, involving an average Cum 31.00 26.00 19.23
horizontal throw up to 2 meters and an average
vertical lift up to 0.50 meter including breaking of
clods.
1.1.2 Manually, with lift up to 0.5m, combined lead up to 50 Cum 42.00 35.00 20.00
meters including breaking of clods.
1.1.3 Mechanically by power shovel, including mechanical Cum 38.00 32.00 18.75
loading and carriage up to 1 Km. By tipper/dumper
(6T capacity)
1.2 In Hard Soil
1.2.1 Pick Axe work, with lead up to 50m.and lift up to Cum 64.00 53.00 20.75
0.5m.
1.2.2 When excavation and loading is done mechanically Cum 41.00 34.00 20.59
using Bull Dozer, Front-end loader and carriage is
done up to 1 Km. by tipper/dumper (6T capacity).

1.3 Blasting including Blasting materials.


1.3.1 Soft Rock with lead up to 50m. And lift up to 0.5m. Cum 174.00 145.00 20.00
1.3.2 Hard rock with lead up to 50m,and lift up to 0.5m Cum 227.00 189.00 20.11
1.4 Chiseling/wedging out rock where blasting is
prohibited.
1.4.1 Soft Rock with lead up to 50 m. and lift up to 0.5 m. Cum 440.00 367.00 19.89
1.4.2 Hard Rock with lead up to 50m.and lift up to 0.5m. Cum 728.00 607.00 19.93
1.5 In Soil unsuitable for road construction such as Cum 49.00 41.00 19.51
marshy soil including pumping out water, removal of
the same and disposal within a lead up to 50m.and lift
up to 0.5m.
2 Extra for Additional lead
As per carriage chapter R-1
3 Dressing of earth work including cutting and filling up Cum 20.00 17.00 17.65
to 15cm [MoRTH Specification Clause 301 to 305]

4 Box cutting/Trenching the Sub Grade to proper slope, 100Sqm 49.00 41.00 19.51
camber and removing inequalities including removing
deleterious stuff and depositing on the road side
slopes (cutting of earth shall be paid separately in the
respective item on the basis of classification of the
excavation done by the Engineer (MoRTH
specification clause 301 to 305)

5 Compensation for earth, taken from private land with Cum 10.00 5.00 100.00
all lead and lift (Land to be arranged by private
negotiations by the contractor) [MoRTH Specification:
Clause 301 to 305].
13

CHAPTER EARTH WORK FOR ROADS


: R-3
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
6 Compaction of original ground with maximum of six 100 Sqm 226.00 188.00 20.21
passes of 8-10 tonnes power roller including filling
depression occurring during rolling [MoRTH
Specification : Clause 305.3.4]
7 Extra for laying earth as per specification for
compaction in 200 mm thick loose layers and
dressing [MoRTH Specification Clause 305.3.5].
7.1 BY MANUAL MEANS : When Laying of earth in layers Cum 5.00 4.00 25.00
is done simultaneously with excavation of earth work
with all lead and lift but excluding rolling and watering

7.2 BY MANUAL MEANS: When lying of earth in layers is Cum 18.00 15.00 20.00
done from stockpiles including breaking of clods and
dressing with all lead and lift but excluding rolling and
watering.
7.3 BY MECHANICAL MEANS, using Motor Grader, from Cum 18.00 15.00 20.00
earth in stock piles with all lead and lift but excluding
rolling and watering.
8 Extra for watering the earth to bring the earth up to Cum 8.00 7.00 14.29
required O.M.C excluding rolling
9 Extra for rolling to specification with the use of Cum 13.00 11.00 18.18
Vibratory roller when earth is at suitable moisture
content with desired field density not less than 95% of
maximum dry density (Modified Heavy Proctor test),
excluding watering.
10 Extra for rolling to specification with the use of Cum 17.00 14.00 21.43
Vibratory roller when earth is at suitable moisture
content with desired field density not less than 100%
of maximum dry density (Modified Heavy Proctor
test).excluding watering.
11 Extra for rolling to specification with Power Roller, 8- Cum 7.00 6.00 16.67
10 tonne when earth is at suitable moisture content
with dry field density not less than 95 % of maximum
dry density (Ordinary Procter test).excluding watering.

12 Extra for rolling to specification with Power Roller, 8- Cum 8.00 7.00 14.29
10 tonne when earth is at suitable moisture content
with dry field density not less than 100 % of maximum
dry density (Ordinary Procter test).excluding watering.

13 Earthwork in excavation in foundation trenches etc.


not exceeding 2 meters depth including dressing of
bottom and sides of trenches, stacking the excavated
soil 3m. Clear from the edge of excavation and
subsequent filling around Hume pipes/masonry in
15cm. Layers with compaction including disposal of
all surplus soil, as directed within a lead of 1000
meters.[MoRTH Specification : Clause 301,304].

13.1 Ordinary Soil Cum 84.00 70.00 20.00


13.2 Pick Axe work (Hard soil) Cum 114.00 95.00 20.00
13.3 Blasting work
14

CHAPTER EARTH WORK FOR ROADS


: R-3
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
13.3.1 Soft Rock Cum 258.00 215.00 20.00
13.3.2 Hard Rock Cum 319.00 266.00 19.92
13.3 Chiseling/Wedging out rock where blasting is
prohibited.
13.3.1 Soft Rock Cum 680.00 567.00 19.93
13.3.2 Hard Rock Cum 1144.00 953.00 20.04
14 Earth filling with surplus soil excavated from
foundation and taken only from outside of building
plinth in 15cm compacted layers, including ramming
watering and consolidation, lead up to 30 meters
[MoRTH Specification : Clause 301,304].
14.1 Ordinary Soil Cum 50.00 42.00 19.05
14.2 Hard Soil (pick Axe work) Cum 73.00 61.00 19.67
15 Earth work in excavation in foundation trenches etc
.in drains and channels etc. not exceeding 2m.depth,
including dressing of bottom and sides of trenches,
stacking the excavated soil 3m Clear from the edge of
excavation including disposal of surplus soil as
directed within a lead of 1000 meters [MoRTH
Specification : Clause 301,304]

15.1 Ordinary Soil (80% of item No.R3-8.1) Cum 66.00 55.00 20.00
15.2 Hard Soil (pick work) (80% of item No. R3-8.2). Cum 95.00 79.00 20.25
15.3 Blasting work
15.3.1 Soft Rock (80% of item No.R3-8.3.1). Cum 196.00 163.00 20.25
15.3.2 Hard Rock (80% of item No.R3-8.3.2) Cum 246.00 205.00 20.00
15.4 Chiseling/Wedging out of rock (where blasting of
prohibited).
15.4.1 Soft Rock (80% of item No.R3-8.4.1) Cum 551.00 459.00 20.04
15.4.2 Hard Rock (80% of item No.R3-8.4.2). Cum 870.00 725.00 20.00
16 Construction of embankment with approved material Cum 168.00 131.00 28.24
obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required
slope and compacting by vibratory roller 8-10 Tonne
to meet requirement of Table 300-2 including cost of
compensation for earth taken from private land with
lead up to 1 Km as per MoRTH specification Clause
No. 305.

17 Construction of embankment with approved materials Cum 71.00 59.00 20.34


deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded
and compacted by vibratory roller 8-10 Tonne to meet
requirement of Table 300-2 as per MoRTH
specification Clause No. 305.

18 Construction of sub grade and earthen shoulders with Cum 182.00 152.00 19.74
approved material obtained from borrow pits with all
lifts and leads, transporting to site, spreading, grading
to require slope and compacted by vibratory roller 8-
10 Tonne to meet requirement of Table 300-2 as per
MoRTH specification Clause No. 305.
15

CHAPTER EARTH WORK FOR ROADS


: R-3
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
19 Loosening of the ground up to a level of 500 mm Cum 44.00 37.00 18.92
below the sub grade level, watered, graded and
compacted in layers by vibratory roller 8-10 Tonne to
meet requirement of Table 300-2 for sub grade
construction as per MoRTH specification Clause No.
305.3.4.
20 Loosening, leveling and Compacting original ground Cum 25.00 21.00 19.05
supporting embankment to facilitate placement of first
layer of embankment, scarified to a depth of 150 mm,
mixed with water at OMC and then compacted by
vibratory roller 8-10 Tonne to achieve minimum dry
density as given in Table 300-2 for embankment
construction as per MoRTH specification Clause No.
305.3.4.

21 Stripping, storing of top soil by road side at 15 m Cum 97.00 81.00 19.75
internal and reapplication on embankment slopes, cut
slopes and other areas in localities where the
available embankment material is not conducive to
plant growth as per MoRTH specifications Clause No.
305.
22 Silt clearance of drains, channels and canals with lift Cum 38.00 32.00 18.75
1.5 Meter. And lead up to 50 Meter.
23 Filling of available excavated earth (excluding rock) in Cum 13.00 11.00 18.18
trenches, plinth sides of foundation etc. in layers not
exceeding 20 cm depth consolidating each deposited
layer by ramming and watering including lead up to
50 Meter. And lift up to 1.5 Meter.

24 Earth work in cutting with lead up to 50 Meter. And lift


up to 1.50 Meter. including finishing of formation to
required camber and grade disposed soil to be
leveled and dressed in
24.1 Blown Sand Cum 16.00 13.00 23.08
24.2 Ordinary Soil Cum 17.00 14.00 21.43
24.3 Clayey Soil Cum 23.00 19.00 21.05
CHAPTER GRANULAR SUB BASE
: R-4
Item No. Item Description Unit Rate Rate (Rs.) %
(Rs.) 2008 VARIATIO
2009 N
1 Providing laying, spreading and compacting Cum 293.00 266.00 10.15
inverted choke of specified graded aggregate in
sub base course in uniform layer on a prepared
base with motor grader and compacting with power
roller etc.(by mechanical means).[MoRTH
Specification : Clause 404.3.2.]
2 Providing and laying granular sub-base material
having P.I. not more than 6 including spreading in
layers not exceeding 150 mm compacted thickness
and consolidation by 8-10 tonne power roller to
required camber and grade including cost of water
and hire charges of machinery including T&P with
all lead (Compacted thickness to be measured).as
per MoRTH specification table 400-1, 400-2,

2.1 For grading-I with CBR value not less than 30. To Cum 496.00 390.00 27.18
attain 100% proctor density.
2.2 For grading-II with CBR value not less than 25. To Cum 486.00 384.00 26.56
attain 100% proctor density.
2.3 For grading-III with CBR value not less than 20.to Cum 481.00 383.00 25.59
attain 100% proctor density.
3 Providing laying spreading and compacting
specified graded sand, gravel as per Table 400-
1,400-2 or any other course material as per design
mix, as per CBR in sub base course including
premixing the material at OMC in wet mix plant,
carriage of mixed material spreading in uniform
layers with motor grader F.E loader on a prepared
base and compacting with vibratory roller to
achieve desired density (as per I.S.2720) including
all material, labor, machinery, lighting guarding,
barricading and maintenance of diversion
complete.[MoRTH specification : Clause 401]. By
mechanical means with lead up to 1 km

3.1 For Grading I Material Cum 686.00 571.00 20.14


3.2 For Grading II Material Cum 687.00 571.00 20.32
3.3 For Grading III Material Cum 687.00 571.00 20.32
3.4 Extra rate for carriage of mixed material additional
lead from:-
3.4.1 2nd km up to 10th km Cum per 2.70 2.70 0.00
Km
3.4.2 11th km up to 20th km Cum per 2.30 2.30 0.00
Km
3.4.3 Beyond 20 Km Cum per 2.10 2.10 0.00
Km
CHAPTER GRANULAR SUB BASE
: R-4
Item No. Item Description Unit Rate Rate (Rs.) %
(Rs.) 2008 VARIATIO
2009 N
4 Providing laying, spreading and compacting Cum 563.00 512.00 9.96
specified graded crushed stone in sub-base course
including premixing the material at OMC in pug mill
(mechanical mixer) carriage of mixed material,
laying in uniform layers with motor grader, F.E.
loader on a prepared surface and compacting with
vibratory compactor to achieve the desired density
including all material, lab our, machinery, lighting
barricading and maintenance of diversion
complete.[MoRTH specification Clause 401]
including 1 Km lead .

4.1 Extra rate for carriage of mixed material additional


lead from:-
4.1.1 2nd km up to 10th km Cum per 2.70 2.70 0.00
Km
4.1.2 11th km up to 20th km Cum per 2.30 2.30 0.00
Km
4.1.3 Beyond 20 Km Cum per 2.10 2.10 0.00
Km
5 Laying and spreading available soil in the sub
grade on a prepared surface, pulverizing (table
400-3), mixing the spreaded soil in place with
rotavator with 3% slacked lime having minimum
content of 70% of CaO, grading with motor grader
and compacting with the vibratory roller 8-10 tonne
at OMC to the desired density to form a layer of
improved sub grade complete as per MoRTH
specification Cl. 402.

5.1 By Mechanical Means Cum 255.00 232.00 9.91


5.2 By Manual Means Cum 242.00 220.00 10.00
6 Providing, Laying and spreading soil on a prepared Cum 327.00 297.00 10.10
sub grade, pulverizing (table 400-3), mixing the
spreaded soil in place with rotavator with 3%
slacked lime having minimum content of 70% of
CaO, grading with motor grader and compacting
with the vibratory roller 8-10 tonne at OMC to
achieve at least 98% of the maximum dry density to
form a layer of sub base complete as per MoRTH
specifications Cl. 402.

6.1 Grading of material for sub-base course Cum 689.00 626.00 10.06
6.2 Grading of material for base course Cum 689.00 626.00 10.06
CHAPTER GRANULAR SUB BASE
: R-4
Item No. Item Description Unit Rate Rate (Rs.) %
(Rs.) 2008 VARIATIO
2009 N
7 Construction of sub-base using lime- Fly ash Cum 314.00 285.00 10.18
admixture with granular soil, free from organic
matter/ deleterious material or clayey silts and low
plasticity clays having PI between 5 and 20 and
liquid limit less than 25 and commercial dry lime
(slacked)
BASE COURSE

Item Description Unit Rate (Rs.) Rate %


2009 (Rs.) VARIATI
2008 ON
Providing, laying, spreading and compacting
stone aggregate of specific sizes as per table
400-7 to Water Bound Macadam specification
including spreading in uniform thickness, hand
packing rolling with vibratory roller in stages to
proper grade and camber, applying and brooming
requisite type of screening and binding materials
to fill up the interstices of coarse aggregates
watering (with water browser) and rolling, making
necessary earthen bund to protect edges, lighting,
guarding, barricading and maintenance of
diversion etc. [MoRTH specification : Clause 404]
( By manual means). (By Manual Means)

Grading II, 63 mm to 45 mm @ 0.91 cum per 10 Cum 907.00 755.00 20.13


Sqm for compacted thickness of 75 mm. (Crusher
broken) Stone screening type 'A'
Grading III, 53 mm to 22.4 mm, @ 0.91 cum per Cum 906.00 819.00 10.62
10 Sqm for compacted thickness of 75 mm.
(Crusher broken) Stone screening type 'B'
Providing, laying, spreading and compacting Cum 913.00 781.00 16.90
stone aggregate for Wet Mix Macadam (as per
table 400-10 and 400-11) specification including
premixing the material with water to OMC in wet
mix plant as per approved design mix, carriage of
mixed material by Tipper to site, laying in uniform
layers with motor grader/Front end Loader/paver
finisher, in sub base/ base course on a well
prepared under base and compacting with
vibratory roller to achieve the desired density
including lighting, guarding, barricading and
maintenance of diversion etc. (MoRTH
specification : Clause 406) by mechanical means
with lead up to 1 Km.

Extra rate for carriage of mixed material additional


lead from :-
2nd km up to 10th km Cum per 2.70 2.70 0.00
Km
11th km up to 20th km Cum per 2.30 2.30 0.00
Km
Beyond 20 Km Cum per 2.10 2.10 0.00
Km
BASE COURSE

Item Description Unit Rate (Rs.) Rate %


2009 (Rs.) VARIATI
2008 ON
Cum 90.00 82.00 9.76
Construction of Median and Island above road
level with approved material (deposited at site
from roadway cutting and excavation for drain and
foundation of other structures), spreaded, graded
and compacted as per MoRTH specification
clause 407.
Construction of median and Island above road Cum 168.00 153.00 9.80
level with approved material brought from borrow
pits, spreaded, sloped and compacted as per
MoRTH specification Clause 407.
Sqm 292.00 265.00 10.19
Construction of footpath/ separator by providing a
150 mm compacted granular sub- base as per
Clause 401 and 25 mm thick cement concrete
grade M-15, over laid with precast concrete tiles
300x300x25 mm in cement mortar 1:3 including
provision of all drainage
Providing crushed stone aggregate, depositing on
a prepared surface by hauling vehicles, spreading
and mixing with a motor grader, watering and
compacting with a vibratory roller 8-10 tonne to
form a layer of sub-base/ base as per MoRTH
specifications Clause 410.
By Mix in place method
(i) For 53 mm maximum size Cum 666.00 605.00 10.08
(ii) For 45 mm maximum size Cum 649.00 590.00 10.00
By Mixing Plant
(i) For 53 mm maximum size Cum 791.00 719.00 10.01
(ii) For 45 mm maximum size Cum 507.00 461.00 9.98
CHAPTE BITUMINOUS CONSTRUCTION
R : R-6
Item No. Item Description Unit Rate (Rs.)
2009

1 Cleaning the existing WBM/WMM surface including Sqm 4.00


removing of binding material and other foreign matter
with wire brushes, small picks, sweeping with brooms
and soft brushes, finally dusting with old gunny bags
and compressed air to receive bituminous treatment
[MoRTH Specification : Clause 501 to 503 &112

2 Cleaning of the existing black topped surfaces with Sqm 2.00


brooms/soft brushes finally dusting with old gunny bags
and compressed air to receive bituminous treatment
[MoRTH Specification 501 to 503 & 112]
3 Scarifying existing stone metal layer up to 75mm thick Sqm 377.00
along with bituminous surface picking up scarified
material within a lead of 100m, sequential spreading the
salvage aggregate with fresh aggregate on prepared
base and consolidation as per WBM specification.
(Comp-acted thickness to be measured) [MoRTH
Specification : Clause 404 & 112]

4 Providing and applying primer coat over prepared Sqm 21.00


surface or granular base with bitumen emulsion as per
IS: 8887 & manufacturer’s specifications @ 6 kg /10
sqm with a self propelled or towed bitumen pressure
sprayer equipped for spraying the material uniformly at
specified rates and temperatures as per MoRTH
specification CI 502 & 112 ( Including cleaning of road
surface )

4.1 Add extra to item No. 4 for 1 Kg / 10 Sqm emulsion Sqm 2.00
5 Providing and applying tack coat on the prepared Sqm 8.00
surface, with bitumen emulsion as per IS : 8887 &
manufacturer’s specifications @ 2 kg /10sqm. With a
self propelled or towed bitumen pressure sprayer
equipped for spraying the material uniformly at specified
rates and temperatures as per MoRTH specification
Clause 503 & 112 ( Including cleaning of bituminous
road surface )

5.1 Add extra to item No. 5 for 1Kg / 10 Sqm emulsion Sqm 2.00
6 Providing and laying bituminous macadam on prepared
surface with specified graded crushed aggregate as per
table 500-4, grading-1for base / binder course including
loading of aggregates with Front end loader and
heating and mixing of stone aggregate and bitumen
(including cost of anti-stripping compound wherever
required) in hot mix plant transporting the mixed
material in tipper and laying mixed material with sensor
paver finisher to the required level and grade rolling by
power roller & vibratory compactor to achieve the
desired density (approved by the department )excluding
cost of primer/tack coat [MoRTH Specification : Clause
504 & 112] with lead of mix 1 Km.

