You are on page 1of 601

Technical Assistance Consultant’s Report

Project Number: 34339-02 (TA 4881)


April 2008

Islamic Republic of Pakistan: Renewable Energy


Policy Formulation and Capacity Development of the
Alternative Energy Development Board

Prepared by Hagler Bailly Pakistan and Mercados EMI, Spain

For Alternative Energy Development Board


Islamic Republic of Pakistan

This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and
ADB and the Government cannot be held liable for its contents. (For project preparatory technical
assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Hagler Bailly Pakistan
Associated with PA Consulting Group Technical, Management, and Economic Counsel

Ref: L9164PRP April 3, 2009

Mr Arif Alauddin
Chief Executive Officer
Alternative Energy Development Board (AEDB)
3, Street 8, F 8/3
Islamabad 44000

Subject: ADB TA 4881-PAK: Final Project Reports

Dear Mr Alauddin,

It gives us great pleasure to submit the final reports for ‘ADB TA 4881-PAK: Renewable
Energy Policy Formulation and Capacity Building of AEDB’, for which Hagler Bailly
Pakistan and Mercados EMI, Spain were engaged by the Asian Development Bank under
Contract No. S/70-128 on June 27, 2007.
As you are aware, the draft final reports were submitted on December 20, 2008, and an
extended review period was designated for receiving comments and feedback, which
concluded on February 28, 2008. We hope the final reports—two copies of which are
enclosed herewith in printed form as well as on a CD, which also contains the RES-E pricing
model developed for the study—will meet your requirements.
I would also like to take this opportunity to thank you for the keen interest and support
extended by AEDB for the completion of this important assignment, and hope that it will
prove to be beneficial for the effective development of the renewable energy sector in
Pakistan.

Sincerely,

Dr Jamil Masud
Director/NTL

Hagler Bailly Pakistan (Pvt.) Ltd.


39, Street 3, E7, Islamabad 44000, Pakistan
Tel: (92 51) 261 0200-07, Fax: (92 51) 261 0208-09
mail@haglerbailly.com.pk, www.haglerbailly.com.pk
Hagler Bailly Pakistan

Encl.:

1. Formulation of Pakistan’s Renewable Energy Policy for On-grid and Off-grid Areas
(R9FR1PRP, dated March 11, 2009)
2. AEDB’s Capacity Assessment and Institutional Needs
(R9CA1PRP, dated March 11, 2009)
3. Pakistan RES-E Model (ver. 1)

cc:

1. Dr Parvez Butt, Member (Energy), Planning Commission, Government of Pakistan,


Islamabad (1 printed copy, 1 CD)
2. Mr Sean O'Sullivan, Director, CWID, Asian Development Bank (ADB), Manila
(3 printed copies, 1 CD)
3. Mr Rune Stroem, Country Director, Asian Development Bank (ADB), Islamabad
(1 printed copy, 1 CD)

2
ADB TA 4881­PAK: 
Renewable Energy Policy Formulation and Capacity Development of AEDB 

Final Report 

Formulation of Pakistan’s 
Renewable Energy Policy 
for On­grid and Off­grid Areas  

Hagler Bailly Pakistan

and

Mercados EMI, Spain

 
Asian Development Bank
Manila
 

Final Report 

Formulation of Pakistan’s 
Renewable Energy Policy 
for On­grid and Off­grid Areas  

Contents 

Abbreviations and Acronyms ....................................................................................... iii 
1  Introduction ............................................................................................................. 1 
2  Proposal for Pakistan’s Medium Term On‐Grid RES‐E Policy ..................................... 4 
2.1  Background ............................................................................................................ 4 
2.2  Extension of RE Short‐term Policy ......................................................................... 5 
2.3  Medium Term RES‐E Policy Highlights ................................................................... 5 
2.3.1  Target Markets .......................................................................................... 5 
2.3.2  Implementation Period ............................................................................. 6 
2.3.3  Consistency Across Policies ....................................................................... 6 
2.3.4  Tariff Incentives ......................................................................................... 6 
2.3.4.1  Selected Approach .................................................................... 6 
2.3.4.2  Structure of Tariffs .................................................................... 7 
2.3.4.3  Indexation for Upfront Tariffs ................................................... 7 
2.3.5  Type of Contracts ...................................................................................... 7 
2.3.6  Allocation of Network Investment Costs ................................................... 7 
2.3.7  Mandatory RE Power Purchasing .............................................................. 7 
2.3.8  Direct Sales ................................................................................................ 7 
2.3.9  Allocation of Carbon Credits...................................................................... 7 
2.3.10  Land and Site Access .................................................................................. 8 
2.3.11  Incentives Other Than Tariffs .................................................................... 8 
2.3.12  Roles of Institutions ................................................................................... 8 
2.3.13  Institutional, Legal, and Regulatory Consents ........................................... 8 
2.3.14  Procedural Requirements .......................................................................... 8 
3  Proposal for Pakistan’s Medium Term Off‐Grid RES‐E Policy .................................... 9 
3.1  Background ............................................................................................................ 9 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  i
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.2  Medium Term Off‐grid RE Policy Recommendations ............................................ 9 
3.2.1  Target Markets .......................................................................................... 9 
3.2.2  Implementation Period ........................................................................... 10 
3.2.3  Rationale and Institutional Organization ................................................ 10 
3.2.4  Targets and Incentives ............................................................................. 13 
3.2.5  Project Funding ........................................................................................ 13 
3.2.6  Pricing ...................................................................................................... 13 
3.2.7  Incentives Other Than Tariffs .................................................................. 14 
3.2.8  Roles of Institutions ................................................................................. 14 
3.2.9  Institutional, Legal and Regulatory Consents .......................................... 14 
3.2.10  Performance Monitoring and Enforcement ............................................ 15 
3.2.11  Allocation of Carbon Credits.................................................................... 15 

Annex I:  Policy for Development of Renewable Energy for Power Generation in 
Pakistan (2009‐2014) ................................................................................ 17 

Annex II:  AEDB Position Paper 1: Proposal for Pakistan’s Medium Term  
On‐Grid RES‐E Policy ................................................................................. 57 

Annex III:  AEDB Position Paper 2: Proposal for Pakistan’s Medium Term  
Off‐Grid RES‐E Policy ................................................................................ 67 

Annex IV:  Working Paper 1: Relevant International Experience in Incentives for 
Renewable Energy: The Case of the EU‐25 and Selected Countries ........... 79 

Annex V:  Working Paper 2: Review of Pakistan’s Short‐term Policy for  
Development of Renewable Energy ........................................................ 153 

Annex VI:  Working Paper 3: Pakistan’s Energy Sector: Market, Growth and  
Supply Options ....................................................................................... 189 

Annex VII:  Working Paper 4: Study of Costs and Potential Penetration of  
On‐grid RE under Different Policies ........................................................ 241 

Annex VIII: Working Paper 5: Development of On‐grid RE in Pakistan:  
Medium Term Policy Recommendations ................................................ 301 

Annex IX:  Working Paper 6: Medium‐term Off‐grid RES‐E Policy Assessment ......... 325 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  ii
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

A  Ampere 
AC  Alternating current 
ACGR  Average compound growth rate 
ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
Ah  Ampere‐hour 
AJK  Azad Jammu and Kashmir 
AKRSP  Aga Khan Rural Support Programme 
API  American Petroleum Institute 
APL  Asia Pipelines Limited 
ARL  Attock Refinery Limited 
bbl  Barrel 
Bcfd  Billion cubic feet per day 
BOI  Board of Investment 
BOO  Build, own, and operate 
BOO  Build‐Own‐Operate 
BP  Basis point 
BPL  Basic poverty line 
BRIC  Brazil, Russia, India, and China 
BST  Bulk supply tariff 
Btu  British thermal unit 
C&F  Carriage and freight 
CAA  Civil Aviation Authority 
CapEx  Capital Expenditures 
CBO  Community‐based organization 
CCGT  Combined cycle gas turbine 
CDM  Clean Development Mechanism 
CER  Certified Emissions Reduction 
cf  Cubic feet 
CFL  Compact fluorescent lamp 
CH4  Methane 
CHASHNUPP  Chashma Nuclear Power Plant 
CHP  Combined heat and power 
cm2  Square centimeter 
CNE  Comisión Nacional de Energía 
CNG  Compressed natural gas 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  iii
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

CO2  Carbon dioxide 
COD  Commercial operations date 
CP  Contract price 
CPI  Consumer Price Index 
CPPA  Central Power Purchasing Agency 
DC  Direct current 
DDGS  Decentralized Distribution Generation Systems 
DGG  Directorate General, Gas 
DGM  Directorate General, Mineral 
DGO  Directorate General, Oil 
DGPC  Directorate General, Petroleum Concessions 
DISCO  Distribution company 
DNA  Designated national agency 
DSM  Demand‐side management 
DVC  Damodar Valley Corporation 
E&P  Exploration and production 
E10  10% ethanol blended gasoline 
EAC  Electricity Authority of Cambodia 
EAD  Economic Affairs Division 
ED  Excise duty 
EDB  Engineering Development Board 
EHV  Extra high voltage 
EIA  Environmental impact assessment 
ENERCON  National Energy Conservation Centre 
EPA  Energy Purchase Agreement, or 
Environmental Protection Agency 
EPC  Engineering, procurement, and construction 
EPD  Environmental Protection Department 
EPE  Energy Policy for Europe 
ERTIC  Programa de Electrificación Rural y Tecnologías de la Información y 
Comunicación 
EU  European Union 
FATA  Federally Administered Tribal Areas 
FBR  Federal Board of Revenue 
FEC  Final energy consumption 
FFV  Flex‐fuel vehicle 
FIT  Feed‐in tariff 
FO  Furnace oil 
FOB  Freight on board 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  iv
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

FX  Foreign exchange 
FY  Financial year 
GDP  Gross domestic product 
GEF  Global Environment Facility 
GENCO  Generation company 
GES  Growth environment score 
GHG  Greenhouse gas 
GoP  Government of Pakistan 
GSA  Gas Sales Agreement 
GTZ  Gesellschaft für Technische Zusammenarbeit GmbH 
GW  Gigawatt 
GWh  Gigawatt‐hour 
ha  Hectare 
HDIP  Hydrocarbon Development Institute of Pakistan 
HDR  Hot dry rock 
HEB  Hydro Electric Board 
HH  Household 
HOBC  High octane blending compound 
HSD  High‐speed diesel 
HSE  Health, safety, and environment 
HSFO  high‐sulfur fuel oil 
HV  High voltage 
I&P  Irrigation and power 
IA  Implementation Agreement 
ICT  Islamabad Capital Territory, or 
information and communication technology  
IEE  Initial Environmental Examination 
IFEM  Inland freight equalization margin 
IFI  International financial institution 
IGCC  Integrated gasification combined cycle 
IIE  Initial environmental examination 
IPDS  Irrigation & Power Department, Sindh 
IPP  Independent power producer 
IREDA  Indian Renewable Energy Development Agency 
IRR  Internal rate of return 
ISCC  Integrated Solar Combined Cycle 
JP  Jet propulsion 
KANUPP  Karachi Nuclear Power Plant 
kcal  Thousand calories 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  v
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

KESC  Karachi Electric Supply Corporation 
kg  Kilogram 
kha  Thousand hectares 
km  Kilometer 
kT  Thousand tonnes 
kV  Kilovolt 
kVArh  Kilovolt Ampere reactive‐hour 
kW  Kilowatt 
kWe  Kilowatt electrical 
kWh  Kilowatt‐hour 
kWp  Kilowatt peak 
KWSB  Karachi Water and Sewerage Board 
lb  Pound 
LDO  Light diesel oil 
LIBOR  London Interbank Offered Rate 
LMM  Locally manufactured machinery 
LNG  Liquefied natural gas 
LoI  Letter of Intent 
LoS  Letter of Support 
LPG  Liquefied petroleum gas 
LRMC  Long run marginal cost 
m  Meter 
MC  Marginal cost 
MGCL  Mari Gas Company Limited 
MMscfd  Million standard cubic feet per day 
MMTPA  Million tonnes per annum 
MNES  Ministry of Non‐Conventional Energy Sources 
MoE  Ministry of Environment 
MoFR  Ministry of Finance and Revenue 
MOGAS  Motor gasoline 
MoPNR  Ministry of Petroleum and Natural Resources 
MoST  Ministry of Science and Technology 
MoWP  Ministry of Water and Power 
MoWP  Ministry of Water and Power 
MPC  Marginal private cost 
MS  Motor spirit 
MSB  Marginal social benefit 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  vi
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

MSC  Marginal social cost, or  
  Medium‐Term Service Contracts 
MSW  Municipal solid waste 
MT  Metric tonne 
MTDF  Medium Term Development Framework 
MTOE  Million tonnes of oil equivalent 
MW  Megawatt 
MWe  Megawatt electrical 
MWh  Megawatt‐hour 
NA  Northern Areas, or 
Not applicable/available 
NAPWD  Northern Areas Public Works Department 
NARC  National Agriculture Research Council 
NEPRA  National Electric Power Regulatory Authority 
NGO  Non‐governmental organization 
NHA  National Highway Authority 
NOx  Nitrous oxides 
NPO  National Productivity Organization 
NREL  US National Renewable Energy Laboratory 
NRL  National Refinery Limited 
NTDC  National Transmission and Dispatch Company 
NTRC  National Transport Research Centre 
NWFP  Northwest Frontier Province 
O&M  Operations and maintenance 
OBA  Output‐based aid 
OECD  Organization for Economic Cooperation and Development 
OGDC  Oil and Gas Development Corporation 
OGEA  Off‐grid Electrification Agency 
OGEAC  Off‐grid Electrification Account 
OGRA  Oil and Gas Regulatory Authority 
OMC  Oil marketing company 
OpEx  Operational expenditure 
P&D  Planning and Development 
PAEC  Pakistan Atomic Energy Commission 
Pak EPA  Pakistan Environment Protection Agency 
PARC  Pakistan Agriculture Research Council 
PARCO  PakArab Refinery Company 
PASMA  Pakistan Sugar Mills Association 
PC  Project Committee 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  vii
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

PCRET  Pakistan Council for Renewable Energy Technologies 
PCSIR  Pakistan Council for Scientific and Industrial Research 
PCU  Project Coordination Unit 
PED  Primary energy demand 
PEPCO  Pakistan Electric Power Company 
PER  Rural Electrification Program (Chile) 
PHA  Pakistan Housing Authority 
PIAC  Pakistan International Airlines Corporation 
PIB  Pakistan Investment Bonds 
PIDC  Pakistan Industrial Development Corporation 
PLF  Plant load factor 
PMD  Pakistan Meteorological Department 
PNAC  Pakistan National Accreditation Council 
PNRA  Pakistan Nuclear Regulatory Authority 
POE  Panel of Experts 
PPA  Power Purchase Agreement 
PPC  Private Power Cell 
PPDB  Punjab Power Development Board 
PPDCL  Punjab Power Development Company Limited 
PPEPCA  Pakistan Petroleum Exploration and Production Companies Association 
PPIB  Private Power and Infrastructure Board 
PPL  Pakistan Petroleum Ltd. 
PR  Pakistan Railway 
PRL  Pakistan Refinery Limited 
PROINFA  Programa de Incentivo às Fontes Alternativas de Energia Elétrica 
PSDP  Public Sector Development Programme 
PSO  Pakistan State Oil Company 
PSQA  Pakistan Standards and Quality Control Authority 
PTC  Production tax credit 
PV  Photovoltaic 
PWD  Public Works Department 
R&D  Research and development 
R&M  Renovation and modernization 
RE  Renewable energy 
REC  Rural Electrification Companies 
RED   Renewable Energy Development 
REDB   Renewable Energy Distribution Backbone 
REDSIP  Renewable Energy Development Sector Investment Program 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  viii
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

REF  Rural Electrification Fund 
RES  Renewable energy source 
RES‐E  Renewable energy sourced‐electricity 
RET  Renewable energy technology 
RFP  Request for proposals 
RGGVY  Rajiv Gandhi Grameen Vidyutikaran Yojana 
ROE  Return‐on‐equity 
RON  Research octane number 
RoR  Run‐of‐river 
RoW  Right of Way 
RPS  Renewable portfolio standard 
SAARC  South Asian Association for Regional Cooperation 
SBP  State Bank of Pakistan 
SC  Self consumption 
SCA  Sindh Coal Authority 
Scf  Standard cubic feet 
SEB  State Electricity Board 
SECP  Securities and Exchange Commission of Pakistan 
SERC  State Electricity Regulatory Commission 
SHS  Solar home system 
SHYDO  Sarhad Hydel Development Organization 
SMEDA  Small and Medium Enterprises Development Authority 
SNGPL  Sui Northern Gas Pipelines Ltd. 
SO2  Sulfur dioxide 
SOx  Oxides of sulfur 
SRO  Statutory regulatory ordinance 
SS  Small‐scale 
SSGCL  Sui Southern Gas Company Ltd. 
SWERA  Solar and Wind Energy Resource Assessment 
T&D  Transmission and distribution 
TA  Technical assistance 
TCE  Technical Control Entity 
Tcf  Trillion cubic feet 
TPA  Tonnes per annum 
TRANSCO  Transmission Company 
TWh  Terawatt‐hour 
UNEP  United Nations Environment Programme 
US  United States 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  ix
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

VC  Variable cost 
VEI  Village Electrification Infrastructure 
W  Watt 
WACC  Weighted average cost of capital 
WAPDA  Water and Power Development Authority 
WHS  Wind home system 
WPI  Wholesale Price Index 
WTE  Waste‐to‐energy 
WTG  Wind turbine generator 
WTP  Willingness‐to‐pay 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  x
 

1 Introduction 
Renewable  energy  development  in  Pakistan  has  been  conceived  under  a  phased, 
evolutionary approach constituting a strategic policy implementation roadmap adopted 
by  the  Government  of  Pakistan  (GoP).  The  initial  phase  (i.e.,  the  ‘short‐term‘)  has 
involved lenient policy measures and strong incentives in order to attract investment in 
this  relatively  new  business  area,  remove  existing  barriers  to  project  implementation, 
and ‘hand‐hold’ reasonable‐sized pioneering projects through to successful commercial 
operation.1  
The  goal  of  this  report,  the  final  output  under  the  Asian  Development  Bank  (ADB)  TA 
4881‐PAK: Renewable Energy Policy Formulation and Capacity Development of AEDB, is 
to help design a sound approach for the development of a medium‐term (i.e., five‐year) 
RE policy for Pakistan that would succeed the current short‐term RE policy in 2009 and 
help create a conducive environment for the growth of the domestic RE industry to at 
least 2014, and upon which future policy directions could then be evolved. 
In  order  to  develop  the  new  policy  proposal,  the  TA  consultants  have  completed  the 
following tasks: 

• An  assessment  of  key  challenges,  threats,  and  opportunities  faced  by  RE  and 
related technologies in Pakistan. This assessment was carried out by analyzing 
the  potential  of  RE  supply  by  comparison  with  alternative  (conventional) 
technologies. 
• A review of the existing RE institutional framework in Pakistan, identifying the 
current  and  future  roles  of  all  stakeholder  institutions  which  could  have  an 
important role or impact in RE promotion or regulation in the country. 
• A  critical  review  of  past  and  present  policies  (especially  the  2006  RE  Policy), 
strategies,  and  incentive  mechanisms  currently  in  place,  and  success  in 
promoting  renewable  energy  development  in  Pakistan  achieved  thus  far. 
Where  problems  or  bottlenecks  were  detected  or  envisaged  in  this  regard, 
possible solutions or actions to overcome these impediments were proposed. 
• A  medium  term  policy  package  of  guidelines,  regulations,  and  incentives  for 
grid‐connected2  RE  power  generation  and  sale  from  priority,  feasible  RE 
technologies. 
• Policy  and  action  guidelines  for  the  development  and  implementation  of 
dispersed  RE  use  in  standalone  or  isolated  grid  configurations,  including 
programmatic, sustainable rural RE energy supply schemes.  

                                                       
1
  Under  the  GoP’s  Policy  for  Development  of  Renewable  Energy  for  Power  Generation,  2006,  issued  by  the 
Alternative Energy Development Board (AEDB), hereinafter referred to as the 2006 RE Policy. 
2
  For the purposes of RE policy terminology, the term ‘grid’ is meant to imply either national or regional electricity 
T&D networks operated by the NTDC/CPPA and/or DISCOs of 11 kV or higher voltage.  Isolated, community‐based 
local distribution networks are considered ‘off‐grid’. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  1
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• A set of comparative economic and pricing criteria for determining optimum RE 
rates for grid‐connected applications, accounting for externalities and marginal 
avoided costs of conventional alternatives. 
• Determination  of  overall  institutional  arrangements  at  the  federal,  provincial, 
and local levels required for the proper implementation of policy and regulatory 
framework,  with  well‐defined  capacity  requirements,  institutional  roles,  and 
procedural arrangements that eliminate ambiguity, delays, and discretion faced 
by investors and end‐users in routine RE application and operation. 
This report is organized as follows: 

• The main body of the report includes a short summary of the policy proposal 
that  was  suggested  by  the  consultants,  discussed  with  stakeholders  at  a 
national  workshop,  and  presented  in  detail  to  the  AEDB,  which  provided  its 
consent in the form of two position papers.  
• Annex I comprises proposed text for a draft policy document, for consideration 
and  approval  by  the  Government  of  Pakistan  as  its  official  medium‐term  RE 
policy statement.  
• Annexes II and III contain the position papers issued by the AEDB, indicating its 
consent to the proposed policy approach. 
• Annex  IV  presents  the  consultants’  evaluation  of  the  development  (and 
potential)  of  renewable  energy  resources  in  Europe  and  selected  emerging 
countries  (China,  India,  and  Brazil),  focusing  on  current  policy  schemes  for 
promoting  renewable  energy  sources,  specifically  for  electricity  generation.  It 
also contains an analysis of various incentive mechanisms and their impact on 
the deployment of different RE technologies, with a special emphasis on widely 
developed options, such as wind, hydro, biogas and biomass, which can operate 
on a grid‐connected, commercial scale.  
• Annex V presents the consultant’s evaluation of Pakistan’s current, short‐term 
RE  policy  2006  (applicable  over  2007  to  2009)  for  the  development  of 
renewable  energy  for  on‐grid  power  generation,  including  a  comprehensive 
analysis of the incentive structure it creates and its performance regarding the 
main RE sources it targets. The focus of the short‐term policy is on RE options 
amenable to immediate commercial development, i.e., small hydro, wind, and 
biomass‐based  power  generation.  This  phase  is  marked  with  beneficial  risk‐
sharing  and  attractive  tariffs  for  developers  so  as  to  enable  a  reasonable 
generation  capacity  to  be  installed  as  ‘first‐of‐kind’  RE  projects  in  the  private 
sector, that can then serve as successful business and technology‐assimilation 
demonstrators.  
• Annex  VI  presents  an  overview  of  Pakistan’s  energy  sector  and  its 
organizational structure, prospects for its growth and anticipated constraints on 
primary  supplies,  and  possible  future  options  and  strategies  that  the  country 
may  adopt  in  order  to  provide  for  the  energy  needs  of  a  rapidly  developing 
economy.  The  purpose  of  this  study  is  to  provide  estimates  of  anticipated 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  2
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

growth in the country’s energy demand, a comparative evaluation of different 
conventional energy supply options available to it, and the circumstances under 
which such needs can be met, especially in terms of electrical power.  
• Annex VII presents an economic assessment of renewable energy deployment 
options in Pakistan, in order to fine‐tune the tools required for the design of a 
successful  medium‐term  RE  policy  for  the  country.  More  specifically,  the 
objective  of  this  annex  is  two‐fold:  firstly,  to  evaluate  the  cost  structures  of 
renewable  energy  sourced‐electricity  (RES‐E)  in  Pakistan,  classifying  different 
renewable sources by the marginal cost of tapping them; secondly, to analyze 
the social and private costs and the potential penetration of each type of RES‐E 
under different policy environments. The model provided in this paper should 
allow  policy  makers  to  move  forward  on  a  more  sound  analytical  basis  that 
allows Pakistan to set feed‐in tariffs, based on avoided cost analysis, for on‐grid 
RES‐E. 
• Annex VIII presents the consultants’ draft proposal for the design of a medium 
term  policy  for  the  development  of  on‐grid  RES‐E  in  Pakistan.    This  proposal 
takes into account the analyses presented in Annexes IV to VII, and has been 
the  basis  for  stakeholder  discussions  and  development  of  the  AEDB  Position 
Paper on medium term on‐grid RES‐E development. 
• Annex IX presents the consultants’ assessment and proposal for the design of a 
medium  term  policy  framework  for  the  development  of  off‐grid  RES‐E  in 
Pakistan. This analysis takes into account some critical issues regarding off‐grid 
renewable energy  services,  selected  relevant  international  experience,  and  an 
assessment of the overall costs implied in the ensuing policy recommendations. 
This document presents general guidelines for formulating a detailed medium 
term  off‐grid  RES‐E  policy  approach  for  Pakistan  that  has  been  the  basis  for 
stakeholder  discussions  and  development  of  the  AEDB  Position  Paper  on 
medium term off‐grid RE development 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  3
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2 Proposal for Pakistan’s Medium Term On­Grid RES­E 
Policy 
2.1 Background 
Our studies (see Annex VII) show that the economic penetration of on‐grid RE power in 
Pakistan should be around 17 TWh per annum by 2020. This would be approximately 7% 
of  total  grid‐based  electrical  power  generation  expected  for  that  year.  Almost  60%  of 
this  future  RE  share  would  be  comprised  of  hydel  plants  that  are  much  cheaper  than 
conventional  fossil  fuel‐based  generation.    The  fact  that  any  capacity  approaching  this 
share is not currently under development indicates that some strong barriers to RES‐E 
investment may exist in the country, especially if we consider that the marginal cost of 
RES‐E is about USD 75/MWh while the cost of generation based on FO is more than USD 
125/MWh.  There  therefore  appears  to  be  a  very  strong  economic  signal  favoring  the 
development  of  RE,  and  it  can  thus  be  concluded  that  some  impediments  are 
responsible for the current lackluster state of RE deployment in the country.  
A  national  on‐grid  RES‐E  policy  should  be  based  on  a  social  assessment  of  costs  and 
benefits. The analysis of natural penetration based on private costs alone represents a 
limited subset of such an analysis. Market failures appear hamper the development of 
about 8 TWh per year of RE in 2020, and so an economic incentive mechanism needs to 
be put in place (assuming that all other barriers will have been removed by then). Under 
social  cost  assessment,  hydel,  biomass,  biogas  and  wind  energy  plants  are  required  to 
generate, in order to replace CCGTs—as a matter of fact, all FO‐based generation would 
need  to  be  replaced,  as  well  as  around  15%  of  gas‐based  generation,  by  2020.  If  the 
policy  to  achieve  these results  is  properly  defined  and  implemented,  the  social  wealth 
(total surplus) that may be created in Pakistan would be about USD 2.1 billion per year. 
Several  symptoms  exist  that  indicate  potential  problems  in  achieving  these  RE 
penetration  goals  unless  policy  elements  are  suitably  adjusted  (see  Annex  VI).  One  of 
the  critical  issues  is  the  existing  dual  mechanism  offered  by  the  regulator,  NEPRA,  for 
setting tariffs for RES‐E projects in Pakistan. In terms of its formulation, the current tariff 
system  for  unsolicited  RE  proposals  is  based  on  a  ‘cost‐plus’  approach.    The  cost‐plus 
computation  requires  a  case‐by‐case  determination  of  the  applicable  tariff  for  every 
single producer.  From the regulator’s point of view, the advantage of this methodology 
is  its  ability  to  reduce  infra‐marginal  rents  (i.e.,  producers’  surplus)  down  to  zero  and, 
therefore,  maximize  the  consumers’  surplus.    Nevertheless,  this  approach  presents 
several major shortcomings, which can be summarized as follows: 

• Investors,  taking  advantage  of  asymmetries  in  project‐related  information 


access,  can  ‘game’  against  the  mechanism  to  enhance  their  infra‐marginal 
rents. 
• It  decreases  the  financial  incentive  to  invest  in  RES‐E  technologies,  as 
developers  are  explicitly  deprived  of  most  of  the  infra‐marginal  rents  (the 
previous point notwithstanding).   

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  4
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• It  increases  in  the  administrative  burden  in  processing  projects  and  verifying 
the cost structures in each case. 
This  approach  has  been  adopted  in  Pakistan  so  far  in  order  to  help  reduce  the 
developer’s  risk,  since  it  guarantees  an  ROE  of  at  least  15%.    While  it  is  true  that  this 
method reduces some of the risks to the developer, it is also true that it eliminates any 
additional incentive to develop these types of projects and can make tariff negotiations 
protracted  and  contentious—which  appears  exactly  to  have  happened  with  respect  to 
the RE IPP experience in Pakistan so far.   
Additionally,  available  international  evidence  shows  that  feed‐in  (upfront)  tariffs  are 
perhaps  the  most  successful  incentive  mechanism  for  developing  RE  capacity. 
International  experience  (see  Annex  IV)  also  shows  that  grid  access,  administrative 
issues,  and  uncertainties  with  respect  to  the  incentive  mechanisms  are  as  relevant  as 
tariffs as far as fostering RE capacity installation is concerned. Moreover, RE technology‐
wise  feed‐in  tariff  would  offer  the  most  economical,  ‘least‐cost’  power  generation  mix 
for the country in the medium term and beyond, and would maximize the social surplus 
created  within  society  through  the  avoided  costs  of  more  expensive  alternatives.  Such 
fixed,  non‐negotiable  tariffs  would  help  circumvent  the  prolonged  rate  negotiations, 
introduce  an  element  of  competition  and  urgency  in  project  implementation,  ensure 
that all commercially feasible RE technologies are simultaneously developed, provide an 
economically viable basis for the regulator to determine sustainable RE pricing, and help 
prioritize available ‘least‐cost’ and ‘best‐site’ RE development on a fast track. 

2.2 Extension of RE Short­term Policy 
This report recommends that the short‐term on‐grid 2006 RE Policy should be officially 
extended to 2009 from its originally stipulated expiry date of June 31, 2008, as appears 
de facto to be the case.  This is required in order to allow projects that are presently at 
an  advanced  processing  stage  to  achieve  financial  closure  under  existing  policy 
stipulations,  as  well  as  to  afford  a  reasonable  timeframe  for  stakeholders  to  confer 
about  and  familiarize  themselves  with  the  medium  term  policy  approach  proposed 
herein.  

2.3 Medium Term RES­E Policy Highlights 
2.3.1 Target Markets 
The  scope  of  this  policy  is  grid‐connected  power  generation  fueled  by  renewable 
resources.  ‘On‐grid  RES‐E’  includes  the  following  technologies,  for  individual  installed 
project capacity greater than 1 MW: 

• Small hydro up to 50 MW 
• PV and solar thermal energy for power generation 
• Wind power generation 
• Municipal solid WTE power 
• Landfill methane recovery, and 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  5
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Bioenergy,  resulting  from  anaerobic  biogas  digestors,  pyrolytic  biomass 


gasification, co‐firing, cogeneration, etc. 

2.3.2 Implementation Period 
The medium term RES‐E policy should be applicable from 2009 to at least 2014, as we 
recognize  that  incentives‐based  policies  require  at  a  minimum  five  years  of  sustained 
promotion  in  order  to  be  successful;  policy  incentives  must  remain  stable  and  assured 
over  a  reasonably  extended  period  in  order  for  investor  confidence  to  build  up, 
supportive  institutional  capacity  to  develop,  and  implementation  bottlenecks  to  be 
gradually and systematically removed. 

2.3.3 Consistency Across Policies 
An  RES‐E  project  that  achieves  financial  closure  before  the  onset  of  the  forthcoming 
medium term policy phase should continue to be guaranteed all the incentives, terms, 
and conditions defined in the presently applicable 2006 RE Policy over the tenure of its 
respective PPA. This approach ensures the consistency and stability of an RE deployment 
climate from the perspective of both investors and power purchasers, as well as other 
relevant stakeholders. 

2.3.4 Tariff Incentives 

2.3.4.1 Selected Approach 
Our proposal for determining bulk RE‐based power procurement tariffs is:  

• Set  upfront  tariffs  for  each  RES‐E  technology  based  on  the  ‘avoided‐cost’  for 
those technologies whose marginal cost is lower than the avoided social cost.  
NEPRA  will  need  to  set  technology‐wise  feed‐in  tariffs  based  on  the 
characteristics  of  the  selected  RES‐E  technologies  (‘supply  curve  analysis’),  
bounded  by  the  range  obtained  from  the  use  of  private  and  social  avoided 
costs. This means for small‐scale hydel, biomass, biogas, and wind, tariffs would 
range between approximate USD 75‐100/MWh (see Annex VII).   
• Set upfront tariffs for each technology based on the marginal cost of providing 
the quota set by the GoP for those technologies whose marginal cost is higher 
than  avoided  social  cost.  An  upfront  tariff  is  also  proposed  to  foster  the 
deployment of any specific RE technology that promises additional benefits to 
society; however, a good policy should prevent a reasonable, justifiable target 
quota for them (defined in terms of installed MW) from being overshot.   
• Discontinue the present system of negotiated RE power purchase tariffs. 
• The competitive bidding alternative (i.e., tendering) must be kept as an option 
for  only  those  technologies  whose  marginal  cost  is  higher  than  the  avoided 
social cost. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  6
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2.3.4.2 Structure of Tariffs 
Upfront  tariffs  should  be  denominated  in  Pakistan  Rupees/kWh.  The  upfront  tariffs 
should be based on a one‐part pricing approach (i.e., a single ‘energy charge’).  Two‐part 
tariffs  (‘capacity  payments’  plus  ‘energy  payments’)  are  difficult  for  most  RES‐E 
technologies, as most of them cannot guarantee capacity availability. 

2.3.4.3 Indexation for Upfront Tariffs 
Upfront tariffs must be adjusted based only on local currency variations.  The indexation 
of  tariffs  with  the  US  dollar  exchange  rate  should  be  automatic,  carried  out  on  a  six‐
monthly  basis.    Another  possibility  presently  is  to  use  a  reference  currency  basket 
comprising of both US Dollars and Euros (e.g., in a 50:50 ratio). 

2.3.5 Type of Contracts 
RE IPP projects for sale of all power output to the grid system shall be implemented on 
the  basis  of  Build,  Own  and  Operate  (BOO)  contracts  valid  for  a  period  not  less  than 
20 years.  

2.3.6 Allocation of Network Investment Costs  
The construction of transmission lines for evacuation of power from any RE IPP should 
be  the  responsibility  of  the  NTDC,  KESC  or  a  DISCO  (depending  on  the  location  and 
supply voltage of the project) if the length of the connection required from the project’s 
outgoing bus bar to existing grid installations is shorter than 20 km, unless the IPP, of its 
own  choice,  undertakes  to  install  such  infrastructure  on  a  mutually  agreed  upon 
transmission charge with the NTDC. The NTDC should bear all expenses associated with 
power balancing on the grid to accommodate priority dispatch. 

2.3.7 Mandatory RE Power Purchasing 
As  long  as  the  CPPA  exists  and  is  carrying  out  its  activities,  all  contracts  for  power 
generation  from  RE  should  be  signed  by  the  CPPA—excepting  ‘direct  sales’.    After  the 
CPPA  eventually  ceases  its  activities,  neither  distributors  nor  transmission  companies 
should  have  the  right  to  reject,  in  part  or  in  entirety,  any  contract  signed  previously 
between  the  CPPA  and  an  RE  power  generator.    NEPRA  should  establish  a  future 
methodology  for  compensating  those  DISCOs/TRANSCOs  that  are  forced  to  accept 
contracts at a stipulated RES‐E feed‐in tariff. 

2.3.8 Direct Sales 
RE  power  producers  should  be  allowed  to  enter  into  direct  (bilateral)  sales  contracts 
with  eligible  end‐use  customers.    In  this  case,  prices  should  not  require  approval  by 
NEPRA. 

2.3.9 Allocation of Carbon Credits  
RE investors should assume the entire risks and benefits of qualifying for and obtaining 
CERs for their RES‐E projects. The current shared allocation of carbon credits under the 
2006  RE  Policy  is  unnecessarily  complicated  and  was  considered  necessary  under  the 
prevailing  ‘cost‐plus’  tariff  methodology.  Additionally,  the  allocation  of  future  CERs  to 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  7
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

the RE developer would act as a stronger financial incentive, especially for those projects 
where costs are closer to the fixed feed‐in tariffs and financial returns relatively lower. 

2.3.10 Land and Site Access 
The federal, provincial, and AJK governments shall facilitate investors in acquiring land 
or  RoW  for  project  development,  as  well  as  in  obtaining  site  access.  However,  the 
primary  responsibility  for  acquiring  land  and  site  access  should  rest  with  the  project 
sponsors. 

2.3.11 Incentives Other Than Tariffs 
We understand that current general incentives, including sovereign risk guarantee, the 
financial regime,  and  the  fiscal  regime,  as  defined  in  the 2006  RE  Policy, are  adequate 
and should be continued into the medium term policy regime as well.   

2.3.12 Roles of Institutions 
We  do  not  recommend  major  changes  in  the  roles  that  each  key  RE  stakeholder 
institution  presently  has  defined  for  itself  in  Pakistan.    However,  some  clarification  of 
AEDB and NEPRA roles may be to the benefit of the policy. 
We strongly believe that the development of competent prefeasibility studies is critical 
for  the  development  of  future  RE  projects  in  Pakistan.  The  cost  and  complexity  of 
undertaking such studies is currently a major barrier to serious investor interest in such 
schemes, and therefore the AEDB and provincial governments must take a leading role 
in identifying and developing such ‘bankable’ studies. 
The  proposal  requires  NEPRA  to  define  feed‐in  tariffs,  as  well  as  to  approve  the 
application of them to specific RE projects, and to adjust grid and distribution codes in 
order to facilitate project development and operation. 

2.3.13 Institutional, Legal, and Regulatory Consents 
We judge that the general existing institutional, legal, and regulatory consents required 
prior  to  the  approval  and  implementation  of  RE  IPP  projects  need  not  be  changed, 
except  for  simplified  permitting  provisions  for  small‐scale  plants  (i.e.,  less  than  5  MW 
capacity). 

2.3.14 Procedural Requirements 
We  believe  that  the  processing  schedule  foreseen  in  the  2006  RE  Policy  is  adequate. 
However,  it  must  be  adjusted  to  the  tariff  regime  that  is  instituted,  and  should  be 
reduced in overall duration to the extent reasonably possible. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  8
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3 Proposal for Pakistan’s Medium Term Off­Grid RES­E 
Policy 
3.1 Background 
Historically, the predominant model for electrification in developing countries has been 
grid  extension  and/or  conventional  energy‐powered  mini‐grids  developed  by  large, 
state‐owned  utilities.  Recently,  the  spectrum  of  electrification  models  has  widened, 
including a long list of off‐grid solutions, such as WHSs and SHSs, amongst many others. 
Annex  B  of  Pakistan’s  2006  RE  Policy  provides  only  a  brief  set  of  guidelines  for  the 
development of small off‐grid hydel projects, with some provisions applying to other RE 
technologies  as  well.  At  present,  there  is  no  national  policy  for  off‐grid  electricity 
investments.  Additionally,  the  guidelines  assign  identical  roles  to  the  AEDB,  provincial, 
and  AJK  governments  for  RES‐E  project  implementation,  and  this  overlapping  can  be 
confusing and counterproductive.  
Several  off‐grid  RE  projects  have  recently  been  initiated  in  Pakistan—with  varing 
outcomes—and  the AEDB  has  been  actively  participating in  such  efforts.  Probably,  the 
most  ambitious  project  has  been  the  Khushaal  Pakistan  program  (2001),  which 
envisaged  100%  electricity  coverage  by  the  end  of  2007,  a  target  which  was  obvioulsy 
not  accomplished.  Currently,  the  most  active  project  is  the  Roshan  Pakistan  program. 
The objective is to provide electrification services to 7,874 isolated villages. So far, 400 
villages have been electrified through this program in Sindh and Balochistan provinces. 
A critical issue in the current rural RE deployment strategy in Pakistan is the absence of a 
clear  demarcation  of  off‐grid  areas  and/or  isolated/scattered  populations.  Such  a 
definition  should  define  the  geographical  areas  for  which  the  grid  extension  would 
remain  uneconomical  into  the  near  future  (say,  next  decade).  This  is  an  essential  first 
step in designing a rural electrification project, as it provides a means for understanding 
key characteristics of the unelectrified villages to be targeted. It was estimated that in 
2006, approximately 40,000 villages in the country lacked electricity services and about 
8,000 out of them could only be electrified based on off‐grid solutions. Despite the lack 
of  proper  data,  it  can  be  estimated  that  for  electrifying  8,000  villages  and  scattered 
populations,  USD 800  million  would  be  required  (see  Annex  IX);  in  case  some  of  the 
villages planned to be electrified by grid extension (around 32,000) also require off‐grid 
solutions, the financial cost would be even higher. 

3.2 Medium Term Off­grid RE Policy Recommendations 
3.2.1 Target Markets 
The target population is that living in ‘off‐grid’ villages.3 These villages can be supplied 
electricity,  and  eventually  drinking  water,  based  on  RE  generation.  The  AEDB  shall  be 

                                                       
3
  For  purposes  of  this  policy,  ‘off‐grid’  settlements  are  defined  as  those  that  are  currently  unelectrified,  are  not 
included in any national or regional grid expansion plan for the next ten years, and are located more than 20 km 
from existing power grid(s).  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  9
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

responsible  for  elaborating  a  database  of  all  villages  falling  under  this  definition,  in 
collaboration with provincial and local governments and electricity utilities.  
RE technologies included in this portfolio consist of, at a minimum: 

• Micro‐ or mini‐hydel 
• Hybrid systems, in which at least one RE source is employed 
• Solar PV and thermal 
• Micro‐ or mini‐wind systems  
• Bioenergy resulting from anaerobic gas digestors, pyrolitic biomass gasification, 
cogeneration, etc. 
Grid  expansion  is  outside  the  scope  of  this  policy,  as  is  any  RE  project  that  plans  to 
electrify a village with an installed generation capacity larger than 1 MW. 

3.2.2 Implementation Period 
The implementation period of this policy shall be 2009 to 2014. 

3.2.3 Rationale and Institutional Organization 
Off‐grid RES‐E based electrification can be developed either: 

• Directly  by  provincial  and/or  local  governments  on  a  voluntary  basis  and/or 
driven by social players without recourse to national subsidies, or 
• Via  national‐provincial  coordination,  in  which  provincial  governments4 
compete for federal government assistance to finance their off‐grid projects.  
Under  the  first  mechanism,  provincial  governments  would  be  fully  in  charge  of 
developing  the  electrification  projects  within  their  respective  territorial  jurisdictions 
using  their  own  funds,  or  contributions  and  investments  from  the  private  sector,  civil 
society, and/or the target communities.  
Under the second alternative, a coordinated national plan would to be set up to assign 
competences to the different parties involved in its execution, in order to maximize their 
operational  potential  and  capabilities  for  achieving  effective  and  efficient  off‐grid 
electrification.  The  main  characteristics  and  tasks  for  stakeholders  in  this  respect  are 
summarized in Exhibit 1. 

                                                       
4
  For  the  remainder  of  the  document,  the  term  ‘provincial’  shall  refer  to  all  distinct  administrative  regions  of  the 
country,  including  the  Punjab,  Sindh,  Northwest  Frontier  Province  (NWFP),  Balochistan,  Northern  Areas  (NA), 
Islamabad Capital Territory (ICT), Federally Administered Tribal Areas (FATA), and Azad Jammu and Kashmir (AJK). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  10
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 1: Proposed Federally‐Assisted Off‐grid RES‐E Deployment Approach 

State-owned Soft loans


banks

Ministry of
Water and OGREA budget
request
Power OGREA

Assessment
National off-grid
AEDB Off-grid
project Portfolio
Guidelines for
OGREA settlement
Villages and scattered Authorizations
Management
population

Provincial
Governments
(REAs) in Authorization
Awarded Tendering Performance
coordination Project Proposals issuance and
Projects Procedure monitoring
set tariffs
with local
governments

Priv. Investors
Developers NGOs
and Cooperatives Project Execution
operators Individuals
Others

IFIs and Financial and technical


donors assistance

 
The main features of the regulation proposed are as follows: 

• The  AEDB  will  act  as  the  national  off‐grid  RES‐E  program  coordinator  and  will 
decide  the  allocation  of  national  funds  to  different  off‐grid  electrification 
projects based on rules previously defined by the Government of Pakistan and 
agreed upon by all provinces/units; 
• The AEDB will create and update, with the assistance of the power utilities and 
provincial governments, a complete assessment of the unelectrified villages and 
scattered communities able to be supplied by RES‐E technologies which shall be 
approved as the off‐grid electrification ‘target’ population for the medium term 
(2010‐2014) by the Federal Cabinet;5  
• Provincial  governments—through  their  respective  Off‐grid  Electrification 
Agency  (OGEA)6—will  be  the  key  stakeholders  for  promoting  off‐grid  rural 
electrification within their provincial borders. Based on the list of annual target 
villages/populations  developed  by  them  in  collaboration  with  the  AEDB  and 
approved  by  the  latter,  each  OGEA  will  prepare  and  submit  to  the  AEDB  a 

                                                       
5
  Any  village  and/or  scattered  population  not  included  in  the  approved  list  finalized  by  the  AEDB  will  be  excluded 
from the off‐grid electrification program and not be eligible for the provisions of the present policy. 
6
  Or any related agency/department designated as such by the provincial government or regional administration for 
the development of all off‐grid rural electrification projects in its territorial jurisdiction. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  11
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

village‐specific  electrification  project  in  which,  at  least,  the  following  aspects 
shall be covered: 
o Socioeconomic characteristics of target village/scattered population. 
o Study on power demand potential and projected supply. 
o Generation technology/ies to be deployed. 
o Number of households to be connected. 
o Implementation period. 
o Total cost of the project, segregated between CapEx and OpEx. 
o Detailed cash flow projections for the project. 
o Social benefits due to project implementation. 
o Quality‐of‐service characteristics. 
• Projects  should  include,  to  the  extent  feasible,  domestic  equipment,  water 
installations, or any other facility that could expedite social development. 
• Projects must strictly fulfill the AEDB’s guidelines for proper benchmarking, and 
analysis.  The  AEDB  will  document  simplified  procedures  for  project  approval, 
including criteria for ranking the projects and the definition of the parameters 
needed.  
• Based on the above, the AEDB will create an annual project portfolio organized 
according  to  a  merit  order  based  solely  on  a  standardized  social  cost‐benefit 
analysis of the projects.  
• Once  a  project  has  been  awarded  by  the  AEDB,  the  relevant  provincial 
government will call for tenders for granting a 10‐year Authorization to develop 
off‐grid  electricity  services  following  technology  specifications  stated  in  the 
electrification  project.    If  convenient  (i.e.,  for  proximate  villages),  several 
projects may be combined for tendering under a single Authorization. 
• The  primary  criterion  for  selecting  the  winning  bid  for  each  Authorization  will 
be  ‘least  subsidy’  demanded  for  capital  investments  for 
electrification/installation. 
• All  types  of  stakeholders  shall  be  eligible  to  participate  in  the  tender  process, 
provided they meet a minimum set of technical qualifications to be defined by 
provincial REAs with the guidance of the AEDB. 
• The  AEDB  will  define  the  standard  Authorization  template  that  the  REAs  will 
apply to specific project tenders. The following contents shall be included: 
o Schedule for electrification. 
o Rights and obligations of the parties. 
o Applicable tariffs or fees. 
o Milestones for subsidy delivery. 
o Quality‐of‐service regulation. 
o Community capacity‐building. 
o Conditions for termination of the Authorization. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  12
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.2.4 Targets and Incentives 
We  recommend  that  about  50%  (final  target  to  be  defined  by  the  GoP)  of  all  off‐grid 
unelectrified villages currently identified should be electrified by end‐2014. The federal 
government  will  provide  subsidies  for  capital  investments  to  the  extent  of  70%  of  the 
total investment required for each RE project. 
The  AEDB  will  approve  projects  based  on  their  respective  social  cost‐benefit  analysis. 
The standardized social cost‐benefit analysis should consider: 

• The subsidy requirement (total, and as a share of total cost). 
• The population involved. 
• The economic development benefits accruing from the projects. 
• The HSE (health, safety, and environment) performance aspects of the projects. 
Remaining capital and O&M costs, including replacement costs, would be financed by: 

• The respective REAs, employing provincial funds. 
• The  tariffs  or  fees  for  the  off‐grid  services  defined  by  the  provincial  OGEA,, 
taking into account the customers’ ability to pay. 
• Community  contributions,  in  the  form  of  sweat  equity  (labor),  land,  and/or 
cash. 
• NGO and private contributions. 
As subsidies are involved, they should be limited to the amounts needed for basic social 
and  human  needs,  including  basic  economic  activities.  Where  additional  quality  and 
quantity is desired, it must be paid for by the customer. 

3.2.5 Project Funding  
In order to provide funding to off‐grid projects, an Off‐grid Rural Electrification Account 
(OGEAC) in the budget for the AEDB should be created. This account could be financed 
by: 

• Government budgetary allocations. 
• Grants and loans by multilateral/bilateral financing and donor agencies. 
• A levy on grid‐supplied retail electricity tariffs. 
The OGEAC settlement is an attribute restricted solely to the AEDB.  Once projects have 
been awarded, tender procedures will direct the transfer to the respective REAs. 

3.2.6 Pricing 
The  REAs  will  define  the  tariff/fee  structure  for  each  Authorization  according  to  the 
following criteria: 

• Tariffs may be technology‐wise differentiated. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  13
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• In standalone systems, a one‐part tariff (Rs/customer) should be preferred. 
• In  community  (mini‐  and  micro‐grids)  system,  a  one‐part  tariff  based  on  the 
contracted capacity (Rs/kW‐contracted) should be preferred.  In these systems, 
each  customer  will  have  a  power  limiter  installed  in  order  to  disconnect 
him/her if the contracted capacity is exceeded. 
• A metering device may be installed for customers paying for higher quantity or 
quality of service. 
• Tariffs may be only indexed to local inflation. 

3.2.7 Incentives Other Than Tariffs 
We believe that the current general financial and fiscal incentives, as defined in the 2006 
RE  Policy,  are  adequate  and  should  be  continued.    Additional  facilities  and  incentives 
may be provided to encourage the local manufacture of RE technologies. 

3.2.8 Roles of Institutions 
The AEDB would play a key role in off‐grid electrification development as it is not only 
the main coordinator of the process at the national level, but will also  be in charge of 
setting  guidelines  for  project  formulation,  implementation,  and  financing.  Additionally, 
the  AEDB  will  elaborate  the  list  of  off‐grid  villages  and  scattered  population  to  be 
supplied by off‐grid RES‐E solutions updated on an annual basis. 
We  recommend  a  greater  involvement  of  provincial  and  local  institutions  in  RES‐E 
deployment  to  off‐grid  locations.  Local  stakeholders  should  also  have  an  active  role  in 
the  process  as  a  means  to  enhancing  community  acceptance  and  ensuring  successful 
deployment and operation. 
The Ministry of Water and power will define the budget request for the OGEAC.  

3.2.9 Institutional, Legal and Regulatory Consents 
Regulatory consents and processing requirements for off‐grid RES‐E services should be 
simplified  to  the  extent  possible,  so  as  to  enable  and  expedite  the  development  of 
projects.  No  regulatory  or  operational  consents  by  NEPRA  and  NTDC/DISCOs  are 
envisaged for such projects. 
For  off‐grid  electrification,  we  suggest  eliminating  the  LoI, LoS,  and  related  guarantees 
required  for  on‐grid  RES‐E  projects.  The  only  consent  necessary  is  the  Project 
Information Memorandum (PIM) for each project, which would include all technical and 
economic features of the project.  
Concerning  environmental  issues,  the  AEDB  proposes  that  the  federal  and  provincial 
EPAs remove the requirement of an Initial Environmental Examination (IEE) for off‐grid 
RE  projects of  up  to  1  MW  capacity.    However,  a  basic environmental  compliance  and 
impact checklist should be developed by the EPAs and required to be completed for all 
projects, primarily to ensure that water rights, flows, and community interests are not 
unduly  infringed  upon.  Additionally,  the  project  developer  should  certify  how  proper 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  14
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

design, engineering, construction, and safety criteria will be addressed in the execution 
of the project. 
The most important consent that would be required is the Authorization issued by the 
REAs on behalf of provincial governments.  

3.2.10 Performance Monitoring and Enforcement 
Project performance must be monitored, but in a light‐handed manner in order to avoid 
huge regulation costs. The monitoring process will have two main parts: 

• Investment plan monitoring: involves verification of the investment milestones 
defined in the Authorization being reached, as a trigger for subsidy payments. 
• Ongoing  performance  monitoring  for  the  duration  of  the  Authorization:  This 
involves  monitoring  that  quality  standards  are  met  throughout  its  period  of 
validity.  The  regulator  will  establish  standards  for  product  quality,  service 
quality,  and  commercial  quality.  It  should  be  noted  that  fewer  standards  that 
can be effectively monitored are preferable to many standards that are poorly 
monitored. 
Performance monitoring and enforcement will be the responsibility of the provincial and 
or local governments. The REAs should develop a program of awareness amongst their 
customers  and  other  community  stakeholders  to  foster  the  direct  monitoring  of  the 
service provider.  

3.2.11 Allocation of Carbon Credits  
We  consider  logical  and  administratively  simpler,  for  RE  investors  to  assume  the  risks 
and  benefits  of  qualifying  for  and  obtaining  CERs,  along  with  the  potential  revenues 
associated with them.  However, the AEDB would assist project developers applying for 
CDM registration through programmatic or clustered, single‐umbrella application cover.  
In  such  cases,  CDM  registration,  validation,  and  verification  costs  and  CER  revenue 
sharing arrangements shall be developed subsequently, as necessary. 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  15
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex I:  Policy for Development of Renewable Energy 
for Power Generation in Pakistan 
(2009­2014) 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  17
 

Policy for 
Development of Renewable Energy 
for Power Generation in Pakistan 
2009­2014 

DRAFT 

 
Government of Pakistan
[Date]

 
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Contents 

1  Introduction ........................................................................................................... 25 
2  Background ............................................................................................................ 25 
3  Strategic Policy Objectives, Goals, and Development Strategy ............................... 26 
3.1  Energy Security .................................................................................................... 26 
3.2  Economic Benefits ............................................................................................... 26 
3.3  Social Equity .......................................................................................................... 27 
3.4  Environmental Protection ..................................................................................... 27 
4  Medium Term On‐grid RES‐E Policy ........................................................................ 27 
4.1  Scope of Policy ...................................................................................................... 27 
4.2  Implementation Period ....................................................................................... 28 
4.3  Consistency Across Policies ................................................................................. 28 
4.4  Private Sector Participation ................................................................................. 28 
4.5  Financial and Fiscal Incentives ............................................................................ 29 
4.5.1  Fiscal Incentives ....................................................................................... 29 
4.5.2  Financial Incentives ................................................................................. 29 
4.6  General Incentives for RE‐Based Power Generators ........................................... 30 
4.6.1  Guaranteed Market: Mandatory Purchase of Electricity ........................ 30 
4.6.2  Grid Connection, Off‐take Voltage, and Interface .................................. 30 
4.6.3  Wheeling .................................................................................................. 30 
4.7  Specific Incentives for Grid‐Connected RE IPPs ................................................... 31 
4.7.1  Carbon Credits ......................................................................................... 31 
4.7.2  Security Package ...................................................................................... 31 
4.7.3  Land and Site Access ................................................................................ 31 
4.8  Facilities for Captive and Grid Spillover Projects ................................................. 32 
4.8.1  Net Purchase and Sales ........................................................................... 32 
4.8.2  Net Metering ........................................................................................... 32 
4.8.3  Banking .................................................................................................... 33 
4.8.4  Projects with Capacity Larger Than 10 MW ............................................ 33 
4.9  Tariffs and Quotas for Grid‐Connected RE IPPs ................................................... 33 
4.9.1  Categorization of Grid‐Connected RE IPPs Projects ................................ 33 
4.9.2  Determination of Long Run Private Avoided Costs ................................. 34 
4.9.2.1  Determination of the Conventional Supply Curve .................. 34 
4.9.2.2  Determination of the RES‐E Supply Curve .............................. 35 
4.9.2.3  Determination of Avoided Cost .............................................. 35 
4.9.3  Determination of Long Run Social Avoided Cost..................................... 36 
4.9.4  Quotas and Premiums for RES‐E Projects ............................................... 36 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  21
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.9.5  Calculation and Communication of Avoided Costs, Premiums, and  
Quotas ..................................................................................................... 37 
4.9.6  Determination of Technology‐wise Upfront Tariffs (Groups A and C) .... 37 
4.9.6.1  Group A Projects ..................................................................... 37 
4.9.6.2  Group C Projects ..................................................................... 37 
4.9.6.3  Upfront Tariff Determination (Groups A & C) ........................ 38 
4.9.6.4  IPP Tariff Determination (Groups A & C) ................................ 38 
4.9.7  Determination of Individual Tariffs (Group B) ......................................... 38 
4.9.7.1  Technical Parameters .............................................................. 38 
4.9.7.2  Financial Parameters ............................................................... 38 
4.9.7.3  Interest on Loans .................................................................... 39 
4.9.7.4  Capital Cost ............................................................................. 40 
4.9.7.5  O&M Cost ................................................................................ 40 
4.9.7.6  Other Incentives ...................................................................... 40 
4.10  Indexation for Upfront Tariffs .............................................................................. 40 
4.10.1  Group A and C Projects ............................................................................ 40 
4.10.2  Group B Projects ...................................................................................... 40 
4.11  Wind and Hydrological Risks ............................................................................... 40 
4.12  Special Requirements for Hydroelectric Projects ................................................ 40 
4.13  Transparency and Visibility of Calculation of Tariff ............................................. 41 
4.14  Compliance with GoP Policies ............................................................................. 41 
4.15  Procedure for Establishing RE IPPs for Sale of All Power to the Grid .................. 41 
4.15.1  Process for RE IPP Proposals ................................................................... 41 
4.15.1.1  Submission of Proposals ......................................................... 42 
4.15.1.2  Evaluation of Proposals and Issuance of Letter of Intent ....... 42 
4.15.1.3  Feasibility Study ...................................................................... 42 
4.15.1.4  Bank Guarantee and Validity Period of Letter of Intent ......... 43 
4.15.1.5  Request for Licensing and Tariff Determination ..................... 43 
4.15.1.6  Request for PSEC Certificate ................................................... 44 
4.15.1.7  Performance Guarantee and Letter of Support ..................... 44 
4.15.2  Process Subsequent to Issuance of LoS ................................................... 45 
4.16  Security Package and Risk Cover ......................................................................... 45 
4.17  Corporate, Fee, and Contractual Arrangements ................................................. 46 
4.17.1  Fee Structure ........................................................................................... 46 
4.17.2  Enterprise Structure and Licensing Requirements .................................. 47 
4.17.3  Lock‐in Period .......................................................................................... 48 
4.17.4  Type of Contracts .................................................................................... 48 
4.17.5  Nature of Equipment ............................................................................... 48 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  22
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

5  Medium Term Off‐grid RES‐E Policy ........................................................................ 48 
5.1  Scope of Policy ..................................................................................................... 48 
5.2  Assessment of Target Populations ....................................................................... 49 
5.3  Medium Term Electrification Targets................................................................... 49 
5.4  Multiple Deployment Approach .......................................................................... 49 
5.5  Coordination Amongst National and Provincial Authorities ............................... 50 
5.5.1  Off‐grid Electrification Agencies .............................................................. 50 
5.5.2  Project Selection ...................................................................................... 50 
5.5.3  Social Cost‐Benefit Analysis ..................................................................... 51 
5.5.4  Project Implementation .......................................................................... 51 
5.6  Subsidies .............................................................................................................. 52 
5.7  Off‐grid Electrification Account ........................................................................... 53 
5.8  Fee Structure ....................................................................................................... 53 
5.9  Financial and Fiscal Incentives ............................................................................ 54 
5.10  Allocation of Carbon Credits ................................................................................ 54 
5.11  Security Package and Risk Cover ......................................................................... 54 
5.12  Institutional, Legal, and Regulatory Consents ..................................................... 54 
5.13  Performance Monitoring and Enforcement ........................................................ 55 
 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  23
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 
Exhibit 1: Example of Conventional Electricity Supply Curve ........................................................ 35 
Exhibit 2: Example of RES‐E Supply Curve ...................................................................................... 35 
Exhibit 3: Example of Avoided Cost Determination ....................................................................... 36 
Exhibit 4: Processing Schedule for Grid‐Connected RE IPPs .......................................................... 41 
Exhibit 5: Fee and Financial Charges for Grid‐Connected RE IPPs ................................................. 47 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  24
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

1 Introduction 
With  a  large  population  of  over  150  million  and  a  rapidly  developing  economy, 
Pakistan’s  energy  needs  are  potentially  huge.    The  country,  historically  a  net  energy 
importer,  is  confronting  serious  imminent  energy  shortages  as  its  economy  and 
population  grow  while  global  fossil  fuel  prices  remain  highly  volatile.    Thus,  Pakistan 
needs  to  initiate  a  sustained,  long‐term  transition  towards  greater  use  of  renewable 
energy (RE)—an indigenous, clean, and abundant resource whose considerable potential 
the country has yet to tap meaningfully. 
The Government of Pakistan (GoP) intends to pursue this objective of harnessing power 
from  renewable  resources  with  the  full  participation  and  collaboration  of  the  private 
sector.    This  document  sets  out  policies  and  strategies  to  exploit  such  resources  and 
attract  investments  in  electricity  generation  projects  utilizing  hydro  (up  to  50 MW 
capacity), wind, solar, and biomass‐derived power (of all capacities).  For hydroelectricity 
(hydel) projects of capacity greater than 50 MW, the applicable policies are described in 
the GoP’s Policy for Power Generation Projects, 2002.  Additional policy guidelines shall 
be issued in the future concerning other RE technologies,  as well as for non‐power RE 
applications, as the sector grows and technology advances take place. 

2 Background 
Recent studies show that the ‘natural’ penetration of on‐grid renewable energy power in 
Pakistan, based on private cost analysis, could reach 17 TWh/year by 2020.  This figure 
represents  around  7%  of  total  grid‐based  electrical  power  generation  expected  in  that 
year.  Almost 60% of this projected RE share would be comprised of hydel plants that are 
much cheaper than combined cycle gas turbines (CCGT) running on fuel oil (FO), which in 
turn  defines  the  price  of  avoided  generation  on  the  national  grid.  Other  renewable 
energy  sourced  electricity  (RES‐E)  technologies  that  should  be  ‘naturally’  developed  in 
Pakistan  include  bagasse‐based  combined  heat  and  power  (CHP)  and  other  types  of 
biomass conversion.   
The same studies have observed that the ‘optimal’ penetration of RE generation when 
social costs are also taken into consideration should increase to around 25 TWh in 2020, 
which is around 10.3% of total on‐grid power generation expected in that year.  Market 
failure (i.e., externalities not properly being internalized) would thus appear hamper the 
development of about 8 TWh/year of RE generation, and so that an economic incentive 
mechanism  needs  to  be  put  in  place  to  realize  this  potential,  assuming  that  all  other 
barriers  that  block  the  development  of  natural  penetration  of  RE  have  also  been 
removed (grid access, difficult to sign sales contracts, etc.) by then. 
Under social cost assessment, not only hydel and biomass plants, but also biogas (from 
farm  slurries,  sewage,  landfills,  etc.)  and  wind  energy  plants  would  be  required  to 
replace CCGTs running on FO and natural gas—as a matter of fact, the studies show that 
all FO‐based generation would need to be replaced, as well as around 15% of gas‐based 
generation in 2020, because the marginal cost of RE for supplying this quota is around 
USD  100/MWh.    If  the  policy  to  achieve  these  results  is  properly  defined  and 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  25
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

implemented, the social wealth (total surplus) that may be created in Pakistan as a result 
would be about USD 2,100 million per year. 
Lessons  learnt  from  the  implementation  of  the  short  term  2006  RE  Policy7  have 
indicated  potential  problems  in  achieving  the  aforementioned  RE  penetration  goals, 
unless policy elements are promptly and suitably adjusted.  This is especially important 
considering  that  the  marginal  cost  of  some  RES‐E  technologies  is  in  the  order  of  USD 
75/MWh,  while  the  cost  of  generation  based  on  FO  has  recently  exceeded  USD 
125/MWh. 
The 2009 Medium Term On‐grid RES‐E Policy contained in this document (see Section 4) 
is based on a social assessment of cost and benefits.  The analysis of natural penetration 
based on private costs alone does not consider externalities, and therefore represents a 
limited subset of such an analysis.  Available international evidence shows that ‘feed‐in’ 
(upfront) tariffs are the best incentive mechanism for developing RE capacity, as can be 
observed  in  the  cases  of  Europe  and  some  BRIC  (Brazil,  Russia,  India  and  China) 
countries.  International experience also shows that an appropriate tariff mechanism is a 
necessary  but  not  a  sufficient  condition  for  developing  RE  energy;  grid  access, 
administrative  issues  (contracts,  licenses,  permits,  procedural  requirements,  etc.),  and 
stability  of  the  incentive  mechanism  are  equally  relevant  for  fostering  the  accelerated 
development of renewable energy.   
Similarly,  the  2009  Medium  Term  Off‐grid  RES‐E  Policy  described  in  this  document 
(Section  5)    will  try  to  create  a  sustainable  environment  where  federal  and  provincial 
institutions,  donors  and  NGOs  can  efficiently  collaborate  with  the  objective  of  rapid 
electrification of remote villages and population settlements.  

3 Strategic Policy Objectives, Goals, and Development 
Strategy 
The strategic objectives of the Government of Pakistan for developing renewable energy 
resources are aimed at enhancing the following parameters: 

3.1 Energy Security 
Mainstreaming  of  renewable  energy  and  greater  use  of  indigenous  resources  can  help 
diversify  Pakistan’s  energy  mix  and  reduce  the  country’s  dependence  on  any  single 
source,  particularly  imported  fossil  fuels,  thereby  mitigating  against  supply  disruptions 
and  price  fluctuation  risks.    Additional  costs  and  risks  relating  to  fuel  stocking, 
transportation,  and  temporary  substitute  arrangements  are  also  irrelevant  for  RE 
systems, except for backup purposes. 

3.2 Economic Benefits 
When  properly  assessed  for  their  externalities,  renewable  energy  options  can  become 
economically  competitive  with  conventional  supplies  on  a  least‐cost  basis.    This  is 
                                                       
7
  Government  of  Pakistan,  Policy  for  Development  of  Renewable  Energy  for  Power  Generation,  2006,  Alternative 
Energy Development Board (AEDB), Ministry of Water and Power, Islamabad: December 2006. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  26
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

particularly true for the more difficult, remote, and underdeveloped areas, where RE can 
also have the greatest impact and the avoided costs of conventional energy supplies can 
be  significant.    RE  can  thus  supplement  the  pool  of  national  energy  supply  options  in 
Pakistan,  expediting  economic  empowerment,  improving  productivity,  and  enhancing 
income‐generating opportunities—especially for currently marginalized segments of the 
population.    Decentralized  RE  systems  can  also  help  reduce  energy  distribution  losses 
and  result  in  system‐wide  and  national  efficiency  gains  (e.g.,  as  measured  by  ‘energy 
intensity’,  or  energy  use  per  unit  of  GDP).    A  growing  renewable  energy  industry  can 
afford  new  prospects  for  employment  and  business  opportunities  amongst  local 
manufacturers and service providers. 

3.3 Social Equity 
Pakistan’s  present  low  per‐capita  consumption  of  energy  can  be  elevated  through 
greater RE use.  Issues relating to social equity—such as equal rights and access for all 
citizens  to  modern  energy  supplies,  improved  human  development  indicators,  poverty 
alleviation, and reduced burden on rural women for biomass fuel collection and use—
can  also  be  addressed  to  a  significant  extent  through  widespread  renewable  energy 
deployment.    RE  can  thus  facilitate  social  service  delivery  and  help  improve  the  well‐
being  of  the  country’s  poorest,  which  presently  have  little  or  no  access  to  modern 
energy services. 

3.4 Environmental Protection 
Local  environmental  and  health  impacts  of  unsustainable  and  inefficient  traditional 
biomass fuels and fossil fuel‐powered electricity generation can largely be circumvented 
through  clean,  renewable  energy  alternatives.    Similarly,  displaced  greenhouse  gas 
emissions  carry  significant  global  climate  change  benefits,  towards  which  Pakistan  has 
pledged action under the UN Framework Convention on Climate Change. 

4 Medium Term On­grid RES­E Policy 
4.1 Scope of Policy 
The Medium Term On‐grid RES‐E Policy is aimed to provide electricity services utilizing 
renewable  technologies  to  consumers  through  connection  to  the  power  grid.8    This 
includes RES‐E generators installed for sale of all or part of their power output to or via 
the grid network. 
For the purposes of this policy statement, renewable energy sourced electricity includes 
the following technologies: 

                                                       
8
  For the purposes of RE policy terminology, the term ‘grid’ is meant to imply either national or regional electricity 
T&D networks operated by the NTDC/CPPA and/or DISCOs of 11 kV or higher voltage.  Isolated, community‐based 
local distribution networks are considered ‘off‐grid’. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  27
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Small hydro of 50 MW or less generation capacity9 
• Solar photovoltaic (PV) and thermal energy for power generation 
• Wind power generation 
• Bagasse‐based generation 
• Non‐bagasse biomass‐based generation 
• Biogas‐based generation 
• Generation based on landfill methane recovery  
• Generation based on sewage gas recovery  
• Municipal or industrial waste‐to‐energy generation. 
Other  RE  technologies—such  as  biofuels,  wave,  tidal,  geothermal  energy,  and  fuel 
cells—are  also  relevant  to  current  and  future  renewable  energy  use  in  Pakistan.  
However, these are not dealt with under this policy, although similar incentives could be 
extended to them on a case‐by‐case basis. 

4.2 Implementation Period 
This  medium-term  RES‐E  policy  will  apply  for  the  period  starting  from  [date  to  be 
defined] and it will continue until at least [date to be defined] 2014, or a minimum of 
five calendar years.  

4.3 Consistency Across Policies 
In order to ensure the consistency and stability of the RE deployment climate, both from 
the perspective of investors and power purchasers, an RE project that achieves financial 
closure  before  the  onset  of  a  subsequent  policy  phase  (i.e.,  from  [date  to  be  defined] 
onwards)  will  continue  to  be  guaranteed  all  the  incentives,  terms,  and  conditions 
defined in the 2009 Medium‐Term RE Policy over the tenure of its PPA/EPA. 

4.4 Private Sector Participation 
The  private  sector  would  be  welcome  to  undertake  projects  falling  in  any  of  the 
following categories: 

• Independent  power  projects  (IPPs)  based  on  new  plants  (for  sale  of  power  to 
the grid only) 
• Captive and grid spillover power projects (i.e., self‐use and sale to utility) 
• Captive power projects (i.e., for self or dedicated use). 

                                                       
9
  Each country has its own definition of hydel plant sizes.  For the purpose of this document, ‘small hydro’ is used to 
collectively  refer  to  hydel  capacity  of  less  than  50 MW,  consisting  of  ‘micro’  hydels  (units  of  less  than  150  kW 
installed capacity), ‘mini’ hydels (150 kW to 5 MW), and ‘small’ hydels (between 5 MW to 50 MW). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  28
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.5 Financial and Fiscal Incentives 
All renewable energy‐based power projects (private, public‐private, or public sector) will 
continue  enjoying  the  same  fiscal  and  financial  incentives  prescribed  in  the  2006  RE 
Policy.  These are enumerated below.  

4.5.1 Fiscal Incentives 

• No  customs  duty  or  sale  tax  for  machinery  equipment  and  spares  (including 
construction  machinery,  equipment,  and  specialized  vehicles  imported  on 
temporary  basis)  meant  for  the  initial  installation  or  for  balancing, 
modernization,  maintenance,  replacement,  or  expansion  after  commissioning 
of projects for power generation utilizing renewable energy resources, subject 
to fulfillment of conditions under the relevant SRO.10 
• Exemption from income tax, including turnover rate tax and withholding tax on 
imports. 
• Repatriation of equity along with dividends freely allowed, subject to rules and 
regulations prescribed by the State Bank of Pakistan. 
• Parties  may  raise  local  and  foreign  finance  in  accordance  with  regulations 
applicable to industry in general.  GoP approval may be required in accordance 
with such regulations. 
• Non‐Muslims and non‐residents shall be exempted from payment of Zakat on 
dividends paid by the company. 

4.5.2 Financial Incentives 

• Permission  for  power  generation  companies  to  issue  corporate  registered 


bonds. 
• Permission to issue shares at discounted prices to enable venture capitalists to 
be provided higher rates of return proportionate to the risk. 
• Permission  for  foreign  banks  to  underwrite  the  issue  of  shares  and  bonds  by 
private  power  companies  (IPPs)  to  the  extent  allowed  under  the  laws  of 
Pakistan. 
• Non‐residents  allowed  purchase  of  securities  issued  by  Pakistani  companies 
without  State  Bank  of  Pakistan’s  permission,  subject  to  prescribed  rules  and 
regulations. 

                                                       
10
  As per SRO (1)/2005 issued by the Ministry of Finance, Revenue and Economic Affairs on June 6, 2005, specifying 
zero customs duty and sales tax on: 
“Machinery, equipment and spares (including construction machinery, equipment and specialized 
vehicles  imported  on  temporary  basis)  meant  for  initial  installation,  balancing,  modernization, 
replacement or expansion of projects for power generation through nuclear and renewable energy 
sources like solar, wind, micro‐hydel bio‐energy, ocean, waste‐to‐energy and hydrogen cell, etc. 
“Spares and maintenance parts required for the above project after commissioning.” 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  29
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Independent rating agencies in Pakistan to facilitate informed decision‐making 
by investors about the risk and profitability of project company’s bonds/TFCs. 

4.6 General Incentives for RE­Based Power Generators 
The provisions stated below shall be made available to all qualifying renewable energy‐
based power projects falling under any of the categories defined in Section 4.4 above. 

4.6.1 Guaranteed Market: Mandatory Purchase of Electricity 
It  shall  be  mandatory  for  the  CPPA  or  the  power  distribution  utilities  to  purchase  all 
electricity offered to them by RE projects established in accordance with the provisions 
given in Section 4.6.2. An EPA contract will be concluded between the project sponsor 
and the CPPA or, eventually, between the project sponsor and the distribution company 
in  whose  service  territory  the  project  may  be  located,  except  for  those  cases  in  which 
the sponsor opts for a ‘direct sale’ to a bulk consumer.  After the CPPA ceases to exist, 
neither distributors nor transmission companies will have the right to reject, in part or in 
entirety,  any  contract  signed  previously  between  the  CPPA  and  an  RE‐based  power 
generator.    NEPRA  will  establish  a  suitable  methodology  for  compensating  those 
DISCOs/TRANSCOs  that  are  forced, under  this  2009  Medium  Term RE Policy,  to  accept 
contracts with NEPRA‐mandated ‘feed‐in’ tariff. 
RE  power  producers  are  allowed  to  enter  into  direct  (bilateral)  sales  contracts  with 
eligible  end‐use  customers.    In  this  case,  electricity  sale  prices  will  not  require  prior 
approval by NEPRA. 

4.6.2 Grid Connection, Off­take Voltage, and Interface 
Electricity shall be purchased from RE power producers at a voltage of: 

• 220 kV  at  the  outgoing  bus  bar  of  the  power  station  if  the  power  station  is 
located within 70 km of an existing 220 kV transmission line 
• 132 kV if it is within 50 km of an existing 132 kV transmission line 
• 11 kV if it is within 5 km of an existing 11 kV transmission line 
• 400 V if it is within 1 km of a 400 V distribution feeder. 
The  minimum  average  power  to  be  supplied  in  each  case  would  be  1,250  kW/km, 
250 kW/km, 100 kW/km, and 20 kW/km, respectively. 
The producer may also undertake to lay a new transmission line for connection with the 
main  electricity  grid.    The  power  purchase  tariff  determination  will  be  adjusted 
accordingly for each of these options. 

4.6.3 Wheeling 
RE power producers shall also be allowed to enter into direct (bilateral) sales contracts 
with end‐use customers.  Under this arrangement, they would be allowed to sell all or a 
part  of  the  power  generated  by  them  directly  to  their  customers,  and  the  rest  to  the 
utility for general distribution.  For direct sales, they shall be required to pay ‘wheeling’ 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  30
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

charges  for  the  use  of  the  transmission  and/or  distribution  grid  network  employed  to 
transport power from the plant to the purchaser.  In practical terms, the IPP shall inject 
electricity into the grid system at one point (subject to the provisions in Section 4.6.2) 
and would be entitled to receive the same amount at any other location upon payment 
of a corresponding wheeling charge, to be determined by NEPRA. This wheeling charge 
will  reflect  the  cost  of  providing  and  maintaining  the  transmission  interconnection, 
including  the  energy  losses  suffered  en  route,  calculated  on  a  utility‐wide  basis  by 
NEPRA. 

4.7 Specific Incentives for Grid­Connected RE IPPs 
Additionally,  specific  incentives  are  provided  under  this  policy  to  renewable  energy‐
based  independent  power  producers  (IPPs)  selling  all  generated  electricity  (minus 
auxiliary consumption) to the grid as described below. 

4.7.1 Carbon Credits 
All  qualifying  RE  power  projects  eligible  for  financing  under  the  Clean  Development 
Mechanism (CDM) shall be encouraged to register for Certified Emission Reduction (CER) 
credits  with  the  CDM  Executive  Board,  either  collectively  or  individually.    The 
Government shall also strive, in collaboration with international development agencies 
and  to  the  extent  possible,  to  facilitate  project  applications  for  such  carbon  credits  in 
order to reduce the associated initial transaction costs for project sponsors.   
The  annual  carbon  revenues  eventually  obtained  shall  be  allocated  to  the  project 
sponsor,  who  shall  be  free  to  negotiate  CER  sales  to  third  parties  in  any  manner  it 
considers appropriate.  

4.7.2 Security Package 
The power purchaser shall enter into a specific Energy Purchase Agreement (EPA), based 
on  a  standard  model  agreement,  with  the  RE  power  producer.    The  Government  of 
Pakistan  shall  also  enter  into  an  Implementation  Agreement  (IA)  which  will  guarantee 
the payment obligation of the public sector power purchaser for power sales extending 
over  the  term  of  the  PPA.    The  EPAs  will  be  much  simpler  than  those  currently 
prescribed for for thermal or large hydro IPPs, and shall be based on the purchase of all 
the energy generated at a per‐kWh rate.  

4.7.3 Land and Site Access 
The  federal  and  provincial11  governments  shall  facilitate  investors  in  acquiring  land  or 
rights‐of‐way (RoWs) for project development, as well as providing site access on a case‐
to‐case  basis  by  leasing,  acquisition  of  RoW,  and/or  construction  of  road  linkages.  
However, the primary responsibility for acquiring land and site access will rest with the 
project sponsors. 

                                                       
11
  For the purposes of this policy document, the term ‘provincial’ shall hereinafter refer to all distinct administrative 
regions  of  the  country,  including  the  Punjab,  Sindh,  Northwest  Frontier  Province  (NWFP),  Balochistan,  Northern 
Areas  (NA),  Islamabad  Capital  Territory  (ICT),  Federally  Administered  Tribal  Areas  (FATA),  and  Azad  Jammu  and 
Kashmir (AJK). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  31
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.8 Facilities for Captive and Grid Spillover Projects 
For  other  categories  of  RE  power  generators  (captive  and  grid  spillover  RE  power 
projects), wishing to sell surplus power to the utility grid, the following facilities shall be 
made available: 

4.8.1 Net Purchase and Sales 
An RE power project, with a capacity larger than 1 MW and less than 10 MW, set up for 
self (captive) or dedicated use, may supply surplus electricity to the power utility (grid 
spillover), while at other times drawing electricity from the utility to supplement its own 
production or local use, subject to the provisions in Section 4.6.2.  In such cases, the net 
electricity 

• supplied by the power producer to the utility in a month (i.e., units supplied by 
the producer minus units received by the producer, if greater than zero), shall 
be paid for by the utility at a tariff equal to the average energy cost per kWh for 
oil‐based power generation (as determined by NEPRA for GENCOs/IPPs over the 
applicable quarter of the year) less 10% , or 
• supplied by the utility to the power producer in a month, (i.e., units received by 
the producer minus units supplied by the producer, if greater than zero), shall 
be  paid  for  by  the  producer  at  the  applicable  retail  tariff  (e.g.,  industrial  or 
commercial rates, depending upon the type of user connection). 
Such net purchase and sales—or ‘net billing’—arrangements will involve measurement 
of the electricity received and supplied to the utility by the power producer using two 
separate sets of unidirectional meters. 

4.8.2 Net Metering 
An RE power project of capacity up to 1 MW set up for self (captive) or dedicated use 
may  also  supply  surplus  electricity  to  the  power  utility  while  at  other  times  drawing 
electricity  from  the  utility  to  supplement  its  own  production  for  local  use,  subject  to 
provisions in Section 4.6.2.  In such cases, the net electricity 

• supplied by the power producer to the utility in a month, i.e., units supplied by 
the producer minus units received by the producer, if greater than zero, or 
• supplied by the utility to the power producer in a month, i.e., units received by 
the producer minus units supplied by the producer, if greater than zero, 
shall be paid for by the utility or the producer, respectively, at the applicable retail tariff 
(e.g., industrial, commercial, or residential rates). 
Such net metering arrangements may involve separate sets of unidirectional meters for 
recording the electricity received and supplied to the utility by the power producer, or 
special  bidirectional  meters  capable  of  instantaneously  recording  net  power  transfers.  
This  facility  would  be  particularly  suitable  for  incentivizing  dispersed  small‐scale  RE 
generation,  such  as  rooftop  PV  panels,  helping  optimize  their  utilization  and  payback 
rates and obviating the need for expensive on‐site storage batteries. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  32
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.8.3 Banking 
For  net  billing  purposes,  a  rolling  account  of  energy  units  will  be  maintained  on  the 
pattern  of  a  bank  account  (i.e.,  debit  or  credit  basis).    Such  banking  accounts  of  net 
energy units shall be maintained on a monthly basis and final balances will be reconciled 
at  the  end  of  the  year  at  the  rates  given  in  Section  4.8.1.    Under  this  arrangement,  a 
producer  may  generate  and  supply  power  to  the  grid  at  one  location  and  receive  an 
equivalent  number  of  units  for  self  use  (say,  at  a  factory)  at  a  different  or  physically 
distant location on the grid at a different time without paying any wheeling charges, but 
subject to the distance limits for power input and off take as noted in Section 4.6.2.  Any 
additional (net) units consumed by the producer (beyond those supplied to the utility at 
the  plant  location)  in  a  given  month  shall  be  billed  by  the  utility  at  the  retail  tariff 
applicable  to  the  type  of  electricity  connection  obtaining  at  the  consumer’s  premises.  
Any  excess  (net)  units  supplied  by  the  producer’s  plant  in  a  given  month  shall  be 
credited to the producer on a rolling monthly basis (i.e., deducted from the next month’s 
consumption).  Any accumulated energy unit credits accruing to the producer at the end 
of the year shall be paid for by the utility at a tariff equal to the average energy cost per 
kWh for oil‐based power generation (as determined by NEPRA for GENCOs/IPPs over the 
preceding fiscal year) less 10%. 

4.8.4 Projects with Capacity Larger Than 10 MW 
For captive and grid spillover RE power generators with a capacity greater than 10 MW, 
wishing to sell surplus power, the provisions included in Section 4.7 shall apply.  

4.9 Tariffs and Quotas for Grid­Connected RE IPPs 
4.9.1 Categorization of Grid­Connected RE IPPs Projects 
For  tariff  determination  purposes,  RES‐E  projects  will  be  grouped  in  three  different 
categories:  
Group A:  
RE  projects  selling  electricity  to  the  utility  (NTDC/CPPA  or  DISCOs)  utilizing  one  of  the 
following technologies:  

• Bagasse‐based generation 
• Non‐bagasse biomass‐based generation 
• Biogas‐based generation 
• Generation based on landfill methane recovery  
• Generation based on sewage gas recovery  
• Small‐scale hydel, with capacity less than 50 MW 
• On‐shore wind generation. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  33
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Group B:  
RES‐E projects selling electricity to the utility (NTDC/CPPA or DISCOs) with special non‐
energy social and environmental benefits (i.e., waste‐to‐energy projects). 
Group C:  
RES‐E projects selling electricity to the utility (NTDC/CPPA or DISCOs) utilizing one of the 
following technologies:  

• Photovoltaics  
• Solar thermal   
• Other RES‐E technologies not included in Groups A or B. 
Technology  wise  upfront  (feed‐in)  tariffs  will  be  determined  for  each  RE  technology 
included in Groups A, B or C. However, for Group B technologies, different tariffs specific 
to each project (i.e., ‘case‐by‐case’ tariffs) may be determined, following the procedure 
described below.  

4.9.2 Determination of Long Run Private Avoided Costs 
In order to determine long run private avoided costs of electricity supply to the national 
grid, the following procedure will be applied:  

4.9.2.1 Determination of the Conventional Supply Curve 
The MoWP, through the Energy Wing of the Planning Commission, shall produce a Long 
Run Least Cost Energy Plan (LREP), which will identify the most economic means to meet 
Pakistan’s  total  energy  demand—in  particular  electricity—using  conventional 
technologies.  Conventional  technologies  include  fossil  fired  and  nuclear  power  plants, 
and hydel larger than 50 MW of installed capacity. The LREP should cover a period of at 
least 15 years.  
Using  the  projects  and  technologies  selected  in  the  LREP  for  the  later  plan  period,  an 
single‐part  energy  price,  expressed  in  USD/kWh,  shall  be  calculated  for  each  of  these 
projects.  An  ordered  list  (from  lowest  to  highest  energy  cost)  will  then  be  formed, 
indicating  for  each  project  the  expected  energy  produced,  the  cumulative  energy 
output, and the energy price.  The  cumulative energy vs. unit electricity cost will form 
the conventional supply curve.  Exhibit 1 shows an example of such a curve.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  34
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 1: Example of Conventional Electricity Supply Curve 

Energy Cumulated
Cost Conventional Supply Curve
Name produced Energy
[USD/MWh]
[TWh/year] [TWh/year] 120
Project 1 1.5 1.5 38.7
Project 2 2 3.5 38.8
100
Project 3 1.8 5.3 38.9
Project 4 3 8.3 40.1
Project 5 4 12.3 40.1
80

Cost [USD/MWh]
Project 6 2 14.3 40.1
Project 7 2.7 17 40.1
Project 8 3 20 40.1 60

40

Project 56 0.9 152.1 92.5 20


Project 57 0.7 152.8 92.8
Project 58 0.6 153.4 93
0
Project 59 0.8 154.2 94
0 20 40 60 80 100 120 140 160
Project 60 1 155.2 96
Cumulated Energy [TWh/year]
 

4.9.2.2 Determination of the RES‐E Supply Curve 
The  MoWP,  through  the  AEDB,  will  determine  an  RES‐E  supply  curve  using  a  similar 
approach to the one used for the conventional electricity supply curve. In deriving this 
curve,  the  AEDB  will  use  its  best  estimation  of  the  potentially  feasible  RE  projects  in 
Pakistan  which  could  be  developed  over  a  reasonable  time  frame—i.e.,  15  years—and 
the cost of such development.  If RE projects cannot be accurately identified individually 
(due  to  the  relatively  large  numbers  and  relatively  small  sizes  involved),  different  cost 
ranges,  based  on  technology  and  location,  may  be  used  for  the  determination  of  the 
RES‐E supply curve.  Exhibit 2 shows an example of such curve.  

Exhibit 2: Example of RES‐E Supply Curve 

450

400

350

300
$/MWh

250

200

150

100

50
Supply Curve (Private Cost) Supply curve (Social Cost)
0
0 10 20 30 40 50 60
TWh/a
 
4.9.2.3 Determination of Avoided Cost 
The long run private avoided cost is the price at which the value of the RE supply curve 
(ordered monotonically from lowest to highest unit costs of energy output) equals the 
value of the conventional electricity supply curve (ordered monotonically from lowest to 
highest unit costs of energy output).  Exhibit 3 shows, graphically, the determination of 
this cost.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  35
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 3: Example of Avoided Cost Determination 

Determination of the Avoided Cost

200

180

160

140 RE Supply Curve


Cost [USD/MWh]

120 Avoided Cost


100

80

60 Conventional Supply Curve

40

20

0
0 20 40 60 80 100 120 140 160

Cumulated Energy [TWh]


 
4.9.3 Determination of Long Run Social Avoided Cost 
The methodology for determining long run social avoided costs is conceptually similar to 
that  described  for  long  run  private  avoided  costs  in  Section  4.9.2,  the  only  difference 
being that the cost of some selected externalities shall also be taken into account. The 
MoWP will determine which externalities need to be included in the calculation, as well 
as  the  methodologies  applied  to  calculate  them.    At  a  minimum,  the  following 
externalities shall be included:  

• Global environmental costs (CO2‐equivalent GHG emissions) 
• Air quality (e.g., NOx, SOx, and particulates), and  
• Fuel dependency. 

4.9.4 Quotas and Premiums for RES­E Projects 
There shall be no quotas and premiums for RES‐E projects falling in Groups A and B.  
For  RES‐E  projects  using  technologies  included  in  Group  C,  the  MoWP  may  establish  a 
maximum quota (total MW of installed capacity nationally for a specified RE technology) 
for such RE options that the GoP considers should be encouraged for long‐term strategic 
or  economic  benefits  that  might  accrue,  with  an  associated  price  premium  allowed 
above the long run social avoided cost for such projects. The AEDB will conduct studies 
in order to determine the minimum premium required in order to make these presently 
uneconomical technologies commercially viable, and shall advise the MoWP accordingly. 
Based  on  the  premium  required,  the  MoWP,  in  consultation  with  the  Ministry  of 
Industries,  Production  and  Special  Incentives  and  the  Ministry  of  Finance,  shall 
determine the national quota(s) to be established for each of the relevant technologies.  
In order to monitor the total installed capacity in technologies for which a premium and 
quota has been established, the AEDB shall maintain an up‐to‐date register of all Group 
C projects reaching financial closure, under construction, or in operation in the country. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  36
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Once the quota has been exhausted, Group C projects may continue to be developed by 
investors, but no premium shall be applicable to such subsequent projects.  

4.9.5 Calculation and Communication of Avoided Costs, Premiums, and 
Quotas 
No  later  than  six  month  of  the  publication  of  this  2009  Medium  Term  RE  Policy,  the 
MoWP will calculate actual figures for: 

• Long run private avoided costs for the national grid (in USD/kWh) 
• Long run social avoided cost for the national grid  (in USD/kWh) 
• The  list  of  technologies  (included  in  Group  C)  which  would  be  entitled  to 
receive  a  price  premium,  and  the  values  of  such  premiums  (i.e.,  price  in 
USD/kWh above the long run social avoided cost) 
• The maximum national quota for each technology (in MW of installed capacity) 
entitled to receive a premium. 
These  values  will  be  communicated  by  the  MoWP  to  the  AEDB  and  NEPRA,  and  they 
shall be used in the determination of upfront (feed‐in) tariffs, quotas, and premiums for 
each RE technology defined in Section 4.1 in the manner described below. 

4.9.6 Determination of Technology­wise Upfront Tariffs (Groups A and C) 
Within three (3) months after the MoWP communicates the values indicated in Section 
4.9.5,  the  AEDB  shall  file  class  tariff  petition(s)  with  NEPRA  for  each  of  the  RE 
technologies included in Groups A and C.  
In  order  to  determine  the  tariff  to  be  requested  for  each  technology,  the  AEDB  shall 
abide by the following procedure:  

4.9.6.1 Group A Projects 
For  projects  utilizing  Group  A  technologies,  the  requested  upfront  tariff  should  not  be 
lower  than  the  system‐wide  long  run  private  avoided  cost  (determined  as  indicated  in 
Section  4.9.2)  and  should  not  be  higher  than  the  long  run  social  avoided  cost 
(determined as indicated in Section 4.9.3).  
The  tariff  requested  should  take  into  consideration  costs  required  for  the  adequate 
development  of  each  technology  and  results  of  calculations  performed  in  the 
determination of the RES‐E supply curve, as indicated in Section 4.9.2. The parameters 
used in these calculation should be included in the tariff petition for NEPRA verification 
and review.  

4.9.6.2 Group C Projects 
For  projects  utilizing  Group  C  technologies,  the  requested  upfront  tariff  shall  be 
calculated as the long run social avoided cost (determined as indicated in Section 4.9.3), 
plus the premium determined by the MoWP for each technology.  The AEDB shall submit 
to NEPRA all supporting information required to assess the actual cost of development 
of these technologies.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  37
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.9.6.3 Upfront Tariff Determination (Groups A & C) 
Within three (3) months of receiving the tariff petition submitted by the AEDB for each 
RE  technology  under  Groups  A  and  C,  NEPRA  will  determine  the  upfront  tariffs  (bulk 
purchase prices to be used in the EPAs) for corresponding projects selling all electricity 
produced to the utility (NTDC/CPPA or DISCOs). Based on the information submitted by 
the AEDB, NEPRA may decide, within a specific technology, different upfront tariffs for 
different ranges of installed capacity, if it considers this suitable. 

4.9.6.4 IPP Tariff Determination (Groups A & C) 
Sponsors of an RES‐E project falling into Groups A or C are required to apply to NEPRA 
for determination of their project’s tariff.  NEPRA shall, based on analysis of the project’s 
qualification and characteristics, issue a determination consistent with the upfront tariff 
corresponding to the relevant RE technology.    

4.9.7 Determination of Individual Tariffs (Group B) 
For projects utilizing Group B technologies, the AEDB shall file class tariff petition(s) with 
NEPRA,  utilizing  the  same  procedure  as  indicated  in  Section  4.9.6.1.  However,  for 
projects with special non‐energy socioeconomic and environmental benefits, a different 
tariff  may  be  requested.  These  kinds  of  projects  will  be  considered  as  ‘Projects  with 
Special Environmental Characteristics’ (PSEC).  
In order for a project to be considered a PSEC, its sponsor must obtain PSEC certification 
for it from the MoWP according to the procedure described in Section 4.15.1.6.  
Upon receipt of the PSEC certificate, the sponsor would be required to apply to NEPRA 
for  determination  of  the  project’s  bulk  power  purchase  tariff  within  a  period  not 
exceeding  three  (3)  calendar  months  from  the  date  of  the  certification.  In  the  case  of 
Group  B  projects,  the guidelines  and  parameters  for  determination  of  tariffs  would  be 
those described below (Sections Error! Reference source not found. to 4.9.7.6). 

4.9.7.1 Technical Parameters 
The net energy available for sale shall be determined after taking into account electrical 
efficiency,  auxiliary  loads,  transformation  efficiency,  etc.,  and  plant  availability.  Plant 
availability  factor  should  be  determined  judiciously,  taking  into  account  suitable 
provisions for anticipated maintenance and forced outages. 
Once a contract (EPA) has been entered into, the parameters adopted at the time of the 
agreement shall not be changed for the duration of the contract. 

4.9.7.2 Financial Parameters 
The following parameters, principles, and assumptions shall be adopted for calculation 
of the IPP tariff: 
1. Debt:Equity Ratio 

• For the purposes of determination of tariff, equity equal of at least 20% of the 
total cost of the project would be the benchmark. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  38
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2. Internal Rate of Return/Return on Equity 

• Tariff should be determined allowing reasonable internal rate of return (IRR) on 
equity investment.   
• IRR  should  be  calculated  over  the  life  of  the  Implementation  Agreement  (IA), 
starting  from  the  date  of  construction  start  (i.e.,  start  of  payments  to 
contractors). 
• IRR  should  be  equal  to  long‐term  interest  rates  based  on  auction  of  ten‐year 
Pakistan  Investment  Bonds  (PIBs)  held  during  the  previous  six  months,  plus  a 
premium of x%, to be determined by NEPRA. 
• For BOOT projects, the investor’s equity shall be allowed to be redeemed after 
completion  of  debt  servicing.    The  redemption  in  equity  shall  be  in  equal 
instalments from the time debt servicing has been completed till the end of the 
concession period.  The effect of exchange rate variations shall be compensated 
for in determining equity redemption.  The projects shall be transferred to the 
GoP at the end of concession period at a notional cost of Rs 1. 
• For BOO projects, there will be no redemption of equity. 

4.9.7.3 Interest on Loans 
Tariff determination will be a two‐step procedure.  Initially, an indicative tariff shall be 
estimated, taking into account expected financial returns at the time of award of LoS so 
as  to  enable  an  IPP  to  achieve  financial  close.   At  this  stage,  interest  rate  ceilings may 
also  be  indicated  with  incentive  provided  for  the  IPP  to  arrange  better  terms  of 
financing.    After  financial  closure,  the  tariff  will  be  finally  fixed  such  that  the  project’s 
debt service cost component equals actual debt servicing plus the incentive. A ceiling for 
rate  of  interest  on  local  loans  of  6‐month  KIBOR12  plus  300  basis  points  for  a  ten‐year 
loan plus two‐year grace period has been agreed upon in recent negotiations with IPPs.  
For foreign loans, the ceiling rate may be taken as LIBOR13 plus a suitable spread for ten‐
year loans with two‐year grace period.  IPPs shall be given an incentive to arrange better 
terms of debt financing.  If the IPP succeeds in arranging better terms by the time the 
project achieves financial close, the overall impact of reduction in debt servicing shall be 
shared,  in  the  case  of  competitively  determined  tariffs  for  solicited  projects  and 
negotiated tariffs for unsolicited projects, on a yearly basis in the following ratio: 
Power Purchaser/Govt: IPP = 60:40 
Wherever  a  floating  interest  rate  regime  is  adopted,  local  loans  may  be  indexed  to 
changes  in  relevant  benchmark  interest  rates,  such  as  KIBOR,  etc.    Likewise,  foreign 
loans may be indexed to changes in relevant benchmark interest rates, such as LIBOR, 
etc.,  and  variation  in  Pakistan  Rupee  to  the  US  Dollar.    Loans  will  be  arranged  by  IPPs 
without GoP guarantee. 

                                                       
12
  Karachi Interbank Offered Rate. 
13
  London Interbank Offered Rate. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  39
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.9.7.4 Capital Cost 
Estimation of an IPP’s capital costs for this kind of projects is a challenging task.  NEPRA 
should  determine  them  after  thoroughly  assessing  market,  vendor,  and  IPP  provided 
information. 

4.9.7.5 O&M Cost 
The  operation  and  maintenance  (O&M)  cost  comprises  of  fixed  and  variable 
components.  NEPRA should access information from the same sources as for the capital 
costs to arrive at a judicious determination of O&M costs, both fixed and variable. 

4.9.7.6 Other Incentives 
All fiscal and financial incentives provided to RE IPPs by the GoP, as given in the policy 
(see Section 4.5) shall be applicable. 

4.10 Indexation for Upfront Tariffs 
4.10.1 Group A and C Projects 
Bulk power purchase tariffs for grid‐connected RE IPPs shall be denominated in Pakistan 
Rupees  per  kilowatt‐hour  (Rs/kWh).    Upfront  tariffs  shall  be  adjusted  automatically  by 
NEPRA on a quarterly basis, based only on local currency variations. IPPs will not have to 
approach NEPRA for such tariff indexation.  
The  benchmark  currency  rate  used  as  a  reference  will  be  the  interbank  rate  for  US 
Dollars (US$) prevailing 30 days prior to the date the upfront tariffs are determined by 
NEPRA. 

4.10.2 Group B Projects 
Indexation  of  tariffs  for  Projects  with  Special  Environmental  Characteristics  (PSEC), 
certified by MoWP under Section 4.15.1.6 shall be decided by NEPRA and included in the 
initial tariff determination of such projects.   

4.11 Wind and Hydrological Risks 
Wind  and/or  hydrological  risks  shall  be  borne  by  the  sponsors  of  wind  and  hydel 
projects,  respectively.  No  related  risk  cover  will  be  considered  in  the  tariff 
determinations. 

4.12 Special Requirements for Hydroelectric Projects 
Each hydroelectric IPP will be required to form a company in accordance with Pakistan’s 
laws  and  the  Companies  Ordinance,  1984  for  the  specific  purpose  of  hydropower 
generation. 
A water use charge will be payable by the generation company to the provincial/regional 
government for the use of water resources by the power project to generate electricity.  
The water use charge will be fixed at Rs 0.15/kWh and shall be adjustable annually for 
inflation  using  the  wholesale  price  index  (WPI)  with  effect  from  commercial  operation 
date (COD). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  40
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.13 Transparency and Visibility of Calculation of Tariff 
NEPRA  shall  provide  complete  soft  and  hard  copies  of  its  assumptions,  inputs  and 
methodology used in the determination of RE IPP tariffs, along with the complete tariff 
computation  and  model,  to  the  IPPs  as  well  as  the  public  domain.    This  would  enable 
better understanding of tariff decisions by all concerned. 

4.14 Compliance with GoP Policies 
NEPRA shall comply with the policies and guidelines of the Government of Pakistan as 
issued, modified, supplemented, and revised from time to time by the government. 

4.15 Procedure for Establishing RE IPPs for Sale of All Power to 
the Grid 
RE‐based  IPP  projects  shall  be  welcomed  by  the  AEDB  and  designated 
provincial/regional  agencies14.  A  Letter  of  Intent  (LoI)  shall  be  issued  to  enable  the 
sponsors to carry out a feasibility study and obtain tariff determination and a generation 
license from NEPRA.  Thereafter, a Letter of Support (LoS) shall be issued to assist the 
sponsors in achieving financial closure for the project. This process is described in detail 
below: 

4.15.1 Process for RE IPP Proposals 
The  schedule  of  activities  leading  to  issuance  of  Letter  of  Intent  (LoI)  and/or  Letter  of 
Support (LoS) is given in Exhibit 4 and explained in the following sections. 

Exhibit 4: Processing Schedule for Grid‐Connected RE IPPs 

Activity/Milestone Maximum Allowance (Days)


1. Submission of proposal on raw site by sponsors –
2. Review of proposal and qualification of sponsors by 30
AEDB/Counterpart Agency
3. Posting of Bank Guarantee by sponsors 15
4. Issuance of Letter of Intent (LoI) by AEDB/CA 7
5. Initial time allowed to carry out feasibility study and Based on schedule submitted
term of the LoI by IPP, subject to maximum of
18 months.
6. For projects in Group B, request for PSEC certification 90
7. Tariff petition and approval of tariff by NEPRA 90
8. Submission of Performance Guarantee by sponsors 15
upon approval of tariff by NEPRA
9. Issuance of LoS by AEDB/CA 7
Note: Indicated time allowance represents maximum processing period.

                                                       
14
  A ‘one‐window’ counterpart agency (CA), functionally similar to the AEDB’s project processing entity, will be set up 
by  each  of  the  provincial  governments  (i.e.,  Sindh,  Balochistan,  Punjab  and  NWFP)    and  regional  administrations 
(i.e., ICT, FATA, NA, AJK) for facilitating RE projects in the country.  For projects located in any of the provinces or 
AJK, proposals may be submitted to the relevant CA, or to the AEDB directly.  For the Northern Areas, FATA, and 
ICT, proposals should be submitted to the AEDB.  In the remainder of this document, the term ‘AEDB/CA’ shall be 
used as a short form to refer to this institutional arrangement. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  41
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.15.1.1 Submission of Proposals 
Any sponsor wishing to undertake a renewable energy IPP project, either on ‘raw’ sites 
or  on  sites  for  which  the  AEDB/CA  has  carried  out  pre‐feasibility  studies,  would  be 
required  to  submit  a  detailed  proposal  to  the  AEDB/CA  which  must  be  in  compliance 
with  applicable  policy  guidelines  and  subject  to  the  provisions  in  Section  4.6.2.    The 
sponsor would be required to submit a detailed information memorandum (PIM) to the 
AEDB/CA, which must include, at a minimum, the following information: 

• Project  name  and  RET  classification  (i.e.,  wind,  solar,  small  hydro,  biomass, 
hybrid, etc.) 
• Statement  of  qualification  of  project  sponsors,  listing  relevant  corporate 
experience, personnel, and financial capacity  
• Project location (including geographical or GPS coordinates) 
• Proposed  net  installed  capacity  (MW)  and  expected  annual  energy  output 
(MWh) 
• Basic outline of plant and structures 
• Estimated distance from the nearest 132 kV or 11 kV line or grid station 
• Summary  implementation  plan,  indicating  specific  project  preparation 
milestones, completion date, and expected COD 
• Previous history of the project, if any 
• Description of technology and main suppliers, and 
• If applicable, relevant information required for PSEC certification. 

4.15.1.2 Evaluation of Proposals and Issuance of Letter of Intent 
Proposals  for  unsolicited  projects  on  raw  sites  or  on  sites  for  which  the  AEDB/CA  has 
carried out pre‐feasibility studies will be examined by a Project Committee appointed by 
the AEDB or CA.  The time for reviewing the proposal should not exceed 30 working days 
from the date of submittal. Proposals approved by the Committee shall be processed by 
the  AEDB/CA  for  issuance  of  a  Letter  of  Intent  (LoI)  against  a  Bank  Guarantee  (see 
Exhibit 5).  This Bank Guarantee should be valid for a period not less than six (6) months 
in excess of the validity of the LoI, following which the provisions of the agreements shall 
be  applicable.    LoIs  for  proposed  projects  shall  include  relevant  project  milestones  to 
enable the AEDB/CA to monitor progress, and the sponsors shall commit to meeting the 
milestones stipulated therein. 

4.15.1.3 Feasibility Study 
Sponsors  shall  enjoy  exclusive  rights  for  carrying  out  a  feasibility  study  at  a  given  site 
during the period of the LoI, as long as they continue to meet the milestones specified in 
the letter. 
The  feasibility  study  shall  be  reviewed  by  a  ‘Panel  of  Experts’  (POE)  appointed  by  the 
AEDB/CA. If at any time during the feasibility study period, the POE determines that the 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  42
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

sponsors have failed to adhere to relevant milestones or to rectify such deviation, or are 
not diligent, the AEDB/CA may serve a notice to the IPP to rectify the situation, failing 
which  it  shall  terminate  the  LoI  and  encash  the  Bank  Guarantee.    In  such  a  case,  the 
sponsors will have no claim for compensation against the any government agency. 
Feasibility  studies  undertaken  by  the  public  sector  and  donor  agencies  will  be  made 
available  to  all  interested  private  entrepreneurs  by  the  AEDB/CAs  against  a  nominal 
administrative fee. The full cost of the feasibility study (up to a reasonable ceiling and as 
reflected on the books of the concerned agency as being the actual cost of the feasibility 
study),  shall  be  indicated  in  the  LoI  and  charged  to  the  project  sponsor  at  the  time  of 
issuance  of  the  Letter  of  Support  (LoS),  and  shall  be  reimbursed  to  the  agency  which 
originally  conducted  the  study,  except  in  the  case  where  such  study  was  conducted 
under grant financing (e.g., donor funding, etc.).  Wherever the GoP has obtained such a 
feasibility  prepared  by  the  public  or  private  sector,  preference  would  be  given  to  the 
award of these projects through international competitive bidding (ICB). 
For  studies  furnished  to  the  private  sector  by  the  AEDB/CA  or  any  public  sector 
organization, investors shall be responsible for verifying any or all aspects of the relevant 
feasibility study, and would be encouraged to carry out additional or alternative project 
appraisal of the site on their own for such purposes. 
In case the feasibility has been completed by the public sector or private sponsor but the 
unsolicited proposal does not materialize for any reason whatsoever, and the AEDB/CA 
wishes  to  invite  bids  using  the  same  feasibility  study,  then  the  cost  of  feasibility  study 
(up to a reasonable ceiling and as per proper audit) will be recovered from the successful 
subsequent bidder, if any, and be reimbursed to the public sector entity or sponsor who 
originally paid for, or conducted, the study. 

4.15.1.4 Bank Guarantee and Validity Period of Letter of Intent 
For issuance of the LoI, sponsors will be required to post a Bank Guarantee (see Exhibit 
5)  in  favor  of  the  AEDB/CA  based  on  the  project’s  estimated  installed  capacity.    This 
guarantee  shall  be  valid  for  a  period  extending  six  (6)  calendar  months  beyond  the 
original  validity  of  the  LoI.    The  initial  validity  of  the  LoI  shall  be  up  to  18  calendar 
months, depending on the size of the project and the schedule committed to by the IPP.  
A one‐time extension to the LoI of up to a maximum period of 180 calendar days may be 
granted  by  the  relevant  AEDB/CA  if  the  Panel  of  Experts  (POE)  deems  the  sponsors’ 
progress  on  the  feasibility  study  to  be  otherwise  satisfactory  and  its  completion 
imminent.    Submission  of  a  Bank  Guarantee  valued  at  twice  the  original  amount  (i.e., 
US$  1,000/MW)  and  valid  for  six  (6)  calendar months  beyond  the  extended  LoI  period 
shall be mandatory to qualify for an LoI extension. 
If  during  the  currency  of  the  LoI,  a  sponsor  wishes  to  withdraw  from  the  project,  the 
extent to which the Bank Guarantee amount shall be encashed will be in proportion to 
the time elapsed since the issuance of the LoI with respect to the total period of the LoI. 

4.15.1.5 Request for Licensing and Tariff Determination  
Upon  completion,  the  feasibility  study  shall  be  reviewed  by  the  POE,  and  if  approved, 
the  AEDB  will  assist  the  project  sponsors  to  apply  to  NEPRA  for  granting  a  generation 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  43
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

license and for the bulk power purchase tariff petition, which in any case should not be 
higher than the upfront tariffs published by NEPRA for the corresponding RE technology. 
NEPRA shall review the information submitted, verify compliance with the requirements 
indicated  in  the  upfront  tariff  determination  for  such  technology  and,  in  case  of 
approval,  issue  the  license  and  tariff  determination.  This  process  should  not  exceed 
three (3) months.  

4.15.1.6 Request for PSEC Certificate  
For  projects  using  technologies  included  in  Group  B,  a  PSEC  certificate  may  be 
requested.  This  request  should  be  made  by  the  project  sponsor  to  the  MoWP  before 
petitioning NEPRA for licensing and tariff determination.  
The request to the MoWP for PESC certification, shall include:  

• The project’s feasibility study. 
• A  supporting  letter  issued  by  the  AEDB  stating  that  the  project  complies  with 
these special characteristics. Such a supporting letter will be issued by the POE 
after  reviewing  the  feasibility  study  provided  by  the  sponsor,  the  additional 
(non‐energy)  socioeconomic  and  environmental  characteristics  of  the  project, 
and  the  improvement  the  project  could  bring  about  for  the  welfare  of  the 
population and local environment.  
• An  estimation  of  the  tariffs  required  (expressed  in  Rs/kWh)  in  order  to  make 
the project commercially viable, with all necessary supporting documentation. 
In  the  estimation  of  this  tariff,  eventual  project  revenues,  other  than  those 
derived from power sales, shall be taken into account (e.g., carbon credits).  
 The  MoWP,  in  consultation  with  the  Ministry  of  Environment,  the  Ministry  of  Finance 
and  any  other  GoP  institution  it  considers  relevant,  will  analyze  the  documentation 
submitted, and solicit additional information from the sponsors, if required.  
In particular, the MoWP shall determine if the project’s positive externalities (benefit to 
environment  and/or  population)  exceed  the  negative  impact  that  the  requested  tariff 
would impose on electricity consumers and power sector financing.  
In case such an analysis shows that a positive impact arises for the society as a whole, 
the GoP, through the MoWP, may issue such PSEC Certificate, taking into consideration 
that  this  issuance  is  facultative  of  the  GoP  and  that  there  is  no  obligation  to  give  any 
reason for a rejection.     

4.15.1.7 Performance Guarantee and Letter of Support 
Subsequent to issue of generation license and determination of the bulk power purchase 
tariff by NEPRA, the project sponsor shall be required to post a Performance Guarantee 
based on project capacity in favor of the AEDB or relevant CA, valid initially for a period 
of  three  (3)  months  in  excess  of  the  validity  of  the  LoS.    Upon  submission  of  the 
Performance Guarantee, a Letter of Support (LoS) shall be issued to the project sponsor 
by the relevant AEDB/CA to enable the project to achieve financial close.  Until financial 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  44
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

close  is  achieved,  the  LoS  shall  govern  the  project  and  supersede  all  other  documents 
and agreements. 
If the LoS is issued by a provincial or regional CA, the AEDB shall be officially notified of 
this.    Similarly,  if  the  LoS  is  issued  by  the  AEDB,  the  relevant  counterpart  agency  in 
whose territory the project is to be located shall be notified.  The AEDB shall maintain a 
central  registry  of  all  approved  RE  IPPs  in  the  country  to  ensure  their  proper 
coordination and facilitation at the federal level. 

4.15.2 Process Subsequent to Issuance of LoS 
After the issuance of the LoS to an RE IPP project, its sponsor will be expected to carry 
out the following activities: 

• Sign the Implementation Agreement (IA), with the AEDB acting on behalf—and 
with  the  permission—of  the  GoP,  and  the  Energy  Purchase  Agreements  (EPA) 
with the power purchaser. 
• Achieve financial close (as defined in the IA or EPA). 
• Achieve construction start (as defined in the IA or EPA). 
• Execute and commission the project according to major milestones established 
in the LoS. 
In  case  of  default  or  departure  from  agreed  milestones  by  project  sponsors,  the 
AEDB/CA  shall  have  the  right  to  terminate  the  LoS  and  encash  the  sponsors’ 
Performance  Guarantee  upon  issuance  of  due  notice  assigning  reasons  for  such  action 
and  after  provision  of  sufficient  opportunity  for  the  rectification  of  such  default.  
However,  in  case  the  delay  is  caused  by  actions  of  the  power  purchaser  or  by  the 
government, the IPP shall not be penalized.   Upon achievement of financial close, the 
security agreements (IA and EPA) shall supersede the LoS and all other documents and 
agreements.    If  the  LoS  expires,  the  IA  and  EPA  and  all  other  agreements  with  any 
government entity shall also automatically terminate. 
The investor, after receiving the LoS, will be required to submit to the relevant AEDB/CA, 
on  a  format  specified  by  the  agency,  a  mutually  acceptable  implementation  schedule 
with  specific  milestones  for  progress  monitoring.  The  AEDB/CA  shall  execute  the 
project’s  Implementation  Agreement  (IA)  on  behalf  of  the  Government  of  Pakistan, 
whereas the Energy Purchase Agreement (EPA) shall be executed between the IPP and 
the buyer upon GoP’s formal approval. 

4.16 Security Package and Risk Cover 
The security package for grid‐connected RE IPPs will comprise of the following: 

• Implementation Agreement (IA), Energy Purchase Agreement (EPA), and Water 
Use Agreement (WUA), as applicable. 
• GoP guarantee on payment obligations of public sector entities.  If some or all 
of  the  utilities  are  restructured  or  privatized  during  the  term  of  various 
agreements,  appropriate  safeguards  shall  be  built  into  the  privatization 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  45
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

agreements so that the IPP contracts are wholly secured over their respective 
contracted terms. 
• Provide protection against specific ‘political’ risks. 
• Provide protection against changes in the tax and duty regime. 
• Ensure  convertibility  of  Pakistani  Rupees  into  US  Dollars  at  the  prevailing 
exchange  rate  and  the  remitability  of  foreign  exchange  to  cover  necessary 
payments  related  to  the  project,  including  debt  servicing,  payment  of 
dividends, and repatriation of equity. 
• Suitable  indexation  of  tariff  components  to  cover  the  risk  of  exchange  rate 
variations. 

4.17 Corporate, Fee, and Contractual Arrangements 
4.17.1 Fee Structure 
Fees  are  to  be  paid  by  sponsors  of  grid‐connected  RE  projects  to  the 
AEDB/Provincial/AJK  Agency  as  indicated  in  Exhibit 5  below.    All  fees  are  subject  to 
revision from time to time. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  46
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 5: Fee and Financial Charges for Grid‐Connected RE IPPs 

Activity Fee Remarks

a. Registration US$ 100 The AEDB/CA will provide


an information package
upon registration
b. Project facilitation and evaluation
expenses for projects registered
with the AEDB/CA:
≤ 5 MW
> 5 MW to 20 MW
US$ 1,000
> 20 MW to 50 MW
US$ 5,000
> 50 MW (i.e., wind, solar w/
AEDB) US$ 10,000
US$ 20,000
c. Bank Guarantee for issuance of US$ 500/MW nameplate capacity or bid bond-
Letter of Intent (LoI) by AEDB/CA specified
d. Reimbursement of public sector As determined Payable prior to issuance of
feasibility study cost, if applicable by AEDB/ LoS, based on actual
CA costs incurred, up to
maximum ceiling
Reimbursement of private sector As per cost
feasibility cost, if applicable ascertained by
AEDB from
relevant
accounts
e. Performance Guarantee for US$ 2,500/MW Payable upon approval of
issuance of Letter of Support (LoS) capacity power purchase tariff by
by AEDB/CA NEPRA

f. Legal fees Subject to a cap of US$ 100,000 for projects


above 50 MW, US$ 50,000 for projects in the
range of 6-50 MW, US$ 20,000 for projects in
the range of 1-5 MW, and no charge for
projects of capacity below 1 MW

Note: Upon financial close, the IPP will provide a Letter of Credit (LC) to the power purchaser as Performance Guarantee
as specified in the EPA (US$3/kW per month), subsequent to which the original Performance Guarantee furnished
at the time of issuance of the LoS shall be released.

4.17.2 Enterprise Structure and Licensing Requirements 
Each  IPP  setting  up  a  plant  meant  only  for  supplying  power  to  the  utility  grid  shall  be 
required  to  form  a  company  in  accordance  with  the  laws  of  Pakistan  under  the 
Companies  Ordinance,  1984,  for  the  specific  purpose  of  power  generation  and  for 
obtaining a generation license from NEPRA.  However, producers who wish to establish 
plants  whose  power  output  is  not  exclusively  for  sale  to  the  utility  (e.g.,  captive  or 
dedicated plants with or without grid spillover provision) would be exempt from such a 
requirement.   

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  47
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.17.3 Lock­in Period 
The ‘Main Sponsor’ (defined as the individual or group holding at least 20% equity in the 
IPP  project),  together  with  other  initial  project  shareholders,  must  hold  51%  of  the 
project equity for a period up to the project’s Commercial Operation Date (COD). 

4.17.4 Type of Contracts 
RE  IPP  projects  for  sale  of  all  power  to  the  grid  may  be  implemented  through  either 
‘Build, Own, and Operate’ (BOO) or ‘Build, Own, Operate, and Transfer’ (BOOT) contracts 
between the parties concerned, valid for a period of not less than 20 years. 
For the other type of projects, no such contracts shall be required.  Instead, for captive, 
dedicated,  or  grid  spillover  projects,  or  projects  availing  ‘net  billing’,  ‘wheeling’  or 
‘banking’ facilities (see Sections 4.6.3, 4.8.1 & 4.8.3), separate contractual arrangements 
will  be  required  between  the  parties  dealing  with  matters  such  as  metering, 
maintenance  of  interconnection,  system  protection,  and  billing  of  net  sales  and 
purchase, wheeling, and banking charges/tariffs, etc. 

4.17.5 Nature of Equipment 
Projects which are meant for generating electricity for the sole purpose of supply to the 
utility (NTDC or DISCOs) grid system, i.e., grid‐connected RE IPPs, will be required to use 
new equipment.  There shall be no such restriction on other producers. 

5 Medium Term Off­grid RES­E Policy  
5.1 Scope of Policy 
The  Medium  Term  Off‐grid  RES‐E  Policy  is  aimed  to  provide  electricity  services  to 
populations  living  in  villages,  settlements,  and  scattered  households  not  connected  to 
the power grid15 by employing renewable or hybrid technologies. The qualifying target 
settlements  are  those  not  included  in  any  national  or  regional  grid  expansion  plans 
spanning the next ten years and are located beyond 20 km of the existing power grid.  
These  villages/scattered  dwellings  can  be  supplied  electricity  based  on  renewable 
sources  of  energy  generation,  either  by  stand‐alone  or  mini‐grid  systems  with  an 
installed generation capacity less than 5 MW. RES‐E technologies addressed under this 
policy include: 

• Micro‐ or mini‐hydel 
• Hybrid  systems,  in  which  at  least  one  renewable  energy  source  is  employed 
besides conventional thermal generation 
• Solar PV and thermal 
• Micro‐ or mini‐wind systems  
                                                       
15
  For the purposes of RE policy terminology, the term ‘grid’ is meant to imply either national or regional electricity 
T&D networks operated by the NTDC/CPPA and/or DISCOs of 11 kV or higher voltage.  Isolated, community‐based 
local distribution networks are considered ‘off‐grid’. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  48
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Bio‐energy  resulting  from  anaerobic  gas  digestors,  pyrolitic  biomass 


gasification, co‐generation, etc. 

5.2 Assessment of Target Populations 
The  AEDB  shall  consolidate  and  update,  with  the  assistance  of  power  utilities  and 
provincial/regional/local governments, a complete assessment of un‐electrified villages 
and scattered communities falling under the scope of this policy. This list should include 
at  the  very  least:  the  name  of  the  village/settlement  and  province/region,  geospatial 
coordinates,  number  of  inhabitants,  and  number  of  households.    This  database  should 
be completed within six (6) months of this policy coming into effect. 

5.3 Medium Term Electrification Targets  
At least 25% of off‐grid un‐electrified villages identified by the AEDB in each province or 
region should be supplied with RE‐sourced electricity by December 31, 2014. 

5.4 Multiple Deployment Approach 
Off‐grid electrification can be developed either: 

• Directly by provincial/regional/local governments on a self‐financed, voluntary 
basis and/or driven by social players without recourse to national subsidies, or 
• Via  national‐provincial  coordination,  in  which  provincial/regional  governments 
compete for federal government assistance to finance their respective off‐grid 
projects.  
Under  the  first  mechanism,  provincial/regional/local  governments  are  fully  entitled  to 
develop  electrification  projects  within  their  own  territorial  jurisdictions.  Each 
province/region  may  develop  a  simplified  regime  for  off‐grid  project  deployment, 
following which bilateral agreements between the parties involved must be reached to 
enforce  project  implementation.  These  agreements  shall  be  arranged  solely  by  the 
relevant  parties  which  would  mutually  decide  on  tariffs,  quality  of  service,  and  other 
contractual terms. 
Under  the  second  alternative,  a  coordinated  plan  amongst  national  and 
provincial/regional  authorities  will  be  set  up  to  assign  competences  to  the  different 
parties  involved  in  order  to  maximize  their  operational  potential  and  capabilities  for 
achieving effective and efficient off‐grid rural electrification utilizing RES‐E.  
The remainder of this policy statement will elaborate exclusively on the framework for 
off‐grid RES‐E deployment utilizing federal funding. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  49
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

5.5 Coordination Amongst National and Provincial Authorities 
5.5.1 Off­grid Electrification Agencies 
Provincial/regional  governments—through  their  respective  Off‐grid  Electrification 
Agency  (OGEA)16  and  in  close  cooperation  with  local  governments—shall  be  the  key 
stakeholders  for  promoting  off‐grid  rural  electrification  within  their  territorial  borders. 
Each  province  shall  create  a  OGEA,  or  assign  the  functions  of  the  OGEA  to  an  existing 
institution, within six (6) months of this policy becoming effective. The functions of the 
OGEA in relation to off‐grid electrification are: 

• Assist  the  AEDB  in  consolidating  and  updating  target  village  and  scattered 
population assessment for off‐grid RES‐E deployment.  
• Prepare  specific  electrification  projects  for  identified  villages  and  scattered 
populations. 
• Provide a single‐window facility for project sponsors at the regional level. 
• Help  develop  and  implement  qualifying  projects,  based  on  the  guidelines 
defined in this policy. 
• Issue tenders, evaluate bids, and issue off‐grid project authorizations. 
• Monitor the quality of service provided by authorization holders. 
• Set the fees for off‐grid services. 
• Manage  and  disburse  allocated  national  subsidy  to  authorized  service 
providers.  
• Wherever  possible,  ensure  the  assistance  and  participation  of  local 
governments in RES‐E deployment. 

5.5.2 Project Selection 
The  AEDB  shall  act  as  the  national  off‐grid  RES‐E  program  coordinator  and  shall 
determine  the  allocation  of  national  funds  to  different  off‐grid  electrification  projects 
based on rules previously defined by the Government of Pakistan. 
Each  provincial/regional  OGEA  will  prepare  and  submit  to  the  AEDB  a  location‐specific 
RE‐based electrification project derived from the approved list of villages and scattered 
populations  consolidated  by  the  AEDB.    Each  project  assessment  shall  cover,  at  a 
minimum, the following aspects: 

• Socioeconomic characteristic of target village/scattered population. 
• Study on power demand potential and projected supply. 
• Generation technology/ies to be deployed. 

                                                       
16
  Or any related agency/department designated as such by the provincial government or regional administration for 
the development of all off‐grid rural electrification projects in its territorial jurisdiction. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  50
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Number of households to be connected. 
• Proposed implementation period. 
• Total  cost  of  the  project,  segregated  between  capital  and  operational 
expenditures. 
• Detailed cash flow projections for the project. 
• Social benefits due to project implementation. 
• Quality‐of‐service characteristics. 
The proposed off‐grid projects should not strictly focus on providing electricity services 
only. It is highly desirable that projects should include, to the extent feasible, domestic 
equipment, water installations, and or any other facility that could help to improve the 
social and human development of the target village/scattered population. 
Each project must strictly comply with the guidelines developed by the AEDB for proper 
comparison, benchmarking, and analysis. It shall be the duty of the AEDB to document 
simplified  procedures  for  project  approval,  including  criteria  for  ranking  projects  and 
definition  of  the  parameters  needed  to  obtain  comparable  project  proposals  (e.g.,  the 
cost of different generation technologies).  
The AEDB shall collect all project proposals and shall create an annual project portfolio. 
This portfolio will be organized according to a merit order based only on the social cost‐
benefit analysis of the project.  

5.5.3 Social Cost­Benefit Analysis 
The  AEDB  will  approve  projects  according  to  a  merit  order  based  on  a  standardized 
social cost‐benefit analysis. The social cost‐benefit analysis shall consider: 

• The  subsidy  requirement  (total  and  as  a  share  of  total  cost),  in  terms  of  both 
capital investment and for operating the service. 
• The beneficiary population involved. 
• The economic development benefits evaluated on the basis of contribution to 
economic output and growth, including direct and indirect economic costs and 
benefits. Among other analyses, this should include the expected improvement 
in,  for  instance,  water  supply,  sanitation,  education,  health,  gender  issues, 
employment,  incomes,  and  other  sustainable  and  human  development 
indicators of the community, instead of just kWh supplied. 
• The HSE (health, safety, and environment) performance aspects of the projects. 

5.5.4 Project Implementation 
Once  a  project  has  been  awarded  by  the  AEDB,  the  OGEAs—in  cooperation  with  local 
governments—shall invite public tenders for granting a 10‐year Authorization to develop 
off‐grid  electricity  services  following  technology  specifications  stated  in  the  relevant 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  51
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

electrification  project.  If  convenient  (i.e.,  for  proximate  projects),  several  concession 
areas or population centers may be grouped under a common tender. 
All  types  of  stakeholders  (cooperatives,  NGOs,  private  individuals,  and  private 
companies) shall  be  eligible  to  participate  in  the  off‐grid  tender  process  provided  they 
meet  a  minimum  set  of  technical  qualifications  to  be  defined  by  the  OGEAs  with  the 
guidance of the AEDB. 
The AEDB shall define the standard Authorization template that the OGEAs will apply to 
specific  project  tenders.  In  the  Authorization,  at  a  minimum  the  following  would  be 
included: 

• Schedule for electrification. 
• Rights and obligations of all parties involved. 
• Applicable tariffs/fees. 
• Milestones for subsidy delivery. 
• Quality of service regulation, including standards adjusted for each technology 
and fines for non‐compliance. 
• Community  capacity  building  (provision  of  technical  training,  productivity 
enhancement,  and  other  incentives  to  promote  community  involvement  and 
economic development of the area). 
• Conditions for termination of the Authorization. 
The  primary  criterion  for  selecting  the  winning  bid  will  be  least  subsidy  demanded  for 
capital investment. 
The  Authorization  to  develop  the  project  shall  be  issued  by  the  OGEA  on  behalf  of 
provincial/regional governments.  

5.6 Subsidies 
The federal government shall provide subsidies for capital investments to the extent of 
70%  of  the  total  investment  required  for  the  project,  as  previously  approved  by  the 
AEDB. 
The remaining capital and O&M costs, including replacement costs, may be financed by 
any, or a combination, of the following: 

• The respective OGEAs, employing provincial/regional government funds. 
• The  tariffs/fees  for  the  off‐grid  services  defined  by  the  OGEA,  taking  into 
account  the  customers’  ability  to  pay  and  instituted  in close  cooperation  with 
local governments 
• Community contribution to such schemes may be in the form of sweat equity 
(labor), land, and/or cash. 
• NGO or private contributions. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  52
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The  provincial/regional  governments  shall  ensure  the  sustainability  of  the  projects  by 
providing adequate funds to the Authorization holder or to the local community, once 
the Authorization is expired. 
As subsidies are provided, they shall be limited to the amounts needed for basic social 
and  human  needs,  including  basic  economic  activities.  Some  consumers  may  want  to 
pay more for higher levels of quality and/or quantity of electricity service, in which case 
the extra quality or quantity must be paid for by the customer as per provisions in the 
bilateral agreement with the service provider. 

5.7 Off­grid Electrification Account 
In order to provide funds to off‐grid projects, an Off‐grid Electrification Account (OGEAC) 
in the budget for the AEDB shall be created. The OGEAC settlement shall be an attribute 
restricted solely to the AEDB. 
The OGEAC shall be financed by: 

• Government  budgetary  allocations.  The  request  for  funds  to  the  Ministry  of 
Finance will be made by the Ministry of Water and Power, as estimated by the 
AEDB in accordance with the off‐grid electrification project targets, and 
• Grants  and  loans  that  multilateral/bilateral  financing  and  donor  agencies  may 
provide. 
Delivery  of  federal  subsidies  shall  be  output‐based  and  only  related  to  capital 
expenditures.    The  OGEAs,  directly or  the  through  local  governments, will  monitor  the 
fulfillment  of  the  milestones  defined  in  the  Authorization  in  terms  of  investment,  and 
ask  for  subsidy  delivery  to  the  AEDB  who  will  transfer  the  funds  to  the  holder  of  the 
Authorization.  The AEDB may develop spot monitoring of the projects in order to cross‐
check the use of these national subsidies.  
The  government—through  state‐owned  banks—will  provide  financing  facilities  at 
preferential rates, collateralized by the future stream of subsidy deliveries defined in the 
Authorization. 

5.8 Fee Structure 
Determination of the level and structure of the off‐grid electricity service fees shall be 
the sole responsibility of the provincial/regional governments, working in collaboration 
with local governments. The OGEAs will define the fee structure for each Authorization 
according to the following criteria: 

• Tariffs may be technology‐wise differentiated. 
• In stand‐alone systems, a one‐part tariff (Rs/customer) shall be preferred. 
• In  community  (mini‐  and  micro‐grids)  system,  one  part‐tariff  based  on  the 
contracted  capacity  (Rs/kW‐contracted)  shall  be  preferred.  In  these  systems, 
each customer will have an on‐site power limiter installed disconnect service if 
the contracted capacity is exceeded. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  53
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• In such cases where the customer is willing to pay for a higher quality or more 
energy than required for basic needs, a metering device may be installed. 
• Tariffs may be only indexed to local inflation. 

5.9 Financial and Fiscal Incentives 
All  projects  under  the  scope  of  this  policy  shall  be  eligible  for  all  fiscal  and  financial 
incentives described in Section 4.5.  These facilities shall be equally applicable to private, 
public‐private, non‐governmental and public sector renewable energy power projects. 

5.10 Allocation of Carbon Credits  
All  qualifying  off‐grid  projects  eligible  for  financing  under  the  Clean  Development 
Mechanism  (CDM)  shall  be  encouraged  to  register  for  Certified  Emissions  Reduction 
(CER) credits with the CDM Executive Board, either collectively or individually.  Holders 
of  the  Authorization  shall  assume  all  costs,  risks,  and  benefits  of  qualifying  for  and 
obtaining  CERs,  including  the  potential  revenues  associated  with  them.    Authorization 
holders  would  be  free  to  arrange  for  independent  funding,  buy‐back,  and  CER  trading 
facilities  with  third  parties  on  their  own.    The  GoP  shall  facilitate  this  process  to  the 
extent possible, excluding financing from public funds of CDM‐related project costs. 

5.11 Security Package and Risk Cover 
Due  to  the  nature  of  the  projects  envisaged  under  the  Off‐Grid  RE  Policy,  no  security 
package or risk cover shall be required or provided. 

5.12 Institutional, Legal, and Regulatory Consents 
Regulatory consents and processing requirements for off‐grid services shall be simplified 
to the extent possible, so as to expedite the development of such projects and enable 
small communities and investors to participate fully in these schemes. 
No  regulatory  or  operational  consents  from  NEPRA,  the  NTDC,  or  DISCOs  shall  be 
required for such projects. The only necessary regulatory consent shall be in the form of 
the  Project  Information  Memorandum  (PIM),  containing  all  technical  and  economic 
features of the project. The PIM shall be developed by the OGEAs and submitted to the 
AEDB  for  review  and  acceptance.    For  projects  not  soliciting  national  funding  support, 
this consent shall also not be required.  
There shall be no requirement from the federal and provincial Environmental Protection 
Agencies (EPAs) for submission of an Initial Environmental Examination (IEE) for off‐grid 
projects  of  up  to  1  MW.    The  EPAs  shall  define  a  simplified  basic  environmental 
compliance and impact checklist that shall be completed by the OGEAs for all projects 
and submitted to the EPAs prior to award of the project by the AEDB, primarily to ensure 
that  water  rights,  flows,  and  community  interests  are  not  unduly  infringed  upon. 
Additionally, as a condition of the Authorization, the project sponsor shall be required to 
certify  how  design,  engineering,  construction,  and  safety  criteria  will  be  addressed 
during the course of its construction and operation. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  54
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

5.13 Performance Monitoring and Enforcement 
Project  performance  shall  be  monitored  by  provincial  and  or  local  governments.  The 
OGEAs will develop a program of awareness in their areas to enable direct monitoring of 
the service provider by customers and other community stakeholders.  
The monitoring process should have two main parts: 

• Investment  plan  monitoring:  This  involves  verification  of  the  investment 


milestones defined in the Authorization being reached as a trigger for the AEDB 
to release subsidy payments. This monitoring shall be performed by the OGEAs. 
• Ongoing  performance  monitoring  for  the  duration  of  the  Authorization:  This 
involves monitoring that service quality standards defined in the Authorization. 
Service  quality  includes  targeted  hours  of  service,  number  and  duration  of 
interruptions,  and  safety  of  the  system.  Quality  of  service  regulation  shall  be 
defined  by  AEDB  as  part  of  the  standard  Authorization,  considering  the 
principles  of  simplicity  and  enforceability.  The  monitoring  shall  be  based  on 
customers’, or other community stakeholders’, claims. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  55
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex II:  AEDB Position Paper 1: 
 Proposal for Pakistan’s Medium Term 
On­Grid RES­E Policy 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  57
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

AEDB Position Paper 1: 
Proposal for Pakistan’s Medium­Term 
On­Grid RES­E Policy 
 

1 Background 
Recent studies developed under ADB TA 4881‐PAK show that the economic penetration 
of on‐grid renewable energy (RE) power in Pakistan should be around 17 TWh in 2020.  
This is around 7% of total grid‐based electrical power generation expected for that year.  
The  fact  that  any  capacity  approaching  this  share  is  not  currently  developed  indicates 
that some strong barriers may exist, especially if we consider that the marginal cost of 
RE  is  around  USD  75/MWh  and  the  cost  of  generation  based  on  FO  is  more  than  USD 
125/MWh.  This provides a very strong economic signal favoring the development of RE, 
and  it  can  therefore  be  concluded  that  some  impediments—of  administrative, 
regulatory, or financial kind—are responsible for the current lackluster RE deployment in 
the country.  Almost 60% of this expected RE share would be comprised of hydel plants 
that are much cheaper than combined cycle gas turbines (CCGT) running on fuel oil (FO), 
which in turn defines the price of avoided generation.  The other two  RE technologies 
that should be ‘naturally’ developed in Pakistan are bagasse‐based combined heat and 
power (CHP) and other types of biomass conversion.  Definitely, small‐scale hydel is the 
cheapest  option  for  developing  RE  in  Pakistan  and  should  be  encouraged  as  early  as 
possible. 
A national on‐grid RE policy should be based on a social assessment of cost and benefits.  
The  analysis  of  natural  penetration  based  on  private  costs  alone  does  not  consider 
externalities,  and  therefore  represents  a  limited  subset  of  such  an  analysis.    The  same 
studies have observed that the optimal penetration of RE generation when social costs 
are also considered should be around 25 TWh  in 2020, which is around 10.3%  of total 
on‐grid power generation expected for that year.  Market failure (i.e., externalities not 
properly  being  internalized)  would  thus  hamper  the  development  of  about  8  TWh  of 
renewable  energy,  and  so  that  an  economic  incentive  mechanism  needs  to  be  put  in 
place,  assuming  that  all  other  barriers  that  block  the  development  of  natural 
penetration of RE have also been removed (grid access, difficult to sign sales contracts, 
etc).  Under social cost assessment, not only hydel and biomass plants, but also biogas 
(from  farm  slurries,  sewage,  landfills,  etc.)  and  wind  energy  plants  are  required  to 
generate, in order to replace CCGTs running on FO and natural gas—as a matter of fact, 
the  studies  show  that  all  FO‐based  generation  would  need  to  be  replaced,  as  well  as 
around  15  %  of  the  gas‐based  generation  in  2020  because  the  marginal  cost  of  RE  for 
supplying this quota is  around USD 100/MWh.  If the policy to achieve these results is 
properly defined and implemented, the social wealth (total surplus) that may be created 
in Pakistan is about USD 2,100 million per year. 
Whereas a year and a half is certainly not a sufficient time period over which to make a 
definitive  diagnosis  of  the  current  short‐term  RE  policy—as  several  projects  are  still 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  59
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

maturing,  and  therefore  additional  time  should  be  allowed  to  evaluate  their  further 
progress  towards  actual  implementation—nevertheless,  several  symptoms  exist  that 
indicate potential problems in achieving the aforementioned RE penetration goals unless 
policy  elements  are  adjusted  promptly.    One  of  the  critical  issues  is  the  existing  dual 
mechanism  for  setting  tariffs  for  RE  projects:  a  developer  may  apply  for  either  the 
upfront  tariff  defined  by  NEPRA  and/or  raise  a  tariff  petition  to  be  reviewed  by  the 
regulator on a case‐by‐case basis.  Obviously, having both possibilities at hand, virtually 
all developers have chosen the second option, and in all proposed RE IPP projects have 
asked  for  tariffs  higher  than  the  upfront  one  offered  by  the  regulator.    In  terms  of  its 
formulation,  the  current  tariff  system  for  unsolicited  RE  proposals  is  based  on  a  ‘cost‐
plus’ approach.  The cost‐plus computation requires a case‐by‐case determination of the 
applicable  tariff  for  every  single  producer.    From  a  regulator’s  point  of  view,  the 
advantage  of  this  methodology  is  the  ability  to  reduce  infra‐marginal  rents  (i.e., 
producers’  surplus)  down  to  zero  and,  therefore,  maximize  the  consumers’  surplus.  
Nevertheless,  this  approach  presents  several  major  shortcomings,  which  can  be 
summarized as follows: 

• Investors,  taking  advantage  of  asymmetries  in  information  access  (as  only  the 
developer  has  intimate  knowledge  of  a  particular  project’s  costs  and 
peculiarities), can ‘game’ against the mechanism to obtain higher infra‐marginal 
rents. 
• It  decreases  the  financial  incentive  to  invest  in  RES‐E  technologies,  as 
developers are deprived of most of the infra‐marginal rents.   
• It  increases in  the  administrative  burden  in  processing  projects,  and  increases 
the possibility of unavoidable systemic delays. 
This approach has been adopted in Pakistan so far in order to help reduce the risk faced 
by the developers who want to undertake such projects, since it guarantees a return‐on‐
equity (ROE) of at least 15 %.  While it is true that this method reduces some of the risks 
to  the  developer,  it  is  also  true  that  it  eliminates  any  additional  incentive  to  develop 
these types of projects.  For instance, the ROE assured is the same regardless the type of 
power  generation  project  under  consideration  (i.e.,  renewable  or  conventional).    This 
can lead to quite curious situations, such as that the upfront tariff allowed by NEPRA for 
conventional  generation  using  reciprocating  engines  burning  diesel  oil  (USD 
119.7/MWh)  is  25%  higher  than  the  upfront  tariff  for  generation  using  wind  (USD 
95/MWh),  regardless  of  the  benefits  that  the  latter  brings  to  the  environment  or  in 
terms of fuel independence.   
Additionally,  available  international  evidence  shows  that  feed‐in  (up‐front)  tariffs  are 
the  best  incentive  mechanism  for  developing  RE  capacity,  as  can  be  observed  in  the 
cases of Europe and some BRIC (Brazil, Russia, India and China) countries.  International 
experience  also  shows  that  the  tariff  is  a  necessary  but  not  a  sufficient  condition  for 
developing  RE  energy;  grid  access,  administrative  issues  (contracts,  licenses,  permits, 
multiple  uncoordinated  processing  windows,  etc.),  and  instability  of  the  incentive 
mechanism are as relevant as the tariff policy for fostering the penetration of renewable 
energy.  A series of detailed annexes (Annexes IV to IX) prepared under ADB TA 4881‐
PAK conclusively indicate that RE technology‐wise feed‐in tariffs—based on an optimal 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  60
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

balance between the marginal social supply curves of RE and conventional generation in 
Pakistan (i.e., on the ‘avoided‐cost’ principle)—would offer the most economical, ‘least‐
cost’  power  generation  mix  for  the  country  in  the  medium  term  and  beyond  (i.e.,  to 
2020) and would maximize the social surplus created in society while at the same time 
allocating a reasonable share to private investors which would serve as a necessary and 
strong  incentive  to  ensure  that  the  RE  penetration  targets  stated  earlier  can  be 
achieved.  Such fixed, non‐negotiable tariffs would help circumvent the protracted rate 
negotiations  that  recently  proposed  RE  IPPs  have  been  embroiled  in,  introduce  an 
element  of  competition  and  urgency  in  project  implementation,  ensure  that  all 
economically  viable  RE  technologies  are  simultaneously  developed,  provide  an 
economically viable basis for the regulator to determine sustainable RE pricing, and help 
prioritize  available  ‘least‐cost’  and  ‘best‐site’  RE  development  on  a  fast  track  that  can 
significantly help kick off the RE power generation industry in Pakistan. 

2 Extension of RE Short­term Policy 
The  current  short‐term  on‐grid  RE  policy  must  be  extended  to  June  30,  2009,  i.e.,  by 
one calendar year beyond the current expiration date of June 30, 2008.  This is required 
in order to allow projects that are presently at an advanced processing stage to achieve 
financial closure under existing policy stipulations as envisaged by the investors, as well 
as  to  afford  a  reasonable  timeframe  for  stakeholders  to  confer  about  the  mid‐term 
policy.  An official announcement to this effect should be made at the earliest to assure 
investors of continuity in the policy environment and allow them to plan accordingly. 

3 RE Medium Term Policy At­a­Glance 
3.1 Target Markets 
The  scope  of  this  policy  is  on‐grid  RE;  ‘on‐grid’  RE  means  grid‐connected  power 
generation  fueled  by  renewable  resources  (either  to  transmission  or  distribution 
systems).    For  purposes  of  RE  policy  definition,  ‘on‐grid  RE’  includes  the  following 
renewable  energy  technologies  (RETs),  for  individual  project  installed  capacity  higher 
than 1 MW: 

• Small hydro of 50 MW or less capacity 
• Solar photovoltaic (PV) and solar thermal energy for power generation 
• Wind power generation 
• Municipal solid waste‐to‐energy (WTE) power 
• Landfill methane recovery, and 
• Bio‐energy resulting from: 
o Anaerobic biogas digestors 
o Pyrolytic biomass gasification, co‐firing, cogeneration, etc. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  61
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.2 Implementation Period 
The  medium‐term  RE  policy  should  be  applied  from  July  1,  2009  to  June  30,  2014.17  
Although  in  the  current  short‐term  Policy  for  Development  of  Renewable  Energy  for 
Power Generation, 2006, the medium‐term policy to be developed was envisaged to be 
implemented  for  a  four‐year  period,  AEDB  recognizes  that  incentives‐based  policies 
require  at  least  five  years  of  sustained  promotion  in  order  to  be  successful  and  bear 
results;  policy  incentives  must  remain  stable  and  assured  over  a  reasonably  extended 
period in order for investment confidence to build up, supportive institutional capacity 
to  develop,  and  implementation  bottlenecks  to  be  gradually  and  systematically 
removed. 

3.3 Consistency Across Policies 
An RE project that achieves financial closure before the onset of the next policy phase 
should continue to be guaranteed all the incentives, terms, and conditions defined in the 
applicable short‐term RE policy over the tenure of its Power Purchase Agreement (PPA).  
An  important  aspect  regarding  various  successive  policy  periods  is  that  of  assuring 
continuity for projects that have been implemented under a certain policy, even in the 
case  that  the  relevant  policy  or  specific  incentives  change  in  the  meantime.    This 
approach  ensures  the  consistency  and  stability  of  an  RE  deployment  climate  from  the 
perspective  of  both  investors  and  power  purchasers,  as  well  as  other  relevant 
stakeholders. 

3.4 Tariff Incentives 
3.4.1 Selected Approach 
AEDB’s  proposal  for  determining  the  RE‐based  power  procurement  tariffs  for  the 
medium‐term policy regime is:  

• To  set  up‐front  tariffs  for  each  technology  based  on  the  ‘avoided‐cost’ 
approach  for  those  technologies  whose  marginal  cost  is  lower  than  the 
avoided social cost.  For these technologies, NEPRA will need to set technology‐
wise feed‐in tariffs based on the characteristics of the RE technologies (‘supply 
curve  analysis’),    bounded  by  the  range  obtained  from  the  use  of  private  and 
social avoided costs.  According the referential studies already developed (see 
Annex VII), this means that for those technologies (small‐scale hydel, biomass, 
biogas,  and  wind),  up‐front  tariffs  would  range  approximately  between  USD 
75/MWh and USD 100/MWh.   
• To  set  up‐front  tariffs  for  each  technology  based  on  the  marginal  cost  of 
providing the quota set by the Government of Pakistan for those technologies 
whose marginal cost is higher than avoided social cost.  An up‐front  tariff is 
also  proposed  to  foster  the  deployment  of  any  specific  RE  technology  that 
promises additional benefits to society (i.e., meets industrial policy  objectives, 
                                                       
17
  This assumes that the current short‐term on‐grid RE policy will be extended to June 30, 2009, as stated earlier, in 
order to allow some wind IPPs presently nearing financial closure to do so by early 2008. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  62
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

creates  employment  opportunities,  provides  economical  disposal  mechanism 


for  wastes,  etc.)  that  are  not  explicitly  included  in  the  supply  curve  of  that 
technology  because  they  are  currently  ‘expensive’  (PV,  solar  thermal,  WTE); 
however, a good policy should prevent a reasonable, justifiable target quota for 
them (defined in terms of installed MW) from being overshot.   
• Discontinue the present system of negotiated RE power purchase tariffs (i.e., 
case‐by‐case petitioning for project tariffs above the up‐front tariff). 
• The competitive bidding alternative (i.e., tendering) must be kept as an option 
for only those technologies whose marginal cost is higher than avoided social 
cost. 

3.4.2 Structure of Tariffs 
Up‐front  tariffs  should  be  denominated  in  Pakistan  Rupees/kWh.    The  up‐front  tariffs 
should be based on a one‐part pricing approach (i.e., a single energy charge).  Two‐part 
tariffs  (capacity  payments  plus  energy  payments)  are  difficult  for  most  RES‐E 
technologies, as most of them cannot guarantee capacity availability—even in the case 
of biomass‐based generation, which may be constrained by seasonal harvests.  Despite 
the fact that some types of hydel plants may be in a position of providing firm capacity 
commitments to the system, for the sake of simplicity the use only an energy charge is 
recommended. 

3.4.3 Indexation for Up­front Tariffs 
Up‐front  tariffs  must  be  adjusted  based  only  on  local  currency  variations.    The 
indexation  of  tariffs  with  the  US  dollar  exchange  rate  should  be  automatic  on  a  six‐
monthly  basis.    Another  possibility  presently  under  discussion  is  to  use  a  reference  a 
currency basket comprising of both US Dollars and Euros (e.g., 50:50). 

3.5 Type of Contract 
The RE projects should be implemented on the basis of ‘Build, Own, and Operate’ (BOO).   

3.6 Allocation of Network Investment Cost  
The construction of transmission lines for evacuation of power from any RE IPP should 
be  the  responsibility  of  the  NTDC,  KESC  or  a  DISCO  (depending  on  the  location  and 
supply voltage of the project) if the length of the connection required from the project’s 
outgoing bus bar to existing grid installations is shorter than 20 km, unless the IPP, of its 
own  choice,  undertakes  to  install  such  infrastructure  on  a  mutually  agreed  upon 
transmission charge with the NTDC.  The NTDC should bear all expenses associated with 
power balancing on the grid to accommodate priority dispatch and variability on account 
of the RE project, and ensure that these expenditures are made in a timely fashion. 

3.7 Mandatory RE Power Purchasing 
Until the CPPA ceases its activities as the central power purchase agency, all contracts 
for power generation from RE concluded under the current RE policy should be signed 
by  the  CPPA—excepting  those  bracketed  as  ‘direct  sales’.    After  the  CPPA  ceases  its 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  63
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

activities,  neither  distributors  nor  transmission  companies  should  have  the  right  to 
reject, in part or in entirety, any contract signed previously between the CPPA and an RE 
power generator.  NEPRA should establish a future methodology for compensating those 
DISCOs/TRANSCOs  that  are  forced  to  accept  contracts  with  a  feed‐in  tariff  under  the 
medium‐term RE policy. 

3.8 Direct Sales 
RE  power  producers  should  be  allowed  to  enter  into  direct  (bilateral)  sales  contracts 
with  eligible  end‐use  customers.    In  that  case,  prices  should  not  require  approval  by 
NEPRA. 

3.9 Allocation of Carbon Credits  
AEDB considers logical as well as administratively simpler for RE investors to assume the 
risks  and  benefits  of  qualifying  for  and  obtaining  certified  emissions  reduction  (CERs), 
along  with  the  potential  revenues  associated  with  them.    The  current  allocation  of 
carbon  credit  revenues  between  RE  investors  (IPPs)  and  the  power  purchasers  (state 
entity) is unnecessarily complicated and was considered necessary under the prevailing 
cost‐plus  tariff  determination  methodology;  however,  with  up‐front  tariffs,  such  a 
situation  would  no  longer  hold.    Additionally,  the  allocation  of  future  CER  revenues 
entirely to the RE developer would act as a much stronger additional financial incentive 
and  would  be  more  consistent  with  CDM  eligibility  under  its  ‘financial  barrier’ 
assessment criteria. 

3.10 Land and Site Access 
The federal, provincial, and AJK governments shall facilitate investors in acquiring land 
or  right‐of‐way  (RoW)  for  project  development,  as  well  as  providing  site  access  on  a 
case‐to‐case basis by leasing, acquisition of RoW, and/or construction of road linkages.  
However, the primary responsibility for acquiring land and site access should rest with 
the project sponsors. 

3.11 Incentives Other Than Tariffs 
AEBD  believes  that  current  general  incentives,  including  the  sovereign  risk  guarantee, 
the  financial  regime,  and  the  fiscal  regime,  as  defined  in  the  2006  RE  policy,  are 
adequate and should be continued into the medium term stage as well.   

3.12 Roles of Institutions 
In  the  medium‐term  RE  policy  tenure,  AEDB  is  not  forecasting  major  changes  in  the 
different  roles  that  each  stakeholder  institution  has  in  facilitating  renewable  energy 
development  and  project  implementation  in  Pakistan.    However,  AEDB  considers  that 
some slight clarification of AEDB and NEPRA roles may be to the benefit of the policy, as 
would some changes brought about by specific policy provisions (e.g., absence of need 
for independent wind speed monitoring and verification). 
AEDB has detected that pre‐feasibility studies are critical for the development of some 
RE  resources  (mostly  hydel  and  some  biogas  projects)  and  for  relatively  immature  or 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  64
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

new  technologies.    The  cost  and  complexity  of  undertaking  such  studies  is  a  major 
barrier  for  the  private  sector  seeking  to  develop  RE  projects  in  Pakistan,  and  often 
readily  bankable  projects  are  not  synchronized  with  the  availability  of  concessional  IFI 
financing  (e.g.,  the  ADB’s  REDSIP  multi‐tranche  RE  financing  facility).    AEDB  and 
provincial  administrations  must  undertake  the  lead  responsibility  of  developing  these 
pre‐feasibility studies, either through GoP and/or IFI financing (grants and/or soft loans). 
In the case of NEPRA, this proposal requires NEPRA to define feed‐in tariffs according to 
the conceptual approaches presented in this paper (and detailed in Annex VII), as well 
as to approve the application of pre‐defined up‐front tariff to a specific RE project, and 
to adjust grid and distribution codes in order not to block the development of RE IPPs.  
This  may  require  a  review  and  adjustment  of  NEPRA  rules,  which  is  currently  being 
undertaken. 

3.13 Institutional, Legal, and Regulatory Consents 
AEDB judges that the existing institutional, legal, and regulatory consents required prior 
to  approval  and  implementation  of  RE  IPP  projects  must  not  be  changed  for  the 
medium‐term RE policy, except for simplified permitting provisions for small‐scale plants 
(i.e., less than 5 MW capacity). 

3.14 Procedural Requirements 
AEDB  believes  that  the  processing  schedule  foreseen  in  the  2006  RE  Policy  is  largely 
adequate.  However, it must be adjusted to the tariff regime that is instituted under the 
medium‐term  RE  policy,  and  should  be  reduced  in  overall  duration  to  the  extent 
reasonably possible. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  65
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex III:  AEDB Position Paper 2: 
Proposal for Pakistan’s Medium Term 
Off­Grid RES­E Policy 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  67
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

AEDB Position Paper 2: 
Proposal for Pakistan’s Medium­Term 
Off­Grid RES­E Policy 

1 Background 
Historically, the predominant model for electrification in developing countries has been 
grid  extension  and/or  conventional  energy‐powered  mini‐grids  developed  by  large, 
state‐owned  utilities.  These  extensions  have  usually  been  financed  through  cross‐
subsidies  between  consumers,  or  by  loans  or  grants  provided  by  the  government. 
Recently, the spectrum of electrification models has widened, including a long list of off‐
grid solutions such as wind and solar home systems (WHSs and SHSs) and isolated mini‐
hydel/wind/solar grids, amongst many others. 
Conceptually,  this  fact  has  already  been  considered  in  devising  the  short‐term 
renewable energy (RE) policy by the Government of Pakistan (GoP).  However, Annexure 
B of Pakistan’s short‐term 2006 RE Policy18 provides only a brief set of guidelines for the 
development of small off‐grid hydel projects, with some provisions applying to other RE‐
sourced electricity (RES‐E) technologies as well. At present, there is no national policy for 
off‐grid  electricity  investments—the  lack  of  which  creates  confusion  amongst 
stakeholders  which,  in  turn,  greatly  affects  the  development  of  rural  electrification.19 
Additionally,  the  guidelines  stated  in  the  2006  RE  Policy  assign  identical  roles  to  the 
AEDB,  provincial,  and  AJK  governments  for  RES‐E  project  implementation.  This 
overlapping  can  be  counterproductive,  as  it  can  create  duplication  of  tasks  amongst 
national and provincial institutions, possible conflicts of interest, and coordination issues 
between the different agencies involved.  
Several  off‐grid  RES‐E  projects  have  recently  been  initiated  in  Pakistan,  either  by  the 
federal  government  or  by  provincial  governments,  with  differing  outcomes.  The  AEDB 
has  been  actively  participating  in  such  efforts,  particularly  in  the  promotion  of  stand‐
alone SHSs (in Sindh and Balochistan) as well as micro‐ and mini‐hydel projects (in AJK, 
Punjab  and  NWFP).  Probably,  the  most  ambitious  project  has  been  the  Khushaal 
Pakistan  program  launched  in  2001,  which  envisaged  100%  electricity  coverage  by  the 
end of 2007, a target which was definitely not accomplished. Currently, the most active 
project, in terms of rural electrification, is the Roshan Pakistan program. The objective is 
to  provide  electrification  services  to  7,874  isolated  villages,  aimed  at  improving  the 
standards  of  living  in  these  communities  by  providing  access  to  lightning,  information 
and  communications  technology,  drinking  water,  and,  as  a  consequence  of  displacing 
fossil  fuels  for  lighting,  better  health  conditions.  Currently,  400  villages  have  been 
electrified or are under the process of electrification through this program. 

                                                       
18
  Alternative Energy Development Board (AEDB), Policy for Development of Renewable Energy for Power Generation, 
2006, Government of Pakistan, Islamabad: December 2006. 
19
  Presently, as in the past, rural electrification in Pakistan is being pursued almost exclusively through state‐financed 
grid extension and limited mini‐grid hydel and thermal (diesel) generation. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  69
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

An important gap in the current GoP electrification strategy is the absence of a formal, 
clear  demarcation  of  off‐grid  areas  and/or  isolated/scattered  populations.  Such  a 
definition should determine the geographical areas and future power markets for which 
extension of the national grid would remain uneconomical into the foreseeable future. 
This is an essential first step in designing any rural electrification project, as it provides a 
means  for  fully  understanding  the  key  characteristics  of  the  unelectrified 
villages/settlements  and  for  properly  assessing  the  deployment  of  appropriate 
generation technologies. Even though precise data are unavailable, it is estimated that in 
2006,  approximately  40,000  villages  in  Pakistan  lacked  electricity  services  and  about 
8,000 out of them could only be electrified based on off‐grid solutions. In some areas, 
such as in Balochistan, the situation is critical, with as much as 90% of the villages not 
having access to grid power and being widely dispersed, with an average province‐wide 
population density as low as 22 inhabitants/km2. Despite the lack of proper data, it can 
be  estimated  that  for  electrifying  8,000  villages  and  scattered  populations,  at  least 
USD 725 million would be required; in case some of the villages to be electrified by grid 
extension (around 32,000)  also require off‐grid solutions, the financial cost can become 
even higher. 
The two most critical issues with respect to the current practice of off‐grid electrification 
are  scale  and  sustainability.  Until  now,  efforts,  both  federal  and  provincial,  though 
successful, have been on a very limited scale. The sheer number of isolated villages and 
scattered  settlements  in  Pakistan  requiring  off‐grid  electricity  provision,  however, 
mandates an  organizational approach and systematic effort on a scale that has not been 
attempted  before  in  the  country.  Secondly,  the  sustainability  of  the  (off‐grid) 
electrification solutions  utilized is also essential, both for ensuring proper operation of 
the installations as well as in terms of continued financing of their capital and recurring 
costs. 
The  proposed  medium‐term  off‐grid  RES‐E  policy  intends  to  overcome  these  issues 
through  appropriate  design  provisions,  as  detailed  in  a  background  study  prepared 
under ADB TA 4881‐PAK (Annex IX). 