6.1 Grading II (19 mm nominal size) - Bitumen @ 3.30 % of Cum 4068.00


mix (60/70 grade) & thickness 50 - 75mm
6.2 Grading I (40 mm nominal size) - Bitumen @ 3.25 % of Cum 4087.00
mix (60/70 grade) & thickness 80 - 100mm
6.3 Extra rate for carriage of mixed material additional lead
from :-
6.3.1 2nd km up to 10th km Cum 2.70
per
Km
6.3.2 11th km up to 20th km Cum 2.30
per
Km
6.3.3 Beyond 20 Km Cum 2.10
per
Km
7 Construction of bituminous penetration macadam over
prepared base by providing a layer of compacted
crushed coarse aggregate (Table 500-6) using chips
spreader with alternate application of bituminous binder
and key aggregates and rolling with a smooth wheeled
steel roller 8-10 tonne capacity to achieve the desired
density (approved by the department) & including cost
of anti-stripping compound wherever required excluding
cost of primer/tack coat complete as per clause 505 of
MoRTH specification.

7.1 50 mm thick. - Bitumen grade 60/70 @ 5 Kg. Per sqm Sqm 242.00

7.2 75 mm thick. - Bitumen grade 60/70 @ 6.8 Kg. Per sqm Sqm 326.00

8 Providing laying and consolidation of crushed stone Sqm 191.00


aggregates on prepared surface as per Built Up Spray
Grout specification, 75 mm thick as base course
compacted in 2 layers composite construction of
crushed stone aggregates with application of bitumen
binder 60/70 grade with spray set at the rate of 15 Kg
per 10 Sqm after each layer and laying key aggregate
on the top of second layer and rolling with power roller,
8-10 tonne, but excluding cost of primer/tack coat.
[MoRTH Specification : Clause 506 & 112]
9 Providing and laying Dense Bituminous Macadam on
prepared surface with specified graded crushed
aggregates as per table 510 and design mix for
base/binder course including loading of material with
Front end loader, heating of binder (including cost of
anti-stripping compound wherever required) aggregate
and filler in hot mix plant 40-60 TPH, transporting the
mixed material by tippers and laying with sensor paver
finisher as per clause 507.3.5 to the required level and
grade rolling by self propelled power rollers and
vibratory rollers or pneumatic tyred roller 150-250KN.
TP=0.7MPa to achieve the desired density (approved by
the department) but excluding cost of primer/tack coat.
[MoRTH Specification : Clause 507 & 112]

9.1 Grading I (40 mm nominal size) - Bitumen @ 4.5 % of Cum 5132.00


mix (60/70 grade) & thickness 50 - 75 mm with lead of
mix material 1km
Grading II (19 mm nominal size) - Bitumen @ 4.5 % of Cum 5142.00
mix (60/70 grade) & thickness 50 - 75 mm with lead of
mix material 1km
9.2 Extra rate for carriage of mixed material additional lead
from :-
9.2.1 2nd km up to 10th km Cum 2.70
per
Km
9.2.2 11th km up to 20th km Cum 2.30
per
Km
9.2.3 Beyond 20 Km Cum 2.10
per
Km
10 Extra labour for pre-coating crushed stone chipping in Cum 315.00
H.M.P. 6-10 TPH with bitumen (0.75%to 1%) including
heating and mixing the material and handling the mixed
material within in a lead of 30 meters. By Mechanical
means [MoRTH Specifications: Clause 510 & 112].

11 Providing, laying and consolidation Semi Dense


Bituminous Concrete, as per Design Mix, on prepared
surface with specified graded crushed aggregates(as
per table 500-15) for wearing coarse including loading
aggregates with Front end loader, heating aggregate
and binder in Hot Mix Plant 40-60 TPH (including cost of
anti-stripping compound wherever required) and
transporting the mixed material with tipper and laying
with paver finisher with Sensor to the required level
rolling with Vibratory Compactor or 150 to 250 KN
pneumatic tyred roller with TP=0.7 Mpa and power roller
to achieve the desired density (as per approved job
mix), but excluding primer/tack coat [MoRTH
Specification Clause 508 & 112]
11.1 Grading I (13 mm nominal size) - Bitumen @4.5 % of
mix & thickness 35 - 40 mm with lead of mix material
1km
11.1.1 60/70 grade Cum 5360.00
11.1.2 CRMB-60 grade Cum 5719.00
11.1.3 PMB - 40 grade Cum 6087.00
11.2 Grading II (10 mm nominal size) - Bitumen @5 % of mix
& thickness 25 - 30 mm with lead of mix material 1km

11.2.1 60/70 grade Cum 5795.00


11.2.2 CRMB-60 grade Cum 6194.00
11.2.3 PMB - 40 grade Cum 6603.00
11.3 Extra rate for carriage of mixed material additional lead
from :-
11.3.1 2nd km up to 10th km Cum 2.70
per
Km
11.3.2 11th km up to 20th km Cum 2.30
per
Km
11.3.3 Beyond 20 Km Cum 2.10
per
Km
12 Providing and laying bituminous concrete as per design
mix on prepared surface with specified graded stone as
per table 500-18 for wearing course including loading of
aggregate with Front end loader and hot mixing of
binder (including cost of anti-stripping compound,
wherever required) and 3% cement filler with
aggregates in hot mix plant 40-60 TPH Transporting the
mix material with tipper and laying with sensor paver
finisher (as per clouse 507.3.5) to the required level ,
grades and rolling with vibratory compactor and
pneumatic tyred roller 150-250 KN,TP=0.7 Mpa, to
achieve the desired density (approved by the
department) excluding cost of primer/tack coat (MoRTH
Specification : Clause -509 & 112)

12.1 Grading I (19 mm nominal size) - Bitumen @ 5 % of mix


& thickness 50 - 65 mm with lead of mix material 1km

12.1.1 60/70 grade Cum 5920.00


12.1.2 CRMB-60 grade Cum 6327.00
12.1.3 PMB - 40 grade Cum 6745.00
12.2 Grading II (13 mm nominal size) - Bitumen @ 5 % of
mix & thickness 30 - 45 mm with lead of mix material
1km
12.2.1 60/70 grade Cum 5910.00
12.2.2 CRMB-60 grade Cum 6317.00
12.2.3 PMB - 40 grade Cum 6735.00
12.3 Extra rate for carriage of mixed material additional lead
from :-
12.3.1 2nd km up to 10th km Cum 2.70
per
Km
12.3.2 11th km up to 20th km Cum 2.30
per
Km
12.3.3 Beyond 20 Km Cum 2.10
per
Km
13 Providing and laying surface dressing as wearing
course consisting of a layer of bituminous binder of
60/70 grade as per Table 500-20,500-21 (Including cost
of anti-stripping compound, wherever required) laid on
the prepared surface, followed by a cover of crushed
stone chipping of specified size (may be pre-coated
also) & rolling with power roller 8-10 T [MoRTH
Specification : Clause 510 & 112]

13.1 19 mm nominal chipping size @ 0.015 cum per sqm & Sqm 58.00
Bitumen @ 1.2 Kg per sqm
13.2 13 mm nominal chipping size @ 0.01 cum per sqm & Sqm 48.00
Bitumen @ 1.0 Kg per sqm
13.3 10 mm nominal chipping size @ 0.008 cum per sqm & Sqm 39.00
Bitumen @ 0.9 Kg per sqm
14 Providing and laying open graded premix carpet 20mm
thick (compacted) on prepared surface in a single
course as wearing course composed of specified
graded crushed aggregates as per Table 500-23,
heating bituminous binder @ 14.6 Kg/10 Sqm.(60/70
grade) and aggregates in Hot Mix Plant (including cost
of anti-stripping compound , wherever required),
transporting the mixed material with tipper and laying
with paver finisher to the required level and grade,
rolling with power roller, 8-10 tonne but excluding cost of
tack and seal coat with lead for mix of material 1 Km.
[MoRTH Specification : Clause 511 & 112]

14.1.1 a) In Hot Mix Plant 40-60 TPH, including loading of Sqm 82.00
aggregates with Front end loader bitumen 60/70 grade

14.1.2 b) In Hot Mix Plant 40-60 TPH, including loading of Sqm. 85.00
aggregates with Front end loader bitumen crumb rubber
modified bitumen- CRMB 60
14.2.1 a) In mini Hot Mix Plant 6-10 TPH bitumen 60/70 grade Sqm 76.00

14.2.2 b) In mini Hot Mix Plant 6-10 TPH crumb rubber Sqm. 78.00
modified bitumen- CRMB 60
15 Providing and laying20mm thick Mix Seal Surfacing on a
prepared surface in a single course composed of
specified graded crushed aggregates as per table (500-
26) premixed with bituminous binder (including cost of
anti-stripping compound , wherever required) with lead
of mixed material up to 1 Km. [MoRTH Specification:
Clause 512 & 112) In a hot mix plant 40-60 TPH with
Front end loader, laying with paver finisher transporting
the mixed material by tipper and rolling with power roller
8-10 tonne to achieve density approved by the
department, but excluding cost of tack coat.

15.1 a) Type "A" (22 Kg. binder per 10 Sqm) bitumen 60/70 Sqm 110.00
grade
15.2 b) Type "A" (22 Kg. Binder per 10 Sqm) crumb rubber Sqm 114.00
modified bitumen- CRMB 60
15.3 a) Type "B" (19 Kg. Binder per 10 Sqm) bitumen 60/70 Sqm 113.00
grade
15.4 b) Type "B" (19 Kg. Binder per 10 Sqm) crumb rubber Sqm 116.00
modified bitumen- CRMB 60
16 Providing and laying seal coat for sealing the voids in a Sqm 45.00
bituminous surface laid to the specified levels, grade
and cross fall, including cleaning and rolling with a
smooth wheeled roller 8 - 10 tonne capacity finished to
required level and grades, complete as per MoRTH
specification clause 513 Type A - comprising of 11.2
mm to 2.36 mm size aggregate @ 0.09 Cum per 10
Sqm and bitumen binder @ 9.8 Kg / 10 sqm complete.

17 Providing and applying premix seal coat type "B" Sqm 33.00
comprising of thin application of fine aggregate (0.06
cum per 10 sqm) premix with 6.8 Kgs. Per 10 sqm
bitumen binder (Grade 60/70) (including cost of anti-
stripping compound wherever required) In mini hot mix
plant 6-10 TPH and laying with mechanical paver and
rolling with power roller 8-10 tonne including all lead of
mix material ( MoRTH Specifications Clause 513)

18 Providing and laying premix seal coat using hot mix


plant and paver finisher with aggregates of 6.7mm size
defined as 100% passing through 11.20mm sieve and
retained on 2.36mm sieve with 0.09 cum per 10 sqm
and 4.5%bitumen including preparation and
transportation of mix, spreading, laying and rolling etc.
complete in all respect including cost of binder.

with lead of mix material 1km


18.1 60/70 grade Sqm 46.00
18.2 CRMB-60 grade Sqm 53.00
19 Providing and laying 25 mm thick mastic asphalt Sqm 353.00
wearing course with paving grade bitumen (PMB - 40)
meeting the requirements given in Table 500-29,
prepared by using mastic cooker and laid to required
level and slope after cleaning the surface, including
providing anti- skid surface with bitumen pre-coated fine
grained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005 cum per 10 Sqm and at an
approximate spacing of 10 Cm center to center in both
directions, pressed into surface when the temperature of
surfaces is not less than 1000 C, protruding 1 mm to 4
mm over mastic surface, all complete as per MoRTH
specification Clause 515.

20 Providing and laying slurry seal consisting of a mixture


of fine aggregates, portland cement filler, bituminous
emulsion and water (as per Table 500-33) on a road
surface including cleaning of surface, mixing of slurry
seal in a suitable mobile plant, laying and compacting to
provide even riding surface as per MoRTH specification
clause 516, complete in all respect as directed by
Engineer in Charge.

20.1 5 mm thickness rolling by Pneumatic tyred roller with Sqm 45.00


individual wheel load not exceeding 1.5 tonne
20.2 3 mm thickness Sqm 31.00
20.3 1.5 mm thickness Sqm 19.00
21 Recycling pavement by cold milling of existing Cum 4197.00
bituminous layers, planning the surface after cold
milling, reclaiming excavated material to the extent of 30
percent of the required quantity, hauling and stock
pilling the reclaimed material near the central recycling
plant after carrying out necessary checks and
evaluation, adding fresh material including rejuvenators
as required, mixing in a hot mix plant, transporting and
laying at site and compacting to the required grade,
level and thickness, all as specified in MoRTH
Specifications Clause 517.

22 Providing and applying low viscosity bitumen emulsion Sqm 26.00


for sealing cracks less than 3 mm wide or incipient
fretting or disintegration in an existing bituminous
surfacing as per MoRTH specification clause 518
complete as directed by Engineer in Charge.

23 Providing , laying and rolling of bituminous cold mix on


prepared base consisting of a mixture of unheated
mineral aggregate ( as per Table - 500 - 36) and binder
(as per Table - 500 - 37), including mixing in a plant of
suitable type and capacity, transporting, laying by
hydrostatic paver finisher with sensor control,
compacting by Pneumatic tyred roller 12-15 tonne &
Smooth wheeled steel roller 6-8 tonne and finishing to
specified grades and levels as per MoRTH specification
clause 519 complete as directed by Engineer in Charge.

23.1 Using bitumen emulsion


23.1.1 9.5mm to 13.2mm nominal size aggregate Cum 7145.00
23.1.2 19mm to 26.5mm nominal size aggregate Cum 7153.00
23.2 Using cutback bitumen
23.2.1 9.5mm to 13.2mm nominal size aggregate Cum 4938.00
23.2.2 19mm to 26.5mm nominal size aggregate Cum 4936.00
24 Providing, laying and rolling sand-asphalt base course Cum 5106.00
(as per Table 500-42) composed of sand (as per Table
500-41), mineral filler @ 2% and bituminous binder @
5% 60/70 bitumen grade on a prepared sub- grade or
sub-base to the lines, levels, grades and cross- sections
as per the drawings including mixing in a plant of
suitable type and capacity, transporting the hot mix to
work site, laying with paver finisher to the required
grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem roller to achieve the desired
density (approved by the department) - for 1 Km. lead &
including cost of anti-stripping compound wherever
required as per MoRTH specification clause 520
complete in all respect.

25 Providing and laying of a stress absorbing membrane


over a cracked road surface, after cleaning with a
mechanical broom, using modified binder complying
with Clause 521, spreading aggregate with hydraulic
chip spreader, sweeping the surface for uniform spread
of aggregates and surface finished to conform to Clause
902 compacting by smooth wheeled roller and as per
MoRTH specification clause 522 complete as directed
by Engineer in Charge.

25.1 Crack width below 6mm using modified binder (PMB - Sqm 45.00
40) @ 9Kg. Per 10 Sqm crushed stone aggregate 0.11
Cum per 10 Sqm.
25.2 Crack width 6mm to 9mm using modified binder (PMB - Sqm 54.00
40) @ 11 Kg. Per 10 Sqm crushed stone aggregate
0.12 Cum per 10 Sqm.
25.3 Crack width above 9mm using modified binder (PMB - Sqm 72.00
40) @ 15 Kg. Per 10 Sqm crushed stone aggregate
0.12 Cum per 10 Sqm.
26 Providing and laying of premix of crushed stone
aggregates (as per Table 500 - 40) and emulsion
binder, mixed in a batch type cold mixing plant, laid over
prepared surface, by hydrostatic paver finisher with
sensor control, rolled with a pneumatic tyred roller
initially and finished with a smooth steel wheel roller , all
as per Clause 519.3
26.1 75 mm thickness comprising 40mm nominal size Cum 4500.00
aggregate and emulsion @ 45 Ltr. Per tonne
26.2 40 mm thickness comprising 14 mm nominal size Cum 6349.00
aggregate and emulsion @ 70 Ltr. Per tonne
26.3 25 mm thickness comprising 6 mm nominal size Cum 7416.00
aggregate and emulsion @ 85 Ltr. Per tonne
27 Spraying of bitumen over cleaned dry surface of Sqm 9.00
crushed cement concrete base at the rate of 25 Kg per
10 Sqm by a bitumen pressure distributor, spreading of
key aggregates at the rate of 0.13 cum per 10 sqm by a
mechanical gritter and rolling the surface as per Clause
506.3.8
28 Cost of bitumen to be added / subtracted when it varies
from job mix formula adopted in any of the above items.

28.1 80/100 Penetration grade tonne 30714.00


28.2 60/70 Penetration grade tonne 31679.00
28.3 CRMB 60 Modified grade tonne 34538.00
28.4 PMB 40 Modified grade tonne 37468.00
28.5 Bitumen Emulsion tonne 28023.00

NOTE:
Deduct the amount of cleaning in item no 4 & 5 if same
is not provided as per item no 1 & 2
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

1 Supplying and fixing pre cast R.C.C. stones (M-15 mix) using
one percent steel reinforcement, including finishing in cement
sand mortar 1:3, earthwork, cement concrete 1:4:8 engraving
letters and numerals, painting with enamel paint etc. complete
as per IRC standard design.
1.1 Km. Stone for NH, SH & MDR ( size 35 x110x25 cm) Each 860.00 860.00 0.00
1.2 5th Km. Stone ( size 50 x152x25 cm) Each 1426.00 1426.00 0.00
1.3 200 Meter stone ( size 15 x10x65 cm) Each 248.00 248.00 0.00
1.4 Boundary stone ( size 15cm dia at top & 20 cm dia at bottom & Each 207.00 207.00 0.00
90 cm high )
1.5 Guide stone ( size 20 x15x120 cm) Each 357.00 357.00 0.00
2 S & F cut stone including earthwork, cement concrete 1:4:8
engraving letters and numerals, as per IRC standard design:

2.1 Km. Stone for NH, SH & MDR ( size 35 x110x25 cm) Each 1026.00 1026.00 0.00
2.2 5th Km. Stone ( size 50 x152.5x25 cm) Each 1553.00 1553.00 0.00
2.3 200 Meter stone ( size 15 x15x90 cm) Each 371.00 371.00 0.00
2.4 Boundary stone ( size 15x15x90cm) Each 378.00 378.00 0.00
2.5 Guide stone ( size 20 x15x120 cm) Each 475.00 475.00 0.00
3a S & F cement concrete pre cast Kerb or Dand up to 60 cm
length over 20 mm thick base of cement mortar1:4 including
jointing earth work, pointing & jointing with cement mortar 1:4 of
size

Chapte Description Unit Including Including


r Code cost of M- cost of M-
20 Mix 20 Mix
Dand/Kerb Dand/Kerb
Complete Complete
3.1 10 x 15 cm Mtr. 63 63
3.2 15 x 15 cm Mtr. 95 95
3.3 20 x 20 cm Mtr. 169 169
3.4 20 x 25 cm Mtr. 211 211
3.5 (20 x 25)/2 x 30 cm Mtr. 285 285
3.6 (20.5 x 25)/2 x 30 cm Mtr. 289 289
3b S & F cement concrete pre cast Kerb or Dand up to 60 cm
length over 20 mm thick base of cement mortar1:4 including
jointing earth work, pointing & jointing with cement mortar 1:4 of
size
Chapte Description Unit Labour for Labour for
r Code fixing only fixing only

3.1 10 x 15 cm Mtr. 8 8
3.2 15 x 15 cm Mtr. 8 8
3.3 20 x 20 cm Mtr. 9 9
3.4 20 x 25 cm Mtr. 9 9
3.5 (20 x 25)/2 x 30 cm Mtr. 12 12
3.6 (20.5 x 25)/2 x 30 cm Mtr. 12 12
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

4 Fixing of cut stone/Precast R.C.C. stones with loading


unloading & Transportation to its fixing site including earth work
& cement concrete (1:4:8) letter and numerals, Painting with
enamel paint etc. foundation as per IRC/MoRTH specifications
complete (excluding the cost of Cut stones/R.C.C. Precast
stones)

4.1 Km Stone for NH, SH & ODR Each 238.00 238.00 0.00
4.2 5th Km Stone Each 352.00 352.00 0.00
4.3 200 Meter Stone Each 94.00 94.00 0.00
4.4 Boundary/Guide Stone Each 94.00 94.00 0.00
5 Labour charges for casting of cement concrete Kerb or Dand
including finishing and curing of size:
5.1 10 X 15 cm, 15 X 15 cm and 15 X 20 cm Mtr 15.00 15.00 0.00
5.2 25 X 25 (22.5+25)/2X30 and (20+25)/2X30 cm Mtr 18.00 18.00 0.00
6 Supply of mandatory / regulatory reflective sign board fixed on
3 meter long Angle Iron of size 65x65x6 mm complete as per
IRC-67-1977 made of 2 mm thick M.S. sheet stove enameled
paint and reflective symbol. Comp. in all respect duly post
painted in alternate band of Black/White synthetic enamel paint
& hold fast at bottom

6.1 Stop signs with definition plate size 30x20 cm


6.1.2 90 cm Octagon each Each 990.00 990.00 0.00
6.1.3 60 cm Octagon each Each 803.00 803.00 0.00
6.2 Give way signs with definition plate size 30x20 cm
6.2.1 90 cm equilateral triangle Each 825.00 825.00 0.00
6.2.2 60 cm equilateral triangle Each 715.00 715.00 0.00
6.3 Prohibitory signs of circular shape
6.3.1 60 cm dia Each 825.00 825.00 0.00
6.3.2 40 cm dia Each 715.00 715.00 0.00
7 Mandatory/ Regulatory retro reflective sign boards 60 cm dia Each 4180.00 4180.00 0.00
made out of 2.0 mm thick aluminium sheet riveted on a frame
of 40X40X3mm angle Iron, face to be fully covered by white/
blue high intensity grade retro reflective sheeting with
Red/white symbol, cut out or screen printed back ground with
epoxy paint, confirming to MoRTH specifications. (1995) CI.
801 with angle iron post 65x65x6 mm 3 M.long. Comp. in all
respect duly post painted in alternate band of Black/White
synthetic enamel paint & hold fast at bottom

8 Supplying cautionary / Warning Reflective sign boards made


out of 2 mm thick M.S. sheet as per IRC –67-1977, stove
enameled and reflective symbol fixed on Angle Iron of size 65 x
65 x 6mm of 3 meter long :
8.1 90 cm equilateral triangle Each 825.00 825.00 0.00
8.2 Guarded/unguarded Railway Crossing with definition plate
90 cm. equilateral triangle Each 1045.00 1045.00 0.00
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

9 Supplying cautionary / warning sign board 90 cm equilateral Each 4235.00 4235.00 0.00
triangle made out of 2.0 mm thick aluminum sheet riveted on a
frame of 40X40X3mm angle Iron, face to be fully covered by
white / blue high intensity grade retro reflective sheeting with
Red/white symbol, cut out or screen printed background with
epoxy paint complete confirming to MoRTH specifications
(1995) Cl. 801 with angle iron post 65 x 65 x 6 mm. Comp. in all
respect duly post painted in alternate band of Black/White
synthetic enamel paint & hold fast at bottom

10 Supplying informatory reflective sign boards make of 2mm thick


M.S.sheet, stove enameled paint as per IRC-67-1977 fixed on
Angle Iron of size 65 x 65 x 6 mm of 3 meter long. Comp. in all
respect duly post painted in alternate band of Black/White
synthetic enamel paint & hold fast at bottom

10.1 80 x 60 mm with size of square 40 cm. Each 880.00 880.00 0.00


10.2 60 x 45 cm with size of square 30 cm. Each 770.00 770.00 0.00
11 Supplying Informatory sign board size 60x80 cm. made out of Each 4400.00 4400.00 0.00
2.0 mm thick aluminum sheet riveted on a frame of
40X40X3mm angle Iron, face to be fully covered by white / blue
high intensity grade retro reflective sheeting with Red/white
symbol, cut out or screen printed background with epoxy paint,
complete confirming to MoRTH specifications (1995) cl. 801
with angle iron post 65 x 65 x 6 mm.3 Mtr. Long. Comp. in all
respect duly post painted in alternate band of Black/White
synthetic enamel paint & hold fast at bottom

12 Installation of sign board having the post like mandatory Each 192.00 192.00 0.00
cautionary & informatory board includes excavation, cement
concrete 1:5:10 (30X30X60) cm and transportation complete.

13 Supplying route Marker reflective sign boards consisting of Each 880.00 880.00 0.00
shield marked on M.S. flat 14 gauge of size 60 x 45 cm and
definition plate of 30 x 25 cm, 14 gauge, fixed on mild steel
posts of Angle Iron of 65X65X6mm – 3mtr.long for NH/SH:
Comp. inall respect duly post painted in alternate band of
Black/White synthetic enamel paint & hold fast at bottom

14 Supply of flood gauge (water Gauge) as per I.R.C. 67 standard Each 825.00 825.00 0.00
200 cm long fixed on angle iron posts 50x50x6 mm, 2.6 M.
long.
15 Fixing of flood gauge (water Gauge) in cement concrete M-15 Each 230.00 230.00 0.00
mix size 30x30x60 cm. complete including transportation
excavation etc. complete
16 Supplying of Cat’s Eye made of aluminium alloy size Each 154.00 154.00 0.00
75x100x22 mm having 21 biconvex lenses embedded in
circular disc of ABS plastic on each side.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

17 Supply of Traffic Cone made out of 1.25 mm thick MS. Sheet, Each 990.00 990.00 0.00
height 1 meter having upper dia, 8 cm, and lower dia.30 cm.
with base plate of size 40x40 cm two hooks are to be provided
for linking M.S. steel chain 12 mm dia, whole body is processed
in orange stoving enamel paint and one reflective band of 200
mm on it, complete in all respect with one chain 3 M long with
each cone.

18 Supplying of men at work sign board (folding type) made of Each 924.00 924.00 0.00
1.25 mm thick M.S. sheet size 900x900x900 mm painted in
white stove enameled paint and reflective machine cut sheet
Men’s emblem and letter MEN AT WORK in red colours and
additional attachment of size 150x900 mm plate for gang
number and name with white stoving enameled back ground
both plates are fixed on a folding stand of M.S. (heavy) steel
tube of size 13.2 mm outer dia as per IS-1239 (part-I) 1979 duly
painted in grey colour and both the plates are painted on back
side in grey enamel paint.

19 Supply of ‘L’ type Bollard made out of 1.25 mm thick M.S. sheet Each 1100.00 1100.00 0.00
height 134 cm, welded in circular type ring section having upper
dia 15 cm. and lower dia 21 cm with another attachment of
15x15 cm circular section with 15 cm. face plate and hold fast
at bottom, whole body is processed in white stoving enamel
and red reflective 3 hands, each of 7.5 cm end one reflective
sheet of 15 cm. dia provided to it complete in all respect.

20 Supply of Swiss Type Bollard made out of 1.25 mm thick M.S. Each 1265.00 1265.00 0.00
sheet, total height 135 cm, the lower portion is made in tapered
circular section having upper dia 15 cm and lower dia 20 cm
with attachment of one mandatory plate 7 mm thick & fixed with
the help of 7 cm long, 30mm dia chrome plated M.S. tube this
part is fixed on the body with another attachment of a cap 30x7
cm. whole body is processed in black stoving enamel and
mandatory plate in Azure blue, with one compulsory keep left
arrow with 10mm border reflective strip each of 7.5 cm on body
complete in all respect.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

21 Supply of Retro-reflective sign boards size 1800x1200 mm Each 24200.00 24200.00 0.00
made out of 2 mm thick aluminium sheet duly framed with 40
mm M.S. black tube (Medium Class) as per IS-1239 (Part-I)
1979 with Inner support of M.S. flat 12x3 mm whole structure is
fixed with two supports each side 75 mm long and 40 mm M.S.
black tube on two posts of 60 mm dia M.S. black tube (Medium
class) as per 1239 (Part-I ) 1979 2.03 meter long each and also
provision of hold fasts of M.S. bars 12 mm and 25 cm long two
on each post. The sheet has to be stove enameled or epoxy
painting one side and other side Green/ blue retro-reflective
high intensity with White Retro reflective sheet. The letters and
numerals have to be made as per IRC 30-1968 and the board
shall be conformed to the MoRTH specification (1995 edition
clause 801). Post and outer frame of board to be painted with
black and white strips of synthetic enamel paint with black and
white strips.

22 Supply of Hazard Marker made out of 2 mm thick M.S. sheet Each 440.00 440.00 0.00
size 300x300x3 mm framed with angle iron 25x25x3 mm and
fixed on channel posts 75x40x6 mm and hold fast at bottom
whole body is painted in white stoving enamel and 6 Nos., 5 cm
dia reflective sheet on white reflective background with
additional border of 1.25 cm all around it.

23 Supply of Swiss type of Hazard marker, made out of 2 mm thick Each 605.00 605.00 0.00
M.S. sheet size of box is 15x15 cm with hold fast at bottom, the
body is painted in orange stoving enamel paint with white/high
intensity grade micro-prismatic type sheeting, on all four side.

24 P & F Delineator with 30 cm. outer dia RCC Hume pipe NP-2 Each 347.00 347.00 0.00
(As per IS-458/ 1971 ) pipe 1.0 M. Long 40 cm embedded in
cement concrete (1:2:4) block of size 50x50x40 cm. including
excavation up to 40 cm depth. The inside of pipe shall be filled
with C.C. (1:2:4) stone grit max size 20 mm or less up to the
top with semi circular humping. The pipes shall be painted
white/black with enamel paint with red dots two Nos. on each
side

24.1 -do- 15 cm outer dia Each 180.00 180.00 0.00


25.1 Supply or Retro-reflective Name Board size 600x900 made out Each 6600.00 6600.00 0.00
of 2mm thick aluminium sheet fixed on post and frame made
out or angle iron 50x50x6mm, 3M long using stainless steel nut
bolts of 8 mm dia, aluminium sheet is covered with high
intensity grade Retro-reflective sheeting and non reflective
letters in black, post duly painted in black and white synthetic
enamel, complete in all respect. Confirming to MoRTH
specifications (1995) c1. 801.

25.2 - Do- size 600x1200 mm Each 8250.00 8250.00 0.00


25.3 - Do- size 900x900 mm Each 9167.00 9167.00 0.00
25.4 - Do- size 900x1200 mm Each 11916.00 11916.00 0.00
25.5 - Do- size 900x1500 mm Each 14667.00 14667.00 0.00
25.6 - Do- size 1200x1200 mm Each 15583.00 15583.00 0.00
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

26 Supply of Chevron sign of size 75x60 cm made out of Each 3300.00 3300.00 0.00
alluminium sheet 2 mm thick with fixing provision on M.S. angle
iron post 50x50x6 mm 3 M long screwed with stainless steel
nut bolts of 8 M dia, plate is covered by high intensity grade
yellow retro-reflective sheeting and black screen printed arrow
on Retro Reflective Sheet, complete in all respect. Comp. in all
respect duly post painted in alternate band of Black/White
synthetic enamel paint & hold fast at bottom

27 Fixing of sign board having two posts including excavation


cement concrete 1:5:10(30X30X60 cms.) and transportation
complete of size. :
27.1 150x120 cm & 120x75 cm Each 350.00 350.00 0.00
27.2 60x75 cm, 90x60 cm, 75x45 cm, & 60x45 cm. Each 305.00 305.00 0.00
28 Supplying Direction and place identification sign board made
out of 2 mm thick M.S. sheet framed to angle iron 40x40x5 mm
and two vertical posts of angle iron of size 65x65x6 mm 3
meter long with hold fasts, stove enameled paint reflective letter
symbol Comp. in all respect duly post painted in alternate band
of Black/White synthetic enamel paint & hold fast at bottom

28.1 150 x 120 cm. Each 2511.00 2511.00 0.00


28.2 120 x 75 cm. Each 2293.00 2293.00 0.00
28.3 90 x 75 cm. Each 1638.00 1638.00 0.00
29 Supply of village Name Board size 600x900 mm made out of Each 1650.00 1650.00 0.00
1.25 mm thick M.S. sheet duly framed with 30mm Outer Dia
Mild Steel tube tightened with M.S. flat 12x3 mm fixed on two
posts of size 40 mm ODMS tube 3M long whole board is
processed in blue/white stoving enamel paint and white/red
machine cut reflective sheet complete in all respect posts duly
painted with black/white synthetic enamel.

30 Providing and fixing 1.2 metres high GI barbed wire fencing P.Rmt 155.00 155.00 0.00
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M-15 graded
cement concrete 30cm.x30cm.x60cm, 0.6 metre below ground
level, every 15th post, last but one end post and corner post
shall be strutted on both sides and end post on one side only
and provided with 9 horizontal lines and 2 diagonals interwoven
with horizontal wires, fixed with GI staples, turn buckles etc.
complete as per MoRTH specification Clause 807.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

31 Providing and fixing 1.8 metre high GI barbed wire fencing with P.Rmt 283.00 283.00 0.00
2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3
metre center to center founded in M-15 grade cement concrete
30cm.x30cm.x60cm, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted on
both sides and end post on one side only and provided with12
horizontal lines and 2 diagonals interwoven with horizontal
wires, fixed with GI staples, turn buckles etc. complete as per
MoRTH specification Clause 807.

32 Providing 1.20 metre high fencing with angle iron posts 50 mm P.Rmt 409.00 409.00 0.00
x 50 mm x 6 mm at 3 metre center to center with 0.40 metre
embedded in M-15 grade cement concrete, corner, end and
every 10th post to be strutted, provided with welded steel wire
fabric of 75 mm x 50 mm mesh and fixed to iron posts by flat
iron 50 x 5 mm and bolts etc. complete in all respects. Welded
steel wire fabric 75x50mm mesh @ 4 Kg./Sqm 4x30x1.2+5
percent wastage.

33 Providing, fixing and erecting 50 mm dia tubular steel pipe P.Rmt 752.00 752.00 0.00
railing as per IS 1239 in 3 rows duly painted on medium weight
steel channels (ISMC series) 100 mm x 50 mm x 1.2 metre
high above ground, 2 mm centre to centre, complete as per
approved drawings as per MoRTH specification Cl. 808.

34 Providing, fixing and erecting 50 mm dia painted tubular steel P.Rmt 439.00 439.00 0.00
pipe as per IS 1239 railing in 3 rows on precast M-20 grade
RCC vertical posts 1.8 metre high (1.2 m above GL) with 3
holes 50 mm dia for pipe, fixed 2 metre centre to centre,
complete as per approved drawing as per MoRTH specification
clause 808.

35 Provision of reinforced cement concrete crash barrier at the P.Rmt 1685.00 1685.00 0.00
edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC: 21 and dowel bars 25 mm dia
, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MoRTH
Circular No. RW/ NH- 33022/ 1/ 94-DO III dated 24th June
1994 as per dimensions in the approved drawing and at
locations directed by the Engineer , all as specified as per
MoRTH specification Cl. 809.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

36 Providing and erecting a "W" metal beam crash barrier P.Rmt 1689.00 1689.00 0.00
comprising of 3 mm thick corrugated sheet metal beam rail, 70
cm above road/ ground level, fixed on CRC rolled channel
vertical post, 150 x 75 x 5 mm spaced 2 mm centre to centre,
1.8 m high, 1.1 m below ground / road level, all steel parts and
fitments to be galvanized by hot dip process, all fittings to
conform to IS: 1367 and IS: 1364 , metal beam rail to be fixed
on the vertical post with a spacer of channel section 150 x 75 x
5 mm, 330 mm long complete as per MoRTH specification
Clause 810.