2 Medium Term Off­grid RES­E Policy Recommendations 
2.1 Target Markets 
The  target population  for  off‐grid  RES‐E  deployment  is  that  living  in  ‘off‐grid’20  villages 
and  remote,  scattered  households.  These  villages/scattered  dwellings  can  be  supplied 
electricity,  and  eventually  drinking  water,  based  on  renewable  sources  of  energy 
generation,  either  by  standalone  or  mini‐grid  systems.  The  AEDB,  along  with  the 
distribution  utilities,  shall  be  responsible  for  elaborating  (and  properly  updating)  a 
database of all villages/settlements falling under the purview of this ‘target’ definition, 
and  this  list  should  include  at  the  very  least:  the  name  of  the  village/settlement  and 

                                                       
20
  For  purposes  of  this  policy,  ‘off‐grid’  settlements  are  defined  as  those  that  are  currently  unelectrified,  are  not 
included in any national or regional grid expansion plan for the next ten years, and are located more than 20 km 
from existing power grid(s).  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  70
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

province,21  its  geospatial  coordinates,  number  of  inhabitants,  and  number  of 
households.  
RES‐E technologies included in this portfolio consist of, at a minimum: 

• Micro‐ or mini‐hydel 
• Hybrid  systems,  in  which  at  least  one  renewable  energy  source  is  employed 
besides conventional thermal generation 
• Solar PV and thermal 
• Micro‐ or mini‐wind systems  
• Bio‐energy  resulting  from  anaerobic  gas  digestors,  pyrolitic  biomass 
gasification, cogeneration, etc. 
Any type of national and/or regional grid expansion is outside the scope of this policy, as 
is any RES‐E project that plans to electrify a village with an installed generation capacity 
larger than 1 MW. 

2.2 Implementation Period 
The implementation period of this policy shall be 2009 to 2014.22 

2.3 Rationale and Institutional Organization 
Off‐grid electrification can be developed either: 

• Directly  by  provincial  and/or  local  governments  on  a  voluntary  basis  and/or 
driven by social players without recourse to national subsidies, or 
• Via national‐provincial coordination in which provincial governments compete 
for federal government assistance to finance their off‐grid projects.  
Under the first mechanism, provincial governments are fully in charge of developing the 
electrification projects within their respective territorial jurisdictions. Each province may 
adopt  its  own  simplified  regime  for  off‐grid  project  deployment,  following  which 
bilateral  agreements  between  the  parties  involved  are  reached  to  enforce  project 
implementation.  These  agreements  are  arranged  solely  by  the  relevant  parties  which 
decide on tariffs, quality of service, and other contractual terms. 
Under  the  second  alternative,  a  coordinated  plan  has  to  be  set  up  to  assign 
competences  to  the  different  parties  involved  in  order  to  maximize  their  operational 
potential and capabilities for achieving effective and efficient off‐grid electrification. The 
main  characteristics  and  tasks  for  stakeholders  in  this  respect  are  summarized  in 
Exhibit 1. 

                                                       
21
  For  brevity,  the  term  ‘province’  or  ‘province/unit’  is  used  in  this  document  to  refer  to  all  mutually  exclusive 
administrative  units  below  the  national  level,  i.e.,  Punjab,  Sindh,  North  West  Frontier  Province  (NWFP), 
Balochistan, Northern Areas (NA), Federally Administered Tribal Areas (FATA), Islamabad Capital Territory (ICT), as 
well as Azad Jammu & Kashmir (AJK). 
22
  Exact calendar date to be determined. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  71
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The  remainder  of  this  paper  deals  specifically  with  the  second  option  (i.e.,  federally‐
assisted off‐grid RES‐E deployment), as the first option (i.e., provincial and alternative or 
self‐financed  off‐grid  electrification)  lies  under  the  purview  of  provincial/local 
administrations. 

Exhibit 1: Proposed Federally Assisted Off‐grid RES‐E Deployment Approach 

State-owned Soft loans


banks

Ministry of
Water and OGREA budget
request
Power OGREA

Assessment
National off-grid
AEDB Off-grid
project Portfolio
Guidelines for
OGREA settlement
Villages and scattered Authorizations
Management
population

Provincial
Governments
(REAs) in Authorization
Awarded Tendering Performance
coordination Project Proposals issuance and
Projects Procedure monitoring
set tariffs
with local
governments

Priv. Investors
Developers NGOs
and Cooperatives Project Execution
operators Individuals
Others

IFIs and Financial and technical


donors assistance

 
The main features of the regulation proposed are as follows: 

• The  AEDB  will  act  as  the  national  off‐grid  RES‐E  program  coordinator  and  will 
decide  on  the  allocation  of  national  funds  to  different  off‐grid  electrification 
projects, based on rules previously defined by the Government of Pakistan and 
agreed upon by all provinces/units;  
• The  AEDB  will  consolidate  and  update—with  the  assistance  of  the  power 
utilities,  provincial  governments,  and  unit  administrations—a  complete 
assessment  of  unelectrified  villages  and  scattered  communities  able  to  be 
supplied by RES‐E technologies on an annual basis; 
• Provincial/unit  governments—through  their  respective  Rural  Electrification 
Agencies (REAs), and in close coordination with local governments—will be the 
key  stakeholders  in  promoting  off‐grid  rural  electrification  within  their 
geographical territories. Based on the list of annual target villages/populations 
developed by them in collaboration with the AEDB and approved by the latter, 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  72
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

each REA will prepare and submit to the AEDB a village‐specific electrification 
project in which, at least, the following aspects shall be covered: 
o Socioeconomic characteristics of target village/scattered population. 
o Study on power demand potential and projected supply. 
o Generation technology/ies to be deployed. 
o Number of households to be connected. 
o Implementation period. 
o Total  cost  of  the  project,  segregated  between  capital  and  operational 
expenditures. 
o Detailed cash flow projections for the project. 
o Social benefits due to project implementation. 
o Quality‐of‐service characteristics. 
• The proposed off‐grid projects should not strictly focus on providing electricity 
services  only.  It  is  highly  desirable  that  projects  should  include,  to  the  extent 
feasible, domestic equipment, water installations, and or any other facility that 
could  help  to  improve  the  social  and  human  development  of  the  target 
village/scattered population. 
• Each project must strictly comply with the guidelines proposed by the AEDB for 
proper comparison, benchmarking, and analysis. It will be the duty of the AEDB 
to  document  simplified  procedures  for  project  approval,  including  criteria  for 
ranking  the  projects  and  the  definition  of  the  parameters  needed  to  obtain 
comparable  project  proposals  (e.g.,  the  costs  of  different  generation 
technologies).  
• The  AEDB  will  collect  all  project  proposals  and  will  create  an  annual  project 
portfolio.  This  portfolio  shall  be  organized  according  to  a  merit  order  based 
solely on a standardized social cost‐benefit analysis of the projects.  
• Once  a  project  has  been  awarded  by  the  AEDB,  the  relevant  provincial 
government,  in  cooperation  with  local  governments  will  call  for  tenders  for 
granting, at least, a 10‐year Authorization to develop off‐grid electricity services 
following  technology  specifications  stated  in  the  electrification  project.  If 
convenient (i.e., for proximate villages), several projects may be combined for 
tendering under a single authorization. 
• The  primary  criterion  for  selecting  the  winning  bid  for  each  Authorization  will 
be  ‘least  subsidy’  demanded  for  capital  investments  for 
electrification/installation. 
• All  types  of  stakeholders  (cooperatives,  NGOs,  private  individuals,  and  private 
companies) shall be eligible to participate in the tender process, provided they 
meet a minimum set of technical qualifications to be defined by provincial REAs 
with the guidance of the AEDB. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  73
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• The  AEDB  will  define  the  standard  Authorization  template  that  the  REAs  will 
apply  to  specific  project  tenders.  In  the  Authorization,  at  a  minimum,  the 
following contents shall be included: 
o Schedule for electrification. 
o Rights and obligations of the parties. 
o Applicable tariffs or fees. 
o Milestones for subsidy delivery. 
o Quality‐of‐service  regulation,  including  standards  adjusted  for  each 
technology and fines for non‐compliance. 
o Community  capacity‐building  (provision  of  technical  training  and  other 
incentives to promote the regional development of the area). 
o Conditions for termination of the Authorization. 

2.4 Targets and Incentives 
At  least  25%  of  all  the  currently  off‐grid  unelectrified  villages  identified  by  the  AEDB 
should be supplied with electricity by December 31, 2014. In order to achieve this target, 
the  federal  government  will  provide  subsidies  for  capital  investments  to  the  extent  of 
70% of the total investment required for each RES‐E project approved by the AEDB. 
The  AEDB  will  approve  projects  according  to  a  merit  order  based  on  their  respective 
social  cost‐benefit  analysis.  The  standardized  social  cost‐benefit  analysis  should 
consider: 

• The subsidy requirement (total and as a share of total cost). 
• The population involved. 
• The economic development benefits evaluated on the basis of contribution to 
economic output and growth, including direct and indirect economic costs and 
benefits. Included, in this respect, should be the expected improvement in, for 
instance,  water  sanitation,  education,  health,  gender  issues,  employment, 
incomes,  and  other  sustainable  and  human  development  indicators  of  the 
community—instead of just kWh supplied. 
• The HSE (health, safety, and environment) performance aspects of the projects. 
The remaining capital and O&M costs, including replacement costs, would be financed 
by: 

• The respective REAs, employing provincial funds. 
• The tariffs or fees for the off‐grid services defined by the provincial REA, taking 
into account the customers’ ability to pay. 
• Community contributions to such schemes may be in the form of sweat equity 
(labor), land, and/or cash. 
• NGO and private contributions. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  74
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

As subsidies are provided, they should be limited to the amounts needed for basic social 
and  human  needs,  including  basic  economic  activities.  Some  consumers  may  want  to 
pay more for higher levels of electricity service, such as more kWhs received and better 
quality  of  service.  In  that  case,  the  extra  quality  and  quantity  must  be  paid  for  by  the 
customer as per provisions in the bilateral agreement with the service provider. 

2.5 Project Funding  
In order to provide funding to off‐grid projects, an Off‐grid Rural Electrification Account 
(OGREA) in the budget for the AEDB should be created. This account could be financed 
by: 

• Government  budgetary  allocations.  The  request  for  funds  to  the  Ministry  of 
Finance will be made by the Ministry of Water and Power as estimated by the 
AEDB/REAs  according  to  the  needs  imposed  by  the  off‐grid  electrification 
project targets. 
• Grants  and  loans  that  multilateral/bilateral  financing  and  donor  agencies  may 
provide. 
• A levy on retail grid‐supplied electricity tariffs. 
The OGREA settlement is an attribute restricted solely to the AEDB. Delivery of subsidies 
should  be  output‐based  and  only  related  to  capital  expenditures.  The  REAs  directly  or 
the through the local government will monitor the fulfillment of the milestones defined 
in the Authorization in terms of investment, and ask the AEDB for subsidy delivery in the 
form  of  funds  transferred  directly  to  the  holder  of  the  Authorization.  The  AEDB  may 
develop spot monitoring of the projects in order to cross‐check the use of these national 
subsidies.  
Additionally,  the  government—through  state‐owned  banks—will  provide  financing 
facilities  at  preferential  rates,  collateralized  by  the  future  stream  of  subsidy  deliveries 
defined in the Authorization. 

2.6 Pricing 
The  level  and  structure  of  the  service  tariff  will  be  the  sole  responsibility  of  the 
provincial  governments,  to  be  developed  in  cooperation  with  local  governments.  The 
REAs  will  define  the  tariff  structure  for  each  Authorization  according  to  the  following 
criteria: 

• Tariffs may be technology‐wise differentiated. 
• In standalone systems, a one‐part tariff (Rs/customer) should be preferred. 
• In  community  (mini‐  and  micro‐grids)  system,  a  one‐part  tariff  based  on  the 
contracted capacity (Rs/kW‐contracted) should be preferred. In these systems, 
each  customer  will  have  a  power  limiter  installed  in  order  to  disconnect 
him/her if the contracted capacity is exceeded. 
• In  those  cases  in  which  the  customer  is  willing  to  pay  for  a  higher  quality  or 
more energy than required for basic needs, a metering device may be installed. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  75
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Tariffs may be only indexed to local inflation. 

2.7 Incentives Other Than Tariffs 
The AEDB believes that the current general financial and fiscal incentives, as defined in 
the 2006 on‐grid RES‐E Policy, are adequate and should be continued into the medium 
term as well and extended to off‐grid RES‐E investors.  Additional facilities and incentives 
may be provided to encourage the local manufacture of RES‐E technologies, with a view 
to  bringing  their  costs  down  and  improving  availability  of  spares  and  local  service  and 
maintenance  capabilities.  It  is  not  considered  necessary  to  issue  sovereign  risk 
guarantees for these types of projects, however. 

2.8 Roles of Institutions 
The  AEDB  recommends  a  greater  involvement  of  provincial  and  local  institutions,  as 
international  experience  shows  positive  results  in  off‐grid  rural  electrification 
deployment  when  regional  and  local  governments  actively  participate  in  the  decision‐
making  and  implementation  process.  According  to  this  view,  provincial  and  local 
governments should be directly involved in the activity of providing electricity services to 
inhabitants  living  in  scattered/isolated  regions.  Local  stakeholders  should  also  have  an 
active role in the process as a means to enhancing community acceptance and ensuring 
successful deployment and operation. 
The AEDB shall play a key role in off‐grid electrification development as it is not only the 
main coordinator of the process at the national level, but will also be in charge of setting 
guidelines for project formulation, implementation, and financing.  
The  Ministry  of  Water  and  power  will  define  the  budget  request  for  the  OGREA.  In 
addition,  the  Ministry  will  provide  all  the  necessary  means  to  assure  that  the  fund  is 
created and properly managed.  

2.9 Institutional, Legal and Regulatory Consents 
Regulatory consents and processing requirements for off‐grid RES‐E services should be 
simplified  to  the  extent  possible,  so  as  to  enable  and  expedite  the  development  of 
projects  and  enable  small  communities  and  investors  to  participate  fully  in  these 
schemes.  Due  to  the  characteristics  of  the  proposed  arrangements,  no  regulatory  or 
operational consents by NEPRA and NTDC /DISCOs are envisaged for such projects. 
The  AEDB  suggests  eliminating  the  Letter  of  Intent  (LoI),  Letter  of  Support  (LoS),  and 
related  guarantees  that  are  required  for  on‐grid  RES‐E  projects.  The  only  consent  that 
should  be  necessary  is  the  Project  Information  Memorandum  (PIM)  for  each  project, 
which  would  include  all  technical  and  economic  features  of  the  project.  This  is  the 
information that the AEDB will utilize to develop the national portfolio of off‐grid RES‐E 
projects. In case the project does not require national funding support, this consent will 
also not be required. 
Concerning  environmental  issues,  The  AEDB  proposes  that  the  federal  and  provincial 
Environmental  Protection  Agencies  (EPAs)  remove  the  requirement  of  an  Initial 
Environmental  Examination  (IEE)  for  off‐grid  RES‐E  projects  of  up  to  1  MW  capacity.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  76
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

However, a basic environmental compliance and impact checklist should be developed 
by  the  EPAs  and  required  to  be  completed  by  the  provincial  REAs  for  all  projects, 
primarily  to  ensure  that  water  rights,  flows,  and  community  interests  are  not  unduly 
infringed upon. Additionally, as a condition of the Authorization, the project developer 
should  certify  how  proper  design,  engineering, construction,  and  safety  criteria  will  be 
addressed in the execution of the project. 
The most important consent that would be required is the Authorization issued by the 
REAs on behalf of provincial governments.  

2.10 Performance Monitoring and Enforcement 
Project performance must be monitored, but in a light‐handed manner in order to avoid 
huge regulation costs. The monitoring process has two main parts: 

• Investment  plan  monitoring:  This  involves  verification  of  the  investment 


milestones  defined  in  the  Authorization  being  reached,  as  a  trigger  for  the 
AEDB to release subsidy payments. 
• Ongoing  performance  monitoring  for  the  duration  of  the  Authorization:  This 
involves monitoring that service quality standards defined in the Authorization 
are met throughout its period of validity. The regulator will establish standards 
for  product  quality,  service  quality,  and  commercial  quality.  Product  quality 
includes  stability  of  voltage  and  stability  of  frequency  relative  to  benchmark 
reference levels. Service quality includes targeted hours of service, number and 
duration of interruptions, and safety of the system. Commercial quality includes 
connection, accuracy in meter readings (for customers whose service requires 
meter  reading),  accuracy  in  billing,  and  response  time  to  resolve  customer 
complaints.  It  should  be  noted  that  fewer  standards  that  can  be  effectively 
monitored are preferable to many standards that are poorly monitored. 
Performance monitoring and enforcement will be the responsibility of the provincial and 
or local governments.  The REAs should develop a program of awareness amongst their 
customers  and  other  community  stakeholders  to  foster  the  direct  monitoring  of  the 
service provider. The monitoring should be based on customers’ (or other stakeholders’) 
claims.  

2.11 Allocation of Carbon Credits  
The  AEDB  considers  logical,  as  well  as  administratively  simpler,  for  RES‐E  investors  to 
assume  the  risks  and  benefits  of  qualifying  for  and  obtaining  Certified  Emissions 
Reductions (CERs), along with the potential revenues associated with them.  However, 
the  AEDB  would  assist  project  developers  applying  for  CDM  registration  through 
programmatic  or  clustered,  single‐umbrella  application  cover.    In  such  cases,  CDM 
registration,  validation,  and  verification  costs  and  CER  revenue  sharing  arrangements 
shall be developed subsequently, as necessary. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  77
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex IV:  Working Paper 1: 
Relevant International Experience in 
Incentives for Renewable Energy: 
The Case of the EU­25 and Selected Countries 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  79
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Working Paper No. 1 

Relevant International Experience in 
Incentives for Renewable Energy: 
The Case of the EU­25 and 
Selected Countries 

Contents 

Exhibits ....................................................................................................................... 83 
Abbreviations and Acronyms ...................................................................................... 85 
1  Objective .......................................................................................................................... 89 
2  Current Policy Schemes for Promoting RE at a Glance ....................................................... 89 
2.1  Price‐based Instruments...................................................................................... 89 
2.2  Quantity‐based Instruments ............................................................................... 90 
3  Current EU‐25 Experience on RE Development .................................................................. 94 
3.1  RES Policy in the EU‐25 ........................................................................................ 94 
3.2  RE Penetration in Electricity Generation ............................................................. 96 
3.3  The EU‐25 Experience in RE Promotion .............................................................. 99 
3.4  RE Development: Country Achievements vis‐à‐vis Promotional Schemes ....... 102 
3.4.1  On‐shore Wind ...................................................................................... 102 
3.4.2  Solid Biomass ......................................................................................... 104 
3.4.3  Biogas..................................................................................................... 105 
3.4.4  Other RE technologies ........................................................................... 106 
4  RE Policies in Selected non‐European Countries .............................................................. 110 
4.1  India ................................................................................................................... 110 
4.1.1  RE Penetration in Electricity Generation ............................................... 111 
4.1.2  Incentives and Policies .......................................................................... 111 
Incentives Other than Tariffs .................................................................. 112 
Current Experience of RE Tariffs in Relevant States .............................. 118 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  81
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.1.3  The Case of Wind Energy ....................................................................... 122 
Incentive Mechanisms ............................................................................ 123 
4.2  China .................................................................................................................. 128 
4.2.1  Background ............................................................................................ 128 
4.2.2  Potential and Incentives ........................................................................ 130 
Bioenergy ................................................................................................ 131 
Hydel ....................................................................................................... 132 
Wind ....................................................................................................... 132 
Solar ........................................................................................................ 133 
4.3  Brazil .................................................................................................................. 134 
4.3.1  Background ............................................................................................ 134 
4.3.2  Potential and Costs ................................................................................ 136 
Biomass ................................................................................................... 136 
Small‐Scale Hydel ................................................................................... 138 
Wind ....................................................................................................... 139 
Solar ........................................................................................................ 140 
4.3.3  Incentive Mechanism: The PROINFA Program ...................................... 141 
5  What Have We Learned from International Experience? ................................................. 143 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  82
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 

Exhibit 1:  Price vs. Quantity Incentives ............................................................................ 91 
Exhibit 2:  RE Incentives at a Glance ................................................................................. 94 
Exhibit 3:  Renewables Penetration Target in Europe......................................................... 95 
Exhibit 4:  RE Penetration in Electricity Generation............................................................ 96 
Exhibit 5:  Total Annual Electricity Generation in the EU‐25 ............................................... 97 
Exhibit 6:  Total Annual RE Electricity Generation in the EU‐25 ........................................... 97 
Exhibit 7:  Wind Electricity Generation in the EU‐25 .......................................................... 98 
Exhibit 8:  Solid Biomass Electricity Generation in the EU‐25 .............................................. 99 
Exhibit 9:  Biogas Electricity Generation in the EU‐25 ........................................................ 99 
Exhibit 10:   Main Instruments for RE Promotion in EU‐25 Countries .................................. 100 
Exhibit 11:  Feed‐in Tariff levels in the EU‐25 .................................................................... 101 
Exhibit 12:   Feed‐in Tariff Levels by Technology in the EU‐25 ............................................ 102 
Exhibit 13:  On‐shore Wind Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 103 
Exhibit 14:  Biomass Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 105 
Exhibit 15:  Biogas Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 106 
Exhibit 16:  Small‐scale Hydel Mid‐term Potential and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 107 
Exhibit 17:  Biowaste Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 107 
Exhibit 18:  Photovoltaic Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 108 
Exhibit 19:  Solar Thermal Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 108 
Exhibit 20:   Tidal and Wave Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 109 
Exhibit 21:  Geothermal Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 .................................................................................................. 109 
Exhibit 22:  RE Installed Capacity and Potential in India (2007) ........................................... 111 
Exhibit 23:  Nationwide Biomass Assessment (Season: Kharif) ........................................... 114 
Exhibit 24:  Gujarat Tariff Order, January 2007 .................................................................. 119 
Exhibit 25:  Rajasthan Tariff Order, March 2007 ................................................................ 119 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  83
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 26:  Andhra Pradesh Tariff Order, March 2004 ....................................................... 120 
Exhibit 27:  State Government Incentives for Wind Power Development in India ................ 124 
Exhibit 28:  Main Assumptions in Up‐front Tariff for Wind Energy in India .......................... 127 
Exhibit 29:  Generation Capacity in China by Technology ................................................... 129 
Exhibit 30:  RE Generation in China .................................................................................. 129 
Exhibit 31:  Generation Cost by Type of Technology in China ............................................. 130 
Exhibit 32:  RE Installed Capacity and Potential in Brazil .................................................... 134 
Exhibit 33:  Brazil’s Generation Potential Using Native (left) and Planted (right) Forests ...... 137 
Exhibit 34:  Brazil’s Generation Potential Using Rice Bran .................................................. 137 
Exhibit 35:  Medium‐term Potential of Small‐scale Hydel in Brazil ...................................... 138 
Exhibit 36:  Brazil’s Wind Energy Potential ........................................................................ 139 
Exhibit 37:  Wind Seasonality in Northeast Region for PROINFA Projects vs. 
Sao Francisco River Volume ........................................................................... 140 
Exhibit 38:  Average Annual Solar Irradiation in Brazil ........................................................ 141 
Exhibit 39:  Results of Tender Procedures in Brazil ............................................................ 142 
 
Box 1:  Main Rural and Household RES Technologies in India ............................... 112 
Box 2:  Brazilian Experience with Ethanol .............................................................. 136 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  84
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
BRIC  Brazil, Russia, India, and China 
CBO  Community‐based organization 
CCGT  Combined cycle gas turbine 
2
cm   Square centimeter 
CO2  Carbon dioxide 
ED  Excise duty 
EHV  Extra high voltage 
EPE  Energy Policy for Europe 
EU  European Union 
FEC  Final energy consumption 
FFV  Flex‐fuel vehicle 
GEF  Global Environment Facility 
GoP  Government of Pakistan 
GW  Gigawatt 
GWh  Gigawatt‐hour 
ha  Hectares 
HV  High voltage 
IPP  Independent power producer 
IREDA  Indian Renewable Energy Development Agency 
ISCC  Integrated Solar Combined Cycle 
kcal  Thousand calories 
kg  Kilogram 
kha  Thousand hectares 
km  Kilometer 
kT  Thousand tonnes 
kV  Kilovolt 
kVArh  Kilovolt Ampere reactive‐hour 
kW  Kilowatt 
kWe  Kilowatt electrical 
kWh  Kilowatt‐hour 
kWp  Kilowatt peak 
LNG  Liquefied natural gas 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  85
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

LPG  Liquefied petroleum gas 
m  Meter 
MC  Marginal cost 
MNES  Ministry of Non‐Conventional Energy Sources 
MSW  Municipal solid waste 
MT  Metric tonne 
MTOE  Million tonnes of oil equivalent 
MW  Megawatt 
MWe  Megawatt electrical 
MWh  Megawatt‐hour 
NEPRA  National Electric Power Regulatory Authority 
NGO  Non‐governmental organization 
NOx  Nitrous oxides 
O&M  Operations and maintenance 
PED  Primary energy demand 
PLF  Plant load factor 
PROINFA  Programa de Incentivo às Fontes Alternativas de Energia Elétrica 
PTC  Production tax credit 
PV  Photovoltaic 
R&D  Research and development 
R&M  Renovation and modernization 
RE  Renewable energy 
RES  Renewable energy source 
RES‐E  Renewable energy sourced‐electricity 
RET  Renewable energy technology 
RPS  Renewable portfolio standard 
SC  Self consumption 
SEB  State Electricity Board 
SERC  State Electricity Regulatory Commission 
SOx  Oxides of sulfur 
SS  Small‐scale 
SWERA  Solar and Wind Energy Resource Assessment 
T&D  Transmission and distribution 
TA  Technical assistance 
TWh  Terawatt‐hour 
UNDP  United Nations Development Programme 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  86
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

UNEP  United Nations Environment Programme 
VC  Variable cost 
WTE  Waste‐to‐energy 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  87
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Relevant International Experience in 
Incentives for Renewable Energy: 
The Case of the EU­25 and 
Selected Countries 

1 Objective 
This Annex presents the consultants’ evaluation of the development (and potential) of 
renewable energy resources in Europe and other selected countries, focusing on current 
policy schemes for promoting renewable energy sources (RES)1 specifically for electricity 
generation. 

The scope of the present study is to analyze how different incentive mechanisms have 
impacted  on  the  deployment  of  different  RE  technologies,  with  special  emphasis  on 
widely developed options such as wind, hydro, biogas and biomass, which can operate in 
on‐grid conditions.  

These analyses will be used as a useful reference to evaluate existing incentives offered 
by  the  Government  of  Pakistan  (GoP)  for  RE  promotion  in  Pakistan,2  and  to  design  a 
sound approach for the development of a medium term RE policy for the country under 
ADB TA 4881‐PAK. 

2 Current Policy Schemes for Promoting RE at a Glance 
Worldwide, policy instruments most frequently used to promote RE deployment include: 

2.1 Price­based Instruments 
• Feed‐in tariffs. Electricity produced using renewable energy sources is sold to the 
network  operator  (or  another  identified  buyer)  at  an  administratively‐set  price 
(typically  higher  than  the  wholesale  electricity  price).  The  strongest  points  of  a 
feed‐in tariff are:  
o Its perceived simplicity for potential investors, 
                                                       
1
  Following the definition adopted by the Government of Pakistan, in this document the term ‘renewable energy’ (or 
RE)  excludes  large  hydro  but  includes  small  hydro  (i.e.,  below  50  MW  capacity),  traditional  biomass  (fuel  wood, 
agricultural and forestry wastes, animal dung, and other unprocessed biomass fuels), and ‘new’ renewables (solar, 
wind,  biomass  gasification,  tide,  geothermal,  and  others).    Additionally,  municipal  solid  waste  (MSW)  is  also 
included, where relevant. 
2
  I.e.,  those  contained  in  the  GoP’s  Policy  for  Development  of  Renewable  Energy  for  Power  Generation,  2006,  and 
NEPRA decisions regarding approved RE IPP tariffs. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  89
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

o Its effectiveness in stimulating RE, and 
o Its  positive  impact  on  technology  diversity,  permitting  strategic  support  for 
technologies that are still far away from market maturity.  
The  weakest  point  of  this  approach  is  the  implicit  lower  level  of  competition 
amongst  power  producers  if  compared,  for  example,  with  green  certificates  or 
tendering  systems  (see  Section  2.2  below).  Although  accompanied  by  a  risk  of 
over‐compensation,  as  will  be  shown  later  in  this  paper,  the  feed‐in  tariff 
mechanism  has  proven  to  be  one  of  the  most  effective  means  of  promoting  a 
rapid deployment of RE technologies for power generation. 
• Price premiums. Electricity produced using renewable energy is entitled to receive 
an additional price component, which is typically set administratively, in addition 
to the electricity price that it can obtain in the market. The premium system has 
historically  been  considered  as  a  kind  of  feed‐in  tariff.  It  has  some  of  the 
advantages of the latter—its perceived simplicity and effectiveness in stimulating 
RE as well as its positive impact on technology diversity—and is better integrated 
in  the  internal  electricity  market  than  a  pure  feed‐in  tariff  system.  However, 
investment  risks  with  the  premium  system  are  higher  than  with  the  feed‐in 
system, as final prices fluctuate with electricity prices in the market. In any case, 
investment  risks  with  the  premium  system  are  still  lower  than  with  green 
certificates.
• Investment  subsidies.  A  financial  subsidy  is  granted  to  investors  developing 
electricity  generation  capacity  intended  to  use  renewable  energy  sources.  These 
mechanisms  include  capital  grants,  third‐party  financing,  consumers  grants  and 
rebates, among many others alternatives. 
• Fiscal incentives. Fiscal rebates are granted on investment in electricity generation 
capacity  intended  to  use  renewable  sources,  or  on  the  energy  produced.  These 
mechanisms include tax credits, excise and property tax exceptions, and/or many 
other similar alternatives. 
• Fossil fuel taxes. Carbon taxes or taxes on other pollutants, such as SOx and NOx, 
are  imposed  on  the  use  of  fossil  fuels.  This  can  indirectly  benefit  renewables  in 
terms of bringing their prices down in comparison to fossil fuels. 

2.2 Quantity­based Instruments 
• Green  certificates.  An  obligation  to  produce  or  consume  a  specified  minimum 
proportion  of  electricity  generated  using  renewable  sources  is  imposed  on 
generators  or  consumers  (more  often  on  load‐serving  entities  on  behalf  of 
consumers).  The  obligation  may  be  fulfilled  directly  or  by  acquiring  green 
certificates from other agents which produced electricity using renewable energy 
sources. The strongest points of this model are its compatibility with the internal 
market and in promoting competition between different RE producers. However, 
the  setting  of  yearly  quotas  and  the  fixing  of  penalties  is  not  a  simple  task  and 
influences  considerably  the  outcome  of  the  system.  The  existence  of  dominant 
market players can complicate the development of a green certificates market, but 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  90
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

a well‐designed system can overcome this situation. The main drawback of green 
certificates is that the complexity and risks associated with these support schemes 
transfer a higher cost to the consumer, while they also usually have considerable 
administrative overheads. 
• Tendering  procedures.  The  state  or  the  regulatory  authority  places  a  series  of 
tenders  for  the  supply  of  renewable  electricity,  which  is  then  supplied  on  a 
contract  basis  at  the  price  resulting  from  the  tender.  The  additional  costs 
generated by the purchase of renewable electricity are passed to end‐consumers 
of  electricity  through  a  specific  levy.  One  of  this  system’s  drawbacks  is  that  if 
competition is too strong, the prices offered are sometimes very low and there is a 
risk of projects not being implemented. On the other hand, it has the advantage of 
fast deployment in order to kick‐start the market in a specific technology sector. 
However, it is not well suited for a large and rapidly growing market due to its high 
administrative  costs,  the  risk  of  unrealistic  bids,  and  the  potential  for  creating 
administrative barriers. 

All  of  the  instruments  described  above  are  inherently  mandatory.  However,  there  is 
another class of incentives based on voluntary decisions by consumers. The best known 
such  system  is  green  pricing,  where  customers  are  given  the  option  to  support  an 
increased level of utility company investment in renewable energy technologies through 
payment  of  an  additional  amount  on  their  electricity  bills  to  cover  the  renewable 
energy’s incremental cost. This system has shown a very low level of effectiveness even 
in affluent countries. 

The  distinguishing  feature  of  these  two  main  sets  of  instruments  is  the  way  in  which 
they stimulate demand for RE: by setting a price for RE or by requiring a certain RE share 
in total electricity consumption. While price‐based systems in some way or another set a 
price per unit of RE and, thus, leave the amount of electricity supplied to be determined 
by  the  market,  quantity‐based  systems  put  an  obligation  upon  consumers/utilities  to 
consume/generate a certain amount of RE while having the price for this electricity set 
by the market, as illustrated in Exhibit 1 below. 

Exhibit 1: Price vs. Quantity Incentives 

 
Exhibit 1 compares the general functioning of a feed‐in tariff (on the left‐hand side) with 
the  general  functioning  of  a  green  certificates  system  (on  the  right‐hand  side).  In  the 
case of a renewable feed‐in tariff, the regulator sets the price, p*, and the market will 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  91
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

decide the associated quantity of RE, q, that results from the intersection of p* and the 
supply curve of RE. Alternatively, in a green certificates system the regulator would set 
the quantity q* and leave it to the market to sort out the price level at the intersection 
of  supply  curve  of  RE  and  q*.  While  all  the  other  price‐based  instruments  mentioned 
above result in a shift of the marginal cost curve to the right, principally by lowering the 
RE’s generation or installation costs, the second quantity‐based instrument—a tendering 
or  auction  system—works  like  a  green  certificates  scheme  where  the  regulator  sets  a 
quantitative target and leaves price‐setting to the competitive process.  

Historically,  feed‐in  tariffs  have  been  the  main  instrument  used  for  promoting 
renewable  energy.  As  they  are  administratively  set  and  usually  constant  over  a 
predefined  period,  they  provide  a  high  degree  of  certainty  for  developers  on  their 
expected revenue stream. In some cases, feed‐in tariffs have been set at such high levels 
that  investors  were  able  to  recover  the  investment  costs  over  a  period  of  only  a  few 
years.  The  main  drawback  of  feed‐in  tariffs  is  that  the  quantitative  outcome,  i.e.,  the 
amount  of  electricity  generated  using  renewables,  depends  on  the  way  the  economic 
agents  respond  to  the  incentive  provided  by  the  tariff.  If  agents  are  more  responsive 
than  estimated  when  setting  the  tariff  level,  then  the  amount  of  electricity  generated 
from renewables will be higher than the expected or required level. Conversely, if agents 
are  less  responsive  than  expected,  the  RE  target  will  not  be  met  and  the  level  of  the 
feed‐in  tariff  would  have  to  be  increased.  Moreover,  as  the  cost  of  generating 
technologies varies over time, the RE tariffs may also need to be adjusted to provide the 
same level of incentives. Therefore, in implementing a system based on a feed‐in tariff, 
the  administration  faces  a  difficult  trade‐off  between  aiming  to  achieve  the  target, 
which may involve repeated adjustment of the tariff level, and the stability of the system 
on which would depend investors’ confidence. Similar drawbacks affect fiscal incentives 
and investment subsidies, with the additional disadvantage, in the latter case, that the 
subsidy provides incentives for the development of generating capacity, but it does not 
necessarily promote its efficient or full utilization to produce electricity. 

While  specific  remedies  have  been  introduced  to  address  these  problems—e.g.,  by 
limiting the capacity which is entitled to benefit from the feed‐in tariff—in the last five 
years  green  certificates  schemes  have  been  launched  in  a  number  of  jurisdictions, 
mainly  in  Europe.  As  mentioned  before,  green  certificates  schemes  represent  a  mirror 
approach to feed‐in tariffs. Where feed‐in tariffs set the level of the incentive and allow 
market agents to determine the quantitative outcome, a green certificates scheme sets 
the quantitative target, in the form of the obligation for market participants to produce 
or procure a predefined share of electricity from renewable sources, while the costs of 
achieving this objective are defined by the available technologies and market conditions. 
Non‐compliance  penalties  may  be  used  to  ensure  that  these  costs  do  not  become 
excessive and, if market conditions tighten, the quantitative target is implicitly relaxed. 

Although in principle the outcomes that both instruments yield should be the same, they 
differ  in  at  least  three  aspects.  Firstly,  rent  allocation  differs  depending  on  the 
instrument: a feed‐in system may imply windfall profits to power generators that do not 
occur  with  quantity‐based  systems,  where  the  decreases  in  marginal  costs  directly 
benefit  consumers.  Secondly,  with  imperfect  information  about  supply  curves,  one  or 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  92
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

the  other  system  might  be  preferred:  if  the  supply  curve  is  gently  sloped,  setting  the 
feed‐in  tariff  at  the  wrong  level  would  result  in  the  wrong  RE  quantity;  while  with  a 
steep cost curve, setting the quantity target wrong could entail excessive costs. Thirdly, 
since the rent allocation differs amongst instruments, this might also have an impact on 
the firms’ dynamic efficiency and R&D expenditure. 

Another key issue is related to the setting of single or multiple levels of feed‐in tariff or 
quotas. If designed properly, a feed‐in tariff will ensure that the cost‐efficiency (or equi‐
marginality) principle (see Annex VI for details) is met purely on the basis that a single 
price  p*  is paid  for  all  RE;  paying a  uniform  price  for  RE will  lead  to  a  mix  of  different 
renewable energy technologies depending on their respective marginal cost curves. The 
story  changes,  however,  if,  for  whatever  reason,  there  is  not  a  single  uniform  feed‐in 
tariff for all RE, but instead a whole system of different tariffs paid for the various RE, 
e.g., one feed‐in for electricity from wind, a different one for solar, and yet another one 
for  geothermal.  Where  a  policy  is  designed  in  such  a  way,  the  principle  of  equi‐
marginality  is  violated,  as  a  given  quantity  of  renewable  energy  will  no  longer  be 
provided at least cost. Similarly, the positive impacts of a green certificates scheme on 
cost‐efficiency  would  be  undermined  by  establishing  the  so‐called  'technology  bands' 
where  different  quotas  are  set  for  individual  renewable  energy  technologies.  This 
analysis does, of course, ignore the issue of dynamic efficiency as described in Annex VII. 

The third primary support mechanism identified above is the tender or auction system, 
in  which  the  regulatory  body  calls  for  tenders  to  provide  energy  from  renewables. 
Usually,  auctions  are  structured  in  such  a  way  that  a  certain  amount  of  additional  RE 
capacity  is  put  out  to  tender  with  bids  being  selected  on  the  basis  of  their  proposed 
generation  costs.  Successful  bidders  are  then  awarded  a  long‐term  power  purchase 
agreement with feed‐in tariffs set at the marginal production cost of the most expensive 
bidder who was still awarded a contract. As all participants in the tender will have to bid 
at  their  respective  long‐run  marginal  cost,  such  an  auction  will  lead  to  a  cost‐efficient 
expansion  of  RE.  However,  this  result  will  only  occur  across  all  renewable  energy 
technologies if the auction is conducted in a technology‐neutral manner. In the case of 
different  technology  bands,  the  most  likely  outcome  will  once  again  be  a  non  cost‐
efficient solution, as marginal costs will vary amongst different RE suppliers. 

From the theoretical point of view, all these instruments are incentive‐based, i.e., they 
rely on price signals to provide incentives for the development of electricity generation 
using  renewable  energy;  the  practical  applications  of  price‐based  and  quantity‐based 
schemes  are  such  that  green  certificate  schemes  tend  to  be  technology  neutral,  while 
most feed‐in schemes are the opposite. As a summary, Exhibit 2 provides the main pros 
and cons of the different mechanisms discussed above. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  93
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 2: RE Incentives at a Glance 

Policy Instrument Advantages Disadvantages

Feed-in • Highly effective • Less compatibility with


tariffs internal markets
• Highly efficient due to the low
risk for investors • Need regular adjustment
• Permit strategic support for • May overcompensate investors
technology innovation

Price • Highly effective • Risk of over-compensation in


premiums the case of high electricity
• Efficient due to the medium
prices without appropriate
risk for investors
adjustment
• Good compatibility with
internal markets
• Permits strategic support for
technology innovation

Investment • Good complement for some • Inefficient as a main


subsidy technologies instrument

Fiscal • Good secondary instrument • Good results only in countries


measures with high taxation and for the
most competitive technologies

Fossil fuel • Reveal the social price of • When a market is set,


taxes conventional energy, allowing inframarginal windfall profit
energy portfolio optimization difficult to assess

Green • Good compatibility with • Less efficient due to higher


certificates internal markets risks and administrative costs;
better designs can overcome
• Competition between
this issue
generators
• Not very appropriate for
• Supports the lowest-cost
developing medium- to long-
technologies
term technologies

Tendering • Fast development, provided • Stop-and-go nature can cause


procedures political will instabilities
• Very good tool for starting • Development blocked if
policies competition too severe

3 Current EU­25 Experience on RE Development 
3.1 RES Policy in the EU­25 

The  European  Council,  in  its  meeting  on  March  2007,  approved  an  Action  Plan—the 
Energy  Policy  for  Europe  (EPE)3—which  establishes  a  specific  quantitative  target  for 
                                                       
3
  Communication from the European Commission to the Council and the European Parliament, An Energy Policy for 
Europe, January 10, 2007, [COM(2007) 1 final]. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  94
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

renewables penetration to be achieved by 2020. More specifically, this target requires a 
20% penetration of renewables in primary energy demand (PED).4  

Exhibit 3: Renewables Penetration Target in Europe 

Renewables Penetration Target


(% of Primary Energy Demand)

20%

15%

10%

5% 

0% 

2006  2010 2010 2020 2020 


Actual Target Expected Target Target
(PED) (FEC) 
 
More  recently,  a  different  definition  of  the  renewables  penetration  target  has  been 
proposed, in which the 20% target is defined with respect to final energy consumption 
(FEC), rather than in primary energy supply terms. 

The 2020 target for renewables penetration compares with a 2006 penetration level (in 
terms  of  primary  energy  demand)  of  7%,  and  a  12%  target  for  2010  set  by  the  White 
Paper on Renewable Sources of Energy, 1997.5  Current forecasts, however, suggest that 
unless  significantly  more  effort  is  deployed,  this  target  will  not  be  fully  achieved,  and 
renewables will  represent  approximately  10%  of  primary energy  production  in  2010.6,7  
The 2020 target, if expressed in terms of PED, would require a doubling of renewables 
penetration  between  2010  and  2020.  However,  if  the  20%  target  for  renewables 
penetration were expressed in FEC terms, it would be significantly less demanding, as it 
would  be  equivalent  to  a  14%  target  in  primary  energy  demand  terms,  just  a  few 
percentage points above the 2010 target.  

                                                       
4
  An additional target is set for the use of biofuels in the transport sector, requiring a 10% penetration by 2020. 
5
  Communication from the European Commission to the Council and the European Parliament, Energy for the Future: 
Renewable  Sources  of  Energy.  White  Paper  for  a  Community  Strategy  and  Action  Plan,  26  November  1997 
[COM(97) 599 final]. 
6
  An additional 2010 target related to electricity generation was also set, requiring renewables to account for at least 
21%  of  total  electricity  production.    Even  in  this  case,  current  estimates  predict  that  the  target  will  not  be  met 
(renewables penetration in electricity generation is expected to reach 19% in 2010, 2% short of the target).  
7
  The  latest  data  on  current  and  expected  renewables  penetration  are  provided  in  the  Communication  from  the 
European  Commission  to  the  Council  and  the  European  Parliament,  Renewable  Energy  Road  Map—Renewable 
Energies in the 21st Century: Building a More Sustainable Future, January 10, 2007 [COM(2006) 0848 final]. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  95
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.2 RE Penetration in Electricity Generation 

The  penetration  of  renewables  in  Europe  has  been  promoted  through  the  setting  of 
community‐wide and national targets and standards. As part of this approach, the use of 
renewables in electricity generation has also been promoted. A specific target was set by 
the 1997 White Paper,8 which required the share of renewables in electricity generation 
to reach 21% by 2010 (an increase of 8% in this share over 10 years). Current estimates 
predict that by 2010, renewables will account for 19% of total electricity generation, 2% 
short of the target. 

Exhibit 4: RE Penetration in Electricity Generation 

Share of Electricity Generation Using RES-E


90

80

70

60
% of PED

50

40

30
 

20

10

0
Netherlands

EU-25
Slovenia
Lithuania

Malta

Slovakia
Poland

Spain

UK
Italy
Latvia

Lux.
Belgium

Sweden
Portugal
Czech

Estonia
Finland

Greece

Ireland
Cyprus

Denmark

Germany

Hungary
France
Austria 

2006 2010 Target


 
Differentiated targets were set for the different member States to reflect their specific 
circumstances  and  their  respective  endowment  of  renewable  potential.  Exhibit  4 
compares the 2010 target assigned to each member state to the actual penetration of 
renewables  in  electricity  generation  for  that  country  in  2006  (including  hydel  as  a 
renewable energy source). 

As  part  of  this  promotion  process,  RE‐based  power  production  in  Europe  has  been 
consistently developing over time, doubling its own generation (in MWh/year) every five 
years,  which  means  an  approximately  20%  average  annual  growth  rate  over  the  last 
fifteen  years.  Exhibit  5  shows  the  evolution  of  electricity  generation  in  the  EU‐25  in 
terms  of  generation  technology;  for  the  purposes  of  the  present  study,  RE  excludes 
hydro  as  this  technology  is  considered  ‘almost’  conventional  (even  though  it  is 
‘renewable’  with  zero  CO2  emissions),  and  usually  is  not  included  in  promotional 
schemes  as  the  remaining  hydel  potential  in  most  European  countries  is  insignificant, 
except re‐powering which can be an interesting option and is currently under analysis in 
                                                       
8
  See Footnote 5.

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  96
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

several countries. 
Exhibit 5: Total Annual Electricity Generation in the EU‐25 

Total Electricity Generation (TWh)

4,000

3,500

3,000

2,500
TWh 

2,000

1,500

1,000

500

1990 1995 2000 2003 2004 2005  2006 


Year

RES-E  Hydro Conventional Generation 


 
A closer look at RE development through the last sixteen years in Europe shows a clear 
picture on the evolutionary pattern followed by each of the main RE technologies.  

As shown in Exhibit 6, wind becomes the leading RE technology from 2000 onwards with 
a  43%  share  of  total  RE  generation,  followed  by  solid  biomass  which  accounts  for 
approximately 26%, and biogas in third place with a 9% share in 2006.  
Exhibit 6: Total Annual RE Electricity Generation in the EU‐25 
  Electricity Generation from RES-E (TWh)
200

180
Solar Thermal 
160
Tide & Wave
140 Photovoltaics

120 Geothermal 
Industrial Waste
TWh

100
Mun. Waste Ren.
80
Mun. Waste Non-Ren.
60
Biogas 
40 Solid Biomass

20 Wind 

0
1990 1995 2000 2003 2004 2005 2006

Year
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  97
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Even though these figures show an outstanding development of at least three types of 
RE technologies, proper understanding of RE development in the EU‐25 requires a more 
in‐depth analysis. Taking into account the three most developed RE technologies—wind, 
biomass  and  biogas—and  breaking  down  each  technology  into  country  shares,  it  is 
possible  to  evaluate  RET‐wise  penetration,  which  will  later  permit  a  comparison  with 
individual promotional schemes by each country. Exhibit 7, Exhibit 8, and Exhibit 9 show 
the country share for each RE technology in 2006; some findings can be easily surmised: 
• Only three countries—Germany, Spain and the United Kingdom—(out of 25) have 
a  significant  presence  in  each  of  these  three  technologies  with  a  country  share 
larger than 5%. 
• Germany  and  Spain  together  account  for  65%  of  the  total  EU‐25  wind  energy 
generation in 2006. 
• Finland holds one quarter of total EU‐25 biomass‐based generation, and Germany 
generates nearly half of the region’s biogas power. 
• France, despite its vast renewable resources, is most noticeably absent. 

These differences in RE penetration can be attributed to at least two main causes: firstly, 
an  unequal  distribution  of  the  potentials  for  each  RE  technology;  secondly,  countries 
with substantial RE potential may not have properly promoted these technologies. 

Typical  instruments  employed  for  RE  promotion  are  explained  next,  together  with  the 
current  experience  in  the  EU‐25,  in  order  to  allow  a  proper  assessment  of  results 
achieved versus RE potential in each country.  

Exhibit 7: Wind Electricity Generation in the EU‐25 

Electricity Generation Using Wind in 2006


(Country Shares) 

22%
5% 7% Denmark 
Germany 

28%  Spain 
UK
37%
Rest 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  98
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 8: Solid Biomass Electricity Generation in the EU‐25 

Electricity Generation Using Solid Biomass in 2006


  (Country Shares) 

31% 
24% Finland 
Germany
Spain 
7% Sweden
UK
14% 15%
Rest
9%

 
Exhibit 9: Biogas Electricity Generation in the EU‐25 

Electricity Generation using Biogas in 2006


(Country Shares) 

16%
20% Germany 
Italy 

Spain 
10%
46% UK
8% Rest 

 
3.3 The EU­25 Experience in RE Promotion  

The  promotion  of  the  use  of  renewable  energy  is  not  a  recent  phenomenon  but  has 
been a main component of European energy and environmental policy for many years.  
As  already  mentioned,  while  targets  have  been  agreed  at  the  EU  level,  the  choice  of 
policy  instruments  for  pursuing  these  targets  has  been  left  to  each  member  state  to 
decide. This has led to the current situation where different member states implement 
widely  different  approaches  towards  promoting  renewables  in  electricity  generation 
within their territories.  

Despite  the  introduction  of  green  certificates  schemes  in  Belgium,  Denmark,  Italy, 
Sweden, and the United Kingdom, and of purchase obligations in Poland, feed‐in tariffs 
still represent the most common ingredient in the EU‐25 renewables promotion policy, 
as  they  are  in  use  in  17  of  the  25  member  states.  Exhibit  10  summarizes  the  main 
instruments  used  in  the  different  EU  jurisdictions  for  promoting  electricity  from 
renewable energy. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  99
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 10:  Main Instruments for RE Promotion in EU‐25 Countries 

Green
Member Feed-in Price Investment Fiscal
Certificates/Purchase
State* Tariffs Premium Subsidies Incentives
Obligation

AT 3 3

BE 3 3 3

CY 3 3

CZ 3 3 3

DK 3 3

EE 3 3

FI 3

FR 3 3

DE 3 3

GR 3 3

HU 3

IE 3

IT 3

LV 3

LT 3

LU 3 3

MT 3

NL (3)

PL 3

PT 3 3 3

SK

SI 3

ES 3 3

SE 3 3

UK 3 3

(3) Since  August  2006,  new  projects  are  not  admitted  to  the  per‐kWh  subsidy  as  it  became  apparent  that  the  Netherlands  are  on  track  to 
achieve the 2010 renewables penetration target. 
*  AT:  Austria,  BE:  Belgium,  CY:  Cyprus,  CZ:  Czech  Republic,  DK:  Denmark,  EE:  Estonia,  FI:  Finland,  FR:  France,  DE:  Germany,  HU:  Hungary, 
IE: Ireland, IT: Italy, LV: Latvia, LU: Luxembourg, MT: Malta, NL: Netherlands, PL: Poland, PT: Portugal, SK: Slovakia, SI: Slovenia, ES: Estonia, 
SE: Sweden, UK: United Kingdom. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  100
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit  10  clearly  shows  that  most  jurisdictions  use  a  combination  of  instruments  to 
promote the use of renewable energy in electricity generation: the policy’s effectiveness 
has therefore to be assessed with respect to the total support provided. Nonetheless, it 
is interesting to compare the level of feed‐in tariffs for different energy sources in the 
different jurisdictions. Error! Not a  valid bookmark self‐reference. shows the range of 
feed‐in  tariffs  available  to  renewable  energy‐based  electricity  generation.  The  same 
range is also shown including Belgium and Luxembourg which appear to have the lowest 
levels of feed‐in tariffs for most energy sources. 

Exhibit 11: Feed‐in Tariff levels in the EU‐25 
 
60

50

40
c€/kWh

31.2 32.0 
30

20

10 8.7 8.8  9.7


8.0  7.7
6.2

Photo- Solar Tide & Wind


Biogas Biomass Biowaste Geothermal
voltaic Thermal Wave

Max. Average Min. Min. (incl. BE & LU) 

 
Except  for  solar  energy,  average  feed‐in  tariffs  in  the  EU  are  around  € 60/MWh  for 
biowaste; between € 70/MWh and € 80/MWh for biomass/biogas, tidal/wave, and wind; 
and  € 100/MWh for geothermal. For solar energy, the average feed‐in tariff is around 
€ 300/MWh  level  and  may  even  be  as  high  as  € 600/MWh.  Another  relevant  point  to 
mention  is  that  in  all  the  countries  where  feed‐in  tariffs  were  set,  this  was  done 
technology‐wise,  although  a  single  feed‐in  tariff  would  have  been  more  efficient  from 
the economic point of view. Hungary and Greece are the exceptions, and additionally in 
some countries, such as Germany and Ireland, the range across technologies is not wide, 
as can be seen in Exhibit 12. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  101
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 12:  Feed‐in Tariff Levels by Technology in the EU‐25 

60.0

50.0

Biogas
40.0 Biomass
c€/kWh 

Biowaste
Geothermal
30.0 Photovoltaic
Solar Thermal 
Tidal & Wave
20.0
Wind 
Hydel SS

10.0

0.0 
Czech Rep.

Spain
Austria

Belgium

Luxembourg

Netherlands
Denmark

France

Greece
Germany

Hungary

Ireland

Portugal
 
Appendix  A  describes  in  more  detail  the  instruments  employed  for  the  promotion  of 
different types of renewable energy used to generate electricity in the different member 
states of the EU‐25. 

3.4 RE Development: Country Achievements vis­à­vis Promotional Schemes 

As already commented, the unequal country‐wise development of RE in the EU‐25 may 
be attributed to two main drivers:  
• Important differences in exploitable RE potential between country members, and 
• Different RE promotional schemes followed by individual member states. 

In  this  section,  this  issue  will  be  addressed  by  analyzing  whether  the  unequal 
deployment of RE technology in the EU‐25 can be attributed to these drivers, or whether 
there could be other issues that could also impinge upon renewables penetration.  

3.4.1 On­shore Wind 

In  the  case  of  on‐shore  wind,  Exhibit  13  presents  information  regarding  wind 
penetration in 2006 and its mid‐term potential9 as well as existing feed‐in tariffs10 in the 
member states.  

                                                       
9
  Mid‐term potential up to 2020 determined by the Optres model (EC‐DG Tren EIE Programme, February 2006). 
10
  Zero tariffs imply that the country is not applying feed‐in tariffs but some other promotional scheme. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  102
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 13: On‐shore Wind Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 

Electricity Generation Using On-Shore Wind  


6 12,0 

5 10,0 

4 8,
TWh/Annu

c€/kWh 

3 6,

2 4,

1 2,

0 0,

Slovakia
Austria

Italy
Belgium

Netherlands
Czech Rep.
Denmark

France

Spain

Sweden
Hungary

Poland
Luxembourg
Greece

UK
Germany

Ireland
Finland

Portugal
Electricity generation in 2004 Increment during 2005-06
Potential up to 2020 Feed-in tariff
 
As  it  can  be  seen,  the  countries  with  largest  on‐shore  wind  potential  are:  France, 
Germany,  Spain,  the  United  Kingdom,  and  Italy,  followed  by  several  other  countries 
where  the  total  potential  is  less  than  10  TWh  per  year.  The  European  experience 
regarding on‐shore wind can be described as follows: 
A. Experience of Member States with Feed‐in Tariffs 
• France, where feed‐in tariffs are the highest amongst the EU‐25, surprisingly has 
almost  non‐existent  wind  deployment,  with  most  of  its  current  wind  electricity 
generation coming from recent development. 
• Germany, Spain and Denmark11 present a large wind penetration with more than 
50%  of  their  mid‐term  potential  already  covered  by  using  smaller  feed‐in  tariffs 
than France. 
• Other  important  countries  in  terms  of  potential  are:  Austria,  Belgium,  Czech 
Republic,  and  Greece;  here,  as  in  France,  the  existence  of  competitive  feed‐in 
tariffs  does  not  seem  to  be  a  sufficient  requirement  for  wind  development  to 
occur. 

The  explanation  for  these  heterogeneous  outcomes  varies  from  country  to  country:  in 
the case of France, administrative as well as grid barriers seem to be the main cause for 
the  lack  of  wind  penetration.  In  other  cases,  such  as  Austria,  Belgium  and  the  Czech 

                                                       
11
  Up to 2000, a high feed‐in tariff resulted in rapid development of wind technology in these countries.  However, the 
system was changed in 2001 to a small premium over the selling price, with much reduced effectiveness.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  103
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Republic,  complex  administrative  mechanisms,  regional  systems,  and  unstable  RE 


policies may be hampering the development of on‐shore wind. 
B. Experience of Member States with Other Promotion Schemes 
• In the case of Italy, the United Kingdom and Sweden, green certificates schemes 
were  used  for  RE  promotion  with  poor  results  in  wind  penetration,  which  may 
reflect, as already mentioned, that wind is not the most cost‐effective technology, 
and/or that the price volatility of green certificates may disincentivize investments 
in this technology. The case of Italy is quite interesting. For many years, Italy had a 
system of multiple feed‐in tariffs; the government however, decided to move to a 
quota  system  because  it  considered  this  solution  more  efficient,  setting  a 
reference  price  for  the  green  certificates  based  on  the  average  feed‐in  tariff 
(during  2006,  the  reference  price  was  c€ 12.8/kWh),  hoping  that  market‐driven 
forces  would  set  the  actual  price  below  this  reference:  however,  prices  are 
currently quite similar to the reference level. It is not so clear if this is due to the 
lack of competition or because of setting tight quotas. 
• In  Finland,  an  exemption  from  the  energy  tax  scheme  was  applied.  Unlike 
electricity  from  fossil  or  nuclear  sources,  renewable  electricity  is  exempted  from 
the Finnish energy tax paid by end‐users. In the case of wind energy, the available 
support is not enough to plug the gap with conventional technologies. 
• In Ireland, a tender system was initially implemented, but then changed to a feed‐
in  tariff  in  2005.  The  effectiveness  of  this  tender  system  in  allowing  rapid 
deployment of wind technology has proved to be very high. 

3.4.2 Solid Biomass 

At  first  glance,  the  penetration  of  solid  biomass  (see  Exhibit  14),  compared  to  its 
potential in the EU‐25, seems to be—with some exceptions (e.g., Finland, Sweden and 
Netherlands)—an unsuccessful story. 

But  biomass  analysis  should  be  conducted  carefully  because,  unlike  other  RE 
technologies—e.g.,  wind—solid  biomass  technologies  are  as  diverse  as  different  forms 
of  biomass  used  as  input.  In  addition,  biomass  technologies  suffer  from  several 
economics‐related  problems,  which  can  be  summarized  as  the  non‐existence  of  a  
‘biomass  market’  that  could  provide  the  necessary  price  signals  for  technology 
development;  plus  the  fact  that,  like  in  any  other  conventional  technology,  generators 
need to enter into long‐term agreements with biomass producers in order to obtain the 
guarantee that they will have enough input for power generation at a given price.12 

These  reasons  may  explain  why,  despite  the  existence  of  high  feed‐in  tariffs,  in  many 
countries—such  as  Germany  and  Spain—the  deployment  of  this  technology  has  been 
relatively modest up to 2004, even though this trend seems to be curving up in the last 
couple of years. 

                                                       
12
  Other important issues include: biomass delivery processes and costs, sustainable harvesting, water resources, etc. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  104
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 14: Biomass Penetration, Mid‐term Potential, and Feed‐in Tariffs in the EU‐25 
 
Electricity Generation Using Biomass 
80,00 16,0

70,00 14,0

60,00 12,0

c€/kWh 
TWh/Annum 

50,00 10,0

40,00 8,0

30,00 6,0

20,00 4,0

10,00 2,0

0,00  0,0

Slovakia
Austria

Poland
Belgium

Luxembourg

Netherlands
Czech Rep.

Denmark

France

Greece

Spain

Sweden
Hungary

Italy

Portugal

UK
Germany

Ireland
Finland

Electricity generation in 2004 Increment during 2005-06 


Potential up to 2020 Feed-in tariff  

Two  exceptions  in  biomass  use  in  the  EU‐25  are  Finland  and  Sweden;  in  both  cases, 
promotional  mechanisms  provide  incentives  for  cost  effective  development  (tax 
exemption in Finland and green certificates in Sweden), and the market seems to have 
responded well to such signals. 

As already mentioned, in the case of the Netherlands, feed‐in tariffs were applied, but as 
the Dutch government realized in 2006 that its RE objectives for 2010 were going to be 
achieved, it decided to suspend the system while considering future policy steps.   

3.4.3 Biogas 

For  biogas,  the  situation  in  the  EU‐25  has  been  similar  to  the  biomass  case,  but  on  a 
smaller  scale.  The  evidence  for  this  is  presented  in  Exhibit  15.  The  development  of 
biogas  technology  is  strongly  dependent  not  only  on  national‐level  promotional 
schemes,  but  also  on  those  at  the  provincial  and  municipal  levels.  This  situation 
introduces additional complexities to the analysis and is difficult to disentangle.  

The  two  EU‐25  countries  with  largest  biogas  development  currently  are  Germany  and 
the  United  Kingdom  and  in  both  countries  landfill  gas  is  the  predominant  technology 
being supported by additional schemes at the municipal level. This situation may explain 
the difference with corresponding development in Spain: in the latter case, the Spanish 
government provided at the outset some low feed‐in tariffs which did not offer enough 
incentives  for  a  proper  development  of  the  technology.  This  situation  has  changed  in 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  105
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

recent  months,  however,  as  the  government  has  increased  tariffs  and  expects  larger 
biogas deployment in the immediate future.   

For the rest of the countries, lack of detailed information on local experience does not 
allow an appraisal of the policies implemented. 

Exhibit 15: Biogas Penetration, Mid‐term Potential, and Feed‐in Tariffs in the EU‐25 

  Electricity Generation Using Biogas

25,00 16,0

14,0
20,00
12,0

c€/kWh
10,0
TWh/Annum

15,00
8,0
10,00 6,0

4,0
5,00
2,0

0,00 0,0

Slovakia

Spain
Austria

Italy

Poland
Belgium

Luxembourg

Netherlands
Czech Rep.

Denmark

France

Sweden
Greece

UK
Hungary

Portugal
Germany

Ireland
Finland

Electricity generation in 2004 Increment during 2005-06 


Potential up to 2020 Feed-in tariff 
 
3.4.4 Other RE technologies 

For the rest of existing RE technologies, it is quite complicated to properly analyze actual 
policy impacts due to several reasons which can be summarized as follows:  
• Technology or industry too incipient (tidal, wave, photovoltaics, and solar thermal) 
• No information regarding electricity generation (small‐scale hydel)  
• Development  of  technology  highly  correlated  with  local  promotional  schemes 
rather than at the national level (biowaste) 
• Too small potential or very region‐specific (geothermal) 

Nevertheless, available information and status of these RE technologies in the EU‐25 is 
presented in Exhibit 16 to Exhibit 21. 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  106
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 16: Small‐scale Hydel Mid‐term Potential and Feed‐in Tariffs in the EU‐25 

Electricity Generation Potential Using Small-Scale Hydel


6,00 10,0
9,0
5,00
8,0
7,0

 
 

4,00

c€/kWh
TWh/Annum

6,0
3,00 5,0
4,0
2,00
3,0
2,0
1,00
1,0
0,00 0,0

Slovakia
Spain
Austria

Italy

Poland
Belgium

Luxembourg
Netherlands
Czech Rep.
Denmark

France

Sweden
Greece

UK
Germany

Hungary

Ireland

Portugal
Finland

Potential up to 2020 Feed-in tariff


 

Exhibit 17: Biowaste Penetration, Mid‐term Potential, and Feed‐in Tariffs in the EU‐25 

Electricity Generation Using Biowaste

14,00 10,0

9,0
12,00
8,0
10,00 7,0
 
 

c€/kWh
TWh/Annum

6,0
8,00
5,0
6,00
4,0

4,00 3,0

2,0
2,00
1,0

0,00 0,0
Slovakia
Luxembourg
Czech Rep.
Denmark

France

Spain
Austria

Italy

Poland
Belgium

Netherlands

Sweden
Greece

UK
Germany
Finland

Hungary
Ireland

Portugal

Electricity generation in 2004 Increment during 2005-06 


Potential up to 2020 Feed-in tariff
 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  107
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 18: Photovoltaic Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 

Electricity Generation Using Photovoltaics

7,00 60,0

6,00 50,0

5,00

 
40,0
 

c€/kWh
TWh/Annum

4,00
30,0
3,00
20,0
2,00

1,00 10,0

0,00 0,0

Slovakia
Austria
Belgium

Luxembourg
Netherlands
Czech Rep.
Denmark

France

Spain
Greece
Hungary

Italy

Poland
Portugal

Sweden
UK
Germany

Ireland
Finland

Electricity generation in 2004 Increment during 2005-06 


Potential up to 2020  Feed-in tariff
 
 

Exhibit 19: Solar Thermal Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 

Electricity Generation Using Solar Thermal


20,00 60,0
18,00
50,0
16,00
 

14,00
 

c€/kWh
TWh/Annum

40,0
12,00
10,00 30,0
8,00
20,0
6,00
4,00
10,0
2,00
0,00 0,0
Slovakia
Spain
Austria

Italy

Poland
Belgium

Luxembourg
Netherlands
Czech Rep.
Denmark

France

Sweden
Greece

UK
Germany

Hungary
Ireland

Portugal
Finland

Electricity generation in 2004 Increment during 2005-06 


Potential up to 2020  Feed-in tariff
 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  108
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 20:  Tidal and Wave Penetration, Mid‐term Potential, and Feed‐in Tariffs 
in the EU‐25 

Electricity Generation Using Tidal & Wave


70,00 12,0

60,00 10,0

50,00
8,0

 
 

c€/kWh
TWh/Annum

40,00
6,0
30,00
4,0
20,00

10,00 2,0

0,00 0,0

Slovakia
Luxembourg
Czech Rep.
Denmark

France

Spain
Austria

Italy

Poland
Belgium

Netherlands

Sweden
Greece

UK
Germany
Finland

Hungary
Ireland

Portugal
Electricity generation in 2004 Increment during 2005-06 
Potential up to 2020  Feed-in tariff
 
 

Exhibit 21: Geothermal Penetration, Mid‐term Potential, and Feed‐in Tariffs in the EU‐25 

Electricity Generation Using Geothermal

8,00  18,0

7,00  16,0

6,00  14,0
12,0
c€/kWh
TWh/Annum

5,00 
10,0
4,00 
8,0
3,00 
6,0
2,00  4,0
1,00  2,0
0,00  0,0
Slovakia
Spain
Austria

Italy

Poland
Belgium

Luxembourg
Netherlands
Czech Rep.
Denmark

France

Sweden
Greece

UK
Hungary

Portugal
Germany

Ireland
Finland

Electricity generation in 2004 Increment during 2005-06 


Potential up to 2020  Feed-in tariff
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  109
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4 RE Policies in Selected non­European Countries 
4.1 India 

The  development  of  renewable  energy  technologies  for  power  generation  in  India  has 
been aided by a variety of policies and support measures from the government. Major 
policy  initiatives  were  taken  to  encourage  private/foreign  direct  investment  to  tap 
energy  from  renewable  energy  sources.  They  include  the  provision  of  both  fiscal  and 
financial incentives and the simplification of administrative procedures.  

These promotional measures include: 
• 100% accelerated depreciation for tax purposes in the first year of the installation 
of RE projects/systems. 
• No  excise  duty  on  manufacture  for  most  of  the  finished  products;  low  import 
tariffs for RE capital equipment, materials and components. 
• Soft  loans  to  manufacturers  and  users  for  commercial  and  near‐commercial  RE 
technologies. 
• Five‐year tax holiday for power generation projects. 
• Feed‐in  tariffs  under  alternate  power  purchase  policy  by  the  government  for 
power generated through RE systems and fed to the grid by the private sector. 
• Facility for banking and wheeling of power. 
• Facility for third‐party sale of renewable energy power. 
• Financial incentives/subsidies for RE devices with high initial cost. 
• Special  thrust  for  renewable  energy  in  the  north‐eastern  region  of  the  country; 
10%  of  Plan  funds  earmarked  for  north‐east  towards  enhanced  and  special 
subsidies. 
• Allotment  of  land  on  long‐term  basis  at  token  lease  rent,  and  when  the  project 
involves energy recovery from municipal waste, the supply of garbage free of cost 
at project site by state governments. 

The development of RE technologies in India depends on both national and state‐level 
policies and regulations. At the national level, incentives for RE deployment arise in two 
different ways: on the one hand, in the form of soft loans, subsidies and other national 
tax  benefits,  and  on  the  other  hand,    through  a  regulatory  framework  that  provides  a 
bearing  point  for  the  states’  regulatory  commissions,  enabling  them  with  proper 
capacities  for  the  promotion  of  RE  technologies.  Accordingly,  at  the  state  level,  the 
importance of State Electricity Regulatory Commissions (SERCs) is extremely high as it is 
a regulatory commission’s duty to study and establish the tariffs and other procedures 
for RE deployment. After the Electricity Act 2003, SERCs were set up in most states of 
the country. The Act has introduced Renewable Portfolio Standards (RPS), under which 
each  power  utility  has  to  source  a  certain  percentage  of  its  supply  from  renewable 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  110
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

generators;  this  percentage  is  defined  at  the  state  level.  Therefore,  SERCs  have  the 
mandate  of  promoting  renewables  either  through  preferential  tariffs,  or  a  minimum 
obligation  on  distribution  companies  to  source  a  certain  share  of  electricity  from 
renewable  energy,  or  both.  As  a  matter  of  fact,  in  many  states  both  mechanisms  live 
together, although this situation may introduce some conflicts in the future.  

4.1.1 RE Penetration in Electricity Generation 

The importance of renewable energy’s increasing role in the overall energy scenario in 
India was recognized in the early 1970s. During the past 30 years, significant efforts have 
been made into the design, development, field demonstration, and large‐scale use of a 
number of renewable energy products and systems. Today, India has one of the world’s 
largest programs for the deployment of renewable energy products and systems.  

India has a large potential for renewable energy in electricity, an estimated aggregate of 
over  85,000 MW.  However,  only  a  fraction  of  the  aggregate  potential  in  RE,  and 
particularly solar energy, has been utilized so far (Exhibit 22). 

Exhibit 22: RE Installed Capacity and Potential in India (2007) 

  RES-E Installed Capacity and Medium-Term Potential 

60.000

50.000

40.000
MW

30.000

20.000

10.000

0
Biomass Wind Hydel SS Waste Solar

Actual Potential
 
4.1.2 Incentives and Policies 

For each type of RE technology, two broad categories of incentives can be observed in 
India:  (1)  fiscal  and  financial  incentives,  and  (2)  up‐front  tariffs.  The  first  type  is  quite 
dependent on the RE technology involved, and therefore they are described separately 
for each technology. A description of the up‐front tariff in some relevant states follows 
after  that.  Wind‐based  power  generation  is  assessed  separately  due  to  its  high 
penetration. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  111
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Incentives Other than Tariffs 

Bio Energy (Biomass and Biogas) 

India  generates  a  vast  amount  of  biomass  material  which  can  be  utilized  for  power 
generation.  The country annually produces fuel wood (200‐300 million tonnes), animal 
waste  (80‐100  million  tonnes)  and  crop  residues  (100‐120  million  tonnes)  which  are 
consumed  as  the  main  biomass  fuels.  Some  19,500 MW  (including  3,500 MW  from 
biomass cogeneration) can be generated from fuel wood and crop residues (400 million 
tonnes  per  annum)  and  bagasse  in  the  sugar  industry.  Programs  are  also  being 
developed for direct combustion and grid interactive gasification using woody biomass 
or agricultural residues, such as crop straws, stalks, and husk. 

The main sources of energy for rural communities, which constitutes the largest part of 
the  population,  are  biomass  fuels  such  as  firewood,  agricultural  residues,  and  cattle 
dung. However, the energy from biomass resources has become unsustainable over the 
years,  mainly  due  to  human  population  explosion  and  the  low  efficiency  of  traditional 
stoves  (chulhas)  used  for  burning  these  fuels.  These  traditional  chulhas  lead  to  higher 
smoke  discharge  which  has  adverse  effects  on  health.  Also,  the  age‐old  practice  of 
burning cattle dung cakes in the kitchen deprives the soil of the much needed organic 
manure, which in turn reduces agricultural productivity. India has been working towards 
promotion  and  development  of  efficient  technologies  for  biogas  production,  improved 
chulhas, biomass gasification, and biomass briquetting. 

Box 1: Main Rural and Household RES Technologies in India 

Improved chulhas: A variety of biomass-based, efficient, smokeless chulhas


has been developed, which are estimated to have efficiencies of between 25-
30%. The fixed type chulhas have two or three pot-holes and the chimneys are
made of bricks/stones and clay, pottery liners, etc. Portable chulhas are made
of metal and metal-clad ceramics. In addition, a chulha for high-altitude use
has also been developed for cooking in colder Himalayan regions.
Biomass gasification: The biomass gasifier converts fuel wood and agricultural
residues into a ‘producer gas’, with a calorific value of 5,500kJ/Nm3, through a
thermo-chemical process. It can be used in burners and boilers and also in
dual-fuel engines, where it is first cleaned to remove particles of tar and then
cooled before use.
Biomass briquetting: Biomass briquettes, made through a manual process,
can be used as cooking fuel in homes, whereas those produced through
mechanical presses can be used in commercial boilers and furnaces.
 
Biogas:  Although  biogas  has  been  mainly  developed  in  India  for  off‐grid  rural  regions, 
including in integrated rural energy systems, a brief presentation is given here in order 
to obtain a full picture of the country’s RE program. 

The  biogas  production  process  involves  the  mixing  of  wet  cattle  dung  with  an  equal 
quantity of water and then storage in the biogas digester plant where it is retained for 
anaerobic  decomposition  in  the  absence  of  air.  The  gas  produced,  with  an  average 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  112
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

methane content of 55% to 75 %, is collected and piped for use in power generation or 
other areas, such as household cooking, depending on the size of the producing plant. 
Three  basic  designs  of  biogas  plants  have  been  developed  in  India—namely,  the  Fixed 
Dome  Deenbandhu  Model,  the  Floating  Gas  Holder  KVIC  (Khadi  and  Village  Industries 
Commission)  model  and  the  Bag  Type  Digester—which  are  promoted  under  two 
projects: one for community use and another for household use. 

The main policies and incentives for biogas use in India are as follows: 
• Special incentives are available for turn‐key entrepreneurs in rural areas to carry 
out biogas installation and maintenance as commercial ventures. 
• Commercial  and  cooperative  banks  provide  loans  for  setting  up  biogas  plants 
under Agricultural Priority Area schemes. 
• Turn‐key job fee, linked with a three‐year free maintenance warranty, provided to 
entrepreneurs, as is support for service charges, training, and publicity.  
• Central subsidy provided to users:  
o Subsidies  are  available  as  an  amount  per  plant  and  varies  depending  on  the 
region where the plant will be situated. 
o Ranges between Rs 2,700‐11,700 (€ 50‐200). 
• Dealership support at Fair Price Shops (FPS) and Public Distribution System (PDS) 
outlets. 
• Organizational and infrastructure support to implementing agencies. 
• Publicity support. 
• Technical  back‐up  units  provide  technical  and  training  support  for  effective 
implementation. 

Biomass:  At  the  national  level,  a  biomass  resource  assessment  program  has  been 
implemented  to  help  identify  locations  where  the  density  of  available  biomass  is 
adequate for power projects.13 

Promotion of biomass‐based power generation is being encouraged through enactment 
of  favorable  policy  regimes  at  the  state  as  well  as  central  levels.  State  policies  include 
buy‐back/wheeling/banking of generated electricity, as well as incentives in the form of 
sales tax exemptions, participation in equity and grants, etc. 

                                                       
13
  http://lab.cgpl.iisc.ernet.in/atlas. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  113
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 23: Nationwide Biomass Assessment (Season: Kharif) 

Crop Biomass Biomass Power


Area
State Production Generation Surplus Potential
(kha)
(kT/yr) (kT/yr) (kT/yr) (MWe)

Andhra Pradesh 1,479.9 1,887.7 4,271.6 734.3 92.0

Assam 666.3 1,792.6 3,046.5 554.8 63.7

Bihar 3,330.0 6,014.9 10,315.3 2,635.3 308.5

Chattisgarh 3,616.1 5,925.9 10,067.3 1,880.4 217.0

Goa 131.0 435.7 749.6 91.1 10.4

Gujarat 4,165.8 5,185.7 11,610.9 2,379.2 302.4

Haryana 1,515.2 3,107.7 5,473.6 3,672.2 439.0

Himachal Pradesh 361.6 772.3 1,832.9 821.2 106.2

Jammu & Kashmir 151.5 314.7 649.5 127.9 17.4

Jharkhand 127.6 259.1 325.8 81.6 9.9

Karnataka 4,020.6 7,888.3 14,837.3 3,306.0 418.5

Kerala 324.4 3,056.4 2,780.4 1,425.7 182.6

Madhya Pradesh 7,107.0 9,125.8 16,697.4 3,814.6 485.7

Maharashtra 7,812.3 10,100.7 18,387.3 4,077.9 514.9

Manipur 72.6 159.4 318.8 31.9 4.1

Nagaland 27.1 87.6 149.2 27.2 3.1

Orissa 1,815.5 1,822.6 3,338.2 870.5 109.1

Punjab 2,633.5 9,215.7 15,933.7 12,211.9 1,453.8

Rajasthan 5,661.2 75,196.8 173,610.5 26,194.5 3,362.3

Tamil Nadu 578.3 2,655.0 3,073.3 1,275.5 164.2

Uttar Pradesh 6,448.4 12,515.5 22,214.9 6,948.9 832.3

Uttaranchal 45.3 88.1 145.6 44.5 5.6

West Bengal 2,049.0 7,893.3 12,989.7 1,299.0 156.0

Total 54,140.0 165,501.5 332,819.1 74,505.9 9,258.9

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  114
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The most important fiscal and financial incentives for biomass use in India are as follows: 
• Interest subsidy up to 3% for commercial biomass power projects.14 
• Capital  subsidy  of  Rs 10  million/MW  (€ 173.5/kW)  for  advanced  biomass 
gasification projects.15 
• Up  to  5%  interest  subsidy  for  biomass/bagasse  cogeneration  (commercial 
projects).16 
• Capital  subsidy  for  cogeneration  projects  in  joint  venture  model/IPP  mode  in 
cooperative/public sector sugar mills; up to Rs 4.5 million/MW (€ 78.22/kW) with a 
maximum of Rs 81 million (€ 1.4 million) per project. 
• Capital  subsidy  for  cogeneration  projects  in  cooperative/public  sector sugar  mills 
through JV companies to be set up by state governments or IPP‐mode projects; for 
JV companies in only four states and four IPP projects (on first‐come‐first‐served 
basis). 
• Financial assistance under the National Biomass Resource Assessment Programme 
(NBRAP) of up to Rs 0.15 million (€ 2,600) per study; financial assistance up to 90% 
of  the  cost,  or  Rs 0.15  million  (€ 2,600)  per  study,  whichever  is  lower,  will  be 
provided to state nodal agencies. 

Waste to Energy 

Urban,  municipal,  and  industrial  wastes  have  a  high  combined  potential  for  energy 
extraction in India of around 2,700 MW, comprising 1,700 MW of power from urban and 
municipal  wastes  and  about  1,000 MW  from  industrial  waste.  India  has  two  programs 
for energy recovery from urban and industrial wastes: 
• The  National  Programme  on  Energy  Recovery  from  Urban,  Municipal  and 
Industrial Wastes. 
• The UNDP‐GEF Project on Development of High Rate Biomethanation Processes.  

The following projects are eligible: 
• Projects  based  on  any  waste,  or  a  mix  of  waste  material  of  renewable  nature 
available  from  urban, municipal  and  industrial  sectors,  other  than  husk,  bagasse, 
straw, stalks, and fines of biomass origin. 
• Projects  based  on  a  mix  of  other  renewable  wastes  from  urban  and  industrial 
sectors, including husk and bagasse. 
• Projects for production of biogas from distillery effluents are not eligible under this 
program.  However,  projects  for  power  generation  from  biogas  being  produced 
from industrial waste, including distillery effluents shall be eligible. 
                                                       
14
  Subject  to  net  interest  rate  (after  the  subsidy)  not  being  less  than  11%  and  a  maximum  subsidy  of  Rs  20  million 
(€ 347,000). 
15
  Maximum subsidy of Rs 80 million (€ 1.39 million). 
16
  Maximum subsidy of Rs 40 million (€ 0.695 million). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  115
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Projects for generation of power from biogas, produced from urban and industrial 
wastes through biogas engines, biogas turbines, dual fuel engines using diesel oil 
up to a maximum of 5% as pilot fuel, and steam turbines with a minimum steam 
pressure of 48 kg/cm2 shall be eligible. 
• Projects based in conversion technologies, namely, biomethanation, pelletisation, 
gasification,  pyrolysis,  incineration,  sanitary  landfilling,  etc.,  or  a  combination  of 
thereof.  

The state governments of Uttar Pradesh, Madhya Pradesh, Tamil Nadu, Andhra Pradesh, 
Maharashtra,  Haryana,  and  Karnataka  have  announced  policy  measures  pertaining  to 
allotment of land, supply of garbage and facilities for evacuation, sale and purchase of 
power to encourage setting up of waste‐to‐energy (WTE) projects. 

The most important fiscal and financial Incentives for WTE projects in India are as follow: 
• Financial assistance as interest subsidy for reducing the rate of interest to 7.5%.17 
• Financial  support  for  the  preparation  of  a  detailed  project  report  and  techno‐
economic feasibility report: 50% of the cost up to Rs 0.2 million (€ 3,500). 
• Financial  assistance  of  up  to  50%  of  capital  cost  of  the  project  limited  to  Rs 30 
million  per  MW  (€ 521.27/kW)  for  innovative  demonstration  projects  for  power 
generation from municipal solid waste and selected industrial waste. 
• Financial  assistance  of  up  to  50%  of  the  incremental  cost  for  power  generation 
from biogas at sewage treatment plants. 
• Incentive of Rs 1.5 million/MWe (€ 26/kWe) to municipal corporations/urban local 
bodies for site clearance, facilitation, and coordination of actions. 
• Incentive  of  Rs 0.5  million/MWe  (€ 8.68/kWe)  to  State  Nodal  Agencies  for  their 
coordinated actions and support. 

Solar Photovoltaic 

India  receives  about  300  clear  sunny  days  per  year  with  a  daily  average  solar  energy 
incident over the country that varies from 4‐7 kWh/m2, depending upon the location. In 
the  last  two  decades,  the  unit  cost  of  photovoltaic  (PV)  technology  has  decreased  by 
more  than  10  times,  increasing  accessibility  for  dispersed  rural  applications.  About 
2.2 MW of on‐grid PV power plants have already been installed in the country.  

The most important fiscal and financial Incentives for PV in India are as follows: 
• MNES financial incentives for solar PV grid‐connected power projects: 
o Detailed project report subsidy of Rs 0.1 million (€ 1 ,740). 
o Investment subsidy of two‐thirds of the cost of the project, with a maximum of 
Rs 20 million (€ 350,000) per 100 kW.  

                                                       
17
  Maximum depends on project type, but ranges between Rs 5‐20 million/MWe (€ 86.7‐347.1/kW). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  116
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

o O&M subsidy of 2.5% with a maximum of Rs 0.5 million (€ 8,700). 
• IREDA financial package for solar photovoltaic power generation systems.  
• MNES financial incentives for solar PV systems (power plants): 
o For  general  areas:  Rs 180,000/kWp  (€ 3,125/kWp)  of  array  capacity  or  50%  of 
ex‐work cost of the project, whichever is smaller. 
o For  north‐eastern  region,  including  Sikkim:  Rs 350,000/kWp  (€ 6,078/kWp)  of 
array capacity or 90% of ex‐work cost of the project, whichever is smaller. 

Solar Thermal 

All technologies employing solar heating come under this category, which also includes 
non‐grid solar thermal technologies. 

For electricity generation, India developed a 140 MW Integrated Solar Combined Cycle 
(ISCC) power plant. The solar thermal component (35 MW) is based on parabolic trough 
collector technology, while the combined cycle power plant (105 MW) operates during 
non‐sunny hours, running on naphtha/natural gas.  

Also, widely employed in India are non‐grid thermal technologies, solar water heating, 
solar  cookers,  solar  air  heating,  and  solar  thermal  building  design.  These  technologies 
receive financial support in terms of interest subsidies. 

Small­Scale Hydel 

The focus of the small‐scale hydel program in India is on promoting commercialization 
and active private sector participation. An estimated potential of about 15,000 MW of SS 
hydel (for projects up to 25 MW) exists in India. 

India has so far set up more than 400 SS hydel projects of up to 25 MW capacity, totaling 
2,013 MW. These projects are spread throughout the country in hilly regions, as well as 
on  canal  drops.  Most  SS  hydel  projects  are  grid‐connected.  However,  there  are  some 
projects  which  are  decentralized  and  are  managed  by  local  community‐based 
organizations (CBOs) or non‐governmental organizations (NGOs). 

The  13  potential  states  which  have  announced  their  policies  for  private  sector 
participation  in  the  SS  hydel  sector  are  Himachal  Pradesh,  Uttar  Pradesh,  Punjab, 
Haryana, Madhya Pradesh, Karnataka, Kerala, Andhra Pradesh, Tamil Nadu, Orissa, West 
Bengal, Maharashtra, and Rajasthan. 

The facilities available in the states include wheeling, banking, attractive buy‐back rates, 
and facility for third‐party sales, among others. 

In  order  to  accelerate  development  of  SS  hydel  power  in  India,  MNES  is  providing 
incentives for:  
• Detailed project report preparation from Rs 0.125 million per MW (€ 2.17/kW) up 
to Rs 0.5 million (€ 8.7/kW), above 10 MW and up to 25 MW. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  117
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Under  special  incentives  for  the  north  east  region  and  Sikkim,  a  capital  grant  of 
Rs 75 million per MW (€ 1,300/kW) is available for SS hydel projects in the region. 
The maximum support per project is Rs 225 million (€ 4 million).  
• Financial support for renovation, modernization, and capacity upgrading of old SS 
hydel stations of up to Rs 26 million per MW (€ 452/kW), or 75% of the R&M cost, 
whichever is lower.  
• Financial  support  for  development/upgrading  of  water  mills  of  up  to  Rs 30,000 
(€ 550)  or  75%  of  project  cost,  in  mechanical  mode  and  Rs 100,000  (€ 1,740)  or 
75% of project cost in electrical/electrical‐plus‐mechanical mode.  
• IREDA  provides  soft  loans  under  MNES  for  setting  up  SS  hydel  projects  of  up  to 
25 MW capacity in the commercial sector. 

Current Experience of RE Tariffs in Relevant States 

As already presented, the development of RES in electricity (RES‐E) technologies in India 
depends  on  both  national  and  states  policies  and  regulations.  Exhibit  24  to  Exhibit  26 
present the current Indian experience in tariff determination in different states. As can 
be seen, methodologies vary in some aspects, while they are concurrent in others. 

One of the most important common approaches for tariff setting is that State Regulatory 
Commissions seem to be applying up‐front tariffs based on a detailed cost assessment, 
leaving  producers  the  incentive  to  choose  the  best  alternative  in  order  to  achieve  the 
project. The approach followed by some SERCs is very interesting because it solves some 
important  and  controversial  issues:  for  instance,  input  price‐setting  for  biomass.  Fuel 
price  in  biomass  projects  is  a  key  issue  as  power  plants  can  run  with  several  biomass 
fuels, including coal (non‐renewable), and also because biomass prices are very volatile; 
if the price of biomass is higher than that of coal, then it is expected that producers will 
switch  coal  for  biomass  as  input,  disregarding  the  objective  of  RE  generation.  In  this 
sense, the approach followed by some SERCs (Andhra Pradesh and Gujarat in the tables) 
is  to  value  biomass  as  the  cost  of  the  alternative  fuel  (coal)  for  which  the  market  is 
usually very liquid and prices can be easily determined. 

Another important issue to comment on is SERCs experience in tariff‐setting for waste‐
to‐energy projects. For instance, Andhra Pradesh’s approach is to relate industrial waste 
to  another  biomass  project.  This  procedure  has  been  adopted  due  to  the  lack  of 
supporting evidence for proper cost and tariff determination, and may be changed in the 
future  when  information  regarding  costs  and  operation  becomes  available.  Regarding 
municipal waste, the procedure for tariff determination is different than that for other 
RE  technologies  as  the  nature  of  the  project  is  different.  For  this  technology  the 
approach followed national guidelines instead of a cost‐based analysis. 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  118
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 24: Gujarat Tariff Order, January 2007 

Cap-
1 Fuel 2 Depreciation Structure Discount
Tariff PLF Capital Cost O&M Fuel Cost SC ROE Tariff Rate
Consumption Rate (Debt Rate
Rate)

Single 80% Rs 40,000 2.5% of 25% of fossil Alternative fuel 8% Linear, 90% of 70:30 14% 10.6% Rs 3.0
Cogeneration

/kW capital cost fuel approach the initial value (10.25%) /kWh (US$
(US$ 1,012 with 5% consumption @ Rs 775/MT (US$ in 20 years; 0.076
/kW) escalation 2,250 kcal/kg 19.6/MT) with 5% 10.75% /kWh) fixed
Bagasse

(SHR 3,700 escalation working capital for 20 years


kcal/kWh)

Single 80% Rs 35,000 7% of capital 1.3 kg/kWh @ Alternative fuel 10% 10.75% for 70:30 14% 11.10% Rs 3.08
/kW cost with 5% 3,300 kcal/kg approach working capital (10.25%) /kWh
(US$ 886.5 escalation (SHR 4,290 Rs 1,000/MT (US$ (0.078
Biogas

/kW) kcal/kWh) 25.3/MT) with 5% /kWh) fixed


escalation for 20 years

1 2
Notes:  Plant load factor,  Self consumption. 

Exhibit 25: Rajasthan Tariff Order, March 2007 

Cap-
1 Fuel 2 Depreciation Structure Discount
Tariff PLF Capital Cost O&M Fuel Cost SC ROE Tariff Rate
Consumption Rate (Debt Rate
Rate)

Dis- 60% - Rs 47,000 4% of Mustard residue Direct fuel AC: SLM 90% of the 70:30 14% 10.6% AC: Rs 4.55/kWh
criminated 70% - /kW capital @ 3,400 approach 12% initial value in (10%) (US$ 0.1153
by tech: air- 75% (US$ 1,190 cost with kcal/kg Rs 1,050/ 20 years; /kWh)
cooled (AC) /kW) for WC 5% (AC SHR: 4,200 MT (US$ 26.6 WC: 12.25% for WC:
or water- escal- kcal/kWh; /MT) with 5% 10% working capital Rs 4.17/kWh
cooled (WC) ation WC SHR: 4,440 escalation (US$
Biomass

kcal/kWh) 0.1056/kWh)
fixed for 20
years

1 2
Notes:  Plant load factor,  Self consumption. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  119
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 26: Andhra Pradesh Tariff Order, March 2004 

Cap-
Fuel
1 Capital 2 Dep-reciation Structure Discount
Tariff PLF O&M Consumptio Fuel Cost SC ROE Tariff Rate
Cost Rate (Debt Rate
n
Rate)

Multi-part, 55% Rs 32,500/k 3% of 1.6 kg/kWh Alternative 9% Linear, 70% of 70:30 16% Not Tariff is divided into
depending on W capital cost @ 2,300 fuel approach the initial (10%) levelized Fixed Cost (depends
PLF (US$ 823 with 4% kcal/kg Rs 575/MT value @ on the year of
/kW) escal-ation (SHR 3,700 (US$ 14.6 7.84% per operation): from
kcal/kWh) /MT) with 5% annum; Rs 1.72/kWh (1st
escal-ation 12% for year) to Rs 0.9/kWh
Bagasse Co-generation

working capital (10th year) and


Variable Cost
(depends on calendar
year): from
Rs 1.02/kWh (2004-
05) to Rs 1.24/kWh
(2008-09)
If PLF>55%, then
VC+0.215
/kWh

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  120
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Multi-part, 80% Rs 40,000 4% of 1.16 kg/kWh Alternative 9% Linear, 70% of 70:30 16% Not Tariff is divided into
depending on /kW capital cost @ 3,200 fuel approach the initial (12%) levelized Fixed Cost (depends
PLF (US$ with 4% kcal/kg Rs 1,000/MT value @ on the year of
1,012/kW) escalation (SHR 3,700 (US$ 25.3 7.84% per operation): from
kcal/kWh) /MT) with 5% annum; Rs 1.61/kWh (1st
escal-ation 12% for year) to Rs 0.87/kWh
working capital (10th year) and
Variable Cost
(depends on calendar
year): from
Rs 1.27/kWh (2004-
05) to Rs 1.54/kWh
(2008-09)
Biomass

If PLF>80%, then
VC+0.215
/kWh

Multi-part, 35% Rs 36,250 - - Water royalty 1% 6.7% per 70:30 16% Not Tariff depends on the
depending on /kW pass-through annum for the (12%) levelized year of operation:
Small Scale Hydel

PLF (US$ 918 therefore not first 10 years; from Rs 2.6/kWh in


/kW) included in 12% for the 1st year to
tariff estima- working capital Rs 1.88/kWh in the
tion 10th year.
If PLF>35%, then
Tariff+0.215
/kWh

This category requires special treatment considering the nature of project activities. The capital cost of the projects is in the range of Rs 60 million/MW. The
Commission is therefore of the opinion that the project of electricity generation from municipal waste should have a different tariff and therefore is inclined to
Municipal

continue the tariff for these projects on the guidelines of MNES without going into the cost details. The Commission likes to retain the base unit price of Rs 2.25
Waste

as on 01-04-2004 and the escalation index of 5% p.a. In other words, the base price as on 01-04-2004 will be Rs 3.37/kWh.

Industrial waste-to-energy projects are managed as biomass projects. Hence, the Commission treats industrial waste-based power projects on par with biomass
Industrial

projects and authorizes purchase of the energy at the rates permitted for sale of power from biomass power projects.
Waste

1 2
Notes:  Plant load factor,  Self consumption. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  121
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

One  last  comment  should  be  made  on  the  type  of  tariffs  adopted  in  the  regions 
under analysis (single, or multi‐part, or discriminated by some criteria). In this case, 
the causes for introducing different tariffs for the same technology differ even in the 
same  state,  such  as  Rajasthan,  where  biomass  projects  are  divided  between  air‐
cooled  and  water‐cooled;  and  wind  projects  where  two  different  tariffs  are  set  for 
two different regions of the state. Even though the choice of determining different 
tariffs for different technologies or regions is strictly political, there is no clear reason 
why  this  policy  should  be  encouraged  as  it  may  create  an  unwanted  distortion  in 
technology  development  (or  in  the  agent’s  behavior)  as  well  as  increase  the 
complexity of the system and tariff determination. 

4.1.3 The Case of Wind Energy 

For wind technology, the Ministry of New and Renewable Energy (MNRE) undertook 
an extensive study of the wind regime, establishing a countrywide network of wind 
speed  measurement  stations.  These  have  made  it  possible  to  assess  the  national 
wind  potential,  and  to  identify  suitable  areas  for  harnessing  wind  power  for 
commercial use. 

The  total  potential  for  wind  power  in  India  was  first  estimated  by  the  Centre  for 
Wind Energy Technology at around 45,000 MW. This figure was also adopted by the 
MNRE as the official estimate of the country’s wind power potential. However, since 
1990, a massive exercise of wind monitoring and wind resource assessment has been 
carried out by government agencies and the private sector has identified many more 
resource areas.18 

Over  the  past  few  years,  the  stability  of  the  Indian  market  has  encouraged  larger 
private  and  public  sector  investments.  It  has  also  stimulated  a  stronger  domestic 
manufacturing  sector;  some  companies  now  source  more  than  80%  of  the 
components for their turbines in India. This has resulted both in more cost effective 
production and in creating additional local employment. Most recently, some Indian 
manufacturers  have  started  to  export  their  products.  About  nine  wind  turbine 
manufacturers are currently offering their products on the Indian market, the major 
players  being  Suzlon,  Enercon,  Vestas  Wind  Technology  India  Pvt.  Ltd,  Vestas  RRB, 
and Pioneer Asia Wind Energy Group. It can be said that India is now emerging as a 
manufacturing and knowledge hub for wind power development. 

The geographical spread of Indian wind power has so far been concentrated in a few 
regions, especially the southern state of Tamil Nadu, which accounts for more than 
half  of  all  installations.  This  is  beginning  to  change,  with  other  states,  including 
Maharashtra, Gujarat, Rajasthan and Karnataka, West Bengal, Madhya Pradesh and 
Andhra Pradesh starting to catch up. 

                                                       
18
  Currently, the Indian Wind Turbine Manufacturers Association (IWTMA) estimates the potential to be of the 
order of 65,000 MW. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  122
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Incentive Mechanisms 

Regarding  fiscal  and  financial  incentives  for  wind  power  development  in  India,  the 
most important ones are: 
• Direct taxes—80% depreciation in the first year of a project’s installation. 
• Tax holiday for 10 years. 
• No income tax to be paid on power sales to utilities. 
• FDI investments are cleared very fast. 

The MNRE has also issued guidelines to all state governments to create an attractive 
environment for the export, purchase, wheeling and banking of electricity generated 
by wind power projects.  

On  the  other  hand,  most  of  the  states  have  up‐front  tariffs.  Different  states  have 
different tariffs for grid‐connected wind farms. Exhibit 27 presents a summary of the 
incentives provided by state governments, and in Exhibit 28 a detailed description of 
the cost assessment for the up‐front tariffs in relevant states is provided. 

One  result  of  these  incentives  and  tariffs  has  been  to  encourage  energy  intensive 
and profit‐making industries and businesses to invest in wind power. In addition, the 
introduction of a Production Tax Credit (PTC) which would attract investment from 
Non‐Resident  Indians  (NRIs),  as  well  as  foreign  investment  in  the  Indian  market,  is 
currently  being  considered.  An  important  attraction  is  that  owning  a  wind  turbine 
assures a profitable power supply compared to the tariff of the high voltage sector. 
Wind farms in India therefore often consist of clusters of individual self‐ generators, 
and  more  than  97%  of  investment  in  the  wind  sector  in  India  has  come  from  the 
private  sector.  Recently,  wind  farms  have  also  come  up  as  independent  power 
producers (IPPs). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  123
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 27: State Government Incentives for Wind Power Development in India 

Buy-back Rate by
Penalty on Infrastructure
Captive Sale to Electricity Third-Party Other
Wheeling Banking kVArh Development
Use Board/Utility Sale Incentives
Consumption Charges
(SEB)

Allowed At par with No info Rs 3.37/kWh Allowed Industry status 10 paise per Rs 1 million/MW
with time- conventional frozen for 5 years under kVArh up to
RPS: 5%
of-day Electricity 10% and
tariff Act 2003, 25 paise per
Andhra
subject to kVArh above
Pradesh
regulation 10%
framed by
respective
SERCs

Idem 4% of energy Not Rs 3.37/kWh Idem ED-exempted, 10 paise per No info


allowed without any demand cut kVArh up to
escalation for 20 30% of wind 10% and
Gujarat years farm installed 20 paise per
capacity KVArh above
10%
RPS: 5%

Idem 5% of energy + Allowed Rs 3.40/kWh Idem No electricity Rs 0.40 per No info


Rs 1.15/kWh as @2% of without any duty for 5 years kVArh
cross-subsidy for energy escalation for 10
Karnataka RPS: 5-10%
third-party sale input years of
commercial
operation

Idem 2% of energy Allowed Rs 4.08/kWh Idem Transmission No info No info


1.5% escalation line borne by
Haryana
Transco (10 km)
RPS: 3-10%

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  124
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Idem 2% of energy + Not Year-wise rates Idem No electricity 27 paise No info


transmission allowed (Rs/kWh) from 1st duty for 5 years per kVArh
Madhya charges as per ERC to 20th year: 3.97,
RPS: 0.5%
Pradesh 3.80, 3.63, 3.40
and 3.30 (from 5th
to 20th year)

Idem 7% of energy + No info Rs 4/kWh Idem - - No info


West Bengal open-access
charges

Allowed 2% of energy as 12 months Rs 3.50/kWh First Allowed Power 25 paise Nil


with time- wheeling + 5% as year of under evacuation per kVArh
of-day T&D loss commissioning Electricity arrangement,
tariff (escalation of Act 2003, approach Road,
Maharashtra 15 paise per year subject to electricity duty,
for 13 years) regulation loan to
framed by cooperative
respective societies19
SERCs
RPS: 750 MW

                                                       
19
  Other incentives are: (a) For evacuation arrangement of wind energy projects, 50% amount will be given as a subsidy through the Green Energy Fund and 50% amount will be given as a 
loan  without  interest  to  private  developers;  the  loan  will  be  repaid  by  MSEB/transmission  licensees  after  commissioning  and  transferring  the  ownership  of  evacuation  arrangement  to 
MSEB/transmission licensees in five equal yearly instalments; (b) 100% expenditure for construction of approach roads will be made through the Green Energy Fund; (c) No electricity duty 
for five years for captive use; (d) 11% share capital will be provided to cooperative sector for setting up wind power projects as a grant through the Green Energy Fund.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  125
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Idem Below 132 kV, 50% Six months For Jaisalmer, Idem Exemption from 5 paise per Rs 0.2
of normal charges Jodhpur, and electricity duty year with million/MW
applicable to 33 kV Barmer districts: @50% for 7 escalation of
declared by Rs 3.60/kWh on 33 years 5% per year
commission + kV or 11kV system
surcharge + and Rs 3.71/kWh
Rajasthan losses20 on EHV system; for
other districts:
Rs 3.78/kWh on
33kV or 11 kV
system and
Rs 3.89/kWh on
EHV system

Idem 5% of energy 5% (12 Rs 2.90/kWh Idem - 25 paise per Rs 2.875


month kVArh if the million/MW
financial ratio of kVArh
year April drawn to KWh
Tamil Nadu to March) exported is up
to 10% and
50 paise per
KVArh for more
than 10%

Note: US$ 1 = Rs 40. 

                                                       
20
  4.5% for supply to consumer directly on EHV system and 8.3% for supply using distribution licensee below 132 kV. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  126
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 28: Main Assumptions in Up‐front Tariff for Wind Energy in India 

Dep- Cap-
Discount
Tariff PLF1 Capital Cost O&M reciation Structure ROE Tariff Rate
Rate
Rate (Debt Rate)

Single 23% Rs 46,500/kW 1.5% of Linear 90% of 70:30 14% 11.38% Rs 3.37/kWh
Gujarat

(US$ 1,178/ capital cost the initial (10.25%) (US$ 0.085/kWh) fixed for 20
kW) with 5% value in 20 years
escalation years

Discrimi-nated 20% to Rs 0.442 lakh/kW 1.25% of Linear 90% of 70:30 (10%) 14% 10.6% For Jaisalmer, Jodhpur and
(depends on 21% (US$ 1,120/ capital cost the initial Barmer districts: Rs 3.60/kWh
districts) kW) with 5% value in 20 (US$ 0.0912/kWh) on 33 kV or
escalation years 11 kV system and Rs 3.71/kWh
Rajasthan

(US$ 0.094/kWh) on EHV


system; for other districts:
Rs 3.78/kWh (US$ 0.0957/kWh)
on 33 kV or 11 kV system and
Rs 3.89/kWh (US$ 0.0985/kWh)
on EHV system

Considering the uncertainties that surround existing wind developments in the area, if a strictly ‘cost plus’ approach were adopted, it would lead
to distortions and would result in higher tariff for the initial years, with the resultant extra burden on consumers.
Andhra Pradesh

The Indian Renewable Energy Association and other developers wanted continuance of the MNES policy. The Commission, therefore, is inclined to
continue the guidelines of MNES in a refined format without going into cost details and to rationalize the tariff by adopting the following
methodology:
Energy purchase rate: The Commission likes to retain the base unit price of Rs 2.25 as on 01-04-2004 and an escalation index of 5% p.a. In
other words, the base price as on 01-04-2004 will be Rs 3.37/kWh. As these projects have no variable expenses and negligible increase in
maintenance costs, the tariff will be frozen for a period of five years.

1 2
Notes:  Plant load factor,  Self consumption. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  127
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.2 China 

4.2.1 Background 

In  less  than  a  generation,  China  has  moved  from  being  a  self‐sufficient  energy 
consumer to becoming the world’s fastest‐growing energy consumer. During the last 
decade, the country has steadily increased its share in the global energy market due 
to the inability of domestic production to cope with escalating energy demand. The 
rise in fossil fuel use has worsened already acute local pollution levels and driven up 
greenhouse  gas  (GHG)  emissions,  increasing  the  pressure  on  the  sustainability  of 
China’s development pattern. 

Coal  is  the  backbone  of  China’s  energy  system.  It  meets  just  over  60%  of  the 
country’s primary energy needs, providing most of the fuel used by power stations 
and  much  of  the  final  energy  used  by  industry,  commercial  businesses,  and 
households.  In  fact,  coal’s  importance  in  the  overall  fuel  mix  has  been  growing  in 
recent  years,  due  to  booming  demand  for  electricity,  which  is  almost  80%  coal‐
based. Oil demand has been growing quickly also, with its share of primary demand 
reaching  19%  in  2005.  Natural  gas  and  the  country’s  many  hydropower  projects 
constitute just 2% of total primary energy supply each. Nuclear power provides less 
than 1% of primary energy. 

Because  of  the  continued  use  by  so  many  rural  households  of  fuel  wood  and  crop 
wastes  for  cooking  and  heating,  biomass  remains  an  important  source  of  energy. 
Still,  its  share  of  primary  demand  is  only  half  what  it  was  two  decades  ago.  Other 
renewables, while growing very rapidly, continue to represent a small overall share 
of energy supplies. 

Power generation currently accounts for just under 40% of total primary energy use 
in China—a slightly higher share than that of the rest of the world. This reflects both 
the relatively large share of electricity in final demand and the low thermal efficiency 
of  power  stations,  despite  some  improvement  in  recent  years.  Coal  remains  the 
dominant  fuel  in  China’s  electricity  mix  with  a  share  of  78%  of  total  electricity 
supplied  in  2005.  In  2006,  nearly  90%  of  new  power‐generation  capacity  was  coal‐
fired, compared to 70% in 2000. The efficiency of coal‐fired generation has gradually 
improved, with the construction of larger, more efficient units and the deployment 
of supercritical and other clean coal technologies. 

Over  the  period  to  2020,  China  needs  to  add  782  GW  to  its  generating  capacity, 
more than the total current installed capacity in the EU‐25. Diversification to other 
energy  sources—especially  nuclear  power  and  non‐hydro  renewables—is  a  high 
priority.  But  even  if  forecasts  for  nuclear  (19,000 MW  by  2020)  and  non‐hydro 
renewables (over 32,000 MW by 2020) are achieved, they will still represent a small 
fraction  of  total  installed  capacity  forecasted  for  2020  (1,300  GW,  see  Exhibit  29). 
Basically,  the  forecasting  implies  some  substitution  (regarding  the  shares)  of  oil‐
based generation by wind generation and combined cycle gas turbines (CCGTs). 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  128
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 29: Generation Capacity in China by Technology 

 
 

Hydropower projects are still the largest alternative to coal,  and 300 GW capacity by 
2020  is  planned21,  yet  while  the  22.5  GW  Three  Gorges  Project  has  encouraged 
further  development,  the  barriers  remain  considerable  –  high  costs  for  dams  and 
long‐distance  transmission,  opposition  to  resettlement  and  ecological  impacts,  and 
complex interregional and transnational water rights issues.  

In addition, the country is actively engaged in the development of other sources of 
renewables  to  generate  electricity,  mainly  wind  power,  biomass  and  solar 
photovoltaic. Generation from these sources is expected to reach 103 TWh in 2020, 
about 2% of total electricity (see Exhibit 30).

Exhibit 30: RE Generation in China 

RES-E Expected Development (TWh)


120

100

80
TWh/Annum

60

40

20

0
1990 2005 2015 2020

Wind Biomass & Waste Geothermal Solar Tidal & Wave


 

                                                       
21
  China  is  the  largest  producer  of  hydroelectricity  in  the  world,  producing  397  TWh  in  2005.    Hydel  power  is 
expected to rise to 802 TWh in 2020, but its share of total power output will fall from 16% to 13%. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  129
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The costs of power generation in the current Chinese context, without a price on CO2 
emissions,  are  shown  in  Exhibit  31.  As  can  be  seen,  coal  is  likely  to  be  the  most 
competitive electricity supply source, followed by ‘advanced’ coal technologies and 
nuclear  power.  Gas  turns  out  to  be  the  most  expensive  option,  with  costs  ranging 
from €c 3.4 to 5.5/kWh. Coal can provide electricity at costs as low as €c  1.9/kWh. 
The construction cost of supercritical coal‐fired power plants is in the range of € 430‐
650/kW, cheaper than any other RE technology. 

Exhibit 31: Generation Cost by Type of Technology in China 

China's Technology-Wise Generating Costs


6,0
5,5
5,0
4,5
4,0
c€/kWh

3,5
3,0
2,5
2,0
1,5
1,0
CCGT Coal Coal Large Nuclear Wind
Advanced Standard Hydel
 
Source: Energy Outlook 2007 – China. EIA. 

A  final  comment  about  the  potential  of  off‐grid  rural  electrification  is  relevant. 
Thanks  to  rising  incomes  and  a  rigorous  policy  of  making  modern  energy  services 
available  to  the  entire  population,  all  but  around  10  million  households  now  have 
some access to electricity in China; and LPG, biogas and natural gas are distributed in 
a  growing  number  of  towns  and  cities.  Improved  stoves  are  also  widely  available 
though,  unfortunately  not  always  used  as  intended:  frequently,  improved  biomass 
stoves that burn efficiently and vent smoke outside the house are left idle in favor of 
small coal briquette stoves that have the advantage of convenience but are often un‐
vented, worsening indoor air quality. 

Although rural electrification programs have been particularly successful, the level of 
electricity  supply  to  a  large  proportion  of  the  rural  population  is  modest.  The 
availability of clean‐burning gaseous fuels is also very limited in rural areas and they 
are not affordable to many families. These issues are addressed in the 11th Five‐Year 
Plan,  which  promotes  the  development  of  off‐grid  renewables,  biogas  and  solar 
thermal  technologies,  among  others,  supported  by  technical  outreach,  grants  and 
credit  facilities.  For  cooking  and  hot  water,  large  integrated  biogas  programs  have 
been  carried  out  through  the  rural  energy  centers  of  the  Ministry  of  Agriculture. 
Nevertheless,  many  millions  of  rural  households  in  China  will  continue  to  rely  on 
traditional biomass to meet much of their energy needs. 

4.2.2 Potential and Incentives 

Renewable  energy  accounted  for  about  15%  of  China’s  total  primary  energy 
consumption  in  2005.  The  main  renewable  energy  source  now  is  biomass,  mainly 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  130
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

used  for  cooking  and  heating  in  rural  households.  In  the  electricity  sector, 
hydropower  is  the  main  renewable  energy  source,  accounting  for  16%  of  total 
generation  in  2005.  Solar  thermal  heating  is  also  well  developed.  The  Chinese 
government plans to significantly expand the use of renewable energy in the future, 
for electricity and heat production and for making transport fuels. 

In order to encourage the development of renewable energy, China has introduced 
the  Renewable  Energy  Law,  which  came  into  effect  on  1  January  2006.  The  law 
provides  for  the  compulsory  connection  to  the  grid  of  power  plants  producing 
electricity  from  renewables.  It  stipulates  that  all  renewable  sources  are  ‘must‐run’ 
and, consequently, they must be purchased. In addition, utilities must provide grid‐
connection services and related technical support.  

The  provisions  of  the  law  establish  that  the  reference  tariff  of  renewable  energy 
projects will be determined by the State Council on the principle of being beneficial 
to  the  development  and  utilization  of  renewable  energy  and  being  economic  and 
reasonable, where timely adjustment will be made on the basis of the development 
of each technology. When there are more than one interested parties in developing 
a  site,  the  tariff  will  be  determined  through  tender;  however,  such  a  tariff  cannot 
exceed  the  level  of  the  reference  tariffs  for  similar  renewable  power  generation 
projects. The difference between the expense that power grid enterprises purchase 
renewable  power  at  and  the  expenses  incurred  in  the  purchase  of  average‐priced 
power generated with conventional energy will be shared among all customers. Grid 
connection expenses may be included into the grid enterprise’s power transmission 
cost and retrieved from the tariff. 

Secondary  legislation  has  set  specific  incentives  mechanism  for  different  RE 
technologies that are explained below. 

Bioenergy 

China’s biomass consumption, at 227 MTOE in 2005, is the largest in the world. It is 
almost entirely traditional biomass. Only 3.3 MTOE were used in power generation in 
2005.  Main  biomass  resources  in  the  country  comprise  agricultural  wastes,  scraps 
from forestry and forest product industries, and municipal waste. Agricultural wastes 
are  widely  distributed  across  the  country.  Among  them,  crop  stalks  suitable  for 
energy production represent a potential of about 105 MTOE yearly.  

In the medium to long term, the forestry sector could provide a yearly potential of 
210  MTOE.  Wastes  from  the  processing  of  agricultural  products  and  manure  from 
livestock  farms  could,  theoretically,  also  contribute  another  80  billion cubic  meters 
of biogas per year. Municipal wastes could provide some 16 billion cubic meters of 
landfill gas. The government’s target calls for 5,500 MW of biomass‐fired generating 
capacity by 2010 and 30,000 MW by 2020. 

In the mid‐term, it is expected that total biomass consumption will remain broadly 
unchanged.  However,  the  utilization  pattern  is  expected  to  change  considerably. 
Traditional  biomass  consumption  will  most  probably  fall  and,  by  contrast,  demand 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  131
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

for  electricity  and  heat  from  biomass,  including  industrial  on‐site  generation,  is 
projected to increase from 8 TWh in 2005 to nearly 100 TWh in 2020. 

Secondary  legislation  implementing  the  Law  on  renewables  sets  a  subsidy  of 
Yuan 0.25 /kWh (c€ 2.3/kWh) for biomass‐fired projects. 

Hydel 

Total  hydel  potential  in  China  (including  both  large  and  small  scale)—some  1,750 
TWh—is  the  highest  in  the  world.  Resources  are  located  mainly  on  the  Yangtze, 
Lancang,  Hongshui  and  Wujiang  rivers.  Further  hydro  development  will  be 
undertaken  because  of  its  economic  advantages  and  advantages  in  reducing 
emissions. Hydropower is projected to increase from 397 TWh in 2005 to 1,005 TWh 
in 2030, but its share in total generation will fall from 16% to 12%. The government’s 
300 GW target is met by 2030 in the Reference Scenario. 

The  huge  Three  Gorges  Dam  on  the  Yangtze  River  in  Hubei  province,  when  fully 
completed in 2009, will have a total installed capacity of 22,500 MW22. Construction 
has recently started on two other very large hydropower plants: the Xiluodu project, 
located  along  the  Jinsha  River  in  south‐western  China,  which,  when  completed  in 
2015, will have a total capacity of 12,600 MW; and the Xiangjiaba project, in Sichuan 
province,  which  is  projected  to  be  completed  also  in  2015,  with  a  capacity  of 
6,000 MW.  

Small‐scale hydropower plants are widely used. About one‐third of China’s counties 
rely on small‐scale hydropower as their main power generation source, with a total 
installed capacity of 50,000 MW. 

For  hydro  plants,  Regulation  701/2001  (on  price  regulation)  applies.  Under  this 
regulation,  some  kind  of  up‐front  tariff  for  coal  and  hydel  is  set.  These  up‐front 
tariffs vary between provinces, but as an average they are around US$ 0.04/kWh. 

Wind 

Installed  wind  power  capacity  in  China  was  1,300 MW  in  2005  which  doubled  in 
2006. By the end of that year, there were 91 wind farms in operation in 16 provinces, 
equipped  with  3,311  wind  turbines.  Besides  large  wind  farms,  over  200,000  stand‐
alone  small‐scale  wind  turbines  provide  electricity  to  households  in  remote  areas. 
With  its  large  land  mass  and  long  coastline,  China  has  relatively  abundant  wind 
resources.  Estimates  by  the  China  Meteorology  Research  Institute,  based  on 
measurements taken at ten meters above ground, indicate a potential of 253 GW for 
onshore  wind  power.  The  institute  estimates  offshore  wind  resources  to  represent 
an exploitable potential of about 750 GW. 

Nevertheless,  the  government’s  target  for  large‐scale  wind  turbines  is  quite 
modest—5,000 MW in 2010 and 30,000 MW in 2020. Wind power development will 

                                                       
22
 There are 14,700 MW currently in operation. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  132
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

need to be accompanied by investment in grid expansion and transmission upgrades.  

The  capital  costs  of  wind  power  projects  in  China  are  lower  than  those  in  North 
America and Europe because of the lower cost for equipment, land and installation. 
In China, companies undertaking wind power projects are not required to purchase 
the  five‐year  warranty  on  equipment,  which  is  standard  practice  in  the  European 
Union and the United States. Thus, investors assume all the risk after two years of 
operation, which banks will accept in China but not elsewhere. Developers may also 
opt  for  equipment  with  lower‐quality  steel  in  order  to  lower  investment 
requirements.  Turbines  are  also  relatively  new  and  untested  in  China,  thus 
potentially yielding slightly more unpredictable output. The domestic manufacturing 
industry—including joint ventures—accounted for 45% of the wind‐turbine market in 
2006. At present, over twenty manufacturers are established in China. Competition 
between foreign and local manufacturers and suppliers of wind turbines and related 
components may put downward pressure on wind turbine prices or may force some 
manufacturers  to  cut  back  on  quality  in  order  to  remain  in  business.  Domestic 
turbine  manufacturers  are  being  supported  by  a  governmental  requirement  that 
more than half of the equipment in the first phase of a wind project must be made in 
China with, in later phases, the domestic manufacturing share increasing to 70%.  

This discrimination against foreign manufacturers and developers is compounded by 
the prospects of low returns on investment, low tariffs in some cases, and a lack of 
transparent, supportive pricing mechanisms such as feed‐in tariffs, and by a lack of 
flexibility  in  implementing  wind  power  projects  (e.g.,  site  selection  and  wind  farm 
size  are  determined  by  the  government).  On  financing,  Chinese  domestic  wind 
power developers can borrow up to 80% of the project’s costs, while there is a 66% 
limit on borrowing by foreign investors. This tends to lower the return‐on‐equity of 
foreign  investor‐owned  projects.  Furthermore,  to  qualify  for  clean  development 
mechanism (CDM) credits, projects are required to be at least 51% Chinese‐owned, 
which forces international investors to hand over control of the project to a Chinese 
partner. Currently, the rate of return to foreign investors on wind projects is around 
2%  to  4%,  which  explains  their  lack  of  enthusiasm.  Domestic  investors  earn  much 
higher returns, of at least 8%, depending on the particulars of the project. 

In  the  case  of  wind  projects,  the  implementation  of  the  Law  does  not  have 
preferential  pricing  policies.  Instead,  the  standard  price  for  wind  power  is 
determined through competitive tendering. There is no minimum wind power price: 
each wind project receives an individual on‐grid price which varies significantly: from 
Yuan 0.382/kWh (c€ 3.64/kWh) to Yuan 0.79/kWh (c€ 7.5/kWh). There are two types 
of tendering procedures, one through the central government and another through 
the provincial/local government.  

Solar 

By  the  end  of  2005,  China’s  installed  capacity  of  photovoltaic  systems  was  about 
70 MW, of which approximately 50% was used to supply electricity in remote rural 
areas without grid connection. Since 2000, China’s domestic PV industry has grown 
rapidly, achieving annual PV module production capacity of approximately 300 MW 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  133
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

at the end of 2006. The future potential is very large, as most areas benefit from high 
solar radiation. The national targets are 300 MW installed by 2010 and 1,800 MW by 
2020.  PV  technology  can  be  expected  to  make  significant  advances  beyond  2020 
along with cost reductions. 

China is the world leader in solar thermal systems for heating and hot water supply. 
About  75  million  m2  of  solar  collectors  are  installed  in  China  at  present.  This 
technology is already cost‐effective. The success of the past is likely to continue. The 
national target for 2010 is 150 million m2, increasing to 300 million m2 in 2020. 

4.3 Brazil 

4.3.1 Background 

Brazil  is  Latin  America’s  largest  energy  consumer,  accounting  for  over  40%  of  the 
region’s consumption. Its energy mix is dominated by renewable energy sources and 
oil.  Its  primary  energy  demand  is  projected  to  grow  annually  at  2.1%,  from  200 
MTOE in 2004 to 352 MTOE in 2030.  

The  country  is  expected  to  continue  to  rely  on  hydropower  to  meet  most  of  its 
power‐generation needs, building about 66 GW of new capacity until 2030. Dams are 
likely  to  be  located  far  from  centers  of  demand,  requiring  large  investments  in 
transmission lines to connect them to the national grid. Brazil has a large renewable 
energy  supply  potential,  with  260  GW  of  technical  hydropower  potential  (some 
12 GW are additional potential in small scale hydel) and 143 GW of technical wind‐
power potential (even though the expected penetration until 2030 is  5,000 MW23), 
and  a  large  potential  in  biomass,  mainly  driven  by  sugar‐cane  bagasse  (see  Exhibit 
32).  Development  of  these  vast  resources,  however,  has  been  hindered  by  cyclical 
economic disruptions and shortages of long‐term and low‐cost capital. 

Exhibit 32: RE Installed Capacity and Potential in Brazil 

  Brazil's mid-term RES-E Potential

16,000
14,000
12,000
10,000
8,000 
MW

6,000 
4,000 
2,000 

Biomass Wind Hydel SS  
Existing (2005) PROINFA (2006-08) Potential  
 

                                                       
23
  Plano Nacional de Energía 2030, Ministerio de Minas y Energía, Brasil. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  134
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Similar  to  other  developing  economies,  Brazil  faces  a  number  of  energy  and 
environmental challenges. Natural gas demand has increased considerably over the 
last  few  years,  as  the  government  kept  gas  prices  low  to  encourage  energy 
diversification. A rapid expansion of gas imports fuelled this growth. In 2006, imports 
from  Bolivia  accounted  for  48%  of  gas  consumption.24    Particularly  in  light  of  the 
recent nationalization of the energy sector in Bolivia, Brazil is seeking to reduce this 
concentrated  gas  import‐dependence  by  accelerating  development  of  the  Espirito 
Santo  and  Santos  basins  and  by  importing  LNG.  Environmental  concerns  will, 
however,  need  to  be  addressed.  Much  more  investment  will  be  needed  to  exploit 
domestic  gas  resources  and  to  expand  the  gas  transportation  and  distribution 
infrastructure.  Hydropower  accounted  for  over  three‐quarters  of  Brazil’s  electricity 
generating capacity in 2005, and the government plans to authorize the building of 
new large hydropower plants; but there are important environmental and financial 
obstacles.  The  government  is  actively  promoting  the  use  of  sugar‐cane  residue 
(bagasse)  for  cogeneration  of  heat  and  power  and  other  non‐hydro  renewables‐
based electricity generation. 

Brazil’s  energy  mix  has  become  more  diversified  over  the  past  several  decades.  In 
1980,  biomass  use  accounted  for  34%  of  total  energy  demand.  Most  of  this  was 
traditionally used for cooking and heating in the residential sector. Total biomass use 
declined  to  27%  in  2004.  The  use  of  biomass  today  is  predominantly  based  on 
modern energy technologies, such as the production of ethanol from sugar cane, the 
cogeneration  of  electricity  from  sugar  cane  bagasse,  the  use  of  sawdust  and  black 
liquor (a by‐product of the pulp and paper industries) and the production of charcoal 
from eucalyptus plantations by steelmakers. Fuel wood use for cooking and heating 
fell  from  25  MTOE  in  1971  to  11  MTOE  in  2004,  though  there  are  indications  that 
high oil prices have recently reversed this trend. Poor households in the north and 
northeast,  the  least  developed  part  of  the  country,  still  rely  predominately  on  fuel 
wood to meet their cooking and heating needs. 

Though it is beyond the scope of this work, it is important to mention the Brazilian 
experience on ethanol which is considered the most successful of the world. Brazil is 
the world’s second‐largest ethanol producer, after the United States, and the world’s 
largest ethanol exporter. Ethanol is derived from sugar cane. Brazil’s national ethanol 
program,  ProAlcool,  was  launched  in  response  to  the  oil  crisis  in  the  1970s.  From 
1983 to 1988, 90% of the 800,000 new cars sold each year on average in Brazil were 
running  on  ethanol.  In  2003,  car  manufacturers,  beginning  with  Volkswagen, 
introduced    ‘flex‐fuel’  vehicles  (FFV),  which  are  capable  of  running  on  any 
combination  of  hydrous  ethanol  and  a  gasoline‐anhydrous  ethanol  blend.  Such 
vehicles  allow  consumers  to  choose  any  combination  of  the  cheapest  fuel  while 
protecting  them  from  any  fuel  shortages.  FFVs  do  not  cost  any  more  than 
conventional vehicles. Today, the government estimates that FFVs account for more 
than three‐quarters of new car sales in Brazil. Pure gasoline is no longer sold. Brazil’s 
ethanol  production  was  15.9  billion  liters  in  2005,  more  than  a  third  of  global 

                                                       
24
  According to official estimates. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  135
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

production,  of which 2.6 billion liters were exported. Brazil has a 50%  share of the 


global ethanol trade (see Box 2 for more details). 

Box 2: Brazilian Experience with Ethanol 

Most of the reduction in the cost of producing ethanol in recent years has come
from the agricultural phase of ethanol production. Around 60% to 70% of the
final cost of ethanol is the cost of the sugar cane. Agricultural yield and the
amount of sucrose in the plant have a strong impact on costs. Average
productivity in Brazil is around 65 tonnes per hectare (MT/ha), but it can be as
high as 100 to 110 T/ha in São Paulo State. Since the beginning of ProAlcool,
yields have improved by about 33% in São Paulo with the development of new
varieties and the improvement of agricultural practices. Many operations have
been mechanised over the past 25 years, but advances in harvesting are more
recent. In the past five years in the midwest, southeast and southern regions,
about 35% of the area planted with sugar cane has been harvested mechanically
and, of this, about 20% has been harvested without previously burning the field.
Up to 90% of the sugar cane is harvested mechanically in some regions. It is
estimated that the widespread application of mechanised harvesting would
achieve a significant further reduction in the per-tonne cost of sugar cane.
Throughout the evolution of ProAlcool, technological priorities have changed.
Initially, the focus was on increasing equipment productivity. The size of
Brazilian mills also increased. Some mills now have a crushing capacity of 6
million tonnes of sugar cane per year and capacity is expected to increase to 10
million tonnes by 2010. The focus was then shifted to improvements in
conversion efficiencies. Over the past 15 years, the primary focus has been on
better management of the processing units. In the future, attention is expected
to be given to reducing water needs. On average, five cubic metres of water are
used for each tonne of sugar cane processed, though values range from 0.7
m3/tonne to 20 m3/tonne. Average ethanol production yields have grown from
3,900 litres per hectare per year (l/ha/year) in the early 1980s to 5,600
l/ha/year in the late 1990s. In the most efficient units, yields are now as high as
8,000 to 10,000 l/ha/year.
To meet rising domestic and export demand for ethanol, the Brazilian
government plans to increase productive capacity and to build ports with storage
tanks and loading facilities. Brazil will also need to establish a clear regulatory
framework in order to increase production and to address the potential
environmental and social impacts of expanding ethanol production in the
country.
 

4.3.2 Potential and Costs 

Biomass 

Brazil has extensive and diverse biomass resources, which are exploited for energy in 
many  ways.  The  country  is  a  highly  efficient  producer  of  large‐scale  industrial 
charcoal, with biomass‐to‐charcoal conversion efficiencies ranging from 30% to 35%, 
particularly  from  plantations.  Charcoal  production  has  increasingly  become  a 
professional activity, with most charcoal being produced from dedicated plantations. 
In  2000,  about  72%  of  charcoal  was  produced  from  eucalyptus  plantations, 
compared with 34% in 1990.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  136
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Almost all sugar‐cane distilleries in Brazil use bagasse‐fired steam turbine systems to 
provide  steam  and  electricity  to  meet  on‐site  factory  needs.  Most  biomass 
cogeneration is in São Paulo state, where 40 sugar mills sell some 1.3 GW of surplus 
power to the grid. The public authorities are promoting bagasse‐based cogeneration 
to  reduce  the  country’s  reliance  on  hydropower.  Apart  from  bagasse,  only  a  small 
proportion of the large potentially recoverable residues from commercial crops and 
forestry are used for energy purposes. Landfill gas is also underdeveloped. With the 
exception  of  bagasse,  there  is  a  lack  of  consistent  and  reliable  data  on  biomass 
resources and their potential as an energy source. This is particularly the case with 
regard  to  residues  in  the  pulp  and  paper  industry,  which  are  produced  in  large 
quantities. 

Exhibit 33: Brazil’s Generation Potential Using Native (left) and Planted (right) 
Forests 

Exhibit 34: Brazil’s Generation Potential Using Rice Bran 

 
The  use  of  bagasse  as  an  input  for  power  generation  is  competitive  with  other 
existing  conventional  technologies.  The  incremental  mid‐term  potential  of  power 
generation  using  sugar  cane  bagasse  accounts  for  up  to  6,400 MW.  Regarding  the 
wood and rice sectors, the identified mid‐term potential at the national level is not 
very  large,  but  potential  at  the  regional  level  must  be  considered  an  important 
option  for  biomass  penetration,  with  an  estimated  incremental  potential  of 
1,300 MW in both segments. Generation costs using rice bran or wood is very similar 
and its value is close to R$ 117/MWh (€ 44.15/MWh). Amongst existing technologies 
for power generation, biogas recovery from landfills is one of the most mitigating of 
all  solutions  for  GHG  emission  reduction.  Biogas  potential  in  Brazil  ranges  from 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  137
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

1,000 MW up to 3,000 MW; in addition, if we take into account recycling measures, 
the  potential  increases  by  an  additional  1,000 MW.  The  generation  cost  for  landfill 
gas is around R$ 191/MWh (€ 72.07/MWh). 

Small‐Scale Hydel  

Up  to  2007  the  installed  capacity  for  this  technology  accounted  for  1,673 MW 
distributed  amongst  280  facilities.  The  mid‐term  potential  identified  for  Brazil  is 
approximately 15,000 MW, spread over 3,000 plants each with an installed capacity 
ranging from 1 MW up to 30 MW (see Exhibit 35). 

Exhibit 35: Medium‐term Potential of Small‐scale Hydel in Brazil 
Potential
State Plants
MW %

Acre 53 0.4% 4
Alagoas 17 0.1% 6
Amapá 37 0.2% 3
Amazonia 366 2.5% 22
Bahía 914 6.1% 87
Ceará 8 0.1% 5
Espíritu Santo 594 4.0% 84
Goiás 659 4.4% 49
Marañaos 275 1.9% 30
Mato Groso 1,445 9.7% 84
Mato Groso do Sul 741 5.0% 70
Minas Gerais 3,920 26.4% 367
Pará 484 3.3% 35
Paraíba 8 0.1% 3
Parana 1,587 10.7% 1,781
Pernanbuco 25 0.2% 5
Piauí 28 0.2% 2
Rio de Janeiro 487 3.3% 55
Rio Grande do Norte 2 0.0% 1
Rio Grande do Sul 839 5.6% 76
Rondonia 442 3.0% 38
Roraima 37 0.2% 2
Santa Catarina 635 4.3% 56
Sao Pablo 1,007 6.8% 102
Tocantins 253 1.7% 22
Total 14,865 100.0% 2,989

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  138
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Several  fiscal  incentives  have  been  developed  at  various  governmental  levels  for 
small‐scale hydel promotion. They can be summarized as follows: 
• Public land use tax exemption. 
• Some  specific  federal  taxes  can  be  used  as  tax‐credits  in  state  and  municipal 
taxes. 
• Federal R&D tax exemption. 
• In  addition  to  the  fiscal  promotion  scheme,  small‐scale  hydel  projects  are 
entitled to sell power to qualified customers (with consumption over 500 kW 
each)  on  a  bilateral  basis.  The  generation  cost  for  this  technology  is  around 
R$ 135/MWh (€ 50.94/MWh), depending on the project’s financial terms. 

Wind 

In  Brazil,  the  existing  potential  for  wind  technology  amounts  to  143.5  GW  even 
though,  as  already  mentioned,  the  government  expects  that  less  than  5%  (some 
5,000 MW) will be developed by 2030. 

Exhibit 36: Brazil’s Wind Energy Potential 

 
 

Generation  costs  involving  wind  technologies  vary  between  R$ 203‐231/MWh 


(€ 76.6‐87.5/MWh),  calculated  using  a  load  factor  that  ranges  between  0.42  and 
0.32, respectively. These prices are higher than the average price for new energy in 
Brazil which is approximately R$ 139/MWh (€ 52.45/MWh).  

Meanwhile, with the development of a national industry for the production of wind 
generators,  production  costs  will  tend  to  reduce  and  as  the  competence  among 
companies  increases,  prices  will  tend  to  reduce  as  well,  making  this  energy  source 
more competitive.  

As  explained  later,  the  PROINFA  program  forecasted  a  wind  penetration  of 
1,423 MW  by  December  2008,  whereas  up  to  April  2007,  wind  generation  in  Brazil 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  139
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

accounted  for  237 MW,  of  which  208 MW  resulted  from  the  PROINFA  project. 
According to Eletrobrás, on average, wind farms committed in the PROINFA project 
should  have  a  load  factor  of  30%,  but  in  the  northeast  region  the  load  factor  has 
increased  to  over  40%  after  the  replacement  of  the  project’s  turbines  for  others 
more suitable for the region.  

Another important fact to point out is that most of the wind farms are located in the 
northeast  region.  This  will  help  the  development  of  small‐scale  hydel  due  to  the 
complementarities  that  exist  between  these  technologies  in  the  region:  the  most 
important  one  is  the  inverse  seasonality  between  prevailing  wind  speeds  and 
availability of water for hydel generation, as shown in Exhibit 37. 

Exhibit 37: Wind Seasonality in Northeast Region for PROINFA Projects 
vs. Sao Francisco River Volume 

Solar 

Solar  energy  in  some  rural  areas  is  the  only  feasible  solution  (technically  and 
economically)  to  provide  inhabitants  with  electricity;  this  is  due  to  low  local 
consumption,  the  scatter  of  population  in  rural  areas,  distances  to  main  transport 
lines, difficulty in accessing the area, as well as due to environmental restrictions. In 
urban areas it has additional efficiency advantages since it can be used not only to 
generate energy but also to heat water. The latter would reduce the ‘electric shower 
consumption problem’ peculiar to the country.25 

According  to  the  SWERA  (Solar  and  Wind  Energy  Resource  Assessment)  project, 
financed  by  the  United  Nations  Environment  Programme  (UNEP),  the  most 
appropriate  areas  to  exploit  solar  energy  in  Brazil  are  the  states  of  Bahia, 
Pernambuco, and Piauí, along with the south, southeast and central regions, in this 
order. The average insolation factor in these states equals 5 kWh/m2/day, as shown 
in Exhibit 38. 

                                                       
25
  Around  36  million  people  in  Brazil  use  electric  showers.    This  technology,  as  it  is  used  today,  at  peak  time 
energy consumption (from 6 pm to 9 pm) uses up about 6 GW.  In other words, electric shower consumption 
corresponds to 10% of the total energy used in Brazil. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  140
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 38: Average Annual Solar Irradiation in Brazil 

 
However, the biggest obstacle for the dissemination of solar energy (both for heating 
and  electricity  generation)  is  still  the  high  initial  costs  and  the  lack  of  low‐interest 
loan  programs  that  could  stimulate  the  sector.  Only  some  government  sponsored 
programs have been developed in some regions, resulting in an installed capacity of 
9 MW. 

4.3.3 Incentive Mechanism: The PROINFA Program 

The Brazilian Alternative Energy Sources Incentive Program (Programa de Incentivo 
às Fontes Alternativas de Energia Elétrica, or PROINFA), launched in 2004, provides 
incentives to stimulate the use of alternative sources of energy. PROINFA’s long‐term 
goal  is  to  increase  the  share  of  wind,  biomass,  and  small  and  medium‐sized 
hydroelectric facilities to 10% of electricity generation by 2020.  

The  Brazilian  government  has  designated  Eletrobrás  (state‐owned  company 


operating  the  HV  grid  and  large  hydro  plants)  as  the  primary  buyer  of  electricity 
generated  by  PROINFA  projects,  entering  into  long‐term  power  purchase 
agreements  at  a  guaranteed  price.  The  guaranteed  price  for  wind  is  90%  of  the 
average  supply  tariff,  70%  for  small  hydro  and  50%  for  biomass.  Several  of  the 
Eletrobrás  Group’s  regional  electricity  companies  are  minority  shareholders  (up  to 
49%) in special purpose entities which own and operate PROINFA projects.  

Brazil’s national development bank (BNDES) agreed to provide 70% of the financing 
for the projects and the Brazilian Energy Fund, launched in December 2004, should 
assist in funding the remaining 30%. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  141
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

PROINFA is being implemented in two phases: 
• In  Phase  1,  Eletrobrás  had  a  target  for  3,300 MW  of  renewable  capacity  by 
2006.  As  of  September  2006,  1,191 MW  of  small  hydro,  1,423 MW  of  wind, 
and 685 MW of biomass capacity had been accepted for PROINFA.26 
• In  Phase  2,  Eletrobrás  will  be  expected  to  lead  the  way  to  the  fulfillment  of 
PROINFA’s 10% goal of electricity generation from renewables resources. 

The main characteristics of the incentives provided are as follows: 
• Price floors for RE power. 
• Costs are distributed to consumers on pro‐rata basis. 
• Tender procedure for energy acquisition. 
• Minimum national participation: 60%. 
• 20‐year contract with Eletrobrás. 
• Up to 70% of contractual income guaranteed. 
• Differences  between  contractual  power  and  generated  power  are  traded  on 
the spot market. 

The results of the tender procedures until now are shown in Exhibit 39. 

Exhibit 39: Results of Tender Procedures in Brazil 

Technology Plants Capacity Energy Average Investment Investment


(MW) (GWh/Annum) Tariff (M€) (€/kW)
(€/MWh)

SS Hydel 63 1,191 6,541 46.4 1,358.50 1,140.64

Wind 54 1,423 3,719 79.8 2,086.80 1,466.47

Biomass 27 685 2,275 38.2 381.13 556.39

Total 144 3,299 12,536 3,826.43 -

                                                       
26
  See  ‘Acompanhamentodas  Centrais  Geradoras  do  PROINFA  ‐  Versão  Agosto  de  2006’  at 
http://www.aneel.gov.br/37.htm. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  142
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

5 What Have We Learned from International Experience? 
In this Annex, we have provided a comprehensive description of most of the relevant 
international  experience  regarding  promotion  of  on‐grid  RE  generation.  It  is  not 
possible to extract specific and definitive conclusions, or even patterns, amongst all 
the  analyzed  cases,  since  these  vary  widely  in  terms  of  both  context  and  details 
among different countries. However, some ‘lessons learnt’ can be discerned. Some 
of these lessons are presented in the following paragraphs as answers to five basic 
questions  that  should  be  kept  in  mind  while  designing  policies  and  regulations  for 
developing RE in a given country or region. 

Which have been the most successful RE stories and what are the common stylized 
facts in those experiences? 

We have seen that the experience of Germany, Denmark, Spain, and India regarding 
wind generation is a successful one. Similarly, the case for biomass in some Nordic 
countries  and  in  Brazil  (bagasse‐based)  has  performed  well.  Both  biogases  and 
biowaste have shown good results in Germany, the Netherlands, Italy, and the UK. 
For solar PV, the only example examined is Germany, but in some countries, such as 
Spain, it is being developed at very high rates. Within the analyzed sample, the only 
country  that  has  developed  geothermal  energy  is  Italy,  as  in  others  countries 
assessed  the  potential  is  negligible.  In  the  three  emerging  countries  studied,  both 
small‐scale  and  large‐scale  hydel  is  being  developed  both  because  there  is  still 
important  potential  and  because  it  is  cost‐effective.  In  EU,  the  remaining  potential 
for hydel is much less significant. 

When analyzing what might be the common issues in these countries, we identified 
at least two main facts:  
• Either they developed a strong national industry on a particular RE technology, 
and/or   
• They  have  a  huge  potential  in  one  RE  resource  and  hence  the  cost  for 
developing  the  corresponding  technology  is  very  competitive,  even  when 
external costs are not internalized in the cost‐benefit analysis. 

The first case is obvious when analyzing the wind sector: all of the most successful 
countries  in  developing  wind  generation  have  a  huge  local  industry  associated: 
Germany (Enercon, Nordex, Repower), Spain (Gamesa, Acciona), Denmark (Vestas), 
and India (Suzlon). The market share of these manufactures is around 80% (if we add 
the remaining successful experience, USA (GE), the market share is 95%). Though a 
less  concentrated  industry,  the  case  for  biogas  in  Germany  can  also  be  cited.  This 
raises  two  new  questions:  (1)  Is  it  necessary  to  develop  an  associated  industry  to 
foster  the  penetration  of  a  new  technology?  and  (2)  Is  it  easy  to  develop  a  new 
industry on renewable energy?  

There  is  no  evidence  that  not  having  an  established  local  industrial  and 
manufacturing base in a specific RET is a binding constraint to foster the penetration 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  143
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

of  renewable  energy.  However,  there  is  some  positive  correlation  between  the 
existence  of  these  industries  and  the  installed  capacity  in  a  country:  72%  of  the 
world’s wind installed capacity is on the aforementioned five countries. Although we 
do not consider this issue a pre‐condition in itself, it might have an influence in the 
regulatory tools chosen to foster the penetration of renewables.  

The  usual,  simple  benchmark  rule—“do  the  same  as  this  or  that  successful 
experience”—may  be  misguiding.  Such  benchmarking  can  be  dangerous  if  is  not 
properly  assessed.  Background  conditions  must  be  carefully  understood  before 
getting  to  final  conclusions.  In  the  case  of  Pakistan,  the  experience  of  Brazil  and 
some EU countries, that in smaller scale are also successful (i.e., Ireland), may be of 
more interest. As will be explained later, it is worthwhile to note that in both these 
experiences, tendering procedures were carried out in order to kick the market off. 

Different  is  the  case  if  the  country  decides  to  initiate  the  development  of  an 
indigenous  industry  in  some  RE  technology.  The  basic  problem  of  this  approach  is 
that,  normally,  the  involved  technologies  require  some  kind  of  a  ‘learning  curve’ 
before  becoming  commercially  viable.  Most  of  the  countries  mentioned  above 
started  research  on  wind  energy at least  ten  years  before  the  technology  could  be 
commercially  developed.  For  instance,  in  the  Spanish  case,  the  first  experimental 
developments  of  large‐scale  wind  turbines  were  carried  out  by  ASINEL  (Spanish 
association  of  the  electrical  industry)  in  the  beginning  of  the  80s.  An  intriguing 
experiment  is  the  Chinese  case,  where  some  important  manufacturers  are  being 
established (i.e., Goldwind); however, the quality of their products is still a matter of 
concern. 

Other successful stories can be found in those countries where the abundance of a 
resource  makes  it  very  cheap,  as  is  the  case  of  bagasse  and  hydel  in  Brazil,  other 
biomass  in  the  Nordic  countries,  geothermal  in  Italy,  etc.  In  these  countries,  the 
policy  looks  for  the  most  cost‐efficient  solution,  but  this  solution  is  not  developed 
based only on market signals. The case of Brazil is very interesting. The power sector 
in Brazil is based on 95 % hydel; probably medium‐size hydel is the cheapest option, 
but this generates the problem of security of supply, i.e., in hydrologically extra‐dry 
years  or  in  some  seasons  during  dry  or  average  years.  Therefore,  some  thermal 
generation  is  considered  a  necessary  complement,  and  for  covering  this  need 
bagasse‐based  generation  is  probably  the  cheapest  option  available.  Successful 
country  experiences  have  developed  RE  technologies  that  are  cheapest  and  better 
suited for the country in the first place.  

It  is  important  to  mention  that  in  all  cases,  even  when  the  technology  is  cost‐
efficient  (as  in  some  cases  of  hydel,  biogases  or  biomass),  a  policy  for  fostering 
technology development is a must. Besides the necessary subsidy to offset the issue 
that  externalities  are  considered  in  private  evaluation  of  conventional  generation, 
there are also financial, grid access, informational, and regulatory barriers that must 
be assessed. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  144
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

How  do  the  three  main  incentive  mechanisms  score:  quotas,  feed‐in  tariff  and 
tendering procedures? 

Broadly  speaking,  evidence  shows  that  feed‐in  tariffs  are  the  best  incentive 
mechanism for developing RE, although this evidence should be carefully managed.  
Quota systems do not seem to be working properly. In our opinion, this is because of 
two main issues: 
• One is inherent to the system—it is more complex than the others as it needs a 
secondary  market  to  trade  the  green  certificates,  a  penalty  mechanism  for 
defaulters, etc. 
• The second one, which can be easily overcome, is related to an inappropriate 
regulatory design in several of the instances examined. 

Tendering  procedures  worked  quite  well  in  many  cases,  at  least  to  kick‐start  the 
market.  The  big  issue  regarding  tendering  systems  is  whether  they  should  only  be 
employed to start the market, or as an ongoing system because, in the latter case, 
they seem to be more complex than a feed‐in tariff system.  

Is it better to have technology‐based incentives or single, common incentives? 
• In the case of feed‐in tariffs and tendering procedures, the issue of single vs. 
technology‐based pricing arises. International evidence shows that except for a 
few  (and  not  very  successful)  European  countries,  almost  all  countries  have 
adopted technology‐based incentive mechanisms. When this point of analysis 
is  reached,  two  issues  should  be  assessed:  technology‐based  incentives  are 
needed to foster the development of expensive technologies that have around 
three  times  higher  cost,  such  as  on‐grid  solar  PV  and  thermal.  Regarding  the 
other  cluster  of  technologies  whose  costs  are  relatively  closer,  the  case  for 
technology‐based incentives is about simplicity vs. fairness.  
• For  all  these  technologies  a  simple  feed‐in  tariff  or  tendering  procedure  may 
be  much  simpler  than  technology‐based  ones,  but  some  infra‐marginal  rents 
appropriated  by  the  producers  may  arise  in  the  case  of  the  cheapest 
technologies.  The  issue  should  be  overcome  by  a  cost  assessment  for  each 
technology in the  specific country.  

Is success only a matter of tariff? 

Definitely not.  Tariff is  a necessary but not a sufficient condition for  developing RE 


energy.  In  our  opinion,  grid  access,  administrative  issues  (contracts,  licenses, 
permits,  multiple  uncoordinated  windows,  facilities,  etc.)  and  instability  of  the 
incentive mechanism are as relevant as the tariff itself for fostering the penetration 
of  renewable  energy.  We  have  seen  cases  such  as  France,  where  the  potential  for 
many  RETs  is  huge  and  the  tariffs  similar  or  higher  than  those  in  other  countries 
which  have  achieved  great  RE  deployment  success;  however,  grid  access  and 
complex administrative mechanisms had blocked development in France until 2006.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  145
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

It  also  important  to  mention  that  small  projects  probably  need  other  types  of 
incentives, such as capital grants, interest rate reductions, etc., because, when these 
projects  are  developed  by  either  the  community  or  very  small  firms,  the  financial 
barriers can be huge. The Indian experience is quite interesting in this regard. 

Are  the  incentive  mechanisms  different  if  designed  for  a  developed  country  from 
those for an emerging one? 

This question implicitly comprises two other questions:  
• Are  the  incentive  mechanisms  different  across  developed  and  emerging 
countries? and  
• Is the level of the tariff for RE different in the two cases? 

There  is  not  enough  evidence  to  enable  a  categorically  statement  that  incentive 
mechanisms  need  to  be  different  depending  on  the  degree  of  the  country’s 
development. Both feed‐in and tendering procedures can be found in developed and 
emerging countries. In our sample, we do not identify emerging countries with quota 
systems, probably because they are quite complex to implement when there is not a 
consolidated (power or financial) market actually operating. 

Although it is foreseeable that the tariff for capital‐intensive technologies should be 
higher in emerging countries because of the higher risk, we do not find a consistent 
difference  across  tariffs  in  the  countries  analyzed.  Probably,  this  is  because  our 
sample only comprises BRIC27 countries which are perceived as less risky than other 
emerging countries. 

                                                       
27
  Brazil, Russia, India, and China. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  146
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Appendix A: RE Promotional Schemes in the EU­25 
Main Supporting Policies Key Factors Biogas Biomass Biowaste Geothermal
Feed-in tariffs plus Biogas: 10.3-16.5 € Electricity:
Investment subsidy (30% aprox) for cents/kWh <200 kW 13 € cents/kWh Electricity: 7 € cents/kWh
Austria 4-12.8 € cents/Kwh
solar thermal, biomass, geothermal, Sewage & landfill: 3-6 € >200 kW 10 € cents/kWh Heat: Investment subsidy
wind and hydro on project basis cents/kWh Heat: Investment subsidy
Green certificates system with 2 € cents/Kwh 2 € cents/Kwh
2 € cents/Kwh
Belgium minimum feed-in tariff plus tax 2 € cents/Kwh Wallonie: investment Heat: (Wallonie) investment
Wallonie: investment subsidy
compensation scheme. subsidy subsidy
Although the government intends to make
Landfill & Sewage:
Governmental grants of 30-40% plus Cyprus less dependent on imported Investment grant;
Cyprus Investment grant plus Investment Subsidy
feed-in tariffs energy, the infraestructure is set up for 6.3 € cents/kWh
6.3 € cents/kWh
fossil fuel generation.

PP: purchase price for the electricity


Minimum feed-in tariffs (Purchase supplied to the network.
8.3-11 € cents/kWwh (PP) 8.5-12.3 € cents/kWwh (PP) 16.4 € cents/kWwh (PP)
Czech Rep price or Green premiums). GP: green premium for the electricity
4.2-7 € cents/Kwh (GP) 4.4-8.2 € cents/Kwh (GP) 12.8 € cents/Kwh (GP)
Taxes reductions supplied to a trader or eligible customer.
Methods may not be combined.

4 € cents/Kwh (guaranteed for


Green certificates system plus feed-in
Denmark 4 € cents/Kwh 10 years) plus 1 € cents/Kwh 4 € cents/Kwh
tariff
guaranteed for RE certificate

Changes in the law opens the possibilities 1.8*Residential price for 7


Estonia Tax incentives plus feed-in tariffs
for producing wind energy profitably. years

Exemption from energy tax for Feed-in tariffs and green certificates are
Finland 4.2 € cents/kWh (aprox)
renewable energy being analysed.

Feed-in tariffs (<12 MW) and


Feed-in tariffs plus tender (>12 MW),
7,5-11 € cents/Kwh (15 7,5-11 € cents/Kwh 10-15 € cents/Kwh (15
France guaranteed for 15-20 years and rates Administrative and grid barrier exists. 7,5-11 € cents/Kwh (15 years)
years) (15 years) years)
adjusted by inflation.
Fiscal incentives

<150 kW 11.5 € cents/Kwh;


<5 MW 15 € cents/kWh
Sewage and landfill: 150 kW<p<500 kW 9.9 €
5 MW<p<10 MW 14 €
Feed-in tariffs. Limited grid capacity hampers the growth <500 kW 7.7 € cents/kWh;
cents/kWh
Germany Investments subsidies (except wind). of onshore wind. Technical problems on cents/Kwh; 500 kW<p<5 MW 8.9 €
10 MW<p<20 MW 8.95 €
Subsidised loans for wind investments. offshore wind. >500 kW to 5 MW 6.6 € cents/kWh
cents/kWh
cents/Kwh 1.5% decrease per year (20
>20 MW 7.16 € cents/kWh
years)

Administrative and grid barrier exists.


Islands: 7.8 € cents/Kwh Islands: 7.8 € cents/Kwh
Feed-in tariffs plus investments Greek government has established rules
Greece - Mainland: 7 € cents/Kwh Mainland: 7 € cents/Kwh
subsidies (30% aprox) for heat. for rational use of geothermal energy in
Investment subsidy (heat) Investment subsidy (heat)
line with the community's view.

No coordinated national action. Insufficient


Hungary Feed-in tariffs (on indefinite term) 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh
investment climate.

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  147
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Hydro L-S SS Hydel Photovoltaics Solar Thermal Tidal & Wave Wind onshore Wind offshore

<20 kWpeak 60 € cents/kWh


Austria 3.15-6.25 € cents/Kwh Investment Subsidy 7.8 € cents/kWh
>20 kWpeak 47 € cents/kWh

15 € cents/Kwh
15 € cents/Kwh
Belgium 5 € cents/Kwh Wallonie: investment 2 € cents/Kwh 5 € cents/Kwh 9 € cents/Kwh
Flandes: subsidy scheme
subsidy
Investment grant; plus: Investment grant; plus:
5 years: 9.2 € cents/kWh 5 years: 9.2 € cents/kWh
Investment grant;
Cyprus Investment Subsidy 10 years: 4.8-9.2 € 10 years: 4.8-9.2 €
<5 kW 20.4 € cents/kWh
cents/kWh (according to cents/kWh (according to
annual wind speed) annual wind speed)

8.7-13.8 € cents/kWwh
49 € cents/kWwh (PP) 49 € cents/kWwh (PP) 8.9 € cents/kWwh (PP)
Czech Rep (PP)
46.4 € cents/Kwh (GP) 46.4 € cents/Kwh (GP) 7.1 € cents/Kwh (GP)
4.9-8.7 € cents/Kwh (GP)

Spot price plus Spot price plus


Denmark environmental premium (1.6 environmental premium (1.6
€ cents/kWh) € cents/kWh)

1.8*Residential price for 1.8*Residential price for 12


Estonia
7 years years

Finland 4.2 € cents/kWh (aprox) 6.9 € cents/kWh (aprox)

0-10 years: 8.2 € cents/kWh 0-10 years: 13 € cents/kWh


6,1-8.6 € cents/Kwh (20 30-45 € cents/Kwh (20 10-15 years: 2.8-8.2 € 10-20 years: 3-13 €
France
years) years) cents/kWh cents/kWh
(15 years) (20 years)

Premiums for
<500 kW 9.67 €
upgrades before 6.19 € cents/kWh plus a
cents/Kwh; 5.5 € cents/kWh plus 3.2 €
2012 or increasing 2.91 € cents/kWh (bonus for
Germany 500 kW<p<5 MW 6.65 € 45.7 € cents/Kwh 45.7 € cents/Kwh cents/kWh (bonus) and 2%
its capacity by 12 years) and 2% yearly
cents/Kwh yearly reduction in tariff.
15% reduction in tariff.
(30 years)
(15 years)

Islands: 7.8 €
Islands: 7.8 € cents/Kwh Islands: 7.8 € cents/Kwh cents/Kwh Islands: 7.8 € cents/Kwh Islands: 7.8 € cents/Kwh
Greece Investment Subsidy (heat)
Mainland: 7 € cents/Kwh Mainland: 7 € cents/Kwh Mainland: 7 € Mainland: 7 € cents/Kwh Mainland: 7 € cents/Kwh
cents/Kwh

Hungary 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh 6-6.8 € cents/Kwh
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  148
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

 
Main Supporting Policies Key Factors Biogas Biomass Biowaste Geothermal

The Renewable Energy Feed-In Tariff


(REFIT) program guarantees power
prices for all registered renewable
Ireland power generators. 7.2 € cents/kWh
Tariffs range from 5.7 € cents/kWh for
wind power to 7.2 € cents/kWh for
biomass.

Certificate system with mandatory Certificates are issued only for plants
demand (cap and trade). producing more than 50 MWh per year.
Italy Tradable green certificates - Tradable green certificates
Funds for specific technologies and/or Problems in obtaining authorisation at local
municipalities. level and high cost of grid connection.

Regulation fixes the total capacity for


instalation and specific volumes for
next year are annually published.
Purchase tariff for small hydro, waste Long-term loan on favourable conditions
Latvia
and biogas is set at the average for projects in private and public sectors.
electricity sales tariff, while tariffs for
wind power plants are approved case-
by-case.

Procedure for promotion of purchasing


There are feed-in tariffs since 2002 but
Lithuania of electricity generated from 6.9 € cents/kWh
with no guaranteed time.
renewable and waste energy sources.

<3 MW 2.5 € cents/kWh for 10


Limitations on eligibility and budget.
Feed-in tariffs plus investments <3 MW 2.5 € cents/kWh years.
Luxembourg Broad range of support measures which
subsidies up to 40%. for 10 years. Investment compensation
may be used cumulatively.
scheme.

Malta is formulating a strategy for


Reduced VAT on solar applications, renewable energy.
Malta
from 15% to 5%. Energy infraestructure up to now has been
oriented to subsidied oil products.

On 18 August 2006, the Dutch Minister of


Economic Affairs suspended MEP subsidy
The MEP is a kWh subsidy paid to
of new projects, given recent information
domestic producers of electricity from
Netherlands indicating hat the Dutch renewable
renewable sources and CHP who feed-
electricty objectives for 2010 will be
in to the national grid.
achieved.
A new MEP from 2008 is forseen.
 
 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  149
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Hydro L-S SS Hydel Photovoltaics Solar Thermal Tidal & Wave Wind onshore Wind offshore

Ireland 5.7 € cents/kWh

Tradable green certificates.


Tradable green Feed-in tariffs ranging from Tradable green
Italy Tax deductions (heat) Tradable green certificates Tradable green certificates
certificates 36 € cents/kWh and 49 € certificates
cents/kWh

Latvia

Lithuania 6.9 € cents/kWh 6.9 € cents/kWh

<50 MW for 20 years


25 € cents/kWh <3 MW 2.5 € cents/kWh for
<3 MW 2.5 € cents/kWh (municipality) Investment compensation 10 years.
Luxembourg
for 10 years. 45-55 € cents/kWh (other) scheme (heat). Investment compesation
Investment compensation scheme.
scheme.

Malta

Netherlands

 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  150
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Main Supporting Policies Key Factors Biogas Biomass Biowaste Geothermal


No clear enforcement mechanism.
There are environmental funds on all levels
Poland Green Power Purchase Obligation
of the administration supporting the
developments of RES

Feed-in tariffs (formula)


Portugal Investments subsidies
Tax incentives

There is no specific support for wind


Current low energy prices.
and solar energy.
Slovakia The government only recognises potential
Biomass is supported in remote rural
for biomass in remote rural areas
areas.
Administrative problems for acquiring
permissions.
<1 MW 6.98 € cents/kWh
Slovenia Feed-in tariffs. Regulation establishes a contractual 6.11 € cents/kWh
>1 MW 6.76 € cents/kWh
framework between network operator and
generator including a 10 year contract.

<500 MW 13.07 (T) - <2 MW 15.89 (T) - 11.53 (P) €


<50 MW
The producer may choose between: 9.77 (P) € c/kWh c/kWh
Transparent support scheme and high feed- 6.89 € cents/kWh (T)
Spain Preferential tariff (T); or >500 MW 9.68 (T) - 5.78 >2 MW 14.65 (T) - 10.09 (P) €
in tariffs deliver high investment certainity. 3.84 € cents/kWh (P)
Premium price (P) (cap and floor) (P) € c/kWh c/kWh
(20 years)
(15 year) (15 year)

The certificate system will form an


incentive to invest in the most cost-
Electricity certificates
Sweden effective options. Green certificates Green certificates
Investment grants for wind
Volatility in prices cause uncertainity on
investors.
Obligatory targets with tradable green Grid connection issues could disadvantage
certificate system. RES support programs.
United Kingdom Climate change levy (0.63 € cent/kWh Obligatory demand is set to 2027 ensuring Green certificates Green certificates
aprox.) long-term demand.
Grant schemes RES-E economically viable.
Sources: EC "The share of renewable energy in the EU" and IEA "Global renewable energy"  
 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  151
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Hydro L-S SS Hydel Photovoltaics Solar Thermal Tidal & Wave Wind onshore Wind offshore

Poland

<5 kW 44.4 € cents/kWh


7.6 € cents/kWh for the first
>5 kW 31.7 € cents/kWh
33 GWh injected in the grid
Portugal for the first 21 GWh injected
or 15 years whatever comes
in the grid or 15 years
first
whatever comes first.