37 Providing and erecting a "Thrie" metal beam crash barrier P.Rmt 2633.00 2633.00 0.00
comprising of 3 mm thick corrugated sheet metal beam rail, 85
Cm above road/ ground level, fixed on ISMC series channel
vertical post, 150 x 75 x 5 mm spaced 2 m centre- to- centre, 2
m high with 1.15 m below ground level , all steel parts and
fitments to be galvanized by hot dip process, all fittings to
conform to IS: 1367 and IS: 1364 , metal beam rail to be fixed
on the vertical post with a space of channel section 150 x 75 x
5 mm , 546 mm long complete as per Clause 810.

38 Providing and erecting a wire rope safety barrier with vertical P.Rmt 1242.00 1242.00 0.00
posts of medium weight RS joist (ISMB series) 100 mm x 75
mm (11.50 Kg/ m) 1.50 m long 0.85 m above ground and 0.65
m below ground level, split at the bottom for better grip,
embedded in M-15 grade cement concrete 450 x 450 x 450 mm
, 1.50 m centre to centre and with 4 horizontal steel wire rope
40 mm dia and anchored at terminal posts 15 m apart. Terminal
post to be embedded in M-15 grade cement concrete
foundation 2400 x 450 x 900 mm (depth), strengthened by a
strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a
tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in
foundation concrete as per approved design and drawing, rate
excluding excavation and cement concrete.

39 Providing and erecting anti- glare screen with rectangular vanes P.Rmt 532.00 532.00 0.00
of size 750 x 500 mm made from MS sheet , 3 mm thick and
fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the
direction of flow of traffic, 1.5 m center to center , top edge of
the screen 1.75 m above ground level, vertical post firmly
embedded in M-15 cement concrete foundation 0.60 m below
ground level , applying 2 coats of paint on exposed faces , all
complete as per approved design and drawings.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

40 Providing and laying of a reinforced cement concrete pipe duct,


300 mm dia, across the road (New construction) , extending
from drain to drain in cuts and toe of slope to toe of slope in
fills, constructing head walls at both ends, providing a minimum
fill of granular material over top and sides of RCC pipe as per
IRC:98-1997 , bedded on a 0.3 m thick layer of granular
material free of rock pieces, outer to outer distance of pipe at
least half dia of pipe subject to minimum 450 mm in case of
double and triple row ducts, joints to be made leak proof, invert
level of duct to be above higher than ground level to prevent
entry of water and dirt, all as per IRC: 98- 1997 and approved
drawings.

40.1 Single row for one utility service P.Rmt 565.00 565.00 0.00
40.2 Double row for two utility services P.Rmt 1037.00 1037.00 0.00
40.3 Three row for three utility services P.Rmt 1588.00 1588.00 0.00
41 Installation of a steel portable barricade with horizontal rail 300 Each 1850.00 1850.00 0.00
mm wide, 2.5 m in length fitted on a "A" frame made with 45 x
45 x 5 mm angle iron section, 1.5 m in height, horizontal rail
painted (2 coats) with yellow and white strips , 150 mm in width
at an angle of 450 , 'A' frame painted with 2 coats of yellow
paint, complete as per IRC: SP:55-2001.

42 Construction of a permanent type barricade made of steel Each 3067.00 3067.00 0.00
components, 1.5 m high from road level, fitted with 3 horizontal
rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle iron
vertical support , painted with yellow and white strips, 150 mm
in width at an angle of 450 , complete as per IRC:SP:55-2001.

43 Construction of a permanent type barricade made of wooden Each 5840.00 5840.00 0.00
components, 1.5 m high from road level, fitted with 3 horizontal
planks 200 mm wide and 3.66 m long on 100 x 100 mm
wooden vertical post, painted with yellow and white strips, 150
mm in width at an angle of 450, complete as per IRC :SP:55-
2001.

44 Construction of a permanent type barricade made with brick Each 4983.00 4983.00 0.00
work in mud mortar, 1.5 m high , 4 m long. 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and white
strips.
46 Provision of metal drum/ empty bitumen drum Delinator, 300 Each 237.00 237.00 0.00
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white 100
mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as per
IRC: SP: 55-2001.
46 Positioning of a smart flagman with a yellow vest and a yellow Each 122.00 122.00 0.00
cap and a red flag 600 x 600 mm securely fastended to a staff
1 m in length for guiding the traffic.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

47 Fabrication & assembling of over head gantary & cantilever P.Kg 57.00 57.00 0.00
type structure as per drawing & design including steel work in
built up tubular trusses , cutting / hoisting, bolting & fixing in
position & applying coat of red oxide paint including special
type of nut, bolts( Bolt up to 750 mm ) and washers complete &
finishing with grey enamel paint .

48 Supply of High Intensity retro reflecting Type IV sign plate P.Sqm 7508.00 7508.00 0.00
made out of 2.0 mm thick aluminium sheet face to be fully
covered with blue / green high intensity grade retro reflective
sheet and logo/ matters, boarder made of with similar type of
white sheeting after etching treatment of aluminium sheet , the
back side is to be painted with epoxy grey paint. The plate is to
be fixed on 40x40x5 mm angle iron frame with help of
aluminium rivets.

49.1 Providing and fixing of Precast concrete interlocking blocks of P.Sqm 295.00 295.00
60mm thick manufactured from fully computerized automatic
stationery hydraulic vibro pressed machine & full computerized
automatic batching plant of class A-I as per BS: 6717-2001.
The C.C. interlocking paving blocks be laid on average 50mm
thick bed of coarse sand and the joint is to be filled with fine
sand. Laying procedure on compacted sub base as defined.
The work includes earth work in cutting of B/T road, cutting of
WBM road and disposal of unserviceable material with all leads
& lifts and stacking of serviceable material complete job is to be
executed as per the instructions of Engineer-in-charge. The
rates to be inclusive of all lead, lifts & taxes General
specification of Blocks:

1. Shape : As specified by Engineer-in-charge


2. Tensile splitting strength and breaking load as per BS: 6717-
2001
3. Colour : Grey cement natural colour
4. Variation in Dimension : Less than 1.6mm
5. Variation in thickness : Less than 3.2mm
49.2 P&F ---do---- 100mm thick ------do------ Class A-1 ----do---- P.Sqm 450.00 450.00 0.00
49.3 P&F ---do---- 100mm thick ------do------ Class A-2 ----do---- P.Sqm 465.00 465.00 0.00
50 Fixing of Hazard marker including excavation & cement Each 70.00 70.00 0.00
concrete (1:3:6) (30x30x30cm size) in foundation, curing
complete as per specifications.
51 Fixing of Bollard including excavation and laying cement Each 140.00 140.00 0.00
concrete (1:3:6) (size 45x45x30cm) in foundation & curing
complete as per specifications
52 Labour charges for fixing of Cat's Eye as per MoRTH Each 5.00 5.00 0.00
specification excluding cost of Cat's Eye.
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
(B) PAINTING WORK #DIV/0!
#DIV/0!
Unit Labour Complete Labour Complete
#DIV/0!
Old Work New Work Old New
#DIV/0!
(Two (Three Work Work
#DIV/0!
Coats) Coats) (Two (Three
Coats) #DIV/0!
Coats)
#DIV/0!
1 Painting with superior grade
#DIV/0!
enamel paint of approved quality to
give an even shade including #DIV/0!
writing, littering, figuring etc. #DIV/0!
complete as per IRC standards of: #DIV/0!

1.1 5th km. Stone Each 54.00 96.00 62.00 #DIV/0!


114.00
#DIV/0!
1.2 Km. Stone for ODR & MDR. Each 42.00 67.00 50.00 72.00
#DIV/0!
1.3 200 M stone & Boundry stone Each 12.00 18.00 14.00 26.00
#DIV/0!
1.4 Parapets, Kerbs, railings, guide Each 19.00 30.00 22.00 #DIV/0!
36.00
stones, guard stones, tree guards & #DIV/0!
posts etc. #DIV/0!
1.5 Sign Boards, traffic Signs (Steel) Each 30.00 60.00 32.00 #DIV/0!
67.00
#DIV/0!
1.6 Water gauges. Mtr. 18.00 30.00 22.00 46.00
#DIV/0!
1.7 Number of bridge & culverts. Each 22.00 48.00 29.00 55.00
#DIV/0!
1.8 Bollards (excluding reflective Each 38.00 60.00 - -
#DIV/0!
strips). #DIV/0!
1.9 Bollards with 3 Nos reflective type 7 Each 222.00 378.00 - #DIV/0!
-
cm wide strips including cost of #DIV/0!
providing new strips. #DIV/0!
2 Painting with superior quality road #DIV/0!
marking paint conforming to IS 164- #DIV/0!
1951 of approved quality to even #DIV/0!
shade as per IRC standard #DIV/0!
including traffic diversion #DIV/0!
arrangement of:
#DIV/0!
2.1 Center line (only painted surface to Sqm. 14.00 29.00 16.00 31.00
#DIV/0!
be measured) #DIV/0!
2.2 Zebra crossing, speed breakers Sqm. 12.00 30.00 14.00 34.00
#DIV/0!
etc. #DIV/0!
3 Lettering & figuring with enamel #DIV/0!
paint of approved quality as per #DIV/0!
IRC standard: #DIV/0!
3.1 Up to 25mm height. Each 0.65 0.90 0.80 #DIV/0!
1.20
CHAP TRAFFIC AND TRANSPORTATION
TER :
R-7
Item Item Description Unit Rate (Rs.) Rate (Rs.) %
No. 2009 2008 VARIATION

4 Providing & fixing letters/ borders from reflective tape of


approved quality of standard width (MORTH Specification
Clause 800)
4.1 Providing and fixing letters Letter 2.35 2.35 0.00
per Cm
Lt.
4.2 P & F Borders (50mm wide) Per Cm 0.50 0.50 0.00
Length

5 White washing of parapets, kerbs, railings, boundary stones,


guard etc. complete:
5.1 New surface-three coats. P.Sqm 3.10 3.10 0.00
5.2 Old surface-two coats. P.Sqm 3.00 3.00 0.00
5.3 Labour charges for white washing P.Sqm 1.80 1.80 0.00
6 Marking Centre Line stop lines etc. on road as per IRC pattern P.Sqm 484.00 484.00 0.00
with thermoplastic paint of approved quality and make with 8%
glass beads laid on the road surface at temperature 160° C
with a special applicator machine complete with labour, material
and traffic diversion arrangements.

7 (-do-) without glass beads (-do-) P.Sqm 414.00 414.00 0.00


8 White washing of trees 1.50 m height complete:
8.1 (i) Girth from 300 mm to 600 mm Each 2.00 2.00 0.00
8.2 (ii) Girth from 600 mm to 900 mm Each 3.50 3.50 0.00
8.3 (iii) Girth from 900 mm to 1800 mm Each 6.00 6.00 0.00
8.4 (iv) Girth above 1800 mm Each 9.00 9.00 0.00
9 Providing and applying 2 coats of water based cement paint to P.Sqm 31.00 31.00 0.00
unplastered concrete surface after cleaning the surface of dirt,
dust, oil, grease, efflorescence and applying paint @ of 1 litre
for 2 sqm.
CHAPTER MAINTENANCE OF ROADS
: R-8
Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
1 Restoration of rain cuts with soil, moorum, gravel or a Cum 71.00 71.00 0.00
mixture of these including all leads and lifts and cost of
arrangement of land, clearing the loose soil, benching for
300 mm width, laying fresh material in layers not
exceeding 250 mm and compacting with plate compactor
or power rammer to restore the original alignment levels
& slopes complete as per MoRTH specification Clause
3002.

2 Making up loss of material/ irregularities on shoulder to Cum 25.00 25 0.00


the design level by adding fresh approved soil with all
leads & lifts and compacting it with plate compactor
complete as per MoRTH specification Clause 3003.

3 Stripping excess soil from the shoulder surface including Sqm 7.00 7.00 0.00
disposal of excess earth side slopes to achieve the
approved level and compacting with plate compactor up
to 75mm average depth complete as per MoRTH
specification clause 3003.
4 Filling pot-holes and patch repairs with open-graded Sqm 86.00 90.00 -4.44
premix surfacing, 20 mm with removal of all failed
material, trimming of completed excavation to provide
firm vertical faces, cleaning of surface, painting of tack
coat on the sides and base of excavation as per Clause
503, back filling the pot holes with hot bituminous
material as per clause 511 using 60/70 grade bitumen
mixed in hot mix plant 40-60 TPH capacity and carriage
with all lead, compacting with 8-10 tonne smooth wheel
roller, trimming & finishing the surface to form a smooth
continuous surface, all as per MoRTH specification
Clause 3004.2

5 Filling pot-holes and patch repairs with bituminous Sqm 227.00 240 -5.42
concrete, 40 mm with removal of all failed material,
trimming of completed excavation to provide firm vertical
faces, cleaning of surface, painting of tack coat on the
sides and base of excavation as per Clause 503 back
filling the pot holes with hot bituminous material using
60/70 grade bitumen @ 5% of total mix & mixed in hot
mix plant 40-60 TPH capacity and carriage with all leads
as per clause 509, compacting with smooth wheel roller
8-10 tonne, trimming & finishing the surface to form a
smooth continuous surface, all as per MoRTH
specification Clause 3004.2

6 Filling of crack using slow- curing bitumen emulsion and R.Mtr. 3.00 2.00 50.00
applying crusher dust in cracks complete as per MoRTH
specification clause 3004.3.3
CHAPTER MAINTENANCE OF ROADS
: R-8
Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
7 Applying crusher dust to areas of road where bleeding of Sqm 0.50 0.50 0.00
excess bitumen has occurred as per MoRTH
specification Clause 3004.4.
8 Removal of existing sealant and re-sealing of R.Mtr. 82.00 82.00 0.00
contraction, longitudinal or expansion joints in concrete
pavement with fresh sealant material hot poured
rubberized bitumen or cold polysulphide type as per
Clause 602.2.8 with appropriate type of primer complete
as per MoRTH specification Clause 3005.2..

9 Removal of earth from the choked hill side drain and Cum 12.00 12.00 0.00
disposing it on the valley side manually complete as per
MoRTH specification Clause 3000.
10 Clearance of landslides in soil and ordinary rock by a Cum 42.00 42.00 0.00
bull- dozer D 80 A-12 , 180 HP and disposal of the same
on the valley side as per MoRTH specification Clause
3000.
11 Clearing of landslide in hard rock requiring blasting for 50 Cum 74.00 74.00 0.00
percent of the boulders and disposal of the same on the
valley side as per MoRTH specification Clause 3000.

12 Labour charges for patching W.B.M. using crushed / Cum 99.00 99.00 0.00
broken aggregates including preparation of pot hole
scarifying and reshaping to the required grade and
camber as per the standard specifications, spreading of
material consolidation with 8-10 tonne power roller,
spreading and consolidation of binding material including
cost of fuel and lubricants and hire charges of T & P

13 Labour charges for premix patching with stone chipping #DIV/0!


mixed with binder as per the detailed specifications
including heating of binder and aggregates, mixing of
aggregated and binder, cleaning the area of patch pot
holes cut to regular shape with vertical side removing all
loose and disintegrated material, application of tack coat
as per the detailed specifications laying of patch with 8-
10 power loader including cost of fuel and hire charges
of T&P

13.1 Using straight run bitumen 10 Sqm 157.00 157.00 0.00


13.2 Using cationic emulsion 10 Sqm 142.00 142.00 0.00
CHAPTER MAINTENANCE OF ROADS
: R-8
Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
14 Labor charges for premix patch work using mix material #DIV/0!
from the hot mix plant including cleaning of patch pot
holes area, cutting it to regular shape vertical edges,
removing all loose and disintegrated material, application
of tack coat as per specifications laying of patching
material and compacting with power roller including cost
of fuel and hire charges of T&P and tack coat

14.1 Using straight run bitumen 10 Sqm 42.00 42.00 0.00


14.2 Using cationic emulsion 10 Sqm 36.00 36.00 0.00
15 Labor charges for penetration patching up to 5 cm depth 10 Sqm 288.00 288.00 0.00
semi ground including heating and spreading of binder,
cleaning the area of patch pot holes cut to regular shape
with vertical side, removing all loose and disintegrated
material, spreading and compacting of aggregate with 8-
10 tonne power roller including cost of fuel and hire
charges of T&P using bitumen @ 50 kg./ 10 Sqm

16 Labour charges for digging out of sludge humps on black Sqm 12.00 12.00 0.00
topped surface including removal & disposing of the
dismantled material aside up to 50 Mtr. lead.
17 Dismantling/Digging out entire road wearing coat of Sqm 200.00 200.00 0.00
bituminous surface including removal of dismantled
material aside up to 50 Mtr. lead.
18 Cutting of black topped surface up to 30mm depth for Sqm 10.00 10.00 0.00
fixing of Kerb/Dand stones/Medians including cleaning of
surface laying bed mortar & removal of dismantled
material with all lead & traffic diversion arrangements
complete
19 Digging out entire WVM surface including sorting out Cum 47.00 47.00 0.00
serviceable material its stacking & removal of rubbish up
to 50 Mtr. lead.
20 Cutting WBM road and soling up to 1.5 Mtr. depth for Sqm 251.00 251.00 0.00
laying pipe line etc. & making good to original condition
complete.
CHAPTER MAINTENANCE OF ROADS
: R-8
Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
21 Providing and laying built up spray grout patching 75mm Sqm 222.00 195.00 13.85
thick in two layers (each layer consisting of spreading
aggregate (crusher broken) @0.50 cum per 10 Sqm area
as per MoRTH specifications, laying first layer after
application of tack coat @ 3.75 Kg per 10 Sqm (including
cost of tack coat) rolling with 8-10 tonne power road
roller application of first spray of binder @ 15 Kg/10 Sqm
spreading & rolling of second layer of course aggregate
with 8-10 tonne power road roller application spray of
binder @ 15 Kg/10 Sqm and laying key aggregate on the
top of second layer & rolling with 8-10 tonne power road
roller including heating & spraying of binder, cleaning of
the area of patch, pot holes, cut to regular shape with
vertical sides, removing all loose & disintegrated material
including cost of coarse aggregate Key aggregate rolling
& hire charges of machinery T&P fuel bitumen etc.
complete.

22 Cutting black topped surface up to 1.5 Mtr. depth Sqm 266.00 266.00 0.00
including all layers of crust for laying pipe line etc. &
making good to original condition (excluding cost of
Bitumen)
23 -----do----- For paver finished surface Sqm 303.00 303.00 0.00
24 Cutting black topped surface up to 0.5 Mtr. depth Sqm 254.00 254.00 0.00
including all layers of crust for laying pipe line etc. for
house connection & making good the with premixed
chips (excluding cost of Bitumen).
25 Cutting WBM surface up to 0.5 Mtr. depth including all Sqm 218.00 218.00 0.00
layers of crust for laying pipe line etc. for house
connection & making good to original condition.
26 Labour charges for removal of up heaved bitumen #DIV/0!
surface on semi-dense carpeted road surface good to
original condition
26.1 Up to 3 cm height Sqm 13.00 13.00 0.00
26.2 Above 3 to 5 cm height Sqm 15.00 15.00 0.00
26.3 Above 5 to 8 cm height Sqm 20.00 20.00 0.00
26.4 Above 8 cm height Sqm 22.00 22.00 0.00
27 Dressing of berms including digging of earth up to 10 cm Sqm 0.65 0.65 0.00
depth
28 Dismantling tile work in floors and roofs laid in cement Sqm 5.80 5.80 0.00
mortar including stacking of serviceable material and
disposal of unserviceable material within 50 Mtr. lead.
CHAPTER MAINTENANCE OF ROADS
: R-8
Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON
29 Providing and fixing steel gate grating and grills made of Kg 55.00 55.00 0.00
angles, tees, square bars or other flats black pipe with
hold fast and fittings complete as per design and drawing
including cutting welding and fabrication with priming
coat of red oxide.
30 Providing stone slab covering over drains including filling Sqm 281.00 281.00 0.00
of joints in cement sand mortar 1:3 with 35mm thick
cement concrete flooring 1:2:4 mix complete with good
finish with stone slab 60 to 75mm thick average.
CHAPTER : HORTICULTURE
R-9
Item No. Item Description Unit Rate (Rs.)
2009

1 Supply at site of work well-decayed farmyard manure, Cum 165.00


from any available source, approved by the Engineer in
charge including carriage, screening and stacking.
2 Supplying at site of work/store Deolied Neem Cake duly Quintal 484.00
packed in used gunny bags.
3 Supplying sludge duly stacked at site/store Cum 66.00
4 Trenching in specified soil up to a depth of 60 cm.
Including removal and stacking of serviceable materials
and than disposal by spreading and neatly leveling within
a lead of 50 meters and making up the trenched area to
proper levels by filling with earth or earth mixed with
sludge or/and farm-yard manure before and after
flooding with water (excluding cost of improved earth and
sludge or farm -yard manure)

4.1 In ordinary soil Cum 9.00


4.2 Extra for work in hard soils.
Note : Extra rate shall be payable for work executed in Cum ---
soil other than ordinary soil at difference of rates of
excavation in ordinary soil and respective soil under item
nos. R3.1-R3.1.2

5 Rough dressing the trenched ground including breaking 100 Sqm 15.50
of clouds.
6 Uprooting weeds from the trenched area after 10 to 15 100Sqm 177.00
days of its flooding with water including disposal of
uprooted vegetation.
7 Fine dressing the ground 100 Sqm 44.00
8 Spreading of sludge farm-yard manure or/and good earth Cum 7.00
in required thickness (cost of sludge, farm-yard manure
or/and good earth to be paid for separately).
9 Mixing earth and sludge or farm-yard manure in Cum 4.50
proportion specified or as directed.
10 Grassing with 'Doob' grass including watering and
maintenance of the lawn for 30 days or more till the
grass forms a thick lawn free from weeds and fit for
moving including supplying good earth if needed.
10.1 In rows 15 cm apart in either direction. 100 Sqm 204.00
10.2 In rows 7.5 cm apart in either direction. 100 Sqm 275.00
10.3 In rows 5 cm apart in either direction. 100 Sqm 352.00
11 Uprooting rank vegetation and weeds by digging the 100 Sqm 880.00
area to a depth of 60cm.removing all weeds and other
growth with roots by forking repeatedly, breaking clods,
rough dressing, flooding with water, uprooting fresh
growth after 10 to 15 days and then fine dressing for
planting new grass, including disposal of all rubbish with
all leads and lifts.
CHAPTER : HORTICULTURE
R-9
Item No. Item Description Unit Rate (Rs.)
2009

12 Filling mixture of earth and sludge farm-yard manure in Cum 3.00


the desired proportion in trenches, flooding with water
and leveling (cost of supplying earth and sludge or farm
yard manure and labour for mixing not included in this
rate).
13 Turfing slopes of old banks with rough, grassing 100 Sqm 297.00
including preparation of ground, supplying and planting
doob grass roots, 15cm apart, supplying and spreading
farm yard manure at rate of 0.18 cum per 100 Sqm and
loosening soil with kassi.
14 Turfing slopes of new banks with rough, grassing 100 Sqm 237.00
including preparation of ground ,supplying and planting
doob grass roots, 15cm apart, supplying and spreading
farm yard manure at rate of 0.18 cum per 100 Sqm and
loosening soil with kassi.
15 Making lawns, including ploughing and dragging with 100 Sqm 297.00
'Swagha'(one man with a pair of bullocks), breaking of
clods, removal of rubbish, dressing and supplying Doob
grass roots, and planting at 15cm apart, including
supplying and spreading of farm- yard manure at the rate
of 0.18 cum per 100 Sqm.
16 Maintenance of lawns or turfing of slopes (rough 100 Sqm 2750.00
grassing) for a period of one year including watering etc.

17 Turfing lawn with fine grassing including ploughing, 100 Sqm 704.00
dressing including breaking of clods, removal of rubbish,
dressing and supplying and spreading of farm yard
manure at rate 0.60 cum per 100 Sqm.

18 Maintenance of lawns with fine grassing for the first year 100 Sqm 3520.00
including watering etc.
19 Planting permanent hedges including digging of trenches 100 8085.00
60cm wide and 45cm deep refilling the excavated earth Meters
mixed with farm yard manure supplied at the rate of 4.65
cum per 100 meters and supplying and planting hedge
plants at 30 cm apart.
20 Maintaining the hedges for the first two years including
watering etc. complete.
20.1 For first year Meters 42.00
20.2 For second year Meters 35.00
21 Digging holes in all kinds of soil and refilling the same
with the excavated earth mixed with well decayed farm
yard manure (cost of well decayed farm yard manure to
be paid separately).
21.1 Hole 1.2 mm dia and 1.2m deep One hole 24.00
21.2 Hole 0.6 m dia and 0.6 m deep Each 11.00
CHAPTER : HORTICULTURE
R-9
Item No. Item Description Unit Rate (Rs.)
2009

22 Planting & maintenance of plants and shrubs.


CHAPTER : HORTICULTURE
R-9
Item No. Item Description Unit Rate (Rs.)
2009

22.1 Plants and shrubs in central verge where verge is 3.0


meters and above (200 plants 800 shrubs in two rows in
one Km).
22.1.1 Planting plants and shrubs in central verge. Meter 12.00
22.1.2 Maintenance of plants and shrubs in Central verge for Meter 74.00
one year.
22.2 Plants and shrubs in central verge where verge is less
than 3.0 meters with one row of 400 shrubs and 100 tree
plants in one Km.
22.2.1 Planting plants and shrubs Meter 6.00
22.2.2 Maintenance of plants and shrubs for one year Meter 39.00
23 Renovating lawns including weeding, chilling the grass, 100 Sqm 482.00
forking the ground, top dressing with forked soil, watering
and maintaining the lawns for 30 days or more till the
grass forms a thick lawn, free from weeds and fit for
moving, Disposal of rubbish as directed, including
supplying good earth, if needed; but excluding the cost of
well decayed farm-yard manure.

24 Half brick circular tree guard in second class bricks, Each 374.00
internal dia 1.25 meters, and Ht. 1.2 meter above ground
and 0.2 meters below ground, bottom two course laid dry
and top three courses in cement mortar 1:6 (1 Cement, 6
Sand) and the intermediate courses being in dry honey
comb masonry, as per design, complete.

25 Edging with 2nd class bricks laid dry length wise Meter 9.00
including excavation refilling, consolidating with and
packing and spreading nearby, the surplus earth within
lead of 50 meters.
CHAPTER : HORTICULTURE
R-9
Item No. Item Description Unit Rate (Rs.)
2009

26 Making tree guard 53 cm dia and 1.3 m high as per Each 166.00
design from empty bitumen drums(supplied by the
department at stock issue rate) including providing and
fixing 2 nos. M.S sheet rings 50 x 0.5 mm with rivets,
complete in all respects.
27 Making tree guard 53cm dia and 2 m high as per design Each 297.00
from empty bitumen drums (supplied by the department
at stock issue rate) including providing and fixing four
legs 40 cm long of 30 x 3 mm M.S. Flat riveted to tree
guard and providing and fixing 2 nos. M.S. sheet rings 50
x 0.5 mm with rivets complete in all respects.

28 Providing and fixing Wrought iron and Mild steel welded Quintal 3355.00
work (using flats, square bars, tees and channel grills,
grating) frames, gates and tree guards of any size and
design etc. including cost of screens and welding rods or
bolts and nuts, complete, fixed in position but without the
cost of excavation and concrete for fixing which will be
paid separately.

29 1.2 meters high fencing with 1.65 meters posts placed at Meter 14.50
every 2.5 to 3 meters apart embedded in cement
concrete blocks and every tenth post to be strutted,
provided with 4 horizontal lines of G.I. barbed wire,
weighing 9.34 Kg per 100 meters (minimum) and fixed
wit G.I. staples, ties to 6mm bar with binding wire or by
providing cut, including drilling holes in the post,
complete( excluding the cost of the post, earthwork and
concrete which is payable extra in the respective item).
CHAPTE CULVERTS
R : R-10
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATI
ON

1 Providing and laying mechanically mixed and vibrated Cement


Concrete in foundation up to a depth of 1.5 meters below
ground level and 1.50 meters above Ground/Bed level.
[MoRTH Specification : Clause 1000/1700]

1.1 Cement concrete 1:4:8 mix crushed stone aggregates 40mm Cum 2086 1896.00 10.02
nominal size.
1.2 Cement concrete 1:4:8 mix hand broken stone aggregates Cum 1791 1628.00 10.01
40mm nominal size.
1.3 Cement concrete 1:3:6 mix crushed stone aggregates 20mm Cum 2497 2270.00 10.00
nominal size.
1.4 Cement concrete 1:3:6 mix with stone aggregate 40mm Cum 2423 2203.00 9.99
crusher broken.
2 Providing and laying Plain cement concrete M15 mix with Cum 2793 2576.00 8.42
stone aggregate 20mm nominal size mechanically mixed and
vibrated, in foundation up to a depth of 1.50 below Ground
level and or 1.50 meters above ground/bed level.

3 Providing and laying Plain cement concrete M15 mix with Cum 2998 2725.00 10.02
stone aggregate20mm nominal size mechanically mixed and
vibrated, in superstructure up to 4 meter above 1.5 meter level
from Bed/Ground level.[MoRTH Specification: Clause
1000/1700]
4 Cum 3390 3703.00 -8.45
Providing and laying RCC M25 mix with stone aggregate
20mm (nominal size) mechanically mixed and vibrated for
RCC work in slab in superstructure up to 4 meter above 1.5
meter level from Bed/ Ground level, excluding steel
reinforcement but including centering and shuttering laid in
position.[MoRTH Specification : Clause 1000/1700]
5 Providing and laying Reinforced cement concrete M20 mix Cum 3119 3104.00 0.48
with stone aggregate 20mm nominal size mechanically mixed
and vibrated for bed plates excluding steel reinforcement but
including centering and shuttering, laid in position .[MoRTH
Specification : Clause 1000/700]

6 Providing and fabricating steel reinforcement for R.C.C works


including cutting, bending, placing in position and binding
complete including cost of binding wire .[MoRTH
Specification : Clause 1000/1600]
6.1 Mild steel and medium tensile steel bars Tonne 39678 39314.00 0.93

6.2 HYSD/TMT bars Tonne 45284 39976.00 13.28

7 Providing and laying First class brick masonry (min.10.5 MPa) Cum 2449 2365.00 3.55
in cement mortar 1:3 up to a depth of 1.50 meters below
ground and above 1.50m from Bed/ground level. [MoRTH
Specification : Clause 1000/1300]
8 Extra for brick works in superstructure up to a height 4 meters Cum 55.00 55.00 0.00
or part thereof above 1.5 meter level from Bed/Ground level
[MoRTH specification: Clause 1000/1300].

9 Providing and laying Brick-on-edge flooring with 1st class Sqm 165.00 165.00 0.00
bricks (min.10.5 Mpa) including cement slurry in cement sand
mortar 1:4 at all levels.[MoRTH Specification : Clause
1000/1300]

10 Providing and laying Coursed / Random Rubble stone Cum 2272 2130.00 6.67
masonry in cement sand mortar 1:3, in foundation up to a
depth of 1.50 meters and also 1.50 meters above Ground
/Bed level [MoRTH Specification : Clause 1000/1400]

11 Extra for coursed/Random rubble stone masonry in Cum 80.00 80.00 0.00
superstructure up to a height of 4 meters or part thereof above
1.50 meters from Ground /Bed level [MoRTH Specification :
Clause 1000/1400]
12 Providing Cement pointing 1:3 deep grooved (cut or weather) Sqm 31.00 31.00 0.00
on brick / stone and tile work at all levels.[MoRTH
Specification : Clause 1000/1300]
13 Providing Cement pointing 1:3, flush on Brick-on-edge floor at Sqm 32.00 32.00 0.00
all levels.[MoRTH Specification: Clause 1000/1300]
14 Providing Cement plaster 12mm thick in cement mortar (1:3) Sqm 63.00 63.00 0.00
at all levels [MoRTH Specification: Clause:1000/1300]

15 Providing and laying reinforced cement concrete pipes N.P.4


for culverts including jointing ends and fixing collar with
cement mortar 1:2 [MoRTH Specification : Clause :
1000/2900]

15.1 900 mm dia Meter 4490 4481.00 0.20


15.2 1000 mm dia Meter 4986 4979.00 0.14
15.3 1200 mm dia Meter 5641 5629.00 0.21
16 Providing and laying Rubble stone kharanja in cement sand Cum 1265.00 1265.00 0.00
mortar 1:3 in flooring at all levels [MoRTH Specification :
Clause : 1400]
17 Providing and laying Dry Boulder Pitching in flooring at all Cum 676.00 660.00 2.42
levels [MoRTH Specification Clause: 2500]

18 Providing and filling in foundation trenches, and at the back of


abutments wing walls etc. and below pipe bed in layers not
exceeding 150mm thick including watering and compacting,
including all lead and lifts.

18.1 Good local sand free from earth [MoRTH Specification : Cum 444.00 327.00 35.78
Section 2100]
18.2 Selected granular material in filling [MoRTH Specification Cum 454.00 336.00 35.12
Clause :1500]
18.3 Filter media behind abutment, wing and return wall [MoRTH Cum 444.00 327.00 35.78
Specification :Clause : 2504]
19 Making and filling expansion joints, with bitumen filler Meter/cm 1.00 1.00 0.00
(Bitumen 40 percent, asbestos 5 percent and sand 55 percent depth
) 12mm wide at any level. [MoRTH Specification : Clause :
2100]

20 Providing and fixing pre-molded bitumen joint filler at any


level, for expansion joints including the cost of sealing
compound and priming coat.[MoRTH Specification : Clause :
2600]

20.1 12mm wide Meter/cm 3.50 3.50 0.00

20.2 25mm wide Meter/cm 6.25 6.25 0.00

21 Reinforced cement concrete M30 mix with stone aggregate Cum 3970 3757.00 5.67
20mm nominal size mechanically mixed and vibrated for
reinforced concrete work in superstructure at any level
excluding steel reinforcement but including centering and
shuttering laid in position [MoRTH Specification : Clause
1000/1700]

22 Providing and laying cement concreting including curing


compaction etc. complete using stone aggregate 20mm
nominal size mechanically mixed & vibrated in foundation and
plinth including the cost of shuttering if required.

22.1 M-25 grade mix 1:1:2 ( 1 cement : 1 sand : 2 graded stone Cum 3608 3174.00 13.67
aggregate)

22.2 M-20 grade mix 1:1.5:3 ( 1 cement : 1.5 sand : 3 graded stone Cum 3439 2889.00 19.04
aggregate).

23 Providing and fixing precast cement concrete coping 1:2:4 Sqm 156.00 142.00 9.86
mix, 50mm thick complete as per specifications
23.1 Providing and laying cement concrete coping 1:2:4 mix, 50mm Sqm 142.00 129.00 10.08
thick complete as per specifications

24 Pointing of stone masonry in cement mortar (1:3) raised & cut Sqm 46.00 42.00 9.52
pointing.
25 Plaster on new surface with cement mortar (1:3) including Sqm 85.00 77.00 10.39
racking of joint etc. complete fine finished 20mm thick.

26 Plaster on new surface with cement mortar (1:4) including Sqm 64.00 58.00 10.34
racking of joint etc. complete fine finished 20mm thick.

27 Random rubble stone masonry for foundation & plinth in 0.00


cement sand mortar above 30 cm thick walls

27.1 In cement sand mortar 1:4 Cum 2145.00 1950.00 10.00


27.2 In cement sand mortar 1:6 Cum 2024.00 1840.00 10.00
28 Random Rubble stone masonry for superstructure up to 4.5 0.00
Mtr. height above plinth/bed level in cement sand mortar for
above 30cm thick walls

28.1 In cement sand mortar 1:4 Cum 2255.00 2050.00 10.00


28.2 In cement sand mortar 1:6 Cum 2090.00 1900.00 10.00
29 Add extra in Item of stone masonry for walls up to 30 cm or Cum 55.00 50.00 10.00
less thickness
30 Providing and fixing of reinforced Ferro-Cement drain covers 0.00
designed for 'A' & 'AA' class loading duly marked on cover
with adequate steel reinforcement having thickness 75mm to
150mm anti corrosive bitumen painted M.S. plate , Rim and
M.S. lifting hooks, Admixtures like plasticizer, bond improving
compound, shrinkage, resistance compound, abrasion
resistant complete as per approved design etc.