Slovakia

<1 MW 6.11 € cents/kWh <36 kW 27.85 €


<1 MW 6.33 € cents/kWh
Slovenia 1 MW<p<10 MW 5.89 € cents/kWh
>1 MW 6.11 € cents/kWh
cents/kWh >36 kW 6.11 € cents/kWh

Preferential tariff only:


Premium cap & floor only: <50 MW
<100 kW 44.04 € cents/kWh
<10 MW 8.52-6.52 € 6.89 € cents/kWh
Premium floor 100 kW<p<10 MW 41.75 € 26.94 € c/kWh (T) 7.32 € c/kWh (T) Premium cap & floor only:
cents/kWh (T)
Spain only: 6.12 € cents/kWh 34.4-25.4 € c/kWh (P) 8.49-7.13 € c/kWh (P) 16.4-8.43 € c/kWh
10 MW<p<50 MW 8-6.12 3.84 € cents/kWh
cents/kWh 10 MW<p<50 MW 22.97 € (25 year) (25 year) (25 year)
€ cents/kWh (P)
cents/kWh
(25 years) (20 years)
(25 years)

Sweden Green certificates Green certificates Green certificates Green certificates

Investment compensation
United Kingdom Green certificates Green certificates Green certificates Green certificates Green certificates
scheme (heat).

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  152
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex V:  Working Paper 2: 
Review of Pakistan’s Short­term Policy for 
Development of Renewable Energy 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  153
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Working Paper No. 2 

Review of Pakistan’s Short­term Policy for 
Development of Renewable Energy 

Contents 

Exhibits ..................................................................................................................... 156 
Abbreviations and Acronyms .................................................................................... 157 
1  Objective .............................................................................................................. 159 
2  Current Short‐term Policy ..................................................................................... 160 
2.1  Short‐term Policy Targets .................................................................................. 160 
2.2  Regulatory Tools for RE Development .............................................................. 160 
2.2.1  Existing Procurement Approaches ........................................................ 160 
2.2.2  Security Package .................................................................................... 161 
2.2.3  Permits and Consents ............................................................................ 161 
2.3  Incentive Mechanisms ....................................................................................... 162 
2.3.1  General Incentives ................................................................................. 162 
2.3.2  Specific Incentives by RE Technology .................................................... 164 
3  Performance of the Short‐term RE Policy.............................................................. 171 
3.1  Overall Performance.......................................................................................... 171 
3.2  Stakeholders Views ........................................................................................... 173 
3.2.1  Alternative Energy Development Board (AEDB) ................................... 173 
3.2.2  National Electric Power Regulatory Authority (NEPRA) ........................ 174 
3.2.3  Private Power and Infrastructure Board (PPIB) ..................................... 175 
3.2.4  Developers (Private Investors) .............................................................. 176 
3.2.5  Developers (State‐owned Investors) ..................................................... 177 
3.2.6  Other Institutions Involved in RE Development .................................... 178 
4  Consultants’ Views on Current Short‐term RE Policy ............................................ 179 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  155
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 

Exhibit 1:  Approved Wind IPP Tariffs .......................................................................... 167 
Exhibit 2:  Reference Small‐Scale Hydel Projects (ADB REDSIP Tranche I) .................. 171 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  156
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
AJK  Azad Jammu and Kashmir 
AKRSP  Aga Khan Rural Support Programme 
BOO  Build, own, and operate 
BP  Basis point 
CDM  Clean Development Mechanism 
CER  Certified Emissions Reduction 
COD  Commercial operations date 
CPI  Consumer Price Index 
DISCO  Distribution Company 
E10  10% ethanol blended gasoline 
EIA  Environmental impact assessment 
EPA  Environmental Protection Agency 
EPC  Engineering, procurement, and construction 
FATA  Federally Administered Tribal Areas 
FX  Foreign exchange 
GENCO  Generation company 
GoP  Government of Pakistan 
GSA  Gas Supply Agreement 
GTZ  Gesellschaft für Technische Zusammenarbeit GmbH 
GWh  Gigawatt‐hour 
HEB  Hydro Electric Board 
IA  Implementation Agreement 
IIE  Initial environmental examination 
IPDS  Irrigation & Power Department, Sindh 
IPP  Independent power producer 
KESC  Karachi Electric Supply Corporation 
kW  Kilowatt 
kWh  Kilowatt‐hour 
LIBOR  London Interbank Offered Rate 
LOI  Letter of Intent 
MW  Megawatt 
MWh  Megawatt‐hour 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  157
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

NA  Northern Areas 
NA  Not applicable/available 
NAPWD  Northern Areas Public Works Department 
NEPRA  National Electric Power Regulatory Authority 
NGO  Non‐governmental organization 
NTDC  National Transmission and Dispatch Company 
NWFP  Northwest Frontier Province 
O&M  Operations and maintenance 
OpEx  Operational expenditure 
PASMA  Pakistan Sugar Mills Association 
PIB  Pakistan Investment Bonds 
PMD  Pakistan Meteorological Department 
POE  Panel of experts 
PPA  Power Purchase Agreement 
PPC  Private Power Cell 
PPDB  Punjab Power Development Board 
PPDCL  Punjab Power Development Company Limited 
PPIB  Private Power and Infrastructure Board 
RE  Renewable energy 
REDSIP  Renewable Energy Development Sector Investment Program 
RES  Renewable energy source 
RFP  Request for proposals 
ROE  Return‐on‐equity 
ROW  Right‐of‐way 
SHYDO  Sarhad Hydel Development Organization 
WAPDA  Water and Power Development Authority 
WPI  Wholesale Price Index 
WTE  Waste‐to‐energy 
WTG  Wind turbine generator 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  158
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Review of Pakistan’s Short­term Policy for 
Development of Renewable Energy 

1 Objective 
This Annex presents the consultant’s evaluation of Pakistan’s current short‐term policy1 
(January 2006 to June 2008) for the development of renewable energy for on‐grid power 
generation, including a comprehensive analysis of the incentive structure it creates and 
its performance regarding the main RE sources it targets.  

As was stated in the Project Inception Report (R7IR1PRP, October 11, 2007), renewable 
energy  development  in  Pakistan  has  been  conceived  under  a  phased,  evolutionary 
approach  constituting  a  strategic  policy  implementation  roadmap  adopted  by  the 
Government  of  Pakistan  (GoP).  The  initial  phase  (i.e.,  the  ‘short‐term  ‘)  involves,  in 
principle, lenient policy measures and strong incentives in order to attract investment in 
this  relatively  new  business  area,  remove  existing  barriers  to  project  implementation, 
and ‘hand‐hold’ reasonable‐sized pioneering projects through to successful commercial 
operation.  

The  focus  of  this  phase  is  on  RE  options  amenable  to  immediate  commercial 
development, i.e., small hydro, wind, and biomass‐based power generation. This phase 
is marked with beneficial risk‐sharing and attractive tariffs for developers so as to enable 
a  reasonable  generation  capacity  to  be  installed  as  ‘first‐of‐kind’  RE  projects  in  the 
private  sector,  that  can  then  serve  as  successful  business  and  technology‐assimilation 
demonstrators.  This  first  phase  also  requires  actions  towards  rural,  off‐grid,  and 
standalone  RE  deployment,  including  the  geographical  demarcation  of  off‐grid  regions 
and the design of legal and regulatory framework for off‐grid and distributed generation. 
However,  off‐grid  and  non‐power  RE  application  will  be  addressed  in  the  latter  half  of 
this project. 

Based  on  best  international  experience  (see  Annex  IV),  a  comprehensive  cost 
assessment of RE and conventional sources (see Annexes VI and VII), and this diagnosis, 
a more comprehensive ‘medium term’ (i.e., to 2012) policy framework for on‐grid RE will 
be prepared for the systematic implementation of feasible RE technologies and scaling 
up of associated capacity deployment in Pakistan.  

                                                       
1
  Approved by the Federal Cabinet and stated in the GoP’s Policy for Development of Renewable Energy for Power 
Generation,  2006,  Alternative  Energy  Development  Board  (AEDB),  Ministry  of  Water  and  Power,  Islamabad, 
December 2006. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  159
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2 Current Short­term Policy 
2.1 Short­term Policy Targets 

During  the  initial  policy  tenure  (ending  on  June  30,  2008),  a  limited  portfolio  of 
independent  power  producer  (IPP)  projects  and  technologies  would  be  approved  for 
development  by  the  GoP,  including  wind,  biomass,  municipal  solid  waste‐to‐energy 
(WTE), and small hydropower plants.2  

In  the  case  of  wind  IPPs,  a  cap  of  50  MW  of  installed  capacity  (net  rated  output)  per 
wind farm was initially set. Additionally, a cumulative wind power generation ceiling of 
300  MW  during  this  phase  on  a  first‐come‐first‐served  basis  was  considered,  but 
subsequently dropped. The case of hydro and WTE plants that are allowed to be sized on 
available  resource  characteristics  and  most  economical  capacity  basis.  However,  only 
IPPs  of  net  installed  capacity  less  than  50  MW  will  be  processed  by  the  Alternative 
Energy Development Board (AEDB) under the GoP’s RE policy, while projects of capacity 
greater than 50 MW are dealt with by the Private Power and Infrastructure Board (PPIB) 
under  the  GoP’s  conventional  power  policy.3    Regarding  biomass  generation  (basically 
bagasse‐based),  the  GoP  allows,  in  the  immediate  term,  the  installation  of  up  to  a 
cumulative cogeneration capacity of 700 MW (power) at the country’s sugar mills. 

2.2 Regulatory Tools for RE Development 

2.2.1 Existing Procurement Approaches 

The current policy basically comprises three different approaches for the procurement 
of RE: 
• Competitive  Bidding  (or  Solicited  RE  IPP  Proposals):  Competitive  bidding  for  a 
RE‐based  IPP  project  to  be  connected—partially  or  fully—to  the  national 
electricity  grid  of  an  installed,  net  rated  capacity  up  to  50  MW  is  allowed.  The 
procedure is managed by AEDB on behalf of GoP. 
• Negotiation  (or  Unsolicited  RE  IPP  Proposals):  Proposals  for  renewable  energy 
IPP projects on ‘raw’ sites (those which could be developed for power generation 
but for which feasibility studies do not exist) may also be submitted to the AEDB. 
Any  sponsor  wishing  to  undertake  this  kind  of  project  must  submit  a  detailed 
proposal  to  the  AEDB;  on  completion,  the  feasibility  study  will  be  reviewed  by 
the  Panel  of  Experts  (POE)  appointed  by  AEDB,  and  if  approved,  the  project’s 
sponsors are allowed to negotiate, within a period not exceeding three months, a 
tariff with the energy purchaser and to obtain a generation license from NEPRA. 
The  power  tariff  is,  however,  subject  to  final  determination  by  NEPRA.  Power 
purchase  tariffs  will  be  negotiated  with  qualifying  projects  under  a  transparent 
formulation  methodology,  guaranteeing  a  minimum  return  on  equity  (ROE)  to 

                                                       
2
  The GoP defines ‘small hydro’ as run‐of‐river hydroelectric generators of less than 50 MW installed capacity. 
3
  Policy for Power Generation Projects, 2002, Private Power and Infrastructure Board (PPIB), Ministry of Water and 
Power, Islamabad, October 2002. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  160
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

the sponsor(s). In case negotiations on tariff between the power purchaser and 
sponsors of the feasibility study are not successful, the project may be processed 
as  a  Solicited  Proposal,  except  that  the  sponsors  who  have  conducted  the 
feasibility study are allowed to participate with some advantages.4  
• Up‐front tariff‐setting: This alternative is only available for wind IPPs. A detailed 
description is provided later in this report. 

2.2.2 Security Package 

The  risk‐sharing  among  the  different  stakeholders  regarding  RE  power  projects 
connected to the national grid is arranged in a list of agreements. Fortunately, most of 
these  agreements  are  standardized,  to  the  extent  possible,  in  order  to  eliminate  the 
need for protracted negotiations. The key agreements are:  
• Power  Purchase  Agreement  (PPA):  between  the  RE  investor/operator  and  the 
Purchaser. Power purchase tariffs and agreements (PPAs) will be negotiated for 
each project for a minimum of 20 years and final approval provided by NEPRA. 
• Implementation  Agreement  (IA):  The  Government  of  Pakistan  will  guarantee, 
through an IA, bulk power purchase by the National Transmission and Dispatch 
Company  (NTDC)  or  relevant  distribution  company  (DISCO)  as  specified  in  the 
PPA  for  the  entire  duration  of  the  agreement,  regardless  of  power  market 
restructuring  and  privatization,  and  will  also  undertake  to  provide  the 
infrastructure for evacuating power from the RE IPP’s bus bar. 
• Gas Supply Agreement (GSA): In case of cogeneration projects, which use gas as 
an alternative fuel to bagasse (beyond the cane‐crushing season). 

2.2.3 Permits and Consents 

Several  permits  and  consents  are  required  from  different government  agencies  before 
construction  of  a  grid‐connected  power  project  can  begin  in  Pakistan.  AEDB  acts  as  a 
‘single  window’  facility  helping  investors  obtain  them  in  a  timely  fashion.  Additional 
requirements may be imposed by financing institutions according to their own safeguard 
requirements. 

The most important GoP permits/consents required include:  

National Electric Power Regulatory Agency (NEPRA):  
• Generation License to construct, own or operate a RE power generation facility 
• Approval of PPA/tariff for generation 
• Second‐tier  supply  authorization  (in  case  the  project  enters  into  a  power  sale 
arrangement with a bulk supplier) 

                                                       
4
  They  do  not  need  to  submit  a  bid  bond  and,  if  approved  by  the  AEDB,  will  be  given  a  chance  to  undertake  the 
project at the lowest tariff offered during the bidding process.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  161
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Transmission  and/or  distribution  licenses  (in  case  the  project  involves  lines  or 
small distribution systems). 

Environmental Protection Agency (EPA): 
• Initial Environmental Examination (IIE) 
• Environmental Impact Assessment (EIA).5 

2.3 Incentive Mechanisms 

The current policy comprises of both general incentives available to any technology and 
specific mechanisms for some RE types. 

2.3.1 General Incentives 

The most relevant general incentives defined in the policy are:

Regarding Sovereign and Political Risks: The GoP commits: 
• To  guarantee  the  contractual  obligations  of  its  entities,  including  WAPDA,  the 
Karachi Electric Supply Corporation (KESC) and provincial/AJK governments, even 
though  some  or  all  of  the  utilities may  by  restructured  or privatized  during  the 
term of various agreements. 
• To provide protection against specific ‘political’ risks. 
• To provide protection against changes in the tax and duty regime. 
• To  ensure  convertibility  of  Pakistani  Rupees  into  US  Dollars  at  the  prevailing 
exchange  rate  and  the  remittability  of  foreign  exchange  to  cover  necessary 
payments  related  to  the  project,  including  debt  servicing  and  payment  of 
dividends.  

Regarding Land and Site Access: The federal, provincial, and AJK governments facilitate 
investors  in  acquiring  land  or  right‐of‐way  (ROW)  for  project  development,  as  well  as 
providing  site  access  on  a  case‐by‐case  basis  by  leasing,  acquisition  of  ROW,  and/or 
construction of road linkages. However, the primary responsibility for acquiring land and 
site access rests with the project sponsors. 

Regarding Financial Regime: The following financial incentives are currently available to 
grid‐connected RE power projects:
• Permission for power generation companies to issue corporate registered bonds 
and to issue shares at discounted prices. 
• Permission for foreign banks to underwrite the issue of shares and bonds by the 
private RE power companies.  

                                                       
5
  If mandated by the EPA after review of IIE. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  162
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Non‐residents  allowed  purchasing  securities  issued  by  Pakistani  companies 


without the central bank’s (i.e., State Bank of Pakistan) permission. 
• Availability of independent credit rating agencies to enable investors to properly 
evaluate risk and profitability of project company’s bonds and share certificates.  

Regarding Fiscal Regime: The following fiscal incentives are available to grid‐connected 
RE power producers: 
• No customs duty or sales tax on the import of RE plant and equipment. 
• No levy of sales tax on RE plant, machinery, and equipment. 
• Exemption from income tax, including turnover rate tax and withholding tax on 
imports. 
• Permission  for  project  company  to  repatriate  equity,  along  with  dividends, 
subject to prescribed rules and regulations. 
• Parties  may  raise  local  and  foreign  finance  in  accordance  with  regulations 
applicable to industry in general. 
• Non‐Muslims  and  non‐residents  shall  be  exempted  from  payment  of  Zakat 
(Islamic tithe) on dividends paid by the company. 

Regarding  Grid  Investment  Costs:  the  NTDC  incurs  the  full  cost  of  transmission 
interconnection  and  grid  strengthening  expenses  required  to  evacuate  electricity  from 
qualifying  RE  IPPs,  bear  any  of  the  expenses  associated  with  power  balancing  to 
accommodate priority dispatch and variability, and ensure that these expenditures are 
made in a timely fashion. 

Regarding Direct Sales: RE power producers are allowed to enter into direct (bilateral) 
sales  contracts  with  end‐use  customers.  For  direct  sales,  they  must  pay  ‘wheeling’ 
charges  for  the  use  of  the  transmission  and/or  distribution  grid  network  used  to 
transport  the  power  from  the  plant  to the purchaser. This  wheeling charge will reflect 
the  cost  of  providing  and  maintaining  the  transmission  interconnection,  including  the 
energy losses suffered en route, calculated on a utility‐wide basis by NEPRA. 

Regarding  Additional  Rents  from  Clean  Development  Mechanism  (CDM)  Under  the 
Kyoto  Protocol:  The  GoP  will  facilitate  project  application  for  carbon  credits  to  the 
extent possible. These credits are allocated based on a credit‐sharing mechanism among 
customers  (reduction  in  the  negotiated  tariff)  and  the  sponsors.  The  annual  carbon 
revenues are divided as follows: (a) an up‐front deduction is made for the administrative 
costs  of  the  joint  CER  management  mechanism;  (b)  an  amount  not  exceeding  that 
required to bring the IPP’s return on equity (ROE) to the level allowed by NEPRA shall be 
payable  to  the  power  purchaser;  and  (c)  the  remaining  revenues  shall  be  divided  in 
equal proportion between the IPP (as a ‘green credit’ for  enhancing the financial returns 
accruing to the project’s investors) and the power purchaser (as ‘green tariff’ support for 
lowering the per unit price of clean RE power.

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  163
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2.3.2 Specific Incentives by RE Technology 

Bagasse­based Cogeneration Projects 

Co‐firing  and  cogeneration  using  bagasse  has  been  in  practice  in  the  country’s  sugar 
mills  for  captive  energy  needs,  and  in  the  last  year  they  have  been  authorized  to  sell 
their  excess  electricity  to  the  grid.  Excepting  this  last  issue,  there  are  no  specific 
incentives  for  this  kind  of  technology;  all  cogeneration  projects  are  allowed  the  same 
incentives  and  facilities  as  applicable  to  all  other  IPPs  under  the  Policy  for  Power 
Generation Projects, 2002; basically, those listed under ‘General Incentives’ heading. 

These  kinds  of  projects  can  be  classified  as  ‘Captive  and  Grid  Spillover  Projects’; 
therefore, they are allowed to sell surplus power to the utility grid. These projects are 
allowed to be billed under a ‘Net Purchase and Sales’ provision in the RE policy, including 
net metering and some conditions for banking. As a matter of facts, these incentives are 
also available for any other RE, where applicable, such as the case of small hydros.  

At  present,  there  is  a  potential  of  around  3,000  MW  of  bagasse‐based  combined  heat 
and  power  (CHP),  much  of  which  could  be  sold  to  the  grid  each  year.  The  power 
generated by the sugar industry at some 83 mills in the country is purchased by NTDC or 
the  relevant  DISCO,  whichever  the  case  may  be,  at  competitive  rates  negotiated  and 
agreed between the two parties and approved by NEPRA. The net electricity supplied by 
the power producer to the utility in a month (i.e., units supplied by the producer minus 
units received by the producer, if greater than zero), is to be paid by the utility at a tariff 
equal  to  the  average  energy  cost  per  kWh  for  oil‐based  power  generation  (as 
determined  by  NEPRA  for  GENCOs/IPPs  over  the  applicable  quarter  of  the  year)  less 
10%.  The  energy  supplied  by  the  utility  to  the  power  producer  in  a  month,  (i.e.,  units 
received by the producer minus units supplied by the producer, if greater than zero), is 
to be paid by the producer at the applicable retail tariff (e.g., industrial or commercial 
rates, depending upon the type of user connection). Such net billing agreements require 
net metering arrangements that involve either separate sets of unidirectional meters for 
recording the electricity received and supplied to the utility by the power producer, or 
special bidirectional meters capable of instantaneously recording net power transfers.  

Additionally,  for  net  billing  purposes,  a  rolling  account  of  energy  units  is  to  be 
maintained on the pattern of a bank account. Such banking accounts of net energy units 
shall be maintained on a monthly basis and final balances will be reconciled at the end of 
the  year  at  the  rates  defined  in  the  previous  paragraph.  Under  this  arrangement,  a 
producer  may  generate  and  supply  power  to  the  grid  at  one  location  and  receive  an 
equivalent number of units for self use at a different or physically distant location on the 
grid  at  a  different  time  without  paying  any  wheeling  charges,  but  subject  to  some 
distance limits for power input and off take.  

Power cogeneration projects are treated as part of the sugar industry, but as separate 
entities for taxation purposes. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  164
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The consultants were informed that there is presently only one project in the pipeline 
for this type of energy sale, actually under processing by PPIB because its size (i.e., 120 
MW). The project is designed to run 4 to 5 months on bagasse and the rest of the time 
on coal—or eventually gas, if it is available. There is no up‐front tariff offered by NEPRA 
for  bagasse‐based  projects.  A  tariff  petition  by  the  Pakistan  Sugar  Mills  Association 
(PASMA)  has  been  presented  to  NEPRA  in  January  2008,  which  is  currently  being 
reviewed.  

Wind IPPs 

Risk Hedging­based Incentives 

Power dispatch and wind speed risk are completely allocated to the off‐taker in the case 
of wind IPPs. It is mandatory for the off‐taker to purchase all electricity available at the 
wind IPP’s outgoing bus bar and dispatch it to the system. Similarly, wind speed risk6 is 
absorbed by the power purchaser.  

 A  ‘Benchmark  Wind  Speed’  based  on  monthly  ‘Mean  of  Means’7  of  wind  speed  is 
determined  from  the  available  wind  data  for  a  given  wind  farm  site.  Annual/monthly 
energy production calculated for the farm corresponding to the benchmark wind speed 
stands  for  the  plant’s  ‘Benchmark  Energy  Production’,  and  the  corresponding  plant 
capacity is called its ‘Benchmark Capacity’. In practice the actual energy production and 
capacity may vary from these benchmark levels due to: (1) variation of wind speeds from 
the benchmark value (a factor beyond the control of the wind power generator), and (2) 
availability of the plant for electricity generation (within the control of the wind power 
generator).  The  principle  adopted  is  that  the  wind  IPP  should  be  made  immune  to 
factors which are beyond its control, but fully responsible for factors within its control. 
In  the  policy,  a  wind  risk  allocation  matrix  representing  this  principle  is  provided:  for 
wind speeds lower than the benchmark, the IPP is compensated; for wind speeds higher 
than the benchmark, a benefit sharing rule is applied. In both cases, however, the IPP is 
assumed be available for dispatch. To enable monitoring of wind speeds independently 
for  the  determination  of  actual  wind  speed  variations  during  the  IPP’s  operation, 
monitoring  masts  are  to  be  set  up  near  the  wind  farm  by  agencies  selected  and 
authorized by the AEDB. 

One  of  the  contentious  issues  with  this  arrangement  is  that  on‐ground  wind  speed 
measurements  are  carried  out  by  the  Pakistan  Meteorological  Department  (PMD)  at 
about  40‐plus  sites  in  the  south  of  the  country  using  30m  masts.  However,  these 
measurements  are  not  certified  to  industry  standards  and  can  at  best  be  used  for 
reference  purposes  only.  Site‐specific  wind  monitoring  has  been  independently 
conducted by several project developers to corroborate the PMD database as well as aid 
                                                       
6
  Important  to  note  that  the  policy’s  ‘wind  risk  cover’  only  provides  for  variations  in  wind  speed,  not  other 
parameters (e.g., wind direction, density, etc.) that can also affect a wind farm’s energy production. 
7
  Monthly ‘Mean of Means’ is the average of mean monthly wind velocities for a given month over a number of years 
for which reliable data are available. At a minimum, this will be based on at least three years’ data from the PMD 
wind  monitoring  mast  nearest  to  the  project  location.  Data  collected  at  a  certain  height  are  extrapolated  by 
standard formulae to the turbine height of the proposed wind farm. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  165
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

in  micrositing  turbines.  However,  this  introduces  additional  upfront  costs,  delays,  and 
uncertainties  in  estimating  project  feasibility  and  negotiating  tariffs,  which  can 
jeopardize project financing and development. 

Economic Considerations 

The  AEDB  has  been  primarily  concentrating  on  facilitating  wind  IPPs  in  the  so‐called 
‘wind corridor’, extending from Keti Bandar to the east of Karachi on the southern coast 
to several hundred kilometers inland to Gharo towards the north‐east in Sindh province, 
where  wind  speeds  are  high  but  which  is  also  in  proximity  to  the  national  power  grid. 
Projects  in  these  areas  therefore  have  to  compete  with  established  efficient 
conventional  generators  (e.g.,  combined  cycle  gas  turbines),  which  makes  any 
preferential tariff treatment and additional grid interconnection costs questionable from 
the  power  purchasing  utility’s  perspective.  It  also  detracts  from  possible  more 
economically  feasible  wind  sites  being  properly  investigated  elsewhere,  such  as  along 
the coastline or inland Balochistan, where the net avoided costs as well as social benefits 
of wind‐based electricity generation could be an order of magnitude higher, even with 
somewhat  elevated  project  development  costs.  Thus,  the  AEDB’s  strategy  of 
concentrating  on  wind  power  exclusively  within  the  competitive  mainstream  national 
power  sector  versus  more  insulated  peripheral  regional  power  markets  merits 
reconsideration. 

Tariff Incentives 

As stated before, under the current short‐term RE policy, the tariff for sale of electricity 
from a wind IPP can be arrived through three alternative mechanisms: 
• Competitive bidding (solicited proposals) 
• Negotiations (unsolicited proposals) 
• Up‐front8 tariff‐setting. 

Regarding  the  bidding  process,  it  may  be  structured  along  either  of  the  following  two 
options: 
• Bidders may be required to submit their competitive proposals for the tariff 
• A  benchmark  tariff  may  be  offered  up‐front,  and  bidders  invited  to  quote  a 
discount on the benchmark price. 

However,  until  now,  the  competitive  bidding  approach  on  power  tariffs  has  not  been 
utilized  by  the  GoP  for  RE  IPPs.  However,  the  other  two  alternatives  have  been 
employed  (negotiated  and  up‐front  tariffs).  For  instance,  in  the  Guidelines  for 
Determination  of  Tariff for  Wind  Power  Generation  issued  by  the  government,  general 
conditions and references on the key parameters employed in tariff computation have 
been defined . Consequently, on the one hand, NEPRA has established an up‐front tariff 

                                                       
8
  In GoP parlance, the terms ‘up‐front tariff’ and ‘indicative tariff’ are used interchangeably. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  166
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

in  US$ 95/MWh;  on  the  other,  there  have  been  several  tariff  petitions  by  sponsors 
proposing payments ranging from US$  100 to 115/MWh, some of these petitions have 
been  assessed  and  approved  by  NEPRA  with  only  slight  rate  modification.  Until  now 
there have been four formal wind IPP tariff petitions filed with the regulator, and three 
of them have received final approval by NEPRA. 

Exhibit 1 summarizes the parameters employed by NEPRA in its computation of the up‐
front wind power tariff as well as tariffs petitioned for by these four wind IPPs. 
Exhibit 1: Approved Wind IPP Tariffs 
Upfront Tariff WinPower Green Power Beacon Energy Zorlu Enerji

Date of Petition Jan. 2007 Feb. 2007 May 2006 Oct. 2006 Apr. 2007

50.6 MW 49.5 MW 48.6 MW


5 MW
Installed Capacity Up to 50 MW (22 x 2.3 MW (33 x 1.5 MW (27 x 1.8 MW
(Enercon WTGs)
Nordex N90 WTGs) GE/Skoda WTGs) Vestas V90 WTGs)

Net Load Factor 31.5% 31.8% 31.5% 40.4% NA

Generation
133.4 141.0 133.4 172.1 NA
(GWh/Year)
Gharo-Keti Bandar Khuti Kun, Mirpur
Location Gharo Creek area NA NA
Corridor Sakro, Thatta

Contract Type BOO BOO BOO BOO NA

Operational Life
20 20 20 20 NA
(Years)
Capital Structure
80:20 80:20 80:20 75:25 NA
(Debt:Equity)
Equipment
Investment NA 1,379 NA 1,545 NA
(US$/kW Installed)
Total EPC
Investment NA 1,952 1,523 2,358 NA
(US$/kW Installed)
Total Investment
Approx.
Cost 2,195 1,750 2,641 NA
1,900
(US$/kW Installed)
OpEx (O&M,
Approx.
Insurance, etc.) 98.8 44.0 58.8 NA
45
(US$/kW Installed)
10y + 1y (Grace)
10y LIBOR + 300 10y + 1y (Grace) 10y + 2y (Grace)
Debt LIBOR + 250-300 NA
BPs LIBOR + 350 BPs LIBOR + 500 BPs
BPs
Real ROE Net of
15% 15% 15% 15% NA
Withholding Tax
Carbon Credit
NA 50:50 100:0 50:50 NA
Sharing Ratio
Petitioned Levelized
NA 109.2 100.2 115.9 104.6
Tariff (US$/MWh)
NEPRA-Approved
Levelized Tariff 95 107.8 NA Pending NA
(US$/MWh)
Reference FX
NA 1.34 1.20 1.28 NA
(US$/€)
Reference FX
61.0 61.0 59.7 60.0 NA
(Pak Rs./US$)

Reference LIBOR 5.4% 5.4% 5.0% 5.4% NA

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  167
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

It  is  important  to  mention  that  the  regulator  has  decided  to  allow  an  incentive  of 
US$ 10/MWh,  in  addition  to  the  negotiated  levelized  tariff,  to  those  IPP  sponsors  who 
can achieve COD within 24 months of tariff determination, or June 30, 2009, whichever 
occurs earlier. 

Other  incentives  are  related  to  the  allowance  for  suitable  (complete)  indexation. 
Generally speaking, negotiated tariff are allowed to be adjusted by changes in financing 
terms (i.e., LIBOR), inflation (i.e., US CPI & US WPI), and foreign exchange risks (i.e., Pak. 
Rs./US$ and/or €/US$ rates), both during the construction period and post‐COD. 

Additionally, If the IPP succeeds in arranging improved financing terms by the time the 
project  achieves  financial  close,  the  overall  impact  of  the  reduced  debt  servicing 
requirement  shall  be  shared  in  the  following  ratio  60:40  (power  purchaser:IPP). 
However, for projects opting for the up‐front tariff, no such sharing will be required and 
the  project  sponsor  shall  be  entitled  to  retain  the  full  benefit  of  any  concessional 
financing obtained below the prescribed interest ceiling. 

Small Hydro IPPs 

As mentioned earlier, the focus of this paper is restricted to small‐scale hydel, defined as 
hydropower stations of capacity equal to or below 50 MW. There are two different set 
of complementary polices currently in place for these kinds of projects: the short term 
national‐level RE policy, which replicates provisions on offer to wind‐based IPPs to small 
hydros, and provincial policies.9 

National Level 

Risk Hedging­based Incentives 

In relation to one of the main risks typically faced by a hydel project, i.e., hydrological 
risk, the national policy is basically a direct translation of the rules providing for wind risk 
cover  to  wind  power  projects.  Hydrological  risk  is  defined  as  the  risk  of  variability  of 
water  flows  in  the  channel  on  which  the  plant  is  sited,  and  therefore  of  the  effective 
energy output of the hydro IPP. Under the current RE policy, this risk is absorbed by the 
power  purchaser.  Similar  to  the  case  of  wind  IPPs,  an  assessment  of  this  ‘Mean 
Flow/Month’,  based  on  monthly  average  water  flow,  is  determined  from  available 
hydrological data. This entails determining mean water flows from the data collected at 
certain specified points upstream of the plant location. Energy production corresponding 
to the mean flow rate is termed ‘Mean Flow Energy Production’. In practice the actual 
energy production and capacity may vary from the mean flow levels due to: (1) variation 
of water flow from the mean flow/month (a factor beyond the control of hydroelectric 
power generator), and (2) availability of the plant for electricity generation (within the 
control of hydroelectric power generator). The principle adopted is once again that the 
hydroelectric  generator  will  be  made  immune  to  factors  which  are  beyond  its  control, 

                                                       
9
  The provinces are independently empowered to set policies and to process and implement power projects based 
on both conventional and renewable technologies up to a capacity limit of 50 MW. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  168
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

but  fully  responsible  for  factors  within  its  control.  In  the  same  way  as  for  wind  risk,  a 
matrix  for  the  allocation  of  hydrological  risk  is  defined  in  the  national  policy  based  on 
exactly the same rationale. 

To enable monitoring of water flow independently, monitoring sensors are to be set up 
by the relevant agency (i.e., AEDB, provincial, or AJK/NA entity) with properly calibrated, 
automated  sensors  and  dataloggers.  The  monitoring  sensors  are  to  be  sited  at  the 
nearest location upstream of the plant site where the total water flow to pass through 
the proposed plant’s turbines is available. 

Additionally,  a  ‘water  use  charge’  is  payable  by  the  hydro  IPP  to  the 
provincial/AJK/Northern  Areas  administration  for  the  use  of  water  resources  by  the 
project  to  generate  electricity.  The  water  use  charge  is  currently  fixed  at  Rs  0.15/kWh 
and is adjustable annually for inflation 

Tariff Incentives 

As described for wind IPPs earlier, the tariff for sale of electricity from a hydel IPP can 
also be arrived at through three alternatives methods: 
• Competitive bidding (solicited proposals) 
• Negotiations (unsolicited proposals) 
• Up‐front tariff‐setting. 

Provincial Level 

The provinces/AJK10 co‐administer investments for power projects and act as the main 
drivers  and  facilitators  in  this  regard.  There  are  six  provincial  institutions  currently 
engaged in the small hydel power sector in different regions of the country: 
• Sarhad Hydel Development Organization (SHYDO): In 1986, the Government of 
NWFP  established  SHYDO  for  carrying  out  hydropower  prospecting  and 
development,  and  to  act  as  a  utility  company  for  isolated  rural  communities  in 
the mountainous areas of the province. With the assistance of WAPDA and GTZ, 
SHYDO has prepared a master plan for the development of NWFP’s hydropower 
potential. SHYDO has identified a hydroelectric potential of more than 6,000 MW 
based  on  such  small  schemes,  and  has  completed  feasibility  studies  of  several 
projects ranging in capacity from 8 MW to 125 MW.  
• Punjab  Power  Development  Board  (PPDB):  PPDB  was  created  in  Punjab’s 
Irrigation  Department  in  1995  for  the  promotion  of  hydropower  generation 
through  the  development  of  hydel  power  stations  on  canal  sites  in  Punjab.  At 

                                                       
10
  The  Northern  Areas  (NA)  and  the  Federally  Administered  Tribal  Areas  (FATA)  do  not  fall  under  the  purview  of 
provincial/AJK governments but are administered directly by the federal government. Provincial‐level policies are 
thus  applicable  only  to  the  respective  provinces  of  the  Punjab,  Sindh,  Northwest  Frontier  Province  (NWFP),  and 
Balochistan.  Azad  Jammu  and  Kashmir  (AJK)  represents  an  autonomous  region also  empowered  to  enact  its  own 
state‐level policy and regulatory framework for projects up to 50 MW. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  169
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

different  canals,  about  324  potential  sites  of  medium‐  and  low‐head  were 
identified, with a total estimated potential capacity of 5,895 MW. 
In  2007,  the  PPDB  was  transformed  into  the  newly‐created  Punjab  Power 
Development  Company  Limited  (PPDCL),  registered  as  an  autonomous 
corporate  body  with  its  own  board  of  directors,  to  develop  and  execute  actual 
hydro projects through government, multilateral, and public‐private partnership. 
• Irrigation  &  Power  Department,  Sindh  (IPDS):  IPDS  is  responsible  for  hydel 
development  and  identification  of  different  hydropower  sites  on  canals  and 
barrages in the Sindh province.  
• AJK  Hydro  Electric  Board  (AJK  HEB)  and  AJK  Private  Power  Cell  (AJK  PPC):  the 
Government of AJK established the AJK HEB in 1989 to implement public sector 
hydropower projects. Additionally, with the intention of providing a one‐window 
facility  and  to  encourage  investment  by  private  developers,  the  AJK  Private 
Power Cell was set up in 1995. 
• Northern  Areas  Public  Works  Department  (NAPWD):  NAPWD  was  established 
with  the  responsibility  for  the  generation  and  distribution  of  electricity  in  the 
mountainous and remote Northern Areas which is currently not connected to the 
national power grid. NAPWD has constructed various mini hydel power stations 
in the region and has built 11 KV lines for the transmission of electric power to 
local towns and communities.  

As  a  consequence  of  the  work  of  these  institutions,  more  than  2,000  MW  of  small‐
scale11 hydro projects have been identified (i.e., feasibility and/or pre‐feasibility studies 
carried out). Additionally, these institutions have released guidelines for hydel projects 
in their respective jurisdictions; in 2005, both SHYDO and PPDB issued their own policies 
in  this  regard.  The  policies  are  quite  similar  and  are  based  on  negotiated  tariffs,  but 
without  sufficient  details  provided  for  unambiguously  determining  tariffs  for  hydel 
projects.  They  seem  to  be  derived  from  the  same  logic  used  for  thermal  or  wind 
projects.  However,  for  storage‐type  hydel  plants,  a  more  sophisticated  pricing 
methodology  is  required.  Nevertheless,  the  projects  that  are  in  the  pipeline  for 
development  are  mostly  of  the  run‐of‐river  type,  so  that  this  deficiency  is  not  an 
important issue for now. 

Though private participation is encouraged, most of the small hydro projects in Pakistan 
have  so  far  been  developed  by  provincial  public  institutions.12  Recently,  The  ADB  has 
allocated a first tranche of US$ 110.4 million loan for development by the public sector 
of eight small hydro plants in the NWFP and Punjab regions. The levelized tariff of these 
projects and their main characteristics are provided in Exhibit 2 below. 

                                                       
11
  And approximately 30,000 MW of medium to large hydels. 
12
  With  the  exception  of  some  community‐owned  microhydels  developed  by  NGOs  (e.g.,  AKRSP  in  the  Northern 
Areas). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  170
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 2: Reference Small‐Scale Hydel Projects (ADB REDSIP Tranche I) 

Province | Punjab | NWFP |


Total/
Deg Daral Average
Location Marala Chianwali Pakpattan Okara Machai Ranolia
Outfall Khwar
Installed Capacity
7.2 5.4 5.0 3.2 4.0 2.63 36.6 11.5 75.5
(MW)
Total Investment
2,260 2,185 2,037 2,281 2,700 1,807 2,700 2,700 2,529.5
(US$/kW)

Plant Factor 77.0% 68.0% 66.5% 80.9% 78.8% 59.4% 62.7% 60.2% 66.3%

FIRR 8.6% 8.1% 7.1% 9.1% 6.7% 8.4% 9.0% 11.8%

Levelized Tariff
38.8 40.2 43.2 37.3 44.8 40.3 37.4 21.4 36.5
(US$/MWh)
Reference FX
60 60 60 60 60 60 60 60 60
(Pak. Rs/US$)

Other RE Sources 

There  are  no  specific  policies  currently  in  place  for  other  RE  sources,  such  as  solar 
thermal,  photovoltaic,  biogas,  waste‐to‐energy,  etc.;  only  isolated  demonstration  or 
pilot‐scale projects outside a consolidated framework have been developed or are under 
implementation. 
• USTDA  has  recently  issued  an  RFP  for  conducting  a  municipal  solid  waste‐to‐
energy feasibility assessment for Karachi. Previously, the World Bank undertook 
a similar assessment for Lahore, but later shelved its plans to fund such a plant.  
• Currently, the New Zealand government is funding a pilot cattle dung gasification 
facility in Landhi, Karachi, which could eventually be scaled up to fire 35 MW gas 
turbine.  
• The GoP recently introduced E10 gasoline sales on a very limited, experimental 
scale,  with  plans  to  increase  volumes  utilizing  ethanol  produced  by  the  sugar 
industry which is currently being almost entirely exported. 

3 Performance of the Short­term RE Policy 
3.1 Overall Performance 

Despite the fact that one and a half year is a very short time to evaluate the adequacy of 
a policy,13 the results achieved so far cannot be qualified as satisfactory. In particular:  
• No new RE power projects have yet materialized under this policy up to now and 
no  projects  are  currently  under  construction,  although  some  wind  and  small 
hydro IPPs are in advanced stages of negotiations. 

                                                       
13
  RE  projects  typically  require  a  relatively  long  time  to  mature  and  reach  the  final stage of financial closure before 
starting construction.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  171
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• No  investor  has  so  far  accepted  the  up‐front  wind  power  tariff  proposed  by 
NEPRA  under  this  policy,  opting  instead  to  petition  for  individually  negotiated 
tariffs. 
• No tender has been launched to develop RES projects (‘solicited proposals‘) and 
none is expected to be launched imminently. 
• In implicit recognition of the failure of wind IPPs to materialize, the GoP is now 
seriously considering undertaking wind farm development in the public sector. 
• Many  of  the  facilities  offered  by  the  policy  to  RE  developers,  such  as  carbon 
financing, net power sales and purchase, banking, and grid interconnection rules, 
have yet to be operationalized. 
• Institutional capacity at both the federal and provincial levels for processing and 
promoting RE investments in line with policy guidelines remains underdeveloped. 

On the other hand, during recent months there have been advances in some areas (or 
projects)  which,  eventually,  can  permit  the  current  situation  to  improve  somewhat  in 
the near future. Among them are:  
• About  70  LOIs  for  the  development  of  pre‐feasibility  studies  of  wind  projects 
have been signed by the AEDB. It is possible that some of these projects may be 
implemented  in  the  future,  although  no  time  constraint  or  element  of 
competition exists for project sponsors to do so. 
• Three  wind  power  projects  have  petitioned  for  tariff  determination  to  NEPRA 
and  obtained  its  final  decision.  At  least  one  of  them  is  progressing  towards 
financial closing.  
• Zorlu Enerji, Turkey, has expressed its intention to construct a 50 MW wind farm 
in the Gharo‐Keti Bandar corridor and have applied for tariff to NEPRA (decision 
still pending). AEDB indicated this project has good chances to materialize as the 
sponsor has ready access to wind turbines.  
• The ADB has a pledged a US$ 500 million public sector loan facility for RE projects 
in Pakistan, and allocated a first tranche of about US$ 130 million for eight small 
hydro schemes in the Punjab and NWFP. A more comprehensive policy and tariff 
regime for the projects to operate under is expected to be in place before start 
of construction. Discussions for the allocation of the second tranche are currently 
underway, consisting mostly of hydro schemes in the Northern Areas. 
• Some  sporadic,  initial  efforts  are  also  underway  for  policy  and  tariff  review  for 
mini/micro hydro and biomass conversion projects, and these are expected to be 
co‐opted into the medium‐term policy development framework. 

In order to identify the strengths and weaknesses of current short‐term RE policy regime 
in  Pakistan,  the  reasons  of  its  relatively  limited  success  thus  far  are  further  analyzed 
below.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  172
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.2 Stakeholders Views  

As was stated in the Inception Report, the medium‐term RE policy development process 
is  expected to  rely  on  extensive  consultations  with  key  stakeholders,  including,  among 
others,  various  relevant  government  agencies  and  regulatory  bodies,  utilities,  power 
producers,  private  industry,  community  and  non‐governmental  organizations,  financial 
institutions, and donor agencies. During the project mission conducted at the beginning 
of  November,  the  Consultants  have  met  with  representatives  from  these  agencies  as 
well  as  key  members  of  the  Project  Consultative  Group  (PCG)  and  potential  private 
investors. 

3.2.1 Alternative Energy Development Board (AEDB) 

Meetings were held with several staff members from AEDB, mainly in the areas of power 
generation from wind and biomass conversion. AEDB confirmed that the only current RE 
projects are small off‐grid hydro power plants constructed on river tributaries and canals 
in northern Pakistan. Unfortunately, no new RE projects have yet materialized under this 
policy  since  it  was  announced  in  December  2006,  although  some  wind  IPPs  are  in 
relatively  advanced  stages  of  negotiations  as  mentioned  earlier.  Some  initial  effort  is 
also  underway  for  policy  and  tariff  review  for  hydro  and  biomass  projects,  but  it  is 
expected  that  most  of  these  deliberations  will  feed  into  the  medium‐term  policy 
development  work.  As  far  as  grid‐connected  RE  power  generation  is  concerned, 
therefore,  the  AEDB  has  been  largely  focused  on  wind  IPP  development  since  its 
inception in 2003, a strategy that may require balancing and broadening in the context 
of the medium term, particularly given the difficulties faced so far in this area as well as 
the economic potential of other RES that also merit serious attention. 

Regarding wind generation, AEDB summarized the problems encountered in the cases of 
the most advanced and protracted IPP negotiations (WinPower and Green Power); these 
problems mirror the views of the developers as well (see below). Two other developers 
that were also prominent in these discussions were Beacon Energy and Zorlu Enerji. The 
case of BE, despite belonging to the group of first movers, currently is at the lowest rank 
in  the  pipeline  and  will  probably  be  discontinued.  On  the  other  hand,  ZE,  a  Turkish 
investor  with  no  local  partner,  has  recently  decided  to  install  5  MW  of  initial  capacity 
and,  although  it  has  no  generation  license  and  approved  tariff,  the  probability  of  its 
successful  commissioning  of  this  farm,  later  to  be  expanded  to  50  MW,  is  high  as  the 
sponsor has access to the wind turbine generators (WTGs) and has even shipped some 
to Pakistan. 

Both the AEDB and investors consider that the negotiation of a tariff in the context of a 
continuously  increasing  price  of  WTGs  in  the  international  market  (along  with  long 
delivery schedules due to high global demand) is the mayor obstacle for realizing short‐
term policy objectives in relation to wind generation. The AEBD supports the investors’ 
view that Euro indexation of the tariff should be allowed, because it is the main driver 
for  cost  increases  on  account  of  most  wind  turbine  equipment  being  of  European 
manufacture. That means that until now, reference prices for WTGs have been European 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  173
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

ones, which make sense, especially as other large non‐European turbine manufacturers, 
such as India’s Suzlon, are not active in Pakistan. 

As for bagasse‐based power cogeneration, the AEDB states that short‐term potential is 
about 500 MW and the main challenge is to switch from low pressure to high pressure 
boiler technology and to increase bagasse availability beyond the current 4 to 5 months. 
Unfortunately,  complementation  with  other  sources  of  biomass,  such  as  rice  husks,  is 
not easy due to logistical constraints and because, in some cases, there is no surplus left 
over from alternative uses (such as in paper and particle board manufacture). Therefore, 
coal or gas are required as fuel for the rest of the year in order to make bagasse projects 
profitable, but indigenous gas and coal are becoming scarce and their availability cannot 
be assured. 

Unfortunately, no accurate data about the exploitable potential for biomass and biogas 
use in Pakistan exists. It is assumed that potential for sewage gas is large—mostly in the 
food  industry—but  this  must  be  confirmed  by  more  detailed  studies.  Other  relevant 
sources  include  municipal  solid  waste‐to‐energy,  though  only  30%  of  garbage  is 
currently collected by urban municipalities (free service, no tipping charges apply) or by 
some private collectors. Basically, all garbage is accumulated in open dumps, which is a 
major environmental concern. The AEBD has stated that it is initiating some studies to 
evaluate these potentials more accurately. 

Despite  some  specific  regulation  for  bagasse‐based  cogeneration,  regulation  for  the 
other  biomass/biogas  generation  sources  is  practically  inexistent.  The  AEDB  has 
requested  the  consultants  to  widen  the  scope  of  biomass  and  biogas  in  the  medium‐
term policy, taking care not to encourage an undesired effect on food prices due to crop 
substitution and diversion. 

3.2.2 National Electric Power Regulatory Authority (NEPRA) 

Meetings  were  held  with  the  Acting  Chairman,  Director  Tariffs,  and  Technical  Adviser, 
NEPRA.  According  to  the  NEPRA  Act,  1997,14  this  regulatory  institution  is  the  only  one 
entitled  to  set  tariffs  for  any  kind  of  grid‐connected  power  generation,  either 
conventional  or  renewable.  The  tariffs  approved  for  renewable  energy  projects 
(especially  wind  projects)  have  been  determined  following  the  guidelines  indicated  in 
the  Policy  for  Development  of  Renewable  Energy,  2006  and  using  project‐specific  data 
provided by individual petitioners.  

An up‐front tariff has been approved for IPPs using wind energy, based on data provided 
by  the  developers  and  international  benchmarking.  However,  up  to  now,  no  projects 
have  been  proposed  based  on  this  up‐front  tariff  (US$ 95/MWh).  NEPRA  considers  it 
unsuitable to determine an up‐front tariff for hydel projects, since these projects have 
large site‐specific differences, and therefore their costs differ significantly; however, GTZ 

                                                       
14
  Regulation  of  Generation,  Transmission  and  Distribution  of  Electric  Power  Act,  1997,  Government  of  Pakistan, 
Islamabad. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  174
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

has proposed introducing feed‐in tariffs for small hydros of less than 5 MW capacity on 
which NEPRA has yet to rule.  

It  was  remarked  by  the  regulator  that  there  were  several  problems  faced  by  it  while 
determining tariffs for wind projects, mainly related with the absence of firm prices for 
the  turbines  and/or  EPC  contractors.  NEPRA  considers  that  tariffs  for  future  projects 
should be determined based on actual EPC contract information and not on budgetary 
(or estimated) data.  

Regarding  bagasse‐based  cogeneration,  it  was  stated  that  the  sugar  industry  is  also 
trying to get an up‐front tariff determination from NEPRA. Until such time that this tariff 
is  determined,  cogeneration  projects  can  enter  into  bilateral  agreements  with 
distribution  companies  at  a  price  not  higher  than  the  reference  price  approved  by 
NEPRA for that distributor. 

NEPRA considers that, due to the electricity shortages expected in 2008 (estimated  to 
be  10‐12%  of  total  energy  demand),  the  most  important  challenge  is  to  increase 
generation  capacity  at  affordable  costs  (cheapest  possible  generation)  and  to  ensure 
that  this  capacity  will  be  available  during  peak  demand.  Wind  power  does  not 
necessarily match either of these two conditions.  

Other comments included:  
• Although NEPRA was involved in the development of the 2006 RE policy, several 
of its views were not accepted.  
• For  wind  energy,  it  considers  that  feed‐in  (or  up‐front)  tariffs,  with  all  the  risks 
allocated to the developer, is a more adequate mechanism than the existing one 
(where some of these risks are allocated to the purchaser).  
• Tendering  some  renewable  energy  projects  (either  wind  or  hydel)  could  be  an 
interesting mechanism to reveal actual prices for this kind of projects as well as 
to foster their implementation.  
• The  RE  policy  should  be  transformed  into  a  Law  to  provide  necessary  legal 
protection  to  the  investors.  A  policy  by  itself,  which  may  change  from  time  to 
time, does not provide the same level of protection.  

3.2.3 Private Power and Infrastructure Board (PPIB) 

Despite it being a very qualified agency for developing power generation, our interest in 
the  PPIB  was  limited  because  only  large  renewable  projects  fall  within  the  agency’s 
scope, basically large hydel and cogeneration (over 50 MW).15 However, as the PPIB has 
compiled what is arguably the most complete hydel potential assessment for Pakistan, 
the consultants focused discussions on this subject. 

                                                       
15
  In a recent amendment, AEDB has been authorized to process all wind IPPs, including those of capacity greater than 
50 MW. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  175
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The PPIB stated that the GoP aims to develop hydel projects, mostly medium size that 
are easier to develop. A PPIB report16 estimates the total small‐scale hydel potential in 
the country at about 2,000 MW, and up to 30,000 MW for medium‐ to large‐scale hydro. 
The  average  investment  cost  that  the  PPIB  employ  in  its  analysis  is  around 
US$ 1,250/KW‐installed. 

The PPIB has mentioned the importance of conducting feasibility studies for developing 
hydel, mostly large ones, as it represent a major barrier for private investors.17 The PPIB 
is  initiating work  on  this  aspect,  setting  criteria  to  prioritize  sites  to  be  developed:  the 
first priority is to be given to sites that are 1) are near the load centers, 2) are easy to 
access and build upon, 3) allow 50 MW to 500 MW of capacity to be installed, and 4) are 
preferably run‐of‐river projects. 

3.2.4 Developers (Private Investors) 

The consultants maintained meetings and conversations with two potential wind power 
IPP developers (Green Power and WinPower) and a hydel IPP developer (Laraib Energy).  

In  both  the  wind  IPP  cases,  the  project  developers  identified  NEPRA  tariff  decision‐
making as the key obstacle for the successful commitment of their projects. They were 
of  the  opinion  that  NEPRA  is  not  fully  cognizant  of  the  peculiar  characteristics  and 
dynamics  of  the  renewable  energy  resource,  technology,  and  costs,  and  consequently 
several problems arise during tariff negotiations. They also consider that the regulation 
related  with  CERs  is  relatively  new,  and  in  order  to  trade  in  them  it  allocates  tasks  to 
governmental institutions, introducing additional risks to the investors.  

The allowed IRR (15%) is considered relatively low if compared with other technologies 
that they perceive to be less risky. The indicated a willingness to accept such returns if 
several  other  risks,  in  addition  to  the  average  wind  speed  risk,  were  also  provided  for 
(i.e., wind direction, variability, etc.) 

They  consider  that  having  a  simple  feed‐in  tariff  for  wind  power,  if  adequately 
calculated, would be more convenient and allow them to better manage all associated 
risks.  

Other problems mentioned were: 
• The  time  required  by  NEPRA  to  take  decisions  about  tariffs  (six  months)  is  too 
long,  and  creates  problems  for  the  investors  (difficulties  to  close  firm  contracts 
with the EPCs) 

                                                       
16
  Pakistan Hydel Power Potential, Private Power and Infrastructure Board (PPIB), Government of Pakistan, Islamabad 
(Undated). 
17
  Similarly, the need for having bankable feasibility studies readily available for small hydro investment consideration 
was  also  highlighted  under  the  Asian  Development  Bank’s  US$ 500  million  Pakistan  Renewable  Energy 
Development Sustainable Investment Program (REDSIP), the lack of which is seriously constraining annual tranche 
allocation and disbursement.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  176
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• The standardized documents included in the security package (in particular, the 
PPA and the IA) were only finalized very recently, and will require further review 
by international legal specialists before being deemed acceptable by developers.  
• The grid code is not fully adapted to wind power plants, since it was developed 
based  on  conventional  technologies  (thermal  and  hydel),  and  needs  to  be 
suitably modified. 
• Currently,  to  close  an  agreement  with  a  WTG  supplier  is  becoming  increasingly 
difficult  due  to  a  surge  in  worldwide  demand  as  well  as  perceived  risks  by 
manufacturers  in  entering  new  markets  such  as  Pakistan.  Most  reputable 
manufacturers only assure deliveries for 2010/2011. To obtain wind turbines in 
the short term (e.g., less than six months) is practically impossible.  

Both developers stated that the help provided by AEDB to them was very valuable, but 
that the agency itself was also on the learning curve.  

Regarding  hydel,  Laraib  Energy  Limited  is  developing  the  New  Bong  Escape  hydro 
project, the first medium‐size hydel IPP. This is an 84 MW project, with 25% of financing 
provided by the ADB under its private sector lending program. This project is based on 
the  earlier  1995  power  policy  focusing  on  hydel  projects,  and  its  processing  started 
before  2002.  Recently,  it  has  reached  financial  closure  and  obtained  necessary 
regulatory licenses to proceed with construction, which is scheduled to start shortly.  

Important comments provided by this developer were:  
• It  considers  1995  power  policy  much  better  than  the  2002  one.  The  new  one 
covers  only  60%  of  hydraulic  risk,  compared  to  the  full  cover  provided  by  the 
previous one. 
• As this was the first private hydel project, no formal implementation documents 
previously  existed.  Therefore,  it  took  a  significant  amount  of  time  to  prepare 
them.  
• As  AJK  (where  the  project  is  located)  is  an  autonomous  region,  the  guarantees 
were need to be provided by the state government. However, the Government 
of AJK was not able to provide adequate guarantees and neither was the NTDC in 
a position to enter into power purchase agreement, since the plant is outside of 
its territorial jurisdiction. The problem remains unresolved to this moment.  
• The tariffs approved by NEPRA for this project is US$ 58.9/MWh. 

3.2.5 Developers (State­owned Investors) 

The  newly‐formed  Punjab  Power  Development  Company  Limited  (PPDCL)  has  the 
authority  to  approve  and  develop  hydel  projects  of  up  to  50  MW  capacity.  A  Project 
Management  unit  has  recently  been  established  to  process  such  projects,  as  a 
prerequisite for the ADB’s REDSIP program, and a total of 140 MW has been identified 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  177
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

for future development at different canal‐based sites;18 there are several more projects 
in the pipeline for which the PPD is planning to conduct feasibility studies. It seems that 
some  local  investors  (industrial  groups)  are  interested  in  taking  up  such  projects;  as 
matter of fact, many of them have been registered for this purpose. The main features 
of these projects are:  
• Project selection criteria are similar to that of the PPIB,  
• The power off‐taker is WAPDA (DISCO), and  
• Site locations are easy to access and construct upon.  

According  to  the  PPDCL’s  experience,  the  average  investment  costs  for  these  projects 
are  on  the  order  of  US$ 2,200/KW  and  typical  time  for  construction  ranges  from  four 
years for small hydel to six years for medium‐ to large‐scale ones, with lack of financing 
being  the  single  most  important  impediment  to  project  implementation.  Fortunately, 
the ADB is willing to fund PPDCL in at least some of these projects. 

The PPD has made a list of recommendations for the development of hydel projects at 
the provincial level: 
• Provincial  authorities  should  provide  single‐window  facilities,  in  close 
cooperation with the AEDB (similar to the PPIB) because federal administration 
can be problematic for small, dispersed projects 
• An up‐front (feed‐in) tariff should be proposed 
• The tariff should be: 
o Different for low‐ and high‐head hydel projects 
o Based on two‐part (energy and capacity) tariff approach 
• Fees and procedures must be simplified for very small projects (e.g., less than 5 
MW) 
• Standardization  of  hydel  turbines  and  related  equipment  to  foster  local  O&M 
suppliers should be encouraged 
• Easy  financing  for  small  projects  is  an  essential  requirement  and  must  be 
provided 
• Off‐grid local distribution networks (‘mini‐grids’) need to be encouraged. 

3.2.6 Other Institutions Involved in RE Development 

The  German  technical  assistance  agency,  Gesellschaft  für  Technische  Zusammenarbeit 


GmbH (GTZ), has been associated, very actively, in small hydro development in Pakistan 
since 1983. It has been extensively involved with WAPDA in undertaking a hydropower 

                                                       
18
  With five projects totaling 24.8 MW being implemented in the Punjab under the first tranche of the ADB’s REDSIP 
facility. An additional three projects of 50.73 MW capacity are also being financed under this tranche in the NWFP. 
See Exhibit 2 for details. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  178
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

inventory and related data collection. Several pre‐feasibility studies were also developed 
under this initiative.  

Currently its efforts are concentrated in the electrification of rural areas using renewable 
energy, in close cooperation with AEDB. GTZ’s Hydropower Promotion Programme (HPP) 
has  the  goal  of  developing  hydropower  cost  effectively,  while  mitigating  any  negative 
social and environmental aspects. Most of the projects included in this program consist 
of off‐grid schemes.  

GTZ is also heavily engaged in the development of solar projects (also mainly in the rural 
areas), promoting the use of solar water heaters (geysers) in the residential sector, and 
in energy conservation projects.  

4 Consultants’ Views on Current Short­term RE Policy 
Having summarized the opinions of different stakeholders on the short term RE policy, 
as well as providing a brief assessment of the actual results obtained so far through the 
implementation of this policy, it is possible to respond to a range of questions that need 
to  be  addressed  before  a  medium‐term  renewable  energy  policy  for  the  country  is 
defined.  The  consultants  will  take  these  issues  into  account  in  the  subsequent  policy 
recommendations to be made to the Government of Pakistan for the medium‐term on‐
grid RE power policy. 

Is the limited success of the short term policy a matter of  ‘insufficient implementation 
time’ (in the sense that projects typically require a longer maturity period), or are there 
important  structural  barriers  which  have  prevented  the  objective  of  rapid  RE 
deployment to be achieved? 

As has been previously mentioned, one and a half years is not adequate time on which 
to base a definitive diagnosis of a policy’s efficacy upon. Several projects are currently at 
their ‘maturity’ stage, and therefore additional time should be allowed before evaluating 
their  ultimate  fate.  However,  several  symptoms  exist  that  indicate  there  currently  are 
several concerns that merit attention, and that these issues can at least partially explain 
why the development of RES in Pakistan is not progressing as was expected:  

• Regardless  of  the  relatively  large  number  of  LOIs  that  have  been  signed  with 
private  developers  to  conduct  feasibility  studies  of  wind  projects,  only  four  or 
five  have  reached  a  state  where  they  can  be  considered  serious  commercial 
projects;  one  of  them  has  practically  abandoned  the  idea  of  constructing  the 
plant,  two  others,  although  formally  progressing,  are  experiencing  significant 
difficulties and only one (Zorlu Enerji) has a real possibility of being implemented 
in  the  near  future.  Interestingly,  this  is  the  only  international  wind  IPP  in  the 
market, the rest of the proposed projects being locally sponsored. It appears that 
the excessive number of LOIs signed by potential investors with the AEDB relates 
more to a strategy of  ‘locking interesting sites’—seeking the possibility of a more 
interesting  situation  in  the  future—rather  than  actually  working  on  developing 
these  projects.  The  lack  of  adequate,  certified  wind  data  measurements 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  179
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

(requiring  additional  on‐site  monitoring)  alone  is  not  a  viable  explanation  for 
delays  in  project  initiation  by  the  sponsors,  since  in  other  parts  of  the  world 
(when  adequate  promotional  incentives  are  in  place)  projects  are  often 
committed with even less reliable data.  

• New  hydel  IPP  projects  are  practically  non‐existent,  and  the  few  which  are 
developing  are  either  being  developed  by  state  owned  institutions  or  are  now 
reaching  maturity  based  on  the  earlier  1995  policy.  Despite  the  huge  hydel 
potential  in  Pakistan,  only  very  few  bankable  feasibility  studies  exist.  Without 
these studies, the development of privately sponsored projects is even harder.  

• Projects  using  renewable  sources  other  than  wind  or  hydel  (i.e.,  solid  biomass, 
waste‐to‐energy)  have  not  yet  reached  a  pre‐feasibility  stage  of  commercial 
assessment.  

Taking all these issues into account, it seems that the requirement of ‘more time’ is not 
the  primary  reason  for  the  limited  development  of  RES  so  far,  and  that  some  changes 
need  to  be  incorporated  in  the  promotional  policy  in  order  to  reach  the  desired 
deployment targets.  

What are the most important problems as perceived by RE developers? 

The two most important problems reported by potential RE IPP developers in Pakistan 
are: tariffs levels and the time required to obtain NEPRA decisions regarding such tariffs.  

As previously mentioned, two systems exists for determining RE tariffs in Pakistan: The 
upfront  tariff  (defined  by  NEPRA  only  for  wind  projects  so  far)  and/or  raising  a  tariff 
petition on a case‐by‐case basis. Not surprisingly, having both possibilities available, all 
of the developers have opted for the second one, and in all cases have asked for tariffs 
higher  than  the  upfront  rate  offered.  To  determine  these  tariffs,  NEPRA  asks  for 
disclosing all the technical and economic documentation related with the project, and it 
determines  a  project‐specific  tariff  using  a  cost‐plus  approach.19  The  time  required  by 
NEPRA to announce a final tariff determination is of about six months from the filing of a 
petition  by  the  sponsor.  The  developer  has  the  option  of  submitting  another  tariff 
petition,  in  case  the  project’s  costs  escalate  in  the  interim  from  what  was  originally 
proposed. This system has presented several of issues, among them:  

• Variation  in  project  costs.  Due  to  the  present  high  world  demand  for  wind 
turbines, the market for such equipment is faced with a shortage of production 
capacity.  As  a  result,  prices  are  increasing  and  the  manufacturers  are  only 
providing  estimated  quotations  for  any  request  that  is  not  firmly  committed. 
Therefore, when the developer files a tariff petition, it has to use these estimated 
quotations, either from the manufacturers itself or from the EPC constructors. As 
the  tariff  decision  requires  about  six  months  to  process,  the  market  conditions 
obtaining at the time the tariff is finally announced may be different from when 
                                                       
19
  The problems associated with the ‘cost‐plus’ approach will be discussed later. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  180
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

the  application  was  first  filed,  and  a  new  tariff  petition  may  need  to  be 
submitted,  starting  the  process  all  over  again.  This  could  lead  to  a  perpetual 
cycle.  As  this  situation  has  occurred  a  couple  of  times,  NEPRA  is  currently 
requesting  firm  EPC  quotations  before  it  proceeds  with  reviewing  tariff 
applications. However, to obtain quotations with more than a one‐year validity is 
extremely difficult for developers to achieve at present.20 

• Possibility  of  gaming.  When,  as  is  currently  the  case  in  Pakistan,  two  options 
exists  for  developing  an  unsolicited  project  (upfront  or  negotiated  tariffs)  the 
normal  behavior  of  a  developer  will  be  to  try  obtain  a  negotiated  tariff,  higher 
than  the  up‐front  one,  as  mentioned  previously.  Even  having  obtained  a  tariff 
decision  that  can  make  the  project  financially  feasible,  the  natural  incentive  to 
file new petitions can persist, especially if another developer obtained a higher 
tariff in the interim. It is not difficult to conceive that a developer will not start 
construction  until  it  is  reasonably  satisfied  that  the  tariff  it  obtained  is  the 
‘highest  one’  it  could  obtain.  As  information  asymmetry  will  always  be  there 
(regardless  of  the  information  disclosed  by  the  developer,  who  is  the  only  one 
privy to actual project costs and performance criteria), the possibility of projects 
to  be  deliberately  delayed  foreseeing  the  possibility  of  iteratively  higher  tariff 
approvals will always remain.21 

Subsequently,  based  on  the  discussion  above,  it  is  clear  that  in  the  medium‐term  RE 
policy the possibility of filing tariff petitions different from the upfront ones (regardless 
of the methodology used to define these upfront tariffs) needs to be discontinued.  

Are  the  guidelines  indicated  in  the  short‐term  policy  adequate  for  promoting  rapid 
deployment of RES projects?  

The short‐term RE policy (valid to end‐June, 2008) included a detailed set of guidelines 
for  determining  the  tariffs  for  wind  projects.22  These  guidelines,  basically  based  on  a 
‘cost‐plus’  approach,  reduce  NEPRA’s  capability  of  selecting  a  different  methodology 
while  determining  individual  projects’  tariffs.  In  any  case,  this  approach  is  consistent 
with  the  methodologies  used  by  NEPRA  to  define  tariffs  for  other  power  generation 
projects  in  the  country,  where,  in  practically  all  cases,  a  cost‐plus  approach  has  been 
used.  

                                                       
20
  In addition of the six months required by NEPRA, additional time is required to obtain all other necessary consents 
and to reach financial closure.  
21
  Note that although this assertion may seem to imply that the petitions filed by the RE IPP developers with NEPRA 
are invariably not accurate, realistic, or contain inaccurate or misleading information, this is not the intention of the 
consultants. Their purpose is rather to point out a systematic flaw in the tariff setting mechanism: that the incentive 
for  obtaining  successively  higher  tariffs  for  a  project  exists  in  all  the  cases  where  the  tariff  can  be  somehow 
‘negotiated’ based on developer‐supplied cost information, rather than being ‘capped’ at some level based on the 
regulator’s own cost information.  
22
  It  also  includes  guidelines  for  small  hydro,  waste‐to‐energy  and  bagasse‐based  cogeneration,  but  in  much  lesser 
detail. In the case of small hydels, the guidelines may be expanded further at a later stage (i.e., to include feed‐in 
tariffs for mini‐ and microhydels).  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  181
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

This particular approach has been adopted for RE IPPs in order to reduce the risk faced 
by the developer in undertaking such kind of pioneering projects, since it guarantees a 
return‐on‐equity  (ROE)  equal  to  the  long‐term  interest  rates  on  ten‐year  Pakistan 
Investment Bonds (PIB) plus a premium. While it is true that this methodology reduces 
some  of  the  financial  risks  assumed  by  the  developer,  it  is  also  apparent  that  this 
arrangement eliminates any further incentive to develop these types of projects.23 The 
ROE  used  (15%)  has  been  the  same  Regardless  of  the  type  of  project  under 
consideration (i.e., using renewable or conventional energy sources). This leads to quite 
a curious situation, for example: 
• The  upfront  tariffs  allowed  by  NEPRA  for  conventional  generation  using 
reciprocating engines burning diesel oil (US$ 119.7/MWh) is 25% higher than the 
upfront tariffs for power generation using wind (US$ 95/MWh), Regardless of the 
benefits the latter brings to the environment or in terms of fuel independence.  
• The  tariffs  approved  for  the  latest  small‐scale  hydel  developments  were  about 
US$ 38/MWh.  This  value  is  only  30%  of  the  tariffs  allowed  to  reciprocating 
engines or 60% of the tariffs approved for gas‐fired conventional generation.  

As a result, there is no special incentive for a developer to commit to RES projects rather 
than  to  develop  less  riskier  conventional  ones,  which  does  not  make  economic  sense. 
The risks of RES projects (particularly wind) can be considered higher, at least because 
there  are  no  projects  of  this  kind  in  operation  at  present  in  Pakistan.  Therefore,  the 
reluctance  of  the  serious  investors  to  undertake  these  types  of  projects  is  naturally 
higher.  

It can be argued that the ‘cost‐plus’ approach, if compared with others, transfers to the 
consumers most of the social surplus (see Annex VII), benefiting them but at the same 
time  decreasing  it  in  absolute  terms.  Therefore,  applying  this  methodology  to  all 
generation  technologies  without  any  other  type  of  discrimination  leads  to  undesired 
results  where  more  expensive  and  pollutant  technologies  develop  and  the  resulting 
average ratepayer price of electricity could be even higher than in the case in which RES 
are used.  

As a result, it is concluded that tariff determination based in the ‘cost‐plus’ approach is 
not  suitable  for  promoting  a  rapid  deployment  of  RES  technologies.  An  up‐front  tariff 
based  on  the  ‘avoid  cost’  approach,  as  computed  and  explained  in  Annex  VII,  would 
seem to be a more appropriate option. 

                                                       
23
  In  fact,  the  guidelines  indicated  in  the  policy  are  not  a  ‘pure’  cost‐plus  approach,  since  they  allow  at  least  two 
additional provisions whereby the developer can obtain potentially even higher returns: 1) the capital cost figures 
used are not the actual ones, but estimated by NEPRA using market data, and 2) the ‘interest on loans’ assumed in 
calculating tariffs is a benchmark; in case the developer manages to arrange better financing terms, the additional 
benefits shall be shared amongst the developer and the purchaser (in a 60:40 ratio, respectively). However, due to 
the reasons mentioned earlier, NEPRA has so far used the actual capital and debt servicing costs provided by the 
developer in arriving at its tariff determinations.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  182
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Is  the  wind  speed  (or  water  flow)  risk  mitigation  mechanism  developed  in  Pakistan 
actually perceived by investors as an important benefit? Should this be maintained in 
the future?  

The AEDB has designed a mechanism to ‘guarantee’ the income of a developer in case 
the  average  wind  speed  (or  average  water  flow,  in  the  case  of  hydel)  in  a  month  at  a 
particular  location  is  lower  than  a  benchmark  obtained  from  a  set  of  measurements 
performed  in  the  past  at  the  site  over  a  reasonable  period  of  time24  by  the  AEDB  or 
other  independent  body.  This  approach  was  developed,  according  to  information 
received from the AEDB, to mitigate the initial reluctance of the developers who might 
feel uncomfortable investing in projects whose profitability depends on data that were 
not  collected  by  them.  To  the  knowledge  of  the  consultants,  this  approach  has  never 
been used in other countries. 

While this mechanism can be considered appropriate for an initial period for its stated 
benefits,  until  such  time  that  the  industry  gains  confidence  on  the  technology  and  its 
commercial viability,  it  is  not  considered  convenient  to  be  maintained indefinitely  into 
the future. There are a number of reasons to eliminate it in the medium‐term RE policy:  
• Variability  of  wind  is  inherent  to  wind  power  generation:  To  determine  this 
variability, as well as to design the hedging mechanism to take it into account, is 
essentially  a  matter  for  the  developer.  It  should  not  be  the  purchaser  who 
assumes it, particularly given the already low plant factors typical of wind farms 
compared to firmer, conventional power availability. This has been the practice 
in all other parts of the world.  
• Reduced  incentives  for  adequate  design:  The  actual  energy  production  from  a 
wind  farm,  at  a  particular  location,  will  depend  on  the  wind  speed  but  also, 
amongst other factors, on the design of the wind farm (i.e., micrositing issues). 
The  layout  of  the  wind  farm  is  entirely  under  the  developer  decision.  It  is  the 
developer, therefore, who should take on the benefits or problems inherent with 
the  project’s  design.  Also,  the  conversion  of  wind  speed  to  energy  depends  on 
several  parameters:  the  type  of  turbines  selected,  the  location  of  the  towers, 
their height, etc. These parameters and their impact will be determined ex‐post 
(that  is  when  the  turbine  selection  and  farm  design  have  been  finalized). 
Therefore,  any  eventual  gain  obtained  due  to  the  design  will  be  automatically 
eliminated (transferred to the consumers) and the incentives for an adequate (or 
optimum) design are thus strongly reduced. 
• Complexity of mechanism: The assumption of  wind speed risk by the purchaser 
requires  constant  on‐site  wind  measurements,  the  development  of  wind  tables 
that can vary over time, and several assumptions regarding turbine efficiency and 
availability,  before  the  monthly  payments  due  to  the  power  producer  can  be 
determined.  It  increases  the  administrative  overheads  relevant  to 
operationalizing  the  tariff  mechanism  considerably,  and  could  lead  to  disputes 

                                                       
24
  Benchmark wind speed measurements are usually based on three‐year rolling averages, while that for water flows 
are typically derived from a more extensive hydrological time‐series database. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  183
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

with  the  developer  regarding  the  accuracy,  quality,  or  adequacy  of  such 
independent wind power measurements.  
• Could lead to endless negotiations: Once one of the risks has been eliminated (in 
fact,  transferred  to  the  consumers),  the  developers  may  ask  for  others  to  be 
removed  as  well  (e.g.,  wind  direction,  variability  of  the  wind  within  a  month, 
etc.).25  This,  in  turn,  may  delay  the  execution  of  some  projects  further  while 
developers wait for such claims to be taken into account.  

Therefore,  it  is  considered  that  in  the  medium‐term  RE  policy,  these  risk  mitigation 
mechanisms  will  be  eliminated  altogether,  and  all  resource  variability  (including  wind 
speed  or  water  flows)  be  transferred  to  the  developer,  who  would  be  in  a  better 
position  to  manage  it.  In  any  case,  if  it  is  considered  that  RES  projects  that  utilize 
unpredictable  resources  (e.g.,  solar,  wind,  or  hydel)  are  more  risky  than  others,  this 
higher risk should be recognized in the IRR allowed and not transferred to the purchaser 
(and, ultimately, to the customers).  

Are  there  other  problems  encountered  by  RE  developers  that  not  directly  related  to 
tariff issues?  

According  with  the  conversations  held  with  representative  developers,  most  other 
problems reportedly faced by them were of much lesser importance than those related 
to power purchase tariffs. Some problems existed in the KESC area, since KESC refused 
to  sign  the  PPA  for  a  renewable  energy  project.  It  was  eventually  resolved,  permitting 
the project to proceed, with the contract agreement signed with the NTDC, despite the 
project being connected to KESC lines  

It  should  be  noted,  however,  that  this  does  not  imply  that  other  than  tariffs,  all  other 
issues  potentially  affecting  RE  projects  can  be  termed  insignificant;  rather,  such 
additional  problems  have  not  come  to  light  so  far  perhaps  because  most  projects 
currently  under  development  have  not  yet  progressed  far  along  the  implementation 
track. In particular, two issues would seem to require urgent attention: 
• Connection to the grid: It needs to be assured that the NTDC (or the DISCO) will 
always  conduct  the  grid  extension  required  to  connect  RES  projects  in  a  timely 
manner and at its own cost, and that it will be adequately compensated for the 
additional costs incurred by the GoP. Otherwise, grid connection may become a 
serious  bottleneck  in  the  future  even  if  projects  successfully  reach  the 
construction stage.  
• Transparent pass‐through for distributors. In several cases, the power purchaser 
for an RE generation project may be a distribution utility, especially in the case of 
small‐sized  plants.  If  the  price  of  the  RES  energy  approved  by  NEPRA  is  higher 
than  the  average  cost  of  energy  purchased  by  the  distributor  from  the  grid 
(which  will  probably  often  be  the  case),  and  the  distributor  is  not  adequately 
compensated for this higher cost, there will be reluctance for the distributor to 

                                                       
25
  For example, see Section 2.3.1. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  184
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

accept  this  energy  (expressed,  for  example,  by  the  utility  creating  ‘artificial 
technical problems’ in order to escape any penalties for failing to assure power 
off‐take). Therefore, transparent compensation for these extra costs needs to be 
explicitly provided for. Two options exist for this purpose:  
o Include these extra costs into the distribution revenue requirements allowed 
by the distributors (e.g., through ‘system benefit charges’26). In this case, this 
should be clearly stated in the tariff structures developed by NEPRA.  
o Sell  all  the  renewable  energy  produced  to  the  Central  Power  Purchasing 
Authority  (CPPA),  regardless  of  the  voltage  at  the  connection  point.  In  this 
case, the cost of procuring this energy can be incorporated by the CPPA in the 
average energy price transferred to all distributors, regardless of the location 
of the renewable project.  

The  advantages  and  disadvantages  of  both  alternatives  will  be  discussed  in  a  separate 
document outlining the medium‐term policy recommendations.  

Are  current  administrative  procedures  (required  consents,  petitions,  processing 


schedules, etc.) a barrier to more rapid deployment of RES projects?  

Potential  developers  have  indicated  problems  with  some  of  the  administrative 
procedures  that  have  delayed  the  execution  of  their  RE  IPP  projects.  Most  of  these 
problems  are  related  to  the  documentation  required  to  be  included  in  the  security 
package (IA, PPA, etc.). They also stated that these issues seem to have been resolved 
now, and that they consider the current contents of the proposed agreements adequate 
and acceptable. These types of problems are typical for first‐of‐kind projects and were to 
be expected.  

However,  it  is  worth  mentioning  that  such  elaborate  administrative  procedures  (the 
majority required to be handled in Islamabad) can be an important (and costly) burden 
for  small‐sized  projects,  especially  those  serving  remote  locations  or  small 
communities.27 This issue was clearly stated by the Punjab Irrigation & Power officials, 
who  recommended  a  single‐window  facility  at  the  provincial  level  to  deal  with  such 
projects.  The  consultants  agree  with  these  comments,  and  recommend  that  the 
medium‐term  policy  create  different  (and  simpler)  procedures  for  these  kinds  of 
projects.  

Are the institutional roles for promoting RES in Pakistan adequately assigned?  

Three  different  institutions  in  Pakistan  are  involved  with  RES  project  development  at 
present: 

                                                       
26
  These  refer  to  competitively‐neutral,  non‐by  passable  ratepayer  charges  allowed  to  utilities  to  enable  them  to 
recover  the  cost  of  mandated  renewable  energy  purchase,  energy  efficiency,  environmental  protection,  and/or 
low‐income assistance programs that the competitive market is unlikely to provide on its own. 
27
  For example, off‐grid hydel projects of a few megawatts capacity.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  185
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• AEDB:  Responsible  for  promoting  RES  projects  and  to  act  as  a  ‘single  window’ 
through  which  developers  can  obtain  the  required  consents,  permits  and 
agreements needed to realize the project.  
• PPIB: Responsible for dealing with bagasse‐based cogeneration projects or hydel 
generation projects larger than 50 MW of installed capacity.  
• NEPRA: Responsible for sanctioning tariffs for grid‐connected RES projects. 

Although,  in  principle,  this  separation  of  responsibilities  can  be  considered  rational,  it 
may  hide  some  problems  which,  eventually,  may  create  a  barrier  to  the  rapid 
deployment of RES projects: 
• It  is  recognized  that,  at  least  in  the  short  term,  some  renewable  energy 
technologies  will  require  tariffs  higher  than  those  applicable  to  conventional 
sources.28  In  this  situation,  NEPRA  is  confronted  by  a  quite  ‘logical’  conflict  of 
interest.29  On  the  one  hand,  it  has  to  protect  the  interest  of  consumers,  and 
therefore set the tariffs as low as practicable, while simultaneously assuring the 
financial  health  of  the  suppliers.  On  the  other,  it  has  to  follow  the  policy 
guidelines  of  the  government,  seeking  to  promote  renewable  energy  sources, 
even  if  the  direct  costs  of  doing  so  are  higher  than  those  for  available 
conventional alternatives.  
The  way  to  ‘resolve’  this  conflict  is  to  establish  clear  guidelines  that  the 
regulatory authority (NEPRA) shall follow in determining these tariffs. That is, for 
example,  the  case  in  the  current  short‐term  policy  for  wind  projects.  However, 
these guidelines do not exist for other renewable energy technologies.  
Even in the case of wind power (where the guidelines are clearly stated), some 
degree  of  discretionary  interpretation  always  exists.  That  is  the  case,  for 
example, in respect of the capital cost component of the  tariffs. The  guidelines 
state that this cost “…shall be determined after thorough market research and by 
accessing  information  provided  by  the  wind  IPP”.  In  most  of  the  cases,  it  is 
practically impossible to determine if a cost provided by an IPP is consistent or 
not with market conditions.30 
It  should  be  noted  that  this  ‘conflict’  is  not  a  characteristic  unique  to  Pakistan, 
but exists in practically all other countries, and this is one of the reasons several 

                                                       
28
  Taking into account that some of the environmental impacts of conventional energy production are not reflected in 
the corresponding approved tariffs. See Annex VII for a more detailed analysis of these issues. 
29
  Article 7 (Powers and Functions of the Authority) of the NEPRA Act XL states: “… In performing its functions under 
this  Act,  the  Authority  shall,  as  far  as  practicable,  protect  the  interests  of  consumers  and  companies  providing 
electric  power  services  in  accordance  with  guidelines…  laid  down  by  the  Federal  Government.”  (underlined 
emphasis by the consultants). 
30
  For  example,  in  the  final  tariff  determination  for  WinPower  Pvt.  Ltd.,  Mr  Abdul  Rahim  Khan  of  NEPRA  issued  an 
additional  note  stating  that:  “The  project  cost  per  kW  for  wind  power  projects…  has  reached  a  level  where  it 
surpasses the threshold of project cost per kW for hydroelectric (run‐of‐river) projects, which are equally desirable 
renewable energy projects… Therefore, priority of induction of various technologies needs to be reviewed.”  This is 
a typical case where the regulatory authority sees a conflict between protecting the consumer and following the 
government’s policy guidelines.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  186
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

nations  have  decided  to  exclude  regulatory  institutions  in  the  determination  of 
the incentives (feed‐in or quotas) for renewable energy technologies, and instead 
maintain them within the ‘policy‐making’ institutions (i.e., the Ministry of Energy 
or similar departments).  

As the powers of the regulatory authority to determine generation tariffs is granted by 
the NEPRA Act XL of 1997 (Article 7), and no changes are proposed by the consultants in 
this regard, it is very important that the medium‐term policy clearly states the guidelines 
for determining the tariffs (or premiums) to be applied to renewable energy projects.31 

                                                       
31
  As  mentioned  before,  it  is  advisable  that  these  guidelines  be  based  on  methodologies  other  than  a  ‘cost‐plus’ 
approach. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  187
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex VI:  Working Paper 3: 
Pakistan’s Energy Sector: Market, Growth 
 and Supply Options 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  189
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Working Paper No. 3 

Pakistan’s Energy Sector: 
Market, Growth, and Supply Options 

Contents 

Exhibits ..................................................................................................................... 193 
Abbreviations and Acronyms .................................................................................... 194 
1  Objective .............................................................................................................. 199 
2  Overview .............................................................................................................. 199 
3  The Pakistan Energy Market ................................................................................. 202 
3.1  Supply and Resource Availability ....................................................................... 202 
3.1.1  Natural Gas ............................................................................................ 202 
3.1.2  Oil ........................................................................................................... 203 
3.1.3  Coal ........................................................................................................ 204 
3.1.4  Electricity ............................................................................................... 205 
Power Generation .................................................................................. 205 
Transmission and Distribution ............................................................... 205 
3.1.5  Alternative and Renewable Energy ....................................................... 206 
3.2  Consumption and Sector‐wise Demand ............................................................ 207 
3.2.1  Industrial Sector .................................................................................... 208 
3.2.2  Residential Sector .................................................................................. 208 
3.2.3  Commercial Sector ................................................................................ 209 
3.2.4  Transportation Sector ............................................................................ 209 
3.2.5  Agriculture Sector .................................................................................. 210 
3.3  Resource Potential and Infrastructure .............................................................. 210 
3.4  Sector Organization ........................................................................................... 213 
3.4.1  Government Agencies ........................................................................... 213 
3.4.2  Utilities and Energy Providers ............................................................... 215 
Power ..................................................................................................... 215 
Oil and Gas ............................................................................................. 215 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  191
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Coal ......................................................................................................... 216 
Nuclear ................................................................................................... 216 
Renewables ............................................................................................ 216 
3.4.3  Regulators .............................................................................................. 218 
3.5  Policy Framework .............................................................................................. 219 
3.6  Comparative Costs ............................................................................................. 220 
3.6.1  Production Costs.................................................................................... 220 
Crude Oil ................................................................................................. 220 
Natural Gas ............................................................................................. 220 
Liquefied Petroleum Gas ........................................................................ 221 
Petroleum Products ............................................................................... 223 
Coal ......................................................................................................... 224 
Electricity ................................................................................................ 224 
3.6.2  Energy Pricing ........................................................................................ 226 
Electricity ................................................................................................ 227 
Natural Gas ............................................................................................. 228 
Liquefied Petroleum Gas ........................................................................ 229 
Petroleum Products ............................................................................... 229 
Alternative Energy .................................................................................. 230 
4  Projected Supply and Demand ............................................................................. 231 
4.1  Fueling Economic Growth ................................................................................. 231 
4.2  Energy Supply and Demand Scenarios .............................................................. 233 
4.2.1  Projected Energy Demand ..................................................................... 233 
4.2.2  Projected Energy Supply and Deficit ..................................................... 235 
The Base Case ......................................................................................... 236 
Low Gas Case .......................................................................................... 236 
Low Hydel Case ...................................................................................... 236 
Low Gas, Low Hydel Case ....................................................................... 236 
4.3  Projected Energy Balances ................................................................................ 237 
5  Economic Implications .......................................................................................... 239 
5.1  Scenario Impacts on Costs and Financing Needs .............................................. 239 
5.2  Optimum Role of Renewable Energy ................................................................ 239 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  192
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 

Exhibit 1:  Pakistan Primary Energy Supplies, 2006‐07 ............................................... 201 
Exhibit 2:  Pakistan Energy Consumption, 2006‐07 ..................................................... 201 
Exhibit 3:  Coal Reserves, FY2007 ................................................................................ 204 
Exhibit 4:  Installed Power Generation Capacity, FY2007 ........................................... 206 
Exhibit 5:  Indigenous Energy Resource Potential, FY2007 ......................................... 212 
Exhibit 6:  GoP Agencies Relevant to Energy Production, Management 
and End Use ................................................................................................ 214 
Exhibit 7:  Energy Utilities and Suppliers ..................................................................... 217 
Exhibit 8:  Relevant Regulatory Agencies .................................................................... 218 
Exhibit 9:  Policy Framework Relevant to Energy Production and Use ....................... 219 
Exhibit 10:  Gas Price Discounting Mechanism.............................................................. 221 
Exhibit 11:  Wellhead Gas Prices (as of June 30, 2007) ................................................. 222 
Exhibit 12:  Price Calculation of Petroleum Products Not Published by Platts ............. 223 
Exhibit 13:  Ex‐Refinery Prices of Petroleum Products (as of June 30, 2007) ............... 224 
Exhibit 14:  Cost of Power Generation at Crude Oil Price of US$ 60/bbl 
and Coal Price of US$ 60/Tonne ................................................................. 225 
Exhibit 15:  Cost of Power Generation at Crude Oil price of US$ 90/bbl 
and Coal Price of US$ 75/Tonne ................................................................. 226 
Exhibit 16:  Average Consumer Electricity Tariffs .......................................................... 227 
Exhibit 17:  Average Consumer Gas Tariffs .................................................................... 228 
Exhibit 18:  Consumer Prices of Petroleum Products as of June 30, 2007 .................... 229 
Exhibit 19:  Energy Use Per Capita for Selected Asian Countries, 2003 ........................ 231 
Exhibit 20:  Electricity Consumption Per Capita in Asia, 1980 & 2002 .......................... 232 
Exhibit 21:  Access to Electricity in Selected Asian Countries, 2000 ............................. 233 
Exhibit 23:  Energy Demand Forecasts at Various Economic Growth Rates ................. 235 
Exhibit 24:  Projected Energy Supply and Deficits ......................................................... 237 
Exhibit 25:  Projected Supply for Imported Energy Resources (Base Case) .................. 237 
Exhibit 26:  Projected Supply for Imported Energy Resources Under the 
Low Gas Supply Scenario ............................................................................ 238 
Exhibit 27:  Projected Supply for Imported Energy Resources Under the 
Low Hydel Supply Scenario ......................................................................... 238 
Exhibit 28:  Projected Supply for Imported Energy Resources Under the 
Low Gas, Low Hydel Supply Scenario ......................................................... 238 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  193
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

ACGR  Average compound growth rate 
ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
AJK  Azad Jammu and Kashmir 
AKRSP  Aga Khan Rural Support Programme 
API  American Petroleum Institute 
APL  Asia Pipelines Limited 
ARL  Attock Refinery Limited 
bbl  Barrels 
Bcfd  Billion cubic feet per day 
BPL  Bosicor Pakistan Limited 
Btu  British thermal unit 
C&F  Carriage and freight 
CAA  Civil Aviation Authority 
CCGT  Combined cycle gas turbine 
CDM  Clean Development Mechanism 
cf  Cubic feet 
CHASHNUPP  Chashma Nuclear Power Plant 
CNG  Compressed natural gas 
CP  Contract price 
DGG  Directorate General, Gas 
DGM  Directorate General, Mineral 
DGO  Directorate General, Oil 
DGPC  Directorate General, Petroleum Concessions 
DISCO  Distribution company 
DNA  Designated national agency 
DSM  Demand‐side management 
E&P  Exploration and production 
EAD  Economic Affairs Division 
EDB  Engineering Development Board 
ENERCON  National Energy Conservation Centre 
EPD  Environmental Protection Department 
FBR  Federal Board of Revenue 
FO  Furnace oil 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  194
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

FOB  Freight on board 
FY  Financial year 
GDP  Gross domestic product 
GENCO  Generation company 
GES  Growth environment score 
GoP  Government of Pakistan 
GSA  Gas sales agreement 
GWh  Gigawatt‐hour 
HDIP  Hydrocarbon Development Institute of Pakistan 
HOBC  High octane blending compound 
HSD  High‐speed diesel 
HSFO  high‐sulfur fuel oil 
I&P  Irrigation and power 
IFEM  Inland freight equalization margin 
IFI  International financial institution 
IPP  Independent power producer 
JP  Jet propulsion 
KANUPP  Karachi Nuclear Power Plant 
KESC  Karachi Electric Supply Corporation 
kV  Kilovolt 
kW  Kilowatt 
kWh  Kilowatt‐hour 
lb  Pound 
LDO  Light diesel oil 
LNG  Liquefied natural gas 
LPG  Liquefied petroleum gas 
MGCL  Mari Gas Company Limited 
MMscfd  Million standard cubic feet per day 
MMTPA  Million tonnes per annum 
MoE  Ministry of Environment 
MoFR  Ministry of Finance and Revenue 
MOGAS  Motor gasoline 
MoPNR  Ministry of Petroleum and Natural Resources 
MoST  Ministry of Science and Technology 
MoWP  Ministry of Water and Power 
MS  Motor spirit 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  195
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

MT  Metric tonnes 
MTDF  Medium Term Development Framework 
MTOE  Million tonnes of oil equivalent 
MW  Megawatt 
NAPWD  Northern Areas Public Works Department 
NARC  National Agriculture Research Council 
NEPRA  National Electric Power Regulatory Authority 
NHA  National Highway Authority 
NPO  National Productivity Organization 
NRL  National Refinery Limited 
NTDC  National Transmission and Dispatch Company 
NTRC  National Transport Research Centre 
NWFP  Northwest Frontier Province 
O&M  Operations and maintenance 
OECD  Organization for Economic Cooperation and Development 
OGDC  Oil and Gas Development Corporation 
OGRA  Oil and Gas Regulatory Authority 
OMC  Oil marketing company 
P&D  Planning and Development 
PAEC  Pakistan Atomic Energy Commission 
Pak EPA  Pakistan Environment Protection Agency 
PARC  Pakistan Agriculture Research Council 
PARCO  PakArab Refinery Company 
PCRET  Pakistan Council for Renewable Energy Technologies 
PCSIR  Pakistan Council for Scientific and Industrial Research 
PEPCO  Pakistan Electric Power Company 
PHA  Pakistan Housing Authority 
PIAC  Pakistan International Airlines Corporation 
PIDC  Pakistan Industrial Development Corporation 
PMD  Pakistan Meteorological Department 
PNAC  Pakistan National Accreditation Council 
PNRA  Pakistan Nuclear Regulatory Authority 
PPEPCA  Pakistan Petroleum Exploration and Production Companies Association 
PPIB  Private Power and Infrastructure Board 
PPL  Pakistan Petroleum Ltd. 
PR  Pakistan Railway 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  196
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

PRL  Pakistan Refinery Limited 
PSO  Pakistan State Oil Company 
PSQA  Pakistan Standards and Quality Control Authority 
PV  Photovoltaic 
PWD  Public Works Department 
RE  Renewable energy 
RES  Renewable energy source 
RES‐E  Renewable energy sourced‐electricity 
RON  Research octane number 
RoR  Run‐of‐river 
SAARC  South Asian Association for Regional Cooperation 
SBP  State Bank of Pakistan 
SCA  Sindh Coal Authority 
Scf  Standard cubic feet 
SECP  Securities and Exchange Commission of Pakistan 
SHYDO  Sarhad Hydel Development Organization 
SMEDA  Small and Medium Enterprises Development Authority 
SNGPL  Sui Northern Gas Pipelines Ltd. 
SRO  Statutory regulatory ordinance 
SSGCL  Sui Southern Gas Company Ltd. 
T&D  Transmission and distribution 
TA  Technical assistance 
Tcf  Trillion cubic feet 
TPA  Tonnes per annum 
TWh  Terawatt‐hour 
WAPDA  Water and Power Development Authority 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  197
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Pakistan’s Energy Sector: 
Market, Growth, and Supply Options 

1 Objective 
This  Annex  presents  an  overview  of  Pakistan’s  energy  sector  and  its  organizational 
structure, prospects for its growth and anticipated constraints on primary supplies, and 
possible future options and strategies that the country may adopt in order to provide for 
the energy needs of a rapidly developing economy. 
The purpose of this study is to provide estimates of anticipated growth in the country’s 
energy demand, a comparative evaluation of different energy supply options available to 
it,  and  the  circumstances  under  which  such  needs  can  be  met,  especially  in  terms  of 
electrical power. This would help determine the role that renewable energy (RE) based 
generation  can  play  in  the  national  context,  to  the  extent  that  availability  and  relative 
costs allow. 
In  this  respect,  this  analysis  should  also  provide  a  useful  base  for  evaluating  the 
economic  merits  of  renewable  energy  sources  (RES)  relative  to  conventional  supply 
options  in  the  energy  mix,1  at  both  the  national  and  local  levels,  and  help  prioritize 
targets  and  policies  aimed  at  the  development  of  appropriate  RE  technologies  in  the 
medium term, as required under ADB TA 4881‐PAK. 

2 Overview 
Pakistan requires increasingly large energy inputs to support the economic development 
needs of a large population which, at over 160 million, makes it the world’s sixth largest 
nation. Furthermore, Pakistan’s population is projected to grow at an annual rate of just 
under  2%,  reaching  190.7  million  by  2015.2    Simultaneously,  the  country’s  pace  of 
economic  development  is  accelerating,  with  annual  GDP  growth  having  averaged  7% 
over  the  last  five  years  and  the  size  of  the  national  economy  and  per  capita  incomes 
doubling  in  less  than  a  decade.  The  significant  strengthening  of  macroeconomic 
fundamentals  and  resilience  of  growth  trends—even  in  the  face  of  serious  and 
unexpected  challenges,  such  as  record  oil  import  prices  and  the  severe  earthquake  of 

                                                       
1
  While this study focuses on the prospects and costs of conventional energy supplies in Pakistan, the economics of 
available RES options are discussed in detail in Annex VII. 
2
  World Population Prospects: The 2006 Revision, Population Database, Department of Economic and Social Affairs, 
Population Division, United Nations, New York: 2007 (data for medium variant projections). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  199
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2002—underpin  current  projections  of  robust  national  economic  growth  over  the 
medium term and beyond.3 
These trends translate into rapidly escalating energy demand: primary energy supply in 
Pakistan has been increasing at 6% per annum over the last five years (see Exhibit 1 and 
Exhibit  2,  respectively,  for  energy  supply  and  use  statistics).4    Over  the  same  period, 
electricity  consumption  in  the  country  has  risen  at  an  average  annual  rate  of  6.8%, 
natural gas by 10.4%, liquefied petroleum gas (LPG) by 17.6%, and coal by 22.8%. Only 
oil  consumption  has  leveled  off  temporarily  due  to  large‐scale  fuel  switching  in  the 
power  and  cement  industry,  displaced  by  natural  gas  and  coal,  respectively—and 
transportation,  due  to  increased  use  of  compressed  natural  gas  (CNG)  in  vehicles. 
Nevertheless,  oil  imports  in  2004‐05  increased  by  4.7%  over  the  preceding  year  (at  a 
44.5% higher cost due to international crude price escalation), and the import bill stood 
at over US$ 7.4 billion in 2006‐2007 compared to US$ 2.7 billion in 2003‐2004. 
Electricity use, in particular, is growing robustly across all sectors—industry, agriculture, 
domestic, and commercial—recording a 10.2% overall jump in 2005‐06 with generation 
increase lagging behind at 9.3% during the same period. The country thus faced serious 
peak electricity supply shortfalls, in the range of 1,500‐2,000 MW, during the summer of 
2007, necessitating significant ‘load shedding’ or forced outages that adversely affected 
economic activity and social services, and are expected to worsen in 2008 and beyond 
before  significant  new  generation  capacity  can  be  brought  online.  Despite  a  steady 
improvement in recent years, system‐wide grid transmission and distribution losses still 
remain high at 24.8% of dispatched power. 
Projecting  forward,  Pakistan’s  Medium  Term  Development  Framework  2005‐2010 
(MTDF) sets out a challenging program in order to achieve 8% average annual national 
GDP  growth.  The  associated  increase  in  energy  consumption  is  forecast  at  12%  per 
annum,  more  than  double  the  rate  witnessed  between  2000  and  2006.  This  will 
increasingly strain Pakistan’s primary energy supply sources. Rising oil consumption and 
flat  domestic  production  will  once  again  trigger  rapidly  increasing  oil  imports,  while 
steadily  depleting  domestic  natural  gas  reserves—in  the  absence  of  substantial  new 
discoveries—will  see  the  country  importing  gas  for  the  first  time  in  its  history,  both 
through  pipelines  as  well  as  in  the  form  of  liquefied  natural  gas  (LNG)  shipments. 
Electricity consumption, slated to grow on average at 8% per annum to 2015 (although 
recent  experience  suggests  even  higher  demand  growth),  will  similarly  require  large 
power  generation  capacity  additions.  Electricity  imports  from  Iran  have  been  in  effect 
for  several  years  now  for  the  Balochistan  coastal  grid,  and  larger  power  imports  from 
Central  Asian  states  to  the  national  grid,  although  logistically  challenging,  are  under 
active GoP consideration. Higher energy demand and imports will also require massive 
investments  in  associated  port  terminals,  storage  facilities,  refining  capacity,  pipeline 
and transmission networks, and surface fuel transport infrastructure. There is increasing 
                                                       
3
  According to a recent assessment, Pakistan is expected to maintain a GDP growth rate of 6.8% per annum in dollar 
terms over the next 45 years. With this rate of increase, national per capita income is projected to reach US$ 7,753 
by  2050  from  US$  737  in  2005.  This  growth  could  accelerate  further  if  the  country’s  Growth  Environment  Score 
(GES) improves in the interim (Global Economics Paper No. 134, Goldman Sachs, New York: December 2005). 
4
  Average  compound  growth  rate  (ACGR)  between  2001‐02  to  2006‐07  (Pakistan  Energy  Yearbook  2007, 
Hydrocarbon Development Institute of Pakistan (HDIP), Government of Pakistan, Islamabad: 2008). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  200
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

realization  of  the  need  to  expedite  exploitation  of  all  indigenously  available  energy 
resources,  especially  the  significant  Thar  coal  deposits  as  well  as  renewable  sources 
(small  hydro,  wind,  solar,  and  biomass),  while  simultaneously  undertaking  large 
hydroelectric  projects  on  the  country’s  main  rivers.  However,  success  in  efforts  to 
enhance  Pakistan’s  energy  supplies  is  subject  to  a  host  of  technical,  financial, 
institutional, and political considerations being addressed in a timely manner, to energy 
market  reforms  and  privatization  of  state‐controlled  institutions  proceeding  smoothly, 
as well as to the efficiency with which available supplies are harnessed and used. 

Exhibit 1: Pakistan Primary Energy Supplies, 2006‐07 

Total Energy Availability, 2006-07 Total Primary Energy Supply, 2006-07

62.498 MTOE 60.388 MTOE

Hydroelectricity Nuclear
7.627 0.546
12.6% 0.9%
Imports Coal Oil
19.835 4.427 18.121
32% 7.3% 30.0%

LPG
0.314
Indigenous
0.5%
Production Natural Gas
42.663 29.312
68% 48.6%

Source: Pakistan Energy Yearbook 2007, Hydrocarbon Development Institute of Pakistan (HDIP), 
Government of Pakistan, Islamabad: 2008. 

Exhibit 2: Pakistan Energy Consumption, 2006‐07 

Total Energy Consumption, 2006-07 Total Energy Use, 2006-07


36.005 MTOE 36.005 MTOE
Transportation Other
Electricity 9.721 0.742
5.922 27%
Oil 2%
16%
10.575
29% Domestic
7.605
Coal 21%
4.149
12%

LPG
0.658 Commercial
2% 1.377
Industry
Natural Gas 15.792 Agriculture 4%
14.701 44% 0.767
41% 2%

Source: Pakistan Energy Yearbook 2007, Hydrocarbon Development Institute of Pakistan (HDIP), 
Government of Pakistan, Islamabad: 2008. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  201
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3 The Pakistan Energy Market 
3.1 Supply and Resource Availability 
Primary  energy  supply  in  Pakistan  was  60.4  MTOE  in  fiscal  year  (FY)  2007,5  with 
indigenous gas accounting for 48.6% of the total, followed by oil at 30% (Exhibit 1). Even 
assuming  a  modest  GDP  growth  rate  of  6.5%  per  year,  overall  demand  for  energy  is 
expected  to  increase  by  a  factor  of  3.5  over  the  next  20  years.  Demand  for  energy  is 
closely linked to the overall economic growth rate, and variations of  over 25% in total 
demand can occur over a 20‐year period for a one percent change in the average annual 
economic growth rate. Given Pakistan’s current plans for the development of its energy 
resources, the deficit in energy supply that will have to be filled with imported fuels is 
expected  to  increase  from  the  current  28%  to  62%  of  the  total  by  FY2025.  While  the 
exploitation of the limited reserves of indigenous oil and gas continues at an adequate 
level, the country is rich in coal and hydel resources which have so far remained grossly 
underutilized.  The  development  of  lignite  reserves  in  Thar,  Sindh,  that  constitute  the 
bulk  of  the  country’s  coal  resources,  is  constrained  mainly  by  challenging  mining 
conditions and the large financial outlays required to exploit them, while the bulk of the 
hydel  opportunities  are  situated  in  remote  locations  where  infrastructure 
development—such as roads and transmission lines—poses a additional costs. Pakistan 
has,  therefore,  given  priority  to  the  import  of  natural  gas,  LNG,  and  power  from 
resource‐rich countries in the region in the medium term until domestic resources can 
be more fully utilized. 
Key  elements  of  an  action  plan  being  pursued  by  the  government  to  enhance  the 
nation’s  energy  supplies,  and  to  manage  risks  associated  with  delays  in  resource 
development and rising world energy prices, include fast‐tracking imports of natural gas 
and  LNG  from  neighboring  countries  to  meet  near‐term  energy  requirements,  and 
accelerated  development  of  Thar  coal  and  of  large‐scale  projects  for  hydroelectric 
power  generation  to  ensure  energy  security  in  the  longer  term.  In  addition  to  the 
development  of  conventional  energy  resources,  programs  are  being  implemented  to 
enhance  the  efficiency  of  the  energy  sector  through  mainstreaming  of  renewable 
energy,  undertaking  integrated  energy  planning,  and  improving  demand‐side 
management to optimize the use of available resources. 

3.1.1 Natural Gas 
Pakistan  is  a  significant  producer  of  natural  gas.  As  of  June  30,  2007,  Pakistan’s  total 
remaining  recoverable  gas  reserves  were  estimated  at  32.4 trillion  cubic  feet  (Tcf),6 
which are adequate for meeting the country’s gas requirement for about 23 years at the 
current production rate of 3.87 billion cubic feet per day (Bcfd). Almost all the presently 
identified oil and gas reserves are onshore. Historically the Sui gas field has been one of 
the country’s major producers and had remained central to gas supplies and associated 
infrastructure  development.  However,  sizeable  gas  discoveries  in  the  past  decade, 
including Qadirpur, Miano, Sawan, Bhit, and Zamzama—with total production of about 
                                                       
5
  i.e., July 1, 2006 to June 30, 2007. 
6
  Equivalent to 28.18 Tcf normalized to 900 Btu/cf. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  202
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

1.5 Bcfd—have changed the overall gas supply situation in the country and have shifted 
the  resource  base  from  Sui  to  these  newly  developed  fields  in  the  south.  A  major 
discovery at the Gurgari gas field, near Kohat, has also recently been made in the NWFP. 
The  bulk  of  natural  gas  production  in  the  province  of  Sindh  is  concentrated  in  and 
around the Indus River Basin.  
The GoP fixes the price at which gas is purchased from producers. The pricing formula 
for  each  gas  field  depends  on  the  pricing  policy  in  force  at  the  time  the  discovery  is 
declared  commercial.  All  the  fields  that  declared  commercial  production  up  until  1985 
had their wellhead prices set on a ‘cost‐plus’ basis. Thereafter, between 1985 and 1994, 
prices of all new gas discoveries were generally linked with price of high‐sulfur fuel oil 
(HSFO). However, under the Petroleum Policy, 1994, the producers’ prices were indexed 
with  the  C&F  price  of  baskets  of  imported  Arabian/Persian  Gulf  crude.  In  December 
1999,  a  new  inflection‐point  based  pricing  framework  with  a  discounted  price 
mechanism  was  defined,  linked  to  the  price  of  a  basket  of  Arabian/Persian  Gulf  crude 
oils. The economic package for the offshore production is based on a Production Sharing 
Agreement (PSA). 
Natural  gas  plays  an  important  role  in  Pakistan’s  economy,  meeting  over  50%  of  the 
country’s demand for commercial energy.7  However, despite the healthy share of gas in 
the  energy  mix,  piped  gas  is  available  to  only  about  18%  of  the  population  of  the 
country. At present, natural gas accounts for 57% of the energy supply requirements of 
the domestic sector, 53% for the commercial sector, 57% for the industrial sector (which 
could  be  even  higher  sans  forced  winter  supply  curtailment),  13.6%  for  the 
transportation sector (in the form of CNG), and 57% of the fuel used in thermal power 
generation.  In  addition,  the  fertilizer  sector  utilizes  12.6%  of  the  total  gas  supply  as 
feedstock.  The  annual  compound  growth  rate  (ACGR)  for  gas  consumption  during  the 
period 2001‐2007 was almost 8.2%.8   
Liquefied  petroleum  gas  (LPG)  use  in  Pakistan  has  been  growing  at  an  ACGR  of  12.6% 
over  the  period  2001‐2007,  and  is  used  mainly  in  the  domestic  (67%)  and  commercial 
(31%)  sectors  as  a  heating  fuel.  In  urban  and  rural  areas  not  connected  to  the  gas 
pipeline network, LPG is the preferred substitute and is sold at its economic cost. As it is 
the  less  developed  areas  that  generally  lack  gas  pipeline  connections,  it  is  the  poorer 
strata of the urban and rural population has to rely on non‐subsidized LPG, with those 
that cannot access or afford it resorting to traditional biomass fuels. 

3.1.2 Oil 
Oil is an important component of Pakistan’s energy economy with its 30% share in the 
national primary energy supplies. While Pakistan’s current gas reserves are ranked sixth 
highest  amongst  Asia‐Pacific  countries,  its  oil  reserves—at  a  modest  353.4 million  US 
barrels—are inadequate to meet the country’s needs. Pakistan thus has to depend upon 
imports of crude oil, furnace oil (FO) and high‐speed diesel (HSD) to the extent of 73.4% 
of  its  requirements  (in  FY2007)  for  these  commodities.  During  FY2007,  Pakistan 
imported crude oil and petroleum products worth US$ 7.45 billion, out of which refined 
                                                       
7
  Pakistan Energy Yearbook 2006, Hydrocarbon Development Institute of Pakistan (HDIP), Islamabad, 2007. 
8
  Ibid. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  203
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

petroleum  products  accounted  for  US$ 3.67 billion.  About  US$ 849 million  surplus 


petroleum  products,  including  naphtha  and  motor  gasoline,  were  exported  during  the 
same period. The seasonal nature of energy demand in the country, and seasonal as well 
as annual variations in hydel power generation, make the oil sector a critical element in 
the nation’s energy management and security concerns. 
Pakistan  has  fairly  well‐developed  infrastructure  for  meeting  the  requirements  of  its 
growing  energy  markets.  This  consists  of  port  handling  facilities,  a  network  of  trunk 
pipelines  transporting  over  12 MMTPA  (million  tonnes  per  annum)  of  crude  oil  and 
products,  seven  refineries  operating  with  a  combined  capacity  of  13.2  MMPTA,  72 
storage depots with a combined storage capacity of 2.8 million tonnes, and a network of 
6,087  retail  outlets  operated  by  nine  oil  marketing  companies  (OMCs).  During  FY2007, 
local  refineries  processed  11.2 million tonnes  of  crude  oil,  of  which  3.1 million tonnes 
(663,392 barrels/day) were produced indigenously and the rest imported. The average 
utilization of refining capacity in the country thus remained at 85% of available capacity. 
Karachi is the only seaport in the country with two port terminals, i.e., Karachi Port and 
Port Qasim, which have a combined operational handling capacity of 35 million TPA.9   

3.1.3 Coal 
Pakistan is potentially rich in coal resources. According to the estimates summarized in 
Exhibit 3, Pakistan’s potential coal reserves exceed 185 billion tonnes. Current domestic 
production,  however,  is  only  3.6  million  tonnes/year,  confined  to  small  deposits 
scattered  throughout  the  country,  and  meets  about  45%  of  the  local  demand  which 
exceeds  7.5  million  tonnes/year.  The  quality  of  coal  mined  is  generally  poor,  and  it  is 
mainly  utilized  in  the  brick  and  cement  industries.  Some  small‐scale  coal‐fired  power 
generation units that were installed in the 1950s were later de‐commissioned as natural 
gas became increasingly available in the country. A power plant of 150 MW capacity has 
been installed by WAPDA at Lakhra in Sindh with Chinese assistance, based on fluidized 
bed  technology.  Capacity  utilization  of  this  plant,  however,  has  been  low  and  it  has 
remained inoperative for extended periods on account of equipment breakdowns.  

Exhibit 3: Coal Reserves, FY2007 
Province/ Reserves Heating Value
Region Million Tonnes Btu/lb
Sindh 184,623 5,219-13,555
Balochistan 217 9,637-15,499
Punjab 235 9,472-15,801
NWFP 90 9,386-14,217
AJK 9 7,336-12,338

Total 185,173

Source: Geological Survey of Pakistan and Pakistan Energy Year Book 2007, 
Hydrocarbon Development Institute of Pakistan (HDIP), Islamabad: 2008. 

                                                       
9
  A second new deep‐water port at Gwadar has not become fully operational yet. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  204
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

As  indicated  in  Exhibit  3,  the  bulk  of  Pakistan’s  coal  reserves  are  located  in  the  Sindh 
province, most of which are associated with the Thar field located in southern Sindh. In 
view  of  the  availability  of  coal  resources  in  the  country,  and  consistent  with  the 
government’s strategy to diversify the fuel mix and to base further expansion of power 
generation capacity on least‐cost principles, the GoP has now given high priority to the 
development  of  coal‐based  power  generating  capacity  in  Thar.  In  the  Medium  Term 
Development  Framework  2005‐10,  a  target  of  10,000  MW  of  coal‐based  power 
generation capacity has been set out to be achieved by 2020. The option of producing 
pipeline quality gas and liquid fuels from coal is also under active consideration, in view 
of the heavy national dependence on imported oil and petroleum products 
The Thar coal resource, however, presents challenges in mining and utilization that are 
related to its high salinity and moisture content, a high stripping ratio, the presence of 
multiple  aquifers,  and  a  high  risk  of  spontaneous  combustion.  While  these  reserves 
present  an  opportunity  for  supplying  indigenous  primary  energy,  extensive 
investigations and development efforts will be required to convert this resource into a 
sustainable fossil fuel reserve. 

3.1.4 Electricity 

Power Generation 
The  installed  electricity  generation  capacity  in  Pakistan  in  2007  was  19,420  MW, 
producing 98,384 GWh, and has been largely stagnant at this level for the previous three 
years.10    The  primary  energy  sources  utilized  for  power  production  are  natural  gas 
(36.4%), hydro (32.5%), oil (28.5%), nuclear and imported (2.5%), and coal (0.1%). 
The  WAPDA  system,  including  independent  power  producers  in  its  service  territory, 
represented 90% of Pakistan’s total installed generation capacity with the KESC system 
making up the remainder (Exhibit 4). At present, countrywide shortfalls in power supply 
are  a  daily  reality.  For  instance,  the  system  peak  load  deficit  was  978  MW  on  May  2, 
2007. This compares with the estimated underrated power capacity of 800 MW. 
To  meet  projected  electricity  demand,  Pakistan’s  power  generation  requirements  are 
expected to grow to 162,590 MW by 2030, or an average increment of 5,700 MW per 
year. This would pose a real challenge to the economy and provide a compelling reason 
to seriously include renewable energy and energy efficiency as a way of minimizing the 
cost  of  additional  electricity  and  fuel  supplies,  as  well  as  the  substantial  associated 
economic risks of failing to achieve the capacity installation target. 

Transmission and Distribution 
In  March  2007,  at  the  national  transmission  level,  power  losses  (including 
transformation  and  grid  stations  losses)  were  8%  of  the  net  generated  power,  an 
increase over the year before, where losses stood at 7.6%. In the same month, losses in 
distribution  added  up  to  18.2%  in  2007  and  19.1%  in  2006.  Total  transmission  and 
distribution (T&D) losses amounted to 23.2% in 2007 and 25.0% in 2006. 
                                                       
10
  The last significant capacity addition to the country’s power generation capacity was the 1,450 MW Ghazi‐Barotha 
hydroelectric project commissioned in 2004. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  205
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 4: Installed Power Generation Capacity, FY2007
System Capacity
WAPDA MW

Hydro (WAPDA and Others) 6,479


Thermal (GENCOs) 4,900
Thermal (IPPs) 5,560

Nuclear (PAEC CHASHNUPP) 325

Subtotal (WAPDA System) 17,264

KESC MW

Thermal (KESC) 1,756


Thermal (IPPs) 262

Nuclear (PAEC KANUPP) 137

Subtotal (KESC System) 2,155

Total Installed Capacity 19,420

Source: Pakistan Energy Yearbook 2007, Hydrocarbon Development Institute of Pakistan (HDIP), 
Islamabad: 2008. 

T&D  losses  are  a  mix  of  ‘technical’  and  ‘non‐technical’  losses.  Technical  losses  require 
investments in infrastructure in order to bring them down to an acceptable level. Non‐
technical  losses  are  a  consequence  of  mismanagement  and  illegal  connections  (i.e., 
theft),  which  hopefully  the  privatization  of  distribution  companies  should  significantly 
contribute in redressing. In the meantime, important efforts to improve the situation are 
being made with modest year‐on‐year improvements. 
As  part  of  its  infrastructure  development  efforts,  the  GoP  has  initiated  an  important 
investment program to improve the electricity T&D system in the country. This program 
is to be implemented during the period 2007‐2016 at a total cost of US$ 3.9 billion, of 
which  the  ADB,  under  its  Power  Transmission  Enhancement  Investment  Program  for 
Pakistan,  is  providing  US$ 800  million.  The  World  Bank,  in  collaboration  with  four 
electricity  distribution  companies  (DISCOs),  is  also  currently  preparing  a  project  to 
reduce  secondary  transmission  and  distribution  energy  losses.  The  DISCOs  have 
prepared  their  component  evaluation  that  includes  both  technical  investments  and 
administrative/managerial  measures.  Loss  reduction  has  potentially  been  estimated  in 
one case to improve from 15% to 12.2%, and in another from 25% to 21.5%. 

3.1.5 Alternative and Renewable Energy 
Pakistan  has  not  yet  been  able  to  successfully  attract  significant  private  sector 
investments in renewable energy generation. The AEDB, the body created specifically for 
this function, has so far focused almost exclusively on wind power IPPs, which have been 
dogged by tariff disputes (see Section 3.6.2) and other operational issues, even though 
substantial  additional  incentives  have  been  on  offer  from  the  GoP  (e.g.,  concessional 
land  leases,  wind  speed  risk  cover,  power  evacuation  guarantees,  fiscal  exemptions, 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  206
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

etc.). However, it is anticipated that these issues will be eventually resolved, and at least 
a handful of wind IPPs will be able to break ground in the coming year. 
Small  hydro  schemes  have  traditionally  been  the  preserve  of  provincial  governments, 
with  several  hundred  micro  hydel  turbines  having  been  installed  primarily  in  the 
northern  mountainous  regions  by  SHYDO,  NAPWD,  and  AKRSP.  The  ADB  has  recently 
processed a loan of US$ 110.4 million11 for eight run‐of‐the‐river mini and small hydro 
projects, both high‐ and low‐head, in the NWFP and Punjab provinces, while its private 
sector financing is involved in the first medium‐sized hydro IPP in Pakistan, the US$ 125 
million 84 MW New Bong Escape project in AJK. These pioneering projects are expected 
to  set  the  stage  for  greater  private  sector  involvement  in  tapping  Pakistan’s  large 
hydroelectric potential (estimated to be over 45,000 MW) based on large rivers, smaller 
tributaries and mountain streams, and the country’s extensive irrigation canal system. 
The New Zealand government is currently financing a pilot‐scale biomass conversion and 
power  generation  project  at  the  Landhi  cattle  colony  in  Karachi,  based  on  methane 
production from animal waste, which has substantial scale‐up and replication potential 
at similar dairy farms in the country. Some initial assessments for municipal solid waste‐
to‐energy  and  landfill  methane  recovery  are  also  being  conducted  in  the  major  cities. 
The country has recently experimented with limited sales of ethanol‐blended gasoline in 
Karachi,  Lahore,  and  Islamabad.  Biomass,  waste,  and  biofuel  resources  represent  a 
promising future alternative energy market for Pakistan, depending on how quickly the 
GoP  can  develop  the  necessary  policy  and  support  infrastructure  for  private  sector 
participation in such supplies and services. 
The  market  potential  is  particularly  high  for  exploiting  solar  energy,  both  photovoltaic 
and  thermal  systems,  where  current  deployment  of  such  systems  is  very  limited. 
Recently  introduced  ‘net  metering  and  sales’  permitting,  which  allows  injection  of 
surplus, small‐scale generation to the grid at attractive rates, when properly developed 
and paired with suitable end‐user financing, could open up a huge market for rooftop PV 
panels in Pakistan, especially in grid‐connected localities, for servicing non‐time critical 
and  daytime  loads  (water  pumping,  fans,  etc.),  thereby  helping  supplement  electricity 
provision, shift peak loads, and reduce consumer bills. Thermal water heating, again in 
combination with gas heating, could also find ready acceptance by both gas utilities and 
their domestic customers. Commercial use of RE (in industry and large buildings) could 
also  be  implemented  through  a  combination  of  incentives,  support  products  and 
services, and appropriate regulations. 

3.2 Consumption and Sector­wise Demand 
In  FY2007,  the  consumption  of  natural  gas  in  Pakistan  was  3,348 MMscfd,  recording  a 
0.1%  decrease  as  compared  to  the  previous  year  due  to  supply  constraints,  which  fell 
short of system‐wide demand by approximately 700 MMscfd. 
Pakistan  consumed  16.8  million  tonnes  of  petroleum  products  during  FY2007, 
registering  an  overall  growth  of  15%  compared  to  the  previous  year.  The  country’s 

                                                       
11
  Out of a total project cost of US$ 149.9 million, including funding for additional feasibility studies and institutional 
capacity building. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  207
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

economic  revival  triggered  increased  consumption  of  furnace  oil  and  light  diesel  oil 
(LDO)—by  46%  and  9%,  respectively—in  the  power  and  agricultural  sectors.  However, 
the impact of higher oil prices was reflected in the demand for petroleum products, as 
the combined demand for motor gasoline, HSD, kerosene and aviation fuel decreased by 
1.3%  in  FY2007.  The  shortage  of  gas  for  power  generation  was  the  other  factor 
responsible  for  the  high  consumption  of  furnace  oil.  The  demand  was  met  through 
import of 8.2 million tonnes of crude oil and 8.3 million tonnes of petroleum products, 
costing the country US$ 7.4 billion in foreign exchange. 
In  FY2007,  coal  imports  recorded  an  increase  of  73%  (excluding  supply  for  Pakistan 
Steel),  contributing  to  an  overall  increase  of  2.3%  in  the  consumption  of  coal  over 
FY2006 as local coal production recorded a drop of 25% over the previous year. 
Electricity consumption in FY2007 was around 72,712 GWh, as compared to 67,603 GWh 
in the preceding year, thus recording an increase of 7.6%. Major increases occurred in 
domestic, industrial and commercial electricity consumption. 

3.2.1 Industrial Sector 
The  industrial  sector  represented  43%  of  the  total  commercial  energy  consumption  in 
Pakistan  during  2006‐07,  a  share  that  remained  unchanged  from  the  previous  year. 
Energy  supply  to  industry  was  based  on  oil  products  (10.3%),  gas  (52.6%),  electricity 
(10.9%), and coal (26.3%).  
In  2005,  the  total  number  of  industrial  electricity  connections  in  Pakistan  was  over 
226,000, of which 99% had loads under 70 kW supplied through the 11 kV and 440 kV 
distribution  network.  The  balance  of  industrial  consumers  was  supplied  through 
dedicated  feeders,  and  accounted  for  about  52%  of  the  total  consumption  in  the 
industrial sector.  
The share of industry in total electricity consumption in Pakistan has decreased over the 
past  ten  years,  and  is  currently  28%  for  WAPDA  and  36.7%  for  KESC,  compared  with 
34.7%  and  40%,  respectively,  in  1990.12    This  seems  contradictory,  however,  to  recent 
economic growth trends in Pakistan. Beginning at the turn of the century, Pakistan has 
entered  a  period  of  strong  economic  development:  between  2000  and  2004,  the 
industrial  sector  improved  its  share  of  GDP  from  22.6%  to  24.5%,  whereas  agriculture 
declined from 26.2% to 23.3%. The manufacturing sector increased from 14.8% in 1999‐
2000  to  17.5%  in  2003‐2004,  with  private  sector  real  investment  in  large‐scale 
manufacturing registering a 25.4% increase in 2003‐2004. Thus, although the decreasing 
portion  of  industry  in  total  electricity  demand  apparently  does  not  seem  to  fit  this 
economic  evolution,  it  indicates  an  even  faster  rise  in  power  consumption  by  other 
categories, particularly the domestic sector.  

3.2.2 Residential Sector 
In  FY2006,  the  domestic  sector  in  Pakistan  comprised  over  14  million  households,  up 
from 8 million a decade ago. The most dominant household energy mix changed from 

                                                       
12
  Raza,  HA,  Energy  Security  for  South  Asia:  Pakistan,  SAARC  Working  Group  on  Energy,  Hydrocarbon  Development 
Institute of Pakistan, Islamabad. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  208
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

kerosene‐biomass‐electricity  in  1994  to  biomass‐electricity  in  the  subsequent  survey 


years. Natural gas‐electricity, undoubtedly the top combination in the so‐called ‘energy 
ladder’,  moved  from  being  the  fourth  most  prevalent  energy  mix  in  the  first  three 
surveys  to  second  in  2001.13    Consequently,  in  FY2007,  of  the  total  domestic  energy 
consumption of 7.6 MTOE, oil accounted for only 1.4% while natural gas and electricity 
represented  57%  and  35.7%,  respectively,  followed  by  LPG  at  5.8%.  Currently,  the 
domestic sector accounts for approximately 45.8% of total electricity consumption in the 
country. 
Electricity  is  available  to  about  50%  of  Pakistan’s  population  (see  Exhibit  21),  and  the 
average consumption per household is currently 172 kWh per month. More than 80% of 
households  with  access  to  electricity  had  incomes  of  less  than  Rs  4,500  a  month  and 
consumed on average 60 kWh per month. 14% of electrified households, with household 
incomes  of  up  to  Rs  7,500  a  month,  consumed  on  average  180  kWh  per  month.  The 
remaining  6%  are  urban  households  that  can  afford  air  conditioners  and  other 
appliances, consuming an average of 1,650 kWh monthly.  
Electricity  tariff  rates  for  household/residential  consumers  are  still  subsidized  by  the 
GoP.  Based  on  data  provided  by  WAPDA  and  electricity  distribution  companies,  the 
average  rate  for  residential  users  was  Rs  3.34/kWh  (less  than  US$ 0.06/kWh)  during 
FY2003.  The  cost  of  supply  to  households  was  well  in  excess  of  US$ 0.08/kWh.  In 
FY2006, this subsidy translated into an annual cost for the GoP of over Rs 80 billion. This 
is  a  situation  where  using  distributed  renewable  energy,  along  with  energy  efficiency 
and  demand  management  programs,  as  a  buffer  may  help  public  authorities  to 
rationalize household tariffs to reflect their true economic value. 

3.2.3 Commercial Sector 
During the year 2006‐07, the commercial sector consumed 1.38 MTOE, or 3.8%, of the 
total commercial energy supply in Pakistan, mainly gas (53.3%), electricity (31.7%), and 
LPG (15%). This sector had over 2.1 million electricity consumers, with an estimated 92% 
of  small‐  and  medium‐sized  shops  consuming  approximately  60 kWh  per  month.  It  is 
possible, however, that a significant number of commercial establishments are currently 
registered as ‘residential’ to take advantage of the subsidized tariff. 

3.2.4 Transportation Sector 
The transportation sector in Pakistan consumed a total of 9.72 MTOE of energy supplies 
in  FY2007, divided between high speed diesel (68.4%), natural gas (13.6%), motor spirit 
(12.2%),  aviation  fuel  (5.6%),  with  others  (HOBC,  kerosene,  LDO,  furnace  oil,  and 
electricity) contributing the remainder. 
In  2007,  Pakistan  became  the  second‐largest  user  in  the  world  of  compressed  natural 
gas  (CNG)  as  a  transportation  fuel, with  1.55  million  vehicles,  or  a  quarter  of  the  total 
number,  employing  this  technology  on  its  roads.14    In  2006,  Pakistan  consumed  130 
                                                       
13
  ESMAP, Household Use of Commercial Energy, The World Bank, February 2006. 
14
  Just  behind  Argentina  with  1.65  million  and  ahead  of  Brazil  with  1.425  million  CNG  vehicles,  according  to  the 
International  Association  of  Natural  Gas  Vehicles  (IANGV).  By  some  estimates,  Pakistan  is  slated  to  become  the 
leading country in world rankings before end‐2007. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  209
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

million cubic feet per day of natural gas as CNG for transportation, which formed 10% of 
all  road  transport  fuels,  while  gasoline  constituted  14%  and  diesel  oil  76%.  There  are 
currently  1,700  CNG  fueling  stations  in  the  country,  65%  of  which  are  dedicated  CNG‐
only stations while 35% are co‐located with liquid fuel dispensing sites, with 200 more 
under construction and some 4,000 new license applications pending. 
The  development  of  the  CNG  industry  in  Pakistan  has  been  achieved  not  through 
government  directives  but  through  market‐oriented  policy  instruments  and  consumer 
choice. Higher gasoline prices (presently the price of CNG represents 46% of the market 
price for gasoline) gave a solid push to a market switchover from gasoline to CNG. Other 
policy incentives, such as deregulated pricing of CNG, liberal licensing, investor‐friendly 
institutional  support,  and  tax  and  duty  exemption  on  conversion  kits  and  dispensing 
equipment, were equally responsible for this dramatic, en masse fuel substitution. Both 
users  as  well  as  private  investors  have  been  quite  enthusiastic  and  responsive  to  the 
CNG policy regime. As a result, an investment of US$ 500 million has been made by the 
private  sector,  mostly  small  and  medium  enterprises,  in  establishing  the  required 
infrastructure for refueling, conversion and manufacturing, and about 28,000 new jobs 
have been created in this industry. 

3.2.5 Agriculture Sector 
Total  energy  consumption  in  the  country’s  vast  agricultural  sector  amounted  to  only 
0.77 MTOE in 2006‐07, consisting mostly of electricity (86.8%) and oil (13.2%). Electricity 
is  mainly  used  in  the  agricultural  sector  for  tubewells  for  irrigation  as  well  as  for  the 
control  of  salinity  and  water  logging.  The  bulk  of  agricultural  consumption  is  in  the 
WAPDA  system.  Agricultural  consumers  account  for  about  12.1%  of  total  electricity 
consumption in the country. High growth rates in electricity demand were seen in this 
sector  during  1985‐1989  (e.g.,  27.3%  in  1998),  and  were  primarily  due  to  the 
introduction of a flat‐rate retail agricultural tariff. Negative growth rates were witnessed 
during 1998 to 2000, as the utility withdrew flat rates for the tubewells and most private 
tubewells converted to diesel oil operation.15  On average, tubewell efficiencies remain 
low and can be significantly improved, while this sector could also benefit greatly from 
dispersed renewable energy supplies, particularly micro hydel, wind, and biogas. 

3.3 Resource Potential and Infrastructure 
The country’s oil and gas reserves are dominated by natural gas that has a 90% share in 
the  total  hydrocarbon  reserves  on  an  energy‐equivalent  basis.  At  present  rates  of 
production,  Pakistan’s  proven  oil  and  gas  reserves  are  estimated  to  last  for  14  and  21 
years, respectively. 
Pakistan’s total recoverable gas reserves are estimated at 32.4 trillion cubic feet (Tcf), as 
of  June  2007.  Natural  gas  production  during  FY2007  was  3,873  million  standard  cubic 
feet  per  day  (MMscfd),  showing  a  1%  increase  from  the  previous  year.  Pakistan 
possesses  an  extensive,  well‐developed  gas  transmission  and  distribution  network 
operated  by  two  utilities:  the  Sui  Northern  Gas  Pipelines  Ltd.  (SNGPL)  and  the  Sui 
                                                       
15
  Raza,  HA,  Energy  Security  for  South  Asia:  Pakistan,  SAARC  Working  Group  on  Energy,  Hydrocarbon  Development 
Institute of Pakistan, Islamabad. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  210
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Southern  Gas  Company  Ltd.  (SSGCL).  In  addition,  there  exists  an  independent  gas 
network supplying low‐Btu gas from dedicated gas fields, such as Mari and Kandhkot, to 
a number of power and fertilizer plants. 
Indigenous  crude  oil  reserves  are  estimated  at  353  million  barrels  as  of  June  2007. 
Average daily oil production was 65,577 barrels in FY2007, recording an increase of 2.8% 
over the last year, but still meets only 17% of the total demand for the country. Pakistan 
is thus heavily dependent on import of crude oil, furnace oil (FO) and high‐speed diesel 
(HSD).16  Local crude oil falls in the API gravity range of 25‐50, with some exceptions. In 
addition to crude oil, Pakistan also produces oil and gas condensate from various fields 
across the country. Both domestically produced crude oil and condensate are processed 
in  local  refineries,  which  are  designed  for  medium  and  light  crudes,  except  Attock 
Refinery Limited, which can process heavier crude oil. 
Although,  the  country  is  rich  in coal  resources, estimated  to  be  185 billion  tonnes,  the 
share of coal in the total energy mix is currently a meager 7%. These coal reserves are 
largely attributed to the Thar deposits which, at an estimated 175 billion tonnes, are the 
third‐largest in the world. Proper estimation of the quality, scale, and economics of Thar 
coal will only be known after detailed test pit investigations are undertaken. 
Pakistan’s energy resource potential is illustrated in Exhibit 5. The reserve‐to‐production 
ratio  is  currently  14  and  21  for  oil  and  gas,  respectively,  while  for  coal  it  is  678.  Only 
about  16%  of  the  country’s  available  hydel  potential  has  been  realized  so  far.  As 
mentioned earlier, there are major unexploited reserves of coal in the Thar Desert in the 
Sindh  province.  The  development  of  these  reserves,  however,  presents  significant 
challenges:  the  coal  is  of  relatively  low  quality  with  a  heating  value  of  5,700  Btu/lb, 
sulfur content of over 1%, ash over 6%, and moisture of about 50%. The overburden to 
be  removed  to  access  the  coal  seams  is  soft  and  has  a  depth  of  between  175  to  230 
meters,  indicating  the  need  for  capital  intensive  open‐pit  mining.  Limited  water 
availability in the area also poses a challenge, while substantial infrastructure needs to 
be  put  in  place  before  investment  in  coal  mining  and  coal‐based  power  generation  at 
this remote location can take place. 
There  is  increasing  recognition  of  the  economic  benefits  associated  with  hydropower 
generation and storage of water for agricultural use. The government’s plans, therefore, 
include an aggressive hydroelectric power development program. Most of the potential 
sites are in the mountainous regions in the north of the country, where construction of 
access roads and resettlement of affected populations pose significant challenges. 
In view of the outlook, risks, timeline, and costs of initiating large‐scale exploitation of 
the domestic energy resource base, Pakistan has given high priority to tapping regional 
energy supplies as a near‐term solution to meeting its energy requirements, and several 
projects for the import of natural gas from countries in the Middle East and Central Asia 
have received serious attention recently. These include pipelines for import of gas from 
Turkmenistan, Iran, and Qatar, respectively. Liquefied natural gas (LNG) import projects 
are  also  being  implemented.  In  addition,  import  of  power  from  Tajikistan  and 

                                                       
16
  Although local crude production may double in a few years’ time on account of sizeable recent discoveries in Kohat 
district in the north of the country. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  211
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Kyrgyzstan,  which  are  rich  in  hydel  resources,  is  also  under  active  consideration.  The 
development  of  these  options  for  importing  energy  has  been  constrained  by  the 
sensitive  regional  security  environment,  volatility  in  the  international  energy  market, 
and the complexities associated with the formulation and implementation of large cross‐
border energy transactions. 

Exhibit 5: Indigenous Energy Resource Potential, FY2007 

Resource Estimated Energy


Potential Content

Oil 353 million bbl 47 MTOE

Gas 28 Tcf @ 900 605 MTOE


Btu/scf

Coal, Measured 3,303 MT 1,477 MTOE

Coal, Inferred 56,382 MT 25,220 MTOE

Coal, 113,798 MT 50,903 MTOE


Hypothetical
Oil Gas Coal
Installed Hydel 6,479 MW Measured

Potential Hydel 41,722 MW

 
Fuel Annual Production Reserves-to-Production Ratio

Oil 25 million bbl 14

Gas 1.4 Tcf @ 900 20


Btu/scf

Coal 3.64 MT 907

Hydel Potential 16%


Realized

Source: Pakistan Energy Yearbook, 2007, Hydrocarbon Development Institute of Pakistan (HDIP), Islamabad: 2008 
Pakistan Hydel Power Potential, Private Power and Infrastructure Board (PPIB), Islamabad: Undated. 

Pakistan has a fairly well‐developed energy infrastructure. The natural gas transmission 
infrastructure connects to over 4 million households and commercial establishments, in 
addition to the bulk of the industries and thermal power generating units in the country, 
and  includes  about  10,000  km  of  high‐pressure  transmission  pipelines  and  about 
250,000 hp of compression capacity. A network of oil pipelines transports crude oil and 
products to inland refineries and market centers. The ports at Karachi are equipped to 
handle  import  of  crude  oil  and  petroleum  products  in  large  enough  volumes  that 
account for a major fraction of the country’s consumption, as well as limited quantities 
of  coal.  The  power  transmission  and  distribution  network  serves  over  16  million 
residential, commercial, and industrial customers, and includes over 40,000 km of high 
tension transmission lines.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  212
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.4 Sector Organization 
Pakistan’s  energy  sector  is  administered  largely  through  federal  government ministries 
and  agencies.  Provincial  government  involvement  is  restricted  to  small‐scale  power 
generation  (<50  MW  capacity  plants),  to  exploration  and  mining  leases  for  natural 
resources  other  than  oil  and  gas  (i.e.,  coal),  and  to  permitting  for  renewable  energy 
projects (wind, hydel, etc.). 

3.4.1 Government Agencies 
Exhibit 6 provides a list of government agencies that are directly or indirectly relevant to 
the  management  and  development  of  Pakistan’s  energy  policies,  resources, 
infrastructure, and end uses. 
The  Planning  Commission  is  responsible  for  overall  energy  planning  and  infrastructure 
development  in  the  country.  It  is  supported  by  the  Energy  Wing  of  the  Planning  and 
Development  Division  for  technical  advice  and  approval  of  all  public  sector  energy 
investments. 
The  Ministry  of  Water  and  Power  (MoWP)  is  the  GoP’s  executive  arm  for  all  issues 
relating to electricity generation, transmission and distribution, pricing, regulation, and 
consumption in the country, and exercises this function through its various line agencies 
as well as relevant autonomous bodies and utilities. It also serves to coordinate and plan 
the  nation’s  power  sector,  formulate  policy  and  specific  incentives,  and  liaise  with 
provincial  governments  on  all  related  issues.  Through  the  Private  Power  and 
Infrastructure Board (PPIB) and the Alternative Energy Development Board (AEDB), the 
Ministry  provides  private  investors  with  one‐window  facilities  for  undertaking 
conventional and renewable IPPs, respectively. 
The  Pakistan  Atomic  Energy  Commission  (PAEC),  an  autonomous  agency,  is  exclusively 
responsible for the country’s civilian nuclear power program.  
The Ministry of Petroleum and Natural Resources (MoPNR), likewise, administers the oil 
and  gas  sector  through  its  various  technical  directorates.  Oil  and  gas  exploration  and 
production policies, concessions, and licenses are managed by the MoPNR, while those 
for  other  minerals,  including  coal,  are  the  preserve  of  provincial  governments.  The 
Hydrocarbon  Development  Institute  of  Pakistan  (HDIP)  is  the  principal  GoP  agency  for 
compiling national energy statistics as well as for R&D in fossil fuel applications. 
The  Ministry  of  Environment  (MoE),  through  the  newly  established  CDM  Cell,  is  the 
Designated National Agency (DNA) for Clean Development Mechanism (CDM) projects in 
the  country  and  for  climate  change‐related  policies  and  activities.  The  Pakistan 
Environment  Protection  Agency  (Pak  EPA)  also  serves  as  one  of  its  line  agencies  and 
technical arms, as does ENERCON, the National Energy Conservation Centre, responsible 
for promotion of energy efficiency and conservation in the country. 
The Ministry of Science and Technology (MoST), through its various line agencies, is also 
engaged in energy‐related research, standardization, and certification. Other ministries, 
such  as  those  for  industries,  communications,  railways,  housing,  and  food  and 
agriculture, are also relevant for policies, incentives and facilities impacting energy use 
and energy efficiency in the key areas of industry, transportation, farming, and buildings. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  213
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 6: GoP Agencies Relevant to Energy Production, Management and End Use 
Agency Subordinate Agency/Department

Planning Commission Planning and Development (P&D) Division (Energy Wing)


Ministry of Water and Power Water and Power Development Authority (WAPDA)
Private Power Infrastructure Board (PPIB)
Alternative Energy Development Board (AEDB)
Ministry of Petroleum and Directorate General, Gas (DGG)
Natural Resources Directorate General, Oil (DGO)
Directorate General, Mineral (DGM)
Directorate General, Petroleum Concessions (DGPC)
Hydrocarbon Development Institute of Pakistan (HDIP)
Ministry of Environment National Energy Conservation Centre (ENERCON)
CDM Cell
Pakistan Environmental Protection Agency (Pak EPA)
Ministry of Science and Pakistan Council for Renewable Energy Technologies (PCRET)
Technology Pakistan Council for Scientific and Industrial Research (PCSIR)
Pakistan National Accreditation Council (PNAC)
Ministry of Industries, Pakistan Industrial Development Corporation (PIDC)
Production, and Special Engineering Development Board (EDB)
Incentives National Productivity Organization (NPO)
Small and Medium Enterprises Development Authority (SMEDA)
Ministry of Textile Industry
Ministry of Communications National Transport Research Centre (NTRC)
National Highway Authority (NHA)
Ministry of Railways Pakistan Railway (PR)
Ministry of Finance and Finance Division (Federal Board of Revenue, FBR)
Revenue Economic Affairs Division (EAD)
Ministry of Food, Agriculture, Pakistan Agriculture Research Council (PARC)
and Livestock National Agriculture Research Council (NARC)
Ministry of Housing and Works Public Works Department (PWD)
Pakistan Housing Authority (PHA)
Ministry of Defence Pakistan Armed Forces
Paramilitary, Border, Airport, and Maritime Security Forces
Civil Aviation Authority (CAA)
Pakistan International Airlines Corporation (PIAC)
Pakistan Meteorological Department (PMD)
Ministry of Defence Production Defence Production Division
Pakistan Atomic Energy
Commission (PAEC)
Provincial Governments Planning and Development Departments
Irrigation and Power (I&P) Departments
Mines and Mineral Development Departments
Environment Protection Departments
Resource Development Corporations/Authorities
Municipal Administrations and
Local Governments

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  214
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

City  planning  and  building  regulation,  which  can  potentially  influence  the  large 
residential  and  commercial  sector  energy  demand,  is  a  function  of  local  governments 
and municipal administration bodies. 
Finally, the Ministry of Finance and Revenue (MoFR), defines and approves all financial 
and  fiscal  terms  and  incentives  applicable  to  the  energy  sector,  including  the  tax  and 
customs regime (through the Federal Board of Revenue, FBR), investment terms, income 
and profit repatriation, etc. The MoFR, through its Economic Affairs Division (EAD), also 
coordinates all external assistance and IFI financing to the energy sector in the country. 

3.4.2 Utilities and Energy Providers 
A listing of relevant energy utilities and service providers in Pakistan is given in Exhibit 7, 
and the institutional organization of the main market segments briefly described below: 

Power 
The  power  market  in  Pakistan  is  undergoing  significant  long‐term  structural  reforms, 
with the ultimate objective of introducing a deregulated and efficient industry operating 
on  competitive  market  principles  with  the  full  participation  of  the  private  sector  in  all 
aspects  of  infrastructure  and  service  provision.  The  Water  and  Power  Development 
Authority  (WAPDA),  the  erstwhile  national  power  monopoly,  has  been  unbundled  into 
separate  generation,  transmission,  and  distribution  entities,17  while  the  vertically‐
integrated  utility  serving  the  Karachi  metropolitan  region,  the  Karachi  Electric  Supply 
Corporation  (KESC),  has  been  privatized.  These  corporatized  entities  have  been 
registered  with  the  Securities  and  Exchange  Commission  of  Pakistan  (SECP)  and  are 
managed  by  their  respective  boards  of  directors.  A  significant  IPP  and  captive  power 
generation capacity is also operational in the country, completely replacing new public 
investment  in  thermal  power  production,  with  planned  private  investment  also 
increasing in wind and small hydro projects. Independent power producers consist of 16 
thermal IPPs in operation, with several more in the pipeline, including the country’s first 
hydroelectric IPP project. WAPDA continues to oversee the construction and operation 
of  large‐  and  medium‐sized  hydroelectric  dams  for  power  production,  as  well  as  to 
manage their use for irrigation through its Water Wing. 

Oil and Gas 
The oil and gas industry in Pakistan consists of a mix of private and public sector entities 
that  fall  under  the  policy  and  administrative  control  of  the  Ministry  of  Petroleum  and 
Natural Resources (MoPNR) and are regulated by the Oil and Gas Regulatory Authority 
(OGRA). Within the MoPNR, the office of the Director General of Petroleum Concessions 
(DGPC)  is  responsible  for  the  award  and  management  of  oil  and  gas  exploration  and 
production  licenses  in  the  country  under  the  GoP’s  petroleum  policy,  which  is  revised 
from  time  to  time  (with  the  July  2007  version  currently  in  effect).  The  Oil  and  Gas 
Development Corporation (OGDC) and Pakistan Petroleum Ltd. (PPL) are the two state‐
owned  exploration  and  production  (E&P)  companies  that  are  together  responsible  for 

                                                       
17
  Consisting  of  four  generating  companies  (GENCOs),  one  T&D  company  (NTDC),  and  nine  distribution  companies 
(DISCOs), all operating under the administrative control of the Pakistan Electric Power Company (PEPCO). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  215
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

about  54%  of  oil  and  44%  of  natural  gas  production  in  the  country.  The  balance 
production of oil and gas is accounted for by about 11 companies in the private sector, 
with additional companies engaged in exploratory drilling. The Directorate General of Oil 
(DGO) is responsible for the administration of oil refining, import, distribution and retail 
operations in Pakistan. The Pakistan State Oil Company (PSO), accounts for about 70% of 
the  retail  oil  market,  with  the  bulk  of  the  balance  shared  by  three  private  sector 
companies. The Sui Northern Gas Pipelines Ltd. (SNGPL) and Sui Southern Gas Company 
Ltd. (SSGCL) are state‐owned corporations that together account for over 79% of the gas 
transmission and distribution operations in the country. Independently‐owned pipelines 
dedicated to supplying lower calorific value gas to power and fertilizer units account for 
the  remaining  business.  The  Directorate  General  of  Gas  (DGG)  in  the  MoPNR  is 
responsible for policy making and administrative management of the natural gas, LPG, 
and compressed natural gas (CNG) industry in the country. The LPG and CNG business is 
almost  entirely  owned  and  managed  by  the  private  sector.  The  government  is 
considering import of liquefied natural gas (LNG), by both the public and private sectors, 
under an LNG policy that is currently under preparation. 

Coal 
Development  and  utilization18  of  coal  resources  falls  under  provincial  governments’ 
jurisdiction, while actual mining and sales are carried out largely by the private sector, 
with  some  public  sector  participation.  The  country’s  large  lignite  deposits  at  Thar  are, 
under  the  aegis  of  the  Sindh  Coal  Authority,  moving  beyond  preliminary  stages  of 
mineability  assessment  to  more  detailed  evaluation,  and  will  likely  eventually  involve 
foreign  investments  for  full‐scale  commercial  exploitation.  Coal  is  also  imported  by 
private  companies,  as  well  as  large  consumers  such  as  the  Pakistan  Steel  Mills  for  its 
coking needs. 

Nuclear 
The  Pakistan  Atomic  Energy  Commission  (PAEC)  builds  and  operates  the  country’s 
civilian  nuclear  power  plants  and  conducts  related  fuel  production,  engineering  and 
maintenance,  training,  and  R&D  through  an  elaborate  network  of  specialized 
subordinate institutions and agencies employing a large pool of skilled manpower.  

Renewables 
Small hydro development has principally been undertaken by provincial agencies, such 
as  the  Sarhad  Hydel  Development  Organization  (SHYDO),  the  Northern  Areas  Public 
Works Department (NAPWD), and NGOs such as the Aga Khan Rural Support Programme 
(AKRSP), primarily in the mountainous north of the country. A number of grid‐connected 
wind IPPs are in late stages of project approval, but none have achieved financial closure 
so  far.  Some  pilot  and  demonstration‐scale  activity  is  also  underway  in  biomass 
conversion  and  waste‐to‐energy  based  power  generation,  while  the  country’s  sugar 
industry engages in bagasse‐based electricity production for self‐use as well as for sale 
to the grid. 
                                                       
18
  Coal  used  for  power  generation  is  managed  by  PPIB  and  WAPDA,  while  the  cement  and  brick  industry  purchase 
directly from coal producers. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  216
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 7: Energy Utilities and Suppliers 
Segment Supplier

Electric Power
Thermal, Hydel, and Nuclear Generating Companies (Thermal, 4)
Generation Independent Power Producers (Thermal, 16)
Water and Power Development Authority (WAPDA
Hydel)
Small Power Producers (Thermal)
Pakistan Atomic Energy Commission (Nuclear, 3)
High-Tension Transmission National Transmission and Dispatch Company
(NTDC)
Low-Tension Distribution Distribution Companies (9)

Oil and Gas


Exploration and Production E&P Companies (26)
Pakistan Petroleum Exploration and Production
Companies Association (PPEPCA)
Oil Pipeline Companies PakArab Refinery Company (PARCO)
Asia Pipelines Limited (APL)
Oil Refineries PakArab Refinery Company (PARCO)
National Refinery Limited (NRL)
Pakistan Refinery Limited (PRL)
Attock Refinery Limited (ARL)
Bosicor Pakistan Limited (BPL)
Dhodak Refinery Limited (DRL)
ENAR Petrotech Refinery (ERL)
Oil Marketing Companies Pakistan State Oil Company Limited (PSO)
Shell Pakistan Limited (Shell)
Chevron Pakistan Limited (Caltex)
Total-PARCO Pakistan Limited (Total)
Attock Petroleum Limited (APL)
Private Companies (4)
Gas Transmission and Distribution Sui Northern Gas Pipelines Limited (SNGPL)
Utilities Sui Southern Gas Company Limited (SSGC)
Mari Gas Company Limited (MGCL)
LPG Companies (58)
CNG Companies (5,476 site licenses)

Coal Thar Coal Company Limited


Lakhra Coal Development Company Limited
Coal Importing Companies

Renewables
Small Hydro Sarhad Hydel Development Organization (SHYDO)
Punjab Irrigation and Power (I&P) Department
Northern Areas Public Works Department (NAPWD)
Aga Khan Rural Support Programme (AKRSP)

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  217
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.4.3 Regulators 
The regulatory framework for the energy sector in Pakistan (Exhibit 8) is relatively new 
and  in  the  process  of  consolidating  powers  and  acquiring  technical  sophistication.  The 
National  Electric  Power  Regulatory  Authority  (NEPRA)  was  established  in  1997,  the  Oil 
and  Gas  Regulatory  Authority  (OGRA)  in  2002,  and  the  Pakistan  Nuclear  Regulatory 
Authority (PNRA) in 2001. These autonomous agencies, to varying degrees, are in need 
of  internal  capacity  building,  but  otherwise  fully  functional  and  with  their  roles 
established in price and procedure setting, licensing, performance and safety standards, 
operational accounting, and implementation of rules and penalties. Coal mine leases and 
operations  are  regulated  by  the  provincial  governments’  mineral  development 
corporations/authorities. 
In  addition  to  these,  several  other  regulatory  agencies  are  also  relevant  to  energy‐
related activities in Pakistan. The Pakistan Environmental Protection Agency (Pak EPA), 
established in 1984, is the apex regulatory body for all aspects relating to the quality of 
air, water, natural resources, and social environment in the country, and functions under 
the  Ministry  of  Environment.  Provincial  EPAs  are  responsible  for  such  functions  within 
their  geographical  jurisdictions,  and  may  augment  the  regulations  set  at  the  federal 
level. The country’s central bank, the State Bank of Pakistan, regulates monetary policy 
and  financial  institutions,  sets  prudential  guidelines,  defines  foreign  exchange 
transaction  and  repatriation  rules,  and  provides  foreign  investment  risk  cover  and 
guarantees,  where  applicable.  The  establishment,  certification,  and  regulation  of 
metrology, performance and quality standards, and testing is carried out by the Pakistan 
Standards  and  Quality  Control  Authority  (PSQA),  formed  in  2000;  its  effectiveness  in 
instituting  energy  efficiency  and  emissions  standards  for  equipment  and  materials, 
however, is presently very limited. Buildings and urban planning, and energy use therein, 
is regulated by the respective municipal administration of each city, and funded by the 
local  government  which  is  also  directly  involved  in  land  use  planning,  zoning,  and 
infrastructure investments. 

Exhibit 8: Relevant Regulatory Agencies 
Sector Regulating Agency

Electric Power National Electric Power Regulatory Authority (NEPRA)

Oil and Gas Oil and Gas Regulatory Authority (OGRA)

Nuclear Power Pakistan Nuclear Regulatory Authority (PNRA)

Standards Pakistan Standards and Quality Control Authority (PSQCA)

Environment Pakistan Environmental Protection Agency (Pak EPA)


Provincial EPAs/EPDs

Urban Planning and Local governments


Services Municipal administrations

Monetary and Prudential State Bank of Pakistan (SBP)

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  218
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.5 Policy Framework 
National  policies,  regulatory  measures,  and  legislation  that  impact  the  production  and 
use  of  energy  in  Pakistan  are  listed  in  Exhibit  9.  In  addition,  the  National  Transport 
Research  Centre  (NTRC)  is  currently  preparing  a  policy  for  road  transport,  including 
measures for system‐wide efficiency improvements, and a policy for the import of LNG is 
under preparation by the MoPNR. The current ADB TA (4881‐PAK) aims to formulate a 
comprehensive set of medium‐term policy measures for the development of renewable 
energy resources to succeed the 2006 RE IPP policy guidelines. 

Exhibit 9: Policy Framework Relevant to Energy Production and Use 
Policy Target Areas

Policy for Power Generation, 2002 Independent power producers (IPPs)

Pakistan Petroleum Policy, 2007 Oil and gas exploration and


production (E&P)

Policy for Development of Renewable Energy for On-grid RE IPPs


Power Generation, 2006

National Energy Conservation Policy, 2006 Demand-side management and


energy efficiency market

Pakistan Environment Protection Act, 1997 Clean, renewable energy use, and
National Conservation Strategy, 1992 resource conservation
National Environment Policy and Action Plan, 2005

National Environment Quality Standards (Revised), Point emissions and pollution control
1999

National Forest Policy, 2001 Biomass use and resource


conservation

Small and Medium Enterprise Policy, 2006 Energy efficiency and RE market

The existing policies focus largely on the production and management of energy supplies 
and related infrastructure investments, with those aimed at regulating the demand side 
relatively weak in specificity and enforcement. As a result, energy use in the country per 
se  is  not  regulated,  and  Pakistan  has  from  time  to  time  had  to  resort  to  mandatory 
energy quotas and usage restrictions when faced with severe supply constraints. These 
include  forced  outages  (‘load  shedding’),  where  the  supply  of  network  electricity  and 
natural  gas  itself  is  deliberately  rationed  out  to  ‘low’  priority  consumer  categories  in 
order  to  manage  seasonal  generation/production  shortages  or  grid  imbalances  due  to 
excess loads. Mandatory usage restrictions include, for example, the current (i.e., 2007‐
08) requirement of commercial close‐of‐business timings and a ban on billboard lighting. 
Such supply and usage regulation represents an extreme, short‐term coping mechanism 
and  therefore  varies  from  time  to  time  in  its  extent  and  severity,  depending  on  the 
prevailing supply shortfall. These methods, however, represent a simplistic and ad hoc 
approach  to  energy  use  management  which  extracts  a  real  and  unaccounted  for 
economic  cost  far  beyond  the  direct  impact  of  such  disruption,  which  can  instead  be 
better  managed  through  more  sophisticated  pricing,  DSM,  and  end‐use  regulation. 
However,  given  the  prevailing  electricity  supply  shortages  and  increasing  gas  demand, 
forced supply quotas and use restrictions are expected to continue in the near future. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  219
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.6 Comparative Costs 
This  section  presents  the  comparative  costs  of  energy  service  delivery  in  Pakistan  by 
resource  type.  Pakistan  is  considered  a  mature  energy  market  in  terms  of  its  well 
defined pricing structure at all levels of the supply chain.  

3.6.1 Production Costs 
Pakistan’s  indigenous  energy  supplies  currently  derive  from  natural  gas,  crude  oil, 
hydroelectric and nuclear power production assets. The country imports energy mainly 
in the form of crude oil, high‐sulfur fuel oil (HSFO), high speed diesel (HSD), and coal to 
meet  the  deficit  between  local  energy  production  and  national  demand  (Section  3.1). 
The  Government  of  Pakistan  has  offered  attractive  policies  for  private  investment  in 
almost all of these energy resources19 and set up institutions to facilitate developers. At 
the  same  time,  the  GoP  has  established  a  framework  for  the  determination  of  retail 
prices for imported energy supplies. A brief review of the procurement costs and pricing 
mechanism for both indigenous and imported energy resources is provided here.  

Crude Oil  
Crude oil is principally imported from Saudi Arabia, Iran, Abu Dhabi, and Qatar by local 
oil refineries on an international market‐based pricing formula. The prices of imported 
as well as local crude oil and petroleum products are thus vulnerable to fluctuations in 
petroleum product prices in the international market. During FY2007, the average price 
of  crude  oil  prevailing  in  Pakistan  based  on  this  arrangement  was  approximately 
US$ 62/bbl.  

Natural Gas   
The GoP fixes the wellhead price at which natural gas is purchased from producers by 
the gas utilities. The bulk purchase pricing formula for each gas field, in effect, depends 
on the pricing policy in force at the time the field discovery is declared commercial. All 
the fields that declared commercial production up to 1985 had their wellhead prices set 
on  a  ‘cost‐plus’  basis.  Thereafter,  between  1985  and  1994,  prices  of  all  new  gas 
discovered  were  generally  linked  with  the  carriage  and  freight  (C&F)  price  of  HSFO. 
However, under the 1994 Petroleum Policy, the producers’ prices were indexed with the 
C&F price of baskets of imported Arabian/Persian Gulf crude. The gas pricing mechanism 
has thus been revised in the past in the following manner: 
• 1985‐1991: Producer prices linked to 66% of HSFO price, less negotiated discount 
• 1991‐1992: Linkage increased to 75% of HSFO price, less negotiated discount 
• 1992‐1993: Linkage increased to 100% of HSFO price, less negotiated discount 
• 1993‐1994:  Floor  price  of  US$ 80  per  tonne,  plus  50%  of  remaining  equivalent 
HSFO price differential (if positive) 
• 1994 & 1997 Petroleum Policies: Based on geological prospects and available gas 
transmission  infrastructure,  the  country  was  divided  into  three  prospective 
                                                       
19
  Except for nuclear power generation, which is undertaken solely by the state. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  220
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

zones. Producer prices were linked to 77.5%, 72.5% and 67.5% of the price of a 
basket of imported crude oil for discoveries in Zones I, II and III, respectively.  
• December 1999: The GoP modified the gas‐pricing framework as spelt out in the 
previous  petroleum  policies  of  1994  and  1997.  A  new  inflection‐point  based 
pricing  framework  with  a  discounted  price  mechanism  was  defined.  This 
discounted price was applicable whenever the C&F price of a basket of imported 
Arabian/Persian Gulf crudes exceeded US$ 15/bbl during the six months prior to 
price notification. The details of this price‐discounting mechanism, also known as 
a sliding‐scale mechanism, are presented in Exhibit 10. 
• May  2000:  The  producer  price  mechanism  offered  in  December  1999  was 
modified  to  account  for  international  inflation  in  oil  prices.  The  discounting 
mechanism mentioned above is applicable for the first four years from the date 
of the signing of the Gas Sales Agreement (GSA), after which the inflection points 
of US$ 15‐20‐25/bbl are raised by US$ 1.  
• 2001  Petroleum  Exploration  and  Production  Policy:  The  formula  was  further 
modified by adding a ceiling price of US$ 36/bbl to the 1999 policy mechanism.  

Exhibit 10: Gas Price Discounting Mechanism 
Ruling Price Applicable Price
US$/bbl US$/bbl

Below US$ 10/bbl Fixed at US$ 10/bbl (floor)

US$ 10-15/bbl 100% of ruling price

US$ 15, plus 50% of the amount by which the price


US$ 15-20/bbl
exceeds US$ 15/bbl

US$ 17.50, plus 30% of the amount by which the price


US$ 20-25/bbl
exceeds US$ 20/bbl

US$ 19, plus 20% of the amount by which the price


Above US$ 25/bbl
exceeds US$ 25/bbl

Source: Directorate General Petroleum Concessions (DGPC), Government of Pakistan, Islamabad. 

It  is  expected  that  this  sliding‐scale  formula  will  continue  to  apply  to  new  pricing 
agreements, with modifications in the inflection points and ceilings to cater for oil price 
escalations.  Exhibit  11  illustrates  the  applicable  current  wellhead  gas  prices  for  fields 
supplying gas to the SNGPL, the SSGCL as well as independent fields dedicated to specific 
power and fertilizer plants in the country.  

Liquefied Petroleum Gas  
In 2006, the GoP linked the LPG base stock price to FOB Saudi ARAMCO Contract Price 
(CP)  for  propane  and  butane,  published  in  Platts  for  the  previous  month  taking  a 
propane‐butane ratio of 40:60. However, in December 2007, the GoP decided to use this 
price  as  a  ceiling  for  LPG  prices  in  the  country,  and  producers  were  allowed  to  offer 
discounts  on  these  prices  in  their  retail  operations.  The  average  local  market  price  of 
LPG, on June 30, 2007, stood at US$ 12.6/MMBtu.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  221
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 11: Wellhead Gas Prices (as of June 30, 2007) 
Wellhead Price
Field
US$/MMBtu

Adhi 1.50
Badar 2.25
Badin Deep Fields 3.20
Bhangali 2.10
Bhit 3.54
Bilal North & Bilal-1 2.23
Chanda 2.71
Dakhni 1.50
Daru 1.31
Dhodak 1.32
Dhurnal 0.27
Hasan 2.33
Kadanwari 6.95
Kandhkot 1.63
Kausar Deep-1, Usman, Umar
2.52
& Ali-1
Loti 1.41
Mazarani 1.75
Meyal 1.31
Miano 3.29
Naimat Basal & Siraj South 2.52
Nandpur 3.79
Pariwali 3.54
Pindori 3.54
Pirkoh 1.41
Qadirpur 2.71
Ratana 3.98
Rehmat 2.52
Sadkal 4.19
Sara/Suri 1.24
Sari Hundi 4.17
Sawan 3.29
Suri 1.63
Turkwal 3.54
Uch 3.92
Zamzama 3.20

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  222
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Petroleum Products 
Ex‐refinery  petroleum  products  are  priced  in  accordance  with  a  formula  based  on  the 
C&F  import  parity  prices  (IPP),  incidental  costs,20  and  import  duty.21    The  Ex‐refinery 
prices are determined by OGRA as part of the build up for determination of consumer 
prices. 
In  the  determination  of  the  IPP,  the  prices  of  naphtha,  HSD,  kerosene,  and  HSFO 
are taken  from  Platts.22    The  bases  of  the  prices  of  other  products  are  presented 
in Exhibit 12. 

Exhibit 12: Price Calculation of Petroleum Products Not Published by Platts 
Source: Oil industry and HBP market intelligence. 

Product Pricing Basis

JP-1 Kerosene + US¢ 1 per gallon

JP-4 50% naphtha + 50% kerosene

JP-8 100% kerosene

LDO 80% HSD + 20% FO

MOGAS Naphtha spot price + Caltex Bahrain-posted price differential of


Naphtha and MS-87 RON, moving average of last three years, subject
to a maximum differential of US$ 60/tonne

HOBC Naphtha spot price + MS-87 RON premium and extrapolated to MS-97
RON based on unitary method

Source: Oil industry and HBP market intelligence. 

These  local  prices  move  upwards  and  downwards  according  to  international  price 
fluctuations,  particularly  in  the  Arabian  Gulf  market.  The  various  price  components, 
except for IPP (which is directly related to global prices), are comparatively stable. The 
prices of HSFO and HSD have been completely de‐regulated by the GoP and these are 
also primarily linked with the prevailing prices of these commodities in the Arabian Gulf 
region. However, oil refineries are assured a certain offtake price for their products. As 
diesel fuel meets a large percentage of land transportation requirements in the country 
(70% of total in 2005‐2006), its production is encouraged through a 10% premium over 
the international market price in its offtake price paid to refiners. Gasoline prices carry 
no such benefit. The current ex‐refinery prices of major petroleum products in Pakistan 
are given in Exhibit 13.  

                                                       
20
  As of FY2002, ‘incidental costs’, also referred to as ‘incidentals’, include marine insurance (0.108% of C&F for white 
and 0.9% for black oil products), letter‐of‐credit commission (0.15% of C&F cost), bank service charges (0.1% of C&F 
cost), wharfage (Keamari: Rs 29 per tonne, FOTCO: Rs 25 per tonne), and ocean losses (0.5% of C&F cost). 
21
  As deemed duty in the calculation of ex‐refinery prices of HSD (10% ad‐valorem), kerosene, LDO, and JP‐4 (5% ad‐
valorem plus 1% surcharge) in the IPP. 
22
  Platts, a division of The McGraw‐Hill Companies based in the US, is a leading independent global provider of energy 
and metals information and is widely used as a respected and reliable source of industry information. For details, 
see www.platts.com. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  223
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 13: Ex‐Refinery Prices of Petroleum Products (as of June 30, 2007) 

Product Ex-Refinery Price


US$/MMBtu

JP-1 15.8
JP-4 17.5
JP-5 18.0

MOGAS 23.0

HOBC 17.5

Kerosene Oil 14.0

LDO 12.8

HSD 15.3

HSFO 8.8

Source: Gazette of Pakistan (Extraordinary Part II) Notification, 
Oil and Gas Regulatory Authority (OGRA), Islamabad: June 15, 2007. 

Coal 
Presently Pakistan is using indigenous as well as imported coal mainly to fuel brick kilns 
and the cement industry. Coal utilization, however, stands at only a fraction of a percent 
in the country’s total energy consumption. Power generation capacity based on coal is 
presently merely 150 MW, based at Lakhra, which is also plagued by chronic technical 
problems and low plant utilization factors.  
Local  coal  is  mostly  of  low  quality,  having  a  heat  content  in  the  range  of  5,000‐6,000 
Btu/lb,  although  some  deposits  are  ranked  at  higher  quality  of  around  10,000  Btu/lb. 
The price of local coal in June 2007 ranged between US$ 1.8/MMBtu to US$ 2.2/MMBtu, 
depending  on  quality.  By  comparison,  the  price  of  imported  coal  is  around 
US$ 2.7/MMBtu.  

Electricity 
The  electricity  regulator,  NEPRA  is  responsible  for  approving  the  purchase  price  of 
power from all producers in Pakistan. In the mid‐1990s, a stimulating pricing policy was 
adopted  and  several  independent  power  producers  (IPPs)  entered  the  market.  From 
10,500 MW in 1992‐1993, the power production capacity in the country grew to 17,500 
MW  in  by  2001‐2002.  By  2002,  these  incentives  had  been  watered  down  and  new 
capacity installation slowed down significantly. At that time, there was still some surplus 
capacity  available  in  the  system  and  the  rising  electricity  demand  was  thus  easily 
satisfied.  This  situation  did  not  last  long,  however,  as  installed  generation  capacity 
stagnated  while  the  economy,  and  consequently  electricity  demand,  picked  up  rapidly 
post  2000.  Presently,  Pakistan  is  experiencing  severe  electricity  shortages  throughout 
the  country,  with  new  generation  projects  currently  in  the  implementation  pipeline 
insufficient for resolving the crisis in the near future. ‘Load shedding’ is once again, after 
a  gap  of  over  a  decade,  a  daily  reality  even  in  big  cities  and  major  industry,  and  the 
supply  situation  is  expected  to  become  worse  before  new  investments  in  additional 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  224
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

generation can be commissioned. In the meantime, a large number of private industrial 
plants  continue  to  install  their  own  ‘captive’  power  production  facilities  to  circumvent 
frequent  and  unpredictable  outages  and  to  keep  their  operations  going.  In  2007,  the 
GoP  allowed  such  plants  to  sell  their  surplus  power  to  the  grid  in  order  to  augment 
overall supply and capacity utilization of generation assets in the country. 
NEPRA has broadly adopted the principal of ‘cost‐plus’ basis, built on a 15‐16% rate of 
return on asset value, in determining power offtake tariffs. Despite different risk profiles 
associated  within  and  across  each  of  the  market  functions,  NEPRA  uses  a  uniform 
mechanism  and  rate‐of‐return  allowance  across  the  board  for  all  types  of  power 
generation  resources  and  technologies.  Fuel  price  variation  is  allowed  to  be  passed 
through to the ratepayer at an approved thermal efficiency rating of the power plants.  
The country has been inconsistent in terms of offering policies and conditions to attract 
investment  in  feasible  indigenous  and  imported  energy  resource  development.  During 
implementation  of  the  2001  Power  Policy,  the  government  had  to  stop  processing  a 
number  of  gas‐based  combined  cycle  power  plant  proposals  as  natural  gas  allocations 
were  redirected  to  other  priority  economic  sectors.  In  the  2001  Power  Policy,  the 
government imposed additional taxes on oil‐based generation to discourage escalating 
imports that later had to be removed as eventually gas became scarce, and fuel oil was 
left as the only remaining choice for power generation to revert to. The government has 
not been able to propose dynamic policies for the development of abundant indigenous 
hydroelectric and coal resources in the country, nor for the large‐scale import of coal for 
power generation which would still be cheaper than imported oil for this purpose. The 
AEDB has offered an RE‐based power policy since 2006, but it has yet to pass the test of 
time  as  so  far  no  RE  IPP  project  has  matured,  and  related  regulations  and  legal 
requirements (grid interconnection, carbon credits, etc.) have not been fully developed.  

Exhibit 14: Cost of Power Generation at Crude Oil Price of US$ 60/bbl and 
Coal Price of US$ 60/Tonne 
12

10

6.94

6
US ¢/kWh

4.82 2.47 1.95 1.07


3.20 0.12

4
1.00 1.00

0.88 0.98 0.88 5.01 4.62


2
3.23 3.23
2.04 1.87 2.04

0
CCGT on CCGT on FO CCGT on LNG Steam Coal- Steam Coal- Hydel RoR Nuclear
Natural Gas Thar Imported

Capital Cost O&M Cost Fuel Cost

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  225
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 15: Cost of Power Generation at Crude Oil price of US$ 90/bbl and 
Coal Price of US$ 75/Tonne 
14

12

10

10.40
8
US ¢/kWh

6.96
6
2.47 2.44
4.29 0.12 1.07

4
1.00 1.00

0.88 0.88 5.01 4.62


0.98
2
3.23 3.23
2.04 1.87 2.04

0
CCGT on CCGT on FO CCGT on LNG Steam Coal- Steam Coal- Hydel RoR Nuclear
Natural Gas Thar Imported

Capital Cost O&M Cost Fuel Cost

 
The exhibits above compare the current cost of power generation in Pakistan based on 
different  technologies  and  fuel  sources  using  the  NEPRA  tariff  determination 
methodology  and  imported  crude  and  coal  prices  corresponding  to  US$ 60/bbl  and 
US$ 60/tonne, respectively (Exhibit 14), and US$ 90/bbl and US$ 75/tonne, respectively 
(Exhibit 15). These data have been used in the economic calculations provided in Annex 
VII. 

3.6.2 Energy Pricing 
As  in  a  number  of  counties  in  the  world,  energy  pricing  remains  a  politically  sensitive 
issue  in  Pakistan.  Higher  international  primary  energy  prices  have  brought  urgency 
within the country to the need for bridging the gap between domestic and international 
prices,  as  well  as  for  removing  relative  price  distortions  between  different  forms  of 
energy.  The  GoP  has  been  reluctant  to  price  energy  to  fully  reflect  its  economic  cost 
because  of  concerns  about  the  adverse  effects  of  price  increases  on  industrial 
competitiveness,  household  budgets  (especially  those  of  low‐income  families),  and  on 
general  inflation—i.e.,  both  immediate  economic  impacts  and  longer  term  social  and 
political ramifications. 
The price of energy should ideally reflect its environmental externalities. This measure, 
though hardly implemented anywhere with much success as it faces enormous political 
and  societal  resistance,  implies  that  governments  would  have  to  modify  the  tariff 
structure for energy (typically electricity) and reduce unnecessary subsidies on energy. If 
done, such an approach should always be undertaken as a combined policy initiative in 
concert with renewable energy development and energy efficiency programs. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  226
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Electricity 
In  terms  of  implications  for  RES‐E,  the  pricing  policy  in  Pakistan’s  power  sector  is  not 
optimal on both the supply and demand sides. On the supply side, NEPRA is responsible 
for  fixing  the  purchase  price  of  power  from  producers.  It  also  determines  the 
transmission  wheeling  charges  and  distribution  margin  for  T&D  companies  that  are 
integral  components  of  cost  of  electricity  services  for  consumers.  The  consumer  tariff 
thus  should  reflect  the  true  cost  of  service  delivery,  taking  in  to  consideration  real 
investments and the cost of operations and service standards across the market chain. 
The tariff mechanism should also be flexible to be able to respond to variations in fuel 
prices  without  significant  regulatory  lag  to  protect  both  the  consumers  as  well  as 
operating entities in the power sector.  
Furthermore,  on  the  demand  side,  tariffs  are  presently  fairly  uniform  all  over  the 
country  for  each  category  of  customer  in  each  DISCO  region.  This  precludes  the  true 
‘delivered’ price of electricity from being charged to the consumer, which induces waste 
and  uneconomic  use  of  the  resource  on  the  one  hand  and  removal  of  ‘least  cost’ 
incentives on the supply side, as the difference is made up through subsidy support to 
the  power  utilities  by  the  government.  The  DISCOs’  purchase  price  from  the  NTDC  is 
based  on  the  system‐wide  average  cost  of  production,  while  NEPRA  determines  an 
appropriate consumer tariff for each DISCO. The difference between the differentiated 
NEPRA‐determined retail tariffs and the uniform GoP‐notified actual ratepayer charges 
are  paid  as  subsidy  to  the  DISCOs.  In  this  manner,  for  example,  residential  base‐level 
consumption is subsidized and industrial and commercial sector consumers are charged 
higher tariffs to compensate for the difference. The impact of such a tariff structure is 
generally negative in economic terms: it creates higher demand, reduces incentives for 
efficient  energy  use  as  well  as  for  developing  and  purchasing  from  RE  generators, 
increases the cost of production and business for the industrial and commercial sectors, 
and significantly impacts on public finances in the form of a recurring annual power tariff 
support subsidy provision of over US$ 1.33 billion (in 2007).  
Exhibit 16 presents the average per unit electricity delivery costs, consumer tariffs, and 
subsidy support provided for different consumer categories by the government. 
Exhibit 16: Average Consumer Electricity Tariffs 
US¢/kWh
Subsidy
Cost of Consumer
Category (Cross
Service Tariff
Subsidy)

Residential 7.5 6.0 1.6


Commercial 13.7 12.1 1.6
Industrial 8.8 7.8 1.0
Bulk 10.1 9.6 0.6
Agricultural 8.2 6.5 1.7
Other 8.0 10.0 (2.0)

Average 8.5 7.2 1.3

Source: Notification SRO 150 (I)/2007 to 158 (I)/2007, Ministry of Water and Power, Government of Pakistan, 
Islamabad: February 23, 2007. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  227
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Natural Gas 
As with electricity tariffs, the government fixes consumer gas prices and maintains them 
at a uniform level throughout the country. The two utilities, SNGPL and SSGCL, supplying 
gas to consumers in their respective operational territories are not required to maintain 
or  provide  a  breakdown  of  costs  of  service  delivery  for  different  segments  of  the 
transmission  and  distribution  system  or  for  supplying  gas  to  different  consumer 
categories. The cost of supplying gas to customers at various locations is therefore not 
accounted  for  and,  regardless  of  the  difference  in  delivered  cost  based  on  location  of 
service provision, all consumers within the same category pay a uniform price. 
It is however, important to note here that the gas sector in general does not receive any 
external  subsidies  from  the  government,  and  these  differences  are  accounted  for 
internally:  the  industrial,  power  generation,  and  commercial  sectors  provide  a  cross 
subsidy  to  low‐income  domestic  and  fertilizer  feedstock  consumers,  which  is  built  into 
their GoP‐notified tariffs (Exhibit 17). The cost of gas nonetheless represents only 55% of 
alternative fuel oil price for industry, while for the residential sector it represents only 
35%  of  alternative  fuel  costs.  In  such  conditions,  it  is  not  surprising,  for  instance,  that 
solar water heaters have hardly displaced gas‐fired heaters in the local market. 

Exhibit 17: Average Consumer Gas Tariffs 
Rs/MMBtu
Cost of Cost of Consumer Cross
Service Service Tariff Subsidy
SNGPL SSGCL

Residential 2.3 2.3 2.3 0.0


Commercial 4.5 4.4 4.5 0.1
Industrial 4.0 4.0 4.0 0.0
Fertilizer Feedstock 1.3 0.6 1.1 0.2
Others 4.2 4.4 4.4 0.2

Average 3.6 3.4 3.4 0.0

Source: Oil and Gas Regulatory Authority (OGRA), Islamabad. 

According to the prevailing policies of the GoP and the methodology adopted by the Oil 
and  Gas  Regulatory  Authority  (OGRA),  the  consumer  price  of  natural  gas  in  Pakistan 
comprises  (i)  the  ‘prescribed  price’  for  the  gas  companies,  and  (ii)  a  ‘gas  development 
surcharge’  (GDS).  OGRA  fixes  the  prescribed  price  for  the  gas  utilities  through  public 
hearings during which relevant stakeholders are consulted. The prescribed price includes 
the following elements: 
• Producer  gas  prices,  which  are  linked  to  international  prices  of  crude  oil  and 
HSFO 
• Excise duty  
• Transmission and distribution costs  
• Depreciation 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  228
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Minimum  return  to  the  gas  companies,  as  stipulated  in  World  Bank/ADB  loan 
covenants. 
The prescribed price is designed to enable the two gas T&D companies to achieve fixed 
returns on assets; the difference between consumer tariffs and prescribed prices is the 
GDS.  The  GoP  determines  consumer  gas  prices  after  adding  or  subtracting  the  GDS  to 
the  prescribed  prices,  and  advises  OGRA  for  notification  in  the  Official  Gazette  of 
Pakistan. 
The cost of gas for industry is 40% of the price of crude oil, and for the residential sector 
it is 22%. As gas imports are expected to increase in the near future, the average market 
price is also expected to increase, and consumers will have little choice but to adjust to 
it. This is expected to slow down the overall increase in gas demand. 

Liquefied Petroleum Gas 
Where the natural gas distribution grid is not present, LPG is substituted as a domestic 
cooking and heating fuel. This is generally the case in many poor urban and rural areas 
of  the  country.  The  market  price  for  LPG  is  its  ‘economic’  price,  without  any  subsidy 
involved. This translates into the anomalous situation where the poorest end up paying 
the highest gas prices in the country.  

Petroleum Products 
The  subject  of  ex‐refinery  petroleum  product  pricing  has  been  discussed  previously  in 
Section  3.6.1.  Except  for  fuel  oil  and  HSD,  other  petroleum  product  sale  prices  are 
determined by OGRA on the basis of a formula provided by the government. The import 
of  HSFO  and  HSD  has  now  been  deregulated,  and  OMCs  are  allowed  to  import  these 
fuels  and  fix  their  sale  prices  on  the  basis  of  average  cost  of  import  and  local  supply 
prices. 

Exhibit 18: Consumer Prices of Petroleum Products as of June 30, 2007 
Retail Price
Product
US$/MMBtu

JP-1 18.2
JP-4 20.1
JP-5 20.7

Premium Motor Gasoline 27.7

HOBC 32.0

Kerosene Oil 17.0

Light Diesel Oil 14.2

HSD 16.9

HSFO 11.5

Source: Gazette of Pakistan (Extraordinary Part II) Notification, 
Oil and Gas Regulatory Authority (OGRA), Islamabad: June 15, 2007. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  229
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

OGRA  reviews,  fixes,  and  notifies  the  ex‐depot  prices  of  the  remaining  regulated 
petroleum  products,  i.e.,  motor  gasoline,  kerosene,  aviation  fuels,  and  LDO,  on  a 
fortnightly  basis  in  accordance  with  the  approved  pricing  formula.  The  prices  are 
uniform  at  29  depot  locations  and  are  pegged  to  Arabian  Gulf  prices.  The  OMCs  are 
allowed  an  Inland  Freight  Equalization  Margin  (IFEM),  a  distribution  a  margin  of  3.5%, 
and  dealer’s  margin  of  4%  on  the  value  of  the  products.  The  OMCs  have  also  been 
allowed  to  charge  the  secondary  freight  costs  from  depots  to  retail  outlets  over  and 
above  the  ex‐depot  prices  under  the  freight  pool  mechanism.  Current  retail  prices  of 
major petroleum products are given in Exhibit 18 above.  

Alternative Energy 
The pricing for alternative energy in Pakistan has been a contentious issue lately. This is 
primarily because neither NEPRA, the body that determines commercial power tariffs for 
grid‐connected  power,  nor  the  AEDB,  meant  to  facilitate  alternative  and  renewable 
energy  investments  in  the  country,  has  as  yet  undertaken  a  proper  economic  and 
comparative analysis of various renewable energy options in the local context, including 
their external and marginal avoided costs (this analysis is provided in Annex VII). In the 
absence of such a basis, the determination of tariffs on a ‘cost‐plus’ formulation deriving 
from  dynamic  market  prices  of  generation  equipment  and  equalizing  risk  perceptions 
with  those  for  more  established  generation  technologies  (who  are  offered  similar 
financial returns) becomes subject to debate, while absolute RE power purchase figures 
are  also  often  incorrectly  compared  with  corresponding  conventional  generation  costs 
that do not account for hidden subsidies for the latter or the external benefits of clean, 
renewable  energy.  Under  the  Policy  for  Development  of  Renewable  Energy  for  Power 
Generation,  2006,  the  Ministry  of  Water  and  Power  issued  guidelines  for  the 
determination of wind and small hydro IPPs using such a formulation in December 2006, 
on  which  grounds  NEPRA  has  since  issued  tariff  notification  for  several  private  sector 
wind power producers in the range of US$ 95‐105/MWh (levelized), but these have not 
yet resulted in any proposed projects from achieving financial closure.23 
In  light  of  the  above,  there  is  a  strong  case  for  undertaking  a  more  comprehensive 
evaluation of such alternative energy pricing, including from additional sources presently 
not  addressed  (biomass  conversion  and  waste‐to‐energy,  solar,  etc.)  which  takes  into 
account  Pakistan’s  current  power  generation  market,  as  well  as  properly  accounts  for 
external  costs  and  benefits,  including  environmental  and  carbon  credits,  peak  load 
reduction,  and  reduced  transmission  and  distribution  losses  that  smaller,  dispersed 
renewable  energy  generation  can  bring  about  for  grid‐connected  loads.  For  off‐grid 
applications in particular, measures to reduce the price of small‐scale renewable energy 
(micro wind and hydro, biogas, solar PV, etc.), can have a profoundly positive effect on 
rural energy access and poverty alleviation, and therefore needs urgent consideration in 
Pakistan  where  the  potential  for  such  technologies  is  extremely  high,  yet  presently 
underdeveloped. 

                                                       
23
  Although a few are in advanced stages of finalization. Apart from tariff negotiations, most wind IPPs have also been 
stymied  by  the  strong  international  demand  for  turbines,  which  has  resulted  in  rising  equipment  prices  and  long 
delivery times. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  230
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4 Projected Supply and Demand  
This  section  presents  the  projected  energy  demand  and  supply  picture  for  Pakistan 
under  normal  economic  growth  conditions  corresponding  to  an  average  6.5%  annual 
growth  in  the  gross  domestic  product  (GDP)  of  the  country.  Pakistan  is  expected  to 
remain  a  net  energy  importer  in  the  foreseeable  future  and,  therefore,  based  on  the 
price of imported energy and security of supplies for the country, several energy import 
scenarios have been discussed and their respective implications evaluated. This should 
set the context in which alternative renewable energy options can be assessed in terms 
of their economic merits and externalities, in addition to their financial costs. 

4.1 Fueling Economic Growth 
Exhibit  19  presents  a  comparison  of  per  capita  energy  consumption  of  various  Asian 
economies,  including  Pakistan.  Pakistan  has  lower  per  capita  energy  use  even  when 
compared  with  the  other  regional  developing  economies,  such  as  Thailand,  China, 
Indonesia and Malaysia, and far below the average for developed OECD countries, but at 
par with nations with similar per capita incomes, such as India and Viet Nam. 

Exhibit 19: Energy Use Per Capita for Selected Asian Countries, 2003 

Singapore

Brunei

Taipei,China

Korea, Rep. of

Japan

Malaysia

Thailand

Mongolia

Korea, PDR

China, People's Rep. of

Indonesia

Philippines

India

Pakistan

Viet Nam

Sri Lanka
Developing Asia

Lao PDR

Bangladesh
OECD Asia

Burma
World

Nepal

0 2 4 6 8 10 12
TOE/Capita

Source: International Energy Outlook 2006, Report # DOE/EIA‐0484(2006), Energy Information Administration, 
US Department of Energy, Washington, DC: 2006. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  231
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

In  terms  of  per  capita  electricity  consumption,  this  disparity  across  economies  is  even 
more apparent (Exhibit 20). Furthermore, there exists a huge latent demand for energy 
services  in  Pakistan  that  cannot  presently  be  met  due  to  resource  constraints,  as 
illustrated  by  the  low  levels  and  quality  of  electrification  for  a  major  portion  of  the 
population  (Exhibit  21),  which  will  invariably  improve  in  the  future  as  the  country 
develops  to  achieve  standards  prevalent  in  more  advanced  economies.  It  can  thus  be 
inferred that per capita, and therefore total, energy consumption in Pakistan is expected 
to  rise  rapidly  with  continued  growth  of  the  economy.  For  instance,  in  comparison  to 
Pakistan’s  annual  per  capita  electricity  consumption  of  469  kWh  in  2002,  the  average 
world  consumption  was  2,465  kWh/year  and  that  in  the  OECD  countries  8,615 
kWh/year. 

Exhibit 20: Electricity Consumption Per Capita in Asia, 1980 & 2002 

Brunei
Japan
Singapore
Korea, Rep. of
Malaysia
Thailand
China, People's Rep. of
Mongolia
Philippines
India
Pakistan
Indonesia
Viet Nam
Development Threshold

Sri Lanka
2002
Myanmar 1980
Lao PDR
World 1980

World 2002

Bangladesh
Nepal
Cambodia

0 2,000 4,000 6,000 8,000 10,000


kWh/Capita
 
Source: Human Development Reports, United Nations Development Programme, New York: 2006 
(http://hdr.undp.org/statistics/data). 

A  level  of  at  least  4,000  kWh/year  is  considered  necessary  for  a  UNDP  Human 
Development  Index  (HDI)  country  value  of  0.9—corresponding  to  ‘developed  society’ 
status—to be achieved, indicating the vast potential for increased energy use and social 
development in Pakistan. Furthermore, Pakistan lies on the initial, steeply rising part of 
the  HDI‐per  capita  electricity  consumption  curve,  which  means  that  even  incremental 
improvements in its per capita electricity use can result in a large increase in its national 
HDI  ranking,  implying  a  very  high  economic  and  social  development  payback  for 
expanded delivery of affordable energy services.24 
                                                       
24
  For a full discussion of the relationship between energy use and economic and social development, see Masud, J, D 
Sharan,  and  B  Lohani,  Energy  for  All:  Addressing  the  Energy,  Poverty  and  Environment  Nexus  in  Asia,  Asian 
Development Bank, Manila: 2006 (http://www.adb.org/Documents/Books/Energy‐for‐All). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  232
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

With  an  expected  annual  GDP  growth  rate  of over  6%  compounded  with  a  net  annual 
population  increase  of  2%  in  the  coming  years,  the  prospects  for  accelerated  energy 
demand in the country, therefore, remain strong.  

Exhibit 21: Access to Electricity in Selected Asian Countries, 2000 

Singapore
Korea, Rep. of
Japan
China, People's Rep. of
Malaysia
Mongolia
Philippines
Thailand
Viet Nam
Sri Lanka
Indonesia
Pakistan
India
Bangladesh
Korea, PDR
Cambodia
Nepal
Myanmar

0% 20% 40% 60% 80% 100%


Percentage of Total Population
 
Source: Earth Trends: Environmental Information, World Resources Institute. Washington, DC: 2006 (http://earthtrends.wri.org). 

4.2 Energy Supply and Demand Scenarios 
In view of the rising price of crude oil, the cost of meeting the energy requirements of a 
rapidly expanding economy such as Pakistan’s can be substantial. However, the country 
has a range of options available to manage its future energy supply and demand needs. 
The choices ultimately made will be determined by the extent to which risks associated 
with variations in the prices and availability of fuels in the international market can be 
managed,  as  well  as  how  well  the  cost  of  delays  or  inability  to  develop  indigenous 
resources can be absorbed.  

4.2.1 Projected Energy Demand  
The  energy  market  in  Pakistan  has  historically  been  characterized  by  suppressed 
demand due to limited supplies and the lack of adequate infrastructure for provision of 
energy services to consumers, a factor that has hindered the country’s economic growth 
and reduced industrial investments in the country. However, realizing these limitations, 
the  government  is  now  seriously  evaluating  plans  to  provide  sustained  and  affordable 
energy to all sectors of the economy and reduce the current deficit between supply and 
actual, as well as latent, demand.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  233
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Based on 30 years of macroeconomic data, the three probable country growth scenarios 
considered  for  this  study  can  be  associated  with  ‘normal’,  ‘high’,  and  ‘low’  growth  in 
GDP over the projection period. The average actual growth trend in the GDP converges 
to  approximately  6.5%  per  annum,  which  has  been  taken  as  the  ‘normal’  growth 
scenario.  
The  projected  energy  demand  at  an  average  annual  GDP  growth  rate  of  6.5%  is 
summarized  in  Exhibit  22.  This  demand  has  been  worked  out  on  the  basis  of 
unconstrained  availability  of  fuels  to  meet  the  energy  needs  of  all  sectors,  keeping  in 
view their respective consumption economics as well as the unavoidable infrastructure 
and technical constraints that are expected to prevail in the foreseeable future. Over the 
next 18‐year period, overall demand for energy in this scenario is expected to increase 
by a factor of 3.3, from the current level of 60 MTOE to 198 MTOE in 2025. The share of 
oil in the energy mix is expected to drop, in view of higher oil prices in the international 
market  and  the  government’s  policy  to  switch  to  lower  cost  alternatives  for  power 
generation, including renewable and nuclear sources. 

Exhibit 22: Projected Energy Demand Under Normal GDP Growth 

FY07 FY10 FY15 FY20 FY25 FY07 FY10 FY15 FY20 FY25
Million TOE % Share

Oil 18 20 29 39 47 30 25 27 26 24
Gas 30 45 55 68 93 49 56 50 46 47
Coal 4 7 9 13 16 7 8 8 8 8
Hydel 8 8 13 22 29 13 9 12 15 15
Renewables - 1 1 3 5 0 1 1 2 2
Nuclear 1 1 2 4 7 1 1 2 3 4
Total 60 80 110 148 198 100 100 100 100 100

Source: Medium‐Term Development Framework: 2005‐10, Planning Commission, Government of Pakistan, Islamabad: 2005. 
Note: Adjusted to GDP growth rate of 6.5% and updated for the base year FY2007 and national power generation plan. 

Sensitivity of demand for energy to the economic growth rate is illustrated in Exhibit 23. 
As  mentioned  earlier,  alternative  scenarios  for  economic  growth  assuming  average 
annual economic growth of 5.5% and 7.4% were also considered to evaluate the impact 
of GDP growth on total demand for energy. The 7.4% GDP growth rate corresponds to 
the  ‘optimistic’  economic  scenario  stated  in  the  GoP’s  MTDF,  while  the  5.5%  rate 
represents  a  ‘reasonably  conservative’  outlook.  Over  the  next  18‐year  period,  the 
demand  for  energy  under  these  different  economic  trends  varies  by  more  than  25%, 
dropping to 155 MTOE for a GDP growth rate of 5.5%, and increasing to 246 MTOE for 
an economic growth rate of 7.4%. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  234
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 23: Energy Demand Forecasts at Various Economic Growth Rates 
300

6.5% Average Annual GDP Growth

250 5.5% Average Annual GDP Growth

7.4% Average Annual GDP Growth

200
Million TOE

150

100

50

0
1996 2000 2005 2010 2015 2020 2025

Source: Medium‐Term Development Framework: 2005‐10, Planning Commission, Government of Pakistan, Islamabad: 2005. 
Note: Adjusted to GDP growth rates shown. 

4.2.2 Projected Energy Supply and Deficit 
Supply‐side projections assume the implementation of current long‐term national plans 
for  power  generation,  with  emphasis  on  the  development  of  coal,  hydel,  and  nuclear 
resources  for  this  purpose,  consistent  with  the  government’s  policy  to  maximize  the 
utilization of indigenous resources and diversify the energy mix.  
In  all  three  economic  growth  scenarios  evaluated  over  the  next  18  years,  Pakistan’s 
estimated  energy  needs  far  exceed  available  indigenous  supplies,  and  the  country’s 
reliance on imported fuels is therefore expected to continue to increase with time. The 
following  energy  supply  cases  were  analyzed  by  taking  into  consideration  total  energy 
requirements, energy deficits and imports, and the cost of imported energy: 
• Base Case: Unconstrained gas imports 
• Low  Gas  Case:  Imported  pipeline  gas  not  available,  LNG  and  imported  coal  to 
replace imported gas assumed in the Base Case 
• Low  Hydel  Case:  Imported  coal  to  replace  hydel  power  generation  assumed  in 
the Base Case 
• Low  Gas,  Low  Hydel  Case:  Imported  coal  to  replace  hydel  power  generation 
assumed in the Low Gas Case. 
The  bases  and  assumptions  for  each  of  these  scenarios  are  explained  in  more  detail 
below. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  235
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The Base Case 
The  Base  Case  assumes  that  the  country  will  be  able  to  import  natural  gas  to  meet 
emerging energy deficits. This is the least‐cost option, given Pakistan’s proximity to gas‐
surplus  regions  of  the  Middle  East  and  Central  Asia,  the  relatively  low  cost  of 
transporting  large  quantities  of  gas  through  pipelines,  and  the  economic  advantage 
offered  by  utilizing  natural  gas  in  end‐uses  such  as  fertilizer  production,  power 
generation with high‐efficiency combined cycle gas turbines (CCGT), cogeneration, and 
compressed  natural  gas  (CNG)  use for  road  transportation.  This  case  assumes  that  the 
gap  in  power  generation  capacity—after  accounting  for  the  generation  planned  on 
hydel,  nuclear,  and  renewable  resources—would  be  filled  by  CCGT  units  operating  on 
imported natural gas. 

Low Gas Case 
The Low Gas Case represents a scenario in which imported pipeline gas is not available, 
and the deficit has to be made up with alternative fuels. In this case, the country would 
need to import LNG to meet established demand, also referred to as ‘essential demand’, 
for natural gas in the residential, commercial, fertilizer, and industrial sectors, as well as 
for  generation  capacity  in  the  power  sector  that  can  operate  only  on  natural  gas.  The 
power  generation  capacity  fueled  by  imported  gas  in  the  Base  Case  would  need  to  be 
operated on imported coal. 

Low Hydel Case 
The  Low  Hydel  Case  represents  a  situation  under  which,  on  account  of  adverse 
environmental or political factors, implemented hydel capacity additions are reduced by 
30%  over  the  Base  Case,  and  the  resulting  gap  in  power  generation  is  filled  with 
imported  coal‐fired  thermal  plants.  The  country  is  assumed,  however,  to  be  able  to 
import gas through pipelines to meet its demand for gas.  

Low Gas, Low Hydel Case 
The  Low  Gas,  Low  Hydel  Case  represents  circumstances  under  which  hydel  capacity 
additions are reduced by 30% as above, and the resulting power generation gap is fueled 
by imported coal. Imported gas through pipelines is also assumed not to be available in 
this case, and the country would therefore have to meet its essential gas requirements 
through imported LNG shipments. 
The  projected  indigenous  energy  supply  and  deficits  corresponding  to  a  6.5%  average 
GDP  growth  rate  are  summarized  in  Exhibit  24.  Domestic  oil  and  gas  production  is 
expected to increase marginally in the near term, but decline in the long run. 
Overall,  the  availability  of  coal,  hydel,  nuclear,  and  renewable  power  generation  is 
projected  to  improve  significantly  from  current  levels  by  2025,  in  line  with  the  GoP’s 
resource  development  plans.  The  availability  of  energy  from  these  sources,  however, 
will  not  be  enough  to  meet  the  growing  demand  of  the  economy.  The  total  energy 
deficit—which is presently 18 MTOE, or 29% of energy demand—is expected to increase 
to  123  MTOE,  corresponding  to  62%  of  total  demand,  by  2025.  This  outlook  clearly 
indicates a need to accelerate the development of the indigenous resource base, and to 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  236
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

supplement this with arrangements to acquire affordable energy from reliable external 
sources. 
Exhibit 24: Projected Energy Supply and Deficits  
Million TOE
FY07 FY10 FY15 FY20 FY25

Indigenous Supply
Oil 3 4 4 3 2
Gas 30 39 34 25 19
Coal 2 2 5 8 12
Hydel 8 8 13 22 29
Renewable and Nuclear 1 1 3 7 12

Total Indigenous Supply 43 55 59 65 75

Total Energy Requirement 60 80 110 148 198

Deficit 18 25 51 83 123
Deficit as % of Energy Requirement 29 32 46 56 62

Source: Medium Term Development Framework: 2005‐10, Planning Commission, Government of Pakistan, Islamabad: 2005. 
Note: Adjusted to GDP growth rate of 6.5% and updated for national power generation plans. 

4.3 Projected Energy Balances 
Based  on  the  country’s  expected  energy  demand  growth,  availability  of  indigenous 
energy  resources,  and  assuming  various  energy  import  options,  the  projected  mix  of 
indigenous  and  imported  energy  required  to  meet  Pakistan’s  needs  in  the  Base  Case 
corresponding to a 6.5% average GDP growth rate is summarized in Exhibit 25.  

Exhibit 25: Projected Supply for Imported Energy Resources (Base Case)  
Million MTOE
FY07 FY10 FY15 FY20 FY25

Total Demand 60 80 110 148 198

Total Indigenous Supply 43 55 59 65 75

Imported Energy Required 18 25 51 83 123


Oil 15 15 25 36 45
Gas/LNG 0 6 21 43 74
Coal 3 4 4 4 4

The  projected  mix  of  imported  energy  supply  under  the  Low  Gas  scenario, 
corresponding to a 6.5% annual GDP growth rate, is shown in Exhibit 26. In this case, the 
total  energy  demand  is  seen  to  increase  compared  to  the  Base  Case  due  to  reduced 
power generation from more efficient gas‐based combined cycle units and consequent 
increase  in  the  use  of  lower  efficiency  coal‐based  plants.  Similarly,  the  differences  in 
operating efficiencies for the other power generation options have also been taken into 
account. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  237
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 26: Projected Supply for Imported Energy Resources Under the Low Gas Supply 
Scenario 
Million MTOE
FY07 FY10 FY15 FY20 FY25

Total Demand 60 80 111 151 205

Total Indigenous Supply 43 55 59 65 75

Imported Energy Required 18 25 52 86 130


Oil 15 15 25 36 45
Gas/LNG 0 5 17 34 50
Coal 3 5 10 17 35

The  projected  mix  of  imported  energy  supply  under  the  Low  Hydel  scenario 
corresponding to a 6.5% annual GDP growth rate is given in Exhibit 27.  

Exhibit 27: Projected Supply for Imported Energy Resources Under the Low Hydel 
Supply Scenario 
Million MTOE
FY07 FY10 FY15 FY20 FY25

Total Demand 60 80 110 148 197

Total Indigenous Supply 43 52 57 61 68

Imported Energy Required 18 27 53 87 129


Oil 15 15 25 36 45
Gas/LNG 0 6 21 43 74
Coal 3 6 6 8 10

The  projected  mix  of  imported  energy  supply  under  the  Low  Gas,  Low  Hydel  supply 
scenario corresponding to a 6.5% annual GDP growth rate is summarized in Exhibit 28. 
This  case  also  assumes  no  gas  imports—therefore,  total  energy  demand  increases  for 
the same reasons as in the Low Gas Case. 

Exhibit 28: Projected Supply for Imported Energy Resources Under the Low Gas, Low 
Hydel Supply Scenario
Million MTOE
FY07 FY10 FY15 FY20 FY25

Total Demand 60 80 111 150 204

Total Indigenous Supply 43 52 55 58 66

Imported Energy Required 18 27 56 92 138


Oil 15 15 25 36 45
Gas/LNG 0 5 17 34 50
Coal 3 7 13 23 43

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  238
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

5 Economic Implications 
5.1 Scenario Impacts on Costs and Financing Needs 
Based on current import parity prices, corresponding to a crude oil price of US$ 90/bbl, 
the  economic  cost  of  Pakistan’s  primary  energy  supply  in  2006  is  estimated  at  US$  22 
billion,  of  which  about  half  is  attributable  to  oil  used  in  the  transportation  sector.  The 
cost of power generation at current energy prices ranges from US¢ 14/kWh for fuel oil‐
fired  plants,  to  US¢ 7/kWh  for  power  plants  operating  on  imported  gas.  With  the 
existing  plans  for  the  development  of  indigenous  resources,  and  unconstrained 
availability of imported gas and LNG, the Base Case cost of imported fuels is expected to 
increase from US$ 7 billion in FY2006 to US$ 58 billion in 2025. 
An  assessment  of  the  long‐term  cost  of  energy  supply  under  alternative  scenarios 
indicates that, compared to the Base Case, an aggressive development of the Thar coal 
resource  will  help  to  reduce  the  annual  energy  import  bill  by  about  US$  1  billion  by 
FY2025.  In  case  pipeline  gas  imports  do  not  materialize,  substitution  of  imported  gas 
with  imported  LNG  and  coal  will  increase  the  cost  of  imported  energy  by  over  US$  4 
billion by the same year. The corresponding cost of delays in development of large‐scale 
hydel projects is estimated at over US$ 5 billion annually by FY2025.  

5.2 Optimum Role of Renewable Energy 
The  development  of  renewable  energy  (and  improvements  in  system‐wide  energy 
efficiency and intensity of use) can not only help offset some of the increased generation 
costs  under  the  various  scenarios  considered  above,  but  also  afford  reduced  overall 
economic costs of energy supply in each case due to RE’s positive economic, social, and 
environmental externalities. 
A detailed assessment of feasible RE deployment and associated financial and economic 
costs under different supply scenarios is provided in Annex VII. This analysis shows that, 
while the total RES‐E (renewable energy source‐electricity) potential in the medium term 
for Pakistan, based on all feasible RE technologies and with all barriers to RE deployment 
removed,  is  55  TWh/year  (or  22%  of  total  power  generation)  by  2020,  the  optimum 
penetration  of  RES‐E  (based  on  economic  least‐cost  evaluation)  is  25  TWh/year  (or 
10.3% of total generation in 2020).25  This compares with a natural penetration level of 
RES‐E  estimated  to  be  17  TWh/year  by  2020  if  only  direct  project‐wise  financial  costs, 
compared to alternative conventional generation, are considered. 
A higher share of RES in the generation mix results in different cost‐benefit implications 
for the economy. Under the optimal case, the cost of generating 25 TWh/year through 
renewable energy technologies would be US$ 1.8 billion/year, and the economic benefit 
to society would be of the order of US$ 2.1 billion/year, shared between producers and 
consumers in the ratio 65:35, respectively. 

                                                       
25
  The  estimated  RES‐E  penetration  rates  are  sensitive  to  assumptions  used  to  calculate  them,  notably  the  cost  of 
capital in the case of ‘optimal’ deployment and the mix of conventional supply alternatives in the case of ‘natural 
penetration’. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  239
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Thus,  it  can  be  concluded  that  given  Pakistan’s  projected  energy  requirements  and 
supply options, renewable energy can play an important role in closing the gap between 
cost‐effective  supply  and  ever  increasing  demand  in  a  manner  that  produces  a  net 
positive  benefit  to  the  economy  and  society  as  a  whole.  This  observation  is  further 
strengthened  when  the  many  additional  benefits  of  distributed  RE  use  (including  non‐
power RES, such as biogas and biofuels) are also taken into consideration. 
It  is  therefore  imperative  for  the  Government  of  Pakistan  to  evolve  a  policy  and 
regulatory  environment  that  encourages  the  development  of  this  untapped  potential 
based on a careful evaluation of the economic feasibility of different RE technologies. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  240
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex VII:  Working Paper 4: 
Study of Costs and Potential Penetration of 
On­grid RE under Different Policies 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  241
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Working Paper No. 4 

Study of Costs and Potential Penetration 
of On­grid RE under Different Policies  

Contents 

Exhibits ..................................................................................................................... 245 
Abbreviations and Acronyms .................................................................................... 247 
1  Objective .............................................................................................................. 249 
2  Methodology for RES Cost and Penetration Assessment ...................................... 249 
1.1  General Approach .............................................................................................. 249 
1.2  General Assumptions of the Model .................................................................. 253 
1.3  Long Run Conventional and RES Supply Curves ................................................ 254 
1.4  Demand Parameters .......................................................................................... 258 
1.5  Data Assessment ............................................................................................... 258 
1.6  RES Technologies Included in the Model .......................................................... 258 
2  RE Supply Curves .................................................................................................. 264 
2.1  Biogas................................................................................................................. 264 
2.2  Solid Biomass ..................................................................................................... 267 
2.3  Waste‐to‐Energy ................................................................................................ 271 
2.4  Small Hydro ....................................................................................................... 272 
2.5  Solar Photovoltaic .............................................................................................. 274 
2.6  Solar Thermal..................................................................................................... 275 
2.7  On‐shore Wind .................................................................................................. 277 
3  Incremental RE Supply Curve for 2020 .................................................................. 279 
4  Incremental Conventional Supply Curve for 2020 ................................................. 280 
5  Costs and Potential of RES Penetration under Different Policies ........................... 283 
5.1  Natural Penetration of Renewable Energy Sources .......................................... 283 
5.2  Optimal Quota of Renewable Energy in 2020 ................................................... 285 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  243
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

5.3  Analysis of Single Feed‐in Tariff Mechanism ..................................................... 287 
5.4  Analysis of Technology‐based Feed‐in Tariff Mechanism ................................. 289 
5.4.1  Optimal Quota‐constrained Analysis..................................................... 289 
Cost‐efficient Case .................................................................................. 289 
Industry Policy‐driven Case .................................................................... 290 
5.4.2  Exhausting the Medium‐term Potential ................................................ 291 
5.5  Sensitivity Analysis............................................................................................. 291 
6  Initial Thoughts on Medium‐term Policy ............................................................... 296 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  244
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 
Exhibit 1: Partial Market Equilibria............................................................................ 250 
Exhibit 2: Equi-marginal Principle Illustrated ............................................................ 250 
Exhibit 3: Cost-efficiency Approach.......................................................................... 252 
Exhibit 4: Equi-marginal Principle in the Real World ................................................ 253 
Exhibit 5: Single RE Supply Curve Computation...................................................... 255 
Exhibit 6: RE Potential Assessment ......................................................................... 256 
Exhibit 7: Pakistan’s Livestock Population for Biogas Potential Estimation, 2006 ... 265 
Exhibit 8: Agricultural Biogas-based Power Supply Curve ....................................... 265 
Exhibit 9: Landfill Gas-based Power Supply Curve .................................................. 266 
Exhibit 10: Sewage Gas-based Power Supply Curve ................................................ 267 
Exhibit 11: Bagasse-based Power Supply Curve ....................................................... 269 
Exhibit 12: Annual Residues Produced by Crop Type ............................................... 270 
Exhibit 13: Non-bagasse Biomass-based Power Supply Curve................................. 270 
Exhibit 14: Urban Population of Pakistan ................................................................... 271 
Exhibit 15: Waste-to-energy Supply Curve ................................................................ 272 
Exhibit 16: Econometric Estimation of Investment Costs for Small Hydro ................. 273 
Exhibit 17: Small Hydro-based Power Supply Curve ................................................. 274 
Exhibit 18: Solar PV Area Estimation for Pakistan ..................................................... 274 
Exhibit 19: PV-based Power Supply Curve ................................................................ 275 
Exhibit 20: Solar Thermal Area Estimation for Pakistan............................................. 276 
Exhibit 21: Solar Thermal-based Power Supply Curve .............................................. 277 
Exhibit 22: Wind potential estimation (near-grid constrained and unconstrained) ..... 278 
Exhibit 23: Wind Potential Maps of Pakistan .............................................................. 278 
Exhibit 24: On-shore Wind-based Power Supply Curve............................................. 279 
Exhibit 25: Total RES-based Power Supply Curve for 2020
(Medium-term Incremental Potential) ....................................................... 279 
Exhibit 26: Basic Data for Determination of Private Supply Curve for
Conventional Energy ................................................................................ 280 
Exhibit 27: Basic Data for Social Supply Curve for Conventional Energy .................. 282 
Exhibit 28: Private and Social Supply Curves for Conventional Energy for 2020 ...... 283 
Exhibit 29: Optimal RES-E Penetration under Private Costs ..................................... 284 
Exhibit 30: RES-E Technology-wise Penetration under Private Costs....................... 284 
Exhibit 31: Optimal RES-E Penetration under Social Costs....................................... 286 
Exhibit 32: RES-E Technology-wise Penetration under Social Costs ........................ 287 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  245
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 33: Distribution of Producer Surplus by RES-E Technology under


Single Feed-in Tariff ................................................................................. 288 
Exhibit 34: Producer Surplus under Multiple Feed-in Tariffs
(Cost-efficient Approach) .......................................................................... 290 
Exhibit 35: Surplus under Multiple Feed-in Tariffs
(Industry Policy-driven Approach) ............................................................ 290 
Exhibit 36: Surpluses under Multiple Feed-in Tariffs Exhausting
Medium-term RES-E Potential ................................................................. 291 
Exhibit 37: Sensitivity Analysis (Differences from Base Case) ................................... 293 
Exhibit 38: Consumer and Producer Surpluses under Different Cases
(Private Cost Evaluation) .......................................................................... 293 
Exhibit 39: Consumer and Producer Surpluses under Different Cases
(Single Feed-in Tariff) ............................................................................... 294 
Exhibit 40: Consumer and Producer Surpluses under Different Cases
(Multiple Feed-in Tariffs Exhausting Medium-term Potential) ................... 294 
Exhibit 41: Consumer and Producer Surpluses under Different Cases
(Multiple Feed-in Tariffs with All-technology Portfolio) ............................. 295 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  246
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
bbl  Barrel 
BP  Basis point 
CCGT  Combined cycle gas turbine 
CH4  Methane 
CHP  Combined heat and power 
CO2  Carbon dioxide 
EU  European Union 
FIT  Feed‐in tariff 
FO  Furnace oil 
GDP  Gross domestic product 
GHG  Greenhouse gas 
GoP  Government of Pakistan 
GW  Gigawatt 
ha  Hectare 
HDR  Hot dry rock 
IGCC  Integrated gasification combined cycle 
IRR  Internal rate of return 
kg  Kilogram 
kWh  Kilowatt‐hour 
KWSB  Karachi Water and Sewerage Board 
LRMC  Long run marginal cost 
m  meter 
MC  Marginal cost 
MPC  Marginal private cost 
MSB  Marginal social benefit 
MSC  Marginal social cost 
NOx  Nitrous oxides 
NREL  US National Renewable Energy Laboratory 
OECD  Organization for Economic Cooperation and Development 
PPIB  Private Power and Infrastructure Board 
PV  Photovoltaic 
R&D  Research and development 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  247
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

RE  Renewable energy 
RES  Renewable energy source 
RES‐E  Renewable energy sourced‐electricity 
SO2  Sulfur dioxide 
SOx  Oxides of sulfur 
SS  Small‐scale 
TWh  Terawatt‐hour 
W  Watt 
WACC  Weighted average cost of capital 
WTE  Waste‐to‐energy 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  248
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Study of Costs and Potential Penetration 
of On­grid RE under Different Policies 

1 Objective 
This  Annex  presents  an  economic  assessment  of  renewable  energy  sources  (RES) 
deployment options in Pakistan, in order to fine‐tune the tools required for the design of 
a successful medium‐term RE policy for the country. More specifically, the objective of 
this  document  is  two‐fold:  firstly,  to  evaluate  the  cost  structures  of  RES  in  Pakistan, 
classifying different renewable sources by the marginal cost of tapping them; secondly, 
to analyze the social and private costs and the potential penetration of each type of RES, 
under  different  policy  environments.  As  will  be  explained  later  in  this  document,  the 
economic assessment of RES has some limitations—however, the model provided in this 
paper should allow policy makers to move forward on a more sound analytical basis. 

2 Methodology for RES Cost and Penetration Assessment 
1.1 General Approach 

In basic economic theory, one prerequisite for economic efficiency is that the marginal 
benefit of any given activity should be equal to its marginal cost. With respect to the use 
of  electricity,  this  would  require  that  the  marginal  social  benefit  (MSB,  commonly 
defined as ‘demand curve’) attributed to the consumption of, say, one kilowatt‐hour of 
electricity,  is  exactly  offset  by  the  marginal  social  cost  (MSC,  commonly  defined  as 
‘supply curve’, incorporating the cost of externalities) of generating this kWh, in order to 
achieve 'Pareto‐optimality'1. In all other cases, society would be better off providing and 
using  more  (i.e.,  where  MSB  exceeds  MSC)  or  less  (i.e.,  where  MSC  exceeds  MSB) 
electricity. Exhibit 1 shows this graphically. 

The  socially  optimal  amount  of  electricity,  in  this  case,  is  at  QE*,  where  the  marginal 
social  cost  of  electricity  production  equals  the  marginal  social  benefit  (at  price  PE*)  of 
consuming  this  electricity.  In  this  figure,  QE  denotes  the  allocation  (consumption)  of 
electricity  with  no  internalization  of  external  costs  (MPC,  or  private  supply  curve),  i.e., 
electricity  supply  depends  on  marginal  private  costs.  From  an  economic  efficiency 
perspective, this private supply curve is incomplete due to a number of market failures 

                                                       
1
  An  economic  system  that  is  Pareto‐optimal  or  Pareto‐efficient  implies  that  no  individual  can  be  made  better  off 
without another being made worse off. Here 'better off' is often interpreted as "put in a more preferred position."  
It  is  commonly  accepted  that  outcomes  that  are  not  Pareto‐optimal  are  to  be  avoided,  and  therefore  Pareto 
efficiency  is  an  important  criterion  for  evaluating  economic  systems  and  public  policies.  If  economic  allocation  in 
any  system  (in  the  real  world  or  in  a  model)  is  not  Pareto‐optimal,  there  is  theoretical  potential  for  a  Pareto 
improvement—an  increase  in  Pareto‐efficiency:  through  reallocation,  improvements  to  at  least  one  participant's 
well‐being can be made without reducing any other participant's well‐being. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  249
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

that  justify  state  intervention;  in  the  case  of  RES  in  electricity  (RES‐E)  markets,  these 
generally fall under two categories: (1) externalities associated with various sources of 
energy,  including  environmental  and  security  of  supply,  and  (2)  under‐investment  in 
technological progress and innovation. 

Exhibit 1: Partial Market Equilibria 

 
In  fact,  when  analyzing policies  to  promote  RES‐E,  we  should  be  more concerned with 
the  allocation  of  electricity  generation  amongst  the  various  technologies,  such  as  RES 
and conventional sources of energy. In this respect, economic efficiency would require 
that the marginal cost of producing the quantity QE* be equalized amongst the sources, 
so  that  the  marginal  social  cost  of  conventional  electricity  generation  (MSCConventional) 
equals the marginal social cost of RES‐E generation (MSCRES) in QE*. This is known as the 
principle of 'equi‐marginality' in economic theory. Exhibit 2 illustrates the equi‐marginal 
principle. 

Exhibit 2: Equi‐marginal Principle Illustrated 

 
In this figure, AE denotes the allocation of electricity generation between conventional 
and  renewable  sources  of  energy,  where  the  share  is  determined  by  the  respective 
marginal private costs (MPC). In contrast, the socially optimal allocation would be where 
marginal  social  costs  are  equalized,  i.e.,  at  AE*,  resulting  in  the  relative  shares  Q(RES) 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  250
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

and  Q(conventional),  which  is  usually  attained  only  when  all  external  costs  are 
internalized. 

However, the electricity market is severely distorted in that external costs tend not to be 
internalized, so market regulation is justified on the grounds of normative theory. These 
market  failures  have  a  propensity  to  suppress  the  complete  marginal  (social)  cost 
associated with the various forms of electricity generation, which should ideally be used 
in  the  decision‐making  process  of  the  economic  actors,  such  as  utility  companies. 
Therefore,  in  such  a  distorted  market,  neither  the  first  criterion  (MSB  =  MSC)  nor  the 
second (MSCConventional = MSCRES) for obtaining optimum economic efficiency in electricity 
markets are necessarily met, and the government thus has a role to play as a regulator. 

The discussion so far has revolved around a description of what in economics is called 
the  'first‐best'  solution,  in  the  sense  that  it  assures  economic  efficiency,  where  the 
marginal  social  costs  equal  the  marginal  social  benefits  of  a  given  policy  or  activity. 
However,  this  seemingly  simple  framework  is  hard  to  translate  into  a  reliable  cost‐
benefit  test,  since  a  large  number  of  input  parameters  are  at  the  core  of  much  of  the 
academic debate, and other parameters are rather difficult to assess; for instance, the 
use of a discount rate for costs and benefits, the value of avoided external costs, such as 
CO2,2 and the time‐path of RES installations, all have a big influence on the final verdict 
but are rather difficult to quantify. 

Therefore, although these kinds of studies can give us, as explained later in Exhibit 4, an 
overall idea of where the optimal allocation can be found, in the real world, however, 
the  concept  of  cost‐efficiency  suggests  that  regulators  set  an  objective  based  on 
available scientific and technical data, and then try to ensure that this objective is met at 
‘least’ cost. In doing so, policy makers make sure that, if efficiency cannot be maintained 
in the strict economic sense, then at least, reaching the goal does not result in a waste of 
the  society's  resources.  Consequently,  economists  suggest  striving  instead  for  the 
'second‐best' solution, which is commonly known as 'cost‐efficiency'.  

The question then is how policy makers can ensure cost‐effectiveness in the expansion 
of RES‐E on a practical basis.  The answer to this is surprisingly simple and can be best 
explained with the help of Exhibit 3. This figure shows the stylized marginal cost curves 
of  three  RES  (A,  B,  C),  which  exhibit  different  slopes.  While  the  marginal  (social)  cost 
curve of source ‘C’ has a relatively gentle slope, the cost curve of source ‘A’ rises much 
more steeply. Cost‐efficiency would be attained once the equi‐marginal principle holds 
among  these  RES,  so  that  MSCA  =  MSCB  =  MSCC.  This  is  also  referred  to  as  ‘static 
efficiency’,  implying  that  no  other  allocation  of  generation  capacity  amongst  different 
RES will yield a lower overall cost of providing a given share of RES. All it takes to achieve 
this  static  efficiency,  in  this  case,  is  a  uniform  price,  p*  (single  feed‐in  tariff),  for 
renewable energy from different sources, which would then be set against the marginal 

                                                       
2
  A  very  well‐known  reference  is  the  work  by  Sundqvist  that  found  vast  differences  for  external  costs  across 
externality studies, e.g., ranging from 0.06 cents/kWh to 72.42 cents/kWh for coal. See Sundqvist, T. “What causes 
the  disparity  of  electricity  externality  estimates?”,  Energy  Policy,  Vol.  32,  Issue  15,  Elsevier  Ltd.,  Amsterdam: 
October 2004. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  251
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

cost curves by economic actors, and yield the quantities QA, QB and QC with the sum of 
the  three,  giving  the  total  RES  share  at  price  p*.  What  the  equi‐marginal  principle 
therefore implies is that there will most likely be a mix of various RES, unless one form of 
electricity generation has a marginal cost curve that dominates all the others, i.e., it is 
always below the MC curves of other RES. 

Exhibit 3: Cost‐efficiency Approach  

 
Coming  back  to  the  real  world,  the  result  of  such  studies  is  shown  in  Exhibit  4.  This 
figure is quite similar to Exhibit 3; however we do not present simple MSCs but bounds, 
i.e., MSC(RES)h represents the highest social supply curve for RES that can be computed; 
on  the  contrary,  MSC(RES)L  stands  for  the  lowest  one.  The  same  analysis  can  be 
performed  regarding  conventional  energy  supply  curves.  Due  to  high  uncertainty  in 
setting  the  parameters  required  to  compute  these  supply  curves  (e.g.,  RES  costs  and 
potentials,  technological  progress  in  both  conventional  and  RES,  discount  rates, 
environmental  costs,  non‐environmental  externalities,  etc.)  we  are  not  able  to  set  a 
single social supply curve, but a probable range. Therefore, we are not able to define a 
single optimum mix, but a space of potential first‐best solutions, as defined by the area 
‘abcd’ in Exhibit 4. Consistent with this area solution, we find a range of prices (Ph‐PL), 
and the corresponding shares Q(RES):Q(Conventional) can therefore vary a lot. Despite 
the  inaccuracies  of  this  type  of  analysis,  it  is  the  best  available  tool  to  evaluate  policy 
decisions  either  within  the  area  solution,  or  outside  it.  For  instance,  in  this  case,  we 
assume that the government has decided to set a policy at PE*:QE*, which is a boundary 
point  solution  for  the  first‐best  space  of  solutions.  Based  on  this  model,  we  can 
compute: 
1. How different is that choice from the market outcome (PE:QE), 
2. What  RES  technologies  (and  what  range  of  these  technologies)  will  be  developed 
under this single feed‐in tariff (PE*), and 
3. What is the private cost of the policy (i.e., [PE* – PE] x [QE* – QE]), 

amongst other interesting policy evaluations. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  252
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 4: Equi‐marginal Principle in the Real World 

 
However, policy makers may not be concerned solely with static efficiency, which does 
not  take  into  account  long‐term  prospects  and  technological  innovation,  and  can 
therefore define a policy decision outside the first‐best space of solutions. In Europe, it is 
understood that any instrument to promote RES should also lead to ‘dynamic efficiency’, 
i.e., should give economic agents an incentive to continuously lower their costs through 
technological progress. In that sense, single feed‐in tariff or quota systems that are best 
for static efficiency are replaced with targeted feed‐in tariffs incorporating technology‐
specific  rates  or  hybrid  schemes.  There  thus  appears  to  be  a  trade‐off  between  static 
and  dynamic  efficiency.  In  general,  feed‐in  tariff  schemes  tend  to  be  used  to  provide 
strategic  support  for  innovative  technologies,  much  more  than  other  primary  support 
schemes  such  as,  in  particular,  tradable  green  certificates.  On  the  other  hand,  green 
certificates schemes, amongst other technology‐neutral schemes, tend to be used to put 
more emphasis on static efficiency, to give preference to renewable energy technologies 
with comparatively lower costs, as was explained in Annex IV. 

The  model  presented  here  for  assessing  the  impact  of  Pakistan’s  on‐grid  electricity 
market on the development of new renewable generation is based on:  
• General  assumptions  (target  year,  static  or  dynamic  efficiency  considered, 
incremental or total modeling, etc.); 
• Social and private supply curves (given costs or probabilistic approach, potential 
estimation by RE class, discount rate, monetarization of externalities, etc.); and 
• Demand side perspectives (energy efficiency, demand forecasting, etc.). 

1.2 General Assumptions of the Model 

The first task in developing the model is to set general assumptions concerning most of 
the variables included in the model. These assumptions include: 
• Definition of the target year: The target year in this study is set at 2020 because 
of the goal of defining a medium term policy. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  253
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Definition  of  the  modeling  approach:  The  model  is  defined  as  incremental. 
Under  an  incremental  approach,  the  social  and  private  supply  curves  for  both 
RES and conventional are computed without considering the installed capacity in 
any  type  of  energy.  Similarly,  only  the  incremental  demand  (total  demand 
forecasted for 2020 less existing total demand) is considered. Decommissioning 
of  existing  conventional  plants  during  the  period  of  analysis  is  examined;  see 
Annex VI for details of this assessment. 
• Efficiency assessment: The goal of this study is mostly related to static efficiency 
assessment;  therefore,  we  compute  the  supply  curves  employing  current  costs 
for different technologies. In some comparable studies, costs were forecasted for 
the end of the analysis period (generally 2020 or beyond), employing experience 
curves that describe how costs decline with cumulative production. Forecasting 
technological development is a crucial activity but not an easy one, especially for 
a  long‐term  horizon;  considerable  efforts  have  been  made  recently  to  improve 
the  modeling  of  technology  development  in  energy  models;  nevertheless,  the 
introduction of this dimension adds other drivers of uncertainty to the model. In 
general, an experience curve is expressed as: CCUM (costs per unit as a function 
of output) = C0 (costs of the first unit produced) x CUM (cumulative production 
over  time) ^  b  (experience  index).3  The  estimation  of  ‘b’  for  each  technology  is 
rather difficult and inaccurate. Besides these problems, technological progress is 
not endless for each technology; generally it presents an S‐shaped curve. In our 
opinion,  the  complexity  and  uncertainty  regarding  the  incorporation  of 
technological progress to the model does not adequately trade off with effort. In 
the  model  provided  in  this  analysis,  we  therefore  employ  current  costs  for  the 
different technologies. This approach penalizes infant technologies such as solar 
and tidal and wave, for instance. 

1.3 Long Run Conventional and RES Supply Curves 

In  general,  renewable  energy  sources  are  characterized  by  a  limited  resource,  with 
output costs rising with increased utilization—as, for example, in the case of wind power 
sites,  where  best  wind  conditions  will  be  exploited  first  and,  as  a  consequence,  once 
such  options  have  been  exhausted,  the  use  of  less  optimal  sites  will  result  in  higher 
generation  costs.  As  stated  previously,  a  proper  tool  to  describe  both  costs  and 
potentials is the (static) marginal cost‐resource (or supply) curve. In principle, a supply 
curve describes the relationship between (categories of) technically available potentials 
(e.g.,  wind  energy,  hydropower,  biogas,  etc.)  and  the  corresponding  (full)  costs  of 
utilizing this potential at a certain point of time. 

On  the  left‐hand  side  of  Exhibit  5,  a  theoretically  ideal  continuous  supply  curve  is 
depicted, taking into account that every location is slightly different from the other and, 
hence, looking  at  all  locations—e.g.,  for  wind  energy  in  a certain  geographical  area—a 
continuous  curve  emerges  after  these  potentials  have  been  classified  and  sorted  in  a 

                                                       
3
  In  many  studies,  a  well‐known  rule  of  thumb,  empirically  proven,  is  commonly  employed:  costs  decline  by  a 
constant percentage with each doubling of units produced. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  254
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

least‐cost way. The stepped function as shown on the right‐hand side represents a more 
practical  approach,  as  in  real  life  the  accuracy  needed  for  a  continuous  design  is 
impossible.  Thereby,  sites  with  similar  economic  characteristics—e.g.,  in  case  of  wind, 
sites  with  same  range  of  full‐load  hours—are  described  by  one  band  and,  hence,  a 
stepped  curve  emerges.  Exhibit  5  shows  a  single  RES  supply  curve;  by  adding  all  the 
different  RES  supply  curves,  sorting  each  step  as  a  function  of  its  cost,  the  total  RES 
supply  curve  can  be  computed.  Similarly,  the  conventional  supply  curve  is  calculated 
based  on  the  available  expansion  plan  defined  by  the  relevant  national  generation 
planning authority. 

Exhibit 5: Single RE Supply Curve Computation 

Immediately, two questions arise: Which cost should we employ, and how do we assess 
the  potential?    As  this  is  an  incremental  study,  all  plants  will  be  new;  in  case  of  new 
plants the economic conditions are described by long run marginal costs (LRMC). With 
respect  to  the  potentials,  we  follow  the  OPTRES  approach4:  for  new  options,  the 
additional  achievable  medium‐term  potentials  need  to  be  assessed  for  each  RES 
category at the country‐level, representing the maximal additional achievable potential 
up  to  the  target  year  under  the  assumption  that  all  existing  barriers  can  be  overcome 
and  all  driving  forces  are  active;  it  represents  the  upper  boundary  of  what  can  be 
realized for  a certain RES category. It is  obvious that for electricity generation a broad 
set  of  different  technologies  based  on  RES  exists  today;  a  sound  research  study, 
exploring  deeper  into  those  potentials  which  are  more  feasible  in  the  medium  term, 
would be required. 

As  shown  in  Exhibit  6,  the  definition  of  potential  is  not  straightforward.  At  least,  four 
classes of RES potentials should be evaluated: 
• Theoretical potential: For the theoretical potential to be derived, general physical 
parameters have to be taken into account (e.g., based on the determination of 
the energy flow resulting from a certain energy resource within the investigated 
region). This represents the upper limit of what can be produced from a certain 
energy  resource,  from a  theoretical  point‐of‐view—of  course,  based  on  current 
scientific knowledge; 

                                                       
4
  Report  of  the  IEE  project  OPTRES:  Assessment  and  Optimisation  of  Renewable  Support  Schemes  in  the  European 
Electricity Market, February 2006. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  255
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Technical  potential:  If  technical  boundary  conditions  (i.e.,  efficiencies  of 


conversion  technologies,  overall  technical  limitations,  as,  for  example,  the  land 
area available for installing wind turbines) are considered, the technical potential 
can be derived. Technical potentials can be assessed in either a static or dynamic 
context,  i.e.,  with  increased  R&D,  conversion  technologies  might  be  improved 
upon and, hence, the technical potential could increase; 
• Realizable potential: The realizable potential represents the maximal achievable 
potential,  assuming  that  all  existing  barriers  can  be  overcome  and  all  driving 
forces  are  active.  Thereby,  general  parameters  are  taken  into  account,  as  for 
example, market growth rates, planning constraints, etc.  
• Medium‐term  potential:  The  medium‐term  potential  is  equal  to  the  realizable 
potential in the target year.  

Exhibit 6: RE Potential Assessment 

Once we have defined that we need LRMC for each step and for each RE/conventional 
source,  as  well  as  the  medium‐term  potential  for  each  step  as  previously  defined,  the 
next  task  is  to  compute  the  supply  curves.  As  mentioned  earlier,  this  task  is  a  rather 
complex one, requiring definitions of many aspects. 

Supply  curve  assessment:  We  followed  two  different  approaches  depending  on  the 
quality of available information. In  those cases where information about potential and 
costs  was  good  enough  (on‐shore  wind,  for  instance),  we  define  a  curve  based  on 
detailed  bottom‐up  cost  assessment.  In  all  other  cases—where  information  was  not 
available  or  accurate—we  develop  a  probabilistic  cost  approach  by  simulating  a  large 
number  of  scenarios  and  combining  values  for  different  key  parameters.  In  order  to 
provide  a  more  realistic  simulation,  each  of  the  available  technologies  (plant 
specifications for each step) has been modeled using a different combination of values 
for the following cost drivers: (1) investment costs; (2) fuel costs for some RES bearing 
opportunity cost (biogas and biomass, for instance); (3) efficiency factors in some types 
of  RES,  and  (4)  load  factors,  in  case  this  information  is  not  available.  In  particular,  for 
each of these cost drivers, four scenarios are considered: a low value, a mid‐low value, a 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  256
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

mid‐high  value  and  a  high  value  scenario,  characterized  by  levels  of  the  cost  drivers 
corresponding to the 10th, 40th, 60th and 90th percentile of a uniform distribution. In both 
cases, O&M costs are assumed to be a fixed percentage of the investment costs, defined 
by  technology.  We  consider  neither  innovative  technologies  such  as  IGCC,5  carbon 
sequestration, etc., in conventional energy (see Annex VI), nor some  of the infant RES 
technologies described in Section 1.6. 

Monetization  of  externalities:  As  is  well  known,  it  is  estimated  that  the  cost  of 
electricity  production  from  coal  and  oil  would  double,  and  that  of  power  production 
from  gas  would  increase  by  30%,  if  externalities  were  considered.  For  the  sake  of 
simplicity  we  consider  the  following  costs  of  externalities:  (1)  global  environmental 
costs, (2) air quality, and (3) fuel dependency. 

We do not consider the cost of externalities affecting RES because: (1) the cost for hydel 
projects  does  include  environmental  and  social  costs;  (2)  we  assume  them  to  be 
negligible  for  wind  power  (visual  interference,  noise,  and  bird  kills)  and  solar  thermal 
and photovoltaic (land use); (3) they are not relevant for the other RE technologies; and 
(4)  we  do  take  into  account  positive  externalities,  such  as  job  creation and  indigenous 
technology development. The only case in which we took externalities into account was 
regarding biomass because, as is later explained, coal is needed to increase the annual 
load factor of such plants.  

Scale assessment: We also develop ad hoc cases based on our experience in emerging 
countries,  regarding  the  development  of  large‐scale  hydel  and  medium‐scale  thermal 
(reciprocating  engines  plants).  As  is  well  known,  due  to  the  high  financial  barriers  in 
developing  large‐scale  hydel,  these  projects  tend  to  be  less  developed  than  would  be 
expected  through  efficient  planning.  On  the  contrary,  reciprocating  engine  plants  and 
similar  fast  installation  technologies  tend  to  be  developed  more  than  would  be 
recommended under sound planning. This issue was discussed in more depth in Annex 
VI.  

Return  on  invested  capital:  From  an  economic  point  of  view,  the  best  approach  is  to 
assume that investment is recovered within the lifetime of the plant; plant lifetimes, in 
turn,  depend  on  technology,  ranging  from  25  years  for  most  RES‐E  technologies  to  as 
much as 50 years for hydel plants. However, this approach has a huge drawback; it does 
not  take  into  consideration  the  financial  barriers  to  investment.  In  order  to  compute 
each  technology’s  LRMC,  we  prefer  employing  a  common  period  of  20  years  for  all 
technologies. 

Determination of capital costs: Scenarios for the capital costs (real pre‐tax ‘plain vanilla’ 
WACC6) are set at 10%, 12%, and 14%, respectively. 

Grid and reserves costs: Grid investment costs are not included in the analysis because 
we estimate the potentials for the different RES constrained to installations less than 25 
                                                       
5
  Integrated gasification combined cycle. 
6
  Weighted average cost of capital. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  257
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

km from existing transmission lines, whenever such information is available, and hence, 
grid interconnection costs are assumed to be negligible. As is well known, some of the 
RES‐E are volatile in the short term (non‐firm energy) and therefore, the system requires 
both  operational  and  ‘cold’  reserves.  Our  model  does  not  consider  the  cost  of  these 
backup reserves, as its determination would require detailed simulations of the power 
system which are beyond the scope of this study. 

1.4 Demand Parameters 

We  will  employ  the  forecasted  demand  for  2020  presented  in  Annex  VI.  According  to 
our  study,  152  TWh  is  the  incremental  energy  demand  for  the  period  2008‐2020,  and 
the need for the corresponding additional power generation capacity is around 35 GW, 
though this would depend on the technological mix. For more details, see Annex VI. 

1.5 Data Assessment 

Currently, no complete detailed assessment of the cost and potentials for different RES‐
E technologies applicable to Pakistan exists that could enable a computation of the RES‐
E  supply  curve  for  the  country.  Therefore,  we  have  identified  a  combination  of 
methodologies  and  sources  to  obtain  a  first  estimate  of  the  parameters  that  will  form 
the base of our model.  

Investment and O&M costs for different technologies were assessed: (1) if available data 
could  be  gathered  from  Pakistani  projects,  these  data  were  privileged,  and  (2)  when 
these data were not available, international experience from our database was taken as 
reference  in  which  we  give  priority  to  regional  costs  (mostly  Indian),  followed  by 
European  ones.  Regarding  the  potentials,  the  methodology  and  the  sources  employed 
depend on the technology under consideration. In Section 2, the costs and methodology 
for estimating the potentials for each technology are provided. 

Investment,  O&M,  and  fuel  costs  for  conventional  energy  have  been  thoroughly 
analyzed  in  Annex  VI.  An  expansion  plan  for  the  period  2008‐2020  based  on  long‐run 
least‐cost  simulations  is  also  provided.  The  incremental  private  conventional  energy 
supply curve provided in this report is based on the results of that study.  

1.6 RES Technologies Included in the Model 

In this analysis, the following RES technologies have been considered: 

Biogas:  Biogas  is  the  gaseous  by‐product  that  results  from  a  natural  decomposition 
process of organic matter. The anaerobic decomposition of such substances comprises 
the conversion of high‐molecular organic bonds, under the absence of oxygen, into low‐
molecular compounds. This process includes the production of a mixed gas, commonly 
referred to as ‘biogas’, consisting of: 
• 50%‐70% methane (CH4); 
• 20%‐40% carbon dioxide (CO2); and 
• Other elements. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  258
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The  energetic  content  of  biogas  is  positively  correlated  to  its  methane  content.  In 
addition,  the  energetic  use  of  methane  is  highly  welcome  from  an  ecological  point  of 
view,  as  atmospheric  releases  of  methane  are  8  to  25  times  more  damaging  than 
equivalent CO2 emissions from a global warming perspective.7 

This RES technology comprises of the following subcategories: 
• Agricultural biogas: This resource results from an anaerobic digestion process of 
biological deposits, such as: 
o farm slurries; and 
o biodegradable fractions of municipal waste. 
• Landfill gas: The main input is the solid waste deposited in landfill sites. 
• Sewage gas: As primary resource, this requires wastewater or sewage, processed 
and refined in a treatment or purification plant. 

Biogas  is  a  non‐fluctuating  energy  resource  as  there  is  no  seasonal  dependence  of  its 
source  inputs.  Therefore,  the  generator  can  decide  when  to  start  or  stop  power 
generation. 

In  this  study  we  will  concentrate  on  on‐grid  power  generation  based  on  biogas  from 
farm  slurries,  landfills,  and  urban  domestic  sewage  gas.  Biogas  obtained  from  the 
biodegradable  fraction  of  municipal  waste  is  a  very  convenient  alternative  for  off‐grid 
and will be evaluated separately at a later stage along with other off‐grid RES options. 
Biogas from industrial sewage is not considered because it would require a very specific 
assessment  customized  to  each  of  Pakistan’s  industrial  clusters,  a  study  that  is  not 
presently  available  as  the  potential  cannot  be  properly  estimated  based  on  general 
assumptions.  

Solid biomass: Commonly, the definition of solid biomass includes four categories: 
• Forestry products; 
• Forestry residues; 
• Agricultural products; and  
• Agricultural residues. 

Based on this definition, a separate assessment of the potential should be undertaken 
for each category. However, conversion technologies in each case are very similar and 
differences are negligible.  

Electricity generation from solid biomass is characterized by: 
• High variable costs due to high volatility in the quality of biomass used as input, 
plus the non‐existence of a biomass market (as a commercial commodity). 

                                                       
7
  Over a 500‐ and 100‐year time horizon, respectively. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  259
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Non‐volatility  of  the  power  output:  as  in  thermal  conventional  generation,  the 
generator can decide when to start or stop the plant in order to maximize profits; 
however, some types of biomass are not available uniformly throughout the year 
and other fuels may be required to optimize returns on investment.  
• Various  energy  conversion  concepts:  Today,  apart  from  ‘simple’  combustion,  a 
variety  of  tested  technological  methods  exist  for  power  production  from 
biomass.  In  general,  a  distinction  must  be  made  between  biomass‐fired  CHP8 
plant, biomass‐fired power plant, and co‐firing plants.  
• Differences in efficiency, brought about by plant size. 
• Transportation distances, with short ones preferable as the economics of power 
production are very sensitive to this cost element.  

We have focused our study in agricultural residues (bagasse, rice husk, straw, etc.). The 
issue of agricultural products (‘energy’ crops) is complex and is being discussed in many 
countries  because  of  its  potential  effect  on  the  price  of  cereals  for  food.  Hence, 
considering  the  huge  potential  of  Pakistan  in  other  types  of  renewables,  we  do  not 
consider  developing  energy  crops  locally  as  of  paramount  importance  at  this  stage. 
Additionally,  it  is  considered  more  appropriate,  from  an  economic  point  of  view,  to 
employ  energy  crops  for  developing  biofuels.  The  case  of  forestry  is  also  difficult  to 
assess. Forestry products are considered renewable if they are related to net additions 
of  forests;  as  can  be  imagined,  this  requires  a  sophisticated  and  precise  monitoring 
mechanism  that  increases  the  administrative  cost  of  this  alternative.  In  particular, 
Pakistan  is  facing  acute  forest  depletion  and  therefore  this  alternative  would  not  be  a 
suitable one to explore as it could increase deforestation pressures. In any case, forestry 
residues  usually  have  a  very  high  alternative  use  cost  and,  thus,  this  is  usually  not  a 
cheap source of biomass. 

Waste‐to‐energy:  the  energetic  part  of  waste  can  be  considered  a  ‘renewable’  energy 
source. Electricity generation from waste is characterized by: 
• Low  variable  costs  but  high  investment  costs,  due  to  the  fact  that  these  plants 
require a high effort for cleaning and purifying the input material.  
• Non‐volatility of the power output. 
• Short distance for waste transportation being desirable. 

Regarding waste‐to‐energy, we should bear in mind the best practices in the world—as 
employed  in  Denmark,  for  instance.  There  are  four  possible  disposal  alternatives  for 
waste,  if  collected:  (1)  recycling;  (2)  waste‐to‐energy  solutions;  (3)  landfills;  and  (4) 
probably,  the  worst  one—open  dumps.  In  the  case  of  Denmark,  there  are  no  open 
dumps; 8% of the total waste is deposited at landfills, 26% is used for waste‐to‐energy, 
and the largest share (66%) is recycled. In the EU, new landfill sites are, in most member 
countries, not allowed to be developed any more. In our analysis of potential and costs, 

                                                       
8
  Combined heat and power. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  260
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

we will take into account the fact that landfills should not be encouraged and waste‐to‐
energy is the second‐best management solution. 

Geothermal: Geothermal power is energy generated by heat stored beneath the Earth's 
surface. This generation is characterized by: 
• High investment costs: high level of uncertainty in the planning phase increases 
investments costs. 
• Low‐temperature energy extraction technology is currently under development. 
• Low  volatility  of  the  power  output:  geothermal  represents  an  almost  non‐
fluctuating source of energy. 

In  this  report,  we  only  take  into  account  proven  technologies  for  geothermal  energy, 
namely  flash  steam  power  plants  (that  need  hot  water  above  180 °C  from  geothermal 
reservoirs) and binary‐cycle (in which the water used is cooler than that in flash steam 
plants  but  higher  than  85 °C).  Other  infant  technologies,  such  as  hot  dry  rock  (HDR) 
geothermal energy and any other type of low‐temperature design, are not considered. 
Additionally,  we  were  not  able  to  get  accurate  data  about  the  potential  for  low‐
temperature  geothermal  energy  in  Pakistan.  General  assumptions  for  estimating 
potential and cost for geothermal are not easy to make; for instance, drilling costs that 
may be up to 50% of the total cost, depend on site conditions. Therefore, we have not 
included geothermal generation in our analysis as an option for Pakistan at this stage. 

Small hydropower (installed capacity below 50 MW): Electricity generation from small 
hydropower plants is characterized by: 
• Proven  technology:  Amongst  all  RES  technologies,  hydel  represents  the  most 
widely  explored  option.  The  various  conversion  technologies  applied  are 
commonly used and commercially well proven. 
• Low  short‐term  volatility,  high  medium‐/long‐term  volatility  of  power  output: 
Hydel represents a fluctuating source of energy. In contrast to wind and solar PV, 
the volatility appears in the medium to long term. It is characterized by a strong 
seasonal dependence, but high annual differences may also occur. 
• High  initial  investment  costs:  A  huge  hindrance  for  small‐scale  hydel  plants 
results  from  the  high  up‐front  investment  costs  and  long  construction  times 
typically involved. 
• Low social acceptance: Public resistance to hydroelectric projects has been rising 
in most parts of the world since the 1980s, though this is a problem primarily for 
large‐scale hydel, particularly those with associated large reservoirs.9 

                                                       
9
  Though obviously also a renewable energy source, large‐scale hydroelectric is considered, both generally and for the 
purposes  of  this  study,  to  fall  in  the  ‘conventional’  energy  category  due  to  its  higher  external  costs  as  well  as 
established status vis‐à‐vis  other ‘mainstream’ power generation technologies. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  261
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Photovoltaics:  Photovoltaic  (PV)  power  cells  use  a  specific  spectrum  of  sunlight  to 
produce electricity through the photoelectric effect. In principle, there are four primary 
applications for PV power systems: 
• As  off‐grid  domestic  rooftop  PV  systems,  that  can  provide  power  to  remote, 
isolated communities. 
• As grid‐connected distributed PV systems, installed to supply power to a building 
or other load that is also connected to the utility grid. 
• As grid‐connected centralized PV systems, installed for two main purposes: as an 
alternative  to  centralized  power  generation  from  fossil  fuels  or  nuclear  energy; 
or for strengthening the utility distribution grid. 
• As  off‐grid  non‐domestic  systems,  to  provide  power  for  a  wide  range  of 
applications, such as telecommunications, water pumps, etc. 

For  the  purposes  of  the  model,  only  grid‐connected  (both  centralized  and  distributed) 
PV  systems  are  of  relevance.  The  most  important  characteristics  with  respect  to  grid‐
connected PV systems are: 
• High  volatility  of  the  power  produced:  Due  to  the  strong  dependence  of  the 
power  output  on  available  sunlight,  short‐,  as  well  as  medium‐  to  long‐term 
fluctuations in output appear; 
• High initial investment costs. 

Solar  thermal:  Solar  thermal  power  plant  technology  has,  for  several  years  now,  been 
considered  a  promising  new  option  for  power  generation.  Nevertheless,  only  a  few 
(hybrid)  solar  thermal  plants  are  operating  well  worldwide.  In  principle,  several 
technological options appear: 
• Parabolic  trough  plant:  Large  cylindrical  parabolic  mirrors  concentrate  the 
sunlight  onto  a  line  of  focus.  Several  of  these  collectors  in  a  row  form  a  solar 
field. Molten salt is used to transport the heat to a (conventional) gas or steam 
turbine. 
• Power  tower  plant:  The  solar  field  feeding  a  central  receiver  system  (i.e.,  the 
power  tower)  is  made  up  of  several  hundred  ground‐based  mirrors  which 
concentrate  sunlight  upon  a  raised  receiver  in  a  central  tower.  As  in  the  case 
above, air or molten salt is used to transport the heat to a (conventional) gas or 
steam turbine. 
• Dish/Stirling technology: Parabolic dish concentrators in this case are, contrary to 
the  one  above,  rather  small  units—in  the  range  of  kilowatts—each  driving 
individual Stirling (high efficiency, closed‐cycle, regenerative, hot air technology) 
engines whose output can be used separately or combined. 

Trough and power tower plant are usually equipped either with a thermal storage block 
or a hybrid fossil burner in order to guarantee a non‐fluctuating power supply. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  262
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

In this paper, we only consider parabolic plants as they are more efficient than power 
tower plants. Dish/Stirling technology is a very good option for off‐grid alternatives, and 
will be treated at a later stage. 

Tidal and wave: In principle, a distinction can be made with respect to application type, 
i.e. shoreline, near‐shore, and off‐shore devices. Off‐shore tidal and wave power is still 
in the R&D stage. We do not consider this technology further here because, due to its 
infancy,  any  assessment  would  be  quiet  inaccurate  for  the  policy  horizon  under 
consideration.  

Wind,  on  and  off‐shore:  Among  the  currently  available  and  commercially  viable 
renewable resources, wind is one of the cheapest possible sources of renewable energy. 
When  considering  the  total  capital  investment  costs  of  locating  and  building  new 
electricity  generation  facilities,  in  some  cases,  it  can  even  be  competitive  with 
conventional  power  generation  technologies.  This  explains  the  keen  interest  power 
companies and private investors worldwide have taken in wind energy in recent years. 

Electricity generation from wind power is characterized by: 
• High volatility of the power output: Due to the strong dependence of the power 
produced on the wind speed (power scales as the cube of wind speed), short‐ as 
well  as  a  medium‐  to  long‐term  fluctuations  can  appear  in  wind‐based 
generation.  In  this  context,  wind  power  prediction  methods  have  been 
developed to partially overcome the associated lack of certainty. The quality of a 
possible  wind  plant  site  can  thus  be  determined  by  deriving  the  local  wind 
climate,  i.e.,  an  analysis  of  average  annual  wind  speeds  and  wind  speed 
distribution. 
• Standardized and proven power conversion technology: The stable and growing 
demand  for  wind  power—starting  in  Europe  within  the  early  1990s—led 
especially  Denmark,  Germany,  and  Spain  to  become  leading  countries  in  wind 
turbine  manufacturing  (at  present,  India  and  USA  are  also  key  players). 
Technological  solutions  between  manufacturers  may  differ  in  detail,  but  in 
general  terms,  the  overall  concepts  utilized  are  proven  and  well  established. 
Typical  plant  sizes  increased  rapidly  during  the  1990s,  driven  mainly  by  the 
growing  demand  for  off‐shore  developments.  Currently,  the  size  of  typical  on‐
shore turbines is in a range of 1 to 2 MW and for off‐shore, the largest available 
turbines are now almost in the 5 MW class. 

In  this  study,  we  only consider  on‐shore  wind farms.  This  is  because,  as  will  be  shown 
later, the potential for on‐shore wind is huge—even taking into account only the highest 
speed classes, it is large enough to exceed operational constraints. Therefore, we believe 
that on‐shore wind generation is a realistic and economic option for the medium‐term 
policy horizon under analysis. 

In the following sections, a computation of the supply curves for each RE technology and 
for the aggregated supply curve relevant to Pakistan is provided. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  263
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2 RE Supply Curves 
As we have previously explained, the supply curve for each RES technology is based on 
the  medium‐term  potential—not  all  the  theoretical  potential—and  on  the  actual  costs 
for  the  different  technologies.  Another  issue  that  is  important  to  point  out  is  that 
Pakistan has no accurate estimation of potentials for any RES technology. We based our 
analysis  on  an  indirect  approach  taking  into  account  available  information;  though  we 
believe the conclusions of our analysis are valid, it is important to fine tune these kinds 
of studies in the future. 

2.1 Biogas 

In the case of bio‐energy, some problems arise in estimating the country potential due 
to the fact that in this case the same input can be used with different energy conversion 
technologies. For example, sugarcane can be used to produce sugar and electricity (i.e., 
with  a  cogeneration  plant),  but  can  also  be  used  to  produce  biofuels  (e.g.,  ethanol). 
Some agricultural residues can also alternatively be used in either a biogas digester or a 
biomass  plant.  This  led  us  to  the  necessity  of  making  some  assumptions  on  crops  and 
other  biomass  inputs  for  the  determination  of  Pakistan’s  bio‐energy  potential. 
Nevertheless, these assumptions were made based on sound criteria and international 
experience. 

In the case of biogas, the approach for the derivation of the primary potential figures is 
explained in more detail separately for each subcategory below.  

Agricultural  biogas:  Farm  slurries  are  the most  common  input  in  biogas  digesters.  The 
potential  has  been  assessed  by  evaluating  the  existing  livestock  population  in  Pakistan 
by  type  of  animal  (buffaloes,  cattle,  goats,  sheep,  poultry,  camels,  asses,  horses  and 
mules have been considered, see Exhibit 7). As can be seen, in terms of numbers, farm 
livestock in Pakistan comprises mainly of poultry which assures a large manure potential 
for  biogas  development.  Once  livestock  has  been  assessed,  the  second  step  is  to 
determine the expected total amount of manure by type of livestock. This was achieved 
by multiplying each type of livestock by its average deposition. Finally, standard energy 
content in terms of biogas (1.1 kWh/kg) was used to determine potential availability of 
biogas‐based energy. The medium‐term penetration for 2020 is estimated to be 1% of 
total potential biogas, as the typical project size of this type tends to be small, due to the 
slurries’  collection  cost.  We  thus  obtain  2.8  TWh  of  medium‐term  potential  for 
agricultural biogas.  

Regarding costs, we have employed the following parameters: 
• Investment cost range: As we found a very large variation in investment costs in 
this technology between experience in the region and Europe, we define a range 
assuming  the  current  investment  cost  in  India  as  the  lower  bound  and  average 
European  cost  as  the  upper  bound.  We  have  thus  derived  the  range  US$  886‐
2,350/kW. 
• O&M cost: 7% of investment cost per year. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  264
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Fuel  cost:  We  have  employed  US$  28/MWh,  including  the  cost  of  collection, 
based on available information (e.g., Gujarat Electricity Regulatory Commission, 
Government of India: Tariff Order 2/2007). 
• Self consumption: 8% of output. 
• Energy conversion efficiency: 0.92 kg/kWh. 
• Load factor range: 60‐80%. 

Exhibit 7: Pakistan’s Livestock Population for Biogas Potential Estimation, 2006 

73.0%

Buffaloes
Cattle
Goats
Sheep
Poultry
Camels
Asses
Horses

5.0% 0.2% Mules

10.2% 5.2%
5.6% 0.8%

0.1%
0.0%

 
Source: Pakistan Economic Survey, 2006‐7, Government of Pakistan, Islamabad: 2007 

Using  this  information  and  the  probabilistic  cost  approach  described  earlier,  the 
agricultural  biogas  technology  supply  curve  was  computed.  It  is  presented  in  Exhibit  8 
for medium‐term penetration assessment in Pakistan. 

Exhibit 8: Agricultural Biogas‐based Power Supply Curve 
140

120

100
USD/MWh

80

60

40

20

Biogas
0
0 500 1000 1500 2000 2500 3000
GWh/a

 
Landfill gas: Due to its relationship with waste, landfill gas potential was estimated vis‐à‐
vis  waste‐to‐energy  and  sewage  gas.  Firstly,  the  amount  of  solid  waste  generation 
expected in the target year was estimated. Then, it was assumed that 20% of this waste 
will be landfilled—which, in the absence of any relevant data, represents a reasonable 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  265
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

first estimate. By applying figures with respect to medium‐term penetration (50%) and 
energy content (200 m3 of landfill gas per tonne of waste with 70% of methane content), 
the  primary  potential  for  landfill  gas  in  Pakistan  in  2020  was  derived—around  300 
GWh/year (see Exhibit 9). 

Regarding costs, we have employed the following parameters: 
• Investment cost range: US$ 1,430‐1,840/kW (based on current European costs). 
• O&M cost: 7% of investment cost per year. 
• Fuel cost: In this conservative estimation, we assumed zero cost for the landfilled 
waste; however, it is important to mention that some experts argue in favor of 
setting  a  negative  cost  to  the  landfilled  waste  due  to  the  methane  emissions 
produced. 
• Self consumption: 8% of output. 
• Energy conversion efficiency range: 32‐36%. 
• Load factor range: 60‐80%. 

Using this information and the probabilistic cost approach, the supply curve for landfill 
gas  was  computed  and  is  presented  in  Exhibit  9  for  medium‐term  penetration  in 
Pakistan. 

Exhibit 9: Landfill Gas‐based Power Supply Curve 
80

70

60

50
USD/MWh

40

30

20

10

Landfill
0
0 50 100 150 200 250 300 350
GWh/a

 
Sewage gas: Water disposal per capita and collection by sewage plants were estimated 
by using information from the Karachi Water and Sewerage Board (KWSB); the amount 
of sewage sludge was assumed to be 10% of total collected sewage. The medium‐term 
potential  for  electricity  from  sewage  gas  was  calculated  by  applying  an  average  gas 
energy content of 6 kWh/m3, an electrical conversion efficiency of 30%, and a medium‐
term  penetration  of  20%.  Based  on  these  assumptions,  we  estimate  120  GWh/year  as 
the potential for power generation from sewage gas in Pakistan. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  266
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Regarding costs, we have employed the following parameters: 
• Investment cost range: US$ 2,300‐3,400/kW (based on current European costs). 
• O&M cost: 7% of investment cost per year. 
• Fuel cost: As in the case of input cost for landfill gas, we assumed no cost for raw 
sewage.  
• Self consumption: 8% of output. 
• Energy conversion efficiency range: 28‐32%. 
• Load factor range: 60‐80%. 

Using this information and the probabilistic cost approach, the supply curve for sewage 
gas  was  computed  and  is  presented  in  Exhibit  10  for  medium‐term  penetration  in 
Pakistan. 

Exhibit 10: Sewage Gas‐based Power Supply Curve 
160

140

120

100
USD/MWh

80

60

40

20

Sewage
0
0 20 40 60 80 100 120 140
GWh/a

 
2.2 Solid Biomass 

As  already  commented,  the  energetic  use  of  biomass  stands  in  competition  to  its 
alternative uses—e.g., use of bagasse and straw in particle board manufacture, as well 
as for cellulosic ethanol—and, in addition, competition also occurs within the energetic 
fraction—e.g.,  solid  biomass,  such  as  wood,  represents  a  traditional  fuel  for  domestic 
heating, especially in rural areas, or, in certain cases, can be used for biofuel production. 

As  discussed  previously,  we  focus  here  on  agricultural  residues.  The  derivation  of  the 
primary  energy  potential  for  agricultural  residues  was  derived  using  the  following 
assumptions: 
• The most prominent representative of this category is straw, residues from rice 
and other crops, and bagasse—all common agricultural byproducts which can be 
utilized  for  combustion.  These  two  categories  present  a  large  potential  for  RES 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  267
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

development in Pakistan, given the scale of its agricultural sector. The approach 
followed  for  this  category  is  to  divide  agricultural  residues  in  two  main 
subcategories: 
o Sugarcane bagasse: This residue is abundant in Pakistan due to the large local 
production of sugarcane, and is well suited for RE‐based cogeneration (even 
though  sugarcane  bagasse  has  alternative  uses,  such  as  input  for  paper  or 
biofuel production, as already mentioned). 
o Straw  and  other  agricultural  residues:  Straw  and  crop  residues  from  wheat, 
rice and cotton, among others, have also been considered for the estimation 
of biomass potential. 

Bagasse‐based Cogeneration: Electricity potential for this technology was estimated by 
first  determining  annual  forecasted  sugarcane  production;  this  was  achieved  by 
multiplying the peak production area (1,100,000 ha in 2002‐3) with the peak production 
yield  (5.32  tonnes/ha)  in  order  to  reflect  possible  medium‐term  productivity 
improvements.  Average  energy  content  (around  4  kWh/kg)  was  applied  to  sugarcane 
bagasse  (estimated  to  be  30%  of  the  production).  Plant  efficiency  was  assumed  to  be 
low  (24%),  as  these  plants  produce  both  steam  and  electricity  (CHP  plants),  and 
medium‐term  penetration  is  expected  to  be  large  (30%)  due  to  the  characteristics  of 
sugarcane  production.  We  thus  estimate  around  5  TWh/year  as  the  medium‐term 
potential for bagasse‐based power generation in Pakistan. 

Regarding costs, we have employed the following parameters: 
• Investment cost range: US$ 887‐1,280/kW (based on current Indian costs). 
• O&M cost: 3% of investment cost per year. 
• Fuel input: Bagasse (5 months/year during sugarcane crushing season) and coal 
(approximately 4 months/year during non‐crushing season).  
• Fuel cost: For coal, we employed the same price as for the computation of the 
conventional  supply  curve  (coal  at  US$  75/tonne  as  defined  in  Annex  VI).  For 
bagasse, the alternative‐use cost in this study was estimated based on the cost of 
coal.  The  idea  is  simple:  if  the  opportunity  cost  of  the  bagasse  (for  instance,  in 
the  paper  industry)  is  less  than  the  cost  of  buying  coal,  the  producer  will  burn 
bagasse, and vice versa. We therefore employed around US$ 30/MWh based on 
this assumption.10 
• Self consumption: 10% of output. 
• Average energy conversion efficiency: 1.16 kWh/kg. 
• Load factor range: 50‐80%. 

                                                       
10
  Based on Indian price ratio of bagasse:coal, applied to a local coal price of US$ 75/tonne (Indian data from Gujarat 
Electricity Regulatory Commission, Government of India: Tariff Order 1/2007). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  268
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

In  the  case  of  this  technology,  private  and  social  costs  of  generation  are  different 
because of the consumption of coal. We have estimated the social cost of bagasse‐based 
energy  generation  taking  CO2  emissions  and  associated  costs  at  0.9  kg/kWh  and  US$ 
30/tonne of CO2, respectively (same figures as employed for conventional energy). 

Using this information and the probabilistic cost approach, the supply curve for bagasse‐
based cogeneration was computed and is presented, both in private and social terms, in 
Exhibit 11 for medium‐term penetration in Pakistan. 

Exhibit 11: Bagasse‐based Power Supply Curve 

90

80

70

60
USD/MWh

50

40

30

20

10
Co-gen (social) Co-gen (Private)
0
0 1000 2000 3000 4000 5000
GWh/a

 
Other  Solid  Biomass‐based  Generation:  Straw  and  other  crop  residue  potential  was 
estimated following an almost identical approach as for sugarcane bagasse. First, peak 
production was determined for the relevant crops (wheat, cotton, rice, maize, and other 
minor crops). Second, respective annual crop production was multiplied by its relevant 
average residue factor and heat content, the results of which are shown in Exhibit 12. 
Lastly,  international  experience  shows  that  5%  for  medium‐term  penetration  is  a 
feasible  value  for  biomass  penetration,  due  to  the  current  difficulties  in  organizing  a 
biomass  market  which  provides  a  clear  price  signal  to  electricity  generators.  We 
obtained around 5 TWh per year as the medium‐term potential. 

Regarding costs, we have employed the following parameters: 
• Investment  cost  range:  US$  1,060‐1,250/kW.  This  range  basically  represents  an 
average between Indian and European costs for this technology. 
• O&M cost: 7% of investment cost per year. 
• Fuel  cost:    We  have  assumed  that  this  technology  will  run  only  on  agricultural 
residues; however, the alternative cost in this study was estimated based on the 
cost  of  coal  (at  US$  75/tonne).  Again,  the  simple  argument  here  is  that  if  the 
opportunity  cost  of  rice  husk,  for  example,  is  less  than  the  cost  of  buying  coal, 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  269
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

the  producer  will  burn  rice  husk,  and  vice  versa.  We  have  therefore  employed 
around US$ 34/MWh as the fuel cost based on this assumption. 
• Self consumption: 10% of output. 
• Energy conversion efficiency: 1.16 kWh/kg. 
• Load factor range: 50‐80%. 

Exhibit 12: Annual Residues Produced by Crop Type 

Other

Wheat

Maize

Rice

Cotton

0 5 10 15 20 25 30 35 40

Mill ton
 
Using  this  information  and  the  probabilistic  cost  approach,  a  supply  curve  for  non‐
bagasse  based  power  generation  was  computed  and  is  presented  in  Exhibit  13  for 
medium‐term penetration in Pakistan. 

Exhibit 13: Non‐bagasse Biomass‐based Power Supply Curve 
100

90

80

70

60
USD/MWh

50

40

30

20

10
Biomass
0
0 500 1000 1500 2000 2500 3000 3500 4000 4500
GWh/a

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  270
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

2.3 Waste­to­Energy 

In  order  to  derive  the  incremental  medium‐term  potential  for  waste‐to‐energy  (WTE) 
generation, the amount of waste expected to be generated in the year 2020 needs to be 
estimated. To obtain a reasonable projection, the following methodology has been used: 
first,  an  econometric  regression  has  been  undertaken  to  estimate  urban  population  in 
Pakistan on 2020 as presented in Exhibit 14. 

Exhibit 14: Urban Population of Pakistan 

80

70

60

50
urban pop (mill)

40

30

20

10

Urban Population Estimated Urban Population


0
1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020
 
Source: Pakistan Economic Survey, 2006‐7, Government of Pakistan, Islamabad: 2007 

Second,  the  total  amount  of  waste  produced  was  determined  by  multiplying  the 
country’s  urban  population  by  average  waste  produced  per  person:  166  kg/person 
(based on data for India) per year. In addition, it has been assumed that waste collection 
will gradually improve in Pakistan’s cities to cover 50% of total waste generated by 2020. 

Finally, medium‐term WTE penetration was estimated to reach 15% of collected waste, 
as  waste‐to‐energy  is  the  best  alternative  for  the  non‐recyclable  proportion  of  waste 
and  international  experts’  recommendations  encourage  the  deployment  of  this 
technology.  Based  on  these  parameters,  we  obtain  500  GWh/year  as  the  potential  for 
WTE generation by 2020. 

Costs have been estimated according to the following parameters: 
• Investment  cost  range:    US$  2,000‐5,800/kW  (based  on  AEDB  prefeasibility 
studies and current European costs). 
• O&M cost: 3.7% of investment cost per year. 
• Fuel  cost:  Following  the  same  consideration  as  for  landfill  and  sewage  gas,  we 
have assumed no cost for the waste input. 
• Self consumption: 8% of output. 
• Energy conversion efficiency range: 18‐22%. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  271
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Load factor range: 50‐80%. 

Using  this  information  and  the  probabilistic  cost  approach,  the  supply  curve  was 
computed and is presented in Exhibit 15 for medium‐term WTE penetration in Pakistan. 

Exhibit 15: Waste‐to‐energy Supply Curve 

250

200

150
$/MWh

100

50

0
0 100 200 300 400 500 600
GWh/a

WTE
 
2.4 Small Hydro 

Pakistan has abundant water resources for electricity generation using small‐scale hydel 
(‘small’ hydro is defined by the Government of Pakistan (GoP) as plants with capacity up 
to  50  MW).  According  to  existing  information,11  this  technology’s  medium‐term 
potential amounts to 1,800 MW, spread over more than 550 projects (this corresponds 
to  around  12  TWh/year).  The  majority  of  these  potential  projects  have  not  yet 
progressed  beyond  preliminary  identification,  but  those  few  that  have  reached  the 
implementation stage provide important information regarding investment costs in this 
sector. 

As part of this study, we have requested from relevant provincial authorities information 
about the main features and costs of different projects (basically, installed capacity and 
annual  generation)  and  have  obtained  very  useful  information.  However,  some 
information gaps exist, and in some cases the energy outputs we obtained based on this 
information were unrealistic. 

In order to  calculate the load factors and investment costs for projects for which  such 


information was not readily available, the following approach was adopted: 
• An  econometric  estimation  for  investment  costs  (in  US$/kW)  related  to  the 
project  size,  with  a  floor  at  US$  2,000/kW  for  projects  smaller  than  5  MW  and 

                                                       
11
  Pakistan Hydel Power Potential, Private Power and Infrastructure Board (PPIB), Government of Pakistan: Islamabad 
2005 and stakeholder data.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  272
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

US$  1,750/kW  for  projects  between  5  MW  and  50  MW.  The  regression  can  be 
seen  in  Exhibit  16.  In  those  cases  where  investment  cost  was  lower  than 
US$ 1,750/kW,  or  where  we  have  no  data,  the  result  of  this  regression  was 
employed. 
• Where  we  had  no  data  about  expected  annual  generation,  we  developed 
statistical estimation of load factors. We also assumed a cap on plant load factors 
at 80%, even though in available feasibility studies projected load factors shown 
were  higher.  For  plants with  an  installed capacity  below  3 MW,  the load  factor 
has been assumed to be 80% for all plants. 

Exhibit 16: Econometric Estimation of Investment Costs for Small Hydro 

 
 

Other cost drivers for small‐scale hydel are summarized below: 
• O&M cost: 3% of investment cost per year. 
• Extra investment cost factor: 5% (due to differences in the construction duration 
between hydel and other RE technologies)   

Exhibit 17 presents the supply curve for small‐scale hydel technology in Pakistan. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  273
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 17: Small Hydro‐based Power Supply Curve 
300

250

200

USD/MWh
150

100

50

SS hydel
0
0 2000 4000 6000 8000 10000 12000 14000
GWh/a

 
2.5 Solar Photovoltaic 

For  analyzing  solar  potential  in  Pakistan,  the  baseline  information  is  provided  by  the 
solar  irradiation  map  developed  for  Pakistan  by  the  US  National  Renewable  Energy 
Laboratory  (NREL),  based  on  GSTHOMER  software.  This  software  allows  computing 
suitable land area by available solar irradiation (for both photovoltaic and solar thermal) 
estimated  as  kWh/m2‐day,  according  to  an  indirect  methodology  which  is  described  in 
the technical papers provided by NREL. ‘Suitable’ land means areas where PV solar farms 
can be installed. Additionally, we develop two different estimations: (1) solar PV which 
can  be  developed  in  urban  areas  (e.g.,  rooftops);  and  (2)  PV  in  non‐wooded  areas  for 
open‐field solar farms. Exhibit 18 presents the PV solar maps of Pakistan obtained with 
the NREL software. 

Exhibit 18: Solar PV Area Estimation for Pakistan 
Direct Solar Irradiance (kWh/m2‐day) 
Open Field PV Area Estimation Rooftop PV Area Estimation

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  274
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Once suitable areas have been estimated, the next step is to adjust them by a full load 
factor which reflects the average amount of hours per day during which the solar cell is 
expected  to  produce  at  peak  capacity.  This  factor  has  been  assumed  (according  to 
international experience) equal to 0.75 for rooftop installations and 0.78 for open‐field 
projects. 

Medium‐term penetration is assumed to be low for open‐field projects, as solar PV is the 
most expensive RE technology and in several places this technology has to compete with 
other  alternative  land  uses.  Therefore,  medium‐term  penetration  for  open  field  PV 
projects  in  Pakistan  is  taken  as  0.3%  of  estimated  total  available  area,  while  for  urban 
rooftop  applications  the  penetration  is  estimated  to  be  at  10%  of  the  estimated 
available area. Even under these assumptions, the medium‐term potential for solar PV in 
Pakistan is very significant, at around 4.5 TWh/year. As this is less than 3% of the total 
electricity  generation  expected  in  2020,  it  is  not  necessary  to  consider  operational 
constraints, as in the case of wind generation. 

Regarding costs, we have employed the following parameters: 
• Investment cost: US$ 5,080‐5,930/kW (based on current European costs). 
• O&M cost: 1% of investment cost. 
• Load factor range: 22‐25%. 

Exhibit 19 presents the supply curve for photovoltaic power generation based on these 
hypotheses and the probabilistic cost approach. 

Exhibit 19: PV‐based Power Supply Curve 
500

450

400

350

300
USD/MWh

250

200

150

100

50
PV
0
0 1000 2000 3000 4000 5000
GWh/a
 
2.6 Solar Thermal  

As  already  mentioned  above  for  the  PV  supply  curve,  the  potential  for  solar  thermal 
projects has been identified using the same software algorithms to estimate solar direct 
irradiation maps for Pakistan provided by NREL, as presented in Exhibit 20. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  275
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The  assessment  of  medium‐term  solar  thermal  penetration  is  based  on  assumptions 
with  respect  to  land  use  (i.e.,  0.2%  of  total  estimated  available  area).  Next,  electricity 
generation potentials are derived by applying plant‐specific conversion efficiencies. We 
thus  obtain  an  estimation  of  about  900  GWh/year  of  solar  thermal  generation  in 
Pakistan in 2020. 

 
Exhibit 20: Solar Thermal Area Estimation for Pakistan 

Direct Solar Irradiance (kWh/m2-day)

Regarding costs, we have employed the following parameters: 
• Investment cost: US$ 2,880‐4,465/kW (based on current European costs). 
• O&M cost: 6% of investment cost. 
• Expected Load factor range (%): 22‐25%. 

Exhibit  21  presents  the  supply  curve  for  solar  thermal  power  generation  technology 
based on these hypotheses and the probabilistic cost approach. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  276
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 21: Solar Thermal‐based Power Supply Curve 
450

400

350

300
USD/MWh

250

200

150

100

50
Solar Th
0
0 100 200 300 400 500 600 700 800 900
GWh/a
 
2.7 On­shore Wind 

Similar  to  the  solar  case,  the  base  information  to  compute  on‐shore  wind  potential  in 
Pakistan is the wind density map developed by the NREL based on GSTHOMER software. 
This software allows a direct computation of the land area under different wind density 
classes, estimated as W/m2 at 50 m height above ground level, according to an indirect 
methodology  which  is  described  in  technical  papers  provided  by  NREL.  The  software 
works with seven different average wind speed classes, ranging from 0 to more than 8.5 
m/s. ‘Suitable’ land again refers to areas where wind farms can be installed. Additionally, 
we  have  developed  two  different  estimations:  (1)  the  potential  constrained  by  setting 
the distance to the electricity grid network to be no greater than 25 km; and (2) the total 
theoretically feasible potential, with no grid proximity constraint. 

There have been other estimations of the wind potential in Pakistan made in the past. 
Recently, NREL presented the results of its studies for Pakistan: under some assumptions 
[i.e., maximum capacity of 5 MW per km2 in areas corresponding to Class 4 and higher 
(more than 400 watt/m2)], they found that 26,400 km2, about 3% of Pakistan’s total land 
area,  is  appropriate  for  installing  wind  farms  producing  a  total  of  up  to  130  GW.  The 
AEDB has identified a potential of 50 GW and indicated the GoP’s intent to help develop 
approximately 3,700 MW of wind power by 2020, a very small part of the total potential 
but probably in line with technological (transmission power stability) constraints. As can 
be seen, the main difference between the two cases lies in the development of the huge 
wind potential in the vast but remote Balochistan province. 

We  have  carried  out  our  simulations  based  on  GSTHOMER  software  calculations,  but 
with  our  own  assumptions  added  on  top.  On  the  one  hand,  our  estimations  are  more 
constrained because of the condition of proximity to existing power lines; on the other 
hand, we consider that current technology allows greater harvest potential—from 5 to 
6.5 MW/km2, depending on wind conditions. There are also probably some differences 
in the definition of suitable land. Once we get the potential for each cluster, we estimate 
the  expected  annual  energy  employing  a  Weibull‐based  modeling  method—by 
employing  a  Weibull  distribution  with  k  =  2  and  wind  speed  as  mean—and  a  typical 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  277
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

power curve for wind turbines of 2 MW at an air density of 1.225 kg/m3. Wind potential 
was scaled from 50 m to 80 m employing the standard rule of 1/7.12 

A  further  restriction  should  be  applied  in  order  to  consider  aspects  of  grid  integration 
and balancing. Based on other countries’ experience and past studies, we have assumed 
that the maximum achievable potential for electricity from wind can be limited to 10% 
of  the  expected  gross  electricity  generation  in  2020.  This  leads  to  approximately  23 
TWh/year  (around  9,000  MW),  according  to  our  estimations,  of  realizable  wind  power 
potential in Pakistan by 2020. In Exhibit 22 and Exhibit 23, the potentials for each of 5 
wind class clusters are shown both analytically and graphically. 

In order to compute the supply curve for wind power in Pakistan, shown in Exhibit 24, 
we  believe  that,  given  the  current  worldwide  wind  turbine  market  conditions,  an 
average  investment  cost  of  US$  2,000/kW‐installed  is  a  reasonable  assumption. 
However, in order to assess the uncertainty regarding investment cost, we have taken 
an  average  between  US$  1,800‐2,200/kW.  For  O&M  costs,  we  assume  US$  50/kW‐
installed per year.  

Exhibit 22: Wind potential estimation (near‐grid constrained and unconstrained) 
Expected
Expected
Km2 Km2 non- Potential Potential (non- Average load Generation
Class Type Generation (Non-
(constrained) (constrained) (constrained) (MW) constrained)(MW) factor (constrained)
constrained) (TWh)
(TWh)
2 Marginal 20,570 93,511 117,249 533,013 21.5% 221.1 1,005.3
3 Fair 9,921 39,324 57,542 228,079 27.2% 136.9 542.4
4 Good 3,421 16,280 20,526 123,156 32.8% 59.0 354.0
5 Excellent 522 4,391 3,263 20,391 36.4% 10.4 65.1
6&7 Oustanding 18 2,445 113 703 41.4% 0.4 2.5
 
Exhibit 23: Wind Potential Maps of Pakistan 

Constrained Estimation Unconstrained Estimation

                                                       
12
  This rule states that the relationship between wind potential and wind speed when height is modified is given by 
[Pota/Potb]=[Wind Speeda/Wind Speedb]3*A where A = 1/7 and a and b are the different heights. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  278
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 24: On‐shore Wind‐based Power Supply Curve 
Operational constraint
140

120

100

80
USD/MWh

60

40

20

Wind
0
0 5000 10000 15000 20000 25000 30000
GWh/a  

3 Incremental RE Supply Curve for 2020 
In this section, we compute the combined RES‐E supply curve for 2020 by adding up the 
supply  curves  of  each  of  the  different  technologies  considered  above  and  re‐ordering 
them based on economic merit order. The total incremental RE supply curve for Pakistan 
is illustrated in Exhibit 25. 

Exhibit 25: Total RES‐based Power Supply Curve for 2020 
(Medium‐term Incremental Potential) 
450

400

350

300
USD/MWh

250

200

150

100

50
Supply Curve (Private Cost) Supply curve (Social Cost)
0
0 10 20 30 40 50 60
TWh/a
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  279
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

As can be seen, according to our rough estimation, the total medium‐term potential for 
RES‐based  on‐grid  power  generation  in  Pakistan  is  around  55  TWh/year.  The  supply 
curve is relatively low‐stepped (from US$ 50/MWh to US$ 120/MWh) up to 50 TWh, and 
then becomes extremely steep because of the high cost of some technologies and the 
higher  extraction  cost  part  of  different  supply  curves.  Note  that  the  private  and  social 
supply curves are quite similar in the case of RES technologies, as the only technology on 
which external cost has an important effect is bagasse‐based CHP. 

4 Incremental Conventional Supply Curve for 2020 
The incremental private (i.e., without externalities) supply curve for conventional energy 
is  drawn  based  on  the  outputs  of  Annex  VI.  In  that  document,  the  cost  of  different 
conventional technologies that can be installed during the period 2008‐2020, based on 
an  international  crude  oil  price  scenario  of  US$  90/bbl,  and  corresponding  investment 
costs  based  on  2007  levels,  were  assessed.  Additionally,  the  optimal  shares  for  each 
generation  based  on  a  simulation  model  for  least‐cost  expansion,  were  computed. 
Exhibit 26 summarizes the key parameters required to compute the private supply curve 
(for details, please refer to Annex VI). 

The  exhibit  also  shows  some  sensitivities  that  will  be  later  employed.  Basically,  we 
simulate  two  kinds  of  sensitivities:  (1)  regarding  the  cost  of  capital,  and  (2)  regarding 
variations  from  the  optimal  least‐cost  expansion  plan,  such  as  those  caused  by  the 
development of fewer hydel plants than expected, less CCGT capacity running on gas, or 
combination of these cases. 

Exhibit 26: Basic Data for Determination of Private Supply Curve for Conventional Energy 
Technology-wise private cost of Conventional Generation - Expected Incremental generation 2008-2020
New CCGT New CCGT Steam Turbine Large Hydel Nuclear
Generation Options
Natural Gas Fuel Oil Local Coal
Total Investment cost (USD/KW) 882 812 1,400 1,547 2,000
Thermal Efficiency (%) 50% 43% 38%
Fuel Cost (USD/MMBtu) 6.29 13.77 2.75
Capital Cost (USc/KWh) 1.79 1.64 2.48 5.01 3.33
O&M Cost (USc/KWh) 0.59 0.81 0.61 0.47 0.63
Fuel Cost (USc/KWh) 4.29 10.92 2.47 - 1.07
Total Generation Cost (USc/KWh) @12 % 6.67 13.38 5.56 5.48 5.04
Total Generation Cost (USc/KWh) @10 % 6.41 13.14 5.20 4.95 4.55

Total Generation Cost (USc/KWh) @14 % 6.94 13.63 5.93 6.03 5.54
Expected Incremental generation 2020
25.05 17.11 28.54 69.18 11.94
(TWh) [Base Case]
Expected Incremental generation 2020 (TWh)
24.89 17.26 61.70 36.02 11.94
[Low Hydel Case]

Expected Incremental generation 2020 (TWh)


9.54 19.26 41.89 69.18 11.94
[Low Gas Case]
Expected Incremental generation 2020 (TWh)
9.54 22.98 71.33 36.02 11.94
[Worse Case]  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  280
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

As was previously mentioned, the cost figures for electricity production from coal and oil 
would be substantially increased if externalities are taken into account. In this analysis, 
we take into account the following external costs: 

Global environmental costs: These include all greenhouse gas emissions having a global 
impact on the earth’s climate. The generation of energy from renewable sources avoids 
CO2  emissions  that  would  otherwise  have  been  released  with  fossil  power  generation; 
hence,  we  need  to  add  related  costs  (of  climate  change  impact  or  mitigation)  to  fossil 
fuel‐based  conventional  generation.  In  order  to  simplify  the  analysis,  we  assume  the 
cost  of  CO2  abated  at  €20/tonne  (US$  30/tonne),  based  on  the  EU‐ETS  forward  curve 
(European CO2 market) and standard average greenhouse gas (GHG) emission rates by 
technology.  Specifically,  we  employed  an  average  emission  rate  of  375  g‐CO2/kWh  for 
gas‐based  CCGT,  900  g‐CO2/kWh  for  coal  plants  and  500  g‐CO2/kWh  for  fuel  oil‐based 
CCGT. 

Air quality: While CO2 emissions from conventional power production are critical due to 
their  global  warming  potential,  nitrogen  oxides  and  sulfur  oxides  do  not  spread  in  the 
atmosphere  on  a  global  scale,  but  are  responsible  for  local/regional  pollution  close  to 
their emission sources. Similar to the case of CO2, as most alternative RES‐E technologies 
do  not  emit  neither  NOx/SO2  nor  particulates,  the  additional  cost  of  local  pollution 
impacts should be added to those for conventional power generation in order to make 
comparisons with RES meaningful. A suitable reference for this cost is the cost of limiting 
the emission of NOx, SO2 and particulates, and a good reference figure in OECD countries 
for  limiting  the  three  pollutants  is  US$  100/kW13  (most  of  the  cost  is  SO2‐related)  and 
variable costs of around US¢ 0.25/kWh. Depending on the plant load factor, the external 
cost of local air quality‐related impacts range from US$ 4/MWh to US$ 6/MWh. 

Fuel dependency: Rising oil prices and the concomitant general increase in energy prices 
(oil  derivatives,  gas,  and  even  coal,  with  some  lag),  reveal  the  vulnerability  and 
dependency on energy imports of most economies, to which Pakistan is no exception as 
is  a  net  importer  of  energy.  Several  recent  studies  (IMF,  200014;  EIA,  200415;  EU‐DG 
ECFIN, 2003‐200616; among others17) have evaluated the effects on national economies 
of a sustained oil price increase. All these reports agree that a sustained increase in oil 
price would cause a decrease of about 0.3%‐0.4% in GDP growth during the first two to 
four  years  in  the  OECD  countries,  and  up  to  3%  in  the  least  developed  countries.  In 
emerging countries, such as Pakistan, the average effect stands for 1% decrease in GDP 

                                                       
13
  There is a range between US$ 80/kW and US$ 140/kW. We preferred to be conservative. 
14
  “The  Impact  of  Higher  Oil  Prices  on  the  Global  Economy”,  December  8,  2000.  Research  Department  Paper. 
International Monetary Fund (IMF), Washington: 2000. 
15
  “Analysis of the Impact of High Oil Prices on the Global Economy”, International Energy Agency, Paris:2004. 
16
  See www.ExternE.info for relevant papers. 
17
  E.g.,  Huntington,  H  G,  “Shares,  Gaps  and  the  Economy’s  Response  to  Oil  Disruptions”,  Energy  Modelling  Forum, 
Stanford  University,  Stanford:  2004;  Bohi,  DR  &  MA  Toman,  The  Economics  of  Energy  Security,  Kluwer.  Boston: 
1996; Brown & Yucel, “Energy Prices and Aggregate Economic Activity: An Interpretive Study”, Quarterly Review of 
Economics and Finance, Federal Reserve Bank of Dallas, Dallas, TX: 2001; Costantini, V & F Gracceva, “Social Costs of 
Energy  Disruptions”,  INDES  Working  Paper  No.  6,  Centre  for  European  Policy  Studies:  2004;.  Cunado  J,  “Do  Oil 
Shocks Matter? Evidence for Some European Countries”. University of Navarra: 2000. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  281
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

growth  during  that  period.  This  kind  of  analysis  underestimates  the  real  effect  of  fuel 
dependency,  because  it  does  not  consider  other  impacts,  such  as  price  volatility, 
shortages, etc. We follow the traditional approach of modeling only a price increase as 
the  other  effects  are  rather  complex  to  estimate  accurately,  and  there  is  no  sound 
international  agreement  on  how  to  properly  assess  them.  Before  carrying  out  an 
estimation of the impact of external fuel dependency for Pakistan, a statement should 
be made: calculating the effect of oil dependency on security of supply is rather complex 
and  full  of  assumptions;  different  studies  have  computed  this  effect  for  different 
countries, and the range derived from international experience is very large—from US$ 
5/MWh  to  US$  300/MWh.  In  our  assessment,  we  have  assumed:  (1)  an  average 
probability of price increase of 20% over a four‐year period, which is a reasonable figure 
with respect to other similar studies and considering that we are working under a crude 
oil base case of US$ 90/bbl; (2) the effect on GDP was assessed considering a four‐year 
impact of 1% per year, taking 2006 as base year GDP; and (3) the share of oil and gas 
imported  for  the    power  sector  in  2020  was  assumed  to  be  20%  of  total  oil  and  gas 
imports (see Annex VI). 

The  external  cost  of  different  conventional  power  generation  technologies  arrived  at 
based on these assumptions are presented in Exhibit 27. 

Exhibit 27: Basic Data for Social Supply Curve for Conventional Energy 
Technology-wise Social Cost of conventional Generation
New CCGT New CCGT Steam Turbine Large Hydel Nuclear
Generation Options
Natural Gas Fuel Oil Local Coal
Private generation cost (Usc/kWh) 6.67 13.38 5.56 5.48 5.04
C02 Ext. Cost (USc/kWh) 1.11 1.5 2.7
Local Pollut. Ext. Cost (USc/kWh) - 0.45 0.43
Security of supply. Ext. Cost (Usc/kWh) 2.48 2.48

Total Generation Cost (USc/KWh) 10.26 17.82 8.69 5.48 5.04


 
Based on the analysis given in Annex VI and the assessment of externalities previously 
described, we may draw the private and social supply curve for conventional energy in 
Pakistan for 2020, which is shown in Exhibit 28. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  282
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 28: Private and Social Supply Curves for Conventional Energy for 2020 
200

180

160

140

120
USD/MWh

100

80

60

40

20

Conventional Private Curve Conventional Social Curve


0
0 20 40 60 80 100 120 140
TWh/a  

5 Costs and Potential of RES Penetration under Different Policies 
5.1 Natural Penetration of Renewable Energy Sources 

The  first  element  that  we  need  to  identify  is  whether,  under  a  private  cost  analysis, 
there are economic signals that may foster the development of RE in the event that all 
other barriers (administrative, regulatory, financial,18 etc.) are removed. The analysis is 
shown in Exhibit 29. This is similar to Exhibit 2, but in this case the private supply curves, 
both for RE and conventional energy, are the results of our estimations for Pakistan in 
the medium term.  

                                                       
18
  By  financial  barriers,  we  mean  the  case  in  which—from  an  economic  point  of  view—some  technologies  could be 
developed but because, for example, of difficulties in the credit market, small producers cannot access the funds 
needed to develop these projects, and such opportunities are therefore not realized. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  283
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 29: Optimal RES‐E Penetration under Private Costs 
  400
375 RES-E Supply Curve
350
Conventional Private Supply Curve
325
300
275
250
$/MWh

225
200
175
150
125
100
75
50
25
0
0 20 40 60 80 100 120 140
TWh/a
 
In Exhibit 29, from the part (X:Y) in which both supply curves meet each other, we can 
get the optimal amount of RE penetration and the marginal cost of RE (the cost of the 
last RE plant that is cheaper than the last conventional plant replaced). In this case, we 
observe that the natural penetration of RES‐E should be around 17 TWh/year—which is 
around  7%  of  total  power  generation  expected  in  2020.  As  we  can  see  in  Exhibit  30, 
almost  60%  of  this  share  is  comprised  of  hydel  plants  that  are  cheaper  than  CCGT 
running on fuel oil (FO), which establish the price of avoided generation. The other two 
RE  technologies  that  should  be  developed  are  bagasse‐based  CHP  and  other  types  of 
biomass.  

Exhibit 30: RES‐E Technology‐wise Penetration under Private Costs 
  RES-E Penetration (@ Private Cost)
(Tech; TWh/a; %)

SS Hydel
9.6
Wind 56.4% Landfill
0.0 0.3
0.0% 1.7%

Solar Th
0.0
0.0%
Sew
0.0
0.0%

PV Biogas
Co-gen 0.7
0.0
4.1 3.8%
0.0% WTE 23.9% Biomass
0.0 2.4
0.2% 13.9%

 
This result shows that all future CCGTs running on FO should be replaced by some RES‐E, 
such  as  small‐scale  hydel  and  biomass.  The  fact  that  this  energy  is  not  currently 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  284
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

developed  indicates  that  some  barriers  may  exist,  especially  if  we  consider  that  the 
marginal cost for RE is around US$ 75/MWh and the cost of generation based on FO is 
higher than US$ 125/MWh. 

Another  important  piece  of  information  that  can  be  derived  from  Exhibit 29  is  the 
manner  in  which  the  avoided  cost  of  generation  based  on  FO  is  distributed  amongst 
different  players  when  replaced  by  cheaper  RES‐E  generation.  The  avoided  cost  is 
distributed between: 
• The cost of generation based on RES‐E; and 
• The surplus, which can be distributed between the producers and consumers. 

These three different areas are drawn in Exhibit 29 (colored bars) in order to show how 
they are computed. The objective of a good renewable energy policy is to maximize the 
total  surplus,  regardless  of  how  this  surplus  is  distributed  between  producers  and 
consumers. We will analyze in the following sections how the distribution of the surplus 
depends on the designed incentive mechanism. In this case, the generation cost of the 
RES‐E  plants  that  replaced  the  CCGT  (FO)  is  around  US$  1,027  million  per  year  (2020), 
the  producer  surplus  is  US$  235  million,  and  the  consumer  surplus  is  about 
US$ 1,024 million; therefore, total surplus is US$ 1,260 million. This means that Pakistani 
society can gain up to around US$ 1.3 billion per year if some of the existing barriers—
that are effectively blocking the effect of economic signals—are removed. 

It should be noted that this analysis is not considering the cost of peaking plants, as it is 
based  on  the  medium‐term  need  for  energy,  not  operational  capacity.  This  may 
underestimate  the  real  avoided  cost  because  it  is  not  considering  the  cost  of  peaking 
plants (gas open turbines or reciprocating engines), which costs are probably higher than 
the cost of the CCGT running on FO because the load factor is much lower for peaking 
plants. 

5.2 Optimal Quota of Renewable Energy in 2020 

A renewable energy policy should be based on a social assessment of cost and benefits. 
The  analysis  given  in  the  previous  section  does  not  consider externalities;  therefore,  it 
forms  a  limited  analysis  meeting  only  minimum  requirements.  In  order  to  identify 
optimal  penetration  under  proper  social  assessment,  the  analysis  performed  in 
Exhibit 29 must be redone, but this time considering the social supply curves, both for 
RES‐E and for conventional energy. This is shown in Exhibit 31. In this case, we observe 
that optimal penetration of RES‐E in Pakistan should be around 25 TWh/year, which is 
around  10.4%  of  total  grid  electricity  generation  expected  in  2020.  It  can  thus  be 
surmised  that  market  failure  (resulting  in  externalities  not  being  internalized)  would 
hamper  the  development  of  about  8  TWh/year  (=  25  TWh/year  –  17  TWh/year)  of 
renewable  energy  in  2020.  To  develop  this  extra  8  TWh/year,  an  economic  incentive 
mechanism is required, as will be discussed later, assuming that all other barriers to the 
development of the first 17 TWh of RES‐E have already been removed. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  285
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 31: Optimal RES‐E Penetration under Social Costs 
 
400
375 RES-E Supply Curve
350
Conventional Social Supply Curve
325
300
275
250
$/MWh

225
200
175
150
125
100
75
50
25
0
0 20 40 60 80 100 120 140
TWh/a
 
As we can see in Exhibit 32, under social cost assessment, not only hydel and biomass 
plants  but  also  biogas  (farm  slurries,  sewage,  landfills,  etc.)  and  wind  power  plants 
would be required to replace both CCGTs running on FO and natural gas; as a matter of 
fact, all FO‐based generation is replaced, as well as around 15% of gas‐based generation. 
The  largest  share  of  RE  generation  is  from  hydel,  as  in  the  previous  case.  Definitely, 
small‐scale hydel is the cheapest option for developing RES‐E in Pakistan, and should be 
encouraged  as  early  as  possible.  It  is  also  important  to  note  that  some  RES‐E 
technologies, such as solar PV or solar thermal, are not economically feasible as on‐grid 
solutions in current price/technology conditions. The penetration of waste‐to‐energy in 
the  medium  term  is  very  small  as  it  is  a  very  expensive  technology;  however,  the 
development of this technology is also related to waste management and can result in 
multiple benefit streams (improved sanitation and lower health costs, etc.), while open 
dumps  and  landfills  are  not  a  sustainable  alternative.  Thus,  this  technology  may  be 
developed for some of these other reasons. 

From Exhibit 31, we can compute the distribution of the avoided cost. In this case, the 
cost of generation based on RES‐E is around US$ 1,800 million per year in 2020 and the 
total surplus stands at US$ 2,100 million per year in 2020. It is relevant to observe that 
total surplus increases by US$ 740 million with respect to the natural penetration case. 
This  implies  that  market  failure  results  in  extracting  around  US$  800  million  per  year 
from Pakistani society. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  286
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 32: RES‐E Technology‐wise Penetration under Social Costs 
  RES-E Penetration (@ Social Cost)
(Tech; TWh/a; %)

Landfill
0.3
1.2%

SS Hydel
11.2
44.1%
Sew
0.1
0.2%
Wind
2.8
11.0%

Biogas
2.2
Solar Th Co-gen 8.5%
0.0 4.6
0.0% 17.9%
PV Biomass
WTE
0.0 4.2
0.2
0.0% 16.5%
0.7%

 
5.3 Analysis of Single Feed­in Tariff Mechanism 

The  simplest  RES‐E  incentive  mechanism  would  be  to  set  a  single  feed‐in  tariff—that 
means  establishing  only  one  feed‐in  tariff  for  all  technologies—at  the  marginal  cost  of 
RES‐E generation under the social cost assessment case, which according to the analysis 
presented  here,  is  US$  103/MWh.  This  mechanism  should  be  equivalent  to  setting  a 
quota at 10.4% of total generation in 2020. However, as was explained in Annex IV, the 
effectiveness  of  the  quota  system  is  worse  than  the  feed‐in  system  because  of  the 
complexities of designing a secondary market for green certificates and the penalties to 
be applied when the quota is not fulfilled. 

The single feed‐in tariff is said to have two mains drawbacks: 
• It  does  not  foster  the  development  of  certain  technologies,  basically  those 
technologies  that  are  more  expensive  than  the  marginal  cost  of  supplying  the 
optimal  quota  of  RES‐E  in  total  generation  (in  this  case,  all  technologies  with 
costs higher than US$ 103/MWh). 
• It  may  generate  high  producer  surplus—and,  hence,  decrease  the  consumer 
surplus, given a total surplus. 

It  must  be  understood  that  neither  the  first  shortcoming  nor  the  second  are 
disadvantageous  from  an  economic  point  of  view  as  they  are  not  related  to  economic 
efficiency: the first one is about long‐term industrial policy, while the second relates to 
wealth  distribution.  The  first  shortcoming  will  be  addressed  in  this  study  by  analyzing 
how  the  total  surplus  is  affected  when  industry‐driven  policies  are  put  in  place. 
Regarding the distribution of the surplus, it is important to observe that: 
• As  a  rule  of  thumb,  multiple  or  technology‐based  feed‐in  tariffs  tend  to  reduce 
the producers’ surplus, given a total surplus. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  287
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• A  cost‐plus  approach,  in  which  the  cost  is  assessed  for  each  plant,  under  the 
hypothesis  of  no  information  asymmetry,  makes  the  producers’  surplus  tend 
towards zero, maximizing the consumers’ surplus. 
• The producers’ surplus is a consequence of the inframarginal rents. Inframarginal 
rents can be observed in all markets, from cookies to power pools, and represent 
a natural incentive for investors to perform an activity.  
• The amount of producer surplus depends on the slope of the RE supply curve in 
the part that is lower than the conventional supply curve. The higher the slope, 
the greater the producer’s surplus. That is why it is extremely important to have 
an idea of the RE supply curve before designing an incentive mechanism for RE. 
• The removal of all of the producers’ surplus by applying a cost‐plus mechanism 
will: (1) on one hand, decrease the incentive to invest in RE technologies; and (2) 
on  the  other  hand,  make  investors  game  against  the  cost‐plus  mechanism—a 
mechanism  in  which  the  information  advantage  is  on  the  producers’  side; 
besides  that,  the  cost‐plus  mechanism  carries  additional  administrative  burden 
and tends to delay the development of RES technologies. 

In this study, we focus on analyzing how the producer’s surplus changes under different 
policies,  starting  with  a  single  feed‐in  tariff.  As  shown  in  Exhibit  33,  the  total  surplus 
under  a  single  feed‐in  tariff  in  Pakistan  in  2020  would  be  around  US$  2.1  billion, 
distributed with about US$ 800 million for producers and US$ 1.3 billion for consumers.  
Exhibit 33: Distribution of Producer Surplus by RES‐E Technology under Single Feed‐in 
Tariff 
 
WTE

Wind

SS Hydel

Solar Thermal

Sewage

PV

Landfill

Biomass

Biogas

Bagasse

0 50 100 150 200 250 300 350 400 450 500


M$/a

 
It  is  very  interesting  to  note  that  the  producer  surplus  is  almost  three‐times  higher  in 
comparison with the case of natural penetration, while the consumer surplus increases 
by  only  30%.  In  Exhibit  33,  it  can  be  observed  how  the  US$  800  million  of  producer 
surplus is shared amongst the producers using different technologies. As can be seen in 
the  exhibit,  small‐scale  hydel  plants  get  the  major  share  of  the  producer’s  surplus 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  288
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

(around  US$  500  million  in  2020),  and  this  extra  revenue  is  actually  an  incentive  to 
develop hydel plants. 

5.4 Analysis of Technology­based Feed­in Tariff Mechanism 

We simulate three different cases in order to identify changes in total surplus and in its 
distribution between producers and consumers: 
• Optimal  quota‐constrained  analysis—cost‐efficient  case:  In  this  case,  we 
assume the same technologies, and the same penetration for each RES‐E, as we 
did  under  the  optimal  quota  analysis,  but  shift  from  a  single  feed‐in  tariff  to 
multiple feed‐in tariffs. 
• Optimal  quota‐constrained  analysis—industry  policy‐driven  case:  In  this  case, 
the same penetration (10.4%) for RES‐E is considered, but all RES‐E technologies 
are  taken  into  account,  including  those  that  they  do  not  qualify  under  the 
optimal  quota  analysis.  Therefore,  the  total  RES‐E  amount  is  the  same,  but  the 
composition of the portfolio is different. 
• Exhausting the medium‐term potential: In this case, we define a set of feed‐in 
tariffs that serve as an economic signal for producing about 55 TWh of renewable 
energy, instead of 25 TWh that is implicit in the optimal quota. 

Except for the first case, the proposed alternatives are not cost‐efficient and, hence, it 
can be expected that the total surplus will be lower under the second and third cases. 

5.4.1 Optimal Quota­constrained Analysis 

Cost‐efficient Case 

In  Exhibit  30  we  can  see  the  RES‐E  portfolio  feasible  under  an  optimal  quota  analysis. 
From  the  RES‐E  supply  curve,  we  can  compute  which  is  the  more  expensive  plant  for 
each  technology  cheaper  than  US$  103/MWh.  The  costs  of  these  plants  would  be  the 
feed‐in tariff (FIT) for each RE. The feed‐in tariffs for each RES‐E generation technology 
are shown in Exhibit 34. 

The feed‐in tariff for each technology is generally lower than the single feed‐in tariff, as 
expected,  and  hence  the  producers’  surplus  is  lower.  In  effect,  the  producers’  surplus 
decreases  from  US$  795  million  to  US$  638  million,  but  the  total  surplus  remains  the 
same—US$ 2,089 million. Thus, there is an increase in the consumers’ surplus of around 
US$ 157 million. From a theoretical point of view, the entire producers’ surplus might be 
converted  into  consumers’  surplus—i.e.,  total  surplus  equal  to  consumer  surplus—but 
this alternative, as mentioned before, has some drawbacks. Multiple feed‐in tariffs stand 
for  an  adequate  trade‐off  for  allocating  producers’  surplus,  as  they  transfer  a  share  to 
the consumers but ensure that the producers’ surplus remains high enough to be able to 
attract investors. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  289
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 34: Producer Surplus under Multiple Feed‐in Tariffs  
(Cost‐efficient Approach) 
FIT by RE Technology
4,500
Gener at i on RE S- E Sur pl us Consumer Sur pl us (USD/MWh)
4,000
Bagasse based CHP 84.8
3,500
1, 2 9 4
1, 4 5 2
Biogas 99.6
3,000
Biomass 86.1
Landfill 73.4
2,500
798 640
2,000
Sewage 101.9
SS Hydel 103.3
1, 5 0 0

Wind 102.3
1, 0 0 0 1, 8 13 1, 8 13

WTE 96.9
500

0
S i ngl e FI T M ul t i pl e FI T

Industry Policy‐driven Case 

In this case, we simulate the situation in which all RES‐E technologies must be installed. 
The penetration for each RES was computed by multiplying the medium‐term potential 
for each RES times the factor ‘optimal quota/medium‐term potential’, which is 45%. The 
feed‐in  tariff  for  each  RES‐E  is  computed  considering  the  cost  of  the  most  expensive 
plant required to cover the required energy from each RES. For instance, in the case of 
small‐scale hydel, the penetration under the optimal quota analysis is about 11.3 TWh, 
while under the current case it is 3.7 TWh; the cost of the most expensive plant to cover 
11.3 TWh per year of generation is US$ 103.3/MWh, but the cost of the most expensive 
plant to cover 3.7 TWh per year of generation is US$ 54.1/MWh. The other feed‐in tariffs 
(FITs) are computed in a similar fashion. In Exhibit 35, the FITs for each RES‐E are shown. 

Exhibit 35: Surplus under Multiple Feed‐in Tariffs (Industry Policy‐driven Approach) 
4,500 FIT by RE Technology
Ge n e r a t i o n R ES - E S u r p l u s C o n su m e r S u r p l u s
4,000 (USD/MWh)
Bagasse based
3,500
1, 2 9 4
879 CHP 68.9
3,000 234 Biogas 75.4
2,500
Biomass 69.6
798 Landfill 54.7
2,000 Sewage 96.0
1, 5 0 0 2,791
SS Hydel 54.1
Wind 109.0
1, 0 0 0 1, 8 13
WTE 96.9
500 Solar Thermal 326.8
0 Photovoltaic 
371.7
S i ngl e FI T M ul t i pl e FI T

It is important to note that, in this case, cheap energy (small‐scale hydel, for instance) is 
replaced  by  more  expensive  energy,  such  as  solar  PV  or  solar  thermal.  This  makes  the 
total surplus decrease from US$ 2,089 million to around US$ 1,100 million. Within the 
power  sector,  this  policy  would  reduce  wealth  by  about  US$  1,000  million  every  year, 
which  it  is  supposed  to  be  created  in  another  area,  for  instance,  through  the 
development  of  a  local  solar  PV  industry.  The  most  affected  agents  are  the  producers 
using the cheapest technologies, who stand to lose around US$ 400 million per year as a 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  290
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

result of such a policy. As can be seen in Exhibit 35, the total surplus decreases because 
the cost of RES‐based generation increases in the same proportion. 

5.4.2 Exhausting the Medium­term Potential 

In this case, we simulate that the total medium‐term RES‐based generation potential—
55  TWh—utilizing  all  RES‐E  technologies,  must  be  installed.  Each  RES‐E  technology’s 
penetration  is  the  corresponding  total  medium‐term  potential  estimated  in  this  study. 
The feed‐in tariff for each RES‐E technology is based on the cost of the most expensive 
plant necessary to cover the medium‐term potential. The only exception is the case of 
small‐scale hydel that has been capped at US$ 103.3/MWh, because from this point the 
supply  curve  becomes  extremely  steep  and,  hence,  the  inframarginal  rent  for  adding 
only 400 GWh of generation per year becomes huge. The feed‐in tariffs for the different 
RE technologies can be seen in Exhibit 36. 

Exhibit 36: Surpluses under Multiple Feed‐in Tariffs Exhausting 
Medium‐term RES‐E Potential 
9,000
FIT by RE Technology
8,000
Generation Cost RES-E Surplus Consumer Surplus (USD/MWh)
7,000 1,251 Bagasse based CHP 84.8
6,000
Biogas 117.5
5,000
Biomass 86.1
4,000
Landfill 73.4
3,000
1,294 6,526 PV 430.5
2,000
798 Sewage 134.2
1,000 1,813
Solar Thermal 427.4
0 SS Hydel 103.3
-1,126
-1,000 Wind 127.0
-2,000 WTE  
216.8
Single FIT Multiple FIT

Installing  55  TWh  of  RES‐E  generation—about  a  22%  quota  with  respect  to  total 
generation in 2020—is not efficient from an economic point of view, because in this case 
cheaper  conventional  energy  is  replaced  by  RES‐E  technologies  that  are  extremely 
expensive. This is notable in the change of the total surplus, which decreases from US$ 
2,089  million  per  year  in  the  cost‐efficient  case  down  to  about  US$  120  million.  As  a 
matter  of  fact,  the  consumers’  surplus  becomes  negative;  this  is  definitely  not  a 
convenient situation for consumers. The cost of generation based on RE increases from 
US$  1,800  million  up  to  around  US$  6,500  million,  and  we  find  a  positive  producers’ 
surplus of about US$ 1,240 million per year in 2020. 

5.5 Sensitivity Analysis  

We now undertake some scenario‐analysis in order to determine the robustness of our 
conclusions. We simulate the following sensitivities: 
• Cost of capital: In our base case, we have considered a 12% real pre‐tax IRR rate. 
We  simulate  two  additional  scenarios  by  adding/subtracting  200  basis  points 
(BPs)  to  the  base  case.  Changes  in  the  cost  of  capital  have  some  effect  on  our 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  291
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

conclusions, since RES technologies, broadly speaking, are more capital‐intensive 
than conventional energy technologies and, hence, ceteris paribus, the higher the 
capital cost, the higher the optimal share of conventional energy in the total. 
• Changes  in  conventional  supply  curve:  In  the base  case  scenario,  we  employ  a 
conventional supply curve based on the outputs of a least‐cost expansion plan. 
Differences  from  this  benchmark  may  change  the  value  of  avoided  costs  and, 
hence, modify the optimal quota of RE and the total surplus. 
• Fuel  cost:  We  have  employed  a  base  case  scenario  which  assumes  the  price  of 
crude  oil  to  be  US$  90/bbl.  Deviations  from  this  figure  may  also  alter  avoided 
costs and, therefore, the conclusions of our study. 

For the two first sensitivities, we run the model again and study the differences between 
the  base  case  and  the  new  scenarios.  In  the  sensitivity  for  fuel  cost,  we  undertake  a 
threshold  study—what  oil  price  scenario  changes  the  conclusions  of  our  study?—since 
this  seems  to  more  convenient  than  conducting  iterative  model  runs  with  different  oil 
prices.  

In Exhibit 37 we present the results of five different scenarios from the base case that 
demonstrate the sensitivity of the analyses presented in this study to changes in the first 
two assumptions bulleted above. 

As can be seen, as far as the optimal quota of RES‐E is concerned, only changes in the 
cost of capital result in some variations from the base case; as expected, when the cost 
of capital decreases down to 10%, the optimal quota for RES‐E increases from 10.4% up 
to  14.1%.  The  natural  penetration  of  RES‐E  does  not  depends  on  the  cost  of  capital, 
however, but on the form of the conventional supply curve; in the ‘worst’ case, natural 
penetration increases up to almost 10%. 

The  ‘low  hydel’  and  ‘low  gas’  conventional  supply  cases  have  a  limited  effect  on 
results—the effect on both the optimal quota and total surplus is negligible. However, 
the ‘worst’ case, in which at the same time there is less hydel and gas generation, has a 
relatively important effect on avoided cost because part of this generation is replaced by 
CCGT running on FO. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  292
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 37: Sensitivity Analysis (Differences from Base Case) 
Low Base Case
Base
Hydel Low Gas Worst @ 10% Base Case
Case
Case Case Case IRR @ 14% IRR
RE Penetration (@Social) 10.4% 0.0% 0.0% 0.0% 3.7% -1.6%
RE Penetration (@Private) 7.0% 0.0% 0.8% 2.3% 0.0% 0.0%
@Social Costs:
RES-E Generation Costs 1,813 - - - 776 - 274
RES-E Surplus 798 - - - 165 - 113
Consumer Surplus 1,294 - - - 5 - 1
Single FIT
@Private Costs:
RES-E Generation Costs 1,027 27 254 514 - 53 84
RES-E Surplus 235 - 26 76 32 - 19 - 3
Consumer Surplus 1,028 - 1 21 240 30 - 38
Multiple FIT-
@Social Costs:
Exhausting the RES-E Generation Costs 6,526 - - - - 624 651
mid-term RES-E Surplus 1,251 - - - - 8 8
potential
Consumer Surplus -1,126 - - 48 292 632 - 659
Multiple FIT - @Social Costs:
Optimal quota- RES-E Generation Costs 2,791 - - - 766 - 179
constrained
analysis, industry RES-E Surplus 234 - - - 156 - 36
policy driven case
Consumer Surplus 879 - - - 26 - 172
Multiple FIT - @Social Costs:
Optimal quota- RES-E Generation Costs 1,813 - - - 776 - 274
constrained
analysis, cost- RES-E Surplus 640 - - - 127 - 71
efficient case
Consumer Surplus 1,452 - - - 44 - 43  
Therefore,  both  in  the  ‘worst’  case  for  conventional  supply  and  in  the  sensitivities 
relating  to  cost  of  capital,  we  can  observe  discernable  changes  in  the  total  surplus.  In 
Exhibit 38 to Exhibit 42, changes in consumers’ and producers’ surpluses in each of the 
different sensitivity scenarios analyzed can be observed. 

Exhibit 38: Consumer and Producer Surpluses under Different Cases 
(Private Cost Evaluation) 
3,500
Consumer Surplus
RES-E Surplus
RES-E Generation Costs
3,000

2,500
1,268

1,049
2,000
USDMM/a

990
1,028 1,027
1,058
267
1,500
311

232
235 209
216
1,000

1,541
1,281
1,027 1,054 1,111
500 974

0
Base Case Low Hydel Case Low Gas Case Worst Case Base Case @ 10% Base Case @ 14%
IRR IRR
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  293
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 39: Consumer and Producer Surpluses under Different Cases 
(Single Feed‐in Tariff) 
6,000
Consumer Surplus
RES-E Surplus
RES-E Generation Costs
5,000

1,299
4,000
USDMM/a

1,294 1,294 1,294 1,294


3,000 963
1,293

798 798 798 798


2,000
685

2,589
1,000
1,813 1,813 1,813 1,813
1,539

0
Base Case Low Hydel Case Low Gas Case Worst Case Base Case @ 10% Base Case @ 14%
IRR IRR

 
Exhibit 40: Consumer and Producer Surpluses under Different Cases 
(Multiple Feed‐in Tariffs Exhausting Medium‐term Potential) 
10,000
Consumer Surplus
RES-E Surplus
RES-E Generation Costs
8,000
1,259
1,251 1,251 1,251 1,251
1,243
6,000

4,000
7,177
USDMM/a

6,526 6,526 6,526 6,526


5,902

2,000

-834
-1,126 -1,126 -1,174 -494
-2,000
-1,785

-4,000
Base Case Low Hydel Case Low Gas Case Worst Case Base Case @ 10% Base Case @ 14%
IRR IRR
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  294
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 41: Consumer and Producer Surpluses under Different Cases 
(Multiple Feed‐in Tariffs with All‐technology Portfolio) 
6,000
Consumer Surplus
RES-E Surplus
RES-E Generation Costs
5,000

905

4,000
390
879 879 879 879
USDMM/a

707
3,000
234 234 234 234
198

2,000
3,557

2,791 2,791 2,791 2,791


2,612
1,000

0
Base Case Low Hydel Case Low Gas Case Worst Case Base Case @ 10% Base Case @ 14%
IRR IRR
 

Exhibit 42: Consumer and Producer Surpluses under Different Cases 
(Multiple Feed‐in Tariffs with Same Technologies and Penetration as under Single 
Feed‐in Tariff) 
6,000
Consumer Surplus
RES-E Surplus
RES-E Generation Costs
5,000

1,496
4,000
USDMM/a

1,452 1,452 1,452 1,452


3,000 767
1,409

640 640 640 640


2,000
569

2,589
1,000
1,813 1,813 1,813 1,813
1,539

0
Base Case Low Hydel Case Low Gas Case Worst Case Base Case @ 10% Base Case @ 14%
IRR IRR
 
Finally,  regarding  the  third  sensitivity  variable—fuel  cost—we  have  observed  that  our 
conclusions  are  completely  valid  even  when  considering  an  oil  price  scenario  of  US$ 
40/bbl.  In  oil  price  scenarios  ranging  between  US$  40/bbl  and  US$  15/bbl,  we  can 
identify  a  positive  total  surplus,  but  one  that  is  completely  appropriated  by  the 
producers. Only when the oil price is lower than US$ 15/bbl the conclusions of this study 
lose their validity. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  295
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

6 Initial Thoughts on Medium­term Policy 
In  this  study  we  have  carried  out  a  comprehensive  cost  assessment  for  the  medium‐
term horizon, identifying the natural and optimal penetration of RES‐E and its costs and 
benefits  for  Pakistani  society.  These  analyses  allow  us  to  answer  a  range  of  questions 
that  should  be  addressed  before  defining  a  medium‐term  renewable  energy  policy  for 
the  country.  We  will  take  into  account  the  following  responses  to  these  important 
questions in our subsequent policy recommendations to the Government of Pakistan for 
the medium‐term on‐grid RES‐E power policy. 

Is it necessary to perform this type of cost assessment before designing a policy for RE 
incentives? 

The  analysis  presented  in  this  study,  though  a  rough  approximation,  can  provide  an 
overall idea of where the optimal allocation of RES can be found, along with its costs and 
benefits.  The  concept  of  cost‐efficiency  suggests  that  policy‐makers  set  an  objective 
based  on  the  available  scientific  and  technical  data,  and  then  try  to  ensure  that  this 
objective  is  met,  on  least‐cost  terms.  In  doing  so,  regulators  ensure  that  if  efficiency 
cannot be maintained in the strict economic sense, then at least reaching the goal does 
not result in a waste of the society's resources. To perform this type of study we need 
data about costs and potentials for the different RES in Pakistan, but also a large number 
of  input  parameters  that  are  at  the  core  of  much  of  the  academic  debate,  and  other 
information  that  is  rather  difficult  to  assess—for  instance,  the  discount  rate  for  costs 
and benefits, the value of avoided external costs, such as CO2, and the timeline of RES 
installation,  etc.  We  found  that  the  information  required  to  compute  the  cost  and 
potentials for RE in Pakistan is often non‐existent, sometimes puzzling, and, in general, 
spread over a large number of regional and central organizations and therefore difficult 
to access and assimilate. 

We would like to mention that an RES‐E policy can be defined without first conducting 
this  type  of  study.  However,  although  such  a  ‘blind’  policy  may  prove  to  be  just  as 
effective as a policy based on a comprehensive RES‐E supply curve assessment, it would 
most likely be less efficient for society (i.e., it would result in more than the optimal RES‐
E share being installed) or may minimize the consumers’ surplus by allocating it fully to 
the producers (i.e., because the slope of the supply curve is not known). 

This  study,  the  first  of  its  type  for  Pakistan,  is  perceived  to  be  adequate  for  settling 
quantitative  issues  regarding  the  medium‐term  policy  for  deployment of  on‐grid  RES‐E 
generation  in  the  country.  Nevertheless,  we  believe  that  continued  and  more  refined 
analysis should be undertaken by the GoP in this area as part of its future energy sector 
planning and policy‐making process. 

Is a natural penetration of RES‐E still possible in the Pakistani context? 

We  have  observed  that  the  natural  penetration  of  RES‐based  grid  power  in  Pakistan 
should be around 17 TWh in 2020. This is around 7% of total grid‐based electrical power 
generation expected for that year. The fact that any capacity approaching this share is 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  296
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

not currently developed indicates that some strong barriers may exist, especially if we 
consider  that  the  marginal  cost  of  RES‐E  is  around  US$  75/MWh  and  the  cost  of 
generation  based  on  FO  is  more  than  US$  125/MWh.  This  provides  a  very  strong 
economic signal favoring the development of RES‐E, and it can therefore be concluded 
that some impediments, of administrative, regulatory, or financial kind, are responsible 
for the current lackluster RES‐E deployment in the country. 

Almost 60% of this RES‐E share is comprised of hydel plants that are cheaper than CCGT 
running on FO, which in turn defines the price of avoided generation. The other two RES‐
E technologies that should be developed in Pakistan are bagasse‐based CHP and other 
types  of  biomass  conversion.  Definitely,  small‐scale  hydel  is  the  cheapest  option  for 
developing RE in Pakistan and should be encouraged as early as possible. 