0.00 #DIV/0!

Span Standard Size Unit Class 'A' Class 'AA'


Loading Loading
30.1 300 to 450mm 600x800mm Sqm 880.00 1045.00
31 Providing and fixing cement concrete Precast Kerb or Rmt 271.00 246.00 10.16
Dand of M-15 grade concrete up to 60 cm length over
20mm thick base of CM (1:6) including required Earth
work, cutting of WBM and BT surface Pointing & jointing
with cement mortar (1:4) of shape as approved by the
Engineer-in-charge the work includes providing laying
and compacting base concrete (1:5:10) 100mm thick
below Dand/Kerb complete in all respect as per
specifications size (20.5+25.0)/2x30cm

32 Providing and laying Precast reinforced cement concrete 0.00


Box culvert section of M-40 grade designed for 'AA' class
loading as per IRC specifications including to effect of
impact, EQ etc. complete on form base of 200mm thick
lean concrete of M-10 grade with aggregate of size
40mm nominal of following internal size the work
includes required safety measures construction of drain
for diversion of flowing water cost of design of RCC
Precast Box and its proof checking from IIT/MNIT Jaipur
complete in all respect as per specifications

32.1 Size 2.00 M x 2.00 M Rmt 36929.00 33572.00 10.00


32.2 Size 1.75 M x 1.75 M Rmt 28278.00 25707.00 10.00
32.3 Size 1.50 M x 1.50 M Rmt 20776.00 18887.00 10.00
32.4 Size 1.50 M x 1.25 M Rmt 19246.00 17496.00 10.00
32.5 Size 1.50 M x 1.00 M Rmt 17122.00 15565.00 10.00
32.6 Size 1.25 M x 1.25 M Rmt 14944.00 13585.00 10.00
32.7 Size 1.25 M x 1.00 M Rmt 14835.00 13486.00 10.00
32.8 Size 1.00 M x 1.00 M Rmt 11604.00 10549.00 10.00
32.9 Size 0.75 M x 0.75 M Rmt 7671.00 6974.00 9.99
32.10 Size 0.60 M x 0.60 M Rmt 5645.00 5132.00 10.00
33 P & P Precast dense cement concrete (Vibro-pressed) 0.00
drain section block of different size as per approved
drawing and design and strength as per IS code:2185
Part-I of grade 'D' (5.00mm) proper quality of
additive/admixture like plasticizer etc. added to produce
high quality and durable drain section blocks of "L"
shape "U" shape etc. as per approved design and
drawing complete with fixing and jointing in C.M. 1:4 in
proper grade and level complete in all respect including
earth work and disposal of surplus earth within 0.5 Km
lead (Cost of steel/welded mesh etc. shall be paid extra).

33.1 40mm thick Sqm 303.00 275.00 10.18


33.2 Up to 60mm thick Sqm 375.00 341.00 9.97
33.3 Up to 80mm thick Sqm 460.00 418.00 10.05
33.4 Up to 115mm thick Sqm 569.00 517.00 10.06
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N

1 Earth work in excavation for foundation of structure


complete with all lift, dewatering shoring and shuttering
etc .including refilling of trenches in 25.mm layers,
ramming, watering and disposal of surplus soil within a
lead of 1000 meters, as per drawing and technical
specification.[MoRTH Specification : Clause : 304]

1.1 In ordinary Soil [MoRTH Specification : Clause : 301] 0

1.1.1 Depth up to 3m Cum. 64 58.00 10.34


1.1.2 Above 3m to 6m depth Cum 75 68.00 10.29
1.1.3 Above 6m depth Cum 89 81.00 9.88
1.2 In hard Soil [MoRTH Specification : Clause : 301] 0
1.2.1 Depth up to 3m Cum 85 77.00 10.39
1.2.2 Above 3m to 6m depth Cum 103 94.00 9.57
1.2.3 Above 6m depth Cum 116 105.00 10.48
1.3 In Ordinary/Soft rock [MoRTH Specification: Clause : 0
301]
1.3.1 If blasting is resorted to [MoRTH Specification : Clause : Cum 177 161.00
302] 9.94
1.3.2 If blasting is not resorted to Cum 432 393.00 9.92
1.4 In hard rock (requiring blasting) [MoRTH Cum 260 236.00
Specification : Clause :301,302] 10.17
1.5 In Hard rock (blasting prohibited) [MoRTH Cum 847 770.00
Specification : Clause :303] 10.00
1.6 In Marshy soil up to 3m.depth. [MoRTH Cum 171 155.00
Specification : Clause : 301] 10.32
1.7 Add Extra for dewatering if required :
1.7.1 Depth up to 3m Cum 10% 10% 0.00
1.7.2 Depth 3 to 6m Cum 20% 20% 0.00
1.7.3 Depth above 6m Cum 30% 30% 0.00
2 Sand filling and compaction by mechanical means in Cum 619.00 470.00 31.70
foundation trenches, in 150mm layers, with all lead and
lift, as per drawing and technical specification, to achieve
field density. [MoRTH Specification : Clause : 304]

3 Back filling behind abutment, wing wall and return wall, in


150mm layers, with mechanical compaction, complete
with all lead and lift, as per drawing and technical
specification. [MoRTH Specification : Clause : 304]

3.1 Gravelly material Cum 454.00 336.00 35.12


3.2 Sandy material Cum 539.00 539.00 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
4 Filter medium behind abutment, wing wall and return Cum 444.00 327.00 35.78
wall, complete as per drawing and technical
specification. (Same as R-7-20.3) [MoRTH
Specification : Clause: Clause:2504].
5 Brick masonry work in cement mortar 1:3, with Cum 2449.00 2386.00 2.64
mechanical mixer, in foundation (at any level) complete,
including all scaffolding etc., excluding pointing and
plastering, as per drawing and technical specification.
[MoRTH Specification : Section 1000,1300]

6 Stone masonry work in cement mortar 1:3 with


mechanical mixer for foundation (any level) complete,
including all scaffolding etc., excluding pointing and
plastering as per drawing and technical specification.
[MoRTH Specification: Section 1000,1400]

6.1 Coursed Rubble Masonry (first sort) Cum 2730.00 2271.00 20.21
6.2 Random Rubble Masonry (coursed/un-coursed). Cum 2272.00 2130.00 6.67
7 Structural cement concrete (Design Mix) in open
foundations, with form work, at any level.
Cement concrete for plain/reinforced concrete in open
foundation as per drawing and technical specification.
[MoRTH Specification : Section 1700(N)&1500(N)].
Using Batching Plant,Transit Mixture, and Concrete
Pump.
7.1 P.C.C.M-15 grade Cum 2793.00 2576.00 8.42
7.2 P.C.C.M-20 grade Cum 3095.00 2889.00 7.13
7.3 P.C.C.M-25 grade Cum 3378.00 3075.00 9.85
7.4 P.C.C.M-30 grade Cum 3401.00 3096.00 9.85
7.5 R.C.C.M-20 grade Cum 3119.00 2934.00 6.31
7.6 R.C.C.M-25 grade Cum 3406.00 3121.00 9.13
7.7 R.C.C.M-30 grade Cum 3415.00 3132.00 9.04
7.8 R.C.C.M-35 grade Cum 3478.00 3197.00 8.79
7.9 R.C.C.M-40 grade Cum 3473.00 3273.00 6.11
8 Providing and laying cutting edge of mild steel for well Tonne 51283.00 69585.00 -26.30
foundation at designed level complete as per drawing
technical specification :[MoRTH Specification : Section :
1200(N) & 1900(N)]
9 Plain/reinforced Cement concrete for well foundations at
designed level, complete with form work, as per drawing
and technical specification. Using Batching Plant, Transit
Mixture, and Concrete Pump.
Structural Concrete (Design mix) in well foundations
[MoRTH Specification: 1200(N), 1500(N),1700(N)]
9.1 Well Curb , including formwork etc.
9.1.1 R.C.C M-20 grade Cum 3389.00 3268.00 3.70
9.1.2 R.C.C.M-25 grade Cum 3846.00 3727.00 3.19
9.1.3 R.C.C.M-35 grade Cum 3965.00 3848.00 3.04
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
9.2 Well steining, including formwork etc.
9.2.1 P.C.C.M-15 Grade Cum 2955.00 2725.00 8.44
9.2.2 P.C.C.M-20 Grade Cum 3274.00 2996.00 9.28
9.2.3 R.C.C.M-20 Grade Cum 3107.00 3268.00 -4.93
9.2.4 P.C.C.M-25 Grade Cum 3391.00 3261.00 3.99
9.2.5 R.C.C.M-25 Grade Cum 3526.00 3280.00 7.50
9.2.6 P.C.C.M-30 Grade Cum 3421.00 3292.00 3.92
9.2.7 R.C.C M-30 Grade Cum 3438.00 3329.00 3.27
9.2.8 R.C.C M-35 Grade Cum 3635.00 3527.00 3.06
9.2.9 R.C.C M-40 Grade Cum 3681.00 3573.00 3.02
9.3 Bottom plug, including forming sump, protective
bounds, chiseling etc.
9.3.1 P.C.C.M-20 grade Cum 3145.00 3040.00 3.45
9.3.2 P.C.C.M-25 grade Cum 3311.00 3208.00 3.21
9.3.3 P.C.C.M-30 grade Cum 3345.00 3242.00 3.18
9.3.4 P.C.C.M-35 grade Cum 3417.00 3314.00 3.11
9.4 Intermediate plug, include extra protective works and
dewatering etc.
9.4.1 P.C.C.M-20 grade Cum 3014.00 2915.00 3.40
9.4.2 P.C.C.M-25 grade Cum 3174.00 3075.00 3.22
9.4.3 P.C.C.M-30 grade Cum 3205.00 3107.00 3.15
9.5 Top plug in Plain Cement Concrete, including extra
protective works and dewatering etc.
9.5.1 P.C.C.M-15 grade Cum 2686.00 2477.00 8.44
9.5.2 P.C.C.M-20 grade Cum 2977.00 2779.00 7.12
9.5.3 P.C.C.M-25 grade Cum 3083.00 2886.00 6.83
9.5.4 P.C.C.M-30 grade Cum 3110.00 2992.00 3.94
9.6 Well cap
9.6.1 R.C.C.M-20 grade Cum 2904.00 2800.00 3.71
9.6.2 R.C.C.M-25 grade Cum 3224.00 3122.00 3.27
9.6.3 R.C.C.M-30 grade Cum 3233.00 3131.00 3.26
9.6.4 R.C.C.M-35 grade Cum 3298.00 3197.00 3.16
9.6.5 R.C.C.M-40 grade Cum 3473.00 3372.00 3.00
10 Sinking of well, true and vertical, through all types of soil
and rock (other than pneumatic method of sinking),
complete as per drawing and technical specification.
[MoRTH Specification : 1200(N)]
10.1 Well of 6m external diameter
10.1.1 In Sandy soil)
10.1.1.1 Depth from 0-3 meters from cutting edge level. Meter 2841.00 2787.00 1.94
10.1.1.2 Beyond 3m up to 10m.depth, Meter 4150.00 4083.00 1.64
10.1.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.1.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.1.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.1.1.7 Add for dewatering if required
10.1.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.1.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.1.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.1.2 In Clayey soil.(Well of 6m. External diameter)
10.1.2.1 Depth from 0-3 meters from cutting edge level. Meter 4147.00 4086.00 1.49
10.1.2.2 Beyond 3m up to 10m.depth, Meter 8960.00 8837.00 1.39
10.1.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.1.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.1.2.7 Add for dewatering if required
10.1.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.1.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.1.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.1.3 In Soft rock. .(Well of 6m. External diameter)
10.1.3.1 Depth from 0-3 meters from cutting edge level. Meter 9993.00 9438.00 5.88
10.1.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.1.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.1.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.1.3.7 Add for dewatering if required
10.1.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.1.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.1.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.1.4 In Hard Rock.(Well of 6m. External diameter)
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.1.4.1 Depth from 0-3 meters from cutting edge level. Meter 11612.00 11500.00 0.97
10.1.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.1.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.1.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.1.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.1.4.7 Add for dewatering if required
10.1.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.1.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.1.4.7.3 Depth above 10m Meter 5% 5% 0.00
10.2 Well of 7m external diameter
10.2.1 In Sandy soil) . (Well of 7m. External diameter)
10.2.1.1 Depth from 0-3 meters from cutting edge level. Meter 4413.00 4346.00 1.54
10.2.1.2 Beyond 3m up to 10m.depth, Meter 6058.00 5977.00 1.36
10.2.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.2.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.2.1.7 Add for dewatering if required
10.2.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.2.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.2.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.2.2 In Clayey soil.(Well of 7m. External diameter)
10.2.2.1 Depth from 0-3 meters from cutting edge level. Meter 6058 5977.00 1.36
10.2.2.2 Beyond 3m up to 10m.depth, Meter 8800 8691.00 1.25
10.2.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.2.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.2.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.2.2.7 Add for dewatering if required
10.2.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.2.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.2.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.2.3 In Soft rock. .(Well of 7m. External diameter)
10.2.3.1 Depth from 0-3 meters from cutting edge level. Meter 9277.00 9500.00 -2.35
10.2.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.2.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.2.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.2.3.7 Add for dewatering if required
10.2.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.2.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.2.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.2.4 In Hard Rock.(Well of 7m. External diameter)
10.2.4.1 Depth from 0-3 meters from cutting edge level. Meter 12966.00 12655.00 2.46
10.2.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.2.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.2.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.2.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.2.4.7 Add for dewatering if required
10.2.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.2.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.2.4.7.3 Depth above 10m Meter 5% 5% 0.00
10.3 Well of 8m external diameter
10.3.1 In Sandy soil)
10.3.1.1 Depth from 0-3 meters from cutting edge level. Meter 5460.00 5378.00 1.52
10.3.1.2 Beyond 3m up to 10m.depth, Meter 6776.00 7000.00 -3.20
10.3.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.3.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.3.1.7 Add for dewatering if required
10.3.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.3.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.3.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.3.2 In Clayey soil.(Well of 8m. External diameter)
10.3.2.1 Depth from 0-3 meters from cutting edge level. Meter 7403.00 8250.00 -10.27
10.3.2.2 Beyond 3m up to 10m.depth, Meter 9396.00 10450.00 -10.09
10.3.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.3.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.3.2.7 Add for dewatering if required
10.3.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.3.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.3.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.3.3 In Soft rock. .(Well of 8m. External diameter)
10.3.3.1 Depth from 0-3 meters from cutting edge level. Meter 10308.00 11000.00 -6.29
10.3.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.3.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.3.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.3.3.7 Add for dewatering if required
10.3.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.3.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.3.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.3.4 In Hard Rock.(Well of 8m. External diameter)
10.3.4.1 Depth from 0-3 meters from cutting edge level. Meter 12750.00 14300.00 -10.84
10.3.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.3.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.3.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.3.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.3.4.7 Add for dewatering if required
10.3.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.3.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.3.4.7.3 Depth above 10m Meter 5% 5% 0.00
10.4 Well of 9m external diameter
10.4.1 In Sandy soil)
10.4.1.1 Depth from 0-3 meters from cutting edge level. Meter 5498.00 5410.00 1.63
10.4.1.2 Beyond 3m up to 10m.depth, Meter 7451.00 7341.00 1.50
10.4.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.4.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.4.1.7 Add for dewatering if required
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.4.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.4.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.4.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.4.2 In Clayey soil.(Well of 9m. External diameter)
10.4.2.1 Depth from 0-3 meters from cutting edge level. Meter 7775.00 8687.00 -10.50
10.4.2.2 Beyond 3m up to 10m.depth, Meter 10155.00 11282.00 -9.99
10.4.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.4.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.4.2.7 Add for dewatering if required
10.4.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.4.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.4.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.4.3 In Soft rock. .(Well of 9m. External diameter)
10.4.3.1 Depth from 0-3 meters from cutting edge level. Meter 13242.00 12829.00 3.22
10.4.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.4.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.4.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.4.3.7 Add for dewatering if required
10.4.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.4.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.4.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.4.4 In Hard Rock.(Well of 9m. External diameter)
10.4.4.1 Depth from 0-3 meters from cutting edge level. Meter 14846.00 14475.00 2.56
10.4.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.4.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.4.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.4.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.4.4.7 Add for dewatering if required
10.4.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.4.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.4.4.7.3 Depth above 10m Meter 5% 5% 0.00
10.5 Well of 10m external diameter
10.5.1 In Sandy soil)
10.5.1.1 Depth from 0-3 meters from cutting edge level. Meter 6734.00 6639.00 1.43
10.5.1.2 Beyond 3m up to 10m.depth, Meter 7827.00 7710.00 1.52
10.5.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.5.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.5.1.7 Add for dewatering if required
10.5.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.5.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.5.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.5.2 In Clayey soil.(Well of 10m. External diameter)
10.5.2.1 Depth from 0-3 meters from cutting edge level. Meter 8364.00 9464.00 -11.62
10.5.2.2 Beyond 3m up to 10m.depth, Meter 9789.00 12290.00 -20.35
10.5.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.5.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.5.2.7 Add for dewatering if required
10.5.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.5.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.5.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.5.3 In Soft rock. .(Well of 10m. External diameter)
10.5.3.1 Depth from 0-3 meters from cutting edge level. Meter 13555.00 13126.00 3.27
10.5.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.5.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.5.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
10.5.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20% 0.00

10.5.3.7 Add for dewatering if required


10.5.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.5.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.5.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.5.4 In Hard Rock.(Well of 10m. External diameter)
10.5.4.1 Depth from 0-3 meters from cutting edge level. Meter 17819.00 17432.00 2.22
10.5.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.5.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.5.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.5.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20% 0.00

10.5.4.7 Add for dewatering if required


10.5.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.5.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.5.4.7.3 Depth above 10m Meter 5% 5% 0.00
10.6 Well of 11m external diameter
10.6.1 In Sandy soil)
10.6.1.1 Depth from 0-3 meters from cutting edge level. Meter 15809.00 13233.00 19.47
10.6.1.2 Beyond 3m up to 10m.depth, Meter 16330.00 16081.00 1.55
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.6.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.6.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
10.6.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
10.6.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20% 0.00