What is the optimal RES‐E quota in the medium‐term for Pakistan? 

An  RES‐E  policy  should  be  based  on  a  social  assessment  of  cost  and  benefits.  The 
analysis  of  natural  penetration  based  on  private  costs  alone  does  not  consider 
externalities, and therefore represents a limited subset of such an analysis. 

We  have  observed  in  this  study  that  the  optimal  penetration  of  RES‐based  power 
generation in Pakistan should be around 25 TWh in 2020, which is around 10.4% of total 
on‐grid generation expected for that year. Market failure (i.e., externalities not properly 
being internalized) thus hampers the development of about 8 TWh of renewable energy 
compared to the expected natural penetration of up to 17 TWh in that year. To develop 
that extra 8 TWh, an economic incentive mechanism needs to be put in place, assuming 
that all other barriers that block the development of natural penetration of RES‐E have 
also been removed. 

Under social cost assessment, not only hydel and biomass plants, but also biogas (from 
farm slurries, sewage, landfills, etc.) and wind energy plants are required to generate, in 
order to replace CCGTs running on FO and natural gas—as a matter of fact, all FO‐based 
generation  would  need  to  be  replaced,  as  well  as  around  15%  of  the  gas‐based 
generation, in our simulation for 2020. 

Is there an economic benefit for Pakistani society in developing the optimal quota for 
RE, and if so, how much? 

We  have  identified  a  total  surplus  of  about  US$  2,100  million  per  year  in  2020  in  our 
base  case  for  optimal  RES‐E  quota  deployment.  The  total  surplus  is  a  measure  of  how 
much wealth is being created within the society as consequence of a policy. 

When is the benefit for society maximized?  

The benefit for society is maximized when the optimal quota (i.e., 25 TWh in 2020) for 
RES‐E is met, and is supplied utilizing all RES‐E plants that are cheaper than the cost of 
the marginal plant needed for meeting the optimal quota—in our study US$ 103/MWh 
in the base case. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  297
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

It is important to note that some RES‐E technologies, such as solar PV or solar thermal, 
are not as economically viable as other RES‐E on‐grid solutions given the current state of 
technology.  Therefore,  in  an  optimal  solution,  they  should  not  be  developed.  The 
penetration  of  waste‐to‐energy  is  very  small,  as  it  is  a  very  expensive  technology; 
however, the development of this technology is related to waste management and other 
benefits, and this technology may be developed anyway for these other reasons. 

How robust are our conclusions? 

Regarding  the  optimal  quota  of  RES‐E,  only  changes  in  the  assumed  cost  of  capital 
generate some variations in the results of this study. When the cost of capital decreases 
to 10%, the optimal quota for RES‐E, as expected, increases—from 10.4% up to 14.1%. 

When simulating different conventional supply curves, we observe that only the ‘worst’ 
conventional energy supply case—in which at the same time there is less hydel and gas 
generation  than  in  the  base  case—has  a  relatively  important  effect  on  avoided  cost, 
because part of this generation is replaced by CCGT running on FO. 

Probably, the cost driver that may change the conclusions most is the price of fuel, as it 
has  a  direct  impact  on  the  estimation  of  the  avoided  cost  of  (thermal)  generation. 
Regarding  fuel  cost,  we  have  observed  that  our  conclusions  remain  completely  valid 
even when considering a crude oil price of US$ 40/bbl. In an oil price scenario ranging 
between US$ 40/bbl and US$ 15/bbl, we identify a positive total surplus, but one that is 
completely appropriated by the producers. For an oil price lower than US$ 15/bbl, the 
conclusions of this report cannot be considered valid. 

Finally, it is relevant to mention that due to the high uncertainty in the set of parameters 
required  to  compute  the  supply  curves  (RES  costs,  potentials  by  each  RES,  technology 
advance  in  both  conventional  and  RES,  discount  rates,  environmental  costs,  non‐
environmental  externalities  sin  conventional  energy,  etc.),  we  have  made  many 
assumptions  based  on  our  experience  and  best  available  criteria.  These  assumptions 
have  an  obvious  effect  on  the  conclusions;  however,  we  believe  that  the  conclusions 
presented  in  this  paper  are  the  most  reliable  that  can  be  obtained  based  on  available 
data in Pakistan. 

Are  there  any  arguments  for  abandoning  the  cost‐efficient  approach?  What  are  the 
costs? 

The  main  argument  against  the  cost‐efficient  approach  is  that  it  does  not  foster  the 
development of certain RES‐E technologies—basically those technologies that are more 
expensive  than  the  marginal  cost  of  supplying  the  optimal  quota  of  RES‐E  in  total 
generation (i.e., in Pakistan’s case, US$ 103/MWh). The cost‐efficient approach is a static 
one, but policy makers might not be concerned solely with ‘static efficiency’ which does 
not take into account long‐term prospects and technological innovation. Therefore, they 
may  define  a  policy  decision  outside  the  first‐best  space  of  solutions.  In  Europe,  for 
instance,  it  is  understood  that  any  instrument  to  promote  RES‐E  should  also  lead  to 
'dynamic efficiency', i.e., should give economic agents an incentive to continuously lower 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  298
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

their costs through technological progress. In that sense, single feed‐in tariffs or a quota 
system  that  are  best  for  static  efficiency  are  replaced  with  multiple  feed‐in  tariffs 
designed with technology‐specific tariff rates or hybrid schemes.  

It is important to note that in this case, cheap energy (small‐scale hydel, for instance) is 
replaced for more expensive energy, such as solar PV, solar thermal, or waste‐to‐energy. 
This  makes  the  total  surplus  decrease  from  around  US$  2,100  million  to  US$  1,100 
million in 2020. Within the power sector, this policy thus reduces wealth by about US$ 
1,000  million  per  year  that  it  is  supposed  to  be  created  in  another  area,  for  instance, 
through the development of a local industry for solar PV, etc. The most affected agents 
are the producers of the cheapest technologies (hydel), who stand to lose around US$ 
400 million per year as a result of such a policy. 

Another alternative is to define a policy for installing all medium‐term potential (55 TWh 
of RES‐E generation, about 22% of total power generation in 2020) in order to foster a 
dynamic industry for all types or RES‐E. This is not efficient from an economic point view, 
because  cheaper  conventional  energy  is  replaced  by  RES‐E  technologies  that  are 
extremely expensive. This is evidenced in the change of the total surplus that decreases 
from US$ 2,100 million per year down to about US$ 120 million. As a matter of fact, the 
consumers’  surplus  in  this  case  is  negative,  and  this  is  definitely  not  appropriate  for 
energy customers. 

Multiple‐equilibrium analysis is beyond the scope of this work, but policy makers should 
understand  that  the  wealth  destroyed  by  a  policy  in  one  sector  must  be  sufficiently 
offset by that created in another, in order to get a net overall increase in wealth within 
society.  

What  are  the  differences  amongst  various  incentives  mechanisms  (quota  system, 
single FIT, multiple FITs, etc.) from an economic point of view? 

The simplest incentive mechanism would be to set a single feed‐in tariff—i.e., establish 
only  one  feed‐in  tariff  for  all  RES‐E  technologies—at  the  marginal  cost  of  RES‐E 
generation  calculated  in  the  social  cost  analysis  which,  according  to  our  estimation,  is 
US$  103/MWh.  This  mechanism  should  be  equivalent  to  setting  a  quota  at  10.4%  of 
Pakistan’s total electricity generation in 2020.  However, as was explained in Annex IV, 
the effectiveness of a quota system is worse than that of a feed‐in system, due to the 
complexities in designing the secondary market for green certificates and penalties for 
when the quota is not fulfilled. Tendering procurements are a very good mechanism for 
starting up the market, but are rather difficult to design as an ongoing policy. 

The single feed‐in tariff may generate a high producer surplus and, hence, decrease the 
consumers’  surplus,  given  a  total  surplus.  The  immediate  alternative—multiple  or 
technology‐based  feed‐in  tariffs—tends  to  reduce  the  producers’  surplus,  given  a total 
surplus.  The  extreme  alternative—a  cost‐plus  approach—in  which  the  cost  is  assessed 
on  a  plant‐basis  under  the  hypothesis  of  no  information  asymmetry,  makes  the 
producers’  surplus  tend  towards  zero,  thus  maximizing  the  consumers’  surplus. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  299
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Therefore,  under  static  economic  analysis,  the  issue  of  the  incentive  mechanism  is  a 
matter of wealth distribution and robustness of the incentive. 

The amount of producers’ surplus depends on the slope of the RES‐E supply curve in the 
part that is lower than the conventional supply curve. The higher the slope, the higher 
the  producers’  surplus  is.  That  is  why  it  is  extremely  important  to  have  an  idea  of  the 
RES‐E  supply  curve  before  designing  an  incentive  mechanism  for  RES.  One  example  of 
the  importance  of  the RES‐E  supply  curve’s  slope  can  be observed  when  analyzing  the 
small‐scale  hydel  supply  curve,  which  from  around  the  US$  100/MWh:11  TWh  mark 
becomes  extremely  steep  and,  hence,  the  inframarginal  rents  can  be  huge  for  adding 
even 400 GWh (out of 11 TWh) of generation per year. 

It  should  be  noted  that  small‐scale  hydel  plants  get  the  major  share  of  the  producers’ 
surplus  (around  US$  500  million  in  2020  in  the  base  case),  and  this  extra  revenue  is 
actually an incentive to develop hydel plants. As a matter of fact, the producers’ surplus 
is an incentive for developing all RES technologies. 

The feed‐in tariffs for each technology are generally lower than the simple feed‐in tariff, 
as expected, and hence the producers’ surplus is lower. In effect, the producers’ surplus 
decreases  from  US$  795  million  to  US$  638  million,  but  the  total  surplus  remains  the 
same—US$  2,089  million.  Therefore,  there  is  an  increase  in  the  consumers’  surplus  of 
around US$ 157 million in the base case for multiple FITs. 

Should the producers’ surplus be completely removed? 

The producers’ surplus is a consequence of inframarginal rents. Inframarginal rents can 
be observed in all markets, from the cookies industry to power pools, and represent a 
natural  incentive  for  investors  to  perform  an  activity.  The  removal  of  all  of  the 
producers’  surplus  by  applying  a  cost‐plus  mechanism  will,  on  the  one  hand,  decrease 
the  incentive  to  invest  in  RES‐E  technologies,  and  on  the  other  hand,  make  investors 
game  against  the  cost‐plus  mechanism—a  mechanism  in  which  the  information 
advantage is on the producers’ side. Besides that, the cost‐plus mechanism is usually a 
greater administrative burden and tends to delay the development of RES technologies. 

Which  incentive  mechanisms  represent  the  best  trade‐off  between  effectiveness  and 
fairness? 

In our opinion, multiple feed‐in tariffs provide the optimal trade‐off between allocation 
of surplus and effectiveness. It cannot be a coincidence that in most parts of the world, 
technology‐based  feed‐in  tariffs  are  the  preferred  mechanism  employed.  The 
temptation of the cost‐plus approach seems to be huge when we think in terms of tariffs 
and customer protection, but an RES policy is really a matter of designing incentives that 
are adequate to fulfill the optimal quota of RES‐E in the medium term, and therefore is a 
matter  of  efficiency.  It  is  usually  better  to  get  50%  of  something  rather  than  100%  of 
nothing. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  300
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex VIII:  Working Paper 5: 
Development of On­grid RE in Pakistan: 
Medium Term Policy Recommendations 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  301
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Working Paper No. 5 

Development of On­grid RE in Pakistan: 
Medium Term Policy Recommendations 

Contents 

Exhibits ..................................................................................................................... 305 
Abbreviations and Acronyms .................................................................................... 306 
1  Objective .............................................................................................................. 309 
2  Target Markets ..................................................................................................... 309 
3  Implementation Period ........................................................................................ 310 
4  Targets and Incentives .......................................................................................... 311 
4.1  Selection of Policy Instrument .......................................................................... 311 
4.2  Incentives and Avoided Cost ............................................................................. 313 
4.3  Technology‐wise Feed‐in RE Tariffs ................................................................... 314 
4.3.1  Approach for  ‘Economic’ Technologies ................................................ 314 
4.3.2  Approach for (Currently) ‘Uneconomic’ Technologies .......................... 314 
4.3.3  Structure of Tariffs ................................................................................. 315 
4.3.4  Indexation for Feed‐in Tariffs ................................................................ 315 
4.4  Type of Contract ................................................................................................ 315 
4.5  Allocation of Network Investment Cost ............................................................ 316 
4.6  Direct Sales ........................................................................................................ 316 
4.7  Allocation of Carbon Credits.............................................................................. 316 
4.8  Land and Site Access .......................................................................................... 317 
4.9  Incentives Other Than Tariffs ............................................................................ 317 
5  Pre‐feasibility Studies ........................................................................................... 318 
6  Roles of Institutions ............................................................................................. 319 
6.1  Power Market Development and Transitional Period ...................................... 319 
7  Institutional, Legal and Regulatory Consents ........................................................ 321 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  303
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

8  Procedural Requirements ..................................................................................... 321 
9  Implementation of Tariffs and Quotas .................................................................. 323 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  304
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 

Exhibit 1:  Institutional Roles in RE Development Over the Medium Term ................ 320 
Exhibit 2:  Illustrative RE Feed‐in Tariffs and Quotas .................................................. 324 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  305
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
AJK  Azad Jammu and Kashmir 
BOI  Board of Investment 
BOO  Build, own, and operate 
CDM  Clean Development Mechanism 
CER  Certified Emissions Reduction 
COD  Commercial operations date 
CPPA  Central Power Purchasing Agency 
DISCO  Distribution Company 
EIA  Environmental Impact Assessment 
FBR  Federal Board of Revenue 
FIT  Feed‐in tariff 
GoP  Government of Pakistan 
IA  Implementation Agreement 
IEE  Initial Environmental Examination 
IFI  International financial institution 
IPP  Independent power producer 
KESC  Karachi Electric Supply Corporation 
LMM  Locally manufactured machinery 
LoI  Letter of Intent 
LoS  Letter of Support 
MoWP  Ministry of Water and Power 
MW  Megawatt 
MWh  Megawatt‐hour 
NEPRA  National Electric Power Regulatory Authority 
NTDC  National Transmission and Dispatch Company 
Pak EPA  Pakistan Environment Protection Agency 
PC  Project Committee 
PCRET  Pakistan Council for Renewable Energy Technologies 
POE  Panel of Experts 
PPA  Power Purchase Agreement 
PSDP  Public Sector Development Programme 
PV  Photovoltaic 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  306
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

R&D  Research and development 
RE  Renewable energy 
RED   Renewable Energy Development 
RES  Renewable energy source 
RES‐E  Renewable energy sourced‐electricity 
RET  Renewable energy technology 
RoW  Right‐of‐way 
TRANSCO  Transmission company 
TWh  Terawatt‐hour 
WAPDA  Water and Power Development Authority 
WTE  Waste‐to‐energy 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  307
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Development of On­grid RE in Pakistan: 
Medium Term Policy Recommendations 

1 Objective 
This  Annex  presents  the  consultants’  draft  proposal  for  the  design  of  a  medium  term 
policy  for  the  development  of  on‐grid  renewable  energy  sourced  electricity  (RES‐E)  in 
Pakistan.    This  proposal  takes  into  account  the  analysis  presented  in  the  preceding 
Annexes:  i.e.,  best  international  practice  and  renewable  energy  (RE)  policy  experience 
(Annex IV), a diagnosis of Pakistan’s current short term on‐grid RE policy (Annex V), and 
a comprehensive economic and comparative assessment of conventional and RE sources 
and supply options in the Pakistani context (Annexes VI and VII). 
This document presents general guidelines for formulating a detailed medium term RE 
policy  framework  for  Pakistan.  Once  the  broad  outline  of  the  policy  approach,  and  its 
underlying  rationale,  have  been  agreed  upon  by  relevant  stakeholders,  detailed 
implementation  measures  for  each  RE  technology  will  be  provided,  constituting  a 
comprehensive medium term RE policy framework (for the period 2008 to 2012) for the 
systematic implementation of RE technologies and scaling up of capacity deployment in 
Pakistan, including the use of off‐grid and non‐power RE resources.   
The  proposal  presented  in  this  paper  focuses  on  on‐grid  renewable  energy.  The 
geographical demarcation of off‐grid regions and the design of the legal and regulatory 
framework  for  off‐grid  and  distributed  generation  will  be  analyzed  in  a  subsequent 
annex (Annex IX). 

2 Target Markets 
‘On‐grid’  RE  means  grid‐connected1  power  generation  fueled  by  renewable  resources 
(either  to  transmission  or  distribution  systems),  selling  power  to  the  Central  Power 
Purchasing Agency (CPPA), to electricity distribution companies (DISCOs), or directly to 
bulk consumers, utilizing national or regional grids for transmission. 
For  purposes  of  RE  policy  definition,  ‘on‐grid  RE’  includes  the  following  renewable 
energy technologies (RETs), for individual project installed capacity higher than 1 MW:2 
• Small hydro of 50 MW or less capacity 
• Solar photovoltaic (PV) and solar thermal energy for power generation 
                                                       
1
  For the purposes of RE policy terminology, the term ‘grid’ is meant to imply either national or regional electricity 
T&D networks operated by the NTDC/CPPA and/or DISCOs of 11 kV or higher voltage.  Isolated, community‐based 
local distribution networks are considered ‘off‐grid’. 
2
  Installations of less than 1 MW capacity will be assessed as part of the off‐grid policy guidelines, as they require a 
simplified approach (i.e., delicensing). 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  309
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• On‐shore wind power generation 
• Municipal solid waste‐to‐energy (WTE) power and landfill methane recovery, and 
• Bio‐energy resulting from: 
o Anaerobic biogas digesters 
o Pyrolytic biomass gasification, co‐firing, or cogeneration. 
Other potential or incipient RE power generation technologies, such as those based on 
wave,  tidal,  off‐shore  wind,  geothermal  energy,  and  fuel  cells—which  could  eventually 
be  relevant  to  future  renewable  energy  use  in  Pakistan—are  not  included  in  the 
mandate of the medium term RE policy regime.  The medium term policy thus focuses, 
as per the RE development roadmap adopted by the GoP, on the optimal deployment of 
currently  mature  and  commercially  feasible  RETs,  with  emerging  technologies  to  be 
assessed subsequently as they move beyond the R&D and pilot implementation stages. 

3 Implementation Period 
Although  in  the  current  short  term  Policy  for  Development  of  Renewable  Energy  for 
Power Generation, 2006, the medium term policy to be developed was envisaged to be 
implemented for a four‐year period, we recognize that incentive‐based policies require 
at least five years of sustained promotion in order to be successful.  
The analysis of the outcome of the short term on‐grid RE policy (December 2006 to date) 
demonstrated that, amongst other issues, such a short period was insufficient in terms 
of  expectations  with  regard  to  its  implementation  goals.  Furthermore,  if  the  policy 
regime is slated to change after only two years of application, the additional effort that 
investors  require  to  understand  the  incentive  mechanism  increases,  investment 
decisions  get  deferred  in  the  hope  of  procuring  additional  incentives  later,  and  thus 
actual capacity deployment may be jeopardized. The consultants’ opinion is that policy 
incentives must remain stable and assured over a reasonably extended period in order 
for investment confidence to build up, supportive institutional capacity to develop, and 
implementation bottlenecks to be gradually and systematically removed. 
Therefore it is suggested that the implementation period of the current short term on‐
grid  policy  be  extended  to  at  least  the  end  of  2008,  and  that  of  the  medium  term  RE 
policy to apply from January 2009 to December 2013 (inclusive).  
After  the  five‐year  medium  term  period,  a  new  RE  deployment  phase  will  begin,  in 
which: 
• Technologies  that  have  not  been  included  in  the  earlier  policy  phases  but  may 
have matured sufficiently in the interim may also be provided specific incentives. 
• The  type  of  incentive  mechanisms  selected  for  the  medium  term  may  be 
changed  in  light  of  experience  gained  as  well  as  given  the  growth  and 
sophistication achieved by the local RE industry. 
• Specific incentive tools and instruments may be retained from the medium term 
phase, but the corresponding values or targets may be revised. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  310
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

An  important  aspect  regarding  various  successive  policy  periods  is  that  of  assuring 
continuity  for  projects  that  have  been  implemented  under  a  certain  policy,  i.e.,  they 
should  not  be  subject  to  any  change  in  the  incentives  they  initially  receive  over  the 
applicable  project  tenure  (usually  the  project’s  operational  lifetime),  even  in  the  case 
that  the  relevant  policy  or  the  incentives  change  in  the  meantime.  This  approach 
ensures the consistency and stability of an RE deployment climate from the perspective 
of  both  investors  and  power  purchasers,  as  well  as  other  relevant  stakeholders 
(financiers,  carbon  creditors,  service  providers,  end  users,  etc.);  this  is  considered 
especially  critical  for  the  long‐term  implementation  of  RE  in  Pakistan  as  a  conducive 
environment for RE development has yet to gain broad acceptance and attract business 
confidence. 
Consequently,  the  consultants  support  the  GoP’s  undertaking  that  any  RE  project  that 
achieves financial closure before the onset of the next policy phase (i.e., January 2009) 
continues  to  be  guaranteed  all  the  incentives  defined  in  the  applicable  short  term  RE 
policy over the tenure of its Power Purchase Agreement (PPA).  

4 Targets and Incentives 
4.1 Selection of Policy Instrument 
When designing an RE policy, some characteristics of RES‐E technologies should be taken 
into  account  in  order  to  properly incorporate the  complexities  that  these  technologies 
add  to  the  analysis.  Even  though  most  of  these  characteristics  have  already  been 
presented in previous Annexes (particularly Annex VII), some of the key features can be 
summarized as follows: 
• Smaller  plant  sizes  (1  to  50  MW),  compared  to  typical  conventional  generation 
options 
• Large variation in investment costs (per MW installed) 
• Heterogeneous technology options for the same renewable source 
• Non‐existence of suitable commodity markets for bio‐energy fuel inputs. 
The  existence  of  these  differences  amongst  various  RES‐E  technologies  increases  the 
asymmetries  in  information  availability  as  well  as  the  complexities  of  tariff 
methodologies based on a ’cost‐plus‘ approach—therefore, simpler approaches must be 
preferred.  In  this  regard,  our  main  recommendation  is  for  Pakistan  to  discontinue  the 
present system of negotiated power purchase tariffs and instead implement, as soon as 
possible,  a  traditional  feed‐in  (or  up‐front)  tariff  for  grid‐connected RE generators.  We 
have  already  thoroughly  analyzed,  in  Annexes  IV  and  VII,  the  main  advantages  and 
drawbacks of each alternative mechanism—including their effect on the corresponding 
social surplus and the distribution of that surplus between consumers and producers—
and therefore only a brief recapitulation is provided below. 
As  discussed  in  Annex  V,  the  current  tariff  system  for  unsolicited  RE  proposals  in 
Pakistan  is  based  on  a  ‘cost‐plus’  approach.  The  cost‐plus  formulation  requires  a case‐

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  311
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

by‐case  determination  of  the  applicable  tariff  for  every  single  producer.3  From  a 
regulator’s  point  of  view,  the  advantage  of  this  methodology  is  the  ability  to  reduce 
infra‐marginal  rents  down  to  zero  and,  therefore,  maximize  the  consumer’s  surplus. 
Nevertheless,  this  approach  presents  several  major  shortcomings,  which  can  be 
summarized as follows: 
• Investors,  taking  advantage  of  asymmetries  in  information  access  (as  only  the 
developer  has  intimate  knowledge  of  a  particular  project’s  costs  and 
peculiarities), can game against the mechanism to obtain infra‐marginal rents. 
• It decreases the financial incentive to invest in RES‐E technologies, as developers 
are deprived of most of the infra‐marginal rents.    
• It increases in the administrative burden in processing projects, and increases the 
possibility of unavoidable systematic delays. 
Therefore,  applying  a  cost‐plus  methodology  for  tariff  estimation  ensures  neither  the 
maximization of the social surplus, nor the effective deployment of RES‐E technologies.  
An  alternative  approach  is  to  develop  a  quota  system,  either  by  defining  a  ‘green 
certificate’ market or through tendering procurement. As was explained in Annex IV, the 
effectiveness  of  the  quota  system  is  worse  than  the  feed‐in  system  because  of  the 
complexities in designing the secondary market for green certificates and the applicable 
penalties  for  when  the  quota  is  not  fulfilled.  Tendering  procurements  are  a  very  good 
mechanism  for  starting  up  the  market,  which  may  be  necessary  for  some  RE 
technologies  in  Pakistan  but  rather  difficult  to design  as  an  ongoing  policy  instrument.  
Furthermore, the main shortfall of this methodology is its crucial assumption of a large 
number  of  participants,  so  that  participants  are  not  afforded  credible  collusion 
opportunities. If this assumption does not hold, and participants are able to collude to 
drive up prices, then the outcome of the auction process will probably be far removed 
from that of a competitive outcome, and could well minimize consumer surplus. 
Feed‐in  tariffs  (FITs)  have  been  (and  still  are)  very  successful  in  Europe  for  promoting 
RES‐E  deployment,  and  represent  the  standard  option  for  ensuring  renewable 
penetration. The main advantages of FITs can be summarized as follows:  
• Simplicity  in  design:  The  FIT  design  process  implies  a  technology‐based  analysis 
of costs, rather than one requiring case‐by‐case analysis. 
• Technology‐specific:  FIT  may  be  designed  equal  for  all  RE  technologies,  or  they 
may  vary  amongst  different  RETs  if  the  government  decides  to  encourage  the 
development of a specific technology. 
• Transparent  and  foreseeable:  With  the  tariff  defined  up  front,  any  investor  is 
easily  able  to  estimate  potential  project  revenues  unambiguously,  and  thus 
decide to invest or obtain financing on a secure basis.    
• Cost‐effective: If the feed‐in tariff is set below the relevant avoided social cost, it 
would represent a cost‐effective option for the society as a whole. 
                                                       
3
  Although up‐front tariffs have been defined for wind power projects in Pakistan, no developer has committed to (or 
has planned on) utilizing these tariffs so far.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  312
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Nevertheless, FITs have some drawbacks due to nature of the system:  
• Even  if  well  designed,  FITs  will  most  probably not  result  in  the  maximization  of 
the consumers’ surplus, and  
• FIT  does  not  necessarily  foster  the  development  of  certain  technologies  (e.g., 
does not encourage use of more costly options that could benefit from eventual 
economies of large scale deployment, but instead favors readily available least‐
cost  RETs),  and  therefore  does  not  cater  to  long‐term  prospects  and 
technological innovation. 
It  must  be  understood,  however,  that  neither  the  first  nor  the  second  potential 
shortcoming of FITs is necessarily disadvantageous from an economic point of view, as 
these are not concerned solely with economic efficiency: the first one relates primarily 
to wealth distribution, while the second is more about long‐term industrial policy. 

4.2 Incentives and Avoided Cost 
One of the most basic principles in energy economics relates to the concept of avoided 
costs: the cost a utility would incur in generating the next increment of electric capacity 
using  its  own  resources.  According  to  this  definition,  any  policy  fostering  the 
development of the cheapest available technology will increase the consumer’s surplus 
when  compared  to  the  most  expensive  technologies.  As  was  presented  in  Annex  VII, 
even considering only private costs, nearly 20 TWh per year of renewable energy were 
ready  to  displace  more  expensive  conventional  technology  (i.e.,  fuel  oil‐based  thermal 
generation) in Pakistan, with associated savings larger than US$ 1 billion per year. This 
scale of RE deployment can be achieved by simply providing incentives to RES‐E through 
a single FIT of about US$ 75/MWh.4 
Therefore,  as  there  is  no  RE  power  market  in  Pakistan  yet,  incentives  for  the 
development  of  RES‐E—even  if  they  generate  some  producers’  surplus—should  be 
provided, at least when the renewable option is clearly cheaper than the avoided private 
cost, since this option would ultimately save the consumers money. Moreover, from an 
economic point of view, incentives should ideally be linked to the avoided social cost—
that is, approximately US$ 103/MWh, if we assume a single RE FIT for Pakistan. 
It needs to be recognized that tariffs and incentives are not exactly the same concept. A 
tariff is the regulated price of a service that, in theory, should be related to the marginal 
cost of providing it; on the other hand, an incentive is not related to the marginal cost—
as a matter of fact, it may be higher to the extent that it remains less than the avoided 
cost in social terms.  
The  consultants’  recommendation  for  determining  the  RE‐based  power  procurement 
prices for the medium term policy regime in Pakistan is:  
• To set feed‐in tariffs for each technology based on the ‘avoided cost’ approach 
for those technologies whose marginal cost is lower than the avoided social cost. 

                                                       
4
  Under  a  cost‐plus  regime,  conventional  fuel  oil‐based  power  generation  would  have  set  the  tariff  at  almost 
US$ 130/MWh, nearly doubling the incentive for RES‐E. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  313
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• To set feed‐in tariff for each technology based on the marginal cost of providing 
the  quota  set  by  the  GoP  for  those  technologies  whose  marginal  cost  is  higher 
than avoided social cost. 

4.3 Technology­wise Feed­in RE Tariffs 

4.3.1 Approach for  ‘Economic’ Technologies 
We  consider  as  ‘economic’  those  technologies  whose  development  costs  are  less  than 
their corresponding avoided social costs.  
For these technologies, the consultants’ recommendation is to set technology‐wise feed‐
in tariffs based on the characteristics of the RES‐E technologies (‘supply curve analysis’),  
bounded  by  the  range  obtained  from  the  use  of  private  and  social  aggregated  supply 
curves  for  conventional  and  RES  power  generation.  That  means  that  the  RE  tariff 
approved  should  lie  within  the  range  delimited  by  private  and  social  avoided  costs, 
respectively.  
• “…bounded  by  the  range  obtained  from  the  use  of  private  and  social 
aggregated supply curves for conventional and RES power generation”: Optimal 
penetration  of  renewable  resources  implies  that  the  incentives  (FIT)  should  be 
set  at  a  level  where  the  avoided  cost  of  conventional  power  generation  equals 
the marginal cost of the most expensive RES‐E plant. However, it is a matter of 
policy  whether  the  relevant  cost  curves  of  conventional  and  RES  power 
generation taken for this purpose are those relating to private or social costs. The 
use  of  private  or  social  cost  curves  will  define  a  range—respectively,  the 
minimum  and  the  maximum  incentives  for  optimal  RES‐E  penetration—within 
which the feed‐in tariffs should be set.  
• “…technology‐wise  feed‐in  tariffs  based  on  the  characteristics  of  RES‐E 
technologies”: the most fundamental problem with a single FIT is the fact that it 
relies  only  on  the  aggregated  RES‐E  cost  curve,  without  take  into  consideration 
the  slopes  of  each  single  RES‐E  technology  supply  curve.  The  impact  of  a  small 
increase in the incentive for one technology may be very large if the elasticity of 
the supply curve is high (a flat supply curve) or very small if the elasticity is low (a 
steep supply curve).5 Therefore, setting individually differentiated incentives for 
each  RES‐E  technology  based  on  an  analysis  of  their  respective  supply  curves, 
bounded  by  the  aforementioned  range,  is  preferable  compared  to  setting  a 
single uniform incentive for all technologies. 

4.3.2 Approach for (Currently) ‘Uneconomic’ Technologies  
In addition to these incentives, a FIT may be proposed to foster the deployment of any 
specific  RES‐E  technology  that  promises  additional  benefits  to  society  that  are  not 
explicitly included in the social supply curve of that technology. Such benefits may arise 
from: 

                                                       
5
  Technical  criteria  may  be  defined  if,  for  instance,  NEPRA  considers  it  necessary,  to  define  the  feed‐in  tariff 
considering the curve’s elasticity, i.e., set the feed‐in when the curve elasticity is 1 or less. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  314
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Reduction of specific local pollutants 
• Local or regional development priorities 
• Selection  of  RETs  which  the  GoP  considers  important  from  an  industrial 
development policy point of view, and 
• Employment promotion, etc. 
The  existence  of  these  FITs  higher  than  the  corresponding  avoided  social  costs  is 
recommended  for  such  cases  in  which  the  cost  of  the  RET  prevents  the  proper 
development  of  a  specific  technology–e.g.,  solar  thermal  and  solar  PV,  as  described  in 
Annex VII.  As these technologies are currently ‘expensive’, a good policy should prevent 
a  reasonable,  justifiable  target  quota  for  them  (defined  in  installed  MW  for  a  given 
period) from being overshot. This quota is a policy matter, and should be defined by the 
government.  The  FIT  for  these  technologies  should  be  capped  consistently  with  the 
quota that the GoP defines by employing a supply curve approach.      

4.3.3 Structure of Tariffs 
Feed‐in tariffs should be denominated in Pakistan Rs/kWh. The feed‐in tariffs should be 
based on one‐part pricing approach (i.e., single energy charge). Two‐part tariffs (capacity 
payments + energy payments) are difficult for most RES‐E technologies, as most of them 
cannot  guarantee  capacity  availability–even  in  the  case  of  biomass‐based  generation, 
which  may  be  constrained  by  seasonal  harvests.  Despite  the  fact  that  some  types  of 
hydel plants may be in a position of providing firm capacity commitments to the system, 
for the sake of simplicity we recommend the use only an energy charge.6 

4.3.4 Indexation for Feed­in Tariffs 
Feed‐in  tariffs  should  be  adjusted  based  only  on  local  currency  variations.    The 
indexation of the feed‐in tariffs with the US dollar exchange rate should be automatic on 
a  six‐monthly  basis.  Another  possibility  (to  be  discussed)  is  to  use  as  a  reference  a 
currency basket with US Dollar and Euro (i.e., 50:50). 
Adjustments  in  the  tariff  for  variation  in  other  parameters,  as  it  is  currently  the  case, 
may excessively complicate the adjustment methodologies without a clear benefit.   

4.4 Type of Contract 
The  RES‐E  projects  should  be  implemented  on  the  basis  of  ‘Build,  Own,  and  Operate’ 
(BOO).  

                                                       
6
  This approach means that the primary energy risk (i.e., wind speed or water inflow variability, volumes or prices of 
biomass, etc.) should be allocated to the developer. The consultants are aware that this approach will increase the 
risks  afforded  by  these  developers,  but  they  take  into  consideration  that:  (i)  The  developers  will  be  in  a  better 
position  to  handle  this  risk;  (ii)  It  will  promote  optimum  project  design,  avoiding  the  possible  over‐investment  in 
capacity, and (iii) the ranges proposed for the tariffs (if set using the proposed methodology) are attractive enough 
for the developers, even if they have to assume the above‐mentioned risk.    

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  315
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.5 Allocation of Network Investment Cost  
It is proposed that the construction of transmission lines for evacuation of power from 
any RE IPP should be the responsibility of the NTDC, KESC or a DISCO (depending on the 
location and supply voltage of the project) if the length of the connection required from 
the project’s outgoing bus bar to existing grid installations is shorter than 20 km, unless 
the IPP, of its own choice, undertakes to install such infrastructure on a mutually agreed 
upon transmission charge with the NTDC. 
The NTDC should bear any of the expenses associated with power balancing on the grid 
to  accommodate  priority  dispatch  and  variability  on  account  of  the  RE  project,  and 
ensure that these expenditures are made in a timely fashion.

4.6 Direct Sales 
RE  power  producers  should  be  allowed  to  enter  into  direct  (bilateral)  sales  contracts 
with  eligible  end‐use  customers.    In  that  case,  prices  should  not  require  approval  by 
NEPRA, but customers should be required to pay ‘wheeling’ charges for the use of the 
transmission  and/or  distribution  grid  network  used  to  transport  the  power  from  the 
plant to the purchaser. 

4.7 Allocation of Carbon Credits  
We consider that the current allocation of carbon credit revenues between RE investors 
(IPPs)  and  the  power  purchasers  (state  entity)  is  unnecessarily  complicated  and  a 
potential  impediment,  rather  than  an  incentive,  for  RE  projects  to  apply  for  CDM 
certification.    This  mechanism  was  perhaps  necessary  under  the  prevailing  cost‐plus 
tariff determination methodology, under which the RE IPP is already guaranteed a fair 
return  on  investment,  and  the  additional  cost  of  RE  power  purchase  is  shifted  to  the 
power  purchaser  and  eventual  ratepayer.    With  fixed  feed‐in  tariffs,  such  a  situation 
would  no  longer  hold,  and  the  RE  IPP  would  have  to  assume  a  greater  portion  of  the 
financial and project risks involved. 
In this respect, it would be both logical as well as administratively simpler for the project 
to also assume the risks and benefits of qualifying for and obtaining CERs, along with the 
potential  revenues  associated  with  them.    This  would  provide  several  important 
advantages over the prevailing methodology for RE carbon credit sharing in Pakistan: 
• The allocation of future CER revenues entirely to the RE developer would act as a 
much  stronger  additional  financial  incentive  for  developing  RE‐based  power 
generation projects (compared to sharing a part of the proceeds), most of which 
would  be  strong  candidates  under  CDM’s  ‘additionality’  clause  given  Pakistan’s 
low‐RE baseline. 
• The  onus  of  applying  for,  validating,  obtaining,  and  undertaking  periodic 
verification as required under the CDM procedures would rest entirely with the 
RE  developer,  who  would  be  better  placed  to  undertake  such  tasks  either 
internally  or  through  contracted  expertise,  and  would  absolve  government 
entitites  (e.g.,  the  AEDB,  NEPRA,  NTDC,  etc.)  to  engage  in  such  cumbersome 
activities  for  which  they  do  not  have  sufficient  administrative  or  management 
capacity. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  316
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• The allocation of CERs to the developers is also consistent with the current CDM 
practice  (in  terms  of  contributing  to  financial  barrier  removal)  and  would 
improve the prospects of a greater number of potential RE projects in Pakistan 
qualifying  for  emissions  certification,  as  compared  to  the  current  CER‐sharing 
mechanism which has yet to be validated by the CDM. 
Our  recommendation  is  therefore  that  the  GoP  should  restrict  its  role  in  the  carbon 
credits market to one of assisting individual developers in obtaining the necessary CDM 
certification.    It  should  assist,  through  expedited  DNA  endorsement,  provision  of  part 
financing  for  application  and  validation  requirements,  establishment  and  sharing  of 
relevant emissions inventories, methodologies, and baseline data, and relevant training 
and awareness building designed to facilitate project application for, verification of, and 
subsequent marketing of carbon credits to the extent possible.  

4.8 Land and Site Access 
The federal, provincial, and AJK governments shall facilitate investors in acquiring land 
or  right‐of‐way  (RoW)  for  project  development,  as  well  as  providing  site  access  on  a 
case‐to‐case basis by leasing, acquisition of RoW, and/or construction of road linkages. 
However, the primary responsibility for acquiring land and site access should rest with 
the project sponsors. 

4.9 Incentives Other Than Tariffs 
The  consultants  believe  that  the  current  general  incentives,  as  defined  in  the  2006  RE 
policy,  are  adequate  and  should  be  continued  into  the  medium  term  stage  as  well.  In 
summary, the key general incentives are: 
Sovereign risk guarantee, including: 
• Guarantees to the contractual obligations of GoP entities, including NTDC (CPPA), 
WAPDA, KESC, DISCOs and provincial/AJK governments, even though some or all 
of  the  utilities  may  by  restructured  or  privatized  during  the  term  of  various 
agreements with RE developers. 
• Protection against specific ‘political’ risks. 
• Protection against changes in the taxes and duties regime. 
• Convertibility of Pakistani Rupees into US Dollars at the prevailing exchange rate 
and the remittability of foreign exchange to cover necessary payments related to 
the project, including debt servicing and payment of dividends.  
Financial regime, including:  
• Permission for power generation companies to issue corporate registered bonds 
and to issue shares at discounted prices. 
• Permission  for  foreign  banks  to  underwrite  the  issue  of  shares  and  bonds  by 
private RE power companies. 
• Non‐residents  allowed  to  purchase  securities  issued  by  Pakistani  companies 
without the State Bank of Pakistan’s permission. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  317
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Abolition of 5% limit on investment of equity in associated undertakings. 
• Locally  manufactured  equipment,  components,  and  machinery  required  for  RE 
projects shall be eligible for financing under the State Bank of Pakistan’s Scheme 
for Financing Locally Manufactured Machinery (LMM). 
• Special  financing  arrangements  specifically  aimed  at  facilitating  investments, 
technology  transfer,  and  local  manufacturing  capacity  in  targeted  renewable 
energy technologies and projects, i.e., a revolving line of credit under the Public 
Sector  Development  Programme  (PSDP)  or  a  Renewable  Energy  Development 
(RED) Fund with multilateral co‐financing. 
Fiscal regime, including:
• No customs duty or sales tax on the import of RE plant and equipment. 
• No levy of sales tax on plants, machinery and equipment. 
• Exemption is already available from income tax, including turnover rate tax and 
withholding tax on imports. 
• Repatriation  of  equity,  along  with  dividends,  is  freely  allowed,  subject  to  the 
prescribed rules and regulations. 
• Parties  may  raise  local  and  foreign  finance  in  accordance  with  regulations 
applicable to industry in general. 
• Non‐Muslims  and  non‐residents  shall  be  exempted  from  payment  of  Zakat  on 
dividends paid by the company. 
In  addition  to  the  above,  facilities  made  available  specifically  to  grid‐connected  RE 
power projects (small‐scale stande‐alone, captive, and spillover generators) in the 2006 
RE policy—i.e., net purchase and sales, net metering, wheeling, and banking—should be 
continued  into  the  medium  term.    In  fact,  these  facilities  need  to  be  properly 
operationalized  through  revision  of  relevant  regulations,  determination  of  applicable 
tariffs,  definition  of  accounting  modalities,  and  provision  of  necessary  metering 
hardware  and  interconnection  arrangements.    Pilot  scale  demonstration  of  such 
mechanisms  would  greatly  help  in  creating  public  awareness  and  devising  effective 
methods  for  implementing  such  useful  and  innovative  ways  of  promoting  widespread 
and  dispersed  RE  deployment (especially  for  rooftop  PV,  biogas‐based  generators,  and 
micro wind turbines). 

5 Pre­feasibility Studies 
Pre‐feasibility  studies  are  critical  for  the  development  of  some  RE  resources  (mostly 
hydel and some biogas projects) and for relatively immature or new technologies.  The 
cost and complexity of undertaking such studies is a major barrier for the private sector 
seeking  to  develop  RE  projects  in  Pakistan.  In  our  view,  the  AEDB  and  provincial 
administrations  must  undertake  the  lead  responsibility  of  developing  these  pre‐
feasibility  studies,  either  through  GoP  and/or  IFI  financing  (grants  and/or  soft  loans). 
Once a pre‐feasibility study has been properly completed, the main features of the RE 
project  should  be  made  public  (through  websites,  newspaper  advertisement,  and 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  318
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

specially organized workshops) for investor to be made aware of project features and to 
be  able  to  independently  analyze  it.  The  pre‐feasibility  studies  may  be  developed  by 
internal  agency  staff  and  budgets  or  by  hiring  external  experts  and  consulting  firms 
through competitive evaluation. In any case, the quality of the studies must ensure that 
potential investors can feel comfortable with them.  Multilateral technical assistance in 
training  and  standardizing  such  RE  IPP  feasibility  assessments  can  play  a  role  in  this 
regard. 

6 Roles of Institutions 
In  the  medium  term  RE  policy  tenure,  we  do  not  recommend  major  changes  in  the 
different  roles  that  each  stakeholder  institution  has  in  facilitating  renewable  energy 
development and project implementation in Pakistan. However, we consider that some 
slight changes (highlighted in bold in Exhibit 1) may improve the effectiveness of the RE 
development  efforts  and  help  expedite  investments.  In  the  following  table,  the  main 
roles of the involved institutions are presented. 
In  particular,  we  emphasis  the  urgent  need  for  technical  and  managerial  capacity 
building with respect to renewable energy project evaluation and implementation at the 
lead RE development agencies: the AEDB in the federal government and provincial/AJK 
departments  dealing  with  RE  IPPs,  as  well  as  in  supporting  agencies  such  as  NEPRA, 
NTDC/CPPA, the DISCOs, the CDM cell in the Ministry of Environment, as well as private 
sector investors and financing institutions. 

6.1 Power Market Development and Transitional Period 
The ongoing development and deregulation of the power market in Pakistan should not 
represent a barrier for the proper deployment of RE power generation in the country.  
From the moment this policy is implemented and until the CPPA ceases its activities as 
the  central  power  purchase  agency,  all  contracts  for  power  generation  from  RES 
concluded under the current RE policy should be signed by the CPPA—excepting those 
bracketed as ‘direct sales’. 
After the CPPA ceases its activities: 
• Neither distributors nor transmission companies should have the right to reject, 
in part or in entirety, any contract signed between the CPPA and a RES‐E power 
generator; and 
• All  new  contracts  signed  between  RES‐E  generators  and  a  distribution  or  a 
transmission  company  shall  never  be  deemed  as  ‘direct  sales’,  and  therefore 
NEPRA shall always approve the tariff for these contracts. 
In  addition,  RES‐E  producers  should  be  allowed  to  sign  sales  contracts  with 
DISCOs/TRANSCOs under non‐discriminatory conditions. Sales contracts must not be an 
instrument to hamper the proper development of renewable energy power generation. 
NEPRA  should  establish  a  future  methodology  for  compensating  those 
DISCOs/TRANSCOs  that  are  forced  to  accept  contracts  with  a  feed‐in  tariff  under  the 
renewable policy. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  319
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 1: Institutional Roles in RE Development over the Medium Term 
Institution Main Role in RE Development

Ministry of Water • Coordinate development of conventional and RE energy sources


and Power • Formulate development policies jointly with Planning Commission
• Issue implementation agreement and security packages with
Ministry of Finance
• Set penetration quota for uneconomic RE technologies

Ministry of Finance • Evaluate impact of proposed policy on the economy as a whole.


(through BOI and FBR) • Approve development policies jointly with MoWP
• Issue implementation agreements and security packages jointly
with MoWP

AEDB • Frame and propose appropriate policies and plans to the GoP
• Develop demonstration programs and projects for off-grid RE
• Promote local manufacturing
• Create awareness and facilitate technology transfer
• Channel international assistance
• One-window facility for processing IPP projects under RE policy
• Develop standard PPAs for each RET
• Develop pre-feasibility studies for RE projects in
coordination with provincial and AJK agencies

NEPRA • Define feed-in tariffs according to the conceptual


approaches provided in these policy recommendations
promptly (within four months)
• Approve the application of pre-defined feed-in tariff to a
specific RE project
• Adjust grid and distribution codes in order not to block the
development of RE IPPs
• Issue licenses for RE power generation projects

WAPDA or CPPA • Sign PPA under consent of AEDB


(as purchasing entity) • Procure all power produced by approved on-grid RE generation
plants during the term of the PPAs and up to cap provided in policy

Power Utilities • Connect RE projects to grid if they comply with requirements of


(NTDC, KESC, & network codes
DISCOs as networks
operators)
PCRET • Foster R&D and technology development relevant to renewable
energy in coordination with the AEDB

Provincial and AJK • Support the implementation of renewable energy projects in close
Agencies coordination with the AEDB
• Facilitate allocation of land use, water rights, and environmental
permitting
• Create awareness of RE amongst end users and customers
• Remove any other local impediments which may hinder RE
development in a province
• Develop pre-feasibility studies for RE projects in
coordination with AEDB
• Harmonize province RE regulations with national
framework

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  320
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

7 Institutional, Legal and Regulatory Consents 
The  institutional,  legal,  and  regulatory  consents  required  prior  to  approval  and 
implementation of RE IPP projects in Pakistan are summarized below: 
AEDB consents: 
• Letter  of  Intent  (LoI),  followed  by  a  Letter  of  Support  (LoS)  and  related 
guarantees 
• Information memorandum for each project, including all technical features of the 
project. 
NEPRA consents: 
• Generation License to construct, own or operate an RE power generation facility 
• Special Purpose Transmission or Distribution License, if necessary  
• Feed‐in tariff approval for the RE IPP 
• Second‐tier  Supply  Authorization  if  the  project  enters  into  a  power  sale 
arrangement with a bulk purchaser. 
Pak EPA consents: 
• Initial  Environmental  Examination  (IEE)  for  hydroelectric  and  waste‐to‐energy 
power generation projects of 50 MW or less capacity. 
• IEE/EIA review fee payment. 
NTDC/KESC/DISCOS consents: 
• Any  RE  installation  must  comply  with  the  technical  requirements  of  the 
(Transmission/Distribution) Grid Code, depending on the voltage level at which it 
is connected to the utility infrastructure. 

8 Procedural Requirements 
Broadly  speaking,  the  processing  schedule  foreseen  in  the  2006  RE  Policy  (which  is 
conceptually  similar  to  that  provided  in  PPIB’s  2002  power  policy)  is  adequate  in  the 
consultants’ opinion. However, it must be adjusted to the tariff regime that is proposed 
under the medium term RE policy, and should be reduced in overall duration. 
A typical revised processing schedule for project proposals for an on‐grid RE IPP project 
should consist of the following steps: 
Submission  of  Proposals:  Proposals  for  renewable  energy  IPP  projects,  either  on  ‘raw’ 
sites  or  on  sites  for  which  the  AEDB  or  provincial  administration  has  carried  out  pre‐
feasibility  studies,  may  be  submitted  to  the  AEDB  or  designated  provincial/AJK 
counterpart agency. Any sponsor wishing to undertake a project should have to submit a 
detailed  information  memorandum  to  the  AEDB/counterpart  agency  (CA),  which  must 
include the following information at a minimum: 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  321
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Project  name  and  RET  classification  (i.e.,  wind,  solar,  small  hydro,  biomass, 
hybrid, etc.) 
• Project location 
• Proposed net installed capacity (MW) and expected annual energy output (MWh) 
• Basic outline of plant and structures 
• Summary  implementation  plan,  indicating  specific  project  preparation 
milestones and expected COD 
• Previous history of the project if any, and 
• Description of technology and main suppliers, etc. 
These  proposals  shall  be  examined  by  a  Project  Committee  (PC)  headed  by  the 
Chairman,  AEDB  and  including  representatives  of  the  CA  from  the  province/state  in 
which  the  project  is  located.  Proposals  approved  by  the  PC  shall  be  processed  by  the 
AEDB  for  issuance  of  LoI.  The  time  for  reviewing  the  proposal  should  not  exceed  45 
working days from the date of submittal. 
LoI  issuance:  The  LoI  shall  require  sponsors  to  carry  out  a  complete  project  feasibility 
study in a period no longer than that predefined for each technology (depending also on 
whether a pre‐feasibility study exists as well as the size of the project). The sponsors will 
thereby  be  required  to  commit  to  meeting  the  standards  and  milestones  stipulated  in 
the LoI. If at any time during the feasibility study period, the AEDB/CA determines that 
the  sponsors  have  failed  to  adhere  to  relevant  milestones/standards  or  rectify  such 
default, the AEDB may terminate the LoI and encash the bank guarantee (the proceeds 
of which shall be shared with the CA in a predetermined ratio). For issuance of the LoI, 
the  sponsors  shall  be  required  to  post,  in  each  case,  a  bank  guarantee  in  favor  of  the 
AEDB  of  the  value  of  US$  500  per  MW  of  the  project’s  installed  capacity,  valid  for  a 
period extending six months beyond the original validity of the LoI. Sponsor must post 
the guarantee within less than 20 working days from approval of proposal. 
On  completion,  the  feasibility  study  shall  be  reviewed  by  an  AEDB‐appointed  Panel  of 
Experts  (POE),  and  if  approved,  the  project’s  sponsors  would  be  allowed  to  ask  for 
application of the corresponding feed‐in tariff to NEPRA within a period not exceeding 
three  months  from  date  of  such  approval,  and  to  obtain  a  generation  license  from 
NEPRA.  
Feed‐in tariff petition: The sponsors will file a feed‐in tariff petition with NEPRA through 
the AEDB. This is a formal procedure in which NEPRA shall assess if the applicable feed‐
in tariff requested is adequate for the proposed project. NEPRA would have 20 working 
days for approval of such a tariff from the date of the petition. 
LoS, IA & PPA agreements: After tariff approval by NEPRA, the AEDB shall issue a Letter 
of Support (LoS)7 against delivery of a Performance Guarantee of the value of US$ 2,500 
                                                       
7
  The  Performance  Guarantee  shall  be  in  the  form  of  an  irrevocable  direct‐pay  letter  of  credit,  issued  by  an 
internationally  recognized  or  a  local  bank  acceptable  to  the  Government  of  Pakistan,  in  favour  of  the  AEDB.  The 
Performance Guarantee must always remain valid for a period  not less than three months in excess of the then‐
prevailing financial close deadline 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  322
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

per MW of installed capacity in favor of the AEDB (should be posted within 30 working 
days  of  tariff  approval),  valid  for  up  to  three  months  beyond  the  date  specified  in  the 
LoS  for  the  project’s  financial  closure.  The  Performance  Guarantee  will  secure  the 
sponsors’ obligations to execute the IA, PPA, and other relevant agreements and achieve 
financial closure within the time period specified. If the LoS expires, the IA and PPA and 
all other agreements with any governmental entity will automatically terminate. Before 
signing the PPA, all consents (see Section 7) must be fulfilled. 
Project  implementation:  The  sponsor  will  be  required  to  submit  to  the  AEDB,  on  a 
format  specified  by  the  organization,  a  mutually  acceptable  implementation  schedule 
with  specific  milestones  for  progress  monitoring.  The  AEDB  and  the  power  purchaser 
will  require  the  successful  bidder  to  submit  periodic  progress  reports  regarding  the 
status  of  contractual  obligations,  consents,  financial  and  physical  progress,  and  a 
summary  table  showing  progress  towards  achievement  of  such  milestones. 
Management of delays in achieving financial close or in achieving commercial operations 
will follow IA and PPA procedures. 
Guarantee  of  pass‐through  tariffs:  In  case  the  RES  is  connected  to  a  distribution  grid, 
some  guarantee  will  be  required  that  the  distributor  will  recover  the  costs  associated 
with the RE power purchase. 

9 Implementation of Tariffs and Quotas 
Based  on  the  modeling  of  conventional  and  RE  supply  curves  carried  out  under  the 
current analysis (see Annexes VI and VII), an example of the design of the proposed set 
of  technology‐wise  feed‐in  tariffs  for  the  medium  term  policy  regime  is  presented  in 
Exhibit 2. In the case of uneconomic technologies, we assume the target quotas that are 
presented  in  the  following  table.  According  to  the  consultants’  estimation  the  total 
potential  RES‐E  capacity  that  could  be  installed  in  Pakistan,  based  on  these  feed‐in 
tariffs, is about 24 TWh/year. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  323
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 2: Illustrative RE Feed‐in Tariffs and Quotas 
RES-E Technology FIT Target Quota
US$/MWh MW

Bagasse-based Generation 76.82 No cap

Biogas 93.98 No cap

Non-bagasse Biomass Generation 85.40 No cap

Landfill Methane Recovery 76.82 No cap

Photovoltaic 430.50 25 MW

Sewage Gas Recovery 102.57 No cap

Small-scale Hydel8 73.95 No cap

Solar Thermal 272.26 25 MW

Wind On-shore9 102.57 No cap

Waste-to-energy 96.3 No cap

                                                       
8
  Of less than 50 MW capacity. This compares with FITs of US$ 75/MWh and US$ 80/MWh proposed for small hydro 
projects  of  capacity  0.5‐5  MW  and  <0.5  MW,  respectively,  in  Micro‐  Mini‐Hydel  (<5  MW)  Feed‐in  Tariff  Study  for 
Pakistan (Draft), GTZ REEP Project, Islamabad, July 2007. 
9
  This compares with US$ 95/MWh indicative up‐front tariff currently offered by NEPRA to wind IPPs. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  324
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Annex IX:  Working Paper 6: 
Medium­term Off­grid RES­E Policy 
Assessment 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  325
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Working Paper No. 6 

Medium­term Off­grid RES­E Policy 
Assessment  

Contents 
Exhibits ..................................................................................................................... 329 
Abbreviations and Acronyms .................................................................................... 330 
1  Objective .............................................................................................................. 333 
2  Issues in Off‐grid RE Services ................................................................................ 333 
3  Cornerstones of Off‐grid RES‐E Framework ........................................................... 337 
3.1  Simplified and Transparent Regulation ............................................................. 337 
3.2  Tailor‐made Regulation ..................................................................................... 338 
3.3  Delegation of Specific Regulatory Tasks to Other Government or  
Non‐Government Entities.................................................................................. 338 
3.4  Socially Acceptable Tariffs and Subsidies .......................................................... 339 
3.5  A Larger Dimension of Service Providers .......................................................... 340 
3.6  Many Regulatory Models to Choose From ........................................................ 341 
3.7  Setting Quality‐of‐Service Standards ................................................................. 342 
4  Selected International Experience ........................................................................ 343 
4.1  Argentina: Off‐grid Electrification in Jujuy Province ......................................... 343 
4.1.1  Tariff and Subsidies ............................................................................... 344 
4.1.2  Results ................................................................................................... 345 
4.2  Bolivia: The IDTR Program ................................................................................. 346 
4.2.1  Results ................................................................................................... 349 
4.3  Cambodia: Isolated Privately Operated Mini‐grids ........................................... 350 
4.3.1  Results ................................................................................................... 351 
4.4  Chile: The PER Program ..................................................................................... 352 
4.4.1  Renewable Energy ................................................................................. 353 
4.4.2  Results ................................................................................................... 354 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  327
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.5  India: The RGGVY Program ................................................................................ 354 
4.5.1  Private Involvement .............................................................................. 356 
4.5.2  Results ................................................................................................... 357 
5  Recent Developments in Pakistan ......................................................................... 360 
5.1  Roshan Pakistan Program .................................................................................. 361 
6  Quantitative Assessment of RES‐E Deployment .................................................... 362 
6.1  Electricity Demand: Simulated Target Villages .................................................. 364 
6.2  Electricity Supply: Generation Alternatives....................................................... 365 
6.3  Optimization Outcomes .................................................................................... 366 
6.4  Medium Term Off‐grid Policy Deployment Costs ............................................. 367 
7  Medium Term Off‐grid RES‐E Policy Recommendations ........................................ 369 
7.1  Target Markets and Technologies ..................................................................... 369 
7.2  Implementation Period ..................................................................................... 369 
7.3  Conceptual Approach ........................................................................................ 370 
7.4  Targets and Incentives ....................................................................................... 372 
7.5  Project Funding .................................................................................................. 373 
7.6  Pricing ................................................................................................................ 374 
7.7  Incentives Other Than Tariffs ............................................................................ 374 
7.8  Roles of Institutions ........................................................................................... 374 
7.9  Institutional, Legal and Regulatory Consents .................................................... 375 
7.10  Performance Monitoring and Enforcement ...................................................... 377 
7.11  Allocation of Carbon Credits .............................................................................. 377 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  328
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibits 
Exhibit 1:  Electricity Supply Models ............................................................................ 336 
Exhibit 2:  EJSED S.A. Customer’s Evolution by Type of Generation Technology ........ 345 
Exhibit 3:  IDTR Program SHS Connections .................................................................. 350 
Exhibit 4:  Regional Rural Electrification Coverage in Chile ......................................... 354 
Exhibit 5:  Progress of RGGVY Projects Sanctioned in India’s Xth Plan ........................ 358 
Exhibit 6:  India’s XIth Plan – Estimated Electrification Costs Norms for Villages ........ 360 
Exhibit 7:  Roshan Pakistan Rural Electrification Program Budget .............................. 362 
Exhibit 8:  Solar and Wind Availability in Target Village Area...................................... 363 
Exhibit 9:  Main Characteristics of Simulated Target Villages ..................................... 365 
Exhibit 10:  Off‐grid Generation Technology Alternatives ............................................. 365 
Exhibit 11:  Additional Simulation Input Parameters .................................................... 366 
Exhibit 12:  Off‐grid Electrification Deployment Simulation  
(Including Hydro Resources) ....................................................................... 367 
Exhibit 13:  Off‐grid Electrification Deployment Simulation  
(Excluding Hydro Resources) ...................................................................... 368 
Exhibit 14:  Off‐grid Electrification Capital and Fuel Costs for 1,850 Villages ............... 368 
Exhibit 15:  Proposed Federally Assisted Off‐grid RES‐E Deployment Approach .......... 370 
Exhibit 16:  Summary of Roles of Institutions in Off‐grid RES‐E Deployment ............... 375 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  329
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Abbreviations and Acronyms 

A  Ampere 
AC  Alternating current 
ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
Ah  Ampere‐hour 
AJK  Azad Jammu and Kashmir 
BPL  Basic poverty line 
BST  Bulk supply tariff 
CBO  Community Based Organization 
CFL  Compact fluorescent lamp 
CNE  Comisión Nacional de Energía 
CPPA  Central Power Purchasing Agency 
DC  Direct current 
DDGS  Decentralized Distribution Generation Systems 
DISCO  Distribution Company 
DVC  Damodar Valley Corporation 
EAC  Electricity Authority of Cambodia 
EIA  Environmental Impact Assessment 
ERTIC  Programa de Electrificación Rural y Tecnologías de la Información y 
Comunicación 
GEF  Global Environment Facility 
GoP  Government of Pakistan 
HH  Household 
ICT  Information and communication technology 
IEE  Initial Environmental Examination 
IRR  Internal rate of return 
KESC  Karachi Electric Supply Corporation 
LoI  Letter of Intent 
LoS  Letter of Support 
MoWP  Ministry of Water and Power 
MSC  Medium‐Term Service Contracts 
MW  Megawatt 
NEPRA  National Electric Power Regulatory Authority 
NGO  Non‐governmental Organization 
NREL  US National Renewable Energy Laboratory 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  330
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

NTDC  National Transmission and Dispatch Company 
NWFP  Northwest Frontier Province 
O&M  Operation and maintenance 
OBA  Output‐based aid 
OGREA  Off‐grid Rural Electrification Account 
Pak EPA  Pakistan Environment Protection Agency 
PCRET  Pakistan Council for Renewable Energy Technologies 
PCU  Project Coordination Unit 
PER  Rural Electrification Program (Chile) 
PV  Photovoltaic 
R&D  Research and development 
RE  Renewable energy 
REC  Rural Electrification Companies 
REDB   Renewable Energy Distribution Backbone 
REF  Rural Electrification Fund 
RES  Renewable energy source 
RES‐E  Renewable energy sourced‐electricity 
RET  Renewable energy technology 
RGGVY  Rajiv Gandhi Grameen Vidyutikaran Yojana 
RoW  Right‐of‐way 
SERC  State Electricity Regulatory Commission 
SHS  Solar home system 
TA  Technical assistance 
TCE  Technical Control Entity 
US  United States 
VEI  Village Electrification Infrastructure 
W  Watt 
WAPDA  Water and Power Development Authority 
WHS  Wind home system 
WTP  Willingness‐to‐pay 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  331
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Medium­term Off­grid RES­E Policy 
Assessment 

1 Objective 
This  Annex  presents  the  consultants’  assessment  and  proposal  for  the  design  of  a 
medium  term  policy  for  the  development  of  off‐grid1  renewable  energy  sourced 
electricity  (RES‐E)  in  Pakistan.  This  analysis  takes  into  account  some  critical  issues 
regarding  off‐grid  renewable  energy  (RE)  services,  selected  relevant  international 
experience,  and  some  assessment  of  the  overall  costs  implied  in  the  ensuing  policy 
recommendations. 
This document presents general guidelines for formulating a detailed medium term off‐
grid RES‐E Policy framework for Pakistan. Once the broad outline of the policy approach, 
and  its  underlying  rationale,  have  been  agreed  upon  by  relevant  stakeholders,  formal 
regulation for the medium‐term period (2009 to 2014) will be issued jointly with on‐grid 
regulation  for  the  systematic  implementation  of  RE  technologies  and  scaling  up  of 
capacity deployment in Pakistan. 
The proposal presented in this paper focuses on off‐grid renewable energy deployment, 
as  policy  measures  for  on‐grid  RE  have  been  discussed  in  the  preceding  annexes  IV  to 
VIII.  It  is  relevant  to  highlight  that  in  the  paper  the  electrification  of  scattered  or  grid‐
isolated  villages  only  is  considered;  traditional  electrification  based  on  grid  extension 
and/or conventionally powered mini‐grids is out of the scope of this review.  However, 
this proposal cannot be completely divorced from an overall national rural electrification 
policy strategy. Unfortunately, the task of rural electrification in Pakistan is distributed 
amongst  different  institutions  and  programs,  which  makes  a  holistic  assessment  more 
difficult. 

2 Issues in Off­grid RE Services 
The proper design of institutions and regulatory systems for electrification is a complex 
undertaking,  especially  for  off‐grid  regions.  This  is  due  to  the  fact  that  the  key  agents 
involved—organizations  (public,  private,  cooperative,  or  NGOs),  system  operators,  and 
end users, amongst others—involved in the development process each have their own, 
sometimes conflicting and often uncoordinated, objectives and incentives. In addition, in 
order  to  achieve  electrification  targets,  power  supply  companies  typically  use  one  or 
several of the following approaches: 
                                                       
1
  For the purposes of RE policy terminology, the term ‘grid’ is meant to imply either national or regional electricity 
T&D networks operated by the NTDC/CPPA and/or DISCOs of 11 kV or higher voltage.  Isolated, community‐based 
local distribution networks are considered ‘off‐grid’. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  333
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• On‐grid solutions: a) traditional grid expansion; or b) bulk resale by community‐
based organizations (CBOs) 
• Off‐grid solutions: a) Isolated mini‐grids; b) solar/wind home systems (SHSs and 
WHSs);  c)  battery‐charging  stations;  d)  centralized/decentralized  biogas 
digesters; amongst others. 
Off‐grid solutions are suitable for providing electricity services to isolated places where, 
either  due  to  difficulties  of  physical  access,  or  simply  because  the  cost  outweighs 
benefits,  grid  extension  is  not  a  feasible  option.  The  implementation  of  decentralized 
technologies  often  requires  decentralized  solutions;  this  requires  the  involvement  of 
local  governments,  small  local  companies,  cooperatives,  etc.,  which  consequently 
necessitates a ‘tailor‐made’ institutional and regulatory design. 
When defining any policy, especially when dealing with off‐grid solutions, policy makers 
need to consider two basic rules: 
1. Regulation is a means to an end, what ultimately matters is the outcome (in this 
case, providing electricity to people who lack this service): 
The final objective of the regulation should be that electrification is carried out in a 
rapid,  sustainable,  and  cost‐efficient  way  while  meeting  minimum  acceptable 
technical  quality‐of‐service  standards  and  end  user  affordability  criteria.  If  the 
designed system cannot achieve this outcome, then it has failed to ‘add value’. 
2. Benefits of the regulation must exceed its costs: 
The  regulator  can  contribute  to  maximizing  the  benefits  of  electrification  by 
minimizing  the  transaction  costs  of  regulation,  i.e.,  the  rules  imposed  by  a 
regulator cost time and money. Regulation creates both direct and indirect costs. 
Direct costs are the ones contemplated in the budget of the regulatory agencies as 
well as the costs incurred by agents for the fulfillment of the regulation. In off‐grid 
electrification, indirect regulatory costs are probably the highest. In many cases, a 
weak  economic  and  financial  enterprise  fails  to  fulfill  all  the  regulatory 
requirements, stopping it from initializing or completing an electrification initiative. 
In  such  cases,  when  the  regulation  pushes  the  enterprise  beyond  an  ‘inflection’ 
point,  then  the  design  has  essentially  failed  to  protect  the  customer  if  they  are 
forced to keep on buying electricity (or other substitutes) at prices (per kWh) much 
higher  than  the  ones  they  could  pay  from  an  operator  that  provides  electricity 
services. 
Historically, the predominant model for electrification in developing countries has been 
grid  extension  and/or  conventional  energy  powered  mini‐grids  made  by  large  state‐
owned utilities. These extensions have usually been financed by cross‐subsidies between 
consumers, or by loans or grants provided by the government. Recently, the spectrum of 
electrification  models  has  widened,  and  the  international  experience  related  to  the 
implementation of those methodologies can be summarized as: 
• Grid  extension  by  distribution  company  (Brazil,  Colombia,  Ghana,  Guatemala, 
India, and Nicaragua) 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  334
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Grid extension by local government, municipality, or private company (Colombia 
and Nicaragua) 
• Bulk resale by a cooperative or a private entrepreneur of grid‐supplied electricity 
to  a  new  area  or  an  area  that  had  been  supplied  by  an  isolated  generator 
(Bangladesh, Cambodia, and Costa Rica) 
• Isolated  village  mini‐grids  combined  with  an  stand‐alone  generator  (Bolivia, 
Cambodia, Ethiopia, Mozambique, Nicaragua, Philippines, and Sri Lanka) 
• WHSs/SHSs/biodigestors  installed  under  a  dealership  or  vendor  delivery  model 
(India, Indonesia, Kenya, and Sri Lanka) 
• WHSs/SHSs  installed  under  a  fee‐for‐service  model  (Argentina,  Laos,  Morocco, 
South Africa) or a mix of both (Bolivia) 
• WHSs/SHSs  installed  through  a  legal  obligation  imposed  on  the  distribution 
company (Argentina and Brazil) 
• Private or community‐owned and operated battery charging stations (Honduras, 
Nicaragua, and Nigeria). 
There are several reasons that may explain this variety of electrification models. Some of 
these are: 
• The  existence  of  private  distribution  companies:  Reforms  in  the  power  sector 
have  usually  resulted  in  some  combination  of  restructuring  and  privatization. 
Private  DISCOs  are  obviously  reluctant  to  supply  those  customers  who  will 
represent losses to them. Unless the reform package includes explicit incentives 
and  obligations  to  promote  electrification,  private  DISCOs  will  not  seek,  by 
themselves,  the  electrification  of  isolates  areas.  Without  proper  incentives, 
private companies will only focus on existing markets or on the more profitable 
ones,  usually  located  on  urban  areas.  This  situation  is  quite  different  from 
traditional state‐owned DISCOs, who can be ‘obligated’ to extend the grid. 
• The existence of economies of scale: All distribution companies face economies 
of  scales  in  developing  a  network.  Therefore,  the  direction  in  which  grid 
extensions take place moves from highly populated areas to less populated ones. 
Marginal—and  isolated—consumers  are  least  preferred  by  DISCOs  due  to  the 
high investment costs involved in serving them and their low demand and ability 
to pay.  
Electrification expenses: Grid extensions can become very expensive in the case 
of isolated, far flung areas. As an example, the cost of extending the grid in some 
rural  areas  of  Brazil  was  estimated  at  US$ 3,000‐4,000  per  customer.  On  the 
other  hand,  off‐grid  electrification  has  the  potential  to  provide  basic  electricity 
services at much lower prices (some typical values range between US$ 300‐1,000 
per  customer).  Hence,  off‐grid  electrification  has  the  potential  to  becoming  an 
economical alternative to typical grid extensions. 
• New and improved technologies: Off‐grid technologies have been updated and 
upgraded from time to time. Renewable energy has started playing a key role in 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  335
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

off‐grid solutions, with some of the most common RES‐E technologies for off‐grid 
application  including  solar  photovoltaic,  mini‐and  microhydel,  small  wind,  and 
biomass.  Usually  these  RES‐E  technologies  can  be  mixed  with  conventional 
generation to provide greater reliability to the system. 
• Decentralized technologies for decentralized business models: One of the main 
characteristics  of  off‐grid  technologies  is  that  they  are  installed  close  to  end‐
users and far away from centralized administrative or operative entities. Due to 
the  isolation  of  customers,  traditional  business  models—and  their  regulation—
have  failed  to  provide  useful  management  solutions  for  these  customers. 
Therefore, off‐grid technologies need business models suited for the purpose in 
terms  of  operation,  maintenance,  and  client  service.  In  some  cases,  micro‐  or 
community‐based enterprises have played a key role in the off‐grid electrification 
process. 
Exhibit  1  summarizes  some  of  the  existing  international  experience  on  off‐grid 
electrification in order to provide information on regulatory policy options. The range of 
models depicted in the exhibit demonstrates that there is no single, ‘unique’ solution for 
off‐grid electrification. Moreover, in many cases more than one model is applied within 
the  same  country,  which  means  that  regulatory  institutions  must  be  flexible  enough 
maybe  to  provide  a  ‘menu  of  solutions’—with  proper  incentives  for  each—amongst 
which stakeholders can choose from. 

Exhibit 1: Electricity Supply Models 

Grid Connected Isolated Single-User


Type
Extension Mini-grid Mini-grid System

Hydel mini-grid
selling to local SHS (Honduras,
customers and Indonesia,
to the main Kenya, Sri
grid (China, Lanka)
Nicaragua) Diesel or hydel
Small & Small grid mini-grid
Decentralized reseller (India) (Cambodia, PV/wind/diesel
Formerly Ethiopia) (Brazil, Chile,
isolated mini- México)
grid now grid Wind or hydel
connected (Argentina,
(Cambodia) Mongolia,
Nepal)

Privatized Off-grid concession (Argentina)


concessionaire
extends grid SHS
Large &
(Argentina, (Bangladesh,
Centralized Technology neutral electrification
Private

Chile, Bolivia,
Guatemala, concession (Senegal)
Morocco, South
Uganda) Africa)

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  336
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Grid Connected Isolated Single-User


Type
Extension Mini-grid Mini-grid System
Multi-service
cooperative
Cooperative Agricultural
with hydel or
finances grid cooperative
diesel micro-
Cooperative extension using diesel
grid
(Bangladesh, generator
(Bangladesh,
Costa Rica) (Bolivia)
Bolivia,
Philippines)
Community
micro-grids Diesel or PV to
(Brazil, power a school,
Non-governmental

Cambodia, clinic,
Honduras, community
Other
Indonesia, center
Community
Nicaragua, Sri (Argentina)
Organization
Lanka)
PV battery
charging
stations
(Nicaragua)
Small state-
owned utility Municipal diesel
Small &
extends grid or hydel mini-
Decentralized
(Brazil, grid (Bolivia)
Colombia)
State utility
Residual state-
extends grid
owned isolated
and sells at
diesel mini-grid
Large & retail
with fuel SHS (Mexico)
Centralized (Botswana,
subsidies
Public

Mozambique,
(Cambodia,
Thailand,
Nicaragua)
Tunisia)

3 Cornerstones of Off­grid RES­E Framework 
In  formulating  an  off‐grid  RE  deployment  strategy,  several  key  cornerstone 
considerations need to be kept in mind, as described below. 

3.1 Simplified and Transparent Regulation 
The  first  cornerstone  represents  the  corollary  of  the  general  and  widely  accepted 
principle  of  regulation  mentioned  earlier:  a  good  regulatory  system  always  minimizes 
regulatory costs. The basis for this principle is simple, since it is of no value to increment 
regulation over the minimum necessary threshold as this imposes additional costs on all 
stakeholders.  Any  type  of  regulation  costs  money  and  time  to  implement  and  comply 
with, and this is true regardless of whether the regulated entity is privately or publicly 
owned.  Most  electricity  firms  in  isolated  areas  are  usually  financially  weak  and  barely 
commercially  viable.  Therefore,  any  increase  in  regulation  can  easily  put  these 
enterprises in a difficult situation by undermining their financial viability. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  337
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

3.2 Tailor­made Regulation 
The  regulation  should  be  adapted  to  the  nature  of  the  entity  that  is  being  regulated. 
Unfortunately, some statutes do not allow such a tailor‐made approach; usually some of 
them are silent regarding grid and off‐grid regulation while others apply the concept of 
‘one  size  fits  all’.  This  is  not  the  best  approach,  as  it  can  lead  to  unnecessary  disputes 
regarding  the  issues  the  regulator  is  legally  authorized  to  delve  into  under  existing 
statutes. 
As we will explain later in this paper, off‐grid RE electrification can be achieved using a 
variety  of  technologies,  regulatory  models,  and  forms  of  ownership.  Therefore,  the 
regulation  of  these  cannot  be  generic.  Some  examples  to  illustrate  this  point  follow. 
Under  a  ‘fee‐for‐service’  model,  one  would  expect  that  the  regulator,  or  some  other 
entity  that  is  acting  as  its  agent,  would  need  to  regulate  both  the  price  and  quality  of 
service. The rationale is that the SHS operator has been granted a legal monopoly and 
therefore  consumers  need  to  be  protected  from  possible  monopolistic  abuses. 
Moreover,  not  only  the  regulator,  but  other  government  agencies  would  also  have  a 
stake—for instance, because, having provided the subsidies, they would want to ensure 
that  the  government  gets  ‘good  value’  for  them.  On  the  contrary,  less  regulation  is 
required for off‐grid RE providers that operate as dealers, as there is a presumption that 
price  regulation  is  not  needed  because  competition  amongst  various  dealers  will  itself 
protect consumers from monopolistic pricing. These differences can also be observed in 
terms of ownership: when a community‐based organization self‐supplies electricity, the 
universal  regulatory  concern  that  the  operator  may  charge  monopolistic  prices 
disappears. Owners of a cooperative do not have an incentive for price gouging because 
this  would  be  equivalent  to  taking  money  from  one  pocket  and  putting  it  in  another. 
Hence, self‐supply offers the possibility of self‐regulation. 

3.3 Delegation of Specific Regulatory Tasks to Other Government or Non­
Government Entities 
The  national  or  regional  regulator  may  allow  (or  even  request)  that  some  specific 
regulatory  tasks  could  be  performed—on  a  temporary  or  permanent  basis—by  other 
governmental or non‐governmental entities. In off‐grid services, it is often more efficient 
for  the  national  regulator  to  delegate  traditional  regulatory  functions  for  entities  that 
are providing off‐grid electrical service. 
Specific  task  delegation  is  especially  desirable  if  an  agency  in  charge  of  rural 
electrification, or a fund that provides capital subsidies (and sometimes also operation 
and maintenance subsidies) to enterprises in charge of providing electrification services, 
already exists. As an example, an electrification agency may impose price caps that the 
distribution company will be required to adhere to in charging its customers. In addition, 
the  electrification  agency  may  impose  specific  requirements  in  certain  areas,  such  as 
new  connection  modalities,  technical  standards,  and  quality  of  service  parameters. 
These  requirements  constitute  the  traditional  area  of  price  and  quality  of  service 
regulation.  Therefore,  in  this  case  the  electrification  agency  becomes  the  de  facto 
regulator. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  338
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

If  the  electrification  agency  thus  becomes  a  de  facto  regulator—due  to  the  conditions 
and requirements imposed to the operator in lieu for the subsidies—then it makes sense 
to transform this entity into the official regulator for several reasons: 
• The  electrification  agency  usually  has  a  better  knowledge  of  the  technical  and 
operational aspects of service deliver than the regulator, particularly in the case 
of isolated, rural service provision. 
• The electrification agency has a better understanding of the cost implications of 
different regulatory requirements. 
• If the regulator decides to undertake traditional regulatory tasks, it would simply 
reenacting many of the determinations already made by the rural electrification 
agency for the preceding reasons. 
• There is an obvious need for coordination between the electrification agency and 
the  regulator,  although  mandated  coordination  between  different  government 
entities is usually slow and tends to produce conflicts. 
• The  two  primary  sources  of  income  for  typical  off‐grid  operators  are  subsidies 
and tariffs. Therefore, subsidy rules and tariff regulation need to be coordinated 
closely. 
• It would avoid confusion and create greater clarity, thereby reducing regulatory 
risks. 
• It would minimize the risk of duplication and overregulation. 
All  of  these  reasons  suggest  that  regulatory  task  delegation—whether  formal  or 
informal, temporary or permanent—constitutes a cornerstone strategy for rural isolated 
electrification.  However,  there  are  some  activities  that  are  better  performed  in  a 
centralized manner, for instance, the creation and use of (legal) model documents to be 
employed  for  the  relationships  between  investor/communities/organizations  and 
customers,  provincial  governments,  etc.  Such  documents,  for  instance  may  include 
model  power  supply  agreements,  model  subsidy  contracts,  and  model  bidding 
documents. 

3.4 Socially Acceptable Tariffs and Subsidies 
The rationale of subsidies for off‐grid electricity provision is to diminish the gap between 
high electrification costs and the typically low capacity to pay (i.e., incomes) of residents 
in isolated, scattered, or remote areas. As in all cases, the government, rather than the 
regulator,  has  primary  responsibility  for  deciding  the  level  of  subsidies,  the  form  of 
subsidies (subsidies to the enterprise, subsidies to some or all consumers, or both), and 
the mechanism for funding the subsidies (external budget transfers, grants or loans, or 
cross‐subsidies).  The  regulatory  agencies  should  have  primary  responsibility  for 
periodically informing the government as to how much the electricity service would cost 
with and without subsidies. 
There are three critical issues relating to such subsidies: 
• One‐time connection subsidies that reduce connection costs for the poor should 
be favored over ongoing consumption subsidies. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  339
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Output‐based  subsidies  that  are  given  in  return  for  performance  should  be 
preferred. 
• Availability  of  funds  should  be  carefully  addressed.  For  example,  rural 
electrification  funds  set  by  law  and  collected  via  a  levy  on  grid‐connected 
customers bills are safer than state budget provisions. 
Regarding tariffs, they should be socially acceptable and thus linked to the ‘willingness‐
to‐pay’  (WTP)  of  the  target  customer  base.  In  addition,  the  regulatory  agency  should 
take account of grants or contributions received from government ministries, national or 
subnational  electrification  funds,  international  donor  organizations,  or  monetary  or  in‐
kind  contributions  from  customers.  As  a  general  rule,  the  level  of  tariffs  should  be 
reduced to take account of grants or contributions of labor, while recognizing that tariffs 
must  recover  O&M  and  the  cost  of  future  replacements  of  any  capital  equipment 
required for the sustainable provision of the service. 
As  the  billing  cost  may  be  important  in  this  type  of  business,  the  regulation  should 
encourage technologies or billing arrangements that will allow consumers to control the 
amount  and  timing  of  their  expenditures  and  thus  reduce  or  manage  their  individual 
expenses. 
Flexibility in pricing is another relevant element of proper regulatory design. Even when 
consumption  is  subsidized,  consumers  may  want  to  pay  more  for  higher  levels  of 
electricity  service,  such  as  more  kilowatt‐hours  (kWh)  received,  stable  voltages,  and 
fewer  outages.  If  consumption  subsidies  are  given,  they  should  be  limited  to  the 
amounts  needed  for  basic  human  needs.  To  some  extent,  regulation  should  allow 
suppliers  and  individuals  or  groups  of  consumers  to  negotiate  direct  agreements  that 
cover  the  term  and  conditions  of  electrical  service,  provided  such  agreements  are 
consistent with the regulation’s general principles and standards. 
The  issue  of  what  ‘basic  human  needs’  means  is  also  critical.  For  instance,  there  has 
been a lot of controversy regarding off‐grid RE‐based electrification with very low per‐
household  installed  capacities,  the  so‐called  ‘poverty  lighting’  problem.    The  ultimate 
goal of an off‐grid electrification policy should be the social integration and sustainable 
development of the communities concerned, and therefore minimum needs should be 
carefully addressed in each case. 

3.5 A Larger Dimension of Service Providers 
In the off‐grid RE arena, an electricity supplier can be a private/state‐owned company, a 
partnership,  an  individual,  a  cooperative,  an  NGO  or  a  sub‐national  government  body. 
This can also have some implication on regulation details. For instance, it is evident that 
an  authorization  granted  by  the  government  to  provide  electrical  service  of  sufficient 
duration  and  exclusivity,  as  an  incentive  for  the  supplier,  will  lead  to  improvements  in 
the number and quality of connections achieved. However, such authorizations cannot 
be costly and complex; as a general rule, smaller entities should have fewer and simpler 
regulatory requirements applicable to them. 
The nature of regulation should also be allowed to vary, depending on the type of entity 
that owns the facilities that are being regulated. Consider, for example, the case of an 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  340
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

isolated  hydel  mini‐grid.  Such  a  system  could  be  owned  and  operated  by  a  private 
company, a cooperative, or some other community‐based organization. In each case, the 
technology remains the same and the legal document issued by the regulator may also 
be the same, but the process of regulatory review, especially with respect to consumer 
prices, may be different. The private mini‐grid operator will be trying to maximize profits 
by charging the highest prices that it believes that its customers can pay. The situation is 
different for a cooperative, in which the owners are also the consumers; if the owner‐
members of the cooperative decide to raise prices, they themselves would have to pay 
the  higher  prices,  being  also  the  customers.  However,  this  does  not  mean  that  the 
regulator  should  take  a  completely  ‘hands‐off’  approach.  It  would  be  naïve  to  believe 
that community‐based organizations will always have good governance; as a matter of 
fact,  good  governance  is  easier  to  achieve  in  small  communities,  but  when  the 
community  becomes  larger,  any  form  of  ownership  requires  regulation,  even  if  it  is  a 
light‐handed one. 

3.6 Many Regulatory Models to Choose From 
Regulatory models for off‐grid electrification services can be classified in two types for 
analysis: the ‘fee‐for‐service’ model and the ‘dealership’ or ‘vendor’ model. However, in 
the real world, hybrid approaches are the most common. 
Under  the  ‘fee‐for‐service’  or  ‘long‐term  authorization’  model,  installations  are  owned 
by the operator. Fee‐for‐service operators often receive capital cost subsidies from the 
government  to  lower  their  connection  charges  for  customers  (and  in  some  cases, 
ongoing  operating  and  maintenance  expenses).  Under  the  fee‐for‐service  model, 
operators  often  work  under  a  concession  or  license  that  grants  an  exclusive  right  and 
obligation to provide service within a specified geographic region for a specified period 
(usually  15‐20  years).  The  concessionaire  is  granted  a  legal  monopoly  (and  a  capital 
subsidy) in return for a specified obligation to serve. The subsidy grant is often bid out, 
so that there is competition ‘for the market’. 
 In contrast, a provider who is a ‘dealer’ operates under a very different business model. 
The  dealer  may  receive  a  nonexclusive  franchise  from  the  government  under  the 
expectation is that the dealer will be one of several dealers, all of whom are competing 
‘in  the  market’  to  provide  the  installations  to  potential  customers,  usually  at  fixed 
subsidies. Typically, the dealer‐provider will sell the equipment and, ideally, installation 
(with  or  without  financing)  to  a  customer.  It  will  have  no  ongoing  obligation  to  that 
customer, unless the dealer is willing to offer an extended warranty or ongoing service 
agreement. Once the equipment is purchased, it is owned by the customer. 
As mentioned above, there are a lot of intermediate approaches. An interesting one is 
‘medium‐term  service  contracts’  (for  instance,  the  Bolivia  IDTR  project).  This  novel 
business model tries to combine the strengths of the fee‐for‐service and dealer models. 
Under  this  hybrid  approach,  subsidies  are  provided  in  return  for  five‐  to  seven‐year 
obligations to develop and serve small local markets. The winners of the medium‐term 
service  contracts  have  the  obligation  to  install  a  minimum  number  of  equipment  sets 
over a period of less than three years, to service systems during an additional four years 
(starting  from  the  date  of  installation),  to  develop  local  markets  on  the  demand  and 
supply side by educating users about the employed technologies, to report on their own 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  341
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

performance, and to conduct user interviews for project evaluation. The operators are 
free  to  choose  between  cash  sales,  microcredit,  and  finance  or  operate  leases,  and 
therefore  have  considerable  freedom  to  choose  the  best  business  solution  for  their 
respective geographic areas and market conditions. 

3.7 Setting Quality­of­Service Standards 
Quality‐of‐service standards should be realistic, affordable, verifiable and enforceable. 
It is counterproductive to try to impose quality standards that are impossible to meet. 
However,  this  does  not  mean  that  they  should  be  altogether  ignored.  The  main  issue 
regarding  quality  standards  is  that  they  are  hard  to  specify  and  monitor,  especially  in 
isolated  or  remote  rural  areas.  In  addition,  when  quality‐of‐service  standards  cannot 
keep up with people’s expectations, disputes increase—this is particularly important in 
the  case  of WHSs  and  SHSs—regarding  remedial  measures and  responsibilities.  Due  to 
the  fact  that  they  are  difficult  to  regulate,  quality  standards  usually  do  not  receive 
proper  attention  by  the  regulator.  The  risk  in  ignoring  quality‐of‐service  is  that  the 
benefits  accruing  from  electrification  projects  may  quickly  disappear  if  the  service 
quality falls short of customers’ requirements. 
Quality‐of‐service standards should be based on the following operational parameters: 
• Quality standards can be established on an input basis, an output basis, or a mix 
of  both.  They  should  be  established  for  those  dimensions  of  service  that  are 
important  to  consumers,  controllable  by  the  operator,  and  capable  of  being 
measured on a reasonably objective basis. 
• Quality  standards  do  not  have  to  be  uniform  across  all  customer  categories  or 
geographic areas. Instead, they should be based on customer’s preferences and 
their willingness to pay for the costs of providing the specified level of quality—
higher quality almost always costs more money. 
• Standards  should  be  established  for  both  technical  and  commercial  dimensions 
of service. They may be: 
o Guaranteed  standards,  where  the  standard  must  be  achieved  for  every 
specified customer. 
o Overall  standards,  where  the  standard  must  be  achieved  on  average  over  a 
stated  period  across  a  specified  customer  category,  but  need  not  to  be 
satisfied at all times for all customers in the category. 
o The operator must inform its customers of these standards. 
• Penalties  and  rewards,  as  well  as  the  standards,  should  be  phased  in  over  a 
reasonable  period.  Any  penalties  should  be  proportionate  to  the  extent  of 
noncompliance and the costs likely to be incurred by the operator in meeting the 
standards. 
• Where  feasible  and  efficient,  penalties  should  be  paid  to  individual  customers. 
Otherwise,  penalties  should  be  used  to  provide  subsidies  to  poor  customers. 
Penalties shall never be used to support the regulator’s budget. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  342
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Any  changes  in  the  standards  should  be  synchronized  with  regulatory 
proceedings to update tariffs for a new tariff‐setting period. 
• The  regulatory  agency  should  have  the  legal  authority  to  delegated  or  contract 
out  quality‐of‐service  monitoring  and  imposition  of  penalties  to  a  third  party, 
subject to appropriate oversight and dispute resolution processes. 
• The  regulatory  agency  should  establish  a  reliable,  objective,  and  publicly 
available  monitoring  system  that  compares  the  quality  of  service  provided  by 
different operators. 

4 Selected International Experience 
Examples from global experience of off‐grid electrification can provide useful lessons for 
the design of an effective policy and regulatory regime. 

4.1 Argentina: Off­grid Electrification in Jujuy Province 
Argentina has been a pioneer in the development of a new methodology for electricity 
deployment in rural isolated areas. Under this approach, concession areas were granted 
with exclusivity rights to private investors in an auction process. Companies bid for the 
subsidy,  and  the  concession  is  awarded  to  the  investor  who  requests  the  smallest 
subsidy.  In  addition,  the  concessionaire  decides  which  technology  will  be  used  to 
provide the electricity service (solar, wind, mini hydel, etc.). 
The  concession  developed  in  the  province  of  Jujuy—as  well  as  in  provinces  across  the 
country—provides  exclusivity  for  electricity  service  delivery,  creating  regulated 
monopolies  (In  Jujuy  the  concession  was  granted  to  EJSED  S.A.).  Therefore,  effective 
regulation becomes paramount for the success of the project. The electricity service is 
guaranteed for a long period of time, in this case 15 years of the concession period. 
In the Argentinean case, concessions were preferred to other alternatives due to several 
factors including: 
• The  creation  of  a  market  with  enough  critical  mass  to  provide  commercially 
sustainable business opportunities for private investors. 
• The  possibility  of  attracting  larger  companies  with  sufficient  internal  financing 
resources. 
• The simplification of the administration processes involved. 
• The  prospects  for  economies  of  scales  and,  consequently,  cost  reduction  to  be 
achieved. 
• Even  though  EJSED  S.A.  provides  electricity  services  using  a  variety  of  different 
technologies—SHS,  diesel  mini‐grid,  solar/wind  mini‐grid  and  micro  hydel  mini‐
grid—the  experience  of  the  company  with  SHS  has  been  the  most  successful, 
given  that  most  of  the  target  population  is  scattered  and  solar  radiance  is  very 
high in this part of Argentina. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  343
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The product included in the tender process is defined as ‘electricity services’. Under the 
concession  contract,  EJSED  S.A.  is  obligated  to  guarantee  the  generation  of 
7.5 kWh/month  of  electricity  (which,  in  most  cases,  is  generated  using  two  solar 
photovoltaic  panels  (50  Wpeak  each),  a  12  A  load  control  and  a  160  Ah  battery)2.  This 
system remains EJSED’s property throughout the concession period (i.e., no transfer to 
the user is allowed). In addition, it is the user’s responsibility to procure and install all 
components required from the electrical connection to inside the house (cables, fuses, 
plugs, light bulbs, switches, etc.).3 
There are no formal contracts between EJSED S.A. and their customers. The user needs 
only to complete a form requesting the service in which some basic rules and terms are 
established. The customer pays an installation fee and a monthly fee for the use of the 
service. In case of a re‐connection, the fee is nearly twice the initial installation fee, as 
this charge is not subsidized. 
4.1.1 Tariff and Subsidies 
Tariff  setting  is  made  at  the  provincial  level.  Electricity  tariffs,  based  on  technical  and 
economic principles, allow the recovery of cost plus an investment return for the service 
provider. 
In the case of SHS, off‐grid electricity is not measured; the user only pays with respect to 
the size of the system s/he is employing. The tariff is therefore designed based on the 
sizes  of  the  photovoltaic  panels  and  the  battery,  i.e.,  the  investment  cost.  Thus,  the 
monthly  fee  allows  the  recovery  of  the  investment  plus  the  present  value  of  the 
operation and maintenance cost, including battery replacements. 
Tariff  subsidies  are  either  based  on  the  residential  expenditure  for  lightning  and  radio 
(‘avoided  cost’)  or  on  the  customer’s  ‘willingness‐to‐pay’  (WTP).4  The  monthly 
expenditure  on  kerosene,  candles,  batteries,  and  bottled  gas  can  be  used  as  a  fair 
indicator  of  the  upper  bound  for  the  electricity  tariff.  From  a  social  point  of  view,  if 
electricity  costs  are  higher  than  alternative  energy  sources,  then  a  subsidy  should  be 
provided to span the gap. 
In  the  case  of  Jujuy  province,  the  concessionaire  finances  40%  of  the  investment  cost, 
10%  is  paid  by  the  customer,  while  the  remaining  50%  is  paid  by  the  provincial 
government.  The  monthly  fee  is  used  to  pay  the  present  value  of  the  operation  and 
maintenance  cost,  plus  the  40%  of  the  investment  cost.  For  very  poor  families,  the 
concessionaire provides financial services for the installation fee. 
Under the PREMER program, subsidies are covered through  a rural electrification fund 
(Fondo  de  Desarrollo  de  la  Electricidad),  World  Bank  loans,  and  a  Global  Environment 

                                                       
2
  This  system  allows  the  use  of:  two  15W  light  bulbs  for  4  hours/day;  one  10  W  radio  for  3  hours/day;  one  20  W 
radio‐cassette player for 1 hour/day; and one 80 W TV (b&w) for 1 hour/day. 
3
  In some regions, the government provides subsidies for the purchase of these components. 
4
 The analysis of willingness‐to‐pay can be a good methodology for assessing subsidies, but—contrary to expectations 
—some  studies have  shown  that  WTP  is  usually  less  than  payment  capacity.  For  example,  many  customers  think 
that  switching  to  electricity  is  worthy  if  this  change  diminishes  the  energy  bill  without  considering  the  additional 
benefits associated to the use of electricity.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  344
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Facility (GEF) grant. These funds were used to provide subsidies during the first six years 
of  the  program;  afterwards,  additional  funds  came  from  a  Tariff  Compensation  Fund, 
also established by the national government.  Tariffs and subsidies are revised biannually 
if costs or market conditions are deemed to have changed substantially in the interim. 
4.1.2 Results 
The cumulative experience gained in off‐grid electrification in Argentina through several 
years of operation of the program described above has provided an important quantum 
of  information  for  analysis  purposes.  Exhibit  2  presents  the  evolution  of  EJSED  S.A. 
customer  numbers  by  generation  technology.  As  can  be  seen,  SHS  has  been  very 
successful  technology,  bearing  in  mind  that  the  process  was  adversely  affected  by  the 
Argentinean economic crisis during 2001‐02. 

Exhibit 2: EJSED S.A. Customer’s Evolution by Type of Generation Technology 

 
The  two  prominent  ‘jumps’  in  the  SHS  connection  trend  may  be  explained  by  the 
following: 
• The  first  public  audience  was  held  in  May  1999  and  set  the  new  tariffs  for  the 
period 1999‐2001. In addition, it was determined that off‐grid customers should 
pay the same connection fee as on‐grid customers, instead of a connection fee 
based on installed capacity. 
• A second public audience was held and new tariffs were set for the period 2001‐
2003.  
Despite the success in terms of customer numbers, several issues with the initiative still 
need to be addressed. These flaws have been allocated to two main categories: 
Operational shortcomings: 
• Lack  of  customer  training  programs.  These  training  courses  should  instruct 
customers on the proper use and capabilities of the installations. 
• Clients continue to face problems related with electricity connections inside their 
houses which they cannot resolve on their own. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  345
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• High  replacement  costs  for  low  energy  consumption  light  bulbs  (i.e.,  CFLs)  not 
compensated for in the tariffs. 
• Use of system elements which are incompatible with the generation technology 
employed. 
• Customer manipulation of generation equipment. 
• Technical reviews are sometimes impossible to be successfully completed due to 
unavailability of or difficulties in accessing the customer, especially those located 
in isolated or distant locations. 
• Non‐existent  or  poor  communication  capabilities  (on  the  customer’s  side)  to 
schedule visits or to report anomalies in the system. 
• Deficiencies  in  the  anomalies  reported  (users  cannot  properly  describe  the 
problems encountered). 
Commercial shortcomings: 
• Billing delivery is often difficult due to isolation of communities served. 
• Collection  is  difficult  because  customers  do  not  use  the  payment  facilities  and 
procedures provided, and instead wait to be contacted. 
• An electrical malfunction inside the house or a burnt light bulb creates collection 
problems, as clients refuse to pay for a service they did not utilize. 
• Difficulties  encountered  in  collecting  charges  for  equipment  that  has  been 
damaged by the client. 
• In SHS, cutting off the service due to non‐payment implies the withdrawal of all 
the  equipment  (in  this  case,  usually  the  service  is  not  restored  due  to  high 
reconnection costs). 

4.2 Bolivia: The IDTR Program5  
With the financial assistance of the World Bank, Bolivia launched a ten year, three‐phase 
adaptable  program  in  2005  to  increase  access  to  electricity,  information,  and 
communications services in rural areas by using innovative, decentralized public‐private 
business models and focusing on productive uses and training of suppliers and users.6 As 
part  of  this  program,  output‐based  aid  (OBA)  subsidies  for  innovative  ‘Medium‐term 
Service  Contracts’  (MSC)  aimed  at  local  market  development  for  SHS  were  be 
competitively awarded in several tenders. 
The  purpose  of  the  Bolivia  ERTIC  Program7  is  to  expand  and  improve  the  delivery  of 
infrastructure  services  through  private‐sector  led  mechanisms  as  a  catalyst  for  the 

                                                       
5
  Programa de Infraestructura Descentralizada para la Transformación Rural. 
6
  The  other  two  phases  of  the  program  are  related  to  transmission  and  distribution  grid  expansions  and  the 
development of rural mobile telephony. 
7
  The Bolivia ERTIC Program (Programa de Electrificación Rural y Tecnologías de la Información y Comunicación) and 
the  Medium‐Term  Service  Contracts  are  financed  by  the  World  Bank.  Locally,  the  program  is  technically 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  346
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

development of rural areas in Bolivia, with a focus on decentralized electricity services 
and information and communication technologies (ICT). The basic program strategy is to 
stimulate the market by assuring the long‐term availability of local support through the 
development of selected local market areas via the so called ‘SHS Medium‐Term Service 
Contracts’ (MSC). 
The  basis  for  any  successful  OBA‐based  transaction  is  a  careful  design  of  the  subsidy 
allocation,  service  obligations,  and  enforcement  mechanisms.  This  is  of  special 
importance for off‐grid projects aimed at attracting private sector operators to remote 
rural markets. 
More specifically, during Phase 1, a tender process was carried out—the winners were 
Isofoton  and  Energetica—with  these  MSCs  for  providing  electrification  services  in  four 
large blocks of the country. These electrification services include SHS installation, credit 
services for paying connection fees, operation and maintenance services, and local post‐
sales technical services development through training courses. 
Some of the basic guiding principles for the transaction included: 
• Service  sustainability  is  ensured  by  the  MSC,  given  that  after  the  installation  of 
the SHS equipment, the service providers have to provide post‐sales services and 
market development activities for an additional period of about three years. 
• The  winning  bidder  has  the  obligation  to  develop  the  local  market  in  his 
respective  area  via  capacity  building  and  monitoring  tasks  on  the  supply  side 
(e.g., training local spare parts and repairs specialists, who would later be able to 
cater  to  future  market  needs)  and  demand  side  (e.g.,  training  users  and 
promoting future sales of PV for domestic, productive, and public uses). Hence, 
each concessionaire will help reduce initial information barriers in his respective 
market  area—an  additional  service  that  will  be  checked,  just  as  the  SHS 
installations themselves, through random audits. 
• Subsidies are paid against outputs (i.e., users provided with satisfactory service, 
local market development services successfully delivered, etc.). 
• To  allow  cost  reduction  and  service  improvements  through  creative  business 
models  by  bidders—while  assuring  service  quality  over  time—the  bidding  and 
service  contracts  allowed  for  a  ‘well  informed  freedom  of  choice’  for  service 
providers  and  users  by  permitting  for  different  ways  of  reaching  the  desired 
outputs  (e.g.,  system  sizes  and  payment  options),  while  fixing  minimum  service 
standards. 
• Productive and public uses are facilitated with additional targeted subsidies. 
The  MSC  service  obligation  sets  the  local  market  development  pattern  via  specific 
activities which are mostly part of the concessionaire’s obligations: 

                                                                                                                                                            
coordinated by the Program Coordination Unit (UCP) of the Ministry of Electricity and Alternative Energies of the 
Government of Bolivia. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  347
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Household visits (about once or twice a year) for checking the systems, training 
users,  and  performing  basic  monitoring  tasks  via  simple  questionnaires  to  be 
signed  by  the  users  (this  decentralization  of  monitoring  allows  for  close 
monitoring  of  compliance  by  the  Project  Coordination  Unit  (PCU)  via  audits  at 
low costs); 
• Ongoing promotion of PV for domestic, productive, and public uses in the service 
area; and 
• Establishment of local microenterprise networks that sell spare parts and repair 
systems  (all  operators  and  technicians  participate  in  a  yearly  ERTIC  Program 
training seminar where early lessons are discussed and capacity is checked). 
Each MSC will be supervised by the Technical Control Entity (TCE) within the PCU of the 
Ministry of Electricity and Alternative Energies. To protect customers’ rights, ensure that 
service quality standards are met, and market development activities and other services 
are carried out, the TCE contracts with specialist firms to conduct random audits. 
In  the  ERTIC  program,  emphasis  is  placed  in  a  scheme  oriented  towards  the  ‘service 
provided’.  Thus,  the  attention  and  the  subsidy  payments  are  geared  to  what  is  really 
relevant: the final product delivered.  
A general difficulty in service specification arises from tensions that existed between the 
need  to  lay  down  a  precise  description  of  the  service  to  be  provided  and  the  need  to 
allow for flexibility and scope for innovation after the award has taken place. By focusing 
to  the  extent  possible  on  desired  ‘outputs’  and  not  on  the  particular characteristics  of 
the  equipment/service  supplier  and  his  business  plan,  a  more  flexible  framework  is 
made  available,  which  gives  service  providers  as  much  freedom  as  possible  for 
responding  to  customer  demands  in  an  innovative  manner.  Providing  this  flexibility—
while assuring quality—is a program objective. For example, PV equipment suppliers are 
allowed to join local microcredit organizations, community organizations, or NGOs in a 
partnership  for  providing  the  services  under  the  necessary  quality  standards  and 
conditions. These partnerships are paid the subsidies upon meeting at least three basic 
objectives: 
• A share of the subsidies (direct customer subsidies) is paid to the provider based 
on actual installations achieved; 
• Another  share  is  paid  against  meeting  performance  targets  related  to  service 
quality,  training  of  local  technicians,  yearly  visits,  user  training,  and  submitting 
regular monitoring protocols (as mentioned above); and 
• A  third  share  is  paid  based  on  meeting  market  development  goals,  such  as 
creating a local spare parts market. 
As  an  ‘output  oriented’  program,  the  minimum  characteristics  of  the  ‘service  to  be 
delivered’ were defined in the bidding documents, such as: 
• Minimum number of users to be connected, 
• Quality of service that must be achieved, as well as quality of PV systems allowed 
under the program, 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  348
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Minimum conditions for managing and maintaining the service, 
• Capacity building and training of local technicians and users in the management 
and maintenance of the service, 
• Other obligations related to the development of the market and the creation of a 
sustainable service. 
The  bidding  documents  included  a  description  of  different  payment  options  (e.g., 
maximum  values  for  upfront  cash,  monthly  payments,  quarterly  payments),  each  of 
which was related to the system size chosen by the customer. 
The project provides several types of subsidies: 
• Direct up‐front OBA customer subsidies on the initial investment cost, paid to the 
supplier on the basis of actual installations achieved; 
• OBA  service  quality  subsidies,  paid  to  supplier  against  installation  and  service 
performance targets achieved; 
• OBA market development service subsidies, paid to the supplier against training 
of local technicians, yearly visits, users training, etc.; and 
• Indirect  market  development  subsidies  (aggressive  overall  promotion  activities, 
support  to  the  formulation  of  business  development  strategies,  training  and 
technical assistance), as well as the benefits from ERTIC central TA activities. 
It is important to note that the planned payment of OBA subsidies over a medium term 
period  are against  installation  and  basic  service  performance  targets  and  do  not  cover 
replacement costs (which are not be subsidized in any way, except for the replacement 
of the first battery). The same applies to any irregular service visits ‘on demand’ that the 
user  might  require,  as  long  as  they  don’t  result  from  system  failures  under  the 
operator’s responsibility. 
4.2.1 Results 
The  fact  that  the  program  has  been  recently  implemented  makes  the  assessment  and 
proper  analysis  of  the  results  difficult,  not  only  in  terms  of  SHSs  installed  but  on  the 
evolution and fulfillment of the additional objectives of the program. 
Exhibit 3 shows the evolution of SHSs installed under the program. As can be seen, after 
a slow start during the first six months of program implementation, the number of new 
customers has significantly increased, reaching 2,700 in the first eighteen months.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  349
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 3: IDTR Program SHS Connections 

3,000 500

450
2,500
400

350
Cummulative Total

New Connections
2,000
300

1,500 250

200
1,000
150

100
500
50

0 0
may-06

ene-07

mar-07

may-07
abr-06

jun-06

ago-06

sep-06

feb-07
oct-06

nov-06

abr-07

jun-07

ago-07

sep-07
jul-06

jul-07
dic-06

Monthly SHS Installed Cummulative SHS installed


 
4.3 Cambodia: Isolated Privately Operated Mini­grids 
In Cambodia, many small private firms operate isolated mini‐grids, providing electricity 
services  to  hundreds  of  residential  customers  and  small  companies.  These  firms, 
informal and spontaneous, known as ‘Rural Electrification Companies’ (REC), are not the 
result of any formal governmental program; they exist simply because there are people 
willing  to  pay  for  electricity  and  others  able  to  sell  it.  Unfortunately,  these  RECs  have 
faced a number of challenges, such as: 
• Increasing numbers of residential customers, 
• Demand for increasing the number of service hours, and 
• Improvements required in the distribution infrastructure. 
In  order  to  overcome  these  issues,  RECs  need  capital  or  access  to  credit  lines,  which 
most  do  not  have.  Where  credit  is  available,  interest  rates  are  usually  high  (20%  or 
higher) and additional collateral requirements stringent. In order to help overcome such 
financing  difficulties,  the  Cambodian  government  has  created  a  Rural  Electrification 
Fund (REF) with the objective of providing subsidies and technical assistance to RECs. 
An  illustrative  example  is  provided  by  an  REC  located  in  the  village  of  Smau  Khney.  In 
2004,  GRET,  a  French  NGO,  developed  a  form of  decentralized  regulation  for  this  REC.  
The regulatory arrangement is based on a 15‐year ‘contract of power supply’ between 
the  Commune  Electrification  Committee  (a  local  government  unit)  and  a  local  private 
developer  living  in  the  village.  The  power  supply  contract  is  supported  by  a  second 
contract  between  GRET  and  the  Commune  Electrification  Committee  that  provides  a 
US$ 45  grant  for  each  new  household  that  is  connected  as  either  a  metered  or  non‐
metered  customer.  This  arrangement  has  effectively  led  to  a  sharing  of  regulatory 
responsibilities  between  the  Electricity  Authority  of  Cambodia  (EAC),  the  national 
electricity regulator, and the commune government. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  350
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The principal obligations and requirements in the power supply contract are: 
• Technical engineering requirements (for example, grounding, types of poles, and 
distance between poles and cables). 
• Location of meters. 
• Responsibility for meters that are intentionally broken or tampered with. 
• Number of new customers to be connected. 
• Limit on time to connect new customers. 
• Amount of the capital cost subsidy (US$ 45 per household). 
• Connection and reconnection rules for customers. 
• Duration of service on weekdays (6 hours) and weekends (11 hours). 
• Subsidized tariff for poor households (US$ 1.20 per 10 watt lamp per month). 
• Duration of the contract (15 years). 
• A local system for handling complaints. 
• Funding of subsidies for poor customers and the administrative expenses of the 
Commune Electrification Committee through an annual US$ 5 fee per household. 
The  contract  is  as  an  example  of  ‘regulation  by  contract’,  since  it  includes  engineering 
requirements that affect technical quality of service (quality of the conductors, distance 
between  poles,  and  minimum  voltage  levels  at  different  locations  on  the  distribution 
grid)  and  economic  requirements  that  affect  commercial  quality  of  service  (hours  of 
service and tariffs for poor households). In addition, it specifies the actual tariffs to be 
paid by poor households.  
However, the contract does not completely replace the regulator, as it includes two very 
specific  disclaimers  that  state  that  both  tariffs  and  general  conditions  of  service  will 
simply  reflect  the  decisions  of  the  EAC.  Therefore,  the  contract  can  be  viewed  as  an 
example  of  a  partial,  downward  delegation  of  regulatory  responsibilities  to  the 
community organization  that  represents  the  interests  of  the  final consumers.  It  clearly 
does not eliminate regulation by the EAC, since the REC is still required to get a license 
from  the  EAC.  However,  the  power  supply  and  incentive  contracts  complement  and 
particularize the EAC’s more general regulatory rules. 
4.3.1 Results 
The program has been successful in that 220 new households have been connected in 
slightly more than a year, average monthly consumption is reported to have increased 
from 8 to 16 kWh, and the developer has plans to install more generation capacity. 
This  sharing  of  regulation  for  an  isolated  mini‐grid  appears  to  produce  at  least  three 
major benefits. 
• First,  the  village  government  became  an  active  agent  in  the  process  because  it 
directly  negotiated  the  contract  with  the  local  developer.  Consequently,  the 
village  government  views  itself  as  responsible  for  ensuring  that  the  developer 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  351
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

complies  with  the  terms  and  conditions  of  the  supply  contract.  This  is  quite 
different from relying on a regulator in the capital to administer a license whose 
terms  and  conditions  may  be  unknown  to  the  village  and  largely  beyond  its 
control. The fact that the village negotiated the contract gives it a greater stake 
in the success of the enterprise.  
• Second, the village government can assist in monitoring compliance with quality‐
of‐service standards. It is easy for a national regulator to issue quality standards 
for decentralized energy service providers. However, it is difficult and expensive 
for a national regulator to actually monitor whether the providers in distant and 
isolated  villages  are  actually  complying  with  the  standards.  If  a  village 
government  is  actively  involved,  it  can  act  as  the  regulator’s  ‘eyes  and  ears’  at 
the  local  level.  This  is  likely  to  be  more  effective  and  less  costly  than  if  the 
regulator  were  to  try  to  maintain  a  large  compliance  staff  in  the  capital  that 
would  need  to  make  numerous  field  trips  to  villages  around  the  country. 
However, if the village government is going to perform the monitoring function, 
it  will  need  resources.  In  Smau  Khney,  the  power  supply  contract  requires  that 
the  private  operator  provide  the  Commune  Electrification  Committee  with  an 
annual budget of about US$ 200.  
• Third,  it  allows  communities  to  act  as  ‘monitors’,  rather  than  ‘operators’. 
Collective  decision‐making  is  always  slower  than  individual  decision‐making. 
Moreover,  committees  and  boards  are  susceptible  to  personality  and  political 
conflicts.  This  is  not  to  say  that  it  is  impossible  for  a  community  to  own  and 
operate  a  mini‐grid  system  or  buy  in  bulk  from  the  main  grid.  There  are 
successful  examples  in  Bangladesh,  Costa  Rica,  and  the  Philippines,  among 
others. But if a community‐based organization, whether a cooperative or village 
electrification committee, is to be successful, it often requires considerable time 
and nurturing. Therefore, in many countries, it may be more efficient to limit the 
role  of  the  community  to  that  of  a  regulatory  monitor  rather  than  a  system 
operator. 
Although  the  sharing  of  regulation  between  the  national  and  regional  regulator  can 
produce these benefits, it may also produce costs. The biggest danger is that there will 
be  overregulation.  The  combination  of  national  and  local  regulation  could  lead  to  too 
many  requirements,  which  may  conflict,  and  too  many  approvals,  which  may  cause 
delays.  In  general,  this  does  not  appear  to  have  been  the  case  in  Smau  Khney.  The 
national regulator reviewed the ‘supply contract’ to ensure that it did not conflict with 
the license that it had issued.  

4.4 Chile: The PER Program 
With the aim of providing electricity services to rural customers, the Chilean government 
launched its Rural Electrification Program (PER) in 1994. The program basically provides 
subsidies to transmission grid extensions to areas in which the DISCO’s internal rate of 
return (IRR) is negative but the cost‐benefit analysis yields a positive rate of return.8  

                                                       
8
  The benefit for the society as a whole increases with the development of the project. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  352
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The main basis of the program can be summarized as follows: 
• The  government  subsidizes  projects  with  positive  social  rate  of  return  but 
negative DISCO’s IRR. 
• Projects  must  be  co‐financed  between  the  government,  the  DISCO,  and  the 
prospective customers. 
• The  investment  program  decision  is  decentralized.  Every  region  (province)  has 
full  legal  authority  to  decide  where,  how,  and  how  much  to  invest  in  rural 
electrification projects. 
• Governmental subsidy is only directed to investments (up to 100%); no subsidy is 
granted for operation or maintenance. 
• Operation  and  maintenance  cost  must  be  recovered  from  customers  through  a 
tariff. 
• The  owners  of  the  infrastructure  can  be  individual  customers,  a  cooperative,  a 
municipal government, or a DISCO. 
The regulator (Comisión Nacional de Energía, or CNE) is responsible for the coordination 
of PER. Regarding this program, its mission is to: 
• Define the goals and the main strategic lines of the program; 
• Supervise its fulfillment in coordination with regional governments; 
• Distribute the annual provision for rural electricity projects to various regions in 
accordance with the national budgetary stipulations; 
• Help  elaborate  technical  studies  for  rural  electrification  projects,  in  particular, 
those  related  to  the  deployment  of  renewable  energy  in  isolated  communities; 
and 
• Seek  international  credit  lines  for  financing  rural  electrification  projects  and 
optimize the use of public funds for this purpose. 
4.4.1 Renewable Energy 
Since  2001,  the  national  government,  with  the  support  of  the  United  Nations‘  Global 
Environment  Fund  (GEF),  has  been  developing  a  program  to  promote  the  use  of 
renewable  energy  for  off‐grid  electrification,  such  as  mini‐and  microhydels,  solar 
photovoltaics  and  small‐scale  wind  generators.  SHSs  are  being  deployed  in  the  four 
northern  regions  in  isolated  rural  areas.  In  these  regions,  the  program  established 
training  courses  for  customers  as  well  as  cooperatives  and  microenterprises  for 
operation and maintenance purposes. In addition, the CNE, in coordination with regional 
and community governments, is carrying out technical and economical feasibility studies 
for  small‐scale  wind  and  hydel  projects.  During  2001,  a  pilot  project  was  developed  in 
Tac  Island  with  a  hybrid  wind‐diesel  system  that  provides  electricity  to  the  72 
households on the island.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  353
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

4.4.2 Results 
The PER has been very successful in several key aspects, such as service coverage. The 
PER allowed an increment in the national coverage of 37%—from 53% in 1992 to 90% in 
2005—as can be seen in Exhibit 4. 
The exhibit shows that seven regions have already achieved a 90% coverage ratio.9 The 
efforts made by IX Region of La Araucanía, which went from 23% coverage to 83%, are 
particularly  worth  remarking,  as  are  those  of  X  Region  of  Los  Lagos  that  increased  its 
coverage from 38% to 87% between 1992 and 2005. These regions represent the largest 
shares of rural and indigenous populations in the country. 

Exhibit 4: Regional Rural Electrification Coverage in Chile 
1992
2005
100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%
I II III IV V VI VII VIII IX X XI XII Reg
Met
Regions
 
4.5 India: The RGGVY Program 
During  2005,  the  Indian  government  launched  the  Rajiv  Gandhi  Grameen  Vidyutikaran 
Yojana  (RGGVY)  Program,  a  five‐year  program (that  merged  and  consolidated  all  other 
existing similar programs under its umbrella) to provide electricity service access to all 
villages and habitations in the country. To implement the program, the government of 
India developed a Rural Electrification Policy in August 2006.  
This policy sets the framework for the deployment of rural electricity across the country. 
To achieve this, the policy defined: 
• A Rural Electrification Plan, which has to be developed by state governments and 
details  the  electrification  delivery  mechanisms  considering,  inter  alia,  the 
available  methodologies,  environmental  norms,  fuel  availability,  number  of 
unelectrified households, distance to the grid, etc.  

                                                       
9
  II Region of Antofagasta, V Region of Valparaiso, VI Region of Libertador Bernardo O’Higgins, VII Region of Maule, 
VIII Region of Bio, XI Region of Aisén del General Carlos Ibáñez del Campo and the Metropolitan Region 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  354
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• Villages considered in the policy, including census villages and rural households 
below the poverty line. 
• The participation of private individuals and other non‐governmental institutions 
for the effective deployment of rural electrification in villages.  
• An  ‘electrified’  village  as  a  village  certified  by  the  Gram  Panchayat  confirming 
that: 
o Basic  electrification  infrastructure,  such  as  distribution  transformers  and 
distribution lines, is provided in the inhabited locality, as well as a minimum 
of one Dalit basti/hamlet, where it exists;  
o Electricity  is  provided  to  public  places  such  as  schools,  panchayat  office, 
health centers, dispensaries, community centers, etc.; and 
o The number of households electrified is at least 10% of the total number of 
households in the village. 
In addition, the policy defines the main goals to be achieved. These are: 
• To provide electricity access to all households by 2009; and 
• To assure quality and reliable power supply at reasonable rates. 
To achieve these goals, the RGGVY program develops a three‐basis project: 
• The construction of a Rural Electricity Distribution Backbone (REDB), with at least 
one 33/11 kV (or 66/11 kV) substation in each block. 
• The development of a Village Electrification Infrastructure (VEI), with at least one 
distribution transformer in each village/habitation. 
• The deployment of Decentralized Distribution Generation Systems (DDGS) where 
grid supply is not feasible or cost‐effective. 
REDB, VEI, and DDGS have also to fulfill the requirements of the agriculture and other 
activities  including  irrigation  pump  sets,  small  and  medium  industries,  cold  chains, 
healthcare and education, and ICT to facilitate the development of rural regions. 
In addition, the program presents other key features such as: 
• Rural  households  below  the  basic  poverty  line  (BPL)  get  100%  subsidy  on 
connection fee charges. 
• Central  government  provides  a  90%  capital  subsidy  for  the  overall  cost  of  the 
project. 
• A  franchise  program  is  developed  for  the  implementation  of  grid  expansion 
projects at the local level. These franchises can be awarded to private individuals, 
NGOs,  cooperatives,  community  associations,  etc.  The  design  of  the 
implementation  model  ensures  revenue  sustainability  to  the  franchise  for  its 
proper development and promotion. 
• A  conducive  environment  for  the  private  deployment  of  mini‐  and  micro‐grids. 
For  these  types  of  projects,  while  developed  by  private  individuals,  the  role  of 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  355
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

the  government  is  to  simplify  procedures  and  requirements  to  facilitate  and 
expedite installation. 
• No discrimination in hours of supply between rural and urban households. 
To  provide  support  and  coordination  in  the  program,  the  Rural  Electrification 
Corporation  Ltd.  (REC)  has  been  designated  as  the  nodal  agency  for  program 
implementation.  All  governmental  funds  for  the  program  are  channeled  through  REC 
which,  apart  from  the  capital  subsidy,  provides  the  remaining  funds  on  soft  terms.  In 
addition to its financial duties, REC also establishes the framework for implementation, 
including  the  formulation  of  technical  specifications,  procurement  and  bidding 
conditions,  guidelines  for  project  formulation,  field  appraisals,  and  concurrent 
monitoring. REC is also responsible for complete oversight on the program from concept 
to completion. 
To achieve these functions, REC has reached an agreement with NTPC (the largest power 
company  in  the  country),  PowerGrid  (central  transmission  company),  NHPC  (largest 
hydel  company  in  the  country),  and  DVC  (Damodar  Valley  Corporation)  to  make 
available  the  project  management  expertise  and  capabilities  of  these  organizations  to 
states  wishing  to  use  their  services.  States  may  choose  from  amongst  the  following 
options: 
• Project  formulation,  development,  and  implementation  involving  system 
planning,  design,  engineering,  and  procurement  of  goods  and  services  and 
construction/implementation/commissioning  of  the  projects  covered  under  the 
program. 
• Formulation and preparation of reports, project approvals, advisory support for 
procurement, project monitoring, and supervision of quality of work. 
• Project monitoring and supervision of quality of work during construction. 
In  addition  to  coordination  and  implementation  assistance  from  different  stakeholders 
at the national and state levels, the policy promotes the directly involvement of district 
committees.  This  participation  is  in  the  form  of  coordination  and  review  of  the 
electrification  process  in  their  respective  districts,  as  well  as  the  review  of  quality‐of‐
service standards attained and the promotion of energy efficiency and conservation. The 
policy  also  grants  the  possibility  to  state  governments  to  extend  the  role  and 
responsibilities of these committees. 
As previously mentioned, private involvement in the program is an important part of the 
Indian  off‐grid  electrification  development.  For  this  to  be  achieved,  the  provision  of 
transparent procedures is essential. 
4.5.1 Private Involvement  
In  India’s  Rural  Electrification  Policy,  the  participation  of  non‐governmental  agents  is 
acknowledged in two different forms:  
• First,  by  franchises,  which  is  the  proposed  model  in  the  methodology  for  the 
deployment  of  gird  expansion  electrification.  As  such,  they  are  the  responsible 
for the distribution of electricity within the village’s borders.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  356
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

The management of these rural distribution entities is developed by a franchisee 
institution.  These  institutions  can  be  non‐governmental  organizations  (NGOs), 
users’  associations,  cooperatives,  or  individual  entrepreneurs.  The  franchisee 
arrangements  may  be  for  systems  including  feeders  from  substations  or  from 
distribution  transformers.  Also,  they  must  entail  purchase  of  bulk  power  (input 
based)  and  operation  and  maintenance  of  the  distribution  infrastructure.  A 
franchisee  arrangement  is  not  a  revenue  model  per  se,  but  it  is  envisaged  as  a 
mechanism  to  ensure  that  commercial  losses  are  reduced,  energy  supplied  is 
billed  and  revenue  is  collected.    In  order  to  maintain  the  franchise’s  revenue 
sustainability,  a  bulk  supply  tariff  (BST)  is  determined  based  on  the  consumer 
mix,  the  prevailing  consumer  tariff,  and  a  likely  load.  This  BST  is  fully  factored 
into  de  submissions  of  the  state  utilities  to  the  State  Electricity  Regulatory 
Commissions  (SERCs)  for  their  respective  revenue  requirements  and  tariff 
determinations.  State  governments,  under  the  Electricity  Act,  are  required  to 
provide  the  requisite  subsidies  to  their  respective  state  utilities  if  they  require 
the tariff for any category of consumers to be lower than that determined by the 
SERC. 
• Second, for projects in isolated areas which are not envisaged to be connected by 
grid expansions, the policy allows private individuals to develop what the policy 
defines  as  ‘stand  alone’  systems.  These  systems  are  mini‐  and  micro‐grids  to 
provide electricity services in off‐grid locations. 
A person entering in this framework has the responsibility for the generation and 
distribution  of  power  in  the  target  village.  The  retail  electricity  tariffs  are  set 
based  on  mutual  agreement  between  the  developer  and  the  customers.  If  the 
developer receives any financial assistance and/or subsidy from the government 
(national or state) or from other agencies, it must be fully passed on to the final 
customers.  The  appropriate  state  commission  has  the  right  to  audit  the  tariff 
scheme  to  verify  the  appropriate  fulfillment  of  this  provision.  The  state 
governments are responsible for the implementation of simplified administrative 
procedures to facilitate the development of these small enterprises. In addition, 
institutional arrangements for backup services and technical support also have to 
be promoted. 
4.5.2 Results 
According  to  latest  available  information,  the  progress  of  the  RGGVY  Program  for 
projects  sanctioned  in  the  Xth  Plan  is  presented  in  Exhibit  5.  Even  though  the  data 
provided by the government shows substantial coverage, with more than 40,000 villages 
and  5,000,000  rural  (and  BPL)  households  electrified,  little  information  is  available  for 
comparison on important issues such as electrification costs per household, classification 
of projects according to applied technology, and so forth. 
However, the government has published estimations of its cost norms for the projects to 
be sanctioned in the XIth plan, and these are presented in Exhibit 6. 
 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  357
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 5: Progress of RGGVY Projects Sanctioned in India’s Xth Plan 
March 2008 
th
Sanctioned in X Plan Award Status Achievements
Projects

Villages
Unelectrified

Villages
Electrified

HH (Lakh)
Access to Rural

BPL HH (Lakh)
Connection to

(Mill. US$)
Sanctioned Cost

Awards

(Mill. US$)
Sanctioned Cost

(Mill. US$)
Award Cost

(Mill. US$)
Fund Disbursed

Villages
Unelectrified

Villages
Electrified

HH (Lakh)
Access to Rural

Certif. Received
Panchayat

BPL HH (Lakh)
Connections to
State

Andhra
17 0 21,623 31.66 21.14 162.04 17 162.04 162.04 92.23 5,614 10.25 8.33
Pradesh
Arunachal
2 237 321 0.07 0.04 10.83 50.57
Pradesh
Assam 3 903 1,746 1.91 1.49 39.51 3 39.51 47.53 26.50 84 175

Bihar 26 17,125 0 8.43 8.43 373.95 26 373.95 482.16 400.60 13,362 0.83 2,194 0.68

Chattisgarh 3 117 3,504 2.70 1.22 37.24 3 37.24 39.77 26.01 296 0.15 0.15

Gujarat 3 0 2,409 2.43 1.88 15.21 3 15.21 21.19 7.88 1,247 0.78 886 0.78

Haryana 4 0 1,075 1.17 0.49 12.12 4 12.12 17.81 9.43 15 0.07 0.07
Himachal
1 0 1,118 0.03 0.01 6.26 1 6.26 6.65 1.92 0.00 0.00
Pradesh
Jammu &
3 103 1,444 0.99 0.60 24.41 2 18.37 19.19 12.35 169 0.04 0.04
Kashmir
Jharkhand 13 8,727 4,379 14.70 9.42 319.30 13 319.29 431.15 222.29 1,259 619 0.03 0.03

Karnataka 17 49 21,152 13.20 6.32 93.85 17 93.85 160.44 121.22 47 17,463 4.25 47 3.75

Kerala 1 0 38 0.24 0.18 4.94 1 4.94 4.86 5.04 0.07 0.07


Madhya
8 115 9,653 5.66 3.11 98.90 8 98.90 133.09 65.72 15 50 0.01 0.01
Pradesh
...Continues 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  358
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

...Continued 
Projects Sanctioned in Xth Plan Award Status Achievements

Villages
Unelectrified

Villages
Electrified

HH (Lakh)
Access to Rural

BPL HH (Lakh)
Connection to

(Mill. US$)
Sanctioned Cost

Awards

(Mill. US$)
Sanctioned Cost

(Mill. US$)
Award Cost

(Mill. US$)
Fund Disbursed

Villages
Unelectrified

Villages
Electrified

HH (Lakh)
Access to Rural

Certif. Received
Panchayat

BPL HH (Lakh)
Connections to
State

Maharashtra 4 0 4,052 3.56 2.63 19.72 3 12.87 13.17 6.76 1,080 0.58 219 0.56

Manipur 2 186 270 0.25 0.14 16.02 1 11.68 17.24 4.64 36 13 0.01 0.01

Meghalaya 2 174 797 0.41 0.24 11.50 2 11.50 13.29 4.99

Mizoram 2 90 209 0.15 0.09 10.44 0.16

Nagaland 2 12 279 0.22 0.14 4.06 2 4.06 4.53 2.52

Orissa 4 2,602 4,637 5.99 3.35 108.53 4 108.53 110.28 60.77 0.00 0.00

Punjab 0.75

Rajasthan 25 1,705 15,608 10.09 7.00 113.31 25 113.31 128.09 81.07 1,628 8,419 4.38 793 2.55

Sikkim 2 16 158 0.10 0.04 6.53

Tamil Nadu 25.20

Tripura 1 48 72 0.21 0.13 4.90 0.27


Uttar
64 29,051 3,287 16.94 11.21 679.88 64 679.88 996.37 717.26 26,985 448 4.47 20,718 4.47
Pradesh
Uttarakhand 13 1,469 14,105 3.57 2.82 160.97 13 160.97 183.22 118.59 1,226 5,230 0.83 1,171 0.83

West Bengal 13 4,283 0 1.46 0.98 96.26 13 96.26 95.96 100.32 3,184 0.95 1,398 0.59

Total 235 67,012 111,936 126.14 83.10 2,430.63 225 2,380.72 3,088.00 2,165.04 47,826 40,838 27.70 27,426 22.92

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  359
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 6: India’s XIth Plan – Estimated Electrification Costs Norms for Villages 

Electrification Type Cost (US$)

Electrification of unelectrified village

In normal terrain 32,500

In hilly, tribal, desert areas 45,000

Intensive electrification of already electrified village

In normal terrain 10,000

In hilly, tribal, desert areas 15,000

Cost of electricity connection to BPL household 55

5 Recent Developments in Pakistan 
Annexure B of Pakistan’s short‐term RES‐E Policy10 provides a brief set of guidelines for 
the development of off‐grid small hydel projects, and contains some provisions for other 
RES‐E  technologies  as  well.  At  present,  there  is  no  other  policy  for  off‐grid  electricity 
investments  and  the  lack  of  a  documented  off‐grid  electrification  strategy  creates 
confusion amongst stakeholders which, in turns, greatly affects the development of rural 
electrification.    Traditionally,  however,  an  aggressive  rural  electrification  program  has 
been pursued by the Government of Pakistan primarily through direct edit to the state‐
owned  power  utility  for  grid  extensions  and  some  public  investments  in  isolated  grids 
and  generation  based  on  diesel  and  small  hydels,  with  little  or  no  private  sector  or 
community involvement. 
Currently, there also does not exist a formal definition of the off‐grid areas11, nor has the 
isolated/scattered  population  been  properly  delimited  for  which  grid  extension  would 
be  uneconomical  into  the  foreseeable  future.12  This  is  an  essential  first  step  for 
designing  any  rural  electrification  project  as  a  means  for  fully  understanding  the  key 
characteristics  of  the  unelectrified  villages  assessing  the  deployment  of  suitable 
generation technologies.  
In addition, the guidelines stated in Annexure B of the 2006 RES‐E Policy assign identical 
roles  to  the  AEDB,  provincial,  and  AJK  governments  for  RE  implementation.  This  is 
counterproductive,  as  it  creates  a  duplication  of  tasks  amongst  national  and  provincial 
institutions, as well as potential conflicts of interest and coordination problems between 
the different stakeholders involved.  

                                                       
10
  Policy for Development of Renewable Energy for Power Generation, 2006, Alternative Energy Development Board 
(AEDB), Ministry of Water and Power, Islamabad, December 2006. 
11
  However,  any  project  feeding  power  to  national/regional  grid  at  11  kV  or  above  can  be  defined  as  an  ‘on‐grid’ 
project.  
12
  However,  for  practical  purposes,  communities  living  more  than  20  km  beyond  the  existing  grid  network  can  be 
considered isolated/scattered populations. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  360
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Even though precise data are unavailable, it is estimated that until 2006, approximately 
40,000  villages  in  Pakistan  lacked  electricity  services.  In  the  southern  province  of 
Balochistan,  as  much  as  90%  of  the  villages  do  not  have  access  to  grid  power  and  are 
widely dispersed, with an average population density as low as 22 inhabitants/km2. 
Several projects have been initiated by the federal government in Pakistan with different 
outcomes.  The  Alternative  Energy  Development  Board  (AEDB)  has  been  actively 
participating  in  such  efforts,  with  the  promotion  of  stand‐alone  SHS  (Sindh  and 
Balochistan) as well as micro and mini‐hydel projects (AJK, Punjab and NWFP). Probably, 
the most ambitious project was the Khushal Pakistan program launched in 2001, which 
envisaged  100%  electricity  coverage  by  the  end  of  2007,  a  target  which  was  definitely 
not accomplished. 
Currently, the most active project, in terms of rural electrification, is the Roshan Pakistan 
program.  The  objective  is  to  provide  electrification  services  to  7,874  isolated  villages: 
6,968  towns  are  located  in  the  Balochistan  province  alone,  while  the  400  remaining 
belong to the Sindh province. In terms of socioeconomic outputs, the program aims to 
improve the standard of living in these communities by providing access to lighting, ICT, 
and drinking water, and, by displacing fossil fuels for lightning, better health conditions.  

5.1 Roshan Pakistan Program 
The  AEDB  is  heading  this  project  and  is  responsible  for  its  overall  planning  and 
implementation.  In  addition,  provincial  governments  are  highly  involved  in  several 
aspects,  such  as,  village  selection,  on‐site  implementation,  and  operation  and 
maintenance services. Private companies are involved in:  
• Supply and installation of SHS systems, 
• Operation and maintenance services (only during the first year), 
• Training of operators, and 
• Providing user information. 
The AEDB has selected solar photovoltaic panels as the technology to be deployed, with 
systems  of  varying  sizes  according  to  users’  needs.  The  federal  government  provides 
capital  investment  subsidies  according  to  criteria  based  on  household  members  and 
dwelling size. Fees paid by customers are proportional to the chosen system capacity.  
In  its  first  phase,  the  program  is  expected  to  provide  SHSs  to  400  villages  (300  in 
Balochistan and 100 in Sindh) and it is expected to be completed during 2009.  
The  federal  government  is  providing  subsidies  for  capital  investments  (see  Exhibit  7), 
with  the  amounts  varying  according  to  the  number  of  occupants  and  rooms  in  the 
dwelling. The users pay only for the operating and maintenance costs. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  361
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 7: Roshan Pakistan Rural Electrification Program Budget 
Million Pakistan Rupees 

Approved 2006-2007 2007-2008 2008-09


Province Project
Budget Allocated Utilized Allocated Utilized Requested

Balochistan 887.718 20.674 20.674 135.000 34.524 366.030

Sindh 280.042 79.326 79.326 115.000 65.476 85.716

Total 1,167.760 100.000 100.000 250.000 100.000 451.746

According to the program baseline, users will pay for energy services (‘fee‐for‐service’) 
to cover operation and maintenance (O&M) costs. O&M will be carried out by operators 
based in villages and trained for this purpose. In addition, local operators will be backed 
by  private  companies  through  training  courses  and  equipment  maintenance  contracts 
during the first year.13 The selection of private companies is done through a tendering 
process.  
In  our  view,  this  program  is  generally  well‐designed  but  has  some  drawbacks,  such  as 
the lack of service provision (O&M) for a reasonable period, while the time required for 
new connections is too long. In the following section, we propose a mechanism that tries 
to  overcome  the  shortcomings  of  this  program  but  it  is  otherwise  based  on  the  same 
principles. 

6 Quantitative Assessment of RES­E Deployment 
The purpose of this section is to analyze different alternatives of off‐grid electrification 
technologies in order to provide a framework for a discussion on the targets and costs of 
implementation of the proposed off‐grid RES‐E policy for Pakistan. 
Lack  of  sufficiently  detailed  information  regarding  presently  unelectrified  villages  and 
scattered populations hampers the possibility of developing an in‐depth analysis on total 
deployment  costs.  However,  we  believe  that  some  important  conclusions  regarding 
electrification costs can be drawn from the analysis presented below. 
For  developing  this  assessment  we  have  largely  relied  on  information  regarding  solar 
irradiation and wind speeds generated by the US National Renewable Energy Laboratory 
(NREL),  as  described  in  Annex  VII.  In  addition,  NREL’s  HOMER  software14  has  been 

                                                       
13
 From the second year onwards, the O&M is in charge of the provincial governments. 
14
  HOMER  is  a  computer  model  that  simplifies  the  task  of  evaluating  design  options  for  both  off‐grid  and  grid‐
connected  power  systems  for  remote,  standalone,  and  distributed  generation  (DG)  applications.  HOMER's 
optimization and sensitivity analysis algorithms allow evaluation of the economic and technical feasibility of a large 
number  of  technology  options  and  account  for  variation  in  technology  costs  and  energy  resource  availability. 
HOMER  can  be  used  to  model  both  conventional  and  renewable  energy  technologies.    HOMER  can  be  freely 
downloaded from www.nrel.gov/homer. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  362
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

employed for optimization purposes to simulate electrification deployment alternatives 
under different demand and supply scenarios in the country. 
Demand and supply specification for these simulations constitutes a paramount element 
in the cost assessment of policy implementation, as the electricity sector presents large 
economies of scale (on the demand side of the equation) and is highly dependent on the 
different  inputs  resources  employed  for  generation  purposes  (relative  scarcity  of  one 
input  or  fuel  with  respect  to  others  may  have  a  large  impact  on  electrification 
technology selection and associated costs).  
In order to overcome theses shortcoming, a set of different demand‐supply alternatives 
are evaluated to obtain a range of results which should allow a better understanding of 
the  impact  of  deploying  different  electrification  technologies  under  different  demand 
(villages’ sizes) scenarios.  
However, the application of this procedure does not entirely resolve the ‘availability of 
natural resources’ issue, as this relies on the specific geographical location of each target 
village.  To  work  out  this  aspect,  an  existing  representative  village  with  average  solar 
irradiation and wind speed incidence has been chosen as the base reference case.  
The  village  of  Kardh,  located  at  the  border  of  the  Balochistan‐Punjab  provinces,15  has 
been selected to serve this purpose. The main geospatial characteristics of the area are 
(see also Exhibit 8): 
• Average wind speed: 4.97 m/s 
• Average solar irradiation: 5.75 kW/h/d 
• Average clearness index: 65% 
• Altitude: 700 m above mean sea level. 

Exhibit 8: Solar and Wind Availability in Target Village Area 
Monthly Averages 
Solar Irradiation & Clearness Index Wind Speed

7
8 100%

7 90% 6
80%
6 5
70%
kWh/m2/d

5 60% 4
m/s

4 50%
3
3 40%
2
30%
2
20% 1
1 10%
0
0 0%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Wind Speed (m/s)

Daily Radiation (kWh/m2/d)


 
Clearness Index

Two  important  natural  resources  remain  to  be  assessed  for  this  prototypical  village, 
hydro  and  biomass  resources,  and  their  impact  on  rural  development  is  anything  but 

                                                       
15
  According to GST HOMER information, the village is located at 29o 5’ N, 69 o 6’ E.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  363
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

negligible.  However,  for  the  sake  of  simplicity  of  this  assessment  and  in  order  to 
maintain a conservative approach, some assumptions need to be established. 
• Hydro resources: A binary approach has been used for this resource: the water 
resource  either  exists  or  does  not;  however,  if  available,  stream  volumes  are 
assumed  to  always  be  sufficient  for  target  village  needs  on  annual  average 
basis,16 with larger villages representing larger stream flows. 
• Biomass resources: Several specific issues complicate the analysis of this RES: 
o Both  availability  and  energy  content  of  different  biomass  types  are 
characterized a large degree of variability.  
o Biomass presents a set of significant alternative uses to electricity generation. 
Biomass burned for cooking and/or heating is the most traditional one. Other 
options,  such  as  biogas  generation  for  cooking/heating  and  also  lightning 
(with the aggregated value of the fertilizer as a by‐product) are also possible.  
Biomass  is  also  a  valuable  industrial  input,  such  as  for  paper  and  board 
manufacture. 
o If biomass is used as a generation technology, a market for biomass should be 
created  to  ensure  the  long‐term  availability  of  the  resource  for  power 
generation.  
Therefore,  a  plausible  assumption  is  that  biomass  will  be  used  for  social  development 
and economic purposes through means other than for electrification, and will therefore 
not be considered in this assessment. 

6.1 Electricity Demand: Simulated Target Villages   
Economies of scale play a key role in the quantitative assessment of the electrification 
processes as their existence allow average electrification costs to be reduced.  
In  order  to  introduce  this  concept  into  the  analysis,  a  set  of  simulated  target 
communities  with  different  household  numbers—and  electricity  demand—has  been 
developed. Four types of settlements have been assumed: scattered households; small 
settlements (hamlets); small villages, and regular villages. 
Household numbers as well as electricity demand and references have been summarized 
in  Exhibit  9.  For  each  type  of  settlement,  an  average  hourly  load  curve  has  been 
designed to be employed by HOMER to optimize the generation mix.  

                                                       
16
  High stream flows during the monsoon period (from June to September) and low hydro values for the remaining 
months of the year. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  364
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 9: Main Characteristics of Simulated Target Villages 
Simulated Target Villages Characteristics

ƒ Small electricity demand, explained mainly by the substitution of candles


Scattered Population and oil lamps for LED or low consumption lighting plus the introduction of
(less than 25 households) other electricity devices, such as radio, small fan and B&W TV set.
ƒ Electricity demand is estimated at 485 Wh/d, with a peak load of 196 W.

ƒ Electricity demand is estimated for a small settlement with an average


Small Settlement number of 50 households, including a small shop.
(50 households) ƒ Electricity demand is estimated at 76 kWh/d, with a peak load of 10 kW.

ƒ Small set of houses, with an average number of 100, including a shope, a


rural school, and a small workshop.
Small Village
ƒ Electricity demand is estimated at 831 kWh/d, with a 100 kW peak power
(100 households)
demand.

ƒ Large set of houses, with an average number of 280, which includes a small
Village market, small school, dispensary, and other workshops.
(280 households) ƒ Electricity demand is estimated at 4.3 MWh/d, with a 500 kW peak load.

 
6.2 Electricity Supply: Generation Alternatives 
The size of the target villages’ electricity demand affects the selection of the generation 
technology to be deployed and, due to the existence of economies of scale, the cost of 
electrification.    For  every  type  of  village,  a  set  of  generation  technologies  have  been 
designed to provide electricity services. Generation technologies included in the analysis 
can be divided in five categories: batteries; diesel generators; mini/microhydels; solar PV 
panels; and mini/micro wind generators. 

Even though available generation technologies are the same for every type of village,17 
the generation capacity deployed for each technology would vary from village to village. 
Exhibit 10 summarizes the technologies and their costs employed in the optimization. 

Exhibit 10: Off‐grid Generation Technology Alternatives 

Technology Standalone Small Settlement Small Village Village

Tech: DC 6V 320 Ah
Battery Cost: US$ 340
O&M: US$ 10/yr

Tech: AC 5 kW Tech: AC 20 kW Tech: AC 50 kW


Diesel
N/A Cost: US$ 6,000 Cost: US$ 18,000 Cost: $28,000
Generator
O&M: US$ 0.2/hr O&M: US$ 0.5/hr O&M: US$ 0.8/hr

Tech: AC 10 kW Tech: AC 100 kW Tech: AC 500 kW


Hydel* N/A Cost: US$ 115,000 Cost: US$ 0.56 mill. Cost: US$1.7 mill.
O&M: US$ 45/yr O&M: US$ 1,400/yr O&M: US$ 7,200/yr

                                                       
17
  For  standalone  (isolated  household)  application,  diesel  and  hydel  have  not  been  considered  as  demand  in  these 
cases would be too small to justify such supply systems.   

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  365
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Technology Standalone Small Settlement Small Village Village

Tech: DC 1 kW
PV Cost: US$ 6,000
O&M: US$5/yr

Tech: DC 0.5 kW Tech: AC 2.5 kW Tech: AC 30 kW


Wind Cost: US$ 1,400 Cost: US$ 4,200 Cost: US$ 50,400
O&M: US$ 100/yr O&M: US$ 100/yr O&M: US$ 500/yr

* It is assumed that hydel projects are 1 km distant from the settlement. 

In addition to generation costs, there are other important parameters to be considered 
in the analysis, such as converter costs, fuel costs, project rate of return; project lifetime, 
and grid connection costs (see Exhibit 11). With respect to quality of service, a maximum 
of 5% of total annual capacity shortage has been set as standard target for all 
alternatives analyzed.  
All these parameters, excepting grid connection costs, were included in the optimization 
software runs. The exclusion of grid connection costs in the optimization process does 
not alter the order of merit of generation technologies, as it represents a fixed expense 
that affects all technologies by the same amount. 

Exhibit 11: Additional Simulation Input Parameters 

Small
Technology Standalone Small Village Village
Settlement

Converter Capacity: 1 kW; Cost: US$ 800; O&M: -

Fuel (Diesel) N/A Fuel price*: US$ 0.48/l

Connection cost: US$ 150/household


Grid Costs N/A
Hydel transmission line: US$ 3,500

Project Lifetime 25 years

Rate of Return 12% per year before taxes

Shortage Capacity 5% of total annual capacity

* Average diesel price, not including transportation costs to remote areas. 

6.3 Optimization Outcomes 
Exhibit 12 and Exhibit 13 present the results of the optimization process, including and 
excluding  hydro  resources,  respectively.  As  can  be  seen,  when  hydro  resources  are 
available, hydel generation becomes the optimum technology in small and large villages 
and provides the cheapest form of electrical energy. If hydro resources are not available, 
however,  then  a  hybrid  system  composed  of  wind  generators  plus  a  diesel  generator 
and batteries are the optimum solution to develop. 
Also, from the analysis of the results, it is clear how economies of scale affect the cost of 
electricity. The larger the settlement, the lower the cost of electricity, and therefore a 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  366
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

proper  analysis  of  target  villages  sizes  becomes  essential  for  choosing  the  cheapest 
generation source. 

6.4 Medium Term Off­grid Policy Deployment Costs 
Lastly,  as  a  rough  guideline  for  analyzing  the  cost  of  implementing  Pakistan’s  off‐grid 
RES‐E policy, let us assume that 7,400 villages still remain to be electrified at the end of 
the first phase of the Roshan Pakistan Program, and that the target of the medium term 
policy is to electrify 25% these—approximately 1,850 villages—using RE technologies.  
By  employing  information  from  the  last  country  census,  it  can  be  assumed  that  the 
distribution of unelectrified settlements can be segregated as follows: 
• Standalone: 30%  
• Small Settlements: 30% 
• Small Villages: 20% 
• Villages: 20% 

Exhibit 12: Off‐grid Electrification Deployment Simulation (Including Hydro Resources) 

Optimization Model Outcomes (Optimum Generation Mix)

User Type
First
Second Third Fourth Fifth
(Optimum)

PV+B W+B PV+W+B


Standalone IC: US$ 735 IC: US$ 1,485 IC: US$ 2,135 - -
CoE: 0.668 CoE: 1.82 CoE: 2.34

W+D+B PV+W+D+B PV+D+B W+D PV+D


Small
IC: US$ 486 IC: US$ 758 IC: US$ 506 IC: US$ 284 IC: US$ 472
Settlement
CoE: 0.414 CoE: 0.441 CoE: 0.490 CoE: 0.637 CoE: 0.684

H+B H+D H+W H+G+B H+W+B


Small
IC: US$ 5,788 IC: US$ 5,780 IC: US$ 6,104 IC: US$ 5,968 IC: US$ 6,292
Village
CoE: 0.266 CoE: 0.265 CoE: 0.280 CoE: 0.274 CoE: 0.289

H H+B H+W H+PV H+D


Village IC: US$ 6,071 IC: US$ 6,151 IC: US$ 6,251 IC: US$ 6,329 IC: US$ 6,171
CoE: 0.150 CoE: 0.153 CoE: 0.155 CoE: 0.157 CoE: 0.154
Note:  B: Batteries; D: Diesel; H: Hydel; PV: Photovoltaic; W: Wind; IC: Investment capital (per household); CoE: Levelized cost of electricity 
in US$/kWh. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  367
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Exhibit 13: Off‐grid Electrification Deployment Simulation (Excluding Hydro Resources) 

Optimization Model Outcomes (Optimum Generation Mix)

User Type
First
Second Third Fourth Fifth
(Optimum)

PV+B W+B PV+W+B


Standalone IC: $735 IC: $1,485 IC: $2,135 - -
CoE: 0.668 CoE: 1.82 CoE: 2.34

W+D+B PV+W+D+B PV+D+B W+D PV+D


Small
IC: $486 IC: $758 IC: $506 IC: $284 IC: $472
Settlement
CoE: 0.414 CoE: 0.441 CoE: 0.490 CoE: 0.637 CoE: 0.684

W+D+B W+D PV+W+D+B PV+D+B PV+D


Small
IC: $1,699 IC: $1,321 IC: $2,899 IC: $1,701 IC: $1,667
Village
CoE: 0.301 CoE: 0.318 CoE: 0.335 CoE: 0.346 CoE: 0.36

W+D+B PV+D+B PV+W+D+B W+D PV+D


Village IC: $904 IC: $985 IC: $1,333 IC: $2,198 IC: $929
CoE: 0.267 CoE: 0.272 CoE: 0.275 CoE: 0.283 CoE: 0.285
Note:  B: Batteries; D: Diesel; H: Hydel; PV: Photovoltaic; W: Wind; IC: Investment capital (per household); CoE: Levelized cost of electricity 
in US$/kWh. 

Only as a practical assumption—although no empirical evidence exists to support this—
let  us  assume  that  50%  of  the  simulated  villages  and  small  villages  possess  hydro 
resources and that all villages are to be electrified using the optimal technology mix. In 
such  a  scenario,  the  investment  cost  of  implementing  this  policy  would  be  US$ 519 
million dollars, as shown in Exhibit 14. 

Exhibit 14: Off‐grid Electrification Capital and Fuel Costs for 1,850 Villages 

Invested Fuel
Cost of Electricity
User Type Capital Expenditure
(US$/kWh)
(Mill. US$) (Mill. US$/year)

Standalone
5.7 0 0.668
(7,770 HH)

Small Settlement
13.5 1.8 0.414
(27,750 HH)

Small Village 0.266 (Hydel)


138.5 7.3
(370,000 HH) 0.301 (No hydel)

Village 0.150 (Hydel)


361.3 51.9
(1,036,000 HH) 0.267 (No hydel)

Total 519.0 61.0

As shown in Exhibit 14, deployment decision does not only depend on invested capital 
expenditures. Hybrid mini‐ and micro‐grids that include diesel generation are available 
at  small  capital  investment,  but  with  a  variable  cost  driven  by  fuel  consumption,  and 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  368
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

therefore  lead  to  higher  cost  of  electricity;  on  the  other  hand,  villages  with  hydro 
resources  available  face  larger  capital  investments  to  develop  hydel  projects,  but  are 
compensated by lower electricity costs subsequently. 
The estimated capital cost to electrify all the target 7,400 villages in Pakistan would be 
roughly four times this value, that is, approximately US$ 2.1 billion.  

7 Medium Term Off­grid RES­E Policy Recommendations 
7.1 Target Markets and Technologies 
For  the  purpose  of  Pakistan’s  medium  term  RES‐S  policy,  the  target  population  is  that 
living  in  off‐grid  villages  and  remote  scattered  households.  These  villages/scattered 
dwellings can be supplied electricity based on renewable sources of energy generation, 
either by stand‐alone or mini‐grid systems. RES‐E technologies included in this portfolio 
consist of, at a minimum: 
• Micro‐ or mini‐hydel 
• Hybrid  systems,  in  which  at  least  one  renewable  energy  source  is  employed 
besides conventional thermal generation 
• Solar PV and thermal 
• Micro‐ or mini‐wind systems  
• Bio‐energy resulting from anaerobic gas digesters, pyrolitic biomass gasification, 
and co‐generation. 
Any type of national and/or regional grid expansions is outside the scope of this policy, 
as  well  as  any  RE  project  that  plans  to  electrify  a  village  with  an  installed  generation 
capacity larger than 1 MW.18 
This policy is developed exclusively for off‐grid rural and isolated areas. These areas are 
defined  as  currently  unelectrified  villages  that  are  not  included  in  any  national  or 
regional grid expansion plan for the next ten years and are located beyond 20 km from 
the existing power grid. The AEDB, along with the distribution utilities, is responsible for 
elaborating  (and  properly  updating)  a  list  of  villages  falling  under  the  purview  of  this 
‘target’ definition, and this list should include at the very least: the name of the village 
and  province,  geospatial  coordinates,  number  of  inhabitants,  and  number  of 
households.  

7.2 Implementation Period 
The  implementation  period  of  this  policy  is  January  2010  to  December  2014,  as  we 
understand that incentive policies require at least five years to have an adequate chance 
to succeed, as previously recommended in Annex VIII.  

                                                       
18
  Covered separately under the on‐grid RES‐E Policy. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  369
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

7.3 Conceptual Approach 
In our approach, off‐grid electrification can be developed either: 
• Directly  by  provincial  and/or  local  governments  on  a  voluntary  basis  and/or 
driven by social players without recourse to national subsidies, or 
• Via  national‐provincial  coordination  in  which  provincial  governments  compete 
for federal government assistance to finance their off‐grid projects.  
Under the first mechanism, provincial governments are fully in charge of developing the 
electrification projects within their territorial jurisdiction. Each province may develop a 
simplified regime for off‐grid project deployment, following which bilateral agreements 
between the parties involved must be reached to enforce project implementation. These 
agreements are arranged solely by the relevant parties which decide on tariffs, quality of 
service, and other contractual terms. 
Under  the  second  alternative,  a  coordinated  plan  has  to  be  set  up  to  assign 
competences  to  the  different  parties  involved  in  order  to  maximize  their  operational 
potential  and  capabilities  for  achieving  effective  and  efficient  off‐grid  rural 
electrification.  The  main  characteristics  and  tasks  for  stakeholders  in  this  respect  are 
summarized in Exhibit 15. 

Exhibit 15: Proposed Federally Assisted Off‐grid RES‐E Deployment Approach 

Ministry of Water OGREA Budget


and Power Request

Assessment of
AEDB Off-grid National Off-grid Project Guidelines for
OGREA Settlem ent
Villages and Scattered Portfolio Managem ent Authorizations
Populations

Provincial Authorization
Governments Awarded Tendering Perform ance
Project Proposals Issuance and
(REAs) Projects Procedure Monitoring
Tariff Setting

Interested Priv.
Stakeholders Inverstors
NGOs Project Execution
Cooperatives
Individuals

 
As  can  be  seen  in  the  exhibit,  the  main  features  of  the  regulation  proposed  are  as 
follows: 
• The  AEDB  will  act  as  the  national  off‐grid  RES‐E  program  coordinator  and  will 
decide the allocation of national funds to different off‐grid electrification projects 
based on rules previously defined by the Government of Pakistan;  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  370
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• The AEDB will create and update, with the assistance of the power utilities and 
provincial governments, a complete assessment of the unelectrified villages and 
scattered communities able to be supplied by RES‐E technologies which shall be 
approved as the off‐grid electrification ‘target’ population for the medium term 
(2010‐2014) by the Federal Cabinet;19  

• Provincial  governments—through  their  respective  Rural  Electrification  Agency 


(REA)20—will be the key stakeholders for promoting off‐grid rural electrification 
within  their  provincial  borders.  Based  on  the  list  of  annual  target 
villages/populations  developed  by  them  in  collaboration  with  the  AEDB  and 
approved by the latter, each REA will prepare and submit to the AEDB a village‐
specific  electrification  project  in  which,  at  least,  the  following  aspects  shall  be 
covered: 
o Socioeconomic characteristic of target village/scattered population. 
o Study on power demand potential and projected supply. 
o Generation technology/ies to be deployed. 
o Number of households to be connected. 
o Implementation period. 
o Total  cost  of  the  project,  segregated  between  capital  and  operational 
expenditures. 
o Detailed cash flow projections for the project. 
o Social benefits due to project implementation. 
o Quality‐of‐service characteristics. 
• The  proposed  off‐grid  projects  should  not  strictly  focus  on  providing  electricity 
services  only.  It  is  highly  desirable  that  projects  should  include,  to  the  extent 
feasible,  domestic equipment,  water  installations,  and  or  any  other  facility  that 
could  help  to  improve  the  social  and  human  development  of  the  target 
village/scattered  population,  as  well  as  provide  for  their  maintenance  by 
qualified personal. 
• Each project must strictly comply with the guidelines proposed by the AEDB for 
proper  comparison,  benchmarking  and  analysis.  Therefore,  it  is  essential  that 
rules are set for this purpose in a clear and transparent manner. It should be the 
duty  of  the  AEDB  to  document  simplified  procedures  for  project  approval, 
including  criteria  for  ranking  the  projects  and  the  definition  of  the  parameters 
needed  to  obtain  comparable  project  proposals  (e.g.,  the  costs  of  different 
generation technologies).  

                                                       
19
  Any  village  and/or  scattered  population  not  included  in  the  approved  list  finalized  by  the  AEDB  will  be  excluded 
from the off‐grid electrification program and not be eligible for the provisions of the present policy. 
20
  Or any related agency/department designated as such by the provincial government for the development of all off‐
grid rural electrification projects in its territorial jurisdiction. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  371
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

• The  AEDB  will  collect  all  project  proposals  and  will  create  an  annual  project 
portfolio. This portfolio will be organized according to a merit order based solely 
on the social cost‐benefit analysis of the project.  
• Once  a  project  has  been  awarded  by  the  AEDB,  the  relevant  provincial 
government will call for tenders for granting, at least, a 10‐year Authorization to 
develop off‐grid electricity services following technology specifications stated in 
the  electrification  project.  If  convenient  (i.e.,  for  proximate  villages),  several 
projects may be combined for tendering under a single authorization. 
• The primary criterion for selecting the winning bid for each Authorization will be 
‘least subsidy’ demanded for capital investments for electrification/installation. 
• All  types  of  stakeholders  (cooperatives,  NGOs,  private  individuals,  and  private 
companies) would be eligible to participate in the tender process if they meet a 
minimum set of technical qualifications to be defined by provincial REAs with the 
guidance of the AEDB. 
• The  AEDB  will  define  the  standard  Authorization  template  that  the  REAs  will 
apply  to  specific  project  tenders.  In  the  Authorization,  at  a  minimum  the 
following contents would be included: 
o Schedule for electrification. 
o Rights and obligations of the parties. 
o Applicable tariffs. 
o Milestones for subsidy delivery. 
o Quality‐of‐service  regulation,  including  standards  adjusted  for  each 
technology and fines for non‐compliance. 
o Community  capacity‐building  (provision  of  technical  training  and  other 
incentives to promote the regional development of the area). 
o Conditions for termination of the Authorization. 

7.4 Targets and Incentives 
Under the proposed medium term off‐grid RES‐E policy, at least, 25% of the off‐grid non‐
electrified  villages  identified  by  the  AEDB  should  be  supplied  with  electricity  by 
December 31, 2014. In order to achieve this target, the federal government will provide 
subsidies for capital investments to the extent of 70% of the total investment required 
for the RES‐E project approved by the AEDB. 
The AEDB will approve projects according to a merit order based on social cost‐benefit 
analysis. The social cost‐benefit analysis should consider: 
• The subsidy requirement (total and as a share of total cost). 
• The population involved. 
• The  economic  development  benefits  evaluated  on  the  basis  of  contribution  to 
economic  output  and  growth,  including  direct  and  indirect  economic  costs  and 
benefits.  Included,  in  this  respect,  should  be  the  expected  improvement  in,  for 
instance,  water  sanitation,  education,  health,  gender  issues,  employment, 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  372
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

incomes,  and  other  sustainable  and  human  development  indicators  of  the 
community—instead of just kWh supplied. 
• The HSE (health, safety, and environment) performance aspects of the projects. 
The remaining capital and O&M costs, including replacement costs, would be financed 
by: 
• The respective REAs, employing provincial funds. 
• The  tariffs  for  the  off‐grid  services  defined  by  the  provincial  REA,  taking  into 
account the customers’ ability to pay. 
• Community  contribution  to  such  schemes  may  be  in  the  form  of  sweat  equity 
(labor), land, and/or cash. 
• NGO contributions. 
As subsidies are provided, they should be limited to the amounts needed for basic social 
and  human  needs,  including  basic  economic  activities.  Some  consumers  may  want  to 
pay more for higher levels of electricity service, such as more kWhs received and better 
quality  of  service.  In  that  case,  the  extra  quality  and  quantity  must  be  paid  for  by  the 
customer as per provisions in the bilateral agreement with the service provider. 

7.5 Project Funding  
In order to provide funding to off‐grid projects, an Off‐grid Rural Electrification Account 
(OGREA) in the budget for the AEDB should be created. This account could be financed 
by: 
• Government  budgetary  allocations.  The  request  for  funds  to  the  Ministry  of 
Finance  will  be  made  by  the  Ministry  of  Water  and  Power  as  estimated  by  the 
AEDB/REAs according to the needs imposed by the off‐grid electrification project 
targets, and 
• Grants  and  loans  that  multilateral/bilateral  financing  and  donor  agencies  may 
provide. 
The OGREA settlement is an attribute restricted solely to the AEDB. Once projects have 
been  awarded,  tender  procedures  will  direct  the  transfer  to  the  respective  REAs. 
Delivery  of  subsidies  should  be  output‐based  and  only  related  to  capital  expenditures. 
The REAs directly or the through the local government will monitor the fulfillment of the 
milestones  defined  in  the  Authorization  in  terms  of  investment,  and  ask  the  AEDB  for 
subsidy  delivery  in  the  form  of  funds  transferred  directly  to  the  holder  of  the 
Authorization. The AEDB may develop spot monitoring of the projects in order to cross‐
check the use of these national subsidies.  
Additionally,  the  government—through  state‐owned  banks—will  provide  financing 
facilities  at  preferential  rates,  collateralized  by  the  future  stream  of  subsidy  deliveries 
defined in the Authorization. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  373
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

7.6 Pricing 
The  level  and  structure  of  the  service  tariff  will  be  the  sole  responsibility  of  the 
provincial  governments,  to  be  developed  in  cooperation  with  local  governments.  The 
REAs  will  define  the  tariff  structure  for  each  Authorization  according  to  the  following 
criteria: 
• Tariffs may be technology‐wise differentiated. 
• In stand‐alone systems, a one‐part tariff (Rs/customer) should be preferred. 
• In  community  (mini‐  and  micro‐grids)  system,  a  one‐part  tariff  based  on  the 
contracted  capacity  (Rs/kW‐contracted)  should  be  preferred.  In  these  systems, 
each customer will have a power limiter installed in order to disconnect him/her 
if the contracted capacity is exceeded. 
• In those cases in which the customer is willing to pay for a higher quality or more 
energy than required for basic needs, a metering device may be installed. 
• Tariffs may be only indexed to local inflation. 

7.7 Incentives Other Than Tariffs 
As  stated  in  Annex  VIII,  the  consultants  believe  that  the  current  general  financial  and 
fiscal incentives, as defined in the 2006 on‐grid RES‐E Policy, are adequate and should be 
continued  into  the  medium  term  as  well  and  extended  to  off‐grid  RES‐E  investors. 
Additional facilities and incentives may be provided to encourage the local manufacture 
of  RES‐E  technologies,  with  a  view  to  bringing  their  costs  down  and  improving 
availability of spares and local service and maintenance capabilities. It is not considered 
necessary to issue sovereign risk guarantees for these types of projects, however. 

7.8 Roles of Institutions 
In the medium term off‐grid RES‐E policy, we do recommend a greater involvement of 
provincial institutions, as international experience shows positive results in off‐grid rural 
electrification  deployment  when  regional  and  local  governments  actively  participate  in 
the  decision‐making  and  implementation  process.  According  to  this  view,  provincial 
governments should be directly involved in the activity of providing electricity services to 
inhabitants  living  in  scattered/isolated  regions.  Local  stakeholders  should  also  have  an 
active role in the process as a means to enhancing community acceptance and ensuring 
successful deployment and operation. 
The AEDB would play a key role in off‐grid electrification development as it is not only 
the main coordinator of the process at the national level, but will also  be in charge of 
setting  guidelines  for  project  formulation,  implementation,  and  financing.  Additionally, 
the  AEDB  will  elaborate  the  list  of  off‐grid  villages  and  scattered  population  to  be 
supplied by off‐grid RES‐E solutions updated on an annual basis. 
The  Ministry  of  Water  and  power  will  define  the  budget  request  for  the  OGREA.  In 
addition,  the  Ministry  will  provide  all  the  necessary  means  to  assure  that  the  fund  is 
created and properly managed.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  374
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

In  Exhibit  16,  a  summary  is  provided  of  the  proposed  roles  for  each  of  the  relevant 
institutions involved. 

7.9 Institutional, Legal and Regulatory Consents 
The  broad  division  of  institutional  responsibilities  proposed  for  off‐grid  RES‐E 
deployment in Pakistan is shown in Exhibit 16. 
Regulatory consents and processing requirements for off‐grid RES‐E services should be 
simplified  to  the  extent  possible,  so  as  to  enable  and  expedite  the  development  of 
projects  and  enable  small  communities  and  investors  to  participate  fully  in  these 
schemes.  Due  to  the  characteristics  of  the  proposed  arrangements,  no  regulatory  or 
operational consents by NEPRA and NTDC/DISCOs are envisaged for such projects. 

Exhibit 16: Summary of Roles of Institutions in Off‐grid RES‐E Deployment 

Institution Main Role

Ministry of Water and • Define budget request for Off-grid Rural


Power Electrification Account (OGREA)

Alternative Energy • Develop demonstration programs and projects for off-


Development Board grid RE
(AEDB) • Promote local manufacturing
• Create awareness and facilitate technology transfer
• Channel international assistance
• Program coordinator
• Set parameters for project cost-benefit analyses
• Decide on projects’ merit order
• OGREA management and issue payment order for
approved projects
• Develop standard authorizations

National Electric Power • None


Regulatory Authority
(NEPRA)

Pakistan Council for • Foster R&D and technology development relevant to


Renewable Energy renewable energy, in coordination with the AEDB
Technologies
(PCRET)

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  375
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

Institution Main Role

Provincial and AJK • Support the implementation of renewable energy


Agencies projects in close coordination with the AEDB
• Facilitate allocation of land use, water rights, and
environmental permitting
• Create awareness of RE amongst end users and
customers
• Remove any other local impediments which may hinder
RE development in a province
• Create provincial Rural Electrification Agencies
REAs)
• Decide on renewable generation technology to be
implemented in each project.
• Elaborate project cost-benefit analysis based on
parameters previously set by the AEDB.
• Cofinance approved rural electrification projects.
• Call for tender process for construction/operation
of each awarded project.
• Set tariff for off-grid services and monitor
performance

WAPDA or CPPA • None


(as purchasing entity)

Power Utilities • None


(NTDC, KESC, & DISCOs as
networks operators)

In relation to the AEDB consents, our proposal is to eliminate the Letter of Intent (LoI), 
Letter of Support (LoS), and related guarantees that are required for on‐grid RE projects. 
The  only  consents  that  should  be  necessary  is  the  Project  Information  Memorandum 
(PIM) for each project, which would include all technical and economic features of the 
project.  This  is  the  information  that  the  AEDB  will  utilize  to  develop  the  national 
portfolio of off‐grid RES‐E projects and develop the ranking for subsidy delivery. In case 
the  project  does  not  require  national  funding  support,  this  consent  will  also  not  be 
required. 
Concerning  environmental  issues,  we  propose  that  the  federal  and  provincial 
Environmental  Protection  Agencies  (EPAs)  remove  the  requirement  of  an  Initial 
Environmental  Examination  (IEE)  for  off‐grid  RES‐E  projects  of  up  to  1  MW  capacity. 
However, a basic environmental compliance and impact checklist will be developed by 
the EPAs and required to be completed by the provincial REAs for all projects, primarily 
to  ensure  that  water  rights,  flows,  and  community  interests  are  not  unduly  infringed 
upon.  Additionally,  as  a  condition  of  the  Authorization,  the  project  developer  should 
certify  how  proper  design,  engineering,  construction,  and  safety  criteria  will  be 
addressed in the execution of the project. 
The most important consent that would be required is the Authorization issued by the 
REAs on behalf of provincial governments.  

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  376
Asian Development Bank  Formulation of Pakistan’s Medium Term Renewable Energy Policy 
TA 4881‐PAK: Final Report  for On‐grid and Off‐grid Areas 

7.10 Performance Monitoring and Enforcement 
Project performance must be monitored, but in a light‐handed manner in order to avoid 
huge regulation costs. The monitoring process has two main parts: 
• Investment  plan  monitoring:  This  involves  verification  of  the  investment 
milestones defined in the Authorization being reached, as a trigger for the AEDB 
to release subsidy payments. 
• Ongoing  performance  monitoring  for  the  duration  of  the  Authorization:  This 
involves  monitoring  that  service  quality  standards  defined  in  the  Authorization 
are  met  throughout  its  period  of  validity.  The  regulator  should  establish 
standards  for  product  quality,  service  quality,  and  commercial  quality.  Product 
quality  includes  stability  of  voltage  and  stability  of  frequency  relative  to 
benchmark  reference  levels.  Service  quality  includes  targeted  hours  of  service, 
number  and  duration  of  interruptions,  and  safety  of  the  system.  Commercial 
quality  includes  connection,  accuracy  in  meter  readings  (for  customers  whose 
service requires meter reading), accuracy in billing, and response time to resolve 
customer  complaints.  It  should  be  note  that  fewer  standards  that  can  be 
effectively  monitored  are  preferable  to  many  standards  that  are  poorly 
monitored. 
Performance  monitoring  and  enforcement  will  be  the  responsibility  of  the  provincial 
REAs.  REAs  should  consider  a  more  flexible  approach  than  the  traditional  role  of  the 
regulator  in  monitoring  quality,  given  that  because  of  the  dispersed,  small  size,  and 
often isolated location of these electrification projects, the cost of an active regulation 
may be a huge burden. The REAs should develop a program of awareness amongst their 
customers  and  other  community  stakeholders  to  foster  the  direct  monitoring  of  the 
service provider. The monitoring should be based on customers’ (or other stakeholders’) 
claims. 

7.11 Allocation of Carbon Credits  
It is considered logical, as well as administratively simpler, for RES‐E investors to assume 
the  risks  and  benefits  of  qualifying  for  and  obtaining  CERs,  along  with  the  potential 
revenues  associated  with  them.    However,  the  AEDB  could  assist  project  developers 
applying  for  CDM  registration  through  programmatic  or  clustered,  single‐umbrella 
application  cover.    In  such  cases,  cost  and  revenue  sharing  arrangements  can  be 
developed subsequently, as necessary. 

Hagler Bailly Pakistan | Mercados EMI


R9FR1PRP ‐ FINAL REPORT: 11/03/09  377
ADB TA 4881­PAK: 
Renewable Energy Policy Formulation and Capacity Development of AEDB 

Final Report 

AEDB’s Capacity Assessment and 
Institutional Needs 

Hagler Bailly Pakistan

and

Mercados EMI, Spain 

 
Asian Development Bank
Manila
 

Final Report 

AEDB’s Capacity Assessment and 
Institutional Needs 

Contents 

Appendices .................................................................................................................. iii 
Exhibits ........................................................................................................................ iv 
Abbreviations and Acronyms ........................................................................................ v 
1  Objective .................................................................................................................. 1 
2  Situation Analysis ..................................................................................................... 3 
2.1  Background to RE Deployment in Pakistan ........................................................... 3 
2.1.1  Potential, Targets, and Achievements....................................................... 3 
2.1.2  Institutional, Legal, and Regulatory Landscape ......................................... 5 
2.2  Establishment and Development of the AEDB ...................................................... 6 
2.3  Performance Issues ............................................................................................... 7 
3  Diagnostic Evaluation ............................................................................................... 8 
3.1  Strategic Objectives ............................................................................................... 8 
3.1.1  GoP’s RE Vision and AEDB Response ......................................................... 8 
3.1.2  Mandate .................................................................................................. 11 
3.1.3  Renewable Energy Key Stakeholders ...................................................... 12 
3.1.4  Target Setting .......................................................................................... 15 
3.1.5  Prioritization of Renewable Energy ......................................................... 16 
3.1.6  Key Findings ............................................................................................. 18 
3.2  Plans and Timelines ............................................................................................. 18 
3.2.1  Key Findings ............................................................................................. 19 
3.3  Resource Deployment ......................................................................................... 20 
3.3.1  Manpower Levels .................................................................................... 20 
3.3.2  AEDB´s Organizational Structure ............................................................. 20 
3.3.3  Salary Structures ...................................................................................... 22 
3.3.4  HRD, Training, and Staff Appraisals ......................................................... 23 
3.3.5  Staff Attrition and Morale ....................................................................... 23 
3.3.6  Key Findings ............................................................................................. 23 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  i
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3.4  Financing .............................................................................................................. 24 
3.4.1  Key Findings ............................................................................................. 26 
3.5  Business Processes .............................................................................................. 26 
3.5.1  Key Findings ............................................................................................. 28 
3.6  Market Intelligence, Communication, and Information Systems ....................... 28 
3.6.1  Key Findings ............................................................................................. 30 
4  Remedial Measures ................................................................................................ 31 
4.1  Institutional Mandates, Roles, and Targets ......................................................... 31 
4.2  Overall Strategic and Planning Capability ........................................................... 33 
4.3  Human Resource and Technical Capability ......................................................... 36 
4.3.1  Staffing Levels .......................................................................................... 37 
4.3.2  Salary Structures ...................................................................................... 39 
4.3.3  Training .................................................................................................... 39 
4.3.4  Technical Training Courses ...................................................................... 40 
4.4  Financing .............................................................................................................. 42 
4.4.1  On‐ grid Expenditures .............................................................................. 42 
4.4.2  Off‐grid Expenditures .............................................................................. 42 
4.5  Business Processes .............................................................................................. 42 
4.6  Communication, Marketing, and Business Intelligence ...................................... 44 
4.7  Institutional Linkages ........................................................................................... 45 
4.8  AEDB´s Performance Evaluation ......................................................................... 45 
4.8.1  Institutional Evaluation ........................................................................... 46 
4.8.2  Service Evaluation ................................................................................... 46 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  ii
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Appendices 

A  AEDB Capacity Assessment Information Request ........................................................ 51 
B  Proposed AEDB Key Job Descriptions ........................................................................... 55 
 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  iii
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibits 

Exhibit 1:  MTDF Energy Mix Plan Projections ................................................................ 11 
Exhibit 2:  AEDB’s Strategic Roadmap ............................................................................. 12 
Exhibit 3:  Institutional Roles in On‐grid RE Development over the Medium Term ....... 13 
Exhibit 4:  Institutional Roles in Off‐grid RE Development over the Medium Term ....... 14 
Exhibit 5:  AEDB Wind Power Development Plan (2011‐2020) ....................................... 15 
Exhibit 6:  AEDB Medium‐term Wind Power Development Plan 2011‐2020 ................. 18 
Exhibit 7:  AEDB Long‐term Vision for Wind Power Development ................................. 19 
Exhibit 8:  AEDB Staff Breakdown by Office and Grade .................................................. 20 
Exhibit 9:  AEDB Organizational Chart ............................................................................. 21 
Exhibit 10:  Summary of AEDB Income and Expenditure, 2007‐ 08 .................................. 24 
Exhibit 11:  Expenditure on AEDB Development Projects ................................................ 25 
Exhibit 12:  Current Donor Funding of Alternative Energy Programs in Pakistan ............ 25 
Exhibit 13:  Wind Power Projects – AEDB Activity Flow Chart .......................................... 27 
Exhibit 14:  Proposed AEDB Strategic Roadmap ............................................................... 33 
Exhibit 15:  Economically Feasible RES‐E Projects by Technology (2020) ......................... 34 
Exhibit 16:  Annual Future Deployment of Feasible RES‐E Projects in Pakistan ............... 35 
Exhibit 17:  Optimum Penetration of RES‐E to 2020 at Social Cost .................................. 35 
Exhibit 18:  Proposed AEDB Organization Chart ............................................................... 36 
Exhibit 19:  Staff by Department ....................................................................................... 37 
Exhibit 20:  Proposed AEDB Organizational Structure ...................................................... 38 
Exhibit 21:   On‐grid Technical Staff Estimate ................................................................... 39 
Exhibit 22:  Off‐grid Technical Staff Estimate .................................................................... 39 
Exhibit 23:  RE Stakeholder Map ....................................................................................... 45 
Exhibit 24:  Suggested AEDB Key Performance Indicators (KPIs) and Targets .................. 46 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  iv
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Abbreviations and Acronyms 

ACR  Annual confidential report 
ADB  Asian Development Bank 
AEDB  Alternative Energy Development Board 
AEF  Alternative Energy Fund 
AJK  Azad Jammu & Kashmir 
AKRSP  Aga Khan Rural Support Programme 
BG  Bank guarantee 
BOI  Board of Investment 
CBO  Community‐based organization 
CDM  Clean Development Mechanism 
CERA  Certified Emissions Reduction Agreement 
CSF  Critical success factor 
DGNRER  Directorate General of New and Renewable Energy Resources 
DISCO  Distribution Company 
DNA  Designated National Agency 
EPC  Engineering, procurement, & construction 
ESCO  Energy services company 
FBR  Federal Board of Revenue 
FTE  Full‐time employee 
GEF  Global Environment Fund 
GoP  Government of Pakistan 
GTZ  Gesellschaft für Technische Zusammenarbeit GmbH 
GW  Gigawatt 
GWh  Gigawatt‐hour 
HR  Human resources 
HRD  Human resource development 
IPP  Independent power producer 
IRET  Institute of Renewable Energy Technologies 
IT  Information Technology 
KESC  Karachi Electric Supply Corporation 
km  Kilometer 
KPI  Key performance indicator 
LoI  Letter of intent 
M&E  Monitoring and evaluation 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  v
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

MHP  Micro hydropower 
MoWP  Ministry of Water and Power 
MTDF  Medium Term Development Framework 
MW  Megawatt 
MWh  Megawatt‐hours 
NARC  National Agricultural Research Centre 
NEPRA  National Electric Power Regulatory Authority 
NGO  Non‐governmental organization 
NIST  National Institute of Silicon Technology 
NREL  National Renewable Energy Laboratory 
NTDC  National Transmission and Dispatch Company 
NUST  National University of Science and Technology 
NWFP  Northwest Frontier Province 
O&M  Operation and maintenance 
ODC  Other direct costs 
OGDC  Oil & Gas Development Corporation 
OGREA  Off‐grid Rural Electrification Account 
OH  Overheads 
PASMA  Pakistan Sugar Mills Association 
PCAT  Pakistan Council for Appropriate Technologies 
PCRET  Pakistan Council for Renewable Energy Technologies 
PG  Performance guarantee 
PMD  Pakistan Meteorological Department 
PPA  Power purchase agreement 
PPIB  Private Power Infrastructure Board 
PPP  Public‐private partnership 
PSC  Public sector comparison 
PV  Photovoltaic 
QA  Quality assurance 
R&D  Research and development 
RE  Renewable energy 
REA  Renewable Energy Agency 
RES‐E  Renewable energy sourced electricity 
RET  Renewable energy technology 
SHS  Solar home system 
SHYDO  Sarhad Hydropower Development Organization 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  vi
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

SOP  Standard operating procedure 
SS  Small‐scale 
TA  Technical assistance 
TPES  Total primary energy supply 
TW  Terawatt 
TWh  Terawatt‐hour 
UNDP  United Nations Development Programme 
US DOE  United States Department of Energy 
USAID  United States Agency for International Development 
VFM  Value‐for‐money 
WAPDA  Water and Power Development Authority 
WHS  Wind home system 
WTE  Waste‐to‐energy 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  vii
 

ADB TA 4881-PAK:
Renewable Energy Policy Formulation and Capacity Development of AEDB

AEDB’s Capacity Assessment 
and Institutional Needs 

1 Objective 
This report presents the consultant’s institutional assessment of the Alternative Energy 
Development  Board  (AEDB)  and  associated  recommendations  to  strengthen  AEDB´s 
capabilities  in  line  with  the  implementation  requirements  of  Pakistan’s  Medium  Term 
Renewable  Energy  Policy  being  developed  under  the  Asian  Development  Bank’s  TA 
4881‐PAK. 
This report builds on the findings and recommendations of previous documents relating 
to national renewable energy (RE)1 development strategy and policy recommendations 
prepared under the TA, particularly Working Papers No 2, 3, and 4.   
The  scope  of  this  paper  covers  a  broad  range  of  topics,  from  AEDB´s  basic  mandate 
through  to  operational  considerations  suited  to  the  proposed  policy  approach.  AEDB´s 
organizational capability has been assessed against eight key dimensions: 
• Mandate and Mission Objectives 
• Strategy and Planning 
• Business Processes 
• Human Resources and Training 
• Finance 
• Market Intelligence, Communication, and Information Systems 
A  four‐step  approach  was  used  to  gather  information  for  purposes  of  conducting  an 
assessment  of  AEDB’s  existing  capacity,  analyzing  gaps,  and  formulating 
recommendations: 
• Personal interaction with AEDB´s senior management 
• Fact‐based analysis of AEDB´s main business areas (e.g., processes, HR, IT, etc.) 
• Face‐to‐face interviews with key external players relevant to AEDB´s operations 
(e.g., government agencies, donors, RE project sponsors, etc.) 
                                                       
1
  Following common practice, in this document the term ‘renewable energy’ (or RE) excludes large hydro (i.e., above 
50  MW  capacity),  but  includes  small  hydro  and  ‘new’  renewables  (i.e.,  solar  photovoltaic  and  thermal,  wind, 
biomass  conversion,  waste‐to‐energy,  etc.).    It  does  not  include  traditional  biomass  (fuel  wood,  agricultural  and 
forestry  wastes,  dung,  and  other  unprocessed  biomass  fuels)  combustion  for  domestic  cooking  and  heating 
purposes. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  1 
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• Detailed information request questionnaires specifically designed to solicit 
existing documentation and information on AEDB’s organization and 
management (Appendix B). 
While  carrying  out  this  assessment,  particular  emphasis  was  placed  on  key  RE 
stakeholders’ and potential investors’ interests and perspective.  
This report is structured in the following three parts: 
• Situation  analysis  of  current  AEDB  capacity,  as  it  relates  to  its  presently 
conceived tasks, operational strategy, and perceived priorities; 
• Diagnostic  evaluation  of  the  effectiveness  (i.e.,  strengths  and  weaknesses, 
accomplishments and failures, etc.) of its performance thus far; 
• Remedial measures for addressing perceived shortcomings, as well as additional 
requirements and modifications specifically envisaged for its role in successfully 
implementing the GoP’s medium‐term RE policy regime. 
We  understand  that  a  detailed  institutional  assessment  of  AEDB  is  presently  being 
conducted  by  the  GoP,  the  findings  of  which  are  not  available  to  the  consultants. 
Therefore,  we  have  placed  greater  emphasis  on  developing  capacity‐related 
recommendations  for  the  medium‐term  future,  in  anticipation  of  approval  by  the 
government of the overall RE policy recommendations being developed under this TA. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  2
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

2 Situation Analysis 
2.1 Background to RE Deployment in Pakistan 
Pakistan  is  a  significant  user  of  hydropower  (currently  about  34%  of  total  generation 
capacity)  and  traditional  biomass.    Most  hydroelectric  generation  comes  from  large 
schemes,  although  small  hydro  projects  are  now  attracting  some  attention.    However, 
the  use  of  other  modern  renewable  technologies  in  Pakistan  remains  insignificant, 
despite the fact that per capita energy use in the country has been increasing at almost 
5% per annum (with electricity generation growing by almost 6%) in recent years, while 
the  share  of  oil  and  natural  gas  in  total  energy  supplies  remains  at  30%  and  50%, 
respectively,  even  as  oil  import  prices  hit  record  highs  and  indigenous  gas  production 
has leveled off recently. 

2.1.1 Potential, Targets, and Achievements 
The  potential  for  the  large‐scale  development  of  renewable  energy  in  Pakistan  is 
considerable, although a systematic assessment of economically viable resources has yet 
to be undertaken for specific technology applications. 
By some estimates, 50 GW of hydropower and a similar amount of wind power potential 
exists, of which only about 16% of hydel potential has been harnessed so far, inclusive of 
large dams.  The current small hydro capacity consists of high‐head plants set up in the 
northern  mountainous  regions,  which  collectively  amount  to  only  about  64  MW, 
although  significant  low‐head  possibilities  also  exist  given  the  country’s  extensive 
irrigation canal network.  Most regions of Pakistan receive abundant solar irradiation—
on  the  order  of  over  2 MWh/m2  and  3,000  hours  of  sunshine  a  year,  which  is  at  the 
highest end of global insolation averages.  Commercially exploitable wind resources also 
exist in many parts, especially in southern Sindh and coastal Balochistan.  Detailed wind 
mapping  could  also  reveal  suitable sites  in  the interior  parts  of  the  country  and  in the 
mountainous  regions.2    To  date,  limited‐scale  ground‐based  wind  data  collection  has 
been undertaken in the southern regions of the country.3  However, no commercial wind 
farms currently exist in Pakistan, and only a few micro turbines have been set up at the 
community level for demonstration purposes.4 
Pakistan’s large agricultural sector produces copious amounts of biomass in the form of 
crop and livestock wastes and residues—such as bagasse, rice husk, and dung—much of 
which is currently collected and used outside the commercial economy as unprocessed 
fuel for cooking and household heating.  This results in significant health impacts due to 
indoor air pollution and loss of productive labor employed in fuel gathering, especially 
for rural women.  More efficient, modern biomass applications include anaerobic biogas 

                                                       
2
  As indicated by the country‐scale wind and solar incidence maps based on computational algorithms published by 
the US National Renewable Energy Laboratory (NREL) in 2007. 
3
  41  wind  masts  have  been  established  by  the  Pakistan  Meteorological  Department,  and  some  additional  ones 
operated by private and donor‐assisted projects, in Sindh and Balochistan in recent years. 
4
  Although  a  few  wind  IPPs  are  in  advanced  stages  of  project  preparation,  with  at  least  one  slated  to  commence 
construction in 2009. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  3
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

digesters,  biofuel  production  (ethanol,  biodiesel,  and  bio‐oil),  pyrolytic gasification,  co‐


firing  and  cogeneration,  feedstock  (including  municipal  solid  waste‐to‐energy),  and 
improved cook stoves.  In Pakistan, other than the use of bagasse for self‐generation in 
the sugar industry, and some work on better cook stove design, virtually none of these 
biomass  conversion  or  end‐use  technologies  has  been  deployed  beyond  the 
experimental  stage.    Pakistan’s  geothermal  potential  remains  unexplored,  particularly 
the occurrence of sites with sufficiently high pressures.  Wave and tidal power, although 
still in the technology development phase, could also eventually find applications along 
the country’s 1,046 km‐long coastline. 
Recently,  the  Government  of  Pakistan  has  placed  increased  emphasis  on  the 
development of the country’s renewable energy resources, initially setting an indicative 
target  in  2003  of  achieving  10%  of  installed  generation  capacity  through  RE  by  2010 
(exclusive  of  large  hydro).    However,  this  non‐binding  target  has  been  revised 
downwards  repeatedly:  to  5%  in  February  2005,  and  1.1%  currently.5    This  is 
symptomatic  of  both  an  absence  of  proper  economic  and  technical  appraisal  of 
beneficial  RE  applications  in  the  local  context,6  as  well  as  an  inability  to  sufficiently 
mobilize  the  necessary  policy,  legislative,  institutional,  and  financial  support  for 
achieving  realizable  goals.7    Nevertheless,  the  necessary  lessons  from  local  and 
international  experience  vis‐à‐vis  the  approach,  scope,  supporting  frameworks, 
sequencing,  inter‐agency  coordination,  and  practical  implementation  modalities 
required  for  a  successful  and  comprehensive  renewable  energy  development  strategy 
are  being  gradually  assimilated.8    Designated  government  counterpart  agencies9  have 
also  been  only  partially  successful  in  utilizing  available  international  assistance  so  far, 
resulting in largely uncoordinated and intermittent support to the local RE development 
process. 
In  comparison  to  the  situation  in  Pakistan,  regional  countries  have  already  taken 
considerable strides in implementing renewable energy capacities—in small hydro (India 
and Nepal), solar PV (India, Sri Lanka, Bangladesh, and Nepal), solar thermal (India and 
Nepal),  biogas  (India  and  Nepal),  wind  (India),  and  biofuels  (India)—building 
incrementally  on  sustained  local  effort  and  capitalizing  on  international  financing  and 
collaboration  opportunities.    Pakistan  thus  needs  to  accelerate,  in  a  nationally 
coordinated  and  institutionalized  manner,  its  RE  facilitation  efforts  on  similar  more 
comprehensive and larger scale bases. 

                                                       
5
  Planning  Commission,  Medium  Term  Development  Framework  2005‐2010,  Government  of  Pakistan,  Islamabad: 
May 2005. 
6
  This is a gap specifically addressed in Working Paper 4. 
7
  Towards this end, a reassessment of the government’s strategic approach and specific policy recommendations for 
the medium‐term (2009‐2014) are the objective of the current ADB TA (4881‐PAK), and outlined in Working Papers 
5 and 6. 
8
  See, for example, Working Papers 1 and 2. 
9
  For example, the Global Environment Facility (GEF) ‘National Focal Point’ and the Clean Development Mechanism 
(CDM) ‘Designated National Agency (DNA)’, both in the Ministry of Environment. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  4
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

2.1.2 Institutional, Legal, and Regulatory Landscape 
At  the  beginning  of  the  current  millennium,  the  institutional  and  policy  landscape 
relating to RE activities in Pakistan presented a cluttered picture.  There were a variety 
of  agencies  claiming  mandates,  sometimes  overlapping  and  conflicting,  that  related 
ultimately to renewable energy use in the country, while at the same time several key 
organizations  that  would  logically  have  a  major  role  to  play  in  this  respect  remained 
uninvolved.    For  instance,  a  Directorate  General  of  New  and  Renewable  Energy 
Resources  (DGNRER)  was  formed  in  the  early  1970s  within  the  Ministry  of  Petroleum 
and  Natural  Resources,  with  a  view  to  piloting  and  implementing  renewable  energy 
sourced  electricity  (RES‐E)  projects,  primarily  for  rural  electrification.    The  Pakistan 
Council for Renewable Energy Technologies (PCRET) was established in 2001 to conduct 
similar  technical  research  and  demonstration  projects,  and  was  itself  a  result  of  the 
consolidation  of  several  agencies  previously  working  on  different  aspects  of  RE 
development,  i.e.,  the  National  Institute  of  Silicon  Technology  (NIST)  and  Pakistan 
Council  for  Appropriate  Technologies  (PCAT).    The  Sarhad  Hydropower  Development 
Organization  (SHYDO)  was  created  in  1986  specifically  for  the  purpose  of  developing 
small  hydro  projects  in  the  NWFP,  while  NGOs,  such  as  the  Aga  Khan  Rural  Support 
Programme  (AKRSP),  independently  undertook  microhydel  schemes  in  the  Northern 
Areas.    The  military  established  its  own  solar  PV  projects  under  the  EME  Workshop 
based in Rawalpindi, while some academic (e.g., at NUST) and donor‐assisted (e.g., GTZ 
and UNDP/GEF) RE initiatives were also undertaken.  
The  Government  of  Pakistan  established  the  Alternative  Energy  Development  Board 
(AEDB)  in  2003  to  promote  the  use  of  renewable  energy  and  help  realize  the 
achievement of national targets (see following section).  As a one‐window facilitator of 
renewable  energy  investments,  this  was  a  welcome  and  necessary  step  towards 
consolidating  the  RE  institutional  framework,  although  the  organization  is  constrained 
by internal capacity issues and an arbitrary mandated ceiling of 50 MW project size, with 
larger RE IPPs being processed by the Private Power and Infrastructure Board (PPIB).10  
Other  relevant  organizations  for  renewable  power  projects  are  the  National  Electric 
Power Regulatory Authority (NEPRA), the various corporatized entities of the Water and 
Power  Development  Authority  (WAPDA),  including  the  National  Transmission  and 
Dispatch Company (NTDC), and the Karachi Electric Supply Corporation (KESC).  None of 
the utilities have as yet been engaged by any private RE power project in the country, 
although  grid  interconnection  studies  for  wind  IPPs  are  underway  and  some  of  the 
corresponding  tariff  determinations  and  power  purchase  agreements  have  been 
negotiated  with  the  regulator.    The  Ministry  of  Environment  also  stakes  a  claim  to 
renewable  energy  projects  due  to  their  climate  change  implications,  being  the 
Designated National Agency (DNA) for CDM registration. 
There is also an apparent overlap of AEDB’s functions with the provincial governments’ 
entitlement  to  develop  power  projects  of  up  to  50 MW  capacity  on  their  own.    The 
situation  becomes  more  complex  if  this  is  to  be  executed through  a  distinct  corporate 
entity  or  if  the  project  is  to  be  connected  to  the  national  grid,  as  this  would  elicit 

                                                       
10
  With the exception of wind IPPs, which are exclusively in AEDB’s domain regardless of their installation size. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  5
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

NEPRA’s regulatory role and presents certain legal anomalies that have yet to be tested 
and resolved in the context of RE power projects.   
With  a  few  exceptions,  renewable  energy  does  not  currently  merit  special  treatment 
under  Pakistan’s  legal  and  regulatory  framework,  and  such  projects  are  largely 
subsumed into the broader classification of ‘power sector projects’.  This results in the 
market penetration of renewables being subjected to the same principles and criteria as 
conventional  energy  projects,  with  hidden  subsidies,  existing  market  bias,  new 
technology  risks,  and  lack  of  accounting  of  external  costs  and  benefits  all  working 
against the introduction of renewable energy investments. 
In  terms  of  a  holistic  assessment  of  all  feasible  renewable  energy  resource  and 
technology  options—their  prioritization,  specific  application  areas  and  targets,  unique 
marketing needs, time‐bound action plans, systematic barrier removal, implementation 
of  institutional  arrangements  and  coordination,  and  commitment  of  financial  support 
and mechanisms—no coherent, integrated government strategy exists.  Some of these 
issues are relevant to the performance of AEDB, while others relate to the absence of a 
systematic policy approach to renewable energy development on a national scale.  The 
current policy11 was devised specifically for the short term (originally to end‐June 2008, 
now  to  be  extended  into  2009)  to  facilitate  several  wind  IPPs  already  in  the  AEDB 
pipeline,  while  the  medium  term  (2009‐2014)  policy  development  initiative  under  the 
present ADB TA is meant to address exactly some of these earlier shortcomings and help 
develop a more enabling environment for AEDB to be able to meet its objectives. 

2.2 Establishment and Development of the AEDB 
The Alternative Energy Development Board (AEDB) was created on May 12, 2003 under 
a  Presidential  decree12  with  the  aim  of  promoting  and  facilitating  the  exploitation  of 
renewable  energy  resources  in  the  country  so  as  to  achieve  the  GoP’s  RE  deployment 
targets.    The  AEDB’s  functions  include  framing  appropriate  policies  and  plans, 
developing projects, promoting local manufacturing, creating awareness and facilitating 
technology  transfer,  channeling  international  assistance,  and  coordinating  all  such 
activities  as  a  supreme  national  facilitating  agency  for  the  development  of  renewable 
energy  in  the  country.    It  has  also  been  designated  as  a  ‘one‐  window’  facility  for 
processing RE power generation projects of less than 50 MW capacity in the country.10 
The  AEDB  Ordinance  provides  financial  and  operational  autonomy  to  the  organization. 
The  Board  was,  for  its  initial  four  years,  headed  by  a  full‐time  Chairman.    In  2008,  the 
Federal  Minister,  Water  and  Power  was  made  the  Board’s  honorary  Chairman,  with  a 
new position of a full‐time Chief Executive created to head its operational activities. The 
Board  also  includes  ex‐officio  members  from  concerned  government 
ministries/divisions, as well as five members from the private sector, including two full‐
time technical members.   In addition, it hires professional staff on competitive market 

                                                       
11
  Alternative Energy Development Board (AEDB), Policy for Development of Renewable Energy for Power Generation, 
2006, Ministry of Water and Power, Islamabad: December 2006. 
12
  Initial  vide  Notification  No.  F.1/7/2003/Admn  II,  dated  May  12,  2003,  subsequently  converted  to  Presidential 
Ordinance  on  April  30,  2005  and  published  as  Ordinance  No.  LVI  of  2007,  Gazette  of  Pakistan,  Government  of 
Pakistan, Islamabad: October 3, 2007. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  6
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

salaries,  free  from  civil  service  rules  and  conditions.  The  Board  relies  on  funding  from 
the government and other international and domestic financial institutions. 
The  AEDB  was  initially  tasked  with  the  fast‐tracked  development  of  renewable  energy 
projects in Pakistan, initially placed under the Cabinet Division and reporting directly to 
the  Prime  Minister.    It  thus  had  the  requisite  GoP  political  support  behind  it  from  the 
outset, and it took advantage of this position by creating a highly visible profile for the 
organization with ambitious plans and targets that were assiduously promoted through 
the media and public events.  From the beginning, the organization focused its activities 
predominantly  on  wind  power  development  through  the  private  sector,  and  for  this 
purpose  undertook  concerted  efforts  to  engage  with  interested  local  and  foreign 
investors.    Its  capacity  development  and  growth  in  subsequent  years  was  thus  heavily 
oriented towards achieving this mission, and by 2006 it found itself deeply entrenched in 
wind  IPP  project  negotiations  on  behalf  of  some  of  the  93  LoIs  it  had  issued  earlier 
(along with 23,646 acres of land concessions it had persuaded the Government of Sindh 
to provide on highly concessionary terms to 15 wind farms, with another 10,330 acres 
provisionally allocated to seven additional projects). 

2.3 Performance Issues  
Nevertheless,  despite  this  progress,  the  AEDB’s  growth  as  a  professional  RE 
development  agency  remains  less  than  satisfactory,  particularly  with  respect  to  RE 
applications  other  than  wind  power.    Despite  having  undertaken  some  pilot 
electrification through PV systems in about 1,000 rural households in all four provinces 
and 100 microwind generators in villages in Sindh and Balochistan during 2004‐05, the 
AEDB  has  not  developed  the  internal  capacity  nor  institutionalized  plans  for  the 
sustainable, scaled‐up deployment of other commercially viable RETs (e.g., small hydros, 
biomass‐fueled  generation,  etc.)  or  for  off‐grid  rural  electrification.    It  has,  in  recent 
years,  also  been  substantially  supported  by  some  donor  agencies  in  helping  promote 
renewable energy policies and projects through targeted technical assistance,13 but this 
has  not  yet  been  leveraged  to  the  AEDB’s  own  technical  capability  enhancement.    At 
present, the Board’s primary objective appears to be to ensure that at least a few of the 
wind IPP projects originally sanctioned through the LoIs achieve financial closure and can 
start construction by 2009.  Thus, judging by its own initial projections, even allowing for 
the  realization  of  some  wind  power  capacity  by  next  year, the  outcome  of  the  AEDB’s 
efforts over the past five years of its existence does not appear to be in line with its own 
stated  objectives,  and  there  seems  to  be  a  need  to  re‐evaluate  its  strategic  approach 
and internal planning and executive capacity. 

                                                       
13
  Such  as  the  GTZ’z  Renewable  Energy  and  Energy  Efficiency  (REEE)  project,  the  ADB’s  Renewable  Energy 
Development  Sustainable  Investment  Programme  (REDSIP),  and  the  USAID’s  Pakistan  RE  resource  assessment 
assistance through the NREL. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  7
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3 Diagnostic Evaluation 
The  situation  analysis  of  the  current  institutional  capacity  for  RE  development  in 
Pakistan presents a mixed picture: several government‐ and donor‐supported initiatives 
have  been  undertaken  in  the  past,  but  these  have  largely  been  disjointed  and 
fragmented, with no clear sustainability mechanisms or long‐term strategy, policy, and 
institutional  frameworks  yet  in  place  to  further  their  goals.    This  has  resulted  in  some 
isolated  successes  and  progress  in  some  aspects  of  framework  and  capacity 
development, but not to the extent required to firmly initiate large‐scale deployment of 
RETs  in  the  country,  nor  a  reliable  vision  of  when  such  capacity  would  indeed  be 
achieved. 
This section provides the consultants’ evaluation of some of the factors responsible for 
this situation, along with some broad prescriptive solutions that could be considered in 
devising  a  more  effective  response  strategy  for  meeting  the  GoP’s  RE  development 
objectives and the commensurate role and capacity of the AEDB over the medium term 
future. 

3.1 Strategic Objectives 
3.1.1 GoP’s RE Vision and AEDB Response 
The  strategic  targets  set  for  RE  development  in  Pakistan  in  the  MTDF  by  the  Planning 
Commission do not appear to be derived from a comprehensive cost‐benefit analysis of 
renewable  versus  other  energy  options,  and  thus  at  best  represent  indicative—rather 
than  necessarily  achievable—targets  based  on  a  practical,  RET‐wise  energy  mix.  
Furthermore,  by  repeatedly  lowering  the  overall  penetration  target  for  RE‐based 
electricity by 2020, the GoP has ensured that even these goals are considered flexible, 
rather  than  mandatory.    This  has  resulted  in  not  only  undermining  the  AEDB’s 
development  as  a  mission‐oriented  organization,  but  also  ensured  that  RE  remains  an 
unreliable  future  option  in  the  minds  of  the  country’s  energy  planners,  policy  makers, 
and investors. 
Furthermore,  even  given  a  non‐binding  planning  target,  the  AEDB  failed  to  assess, 
elaborate,  and  plan  its  own  strategy  professionally  for  achieving  the  GoP’s  stated 
objectives.    Instead  of  taking  the  broad  mandate  and  clear  intent  of  the  GoP  for 
substantially  increased  RE  deployment  in  the  country  and  developing  it  further  into 
economically  and  operationally  feasible  plans,  RET‐wise  strategies  (including  for  non‐
power  RE  development  which  the  MTDF  omits  from  its  targets),  and  intermediate 
actions  and  milestones,  the  AEDB  set  about  adopting  ad  hoc  approaches  to  both  RE 
capacity  development  (i.e.,  almost  exclusively  through  wind  IPPs)  and  rural 
electrification  (through  standalone  PV  and  wind  home  systems).    There  was  no 
systematic  socioeconomic  analysis  undertaken  of  the  various  RET  technologies, 
resources,  and  markets  in  Pakistan  that  could  help  guide  the  AEDB  develop  its  annual 
operational  plans,  recommend  appropriate  policy  measures,  mobilize  resources  and 
develop  its  own  capacity  accordingly,  and  ensure  that  the  least‐cost  RE  projects  get 
priority attention. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  8
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Instead,  the  Board  locked  itself  into  a  very  difficult  track,  of  meeting  ambitious  GoP 
targets  with  an  arbitrarily  selected  RET  focus.    For  instance,  by  selecting  the  locally 
untested  and  relatively  expensive  and  sophisticated  wind  turbine  technology  for 
initiating  large‐scale  RES‐E  capacity  installations,  the  AEDB  unwittingly  made  several 
strategic errors that have affected its own effectiveness since, both perceived and real: 
• For  Pakistan,  small  hydro—followed  by  biomass  conversion—are  by  far  the 
lowest‐cost  and  technologically  easily  indigenized  RET,  with  vast  resource 
potential  for  both,  especially  in  difficult,  off‐grid  terrain  where  conventional 
power  generation  and  grid  extension  is  particularly  costly.    Thus,  these 
technologies are not only financially and practically inherently more feasible and 
readily deployable, but enjoy the advantage of higher avoided costs which would 
also  make  them  financially  very  attractive  to  the  utilities  and  rate  payers.    By 
contrast,  grid‐connected  wind  IPPs  in  the  Keti  Bandar‐Gharo  wind  corridor 
especially selected by the AEDB for accelerated development, have to compete 
directly  with  large  hydel  and  CCGT‐supplied  power  on  the  national  grid,  suffer 
from  relatively  lower  plant  factors and,  being  relatively  new  technology,  higher 
financial risks and costs.  Not surprisingly, these projects have been plagued by 
protracted  tariff  negotiations  with  NEPRA,  with  the  regulator  and  utilities 
unwilling  to  accept  premium  prices  demanded  for  their  variable  output  under 
dispatch priority, while providing interconnect and backup supplies at additional 
cost. 
• Having  committed  itself  to  the  wind  IPP  route,  the  AEDB  found  itself  largely 
advocating  on  behalf  of  private  investors  with  government  agencies  for  the 
necessary tariffs, permits, incentives, and guarantees deemed necessary to invite 
investment in this relatively new area.  While this was in keeping with the AEDB’s 
stated role as a ‘one‐window’ facilitator of private RE investment, it was however 
perceived  by  most  other  key  stakeholders—regulators,  utilities,  and  competing 
generators—as favoring wind investors unnecessarily.  This argument holds some 
merit, although if only because the AEDB was following NEPRA’s own ‘cost‐plus’ 
pricing  formulation  to  justify  high  tariffs  and  risk  guarantees  to  the  wind  IPPs.  
The AEDB thus was embroiled in justifying investors’ escalating capital costs and 
power  buyback  demands  on  the  one  hand,  while  itself  not  having  established 
economic  price  benchmarks  for  wind  power  nor  being  privy  to  the  actual  IPP 
project costs.  This situation could have been avoided, for instance, by offering an 
initial fixed quota of wind power purchase on competitive tenders, instead of on 
a  guaranteed  returns  and  wind  risk  cover  basis.    In  the  process,  however,  not 
only did the AEDB get embroiled with haggling on behalf of the IPP sponsors with 
key  agencies,  which  at  times  led  to  acrimony  and  the  creation  of  a  degree  of 
mistrust  between  itself  and  the  regulator,  but  also  had  to  put  in  considerably 
more  effort  into  such  case‐by‐case  negotiations,  at  the  detriment  of  its  other 
activities.    This  singular  and  consuming  preoccupation  with  wind  IPP 
development  has  been  a  cause  for  both  good  (in  terms  of  organizational 
understanding of IPP requirements) and bad (in terms of actual projects realized 
and  other  RET  capacities  developed)  with  respect  to  AEDB’s  own  capability 
development, but overall has not been an optimal strategy by any means. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  9
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• The  AEDB’s  other  strategic  mistake  with  respect  to  its  GoP‐assigned  targets 
was—in the absence of an internal evaluation and planning process—its inability 
to assess, request, and secure the necessary technical, manpower, and financial 
resources  from  the  government  in  order  to  fulfill  its  mandate.    This  oversight 
eventually cost the organization dearly, as it accepted a very ambitious mission 
without the necessary means for achieving its objectives.  In fact, for much of its 
existence,  the  AEDB  has  had  to  fight  for  even  the  rudimentary  staffing  and 
budgeting resources that it had originally been sanctioned, its continued efforts 
in this regard being stymied by the increasingly mixed views on its performance 
so  far  by  decision‐makers  within  the  GoP.    This  is  a  vicious  cycle  that  must  be 
broken,  and  the  Board  should  be  provided  with  clear  means  and  a  reasonable 
timeline to mature and establish itself as a professional body, before a realistic 
appraisal of its performance and regular accountability mechanisms to gauge its 
effectiveness are deployed. 
• The  AEDB’s  considerable  investment  in  wind  IPP  development  also  detracted  it 
from  other  RE  project  development,  internal  planning,  capacity  building  and 
training,  and  donor  coordination  activities  that  could  have  helped  salvage  its 
reputation had they been undertaken with greater vigor.  Thus, for instance, the 
AEDB  remains  without  an  operational  mechanism  to  facilitate  the  regular 
disbursement of REDSIP tranches,14 in coordination with provincial and regional 
governments,  for  public  sector  RE  projects,  or  for  sustainable  development  of 
off‐grid  RE‐supplemented  electrification,  or  for  specific  biomass  projects—all 
areas in which it could easily have achieved visible results with much less effort 
than  that  expended  on  wind  IPP  development  so  far.    As  for  wind  power,  the 
AEDB would have done well to simultaneously explore off‐grid locations to install 
pilot demonstration‐type projects (for which GEF funds were readily available to 
it),  as  the  higher  tariffs  could  more  easily  be  justified  here  on  grounds  of  even 
higher avoided electricity supply costs and greater local socioeconomic benefits. 
• Finally, the AEDB does not seem to have undertaken a thorough internal review 
of  its  strategy  and  planning  processes,  despite  the  evident  lessons  and  difficult 
experience it has faced in meeting its initially‐publicized objectives.  To an extent, 
the  organization  became  a  victim  of  its  own  hype,  and  has  taken  longer  than 
necessary  to  evaluate  its  performance,  ‘unlearn’  errant  strategies,  and 
implement  corrective  actions.    The  MoWP,  in  the  2006  RE  Policy,  laid  out  a 
phased roadmap in which the initial policy regime was deliberately curtailed to 
the short term (i.e., to June 31, 2008, now to be extended to 2009), to allow for a 
more  thought‐out  policy  strategy  to  be  developed  for  the  subsequent  medium 
term.    In  effect,  this  should  provide  the  AEDB  with  the  necessary  means  to 
review  its  strategic  direction,  and  to  proceed  in  a  more  rational  manner  by 
‘reinventing’ itself for the future. 
                                                       
14
 The ADB’s REDSIP multi‐tranche financing facility (MFF) has made a considerable fund of USD 0.51 billion available 
to the GoP for ready financing of public sector RE projects; however, its disbursement has been very slow for the 
first two tranches, with the provincial governments and AEDB failing to come up with a pipeline of RE projects and 
the  necessary  implementation  capacities.    At  present,  there  are  no  visible  project  identification  preparations 
underway either for the third REDSIP tranche. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  10
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3.1.2 Mandate  
AEDB´s strategic directions and targets are currently defined by two main documented 
sources,  the  AEDB  Ordinance  and  the  GoP’s  Medium  Term  Development  Framework 
(MTDF).  The  Ordinance  describes  broad  strategic  directions  for  the  organization  which 
are supplemented by the quantitative objectives relating to national energy security set 
by the government in the MTDF. These objectives are: 
• 7% of total national power generation capacity (i.e., 9,700 MW), or 2.5% of total 
primary  energy  supply  (TPES),  to  be  generated  through  renewable  energy 
technologies by 2030 (Exhibit 1). 
• Electrification  of  7,874  remote  villages  in  Sindh  and  Balochistan  provinces 
through renewable energy technologies, out of a total of 12,585 to be electrified 
throughout the country by 2010. 
• Development  of  a  comprehensive  plan  for  the  development  of  solar  products 
(solar lights, solar fans, solar cookers, solar geysers) through the participation of 
the private sector. 

Exhibit 1: MTDF Energy Mix Plan Projections 
180

Oil
160
Natural Gas
Coal
140 Renewables
Hydro
120 Nuclear

100
MTOE

80

60

40

20

 
Source: Medium Term Development Framework 2005‐2010, Government of Pakistan. 

In  parallel,  the  AEDB  has  been  involved  in  the  implementation  of  pilot  projects  across 
Pakistan which has resulted in numerous activities on the ground, including: 
• Solar electrification 
• Solar water pumping 
• Micro and mega wind projects 
• Microhydel 
• Biodiesel 
• Fuel cells 
• Earthquake relief. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  11
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

We  are  not aware  of  any  strategic  roadmap  or  internal  planning  clearly linking  AEDB’s 
actual activities on the ground to the directions and objectives set in the Ordinance and 
MTDF. For instance, how do the first two objectives listed above from the MDTF (7% of 
total  national  power  generation  by  2030  and  electrification  of  7,874  villages)  break 
down into specific AEDB actions and achievable annual targets? 
Using  the  Ordinance  and  MTDF,  Error!  Reference  source  not  found.  aims  to  rebuild 
AEDB´s strategic roadmap linking AEDB´s strategic goals to its operational performance 
targets.  The  exhibit  highlights  some  gaps  in  the  roadmap  which  would  need  to  be 
addressed  for  AEDB  to  meet  the  MTDF  objectives  stated  above.  It  is  pertinent  to 
mention  here  that  the  limited  visibility  of  overall  internal  strategic  planning, 
documentation, and communication within a ‘lead’ institution such as the AEDB can also 
have  a  potentially  adverse  or  demoralizing  effect  on  prospective  investors,  suppliers, 
financiers,  and  other  agencies  involved  in  renewable  energy  development  in  the 
country. 
Exhibit 2: AEDB’s Strategic Roadmap 
Strategic
Vision Mission CSFs KPIs/Targets
Objectives

Develop national strategy,


policies, and plans Not defined Not defined
Promote all alternative energy resources in Pakistan

Evaluate, monitor, and


certify RE projects Not defined Not defined
Not defined

• % of LOIs materialized
Facilitate power generation • % of electricity produced from RE
through RE sources: • Set up as one-window facility • # RES-E generation licences issued
• Cost/benefit
• Identify RE project opportunities • 700 MW wind by 2010
Ensure 7% national power
capacity from RE by 2030 • Promote and facilitate RE projects
• # villages electrified
• Conduct feasibility studies • # houses electrified
Electrify 7,874 villages in • Carry out technical and financial • Cost/benefit
Sindh & Balochistan through
evaluations of proposals • Quality of feasibility studies?
RE by [date not defined] • Provide assistance in licensing and tariff • # months for project implementation
petitions
• % of private sector involvement
• Coordinate activities with national agencies • # projects developed
Build up plan for development
of solar energy with • Assist in the implementation projects • # beneficiaries from projects
participation of private sector • # months project implementation
• Set up alternative RE pilot projects • # villages electrified
• Budgeted vs. actual outlays
 
Note: CSF: Critical success factor, KPI: Key performance indicator. 

3.1.3 Renewable Energy Key Stakeholders 
The AEDB has a key role in coordinating the activities and promoting the interests of key 
renewable  energy  stakeholders  in  Pakistan.  This  function  requires  in‐depth  knowledge 
of the activities of each stakeholder category and strong working relationships with all 
parties  involved.    In  this  respect,  Exhibit  3  presents  the  proposed  roles  of  key 
government agencies in on‐grid RE development over the medium term, while Exhibit 4 
illustrates the case for off‐grid RE‐based electrification 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  12
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 3: Institutional Roles in On‐grid RE Development over the Medium Term 
Institution Main Role in RE Development

Ministry of Water • Coordinate development of conventional and RE energy sources


and Power • Formulate development policies jointly with Planning Commission
• Issue implementation agreement and security packages with
Ministry of Finance
• Set penetration quota for uneconomic RE technologies

Ministry of Finance • Evaluate impact of proposed policy on the economy as a whole.


(through BOI and • Approve development policies jointly with MoWP
FBR) • Issue implementation agreements and security packages jointly
with MoWP

AEDB • Frame and propose appropriate policies and plans to the GoP
• Develop demonstration programs and projects for off-grid RE
• Promote local manufacturing
• Create awareness and facilitate technology transfer
• Channel international assistance
• One-window facility for processing IPP projects under RE policy
• Develop standard PPAs for each RET
• Develop pre-feasibility studies for RE projects in
coordination with provincial and AJK agencies

NEPRA • Define feed-in tariffs according to the conceptual


approaches provided in these policy recommendations
promptly (within four months)
• Approve the application of pre-defined feed-in tariff to a
specific RE project
• Adjust grid and distribution codes in order not to block the
development of RE IPPs
• Issue licenses for RE power generation projects

WAPDA or CPPA • Sign PPA under consent of AEDB


(as purchasing entity) • Procure all power produced by approved on-grid RE generation
plants during the term of the PPAs and up to cap provided in policy

Power Utilities • Connect RE projects to grid if they comply with requirements of


(NTDC, KESC, & network codes
DISCOs as networks
operators)

PCRET • Foster R&D and technology development relevant to renewable


energy in coordination with the AEDB

Provincial and AJK • Support the implementation of renewable energy projects in close
Agencies coordination with the AEDB
• Facilitate allocation of land use, water rights, and environmental
permitting
• Create awareness of RE amongst end users and customers
• Remove any other local impediments which may hinder RE
development in a province
• Develop pre-feasibility studies for RE projects in
coordination with AEDB
• Harmonize province RE regulations with national
framework

Source: ADB TA 4881‐PAK Working Paper 5. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  13
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 4: Institutional Roles in Off‐grid RE Development over the Medium Term 

Institution Main Role

Ministry of Water and • Define budget request for Off-grid Rural


Power Electrification Account (OGREA)

Alternative Energy • Develop demonstration programs and projects for off-


Development Board grid RE
(AEDB) • Promote local manufacturing
• Create awareness and facilitate technology transfer
• Channel international assistance
• Program coordinator
• Set parameters for project cost-benefit analyses
• Decide on projects’ merit order
• OGREA management and issue payment order for
approved projects
• Develop standard authorizations

National Electric Power • None


Regulatory Authority
(NEPRA)

Pakistan Council for • Foster R&D and technology development relevant to


Renewable Energy renewable energy, in coordination with the AEDB
Technologies
(PCRET)

Provincial and AJK • Support the implementation of renewable energy


Agencies projects in close coordination with the AEDB
• Facilitate allocation of land use, water rights, and
environmental permitting
• Create awareness of RE amongst end users and
customers
• Remove any other local impediments which may hinder
RE development in a province
• Create provincial Rural Electrification Agencies
REAs)
• Decide on renewable generation technology to be
implemented in each project.
• Elaborate project cost-benefit analysis based on
parameters previously set by the AEDB.
• Cofinance approved rural electrification projects.
• Call for tender process for construction/operation
of each awarded project.
• Set tariff for off-grid services and monitor
performance

WAPDA or CPPA • None


(as purchasing entity)

Power Utilities • None


(NTDC, KESC, & DISCOs as
networks operators)

Source: ADB TA 4881‐PAK Working Paper 6. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  14
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

In  its  one‐stop  RE  facilitation  role,  the  AEDB  needs  to  develop  a  strong  network  of 
contacts  and  relationships  within  each  of  the  entities  listed  in  the  preceding  two 
exhibits.  The  AEDB  would  need  to  act  as  an  umbrella  for  all  RE‐related  activities  and 
foster cooperation amongst the various institutions involved in RE activities, as well as 
serving as the central repository of all information, data, and networking links related to 
renewable energy in Pakistan. 

3.1.4 Target Setting  
Key  time‐bound  quantitative  interim  RE  capacity  deployment  targets are  necessary  for 
the  government  to  be  able  to  assess  and  review  the  performance  of  the  AEDB  in 
promoting  and  developing  RE  and  meeting  its  long‐term  goals.  This  is  turn  would 
increase the accountability as well as the credibility of the agency and allow corrective 
mid‐course actions to be taken, if necessary, in response to any shortfalls observed.  The 
AEDB  has  developed  and  documented  some  measurable  targets  against  which  its 
performance could be evaluated in two specific areas so far: wind power generation and 
RE‐based rural electrification. 
For  wind  power  generation,  AEDB’s  short  term    (2005‐2010)  and  medium  term  (2011‐
2020) plans set forth the targets highlighted in Exhibit 5 below. The aim is to reach 3,730 
MW of installed wind power generation capacity by 2020 and 9,700 MW by 2030.  

Exhibit 5: AEDB Wind Power Development Plan (2011‐2020) 

A few of points are worth noting here:  
• The  Government’s  long  term  vision  of  9,700  MW  of  power  generation 
from  renewable  energy  by  2030  seems  to  be  planned  to  be  achieved 
solely  through  wind  turbines,  disregarding  other  renewable  energy 
technologies (RETs). 
• There is no breakdown or quantitative analysis to detail how the target of 
9,700  MW  by  2030  is  actually  to  be  reached  (i.e.,  annual  capacity 
additions, costs, locations, etc.).  

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  15
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• No  detailed  plans  have  been  shared  with  the  consultant  that  assess  the 
actual  feasibility,  from  AEDB´s  own  capacity  viewpoint,  of  implementing 
the actions and facilities that would be required to reach these targets. 
Under Rural Village Electrification, the MTDF sets the target of electrifying 7,874 villages 
in  Sindh  and  Balochistan  provinces  (6,968  and  906  villages,  respectively).  The  main 
delivery mechanism to meet program objectives are solar PV and wind power to supply 
electricity and associated appliances (SHSs, WHSs, efficient lighting, solar cookers, solar 
water disinfectors, etc.).  
To  date,  eleven  villages,  totaling  a  thousand  households,  have  been  electrified  using 
solar  PV  systems  .  Another    18  villages  with  691  houses  (100  turbines)  have  been 
provided electricity through 100 micro‐wind generators installed. While this represents a 
useful start and provides operational experience and demonstration benefits, the AEDB 
does not seem to have conducted detailed planning on critical issues relating to: 
• Cost‐effective  choice  of  RETs  to  be  deployed,  given  village  characteristics  and 
available RE resources. 
• Program design for scaling up village electrification through RES‐E, including cost 
and management requirements. 
• Demarcation  of  future  villages/areas  to  be  electrified  using  RES‐E,  including 
socioeconomic  benefit‐cost  analysis  against  alternative  options  (hybrid  and 
standalone thermal, grid extension, etc.) and annual deployment targets. 
• Financial  and  institutional  sustainability  of  large‐scale  RES‐E  deployment  in 
unelectrified  villages,  including  project  selection  criteria,  delivery  mechanisms, 
service charges, and cost and revenue sharing, etc. 
Therefore, at this stage, it is unclear what AEDB’s development and rollout plans are to 
support  the  rural  electrification  program  outlined  in  the  MTDF  of  electrifying  villages 
through RE, nor does there appear to be any systematic effort underway to address this 
planning requirement.  
Thus,  for  both  grid‐connected  and  off‐grid  RES‐E  deployment,  the  AEDB’s  approach, 
technology selection, and activities appear to be ad hoc, short‐term, and project‐based.  
It seem evident that while the organization is trying to gain experience through limited 
intervention  and  somewhat  arbitrary  focus  in  a  ‘bottom  up’  approach,  it  has  not  yet 
attempted  to  define  its  activities  in  a  ‘top  down’  manner,  i.e.,  by  working  backwards 
from its assigned long‐term RES‐E capacity targets to determine the most economic RET 
mix,  institutional  and  policy  requirements,  resource  and  capacity  needs,  and  related 
timelines and workplans. 

3.1.5 Prioritization of Renewable Energy 
The  AEDB´s  mandate  is  broad  and  encompasses  a  wide  range  of  on‐grid  and  off‐grid 
RETs (solar PV and thermal, wind, small hydel, biomass conversion, biofuels, WTE, etc.). 
To  our  knowledge,  there  is  no evidence  of  a systematic and  economic  prioritization  of 
the  various  RETs  undertaken  by  the  AEDB  against  deployment  scenarios  (e.g.,  on‐  and 
off‐grid, centralized and distributed, geographical and end‐use markets, etc.) or relevant 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  16
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

financial and social costs (e.g., alternative conventional generation, fuel prices, avoided 
costs,  externalities,  etc.)  that  could  help  trigger  corresponding  implementation 
strategies as well as providing sound justification for resource allocation and pricing in 
favor of RE supplies. The AEDB’s initial, continuing and predominant emphasis has been 
on developing grid‐connected wind IPPs (and that too in a prescribed ‘wind corridor’ in 
southern  Sindh),  and  in  facilitating  private  investors  by  negotiating  favorable 
government  incentives,  risk  guarantees,  and  tariffs  on  their  behalf.    This  approach  has 
several obvious drawbacks: 
• By  directing  all  of  its  attention  on  a  single  RET,  the  AEDB  has  not  been  able  to 
evaluate  other  feasible  alternatives  and  facilitate  their  development  in  the 
interim,  just  as  its  own  capabilities  and  experience  in  these  RETs  has  remained 
stunted. 
• By  not  conducting  a  sustained  economic  evaluation  of  different  RETs,  and  in 
particular  for  prioritized  wind  generation,  the  AEDB  has  not  been  able  to 
determine justifiable tariffs on avoided or least cost basis, and has instead spent 
considerable effort in supporting IPP petitions with the regulator based on ever‐
escalating  financial  costs,  which  in  turn  has  perhaps  created  an  unnecessary 
impression  of  unduly  favorable  terms  being  offered  to  the  wind  IPPs  and  a 
certain level of institutional discord on the subject within the government. 
• By  placing  its  emphasis  almost  exclusively  on  wind  IPPs,  including  publicizing 
unconfirmed  investor  interest  in  projects  prematurely  (e.g.,  LoIs  signed, 
unlimited  capacity  quota)  and  making  hasty  concessions  (e.g.,  with  respect  to 
investor  screening,  allocating  land  leases,  etc.),  the  AEDB  exposed  itself  to  the 
risk of a failure or delay in corresponding capacity deployment (for these or other 
reasons) becoming the sole measure tarnishing the institution’s performance and 
public perception.   This  appears to have happened, placing further pressure on 
the  organization  to  deliver  on  a  difficult  target  (wind  farms  represent  a  new, 
sophisticated  technology  locally,  involve  high  capital  costs,  and  rely  on 
unpredictable overseas suppliers and prices, etc.). 
• The  lack  of  attention  to  other  feasible  and  more  accessible  RETs  (in  particular, 
small  hydro  and  biomass  conversion)  by  the  AEDB  has  resulted  in  many  ready, 
fast  track,  and  least  cost  options  not  being  developed,  or  their  potential  and 
feasibility being properly assessed, or available financing (such as ADB’s REDSIP 
facility and CDM) from being optimally utilized, representing an economic loss to 
the country and additional time now being required to develop these options. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  17
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3.1.6 Key Findings 

• No developed strategic roadmap or annual workplans clearly articulating RE 
deployment objectives and operational goals in place. 
• Limited overall RE evaluation, prioritization, and project portfolio development 
and management capability exists. 
• Limited measurable targets, key performance indicators (KPIs),  to assess 
AEDB´s performance and implementation efforts 
• Where targets do exist, it is unclear how they were devised or will be achieved, 
given the lack of detailed plans. 
• Lack of comparative socioeconomic RET benefit‐cost evaluation and pricing 
capability. 

3.2 Plans and Timelines 
As  stated  earlier,  the  AEDB  has  developed  short‐  (2005‐2010)  and  medium‐term  plans 
(2011‐2020),  mainly  for  wind  power  installation.  These  plans  set  overall  generation 
targets on a yearly basis. The short‐term plan establishes the development of 700 MW 
of wind energy by year 2010 by private investors, while the medium‐term plan targets 
3,730 MW by 2020. The long‐term vision (up to 2030) is to achieve 9,700 MW (Exhibit 6 
and Exhibit 7). 

Exhibit 6: AEDB Medium‐term Wind Power Development Plan 2011‐2020 

Year Additional Wind Power Cumulative Wind Power


Generation Capacity Generation Capacity
(MW) (MW)

2011 200 680 (by 2010) + 200 = 880


2013 20 880 + 200 = 1,080
2014 150 1,080 + 150 = 1,230
2015 200 1,230 + 200 = 1,430
2016 250 1,430 + 250 = 1,680
2016 250 1,680 + 250 = 1,930
2017 400 1,930 + 400 = 2,330
2018 400 2,330 + 400 = 2,730
2019 500 2,730 + 500 = 3,230
2020 500 3,230 + 500 = 3,730

Source: AEDB website (www.aedb.org). 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  18
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 7: AEDB Long‐term Vision for Wind Power Development 

 
Source: AEDB Profile, 2005‐2006. 

Beyond this, there does not appear to be any evident of further planning detailing how 
such  targets  are  to  be  achieved,  and  what  mechanisms  the  AEDB  intends  to  deploy  in 
case  interim  results  are  not  achieved  as  indicated  in  the  timelines.  Typically,  Level  1‐3 
plans would be expected to be in place, where Level 3 plans would list the subtasks and 
activities required to meet the targets set in the Level 1 (or master) plan. Level 3 and 2 
plans  would  roll  up  to  the  Level  1  plan,  which  would  highlight  the  main  planning  
building blocks with associated timeline. 
A ‘bottom up’ planning exercise would be beneficial in this respect on several accounts: 
• To validate how realistically ‘achievable’ the government RE targets are. 
• To  provide  an  understanding  of  the  level  of  effort,  timeline,  and  resources 
required to meet set targets.  
• To  provide  greater  clarity  and  confidence  in  the  AEDB´s  overall  delivery 
capability. 
• To allow for the establishment of measurable internal milestones and indicators 
for assessing the AEDB´s performance. 
• To  allow  for  the  development  of  corrective  actions  and  feedback  loops  for  the 
AEDB to pre‐empt shortfalls and refine or redirect its efforts. 
To  our  knowledge,  no  other  targets  or  plans  have  been  created  by  the  AEDB  for  the 
development of RETs other than grid‐connected wind farms. 

3.2.1   Key Findings 

• No systematic ‘bottom up’ approach to planning. 
• Lack of detailed RET‐wise plans, timelines, and interim performance indicators. 
• No overall master plan setting institutional direction, growth, and capacity 
building directions. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  19
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3.3 Resource Deployment 
3.3.1 Manpower Levels 
The  AEDB  currently  has  102  staff  members  on  its  payroll,  spread  over    three  offices 
located in Islamabad, Karachi, and Quetta (Exhibit 8). The majority (85%) of the staff is 
located  at  its  headquarters  in  Islamabad.    A  quarter  of  the  AEDB’s  personnel  (i.e.,  26 
persons) are officers, with the remaining staff involved in support functions. 

Exhibit 8: AEDB Staff Breakdown by Office and Grade 
Islamabad Office Karachi Office Quetta Office

Of f icer
Of f icer 17%
28%

Non-
Of f icer Non- Non-
72% Of f icer Of f icer
83% 100%

 
Source: Alternative Energy Development Board. 

Against  the  AEDB´s  proposed  organizational  chart,15  there  are  numerous  key  positions 
not presently filled in. At this stage, it is unclear whether this is a result of underfunding, 
shortage  of  qualified  candidates,  uncompetitive  financial  packages  offered,  or  staff 
turnover. 
The AEDB´s organizational chart indicates a total staff strength of 101, with only 23 staff 
currently  posted  and  78  vacancies.  These  vacancies  include  senior  and  mid‐level 
positions  within  the  organization  and  exclude  any  support/administrative  staff.  At  this 
stage, it is unclear whether the vacancies would require support staff in line with AEDB´s 
current officer/support staff ratio of 1:4.  Overall, the AEDB´s currently planned staffing 
level is 180 full‐time employees (FTEs). 

3.3.2 AEDB´s Organizational Structure 
The AEDB is presently organized around four main departments: 
• Power Projects, which manages RE pilots and IPPs (excluding hydro). 
• Energy Management, groups policy, quality, financing, and hydro functions. 
• Finance and Administration, for institutional management functions. 
• Institute  of  Renewable  Energy  Technology  (IRET),  for  training  and  technical 
capacity development in RETs. 

                                                       
15
  Approved by the Board but not yet officially sanctioned by the GoP. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  20
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

As  mentioned  in  the  previous  section,  78%  of  all  posting  identified  in  AEDB´s 
organizational chart are currently vacant (see Exhibit 9). In particular, several technical 
postings which would be key to the identification and development of renewable energy 
projects remain unfilled. They include: 
1. Director, Hydro 
1. Director, Solar 
2. Director, Wind 
3. Director, Biomass 

Exhibit 9: AEDB Organizational Chart 
Board

Chairman

CEO Secretary

Energy
Power Project Finance & Admin Pro Rector IRET
Management
(General Director) (General Director) (General Director)
(General Director)

Solar Thermal
Policy Director Finance Director
Director
Solar PV Director Hydro Director Admin Director
CDM/Emerging International
Wind Director Technologies Cooperation
Director Director
Provincial
Biomass Director TMM/QA Director Coordination
Director
Marketing/Logistics
Director
 
Source: AEDB. 

The AEDB´ current organizational structure contains most of the key roles that would be 
expected in an organization with its mandate. However, a realignment of some functions 
would  enable  a  clearer  demarcation  of  roles  and  responsibilities,  as  some  anomalies 
appear to exist: 
1. The Director, Hydro belongs to the Energy Management department, whereas all 
other forms of Renewable Energy are allotted to the Power Projects department.  
2. The Finance and Administration department is composed of mixed functions and 
activities (e.g., International and National Coordination, Marketing and Logistics). 
3. The role of the Director, Marketing seems unclear.  

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  21
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

4. Emerging  technologies  functions  would  appear  to  benefit  from  synergies  with 
the  Institute  of  Renewable  Energy  Technology  (IRET)  rather  than  the  Energy 
Management Department 
5. Training  and  Quality  Assurance  functions  would  need  to  be  split.  Quality 
Assurance would need to be relocated to ensure the visibility and independence 
of the function 
6. There  is  no  mention  of  IT  or  business  intelligence  activities  within  the 
organizational structure. 
In Working Paper 4, the consultants have identified several RE generation mixes where 
hydel  is  preponderant,  given,  amongst  other  criteria,  Pakistan’s  abundant  hydel 
potential and its low life‐cycle costs per unit of energy produced. It is worth noting that 
the  AEDB´s  current  staffing  across  different  RETs  does  not  reflect  Pakistan’s  hydel 
priorities  that  would  result  from  a  ‘least  cost’  generation  mix.  Indeed,  the  current 
organogram  shows  AEDB´s  Wind  Directorate  to  be  the  department  with  most  staff.  
Although  this  follows  from  the  discussion  in  Section  3.1.5,  the  AEDB  was  unable  to 
provide a rationale for this bias. 
The lack of detailed job descriptions hindered the consultant’s effort to identify where 
specific key activities and roles lie in the present institutional structure: 
• Economic  assessment  of  renewable  energy  sources,  markets,  and  deployment 
options, as detailed in Working Paper 4.  
• Renewable resource data collection and dissemination, as per AEDB´s mandate. 
• Administration  and  maintenance  of  client  and  vendor  databases,  project  site 
inventory,  archive  of  project  feasibility  studies,  and  other  relevant  information. 
There  is  no  distinct  Information  Technology  and/or  Services  department  to 
support AEDB´s activities and facilitate investor and public enquires. 

3.3.3 Salary Structures 
At the time of writing this report, the AEDB´s salary structure had not been shared with 
the consultants. However, we were given to understand that AEDB´s compensation can 
be commensurate with market rates and that the organization is not strictly bound by 
government  salary  structures.    This  is  stated  explicitly  in  the  AEDB  Ordinance,  which 
assigns the Board the right to regulate: 
• “Terms and conditions along with remuneration and privileges, etc., for 
appointment of officers, staff members, experts, advisors, and consultants, etc.; 
• “Prescription of different scales and grades, etc., for the remuneration and 
privileges of officers, staff members, experts, advisors, and consultants, etc., of 
the Board.” 
Various renewable energy stakeholders in Pakistan interviewed during the course of this 
TA have reported an acute shortage of qualified renewable energy technical staff. This 
would necessarily result in a competitive job market for such professionals, where the 
AEDB might not be best placed to attract the most talented individuals unless it offers 
attractive  working  conditions,  remuneration,  and  benefits  to  its  employees.  At  least  in 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  22
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

terms of job security, long‐term service benefits, contract extensions, and even payment 
of  salaries  on  time—leaving  aside  the  matter  of  actual  compensation  levels—the 
anecdotal evidence of the AEDB’s ability to inculcate employee confidence and faith in 
career advancement appears to have been less than satisfactory so far. 

3.3.4 HRD, Training, and Staff Appraisals 
As part of the overall compensation package, human resource development (HRD) and 
on‐the‐job  training  is  a  key  element  for  recruiting,  retaining,  and  improving  any 
organization’s workforce.  The AEDB has provided its officers the opportunity to attend 
local  training  sessions  and  workshops,  mostly  in  collaboration  with  donor  agencies,  as 
well as participation in international trade fairs, conferences and study tours. However, 
at  this  stage,  there  is  no  structured  training  program  being  carried  out  in  specific 
technical  or  managerial  skills,  nor  does  there  appear  to  be  any  formal  training  needs 
analysis having been conducted.  Course and trainee selection appears to be somewhat 
arbitrary,  subject  to  availability,  rather  than  based  on  specific  and  systematic 
departmental and personnel professional development goals.  There are no regular staff 
appraisal  mechanisms  instituted  that  can  monitor  technical  and  management  skills 
development, other than the standard GoP annual confidential reports (ACRs). 
These  HRD  and  staff  training  and  evaluation  deficiencies  can  seriously  undermine  the 
AEDB’s  ability  to  incrementally  build  its  institutional  capacity,  ensure  the  provision  of 
proper design and management of its expanding programs and projects, and instill the 
necessary  confidence  both  within  its  staff  and  amongst  its  various  interlocutors 
(investors,  donors,  government  agencies,  etc.)  about  its  professional  capabilities  and 
ability to deliver on its functions and pledges. 

3.3.5 Staff Attrition and Morale 
We understand staff attrition to be in the order of 20% per year, which is above average 
acceptable rates. Various reasons can be put forward for this—which can be collectively 
attributed to an overall lack of a truly professional environment that can result in higher 
levels of job satisfaction and future career prospects within the organization for all levels 
of staff—but it is not surprising that they can lead to unnecessary staff turnover, unfilled 
vacancies, and a drain of the AEDB´s scarce resources and nascent experience base. 

3.3.6 Key Findings  

• An organization not fully aligned and structured to meet its strategic objectives. 
• Organizational structure and staffing levels would need to be streamlined, with 
key functions realigned. 
• Inadequate remuneration mechanism, which fails to attract and retain best 
available talent. 
• Lack of HRD and training programs geared towards long‐term professional 
capacity building. 
• Significant staff shortages, especially in key technical roles. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  23
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3.4 Financing 
AEDB´s financing relies on funds, loans, and grants provided by the federal government, 
provincial or local authorities, donor agencies, and charges for services, which are placed 
in  the  Alternative  Energy  Fund  (AEF)  specifically  created  under  the  AEDB  Ordinance  to 
enable it to meet its recurring operational expenses (e.g., salaries, establishment costs, 
etc.) as well as for program and project execution.  Initially, the federal government has 
unwritten  the  entire  expenditure  of  the  AEDB,  until  such  time  that  the  AEDB  can  fully 
finance the AEF from its own resources, charges, and revenue streams. 
During the year 2007‐08, 75% of the Board’s income derived from funds provided by the 
federal government, and only 10% of the total income was generated by AEDB service 
charges  to  private  entities.    Expenses  were  primarily  related  to  personnel  and 
operational costs, with a small amount for reparation and maintenance, as illustrated in 
Exhibit 10. 
The AEF is also used by the AEDB to promote its pilot RE demonstration and deployment 
projects in recent years.  In the years 2004‐05 and 2005‐06, around 46% of the budget 
allocated was to promote the Solar Home Program, which consisted of electrification of 
remote  villages  through  solar  PV  technology,  with  1,001  houses  electrified  under  this 
program (Exhibit 11). 
The financing of AEDB’s focal RES‐E technology so far, wind power, is based on private 
investment in IPPs; at present, seven investors have finished detailed feasibility studies 
and have applied for generation licenses from NEPRA, of which five have been granted.  

Exhibit 10: Summary of AEDB Income and Expenditure, 2007‐ 08 

 
Source: Summary of Income and Expenditure of Alternative Energy Fund during 2007‐08, AEDB. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  24
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 11: Expenditure on AEDB Development Projects 

50.000

45.000
40.000

35.000
30.000
(Mill PKR)

25.000
20.000

15.000
10.000
5.000
0
Pilo Project Pilot Solar Supply Solar
Emerging 100 Solar Solar Fuel cell
Wind Project Homes Chain Bio Diesel Water
Tech Homes Thermal Vehicle
Turbines Micro Program Mechanism Punping

2004/2005 22.400 15.400 9.600 3.900 46.540


2005/2006 3.534 2.400 2.167 40.000 3.000 13.849 11.667 1.271 10.000
2006/2007 9.700 2.276 931 5.000
2007/2008 12.550 3.140 1.525 10.260

 
Source: Summary of budget and expenditures of development projects provided by AEDB 

The  information  provided  to  the  consultants  by  the  AEDB  shows  that  a  budgeting  and 
expenditure  development  process  exists  within  the  organization,  although  the  criteria 
for deciding on allocation of funds is not clear.  At present, the data provided contain ten 
projects for the period 2004‐05 to 2007‐08, including details on allocated amounts and 
expenditures for every project. 
Other  financing  sources  comprise  of  different  international  financing  institutions  and 
bilateral  programs  that  have  granted  funds  for  the  development  of  alternative 
renewable energies, such as those shown in Exhibit 12. 

Exhibit 12: Current Donor Funding of Alternative Energy Programs in Pakistan 

Donor Amount
(Million USD)

UNDP/GEF 3.82
GTZ 3.5
ADB 0.7
USAID 1.9
Total 9.92

Source: Alternative Energy Development Board. 

It is clear that a master plan is necessary to link the AEDB’s detailed annual workplans, 
establishment  and  recurring  costs,  budgetary  allocations,  and  project‐wise  resource 
requirements with sources of government and self‐generated income, IFI financing, and 
other  available  funding  to  provide  for  a  sustainable  and  practical  transition  to  the 
organization’s long‐term financial viability and resource mobilization activities. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  25
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

3.4.1 Key Findings 

• The AEDB relies primarily on the government’s financial support. 
• External financing options have been explored only for commercial wind IPPs. 
• No direct links of budgetary allocations with institutional workplans and targets 
exist. 
• Mechanisms and master plan for mobilizing increased resources for transition 
to future self‐sustainability not addressed. 

3.5 Business Processes 
A set of rules (or procedures) for the establishment of the Board and the conduct of its 
business  have  been  defined.  The  rules  present the  nomination  of  members,  functions, 
duties, meetings, etc.  
A sequence of activities for establishing an RE IPP exists only for wind and small hydro 
power projects in the current policy framework, for which the AEDB is the implementing 
agency.    For  other  RETs,  such  information  has  not  been  developed,  and  the  AEDB’s 
existing business processes are primary focused on promoting wind energy (see Exhibit 
13 for relevant process details). 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  26
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 13: Wind Power Projects – AEDB Activity Flow Chart 

 
Source: AEDB Web Page 

In an organization such as AEDB, detailed business process would be expected to cover 
all core business activities, such as: 
• Annual Planning and Budgeting 
• Employee and Office Management 
• Financial Management 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  27
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• Financial and Administrative Audits 
• Project Management 
• Reporting and Communications 
• Monitoring and Evaluation 
• Information Processing and Dissemination 
• Document Control, Management, and Archiving 
• Public Relations 
• Investor Screening and Evaluation 
• Project Feasibility Assessment 
• Tendering and Bid Evaluation 
• Procurement 
• Inventory 
Apart from annual financial audits conducted by an independent chartered accountant 
engaged by the AEDB, and given that the Board has now been in existence for five years, 
a general audit by the Auditor General of Pakistan’s office would also prove beneficial at 
this stage.16  It is commendable that an independent administrative audit of the AEDB is 
presently being undertaken by the GoP, the findings of which were not available at the 
time of writing of this report. 

3.5.1 Key Findings 

• Business processes need to be developed in key functional and administrative 
areas and fully documented in a set of AEDB standard operating procedures 
(SOPs).  
• AEDB should establish, in addition to annual financial audits, a schedule of 
externally‐conducted institutional and performance audits in order to be able 
to highlight key deficiencies and undertake timely remedial strategies. 

3.6 Market Intelligence, Communication, and Information 
Systems 
From  its  inception,  the  AEDB  has  stressed  public  awareness‐raising  about  renewable 
energy use and undertaken sustained interaction with private investors interested in RE 
IPPs.    This  has  been  achieved  largely  through  individual  meetings,  promotional  road 
shows,  conferences  and  workshops,  media  interaction,  participation  in  trade  fairs  and 
seminars, and active advocacy on the part of the AEDB of RE stakeholder interests within 
the government. 

                                                       
16
  As per Auditor General’s (Functions, Powers and Terms and Conditions of Service) Ordinance, 2001 (XXIII of 2001). 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  28
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

However, as with many of its other functions, this important role is performed largely on 
an  ad  hoc  basis,  making  use  of  available  opportunities  (e.g.,  donor  support,  vendor‐
sponsored events, trade events, etc.) or personal initiative by key officials.  There is no 
separate budgetary provision or plan for promotional and awareness raising activities by 
the  AEDB  in  line  with  its  overall  organizational  workplan  objectives.    In  fact,  partly 
because of the disconnect between its public relations vigor and actual implementation 
capacities, the organization has often suffered the fallout of an ‘oversell’, especially with 
regard  to  wind  IPP  development  (against  LoIs  publicized)  and  actual  RE  deployment 
(against oft‐repeated GoP RE targets). 
The  organization  has  so  far  also  not  been  the  focal  point  for  the  development  and 
dissemination  of  RE  resource  potential  data,  which  is  essential  for  facilitating  investor 
actions beyond the initial expressions of interest.  A key function of the AEDB could be as 
the  custodian  and  clearing  house  of  consolidated  data,  including  the  conduct  of 
additional  resource  mapping  and  measurements,  which  could  then  be  made  publicly 
available at little or no cost to all concerned stakeholders.  Instead this function has so 
far  been  housed  in  disparate  organizations,  each  of  which  follow  their  own 
standardization,  measurement,  and  dissemination  protocols,  making  the  information 
difficult  and  costly  to  access  as  well  as  undermining  its  bankability  and  currency.    For 
instance,  ground‐based  wind  monitoring  is  conducted  and  collated  by  the  Pakistan 
Meteorological Department (PMD), and does not conform to internationally acceptable 
measurement standards; computed countrywide solar insolation and wind speed maps 
developed by the US NREL are available with the AEDB but not placed on its web site, 
nor yet been cross‐verified with actual existing values; small hydro site identification and 
feasibility  studies  conducted  by  GTZ/KFW  reside  with  the  PPIB,  but  have  not  been 
updated or added to for over a decade; information on bagasse use is collected by the 
Pakistan Sugar Mills Association (PASMA), but not publicly available; there is little or no 
consolidated  information  on  other  biomass  resources,  and  what  exists  is  scattered 
amongst various institutions (e.g., NARC); etc. 
The  consultant  has  been  made  aware  of  several  small  information  repositories  within 
the AEDB, such as organizations involved in the development of biomass/waste/biogas, 
and a list of solar equipment suppliers. 
However, the consultant has not come across the sort of organized, detailed, and up‐to‐
date  databases  that  a  central,  one‐window  organization  such  as  the  AEDB  would  be 
expected to maintain, for example: 
• Comprehensive  databases  of  technologies,  international  trends,  manufacturers, 
vendors,  potential  investors,  key  contacts,  organizations,  associations,  events, 
etc., relevant to RE development. 
• RE  resource  and  market  data  (wind  data,  solar  maps,  comparative  costs, 
consumers and applications, geographical potential, etc.). 
• Library  and  information  services  on  technical  aspects  of  RE  projects  and 
implementation mechanisms. 
• Database  of  project  sites,  feasibility  studies  and  project‐specific  information  by 
RET. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  29
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• Directory  of  RE  financing  options,  programs,  and  mechanisms,  along  with 
information on eligibility criteria and application procedures. 
As  part  of  its  knowledge  transfer  and  sharing  role,  the  AEDB  would  need  to  log  and 
update such information on a systematic and regular basis, with convenient access and 
dissemination  mechanisms  set  up  (such  as  through  a  much  expanded,  data‐intensive 
web portal).  To the extent that related information is presently being processed by the 
AEDB,  it  is  done  in  a  largely  unorganized  manner,  reducing  its  utility  and  convenience 
both for the information seeker as well as the provider. 
The  AEDB  is  currently  a  member  of  the  Pakistan  Wind  Energy  Association  and  World 
Wind Energy Association. The Consultant has not been made aware of any other trade 
or association memberships by the AEDB, nor of any significant publications to its credit.  
The  membership  of  relevant  professional  bodies  of  international  stature,  and 
contribution  to  reputable  journals  on  RE  technologies  and  applications,  should  be  an 
important  means  by  which  the  AEDB  can  elevate  its  own  technical  capabilities  and 
professional  credibility,  channel  technology  transfer,  facilitate  international 
collaboration and partnerships, and visibility. 

3.6.1 Key Findings  

• Information collection and dissemination role of the AEDB is not organized, and 
key elements remain with other institutions with little coordination or 
consolidation. 
• The AEDB should assume the role of a central clearing house of information on 
all aspects of RE development, but at present its capabilities in this respect are 
very limited. 
• Interaction with international RE actors, activities, associations, fora, and 
publications needs to be undertaken through more meaningful collaboration 
and participation to expedite transfer of knowledge, skills, and help build the 
AEDB’s credibility. 
• The AEDB has been successful in raising the profile of RE in general, but has not 
been able to follow up effectively on the interest and expectations thus 
created. 
• Standalone PR activities are regularly undertaken, but do not roll up to a master 
information and communication plan. 
• Absence of structured and detailed data repository and dissemination 
protocols, infrastructure, and mechanisms. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  30
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

4 Remedial Measures 
In this section, we suggest basic remedial measures that the consultants deem necessary 
to: 
• Transform  the  AEDB  into  a  more  professional,  streamlined  entity  that  is  better 
able  to  deliver  on  its  stated  objectives  by  filling  in  existing  capability  gaps  in 
terms of resources and operations. 
• Augment the AEDB’s capacity in line with the consultants recommendations on 
the  medium‐term  RE  policy  regime,  to  ensure  effective  implementation  of 
specific roles and facilities envisioned therein. 
As with the preceding diagnostic evaluation of the current capacity of the AEDB, future 
capacity‐building recommendations are addressed for all primary aspects relevant to the 
organization’s functioning: 
• Mandate and Mission Objectives 
• Strategy and Planning 
• Business Processes 
• Human Resources and Training 
• Finance 
• Market Intelligence, Communication, and Information Systems 

4.1 Institutional Mandates, Roles, and Targets 
Given  that  the  AEDB  is  still  a  relatively  young  organization,  and  that  the  next  phase 
(medium term) will be crucial to its ultimate success as an effective arm of the GoP for 
achieving its RE deployment targets, a broad strategic capacity development outline can 
be drawn up for the organization that allows its systematic evolution into a professional 
agency  that  can  play  its  assigned  leadership  role  more  effectively  and  instill  greater 
confidence amongst all RE stakeholders in its capabilities.  Such a strategic vision for the 
AEDB  would  consolidate  on  its  existing  strengths  and  resources,  additional  GoP 
commitments, available donor‐provided technical assistance, as well as activities to be 
undertaken by the AEDB itself in the future.  Such a strategy would consist of: 
• An  economic  cost‐benefit  analysis  of  various  commercially  mature  RES‐E 
technologies  readily  implementable  in  Pakistan,  with  a  technology‐wise 
prioritization  of  capacity  development  potential  based  on  least  cost  economic 
principles (including, to the extent possible, externalities).  This would define the 
basic rationale, targets, and mix to be developed in the long run towards which 
all  of  AEDB’s  actions  can  be  directed.    To  an  extent,  Working  Paper  4  provides 
the  necessary  methodology  for  this  purpose  which  can  be  further  refined, 
discussed amongst all stakeholders and potential investors, and updated by the 
AEDB from time to time. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  31
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• The  adoption  of  a  policy  approach  towards  developing  RE  IPPs,  based  on  the 
economically feasible RETs and targets determined above, including pricing, tariff 
mechanisms,  incentives,  and  regulatory  measures  required  to  facilitate  private 
and  public  investments  in  such  projects,  and  leveraging  of  available  local  and 
international  facilities  towards  this  end  (e.g.,  fiscal  measures,  carbon  financing, 
grants  and  technical  assistance,  etc.).    Working  Paper  5  recommends,  for  the 
medium term (i.e., to at least 2014), the establishment of RET‐wise feed in tariffs, 
including  an  upper  RES‐E  price  cap  (based  on  system‐wide  long‐term  marginal 
cost  of  incremental  supplies),  and  limited,  tendered  quotas  of  some  key  RETs 
that may presently be uncompetitive. 
• The  development  of  an  off‐grid  RES‐E  deployment  plan,  with  provisions  for 
operational  and  financial  sustainability  into  the  future,  on  a  large  scale.    The 
development of pilot rural electrification schemes should only be undertaken as 
a prelude to such a program to test its elements and deployment options, not as 
a  standalone  activity  in  itself  as  is  presently  being  done  under  the  Roshan 
Pakistan  program.    Working  Paper  6  outlines  a  plan  for  the  establishment  of  a 
nationally‐funded  off‐grid  RE‐based  electrification  program  that  can  serve  as  a 
useful model for detailed design. 
• The  development,  through  additional  TA  support,  of  programs  and  policies  for 
facilitating  non‐power  RE  applications  (such  as  biogas  and  biofuels),  in  concert 
with relevant suppliers and market players. 
• Based  on  the  above,  the  development  of  quarterly,  annual,  and  five‐year  work 
plans  for  the  AEDB,  for  both  routine  as  well  as  program  and  project  activities 
envisaged, along with specification of the corresponding timelines, financial and 
human  resource  requirements,  organizational  structures,  business  processes, 
KPIs, and monitoring and reporting means.  Such plans should be developed to 
build up AEDB’s capacity gradually over the plan period, prioritizing key actions 
up front and deferring less critical elements of its mandate to later stages.  It is 
important that such a planning process clearly defines the focus and methods to 
be  adopted  for  achieving  both  short‐  and  long‐term  objectives  of  the 
organization.    For  the  next  at  least  three‐year  period,  an  upfront  lump  sum 
provision  of  the  necessary  financial  resources—to  help  the  AEDB  fund  its 
establishment and recurring requirements and recruit the best available talent—
should be provided by the GoP and supplemented by donor grants.17 
• Mechanisms  for  stakeholder  feedback,  internal  performance  evaluation, 
planning  and  policy  updates,  continuing  staff  and  technical  resource 
development, and eventually self‐generated revenues, should become the basis 
for  the  sustained  growth  and  development  of  the  AEDB  beyond  the  next  five 
years. 
Clear linkages between the different components of the AEDB´s strategic roadmap are 
necessary  to  develop  an  operational  approach  which  is  both  implementable  and 
measurable.  Exhibit  14  highlights  the  links  between  the  proposed  institutional  vision, 
                                                       
17
  Much as was the case initially for the USAID‐supported establishment of the Energy Wing, P&D Division, and PPIB. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  32
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

mission  statement,  strategic  objectives,  critical  success  factors,  and  targets  which  are 
discussed further below. 

Exhibit 14: Proposed AEDB Strategic Roadmap 
Strategic
Vision Mission CSFs KPIs/Targets
Objectives
• Set up planning unit
• Number plans & planning reviews
Promote the development of renewable energy technologies in Pakistan by encouraging

• Conduct inter-agency planning workshops


private sector participation and ensure financing to support RE implementation in an

• Understand activity interdependencies • Number workshops planned and


Develop national strategy, • Set up achievable and measurable goals delivered in a year
policies, and plans • Establish strong relationship with MoWP • Policy and program initiatives
Promote all alternative energy resources in Pakistan

• Conduct detailed RE economic evaluation undertaken


• Seek private and institutional
• Funding mobilized each year
funding/donors

• Define evaluation criteria


• Number of pilot projects in a year
• Define clear and auditable certification
efficient and transparent manner

Evaluate, monitor, and criteria • Time to finish evaluation of projects


certify RE projects • Define monitoring indicators and process • Number of certify projects
• Identify qualified resources to • Number of qualified staff in place
evaluate/monitor and certify RE projects

• % of LOIs materialized
• Set up as one-window facility • % of electricity produced from RE
Facilitate power generation • Identify and promote RE project • # generation licences issued
through RE sources: opportunities • Cost/benefit of on-grid RE projects
• Conduct RES-E feasibility studies • 25 TWh/year RES-E by 2020
Ensure 10.3% of national • Manage OGREA funds and award off-grid • # villages electrified
power capacity from RE by concessions with provincial REAs
• # households electrified
2020 • Carry out technical and financial • Cost/benefit of off-grid RE
evaluations of on-grid proposals and off-
• Bankability of feasibility studies
grid authorization tenders
• # months taken for project
Electrify 1,968 villages in • Provide assistance in licensing and tariff implementation
through RE by 2014 petitions
• Coordinate activities with national • % of private sector involvement
agencies, provide policy inputs, and assist • # projects developed
Build up indigenous RE in RE FIT review • # beneficiaries from projects
industry with participation of • Set up RE demonstration projects and • # months project implementation
private sector awareness programs • # villages electrified
• Establish RE training through IRET • % RETs indigenized
 
Note: CSF: Critical success factor, KPI: Key performance indicator. 

In our preceding diagnostic, we highlighted some of the roadmap components that were 
missing  at  present  in  the  AEDB’s  current  capabilities  and  plans.  This  is  particularly 
applicable  to  the  critical  success  factors  (CSFs)  and  associated  key  performance 
indicators/targets  (KPIs)  with  respect  to  overall  RE  deployment  strategy,  RET 
prioritization, institutional planning, and project evaluation and pipeline development. 

4.2 Overall Strategic and Planning Capability  
Pakistan’s incremental electricity demand for the period 2008‐2020 is about 152  TWh, 
and  according  to  the  consultants’  analysis,  renewable  technology  penetration—taking 
social costs into account—corresponds to 25 TWh per year by 2020 (see Working Paper 
4).  Under the social cost assessment, not only hydel and biomass plants, but also biogas 
(sewage,  landfills,  etc.)  and  wind  power  plants  would  be  required  to  replace  CCGTs 
running  on  both  FO  and  natural  gas.    It  is  also  important  to  note  that  some  RES‐E 
technologies, such as solar PV or solar thermal, are not economically feasible as on‐grid 
solutions in current price/technology conditions.  The penetration of waste‐to‐energy in 
the medium term is considered very small as it is a very expensive technology, but could 
be developed for its substantial other benefits (i.e., sanitation and health). 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  33
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

In  order  to  achieve  this  penetration,  it  would  be  necessary  to  build  around  1,738 
renewable  projects18  relying  on  a  combination  of  different  RE  technologies  during  the 
period  2008‐2020,  assuming  different  construction  times  (Exhibit  15)  for  each 
technology and that feasibility assessments in each case would add another year to the 
project timeline. 

Exhibit 15: Economically Feasible RES‐E Projects by Technology (2020) 

RE Technology Estimated Number of Typical Construction


Projects Period
(Years)

Landfill Gas 11 0.5


Sewage Gas 3 0.5
Biogas 1,171 0.5
Biomass Conversion 57 0.5
Cogeneration 31 0.5
Waste-to-Energy 0 1.0
Wind 22 1.5
Small-scale Hydel 443 2.0

A  high‐level  indication  of  the  annual  penetration  rates  by  RET  for  these  projects  is 
presented in the chart in Exhibit 16 below and the indicative mix of RETs in overall RES‐S 
supply in 2020 is shown in Exhibit 17. 
Although at this stage the exact numbers are only indicative, based on the consultants’ 
preliminary  determination  of  the  optimum  penetration  of  RES‐E  under  social  cost 
considerations derived from a limited data set, they represent the kind of more detailed 
and refined technology‐ and project‐wise economic feasibility assessment and portfolio 
development  that  the  AEDB  needs  to  undertake—and  review  on  a  continuous,  annual 
basis—on which to underpin its short‐, medium‐, and long‐term target‐setting and work 
plan development. 

                                                       
18
  Based  on  RET‐wise  supply  curves  developed  for  Pakistan  in  Working  Paper  4.    Number  presented  only  for 
illustrative  purposes;  actual  project  identification  would  require  more  detailed  feasibility  and  current  cost 
estimation. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  34
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 16: Annual Future Deployment of Feasible RES‐E Projects in Pakistan 

Technology /Years 1 2 3 4 5 6 7 8 9 10 11 12

Hydel
45
45 Projects
Projects the
the first
first 33 years
years and
and 443
– Feasibility assessment projects
44
44 projects
projects the
the rest
rest ofof years
years
– EPCIC

Co-gen 33 Projects
Projects the
the first
first 99 years
years and
and 31
– EPCIC 22 projects
projects the
the rest
rest two
two years
years projects

Biomass
66 Projects
Projects the
the first
first 22 years
years and
and 57
– Feasibility assessment 55 projects
projects the
the rest
rest ofof years
years projects
– EPCIC

Wind
– Feasibility assessment 22 Projects
Projects every
every year
year 22
projects
– EPCIC

Biogas
107
107 Projects
Projects the
the first
first 55 years
years and
and
– Feasibility assessment 1171
106
106 projects
projects the
the rest
rest ofof years
years projects
– EPCIC

Landfill
11
– Feasibility assessment 11 project projects
project on
on year
year 77 and
and 22
– EPCIC projects
projects on
on the
the next
next years
years

Sew
3
– Feasibility assessment projects
11 Project
Project for
for in
in year
year 5,6
5,6 and
and 77
– EPCIC
 
 

Exhibit 17: Optimum Penetration of RES‐E to 2020 at Social Cost                                                 

RES-E Penetration (@ Social Cost)


(Tech; TWh/a; %)
SS Hydel
11.2 Landfill
44.3% 0.3
1.2%

Sew
Wind
0.1
2.8
0.2%
11.1%

Solar Th Biogas
0.0 2.2
0.0% Co-gen
8.5%
4.6
WTE 18.0%
PV
0.0 Biomass
0.0
0.2% 4.2
0.0%
16.5%

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  35
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

4.3 Human Resource and Technical Capability 
As  mentioned  in  the  previous  section,  most  of  the  main  departmental  functions  are 
already indicated in the AEDB´s current organizational structure (Exhibit 9). We would, 
however, suggest a generally leaner and flatter organization, with more technical depth 
and  stronger  management  capability  in  order  to  support  the  AEDB´s  future 
development.  In  particular,  there  should  be  a  clear  demarcation  between  the 
organization’s core activities and various support functions. Support functions should be 
simplified  by  having  clearly  defined  departments,  such  as  IT,  Finance,  Admin,  and  HR. 
New  functions,  such  as  Legal  and  Institutional  Communications,  have  been  regrouped 
under Corporate Services. The Quality Assurance role, previously shown under Director 
General,  TMM/QA,  is  now  shown  reporting  to  the  CEO.  The  key  roles  of  the 
organizational structure are shown in Exhibit 18. 

Exhibit 18: Proposed AEDB Organization Chart  

Board

Chairman

CEO

•Legal Corporate
Quality Assurance
•Communication Services

R&D RE Administration and


On-Grid Off-Grid IT HR Procurement
Finance
/Logistics

Technical Technical • Field testing of • Administration • Management of • Recruit, select • RFIs


renewable budgets ITC resources
•RES-E projects •RES-E projects technologies and train
• Train and • RFPs
•Develop •Project • Tax reports
• Development of support users • Promote career
feasibility studies supervision • Payroll • Supplier
prototype pilot development
• Project •Construction programs • Develop and selection for
management supervision • Accounting implement new • Support
records pilots
•Contract • Technical systems
research and employee
negotiation • Grant/subsidy • Data security training • Logistics for
business management
•Technical Commercial intelligence and protection pilots
evaluation of • Fund • Procurement
tenders •Policy and • Conduct • Coordinate • Tender,
management incidence activities
commercial workshops and evaluate, and
incentives training courses resolution
award off-grid
•Evaluate projects authorizations
•Manage licenses
Commercial •Tariff & regulation
assistance
• Policy and
commercial •Fund raising
• Management of •Relation with
licenses institutions and
• Tariff & donors Core Activities Support Functions
regulation •Demarcate off-
assistance grid electrification
• Manage CDM targets
projects

 
The On‐grid Technical Projects department would regroup thermal, solar, wind, biomass 
and  hydro  technical  competencies  that  are  presently  separately  compartmentalized. 
Particular  emphasis  should  be  given  to  this  core  department  with  regard  to  qualified 
staff and training needs. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  36
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Based on the organizational structure proposed, detailed job descriptions at the Director 
levels for each department, specifying the duties and responsibilities, qualifications, and 
required experience have been developed (see Appendix B). 

4.3.1 Staffing Levels 
Appropriate personnel levels have been estimated under the new AEDB structure.  It is 
estimated that the AEDB would require approximately 80 FTEs to fulfill its RE mandate 
based on working assumptions which we have detailed below. 
The  majority  of  the  80 FTEs  would  be  assigned  to  on‐  and  off‐grid  projects.  Exhibit  19 
provides a break of staff by department.  

Exhibit 19: Staff by Department 

Department Full-time Employees


(FTEs)

Core

On-grid 37

Off-grid 12

R&D 7

Support

Admin & Finance 5

IT 3

Human Resources 4

Procurement/Logistics 5

Corporate Services 3

Quality Assurance 2

The  associated  proposed  organizational  structure  (Exhibit  20)  suggests  a  leaner 


organization focused on the AEDB’s core capabilities in on‐ and off‐grid RE development. 
The proposed staffing levels assume that all core activities will be performed in‐house; 
however,  some  technical  activities,  such  as  feasibility  studies,  etc.,  should  be 
outsourced.  The  staff  productivity  ratios  for  the  technical  activities  are  based  on  the 
number of projects to be developed every year to achieve the 2020 targets (on grid and 
off grid) as estimated in Exhibit 16.  Exhibit 21summarizes the number of annual on‐grid 
RES‐E projects, split by technology, that the AEDB should target implementing to 2020 
and  the  corresponding  staffing  requirements,  while  Exhibit  22  does  the  same  for  the 
staff required for RES‐E based off‐grid village electrification. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  37
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 20: Proposed AEDB Organizational Structure 

Board

Chairman

CEO

Corporate Quality
services Assurance

Procurement/L
On-Grid Off-Grid R&D RE Administration &
IT Director HR Director ogistics
Director Director Director Finance Director
Director

Technical Commecial Technical Commecial Finance Procurement Logistics


Admin Deputy IT Deputy HR Deputy
Deputy Deputy Deputy Deputy Deputy Deputy Deputy

Solar

Geothermal

Biomass &
Biogass

Professional Professional Professional Professional Wind

Assistant Assistant Assistant Assistant Assistant Assistant Assistant Assistant Assistant Assistant Assistant

1
3 1 2
1 1 1 1 1 1 1
1 1 1 1 1 1 1 2 1 1

16 16 5 2 4

1 1 1 1 2 1 1 1 1 1 1

18 1 18 7 1 4 10 2 3 2 5 4 2 1 2 80

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  38 
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Exhibit 21:  On‐grid Technical Staff Estimate 

RE Technology Annual Projects

Hydel 45
Biomass 6
Wind 2
Biogas 107
Sewage and Landfill Gas 1
Total 161

Staffing

Productivity Ratio 10

Total On-grid Technical FTEs 16

Exhibit 22: Off‐grid Technical Staff Estimate 

Working Assumptions

No. of Villages to Electrify by 2020 7,874

No. of Remaining Years to 2020 12

No. of Villages To Be Electrified Annually 656

No. of Villages Electrified/FTE 130

Total Off-grid Technical FTEs 5

4.3.2 Salary Structures 
For key technical roles, the AEDB needs to be able to offer competitive, market‐based 
rates of staff remuneration and benefits, and therefore should be at liberty to deviate 
from the standard GoP salary scales, which the AEDB Ordinance permits it to do.  

4.3.3 Training  
In addition to technical courses on key topics pertinent to the core functions, it is critical 
that staff members are familiar with methods for determining project economics, as well 
as  being  well‐versed  in  project  management  issues,  in  particular  for  evaluating  and 
implementing  commercial‐scale  projects  and  programs.  Three  types  of  courses  are 
therefore required: 
• Technical training courses covering priority RETs, such as SS hydel, wind, solar PV 
and thermal, and biomass conversion 
• Economics and financial courses related to the development of RES‐E projects 
• Project management/private & public project development 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  39 
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

4.3.4 Technical Training Courses 
For  each  type  of  technology,  the  technical  training  courses  should  cover  at  least  the 
following topics, suited to different tiers of the technical staff: 

Solar Energy 
• Types of solar technologies (both PV and thermal) and systems (distributed and 
centralized) and comparative performance characteristics and applications 
• Solar radiation, characteristics and measurement (propagation of solar radiation 
in  the  atmosphere,  solar  constant,  terrestrial  radiation,  radiation‐measuring 
instruments,  estimation  of  solar  radiation  on  horizontal  and  inclined  surfaces, 
etc.) 
• Basic heat transfer in solar collectors, selected surfaces, flat‐plate collectors (air 
and water) 
• Testing and standardization of solar thermal appliances and systems 
• Market  potential,  costs,  market  and  R&D  trends,  techno‐economic  analysis  of 
solar  PV  and  thermal  utilization,  barriers  to  technology  diffusion,  future 
prospects, etc. 
• Local assembly and manufacture and systems integration 

Biomass Energy 
• Characterization  of  biomass  resources  (determination  of  calorific  value, 
elementary analysis, determination of ash content, etc.) 
• Thermo‐chemical  conversion  technologies  and  main  design  characteristics, 
processes based on combustion (furnace for the combustion of biomass, power 
generation, cogenerated heat) 
• Biomass processes (biomass gasification, pyrolis, etc.) 
• Economic  aspects,  present  status  and  prospects  in  the  near  future,  potential 
markets, and technology indigenization 

Wind Energy 
• Wind resource assessment, measurement standards, and mapping 
• Design and layout of wind farms, including wind harvest optimization 
• Wind turbine technology and ancillary systems, costs, and indigenization 
• Grid Integration of wind turbines, backup power requirements, quality issues 
• Testing and certification of wind turbines 
• O&M aspects of wind farms 
• Environmental assessment of wind projects, externalities 
• Economic and financial evaluation of wind IPPs 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  40
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Hydel Energy 
• World trends in hydropower development, advantages and disadvantages  
• Hydropower technologies, turbine types 
• On‐ and off‐grid SS hydel applications and markets 
• Hydropower economics and financial evaluation 
• Characteristics components of SS hydropower systems 
• Tools for micro hydropower (MHP) system design 
• Principle causes of MHP failures, and O&M requirements 
• Community management of MHPs  

Economics and Financial  
• Recent trends shaping current and future international project finance 
• Fundamentals  of  economic  assessment  (cash  flows,  inflation,  time  points  and 
periods,  discount  rates,  cost  of  capital,  present  value,  taxes,  fixed  charge  rate, 
financing, investor perspective, uncertainty and risk cover, selection criteria and 
evaluation matrices, etc.) 
• Tools  for  financial  and  economic  analysis  (net  present  value,  life‐cycle  cost, 
revenue requirements, levelized cost of energy, annualized value, internal rate of 
return,  payback  period,  benefit‐to‐cost  ratio,  savings‐to‐investment  ratio, 
integrated,  integrated  resource  planning,  consumer/producer  surplus, 
comparative costs, avoided costs, marginal costs, etc.) 
• Special issues in RE assessment (system boundaries, system sizing, plant factor, 
externalities,  government  investments,  backup  and  hybrid  systems,  storage 
requirements,  operation  and  maintenance,  capacity  and  energy  value,  salvage 
and decommissioning, unequal lifetimes, etc.) 
• Project  financial  modeling  and  analysis,  including  techniques  for  designing  and 
using spreadsheet‐based project financing models 
• Advanced techniques for risk modeling and quantification  
• Design of project finance models for public sector comparison (PSCs) and value‐
for‐money (VFM) benefits of project financing proposals 
• Financial  modeling  applied  in  the  renegotiation  of  infrastructure  concession 
contracts and financial restructuring 

Project Management and Private­Public Project (PPP) Development 
• Designing policy priorities and objectives for PPP and efficient SERVICE Delivery 
• PPP strategies and structuring options 
• Planning for and feasibility of PPP projects (pre‐feasibility planning and analysis 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  41
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• Feasibility  study  requirements:  economic,  financial,  social,  legal/regulatory,  and 


technical criteria 
• Risk identification, mitigation, and allocation programming 
• Procurement and contract monitoring 
• Designing  strategic  frameworks  for  PPP,  legal  prerequisites  for  promoting 
investment 
• Developing the institutional framework for improved service delivery, promoting 
improved service delivery through competition and contract compliance 

4.4 Financing 
This section provides high‐level budgetary indications for the development of the 2020 
RES‐E  targets  for  Pakistan.  In  particular  we  focus  on  two  key  funding  requirements 
relevant to RES‐E deployment in Pakistan: 
• Expenditures for on‐grid RES‐E projects 
• Expenditures for off‐grid RES‐E projects. 

4.4.1 On­ grid Expenditures 
For on‐grid deployment, RES‐E projects would be financed by private investors from the 
feasibility  stage  through  to  commissioning  and  operation,  in  the  independent  power 
producer  (IPP)  mode.  The  only  exception  to  this  is  hydel  (and  possibly  some  biomass‐
based  generation  schemes)  where  we  suggest  that  the  AEDB  finance  initial  feasibility 
studies, given the small size of the projects involved and where this could help lower the 
transaction  costs  for  private  developers,  an  also  help  identify,  expedite,  and  facilitate 
the overall investor application and project development process.  
We  estimate  there  are  approximately  99  SS  hydel  projects  to  be  developed  between 
now and 2020. A feasibility study for a SS hydel project costs to the order of USD 20,000 
to 30,000. Therefore, the total budget for hydel feasibility development would be USD 3 
million.  

4.4.2 Off­grid Expenditures 
Given  the  social  dimension  of  off‐grid  projects,  these  would  be  mostly  funded  either 
through government grants/funds or via local, donors, and other private or civil society 
(e.g., NGOs, etc.) sponsors. Based on the target put forward in Working Paper 6 for rural 
electrification  (i.e.,  1,850  villages,  or  25%  of  7,400  off‐grid  villages  identified  for  RE‐
based  electrification  in  the  MTDF  still  remaining  to  be  electrified  at  the  end  of  the 
Roshan Pakistan program’s first phase) during the medium‐term (to 2014), we anticipate 
that approximately USD 519 million would be required for this purpose. 

4.5 Business Processes 
In  the  first  instance,  the  current  working  procedures  at  the  AEDB  would  need  to  be 
properly documented. At a minimum these procedures should cover the following areas: 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  42
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• Annual Planning and Budgeting: Based on project development plans, recurring 
expense heads, capital investment requirements, expansion and upgrade needs, 
training and HRD, other direct expenses (ODCs) and overheads (OHs). 
• Employee  and  Office  Management:  Employee  handbook,  rules  of  business, 
workplace policies and protocols, administrative procedures, etc. 
• Financial  Management:  Accounting  procedures,  accounting  and  financial 
reporting software, transaction handling, entries, approvals and verification, etc. 
• Financial  and  Administrative  Audits:  Conformity  with  accepted  accounting 
practices,  accounts  documentation,  independent  chartered  accountant  audits, 
internal and external administrative audits, etc. 
• Project  Management:  Deployment  of  project  management  tools  and 
procedures, project tracking and monitoring, client interaction and coordination, 
inter‐agency liaison, etc. 
• Reporting  and  Communications:  Internal  monthly,  quarterly  and  annual 
reporting,  report  formats,  lines  of  communication,  internal  information  access 
and control, external reporting, report directories and archiving, etc. 
• Monitoring and Evaluation: M&E protocols, mid‐course evaluations, remediation 
mechanisms, and feed‐back loops. 
• Information  Processing  and  Dissemination:  RE  resource  data  collection, 
database development, and dissemination, public access mechanisms, technical 
data repository and library implementation, external sourcing and subscriptions, 
market  intelligence,  financial  and  costing  information,  investor  and  consumer 
advisory services, establishment of directories and metadata links, etc. 
• Document Control, Management, and Archiving: Physical document cataloguing 
and archiving, electronic file storage and logging, online and physical search and 
retrieval systems, duplication and backup provisions, content classification, etc. 
• Public  Relations:  Annual  public  relations  campaigns  and  awareness  raising 
programs,  seminars,  workshops  and  road  shows,  media‐based  RE  information 
dissemination,  educational  and  targeted  events,  investor  liaison  and  facilitation 
mechanisms, client and investor feedback response systems, etc. 
• Investor  Screening  and  Evaluation:  Background  and  credit  worthiness  checks, 
minimum information requirements, prioritization, terms of engagement, etc. 
• Project  feasibility  assessment:  Project  and  site  identification,  content 
development, contracting, evaluation and due diligence, dissemination, etc. 
• Tendering  and  Bid  Evaluation:  Tender  design,  procedures  and  terms  for  bid 
acceptance,  bid  evaluation  and  ranking,  contract  design  and  award,  contract 
negotiations and management, contractor verification and job acceptance, etc. 
• Procurement:  Procurement  Procedures,  cost  quotations,  supplier  criteria, 
validation and acceptance, performance and quality guarantees, etc. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  43
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

• Inventory  Control:  Inventory  cataloguing  and  tagging,  record  maintenance  and 


updates, periodic audits, etc. 
These  working  procedures  would  need  to  detail  the  step‐by‐step  activities  required  to 
perform each of the subtasks involved. In this respect, sample processes and procedures 
from other relevant established organizations (e.g., PPIB, OGDC, etc.) could be used as a 
basis  by  the  AEDB,  while  some  could  be  custom‐tailored  or  developed  from  scratch 
following ‘work breakdown’ principles). 
A  second  step  would  be  a  complete  review/audit  of  the  procedures  by  a  qualified 
auditor  to  assess  (a)  the  validity  of  the  procedures  and  (b)  compliance  level  amongst 
various AEDB departments and staff levels. 
Ultimately,  the  AEDB  could  seek  accreditation  as  a  quality  business  entity  by  an 
international agency (say, to ISO 9000 standard) in order to consolidate its position as a 
center of excellence in RE and set an example for the industry at large. 

4.6 Communication, Marketing, and Business Intelligence 
At the national level, AEDB’s communication and marketing activities must be enhanced 
in order to extend the renewable power knowledge base and to raise general awareness 
about renewable energy sources amongst stakeholders and energy consumers.  For this 
purpose, a strong relationship with relevant institutional agencies (e.g., PCRET, NEPRA, 
etc.) and sources of business information  must be established. 
A  first  step  in  this  direction  would  be  the  development  of  an  institutional  business 
intelligence  plan,  on  which  such  capability  could  be  gradually  built  up.    This  would 
comprise of, at a minimum, the following main elements: 
• Directories  of  local  and  international  RE  investors,  manufacturers,  equipment 
vendors,  consultants,  service  providers,  institutions  and  implementing  agencies 
(government, private sector, NGO, CBO, ESCO, etc.), key individual contacts, and 
financing institutions (commercial bank and leasing, IFI, carbon market, special‐
purpose funds, etc.). 
• Updated  information  base  of  commercially  viable  RE  technologies,  applications 
and  markets,  delivery  mechanisms,  promotional  programs,  implementation 
experience, comparative costs, pricing and tariffs, etc. 
• Listing  of  international  information  and  networking  resources  (journals,  web 
sites,  online  databases, trade  news services,  industry  associations,  conferences, 
equipment  fairs,  etc.),  including  membership,  subscription,  and  participation 
plans revised on an annual basis. 
• Development,  improvement  and  expansion  of  in‐house  information 
dissemination mechanisms for handling public queries and information requests, 
investor  needs,  internal  institutional  knowledge  requirements,  compilation  and 
publication of RE resource data and promotional materials employing library and 
document/digital  archiving  systems,  computerized  databases  and  metadata 
catalogs,  data‐rich  website  and  web  portals,  newsletter  and  other  periodicals, 
and client feedback response systems. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  44
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

These systems, once developed at the AEDB, can then be easily replicated or linked with 
similar  provincial  level  marketing  capabilities  at  AEDB  suboffices  or  relevant  provincial 
government agencies dealing with RE promotion. At the national and provincial level, an 
annual schedule of promotional and informational workshops and seminars would also 
need to be planned and conducted each year, to keep stakeholders abreast of RE market 
trends,  technologies,  policy  and  regulatory  issues,  financing  opportunities,  and  the 
activities and facilities undertaken by the AEDB and other institutional service providers. 

4.7 Institutional Linkages 
Formal linkages of key institutions are required to encourage and develop a coordinated 
approach to RE development. Exhibit 23 maps the major stakeholders which would need 
to be considered. 
 

Exhibit 23: RE Stakeholder Map 

Consumers

Interest
Groups

AEDB Employees
Suppliers
Local Govts
PPIB Donors
Media WAPDA Auditor
NGOs
IPPs
AEDB
KESC
Investors MPs

MoWP
NEPRA

DISCOs

Unions

Lobbyists
 
 

4.8 AEDB´s Performance Evaluation 
Institutional performance measurement and review at the AEDB should be carried out 
on two distinct levels: 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  45
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

4.8.1 Institutional Evaluation 
At the institutional program and project level, performance should be assessed against 
relevant  planned  activities  and  timelines  detailed  in  the  AEDB’s  annual  workplans, 
specific  project  plans,  internal  capacity  development  targets,  and  overall  time‐bound 
objectives  quantified  in  AEDB’s  strategic  roadmap  (e.g.,  installed  RES‐E  capacity, 
technology indigenization, village electrification, etc.).  Exhibit 24 highlights some of the 
key  performance  indicators  that  could  be  used  to  monitor  the  agency´s  institutional 
performance. 

Exhibit 24: Suggested AEDB Key Performance Indicators (KPIs) and Targets 
KPIs/Targets

• Number plans & planning reviews


• Number workshops planned and
delivered in a year
• Policy and program initiatives
undertaken
• Funding mobilized each year

• Number of pilot projects in a year


• Time to finish evaluation of projects
• Number of certify projects
• Number of qualified staff in place

• % of LOIs materialized
• % of electricity produced from RE
• # generation licences issued
• Cost/benefit of on-grid RE projects
• 25 TWh/year RES-E by 2020
• # villages electrified
• # households electrified
• Cost/benefit of off-grid RE
• Bankability of feasibility studies
• # months taken for project
implementation
• % of private sector involvement
• # projects developed
• # beneficiaries from projects
• # months project implementation
• # villages electrified
• % RETs indigenized
 
4.8.2 Service Evaluation 
At  the  end‐user  level,  performance  should  also  be  monitored  to  assess  the  ultimate 
results  of  the  AEDB’s  efforts,  i.e.,  the  actual  performance of  RE  implemented  projects, 
partner agencies, concession‐holders, service providers and contractors, etc., in terms of 
product  quality,  service  quality,  commercial  quality,  and  client  satisfaction.  ‘Product 
quality’  includes,  for  instance,  stability  of  RES‐E  voltage  relative  to  targeted  levels  and 
stability of frequency relative to targeted levels. ‘Service quality’ includes targeted hours 
of service, number and duration of interruptions, and safety of the system. ‘Commercial 
quality’  includes  connection,  accuracy  in  meter  reading  (for  customers  whose  service 
requires  meter  reading),  accuracy  in  billing,  and  response  time  to  resolve  customer 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  46
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

complaints.  An  important  element  of  the  AEDB’s  annual  institutional  performance 
review should be based on independent external stakeholder (e.g., RE investors, partner 
agencies,  donors,  etc.)  feedback  and  perceptions  of  the  Board’s  efficacy  in  meeting  its 
general RE facilitation, promotional, information dissemination, policy implementation, 
and efficiency of its related business processes and procedures. 
Whilst  this  evaluation  role  should,  strictly  speaking,  be  conducted  by  an  independent 
evaluator,  it  requires  careful  monitoring  by  the  AEDB  as  well  to  assess  and  effectively 
guide the long term impact of RE development in Pakistan. 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  47
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

Appendices 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  49
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

A AEDB Capacity Assessment Information Request 
ADB Renewable Energy Policy Formulation and Capacity Development of AEDB
Data Request - August 2008

Version Control
Rev Author Description Date
1 Hagler Bailly / Data request issued to client 9/9/2005

Index
Sheet No Name Description Status
1 Instructions sheet Completed
2 Data request sheet Completed  

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  51 
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

 
ADB Renewable Energy Policy Formulation and Capacity Development of AEDB
Data Request - August 2008

Project
At the request of the Asian Development Bank, consultants have been retained to perform an institutional assessment of AEDB and identify improvement opportunities.
Objectives

Project
Our assessment is to be based on a series of meetings with stakeholders supplemented with various document requests.
Methodology

The tab "Data Request" list all AEDS-related documents which are required, broken down into eight sections:
Strategy and Planning
AEDS´s Business Process
HR and Training
Finance
Technical Project Information
Key Stakeholders
Communication and RE Business Intelligence
Information Systems

For each document request, could you please:


1. Fill in as appropriate columns E, F or G.
Instructions If data/document is available, please list document name and reference in column E.
If data/ document is under development, please list the document name and reference and the expected completion date in column F.
If data/document does not exist, please fill in the expected completion date in Column G or indicate if not under development.

2. Where the document exists OR is under development, please provide the documents preferably in electronic format or in paper copy.

Please provide the information by close of business Monday, 15th September 2008 to the contact address below.

Dr Jamil Masud
Hagler Bailly Pakistan
Contact 39, Street 3, E7
Islamabad 44000
Tel: +(92 51) 261 0200-07, Fax: +(92 51) 261 0208-09, Email: jmasud@haglerbailly.com.pk  

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  52
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

 
ADB Renewable Energy Policy Formulation and Capacity Development of AEDB
Data Request - August 2008

Document Under Development


Doc No Data Request Document Available Document Not Developed
(Please list document reference and
(Please list document reference) (Expected availability date: mm/yy)
expected completion date: mm/yy)

Strategy and Planning


1 AEDB Ordnance and charter documents
2 AEDB service rules
3 Brief description of AEDB´s mission statement and key functions
4 Detailed annual/quarterly/monthly operational plans, targets, and milestones
AEDB´s Business Procedures
5
All existing business procedures (e.g., investor evaluation, internal auditing, project and administrative
management, escalation process for conflict resolution, staff appraisal, exterrnal appraisal, request
compliance, performance evaluation, document/inventory control, etc.) and rules (e.g., business rules,
employee handbook, client handling guidelines, communications protocols, contract and legal review,
etc.)

HR and Training
6 Number of AEDB offices and locations, and affiliated/counterpart provincial departments/agencies
7 Existing organisational charts, with departments and positions, for all AEDB offices
8 Roles and responsibility description for key positions (include stardardized job descriptions)
9 Existing staffing numbers, names and positions for each AEDB office
10 CVs of key staff members (defined in item 7)
11 Current recruitment plans
12 Annual staff attrition rate for the last three years
13 Training need analysis and requirements
14 Training budget for the last three years
15 Provide three filled in staff appraisals for the past three years in each case
Finance
16 Salary structure by position and level, along with benefits and contract terms
17 Audited fnancial statements for AEDB for the past three years
18 Sources and amount of AEDB funding/revenues (i.e., government, donors, etc.) by actual
disbursement for last three years
Technical Project Information
19
Detailed list of past and current technical/promotional demonstration projects, with selection
basis/criteria and precise long-term objective and follow-on provisions
20
Planned technical/promotional demonstration projects, with selection basis/criteria and precise long-
term objective and follow-on provisions

Key Stakeholders (Clients, GoP Agencies, Investors, Donors)


21 List of existing clients/investors and partner agencies
22 List of active donors and coordination process between and within donor-funded activities
23 Coordination process with provincial/local governments
24 Client/investor/key stakeholder feedback process and response mechanism/actions
25 No. of clients requests/contacts received over past three years, along with logging process, response
mechanism, and actions triggered
Communication and Business Intelligence
26 Current external communication, awareness raising, and promotional plans
27 Communications and promotional budget for the last three years
28 Please list attendance by AEDB personnel in RE conferences and trade events in 2007 (national and
international)
29 Please list memberships to national and international RE groups/forums/industry and trade associations
Information Systems
30 Existence of an investors and vendors database (please provide five outputs from data repository
illustrating data structure)
31 Existence of RE library and infromation service (please provide five outputs from data repository,
cataloging and access mechanism, and usage data)
32 Organization, ownership and dissemination mechanisms for RE resource and technical data (wind
data, solar maps, suppliers, prices, etc.)
33 Database/archive of project sites, feasibility studies, and project-specific information generation and
sharing mechanisms)
34 Planned IT and information dissemination investments
 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  53
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

B Proposed AEDB Key Job Descriptions 
C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS

AE D B T echnical projects O n G rid D irector 1

DE S C R IP T IO N C HAR T
S ummary
O verall res pons ible for the O n‐G rid projects  from the technical and commercial point of view.
Duties  and R es pons ibilities

• P erform feas ibility s tudies


• D evelop requirements  documents
• T echnical evaluation of tenders  
• E ns ure s us tainability of all projects Board

• R is k management
• D evelops  and implements  methods  and procedures  for monitoring projects Chairman

• R ecommends  and s ecures  contractual agreements for technical s ervices  and products


• Identifies  project team training and tool needs CEO

• Mentors  project team members  
• D efines  S L As for s uppliers
• R es pons ible for O &M Corporate
Services
Quality Assurance

• E valuate new projects
• Manage C D M P rojects
• C ommercial E valuation of tenders Technical Projects
Policy and R&D RE Administration and
IT HR
Logistics
Commercial Finance /Procurement

• Interface for licens es  proces s
• T ariff & regulation As s is tance
• T racks  and identifies  new inves tment opportunities
• C ontract negotiation
B ac kground K PI

A c ademic       E xperienc e


• C ertified E lectrical  • T en years  of experience  • Number of feas ibility s tudies  
E ngineer in utility cons truction  completed in a year
• Mas ters  D egree in  projects • Number of technical tender 
B us ines s  Adminis tration • E xtens ive experience of  as s es s ments  in a year.
carrying out feas ibility  • Number of commercial tender 
s tudies as s es s ments  in a year.
• E xtens ive experience in  • Number of  converted tenders  into 
R E  technologies projects
 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  55
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS

AE D B T echnical projects O ff G rid D irector D irector 1

DE S C R IP T IO N C H AR T
S ummary
O verall res pons ible for the on O ff‐G rid projects  from the technical and commercial point of view
Duties  and R es pons ibilities

• P rojects / pilot s upervis ion


• D evelop requirements  documents
• T echnical evaluation of projects
• P rojects / pilot s upervis ion
• E ns ure s us tainability of all projects
Board

• R is k management
• F und allocation  Chairman

• D evelops  and implements  methods  and procedures  for monitoring projects


• R ecommends  and s ecures  contractual agreements  for technical s ervices  and products CEO

• Identifies  project team training and tool needs
• Mentors  project team members   Corporate
Quality Assurance
Services

• D efines  S L As for s uppliers


• R es pons ible for O &M
• Manages  relations hips  with donor and multilateral ins titutions
• Interface for licens es  proces s Technical Projects
Policy and
Commercial
R&D RE Administration and
Finance
IT HR
Logistics
/Procurement

B ac kground KPI

A c ademic       E xperienc e


• C ertified E lectrical  • T en years  of experience  • Number of  villages  electrified in a 
E ngineer in utility cons truction  year
• Mas ters  D egree in  projects • O n time delivery of pilot projects
B us ines s  Adminis tration • E xtens ive experience in  • Amount of money collected 
R E  technologies

 
 
C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS
R enewables R es earch and 
AE D B R &D  R E  D irector 1
D evelopment

DE S C R IP T IO N C HAR T
S ummary

D irects  R &E  res earch and related field applications  and dis s eminates  R &E  information to the 


wider community. 

Duties  and R es pons ibilities

• F ield tes ting of renewable technology  Board

• D evelopment of prototype pilot programmers
• T echnical R es earch and bus ines s  intelligence Chairman

• C onduct works hops  and dis s eminate R &D  related information


• C oordinates  res earch and development activities  for renewable technologies . P lans  and  
CEO
formulates  as pects  of res earch and development propos als . 
• R eviews  and analyzes  pilot projects   to determine if benefits  derived and pos s ible 
applications  jus tify expenditures . Corporate
Services
Quality Assurance

Policy and R&D RE Administration and Logistics


Technical Projects IT HR
B ac kground KPI Commercial Finance /Procurement

A c ademic                                            E xperienc e


• Number of prototypes  converted into 
• P hD  in E lectrical  • E xtens ive experience in 
pilot projects
E ngineering R &D  renewable projects
• Number of publications  in a year

 
 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  56
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

 
C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS

AE D B Adminis tration and F inance Adminis tration and F inance D irector 1

DE S C R IP T IO N C HAR T
S ummary

D evelops  and implements  effective accounting, treas ury and management procedures  that 


meet a high level of compliance with es tablis hed regulatory controls .  P rovides  information to 
s upport efficient management decis ions  and Q uality C os t Management and C ontrol. 
R es pons ible for the co‐ordination and direction of all activities  in the adminis tration and finance 
D ivis ion. Board

Duties  and R es pons ibilities

• P lan and manage the C ompany's  financial requirements  and budgets . Chairman

• Undertake accounting activities  and analyze the C ompany's  as s ets , liabilities  and equity.


• S et and monitor the F inance quality s tandards , indicators  and goals . CEO

• S et and monitor C ompany ris ks  s trategies  and policies .


• F ormulate, enhance, integrate, document, communicate and implement finance s tandards ,  Corporate
Quality Assurance
policies , guidelines  and procedures . Services

• F und cus tody and management
• P erform P roces s  Management for accounting records , cas h flows , inves tments  as s es s ment, 
T axing and P ayroll. Technical Projects
Policy and R&D RE Administration and
IT HR
Logistics
Commercial Finance /Procurement

B ac kground KPI

A c ademic                                            E xperienc e

• E conomics  G raduate • Minimum of 10 years  of  • B udget deviation


• Mas ters  D egree in  experience in  • %  of funds  allocated to actual 
E conomics Management at  projects /pilots
corporate level

       
C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS

AEDB IT IT  D irector 1

DE S C R IP T IO N C HAR T
S ummary
D irects  and manages  computing and information technolog y s trategic plans , policies , programs  
and s chedules  for bus ines s  and finance data proces s ing, computer s ervices , network 
communications  and management information s ervices . 
Duties  and R es pons ibilities

• D evelop reliable data repos itory (s uppliers , vendors , potential inves tors ).  Board

• S upport future IS /IT ‐related requirements  of the company.


• P rovide and efficient us e of IS /IT  res ources  within the approved budget. Chairman

• Implement meas ures  to improve IS /IT ‐related activities  to meet end us ers  s atis faction


• P erform C ontract Management of application s oftware and IS /IT  profes s ional and contractual 
CEO

s ervices .
• S et and monitor IS /IT  quality s tandards , indicators  and goals . 
• F ormulate, enhance, integrate, document, communicate and implement IS  s tandards ,  Corporate
Services
Quality Assurance

policies , guidelines  and procedures .

B ac kground KPI Policy and R&D RE Administration and Logistics


Technical Projects IT HR
Commercial Finance /Procurement

A c ademic                                            E xperienc e


• R eliability level of IS /IT  Infras tructure
• Mas ters  D egree in  • 10 years  of experience in 
• S L A O n‐T ime D elivery
Information T echnolog y  a s enior‐level 
• Application Availability
or C omputer S cience Information T echnolog y 
• R es pons e T ime – All Applications
pos ition
• E nd us er s atis faction index

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  57
Asian Development Bank  AEDB Capacity Assessment 
TA 4881‐PAK: Final Report  and Institutional Needs 

C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS

AE D B H uman R es ources H uman R es ources  D irector 1

DE S C R IP T IO N C HAR T
S ummary

D efines  and promotes  the introduction of policies , plans  and procedures  for the management 


and development of the C ompany’s  pers onnel. P lans  human res ources  requirements  and 
implements  thos e plans  which bes t allow the C ompany to recruit, retain and develop 
employees .
Duties  and R es pons ibilities

• D raw up and propos e Human R es ources  policies ; s upervis e their development.


• D evelop and manage in‐hous e communication plans  s upporting changes  to policies . Board

• D efine and introduce new means , channels  and communication s ys tems  within the C ompany 


which allow for horizontal and vertical flow of information. Chairman

• D es ign all P ers onnel Management procedures  and s ys tems  that are required for: recruitment 


and s creening, job placement, development of job des criptions , remuneration and s ocial 
CEO

benefits , career and s ucces s ion plans , pers onnel training and development plans , evaluation 


of pers onnel performance, and promotion of mobility.
• D efine and s ubmit the remuneration policy to the Management C ommittee and manage its   Corporate
Services
Quality Assurance

implementation.
• P repare and up‐date the E mployee R ules .
• E ns ure compliance with health and s afety regulations .  Approve, co‐ordinate and s upervis e all 
Policy and R&D RE Administration and Logistics
actions  to ens ure the phys ical s afety of pers onnel and facilities . Technical Projects
Commercial Finance
IT HR
/Procurement

• D raw up the neces s ary policies  and procedures .


• D raw up the annual P ers onnel T raining and D evelopment plans , drafted jointly with the 
different C ompany units .
B ac kground KPI
A c ademic                                            E xperienc e
• T en years  of experience  • T otal L abor C os t
• Mas ters  D egree in  in a s enior‐level H uman  • E mployee S atis faction Index
Human R es ources   R es ource Management  • T ime lines  completion of trainings  
Management pos ition and development plans .
 
C O MP ANY F UNC T IO NAL  AR E A J O B  T IT L E P O S IT IO NS

AE D B P rocurement and L ogis tics P rocurement and L ogis tics  D irector 1

DE S C R IP T IO N C HAR T
S ummary
Meeting and verifying the procurement needs  of the C ompany departments  to ens ure timely, 
adequate and cos t‐efficient purchas ing of goods  and s ervices .
Duties  and R es pons ibilities

• Monitor, and co‐ordinate with the different areas  of the C ompany, res ource needs .  P rioritize 


and initiate the acquis ition of equipment and s ervices .
• Analyze the prices  and s ervices  offered by s uppliers  of equipment and s ervices . Board

• D evelop relations  with s uppliers  and negotiate appropriate price and contract conditions .


• D efine procurement and s upplies  procedures  (S tock Management, S tore of E quipments , 
Chairman

acquis ition, vendor accreditation and evaluation).
• Analyze the valuation of inventories  and promote activities  to optimize cos ts .
• S upervis e S tore Management, s olving any problem that may aris e.  CEO

• Monitor the quality and fulfillment of the contractual conditions  of the s ervices  hired, taking 


corrective meas ures  as  required. Corporate
Quality Assurance
Services

• Monitor delivery miles tones  defined with s uppliers , taking corrective meas ures  in cas e of 


deviations .
• P erform activities  and tas ks  included in the E mergency P lans .
• E ns ure that ongoing corporate s ervices  are procured efficiently Technical Projects
Policy and
Commercial
R&D RE Administration and
Finance
IT HR
Logistics
/Procurement

• P urchas e, control, dis tribute and replace office furniture and s upplies .


• C arry out maintenance, outfitting and improvement works . 