10.6.1.7 Add for dewatering if required


10.6.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.6.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.6.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.6.2 In Clayey soil.(Well of 11m. External diameter)
10.6.2.1 Depth from 0-3 meters from cutting edge level. Meter 13900.00 13682.00 1.59
10.6.2.2 Beyond 3m up to 10m.depth, Meter 19961.00 19641.00 1.63
10.6.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.6.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.6.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.6.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.6.2.7 Add for dewatering if required
10.6.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.6.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.6.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.6.3 In Soft rock. .(Well of 11m. External diameter)
10.6.3.1 Depth from 0-3 meters from cutting edge level. Meter 30517 29554.00 3.26
10.6.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.6.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.6.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.6.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.6.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.6.3.7 Add for dewatering if required
10.6.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.6.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.6.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.6.4 In Hard Rock.(Well of 11m. External diameter)
10.6.4.1 Depth from 0-3 meters from cutting edge level. Meter 40497.00 39661.00 2.11
10.6.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.6.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.6.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.6.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.6.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.6.4.7 Add for dewatering if required
10.6.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.6.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.6.4.7.3 Depth above 10m Meter 5% 5% 0.00
10.7 Well of 12m external diameter
10.7.1 In Sandy soil)
10.7.1.1 Depth from 0-3 meters from cutting edge level. Meter 32164.00 31734.00 1.36
10.7.1.2 Beyond 3m up to 10m.depth, Meter 35504.00 34972.00 1.52
10.7.1.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.7.1.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.7.1.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.7.1.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.7.1.7 Add for dewatering if required
10.7.1.7.1 Depth up to 3m Meter 5% 5% 0.00
10.7.1.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.7.1.7.3 Depth above 10m Meter 5% 5% 0.00
10.7.2 In Clayey soil.(Well of 12m. External diameter)
10.7.2.1 Depth from 0-3 meters from cutting edge level. Meter 34376.00 33882.00 1.46
10.7.2.2 Beyond 3m up to 10m.depth, Meter 51733.00 51060.00 1.32
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.7.2.3 Beyond 10m up to 20m depth : Add 5% for every Meter 5% 5%
additional meter depth of sinking over the rate of sinking
for the previous meter. 0.00
10.7.2.4 Beyond 20m up to 30m depth: Add 7.5% for every Meter 7.50% 7.50%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.7.2.5 Beyond 30m up to 40m depth: Add 10% for every Meter 10% 10%
additional meter depth of sinking over the rate of sinking
for the previous meter 0.00
10.7.2.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20%
0.00
10.7.2.7 Add for dewatering if required
10.7.2.7.1 Depth up to 3m Meter 5% 5% 0.00
10.7.2.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.7.2.7.3 Depth above 10m Meter 5% 5% 0.00
10.7.3 In Soft rock.
10.7.3.1 Depth from 0-3 meters from cutting edge level. Meter 73002.00 70861.00 3.02
10.7.3.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.7.3.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.7.3.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
10.7.3.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
10.7.3.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20% 0.00

10.7.3.7 Add for dewatering if required


10.7.3.7.1 Depth up to 3m Meter 5% 5% 0.00
10.7.3.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.7.3.7.3 Depth above 10m Meter 5% 5% 0.00
10.7.4 In Hard Rock.(Well of 12m. External diameter)
10.7.4.1 Depth from 0-3 meters from cutting edge level. Meter 95238.00 93604.00 1.75
10.7.4.2 Beyond 3m up to 10m depth : Add 5.00% for every Meter 5.00% 5.00% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.7.4.3 Beyond 10m up to 20m depth : Add 7.5% for every Meter 7.50% 7.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter.
10.7.4.4 Beyond 20m up to 30m depth: Add 10.00% for every Meter 10.00% 10.00% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
10.7.4.5 Beyond 30m up to 40m depth: Add 12.50% for every Meter 12.50% 12.50% 0.00
additional meter depth of sinking over the rate of sinking
for the previous meter
10.7.4.6 Kent ledge(supports, loading arrangement, labour etc.) Meter 20% 20% 0.00

10.7.4.7 Add for dewatering if required


10.7.4.7.1 Depth up to 3m Meter 5% 5% 0.00
10.7.4.7.2 Depth 3 to10m Meter 5% 5% 0.00
10.7.4.7.3 Depth above 10m Meter 5% 5% 0.00
11 Sand filling with compaction in wells complete as per Cum 619.00 470 31.70
level on drawing and technical specification. [MoRTH
Specification : Clause 1207(N)]
12 Providing and laying Steel reinforcement at any level in
foundation complete as per drawing and technical
Specification.[MoRTH Specification : Section: 1600(N)]

12.1 HYSD bar reinforcement Tonnes 45284.00 58697.00 -22.85


12.2 Mild Steel reinforcement Tonnes 39678.00 57538.00 -31.04
13 Pneumatic sinking of wells complete as per drawing and Lump --- ---
technical specification.[MoRTH Specification : Section Sum
1200(N)]
14 Providing structural steel liner for curbs and seining for Tonnes 46907.00 69585.00 -32.59
wells including fabricating and setting out as per detailed
drawing .[MoRTH Specification : Section
1200(N)&1900(N)]
15 Board/cast-in-situ R.C.C piles complete as per drawing
and technical specification. [MoRTH Specification :
Section 1100,1600&1700(N)] Using Batching
Plant,Transit Mixture, and Concrete Pump.
15.1 750 mm dia piles (excluding reinforcement)
15.1.1 Concrete M25 in R.C.C (Design mix) Meter 3508.00 3419.00 2.60
15.1.2 Concrete M30 in R.C.C (Design mix) Meter 3558.00 3498.00 1.72
15.1.3 Concrete M35 in R.C.C (Design mix) Meter 3625.00 3577.00 1.34
15.2 1000mm dia pile (excluding reinforcement)
15.2.1 Concrete M25 in R.C.C (Design mix) Meter 5738.00 5629.00 1.94
15.2.2 Concrete M30 in R.C.C (Design mix) Meter 5868.00 5755.00 1.96
15.2.3 Concrete M35 in R.C.C (Design mix) Meter 5966.00 5880.00 1.46
15.3 1200mm dia piles (excluding reinforcement)
15.3.1 Concrete M25 in R.C.C (Design mix) Meter 7225.00 7027.00 2.82
15.3.2 Concrete M30 in R.C.C (Design mix) Meter 7452.00 7252.00 2.76
15.3.3 Concrete M35 in R.C.C (Design mix) Meter 7600.00 7476.00 1.66
16 Reinforced cement concrete in pile cap complete at all
levels with steel formwork etc. as per drawing and
technical specification. Using Batching Plant,Transit
Mixture, and Concrete Pump.
16.1 Design mix concrete. [MoRTH Specification :
1100(N),1500(N), 1700(N)]
16.1.1 M20 grade Cum 2921.00 2817.00 3.69
CHAPTER FOUNDATIONS
R11
Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %
2009 2008 VARIATIO
N
16.1.2 M25 grade Cum 3229.00 3127.00 3.26
16.1.1 M30 grade Cum 3264.00 3162.00 3.23
16.1.2 M35 grade Cum 3348.00 3247.00 3.11
16.1.2 M40 grade Cum 3600.00 3500.00 2.86
16.3 If the bottom level of pile cap is below the water table,
add20% extra for under water concreting/ dewatering/
shoring, [MoRTH Specification: 1100(N),1500(N),
1700(N)]
16.4 If the pile cap rests on ground add for leveling course. Cum 2613.00 2413.00 8.29
[MoRTH Specification : 100(N),1500(N),1700(N)]
17 Driven cast-in-place true and vertical R.C.C piles
complete as per drawing and technical specification.
[MoRTH Specification : Section : 1100,1600,1700 (N)]

Concrete M35 in R.C.C (Design mix)


17.1 750 mm dia piles Meter 2456.00 2356.00 4.24
17.1 1000mm dia piles Meter 3850.00 3800.00 1.32
17.1 1200 mm dia piles Meter 5660.00 5540.00 2.17
18 Driven precast true and vertical R.C.C piles complete as
per drawing and technical specification.[MoRTH
Specification : Section : 1100,1600,1700 (N)]
18.1 550mm dia piles (excluding reinforcement)
18.1.1 Concrete M25 in R.C.C (Design mix) Meter 1690.00 1536.00 10.03
18.1.2 Concrete M30 in R.C.C (Design mix) Meter 1749.00 1590.00 10.00
18.1.3 Concrete M35 in R.C.C (Design mix) Meter 1815.00 1650.00 10.00
18.2 500mm dia piles (excluding reinforcement)
18.2.1 Concrete M25 in R.C.C (Design mix) Meter 1412.00 1284.00 9.97
18.2.2 Concrete M30 in R.C.C (Design mix) Meter 1478.00 1344.00 9.97
18.2.3 Concrete M35 in R.C.C (Design mix) Meter 1544.00 1404.00 9.97
18.3 450mm dia piles (excluding reinforcement)
18.3.1 Concrete M25 in R.C.C (Design mix) Meter 1122.00 1020.00 10.00
18.3.2 Concrete M30 in R.C.C (Design mix) Meter 1175.00 1068.00 10.02
18.3.3 Concrete M35 in R.C.C (Design mix) Meter 1241.00 1128.00 10.02
18.4 750mm dia piles (excluding reinforcement)
Concrete M35 in R.C.C (Design mix) Meter 2042.00 1856.00 10.02
18.5 1200mm dia piles (excluding reinforcement)
Concrete M35 in R.C.C (Design mix) Meter 3455.00 3141.00 10.00
19 Steel Reinforcement for Board/Cast-in situ piles as per
design (Rate may taken from the relevant item of
reinforcement in foundation work)
19.1 H Y S D steel Tonne 45284.00 58697.00 -22.85
19.1 Mild Steel. Tonne 39678.00 57538.00 -31.04
20 Load testing of piles.
20.1 Initial and routine test for vertical load testing. Tonne 440.00 400.00 10.00
load
20.2 For lateral load testing of pile Each 15840.00 14400.00 10.00
pile
CHAPTER SUB STRUCTURE
: R-12

Item No. Item Description Unit Rate (Rs.) Rate (Rs.)


2009 2008

1 Brick Masonry work in cement mortar 1:3 for


substructure complete, with scaffolding, excluding
pointing and plastering, as per drawing and technical
specification. [MoRTH Specification: Section 1300].
1.1 Up to 5 meter height Cum 2463.00 2365.00
1.2 For height above 5 meters Cum 2460.00 2399.00
2 Stone masonry work in cement mortar 1:3 for
substructure complete, with scaffolding excluding
pointing and plastering as per drawing and technical
specification [MoRTH Specification: Section 1400]
2.1 Coursed Rubble Masonry (Ist sort)
2.1.1 Up to 5 meter height Cum 2407.00 2245.00
2.1.2 For height above 5 meter Cum 2400.00 2280.00
2.2 Random Rubble masonry (coursed/un-coursed)
2.2.1 Up to 5 meter height Cum 2335.00 2192.00
2.2.2 For height above 5 meter Cum 2386.00 2232.00
3 Structural Cement concrete for plain concrete/ reinforced
concrete for substructure at any level, complete as per
drawing and technical specification. Using Batching
Plant, Transit Mixture, and Concrete Pump.

3.1 Design mix concrete- [MoRTH Specification: Clause


1500(N), & 1700(N)] P.C.C
3.1.1 P.C.C.M15 grade
3.1.1.1 Up to 5 meter height Cum 2955.00 2725.00
3.1.1.2 For 5m to 10m height Cum 2841.00 2841.00
3.1.1.3 Above 10m height Cum 2957.00 2957.00
3.1.2 P.C.C.M.20 grade
3.1.2.1 Up to 5 meter height Cum 3274.00 3057.00
3.1.2.2 For 5m to 10m height Cum 3204.00 3204.00
3.1.2.3 Above 10m height Cum 3351.00 3351.00
3.1.3 P.C.C.M25 grade
3.1.3.1 Up to 5 meter height Cum 3391.00 3261.00
3.1.3.2 For 5m to 10m height Cum 3515.00 3380.00
3.1.3.3 Above 10m height Cum 3669.00 3528.00
3.1.4 P.C.C.M.30 grade
3.1.4.1 Up to 5 meter height Cum 3421.00 3292.00
3.1.4.2 For 5m to 10m height Cum 3545.00 3411.00
3.1.4.3 Above 10m height Cum 3701.00 3561.00
3.2 Design mix concrete - [MoRTH Specification : Clause
1500&1700] R.C.C
3.2.1 R.C.C.M20 grade , including formwork.
3.2.1.1 Up to 5 meter height Cum 3107.00 2996.00
3.2.1.2 For 5m to 10m height Cum 3220.00 3105.00
CHAPTER SUB STRUCTURE
: R-12

Item No. Item Description Unit Rate (Rs.) Rate (Rs.)


2009 2008

3.2.1.3 Above 10m height Cum 3361.00 3241.00


3.2.2 R.C.C.M25 grade, including formwork.
3.2.2.1 Up to 5 meter height Cum 3526.00 3417.00
3.2.2.2 For 5m to 10m height Cum 3641.00 3528.00
3.2.2.3 Above 10m height Cum 3814.00 3969.00
3.2.3 R.C.C.M30 grade, including formwork
3.2.3.1 Up to 5 meter height Cum 3438.00 3472.00
3.2.3.2 For 5m to 10m height Cum 3535.00 3566.00
3.2.3.3 Above 10m height Cum 3672.00 3708.00
3.2.4 R.C.C.M35 grade
3.2.4.1 Up to 5 meter height Cum 3635.00 3527.00
3.2.4.2 For 5m to 10m height Cum 3714.00 3604.00
3.2.4.3 Above 10m height Cum 3833.00 3720.00
3.2.5 R.C.C.M40 grade
3.2.5.1 Up to 5 meter height Cum 3864.00 3864.00
3.2.5.2 For 5m to 10m height Cum 3953.00 3953.00
3.2.5.3 Above 10m height Cum 4107.00 4107.00
4 Pointing of any design with cement mortar (1:3)on Brick / 10 Sqm 317.00 308.00
Stone work in substructure at any height [MoRTH
Specification: Clause 1309]
5 Plaster on new surface with cement mortar (1:3) Sqm 69.00 63.00
including racking of joint etc. complete fine finished
20mm thick.
6 Steel reinforcement in substructure complete.[MoRTH
Specification : Section 1600(N)]
6.1 HYSD bar reinforcement Tonne 45334.00 58697.00
6.2 MS reinforcement Tonne 39394.00 57538.00
7 Supplying, fitting and fixing in position true to line and Tonne 196.00 245.00
level Cast Steel Rocker Bearing confirming to IRC:83 Capacity
(Part-I -Section IX) complete including all accessories as
per drawing and technical specification. [MoRTH
Specification : Section :2000(N)]
8 Supplying fitting and fixing in position true to line and Tonne 294.00 410.00
level Forged Steel Roller Bearing confirming to IRC:83 Capacity
(Part-I-Section IX) complete including all accessories as
per drawing and technical specification. [MoRTH
Specification Section 2000(N)]
CHAPTER SUB STRUCTURE
: R-12

Item No. Item Description Unit Rate (Rs.) Rate (Rs.)


2009 2008

9 Supplying fitting and fixing in position true to line and Tonne 384.00 384.00
level Sliding Plate Bearing with PTFE surface sliding on Capacity
stainless steel complete including all accessories as per
drawing and technical specification and BS:5400,
Section 9.1 &9.2 (for PTFE) [MoRTH Specification
Section 2000 (N)
10 Supplying fitting and fixing in position true to line and Cm3 0.80 0.80
level, Elastromeric Bearing confirming to IRC: 83 (Part II-
Section IX) complete including all accessories as per
drawing and technical specification.[MoRTH
Specification Section 2000(N)]
11 Supplying fitting and fixing in position true to line and Tonne 490.00 490.00
level, POT-PTFE Bearing suitable for biaxial movement Capacity
as per drawing and BS:5400 Sections 9.1 & 9.2 [MoRTH
Specification Section 2000(N)]
12 Supplying fitting and fixing in position true to line and Tonne 384.00 384.00
level, Sliding Plate Bearing with stainless steel plate Capacity
sliding on stainless steel plate with mild steel matrix
[MoRTH Specification : Section 2000(N)]
13 Providing A.C pipe Weep holes 100mm dia in Meter 44.00 40.00
Masonry/Plain Concrete/.Reinforced Concrete abutment,
wing wall/return wall complete as per drawing and
technical specification.[MoRTH Specification Clause
2205]
14 Providing A.C pipe Weep holes 150mm dia in Meter 66.00 60.00
Masonry/Plain Concrete/.Reinforced Concrete abutment,
wing wall/return wall complete as per drawing and
technical specification.[MoRTH Specification Clause
2205]
15 Providing and laying Expansion Joint complete as per
drawing and technical specification
15.1 With 20mm thick Galvanized mild steel plate.[MoRTH Meter 1071.00 974.00
Specification : Section 2100(N), 2600(N)]
15.2 Providing & fixing 2 mm thick corrugated copper plate in Meter 1675.00
expansion joint complete as per drawing & Technical
Specification.
15.4 Providing & fixing 20 mm thick compressible fibre board Meter 131.00 524.00
in expansion joint complete as per drawing & Technical
Specification.
15.5 Providing & Fixing in position 20mm thick moldedulded Meter 80.00 263.00
joint filler in expansion joint complete.
15.6 Providing and filling joint sealing compound -Coarse Meter per 10.00 10.00
sand with bitumen (6% by weight) Cms
depth
CHAPTER SUB STRUCTURE
: R-12

Item No. Item Description Unit Rate (Rs.) Rate (Rs.)