B ac kground KPI

A c ademic                                            E xperienc e


• Materials  & S upplies  Inventory
• E conomics  G raduate • Minimum of 10 years  of  • %  procurement s avings
experience in  • %  goods  and s ervices  dis counts  
Management at 
corporate level
 
 

Hagler Bailly Pakistan | Mercados EMI


R9CA1PRP ‐ AEDB CAPACITY ASSESSMENT: 11/03/09  58
ADB TA 4881-PAK:
Renewable Energy Policy Model
Madrid - London - Moscow - New Delhi

Tables Figures

Input Data Total Conv + RES Bagasse-based Landfill Gas Small S. Hydel WTE

Tech References Total Conv Biogas Photovoltaic Solar Thermal

Results Total RES Biomass Sewage Wind


Home
CO2 Assumptions Model Assumptions
Emissions Factors (g/kWh) Discount rate (pre-tax) 12.0%
Fuel 500 Inv. Recovery Period (RES-E) 20 years (blank maintains technical lifetime)
Gas 370 Inv. Recovery Period (Conv) 30 years
Coal 900
Average 590 Cost Drivers Percentile
Emissions Price (€/tCO2) Investment Cost 0.1 0.4 0.6 0.9
Value 30 Load Factor 0.1 0.4 0.6 0.9
Fuel 0.1 0.4 0.6 0.9

Run Model
Home
Electricity price ($/MWh) Investment Cost ($/kW) Self Fuel cost ($/MWh) Efficiency (%) Lifetime Load Factor (%) Capacity Generation
Category Specification min max min max O&M Cons min max min max (years) min max avg Potential (MW) Potential (MWh)
Landfill 47.71 73.40 1,430.0 1,840.0 7.0% 8.0% 0.0 0.0 32% 36% 25 60% 80% 70% 48 295,011
Biogas Sewage 78.16 134.24 2,300.0 3,400.0 7.0% 8.0% 0.0 0.0 28% 32% 25 60% 80% 70% 20 122,111
Agricultural biogas plant 61.12 117.53 886.5 2,350.0 7.0% 8.0% 27.6 27.6 25 60% 80% 70% 466 2,856,252
Biomass 64.49 86.11 1,062.6 1,249.5 4.0% 10.0% 33.4 35.1 26% 30% 30 50% 80% 65% 817 4,653,239
Biomass
Cogeneration 61.42 84.83 823.0 1,280.0 3.0% 10.0% 26.5 35.6 22% 27% 30 50% 80% 65% 888 5,056,983
Waste WTE 65.54 216.83 2,000.0 5,800.0 3.7% 8.0% 0.0 0.0 18% 22% 30 50% 80% 65% 91 516,768
Photovoltaics PV plant 343.45 430.50 5,080.0 5,930.0 1.0% - 0.0 0.0 - - 25 22% 25% 24% 2,177 4,482,362
Solar Thermal Solar Thermal 272.26 427.41 2,880.0 4,465.0 6.0% - 0.0 0.0 33% 38% 30 22% 25% 24% 414 853,235
Good 108.15 126.96 1,800.0 2,200.0 3.5% - 0.0 0.0 - - 25 33% 33% 33% 4,862 13,971,272
Wind Onshore Excelent 102.32 120.12 1,890.0 2,310.0 3.5% - 0.0 0.0 - - 25 36% 36% 36% 3,264 10,408,654
Outstanding 94.46 110.89 1,984.5 2,425.5 3.5% - 0.0 0.0 - - 25 41% 41% 41% 112 407,603
Hydel SS Hydel 42.97 405.73
Curve 1 - Conventional Private Curve

Private Cost Generation Cum Generation


Code ($/MWh) (GWh) (GWh)
Nuke 50.4 11,937 11,937
LSH 54.8 69,180 81,117
Coal 55.6 28,539 109,656
Gas 66.7 25,047 134,703
Fuel 133.8 17,110 151,813

Home

References:
Coal Coal Power Plant
Fuel Fuel Oil Power Plant
Gas CCGT Natural Gas
LSH Large Scale Hydel
Nuke Nuclear Power Plant
SSH Small Scale Hydel
bag Bagasse-based Cogeneration
biom Biomass Power Plant
biog Biogas Power Plant
sew Sewage Power Plant
LFG Landfill gas Power Plant
WTE Waste-to-Energy Power Plant
PV Photovoltaic Power Plant
ST Solar Thermal Power Plant
WD Wind Generation Park

50.4 0
50.4 11,937
54.8 11,937
54.8 81,117
55.6 81,117
55.6 109,656
66.7 109,656
66.7 134,703
133.8 134,703
133.8 151,813
Curve 2 - Conventional Social Curve

Social Cost Generation Cum


Code ($/MWh) (GWh) Generation
Nuke 50.4 11,937 11,937
LSH 54.8 69,180 81,117
Coal 86.9 28,539 109,656
Gas 102.6 25,047 134,703
Fuel 178.2 17,110 151,813

50.4 0
50.4 11,937
54.8 11,937
54.8 81,117
86.9 81,117
86.9 109,656
102.6 109,656
102.6 134,703
178.2 134,703
178.2 151,813
Curve 3 - RES Curve (social)

Cost Generation Cum


Code ($/MWh) (GWh) Generation
SSH 43.0 45 45
SSH 43.0 42 87
SSH 43.0 35 122
SSH 43.0 35 157
SSH 43.0 169 326
SSH 43.0 185 511
SSH 43.0 84 595
SSH 43.0 224 819
SSH 45.0 80 900
SSH 45.2 107 1,007
SSH 45.2 77 1,083
SSH 45.6 186 1,269
SSH 46.2 57 1,326
SSH 47.2 196 1,522
LFG 47.7 5 1,528
LFG 47.7 5 1,533
LFG 47.7 5 1,538
LFG 47.7 5 1,543
SSH 49.1 29 1,572
SSH 49.1 22 1,594
SSH 49.1 17 1,611
SSH 49.1 12 1,623
SSH 49.1 34 1,656
SSH 49.1 31 1,688
SSH 49.1 5 1,693
SSH 49.1 25 1,717
SSH 49.1 25 1,742
SSH 49.1 15 1,757
SSH 49.1 7 1,764
SSH 49.1 22 1,786
SSH 49.1 20 1,807
SSH 49.1 34 1,840
SSH 49.1 15 1,855
SSH 49.1 14 1,869
SSH 49.1 14 1,883
SSH 49.1 14 1,897
SSH 49.1 6 1,902
SSH 49.1 4 1,906
SSH 49.1 5 1,911
SSH 49.1 12 1,923
SSH 49.1 12 1,935
SSH 49.1 11 1,946
SSH 49.1 11 1,956
SSH 49.1 10 1,967
SSH 49.1 5 1,972
SSH 49.1 12 1,984
SSH 49.1 4 1,988
SSH 49.1 10 1,997
SSH 49.1 8 2,005
SSH 49.1 8 2,013
SSH 49.1 8 2,020
SSH 49.1 8 2,028
SSH 49.1 7 2,034
SSH 49.1 6 2,041
SSH 49.1 34 2,075
SSH 49.1 4 2,078
SSH 49.1 2 2,081
SSH 50.1 7 2,087
SSH 50.1 59 2,146
SSH 50.5 5 2,151
SSH 50.9 4 2,154
Curve 3 - RES Curve (social)
SSH 50.9 7 2,161
SSH 51.3 42 2,203
SSH 51.4 6 2,209
SSH 51.4 17 2,226
SSH 51.5 66 2,292
SSH 51.6 58 2,350
SSH 51.7 18 2,368
LFG 51.7 5 2,372
LFG 51.7 5 2,377
LFG 51.7 5 2,382
LFG 51.7 5 2,387
LFG 51.7 5 2,392
LFG 51.7 5 2,397
LFG 51.7 5 2,402
LFG 51.7 5 2,407
SSH 51.7 17 2,424
SSH 51.8 17 2,441
SSH 51.8 17 2,457
SSH 52.0 4 2,461
SSH 52.1 5 2,467
SSH 52.2 29 2,495
SSH 52.2 11 2,506
SSH 52.2 12 2,518
SSH 52.2 5 2,522
SSH 52.2 6 2,529
SSH 52.2 16 2,545
SSH 52.3 19 2,564
SSH 52.3 6 2,570
SSH 52.3 9 2,579
SSH 52.3 7 2,586
SSH 52.4 3 2,589
SSH 52.4 17 2,605
SSH 52.5 16 2,622
SSH 52.5 16 2,637
SSH 52.6 15 2,653
SSH 52.8 18 2,671
SSH 52.9 14 2,685
SSH 52.9 26 2,711
SSH 52.9 16 2,726
SSH 53.1 18 2,744
SSH 53.2 16 2,760
SSH 53.2 11 2,771
SSH 53.2 15 2,786
SSH 53.3 16 2,802
SSH 53.3 7 2,809
SSH 53.3 227 3,035
SSH 53.4 20 3,055
SSH 53.4 15 3,070
SSH 53.5 18 3,088
SSH 53.6 143 3,231
SSH 53.6 135 3,366
SSH 53.8 20 3,386
SSH 53.8 20 3,407
SSH 53.8 20 3,427
SSH 53.8 15 3,442
SSH 53.8 15 3,456
SSH 53.9 20 3,477
SSH 53.9 15 3,492
SSH 53.9 83 3,575
SSH 53.9 15 3,589
SSH 53.9 4 3,593
SSH 54.0 21 3,614
SSH 54.1 100 3,714
SSH 54.1 6 3,720
Curve 3 - RES Curve (social)
SSH 54.1 19 3,739
SSH 54.2 111 3,850
SSH 54.2 22 3,872
SSH 54.2 14 3,887
SSH 54.2 8 3,895
SSH 54.3 7 3,901
SSH 54.3 94 3,995
LFG 54.4 5 4,000
LFG 54.4 5 4,005
LFG 54.4 5 4,011
LFG 54.4 5 4,016
SSH 54.5 14 4,030
SSH 54.6 23 4,053
SSH 54.6 95 4,148
SSH 54.6 252 4,401
SSH 54.6 3 4,404
SSH 54.7 4 4,408
LFG 54.7 4 4,412
LFG 54.7 4 4,417
LFG 54.7 4 4,421
LFG 54.7 4 4,426
SSH 54.8 13 4,439
SSH 54.9 23 4,462
SSH 54.9 8 4,470
SSH 54.9 24 4,494
SSH 54.9 13 4,506
SSH 55.0 25 4,531
SSH 55.0 25 4,557
SSH 55.0 25 4,582
SSH 55.2 9 4,591
SSH 55.3 26 4,617
SSH 55.3 26 4,643
SSH 55.3 9 4,652
SSH 55.4 8 4,660
SSH 55.5 14 4,674
SSH 55.6 14 4,688
SSH 55.7 78 4,765
SSH 55.8 76 4,841
SSH 55.9 6 4,847
SSH 55.9 75 4,923
SSH 56.0 280 5,203
SSH 56.0 54 5,257
SSH 56.0 74 5,330
SSH 56.0 126 5,457
SSH 56.0 3 5,460
LFG 56.0 5 5,465
LFG 56.0 5 5,469
LFG 56.0 5 5,474
LFG 56.0 5 5,479
SSH 56.1 56 5,535
SSH 56.4 5 5,540
SSH 56.5 51 5,591
SSH 56.7 28 5,619
SSH 56.9 8 5,628
SSH 57.0 13 5,640
SSH 57.0 13 5,653
SSH 57.0 17 5,669
SSH 57.0 28 5,698
SSH 57.1 29 5,726
SSH 57.2 315 6,042
SSH 57.3 42 6,084
SSH 57.4 56 6,140
SSH 57.5 42 6,182
SSH 57.7 3 6,184
Curve 3 - RES Curve (social)
SSH 57.7 29 6,213
SSH 57.8 18 6,231
SSH 57.8 5 6,236
SSH 57.9 29 6,265
SSH 58.0 15 6,280
SSH 58.0 28 6,309
SSH 58.0 126 6,435
SSH 58.0 12 6,447
SSH 58.0 13 6,459
LFG 58.3 5 6,464
LFG 58.3 5 6,469
LFG 58.3 5 6,475
LFG 58.3 5 6,480
SSH 58.4 9 6,489
SSH 58.6 12 6,501
SSH 58.8 7 6,507
LFG 58.9 5 6,512
LFG 58.9 5 6,517
LFG 58.9 5 6,522
LFG 58.9 5 6,526
SSH 58.9 11 6,537
SSH 58.9 8 6,545
SSH 59.1 52 6,597
SSH 59.1 3 6,600
SSH 59.1 10 6,609
SSH 59.2 11 6,621
LFG 59.3 4 6,625
LFG 59.3 4 6,630
LFG 59.3 4 6,634
LFG 59.3 4 6,639
SSH 59.5 11 6,650
SSH 59.6 11 6,661
SSH 59.6 5 6,666
SSH 59.8 10 6,675
SSH 59.9 6 6,682
SSH 60.0 32 6,713
LFG 60.0 4 6,718
LFG 60.0 4 6,722
LFG 60.0 4 6,726
LFG 60.0 4 6,730
SSH 60.3 11 6,740
SSH 60.3 23 6,764
SSH 60.4 13 6,777
SSH 60.4 21 6,798
SSH 60.4 24 6,823
SSH 60.5 8 6,830
SSH 60.6 10 6,840
SSH 60.7 52 6,892
SSH 60.7 18 6,910
SSH 60.7 7 6,917
SSH 60.8 34 6,951
SSH 60.8 22 6,973
SSH 60.8 10 6,983
SSH 60.9 41 7,024
SSH 61.0 16 7,039
Biog 61.1 46 7,085
Biog 61.1 46 7,131
Biog 61.1 46 7,177
Biog 61.1 46 7,222
SSH 61.4 39 7,262
Bag 61.4 84 7,346
SSH 61.5 33 7,379
SSH 61.5 10 7,388
SSH 61.7 210 7,599
Curve 3 - RES Curve (social)
SSH 61.8 29 7,628
SSH 61.8 10 7,638
SSH 61.9 9 7,647
Bag 62.0 74 7,721
SSH 62.0 9 7,731
SSH 62.1 18 7,749
SSH 62.2 9 7,758
LFG 62.4 4 7,762
LFG 62.4 4 7,767
LFG 62.4 4 7,771
LFG 62.4 4 7,776
SSH 62.4 9 7,785
SSH 62.4 34 7,819
SSH 62.4 36 7,855
Bag 62.4 68 7,923
SSH 62.4 5 7,928
SSH 62.5 24 7,952
SSH 62.7 4 7,957
SSH 62.8 38 7,995
SSH 63.0 9 8,004
SSH 63.0 9 8,013
SSH 63.1 58 8,071
LFG 63.2 5 8,075
LFG 63.2 5 8,080
LFG 63.2 5 8,085
LFG 63.2 5 8,089
Bag 63.2 58 8,147
SSH 63.5 9 8,156
SSH 63.7 9 8,165
SSH 63.8 58 8,223
Biog 63.9 42 8,265
Biog 63.9 42 8,308
Biog 63.9 42 8,350
Biog 63.9 42 8,392
SSH 64.0 5 8,397
SSH 64.0 256 8,653
SSH 64.1 49 8,703
Bag 64.2 84 8,787
SSH 64.2 10 8,797
SSH 64.3 8 8,805
SSH 64.5 4 8,809
SSH 64.5 252 9,062
Biom 64.5 78 9,139
SSH 64.5 7 9,146
SSH 64.6 96 9,242
SSH 64.7 8 9,250
Bag 64.7 74 9,324
SSH 64.8 9 9,333
SSH 64.9 9 9,342
SSH 64.9 8 9,350
SSH 64.9 5 9,355
SSH 64.9 22 9,377
SSH 64.9 8 9,386
SSH 64.9 8 9,394
SSH 65.0 8 9,402
Biom 65.0 78 9,479
LFG 65.0 4 9,483
LFG 65.0 4 9,488
LFG 65.0 4 9,492
LFG 65.0 4 9,496
Bag 65.1 68 9,564
Bag 65.1 84 9,648
SSH 65.2 35 9,683
SSH 65.2 158 9,841
Curve 3 - RES Curve (social)
SSH 65.2 127 9,968
SSH 65.3 55 10,023
Biom 65.3 78 10,101
SSH 65.5 7 10,107
SSH 65.5 8 10,115
SSH 65.5 4 10,119
SSH 65.5 8 10,127
WTE 65.5 10 10,136
WTE 65.5 10 10,146
WTE 65.5 10 10,156
WTE 65.5 10 10,165
SSH 65.6 8 10,173
SSH 65.6 8 10,181
SSH 65.7 5 10,186
SSH 65.7 27 10,213
Biom 65.9 78 10,291
SSH 65.9 105 10,396
Bag 65.9 58 10,454
Bag 66.0 84 10,538
SSH 66.0 8 10,546
Biog 66.0 40 10,585
Biog 66.0 40 10,625
Biog 66.0 40 10,665
Biog 66.0 40 10,705
Biom 66.1 78 10,783
Bag 66.1 74 10,857
SSH 66.3 68 10,925
Bag 66.5 74 10,999
Biom 66.6 78 11,077
LFG 66.9 4 11,081
LFG 66.9 4 11,086
LFG 66.9 4 11,090
LFG 66.9 4 11,094
Bag 66.9 68 11,162
Biom 67.0 78 11,240
Bag 67.0 68 11,308
SSH 67.2 8 11,315
SSH 67.2 8 11,323
SSH 67.2 8 11,331
SSH 67.2 8 11,339
SSH 67.2 8 11,346
SSH 67.2 8 11,354
SSH 67.2 4 11,358
Biom 67.2 78 11,435
Biom 67.5 78 11,513
SSH 67.6 8 11,521
Bag 67.6 84 11,605
SSH 67.6 8 11,612
Biom 67.7 78 11,690
SSH 67.8 68 11,758
Bag 67.8 58 11,816
Bag 67.9 84 11,900
SSH 67.9 7 11,907
Biom 68.0 78 11,985
SSH 68.1 7 11,992
SSH 68.1 7 11,999
SSH 68.2 7 12,006
LFG 68.4 4 12,010
LFG 68.4 4 12,014
LFG 68.4 4 12,018
LFG 68.4 4 12,022
Biom 68.5 78 12,099
SSH 68.6 7 12,106
Biom 68.6 68 12,175
Curve 3 - RES Curve (social)
Bag 68.6 58 12,233
SSH 68.6 3 12,236
Bag 68.7 84 12,320
Biom 68.8 78 12,397
SSH 68.8 7 12,404
SSH 68.8 13 12,417
SSH 68.9 7 12,424
Bag 68.9 74 12,499
SSH 68.9 7 12,505
Bag 68.9 74 12,580
Biom 69.1 68 12,648
Bag 69.2 74 12,723
Biom 69.3 78 12,800
Biom 69.4 68 12,869
Biom 69.6 78 12,946
Bag 69.7 68 13,014
SSH 69.7 6 13,020
Bag 69.7 84 13,104
SSH 69.7 3 13,107
Bag 69.7 68 13,175
Biog 69.8 36 13,211
Biog 69.8 36 13,248
Biog 69.8 36 13,284
Biog 69.8 36 13,321
Biom 70.0 68 13,389
Bag 70.0 68 13,457
SSH 70.1 6 13,463
SSH 70.1 20 13,483
Biom 70.1 78 13,561
SSH 70.2 10 13,570
Bag 70.3 84 13,655
Biom 70.4 68 13,723
Bag 70.5 58 13,781
SSH 70.5 16 13,797
SSH 70.6 6 13,803
SSH 70.7 196 13,999
Bag 70.7 74 14,074
SSH 70.8 6 14,080
Biom 70.9 68 14,148
SSH 71.0 6 14,154
SSH 71.2 6 14,161
Biom 71.3 68 14,229
Bag 71.3 84 14,313
Bag 71.3 58 14,371
Bag 71.5 68 14,439
SSH 71.5 29 14,468
Biom 71.6 68 14,536
Bag 71.7 74 14,611
Biom 71.8 68 14,679
SSH 71.8 6 14,685
Biom 72.0 62 14,748
SSH 72.1 5 14,752
Biom 72.1 68 14,821
Bag 72.1 84 14,905
Bag 72.2 58 14,963
SSH 72.4 6 14,969
Bag 72.4 84 15,053
SSH 72.4 6 15,059
Biom 72.5 68 15,127
Biom 72.5 62 15,190
Bag 72.8 68 15,257
Biom 72.8 62 15,320
SSH 72.9 6 15,325
Biom 73.0 68 15,394
Curve 3 - RES Curve (social)
SSH 73.1 3 15,397
Bag 73.1 74 15,471
SSH 73.1 6 15,477
SSH 73.1 39 15,515
Bag 73.1 58 15,573
SSH 73.2 3 15,576
SSH 73.2 64 15,640
SSH 73.2 5 15,646
SSH 73.2 5 15,651
SSH 73.3 3 15,654
Biom 73.4 62 15,716
LFG 73.4 4 15,720
LFG 73.4 4 15,725
LFG 73.4 4 15,729
LFG 73.4 4 15,733
Bag 73.4 74 15,807
Biom 73.4 68 15,876
Bag 73.5 74 15,950
SSH 73.7 14 15,964
SSH 73.7 5 15,969
SSH 73.7 5 15,975
Biom 74.0 68 16,043
Biom 74.0 62 16,105
Bag 74.0 84 16,190
SSH 74.1 14 16,203
WTE 74.2 8 16,212
WTE 74.2 8 16,220
WTE 74.2 8 16,229
WTE 74.2 8 16,237
Bag 74.3 68 16,305
Biom 74.3 68 16,373
SSH 74.3 5 16,379
Biom 74.5 62 16,441
SSH 74.6 5 16,446
Bag 74.6 68 16,514
Bag 74.6 68 16,582
Biom 74.8 68 16,650
Biom 74.8 62 16,713
SSH 74.9 5 16,718
Bag 74.9 84 16,802
Bag 74.9 58 16,860
SSH 75.0 5 16,865
SSH 75.2 40 16,904
SSH 75.2 42 16,946
SSH 75.2 4 16,950
Biom 75.3 62 17,012
Biom 75.4 62 17,075
Biog 75.4 46 17,121
Biog 75.4 46 17,166
Biog 75.4 46 17,212
Biog 75.4 46 17,258
SSH 75.4 3 17,261
SSH 75.4 4 17,265
SSH 75.4 5 17,270
SSH 75.4 5 17,275
SSH 75.6 3 17,278
SSH 75.8 5 17,283
SSH 75.8 5 17,288
Biom 75.8 62 17,350
Bag 75.8 84 17,434
Bag 75.9 74 17,509
Bag 75.9 58 17,567
SSH 76.0 5 17,571
Biom 76.2 62 17,634
Curve 3 - RES Curve (social)
Bag 76.2 74 17,708
SSH 76.3 7 17,715
SSH 76.4 8 17,723
SSH 76.4 5 17,727
SSH 76.6 5 17,732
Biom 76.7 62 17,794
Bag 76.7 58 17,852
SSH 77.2 4 17,857
Biom 77.3 62 17,919
Bag 77.3 68 17,987
Bag 77.4 68 18,055
Bag 77.6 58 18,113
SSH 77.6 4 18,117
Bag 77.7 74 18,191
Biom 77.8 62 18,254
Biom 78.2 62 18,316
Sew 78.2 2 18,318
Sew 78.2 2 18,320
Sew 78.2 2 18,323
Sew 78.2 2 18,325
SSH 78.2 79 18,404
SSH 78.2 4 18,408
SSH 78.3 4 18,412
SSH 78.5 4 18,417
Biom 78.5 53 18,470
SSH 78.5 4 18,474
Bag 78.6 84 18,558
Biom 78.7 62 18,621
SSH 78.7 4 18,625
Biom 79.0 53 18,678
SSH 79.1 4 18,682
Bag 79.2 68 18,750
SSH 79.2 4 18,754
Biog 79.3 42 18,796
Biog 79.3 42 18,838
Biog 79.3 42 18,880
Biog 79.3 42 18,923
Biom 79.4 53 18,976
Bag 79.5 58 19,034
SSH 79.8 4 19,038
Biom 79.9 53 19,091
Bag 80.3 58 19,149
SSH 80.3 2 19,152
SSH 80.3 4 19,155
SSH 80.4 4 19,159
Bag 80.4 74 19,233
SSH 80.5 4 19,237
SSH 80.7 85 19,322
Biom 80.8 53 19,376
SSH 81.2 4 19,379
Biom 81.4 53 19,433
WTE 81.4 8 19,440
WTE 81.4 8 19,448
WTE 81.4 8 19,456
WTE 81.4 8 19,463
SSH 81.5 4 19,467
SSH 81.5 4 19,471
Biom 81.7 53 19,524
SSH 81.8 26 19,550
Bag 81.9 68 19,618
SSH 82.1 3 19,621
Bag 82.1 58 19,679
Biom 82.2 53 19,732
Biog 82.4 40 19,772
Curve 3 - RES Curve (social)
Biog 82.4 40 19,812
Biog 82.4 40 19,852
Biog 82.4 40 19,892
Biom 82.4 53 19,945
SSH 82.4 4 19,949
SSH 82.5 3 19,952
SSH 82.8 3 19,956
SSH 82.8 238 20,194
Biom 82.9 53 20,247
SSH 83.0 3 20,251
Biom 83.3 53 20,304
Biom 83.8 53 20,357
SSH 83.8 3 20,360
SSH 84.2 3 20,363
SSH 84.2 98 20,461
SSH 84.2 3 20,464
SSH 84.3 2 20,466
SSH 84.6 32 20,498
Sew 84.7 2 20,500
Sew 84.7 2 20,502
Sew 84.7 2 20,504
Sew 84.7 2 20,506
Biom 84.7 53 20,559
Bag 84.8 58 20,617
Biog 84.9 46 20,663
Biog 84.9 46 20,709
Biog 84.9 46 20,755
Biog 84.9 46 20,800
Biom 85.3 53 20,854
SSH 85.5 3 20,857
Biom 85.6 53 20,910
SSH 85.7 3 20,913
SSH 85.9 3 20,916
SSH 86.0 15 20,931
Biom 86.1 53 20,984
SSH 86.7 3 20,987
SSH 86.8 4 20,990
SSH 87.2 3 20,993
SSH 87.2 97 21,090
SSH 87.4 3 21,093
SSH 87.4 2 21,095
Biog 87.7 36 21,131
Biog 87.7 36 21,168
Biog 87.7 36 21,204
Biog 87.7 36 21,240
SSH 87.7 5 21,245
SSH 87.9 3 21,248
SSH 88.1 3 21,251
SSH 88.6 4 21,255
SSH 88.7 3 21,258
SSH 88.8 3 21,260
Sew 88.9 2 21,262
Sew 88.9 2 21,264
Sew 88.9 2 21,267
Sew 88.9 2 21,269
SSH 88.9 3 21,271
SSH 89.0 3 21,274
SSH 89.2 12 21,286
SSH 89.4 2 21,288
SSH 89.6 2 21,291
Biog 89.6 42 21,333
Biog 89.6 42 21,375
Biog 89.6 42 21,417
Biog 89.6 42 21,460
Curve 3 - RES Curve (social)
Sew 89.7 2 21,461
Sew 89.7 2 21,463
Sew 89.7 2 21,465
Sew 89.7 2 21,467
SSH 89.9 5 21,472
SSH 90.0 2 21,475
SSH 90.0 2 21,477
SSH 90.1 3 21,480
SSH 90.5 4 21,484
SSH 91.1 2 21,486
SSH 91.2 2 21,488
SSH 91.2 2 21,491
SSH 91.5 2 21,493
SSH 91.9 13 21,506
SSH 91.9 2 21,508
SSH 92.0 2 21,510
SSH 92.2 2 21,512
SSH 92.5 2 21,515
SSH 92.6 2 21,517
SSH 92.8 2 21,519
SSH 92.9 3 21,522
Biog 93.3 40 21,561
Biog 93.3 40 21,601
Biog 93.3 40 21,641
Biog 93.3 40 21,681
SSH 93.3 3 21,684
SSH 93.6 2 21,686
SSH 93.7 2 21,688
SSH 93.7 2 21,690
SSH 93.7 3 21,693
SSH 93.8 3 21,696
SSH 93.9 3 21,698
WD 94.5 6 21,705
WD 94.5 6 21,711
WD 94.5 6 21,717
WD 94.5 6 21,724
WD 94.5 6 21,730
WD 94.5 6 21,737
WD 94.5 6 21,743
WD 94.5 6 21,749
WD 94.5 6 21,756
WD 94.5 6 21,762
WD 94.5 6 21,768
WD 94.5 6 21,775
WD 94.5 6 21,781
WD 94.5 6 21,788
WD 94.5 6 21,794
WD 94.5 6 21,800
SSH 94.8 2 21,802
SSH 95.1 2 21,804
WTE 95.2 7 21,811
WTE 95.2 7 21,818
WTE 95.2 7 21,824
WTE 95.2 7 21,831
SSH 95.2 2 21,833
SSH 95.4 2 21,835
SSH 95.7 2 21,837
SSH 95.9 2 21,839
SSH 95.9 2 21,841
Sew 96.0 2 21,843
Sew 96.0 2 21,845
Sew 96.0 2 21,847
Sew 96.0 2 21,849
SSH 96.1 2 21,851
Curve 3 - RES Curve (social)
Sew 96.3 2 21,853
Sew 96.3 2 21,855
Sew 96.3 2 21,857
Sew 96.3 2 21,859
SSH 96.5 2 21,861
SSH 96.7 273 22,134
WTE 96.9 10 22,143
WTE 96.9 10 22,153
WTE 96.9 10 22,162
WTE 96.9 10 22,172
SSH 97.4 2 22,174
SSH 97.6 2 22,176
SSH 97.6 2 22,178
SSH 97.8 2 22,180
SSH 97.8 3 22,183
SSH 98.1 2 22,185
SSH 98.2 3 22,187
SSH 98.3 2 22,189
SSH 98.3 2 22,191
Sew 98.3 2 22,193
Sew 98.3 2 22,194
Sew 98.3 2 22,196
Sew 98.3 2 22,198
SSH 98.8 6 22,203
Biog 99.1 46 22,249
Biog 99.1 46 22,295
Biog 99.1 46 22,340
Biog 99.1 46 22,386
SSH 99.1 2 22,388
SSH 99.2 2 22,390
SSH 99.3 3 22,393
SSH 99.4 2 22,395
SSH 99.4 2 22,396
SSH 99.6 2 22,398
Biog 99.6 36 22,435
Biog 99.6 36 22,471
Biog 99.6 36 22,508
Biog 99.6 36 22,544
SSH 99.7 2 22,546
SSH 100.5 2 22,547
SSH 100.5 49 22,596
WD 100.6 6 22,602
WD 100.6 6 22,609
WD 100.6 6 22,615
WD 100.6 6 22,621
WD 100.6 6 22,628
WD 100.6 6 22,634
WD 100.6 6 22,641
WD 100.6 6 22,647
WD 100.6 6 22,653
WD 100.6 6 22,660
WD 100.6 6 22,666
WD 100.6 6 22,672
WD 100.6 6 22,679
WD 100.6 6 22,685
WD 100.6 6 22,691
WD 100.6 6 22,698
SSH 101.0 105 22,803
SSH 101.1 25 22,828
SSH 101.8 2 22,829
SSH 101.9 2 22,831
Sew 101.9 2 22,833
Sew 101.9 2 22,835
Sew 101.9 2 22,836
Curve 3 - RES Curve (social)
Sew 101.9 2 22,838
SSH 102.1 3 22,841
SSH 102.2 2 22,843
SSH 102.3 2 22,844
WD 102.3 163 23,007
WD 102.3 163 23,170
WD 102.3 163 23,332
WD 102.3 163 23,495
WD 102.3 163 23,657
WD 102.3 163 23,820
WD 102.3 163 23,983
WD 102.3 163 24,145
WD 102.3 163 24,308
WD 102.3 163 24,471
WD 102.3 163 24,633
WD 102.3 163 24,796
WD 102.3 163 24,959
WD 102.3 163 25,121
WD 102.3 163 25,284
WD 102.3 163 25,446
SSH 102.4 2 25,448
SSH 102.6 6 25,454
SSH 103.3 2 25,455
SSH 103.8 2 25,457
Sew 104.0 2 25,459
Sew 104.0 2 25,461
Sew 104.0 2 25,463
Sew 104.0 2 25,465
SSH 104.1 3 25,468
SSH 104.4 3 25,470
SSH 104.5 1 25,472
SSH 104.6 2 25,474
SSH 104.6 1 25,475
WD 104.7 6 25,482
WD 104.7 6 25,488
WD 104.7 6 25,494
WD 104.7 6 25,501
WD 104.7 6 25,507
WD 104.7 6 25,514
WD 104.7 6 25,520
WD 104.7 6 25,526
WD 104.7 6 25,533
WD 104.7 6 25,539
WD 104.7 6 25,545
WD 104.7 6 25,552
WD 104.7 6 25,558
WD 104.7 6 25,565
WD 104.7 6 25,571
WD 104.7 6 25,577
SSH 104.9 1 25,579
SSH 105.0 43 25,622
Biog 105.0 42 25,664
Biog 105.0 42 25,706
Biog 105.0 42 25,749
Biog 105.0 42 25,791
SSH 105.4 1 25,792
SSH 105.6 1 25,794
SSH 105.7 1 25,795
SSH 105.7 3 25,798
SSH 106.6 1 25,800
Sew 106.7 2 25,802
Sew 106.7 2 25,804
Sew 106.7 2 25,806
Sew 106.7 2 25,808
Curve 3 - RES Curve (social)
SSH 106.9 1 25,810
SSH 107.0 1 25,811
SSH 107.9 1 25,812
WD 108.1 218 26,031
WD 108.1 218 26,249
WD 108.1 218 26,467
WD 108.1 218 26,686
WD 108.1 218 26,904
WD 108.1 218 27,122
WD 108.1 218 27,340
WD 108.1 218 27,559
WD 108.1 218 27,777
WD 108.1 218 27,995
WD 108.1 218 28,214
WD 108.1 218 28,432
WD 108.1 218 28,650
WD 108.1 218 28,869
WD 108.1 218 29,087
WD 108.1 218 29,305
SSH 108.6 3 29,308
SSH 108.6 1 29,310
WD 109.0 163 29,472
WD 109.0 163 29,635
WD 109.0 163 29,797
WD 109.0 163 29,960
WD 109.0 163 30,123
WD 109.0 163 30,285
WD 109.0 163 30,448
WD 109.0 163 30,611
WD 109.0 163 30,773
WD 109.0 163 30,936
WD 109.0 163 31,099
WD 109.0 163 31,261
WD 109.0 163 31,424
WD 109.0 163 31,586
WD 109.0 163 31,749
WD 109.0 163 31,912
SSH 109.2 6 31,917
SSH 109.2 1 31,919
SSH 109.2 1 31,920
SSH 109.4 1 31,921
Biog 109.6 40 31,961
Biog 109.6 40 32,001
Biog 109.6 40 32,041
Biog 109.6 40 32,080
SSH 109.7 1 32,082
WTE 109.8 8 32,090
WTE 109.8 8 32,099
WTE 109.8 8 32,107
WTE 109.8 8 32,115
SSH 109.9 1 32,117
SSH 109.9 1 32,118
SSH 110.0 3 32,121
Sew 110.1 2 32,123
Sew 110.1 2 32,124
Sew 110.1 2 32,126
Sew 110.1 2 32,128
SSH 110.5 1 32,129
SSH 110.7 1 32,130
SSH 110.9 1 32,131
WD 110.9 6 32,138
WD 110.9 6 32,144
WD 110.9 6 32,151
WD 110.9 6 32,157
Curve 3 - RES Curve (social)
WD 110.9 6 32,163
WD 110.9 6 32,170
WD 110.9 6 32,176
WD 110.9 6 32,182
WD 110.9 6 32,189
WD 110.9 6 32,195
WD 110.9 6 32,202
WD 110.9 6 32,208
WD 110.9 6 32,214
WD 110.9 6 32,221
WD 110.9 6 32,227
WD 110.9 6 32,233
SSH 111.4 2 32,236
Sew 111.8 2 32,237
Sew 111.8 2 32,239
Sew 111.8 2 32,241
Sew 111.8 2 32,242
SSH 112.3 1 32,243
SSH 112.7 1 32,244
SSH 112.8 2 32,247
SSH 113.1 1 32,248
WD 113.4 163 32,410
WD 113.4 163 32,573
WD 113.4 163 32,736
WD 113.4 163 32,898
WD 113.4 163 33,061
WD 113.4 163 33,224
WD 113.4 163 33,386
WD 113.4 163 33,549
WD 113.4 163 33,711
WD 113.4 163 33,874
WD 113.4 163 34,037
WD 113.4 163 34,199
WD 113.4 163 34,362
WD 113.4 163 34,525
WD 113.4 163 34,687
WD 113.4 163 34,850
SSH 115.2 6 34,856
WD 115.2 218 35,074
WD 115.2 218 35,292
WD 115.2 218 35,511
WD 115.2 218 35,729
WD 115.2 218 35,947
WD 115.2 218 36,166
WD 115.2 218 36,384
WD 115.2 218 36,602
WD 115.2 218 36,821
WD 115.2 218 37,039
WD 115.2 218 37,257
WD 115.2 218 37,475
WD 115.2 218 37,694
WD 115.2 218 37,912
WD 115.2 218 38,130
WD 115.2 218 38,349
Sew 115.6 2 38,351
Sew 115.6 2 38,353
Sew 115.6 2 38,355
Sew 115.6 2 38,357
SSH 115.6 1 38,358
SSH 115.7 4 38,362
SSH 116.2 2 38,364
SSH 116.4 1 38,365
SSH 117.1 1 38,366
SSH 117.3 3 38,369
Curve 3 - RES Curve (social)
Biog 117.5 36 38,405
Biog 117.5 36 38,442
Biog 117.5 36 38,478
Biog 117.5 36 38,514
WTE 117.9 10 38,524
WTE 117.9 10 38,534
WTE 117.9 10 38,543
WTE 117.9 10 38,553
SSH 118.7 1 38,554
SSH 118.9 1 38,555
SSH 118.9 1 38,555
SSH 119.5 6 38,561
SSH 119.6 5 38,567
WD 119.9 218 38,785
WD 119.9 218 39,003
WD 119.9 218 39,221
WD 119.9 218 39,440
WD 119.9 218 39,658
WD 119.9 218 39,876
WD 119.9 218 40,095
WD 119.9 218 40,313
WD 119.9 218 40,531
WD 119.9 218 40,750
WD 119.9 218 40,968
WD 119.9 218 41,186
WD 119.9 218 41,405
WD 119.9 218 41,623
WD 119.9 218 41,841
WD 119.9 218 42,059
WD 120.1 163 42,222
WD 120.1 163 42,385
WD 120.1 163 42,547
WD 120.1 163 42,710
WD 120.1 163 42,873
WD 120.1 163 43,035
WD 120.1 163 43,198
WD 120.1 163 43,360
WD 120.1 163 43,523
WD 120.1 163 43,686
WD 120.1 163 43,848
WD 120.1 163 44,011
WD 120.1 163 44,174
WD 120.1 163 44,336
WD 120.1 163 44,499
WD 120.1 163 44,662
WTE 120.4 8 44,669
WTE 120.4 8 44,677
WTE 120.4 8 44,685
WTE 120.4 8 44,692
SSH 120.6 1 44,693
SSH 120.6 1 44,694
SSH 120.6 1 44,695
Sew 120.8 2 44,697
Sew 120.8 2 44,698
Sew 120.8 2 44,700
Sew 120.8 2 44,702
SSH 120.8 4 44,706
SSH 120.9 2 44,708
SSH 121.6 1 44,708
SSH 121.8 126 44,834
Sew 122.4 2 44,836
Sew 122.4 2 44,838
Sew 122.4 2 44,840
Sew 122.4 2 44,842
Curve 3 - RES Curve (social)
SSH 122.9 2 44,844
SSH 124.8 1 44,844
SSH 125.4 3 44,847
SSH 126.6 1 44,848
WD 127.0 218 45,066
WD 127.0 218 45,285
WD 127.0 218 45,503
WD 127.0 218 45,721
WD 127.0 218 45,940
WD 127.0 218 46,158
WD 127.0 218 46,376
WD 127.0 218 46,594
WD 127.0 218 46,813
WD 127.0 218 47,031
WD 127.0 218 47,249
WD 127.0 218 47,468
WD 127.0 218 47,686
WD 127.0 218 47,904
WD 127.0 218 48,123
WD 127.0 218 48,341
SSH 127.2 1 48,342
SSH 127.8 1 48,342
SSH 128.1 1 48,343
SSH 128.3 5 48,349
SSH 130.7 1 48,350
SSH 131.1 1 48,350
SSH 131.1 0 48,351
SSH 131.5 0 48,351
SSH 131.8 1 48,352
SSH 133.2 0 48,353
WTE 133.5 8 48,361
WTE 133.5 8 48,370
WTE 133.5 8 48,378
WTE 133.5 8 48,386
SSH 134.0 1 48,388
Sew 134.2 2 48,390
Sew 134.2 2 48,391
Sew 134.2 2 48,393
Sew 134.2 2 48,395
SSH 134.5 0 48,395
SSH 135.6 0 48,396
SSH 135.8 1 48,397
SSH 136.6 1 48,398
SSH 136.8 2 48,400
SSH 138.8 0 48,400
WTE 140.8 7 48,407
WTE 140.8 7 48,413
WTE 140.8 7 48,420
WTE 140.8 7 48,426
SSH 140.9 0 48,427
SSH 141.3 1 48,428
SSH 141.4 0 48,429
SSH 143.1 0 48,429
SSH 145.9 1 48,430
SSH 146.0 0 48,431
WTE 146.4 8 48,438
WTE 146.4 8 48,446
WTE 146.4 8 48,454
WTE 146.4 8 48,461
SSH 149.0 0 48,462
SSH 149.1 1 48,463
WTE 149.2 10 48,472
WTE 149.2 10 48,482
WTE 149.2 10 48,491
Curve 3 - RES Curve (social)
WTE 149.2 10 48,501
SSH 149.5 0 48,501
SSH 152.7 0 48,502
SSH 153.4 0 48,502
SSH 153.9 1 48,503
SSH 154.3 0 48,503
SSH 155.5 0 48,503
SSH 155.9 1 48,505
SSH 156.3 12 48,517
SSH 157.0 1 48,518
SSH 157.7 0 48,518
SSH 160.2 3 48,521
SSH 161.8 0 48,521
SSH 163.5 0 48,521
SSH 164.6 1 48,522
SSH 167.2 1 48,523
WTE 169.0 8 48,531
WTE 169.0 8 48,540
WTE 169.0 8 48,548
WTE 169.0 8 48,557
WTE 171.2 7 48,563
WTE 171.2 7 48,570
WTE 171.2 7 48,576
WTE 171.2 7 48,583
SSH 172.9 0 48,583
SSH 175.0 0 48,583
SSH 176.0 0 48,584
SSH 177.7 2 48,585
SSH 178.6 1 48,586
SSH 179.6 1 48,587
SSH 181.3 1 48,588
SSH 184.0 0 48,588
WTE 185.4 8 48,596
WTE 185.4 8 48,604
WTE 185.4 8 48,611
WTE 185.4 8 48,619
SSH 190.8 0 48,619
SSH 198.0 2 48,622
SSH 199.9 1 48,622
SSH 200.2 1 48,623
SSH 203.9 1 48,624
SSH 203.9 1 48,625
SSH 204.8 0 48,625
SSH 205.1 1 48,626
SSH 210.8 1 48,627
SSH 211.2 0 48,627
SSH 211.5 1 48,628
SSH 213.3 1 48,629
SSH 215.7 1 48,631
SSH 215.8 1 48,631
WTE 216.8 7 48,638
WTE 216.8 7 48,644
WTE 216.8 7 48,651
WTE 216.8 7 48,657
SSH 219.8 0 48,658
SSH 222.3 1 48,659
SSH 224.1 1 48,660
SSH 226.4 0 48,660
SSH 232.4 1 48,660
SSH 238.1 0 48,661
SSH 238.1 0 48,661
SSH 245.0 0 48,661
SSH 252.9 5 48,665
ST 272.3 14 48,679
Curve 3 - RES Curve (social)
ST 272.3 14 48,693
ST 272.3 14 48,707
ST 272.3 14 48,722
ST 282.6 14 48,735
ST 282.6 14 48,749
ST 282.6 14 48,762
ST 282.6 14 48,776
ST 289.9 13 48,789
ST 289.9 13 48,802
ST 289.9 13 48,815
ST 289.9 13 48,828
ST 301.6 13 48,841
ST 301.6 13 48,853
ST 301.6 13 48,866
ST 301.6 13 48,879
ST 314.9 14 48,893
ST 314.9 14 48,907
ST 314.9 14 48,921
ST 314.9 14 48,935
SSH 317.7 4 48,939
ST 326.8 14 48,953
ST 326.8 14 48,966
ST 326.8 14 48,980
ST 326.8 14 48,993
ST 335.2 13 49,006
ST 335.2 13 49,019
ST 335.2 13 49,033
ST 335.2 13 49,046
ST 343.3 14 49,060
ST 343.3 14 49,074
ST 343.3 14 49,088
ST 343.3 14 49,102
PV 343.5 74 49,175
PV 343.5 74 49,249
PV 343.5 74 49,323
PV 343.5 74 49,396
ST 348.8 13 49,409
ST 348.8 13 49,422
ST 348.8 13 49,434
ST 348.8 13 49,447
ST 356.3 14 49,460
ST 356.3 14 49,474
ST 356.3 14 49,487
ST 356.3 14 49,501
PV 356.4 71 49,572
PV 356.4 71 49,643
PV 356.4 71 49,714
PV 356.4 71 49,785
PV 360.4 74 49,858
PV 360.4 74 49,932
PV 360.4 74 50,005
PV 360.4 74 50,079
ST 365.5 13 50,092
ST 365.5 13 50,105
ST 365.5 13 50,119
ST 365.5 13 50,132
PV 365.7 69 50,201
PV 365.7 69 50,270
PV 365.7 69 50,339
PV 365.7 69 50,408
PV 371.7 74 50,482
PV 371.7 74 50,555
PV 371.7 74 50,629
PV 371.7 74 50,703
Curve 3 - RES Curve (social)
PV 374.0 71 50,774
PV 374.0 71 50,845
PV 374.0 71 50,916
PV 374.0 71 50,986
ST 380.2 13 50,999
ST 380.2 13 51,012
ST 380.2 13 51,024
ST 380.2 13 51,037
PV 380.4 66 51,104
PV 380.4 66 51,170
PV 380.4 66 51,236
PV 380.4 66 51,303
PV 383.7 69 51,372
PV 383.7 69 51,441
PV 383.7 69 51,510
PV 383.7 69 51,579
PV 385.8 71 51,650
PV 385.8 71 51,721
PV 385.8 71 51,792
PV 385.8 71 51,863
ST 385.9 14 51,877
ST 385.9 14 51,891
ST 385.9 14 51,905
ST 385.9 14 51,919
PV 388.7 74 51,993
PV 388.7 74 52,066
PV 388.7 74 52,140
PV 388.7 74 52,214
PV 395.7 69 52,283
PV 395.7 69 52,352
PV 395.7 69 52,421
PV 395.7 69 52,490
PV 399.2 66 52,557
PV 399.2 66 52,623
PV 399.2 66 52,690
PV 399.2 66 52,756
ST 400.5 14 52,770
ST 400.5 14 52,783
ST 400.5 14 52,797
ST 400.5 14 52,810
PV 403.4 71 52,881
PV 403.4 71 52,952
PV 403.4 71 53,023
PV 403.4 71 53,094
SSH 405.7 33 53,127
ST 410.8 13 53,140
ST 410.8 13 53,153
ST 410.8 13 53,166
ST 410.8 13 53,179
PV 411.7 66 53,246
PV 411.7 66 53,312
PV 411.7 66 53,379
PV 411.7 66 53,445
PV 413.8 69 53,514
PV 413.8 69 53,583
PV 413.8 69 53,653
PV 413.8 69 53,722
ST 427.4 13 53,734
ST 427.4 13 53,747
ST 427.4 13 53,760
ST 427.4 13 53,772
PV 430.5 66 53,839
PV 430.5 66 53,905
PV 430.5 66 53,972
Curve 3 - RES Curve (social)
PV 430.5 66 54,038
Curve 4 - Electricity Curve (Private)

Private Cost Generation Cum


Code ($/MWh) (GWh) Generation
SSH 43.0 45 45
SSH 43.0 42 87
SSH 43.0 35 122
SSH 43.0 35 157
SSH 43.0 169 326
SSH 43.0 185 511
SSH 43.0 84 595
SSH 43.0 224 819
SSH 45.0 80 900
SSH 45.2 107 1,007
SSH 45.2 77 1,083
SSH 45.6 186 1,269
SSH 46.2 57 1,326
SSH 47.2 196 1,522
LFG 47.7 5 1,528
LFG 47.7 5 1,533
LFG 47.7 5 1,538
LFG 47.7 5 1,543
SSH 49.1 29 1,572
SSH 49.1 22 1,594
SSH 49.1 17 1,611
SSH 49.1 12 1,623
SSH 49.1 34 1,656
SSH 49.1 31 1,688
SSH 49.1 5 1,693
SSH 49.1 25 1,717
SSH 49.1 25 1,742
SSH 49.1 15 1,757
SSH 49.1 7 1,764
SSH 49.1 22 1,786
SSH 49.1 20 1,807
SSH 49.1 34 1,840
SSH 49.1 15 1,855
SSH 49.1 14 1,869
SSH 49.1 14 1,883
SSH 49.1 14 1,897
SSH 49.1 6 1,902
SSH 49.1 4 1,906
SSH 49.1 5 1,911
SSH 49.1 12 1,923
SSH 49.1 12 1,935
SSH 49.1 11 1,946
SSH 49.1 11 1,956
SSH 49.1 10 1,967
SSH 49.1 5 1,972
SSH 49.1 12 1,984
SSH 49.1 4 1,988
SSH 49.1 10 1,997
SSH 49.1 8 2,005
SSH 49.1 8 2,013
SSH 49.1 8 2,020
SSH 49.1 8 2,028
SSH 49.1 7 2,034
SSH 49.1 6 2,041
SSH 49.1 34 2,075
SSH 49.1 4 2,078
SSH 49.1 2 2,081
SSH 50.1 7 2,087
SSH 50.1 59 2,146
Nuke 50.4 11,937 14,083
SSH 50.5 5 14,087
Curve 4 - Electricity Curve (Private)
Bag 50.9 84 14,172
SSH 50.9 4 14,175
SSH 50.9 7 14,182
SSH 51.3 42 14,224
SSH 51.4 6 14,230
SSH 51.4 17 14,247
SSH 51.5 66 14,313
SSH 51.6 58 14,371
SSH 51.7 18 14,389
LFG 51.7 5 14,393
LFG 51.7 5 14,398
LFG 51.7 5 14,403
LFG 51.7 5 14,408
LFG 51.7 5 14,413
LFG 51.7 5 14,418
LFG 51.7 5 14,423
LFG 51.7 5 14,428
SSH 51.7 17 14,445
SSH 51.8 17 14,462
SSH 51.8 17 14,478
SSH 52.0 4 14,482
SSH 52.1 5 14,488
SSH 52.2 29 14,516
SSH 52.2 11 14,527
SSH 52.2 12 14,539
SSH 52.2 5 14,543
SSH 52.2 6 14,550
SSH 52.2 16 14,566
SSH 52.3 19 14,585
SSH 52.3 6 14,591
SSH 52.3 9 14,600
SSH 52.3 7 14,607
SSH 52.4 3 14,610
SSH 52.4 17 14,626
SSH 52.5 16 14,643
SSH 52.5 16 14,658
SSH 52.6 15 14,674
SSH 52.8 18 14,692
SSH 52.9 14 14,706
SSH 52.9 26 14,732
SSH 52.9 16 14,747
SSH 53.1 18 14,765
SSH 53.2 16 14,781
SSH 53.2 11 14,792
SSH 53.2 15 14,807
SSH 53.3 16 14,823
SSH 53.3 7 14,829
SSH 53.3 227 15,056
SSH 53.4 20 15,076
SSH 53.4 15 15,091
SSH 53.5 18 15,109
SSH 53.6 143 15,252
SSH 53.6 135 15,387
Bag 53.6 84 15,471
SSH 53.8 20 15,491
SSH 53.8 20 15,512
SSH 53.8 20 15,532
SSH 53.8 15 15,547
SSH 53.8 15 15,562
SSH 53.9 20 15,582
SSH 53.9 15 15,597
SSH 53.9 83 15,680
SSH 53.9 15 15,694
SSH 53.9 4 15,698
Curve 4 - Electricity Curve (Private)
SSH 54.0 21 15,719
Bag 54.0 74 15,794
SSH 54.1 100 15,894
SSH 54.1 6 15,900
SSH 54.1 19 15,919
SSH 54.2 111 16,030
SSH 54.2 22 16,052
SSH 54.2 14 16,066
SSH 54.2 8 16,074
SSH 54.3 7 16,081
SSH 54.3 94 16,175
LFG 54.4 5 16,180
LFG 54.4 5 16,185
LFG 54.4 5 16,190
LFG 54.4 5 16,195
SSH 54.5 14 16,210
SSH 54.6 23 16,232
SSH 54.6 95 16,328
Bag 54.6 84 16,412
SSH 54.6 252 16,664
SSH 54.6 3 16,668
SSH 54.7 4 16,672
LFG 54.7 4 16,676
LFG 54.7 4 16,681
LFG 54.7 4 16,685
LFG 54.7 4 16,690
SSH 54.8 13 16,703
LSH 54.8 69,180 85,883
SSH 54.9 23 85,906
SSH 54.9 8 85,914
SSH 54.9 24 85,938
SSH 54.9 13 85,950
SSH 55.0 25 85,975
SSH 55.0 25 86,000
SSH 55.0 25 86,026
SSH 55.2 9 86,035
SSH 55.3 26 86,061
SSH 55.3 26 86,087
SSH 55.3 9 86,096
SSH 55.4 8 86,104
Bag 55.5 84 86,188
SSH 55.5 14 86,202
Coal 55.6 28,539 114,741
SSH 55.6 14 114,755
SSH 55.7 78 114,833
SSH 55.8 76 114,909
SSH 55.9 6 114,915
SSH 55.9 75 114,990
SSH 56.0 280 115,271
SSH 56.0 54 115,325
SSH 56.0 74 115,398
SSH 56.0 126 115,524
SSH 56.0 3 115,527
LFG 56.0 5 115,532
LFG 56.0 5 115,537
LFG 56.0 5 115,542
LFG 56.0 5 115,546
SSH 56.1 56 115,603
SSH 56.4 5 115,608
SSH 56.5 51 115,659
Bag 56.6 68 115,727
SSH 56.7 28 115,755
Bag 56.7 74 115,829
SSH 56.9 8 115,837
Curve 4 - Electricity Curve (Private)
SSH 57.0 13 115,850
SSH 57.0 13 115,863
SSH 57.0 17 115,879
SSH 57.0 28 115,908
SSH 57.1 29 115,936
Bag 57.1 84 116,020
SSH 57.2 315 116,336
SSH 57.3 42 116,378
Bag 57.3 84 116,462
SSH 57.4 56 116,518
SSH 57.5 42 116,560
SSH 57.7 3 116,563
SSH 57.7 29 116,592
SSH 57.8 18 116,609
SSH 57.8 5 116,614
SSH 57.9 29 116,643
SSH 58.0 15 116,659
SSH 58.0 28 116,687
SSH 58.0 126 116,813
SSH 58.0 12 116,825
SSH 58.0 13 116,837
Bag 58.2 84 116,922
Bag 58.2 74 116,996
LFG 58.3 5 117,001
LFG 58.3 5 117,006
LFG 58.3 5 117,012
LFG 58.3 5 117,017
SSH 58.4 9 117,026
Bag 58.6 74 117,100
SSH 58.6 12 117,112
SSH 58.8 7 117,119
LFG 58.9 5 117,123
LFG 58.9 5 117,128
LFG 58.9 5 117,133
LFG 58.9 5 117,138
SSH 58.9 11 117,148
SSH 58.9 8 117,156
SSH 59.1 52 117,208
SSH 59.1 3 117,211
SSH 59.1 10 117,221
Bag 59.2 84 117,305
SSH 59.2 11 117,316
LFG 59.3 4 117,321
LFG 59.3 4 117,325
LFG 59.3 4 117,330
LFG 59.3 4 117,334
Bag 59.3 68 117,402
SSH 59.5 11 117,413
SSH 59.6 11 117,424
SSH 59.6 5 117,429
Bag 59.8 84 117,513
SSH 59.8 10 117,523
SSH 59.9 6 117,529
SSH 60.0 32 117,561
LFG 60.0 4 117,565
LFG 60.0 4 117,569
LFG 60.0 4 117,573
LFG 60.0 4 117,577
SSH 60.3 11 117,588
SSH 60.3 23 117,611
SSH 60.4 13 117,624
SSH 60.4 21 117,646
SSH 60.4 24 117,670
SSH 60.5 8 117,678
Curve 4 - Electricity Curve (Private)
SSH 60.6 10 117,688
SSH 60.7 52 117,740
SSH 60.7 18 117,758
SSH 60.7 7 117,765
Bag 60.8 84 117,849
SSH 60.8 34 117,883
SSH 60.8 22 117,905
SSH 60.8 10 117,915
SSH 60.9 41 117,956
Bag 60.9 74 118,030
SSH 61.0 16 118,046
Bag 61.0 74 118,120
Biog 61.1 46 118,166
Biog 61.1 46 118,212
Biog 61.1 46 118,257
Biog 61.1 46 118,303
Bag 61.1 68 118,371
Bag 61.2 68 118,439
Bag 61.3 74 118,513
SSH 61.4 39 118,552
SSH 61.5 33 118,585
SSH 61.5 10 118,595
Bag 61.5 58 118,653
Bag 61.6 84 118,737
SSH 61.7 210 118,947
SSH 61.8 29 118,977
SSH 61.8 10 118,986
Bag 61.9 84 119,071
SSH 61.9 9 119,080
SSH 62.0 9 119,089
SSH 62.1 18 119,107
SSH 62.2 9 119,117
LFG 62.4 4 119,121
LFG 62.4 4 119,125
LFG 62.4 4 119,130
LFG 62.4 4 119,134
SSH 62.4 9 119,143
SSH 62.4 34 119,178
SSH 62.4 36 119,214
SSH 62.4 5 119,219
SSH 62.5 24 119,243
SSH 62.7 4 119,248
Bag 62.7 74 119,322
SSH 62.8 38 119,360
SSH 63.0 9 119,369
SSH 63.0 9 119,378
SSH 63.1 58 119,436
LFG 63.2 5 119,440
LFG 63.2 5 119,445
LFG 63.2 5 119,450
LFG 63.2 5 119,455
SSH 63.5 9 119,464
Bag 63.5 84 119,548
SSH 63.7 9 119,557
Bag 63.7 74 119,631
SSH 63.8 58 119,689
Bag 63.9 68 119,757
Bag 63.9 68 119,825
Biog 63.9 42 119,867
Biog 63.9 42 119,909
Biog 63.9 42 119,951
Biog 63.9 42 119,993
SSH 64.0 5 119,998
SSH 64.0 256 120,255
Curve 4 - Electricity Curve (Private)
SSH 64.1 49 120,304
SSH 64.2 10 120,314
Bag 64.2 68 120,382
Bag 64.3 58 120,440
SSH 64.3 8 120,448
Bag 64.3 84 120,532
SSH 64.5 4 120,537
SSH 64.5 252 120,789
Biom 64.5 78 120,866
SSH 64.5 7 120,873
SSH 64.6 96 120,969
SSH 64.7 8 120,977
SSH 64.8 9 120,986
SSH 64.9 9 120,995
SSH 64.9 8 121,003
SSH 64.9 5 121,008
SSH 64.9 22 121,030
SSH 64.9 8 121,038
SSH 64.9 8 121,047
SSH 65.0 8 121,055
Biom 65.0 78 121,132
LFG 65.0 4 121,136
LFG 65.0 4 121,140
LFG 65.0 4 121,145
LFG 65.0 4 121,149
Bag 65.2 74 121,223
SSH 65.2 35 121,258
SSH 65.2 158 121,416
SSH 65.2 127 121,543
SSH 65.3 55 121,598
Bag 65.3 84 121,683
Biom 65.3 78 121,760
SSH 65.5 7 121,767
SSH 65.5 8 121,774
Bag 65.5 74 121,849
SSH 65.5 4 121,853
SSH 65.5 8 121,861
WTE 65.5 10 121,870
WTE 65.5 10 121,880
WTE 65.5 10 121,889
WTE 65.5 10 121,899
Bag 65.5 74 121,973
SSH 65.6 8 121,981
SSH 65.6 8 121,989
SSH 65.7 5 121,994
SSH 65.7 27 122,021
Bag 65.7 68 122,089
Biom 65.9 78 122,167
SSH 65.9 105 122,272
SSH 66.0 8 122,279
Biog 66.0 40 122,319
Biog 66.0 40 122,359
Biog 66.0 40 122,399
Biog 66.0 40 122,439
Bag 66.1 58 122,497
Biom 66.1 78 122,574
SSH 66.3 68 122,642
Biom 66.6 78 122,720
Gas 66.7 25,047 147,767
Bag 66.9 58 147,825
LFG 66.9 4 147,829
LFG 66.9 4 147,834
LFG 66.9 4 147,838
LFG 66.9 4 147,843
Curve 4 - Electricity Curve (Private)
Biom 67.0 78 147,920
Bag 67.0 68 147,988
SSH 67.2 8 147,996
SSH 67.2 8 148,004
SSH 67.2 8 148,011
SSH 67.2 8 148,019
SSH 67.2 8 148,027
SSH 67.2 8 148,034
SSH 67.2 4 148,038
Biom 67.2 78 148,116
Biom 67.5 78 148,193
SSH 67.6 8 148,201
SSH 67.6 8 148,208
Biom 67.7 78 148,286
SSH 67.8 68 148,354
SSH 67.9 7 148,361
Bag 67.9 74 148,435
Biom 68.0 78 148,513
Bag 68.0 84 148,597
SSH 68.1 7 148,604
SSH 68.1 7 148,611
SSH 68.2 7 148,618
Bag 68.3 74 148,693
LFG 68.4 4 148,697
LFG 68.4 4 148,701
LFG 68.4 4 148,705
LFG 68.4 4 148,709
Bag 68.4 68 148,777
Biom 68.5 78 148,854
SSH 68.6 7 148,861
Biom 68.6 68 148,930
SSH 68.6 3 148,933
Biom 68.8 78 149,010
SSH 68.8 7 149,017
Bag 68.8 68 149,085
Bag 68.8 58 149,143
SSH 68.8 13 149,156
Bag 68.8 68 149,224
SSH 68.9 7 149,230
SSH 68.9 7 149,237
Biom 69.1 68 149,306
Biom 69.3 78 149,383
Biom 69.4 68 149,452
Bag 69.6 58 149,510
Biom 69.6 78 149,587
SSH 69.7 6 149,593
SSH 69.7 3 149,596
Bag 69.7 74 149,671
Biog 69.8 36 149,707
Biog 69.8 36 149,743
Biog 69.8 36 149,780
Biog 69.8 36 149,816
Biom 70.0 68 149,885
SSH 70.1 6 149,891
SSH 70.1 20 149,911
Biom 70.1 78 149,988
SSH 70.2 10 149,998
Biom 70.4 68 150,066
Bag 70.5 58 150,124
SSH 70.5 16 150,140
SSH 70.6 6 150,147
SSH 70.7 196 150,343
SSH 70.8 6 150,349
Biom 70.9 68 150,417
Curve 4 - Electricity Curve (Private)
SSH 71.0 6 150,424
SSH 71.2 6 150,430
Biom 71.3 68 150,498
Bag 71.4 58 150,556
Bag 71.5 68 150,624
SSH 71.5 29 150,653
Bag 71.6 68 150,720
Biom 71.6 68 150,789
Biom 71.8 68 150,857
SSH 71.8 6 150,863
Biom 72.0 62 150,926
SSH 72.1 5 150,931
Biom 72.1 68 150,999
SSH 72.4 6 151,005
SSH 72.4 6 151,010
Bag 72.5 74 151,085
Biom 72.5 68 151,153
Biom 72.5 62 151,216
Biom 72.8 62 151,278
SSH 72.9 6 151,284
Biom 73.0 68 151,352
SSH 73.1 3 151,355
SSH 73.1 6 151,360
SSH 73.1 39 151,399
SSH 73.2 3 151,402
SSH 73.2 64 151,466
SSH 73.2 5 151,472
SSH 73.2 5 151,477
Bag 73.2 58 151,535
SSH 73.3 3 151,538
Biom 73.4 62 151,600
Bag 73.4 68 151,668
LFG 73.4 4 151,672
LFG 73.4 4 151,676
LFG 73.4 4 151,680
LFG 73.4 4 151,685
Biom 73.4 68 151,753
SSH 73.7 14 151,767
SSH 73.7 5 151,772
SSH 73.7 5 151,778
Biom 74.0 68 151,846
Biom 74.0 62 151,908
SSH 74.1 14 151,922
Bag 74.2 58 151,980
WTE 74.2 8 151,989
WTE 74.2 8 151,997
WTE 74.2 8 152,005
WTE 74.2 8 152,014
Biom 74.3 68 152,082
SSH 74.3 5 152,087
Biom 74.5 62 152,150
SSH 74.6 5 152,155
Biom 74.8 68 152,224
Biom 74.8 62 152,286
SSH 74.9 5 152,291
SSH 75.0 5 152,296
Bag 75.0 58 152,354
SSH 75.2 40 152,393
SSH 75.2 42 152,435
SSH 75.2 4 152,439
Biom 75.3 62 152,501
Biom 75.4 62 152,564
Biog 75.4 46 152,610
Biog 75.4 46 152,655
Curve 4 - Electricity Curve (Private)
Biog 75.4 46 152,701
Biog 75.4 46 152,747
SSH 75.4 3 152,750
SSH 75.4 4 152,754
SSH 75.4 5 152,759
SSH 75.4 5 152,764
SSH 75.6 3 152,767
SSH 75.8 5 152,772
SSH 75.8 5 152,777
Biom 75.8 62 152,839
Bag 75.9 58 152,897
SSH 76.0 5 152,902
Bag 76.1 68 152,969
Biom 76.2 62 153,032
SSH 76.3 7 153,039
SSH 76.4 8 153,046
SSH 76.4 5 153,051
SSH 76.6 5 153,056
Biom 76.7 62 153,118
SSH 77.2 4 153,122
Biom 77.3 62 153,185
SSH 77.6 4 153,189
Bag 77.8 58 153,247
Biom 77.8 62 153,310
Biom 78.2 62 153,372
Sew 78.2 2 153,374
Sew 78.2 2 153,376
Sew 78.2 2 153,378
Sew 78.2 2 153,380
SSH 78.2 79 153,460
SSH 78.2 4 153,464
SSH 78.3 4 153,468
SSH 78.5 4 153,472
Biom 78.5 53 153,526
SSH 78.5 4 153,530
Bag 78.6 58 153,588
Biom 78.7 62 153,650
SSH 78.7 4 153,654
Biom 79.0 53 153,708
SSH 79.1 4 153,711
SSH 79.2 4 153,715
Biog 79.3 42 153,758
Biog 79.3 42 153,800
Biog 79.3 42 153,842
Biog 79.3 42 153,884
Biom 79.4 53 153,938
SSH 79.8 4 153,942
Biom 79.9 53 153,995
SSH 80.3 2 153,997
SSH 80.3 4 154,001
SSH 80.4 4 154,005
Bag 80.4 58 154,063
SSH 80.5 4 154,066
SSH 80.7 85 154,152
Biom 80.8 53 154,205
SSH 81.2 4 154,209
Biom 81.4 53 154,262
WTE 81.4 8 154,270
WTE 81.4 8 154,277
WTE 81.4 8 154,285
WTE 81.4 8 154,293
SSH 81.5 4 154,296
SSH 81.5 4 154,300
Biom 81.7 53 154,353
Curve 4 - Electricity Curve (Private)
SSH 81.8 26 154,379
SSH 82.1 3 154,382
Biom 82.2 53 154,436
Biog 82.4 40 154,476
Biog 82.4 40 154,516
Biog 82.4 40 154,555
Biog 82.4 40 154,595
Biom 82.4 53 154,649
SSH 82.4 4 154,653
SSH 82.5 3 154,656
SSH 82.8 3 154,659
SSH 82.8 238 154,898
Biom 82.9 53 154,951
SSH 83.0 3 154,954
Bag 83.1 58 155,012
Biom 83.3 53 155,065
Biom 83.8 53 155,119
SSH 83.8 3 155,122
SSH 84.2 3 155,124
SSH 84.2 98 155,222
SSH 84.2 3 155,225
SSH 84.3 2 155,228
SSH 84.6 32 155,260
Sew 84.7 2 155,262
Sew 84.7 2 155,264
Sew 84.7 2 155,266
Sew 84.7 2 155,268
Biom 84.7 53 155,321
Biog 84.9 46 155,367
Biog 84.9 46 155,412
Biog 84.9 46 155,458
Biog 84.9 46 155,504
Biom 85.3 53 155,557
SSH 85.5 3 155,560
Biom 85.6 53 155,614
SSH 85.7 3 155,616
SSH 85.9 3 155,619
SSH 86.0 15 155,634
Biom 86.1 53 155,687
SSH 86.7 3 155,690
SSH 86.8 4 155,694
SSH 87.2 3 155,696
SSH 87.2 97 155,793
SSH 87.4 3 155,796
SSH 87.4 2 155,798
Biog 87.7 36 155,835
Biog 87.7 36 155,871
Biog 87.7 36 155,907
Biog 87.7 36 155,944
SSH 87.7 5 155,949
SSH 87.9 3 155,952
SSH 88.1 3 155,954
SSH 88.6 4 155,958
SSH 88.7 3 155,961
SSH 88.8 3 155,964
Sew 88.9 2 155,966
Sew 88.9 2 155,968
Sew 88.9 2 155,970
Sew 88.9 2 155,972
SSH 88.9 3 155,975
SSH 89.0 3 155,977
SSH 89.2 12 155,989
SSH 89.4 2 155,992
SSH 89.6 2 155,994
Curve 4 - Electricity Curve (Private)
Biog 89.6 42 156,036
Biog 89.6 42 156,079
Biog 89.6 42 156,121
Biog 89.6 42 156,163
Sew 89.7 2 156,165
Sew 89.7 2 156,167
Sew 89.7 2 156,169
Sew 89.7 2 156,170
SSH 89.9 5 156,176
SSH 90.0 2 156,178
SSH 90.0 2 156,181
SSH 90.1 3 156,183
SSH 90.5 4 156,187
SSH 91.1 2 156,189
SSH 91.2 2 156,192
SSH 91.2 2 156,194
SSH 91.5 2 156,196
SSH 91.9 13 156,209
SSH 91.9 2 156,211
SSH 92.0 2 156,214
SSH 92.2 2 156,216
SSH 92.5 2 156,218
SSH 92.6 2 156,220
SSH 92.8 2 156,222
SSH 92.9 3 156,225
Biog 93.3 40 156,265
Biog 93.3 40 156,305
Biog 93.3 40 156,345
Biog 93.3 40 156,385
SSH 93.3 3 156,387
SSH 93.6 2 156,389
SSH 93.7 2 156,391
SSH 93.7 2 156,393
SSH 93.7 3 156,396
SSH 93.8 3 156,399
SSH 93.9 3 156,402
WD 94.5 6 156,408
WD 94.5 6 156,415
WD 94.5 6 156,421
WD 94.5 6 156,427
WD 94.5 6 156,434
WD 94.5 6 156,440
WD 94.5 6 156,446
WD 94.5 6 156,453
WD 94.5 6 156,459
WD 94.5 6 156,466
WD 94.5 6 156,472
WD 94.5 6 156,478
WD 94.5 6 156,485
WD 94.5 6 156,491
WD 94.5 6 156,497
WD 94.5 6 156,504
SSH 94.8 2 156,506
SSH 95.1 2 156,508
WTE 95.2 7 156,514
WTE 95.2 7 156,521
WTE 95.2 7 156,528
WTE 95.2 7 156,534
SSH 95.2 2 156,536
SSH 95.4 2 156,538
SSH 95.7 2 156,540
SSH 95.9 2 156,542
SSH 95.9 2 156,544
Sew 96.0 2 156,546
Curve 4 - Electricity Curve (Private)
Sew 96.0 2 156,548
Sew 96.0 2 156,550
Sew 96.0 2 156,553
SSH 96.1 2 156,555
Sew 96.3 2 156,557
Sew 96.3 2 156,559
Sew 96.3 2 156,560
Sew 96.3 2 156,562
SSH 96.5 2 156,564
SSH 96.7 273 156,837
WTE 96.9 10 156,847
WTE 96.9 10 156,856
WTE 96.9 10 156,866
WTE 96.9 10 156,875
SSH 97.4 2 156,877
SSH 97.6 2 156,880
SSH 97.6 2 156,881
SSH 97.8 2 156,883
SSH 97.8 3 156,886
SSH 98.1 2 156,888
SSH 98.2 3 156,891
SSH 98.3 2 156,893
SSH 98.3 2 156,894
Sew 98.3 2 156,896
Sew 98.3 2 156,898
Sew 98.3 2 156,899
Sew 98.3 2 156,901
SSH 98.8 6 156,907
Biog 99.1 46 156,952
Biog 99.1 46 156,998
Biog 99.1 46 157,044
Biog 99.1 46 157,090
SSH 99.1 2 157,091
SSH 99.2 2 157,093
SSH 99.3 3 157,096
SSH 99.4 2 157,098
SSH 99.4 2 157,100
SSH 99.6 2 157,102
Biog 99.6 36 157,138
Biog 99.6 36 157,175
Biog 99.6 36 157,211
Biog 99.6 36 157,247
SSH 99.7 2 157,249
SSH 100.5 2 157,251
SSH 100.5 49 157,299
WD 100.6 6 157,306
WD 100.6 6 157,312
WD 100.6 6 157,319
WD 100.6 6 157,325
WD 100.6 6 157,331
WD 100.6 6 157,338
WD 100.6 6 157,344
WD 100.6 6 157,350
WD 100.6 6 157,357
WD 100.6 6 157,363
WD 100.6 6 157,369
WD 100.6 6 157,376
WD 100.6 6 157,382
WD 100.6 6 157,389
WD 100.6 6 157,395
WD 100.6 6 157,401
SSH 101.0 105 157,506
SSH 101.1 25 157,531
SSH 101.8 2 157,533
Curve 4 - Electricity Curve (Private)
SSH 101.9 2 157,534
Sew 101.9 2 157,536
Sew 101.9 2 157,538
Sew 101.9 2 157,540
Sew 101.9 2 157,542
SSH 102.1 3 157,545
SSH 102.2 2 157,546
SSH 102.3 2 157,548
WD 102.3 163 157,710
WD 102.3 163 157,873
WD 102.3 163 158,036
WD 102.3 163 158,198
WD 102.3 163 158,361
WD 102.3 163 158,524
WD 102.3 163 158,686
WD 102.3 163 158,849
WD 102.3 163 159,012
WD 102.3 163 159,174
WD 102.3 163 159,337
WD 102.3 163 159,499
WD 102.3 163 159,662
WD 102.3 163 159,825
WD 102.3 163 159,987
WD 102.3 163 160,150
SSH 102.4 2 160,152
SSH 102.6 6 160,157
SSH 103.3 2 160,159
SSH 103.8 2 160,160
Sew 104.0 2 160,162
Sew 104.0 2 160,164
Sew 104.0 2 160,166
Sew 104.0 2 160,168
SSH 104.1 3 160,171
SSH 104.4 3 160,174
SSH 104.5 1 160,175
SSH 104.6 2 160,177
SSH 104.6 1 160,179
WD 104.7 6 160,185
WD 104.7 6 160,192
WD 104.7 6 160,198
WD 104.7 6 160,204
WD 104.7 6 160,211
WD 104.7 6 160,217
WD 104.7 6 160,223
WD 104.7 6 160,230
WD 104.7 6 160,236
WD 104.7 6 160,242
WD 104.7 6 160,249
WD 104.7 6 160,255
WD 104.7 6 160,262
WD 104.7 6 160,268
WD 104.7 6 160,274
WD 104.7 6 160,281
SSH 104.9 1 160,282
SSH 105.0 43 160,325
Biog 105.0 42 160,368
Biog 105.0 42 160,410
Biog 105.0 42 160,452
Biog 105.0 42 160,494
SSH 105.4 1 160,496
SSH 105.6 1 160,497
SSH 105.7 1 160,499
SSH 105.7 3 160,502
SSH 106.6 1 160,503
Curve 4 - Electricity Curve (Private)
Sew 106.7 2 160,505
Sew 106.7 2 160,507
Sew 106.7 2 160,510
Sew 106.7 2 160,512
SSH 106.9 1 160,513
SSH 107.0 1 160,514
SSH 107.9 1 160,516
WD 108.1 218 160,734
WD 108.1 218 160,952
WD 108.1 218 161,171
WD 108.1 218 161,389
WD 108.1 218 161,607
WD 108.1 218 161,826
WD 108.1 218 162,044
WD 108.1 218 162,262
WD 108.1 218 162,480
WD 108.1 218 162,699
WD 108.1 218 162,917
WD 108.1 218 163,135
WD 108.1 218 163,354
WD 108.1 218 163,572
WD 108.1 218 163,790
WD 108.1 218 164,009
SSH 108.6 3 164,012
SSH 108.6 1 164,013
WD 109.0 163 164,176
WD 109.0 163 164,338
WD 109.0 163 164,501
WD 109.0 163 164,664
WD 109.0 163 164,826
WD 109.0 163 164,989
WD 109.0 163 165,151
WD 109.0 163 165,314
WD 109.0 163 165,477
WD 109.0 163 165,639
WD 109.0 163 165,802
WD 109.0 163 165,965
WD 109.0 163 166,127
WD 109.0 163 166,290
WD 109.0 163 166,453
WD 109.0 163 166,615
SSH 109.2 6 166,621
SSH 109.2 1 166,622
SSH 109.2 1 166,623
SSH 109.4 1 166,624
Biog 109.6 40 166,664
Biog 109.6 40 166,704
Biog 109.6 40 166,744
Biog 109.6 40 166,784
SSH 109.7 1 166,785
WTE 109.8 8 166,794
WTE 109.8 8 166,802
WTE 109.8 8 166,810
WTE 109.8 8 166,819
SSH 109.9 1 166,820
SSH 109.9 1 166,821
SSH 110.0 3 166,824
Sew 110.1 2 166,826
Sew 110.1 2 166,828
Sew 110.1 2 166,830
Sew 110.1 2 166,832
SSH 110.5 1 166,833
SSH 110.7 1 166,834
SSH 110.9 1 166,835
Curve 4 - Electricity Curve (Private)
WD 110.9 6 166,841
WD 110.9 6 166,848
WD 110.9 6 166,854
WD 110.9 6 166,860
WD 110.9 6 166,867
WD 110.9 6 166,873
WD 110.9 6 166,880
WD 110.9 6 166,886
WD 110.9 6 166,892
WD 110.9 6 166,899
WD 110.9 6 166,905
WD 110.9 6 166,911
WD 110.9 6 166,918
WD 110.9 6 166,924
WD 110.9 6 166,930
WD 110.9 6 166,937
SSH 111.4 2 166,939
Sew 111.8 2 166,941
Sew 111.8 2 166,942
Sew 111.8 2 166,944
Sew 111.8 2 166,946
SSH 112.3 1 166,947
SSH 112.7 1 166,948
SSH 112.8 2 166,950
SSH 113.1 1 166,951
WD 113.4 163 167,114
WD 113.4 163 167,276
WD 113.4 163 167,439
WD 113.4 163 167,602
WD 113.4 163 167,764
WD 113.4 163 167,927
WD 113.4 163 168,090
WD 113.4 163 168,252
WD 113.4 163 168,415
WD 113.4 163 168,578
WD 113.4 163 168,740
WD 113.4 163 168,903
WD 113.4 163 169,065
WD 113.4 163 169,228
WD 113.4 163 169,391
WD 113.4 163 169,553
SSH 115.2 6 169,559
WD 115.2 218 169,778
WD 115.2 218 169,996
WD 115.2 218 170,214
WD 115.2 218 170,433
WD 115.2 218 170,651
WD 115.2 218 170,869
WD 115.2 218 171,087
WD 115.2 218 171,306
WD 115.2 218 171,524
WD 115.2 218 171,742
WD 115.2 218 171,961
WD 115.2 218 172,179
WD 115.2 218 172,397
WD 115.2 218 172,616
WD 115.2 218 172,834
WD 115.2 218 173,052
Sew 115.6 2 173,054
Sew 115.6 2 173,056
Sew 115.6 2 173,058
Sew 115.6 2 173,060
SSH 115.6 1 173,061
SSH 115.7 4 173,065
Curve 4 - Electricity Curve (Private)
SSH 116.2 2 173,067
SSH 116.4 1 173,068
SSH 117.1 1 173,069
SSH 117.3 3 173,072
Biog 117.5 36 173,109
Biog 117.5 36 173,145
Biog 117.5 36 173,182
Biog 117.5 36 173,218
WTE 117.9 10 173,227
WTE 117.9 10 173,237
WTE 117.9 10 173,247
WTE 117.9 10 173,256
SSH 118.7 1 173,257
SSH 118.9 1 173,258
SSH 118.9 1 173,259
SSH 119.5 6 173,265
SSH 119.6 5 173,270
WD 119.9 218 173,488
WD 119.9 218 173,707
WD 119.9 218 173,925
WD 119.9 218 174,143
WD 119.9 218 174,362
WD 119.9 218 174,580
WD 119.9 218 174,798
WD 119.9 218 175,016
WD 119.9 218 175,235
WD 119.9 218 175,453
WD 119.9 218 175,671
WD 119.9 218 175,890
WD 119.9 218 176,108
WD 119.9 218 176,326
WD 119.9 218 176,545
WD 119.9 218 176,763
WD 120.1 163 176,926
WD 120.1 163 177,088
WD 120.1 163 177,251
WD 120.1 163 177,413
WD 120.1 163 177,576
WD 120.1 163 177,739
WD 120.1 163 177,901
WD 120.1 163 178,064
WD 120.1 163 178,227
WD 120.1 163 178,389
WD 120.1 163 178,552
WD 120.1 163 178,714
WD 120.1 163 178,877
WD 120.1 163 179,040
WD 120.1 163 179,202
WD 120.1 163 179,365
WTE 120.4 8 179,373
WTE 120.4 8 179,380
WTE 120.4 8 179,388
WTE 120.4 8 179,396
SSH 120.6 1 179,397
SSH 120.6 1 179,397
SSH 120.6 1 179,398
Sew 120.8 2 179,400
Sew 120.8 2 179,402
Sew 120.8 2 179,403
Sew 120.8 2 179,405
SSH 120.8 4 179,409
SSH 120.9 2 179,411
SSH 121.6 1 179,412
SSH 121.8 126 179,538
Curve 4 - Electricity Curve (Private)
Sew 122.4 2 179,540
Sew 122.4 2 179,542
Sew 122.4 2 179,543
Sew 122.4 2 179,545
SSH 122.9 2 179,547
SSH 124.8 1 179,548
SSH 125.4 3 179,551
SSH 126.6 1 179,552
WD 127.0 218 179,770
WD 127.0 218 179,988
WD 127.0 218 180,206
WD 127.0 218 180,425
WD 127.0 218 180,643
WD 127.0 218 180,861
WD 127.0 218 181,080
WD 127.0 218 181,298
WD 127.0 218 181,516
WD 127.0 218 181,735
WD 127.0 218 181,953
WD 127.0 218 182,171
WD 127.0 218 182,389
WD 127.0 218 182,608
WD 127.0 218 182,826
WD 127.0 218 183,044
SSH 127.2 1 183,045
SSH 127.8 1 183,046
SSH 128.1 1 183,047
SSH 128.3 5 183,052
SSH 130.7 1 183,053
SSH 131.1 1 183,054
SSH 131.1 0 183,054
SSH 131.5 0 183,055
SSH 131.8 1 183,056
SSH 133.2 0 183,056
WTE 133.5 8 183,065
WTE 133.5 8 183,073
WTE 133.5 8 183,082
WTE 133.5 8 183,090
Fuel 133.8 17,110 200,200
SSH 134.0 1 200,201
Sew 134.2 2 200,203
Sew 134.2 2 200,205
Sew 134.2 2 200,206
Sew 134.2 2 200,208
SSH 134.5 0 200,208
SSH 135.6 0 200,209
SSH 135.8 1 200,210
SSH 136.6 1 200,211
SSH 136.8 2 200,213
SSH 138.8 0 200,213
WTE 140.8 7 200,220
WTE 140.8 7 200,227
WTE 140.8 7 200,233
WTE 140.8 7 200,240
SSH 140.9 0 200,240
SSH 141.3 1 200,242
SSH 141.4 0 200,242
SSH 143.1 0 200,242
SSH 145.9 1 200,244
SSH 146.0 0 200,244
WTE 146.4 8 200,252
WTE 146.4 8 200,259
WTE 146.4 8 200,267
WTE 146.4 8 200,275
Curve 4 - Electricity Curve (Private)
SSH 149.0 0 200,275
SSH 149.1 1 200,276
WTE 149.2 10 200,285
WTE 149.2 10 200,295
WTE 149.2 10 200,305
WTE 149.2 10 200,314
SSH 149.5 0 200,314
SSH 152.7 0 200,315
SSH 153.4 0 200,315
SSH 153.9 1 200,316
SSH 154.3 0 200,316
SSH 155.5 0 200,316
SSH 155.9 1 200,318
SSH 156.3 12 200,330
SSH 157.0 1 200,331
SSH 157.7 0 200,331
SSH 160.2 3 200,334
SSH 161.8 0 200,334
SSH 163.5 0 200,334
SSH 164.6 1 200,335
SSH 167.2 1 200,336
WTE 169.0 8 200,345
WTE 169.0 8 200,353
WTE 169.0 8 200,362
WTE 169.0 8 200,370
WTE 171.2 7 200,377
WTE 171.2 7 200,383
WTE 171.2 7 200,390
WTE 171.2 7 200,396
SSH 172.9 0 200,397
SSH 175.0 0 200,397
SSH 176.0 0 200,397
SSH 177.7 2 200,399
SSH 178.6 1 200,399
SSH 179.6 1 200,401
SSH 181.3 1 200,401
SSH 184.0 0 200,402
WTE 185.4 8 200,409
WTE 185.4 8 200,417
WTE 185.4 8 200,425
WTE 185.4 8 200,432
SSH 190.8 0 200,433
SSH 198.0 2 200,435
SSH 199.9 1 200,436
SSH 200.2 1 200,436
SSH 203.9 1 200,437
SSH 203.9 1 200,438
SSH 204.8 0 200,438
SSH 205.1 1 200,440
SSH 210.8 1 200,440
SSH 211.2 0 200,440
SSH 211.5 1 200,442
SSH 213.3 1 200,443
SSH 215.7 1 200,444
SSH 215.8 1 200,444
WTE 216.8 7 200,451
WTE 216.8 7 200,458
WTE 216.8 7 200,464
WTE 216.8 7 200,471
SSH 219.8 0 200,471
SSH 222.3 1 200,472
SSH 224.1 1 200,473
SSH 226.4 0 200,473
SSH 232.4 1 200,474
Curve 4 - Electricity Curve (Private)
SSH 238.1 0 200,474
SSH 238.1 0 200,474
SSH 245.0 0 200,474
SSH 252.9 5 200,479
ST 272.3 14 200,493
ST 272.3 14 200,507
ST 272.3 14 200,521
ST 272.3 14 200,535
ST 282.6 14 200,548
ST 282.6 14 200,562
ST 282.6 14 200,575
ST 282.6 14 200,589
ST 289.9 13 200,602
ST 289.9 13 200,615
ST 289.9 13 200,628
ST 289.9 13 200,641
ST 301.6 13 200,654
ST 301.6 13 200,667
ST 301.6 13 200,679
ST 301.6 13 200,692
ST 314.9 14 200,706
ST 314.9 14 200,720
ST 314.9 14 200,734
ST 314.9 14 200,748
SSH 317.7 4 200,752
ST 326.8 14 200,766
ST 326.8 14 200,779
ST 326.8 14 200,793
ST 326.8 14 200,806
ST 335.2 13 200,820
ST 335.2 13 200,833
ST 335.2 13 200,846
ST 335.2 13 200,859
ST 343.3 14 200,873
ST 343.3 14 200,887
ST 343.3 14 200,901
ST 343.3 14 200,915
PV 343.5 74 200,989
PV 343.5 74 201,062
PV 343.5 74 201,136
PV 343.5 74 201,210
ST 348.8 13 201,222
ST 348.8 13 201,235
ST 348.8 13 201,247
ST 348.8 13 201,260
ST 356.3 14 201,274
ST 356.3 14 201,287
ST 356.3 14 201,301
ST 356.3 14 201,314
PV 356.4 71 201,385
PV 356.4 71 201,456
PV 356.4 71 201,527
PV 356.4 71 201,598
PV 360.4 74 201,671
PV 360.4 74 201,745
PV 360.4 74 201,819
PV 360.4 74 201,892
ST 365.5 13 201,905
ST 365.5 13 201,919
ST 365.5 13 201,932
ST 365.5 13 201,945
PV 365.7 69 202,014
PV 365.7 69 202,083
PV 365.7 69 202,152
Curve 4 - Electricity Curve (Private)
PV 365.7 69 202,222
PV 371.7 74 202,295
PV 371.7 74 202,369
PV 371.7 74 202,442
PV 371.7 74 202,516
PV 374.0 71 202,587
PV 374.0 71 202,658
PV 374.0 71 202,729
PV 374.0 71 202,800
ST 380.2 13 202,812
ST 380.2 13 202,825
ST 380.2 13 202,838
ST 380.2 13 202,850
PV 380.4 66 202,917
PV 380.4 66 202,983
PV 380.4 66 203,050
PV 380.4 66 203,116
PV 383.7 69 203,185
PV 383.7 69 203,254
PV 383.7 69 203,324
PV 383.7 69 203,393
PV 385.8 71 203,464
PV 385.8 71 203,535
PV 385.8 71 203,606
PV 385.8 71 203,676
ST 385.9 14 203,690
ST 385.9 14 203,704
ST 385.9 14 203,718
ST 385.9 14 203,732
PV 388.7 74 203,806
PV 388.7 74 203,880
PV 388.7 74 203,953
PV 388.7 74 204,027
PV 395.7 69 204,096
PV 395.7 69 204,165
PV 395.7 69 204,234
PV 395.7 69 204,304
PV 399.2 66 204,370
PV 399.2 66 204,436
PV 399.2 66 204,503
PV 399.2 66 204,569
ST 400.5 14 204,583
ST 400.5 14 204,596
ST 400.5 14 204,610
ST 400.5 14 204,623
PV 403.4 71 204,694
PV 403.4 71 204,765
PV 403.4 71 204,836
PV 403.4 71 204,907
SSH 405.7 33 204,940
ST 410.8 13 204,953
ST 410.8 13 204,966
ST 410.8 13 204,979
ST 410.8 13 204,993
PV 411.7 66 205,059
PV 411.7 66 205,125
PV 411.7 66 205,192
PV 411.7 66 205,258
PV 413.8 69 205,328
PV 413.8 69 205,397
PV 413.8 69 205,466
PV 413.8 69 205,535
ST 427.4 13 205,548
ST 427.4 13 205,560
Curve 4 - Electricity Curve (Private)
ST 427.4 13 205,573
ST 427.4 13 205,586
PV 430.5 66 205,652
PV 430.5 66 205,718
PV 430.5 66 205,785
PV 430.5 66 205,851
Curve 5 - Electricity Curve (Social)

Cost Generation Cum


Code ($/MWh) (GWh) Generation
SSH 43.0 45 45
SSH 43.0 42 87
SSH 43.0 35 122
SSH 43.0 35 157
SSH 43.0 169 326
SSH 43.0 185 511
SSH 43.0 84 595
SSH 43.0 224 819
SSH 45.0 80 900
SSH 45.2 107 1,007
SSH 45.2 77 1,083
SSH 45.6 186 1,269
SSH 46.2 57 1,326
SSH 47.2 196 1,522
LFG 47.7 5 1,528
LFG 47.7 5 1,533
LFG 47.7 5 1,538
LFG 47.7 5 1,543
SSH 49.1 29 1,572
SSH 49.1 22 1,594
SSH 49.1 17 1,611
SSH 49.1 12 1,623
SSH 49.1 34 1,656
SSH 49.1 31 1,688
SSH 49.1 5 1,693
SSH 49.1 25 1,717
SSH 49.1 25 1,742
SSH 49.1 15 1,757
SSH 49.1 7 1,764
SSH 49.1 22 1,786
SSH 49.1 20 1,807
SSH 49.1 34 1,840
SSH 49.1 15 1,855
SSH 49.1 14 1,869
SSH 49.1 14 1,883
SSH 49.1 14 1,897
SSH 49.1 6 1,902
SSH 49.1 4 1,906
SSH 49.1 5 1,911
SSH 49.1 12 1,923
SSH 49.1 12 1,935
SSH 49.1 11 1,946
SSH 49.1 11 1,956
SSH 49.1 10 1,967
SSH 49.1 5 1,972
SSH 49.1 12 1,984
SSH 49.1 4 1,988
SSH 49.1 10 1,997
SSH 49.1 8 2,005
SSH 49.1 8 2,013
SSH 49.1 8 2,020
SSH 49.1 8 2,028
SSH 49.1 7 2,034
SSH 49.1 6 2,041
SSH 49.1 34 2,075
SSH 49.1 4 2,078
SSH 49.1 2 2,081
SSH 50.1 7 2,087
SSH 50.1 59 2,146
Nuke 50.4 11,937 14,083
SSH 50.5 5 14,087
Curve 5 - Electricity Curve (Social)
SSH 50.9 4 14,091
SSH 50.9 7 14,098
SSH 51.3 42 14,140
SSH 51.4 6 14,146
SSH 51.4 17 14,163
SSH 51.5 66 14,229
SSH 51.6 58 14,287
SSH 51.7 18 14,304
LFG 51.7 5 14,309
LFG 51.7 5 14,314
LFG 51.7 5 14,319
LFG 51.7 5 14,323
LFG 51.7 5 14,329
LFG 51.7 5 14,334
LFG 51.7 5 14,339
LFG 51.7 5 14,344
SSH 51.7 17 14,361
SSH 51.8 17 14,378
SSH 51.8 17 14,394
SSH 52.0 4 14,398
SSH 52.1 5 14,403
SSH 52.2 29 14,432
SSH 52.2 11 14,443
SSH 52.2 12 14,455
SSH 52.2 5 14,459
SSH 52.2 6 14,465
SSH 52.2 16 14,482
SSH 52.3 19 14,501
SSH 52.3 6 14,507
SSH 52.3 9 14,516
SSH 52.3 7 14,523
SSH 52.4 3 14,525
SSH 52.4 17 14,542
SSH 52.5 16 14,558
SSH 52.5 16 14,574
SSH 52.6 15 14,590
SSH 52.8 18 14,608
SSH 52.9 14 14,621
SSH 52.9 26 14,647
SSH 52.9 16 14,663
SSH 53.1 18 14,681
SSH 53.2 16 14,696
SSH 53.2 11 14,708
SSH 53.2 15 14,723
SSH 53.3 16 14,739
SSH 53.3 7 14,745
SSH 53.3 227 14,972
SSH 53.4 20 14,992
SSH 53.4 15 15,007
SSH 53.5 18 15,025
SSH 53.6 143 15,168
SSH 53.6 135 15,303
SSH 53.8 20 15,323
SSH 53.8 20 15,343
SSH 53.8 20 15,364
SSH 53.8 15 15,378
SSH 53.8 15 15,393
SSH 53.9 20 15,414
SSH 53.9 15 15,428
SSH 53.9 83 15,511
SSH 53.9 15 15,526
SSH 53.9 4 15,530
SSH 54.0 21 15,551
SSH 54.1 100 15,651
Curve 5 - Electricity Curve (Social)
SSH 54.1 6 15,657
SSH 54.1 19 15,676
SSH 54.2 111 15,787
SSH 54.2 22 15,809
SSH 54.2 14 15,823
SSH 54.2 8 15,832
SSH 54.3 7 15,838
SSH 54.3 94 15,932
LFG 54.4 5 15,937
LFG 54.4 5 15,942
LFG 54.4 5 15,947
LFG 54.4 5 15,952
SSH 54.5 14 15,967
SSH 54.6 23 15,989
SSH 54.6 95 16,085
SSH 54.6 252 16,337
SSH 54.6 3 16,341
SSH 54.7 4 16,345
LFG 54.7 4 16,349
LFG 54.7 4 16,354
LFG 54.7 4 16,358
LFG 54.7 4 16,363
SSH 54.8 13 16,376
LSH 54.8 69,180 85,556
SSH 54.9 23 85,579
SSH 54.9 8 85,587
SSH 54.9 24 85,611
SSH 54.9 13 85,623
SSH 55.0 25 85,648
SSH 55.0 25 85,673
SSH 55.0 25 85,699
SSH 55.2 9 85,708
SSH 55.3 26 85,733
SSH 55.3 26 85,760
SSH 55.3 9 85,769
SSH 55.4 8 85,777
SSH 55.5 14 85,790
SSH 55.6 14 85,804
SSH 55.7 78 85,882
SSH 55.8 76 85,958
SSH 55.9 6 85,964
SSH 55.9 75 86,039
SSH 56.0 280 86,320
SSH 56.0 54 86,374
SSH 56.0 74 86,447
SSH 56.0 126 86,573
SSH 56.0 3 86,577
LFG 56.0 5 86,581
LFG 56.0 5 86,586
LFG 56.0 5 86,591
LFG 56.0 5 86,596
SSH 56.1 56 86,652
SSH 56.4 5 86,657
SSH 56.5 51 86,708
SSH 56.7 28 86,736
SSH 56.9 8 86,744
SSH 57.0 13 86,757
SSH 57.0 13 86,770
SSH 57.0 17 86,786
SSH 57.0 28 86,814
SSH 57.1 29 86,843
SSH 57.2 315 87,158
SSH 57.3 42 87,201
SSH 57.4 56 87,257
Curve 5 - Electricity Curve (Social)
SSH 57.5 42 87,298
SSH 57.7 3 87,301
SSH 57.7 29 87,330
SSH 57.8 18 87,348
SSH 57.8 5 87,352
SSH 57.9 29 87,382
SSH 58.0 15 87,397
SSH 58.0 28 87,425
SSH 58.0 126 87,552
SSH 58.0 12 87,563
SSH 58.0 13 87,576
LFG 58.3 5 87,581
LFG 58.3 5 87,586
LFG 58.3 5 87,591
LFG 58.3 5 87,596
SSH 58.4 9 87,606
SSH 58.6 12 87,617
SSH 58.8 7 87,624
LFG 58.9 5 87,629
LFG 58.9 5 87,634
LFG 58.9 5 87,638
LFG 58.9 5 87,643
SSH 58.9 11 87,654
SSH 58.9 8 87,662
SSH 59.1 52 87,714
SSH 59.1 3 87,716
SSH 59.1 10 87,726
SSH 59.2 11 87,737
LFG 59.3 4 87,742
LFG 59.3 4 87,746
LFG 59.3 4 87,751
LFG 59.3 4 87,755
SSH 59.5 11 87,767
SSH 59.6 11 87,777
SSH 59.6 5 87,782
SSH 59.8 10 87,792
SSH 59.9 6 87,799
SSH 60.0 32 87,830
LFG 60.0 4 87,834
LFG 60.0 4 87,838
LFG 60.0 4 87,842
LFG 60.0 4 87,847
SSH 60.3 11 87,857
SSH 60.3 23 87,881
SSH 60.4 13 87,893
SSH 60.4 21 87,915
SSH 60.4 24 87,939
SSH 60.5 8 87,947
SSH 60.6 10 87,957
SSH 60.7 52 88,009
SSH 60.7 18 88,027
SSH 60.7 7 88,034
SSH 60.8 34 88,068
SSH 60.8 22 88,090
SSH 60.8 10 88,100
SSH 60.9 41 88,140
SSH 61.0 16 88,156
Biog 61.1 46 88,202
Biog 61.1 46 88,248
Biog 61.1 46 88,293
Biog 61.1 46 88,339
SSH 61.4 39 88,378
Bag 61.4 84 88,463
SSH 61.5 33 88,495
Curve 5 - Electricity Curve (Social)
SSH 61.5 10 88,505
SSH 61.7 210 88,715
SSH 61.8 29 88,745
SSH 61.8 10 88,754
SSH 61.9 9 88,764
Bag 62.0 74 88,838
SSH 62.0 9 88,847
SSH 62.1 18 88,866
SSH 62.2 9 88,875
LFG 62.4 4 88,879
LFG 62.4 4 88,884
LFG 62.4 4 88,888
LFG 62.4 4 88,893
SSH 62.4 9 88,901
SSH 62.4 34 88,936
SSH 62.4 36 88,972
Bag 62.4 68 89,040
SSH 62.4 5 89,045
SSH 62.5 24 89,069
SSH 62.7 4 89,074
SSH 62.8 38 89,111
SSH 63.0 9 89,121
SSH 63.0 9 89,130
SSH 63.1 58 89,187
LFG 63.2 5 89,192
LFG 63.2 5 89,197
LFG 63.2 5 89,202
LFG 63.2 5 89,206
Bag 63.2 58 89,264
SSH 63.5 9 89,273
SSH 63.7 9 89,282
SSH 63.8 58 89,340
Biog 63.9 42 89,382
Biog 63.9 42 89,424
Biog 63.9 42 89,467
Biog 63.9 42 89,509
SSH 64.0 5 89,514
SSH 64.0 256 89,770
SSH 64.1 49 89,819
Bag 64.2 84 89,904
SSH 64.2 10 89,914
SSH 64.3 8 89,922
SSH 64.5 4 89,926
SSH 64.5 252 90,178
Biom 64.5 78 90,256
SSH 64.5 7 90,263
SSH 64.6 96 90,359
SSH 64.7 8 90,367
Bag 64.7 74 90,441
SSH 64.8 9 90,450
SSH 64.9 9 90,459
SSH 64.9 8 90,467
SSH 64.9 5 90,472
SSH 64.9 22 90,494
SSH 64.9 8 90,502
SSH 64.9 8 90,510
SSH 65.0 8 90,519
Biom 65.0 78 90,596
LFG 65.0 4 90,600
LFG 65.0 4 90,604
LFG 65.0 4 90,608
LFG 65.0 4 90,612
Bag 65.1 68 90,680
Bag 65.1 84 90,765
Curve 5 - Electricity Curve (Social)
SSH 65.2 35 90,800
SSH 65.2 158 90,957
SSH 65.2 127 91,085
SSH 65.3 55 91,140
Biom 65.3 78 91,217
SSH 65.5 7 91,224
SSH 65.5 8 91,232
SSH 65.5 4 91,236
SSH 65.5 8 91,244
WTE 65.5 10 91,253
WTE 65.5 10 91,263
WTE 65.5 10 91,272
WTE 65.5 10 91,282
SSH 65.6 8 91,290
SSH 65.6 8 91,298
SSH 65.7 5 91,303
SSH 65.7 27 91,330
Biom 65.9 78 91,407
SSH 65.9 105 91,512
Bag 65.9 58 91,570
Bag 66.0 84 91,655
SSH 66.0 8 91,662
Biog 66.0 40 91,702
Biog 66.0 40 91,742
Biog 66.0 40 91,782
Biog 66.0 40 91,822
Biom 66.1 78 91,899
Bag 66.1 74 91,974
SSH 66.3 68 92,041
Bag 66.5 74 92,116
Biom 66.6 78 92,193
LFG 66.9 4 92,198
LFG 66.9 4 92,202
LFG 66.9 4 92,207
LFG 66.9 4 92,211
Bag 66.9 68 92,279
Biom 67.0 78 92,357
Bag 67.0 68 92,424
SSH 67.2 8 92,432
SSH 67.2 8 92,440
SSH 67.2 8 92,448
SSH 67.2 8 92,455
SSH 67.2 8 92,463
SSH 67.2 8 92,471
SSH 67.2 4 92,475
Biom 67.2 78 92,552
Biom 67.5 78 92,630
SSH 67.6 8 92,637
Bag 67.6 84 92,722
SSH 67.6 8 92,729
Biom 67.7 78 92,807
SSH 67.8 68 92,875
Bag 67.8 58 92,933
Bag 67.9 84 93,017
SSH 67.9 7 93,024
Biom 68.0 78 93,101
SSH 68.1 7 93,108
SSH 68.1 7 93,115
SSH 68.2 7 93,122
LFG 68.4 4 93,126
LFG 68.4 4 93,131
LFG 68.4 4 93,135
LFG 68.4 4 93,139
Biom 68.5 78 93,216
Curve 5 - Electricity Curve (Social)
SSH 68.6 7 93,223
Biom 68.6 68 93,292
Bag 68.6 58 93,350
SSH 68.6 3 93,352
Bag 68.7 84 93,437
Biom 68.8 78 93,514
SSH 68.8 7 93,521
SSH 68.8 13 93,534
SSH 68.9 7 93,541
Bag 68.9 74 93,615
SSH 68.9 7 93,622
Bag 68.9 74 93,697
Biom 69.1 68 93,765
Bag 69.2 74 93,839
Biom 69.3 78 93,917
Biom 69.4 68 93,985
Biom 69.6 78 94,063
Bag 69.7 68 94,131
SSH 69.7 6 94,137
Bag 69.7 84 94,221
SSH 69.7 3 94,224
Bag 69.7 68 94,292
Biog 69.8 36 94,328
Biog 69.8 36 94,365
Biog 69.8 36 94,401
Biog 69.8 36 94,437
Biom 70.0 68 94,506
Bag 70.0 68 94,574
SSH 70.1 6 94,580
SSH 70.1 20 94,600
Biom 70.1 78 94,677
SSH 70.2 10 94,687
Bag 70.3 84 94,771
Biom 70.4 68 94,840
Bag 70.5 58 94,898
SSH 70.5 16 94,913
SSH 70.6 6 94,920
SSH 70.7 196 95,116
Bag 70.7 74 95,190
SSH 70.8 6 95,197
Biom 70.9 68 95,265
SSH 71.0 6 95,271
SSH 71.2 6 95,277
Biom 71.3 68 95,346
Bag 71.3 84 95,430
Bag 71.3 58 95,488
Bag 71.5 68 95,556
SSH 71.5 29 95,585
Biom 71.6 68 95,653
Bag 71.7 74 95,727
Biom 71.8 68 95,796
SSH 71.8 6 95,802
Biom 72.0 62 95,864
SSH 72.1 5 95,869
Biom 72.1 68 95,937
Bag 72.1 84 96,022
Bag 72.2 58 96,080
SSH 72.4 6 96,086
Bag 72.4 84 96,170
SSH 72.4 6 96,175
Biom 72.5 68 96,244
Biom 72.5 62 96,306
Bag 72.8 68 96,374
Biom 72.8 62 96,437
Curve 5 - Electricity Curve (Social)
SSH 72.9 6 96,442
Biom 73.0 68 96,511
SSH 73.1 3 96,513
Bag 73.1 74 96,588
SSH 73.1 6 96,593
SSH 73.1 39 96,632
Bag 73.1 58 96,690
SSH 73.2 3 96,693
SSH 73.2 64 96,757
SSH 73.2 5 96,763
SSH 73.2 5 96,768
SSH 73.3 3 96,771
Biom 73.4 62 96,833
LFG 73.4 4 96,837
LFG 73.4 4 96,841
LFG 73.4 4 96,845
LFG 73.4 4 96,850
Bag 73.4 74 96,924
Biom 73.4 68 96,992
Bag 73.5 74 97,067
SSH 73.7 14 97,081
SSH 73.7 5 97,086
SSH 73.7 5 97,091
Biom 74.0 68 97,160
Biom 74.0 62 97,222
Bag 74.0 84 97,306
SSH 74.1 14 97,320
WTE 74.2 8 97,329
WTE 74.2 8 97,337
WTE 74.2 8 97,345
WTE 74.2 8 97,354
Bag 74.3 68 97,422
Biom 74.3 68 97,490
SSH 74.3 5 97,495
Biom 74.5 62 97,558
SSH 74.6 5 97,563
Bag 74.6 68 97,631
Bag 74.6 68 97,699
Biom 74.8 68 97,767
Biom 74.8 62 97,830
SSH 74.9 5 97,835
Bag 74.9 84 97,919
Bag 74.9 58 97,977
SSH 75.0 5 97,982
SSH 75.2 40 98,021
SSH 75.2 42 98,063
SSH 75.2 4 98,067
Biom 75.3 62 98,129
Biom 75.4 62 98,192
Biog 75.4 46 98,237
Biog 75.4 46 98,283
Biog 75.4 46 98,329
Biog 75.4 46 98,375
SSH 75.4 3 98,378
SSH 75.4 4 98,382
SSH 75.4 5 98,387
SSH 75.4 5 98,391
SSH 75.6 3 98,395
SSH 75.8 5 98,400
SSH 75.8 5 98,404
Biom 75.8 62 98,467
Bag 75.8 84 98,551
Bag 75.9 74 98,625
Bag 75.9 58 98,683
Curve 5 - Electricity Curve (Social)
SSH 76.0 5 98,688
Biom 76.2 62 98,750
Bag 76.2 74 98,825
SSH 76.3 7 98,832
SSH 76.4 8 98,839
SSH 76.4 5 98,844
SSH 76.6 5 98,849
Biom 76.7 62 98,911
Bag 76.7 58 98,969
SSH 77.2 4 98,973
Biom 77.3 62 99,036
Bag 77.3 68 99,104
Bag 77.4 68 99,171
Bag 77.6 58 99,229
SSH 77.6 4 99,234
Bag 77.7 74 99,308
Biom 77.8 62 99,371
Biom 78.2 62 99,433
Sew 78.2 2 99,435
Sew 78.2 2 99,437
Sew 78.2 2 99,439
Sew 78.2 2 99,441
SSH 78.2 79 99,521
SSH 78.2 4 99,525
SSH 78.3 4 99,529
SSH 78.5 4 99,533
Biom 78.5 53 99,587
SSH 78.5 4 99,591
Bag 78.6 84 99,675
Biom 78.7 62 99,737
SSH 78.7 4 99,741
Biom 79.0 53 99,795
SSH 79.1 4 99,799
Bag 79.2 68 99,867
SSH 79.2 4 99,871
Biog 79.3 42 99,913
Biog 79.3 42 99,955
Biog 79.3 42 99,997
Biog 79.3 42 100,039
Biom 79.4 53 100,093
Bag 79.5 58 100,151
SSH 79.8 4 100,155
Biom 79.9 53 100,208
Bag 80.3 58 100,266
SSH 80.3 2 100,268
SSH 80.3 4 100,272
SSH 80.4 4 100,276
Bag 80.4 74 100,350
SSH 80.5 4 100,354
SSH 80.7 85 100,439
Biom 80.8 53 100,493
SSH 81.2 4 100,496
Biom 81.4 53 100,549
WTE 81.4 8 100,557
WTE 81.4 8 100,565
WTE 81.4 8 100,573
WTE 81.4 8 100,580
SSH 81.5 4 100,584
SSH 81.5 4 100,587
Biom 81.7 53 100,641
SSH 81.8 26 100,666
Bag 81.9 68 100,734
SSH 82.1 3 100,738
Bag 82.1 58 100,796
Curve 5 - Electricity Curve (Social)
Biom 82.2 53 100,849
Biog 82.4 40 100,889
Biog 82.4 40 100,929
Biog 82.4 40 100,969
Biog 82.4 40 101,009
Biom 82.4 53 101,062
SSH 82.4 4 101,066
SSH 82.5 3 101,069
SSH 82.8 3 101,073
SSH 82.8 238 101,311
Biom 82.9 53 101,364
SSH 83.0 3 101,367
Biom 83.3 53 101,421
Biom 83.8 53 101,474
SSH 83.8 3 101,477
SSH 84.2 3 101,480
SSH 84.2 98 101,578
SSH 84.2 3 101,581
SSH 84.3 2 101,583
SSH 84.6 32 101,615
Sew 84.7 2 101,617
Sew 84.7 2 101,619
Sew 84.7 2 101,621
Sew 84.7 2 101,623
Biom 84.7 53 101,676
Bag 84.8 58 101,734
Biog 84.9 46 101,780
Biog 84.9 46 101,826
Biog 84.9 46 101,872
Biog 84.9 46 101,917
Biom 85.3 53 101,971
SSH 85.5 3 101,973
Biom 85.6 53 102,027
SSH 85.7 3 102,030
SSH 85.9 3 102,033
SSH 86.0 15 102,047
Biom 86.1 53 102,101
SSH 86.7 3 102,104
SSH 86.8 4 102,107
Coal 86.9 28,539 130,647
SSH 87.2 3 130,649
SSH 87.2 97 130,746
SSH 87.4 3 130,749
SSH 87.4 2 130,751
Biog 87.7 36 130,787
Biog 87.7 36 130,824
Biog 87.7 36 130,860
Biog 87.7 36 130,896
SSH 87.7 5 130,902
SSH 87.9 3 130,904
SSH 88.1 3 130,907
SSH 88.6 4 130,911
SSH 88.7 3 130,914
SSH 88.8 3 130,916
Sew 88.9 2 130,919
Sew 88.9 2 130,921
Sew 88.9 2 130,923
Sew 88.9 2 130,925
SSH 88.9 3 130,928
SSH 89.0 3 130,930
SSH 89.2 12 130,942
SSH 89.4 2 130,944
SSH 89.6 2 130,947
Biog 89.6 42 130,989
Curve 5 - Electricity Curve (Social)
Biog 89.6 42 131,031
Biog 89.6 42 131,074
Biog 89.6 42 131,116
Sew 89.7 2 131,118
Sew 89.7 2 131,120
Sew 89.7 2 131,121
Sew 89.7 2 131,123
SSH 89.9 5 131,129
SSH 90.0 2 131,131
SSH 90.0 2 131,133
SSH 90.1 3 131,136
SSH 90.5 4 131,140
SSH 91.1 2 131,142
SSH 91.2 2 131,145
SSH 91.2 2 131,147
SSH 91.5 2 131,149
SSH 91.9 13 131,162
SSH 91.9 2 131,164
SSH 92.0 2 131,166
SSH 92.2 2 131,169
SSH 92.5 2 131,171
SSH 92.6 2 131,173
SSH 92.8 2 131,175
SSH 92.9 3 131,178
Biog 93.3 40 131,218
Biog 93.3 40 131,258
Biog 93.3 40 131,297
Biog 93.3 40 131,337
SSH 93.3 3 131,340
SSH 93.6 2 131,342
SSH 93.7 2 131,344
SSH 93.7 2 131,346
SSH 93.7 3 131,349
SSH 93.8 3 131,352
SSH 93.9 3 131,355
WD 94.5 6 131,361
WD 94.5 6 131,367
WD 94.5 6 131,374
WD 94.5 6 131,380
WD 94.5 6 131,386
WD 94.5 6 131,393
WD 94.5 6 131,399
WD 94.5 6 131,406
WD 94.5 6 131,412
WD 94.5 6 131,418
WD 94.5 6 131,425
WD 94.5 6 131,431
WD 94.5 6 131,437
WD 94.5 6 131,444
WD 94.5 6 131,450
WD 94.5 6 131,457
SSH 94.8 2 131,459
SSH 95.1 2 131,461
WTE 95.2 7 131,467
WTE 95.2 7 131,474
WTE 95.2 7 131,480
WTE 95.2 7 131,487
SSH 95.2 2 131,489
SSH 95.4 2 131,491
SSH 95.7 2 131,493
SSH 95.9 2 131,495
SSH 95.9 2 131,497
Sew 96.0 2 131,499
Sew 96.0 2 131,501
Curve 5 - Electricity Curve (Social)
Sew 96.0 2 131,503
Sew 96.0 2 131,505
SSH 96.1 2 131,507
Sew 96.3 2 131,509
Sew 96.3 2 131,511
Sew 96.3 2 131,513
Sew 96.3 2 131,515
SSH 96.5 2 131,517
SSH 96.7 273 131,790
WTE 96.9 10 131,799
WTE 96.9 10 131,809
WTE 96.9 10 131,818
WTE 96.9 10 131,828
SSH 97.4 2 131,830
SSH 97.6 2 131,832
SSH 97.6 2 131,834
SSH 97.8 2 131,836
SSH 97.8 3 131,839
SSH 98.1 2 131,841
SSH 98.2 3 131,844
SSH 98.3 2 131,845
SSH 98.3 2 131,847
Sew 98.3 2 131,849
Sew 98.3 2 131,851
Sew 98.3 2 131,852
Sew 98.3 2 131,854
SSH 98.8 6 131,859
Biog 99.1 46 131,905
Biog 99.1 46 131,951
Biog 99.1 46 131,997
Biog 99.1 46 132,042
SSH 99.1 2 132,044
SSH 99.2 2 132,046
SSH 99.3 3 132,049
SSH 99.4 2 132,051
SSH 99.4 2 132,053
SSH 99.6 2 132,055
Biog 99.6 36 132,091
Biog 99.6 36 132,127
Biog 99.6 36 132,164
Biog 99.6 36 132,200
SSH 99.7 2 132,202
SSH 100.5 2 132,204
SSH 100.5 49 132,252
WD 100.6 6 132,259
WD 100.6 6 132,265
WD 100.6 6 132,271
WD 100.6 6 132,278
WD 100.6 6 132,284
WD 100.6 6 132,290
WD 100.6 6 132,297
WD 100.6 6 132,303
WD 100.6 6 132,310
WD 100.6 6 132,316
WD 100.6 6 132,322
WD 100.6 6 132,329
WD 100.6 6 132,335
WD 100.6 6 132,341
WD 100.6 6 132,348
WD 100.6 6 132,354
SSH 101.0 105 132,459
SSH 101.1 25 132,484
SSH 101.8 2 132,485
SSH 101.9 2 132,487
Curve 5 - Electricity Curve (Social)
Sew 101.9 2 132,489
Sew 101.9 2 132,491
Sew 101.9 2 132,493
Sew 101.9 2 132,495
SSH 102.1 3 132,497
SSH 102.2 2 132,499
SSH 102.3 2 132,501
WD 102.3 163 132,663
WD 102.3 163 132,826
WD 102.3 163 132,988
WD 102.3 163 133,151
WD 102.3 163 133,314
WD 102.3 163 133,476
WD 102.3 163 133,639
WD 102.3 163 133,802
WD 102.3 163 133,964
WD 102.3 163 134,127
WD 102.3 163 134,290
WD 102.3 163 134,452
WD 102.3 163 134,615
WD 102.3 163 134,777
WD 102.3 163 134,940
WD 102.3 163 135,103
SSH 102.4 2 135,104
SSH 102.6 6 135,110
Gas 102.6 25,047 160,157
SSH 103.3 2 160,159
SSH 103.8 2 160,160
Sew 104.0 2 160,162
Sew 104.0 2 160,164
Sew 104.0 2 160,166
Sew 104.0 2 160,168
SSH 104.1 3 160,171
SSH 104.4 3 160,174
SSH 104.5 1 160,175
SSH 104.6 2 160,177
SSH 104.6 1 160,179
WD 104.7 6 160,185
WD 104.7 6 160,192
WD 104.7 6 160,198
WD 104.7 6 160,204
WD 104.7 6 160,211
WD 104.7 6 160,217
WD 104.7 6 160,223
WD 104.7 6 160,230
WD 104.7 6 160,236
WD 104.7 6 160,242
WD 104.7 6 160,249
WD 104.7 6 160,255
WD 104.7 6 160,262
WD 104.7 6 160,268
WD 104.7 6 160,274
WD 104.7 6 160,281
SSH 104.9 1 160,282
SSH 105.0 43 160,325
Biog 105.0 42 160,368
Biog 105.0 42 160,410
Biog 105.0 42 160,452
Biog 105.0 42 160,494
SSH 105.4 1 160,496
SSH 105.6 1 160,497
SSH 105.7 1 160,499
SSH 105.7 3 160,502
SSH 106.6 1 160,503
Curve 5 - Electricity Curve (Social)
Sew 106.7 2 160,505
Sew 106.7 2 160,507
Sew 106.7 2 160,510
Sew 106.7 2 160,512
SSH 106.9 1 160,513
SSH 107.0 1 160,514
SSH 107.9 1 160,516
WD 108.1 218 160,734
WD 108.1 218 160,952
WD 108.1 218 161,171
WD 108.1 218 161,389
WD 108.1 218 161,607
WD 108.1 218 161,826
WD 108.1 218 162,044
WD 108.1 218 162,262
WD 108.1 218 162,480
WD 108.1 218 162,699
WD 108.1 218 162,917
WD 108.1 218 163,135
WD 108.1 218 163,354
WD 108.1 218 163,572
WD 108.1 218 163,790
WD 108.1 218 164,009
SSH 108.6 3 164,012
SSH 108.6 1 164,013
WD 109.0 163 164,176
WD 109.0 163 164,338
WD 109.0 163 164,501
WD 109.0 163 164,664
WD 109.0 163 164,826
WD 109.0 163 164,989
WD 109.0 163 165,151
WD 109.0 163 165,314
WD 109.0 163 165,477
WD 109.0 163 165,639
WD 109.0 163 165,802
WD 109.0 163 165,965
WD 109.0 163 166,127
WD 109.0 163 166,290
WD 109.0 163 166,453
WD 109.0 163 166,615
SSH 109.2 6 166,621
SSH 109.2 1 166,622
SSH 109.2 1 166,623
SSH 109.4 1 166,624
Biog 109.6 40 166,664
Biog 109.6 40 166,704
Biog 109.6 40 166,744
Biog 109.6 40 166,784
SSH 109.7 1 166,785
WTE 109.8 8 166,794
WTE 109.8 8 166,802
WTE 109.8 8 166,810
WTE 109.8 8 166,819
SSH 109.9 1 166,820
SSH 109.9 1 166,821
SSH 110.0 3 166,824
Sew 110.1 2 166,826
Sew 110.1 2 166,828
Sew 110.1 2 166,830
Sew 110.1 2 166,832
SSH 110.5 1 166,833
SSH 110.7 1 166,834
SSH 110.9 1 166,835
Curve 5 - Electricity Curve (Social)
WD 110.9 6 166,841
WD 110.9 6 166,848
WD 110.9 6 166,854
WD 110.9 6 166,860
WD 110.9 6 166,867
WD 110.9 6 166,873
WD 110.9 6 166,880
WD 110.9 6 166,886
WD 110.9 6 166,892
WD 110.9 6 166,899
WD 110.9 6 166,905
WD 110.9 6 166,911
WD 110.9 6 166,918
WD 110.9 6 166,924
WD 110.9 6 166,930
WD 110.9 6 166,937
SSH 111.4 2 166,939
Sew 111.8 2 166,941
Sew 111.8 2 166,942
Sew 111.8 2 166,944
Sew 111.8 2 166,946
SSH 112.3 1 166,947
SSH 112.7 1 166,948
SSH 112.8 2 166,950
SSH 113.1 1 166,951
WD 113.4 163 167,114
WD 113.4 163 167,276
WD 113.4 163 167,439
WD 113.4 163 167,602
WD 113.4 163 167,764
WD 113.4 163 167,927
WD 113.4 163 168,090
WD 113.4 163 168,252
WD 113.4 163 168,415
WD 113.4 163 168,578
WD 113.4 163 168,740
WD 113.4 163 168,903
WD 113.4 163 169,065
WD 113.4 163 169,228
WD 113.4 163 169,391
WD 113.4 163 169,553
SSH 115.2 6 169,559
WD 115.2 218 169,778
WD 115.2 218 169,996
WD 115.2 218 170,214
WD 115.2 218 170,433
WD 115.2 218 170,651
WD 115.2 218 170,869
WD 115.2 218 171,087
WD 115.2 218 171,306
WD 115.2 218 171,524
WD 115.2 218 171,742
WD 115.2 218 171,961
WD 115.2 218 172,179
WD 115.2 218 172,397
WD 115.2 218 172,616
WD 115.2 218 172,834
WD 115.2 218 173,052
Sew 115.6 2 173,054
Sew 115.6 2 173,056
Sew 115.6 2 173,058
Sew 115.6 2 173,060
SSH 115.6 1 173,061
SSH 115.7 4 173,065
Curve 5 - Electricity Curve (Social)
SSH 116.2 2 173,067
SSH 116.4 1 173,068
SSH 117.1 1 173,069
SSH 117.3 3 173,072
Biog 117.5 36 173,109
Biog 117.5 36 173,145
Biog 117.5 36 173,182
Biog 117.5 36 173,218
WTE 117.9 10 173,227
WTE 117.9 10 173,237
WTE 117.9 10 173,247
WTE 117.9 10 173,256
SSH 118.7 1 173,257
SSH 118.9 1 173,258
SSH 118.9 1 173,259
SSH 119.5 6 173,265
SSH 119.6 5 173,270
WD 119.9 218 173,488
WD 119.9 218 173,707
WD 119.9 218 173,925
WD 119.9 218 174,143
WD 119.9 218 174,362
WD 119.9 218 174,580
WD 119.9 218 174,798
WD 119.9 218 175,016
WD 119.9 218 175,235
WD 119.9 218 175,453
WD 119.9 218 175,671
WD 119.9 218 175,890
WD 119.9 218 176,108
WD 119.9 218 176,326
WD 119.9 218 176,545
WD 119.9 218 176,763
WD 120.1 163 176,926
WD 120.1 163 177,088
WD 120.1 163 177,251
WD 120.1 163 177,413
WD 120.1 163 177,576
WD 120.1 163 177,739
WD 120.1 163 177,901
WD 120.1 163 178,064
WD 120.1 163 178,227
WD 120.1 163 178,389
WD 120.1 163 178,552
WD 120.1 163 178,714
WD 120.1 163 178,877
WD 120.1 163 179,040
WD 120.1 163 179,202
WD 120.1 163 179,365
WTE 120.4 8 179,373
WTE 120.4 8 179,380
WTE 120.4 8 179,388
WTE 120.4 8 179,396
SSH 120.6 1 179,397
SSH 120.6 1 179,397
SSH 120.6 1 179,398
Sew 120.8 2 179,400
Sew 120.8 2 179,402
Sew 120.8 2 179,403
Sew 120.8 2 179,405
SSH 120.8 4 179,409
SSH 120.9 2 179,411
SSH 121.6 1 179,412
SSH 121.8 126 179,538
Curve 5 - Electricity Curve (Social)
Sew 122.4 2 179,540
Sew 122.4 2 179,542
Sew 122.4 2 179,543
Sew 122.4 2 179,545
SSH 122.9 2 179,547
SSH 124.8 1 179,548
SSH 125.4 3 179,551
SSH 126.6 1 179,552
WD 127.0 218 179,770
WD 127.0 218 179,988
WD 127.0 218 180,206
WD 127.0 218 180,425
WD 127.0 218 180,643
WD 127.0 218 180,861
WD 127.0 218 181,080
WD 127.0 218 181,298
WD 127.0 218 181,516
WD 127.0 218 181,735
WD 127.0 218 181,953
WD 127.0 218 182,171
WD 127.0 218 182,389
WD 127.0 218 182,608
WD 127.0 218 182,826
WD 127.0 218 183,044
SSH 127.2 1 183,045
SSH 127.8 1 183,046
SSH 128.1 1 183,047
SSH 128.3 5 183,052
SSH 130.7 1 183,053
SSH 131.1 1 183,054
SSH 131.1 0 183,054
SSH 131.5 0 183,055
SSH 131.8 1 183,056
SSH 133.2 0 183,056
WTE 133.5 8 183,065
WTE 133.5 8 183,073
WTE 133.5 8 183,082
WTE 133.5 8 183,090
SSH 134.0 1 183,091
Sew 134.2 2 183,093
Sew 134.2 2 183,095
Sew 134.2 2 183,096
Sew 134.2 2 183,098
SSH 134.5 0 183,099
SSH 135.6 0 183,099
SSH 135.8 1 183,100
SSH 136.6 1 183,102
SSH 136.8 2 183,103
SSH 138.8 0 183,104
WTE 140.8 7 183,110
WTE 140.8 7 183,117
WTE 140.8 7 183,123
WTE 140.8 7 183,130
SSH 140.9 0 183,130
SSH 141.3 1 183,132
SSH 141.4 0 183,132
SSH 143.1 0 183,133
SSH 145.9 1 183,134
SSH 146.0 0 183,134
WTE 146.4 8 183,142
WTE 146.4 8 183,150
WTE 146.4 8 183,157
WTE 146.4 8 183,165
SSH 149.0 0 183,165
Curve 5 - Electricity Curve (Social)
SSH 149.1 1 183,166
WTE 149.2 10 183,176
WTE 149.2 10 183,185
WTE 149.2 10 183,195
WTE 149.2 10 183,204
SSH 149.5 0 183,205
SSH 152.7 0 183,205
SSH 153.4 0 183,205
SSH 153.9 1 183,206
SSH 154.3 0 183,206
SSH 155.5 0 183,207
SSH 155.9 1 183,208
SSH 156.3 12 183,220
SSH 157.0 1 183,221
SSH 157.7 0 183,221
SSH 160.2 3 183,224
SSH 161.8 0 183,224
SSH 163.5 0 183,225
SSH 164.6 1 183,226
SSH 167.2 1 183,226
WTE 169.0 8 183,235
WTE 169.0 8 183,243
WTE 169.0 8 183,252
WTE 169.0 8 183,260
WTE 171.2 7 183,267
WTE 171.2 7 183,273
WTE 171.2 7 183,280
WTE 171.2 7 183,287
SSH 172.9 0 183,287
SSH 175.0 0 183,287
SSH 176.0 0 183,287
SSH 177.7 2 183,289
Fuel 178.2 17,110 200,399
SSH 178.6 1 200,399
SSH 179.6 1 200,401
SSH 181.3 1 200,401
SSH 184.0 0 200,402
WTE 185.4 8 200,409
WTE 185.4 8 200,417
WTE 185.4 8 200,425
WTE 185.4 8 200,432
SSH 190.8 0 200,433
SSH 198.0 2 200,435
SSH 199.9 1 200,436
SSH 200.2 1 200,436
SSH 203.9 1 200,437
SSH 203.9 1 200,438
SSH 204.8 0 200,438
SSH 205.1 1 200,440
SSH 210.8 1 200,440
SSH 211.2 0 200,440
SSH 211.5 1 200,442
SSH 213.3 1 200,443
SSH 215.7 1 200,444
SSH 215.8 1 200,444
WTE 216.8 7 200,451
WTE 216.8 7 200,458
WTE 216.8 7 200,464
WTE 216.8 7 200,471
SSH 219.8 0 200,471
SSH 222.3 1 200,472
SSH 224.1 1 200,473
SSH 226.4 0 200,473
SSH 232.4 1 200,474
Curve 5 - Electricity Curve (Social)
SSH 238.1 0 200,474
SSH 238.1 0 200,474
SSH 245.0 0 200,474
SSH 252.9 5 200,479
ST 272.3 14 200,493
ST 272.3 14 200,507
ST 272.3 14 200,521
ST 272.3 14 200,535
ST 282.6 14 200,548
ST 282.6 14 200,562
ST 282.6 14 200,575
ST 282.6 14 200,589
ST 289.9 13 200,602
ST 289.9 13 200,615
ST 289.9 13 200,628
ST 289.9 13 200,641
ST 301.6 13 200,654
ST 301.6 13 200,667
ST 301.6 13 200,679
ST 301.6 13 200,692
ST 314.9 14 200,706
ST 314.9 14 200,720
ST 314.9 14 200,734
ST 314.9 14 200,748
SSH 317.7 4 200,752
ST 326.8 14 200,766
ST 326.8 14 200,779
ST 326.8 14 200,793
ST 326.8 14 200,806
ST 335.2 13 200,820
ST 335.2 13 200,833
ST 335.2 13 200,846
ST 335.2 13 200,859
ST 343.3 14 200,873
ST 343.3 14 200,887
ST 343.3 14 200,901
ST 343.3 14 200,915
PV 343.5 74 200,989
PV 343.5 74 201,062
PV 343.5 74 201,136
PV 343.5 74 201,210
ST 348.8 13 201,222
ST 348.8 13 201,235
ST 348.8 13 201,247
ST 348.8 13 201,260
ST 356.3 14 201,274
ST 356.3 14 201,287
ST 356.3 14 201,301
ST 356.3 14 201,314
PV 356.4 71 201,385
PV 356.4 71 201,456
PV 356.4 71 201,527
PV 356.4 71 201,598
PV 360.4 74 201,671
PV 360.4 74 201,745
PV 360.4 74 201,819
PV 360.4 74 201,892
ST 365.5 13 201,905
ST 365.5 13 201,919
ST 365.5 13 201,932
ST 365.5 13 201,945
PV 365.7 69 202,014
PV 365.7 69 202,083
PV 365.7 69 202,152
Curve 5 - Electricity Curve (Social)
PV 365.7 69 202,222
PV 371.7 74 202,295
PV 371.7 74 202,369
PV 371.7 74 202,442
PV 371.7 74 202,516
PV 374.0 71 202,587
PV 374.0 71 202,658
PV 374.0 71 202,729
PV 374.0 71 202,800
ST 380.2 13 202,812
ST 380.2 13 202,825
ST 380.2 13 202,838
ST 380.2 13 202,850
PV 380.4 66 202,917
PV 380.4 66 202,983
PV 380.4 66 203,050
PV 380.4 66 203,116
PV 383.7 69 203,185
PV 383.7 69 203,254
PV 383.7 69 203,324
PV 383.7 69 203,393
PV 385.8 71 203,464
PV 385.8 71 203,535
PV 385.8 71 203,606
PV 385.8 71 203,676
ST 385.9 14 203,690
ST 385.9 14 203,704
ST 385.9 14 203,718
ST 385.9 14 203,732
PV 388.7 74 203,806
PV 388.7 74 203,880
PV 388.7 74 203,953
PV 388.7 74 204,027
PV 395.7 69 204,096
PV 395.7 69 204,165
PV 395.7 69 204,234
PV 395.7 69 204,304
PV 399.2 66 204,370
PV 399.2 66 204,436
PV 399.2 66 204,503
PV 399.2 66 204,569
ST 400.5 14 204,583
ST 400.5 14 204,596
ST 400.5 14 204,610
ST 400.5 14 204,623
PV 403.4 71 204,694
PV 403.4 71 204,765
PV 403.4 71 204,836
PV 403.4 71 204,907
SSH 405.7 33 204,940
ST 410.8 13 204,953
ST 410.8 13 204,966
ST 410.8 13 204,979
ST 410.8 13 204,993
PV 411.7 66 205,059
PV 411.7 66 205,125
PV 411.7 66 205,192
PV 411.7 66 205,258
PV 413.8 69 205,328
PV 413.8 69 205,397
PV 413.8 69 205,466
PV 413.8 69 205,535
ST 427.4 13 205,548
ST 427.4 13 205,560
Curve 5 - Electricity Curve (Social)
ST 427.4 13 205,573
ST 427.4 13 205,586
PV 430.5 66 205,652
PV 430.5 66 205,718
PV 430.5 66 205,785
PV 430.5 66 205,851
Curve 6 - RES-E Curve (Private)

Cost Generation Cum


Code ($/MWh) (GWh) Generation
SSH 43.0 45 45
SSH 43.0 42 87
SSH 43.0 35 122
SSH 43.0 35 157
SSH 43.0 169 326
SSH 43.0 185 511
SSH 43.0 84 595
SSH 43.0 224 819
SSH 45.0 80 900
SSH 45.2 107 1,007
SSH 45.2 77 1,083
SSH 45.6 186 1,269
SSH 46.2 57 1,326
SSH 47.2 196 1,522
LFG 47.7 5 1,528
LFG 47.7 5 1,533
LFG 47.7 5 1,538
LFG 47.7 5 1,543
SSH 49.1 29 1,572
SSH 49.1 22 1,594
SSH 49.1 17 1,611
SSH 49.1 12 1,623
SSH 49.1 34 1,656
SSH 49.1 31 1,688
SSH 49.1 5 1,693
SSH 49.1 25 1,717
SSH 49.1 25 1,742
SSH 49.1 15 1,757
SSH 49.1 7 1,764
SSH 49.1 22 1,786
SSH 49.1 20 1,807
SSH 49.1 34 1,840
SSH 49.1 15 1,855
SSH 49.1 14 1,869
SSH 49.1 14 1,883
SSH 49.1 14 1,897
SSH 49.1 6 1,902
SSH 49.1 4 1,906
SSH 49.1 5 1,911
SSH 49.1 12 1,923
SSH 49.1 12 1,935
SSH 49.1 11 1,946
SSH 49.1 11 1,956
SSH 49.1 10 1,967
SSH 49.1 5 1,972
SSH 49.1 12 1,984
SSH 49.1 4 1,988
SSH 49.1 10 1,997
SSH 49.1 8 2,005
SSH 49.1 8 2,013
SSH 49.1 8 2,020
SSH 49.1 8 2,028
SSH 49.1 7 2,034
SSH 49.1 6 2,041
SSH 49.1 34 2,075
SSH 49.1 4 2,078
SSH 49.1 2 2,081
SSH 50.1 7 2,087
SSH 50.1 59 2,146
SSH 50.5 5 2,151
Bag 50.9 84 2,235
Curve 6 - RES-E Curve (Private)
SSH 50.9 4 2,239
SSH 50.9 7 2,246
SSH 51.3 42 2,287
SSH 51.4 6 2,293
SSH 51.4 17 2,311
SSH 51.5 66 2,376
SSH 51.6 58 2,434
SSH 51.7 18 2,452
LFG 51.7 5 2,457
LFG 51.7 5 2,461
LFG 51.7 5 2,466
LFG 51.7 5 2,471
LFG 51.7 5 2,476
LFG 51.7 5 2,481
LFG 51.7 5 2,486
LFG 51.7 5 2,491
SSH 51.7 17 2,508
SSH 51.8 17 2,525
SSH 51.8 17 2,542
SSH 52.0 4 2,546
SSH 52.1 5 2,551
SSH 52.2 29 2,580
SSH 52.2 11 2,590
SSH 52.2 12 2,602
SSH 52.2 5 2,607
SSH 52.2 6 2,613
SSH 52.2 16 2,629
SSH 52.3 19 2,649
SSH 52.3 6 2,654
SSH 52.3 9 2,663
SSH 52.3 7 2,670
SSH 52.4 3 2,673
SSH 52.4 17 2,689
SSH 52.5 16 2,706
SSH 52.5 16 2,722
SSH 52.6 15 2,737
SSH 52.8 18 2,755
SSH 52.9 14 2,769
SSH 52.9 26 2,795
SSH 52.9 16 2,810
SSH 53.1 18 2,828
SSH 53.2 16 2,844
SSH 53.2 11 2,855
SSH 53.2 15 2,871
SSH 53.3 16 2,886
SSH 53.3 7 2,893
SSH 53.3 227 3,119
SSH 53.4 20 3,139
SSH 53.4 15 3,155
SSH 53.5 18 3,172
SSH 53.6 143 3,315
SSH 53.6 135 3,450
Bag 53.6 84 3,534
SSH 53.8 20 3,555
SSH 53.8 20 3,575
SSH 53.8 20 3,595
SSH 53.8 15 3,610
SSH 53.8 15 3,625
SSH 53.9 20 3,645
SSH 53.9 15 3,660
SSH 53.9 83 3,743
SSH 53.9 15 3,758
SSH 53.9 4 3,762
SSH 54.0 21 3,782
Curve 6 - RES-E Curve (Private)
Bag 54.0 74 3,857
SSH 54.1 100 3,957
SSH 54.1 6 3,963
SSH 54.1 19 3,982
SSH 54.2 111 4,093
SSH 54.2 22 4,115
SSH 54.2 14 4,130
SSH 54.2 8 4,138
SSH 54.3 7 4,144
SSH 54.3 94 4,238
LFG 54.4 5 4,243
LFG 54.4 5 4,248
LFG 54.4 5 4,253
LFG 54.4 5 4,259
SSH 54.5 14 4,273
SSH 54.6 23 4,296
SSH 54.6 95 4,391
Bag 54.6 84 4,475
SSH 54.6 252 4,728
SSH 54.6 3 4,731
SSH 54.7 4 4,735
LFG 54.7 4 4,740
LFG 54.7 4 4,744
LFG 54.7 4 4,749
LFG 54.7 4 4,753
SSH 54.8 13 4,766
SSH 54.9 23 4,790
SSH 54.9 8 4,797
SSH 54.9 24 4,821
SSH 54.9 13 4,834
SSH 55.0 25 4,859
SSH 55.0 25 4,884
SSH 55.0 25 4,909
SSH 55.2 9 4,918
SSH 55.3 26 4,944
SSH 55.3 26 4,970
SSH 55.3 9 4,979
SSH 55.4 8 4,987
Bag 55.5 84 5,071
SSH 55.5 14 5,085
SSH 55.6 14 5,099
SSH 55.7 78 5,177
SSH 55.8 76 5,253
SSH 55.9 6 5,259
SSH 55.9 75 5,334
SSH 56.0 280 5,614
SSH 56.0 54 5,668
SSH 56.0 74 5,742
SSH 56.0 126 5,868
SSH 56.0 3 5,871
LFG 56.0 5 5,876
LFG 56.0 5 5,881
LFG 56.0 5 5,885
LFG 56.0 5 5,890
SSH 56.1 56 5,947
SSH 56.4 5 5,952
SSH 56.5 51 6,003
Bag 56.6 68 6,071
SSH 56.7 28 6,098
Bag 56.7 74 6,173
SSH 56.9 8 6,181
SSH 57.0 13 6,194
SSH 57.0 13 6,206
SSH 57.0 17 6,223
Curve 6 - RES-E Curve (Private)
SSH 57.0 28 6,251
SSH 57.1 29 6,280
Bag 57.1 84 6,364
SSH 57.2 315 6,680
SSH 57.3 42 6,722
Bag 57.3 84 6,806
SSH 57.4 56 6,862
SSH 57.5 42 6,904
SSH 57.7 3 6,906
SSH 57.7 29 6,935
SSH 57.8 18 6,953
SSH 57.8 5 6,958
SSH 57.9 29 6,987
SSH 58.0 15 7,002
SSH 58.0 28 7,031
SSH 58.0 126 7,157
SSH 58.0 12 7,169
SSH 58.0 13 7,181
Bag 58.2 84 7,265
Bag 58.2 74 7,340
LFG 58.3 5 7,345
LFG 58.3 5 7,350
LFG 58.3 5 7,355
LFG 58.3 5 7,360
SSH 58.4 9 7,370
Bag 58.6 74 7,444
SSH 58.6 12 7,456
SSH 58.8 7 7,462
LFG 58.9 5 7,467
LFG 58.9 5 7,472
LFG 58.9 5 7,477
LFG 58.9 5 7,481
SSH 58.9 11 7,492
SSH 58.9 8 7,500
SSH 59.1 52 7,552
SSH 59.1 3 7,555
SSH 59.1 10 7,565
Bag 59.2 84 7,649
SSH 59.2 11 7,660
LFG 59.3 4 7,664
LFG 59.3 4 7,669
LFG 59.3 4 7,673
LFG 59.3 4 7,678
Bag 59.3 68 7,746
SSH 59.5 11 7,757
SSH 59.6 11 7,768
SSH 59.6 5 7,773
Bag 59.8 84 7,857
SSH 59.8 10 7,867
SSH 59.9 6 7,873
SSH 60.0 32 7,905
LFG 60.0 4 7,909
LFG 60.0 4 7,913
LFG 60.0 4 7,917
LFG 60.0 4 7,921
SSH 60.3 11 7,932
SSH 60.3 23 7,955
SSH 60.4 13 7,968
SSH 60.4 21 7,990
SSH 60.4 24 8,014
SSH 60.5 8 8,022
SSH 60.6 10 8,032
SSH 60.7 52 8,084
SSH 60.7 18 8,102
Curve 6 - RES-E Curve (Private)
SSH 60.7 7 8,109
Bag 60.8 84 8,193
SSH 60.8 34 8,227
SSH 60.8 22 8,249
SSH 60.8 10 8,259
SSH 60.9 41 8,299
Bag 60.9 74 8,374
SSH 61.0 16 8,389
Bag 61.0 74 8,464
Biog 61.1 46 8,510
Biog 61.1 46 8,555
Biog 61.1 46 8,601
Biog 61.1 46 8,647
Bag 61.1 68 8,715
Bag 61.2 68 8,782
Bag 61.3 74 8,857
SSH 61.4 39 8,896
SSH 61.5 33 8,929
SSH 61.5 10 8,939
Bag 61.5 58 8,997
Bag 61.6 84 9,081
SSH 61.7 210 9,291
SSH 61.8 29 9,320
SSH 61.8 10 9,330
Bag 61.9 84 9,414
SSH 61.9 9 9,424
SSH 62.0 9 9,433
SSH 62.1 18 9,451
SSH 62.2 9 9,460
LFG 62.4 4 9,465
LFG 62.4 4 9,469
LFG 62.4 4 9,474
LFG 62.4 4 9,478
SSH 62.4 9 9,487
SSH 62.4 34 9,521
SSH 62.4 36 9,558
SSH 62.4 5 9,562
SSH 62.5 24 9,587
SSH 62.7 4 9,591
Bag 62.7 74 9,666
SSH 62.8 38 9,704
SSH 63.0 9 9,713
SSH 63.0 9 9,722
SSH 63.1 58 9,779
LFG 63.2 5 9,784
LFG 63.2 5 9,789
LFG 63.2 5 9,794
LFG 63.2 5 9,798
SSH 63.5 9 9,807
Bag 63.5 84 9,892
SSH 63.7 9 9,901
Bag 63.7 74 9,975
SSH 63.8 58 10,033
Bag 63.9 68 10,100
Bag 63.9 68 10,168
Biog 63.9 42 10,211
Biog 63.9 42 10,253
Biog 63.9 42 10,295
Biog 63.9 42 10,337
SSH 64.0 5 10,342
SSH 64.0 256 10,599
SSH 64.1 49 10,648
SSH 64.2 10 10,658
Bag 64.2 68 10,726
Curve 6 - RES-E Curve (Private)
Bag 64.3 58 10,784
SSH 64.3 8 10,792
Bag 64.3 84 10,876
SSH 64.5 4 10,880
SSH 64.5 252 11,133
Biom 64.5 78 11,210
SSH 64.5 7 11,217
SSH 64.6 96 11,313
SSH 64.7 8 11,321
SSH 64.8 9 11,330
SSH 64.9 9 11,338
SSH 64.9 8 11,347
SSH 64.9 5 11,352
SSH 64.9 22 11,374
SSH 64.9 8 11,382
SSH 64.9 8 11,390
SSH 65.0 8 11,399
Biom 65.0 78 11,476
LFG 65.0 4 11,480
LFG 65.0 4 11,484
LFG 65.0 4 11,488
LFG 65.0 4 11,492
Bag 65.2 74 11,567
SSH 65.2 35 11,602
SSH 65.2 158 11,760
SSH 65.2 127 11,887
SSH 65.3 55 11,942
Bag 65.3 84 12,026
Biom 65.3 78 12,104
SSH 65.5 7 12,110
SSH 65.5 8 12,118
Bag 65.5 74 12,192
SSH 65.5 4 12,197
SSH 65.5 8 12,204
WTE 65.5 10 12,214
WTE 65.5 10 12,224
WTE 65.5 10 12,233
WTE 65.5 10 12,243
Bag 65.5 74 12,317
SSH 65.6 8 12,325
SSH 65.6 8 12,333
SSH 65.7 5 12,338
SSH 65.7 27 12,365
Bag 65.7 68 12,433
Biom 65.9 78 12,510
SSH 65.9 105 12,616
SSH 66.0 8 12,623
Biog 66.0 40 12,663
Biog 66.0 40 12,703
Biog 66.0 40 12,743
Biog 66.0 40 12,783
Bag 66.1 58 12,841
Biom 66.1 78 12,918
SSH 66.3 68 12,986
Biom 66.6 78 13,063
Bag 66.9 58 13,121
LFG 66.9 4 13,126
LFG 66.9 4 13,130
LFG 66.9 4 13,135
LFG 66.9 4 13,139
Biom 67.0 78 13,217
Bag 67.0 68 13,285
SSH 67.2 8 13,292
SSH 67.2 8 13,300
Curve 6 - RES-E Curve (Private)
SSH 67.2 8 13,308
SSH 67.2 8 13,315
SSH 67.2 8 13,323
SSH 67.2 8 13,331
SSH 67.2 4 13,335
Biom 67.2 78 13,412
Biom 67.5 78 13,490
SSH 67.6 8 13,497
SSH 67.6 8 13,505
Biom 67.7 78 13,583
SSH 67.8 68 13,651
SSH 67.9 7 13,658
Bag 67.9 74 13,732
Biom 68.0 78 13,809
Bag 68.0 84 13,894
SSH 68.1 7 13,901
SSH 68.1 7 13,908
SSH 68.2 7 13,915
Bag 68.3 74 13,989
LFG 68.4 4 13,993
LFG 68.4 4 13,997
LFG 68.4 4 14,001
LFG 68.4 4 14,005
Bag 68.4 68 14,073
Biom 68.5 78 14,151
SSH 68.6 7 14,158
Biom 68.6 68 14,226
SSH 68.6 3 14,229
Biom 68.8 78 14,307
SSH 68.8 7 14,313
Bag 68.8 68 14,381
Bag 68.8 58 14,439
SSH 68.8 13 14,452
Bag 68.8 68 14,520
SSH 68.9 7 14,527
SSH 68.9 7 14,534
Biom 69.1 68 14,602
Biom 69.3 78 14,680
Biom 69.4 68 14,748
Bag 69.6 58 14,806
Biom 69.6 78 14,884
SSH 69.7 6 14,890
SSH 69.7 3 14,893
Bag 69.7 74 14,967
Biog 69.8 36 15,004
Biog 69.8 36 15,040
Biog 69.8 36 15,076
Biog 69.8 36 15,113
Biom 70.0 68 15,181
SSH 70.1 6 15,188
SSH 70.1 20 15,207
Biom 70.1 78 15,285
SSH 70.2 10 15,295
Biom 70.4 68 15,363
Bag 70.5 58 15,421
SSH 70.5 16 15,437
SSH 70.6 6 15,443
SSH 70.7 196 15,639
SSH 70.8 6 15,646
Biom 70.9 68 15,714
SSH 71.0 6 15,720
SSH 71.2 6 15,726
Biom 71.3 68 15,795
Bag 71.4 58 15,853
Curve 6 - RES-E Curve (Private)
Bag 71.5 68 15,920
SSH 71.5 29 15,949
Bag 71.6 68 16,017
Biom 71.6 68 16,085
Biom 71.8 68 16,154
SSH 71.8 6 16,160
Biom 72.0 62 16,222
SSH 72.1 5 16,227
Biom 72.1 68 16,295
SSH 72.4 6 16,301
SSH 72.4 6 16,307
Bag 72.5 74 16,381
Biom 72.5 68 16,450
Biom 72.5 62 16,512
Biom 72.8 62 16,575
SSH 72.9 6 16,580
Biom 73.0 68 16,649
SSH 73.1 3 16,652
SSH 73.1 6 16,657
SSH 73.1 39 16,696
SSH 73.2 3 16,699
SSH 73.2 64 16,763
SSH 73.2 5 16,768
SSH 73.2 5 16,774
Bag 73.2 58 16,832
SSH 73.3 3 16,834
Biom 73.4 62 16,897
Bag 73.4 68 16,965
LFG 73.4 4 16,969
LFG 73.4 4 16,973
LFG 73.4 4 16,977
LFG 73.4 4 16,981
Biom 73.4 68 17,050
SSH 73.7 14 17,063
SSH 73.7 5 17,069
SSH 73.7 5 17,074
Biom 74.0 68 17,143
Biom 74.0 62 17,205
SSH 74.1 14 17,219
Bag 74.2 58 17,277
WTE 74.2 8 17,285
WTE 74.2 8 17,293
WTE 74.2 8 17,302
WTE 74.2 8 17,310
Biom 74.3 68 17,379
SSH 74.3 5 17,384
Biom 74.5 62 17,446
SSH 74.6 5 17,452
Biom 74.8 68 17,520
Biom 74.8 62 17,582
SSH 74.9 5 17,587
SSH 75.0 5 17,592
Bag 75.0 58 17,650
SSH 75.2 40 17,690
SSH 75.2 42 17,732
SSH 75.2 4 17,736
Biom 75.3 62 17,798
Biom 75.4 62 17,860
Biog 75.4 46 17,906
Biog 75.4 46 17,952
Biog 75.4 46 17,998
Biog 75.4 46 18,043
SSH 75.4 3 18,047
SSH 75.4 4 18,051
Curve 6 - RES-E Curve (Private)
SSH 75.4 5 18,055
SSH 75.4 5 18,060
SSH 75.6 3 18,064
SSH 75.8 5 18,068
SSH 75.8 5 18,073
Biom 75.8 62 18,135
Bag 75.9 58 18,193
SSH 76.0 5 18,198
Bag 76.1 68 18,266
Biom 76.2 62 18,328
SSH 76.3 7 18,335
SSH 76.4 8 18,343
SSH 76.4 5 18,348
SSH 76.6 5 18,352
Biom 76.7 62 18,415
SSH 77.2 4 18,419
Biom 77.3 62 18,481
SSH 77.6 4 18,486
Bag 77.8 58 18,544
Biom 77.8 62 18,606
Biom 78.2 62 18,668
Sew 78.2 2 18,671
Sew 78.2 2 18,673
Sew 78.2 2 18,675
Sew 78.2 2 18,677
SSH 78.2 79 18,756
SSH 78.2 4 18,760
SSH 78.3 4 18,765
SSH 78.5 4 18,769
Biom 78.5 53 18,822
SSH 78.5 4 18,826
Bag 78.6 58 18,884
Biom 78.7 62 18,947
SSH 78.7 4 18,951
Biom 79.0 53 19,004
SSH 79.1 4 19,008
SSH 79.2 4 19,012
Biog 79.3 42 19,054
Biog 79.3 42 19,096
Biog 79.3 42 19,139
Biog 79.3 42 19,181
Biom 79.4 53 19,234
SSH 79.8 4 19,238
Biom 79.9 53 19,292
SSH 80.3 2 19,294
SSH 80.3 4 19,298
SSH 80.4 4 19,301
Bag 80.4 58 19,359
SSH 80.5 4 19,363
SSH 80.7 85 19,448
Biom 80.8 53 19,502
SSH 81.2 4 19,505
Biom 81.4 53 19,558
WTE 81.4 8 19,566
WTE 81.4 8 19,574
WTE 81.4 8 19,582
WTE 81.4 8 19,589
SSH 81.5 4 19,593
SSH 81.5 4 19,596
Biom 81.7 53 19,650
SSH 81.8 26 19,676
SSH 82.1 3 19,679
Biom 82.2 53 19,732
Biog 82.4 40 19,772
Curve 6 - RES-E Curve (Private)
Biog 82.4 40 19,812
Biog 82.4 40 19,852
Biog 82.4 40 19,892
Biom 82.4 53 19,945
SSH 82.4 4 19,949
SSH 82.5 3 19,952
SSH 82.8 3 19,956
SSH 82.8 238 20,194
Biom 82.9 53 20,247
SSH 83.0 3 20,251
Bag 83.1 58 20,309
Biom 83.3 53 20,362
Biom 83.8 53 20,415
SSH 83.8 3 20,418
SSH 84.2 3 20,421
SSH 84.2 98 20,519
SSH 84.2 3 20,522
SSH 84.3 2 20,524
SSH 84.6 32 20,556
Sew 84.7 2 20,558
Sew 84.7 2 20,560
Sew 84.7 2 20,562
Sew 84.7 2 20,564
Biom 84.7 53 20,617
Biog 84.9 46 20,663
Biog 84.9 46 20,709
Biog 84.9 46 20,755
Biog 84.9 46 20,800
Biom 85.3 53 20,854
SSH 85.5 3 20,857
Biom 85.6 53 20,910
SSH 85.7 3 20,913
SSH 85.9 3 20,916
SSH 86.0 15 20,931
Biom 86.1 53 20,984
SSH 86.7 3 20,987
SSH 86.8 4 20,990
SSH 87.2 3 20,993
SSH 87.2 97 21,090
SSH 87.4 3 21,093
SSH 87.4 2 21,095
Biog 87.7 36 21,131
Biog 87.7 36 21,168
Biog 87.7 36 21,204
Biog 87.7 36 21,240
SSH 87.7 5 21,245
SSH 87.9 3 21,248
SSH 88.1 3 21,251
SSH 88.6 4 21,255
SSH 88.7 3 21,258
SSH 88.8 3 21,260
Sew 88.9 2 21,262
Sew 88.9 2 21,264
Sew 88.9 2 21,267
Sew 88.9 2 21,269
SSH 88.9 3 21,271
SSH 89.0 3 21,274
SSH 89.2 12 21,286
SSH 89.4 2 21,288
SSH 89.6 2 21,291
Biog 89.6 42 21,333
Biog 89.6 42 21,375
Biog 89.6 42 21,417
Biog 89.6 42 21,460
Curve 6 - RES-E Curve (Private)
Sew 89.7 2 21,461
Sew 89.7 2 21,463
Sew 89.7 2 21,465
Sew 89.7 2 21,467
SSH 89.9 5 21,472
SSH 90.0 2 21,475
SSH 90.0 2 21,477
SSH 90.1 3 21,480
SSH 90.5 4 21,484
SSH 91.1 2 21,486
SSH 91.2 2 21,488
SSH 91.2 2 21,491
SSH 91.5 2 21,493
SSH 91.9 13 21,506
SSH 91.9 2 21,508
SSH 92.0 2 21,510
SSH 92.2 2 21,512
SSH 92.5 2 21,515
SSH 92.6 2 21,517
SSH 92.8 2 21,519
SSH 92.9 3 21,522
Biog 93.3 40 21,561
Biog 93.3 40 21,601
Biog 93.3 40 21,641
Biog 93.3 40 21,681
SSH 93.3 3 21,684
SSH 93.6 2 21,686
SSH 93.7 2 21,688
SSH 93.7 2 21,690
SSH 93.7 3 21,693
SSH 93.8 3 21,696
SSH 93.9 3 21,698
WD 94.5 6 21,705
WD 94.5 6 21,711
WD 94.5 6 21,717
WD 94.5 6 21,724
WD 94.5 6 21,730
WD 94.5 6 21,737
WD 94.5 6 21,743
WD 94.5 6 21,749
WD 94.5 6 21,756
WD 94.5 6 21,762
WD 94.5 6 21,768
WD 94.5 6 21,775
WD 94.5 6 21,781
WD 94.5 6 21,788
WD 94.5 6 21,794
WD 94.5 6 21,800
SSH 94.8 2 21,802
SSH 95.1 2 21,804
WTE 95.2 7 21,811
WTE 95.2 7 21,818
WTE 95.2 7 21,824
WTE 95.2 7 21,831
SSH 95.2 2 21,833
SSH 95.4 2 21,835
SSH 95.7 2 21,837
SSH 95.9 2 21,839
SSH 95.9 2 21,841
Sew 96.0 2 21,843
Sew 96.0 2 21,845
Sew 96.0 2 21,847
Sew 96.0 2 21,849
SSH 96.1 2 21,851
Curve 6 - RES-E Curve (Private)
Sew 96.3 2 21,853
Sew 96.3 2 21,855
Sew 96.3 2 21,857
Sew 96.3 2 21,859
SSH 96.5 2 21,861
SSH 96.7 273 22,134
WTE 96.9 10 22,143
WTE 96.9 10 22,153
WTE 96.9 10 22,162
WTE 96.9 10 22,172
SSH 97.4 2 22,174
SSH 97.6 2 22,176
SSH 97.6 2 22,178
SSH 97.8 2 22,180
SSH 97.8 3 22,183
SSH 98.1 2 22,185
SSH 98.2 3 22,187
SSH 98.3 2 22,189
SSH 98.3 2 22,191
Sew 98.3 2 22,193
Sew 98.3 2 22,194
Sew 98.3 2 22,196
Sew 98.3 2 22,198
SSH 98.8 6 22,203
Biog 99.1 46 22,249
Biog 99.1 46 22,295
Biog 99.1 46 22,340
Biog 99.1 46 22,386
SSH 99.1 2 22,388
SSH 99.2 2 22,390
SSH 99.3 3 22,393
SSH 99.4 2 22,395
SSH 99.4 2 22,396
SSH 99.6 2 22,398
Biog 99.6 36 22,435
Biog 99.6 36 22,471
Biog 99.6 36 22,508
Biog 99.6 36 22,544
SSH 99.7 2 22,546
SSH 100.5 2 22,547
SSH 100.5 49 22,596
WD 100.6 6 22,602
WD 100.6 6 22,609
WD 100.6 6 22,615
WD 100.6 6 22,621
WD 100.6 6 22,628
WD 100.6 6 22,634
WD 100.6 6 22,641
WD 100.6 6 22,647
WD 100.6 6 22,653
WD 100.6 6 22,660
WD 100.6 6 22,666
WD 100.6 6 22,672
WD 100.6 6 22,679
WD 100.6 6 22,685
WD 100.6 6 22,691
WD 100.6 6 22,698
SSH 101.0 105 22,803
SSH 101.1 25 22,828
SSH 101.8 2 22,829
SSH 101.9 2 22,831
Sew 101.9 2 22,833
Sew 101.9 2 22,835
Sew 101.9 2 22,836
Curve 6 - RES-E Curve (Private)
Sew 101.9 2 22,838
SSH 102.1 3 22,841
SSH 102.2 2 22,843
SSH 102.3 2 22,844
WD 102.3 163 23,007
WD 102.3 163 23,170
WD 102.3 163 23,332
WD 102.3 163 23,495
WD 102.3 163 23,657
WD 102.3 163 23,820
WD 102.3 163 23,983
WD 102.3 163 24,145
WD 102.3 163 24,308
WD 102.3 163 24,471
WD 102.3 163 24,633
WD 102.3 163 24,796
WD 102.3 163 24,959
WD 102.3 163 25,121
WD 102.3 163 25,284
WD 102.3 163 25,446
SSH 102.4 2 25,448
SSH 102.6 6 25,454
SSH 103.3 2 25,455
SSH 103.8 2 25,457
Sew 104.0 2 25,459
Sew 104.0 2 25,461
Sew 104.0 2 25,463
Sew 104.0 2 25,465
SSH 104.1 3 25,468
SSH 104.4 3 25,470
SSH 104.5 1 25,472
SSH 104.6 2 25,474
SSH 104.6 1 25,475
WD 104.7 6 25,482
WD 104.7 6 25,488
WD 104.7 6 25,494
WD 104.7 6 25,501
WD 104.7 6 25,507
WD 104.7 6 25,514
WD 104.7 6 25,520
WD 104.7 6 25,526
WD 104.7 6 25,533
WD 104.7 6 25,539
WD 104.7 6 25,545
WD 104.7 6 25,552
WD 104.7 6 25,558
WD 104.7 6 25,565
WD 104.7 6 25,571
WD 104.7 6 25,577
SSH 104.9 1 25,579
SSH 105.0 43 25,622
Biog 105.0 42 25,664
Biog 105.0 42 25,706
Biog 105.0 42 25,749
Biog 105.0 42 25,791
SSH 105.4 1 25,792
SSH 105.6 1 25,794
SSH 105.7 1 25,795
SSH 105.7 3 25,798
SSH 106.6 1 25,800
Sew 106.7 2 25,802
Sew 106.7 2 25,804
Sew 106.7 2 25,806
Sew 106.7 2 25,808
Curve 6 - RES-E Curve (Private)
SSH 106.9 1 25,810
SSH 107.0 1 25,811
SSH 107.9 1 25,812
WD 108.1 218 26,031
WD 108.1 218 26,249
WD 108.1 218 26,467
WD 108.1 218 26,686
WD 108.1 218 26,904
WD 108.1 218 27,122
WD 108.1 218 27,340
WD 108.1 218 27,559
WD 108.1 218 27,777
WD 108.1 218 27,995
WD 108.1 218 28,214
WD 108.1 218 28,432
WD 108.1 218 28,650
WD 108.1 218 28,869
WD 108.1 218 29,087
WD 108.1 218 29,305
SSH 108.6 3 29,308
SSH 108.6 1 29,310
WD 109.0 163 29,472
WD 109.0 163 29,635
WD 109.0 163 29,797
WD 109.0 163 29,960
WD 109.0 163 30,123
WD 109.0 163 30,285
WD 109.0 163 30,448
WD 109.0 163 30,611
WD 109.0 163 30,773
WD 109.0 163 30,936
WD 109.0 163 31,099
WD 109.0 163 31,261
WD 109.0 163 31,424
WD 109.0 163 31,586
WD 109.0 163 31,749
WD 109.0 163 31,912
SSH 109.2 6 31,917
SSH 109.2 1 31,919
SSH 109.2 1 31,920
SSH 109.4 1 31,921
Biog 109.6 40 31,961
Biog 109.6 40 32,001
Biog 109.6 40 32,041
Biog 109.6 40 32,080
SSH 109.7 1 32,082
WTE 109.8 8 32,090
WTE 109.8 8 32,099
WTE 109.8 8 32,107
WTE 109.8 8 32,115
SSH 109.9 1 32,117
SSH 109.9 1 32,118
SSH 110.0 3 32,121
Sew 110.1 2 32,123
Sew 110.1 2 32,124
Sew 110.1 2 32,126
Sew 110.1 2 32,128
SSH 110.5 1 32,129
SSH 110.7 1 32,130
SSH 110.9 1 32,131
WD 110.9 6 32,138
WD 110.9 6 32,144
WD 110.9 6 32,151
WD 110.9 6 32,157
Curve 6 - RES-E Curve (Private)
WD 110.9 6 32,163
WD 110.9 6 32,170
WD 110.9 6 32,176
WD 110.9 6 32,182
WD 110.9 6 32,189
WD 110.9 6 32,195
WD 110.9 6 32,202
WD 110.9 6 32,208
WD 110.9 6 32,214
WD 110.9 6 32,221
WD 110.9 6 32,227
WD 110.9 6 32,233
SSH 111.4 2 32,236
Sew 111.8 2 32,237
Sew 111.8 2 32,239
Sew 111.8 2 32,241
Sew 111.8 2 32,242
SSH 112.3 1 32,243
SSH 112.7 1 32,244
SSH 112.8 2 32,247
SSH 113.1 1 32,248
WD 113.4 163 32,410
WD 113.4 163 32,573
WD 113.4 163 32,736
WD 113.4 163 32,898
WD 113.4 163 33,061
WD 113.4 163 33,224
WD 113.4 163 33,386
WD 113.4 163 33,549
WD 113.4 163 33,711
WD 113.4 163 33,874
WD 113.4 163 34,037
WD 113.4 163 34,199
WD 113.4 163 34,362
WD 113.4 163 34,525
WD 113.4 163 34,687
WD 113.4 163 34,850
SSH 115.2 6 34,856
WD 115.2 218 35,074
WD 115.2 218 35,292
WD 115.2 218 35,511
WD 115.2 218 35,729
WD 115.2 218 35,947
WD 115.2 218 36,166
WD 115.2 218 36,384
WD 115.2 218 36,602
WD 115.2 218 36,821
WD 115.2 218 37,039
WD 115.2 218 37,257
WD 115.2 218 37,475
WD 115.2 218 37,694
WD 115.2 218 37,912
WD 115.2 218 38,130
WD 115.2 218 38,349
Sew 115.6 2 38,351
Sew 115.6 2 38,353
Sew 115.6 2 38,355
Sew 115.6 2 38,357
SSH 115.6 1 38,358
SSH 115.7 4 38,362
SSH 116.2 2 38,364
SSH 116.4 1 38,365
SSH 117.1 1 38,366
SSH 117.3 3 38,369
Curve 6 - RES-E Curve (Private)
Biog 117.5 36 38,405
Biog 117.5 36 38,442
Biog 117.5 36 38,478
Biog 117.5 36 38,514
WTE 117.9 10 38,524
WTE 117.9 10 38,534
WTE 117.9 10 38,543
WTE 117.9 10 38,553
SSH 118.7 1 38,554
SSH 118.9 1 38,555
SSH 118.9 1 38,555
SSH 119.5 6 38,561
SSH 119.6 5 38,567
WD 119.9 218 38,785
WD 119.9 218 39,003
WD 119.9 218 39,221
WD 119.9 218 39,440
WD 119.9 218 39,658
WD 119.9 218 39,876
WD 119.9 218 40,095
WD 119.9 218 40,313
WD 119.9 218 40,531
WD 119.9 218 40,750
WD 119.9 218 40,968
WD 119.9 218 41,186
WD 119.9 218 41,405
WD 119.9 218 41,623
WD 119.9 218 41,841
WD 119.9 218 42,059
WD 120.1 163 42,222
WD 120.1 163 42,385
WD 120.1 163 42,547
WD 120.1 163 42,710
WD 120.1 163 42,873
WD 120.1 163 43,035
WD 120.1 163 43,198
WD 120.1 163 43,360
WD 120.1 163 43,523
WD 120.1 163 43,686
WD 120.1 163 43,848
WD 120.1 163 44,011
WD 120.1 163 44,174
WD 120.1 163 44,336
WD 120.1 163 44,499
WD 120.1 163 44,662
WTE 120.4 8 44,669
WTE 120.4 8 44,677
WTE 120.4 8 44,685
WTE 120.4 8 44,692
SSH 120.6 1 44,693
SSH 120.6 1 44,694
SSH 120.6 1 44,695
Sew 120.8 2 44,697
Sew 120.8 2 44,698
Sew 120.8 2 44,700
Sew 120.8 2 44,702
SSH 120.8 4 44,706
SSH 120.9 2 44,708
SSH 121.6 1 44,708
SSH 121.8 126 44,834
Sew 122.4 2 44,836
Sew 122.4 2 44,838
Sew 122.4 2 44,840
Sew 122.4 2 44,842
Curve 6 - RES-E Curve (Private)
SSH 122.9 2 44,844
SSH 124.8 1 44,844
SSH 125.4 3 44,847
SSH 126.6 1 44,848
WD 127.0 218 45,066
WD 127.0 218 45,285
WD 127.0 218 45,503
WD 127.0 218 45,721
WD 127.0 218 45,940
WD 127.0 218 46,158
WD 127.0 218 46,376
WD 127.0 218 46,594
WD 127.0 218 46,813
WD 127.0 218 47,031
WD 127.0 218 47,249
WD 127.0 218 47,468
WD 127.0 218 47,686
WD 127.0 218 47,904
WD 127.0 218 48,123
WD 127.0 218 48,341
SSH 127.2 1 48,342
SSH 127.8 1 48,342
SSH 128.1 1 48,343
SSH 128.3 5 48,349
SSH 130.7 1 48,350
SSH 131.1 1 48,350
SSH 131.1 0 48,351
SSH 131.5 0 48,351
SSH 131.8 1 48,352
SSH 133.2 0 48,353
WTE 133.5 8 48,361
WTE 133.5 8 48,370
WTE 133.5 8 48,378
WTE 133.5 8 48,386
SSH 134.0 1 48,388
Sew 134.2 2 48,390
Sew 134.2 2 48,391
Sew 134.2 2 48,393
Sew 134.2 2 48,395
SSH 134.5 0 48,395
SSH 135.6 0 48,396
SSH 135.8 1 48,397
SSH 136.6 1 48,398
SSH 136.8 2 48,400
SSH 138.8 0 48,400
WTE 140.8 7 48,407
WTE 140.8 7 48,413
WTE 140.8 7 48,420
WTE 140.8 7 48,426
SSH 140.9 0 48,427
SSH 141.3 1 48,428
SSH 141.4 0 48,429
SSH 143.1 0 48,429
SSH 145.9 1 48,430
SSH 146.0 0 48,431
WTE 146.4 8 48,438
WTE 146.4 8 48,446
WTE 146.4 8 48,454
WTE 146.4 8 48,461
SSH 149.0 0 48,462
SSH 149.1 1 48,463
WTE 149.2 10 48,472
WTE 149.2 10 48,482
WTE 149.2 10 48,491
Curve 6 - RES-E Curve (Private)
WTE 149.2 10 48,501
SSH 149.5 0 48,501
SSH 152.7 0 48,502
SSH 153.4 0 48,502
SSH 153.9 1 48,503
SSH 154.3 0 48,503
SSH 155.5 0 48,503
SSH 155.9 1 48,505
SSH 156.3 12 48,517
SSH 157.0 1 48,518
SSH 157.7 0 48,518
SSH 160.2 3 48,521
SSH 161.8 0 48,521
SSH 163.5 0 48,521
SSH 164.6 1 48,522
SSH 167.2 1 48,523
WTE 169.0 8 48,531
WTE 169.0 8 48,540
WTE 169.0 8 48,548
WTE 169.0 8 48,557
WTE 171.2 7 48,563
WTE 171.2 7 48,570
WTE 171.2 7 48,576
WTE 171.2 7 48,583
SSH 172.9 0 48,583
SSH 175.0 0 48,583
SSH 176.0 0 48,584
SSH 177.7 2 48,585
SSH 178.6 1 48,586
SSH 179.6 1 48,587
SSH 181.3 1 48,588
SSH 184.0 0 48,588
WTE 185.4 8 48,596
WTE 185.4 8 48,604
WTE 185.4 8 48,611
WTE 185.4 8 48,619
SSH 190.8 0 48,619
SSH 198.0 2 48,622
SSH 199.9 1 48,622
SSH 200.2 1 48,623
SSH 203.9 1 48,624
SSH 203.9 1 48,625
SSH 204.8 0 48,625
SSH 205.1 1 48,626
SSH 210.8 1 48,627
SSH 211.2 0 48,627
SSH 211.5 1 48,628
SSH 213.3 1 48,629
SSH 215.7 1 48,631
SSH 215.8 1 48,631
WTE 216.8 7 48,638
WTE 216.8 7 48,644
WTE 216.8 7 48,651
WTE 216.8 7 48,657
SSH 219.8 0 48,658
SSH 222.3 1 48,659
SSH 224.1 1 48,660
SSH 226.4 0 48,660
SSH 232.4 1 48,660
SSH 238.1 0 48,661
SSH 238.1 0 48,661
SSH 245.0 0 48,661
SSH 252.9 5 48,665
ST 272.3 14 48,679
Curve 6 - RES-E Curve (Private)
ST 272.3 14 48,693
ST 272.3 14 48,707
ST 272.3 14 48,722
ST 282.6 14 48,735
ST 282.6 14 48,749
ST 282.6 14 48,762
ST 282.6 14 48,776
ST 289.9 13 48,789
ST 289.9 13 48,802
ST 289.9 13 48,815
ST 289.9 13 48,828
ST 301.6 13 48,841
ST 301.6 13 48,853
ST 301.6 13 48,866
ST 301.6 13 48,879
ST 314.9 14 48,893
ST 314.9 14 48,907
ST 314.9 14 48,921
ST 314.9 14 48,935
SSH 317.7 4 48,939
ST 326.8 14 48,953
ST 326.8 14 48,966
ST 326.8 14 48,980
ST 326.8 14 48,993
ST 335.2 13 49,006
ST 335.2 13 49,019
ST 335.2 13 49,033
ST 335.2 13 49,046
ST 343.3 14 49,060
ST 343.3 14 49,074
ST 343.3 14 49,088
ST 343.3 14 49,102
PV 343.5 74 49,175
PV 343.5 74 49,249
PV 343.5 74 49,323
PV 343.5 74 49,396
ST 348.8 13 49,409
ST 348.8 13 49,422
ST 348.8 13 49,434
ST 348.8 13 49,447
ST 356.3 14 49,460
ST 356.3 14 49,474
ST 356.3 14 49,487
ST 356.3 14 49,501
PV 356.4 71 49,572
PV 356.4 71 49,643
PV 356.4 71 49,714
PV 356.4 71 49,785
PV 360.4 74 49,858
PV 360.4 74 49,932
PV 360.4 74 50,005
PV 360.4 74 50,079
ST 365.5 13 50,092
ST 365.5 13 50,105
ST 365.5 13 50,119
ST 365.5 13 50,132
PV 365.7 69 50,201
PV 365.7 69 50,270
PV 365.7 69 50,339
PV 365.7 69 50,408
PV 371.7 74 50,482
PV 371.7 74 50,555
PV 371.7 74 50,629
PV 371.7 74 50,703
Curve 6 - RES-E Curve (Private)
PV 374.0 71 50,774
PV 374.0 71 50,845
PV 374.0 71 50,916
PV 374.0 71 50,986
ST 380.2 13 50,999
ST 380.2 13 51,012
ST 380.2 13 51,024
ST 380.2 13 51,037
PV 380.4 66 51,104
PV 380.4 66 51,170
PV 380.4 66 51,236
PV 380.4 66 51,303
PV 383.7 69 51,372
PV 383.7 69 51,441
PV 383.7 69 51,510
PV 383.7 69 51,579
PV 385.8 71 51,650
PV 385.8 71 51,721
PV 385.8 71 51,792
PV 385.8 71 51,863
ST 385.9 14 51,877
ST 385.9 14 51,891
ST 385.9 14 51,905
ST 385.9 14 51,919
PV 388.7 74 51,993
PV 388.7 74 52,066
PV 388.7 74 52,140
PV 388.7 74 52,214
PV 395.7 69 52,283
PV 395.7 69 52,352
PV 395.7 69 52,421
PV 395.7 69 52,490
PV 399.2 66 52,557
PV 399.2 66 52,623
PV 399.2 66 52,690
PV 399.2 66 52,756
ST 400.5 14 52,770
ST 400.5 14 52,783
ST 400.5 14 52,797
ST 400.5 14 52,810
PV 403.4 71 52,881
PV 403.4 71 52,952
PV 403.4 71 53,023
PV 403.4 71 53,094
SSH 405.7 33 53,127
ST 410.8 13 53,140
ST 410.8 13 53,153
ST 410.8 13 53,166
ST 410.8 13 53,179
PV 411.7 66 53,246
PV 411.7 66 53,312
PV 411.7 66 53,379
PV 411.7 66 53,445
PV 413.8 69 53,514
PV 413.8 69 53,583
PV 413.8 69 53,653
PV 413.8 69 53,722
ST 427.4 13 53,734
ST 427.4 13 53,747
ST 427.4 13 53,760
ST 427.4 13 53,772
PV 430.5 66 53,839
PV 430.5 66 53,905
PV 430.5 66 53,972
Curve 6 - RES-E Curve (Private)
PV 430.5 66 54,038
Curve 7 - Small Scale Hydel

Cost Generation Cum


Code ($/MWh) (GWh) Generation
SSH 43.0 45 45
SSH 43.0 42 87
SSH 43.0 35 122
SSH 43.0 35 157
SSH 43.0 169 326
SSH 43.0 185 511
SSH 43.0 84 595
SSH 43.0 224 819
SSH 45.0 80 900
SSH 45.2 107 1,007
SSH 45.2 77 1,083
SSH 45.6 186 1,269
SSH 46.2 57 1,326
SSH 47.2 196 1,522
SSH 49.1 29 1,552
SSH 49.1 22 1,574
SSH 49.1 17 1,590
SSH 49.1 12 1,602
SSH 49.1 34 1,636
SSH 49.1 31 1,667
SSH 49.1 5 1,672
SSH 49.1 25 1,697
SSH 49.1 25 1,721
SSH 49.1 15 1,737
SSH 49.1 7 1,744
SSH 49.1 22 1,766
SSH 49.1 20 1,786
SSH 49.1 34 1,820
SSH 49.1 15 1,834
SSH 49.1 14 1,849
SSH 49.1 14 1,863
SSH 49.1 14 1,876
SSH 49.1 6 1,882
SSH 49.1 4 1,885
SSH 49.1 5 1,890
SSH 49.1 12 1,902
SSH 49.1 12 1,914
SSH 49.1 11 1,925
SSH 49.1 11 1,936
SSH 49.1 10 1,946
SSH 49.1 5 1,951
SSH 49.1 12 1,963
SSH 49.1 4 1,967
SSH 49.1 10 1,977
SSH 49.1 8 1,984
SSH 49.1 8 1,992
SSH 49.1 8 2,000
SSH 49.1 8 2,007
SSH 49.1 7 2,014
SSH 49.1 6 2,020
SSH 49.1 34 2,054
SSH 49.1 4 2,058
SSH 49.1 2 2,060
SSH 50.1 7 2,067
SSH 50.1 59 2,125
SSH 50.5 5 2,130
SSH 50.9 4 2,134
SSH 50.9 7 2,141
SSH 51.3 42 2,182
SSH 51.4 6 2,188
SSH 51.4 17 2,206
Curve 7 - Small Scale Hydel
SSH 51.5 66 2,271
SSH 51.6 58 2,330
SSH 51.7 18 2,347
SSH 51.7 17 2,364
SSH 51.8 17 2,381
SSH 51.8 17 2,397
SSH 52.0 4 2,401
SSH 52.1 5 2,407
SSH 52.2 29 2,435
SSH 52.2 11 2,446
SSH 52.2 12 2,458
SSH 52.2 5 2,462
SSH 52.2 6 2,469
SSH 52.2 16 2,485
SSH 52.3 19 2,504
SSH 52.3 6 2,510
SSH 52.3 9 2,519
SSH 52.3 7 2,526
SSH 52.4 3 2,529
SSH 52.4 17 2,545
SSH 52.5 16 2,562
SSH 52.5 16 2,577
SSH 52.6 15 2,593
SSH 52.8 18 2,611
SSH 52.9 14 2,625
SSH 52.9 26 2,651
SSH 52.9 16 2,666
SSH 53.1 18 2,684
SSH 53.2 16 2,700
SSH 53.2 11 2,711
SSH 53.2 15 2,726
SSH 53.3 16 2,742
SSH 53.3 7 2,748
SSH 53.3 227 2,975
SSH 53.4 20 2,995
SSH 53.4 15 3,010
SSH 53.5 18 3,028
SSH 53.6 143 3,171
SSH 53.6 135 3,306
SSH 53.8 20 3,326
SSH 53.8 20 3,346
SSH 53.8 20 3,367
SSH 53.8 15 3,382
SSH 53.8 15 3,396
SSH 53.9 20 3,417
SSH 53.9 15 3,432
SSH 53.9 83 3,515
SSH 53.9 15 3,529
SSH 53.9 4 3,533
SSH 54.0 21 3,554
SSH 54.1 100 3,654
SSH 54.1 6 3,660
SSH 54.1 19 3,679
SSH 54.2 111 3,790
SSH 54.2 22 3,812
SSH 54.2 14 3,827
SSH 54.2 8 3,835
SSH 54.3 7 3,841
SSH 54.3 94 3,935
SSH 54.5 14 3,949
SSH 54.6 23 3,972
SSH 54.6 95 4,068
SSH 54.6 252 4,320
SSH 54.6 3 4,323
Curve 7 - Small Scale Hydel
SSH 54.7 4 4,327
SSH 54.8 13 4,341
SSH 54.9 23 4,364
SSH 54.9 8 4,372
SSH 54.9 24 4,395
SSH 54.9 13 4,408
SSH 55.0 25 4,433
SSH 55.0 25 4,458
SSH 55.0 25 4,483
SSH 55.2 9 4,493
SSH 55.3 26 4,518
SSH 55.3 26 4,545
SSH 55.3 9 4,553
SSH 55.4 8 4,561
SSH 55.5 14 4,575
SSH 55.6 14 4,589
SSH 55.7 78 4,667
SSH 55.8 76 4,743
SSH 55.9 6 4,749
SSH 55.9 75 4,824
SSH 56.0 280 5,104
SSH 56.0 54 5,158
SSH 56.0 74 5,232
SSH 56.0 126 5,358
SSH 56.0 3 5,361
SSH 56.1 56 5,418
SSH 56.4 5 5,423
SSH 56.5 51 5,474
SSH 56.7 28 5,502
SSH 56.9 8 5,510
SSH 57.0 13 5,523
SSH 57.0 13 5,535
SSH 57.0 17 5,552
SSH 57.0 28 5,580
SSH 57.1 29 5,609
SSH 57.2 315 5,924
SSH 57.3 42 5,966
SSH 57.4 56 6,022
SSH 57.5 42 6,064
SSH 57.7 3 6,067
SSH 57.7 29 6,096
SSH 57.8 18 6,114
SSH 57.8 5 6,118
SSH 57.9 29 6,147
SSH 58.0 15 6,163
SSH 58.0 28 6,191
SSH 58.0 126 6,317
SSH 58.0 12 6,329
SSH 58.0 13 6,342
SSH 58.4 9 6,351
SSH 58.6 12 6,363
SSH 58.8 7 6,369
SSH 58.9 11 6,380
SSH 58.9 8 6,388
SSH 59.1 52 6,440
SSH 59.1 3 6,443
SSH 59.1 10 6,452
SSH 59.2 11 6,464
SSH 59.5 11 6,475
SSH 59.6 11 6,486
SSH 59.6 5 6,491
SSH 59.8 10 6,501
SSH 59.9 6 6,507
SSH 60.0 32 6,539
Curve 7 - Small Scale Hydel
SSH 60.3 11 6,549
SSH 60.3 23 6,573
SSH 60.4 13 6,585
SSH 60.4 21 6,607
SSH 60.4 24 6,631
SSH 60.5 8 6,639
SSH 60.6 10 6,649
SSH 60.7 52 6,701
SSH 60.7 18 6,719
SSH 60.7 7 6,726
SSH 60.8 34 6,760
SSH 60.8 22 6,782
SSH 60.8 10 6,792
SSH 60.9 41 6,832
SSH 61.0 16 6,848
SSH 61.4 39 6,887
SSH 61.5 33 6,920
SSH 61.5 10 6,930
SSH 61.7 210 7,140
SSH 61.8 29 7,169
SSH 61.8 10 7,179
SSH 61.9 9 7,188
SSH 62.0 9 7,198
SSH 62.1 18 7,216
SSH 62.2 9 7,225
SSH 62.4 9 7,234
SSH 62.4 34 7,268
SSH 62.4 36 7,304
SSH 62.4 5 7,309
SSH 62.5 24 7,334
SSH 62.7 4 7,338
SSH 62.8 38 7,376
SSH 63.0 9 7,385
SSH 63.0 9 7,394
SSH 63.1 58 7,452
SSH 63.5 9 7,461
SSH 63.7 9 7,470
SSH 63.8 58 7,527
SSH 64.0 5 7,532
SSH 64.0 256 7,789
SSH 64.1 49 7,838
SSH 64.2 10 7,848
SSH 64.3 8 7,856
SSH 64.5 4 7,861
SSH 64.5 252 8,113
SSH 64.5 7 8,120
SSH 64.6 96 8,216
SSH 64.7 8 8,224
SSH 64.8 9 8,232
SSH 64.9 9 8,241
SSH 64.9 8 8,249
SSH 64.9 5 8,255
SSH 64.9 22 8,277
SSH 64.9 8 8,285
SSH 64.9 8 8,293
SSH 65.0 8 8,301
SSH 65.2 35 8,336
SSH 65.2 158 8,494
SSH 65.2 127 8,621
SSH 65.3 55 8,677
SSH 65.5 7 8,683
SSH 65.5 8 8,691
SSH 65.5 4 8,695
SSH 65.5 8 8,703
Curve 7 - Small Scale Hydel
SSH 65.6 8 8,711
SSH 65.6 8 8,718
SSH 65.7 5 8,723
SSH 65.7 27 8,751
SSH 65.9 105 8,856
SSH 66.0 8 8,863
SSH 66.3 68 8,931
SSH 67.2 8 8,939
SSH 67.2 8 8,947
SSH 67.2 8 8,954
SSH 67.2 8 8,962
SSH 67.2 8 8,970
SSH 67.2 8 8,977
SSH 67.2 4 8,981
SSH 67.6 8 8,989
SSH 67.6 8 8,996
SSH 67.8 68 9,064
SSH 67.9 7 9,071
SSH 68.1 7 9,078
SSH 68.1 7 9,085
SSH 68.2 7 9,092
SSH 68.6 7 9,099
SSH 68.6 3 9,102
SSH 68.8 7 9,109
SSH 68.8 13 9,122
SSH 68.9 7 9,129
SSH 68.9 7 9,136
SSH 69.7 6 9,142
SSH 69.7 3 9,145
SSH 70.1 6 9,151
SSH 70.1 20 9,171
SSH 70.2 10 9,181
SSH 70.5 16 9,196
SSH 70.6 6 9,203
SSH 70.7 196 9,399
SSH 70.8 6 9,405
SSH 71.0 6 9,411
SSH 71.2 6 9,418
SSH 71.5 29 9,446
SSH 71.8 6 9,452
SSH 72.1 5 9,457
SSH 72.4 6 9,463
SSH 72.4 6 9,469
SSH 72.9 6 9,474
SSH 73.1 3 9,477
SSH 73.1 6 9,482
SSH 73.1 39 9,521
SSH 73.2 3 9,524
SSH 73.2 64 9,588
SSH 73.2 5 9,594
SSH 73.2 5 9,599
SSH 73.3 3 9,602
SSH 73.7 14 9,616
SSH 73.7 5 9,621
SSH 73.7 5 9,626
SSH 74.1 14 9,640
SSH 74.3 5 9,645
SSH 74.6 5 9,650
SSH 74.9 5 9,655
SSH 75.0 5 9,660
SSH 75.2 40 9,700
SSH 75.2 42 9,742
SSH 75.2 4 9,746
SSH 75.4 3 9,749
Curve 7 - Small Scale Hydel
SSH 75.4 4 9,753
SSH 75.4 5 9,757
SSH 75.4 5 9,762
SSH 75.6 3 9,766
SSH 75.8 5 9,770
SSH 75.8 5 9,775
SSH 76.0 5 9,780
SSH 76.3 7 9,787
SSH 76.4 8 9,794
SSH 76.4 5 9,799
SSH 76.6 5 9,804
SSH 77.2 4 9,808
SSH 77.6 4 9,812
SSH 78.2 79 9,892
SSH 78.2 4 9,896
SSH 78.3 4 9,900
SSH 78.5 4 9,904
SSH 78.5 4 9,908
SSH 78.7 4 9,912
SSH 79.1 4 9,916
SSH 79.2 4 9,920
SSH 79.8 4 9,924
SSH 80.3 2 9,926
SSH 80.3 4 9,930
SSH 80.4 4 9,934
SSH 80.5 4 9,937
SSH 80.7 85 10,023
SSH 81.2 4 10,026
SSH 81.5 4 10,030
SSH 81.5 4 10,034
SSH 81.8 26 10,059
SSH 82.1 3 10,063
SSH 82.4 4 10,067
SSH 82.5 3 10,070
SSH 82.8 3 10,073
SSH 82.8 238 10,312
SSH 83.0 3 10,315
SSH 83.8 3 10,318
SSH 84.2 3 10,320
SSH 84.2 98 10,418
SSH 84.2 3 10,421
SSH 84.3 2 10,424
SSH 84.6 32 10,456
SSH 85.5 3 10,459
SSH 85.7 3 10,461
SSH 85.9 3 10,464
SSH 86.0 15 10,479
SSH 86.7 3 10,482
SSH 86.8 4 10,486
SSH 87.2 3 10,488
SSH 87.2 97 10,585
SSH 87.4 3 10,588
SSH 87.4 2 10,590
SSH 87.7 5 10,595
SSH 87.9 3 10,598
SSH 88.1 3 10,601
SSH 88.6 4 10,605
SSH 88.7 3 10,607
SSH 88.8 3 10,610
SSH 88.9 3 10,612
SSH 89.0 3 10,615
SSH 89.2 12 10,627
SSH 89.4 2 10,629
SSH 89.6 2 10,632
Curve 7 - Small Scale Hydel
SSH 89.9 5 10,637
SSH 90.0 2 10,640
SSH 90.0 2 10,642
SSH 90.1 3 10,645
SSH 90.5 4 10,648
SSH 91.1 2 10,651
SSH 91.2 2 10,653
SSH 91.2 2 10,655
SSH 91.5 2 10,658
SSH 91.9 13 10,671
SSH 91.9 2 10,673
SSH 92.0 2 10,675
SSH 92.2 2 10,677
SSH 92.5 2 10,679
SSH 92.6 2 10,682
SSH 92.8 2 10,684
SSH 92.9 3 10,686
SSH 93.3 3 10,689
SSH 93.6 2 10,691
SSH 93.7 2 10,693
SSH 93.7 2 10,695
SSH 93.7 3 10,698
SSH 93.8 3 10,701
SSH 93.9 3 10,704
SSH 94.8 2 10,706
SSH 95.1 2 10,708
SSH 95.2 2 10,710
SSH 95.4 2 10,712
SSH 95.7 2 10,714
SSH 95.9 2 10,716
SSH 95.9 2 10,718
SSH 96.1 2 10,720
SSH 96.5 2 10,722
SSH 96.7 273 10,994
SSH 97.4 2 10,996
SSH 97.6 2 10,999
SSH 97.6 2 11,000
SSH 97.8 2 11,002
SSH 97.8 3 11,005
SSH 98.1 2 11,007
SSH 98.2 3 11,010
SSH 98.3 2 11,012
SSH 98.3 2 11,013
SSH 98.8 6 11,019
SSH 99.1 2 11,021
SSH 99.2 2 11,022
SSH 99.3 3 11,026
SSH 99.4 2 11,027
SSH 99.4 2 11,029
SSH 99.6 2 11,031
SSH 99.7 2 11,033
SSH 100.5 2 11,035
SSH 100.5 49 11,083
SSH 101.0 105 11,188
SSH 101.1 25 11,213
SSH 101.8 2 11,215
SSH 101.9 2 11,216
SSH 102.1 3 11,219
SSH 102.2 2 11,221
SSH 102.3 2 11,222
SSH 102.4 2 11,224
SSH 102.6 6 11,230
SSH 103.3 2 11,231
SSH 103.8 2 11,233
Curve 7 - Small Scale Hydel
SSH 104.1 3 11,236
SSH 104.4 3 11,238
SSH 104.5 1 11,240
SSH 104.6 2 11,242
SSH 104.6 1 11,243
SSH 104.9 1 11,245
SSH 105.0 43 11,288
SSH 105.4 1 11,289
SSH 105.6 1 11,291
SSH 105.7 1 11,292
SSH 105.7 3 11,295
SSH 106.6 1 11,297
SSH 106.9 1 11,298
SSH 107.0 1 11,300
SSH 107.9 1 11,301
SSH 108.6 3 11,304
SSH 108.6 1 11,305
SSH 109.2 6 11,311
SSH 109.2 1 11,312
SSH 109.2 1 11,313
SSH 109.4 1 11,315
SSH 109.7 1 11,316
SSH 109.9 1 11,317
SSH 109.9 1 11,318
SSH 110.0 3 11,321
SSH 110.5 1 11,322
SSH 110.7 1 11,323
SSH 110.9 1 11,324
SSH 111.4 2 11,326
SSH 112.3 1 11,328
SSH 112.7 1 11,329
SSH 112.8 2 11,331
SSH 113.1 1 11,332
SSH 115.2 6 11,338
SSH 115.6 1 11,339
SSH 115.7 4 11,343
SSH 116.2 2 11,345
SSH 116.4 1 11,346
SSH 117.1 1 11,347
SSH 117.3 3 11,350
SSH 118.7 1 11,351
SSH 118.9 1 11,352
SSH 118.9 1 11,353
SSH 119.5 6 11,359
SSH 119.6 5 11,364
SSH 120.6 1 11,365
SSH 120.6 1 11,366
SSH 120.6 1 11,367
SSH 120.8 4 11,371
SSH 120.9 2 11,373
SSH 121.6 1 11,373
SSH 121.8 126 11,499
SSH 122.9 2 11,501
SSH 124.8 1 11,502
SSH 125.4 3 11,505
SSH 126.6 1 11,506
SSH 127.2 1 11,506
SSH 127.8 1 11,507
SSH 128.1 1 11,508
SSH 128.3 5 11,514
SSH 130.7 1 11,515
SSH 131.1 1 11,515
SSH 131.1 0 11,516
SSH 131.5 0 11,516
Curve 7 - Small Scale Hydel
SSH 131.8 1 11,517
SSH 133.2 0 11,518
SSH 134.0 1 11,519
SSH 134.5 0 11,519
SSH 135.6 0 11,520
SSH 135.8 1 11,521
SSH 136.6 1 11,522
SSH 136.8 2 11,524
SSH 138.8 0 11,524
SSH 140.9 0 11,525
SSH 141.3 1 11,526
SSH 141.4 0 11,527
SSH 143.1 0 11,527
SSH 145.9 1 11,528
SSH 146.0 0 11,529
SSH 149.0 0 11,529
SSH 149.1 1 11,530
SSH 149.5 0 11,530
SSH 152.7 0 11,530
SSH 153.4 0 11,531
SSH 153.9 1 11,532
SSH 154.3 0 11,532
SSH 155.5 0 11,532
SSH 155.9 1 11,534
SSH 156.3 12 11,546
SSH 157.0 1 11,547
SSH 157.7 0 11,547
SSH 160.2 3 11,549
SSH 161.8 0 11,550
SSH 163.5 0 11,550
SSH 164.6 1 11,551
SSH 167.2 1 11,552
SSH 172.9 0 11,552
SSH 175.0 0 11,552
SSH 176.0 0 11,552
SSH 177.7 2 11,554
SSH 178.6 1 11,555
SSH 179.6 1 11,556
SSH 181.3 1 11,557
SSH 184.0 0 11,557
SSH 190.8 0 11,557
SSH 198.0 2 11,560
SSH 199.9 1 11,560
SSH 200.2 1 11,561
SSH 203.9 1 11,562
SSH 203.9 1 11,563
SSH 204.8 0 11,563
SSH 205.1 1 11,564
SSH 210.8 1 11,565
SSH 211.2 0 11,565
SSH 211.5 1 11,566
SSH 213.3 1 11,567
SSH 215.7 1 11,569
SSH 215.8 1 11,569
SSH 219.8 0 11,569
SSH 222.3 1 11,570
SSH 224.1 1 11,571
SSH 226.4 0 11,571
SSH 232.4 1 11,572
SSH 238.1 0 11,572
SSH 238.1 0 11,572
SSH 245.0 0 11,572
SSH 252.9 5 11,577
SSH 317.7 4 11,581
Curve 7 - Small Scale Hydel
SSH 405.7 33 11,614
Curve 8 - Bagasse-based Cogeneration (social)

Cost Generation Cum


Code ($/MWh) (GWh) Generation
Bag 61.4 84 84
Bag 62.0 74 159
Bag 62.4 68 226
Bag 63.2 58 284
Bag 64.2 84 369
Bag 64.7 74 443
Bag 65.1 68 511
Bag 65.1 84 595
Bag 65.9 58 653
Bag 66.0 84 737
Bag 66.1 74 812
Bag 66.5 74 886
Bag 66.9 68 954
Bag 67.0 68 1,022
Bag 67.6 84 1,106
Bag 67.8 58 1,164
Bag 67.9 84 1,248
Bag 68.6 58 1,306
Bag 68.7 84 1,391
Bag 68.9 74 1,465
Bag 68.9 74 1,539
Bag 69.2 74 1,614
Bag 69.7 68 1,682
Bag 69.7 84 1,766
Bag 69.7 68 1,834
Bag 70.0 68 1,901
Bag 70.3 84 1,986
Bag 70.5 58 2,044
Bag 70.7 74 2,118
Bag 71.3 84 2,202
Bag 71.3 58 2,260
Bag 71.5 68 2,328
Bag 71.7 74 2,403
Bag 72.1 84 2,487
Bag 72.2 58 2,545
Bag 72.4 84 2,629
Bag 72.8 68 2,697
Bag 73.1 74 2,771
Bag 73.1 58 2,829
Bag 73.4 74 2,904
Bag 73.5 74 2,978
Bag 74.0 84 3,062
Bag 74.3 68 3,130
Bag 74.6 68 3,198
Bag 74.6 68 3,266
Bag 74.9 84 3,350
Bag 74.9 58 3,408
Bag 75.8 84 3,492
Bag 75.9 74 3,567
Bag 75.9 58 3,625
Bag 76.2 74 3,699
Bag 76.7 58 3,757
Bag 77.3 68 3,825
Bag 77.4 68 3,893
Bag 77.6 58 3,951
Bag 77.7 74 4,025
Bag 78.6 84 4,109
Bag 79.2 68 4,177
Bag 79.5 58 4,235
Bag 80.3 58 4,293
Bag 80.4 74 4,367
Curve 8 - Bagasse-based Cogeneration (social)
Bag 81.9 68 4,435
Bag 82.1 58 4,493
Bag 84.8 58 4,551
Curve 9 - Biomass

Cost Generation Cum


Code ($/MWh) (GWh) Generation
Biom 53.4 78 78
Biom 53.4 78 155
Biom 53.4 78 233
Biom 53.4 78 310
Biom 53.4 78 388
Biom 53.4 78 465
Biom 53.4 78 543
Biom 53.4 78 620
Biom 53.4 78 698
Biom 53.4 78 775
Biom 53.4 78 853
Biom 53.4 78 930
Biom 53.4 68 999
Biom 53.4 78 1,076
Biom 53.4 68 1,145
Biom 53.4 78 1,222
Biom 62.4 68 1,291
Biom 62.4 78 1,368
Biom 62.4 68 1,437
Biom 62.4 78 1,514
Biom 62.4 68 1,583
Biom 62.4 68 1,651
Biom 62.4 68 1,719
Biom 62.4 68 1,788
Biom 62.4 68 1,856
Biom 62.4 62 1,919
Biom 62.4 68 1,987
Biom 62.4 68 2,056
Biom 62.4 62 2,118
Biom 62.4 62 2,181
Biom 62.4 68 2,249
Biom 62.4 62 2,311
Biom 68.5 68 2,380
Biom 68.5 68 2,448
Biom 68.5 62 2,511
Biom 68.5 68 2,579
Biom 68.5 62 2,642
Biom 68.5 68 2,710
Biom 68.5 62 2,772
Biom 68.5 62 2,835
Biom 68.5 62 2,897
Biom 68.5 62 2,960
Biom 68.5 62 3,022
Biom 68.5 62 3,085
Biom 68.5 62 3,147
Biom 68.5 62 3,209
Biom 68.5 62 3,272
Biom 68.5 53 3,325
Biom 77.5 62 3,388
Biom 77.5 53 3,441
Biom 77.5 53 3,494
Biom 77.5 53 3,548
Biom 77.5 53 3,601
Biom 77.5 53 3,654
Biom 77.5 53 3,708
Biom 77.5 53 3,761
Biom 77.5 53 3,814
Biom 77.5 53 3,868
Biom 77.5 53 3,921
Biom 77.5 53 3,974
Biom 77.5 53 4,028
Curve 9 - Biomass
Biom 77.5 53 4,081
Biom 77.5 53 4,135
Biom 77.5 53 4,188
Curve 10 - Biogas

Cost Generation Cum


Code ($/MWh) (GWh) Generation
Biog 61.1 46 46
Biog 61.1 46 92
Biog 61.1 46 137
Biog 61.1 46 183
Biog 63.9 42 225
Biog 63.9 42 267
Biog 63.9 42 310
Biog 63.9 42 352
Biog 66.0 40 392
Biog 66.0 40 432
Biog 66.0 40 472
Biog 66.0 40 511
Biog 69.8 36 548
Biog 69.8 36 584
Biog 69.8 36 621
Biog 69.8 36 657
Biog 75.4 46 703
Biog 75.4 46 748
Biog 75.4 46 794
Biog 75.4 46 840
Biog 79.3 42 882
Biog 79.3 42 924
Biog 79.3 42 967
Biog 79.3 42 1,009
Biog 82.4 40 1,049
Biog 82.4 40 1,089
Biog 82.4 40 1,129
Biog 82.4 40 1,168
Biog 84.9 46 1,214
Biog 84.9 46 1,260
Biog 84.9 46 1,306
Biog 84.9 46 1,351
Biog 87.7 36 1,388
Biog 87.7 36 1,424
Biog 87.7 36 1,461
Biog 87.7 36 1,497
Biog 89.6 42 1,539
Biog 89.6 42 1,581
Biog 89.6 42 1,624
Biog 89.6 42 1,666
Biog 93.3 40 1,706
Biog 93.3 40 1,746
Biog 93.3 40 1,785
Biog 93.3 40 1,825
Biog 99.1 46 1,871
Biog 99.1 46 1,917
Biog 99.1 46 1,963
Biog 99.1 46 2,008
Biog 99.6 36 2,045
Biog 99.6 36 2,081
Biog 99.6 36 2,117
Biog 99.6 36 2,154
Biog 105.0 42 2,196
Biog 105.0 42 2,238
Biog 105.0 42 2,281
Biog 105.0 42 2,323
Biog 109.6 40 2,363
Biog 109.6 40 2,403
Biog 109.6 40 2,442
Biog 109.6 40 2,482
Biog 117.5 36 2,519
Curve 10 - Biogas
Biog 117.5 36 2,555
Biog 117.5 36 2,591
Biog 117.5 36 2,628
Curve 10 - Sewage

Cost Generation Cum


Code ($/MWh) (GWh) Generation
Sew 78.2 2 2
Sew 78.2 2 4
Sew 78.2 2 6
Sew 78.2 2 9
Sew 84.7 2 10
Sew 84.7 2 12
Sew 84.7 2 14
Sew 84.7 2 16
Sew 88.9 2 18
Sew 88.9 2 21
Sew 88.9 2 23
Sew 88.9 2 25
Sew 89.7 2 27
Sew 89.7 2 29
Sew 89.7 2 30
Sew 89.7 2 32
Sew 96.0 2 34
Sew 96.0 2 37
Sew 96.0 2 39
Sew 96.0 2 41
Sew 96.3 2 43
Sew 96.3 2 45
Sew 96.3 2 47
Sew 96.3 2 49
Sew 98.3 2 50
Sew 98.3 2 52
Sew 98.3 2 54
Sew 98.3 2 55
Sew 101.9 2 57
Sew 101.9 2 59
Sew 101.9 2 61
Sew 101.9 2 63
Sew 104.0 2 65
Sew 104.0 2 67
Sew 104.0 2 69
Sew 104.0 2 71
Sew 106.7 2 73
Sew 106.7 2 75
Sew 106.7 2 77
Sew 106.7 2 79
Sew 110.1 2 81
Sew 110.1 2 83
Sew 110.1 2 85
Sew 110.1 2 87
Sew 111.8 2 88
Sew 111.8 2 90
Sew 111.8 2 92
Sew 111.8 2 93
Sew 115.6 2 95
Sew 115.6 2 97
Sew 115.6 2 99
Sew 115.6 2 101
Sew 120.8 2 103
Sew 120.8 2 105
Sew 120.8 2 106
Sew 120.8 2 108
Sew 122.4 2 110
Sew 122.4 2 112
Sew 122.4 2 113
Sew 122.4 2 115
Sew 134.2 2 117
Curve 10 - Sewage
Sew 134.2 2 119
Sew 134.2 2 120
Sew 134.2 2 122
Curve 11 - Landfill gas

Cost Generation Cum


Code ($/MWh) (GWh) Generation
LFG 47.7 5 5
LFG 47.7 5 10
LFG 47.7 5 15
LFG 47.7 5 21
LFG 51.7 5 25
LFG 51.7 5 30
LFG 51.7 5 35
LFG 51.7 5 40
LFG 51.7 5 45
LFG 51.7 5 50
LFG 51.7 5 55
LFG 51.7 5 60
LFG 54.4 5 65
LFG 54.4 5 70
LFG 54.4 5 75
LFG 54.4 5 81
LFG 54.7 4 85
LFG 54.7 4 90
LFG 54.7 4 94
LFG 54.7 4 99
LFG 56.0 5 103
LFG 56.0 5 108
LFG 56.0 5 113
LFG 56.0 5 117
LFG 58.3 5 123
LFG 58.3 5 128
LFG 58.3 5 133
LFG 58.3 5 138
LFG 58.9 5 143
LFG 58.9 5 148
LFG 58.9 5 152
LFG 58.9 5 157
LFG 59.3 4 161
LFG 59.3 4 166
LFG 59.3 4 170
LFG 59.3 4 175
LFG 60.0 4 179
LFG 60.0 4 183
LFG 60.0 4 187
LFG 60.0 4 191
LFG 62.4 4 196
LFG 62.4 4 200
LFG 62.4 4 205
LFG 62.4 4 209
LFG 63.2 5 214
LFG 63.2 5 219
LFG 63.2 5 223
LFG 63.2 5 228
LFG 65.0 4 232
LFG 65.0 4 236
LFG 65.0 4 240
LFG 65.0 4 244
LFG 66.9 4 249
LFG 66.9 4 253
LFG 66.9 4 258
LFG 66.9 4 262
LFG 68.4 4 266
LFG 68.4 4 271
LFG 68.4 4 275
LFG 68.4 4 279
LFG 73.4 4 283
Curve 11 - Landfill gas
LFG 73.4 4 287
LFG 73.4 4 291
LFG 73.4 4 295
Curve 12 - Waste-to-Energy

Cost Generation Cum


Code ($/MWh) (GWh) Generation
WTE 65.5 10 10
WTE 65.5 10 19
WTE 65.5 10 29
WTE 65.5 10 38
WTE 74.2 8 47
WTE 74.2 8 55
WTE 74.2 8 64
WTE 74.2 8 72
WTE 81.4 8 80
WTE 81.4 8 87
WTE 81.4 8 95
WTE 81.4 8 103
WTE 95.2 7 109
WTE 95.2 7 116
WTE 95.2 7 123
WTE 95.2 7 129
WTE 96.9 10 139
WTE 96.9 10 148
WTE 96.9 10 158
WTE 96.9 10 167
WTE 109.8 8 176
WTE 109.8 8 184
WTE 109.8 8 193
WTE 109.8 8 201
WTE 117.9 10 211
WTE 117.9 10 220
WTE 117.9 10 230
WTE 117.9 10 240
WTE 120.4 8 247
WTE 120.4 8 255
WTE 120.4 8 263
WTE 120.4 8 270
WTE 133.5 8 279
WTE 133.5 8 287
WTE 133.5 8 296
WTE 133.5 8 304
WTE 140.8 7 311
WTE 140.8 7 317
WTE 140.8 7 324
WTE 140.8 7 330
WTE 146.4 8 338
WTE 146.4 8 346
WTE 146.4 8 354
WTE 146.4 8 361
WTE 149.2 10 371
WTE 149.2 10 380
WTE 149.2 10 390
WTE 149.2 10 400
WTE 169.0 8 408
WTE 169.0 8 416
WTE 169.0 8 425
WTE 169.0 8 433
WTE 171.2 7 440
WTE 171.2 7 446
WTE 171.2 7 453
WTE 171.2 7 460
WTE 185.4 8 467
WTE 185.4 8 475
WTE 185.4 8 483
WTE 185.4 8 490
WTE 216.8 7 497
Curve 12 - Waste-to-Energy
WTE 216.8 7 504
WTE 216.8 7 510
WTE 216.8 7 517
Curve 13 - Photovoltaic

Cost Generation Cum


Code ($/MWh) (GWh) Generation
PV 343.5 74 74
PV 343.5 74 147
PV 343.5 74 221
PV 343.5 74 294
PV 356.4 71 365
PV 356.4 71 436
PV 356.4 71 507
PV 356.4 71 578
PV 360.4 74 652
PV 360.4 74 725
PV 360.4 74 799
PV 360.4 74 873
PV 365.7 69 942
PV 365.7 69 1,011
PV 365.7 69 1,080
PV 365.7 69 1,149
PV 371.7 74 1,223
PV 371.7 74 1,296
PV 371.7 74 1,370
PV 371.7 74 1,444
PV 374.0 71 1,515
PV 374.0 71 1,586
PV 374.0 71 1,656
PV 374.0 71 1,727
PV 380.4 66 1,794
PV 380.4 66 1,860
PV 380.4 66 1,927
PV 380.4 66 1,993
PV 383.7 69 2,062
PV 383.7 69 2,132
PV 383.7 69 2,201
PV 383.7 69 2,270
PV 385.8 71 2,341
PV 385.8 71 2,412
PV 385.8 71 2,483
PV 385.8 71 2,554
PV 388.7 74 2,627
PV 388.7 74 2,701
PV 388.7 74 2,774
PV 388.7 74 2,848
PV 395.7 69 2,917
PV 395.7 69 2,986
PV 395.7 69 3,055
PV 395.7 69 3,125
PV 399.2 66 3,191
PV 399.2 66 3,257
PV 399.2 66 3,324
PV 399.2 66 3,390
PV 403.4 71 3,461
PV 403.4 71 3,532
PV 403.4 71 3,603
PV 403.4 71 3,674
PV 411.7 66 3,741
PV 411.7 66 3,807
PV 411.7 66 3,873
PV 411.7 66 3,940
PV 413.8 69 4,009
PV 413.8 69 4,078
PV 413.8 69 4,147
PV 413.8 69 4,217
PV 430.5 66 4,283
Curve 13 - Photovoltaic
PV 430.5 66 4,349
PV 430.5 66 4,416
PV 430.5 66 4,482
Curve 14 - Solar Thermal

Cost Generation Cum


Code ($/MWh) (GWh) Generation
ST 272.3 14 14
ST 272.3 14 28
ST 272.3 14 42
ST 272.3 14 56
ST 282.6 14 70
ST 282.6 14 83
ST 282.6 14 97
ST 282.6 14 110
ST 289.9 13 123
ST 289.9 13 136
ST 289.9 13 150
ST 289.9 13 163
ST 301.6 13 175
ST 301.6 13 188
ST 301.6 13 201
ST 301.6 13 213
ST 314.9 14 227
ST 314.9 14 241
ST 314.9 14 255
ST 314.9 14 269
ST 326.8 14 283
ST 326.8 14 296
ST 326.8 14 310
ST 326.8 14 323
ST 335.2 13 337
ST 335.2 13 350
ST 335.2 13 363
ST 335.2 13 376
ST 343.3 14 390
ST 343.3 14 404
ST 343.3 14 418
ST 343.3 14 432
ST 348.8 13 445
ST 348.8 13 457
ST 348.8 13 470
ST 348.8 13 483
ST 356.3 14 496
ST 356.3 14 510
ST 356.3 14 523
ST 356.3 14 537
ST 365.5 13 550
ST 365.5 13 563
ST 365.5 13 576
ST 365.5 13 589
ST 380.2 13 602
ST 380.2 13 615
ST 380.2 13 627
ST 380.2 13 640
ST 385.9 14 654
ST 385.9 14 668
ST 385.9 14 682
ST 385.9 14 696
ST 400.5 14 709
ST 400.5 14 723
ST 400.5 14 736
ST 400.5 14 750
ST 410.8 13 763
ST 410.8 13 776
ST 410.8 13 789
ST 410.8 13 803
ST 427.4 13 815
Curve 14 - Solar Thermal
ST 427.4 13 828
ST 427.4 13 841
ST 427.4 13 853
Curve 15 - Wind

Cost Generation Cum


Code ($/MWh) (GWh) Generation
WD 94.5 6 6
WD 94.5 6 13
WD 94.5 6 19
WD 94.5 6 25
WD 94.5 6 32
WD 94.5 6 38
WD 94.5 6 45
WD 94.5 6 51
WD 94.5 6 57
WD 94.5 6 64
WD 94.5 6 70
WD 94.5 6 76
WD 94.5 6 83
WD 94.5 6 89
WD 94.5 6 96
WD 94.5 6 102
WD 100.6 6 108
WD 100.6 6 115
WD 100.6 6 121
WD 100.6 6 127
WD 100.6 6 134
WD 100.6 6 140
WD 100.6 6 146
WD 100.6 6 153
WD 100.6 6 159
WD 100.6 6 166
WD 100.6 6 172
WD 100.6 6 178
WD 100.6 6 185
WD 100.6 6 191
WD 100.6 6 197
WD 100.6 6 204
WD 102.3 163 366
WD 102.3 163 529
WD 102.3 163 692
WD 102.3 163 854
WD 102.3 163 1,017
WD 102.3 163 1,180
WD 102.3 163 1,342
WD 102.3 163 1,505
WD 102.3 163 1,668
WD 102.3 163 1,830
WD 102.3 163 1,993
WD 102.3 163 2,155
WD 102.3 163 2,318
WD 102.3 163 2,481
WD 102.3 163 2,643
WD 102.3 163 2,806
WD 104.7 6 2,812
WD 104.7 6 2,819
WD 104.7 6 2,825
WD 104.7 6 2,831
WD 104.7 6 2,838
WD 104.7 6 2,844
WD 104.7 6 2,851
WD 104.7 6 2,857
WD 104.7 6 2,863
WD 104.7 6 2,870
WD 104.7 6 2,876
WD 104.7 6 2,882
WD 104.7 6 2,889
Curve 15 - Wind
WD 104.7 6 2,895
WD 104.7 6 2,901
WD 104.7 6 2,908
WD 108.1 218 3,126
WD 108.1 218 3,344
WD 108.1 218 3,563
WD 108.1 218 3,781
WD 108.1 218 3,999
WD 108.1 218 4,218
WD 108.1 218 4,436
WD 108.1 218 4,654
WD 108.1 218 4,873
WD 108.1 218 5,091
WD 108.1 218 5,309
WD 108.1 218 5,527
WD 108.1 218 5,746
WD 108.1 218 5,964
WD 108.1 218 6,182
WD 108.1 218 6,401
WD 109.0 163 6,563
WD 109.0 163 6,726
WD 109.0 163 6,889
WD 109.0 163 7,051
WD 109.0 163 7,214
WD 109.0 163 7,376
WD 109.0 163 7,539
WD 109.0 163 7,702
WD 109.0 163 7,864
WD 109.0 163 8,027
WD 109.0 163 8,190
WD 109.0 163 8,352
WD 109.0 163 8,515
WD 109.0 163 8,678
WD 109.0 163 8,840
WD 109.0 163 9,003
WD 110.9 6 9,009
WD 110.9 6 9,016
WD 110.9 6 9,022
WD 110.9 6 9,028
WD 110.9 6 9,035
WD 110.9 6 9,041
WD 110.9 6 9,047
WD 110.9 6 9,054
WD 110.9 6 9,060
WD 110.9 6 9,067
WD 110.9 6 9,073
WD 110.9 6 9,079
WD 110.9 6 9,086
WD 110.9 6 9,092
WD 110.9 6 9,098
WD 110.9 6 9,105
WD 113.4 163 9,267
WD 113.4 163 9,430
WD 113.4 163 9,593
WD 113.4 163 9,755
WD 113.4 163 9,918
WD 113.4 163 10,081
WD 113.4 163 10,243
WD 113.4 163 10,406
WD 113.4 163 10,568
WD 113.4 163 10,731
WD 113.4 163 10,894
WD 113.4 163 11,056
WD 113.4 163 11,219
Curve 15 - Wind
WD 113.4 163 11,382
WD 113.4 163 11,544
WD 113.4 163 11,707
WD 115.2 218 11,925
WD 115.2 218 12,144
WD 115.2 218 12,362
WD 115.2 218 12,580
WD 115.2 218 12,798
WD 115.2 218 13,017
WD 115.2 218 13,235
WD 115.2 218 13,453
WD 115.2 218 13,672
WD 115.2 218 13,890
WD 115.2 218 14,108
WD 115.2 218 14,327
WD 115.2 218 14,545
WD 115.2 218 14,763
WD 115.2 218 14,981
WD 115.2 218 15,200
WD 119.9 218 15,418
WD 119.9 218 15,636
WD 119.9 218 15,855
WD 119.9 218 16,073
WD 119.9 218 16,291
WD 119.9 218 16,510
WD 119.9 218 16,728
WD 119.9 218 16,946
WD 119.9 218 17,164
WD 119.9 218 17,383
WD 119.9 218 17,601
WD 119.9 218 17,819
WD 119.9 218 18,038
WD 119.9 218 18,256
WD 119.9 218 18,474
WD 119.9 218 18,693
WD 120.1 163 18,855
WD 120.1 163 19,018
WD 120.1 163 19,180
WD 120.1 163 19,343
WD 120.1 163 19,506
WD 120.1 163 19,668
WD 120.1 163 19,831
WD 120.1 163 19,994
WD 120.1 163 20,156
WD 120.1 163 20,319
WD 120.1 163 20,482
WD 120.1 163 20,644
WD 120.1 163 20,807
WD 120.1 163 20,969
WD 120.1 163 21,132
WD 120.1 163 21,295
WD 127.0 218 21,513
WD 127.0 218 21,731
WD 127.0 218 21,950
WD 127.0 218 22,168
WD 127.0 218 22,386
WD 127.0 218 22,605
WD 127.0 218 22,823
WD 127.0 218 23,041
WD 127.0 218 23,259
WD 127.0 218 23,478
WD 127.0 218 23,696
WD 127.0 218 23,914
WD 127.0 218 24,133
Curve 15 - Wind
WD 127.0 218 24,351
WD 127.0 218 24,569
WD 127.0 218 24,788
Curve 16 - Bagasse-based Cogeneration (private)

Cost Generation Cum


Code ($/MWh) (GWh) Generation
bag 50.9 84 84
bag 53.6 84 168
bag 54.0 74 243
bag 54.6 84 327
bag 55.5 84 411
bag 56.6 68 479
bag 56.7 74 554
bag 57.1 84 638
bag 57.3 84 722
bag 58.2 84 806
bag 58.2 74 881
bag 58.6 74 955
bag 59.2 84 1,039
bag 59.3 68 1,107
bag 59.8 84 1,191
bag 60.8 84 1,276
bag 60.9 74 1,350
bag 61.0 74 1,424
bag 61.1 68 1,492
bag 61.2 68 1,560
bag 61.3 74 1,635
bag 61.5 58 1,693
bag 61.6 84 1,777
bag 61.9 84 1,861
bag 62.7 74 1,935
bag 63.5 84 2,020
bag 63.7 74 2,094
bag 63.9 68 2,162
bag 63.9 68 2,230
bag 64.2 68 2,298
bag 64.3 58 2,356
bag 64.3 84 2,440
bag 65.2 74 2,514
bag 65.3 84 2,598
bag 65.5 74 2,673
bag 65.5 74 2,747
bag 65.7 68 2,815
bag 66.1 58 2,873
bag 66.9 58 2,931
bag 67.0 68 2,999
bag 67.9 74 3,073
bag 68.0 84 3,157
bag 68.3 74 3,232
bag 68.4 68 3,300
bag 68.8 68 3,368
bag 68.8 58 3,425
bag 68.8 68 3,493
bag 69.6 58 3,551
bag 69.7 74 3,626
bag 70.5 58 3,684
bag 71.4 58 3,742
bag 71.5 68 3,810
bag 71.6 68 3,877
bag 72.5 74 3,952
bag 73.2 58 4,010
bag 73.4 68 4,078
bag 74.2 58 4,136
bag 75.0 58 4,194
bag 75.9 58 4,252
bag 76.1 68 4,319
bag 77.8 58 4,377
Curve 16 - Bagasse-based Cogeneration (private)
bag 78.6 58 4,435
bag 80.4 58 4,493
bag 83.1 58 4,551
Home
Total Electricity Supply Curve
(mid-tem incremental potential)
500
Electricity Supply Curve (Private)
450
Electricity Supply Curve (Social)

400

350

300
$/MWh

250

200

150

100

50

0
0 50 100 150 200 250
GWh
Home
Total RES-E Supply Curve
(mid-term incremental potential)

450

400

350

300
$/MWh

250

200

150

100

50
Supply Curve (Private Cost) Supply curve (Social Cost)
0
0 10 20 30 40 50 60
TWh/a
Home
160

140

120

100
$/MWh

80

60

40

20

0
0 20 40 60 80 100 120 140
GWh/a

Sewage
Home
80

70

60

50
$/MWh

40

30

20

10

0
0 50 100 150 200 250 300 350
GWh/a

Landfill
Home
140

120

100

80
$/MWh

60

40

20

0
0 500 1000 1500 2000 2500 3000
GWh/a

Biogas
Home
90

80

70

60
$/MWh

50

40

30

20

10

0
0 500 1000 1500 2000 2500 3000 3500 4000 4500
GWh/a

Biomass
Home
90

80

70

60
$/MWh

50

40

30

20

10

0
0 1000 2000 3000 4000 5000
GWh/a

Co-gen (social) Co-gen (Private)


Home
250

200

150
$/MWh

100

50

0
0 100 200 300 400 500 600
GWh/a

WTE
Home
500

450

400

350

300
$/MWh

250

200

150

100

50

0
0 1000 2000 3000 4000 5000
GWh/a

PV
Home
450

400

350

300
$/MWh

250

200

150

100

50

0
0 100 200 300 400 500 600 700 800 900
GWh/a

Solar Th
Home
140

120

100

80
$/MWh

60

40

20

0
0 5000 10000 15000 20000 25000 30000
GWh/a

Wind
Home
450

400

350

300
$/MWh

250

200

150

100

50

0
0 2000 4000 6000 8000 10000 12000 14000
GWh/a

SS hydel
Home
Conventional Electricity Supply Curve
(mid-term incremental)

200

180

160

140

120
$/MWh

100

80

60

40

20

0
0 20 40 60 80 100 120 140 160
TWh/a

Conventional Private Curve Conventional Social Curve


Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
W1 1 1 108.15 0.10 0.10 0.10 20 218.30 218.3
W1 2 2 108.15 0.10 0.10 0.40 20 218.30 436.6
W1 3 3 108.15 0.10 0.10 0.60 20 218.30 654.9
W1 4 4 108.15 0.10 0.10 0.90 20 218.30 873.2
W1 5 5 108.15 0.10 0.40 0.10 20 218.30 1,091.5
W1 6 6 108.15 0.10 0.40 0.40 20 218.30 1,309.8
W1 7 7 108.15 0.10 0.40 0.60 20 218.30 1,528.1
W1 8 8 108.15 0.10 0.40 0.90 20 218.30 1,746.4
W1 9 9 108.15 0.10 0.60 0.10 20 218.30 1,964.7
W1 10 10 108.15 0.10 0.60 0.40 20 218.30 2,183.0
W1 11 11 108.15 0.10 0.60 0.60 20 218.30 2,401.3
W1 12 12 108.15 0.10 0.60 0.90 20 218.30 2,619.6
W1 13 13 108.15 0.10 0.90 0.10 20 218.30 2,837.9
W1 14 14 108.15 0.10 0.90 0.40 20 218.30 3,056.2
W1 15 15 108.15 0.10 0.90 0.60 20 218.30 3,274.5
W1 16 16 108.15 0.10 0.90 0.90 20 218.30 3,492.8
W1 17 17 115.20 0.40 0.10 0.10 20 218.30 3,711.1
W1 18 18 115.20 0.40 0.10 0.40 20 218.30 3,929.4
W1 19 19 115.20 0.40 0.10 0.60 20 218.30 4,147.7
W1 20 20 115.20 0.40 0.10 0.90 20 218.30 4,366.0
W1 21 21 115.20 0.40 0.40 0.10 20 218.30 4,584.3
W1 22 22 115.20 0.40 0.40 0.40 20 218.30 4,802.6
W1 23 23 115.20 0.40 0.40 0.60 20 218.30 5,020.9
W1 24 24 115.20 0.40 0.40 0.90 20 218.30 5,239.2
W1 25 25 115.20 0.40 0.60 0.10 20 218.30 5,457.5
W1 26 26 115.20 0.40 0.60 0.40 20 218.30 5,675.8
W1 27 27 115.20 0.40 0.60 0.60 20 218.30 5,894.1
W1 28 28 115.20 0.40 0.60 0.90 20 218.30 6,112.4
W1 29 29 115.20 0.40 0.90 0.10 20 218.30 6,330.7
W1 30 30 115.20 0.40 0.90 0.40 20 218.30 6,549.0
W1 31 31 115.20 0.40 0.90 0.60 20 218.30 6,767.3
W1 32 32 115.20 0.40 0.90 0.90 20 218.30 6,985.6
W1 33 33 119.90 0.60 0.10 0.10 20 218.30 7,203.9
W1 34 34 119.90 0.60 0.10 0.40 20 218.30 7,422.2
W1 35 35 119.90 0.60 0.10 0.60 20 218.30 7,640.5
W1 36 36 119.90 0.60 0.10 0.90 20 218.30 7,858.8
W1 37 37 119.90 0.60 0.40 0.10 20 218.30 8,077.1
W1 38 38 119.90 0.60 0.40 0.40 20 218.30 8,295.4
W1 39 39 119.90 0.60 0.40 0.60 20 218.30 8,513.7
W1 40 40 119.90 0.60 0.40 0.90 20 218.30 8,732.0
W1 41 41 119.90 0.60 0.60 0.10 20 218.30 8,950.3
W1 42 42 119.90 0.60 0.60 0.40 20 218.30 9,168.6
W1 43 43 119.90 0.60 0.60 0.60 20 218.30 9,386.9
W1 44 44 119.90 0.60 0.60 0.90 20 218.30 9,605.2
W1 45 45 119.90 0.60 0.90 0.10 20 218.30 9,823.6
W1 46 46 119.90 0.60 0.90 0.40 20 218.30 10,041.9
W1 47 47 119.90 0.60 0.90 0.60 20 218.30 10,260.2
W1 48 48 119.90 0.60 0.90 0.90 20 218.30 10,478.5
W1 49 49 126.96 0.90 0.10 0.10 20 218.30 10,696.8
W1 50 50 126.96 0.90 0.10 0.40 20 218.30 10,915.1
W1 51 51 126.96 0.90 0.10 0.60 20 218.30 11,133.4
W1 52 52 126.96 0.90 0.10 0.90 20 218.30 11,351.7
W1 53 53 126.96 0.90 0.40 0.10 20 218.30 11,570.0
W1 54 54 126.96 0.90 0.40 0.40 20 218.30 11,788.3
W1 55 55 126.96 0.90 0.40 0.60 20 218.30 12,006.6
W1 56 56 126.96 0.90 0.40 0.90 20 218.30 12,224.9
W1 57 57 126.96 0.90 0.60 0.10 20 218.30 12,443.2
W1 58 58 126.96 0.90 0.60 0.40 20 218.30 12,661.5
W1 59 59 126.96 0.90 0.60 0.60 20 218.30 12,879.8
W1 60 60 126.96 0.90 0.60 0.90 20 218.30 13,098.1
W1 61 61 126.96 0.90 0.90 0.10 20 218.30 13,316.4
W1 62 62 126.96 0.90 0.90 0.40 20 218.30 13,534.7
W1 63 63 126.96 0.90 0.90 0.60 20 218.30 13,753.0
W1 64 64 126.96 0.90 0.90 0.90 20 218.30 13,971.3
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
W2 1 1 102.32 0.10 0.10 0.10 20 162.64 162.6
W2 2 2 102.32 0.10 0.10 0.40 20 162.64 325.3
W2 3 3 102.32 0.10 0.10 0.60 20 162.64 487.9
W2 4 4 102.32 0.10 0.10 0.90 20 162.64 650.5
W2 5 5 102.32 0.10 0.40 0.10 20 162.64 813.2
W2 6 6 102.32 0.10 0.40 0.40 20 162.64 975.8
W2 7 7 102.32 0.10 0.40 0.60 20 162.64 1,138.4
W2 8 8 102.32 0.10 0.40 0.90 20 162.64 1,301.1
W2 9 9 102.32 0.10 0.60 0.10 20 162.64 1,463.7
W2 10 10 102.32 0.10 0.60 0.40 20 162.64 1,626.4
W2 11 11 102.32 0.10 0.60 0.60 20 162.64 1,789.0
W2 12 12 102.32 0.10 0.60 0.90 20 162.64 1,951.6
W2 13 13 102.32 0.10 0.90 0.10 20 162.64 2,114.3
W2 14 14 102.32 0.10 0.90 0.40 20 162.64 2,276.9
W2 15 15 102.32 0.10 0.90 0.60 20 162.64 2,439.5
W2 16 16 102.32 0.10 0.90 0.90 20 162.64 2,602.2
W2 17 17 109.00 0.40 0.10 0.10 20 162.64 2,764.8
W2 18 18 109.00 0.40 0.10 0.40 20 162.64 2,927.4
W2 19 19 109.00 0.40 0.10 0.60 20 162.64 3,090.1
W2 20 20 109.00 0.40 0.10 0.90 20 162.64 3,252.7
W2 21 21 109.00 0.40 0.40 0.10 20 162.64 3,415.3
W2 22 22 109.00 0.40 0.40 0.40 20 162.64 3,578.0
W2 23 23 109.00 0.40 0.40 0.60 20 162.64 3,740.6
W2 24 24 109.00 0.40 0.40 0.90 20 162.64 3,903.2
W2 25 25 109.00 0.40 0.60 0.10 20 162.64 4,065.9
W2 26 26 109.00 0.40 0.60 0.40 20 162.64 4,228.5
W2 27 27 109.00 0.40 0.60 0.60 20 162.64 4,391.2
W2 28 28 109.00 0.40 0.60 0.90 20 162.64 4,553.8
W2 29 29 109.00 0.40 0.90 0.10 20 162.64 4,716.4
W2 30 30 109.00 0.40 0.90 0.40 20 162.64 4,879.1
W2 31 31 109.00 0.40 0.90 0.60 20 162.64 5,041.7
W2 32 32 109.00 0.40 0.90 0.90 20 162.64 5,204.3
W2 33 33 113.45 0.60 0.10 0.10 20 162.64 5,367.0
W2 34 34 113.45 0.60 0.10 0.40 20 162.64 5,529.6
W2 35 35 113.45 0.60 0.10 0.60 20 162.64 5,692.2
W2 36 36 113.45 0.60 0.10 0.90 20 162.64 5,854.9
W2 37 37 113.45 0.60 0.40 0.10 20 162.64 6,017.5
W2 38 38 113.45 0.60 0.40 0.40 20 162.64 6,180.1
W2 39 39 113.45 0.60 0.40 0.60 20 162.64 6,342.8
W2 40 40 113.45 0.60 0.40 0.90 20 162.64 6,505.4
W2 41 41 113.45 0.60 0.60 0.10 20 162.64 6,668.0
W2 42 42 113.45 0.60 0.60 0.40 20 162.64 6,830.7
W2 43 43 113.45 0.60 0.60 0.60 20 162.64 6,993.3
W2 44 44 113.45 0.60 0.60 0.90 20 162.64 7,155.9
W2 45 45 113.45 0.60 0.90 0.10 20 162.64 7,318.6
W2 46 46 113.45 0.60 0.90 0.40 20 162.64 7,481.2
W2 47 47 113.45 0.60 0.90 0.60 20 162.64 7,643.9
W2 48 48 113.45 0.60 0.90 0.90 20 162.64 7,806.5
W2 49 49 120.12 0.90 0.10 0.10 20 162.64 7,969.1
W2 50 50 120.12 0.90 0.10 0.40 20 162.64 8,131.8
W2 51 51 120.12 0.90 0.10 0.60 20 162.64 8,294.4
W2 52 52 120.12 0.90 0.10 0.90 20 162.64 8,457.0
W2 53 53 120.12 0.90 0.40 0.10 20 162.64 8,619.7
W2 54 54 120.12 0.90 0.40 0.40 20 162.64 8,782.3
W2 55 55 120.12 0.90 0.40 0.60 20 162.64 8,944.9
W2 56 56 120.12 0.90 0.40 0.90 20 162.64 9,107.6
W2 57 57 120.12 0.90 0.60 0.10 20 162.64 9,270.2
W2 58 58 120.12 0.90 0.60 0.40 20 162.64 9,432.8
W2 59 59 120.12 0.90 0.60 0.60 20 162.64 9,595.5
W2 60 60 120.12 0.90 0.60 0.90 20 162.64 9,758.1
W2 61 61 120.12 0.90 0.90 0.10 20 162.64 9,920.7
W2 62 62 120.12 0.90 0.90 0.40 20 162.64 10,083.4
W2 63 63 120.12 0.90 0.90 0.60 20 162.64 10,246.0
W2 64 64 120.12 0.90 0.90 0.90 20 162.64 10,408.7
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
W3 1 1 94.46 0.10 0.10 0.10 20 6.37 6.4
W3 2 2 94.46 0.10 0.10 0.40 20 6.37 12.7
W3 3 3 94.46 0.10 0.10 0.60 20 6.37 19.1
W3 4 4 94.46 0.10 0.10 0.90 20 6.37 25.5
W3 5 5 94.46 0.10 0.40 0.10 20 6.37 31.8
W3 6 6 94.46 0.10 0.40 0.40 20 6.37 38.2
W3 7 7 94.46 0.10 0.40 0.60 20 6.37 44.6
W3 8 8 94.46 0.10 0.40 0.90 20 6.37 51.0
W3 9 9 94.46 0.10 0.60 0.10 20 6.37 57.3
W3 10 10 94.46 0.10 0.60 0.40 20 6.37 63.7
W3 11 11 94.46 0.10 0.60 0.60 20 6.37 70.1
W3 12 12 94.46 0.10 0.60 0.90 20 6.37 76.4
W3 13 13 94.46 0.10 0.90 0.10 20 6.37 82.8
W3 14 14 94.46 0.10 0.90 0.40 20 6.37 89.2
W3 15 15 94.46 0.10 0.90 0.60 20 6.37 95.5
W3 16 16 94.46 0.10 0.90 0.90 20 6.37 101.9
W3 17 17 100.62 0.40 0.10 0.10 20 6.37 108.3
W3 18 18 100.62 0.40 0.10 0.40 20 6.37 114.6
W3 19 19 100.62 0.40 0.10 0.60 20 6.37 121.0
W3 20 20 100.62 0.40 0.10 0.90 20 6.37 127.4
W3 21 21 100.62 0.40 0.40 0.10 20 6.37 133.7
W3 22 22 100.62 0.40 0.40 0.40 20 6.37 140.1
W3 23 23 100.62 0.40 0.40 0.60 20 6.37 146.5
W3 24 24 100.62 0.40 0.40 0.90 20 6.37 152.9
W3 25 25 100.62 0.40 0.60 0.10 20 6.37 159.2
W3 26 26 100.62 0.40 0.60 0.40 20 6.37 165.6
W3 27 27 100.62 0.40 0.60 0.60 20 6.37 172.0
W3 28 28 100.62 0.40 0.60 0.90 20 6.37 178.3
W3 29 29 100.62 0.40 0.90 0.10 20 6.37 184.7
W3 30 30 100.62 0.40 0.90 0.40 20 6.37 191.1
W3 31 31 100.62 0.40 0.90 0.60 20 6.37 197.4
W3 32 32 100.62 0.40 0.90 0.90 20 6.37 203.8
W3 33 33 104.73 0.60 0.10 0.10 20 6.37 210.2
W3 34 34 104.73 0.60 0.10 0.40 20 6.37 216.5
W3 35 35 104.73 0.60 0.10 0.60 20 6.37 222.9
W3 36 36 104.73 0.60 0.10 0.90 20 6.37 229.3
W3 37 37 104.73 0.60 0.40 0.10 20 6.37 235.6
W3 38 38 104.73 0.60 0.40 0.40 20 6.37 242.0
W3 39 39 104.73 0.60 0.40 0.60 20 6.37 248.4
W3 40 40 104.73 0.60 0.40 0.90 20 6.37 254.8
W3 41 41 104.73 0.60 0.60 0.10 20 6.37 261.1
W3 42 42 104.73 0.60 0.60 0.40 20 6.37 267.5
W3 43 43 104.73 0.60 0.60 0.60 20 6.37 273.9
W3 44 44 104.73 0.60 0.60 0.90 20 6.37 280.2
W3 45 45 104.73 0.60 0.90 0.10 20 6.37 286.6
W3 46 46 104.73 0.60 0.90 0.40 20 6.37 293.0
W3 47 47 104.73 0.60 0.90 0.60 20 6.37 299.3
W3 48 48 104.73 0.60 0.90 0.90 20 6.37 305.7
W3 49 49 110.89 0.90 0.10 0.10 20 6.37 312.1
W3 50 50 110.89 0.90 0.10 0.40 20 6.37 318.4
W3 51 51 110.89 0.90 0.10 0.60 20 6.37 324.8
W3 52 52 110.89 0.90 0.10 0.90 20 6.37 331.2
W3 53 53 110.89 0.90 0.40 0.10 20 6.37 337.5
W3 54 54 110.89 0.90 0.40 0.40 20 6.37 343.9
W3 55 55 110.89 0.90 0.40 0.60 20 6.37 350.3
W3 56 56 110.89 0.90 0.40 0.90 20 6.37 356.7
W3 57 57 110.89 0.90 0.60 0.10 20 6.37 363.0
W3 58 58 110.89 0.90 0.60 0.40 20 6.37 369.4
W3 59 59 110.89 0.90 0.60 0.60 20 6.37 375.8
W3 60 60 110.89 0.90 0.60 0.90 20 6.37 382.1
W3 61 61 110.89 0.90 0.90 0.10 20 6.37 388.5
W3 62 62 110.89 0.90 0.90 0.40 20 6.37 394.9
W3 63 63 110.89 0.90 0.90 0.60 20 6.37 401.2
W3 64 64 110.89 0.90 0.90 0.90 20 6.37 407.6
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
ST 1 1 301.56 0.10 0.10 0.10 20 12.65 12.7
ST 2 2 301.56 0.10 0.10 0.40 20 12.65 25.3
ST 3 3 301.56 0.10 0.10 0.60 20 12.65 38.0
ST 4 4 301.56 0.10 0.10 0.90 20 12.65 50.6
ST 5 5 289.87 0.10 0.40 0.10 20 13.16 63.8
ST 6 6 289.87 0.10 0.40 0.40 20 13.16 76.9
ST 7 7 289.87 0.10 0.40 0.60 20 13.16 90.1
ST 8 8 289.87 0.10 0.40 0.90 20 13.16 103.3
ST 9 9 282.56 0.10 0.60 0.10 20 13.50 116.8
ST 10 10 282.56 0.10 0.60 0.40 20 13.50 130.3
ST 11 11 282.56 0.10 0.60 0.60 20 13.50 143.8
ST 12 12 282.56 0.10 0.60 0.90 20 13.50 157.3
ST 13 13 272.26 0.10 0.90 0.10 20 14.01 171.3
ST 14 14 272.26 0.10 0.90 0.40 20 14.01 185.3
ST 15 15 272.26 0.10 0.90 0.60 20 14.01 199.3
ST 16 16 272.26 0.10 0.90 0.90 20 14.01 213.3
ST 17 17 348.76 0.40 0.10 0.10 20 12.65 226.0
ST 18 18 348.76 0.40 0.10 0.40 20 12.65 238.6
ST 19 19 348.76 0.40 0.10 0.60 20 12.65 251.3
ST 20 20 348.76 0.40 0.10 0.90 20 12.65 263.9
ST 21 21 335.23 0.40 0.40 0.10 20 13.16 277.1
ST 22 22 335.23 0.40 0.40 0.40 20 13.16 290.2
ST 23 23 335.23 0.40 0.40 0.60 20 13.16 303.4
ST 24 24 335.23 0.40 0.40 0.90 20 13.16 316.6
ST 25 25 326.78 0.40 0.60 0.10 20 13.50 330.1
ST 26 26 326.78 0.40 0.60 0.40 20 13.50 343.6
ST 27 27 326.78 0.40 0.60 0.60 20 13.50 357.1
ST 28 28 326.78 0.40 0.60 0.90 20 13.50 370.6
ST 29 29 314.87 0.40 0.90 0.10 20 14.01 384.6
ST 30 30 314.87 0.40 0.90 0.40 20 14.01 398.6
ST 31 31 314.87 0.40 0.90 0.60 20 14.01 412.6
ST 32 32 314.87 0.40 0.90 0.90 20 14.01 426.6
ST 33 33 380.22 0.60 0.10 0.10 20 12.65 439.3
ST 34 34 380.22 0.60 0.10 0.40 20 12.65 451.9
ST 35 35 380.22 0.60 0.10 0.60 20 12.65 464.6
ST 36 36 380.22 0.60 0.10 0.90 20 12.65 477.2
ST 37 37 365.47 0.60 0.40 0.10 20 13.16 490.4
ST 38 38 365.47 0.60 0.40 0.40 20 13.16 503.5
ST 39 39 365.47 0.60 0.40 0.60 20 13.16 516.7
ST 40 40 365.47 0.60 0.40 0.90 20 13.16 529.9
ST 41 41 356.26 0.60 0.60 0.10 20 13.50 543.4
ST 42 42 356.26 0.60 0.60 0.40 20 13.50 556.9
ST 43 43 356.26 0.60 0.60 0.60 20 13.50 570.4
ST 44 44 356.26 0.60 0.60 0.90 20 13.50 583.9
ST 45 45 343.27 0.60 0.90 0.10 20 14.01 597.9
ST 46 46 343.27 0.60 0.90 0.40 20 14.01 611.9
ST 47 47 343.27 0.60 0.90 0.60 20 14.01 625.9
ST 48 48 343.27 0.60 0.90 0.90 20 14.01 639.9
ST 49 49 427.41 0.90 0.10 0.10 20 12.65 652.6
ST 50 50 427.41 0.90 0.10 0.40 20 12.65 665.2
ST 51 51 427.41 0.90 0.10 0.60 20 12.65 677.9
ST 52 52 427.41 0.90 0.10 0.90 20 12.65 690.5
ST 53 53 410.83 0.90 0.40 0.10 20 13.16 703.7
ST 54 54 410.83 0.90 0.40 0.40 20 13.16 716.9
ST 55 55 410.83 0.90 0.40 0.60 20 13.16 730.0
ST 56 56 410.83 0.90 0.40 0.90 20 13.16 743.2
ST 57 57 400.47 0.90 0.60 0.10 20 13.50 756.7
ST 58 58 400.47 0.90 0.60 0.40 20 13.50 770.2
ST 59 59 400.47 0.90 0.60 0.60 20 13.50 783.7
ST 60 60 400.47 0.90 0.60 0.90 20 13.50 797.2
ST 61 61 385.88 0.90 0.90 0.10 20 14.01 811.2
ST 62 62 385.88 0.90 0.90 0.40 20 14.01 825.2
ST 63 63 385.88 0.90 0.90 0.60 20 14.01 839.2
ST 64 64 385.88 0.90 0.90 0.90 20 14.01 853.2
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
PV 1 1 380.42 0.10 0.10 0.10 20 66.46 66.5
PV 2 2 380.42 0.10 0.10 0.40 20 66.46 132.9
PV 3 3 380.42 0.10 0.10 0.60 20 66.46 199.4
PV 4 4 380.42 0.10 0.10 0.90 20 66.46 265.8
PV 5 5 365.66 0.10 0.40 0.10 20 69.14 335.0
PV 6 6 365.66 0.10 0.40 0.40 20 69.14 404.1
PV 7 7 365.66 0.10 0.40 0.60 20 69.14 473.3
PV 8 8 365.66 0.10 0.40 0.90 20 69.14 542.4
PV 9 9 356.44 0.10 0.60 0.10 20 70.93 613.3
PV 10 10 356.44 0.10 0.60 0.40 20 70.93 684.3
PV 11 11 356.44 0.10 0.60 0.60 20 70.93 755.2
PV 12 12 356.44 0.10 0.60 0.90 20 70.93 826.1
PV 13 13 343.45 0.10 0.90 0.10 20 73.61 899.8
PV 14 14 343.45 0.10 0.90 0.40 20 73.61 973.4
PV 15 15 343.45 0.10 0.90 0.60 20 73.61 1,047.0
PV 16 16 343.45 0.10 0.90 0.90 20 73.61 1,120.6
PV 17 17 399.20 0.40 0.10 0.10 20 66.46 1,187.1
PV 18 18 399.20 0.40 0.10 0.40 20 66.46 1,253.5
PV 19 19 399.20 0.40 0.10 0.60 20 66.46 1,320.0
PV 20 20 399.20 0.40 0.10 0.90 20 66.46 1,386.4
PV 21 21 383.71 0.40 0.40 0.10 20 69.14 1,455.6
PV 22 22 383.71 0.40 0.40 0.40 20 69.14 1,524.7
PV 23 23 383.71 0.40 0.40 0.60 20 69.14 1,593.9
PV 24 24 383.71 0.40 0.40 0.90 20 69.14 1,663.0
PV 25 25 374.04 0.40 0.60 0.10 20 70.93 1,733.9
PV 26 26 374.04 0.40 0.60 0.40 20 70.93 1,804.9
PV 27 27 374.04 0.40 0.60 0.60 20 70.93 1,875.8
PV 28 28 374.04 0.40 0.60 0.90 20 70.93 1,946.7
PV 29 29 360.41 0.40 0.90 0.10 20 73.61 2,020.3
PV 30 30 360.41 0.40 0.90 0.40 20 73.61 2,094.0
PV 31 31 360.41 0.40 0.90 0.60 20 73.61 2,167.6
PV 32 32 360.41 0.40 0.90 0.90 20 73.61 2,241.2
PV 33 33 411.72 0.60 0.10 0.10 20 66.46 2,307.6
PV 34 34 411.72 0.60 0.10 0.40 20 66.46 2,374.1
PV 35 35 411.72 0.60 0.10 0.60 20 66.46 2,440.6
PV 36 36 411.72 0.60 0.10 0.90 20 66.46 2,507.0
PV 37 37 395.75 0.60 0.40 0.10 20 69.14 2,576.2
PV 38 38 395.75 0.60 0.40 0.40 20 69.14 2,645.3
PV 39 39 395.75 0.60 0.40 0.60 20 69.14 2,714.5
PV 40 40 395.75 0.60 0.40 0.90 20 69.14 2,783.6
PV 41 41 385.77 0.60 0.60 0.10 20 70.93 2,854.5
PV 42 42 385.77 0.60 0.60 0.40 20 70.93 2,925.5
PV 43 43 385.77 0.60 0.60 0.60 20 70.93 2,996.4
PV 44 44 385.77 0.60 0.60 0.90 20 70.93 3,067.3
PV 45 45 371.71 0.60 0.90 0.10 20 73.61 3,140.9
PV 46 46 371.71 0.60 0.90 0.40 20 73.61 3,214.5
PV 47 47 371.71 0.60 0.90 0.60 20 73.61 3,288.2
PV 48 48 371.71 0.60 0.90 0.90 20 73.61 3,361.8
PV 49 49 430.50 0.90 0.10 0.10 20 66.46 3,428.2
PV 50 50 430.50 0.90 0.10 0.40 20 66.46 3,494.7
PV 51 51 430.50 0.90 0.10 0.60 20 66.46 3,561.2
PV 52 52 430.50 0.90 0.10 0.90 20 66.46 3,627.6
PV 53 53 413.80 0.90 0.40 0.10 20 69.14 3,696.8
PV 54 54 413.80 0.90 0.40 0.40 20 69.14 3,765.9
PV 55 55 413.80 0.90 0.40 0.60 20 69.14 3,835.0
PV 56 56 413.80 0.90 0.40 0.90 20 69.14 3,904.2
PV 57 57 403.37 0.90 0.60 0.10 20 70.93 3,975.1
PV 58 58 403.37 0.90 0.60 0.40 20 70.93 4,046.0
PV 59 59 403.37 0.90 0.60 0.60 20 70.93 4,117.0
PV 60 60 403.37 0.90 0.60 0.90 20 70.93 4,187.9
PV 61 61 388.67 0.90 0.90 0.10 20 73.61 4,261.5
PV 62 62 388.67 0.90 0.90 0.40 20 73.61 4,335.1
PV 63 63 388.67 0.90 0.90 0.60 20 73.61 4,408.7
PV 64 64 388.67 0.90 0.90 0.90 20 73.61 4,482.4
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
WTE 1 1 95.21 0.10 0.10 0.10 20 6.58 6.6
WTE 2 2 95.21 0.10 0.10 0.40 20 6.58 13.2
WTE 3 3 95.21 0.10 0.10 0.60 20 6.58 19.8
WTE 4 4 95.21 0.10 0.10 0.90 20 6.58 26.3
WTE 5 5 81.39 0.10 0.40 0.10 20 7.70 34.0
WTE 6 6 81.39 0.10 0.40 0.40 20 7.70 41.7
WTE 7 7 81.39 0.10 0.40 0.60 20 7.70 49.4
WTE 8 8 81.39 0.10 0.40 0.90 20 7.70 57.1
WTE 9 9 74.21 0.10 0.60 0.10 20 8.45 65.6
WTE 10 10 74.21 0.10 0.60 0.40 20 8.45 74.0
WTE 11 11 74.21 0.10 0.60 0.60 20 8.45 82.5
WTE 12 12 74.21 0.10 0.60 0.90 20 8.45 90.9
WTE 13 13 65.54 0.10 0.90 0.10 20 9.57 100.5
WTE 14 14 65.54 0.10 0.90 0.40 20 9.57 110.1
WTE 15 15 65.54 0.10 0.90 0.60 20 9.57 119.6
WTE 16 16 65.54 0.10 0.90 0.90 20 9.57 129.2
WTE 17 17 140.82 0.40 0.10 0.10 20 6.58 135.8
WTE 18 18 140.82 0.40 0.10 0.40 20 6.58 142.4
WTE 19 19 140.82 0.40 0.10 0.60 20 6.58 148.9
WTE 20 20 140.82 0.40 0.10 0.90 20 6.58 155.5
WTE 21 21 120.38 0.40 0.40 0.10 20 7.70 163.2
WTE 22 22 120.38 0.40 0.40 0.40 20 7.70 170.9
WTE 23 23 120.38 0.40 0.40 0.60 20 7.70 178.6
WTE 24 24 120.38 0.40 0.40 0.90 20 7.70 186.3
WTE 25 25 109.76 0.40 0.60 0.10 20 8.45 194.8
WTE 26 26 109.76 0.40 0.60 0.40 20 8.45 203.2
WTE 27 27 109.76 0.40 0.60 0.60 20 8.45 211.7
WTE 28 28 109.76 0.40 0.60 0.90 20 8.45 220.1
WTE 29 29 96.93 0.40 0.90 0.10 20 9.57 229.7
WTE 30 30 96.93 0.40 0.90 0.40 20 9.57 239.3
WTE 31 31 96.93 0.40 0.90 0.60 20 9.57 248.8
WTE 32 32 96.93 0.40 0.90 0.90 20 9.57 258.4
WTE 33 33 171.22 0.60 0.10 0.10 20 6.58 265.0
WTE 34 34 171.22 0.60 0.10 0.40 20 6.58 271.6
WTE 35 35 171.22 0.60 0.10 0.60 20 6.58 278.1
WTE 36 36 171.22 0.60 0.10 0.90 20 6.58 284.7
WTE 37 37 146.37 0.60 0.40 0.10 20 7.70 292.4
WTE 38 38 146.37 0.60 0.40 0.40 20 7.70 300.1
WTE 39 39 146.37 0.60 0.40 0.60 20 7.70 307.8
WTE 40 40 146.37 0.60 0.40 0.90 20 7.70 315.5
WTE 41 41 133.45 0.60 0.60 0.10 20 8.45 324.0
WTE 42 42 133.45 0.60 0.60 0.40 20 8.45 332.4
WTE 43 43 133.45 0.60 0.60 0.60 20 8.45 340.9
WTE 44 44 133.45 0.60 0.60 0.90 20 8.45 349.3
WTE 45 45 117.86 0.60 0.90 0.10 20 9.57 358.9
WTE 46 46 117.86 0.60 0.90 0.40 20 9.57 368.4
WTE 47 47 117.86 0.60 0.90 0.60 20 9.57 378.0
WTE 48 48 117.86 0.60 0.90 0.90 20 9.57 387.6
WTE 49 49 216.83 0.90 0.10 0.10 20 6.58 394.2
WTE 50 50 216.83 0.90 0.10 0.40 20 6.58 400.7
WTE 51 51 216.83 0.90 0.10 0.60 20 6.58 407.3
WTE 52 52 216.83 0.90 0.10 0.90 20 6.58 413.9
WTE 53 53 185.35 0.90 0.40 0.10 20 7.70 421.6
WTE 54 54 185.35 0.90 0.40 0.40 20 7.70 429.3
WTE 55 55 185.35 0.90 0.40 0.60 20 7.70 437.0
WTE 56 56 185.35 0.90 0.40 0.90 20 7.70 444.7
WTE 57 57 169.00 0.90 0.60 0.10 20 8.45 453.2
WTE 58 58 169.00 0.90 0.60 0.40 20 8.45 461.6
WTE 59 59 169.00 0.90 0.60 0.60 20 8.45 470.1
WTE 60 60 169.00 0.90 0.60 0.90 20 8.45 478.5
WTE 61 61 149.25 0.90 0.90 0.10 20 9.57 488.1
WTE 62 62 149.25 0.90 0.90 0.40 20 9.57 497.6
WTE 63 63 149.25 0.90 0.90 0.60 20 9.57 507.2
WTE 64 64 149.25 0.90 0.90 0.90 20 9.57 516.8
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
Land 1 1 60.02 0.10 0.10 0.10 20 4.08 4.1
Land 2 2 60.02 0.10 0.10 0.40 20 4.08 8.2
Land 3 3 60.02 0.10 0.10 0.60 20 4.08 12.2
Land 4 4 60.02 0.10 0.10 0.90 20 4.08 16.3
Land 5 5 54.72 0.10 0.40 0.10 20 4.48 20.8
Land 6 6 54.72 0.10 0.40 0.40 20 4.48 25.3
Land 7 7 54.72 0.10 0.40 0.60 20 4.48 29.8
Land 8 8 54.72 0.10 0.40 0.90 20 4.48 34.2
Land 9 9 51.68 0.10 0.60 0.10 20 4.74 39.0
Land 10 10 51.68 0.10 0.60 0.40 20 4.74 43.7
Land 11 11 51.68 0.10 0.60 0.60 20 4.74 48.5
Land 12 12 51.68 0.10 0.60 0.90 20 4.74 53.2
Land 13 13 47.71 0.10 0.90 0.10 20 5.14 58.3
Land 14 14 47.71 0.10 0.90 0.40 20 5.14 63.5
Land 15 15 47.71 0.10 0.90 0.60 20 5.14 68.6
Land 16 16 47.71 0.10 0.90 0.90 20 5.14 73.8
Land 17 17 65.04 0.40 0.10 0.10 20 4.08 77.8
Land 18 18 65.04 0.40 0.10 0.40 20 4.08 81.9
Land 19 19 65.04 0.40 0.10 0.60 20 4.08 86.0
Land 20 20 65.04 0.40 0.10 0.90 20 4.08 90.1
Land 21 21 59.30 0.40 0.40 0.10 20 4.48 94.6
Land 22 22 59.30 0.40 0.40 0.40 20 4.48 99.0
Land 23 23 59.30 0.40 0.40 0.60 20 4.48 103.5
Land 24 24 59.30 0.40 0.40 0.90 20 4.48 108.0
Land 25 25 56.01 0.40 0.60 0.10 20 4.74 112.7
Land 26 26 56.01 0.40 0.60 0.40 20 4.74 117.5
Land 27 27 56.01 0.40 0.60 0.60 20 4.74 122.2
Land 28 28 56.01 0.40 0.60 0.90 20 4.74 127.0
Land 29 29 51.70 0.40 0.90 0.10 20 5.14 132.1
Land 30 30 51.70 0.40 0.90 0.40 20 5.14 137.2
Land 31 31 51.70 0.40 0.90 0.60 20 5.14 142.4
Land 32 32 51.70 0.40 0.90 0.90 20 5.14 147.5
Land 33 33 68.39 0.60 0.10 0.10 20 4.08 151.6
Land 34 34 68.39 0.60 0.10 0.40 20 4.08 155.7
Land 35 35 68.39 0.60 0.10 0.60 20 4.08 159.8
Land 36 36 68.39 0.60 0.10 0.90 20 4.08 163.8
Land 37 37 62.35 0.60 0.40 0.10 20 4.48 168.3
Land 38 38 62.35 0.60 0.40 0.40 20 4.48 172.8
Land 39 39 62.35 0.60 0.40 0.60 20 4.48 177.3
Land 40 40 62.35 0.60 0.40 0.90 20 4.48 181.7
Land 41 41 58.89 0.60 0.60 0.10 20 4.74 186.5
Land 42 42 58.89 0.60 0.60 0.40 20 4.74 191.2
Land 43 43 58.89 0.60 0.60 0.60 20 4.74 196.0
Land 44 44 58.89 0.60 0.60 0.90 20 4.74 200.7
Land 45 45 54.36 0.60 0.90 0.10 20 5.14 205.8
Land 46 46 54.36 0.60 0.90 0.40 20 5.14 211.0
Land 47 47 54.36 0.60 0.90 0.60 20 5.14 216.1
Land 48 48 54.36 0.60 0.90 0.90 20 5.14 221.3
Land 49 49 73.40 0.90 0.10 0.10 20 4.08 225.3
Land 50 50 73.40 0.90 0.10 0.40 20 4.08 229.4
Land 51 51 73.40 0.90 0.10 0.60 20 4.08 233.5
Land 52 52 73.40 0.90 0.10 0.90 20 4.08 237.6
Land 53 53 66.93 0.90 0.40 0.10 20 4.48 242.1
Land 54 54 66.93 0.90 0.40 0.40 20 4.48 246.5
Land 55 55 66.93 0.90 0.40 0.60 20 4.48 251.0
Land 56 56 66.93 0.90 0.40 0.90 20 4.48 255.5
Land 57 57 63.21 0.90 0.60 0.10 20 4.74 260.2
Land 58 58 63.21 0.90 0.60 0.40 20 4.74 265.0
Land 59 59 63.21 0.90 0.60 0.60 20 4.74 269.7
Land 60 60 63.21 0.90 0.60 0.90 20 4.74 274.5
Land 61 61 58.35 0.90 0.90 0.10 20 5.14 279.6
Land 62 62 58.35 0.90 0.90 0.40 20 5.14 284.7
Land 63 63 58.35 0.90 0.90 0.60 20 5.14 289.9
Land 64 64 58.35 0.90 0.90 0.90 20 5.14 295.0
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
Sew 1 1 98.33 0.10 0.10 0.10 20 1.69 1.7
Sew 2 2 98.33 0.10 0.10 0.40 20 1.69 3.4
Sew 3 3 98.33 0.10 0.10 0.60 20 1.69 5.1
Sew 4 4 98.33 0.10 0.10 0.90 20 1.69 6.8
Sew 5 5 89.66 0.10 0.40 0.10 20 1.85 8.6
Sew 6 6 89.66 0.10 0.40 0.40 20 1.85 10.5
Sew 7 7 89.66 0.10 0.40 0.60 20 1.85 12.3
Sew 8 8 89.66 0.10 0.40 0.90 20 1.85 14.2
Sew 9 9 84.68 0.10 0.60 0.10 20 1.96 16.1
Sew 10 10 84.68 0.10 0.60 0.40 20 1.96 18.1
Sew 11 11 84.68 0.10 0.60 0.60 20 1.96 20.1
Sew 12 12 84.68 0.10 0.60 0.90 20 1.96 22.0
Sew 13 13 78.16 0.10 0.90 0.10 20 2.13 24.1
Sew 14 14 78.16 0.10 0.90 0.40 20 2.13 26.3
Sew 15 15 78.16 0.10 0.90 0.60 20 2.13 28.4
Sew 16 16 78.16 0.10 0.90 0.90 20 2.13 30.5
Sew 17 17 111.80 0.40 0.10 0.10 20 1.69 32.2
Sew 18 18 111.80 0.40 0.10 0.40 20 1.69 33.9
Sew 19 19 111.80 0.40 0.10 0.60 20 1.69 35.6
Sew 20 20 111.80 0.40 0.10 0.90 20 1.69 37.3
Sew 21 21 101.93 0.40 0.40 0.10 20 1.85 39.1
Sew 22 22 101.93 0.40 0.40 0.40 20 1.85 41.0
Sew 23 23 101.93 0.40 0.40 0.60 20 1.85 42.8
Sew 24 24 101.93 0.40 0.40 0.90 20 1.85 44.7
Sew 25 25 96.27 0.40 0.60 0.10 20 1.96 46.7
Sew 26 26 96.27 0.40 0.60 0.40 20 1.96 48.6
Sew 27 27 96.27 0.40 0.60 0.60 20 1.96 50.6
Sew 28 28 96.27 0.40 0.60 0.90 20 1.96 52.6
Sew 29 29 88.87 0.40 0.90 0.10 20 2.13 54.7
Sew 30 30 88.87 0.40 0.90 0.40 20 2.13 56.8
Sew 31 31 88.87 0.40 0.90 0.60 20 2.13 58.9
Sew 32 32 88.87 0.40 0.90 0.90 20 2.13 61.1
Sew 33 33 120.78 0.60 0.10 0.10 20 1.69 62.7
Sew 34 34 120.78 0.60 0.10 0.40 20 1.69 64.4
Sew 35 35 120.78 0.60 0.10 0.60 20 1.69 66.1
Sew 36 36 120.78 0.60 0.10 0.90 20 1.69 67.8
Sew 37 37 110.12 0.60 0.40 0.10 20 1.85 69.7
Sew 38 38 110.12 0.60 0.40 0.40 20 1.85 71.5
Sew 39 39 110.12 0.60 0.40 0.60 20 1.85 73.4
Sew 40 40 110.12 0.60 0.40 0.90 20 1.85 75.2
Sew 41 41 104.00 0.60 0.60 0.10 20 1.96 77.2
Sew 42 42 104.00 0.60 0.60 0.40 20 1.96 79.2
Sew 43 43 104.00 0.60 0.60 0.60 20 1.96 81.1
Sew 44 44 104.00 0.60 0.60 0.90 20 1.96 83.1
Sew 45 45 96.00 0.60 0.90 0.10 20 2.13 85.2
Sew 46 46 96.00 0.60 0.90 0.40 20 2.13 87.3
Sew 47 47 96.00 0.60 0.90 0.60 20 2.13 89.5
Sew 48 48 96.00 0.60 0.90 0.90 20 2.13 91.6
Sew 49 49 134.24 0.90 0.10 0.10 20 1.69 93.3
Sew 50 50 134.24 0.90 0.10 0.40 20 1.69 95.0
Sew 51 51 134.24 0.90 0.10 0.60 20 1.69 96.7
Sew 52 52 134.24 0.90 0.10 0.90 20 1.69 98.3
Sew 53 53 122.40 0.90 0.40 0.10 20 1.85 100.2
Sew 54 54 122.40 0.90 0.40 0.40 20 1.85 102.0
Sew 55 55 122.40 0.90 0.40 0.60 20 1.85 103.9
Sew 56 56 122.40 0.90 0.40 0.90 20 1.85 105.8
Sew 57 57 115.60 0.90 0.60 0.10 20 1.96 107.7
Sew 58 58 115.60 0.90 0.60 0.40 20 1.96 109.7
Sew 59 59 115.60 0.90 0.60 0.60 20 1.96 111.6
Sew 60 60 115.60 0.90 0.60 0.90 20 1.96 113.6
Sew 61 61 106.70 0.90 0.90 0.10 20 2.13 115.7
Sew 62 62 106.70 0.90 0.90 0.40 20 2.13 117.9
Sew 63 63 106.70 0.90 0.90 0.60 20 2.13 120.0
Sew 64 64 106.70 0.90 0.90 0.90 20 2.13 122.1
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
Biogas 1 1 69.76 0.10 0.10 0.10 20 36.37 36.4
Biogas 2 2 69.76 0.10 0.10 0.40 20 36.37 72.7
Biogas 3 3 69.76 0.10 0.10 0.60 20 36.37 109.1
Biogas 4 4 69.76 0.10 0.10 0.90 20 36.37 145.5
Biogas 5 5 66.04 0.10 0.40 0.10 20 39.89 185.4
Biogas 6 6 66.04 0.10 0.40 0.40 20 39.89 225.2
Biogas 7 7 66.04 0.10 0.40 0.60 20 39.89 265.1
Biogas 8 8 66.04 0.10 0.40 0.90 20 39.89 305.0
Biogas 9 9 63.91 0.10 0.60 0.10 20 42.23 347.2
Biogas 10 10 63.91 0.10 0.60 0.40 20 42.23 389.5
Biogas 11 11 63.91 0.10 0.60 0.60 20 42.23 431.7
Biogas 12 12 63.91 0.10 0.60 0.90 20 42.23 473.9
Biogas 13 13 61.12 0.10 0.90 0.10 20 45.75 519.7
Biogas 14 14 61.12 0.10 0.90 0.40 20 45.75 565.4
Biogas 15 15 61.12 0.10 0.90 0.60 20 45.75 611.2
Biogas 16 16 61.12 0.10 0.90 0.90 20 45.75 656.9
Biogas 17 17 87.68 0.40 0.10 0.10 20 36.37 693.3
Biogas 18 18 87.68 0.40 0.10 0.40 20 36.37 729.7
Biogas 19 19 87.68 0.40 0.10 0.60 20 36.37 766.0
Biogas 20 20 87.68 0.40 0.10 0.90 20 36.37 802.4
Biogas 21 21 82.38 0.40 0.40 0.10 20 39.89 842.3
Biogas 22 22 82.38 0.40 0.40 0.40 20 39.89 882.2
Biogas 23 23 82.38 0.40 0.40 0.60 20 39.89 922.1
Biogas 24 24 82.38 0.40 0.40 0.90 20 39.89 961.9
Biogas 25 25 79.34 0.40 0.60 0.10 20 42.23 1,004.2
Biogas 26 26 79.34 0.40 0.60 0.40 20 42.23 1,046.4
Biogas 27 27 79.34 0.40 0.60 0.60 20 42.23 1,088.6
Biogas 28 28 79.34 0.40 0.60 0.90 20 42.23 1,130.9
Biogas 29 29 75.36 0.40 0.90 0.10 20 45.75 1,176.6
Biogas 30 30 75.36 0.40 0.90 0.40 20 45.75 1,222.4
Biogas 31 31 75.36 0.40 0.90 0.60 20 45.75 1,268.1
Biogas 32 32 75.36 0.40 0.90 0.90 20 45.75 1,313.9
Biogas 33 33 99.62 0.60 0.10 0.10 20 36.37 1,350.2
Biogas 34 34 99.62 0.60 0.10 0.40 20 36.37 1,386.6
Biogas 35 35 99.62 0.60 0.10 0.60 20 36.37 1,423.0
Biogas 36 36 99.62 0.60 0.10 0.90 20 36.37 1,459.3
Biogas 37 37 93.27 0.60 0.40 0.10 20 39.89 1,499.2
Biogas 38 38 93.27 0.60 0.40 0.40 20 39.89 1,539.1
Biogas 39 39 93.27 0.60 0.40 0.60 20 39.89 1,579.0
Biogas 40 40 93.27 0.60 0.40 0.90 20 39.89 1,618.9
Biogas 41 41 89.62 0.60 0.60 0.10 20 42.23 1,661.1
Biogas 42 42 89.62 0.60 0.60 0.40 20 42.23 1,703.3
Biogas 43 43 89.62 0.60 0.60 0.60 20 42.23 1,745.6
Biogas 44 44 89.62 0.60 0.60 0.90 20 42.23 1,787.8
Biogas 45 45 84.85 0.60 0.90 0.10 20 45.75 1,833.6
Biogas 46 46 84.85 0.60 0.90 0.40 20 45.75 1,879.3
Biogas 47 47 84.85 0.60 0.90 0.60 20 45.75 1,925.1
Biogas 48 48 84.85 0.60 0.90 0.90 20 45.75 1,970.8
Biogas 49 49 117.53 0.90 0.10 0.10 20 36.37 2,007.2
Biogas 50 50 117.53 0.90 0.10 0.40 20 36.37 2,043.5
Biogas 51 51 117.53 0.90 0.10 0.60 20 36.37 2,079.9
Biogas 52 52 117.53 0.90 0.10 0.90 20 36.37 2,116.3
Biogas 53 53 109.60 0.90 0.40 0.10 20 39.89 2,156.2
Biogas 54 54 109.60 0.90 0.40 0.40 20 39.89 2,196.0
Biogas 55 55 109.60 0.90 0.40 0.60 20 39.89 2,235.9
Biogas 56 56 109.60 0.90 0.40 0.90 20 39.89 2,275.8
Biogas 57 57 105.05 0.90 0.60 0.10 20 42.23 2,318.1
Biogas 58 58 105.05 0.90 0.60 0.40 20 42.23 2,360.3
Biogas 59 59 105.05 0.90 0.60 0.60 20 42.23 2,402.5
Biogas 60 60 105.05 0.90 0.60 0.90 20 42.23 2,444.7
Biogas 61 61 99.09 0.90 0.90 0.10 20 45.75 2,490.5
Biogas 62 62 99.09 0.90 0.90 0.40 20 45.75 2,536.2
Biogas 63 63 99.09 0.90 0.90 0.60 20 45.75 2,582.0
Biogas 64 64 99.09 0.90 0.90 0.90 20 45.75 2,627.8
Home
Cost Load Gen Cum Gen
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh
Biomass 1 1 78.52 0.10 0.10 0.10 20 53.36 53.4
Biomass 2 2 79.03 0.10 0.10 0.40 20 53.36 106.7
Biomass 3 3 79.37 0.10 0.10 0.60 20 53.36 160.1
Biomass 4 4 79.89 0.10 0.10 0.90 20 53.36 213.4
Biomass 5 5 71.99 0.10 0.40 0.10 20 62.42 275.8
Biomass 6 6 72.50 0.10 0.40 0.40 20 62.42 338.3
Biomass 7 7 72.84 0.10 0.40 0.60 20 62.42 400.7
Biomass 8 8 73.36 0.10 0.40 0.90 20 62.42 463.1
Biomass 9 9 68.59 0.10 0.60 0.10 20 68.46 531.5
Biomass 10 10 69.11 0.10 0.60 0.40 20 68.46 600.0
Biomass 11 11 69.45 0.10 0.60 0.60 20 68.46 668.5
Biomass 12 12 69.96 0.10 0.60 0.90 20 68.46 736.9
Biomass 13 13 64.49 0.10 0.90 0.10 20 77.52 814.4
Biomass 14 14 65.01 0.10 0.90 0.40 20 77.52 891.9
Biomass 15 15 65.35 0.10 0.90 0.60 20 77.52 969.5
Biomass 16 16 65.86 0.10 0.90 0.90 20 77.52 1,047.0
Biomass 17 17 80.85 0.40 0.10 0.10 20 53.36 1,100.3
Biomass 18 18 81.36 0.40 0.10 0.40 20 53.36 1,153.7
Biomass 19 19 81.71 0.40 0.10 0.60 20 53.36 1,207.0
Biomass 20 20 82.22 0.40 0.10 0.90 20 53.36 1,260.4
Biomass 21 21 73.98 0.40 0.40 0.10 20 62.42 1,322.8
Biomass 22 22 74.49 0.40 0.40 0.40 20 62.42 1,385.2
Biomass 23 23 74.84 0.40 0.40 0.60 20 62.42 1,447.6
Biomass 24 24 75.35 0.40 0.40 0.90 20 62.42 1,510.1
Biomass 25 25 70.41 0.40 0.60 0.10 20 68.46 1,578.5
Biomass 26 26 70.92 0.40 0.60 0.40 20 68.46 1,647.0
Biomass 27 27 71.27 0.40 0.60 0.60 20 68.46 1,715.4
Biomass 28 28 71.78 0.40 0.60 0.90 20 68.46 1,783.9
Biomass 29 29 66.10 0.40 0.90 0.10 20 77.52 1,861.4
Biomass 30 30 66.61 0.40 0.90 0.40 20 77.52 1,938.9
Biomass 31 31 66.95 0.40 0.90 0.60 20 77.52 2,016.4
Biomass 32 32 67.47 0.40 0.90 0.90 20 77.52 2,094.0
Biomass 33 33 82.41 0.60 0.10 0.10 20 53.36 2,147.3
Biomass 34 34 82.92 0.60 0.10 0.40 20 53.36 2,200.7
Biomass 35 35 83.26 0.60 0.10 0.60 20 53.36 2,254.0
Biomass 36 36 83.78 0.60 0.10 0.90 20 53.36 2,307.4
Biomass 37 37 75.31 0.60 0.40 0.10 20 62.42 2,369.8
Biomass 38 38 75.82 0.60 0.40 0.40 20 62.42 2,432.2
Biomass 39 39 76.17 0.60 0.40 0.60 20 62.42 2,494.6
Biomass 40 40 76.68 0.60 0.40 0.90 20 62.42 2,557.0
Biomass 41 41 71.62 0.60 0.60 0.10 20 68.46 2,625.5
Biomass 42 42 72.14 0.60 0.60 0.40 20 68.46 2,694.0
Biomass 43 43 72.48 0.60 0.60 0.60 20 68.46 2,762.4
Biomass 44 44 72.99 0.60 0.60 0.90 20 68.46 2,830.9
Biomass 45 45 67.17 0.60 0.90 0.10 20 77.52 2,908.4
Biomass 46 46 67.68 0.60 0.90 0.40 20 77.52 2,985.9
Biomass 47 47 68.03 0.60 0.90 0.60 20 77.52 3,063.4
Biomass 48 48 68.54 0.60 0.90 0.90 20 77.52 3,140.9
Biomass 49 49 84.74 0.90 0.10 0.10 20 53.36 3,194.3
Biomass 50 50 85.25 0.90 0.10 0.40 20 53.36 3,247.6
Biomass 51 51 85.60 0.90 0.10 0.60 20 53.36 3,301.0
Biomass 52 52 86.11 0.90 0.10 0.90 20 53.36 3,354.4
Biomass 53 53 77.30 0.90 0.40 0.10 20 62.42 3,416.8
Biomass 54 54 77.82 0.90 0.40 0.40 20 62.42 3,479.2
Biomass 55 55 78.16 0.90 0.40 0.60 20 62.42 3,541.6
Biomass 56 56 78.67 0.90 0.40 0.90 20 62.42 3,604.0
Biomass 57 57 73.44 0.90 0.60 0.10 20 68.46 3,672.5
Biomass 58 58 73.95 0.90 0.60 0.40 20 68.46 3,740.9
Biomass 59 59 74.30 0.90 0.60 0.60 20 68.46 3,809.4
Biomass 60 60 74.81 0.90 0.60 0.90 20 68.46 3,877.8
Biomass 61 61 68.77 0.90 0.90 0.10 20 77.52 3,955.4
Biomass 62 62 69.29 0.90 0.90 0.40 20 77.52 4,032.9
Biomass 63 63 69.63 0.90 0.90 0.60 20 77.52 4,110.4
Biomass 64 64 70.15 0.90 0.90 0.90 20 77.52 4,187.9
Home
Cost Load Gen Cum Gen CO2 emissions Cum CO2 Emissions Private Cost
Plant
$/MWh Inv Costs Factor Fuel Lifetime GWh GWh tn tn $/MWh
Co-gen 1 1 63.22 0.10 0.10 0.10 20 57.99 58.0 3,282 3,282 61.52
Co-gen 2 2 65.95 0.10 0.10 0.40 20 57.99 116.0 3,282 6,564 64.25
Co-gen 3 3 67.77 0.10 0.10 0.60 20 57.99 174.0 3,282 9,847 66.07
Co-gen 4 4 70.50 0.10 0.10 0.90 20 57.99 231.9 3,282 13,129 68.80
Co-gen 5 5 62.39 0.10 0.40 0.10 20 67.83 299.8 13,129 26,257 56.58
Co-gen 6 6 65.11 0.10 0.40 0.40 20 67.83 367.6 13,129 39,386 59.31
Co-gen 7 7 66.93 0.10 0.40 0.60 20 67.83 435.4 13,129 52,515 61.12
Co-gen 8 8 69.66 0.10 0.40 0.90 20 67.83 503.3 13,129 65,644 63.85
Co-gen 9 9 61.95 0.10 0.60 0.10 20 74.40 577.7 19,693 85,337 54.01
Co-gen 10 10 64.68 0.10 0.60 0.40 20 74.40 652.1 19,693 105,030 56.74
Co-gen 11 11 66.50 0.10 0.60 0.60 20 74.40 726.5 19,693 124,723 58.55
Co-gen 12 12 69.22 0.10 0.60 0.90 20 74.40 800.9 19,693 144,416 61.28
Co-gen 13 13 61.42 0.10 0.90 0.10 20 84.24 885.1 29,540 173,955 50.91
Co-gen 14 14 64.15 0.10 0.90 0.40 20 84.24 969.3 29,540 203,495 53.63
Co-gen 15 15 65.97 0.10 0.90 0.60 20 84.24 1,053.6 29,540 233,035 55.45
Co-gen 16 16 68.70 0.10 0.90 0.90 20 84.24 1,137.8 29,540 262,574 58.18
Co-gen 17 17 68.60 0.40 0.10 0.10 20 57.99 1,195.8 3,282 265,856 66.90
Co-gen 18 18 71.33 0.40 0.10 0.40 20 57.99 1,253.8 3,282 269,138 69.63
Co-gen 19 19 73.14 0.40 0.10 0.60 20 57.99 1,311.8 3,282 272,421 71.45
Co-gen 20 20 75.87 0.40 0.10 0.90 20 57.99 1,369.8 3,282 275,703 74.17
Co-gen 21 21 66.98 0.40 0.40 0.10 20 67.83 1,437.6 13,129 288,832 61.18
Co-gen 22 22 69.71 0.40 0.40 0.40 20 67.83 1,505.4 13,129 301,960 63.90
Co-gen 23 23 71.53 0.40 0.40 0.60 20 67.83 1,573.3 13,129 315,089 65.72
Co-gen 24 24 74.25 0.40 0.40 0.90 20 67.83 1,641.1 13,129 328,218 68.45
Co-gen 25 25 66.14 0.40 0.60 0.10 20 74.40 1,715.5 19,693 347,911 58.20
Co-gen 26 26 68.87 0.40 0.60 0.40 20 74.40 1,789.9 19,693 367,604 60.93
Co-gen 27 27 70.69 0.40 0.60 0.60 20 74.40 1,864.3 19,693 387,297 62.75
Co-gen 28 28 73.41 0.40 0.60 0.90 20 74.40 1,938.7 19,693 406,990 65.47
Co-gen 29 29 65.13 0.40 0.90 0.10 20 84.24 2,022.9 29,540 436,530 54.61
Co-gen 30 30 67.85 0.40 0.90 0.40 20 84.24 2,107.2 29,540 466,069 57.33
Co-gen 31 31 69.67 0.40 0.90 0.60 20 84.24 2,191.4 29,540 495,609 59.15
Co-gen 32 32 72.40 0.40 0.90 0.90 20 84.24 2,275.6 29,540 525,148 61.88
Co-gen 33 33 72.18 0.60 0.10 0.10 20 57.99 2,333.6 3,282 528,430 70.49
Co-gen 34 34 74.91 0.60 0.10 0.40 20 57.99 2,391.6 3,282 531,713 73.21
Co-gen 35 35 76.73 0.60 0.10 0.60 20 57.99 2,449.6 3,282 534,995 75.03
Co-gen 36 36 79.46 0.60 0.10 0.90 20 57.99 2,507.6 3,282 538,277 77.76
Co-gen 37 37 70.05 0.60 0.40 0.10 20 67.83 2,575.4 13,129 551,406 64.24
Co-gen 38 38 72.77 0.60 0.40 0.40 20 67.83 2,643.2 13,129 564,534 66.97
Co-gen 39 39 74.59 0.60 0.40 0.60 20 67.83 2,711.1 13,129 577,663 68.78
Co-gen 40 40 77.32 0.60 0.40 0.90 20 67.83 2,778.9 13,129 590,792 71.51
Co-gen 41 41 68.93 0.60 0.60 0.10 20 74.40 2,853.3 19,693 610,485 60.99
Co-gen 42 42 71.66 0.60 0.60 0.40 20 74.40 2,927.7 19,693 630,178 63.72
Co-gen 43 43 73.48 0.60 0.60 0.60 20 74.40 3,002.1 19,693 649,871 65.54
Co-gen 44 44 76.21 0.60 0.60 0.90 20 74.40 3,076.5 19,693 669,564 68.27
Co-gen 45 45 67.59 0.60 0.90 0.10 20 84.24 3,160.7 29,540 699,104 57.07
Co-gen 46 46 70.32 0.60 0.90 0.40 20 84.24 3,245.0 29,540 728,643 59.80
Co-gen 47 47 72.14 0.60 0.90 0.60 20 84.24 3,329.2 29,540 758,183 61.62
Co-gen 48 48 74.87 0.60 0.90 0.90 20 84.24 3,413.5 29,540 787,722 64.35
Co-gen 49 49 77.56 0.90 0.10 0.10 20 57.99 3,471.4 3,282 791,005 75.86
Co-gen 50 50 80.29 0.90 0.10 0.40 20 57.99 3,529.4 3,282 794,287 78.59
Co-gen 51 51 82.11 0.90 0.10 0.60 20 57.99 3,587.4 3,282 797,569 80.41
Co-gen 52 52 84.83 0.90 0.10 0.90 20 57.99 3,645.4 3,282 800,851 83.14
Co-gen 53 53 74.64 0.90 0.40 0.10 20 67.83 3,713.2 13,129 813,980 68.84
Co-gen 54 54 77.37 0.90 0.40 0.40 20 67.83 3,781.1 13,129 827,109 71.56
Co-gen 55 55 79.19 0.90 0.40 0.60 20 67.83 3,848.9 13,129 840,237 73.38
Co-gen 56 56 81.92 0.90 0.40 0.90 20 67.83 3,916.7 13,129 853,366 76.11
Co-gen 57 57 73.13 0.90 0.60 0.10 20 74.40 3,991.1 19,693 873,059 65.18
Co-gen 58 58 75.85 0.90 0.60 0.40 20 74.40 4,065.5 19,693 892,752 67.91
Co-gen 59 59 77.67 0.90 0.60 0.60 20 74.40 4,139.9 19,693 912,445 69.73
Co-gen 60 60 80.40 0.90 0.60 0.90 20 74.40 4,214.3 19,693 932,138 72.46
Co-gen 61 61 71.29 0.90 0.90 0.10 20 84.24 4,298.6 29,540 961,678 60.77
Co-gen 62 62 74.02 0.90 0.90 0.40 20 84.24 4,382.8 29,540 991,217 63.50
Co-gen 63 63 75.84 0.90 0.90 0.60 20 84.24 4,467.0 29,540 1,020,757 65.32
Co-gen 64 64 78.57 0.90 0.90 0.90 20 84.24 4,551.3 29,540 1,050,297 68.05
Home

Cost Load Cum Gen


Plant
$/MWh Inv Costs Factor Lifetime Gen GWh
Northen Areas Tormic Phase II 67.76 1,838 51% 20 68.00 68
Northen Areas Harpo Phase II 66.34 1,838 52% 20 67.64 136
Northwest Frontier Baral Darra 100.51 3,471 65% 20 48.67 184
Northen Areas Chhantir 73.14 1,838 47% 20 38.70 223
Sindh Sukkur 65.19 1,838 53% 20 35.11 258
Punjab Chenab/Marala 62.84 2,687 80% 20 37.84 296
Northwest Frontier Ushiri 84.65 3,008 66% 20 32.03 328
Northen Areas Sai Phase I 64.14 1,838 54% 20 49.29 377
Northen Areas Phandar-Chhashi Alt II 63.80 1,838 54% 20 57.58 435
Northen Areas Phandar-Chhashi Alt I 63.11 1,838 54% 20 57.74 493
Northwest Frontier Karora New 81.85 1,838 42% 20 25.75 518
Northen Areas Baru 62.38 1,838 55% 20 34.30 553
Northwest Frontier Rosh Gol, Alt 2 62.38 1,838 55% 20 36.21 589
Northwest Frontier Batal Khwar 57.29 1,838 60% 20 42.05 631
Northwest Frontier Bhimbal 61.42 1,838 56% 20 39.22 670
Northwest Frontier Mastuj River 2 60.85 1,838 56% 20 40.63 711
Punjab Chenab/Marala 60.81 1,838 57% 20 33.94 745
Northwest Frontier Barum Gol 75.22 1,838 46% 20 39.63 784
Northen Areas Sai Phase 59.05 1,838 58% 20 52.01 836
Northwest Frontier Chokel Khwar 75.22 1,838 46% 20 42.03 878
Punjab Chenab/Marala 73.18 2,710 69% 20 63.84 942
AJ & Kashmir Madar Butdara 51.61 1,838 67% 20 58.34 1,001
Punjab Chenab/Marala 60.02 1,838 57% 20 31.65 1,032
Punjab Chenab/Panjnad 156.25 1,838 22% 20 12.12 1,044
Northwest Frontier Lutkho River 405.73 12,903 59% 20 32.78 1,077
AJ & Kashmir Naghdar 51.45 1,838 67% 20 65.55 1,143
Northwest Frontier Y.I.A Golen 78.17 3,343 80% 20 79.19 1,222
Northwest Frontier Kedam Khwar 42.97 1,838 80% 20 44.85 1,267
Punjab Main Line Lower (Upper 105.04 4,492 80% 20 43.15 1,310
Northwest Frontier Turkho River, Alt 2 56.48 1,838 61% 20 51.18 1,361
Northwest Frontier Rosh Gol, Alt 1 42.97 1,838 80% 20 42.05 1,403
Punjab Chenab/Marala 56.13 1,838 61% 20 56.44 1,460
Punjab Chenab/Marala 55.96 1,838 61% 20 73.52 1,533
Punjab Indus/Chasma 87.24 3,731 80% 20 97.06 1,630
Northwest Frontier Bimbal 55.90 1,838 61% 20 75.42 1,706
AJ & Kashmir Doarian 55.81 1,838 62% 20 76.08 1,782
Punjab Chenab/Marala 55.69 1,838 62% 20 77.84 1,859
Northen Areas Naltar Phase III 62.50 1,838 55% 20 24.38 1,884
Northwest Frontier Damtour 65.87 2,817 80% 20 105.12 1,989
Northwest Frontier Balkanai 42.97 1,838 80% 20 35.04 2,024
Northwest Frontier Gande Gar 42.97 1,838 80% 20 35.04 2,059
Northwest Frontier Gomal Zam 64.59 2,172 63% 20 95.90 2,155
Northen Areas Parishing Phase III 61.75 2,077 63% 20 29.21 2,184
Northen Areas Skardu Phase-IV, AIt.II 60.72 2,042 63% 20 51.81 2,236
Northen Areas Naltar Phase V 54.56 1,838 63% 20 95.48 2,331
AJ & Kashmir Shontar 54.16 1,838 63% 20 111.21 2,443
Northen Areas Naltar IlI 54.09 1,838 64% 20 100.21 2,543
Northwest Frontier Ranolia 45.23 1,838 76% 20 76.56 2,619
Northwest Frontier Arkari Gol (Alt 1) 53.60 1,838 64% 20 134.83 2,754
AJ & Kashmir Luat 42.97 1,838 80% 20 168.89 2,923
Northwest Frontier Tank Zam 53.59 1,838 64% 20 143.30 3,066
Northwest Frontier Owir Gol 60.99 2,100 64% 20 15.63 3,082
Northwest Frontier Dadar 60.81 2,100 65% 20 22.07 3,104
Punjab Chenab/Marala 60.73 2,100 65% 20 18.13 3,122
Punjab Sutlej/Sulemanki 49.11 2,100 80% 20 29.43 3,152
Punjab Ravi/ Balloki 49.11 2,100 80% 20 21.72 3,173
Punjab Indus/Taunsa 60.28 2,100 65% 20 23.41 3,197
Punjab Lower bari doab 60.44 2,100 65% 20 24.48 3,221
Punjab Chenab/Trimmu 49.11 2,100 80% 20 16.82 3,238
Northwest Frontier Biar 59.15 2,100 66% 20 9.89 3,248
Punjab Ravi/ Balloki 70.15 2,100 56% 20 9.81 3,258
Northen Areas Rumboka 62.36 2,100 63% 20 8.83 3,267
Northen Areas Ishkuman 58.94 2,100 67% 20 10.51 3,277
Punjab Ravi/ Balloki 58.94 2,100 67% 20 7.88 3,285
Northen Areas Kar Gah Phase XI 85.97 2,100 46% 20 14.81 3,300
Punjab Chenab/Panjnad 66.01 2,365 67% 20 7.63 3,308
Punjab Chenab/Khanki 49.11 2,100 80% 20 11.56 3,319
Northen Areas Gulmiti 58.42 2,100 67% 20 9.43 3,328
Punjab Ravi/ Balloki 57.99 2,100 68% 20 15.43 3,344
Northwest Frontier Ayun 57.87 2,100 68% 20 29.46 3,373
AJ & Kashmir Taobat 57.70 2,100 68% 20 29.22 3,403
Punjab Chenab/Khanki 49.11 2,100 80% 20 33.64 3,436
Northen Areas Skardu Phase IV, AIt.I 57.06 2,100 69% 20 28.65 3,465
Punjab Ravi/ Balloki 57.04 2,100 69% 20 16.59 3,481
AJ & Kashmir Battar 57.04 2,100 69% 20 28.23 3,510
Northwest Frontier Garbral River 58.01 2,140 69% 20 28.24 3,538
Northen Areas Kar Gah Phase X 56.88 2,100 69% 20 8.47 3,546
Punjab Chenab/Marala 56.68 2,100 69% 20 27.69 3,574
Punjab Chenab/Marala 57.77 2,100 68% 20 17.57 3,592
Punjab Chenab/Marala 49.11 2,100 80% 20 31.39 3,623
Northen Areas Manthoka (Upgrade) 49.11 2,100 80% 20 5.26 3,628
Northwest Frontier Anakar gol 57.77 2,100 68% 20 4.53 3,633
Northen Areas Asambar 55.43 2,100 71% 20 8.07 3,641
Punjab Ravi/ Sidhuni 55.34 2,100 71% 20 26.34 3,667
Punjab Indus/Jinnah 55.34 2,100 71% 20 8.71 3,676
Northen Areas Basho Phase III 55.27 2,100 71% 20 25.57 3,702
Punjab Jhelum/Mangla 55.19 2,100 71% 20 9.35 3,711
Northen Areas Phultukish 72.07 2,100 55% 20 4.73 3,716
Punjab Chenab/Qadirabad 55.05 2,100 71% 20 25.27 3,741
Northen Areas Dichil 55.03 2,100 71% 20 25.01 3,766
Northwest Frontier Khghan (Alt 1) 54.97 2,100 71% 20 25.04 3,791
Northen Areas Jaglot Alt I 54.87 2,100 72% 20 23.77 3,815
Northen Areas Tangir Phase III 60.40 2,131 66% 20 21.39 3,836
Punjab Indus/Taunsa 54.85 2,100 72% 20 23.21 3,859
Northen Areas Lupghar 54.69 2,100 72% 20 3.96 3,863
Northen Areas Nolti (NAPWD) 54.56 2,100 72% 20 22.72 3,886
Punjab Chenab/Qadirabad 49.11 2,100 80% 20 24.53 3,911
Punjab Ravi/ Balloki 49.11 2,100 80% 20 24.53 3,935
Punjab Main line lower UCC 54.17 2,100 73% 20 21.95 3,957
Punjab Indus/Taunsa 49.11 2,100 80% 20 15.42 3,972
Punjab Main line lower UCC 53.96 2,100 73% 20 20.79 3,993
Northen Areas Bahushtaro Gol 49.11 2,100 80% 20 6.94 4,000
Northen Areas Basho Phase II 70.55 2,100 56% 20 15.61 4,016
Punjab Pakpattan Canal Upper 53.85 2,100 73% 20 20.45 4,036
Northwest Frontier Laspur River 53.78 2,100 73% 20 20.48 4,057
AJ & Kashmir Dakhari 53.78 2,100 73% 20 20.34 4,077
AJ & Kashmir Chamm Fall 53.76 2,100 73% 20 20.16 4,097
AJ & Kashmir Shahrian 49.11 2,100 80% 20 22.03 4,119
Punjab Ravi/ Balloki 64.91 2,776 80% 20 22.01 4,141
Punjab Sutlej/Islam 53.42 2,100 74% 20 19.97 4,161
Northen Areas Parishing Phase IV 49.11 2,100 80% 20 20.32 4,182
Punjab Jhelum/Mangla 53.26 2,100 74% 20 15.51 4,197
Northen Areas Sher Qila Phase II 53.26 2,100 74% 20 6.59 4,204
Northen Areas Boldas Phase II 53.08 2,100 74% 20 18.03 4,222
Northwest Frontier Chokel Khwawar 69.66 2,904 78% 20 6.08 4,228
Punjab Jhelum/Mangla 52.89 2,100 74% 20 13.66 4,241
Punjab Indus/Taunsa 52.89 2,100 74% 20 25.96 4,267
Northwest Frontier Naran 52.80 2,100 74% 20 17.99 4,285
Northwest Frontier Dardabahm Gol, Alt 3 52.43 2,100 75% 20 2.63 4,288
AJ & Kashmir Riali-II 49.11 2,100 80% 20 33.56 4,322
Northwest Frontier Rehmat Shah Sind 52.31 2,100 75% 20 5.66 4,327
Northen Areas Kar Gah Phase VIII 52.31 2,100 75% 20 9.21 4,336
Punjab Jhelum/Rasul 52.31 2,100 75% 20 6.97 4,343
Northen Areas Dahimal 52.26 2,100 75% 20 19.10 4,362
Punjab Jhelum/Mangla 52.20 2,100 75% 20 11.87 4,374
Punjab Chenab/Khanki 52.19 2,100 75% 20 10.55 4,385
Punjab Chenab/Panjnad 52.19 2,100 75% 20 28.66 4,414
Northwest Frontier Arkari Gol (Alt 2) 42.97 1,838 80% 20 185.01 4,599
Northwest Frontier Turkho River, Alt 1 50.14 2,021 75% 20 58.78 4,657
Northen Areas Bashu 45.60 1,849 76% 20 186.06 4,843
Northwest Frontier Machi Branch 47.24 2,020 80% 20 196.22 5,040
Punjab Chenab/Marala 51.68 2,100 76% 20 17.54 5,057
Northwest Frontier Rich Gol 68.83 2,100 57% 20 13.01 5,070
Punjab Jhelum/Rasul 51.42 2,100 76% 20 17.40 5,088
Northwest Frontier Tirich Gol, Alt 2 A 44.97 1,838 76% 20 80.35 5,168
Punjab Head Main Line Upper C 51.25 2,095 76% 20 41.53 5,209
Northwest Frontier Harban Gah, Harban 51.35 2,100 77% 20 6.03 5,215
Northen Areas Nomal 53.47 2,287 80% 20 17.52 5,233
Northwest Frontier Khelian Khwar 51.72 2,126 77% 20 16.84 5,250
Northen Areas Hispar Phase II 51.84 2,134 77% 20 16.87 5,267
AJ & Kashmir Dudainal 61.67 2,637 80% 20 210.24 5,477
Northwest Frontier Tirich Gol, Alt 1 A 42.97 1,838 80% 20 84.10 5,561
Northwest Frontier Chaudwan 51.84 2,134 77% 20 16.52 5,578
Northen Areas Gavis 52.23 2,161 77% 20 4.61 5,582
Northwest Frontier Chakosh Gol, Alt 1 52.23 2,161 77% 20 6.30 5,588
Punjab Jhelum/Mangla 52.23 2,161 77% 20 16.47 5,605
AJ & Kashmir Hotreri 52.45 2,175 78% 20 16.51 5,621
Punjab Lower Bari Doab 52.52 2,180 78% 20 16.32 5,638
Northen Areas Gainji 52.52 2,180 78% 20 15.92 5,654
Northwest Frontier DongaiGah 42.97 1,838 80% 20 224.26 5,878
Northen Areas Shushkati 50.52 2,100 78% 20 4.70 5,883
Northwest Frontier Swat River 52.65 2,188 78% 20 15.48 5,898
AJ & Kashmir Hajira 52.90 2,205 78% 20 15.51 5,914
Punjab Upper Gugera Br. 53.20 2,226 78% 20 15.55 5,929
Punjab Chenab/Marala 53.21 2,226 78% 20 11.31 5,941
Punjab Indus/Taunsa 53.22 2,227 78% 20 15.43 5,956
Northen Areas Harpo Phase II 53.30 2,232 78% 20 226.50 6,182
Northwest Frontier Kaghozi Gol (Alt 2) 53.43 2,241 78% 20 15.27 6,198
Northen Areas Talu 46.21 1,976 80% 20 56.76 6,254
Northwest Frontier Bhimbal 53.81 2,266 79% 20 14.79 6,269
Punjab Chenab/Trimmu 53.81 2,267 79% 20 14.79 6,284
Northen Areas Naltar Phase IV 53.90 2,272 79% 20 14.68 6,299
Northwest Frontier Tirich Gol, Alt 3A 53.93 2,275 79% 20 82.96 6,382
Punjab Chenab/Qadirabad 53.94 2,275 79% 20 14.64 6,396
Punjab Chenab/Qadirabad 49.11 2,100 80% 20 14.83 6,411
Northwest Frontier Jashil Gah, G1 54.11 2,287 79% 20 18.70 6,430
Punjab Jhelum/Rasul 54.21 2,294 79% 20 14.44 6,444
Northwest Frontier Serai, Karora 54.29 2,299 79% 20 93.70 6,538
Punjab Chenab/Qadirabad 49.11 2,100 80% 20 14.45 6,552
Northen Areas Sermik Phase II 54.53 2,316 79% 20 14.24 6,567
Northen Areas Doyian 54.63 2,323 80% 20 252.40 6,819
Northwest Frontier Birzin 54.64 2,323 80% 20 3.48 6,823
Punjab Chenab/Panjnad 54.79 2,333 80% 20 13.26 6,836
Punjab Indus/Taunsa 73.68 3,138 80% 20 13.96 6,850
Northen Areas Chhichi 54.86 2,338 80% 20 7.68 6,857
Northwest Frontier Ushiri (Alt 2) 54.10 2,311 80% 20 6.30 6,864
Punjab Chenab/Marala 55.52 2,374 80% 20 13.88 6,878
Northen Areas Sermik Phase III 55.64 2,379 80% 20 13.88 6,892
AJ & Kashmir Sharda 49.11 2,100 80% 20 13.68 6,905
Punjab Ravi/Balloki 57.43 2,456 80% 20 56.06 6,961
Northwest Frontier Kaghozi Gol (Alt 1) 49.11 2,100 80% 20 13.59 6,975
Northen Areas Hassanabad Phase VI 54.93 2,349 80% 20 12.61 6,988
AJ & Kashmir Gumot Nar 55.95 2,393 80% 20 280.32 7,268
Northwest Frontier Karora 55.95 2,393 80% 20 53.96 7,322
Punjab Chenab/Khanki 60.40 2,583 80% 20 12.93 7,335
Northwest Frontier Kao Gol, Alt 1 91.86 3,928 80% 20 12.85 7,348
Northen Areas Birgal 49.11 2,100 80% 20 5.61 7,353
Northen Areas Darel Phase IV 56.97 2,436 80% 20 12.61 7,366
Northwest Frontier Bumburet 57.01 2,438 80% 20 12.61 7,378
AJ & Kashmir Jagran-Il 57.21 2,446 80% 20 315.36 7,694
Northen Areas Dango Das 49.11 2,100 80% 20 3.50 7,697
Northen Areas Naltar Phase II 52.13 2,229 80% 20 5.26 7,703
Punjab Indus/Taunsa 57.49 2,458 80% 20 41.87 7,744
Northwest Frontier Seo Khwar 49.11 2,100 80% 20 4.98 7,749
Northen Areas Kar Gah Phase IX 49.11 2,100 80% 20 11.91 7,761
Northen Areas Tolti 49.11 2,100 80% 20 11.88 7,773
Northwest Frontier Koto 58.04 2,482 80% 20 126.14 7,899
Punjab Indus/Taunsa 58.04 2,482 80% 20 11.75 7,911
Punjab Chenab/Marala 58.04 2,482 80% 20 12.61 7,924
Northwest Frontier Ushiri (Alt 1) 58.57 2,504 80% 20 11.56 7,935
Northen Areas Hasis 59.10 2,527 80% 20 2.80 7,938
Northwest Frontier Murdan 49.11 2,100 80% 20 11.21 7,949
AJ & Kashmir Riali-I 59.21 2,532 80% 20 11.21 7,960
AJ & Kashmir Samani 59.46 2,543 80% 20 11.21 7,972
AJ & Kashmir Riali-I 59.61 2,549 80% 20 10.89 7,983
Northen Areas Sermik Phase III 59.93 2,563 80% 20 6.38 7,989
Punjab Sutlej/Islam 60.26 2,577 80% 20 10.58 7,999
Northen Areas Darel Phase III 49.11 2,100 80% 20 10.51 8,010
AJ & Kashmir Dghanwan 49.11 2,100 80% 20 10.37 8,020
Northwest Frontier Bangroan Khwar, Barigo 64.19 2,745 80% 20 10.29 8,031
Northen Areas Chilas Phase III 49.11 2,100 80% 20 4.91 8,036
Punjab Chenab/Qadirabad 60.50 2,587 80% 20 7.71 8,043
Punjab Sutlej/Islam 60.63 2,593 80% 20 10.11 8,053
Punjab Jhelum/Mangla 60.85 2,602 80% 20 9.94 8,063
Northen Areas Darmodar I 49.11 2,100 80% 20 12.05 8,075
Punjab Chenab/Marala 61.50 2,630 80% 20 32.73 8,108
Northen Areas Masholan Gol 61.51 2,630 80% 20 9.81 8,118
Northen Areas Balti 2 61.80 2,643 80% 20 9.74 8,128
Northen Areas Kustang 49.11 2,100 80% 20 3.99 8,132
Northwest Frontier Jashil Gah, Badakk 49.11 2,100 80% 20 9.63 8,141
Northwest Frontier Thal 61.90 2,647 80% 20 9.31 8,151
Punjab Chenab/Khanki 62.01 2,652 80% 20 9.30 8,160
Northen Areas Bahach Handrap HPP 62.10 2,655 80% 20 18.22 8,178
Punjab Chenab/Khanki 62.20 2,660 80% 20 9.16 8,187
Northen Areas Gulmiti Alt I 62.98 2,693 80% 20 9.11 8,196
Northen Areas Naz Bar 62.98 2,693 80% 20 9.06 8,205
Punjab Indus/Taunsa 63.46 2,714 80% 20 9.02 8,214
Punjab Sutlej/Sulemanki 63.71 2,724 80% 20 8.97 8,223
Northen Areas Damot 64.03 2,738 80% 20 4.91 8,228
Northwest Frontier Daral Khwar 64.05 2,739 80% 20 256.49 8,485
Northen Areas Bubind Phase II 64.25 2,748 80% 20 7.71 8,493
Northen Areas Aitit HPP 64.48 2,757 80% 20 252.29 8,745
Northwest Frontier Kaghan (Alt 2) 64.82 2,772 80% 20 8.62 8,753
Punjab Jhelum/Rasul 64.87 2,774 80% 20 8.62 8,762
Punjab Indus/Taunsa 64.89 2,775 80% 20 8.41 8,770
Punjab Ravi/ Balloki 64.93 2,776 80% 20 8.30 8,779
Punjab Ravi/ Balloki 64.94 2,777 80% 20 8.17 8,787
Punjab Indus/Taunsa 65.00 2,780 80% 20 8.16 8,795
Northen Areas Singal Phase II 59.82 2,558 80% 20 9.81 8,805
Punjab Indus/Jinnah 54.24 2,320 80% 20 8.08 8,813
Northen Areas Hashopi Phase II 62.72 2,682 80% 20 4.49 8,818
Sindh Sukkur 65.20 2,788 80% 20 157.75 8,975
Sindh Sukkur 65.20 2,788 80% 20 127.20 9,102
Northwest Frontier Jabori 65.29 2,792 80% 20 55.29 9,158
Punjab Chenab/Marala 64.65 2,765 80% 20 7.99 9,166
Northen Areas Chumar Khan Phase I 65.46 2,799 80% 20 6.59 9,172
Punjab Ravi/ Balloki 65.46 2,799 80% 20 7.64 9,180
Northwest Frontier Soyal Khwar (Alt 2) 65.52 2,802 80% 20 7.85 9,188
Punjab Chenab/Marala 65.65 2,807 80% 20 7.83 9,196
Punjab Ravi/ Balloki 65.65 2,807 80% 20 7.83 9,203
Northwest Frontier Sheringal 65.69 2,809 80% 20 4.98 9,208
Northwest Frontier Gandegah 65.71 2,810 80% 20 27.33 9,236
Punjab Jhelum/Mangla 49.11 2,100 80% 20 7.81 9,244
Punjab Indus/Jinnah 49.11 2,100 80% 20 7.81 9,251
Punjab Ravi/ Balloki 67.16 2,872 80% 20 7.79 9,259
Northen Areas Darel Phase V 67.16 2,872 80% 20 7.71 9,267
Northen Areas Roshan Alt.2 67.16 2,872 80% 20 7.71 9,275
Northen Areas Darmodar-2 67.16 2,872 80% 20 7.67 9,282
Northwest Frontier Patrak 67.16 2,872 80% 20 7.61 9,290
Punjab Jhelum/Mangla 67.16 2,872 80% 20 7.61 9,298
Northen Areas Chilas Phase IV 67.16 2,872 80% 20 4.20 9,302
Punjab Ravi/ Balloki 76.39 3,267 80% 20 7.59 9,309
Punjab Indus/Taunsa 49.11 2,100 80% 20 7.54 9,317
Punjab Ravi/ Balloki 49.11 2,100 80% 20 7.54 9,324
Punjab Indus/Taunsa 67.56 2,889 80% 20 7.53 9,332
Punjab Ravi/ Balloki 67.63 2,892 80% 20 7.52 9,339
Northen Areas Tangir Phase IV 80.75 3,453 80% 20 85.50 9,425
Northwest Frontier Chitral 67.91 2,904 80% 20 7.01 9,432
AJ & Kashmir Jari 68.10 2,912 80% 20 7.01 9,439
AJ & Kashmir Sarhota 68.15 2,914 80% 20 7.01 9,446
AJ & Kashmir Rerah 68.17 2,915 80% 20 7.01 9,453
AJ & Kashmir Pothi 64.52 2,759 80% 20 7.01 9,460
AJ & Kashmir Kotli Ban 68.58 2,933 80% 20 7.01 9,467
AJ & Kashmir Barar 50.92 2,178 80% 20 7.01 9,474
Punjab Sutlej/Sulemanki 68.78 2,941 80% 20 6.87 9,481
Punjab Ravi/ Balloki 68.85 2,944 80% 20 6.85 9,488
Punjab Sutlej/Islam 68.92 2,947 80% 20 6.76 9,494
Punjab Sutlej/Islam 58.82 2,515 80% 20 6.70 9,501
Punjab Indus/Taunsa 50.11 2,143 80% 20 6.69 9,508
Punjab Indus/Jinnah 54.26 2,321 80% 20 6.68 9,515
Punjab Sutlej/Sulemanki 49.11 2,100 80% 20 6.55 9,521
Northen Areas Ghoro 69.68 2,980 80% 20 3.08 9,524
Punjab Chenab/Marala 70.08 2,997 80% 20 6.49 9,531
Northwest Frontier Bela 70.13 2,999 80% 20 19.62 9,550
Punjab Sutlej/Sulemanki 49.11 2,100 80% 20 6.47 9,557
Punjab Chenab/Marala 70.56 3,017 80% 20 6.45 9,563
AJ & Kashmir Jing 101.10 4,324 80% 20 24.63 9,588
Punjab Chenab/Khanki 70.77 3,026 80% 20 6.22 9,594
Punjab Chenab/Khanki 71.03 3,037 80% 20 6.11 9,600
Punjab Jhelum/Mangla 71.21 3,045 80% 20 6.10 9,606
Northwest Frontier Summer Gah 70.67 3,022 80% 20 196.22 9,802
Northen Areas Daintar 71.54 3,059 80% 20 28.73 9,831
Punjab Indus/Jinnah 71.81 3,071 80% 20 5.98 9,837
Northen Areas Shigar Phase III 55.86 2,389 80% 20 5.75 9,843
Punjab Indus/Jinnah 115.18 4,926 80% 20 5.92 9,849
Punjab Indus/Jinnah 102.57 4,386 80% 20 5.85 9,855
Punjab Chenab/Khanki 72.38 3,095 80% 20 5.80 9,861
Punjab Chenab/Khanki 72.43 3,097 80% 20 5.72 9,866
Punjab Indus/Chasma 72.93 3,119 80% 20 5.65 9,872
AJ & Kashmir Jana Wai 49.11 2,100 80% 20 33.64 9,906
Punjab Indus/Jinnah 73.14 3,128 80% 20 5.51 9,911
Punjab Indus/Chasma 73.20 3,130 80% 20 5.49 9,917
Punjab Chenab/Trimmu 73.20 3,130 80% 20 5.38 9,922
Northen Areas Narh 73.35 3,137 80% 20 2.87 9,925
Northwest Frontier Dongai Gah, Jalkot Nalla 128.33 5,488 80% 20 5.33 9,930
Northen Areas Gulmiti Alt II 49.11 2,100 80% 20 3.50 9,934
Northen Areas Kachura Phase V 55.98 2,394 80% 20 126.14 10,060
Punjab Indus/Jinnah 89.92 3,845 80% 20 5.31 10,065
Punjab Ravi/ Balloki 73.74 3,154 80% 20 5.31 10,070
Punjab Indus/Taunsa 73.74 3,154 80% 20 5.28 10,076
Punjab Chenab/Marala 74.13 3,170 80% 20 13.67 10,089
Northwest Frontier Kapar Banda Gah 74.31 3,178 80% 20 5.19 10,094
Punjab Sutlej/Islam 74.57 3,189 80% 20 5.19 10,100
Punjab Chenab/Khanki 56.38 2,411 80% 20 5.10 10,105
Punjab Indus/Jinnah 64.90 2,775 80% 20 5.06 10,110
Punjab Jhelum/Rasul 74.86 3,201 80% 20 5.00 10,115
Punjab Chenab/Marala 59.63 2,550 80% 20 4.94 10,120
AJ & Kashmir Sarswah 62.44 2,670 80% 20 4.91 10,125
Punjab Ravi/Balloki 75.03 3,208 80% 20 4.86 10,130
Northen Areas Chalt Phase III 75.23 3,217 80% 20 3.57 10,133
Northen Areas Kiris AIt.2- Phase II 51.95 2,222 80% 20 3.99 10,137
Punjab Chenab/Khanki 75.40 3,224 80% 20 4.83 10,142
Punjab Sutlej/Sulemanki 75.40 3,224 80% 20 4.83 10,147
Northen Areas Serbal Gol 50.91 2,177 80% 20 3.57 10,150
Punjab Sutlej/Islam 75.78 3,240 80% 20 4.75 10,155
Punjab Jhelum/Mangla 75.81 3,242 80% 20 4.74 10,160
Punjab Indus/Taunsa 76.02 3,251 80% 20 4.70 10,165
Punjab Jhelum/Mangla 317.66 12,565 74% 20 4.29 10,169
Northen Areas Karapchu 76.34 3,265 80% 20 6.94 10,176
Northwest Frontier Soyal Khwar (Alt 1) 76.41 3,268 80% 20 4.63 10,180
Punjab Chenab/Khanki 76.63 3,277 80% 20 4.58 10,185
Punjab Chenab/Qadirabad 64.45 2,756 80% 20 4.48 10,189
Punjab Indus/Taunsa 77.18 3,301 80% 20 4.41 10,194
Northen Areas Nasirabad HPP 45.21 1,933 80% 20 107.22 10,301
Punjab Chenab/Marala 120.82 5,167 80% 20 4.29 10,305
Northen Areas Roshan AIt.1 77.56 3,317 80% 20 4.27 10,310
Punjab Indus/Taunsa 78.22 3,345 80% 20 4.24 10,314
Punjab Ravi/ Balloki 78.30 3,349 80% 20 4.23 10,318
Northen Areas Damiodar (HEPO) 78.50 3,357 80% 20 4.20 10,322
Punjab Chenab/Khanki 78.54 3,359 80% 20 4.13 10,326
Punjab Chenab/Marala 65.48 2,800 80% 20 4.11 10,331
Punjab Ravi/Balloki 78.71 3,366 80% 20 4.02 10,335
Northen Areas Chumar Khan Phase II 84.17 3,599 80% 20 2.59 10,337
Punjab Chenab/Trimmu 79.12 3,383 80% 20 3.94 10,341
Punjab Sutlej/Sulemanki 79.24 3,389 80% 20 3.93 10,345
Punjab Chenab/Marala 79.84 3,414 80% 20 3.92 10,349
Northen Areas Sai Phase II 60.74 2,597 80% 20 6.80 10,356
Punjab Ravi/ Sidhuni 75.38 3,224 80% 20 3.80 10,360
Punjab Chenab/Marala 90.46 3,868 80% 20 3.76 10,363
Punjab Sutlej/Sulemanki 80.32 3,435 80% 20 3.76 10,367
Punjab Chenab/Khanki 80.37 3,437 80% 20 3.67 10,371
Punjab Chenab/Panjnad 86.82 3,713 80% 20 3.62 10,374
Northen Areas Bulashbar 80.46 3,441 80% 20 3.50 10,378
Northen Areas Gupis 81.23 3,474 80% 20 3.57 10,381
Punjab Ravi/ Sidhuni 81.51 3,486 80% 20 3.57 10,385
Punjab Sutlej/Sulemanki 81.51 3,486 80% 20 3.54 10,389
Northen Areas Sosat 82.09 3,510 80% 20 3.43 10,392
Northwest Frontier Kumrat 82.43 3,525 80% 20 4.13 10,396
Punjab Sutlej/Sulemanki 75.59 3,232 80% 20 3.38 10,400
Punjab Indus/Jinnah 75.37 3,129 78% 20 3.28 10,403
Punjab Chenab/Khanki 82.78 3,540 80% 20 3.37 10,406
Northen Areas Thali Alt I 82.78 3,540 80% 20 238.27 10,644
Punjab Ravi/ Sidhuni 83.04 3,551 80% 20 3.22 10,648
Punjab Sutlej/Sulemanki 55.98 2,394 80% 20 3.20 10,651
Punjab Indus/Jinnah 73.17 3,129 80% 20 3.17 10,654
Northen Areas Balti-1 82.50 3,528 80% 20 3.08 10,657
Northen Areas Thang 53.94 2,307 80% 20 3.92 10,661
Northen Areas Harchu 83.82 3,584 80% 20 2.80 10,664
Northen Areas Hamuchal HPP 84.19 3,600 80% 20 98.11 10,762
Punjab Chenab/Khanki 84.25 3,603 80% 20 3.01 10,765
Northen Areas Niaslo 84.30 3,605 80% 20 2.38 10,767
Punjab Indus/Taunsa 104.09 4,451 80% 20 2.96 10,770
Punjab Sutlej/Sulemanki 125.44 5,364 80% 20 2.95 10,773
Punjab Indus/Taunsa 109.96 4,702 80% 20 2.92 10,776
Northen Areas Nero Phase II 85.48 3,655 80% 20 2.87 10,779
Punjab Ravi/Balloki 85.71 3,665 80% 20 2.87 10,782
Punjab Jhelum/Mangla 85.89 3,673 80% 20 2.85 10,785
Punjab Jhelum/Rasul 102.14 4,368 80% 20 2.84 10,788
Punjab Sutlej/Sulemanki 93.75 4,009 80% 20 2.83 10,790
Punjab Chenab/Khanki 68.64 2,935 80% 20 2.81 10,793
Punjab Jhelum/Rasul 86.67 3,706 80% 20 2.79 10,796
Punjab Chenab/Trimmu 87.35 3,735 80% 20 2.77 10,799
Northen Areas Daltar HPP 87.73 3,752 80% 20 5.19 10,804
Punjab Chenab/Marala 87.86 3,757 80% 20 2.73 10,807
Punjab Sutlej/Sulemanki 88.12 3,768 80% 20 2.73 10,809
Punjab Sutlej/Sulemanki 73.06 3,124 80% 20 2.72 10,812
Northen Areas Thagas 88.63 3,790 80% 20 3.99 10,816
Punjab Chenab/Trimmu 88.66 3,791 80% 20 2.63 10,819
Punjab Chenab/Khanki 88.79 3,797 80% 20 2.62 10,821
Punjab Ravi/ Sidhuni 88.93 3,803 80% 20 2.62 10,824
Punjab Sutlej/Sulemanki 88.99 3,806 80% 20 2.59 10,827
Punjab Chenab/Marala 89.20 3,815 80% 20 11.91 10,839
Punjab Sutlej/Sulemanki 98.22 4,200 80% 20 2.55 10,841
Punjab Indus/Jinnah 93.30 3,990 80% 20 2.54 10,844
Punjab Chenab/Trimmu 87.17 3,728 80% 20 2.52 10,846
Punjab Sutlej/Sulemanki 57.70 2,468 80% 20 2.50 10,849
Punjab Chenab/Khanki 49.11 2,100 80% 20 2.49 10,851
Punjab Chenab/Panjnad 89.41 3,823 80% 20 2.47 10,854
Punjab Chenab/Trimmu 89.62 3,832 80% 20 2.47 10,856
Northen Areas Olding Phase II 93.74 4,009 80% 20 2.80 10,859
Punjab Chenab/Marala 97.59 4,173 80% 20 2.41 10,861
Punjab Indus/Jinnah 90.02 3,849 80% 20 2.40 10,864
Punjab Ravi/ Balloki 90.05 3,851 80% 20 2.40 10,866
Northen Areas Burzil Alt II 90.12 3,854 80% 20 2.73 10,869
Northen Areas Mngio HPP 108.55 4,642 80% 20 3.08 10,872
Punjab Ravi/ Balloki 91.08 3,895 80% 20 2.38 10,874
Punjab Chenab/Marala 91.15 3,898 80% 20 2.31 10,877
Punjab Indus/Taunsa 91.15 3,898 80% 20 2.28 10,879
Punjab Chenab/Khanki 112.81 4,824 80% 20 2.28 10,881
Punjab Ravi/ Sidhuni 80.30 3,434 80% 20 2.26 10,883
Northen Areas Muduli 91.54 3,914 80% 20 2.24 10,886
Punjab Ravi/ Balloki 91.92 3,931 80% 20 2.23 10,888
Northen Areas Buniyal 92.00 3,934 80% 20 2.24 10,890
Punjab Chenab/Khanki 92.24 3,944 80% 20 2.21 10,892
Punjab Ravi/ Balloki 92.48 3,955 80% 20 2.18 10,895
Punjab Jhelum/Mangla 92.56 3,958 80% 20 2.17 10,897
Punjab Chenab/Marala 92.80 3,969 80% 20 2.12 10,899
Northen Areas Hoh 92.89 3,972 80% 20 2.73 10,902
Punjab Indus/Taunsa 93.55 4,001 80% 20 2.10 10,904
Punjab Chenab/Khanki 93.72 4,008 80% 20 2.09 10,906
Punjab Indus/Jinnah 93.72 4,008 80% 20 2.09 10,908
Punjab Jhelum/Rasul 87.38 3,737 80% 20 2.07 10,910
Northen Areas Hassanabad Phase VII 93.89 4,015 80% 20 2.80 10,913
Punjab Ravi/ Sidhuni 213.31 4,773 42% 20 1.07 10,914
Punjab Sutlej/Sulemanki 94.77 4,053 80% 20 2.05 10,916
Punjab Sutlej/Sulemanki 95.13 4,068 80% 20 2.03 10,918
Punjab Chenab/Khanki 95.22 4,072 80% 20 2.00 10,920
Punjab Chenab/Khanki 95.40 4,080 80% 20 2.00 10,922
Punjab Chenab/Trimmu 95.91 4,102 80% 20 1.99 10,924
Punjab Ravi/Balloki 95.68 4,091 80% 20 1.98 10,926
Punjab Chenab/Khanki 95.86 4,099 80% 20 1.98 10,928
Punjab Jhelum/Rasul 96.05 4,107 80% 20 1.97 10,930
Punjab Ravi/ Sidhuni 96.53 4,128 80% 20 1.96 10,932
Punjab Chenab/Khanki 104.55 4,471 80% 20 1.91 10,934
Northen Areas Thali Alt II 96.72 4,136 80% 20 272.61 11,206
Punjab Chenab/Khanki 97.41 4,166 80% 20 1.89 11,208
Northen Areas Derdi 119.49 5,110 80% 20 5.96 11,214
Punjab Chenab/Khanki 97.61 4,174 80% 20 1.84 11,216
Punjab Indus/Chasma 97.80 4,182 80% 20 1.83 11,218
Northwest Frontier Dir Alt No.1 97.82 4,183 80% 20 3.15 11,221
Punjab Ravi/ Sidhuni 98.13 4,196 80% 20 1.82 11,223
Punjab Chenab/Trimmu 98.33 4,205 80% 20 1.81 11,225
Punjab Chenab/Khanki 98.33 4,205 80% 20 1.80 11,226
Northen Areas Brodas 98.75 4,223 80% 20 5.54 11,232
Punjab Sutlej/Sulemanki 99.13 4,239 80% 20 1.75 11,234
Punjab Indus/Jinnah 99.18 4,241 80% 20 1.72 11,235
Northen Areas Aspai Alt-II 99.29 4,246 80% 20 3.22 11,239
Punjab Chenab/Khanki 99.40 4,251 80% 20 1.70 11,240
Punjab Ravi/ Balloki 99.42 4,252 80% 20 1.69 11,242
Northen Areas Mian HPP 99.62 4,260 80% 20 2.17 11,244
Punjab Chenab/Trimmu 99.73 4,265 80% 20 1.68 11,246
Punjab Chenab/Khanki 100.49 4,297 80% 20 1.67 11,248
Northen Areas Henzal HPP 100.98 4,318 80% 20 105.12 11,353
Punjab Jhelum/Rasul 101.81 4,354 80% 20 1.64 11,354
Punjab Jhelum/Rasul 101.93 4,359 80% 20 1.63 11,356
Punjab Chenab/Khanki 120.88 5,169 80% 20 1.63 11,358
Punjab Sutlej/Sulemanki 102.17 4,369 80% 20 1.63 11,359
Punjab Sutlej/Sulemanki 102.30 4,375 80% 20 1.58 11,361
Punjab Chenab/Marala 102.42 4,380 80% 20 1.57 11,362
Punjab Chenab/Panjnad 103.30 4,418 80% 20 1.56 11,364
Punjab Chenab/Khanki 103.82 4,440 80% 20 1.52 11,365
Northen Areas Sumayar Phase II 104.35 4,462 80% 20 2.66 11,368
Punjab Chenab/Marala 104.48 4,468 80% 20 1.49 11,370
Punjab Chenab/Khanki 205.12 8,772 80% 20 1.46 11,371
Punjab Jhelum/Rasul 134.04 5,732 80% 20 1.46 11,372
Punjab Ravi/ Sidhuni 104.62 4,474 80% 20 1.46 11,374
Punjab Chenab/Khanki 104.89 4,486 80% 20 1.45 11,375
Punjab Sutlej/Sulemanki 105.45 4,509 80% 20 1.44 11,377
Punjab Jhelum/Mangla 105.59 4,515 80% 20 1.44 11,378
Punjab Sutlej/Sulemanki 105.73 4,521 80% 20 1.44 11,380
Northen Areas Zhojat Gol 105.73 4,521 80% 20 3.22 11,383
Punjab Ravi/ Sidhuni 136.65 5,843 80% 20 1.41 11,384
AJ & Kashmir Patni 106.59 4,558 80% 20 1.40 11,386
Punjab Sutlej/Sulemanki 106.89 4,571 80% 20 1.39 11,387
Punjab Chenab/Trimmu 107.03 4,577 80% 20 1.37 11,389
Punjab Sutlej/Sulemanki 107.95 4,616 80% 20 1.34 11,390
Punjab Chenab/Khanki 108.57 4,643 80% 20 1.32 11,391
Northen Areas Kilik 160.18 6,850 80% 20 2.59 11,394
Punjab Chenab/Marala 179.56 7,679 80% 20 1.31 11,395
Northwest Frontier Lower Thal 109.21 4,670 80% 20 5.61 11,401
Punjab Chenab/Khanki 109.21 4,670 80% 20 1.22 11,402
Punjab Chenab/Khanki 109.21 4,670 80% 20 1.22 11,403
Punjab Ravi/ Sidhuni 109.44 4,680 80% 20 1.20 11,404
Punjab Jhelum/Rasul 109.70 4,691 80% 20 1.19 11,406
Punjab Jhelum/Rasul 109.87 4,698 80% 20 1.17 11,407
Punjab Chenab/Khanki 109.87 4,698 80% 20 1.16 11,408
Punjab Ravi/Balloki 110.54 4,727 80% 20 1.12 11,409
Punjab Ravi/ Sidhuni 110.72 4,735 80% 20 1.11 11,410
Punjab Jhelum/Rasul 110.89 4,742 80% 20 1.11 11,411
Northen Areas Hayul (Chatorkhand) 111.41 4,764 80% 20 2.10 11,413
Punjab Sutlej/Sulemanki 112.31 4,803 80% 20 1.09 11,414
Punjab Jhelum/Mangla 112.68 4,818 80% 20 1.07 11,415
Punjab Jhelum/Mangla 113.05 4,834 80% 20 1.07 11,417
Punjab Sutlej/Sulemanki 115.61 4,944 80% 20 1.07 11,418
Northen Areas Shirting Phase II 115.67 4,946 80% 20 4.42 11,422
Northen Areas Rama Phase II 116.24 4,971 80% 20 1.82 11,424
Punjab Jhelum/Rasul 145.88 6,238 80% 20 1.04 11,425
Punjab Ravi/ Balloki 135.77 5,806 80% 20 1.03 11,426
Punjab Indus/Jinnah 116.45 4,980 80% 20 1.00 11,427
Punjab Ravi/Balloki 117.09 5,007 80% 20 0.95 11,428
Northen Areas Mehdiabad 117.31 5,017 80% 20 3.22 11,431
Punjab Chenab/Khanki 224.05 9,581 80% 20 0.91 11,432
Punjab Chenab/Khanki 118.66 5,074 80% 20 0.90 11,433
Punjab Ravi/ Sidhuni 118.89 5,084 80% 20 0.88 11,434
Punjab Chenab/Khanki 118.89 5,084 80% 20 0.88 11,435
Northen Areas Gidiaksdo 119.60 5,114 80% 20 5.26 11,440
Punjab Chenab/Khanki 120.57 5,156 80% 20 0.82 11,441
Punjab Chenab/Khanki 120.57 5,156 80% 20 0.81 11,442
Punjab Sutlej/Sulemanki 120.57 5,156 80% 20 0.81 11,442
Punjab Ravi/Balloki 153.87 6,580 80% 20 0.81 11,443
Punjab Chenab/Khanki 232.44 9,940 80% 20 0.80 11,444
Punjab Chenab/Khanki 121.57 5,199 80% 20 0.77 11,445
Northwest Frontier Pehur 121.83 5,210 80% 20 126.14 11,571
Northwest Frontier Kolandai 122.87 5,254 80% 20 1.68 11,573
Punjab Sutlej/Sulemanki 149.08 6,375 80% 20 0.75 11,573
Punjab Sutlej/Sulemanki 199.94 8,550 80% 20 0.73 11,574
Northen Areas Nero Phase I 215.72 9,225 80% 20 1.19 11,575
Northen Areas Minapin Phase III 136.80 5,850 80% 20 1.61 11,577
Northen Areas Amni 124.80 5,337 80% 20 0.98 11,578
Punjab Chenab/Khanki 200.21 8,562 80% 20 0.68 11,578
Punjab Sutlej/Sulemanki 181.32 7,754 80% 20 0.64 11,579
Punjab Chenab/Marala 126.57 5,412 80% 20 0.64 11,580
Punjab Indus/Jinnah 127.18 5,438 80% 20 0.64 11,580
Punjab Chenab/Khanki 127.80 5,465 80% 20 0.61 11,581
Northen Areas Khaiber Phase II 128.12 5,479 80% 20 1.19 11,582
Punjab Sutlej/Sulemanki 210.75 9,013 80% 20 0.57 11,583
Punjab Chenab/Khanki 215.77 9,227 80% 20 0.54 11,583
Northen Areas Burzil Alt I 130.67 5,588 80% 20 0.98 11,584
Punjab Ravi/Balloki 131.13 5,607 80% 20 0.53 11,585
Punjab Indus/Jinnah 131.13 5,607 80% 20 0.50 11,585
Punjab Chenab/Khanki 131.48 5,622 80% 20 0.49 11,586
Northen Areas Rattu Phase II 131.84 5,638 80% 20 1.05 11,587
Punjab Chenab/Khanki 133.16 5,694 80% 20 0.48 11,587
Punjab Chenab/Khanki 134.46 5,750 80% 20 0.47 11,588
Punjab Chenab/Khanki 135.65 5,801 80% 20 0.47 11,588
Punjab Chenab/Marala 138.79 5,935 80% 20 0.46 11,589
Punjab Chenab/Marala 140.91 6,026 80% 20 0.45 11,589
Northen Areas Phakor 141.30 6,042 80% 20 1.47 11,591
Punjab Ravi/ Balloki 141.39 6,046 80% 20 0.41 11,591
Punjab Chenab/Khanki 143.13 6,121 80% 20 0.40 11,591
Punjab Chenab/Khanki 146.04 6,245 80% 20 0.39 11,592
Punjab Indus/Jinnah 149.04 6,374 80% 20 0.37 11,592
Punjab Chenab/Khanki 149.53 6,394 80% 20 0.33 11,593
Punjab Chenab/Khanki 152.72 6,531 80% 20 0.32 11,593
Punjab Chenab/Khanki 153.40 6,560 80% 20 0.32 11,593
Punjab Chenab/Khanki 154.29 6,598 80% 20 0.31 11,594
Punjab Chenab/Khanki 155.50 6,650 80% 20 0.30 11,594
Northwest Frontier Sundraul 155.86 6,665 80% 20 1.47 11,595
Northen Areas Doko 156.97 6,713 80% 20 0.91 11,596
Punjab Sutlej/Sulemanki 157.73 6,745 80% 20 0.27 11,596
Punjab Chenab/Khanki 161.76 6,918 80% 20 0.24 11,597
Punjab Chenab/Khanki 163.51 6,992 80% 20 0.22 11,597
Northen Areas Gurikot 164.59 7,038 80% 20 0.98 11,598
Northen Areas Ghakuch 167.24 7,152 80% 20 0.91 11,599
Punjab Chenab/Khanki 172.92 7,395 80% 20 0.20 11,599
Punjab Sutlej/Sulemanki 175.00 7,484 80% 20 0.20 11,599
Punjab Chenab/Khanki 175.96 7,525 80% 20 0.19 11,599
Northwest Frontier Baraul Bandai 177.70 7,599 80% 20 1.68 11,601
Northen Areas Gozer/ Gulo 178.59 7,637 80% 20 0.84 11,602
Punjab Sutlej/Islam 183.96 7,867 80% 20 0.18 11,602
Punjab Chenab/Khanki 190.76 8,157 80% 20 0.17 11,602
Northen Areas Aspai Alt-I 197.95 8,465 80% 20 2.31 11,605
Northen Areas Abgarch 203.90 8,719 80% 20 0.98 11,606
Northwest Frontier Dir Alt. No.2 203.90 8,719 80% 20 0.84 11,606
Punjab Chenab/Marala 204.81 8,759 80% 20 0.15 11,607
Punjab Chenab/Khanki 211.21 9,032 80% 20 0.15 11,607
Northen Areas Rathok 211.47 9,043 80% 20 1.12 11,608
Northwest Frontier Booni 219.76 9,398 80% 20 0.14 11,608
Northen Areas Franshat 222.30 9,506 80% 20 1.05 11,609
Punjab Sutlej/Islam 226.36 9,680 80% 20 0.12 11,609
Punjab Jhelum/Mangla 238.08 10,181 80% 20 0.12 11,609
Punjab Chenab/Khanki 238.08 10,181 80% 20 0.11 11,609
Punjab Jhelum/Rasul 245.01 10,478 80% 20 0.10 11,609
Punjab Jhelum/Mangla 252.88 10,814 80% 20 4.67 11,614
Home
Private Technology-wise Cost of Power Generation in Pakistan for the Year 2007
New CCGT New CCGT New CCGT Steam Turbine Steam Turbine Hydel RoR Nuclear
Generation Options
Natural Gas Fuel Oil LNG Thar Coal Imported Coal
Project Installed Capex ($/KW) 882 812 882 1,400 1,400 1,547 2,000 Technology-wise Incremental Energy Generation (GWh)
Project Life (Years) 30 30 30 30 30 30 30 GAS CCGT FO CCGT Coal Hydro Nuclear Total
Real IRR pre-tax 12% 12% 12% 12% 12% 12% 12% 608 608 - 622 4,091 5,928
Annualized Capex ($/KW/Yr) 110 101 110 174 174 192 248 321 300 - 1,927 - 2,547
Fixed O&M ($/KW/Yr) 30 32 30 29 30 31 30 3,831 3,352 - 432 - 7,614
Load Factor 70% 70% 70% 80% 80% 75% 85% 4,784 3,914 - 689 - 9,387
Operation Hours 6,132 6,132 6,132 7,008 7,008 6,570 7,446 651 498 1,861 6,530 - 9,540
Variable O&M (US c/kWh) 0.1 0.3 0.1 0.2 0.2 0.2 1,581 1,129 4,963 5,166 - 12,840
0.4892 0.5184 0.4892 0.4109 0.4244 0.4709 0.3995 (79) (53) 3,102 4,070 4,091 11,132
Fuel Cost 2,491 1,549 - 8,386 - 12,426
Thermal Efficiency (%) 50% 43% 50% 38% 38% 4,764 2,758 3,723 928 (335) 11,838

Heat Rates (Btu/kWh) 6,824 7,935 6,824 8,979 8,979 973 524 - 12,438 - 13,934
Fuel Cost ($/MMBtu) 6.29 13.77 10.21 2.75 2.70 4,120 2,060 3,723 8,921 - 18,823
Fuel cost (US c/kWh) 4.29 10.92 6.96 2.47 2.42 1.07 1,183 548 - 9,536 4,091 15,358
Variable Costs (US c/kWh) 4.39 11.22 7.06 2.67 2.62 - 1.31 (180) (77) 11,168 9,536 - 20,446
25,047 17,110 28,539 69,180 11,937 151,813
All Costs Cents/kWh
Capital Cost 1.79 1.64 1.79 2.48 2.48 5.01 3.33
O&M Cost 0.59 0.81 0.59 0.61 0.62 0.47 0.63
Fuel Cost 4.29 10.92 6.96 2.47 2.42 - 1.07
Total Generation Costs 6.67 13.38 9.34 5.56 5.53 5.48 5.04

Social Technology-wise Cost of Power Generation in Pakistan for the Year 2007
New CCGT New CCGT New CCGT Steam Turbine Steam Turbine Hydel RoR Nuclear
Generation Options
Natural Gas Fuel Oil LNG Thar Coal Imported Coal
Private generation cost (Usc/kWh) 6.67 13.38 9.34 5.56 5.53 5.48 5.04
CO2 price (USD/tnCO2) 30 30 30 30 30
Average emission rate (tnCO2/MWh) 0.37 0.5 0.37 0.9 0.9
C02 Ext. Cost (Usc/kWh) 1.11 1.5 1.11 2.7 2.7
SO2, NOX, partic., etc Investmnet
cost to avoid (USD/KW-installed) 100 100 85
Real IRR pre-tax 12% 12% 12% 12% 12%
Annualized Capex ($/KW/Yr) 12.41 € 12.41 € 10.55 €
Operation Hours 6,132 6,132 6,132 7,008 7,008
O&M SO2, NOX, Part. (Usc/kWh) 0.25 0.25 0.25
Local Pollut. Ext. Cost (Usc/kWh) - 0.45 - 0.43 0.40
Prob. Oil jump 20% 20% 20%
Effect on GDP loss (USDMM) 3,664.00 3,664.00 3,664.00
% Oil & Gas imported to power sector 20% 20% 20%
Security of supply. Ext. Cost (Usc/kW 2.48 2.48 2.48
Total Generation Costs 10.26 17.82 12.93 8.69 8.63 5.48 5.04
- -
Notes:
1 Capital and O&M costs are based on US$ 2007 prices.
2 Capital and O&M costs for CCGT plants were taken from latest NEPRA determinations made for upcoming IPPs in the country.
3 Capital and O&M costs for coal based plants were taken from a latest study conducted for ADB to develop Thar coal.
4 Capital and O&M costs for run-of-river (RoR) hydro electric power plants are based on an average cost of a basket of hydroelectric projects for which feasibility studies have been conducted.
5 The costs for nuclear power plants are indicative and used by NTDC for planning comparisons.
6 Price of gas has been taken at parity with the price of gas imported from Iran in accordance with IPI pricing formula.
7 Fuel oil and LNG costs are based on 90 US $/barrel crude oil.
8 Imported coal price is based on import price of US $ 75/tonne.

You might also like