2009 2008

16 Providing and laying of an elastomeric slab steel Meter 10181.00 10179.00


expansion joint, catering to right or skew (less than 20
deg., moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed b

16.1 Providing and laying of compression seal joint consisting Meter 2078.00
of steel armoured nosing at two edges of the joint gap
suitably anchored to the deck concrete and a preformed
chloroprene elastomer or closed cell foam joint sealer
compressed and fixed into the jo
16.2 Providing and laying of a strip seal expansion joint Meter 8908.00
catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring
16.3 Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal Meter 8485.00
expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier
16.4 Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal Meter 9699.00
expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
%
VARIATI
ON

4.14
2.54

7.22
5.26

6.52
6.90

8.44
0.00
0.00

7.10
0.00
0.00

3.99
3.99
4.00

3.92
3.93
3.93

3.70
3.70
%
VARIATI
ON

3.70

3.19
3.20
-3.91

-0.98
-0.87
-0.97

3.06
3.05
3.04

0.00
0.00
0.00
2.92

9.52

-22.77
-31.53
-20.00

-28.29
%
VARIATI
ON

0.00

0.00

0.00

0.00

10.00

10.00

9.96

-75.00

-69.58

0.00
%
VARIATI
ON

0.02
CHAPTER SUPERSTRUCTURE
: R-13
Item No. Item Description Unit Rate (Rs.) Rate (Rs.)
2009 2008

1 Structural Cement concrete for reinforced concrete/PSC


in superstructure complete including steel formwork,
scaffolding etc. as per drawing and technical
specification. Using Batching Plant, Transit Mixture, and
Concrete Pump.
Design mix concrete [MoRTH Specification
1500(N)&1700(N)]
1.1 M 20 grade
1.1.1 Solid slab superstructure
1.1.1.1 Height up to 5m Cum 3225.00 3231.00
1.1.1.2 Height from 5m to 10m Cum 3360.00 3365.00
1.1.1.3 Height above 10m Cum 3494.00 3500.00
1.1.2 T-beam and slab Superstructure
1.1.2.1 Height up to 5m Cum 3360.00 3365.00
1.1.2.2 Height from 5m to 10m Cum 3494.00 3500.00
1.1.2.3 Height above 10m Cum 3628.00 3634.00
1.2 M 25 grade
1.2.1 Solid slab superstructure
1.2.1.1 Height up to 5m Cum 3581.00 3588.00
1.2.1.2 Height from 5m to 10m Cum 3730.00 3738.00
1.2.1.3 Height above 10m Cum 3880.00 3887.00
1.2.2 T-beam and slab Superstructure
1.2.2.1 Height up to 5m Cum 3730.00 3738.00
1.2.2.2 Height from 5m to 10m Cum 3880.00 3887.00
1.2.2.3 Height above 10m Cum 4029.00 4037.00
1.3 M 30 grade
1.3.1 Solid slab superstructure
1.3.1.1 Height up to 5m Cum 3626.00 3633.00
1.3.1.2 Height from 5m to 10m Cum 3777.00 3784.00
1.3.1.3 Height above 10m Cum 3928.00 3936.00
1.3.2 T-beam and slab Superstructure
1.3.2.1 Height up to 5m Cum 3777.00 3784.00
1.3.2.2 Height from 5m to 10m Cum 3928.00 3936.00
1.3.2.3 Height above 10m Cum 4079.00 4087.00
1.4 M 35 grade
1.4.1 Solid slab superstructure
1.4.1.1 Height up to 5m Cum 3656.00 3664.00
1.4.1.2 Height from 5m to 10m Cum 3811.00 3819.00
1.4.1.3 Height above 10m Cum 3966.00 3974.00
1.4.2 T-beam and slab Superstructure
1.4.2.1 Height up to 5m Cum 3811.00 3918.00
1.4.2.2 Height from 5m to 10m Cum 3966.00 3974.00
1.4.2.3 Height above 10m Cum 4121.00 4129.00
1.4.3 Box girder and balanced cantilever superstructure
1.4.3.1 Height up to 5m Cum 4276.00 4285.00
1.4.3.2 Height from 5m to 10m Cum 4586.00 4595.00
CHAPTER SUPERSTRUCTURE
: R-13
Item No. Item Description Unit Rate (Rs.) Rate (Rs.)
2009 2008

1.4.3.3 Height above 10m Cum 4895.00 4906.00


1.5 M 40 grade
1.5.1 Solid slab/Voided slab superstructure
1.5.1.1 Height up to 5m Cum 3829.00 3837.00
1.5.1.2 Height from 5m to 10m Cum 3992.00 3999.00
1.5.1.3 Height above 10m Cum 4154.00 4162.00
1.5.2 T-beam, slab , precast girders and slab for
Superstructure including transportation and launching up
to 40m span.
1.5.2.1 Height up to 5m Cum 3992.00 3999.00
1.5.2.2 Height from 5m to 10m Cum 4154.00 4162.00
1.5.2.3 Height above 10m Cum 4316.00 4325.00
1.5.3 Box girder and balanced cantilever superstructure
1.5.3.1 Height up to 5m Cum 4478.00 4487.00
1.5.3.2 Height from 5m to 10m Cum 4803.00 4812.00
1.5.3.3 Height above 10m Cum 5128.00 5137.00
1.6 M 45 grade
1.6.1 Solid slab/Voided slab superstructure
1.6.1.1 Height up to 5m Cum 3980.00 3988.00
1.6.1.2 Height from 5m to 10m Cum 4151.00 4160.00
1.6.1.3 Height above 10m Cum 4323.00 4332.00
1.6.2 T-beam, slab , precast girders and slab for Superstructure
including transportation and launching up to 40m span.

1.6.2.1 Height up to 5m Cum 4151.00 4160.00


1.6.2.2 Height from 5m to 10m Cum 4323.00 4332.00
1.6.2.3 Height above 10m Cum 4494.00 4504.00
1.6.3 Box girder and balanced cantilever superstructure
1.6.3.1 Height up to 5m Cum 4666.00 4675.00
1.6.3.2 Height from 5m to 10m Cum 5009.00 5019.00
1.6.3.3 Height above 10m Cum 5352.00 5363.00
1.7 M 50 grade ( PSC )
1.7.1 Box girder and balanced cantilever superstructure
1.7.1.1 Height up to 5m Cum 4810.00 4821.00
1.7.1.2 Height from 5m to 10m Cum 5167.00 5178.00
1.7.1.3 Height above 10m Cum 5523.00 5535.00
1.8 M 55 grade (PSC )
1.8.1 Box girder and balanced cantilever superstructure
1.8.1.1 Height up to 5m Cum 5091.00 5102.00
1.8.1.2 Height from 5m to 10m Cum 5468.00 5480.00
1.8.1.3 Height above 10m Cum 5845.00 5858.00
2 Providing and laying HYSD bar reinforcement at any Tonne 45812.00 58697.00
level in superstructure complete as per drawing and
technical specification .[MoRTH Specification 1600(N)]
CHAPTER SUPERSTRUCTURE
: R-13
Item No. Item Description Unit Rate (Rs.) Rate (Rs.)
2009 2008

3 Providing and laying High tensile steel wires/strands at Tonne 93153.00 103877.00
any level including all accessories for stressing, stressing
operations and grouting complete as per drawing and
technical specification.[MoRTH Specification 1800(N)]

4 Reinforced cement concrete wearing coat at any level


including formwork and reinforcement completed as per
drawing and technical specification. [MoRTH
Specification 2202(N),1500(N)&1700(N)]
4.1 M 30 grade Cum 6661.00 7668.00
4.1 M 35 grade Cum 6703.00 7710.00
4.1 M 40 grade Cum 6873.00 7880.00
5 Providing and laying 12mm thick bitumen mastic wearing Sqm 157.00 180.00
coat with bitumen of grade S35 as per Table 500-27, 14-
17% by weight on prepared base including the coarse
aggregate as per table 500-29, and lime stone powder
as filler, complete including tack coat. [MoRTH
specification clause 515]
6 Providing and laying reinforced Cement Concrete grade
M30 design mix railing complete as per drawing and
technical specification. [MoRTH Specification:
1500,1600&1700]
6.1 Pre-cast R.C.C railing Meter 1151.00 1411.00
6.2 Cast in situ Meter 1114.00 1362.00
7 Providing and fixing Mild steel railing, galvanized or Meter 1910.00 2615.00
painted, complete as per drawing and technical
specification. [MoRTH Specification: 1900(N) & 2703(N)]

8 PCC M-15 grade leveling course below approach slab Cum 2495.00 2477.00
complete as per drawing and MoRTH specifications
clause 14.10.
9 Reinforced cement concrete approach slab including
reinforcement and formwork complete as per drawing
and MoRTH specifications section 1500, 1600, 1700,
2704.
9.1 M 30 grade Cum 5371.00 5086.00
9.2 M 35 grade Cum 5454.00 5169.00
9.3 M 40 grade Cum 5537.00 5252.00
10 P&F on culverts/ bridges deck rain water spouts made of Each 1048.00 391.00
cast iron as per MoRTH specification complete
%
VARIATIO
N

-0.19
-0.15
-0.17

-0.15
-0.17
-0.17

-0.20
-0.21
-0.18

-0.21
-0.18
-0.20

-0.19
-0.18
-0.20

-0.18
-0.20
-0.20

-0.22
-0.21
-0.20

-2.73
-0.20
-0.19

-0.21
-0.20
%
VARIATIO
N
-0.22

-0.21
-0.18
-0.19

-0.18
-0.19
-0.21

-0.20
-0.19
-0.18

-0.20
-0.22
-0.21

-0.21
-0.22

-0.19
-0.20
-0.21

-0.23
-0.21
-0.22

-0.22
-0.22
-0.22

-21.95
%
VARIATIO
N

-10.32

-13.13
-13.06
-12.78

-12.78

-18.43
-18.21

-26.96

0.73

5.60
5.51
5.43
168.03
CHAPTER RIVER TRAINING AND PROTECTION WORK
: R-14

Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %


2009 2008 VARIATI
ON

1 Providing and laying specified Apron complete as per


drawing and technical specification. [MoRTH
Specification : Clause: 2503]
1.1 Boulder/Quarry stone not less than 40 kg (Specific Cum 563.00 531.00 6.03
gravity not less than 2.65)
1.2 Boulder/Quarry stone not less than 40 kg , in wire crates, Cum 1416.00 1403.00 0.93
3x1.5x1.25 meter with wire diameter not less than 4mm
mesh not more than 150mm.
1.3 Cement concrete blocks (in M-15 grade) Size Cum 2647.00 2628.00 0.72
0.50x0.50x0.50m each complete with form work etc.
[MoRTH Specification: Clause:2504]
2 Providing and laying graded stone aggregate Filter Cum 400.00 381.00 4.99
Material underneath pitching on slopes complete as per
drawing and technical Specification [MoRTH
Specification : Clause 2504]
3 Providing and laying Pitching on slopes complete as per
drawing and technical specification [MoRTH
Specification Clause 2504]
3.1 With R.R Stone, weighing not less than 40 Kg, thickness Cum 563.00 531.00 6.03
not less than 150mm (Specific gravity not less than 2.65)

3.2 With Cement Concrete block M15 grade, complete with Cum 2647.00 2628.00 0.72
form work etc. [MoRTH Specification: Clause:
2504,1700]
4 Providing and laying Flooring Rubble stone/ C.C M15
block over bedding complete as per drawing and
technical specification. [MoRTH Specification: Clause
2505,1700]
4.1 Rubble stone laid in cement mortar 1:3 Cum 2439.00 2381.00 2.44
4.2 Cement concrete block in M15 grade including form work Cum 2518.00 2460.00 2.36

4.3 If cement concrete (M15) bedding is provided Cum 3486.00 3076.00 13.33
5 Supply of wire crates in required size made of hot dipped sqm 220.00 200.00 10.00
G I wire 4 mm dia having mesh of 10 cm X10 cm surface
area
6 Labour Charges --
6.1 For dumping of boulders / stones including hand packing Cum 199.00 181.00 9.94
where necessary
6.2 For stone pitching for slopes Cum 199.00 181.00 9.94
6.3 For dry stone masonry for toe walls Cum 199.00 181.00 9.94
6.4 For laying boulders in bed Cum 103.00 94.00 9.57
6.5 For filling wire crates made of 5mm dia G I wire by stone Cum 259.00 235.00 10.21
in specified position at site including 5 mm dia G I wire
for binding complete in all respect .
CHAPTER RIVER TRAINING AND PROTECTION WORK
: R-14

Item No. Item Description Unit Rate (Rs.) Rate (Rs.) %


2009 2008 VARIATI
ON

7 Providing and construction of a gabian structure for Cum 1758.00 1598.00 10.01
retaining earth with segments of wire crates of size 7 m x
3 m x 0.6 m each divided into 1.5 m compartments by
cross netting, made from 4 mm galvanized steel wire @
32 Kg per 10 Sqm having minimum tensile strength of
300 Mpa conforming to IS: 280 and galvanizing coating
conforming to IS : 4826 , woven into mesh with double
twist, mesh size not exceeding 100 x 100 mm , filled with
boulders with least dimension of 200 mm , all loose ends
to be tied with 4 mm galvanized steel wire complete as
per MoRTH specification clause 2503.3

8 Providing and constructing gabian structures for erosion Cum 3357.00 3052.00 9.99
control, river training works and protection works with
wire crates of size 2 m x 1 m x 0.3 m each divided into 1
m compartments by cross netting, made from 4 mm
galvanized steel wire @ 32 Kg per 10 Sqm having
minimum tensile strength of 300 Mpa conforming to IS :
280 and galvanizing coating conforming to IS: 4826 ,
woven into mesh with double twist, mesh size not
exceeding 100 mm x 100 mm filled with boulders with
least dimension of 200 mm, all loose ends to be securely
tied with 4 mm galvanized steel wire complete as per
MoRTH specification clause 2503.3
CHAPTER REPAIR & REHABILITATION
: R-15
Item No. Item Description Unit Rate (Rs.) Rate (Rs.)
2009 2008

1 Removal of existing cement concrete wearing coat Sqm 187.00 170.00


manually or with the help of jack hammers including its
disposal within a lead of 1000 meters, complete as per
technical specification without causing any detrimental
effect to any part of the bridge structure (MoRTH
specifications clause 2809,100)
2 Grunting (Minimum density 2T/Cum) on concrete/ Sqm 1326.00 1205.00
masonry surface with wire mesh and cement mortar 1:3,
applied with compressor after cleaning surface and
applying with epoxy complete as per technical
specification. [MoRTH Specification : Clause: 2807]
3 Providing and inserting nipples with approved fixing 0.00
compound after drilling holes for grouting as per
technical specification including subsequent cutting/
removal and sealing of the holes as necessary of nipples
after completion of grouting with:
3.1 Cement grout [MoRTH Specification : Clause: 2806] Each 64.00 58.00
3.2 Epoxy grout [MoRTH Specification: Clause: 2803] Each 101.00 92.00
4 Sealing of cracks by injection process through nipples 0.00
complete with material and labour as per drawing and
technical specification [MoRTH Specification:
Clause:2803]
4.1 Cement grout Kg 86.00 78.00
4.2 Cement mortar (1:1) grout Kg 83.00 75.00
4.3 Epoxy grout Kg 2200.00 2000.00
5 Carrying out repair of RCC M-30 railing to bring it to the Mtr 83.00 75.00
original shape complete in all respect
6 Repair to steel railing to bring it to the original shape Mtr 187.00 170.00
complete in all respect
7 Repair of concrete crash barrier with cement concrete of Mtr 96.00 87.00
M-30 grade by cutting and trimming the damaged portion
to a regular shape, cleaning the area to be repaired
thoroughly, applying cement concrete after erection of
proper form work
8 Replacement of damaged mild steel railing including Mtr 70.00 64.00
dismantling old railing & disposal of dismantled material

9 Replacement of damaged concrete railing including Mtr 83.00 75.00


dismantling old railing & disposal of dismantled material

10 Replacement of bearings complete as per technical No. 58071.00 52792.00


specifications including lifting of super structures span by
jacking up from below I.e. by placing the jacks on pier/
abutment caps for span length of 30 Meter
CHAPTER REPAIR & REHABILITATION
: R-15
Item No. Item Description Unit Rate (Rs.) Rate (Rs.)
2009 2008

11 Rectification of bearings as per technical specifications No. 31451.00 28592.00


including lifting of super structures span by jacking up
from below I.e. by placing the jacks on pier/ abutment
caps for span length of 30 Meter

12 Providing and laying strip seal expansion joint catering to Mtr 9798.00 8907.00
maximum horizontal movement up to 70mm complete as
per approved drawing and IRC specifications including
acceptance testing as specified to be installed under
supervision of a specialist manufacturer (MoRTH Sp."
2600) including arrangement of traffic during
replacement of joint.

13 Repairs of Hair-line (Non structural) cracks by chiseling Kg 370.00 336.00


the surface making a groove of 25mm x25mm or 12mm x
12mm as per requirement and priming the surface with
Nitroprimer-25 (Epoxy primer) or equivalent followed by
sealing the cracks with Nitro mortars (High strength
reinstatement pre packed Epoxy mortar) or equivalent
and finishing off epoxy product having following
properties.

(i) Compressive strength 60 N/Sqmm (28 days) 0.00


(ii) Flexural strength 20 N/Sqmm (28 days) 0.00
(iii) Tensile strength 10 N/Sqmm (28 days) 0.00
14 Providing protection coatings on the well caps and piers Sqm 550.00 500.00
coating of surface with Into Cote ET-550 (Epoxy Tar
based high performance resin coating or equivalent) and
having specific gravity mixed (1.40) approximately) and
volume solids mixed 66% and recommended thickness
of 350 microns (DFT) applied in two coats (approx. 175
microns per coat) after cleaning the surface thoroughly.

15 Providing and filling joint filler compound confirming to Rmt 12.00 11.00
IS: 1834 for each 25mm width & 25mm depth
%
VARIATI
ON

10.00

10.04

10.34
9.78

10.26
10.67
10.00
10.67

10.00

10.34

9.38

10.67

10.00
%
VARIATI
ON

10.00

10.00

10.12

10.00

9.09
Chapter Description Unit Labour Including Including Including
Code for cost of M- cost of M- cost of M-
fixing 10 Mix 15 Mix 20 Mix
only Dand / Dand / Kerb Dand/Kerb
Kerb Complete Complete
Complete

3.1 10 x 15 cm Mtr. 8 55 58 63
3.2 15 x 15 cm Mtr. 8 75 89 95
3.3 20 x 20 cm Mtr. 9 120 159 169
3.4 20 x 25 cm Mtr. 9 150 196 211
3.5 (20 x 25)/2 x 30 Mtr. 12 200 265 285
cm
3.6 (20.5 x 25)/2 x Mtr. 12 220 270 289
30 cm

You might also like