HT Switchgear:
Megger test was carried out between the phases (CB close), between phase and
earth (CB close), Across Contacts (CB open).
Through micro ohm meter the resistance value was checked across the contact with
CB close.
Timer Test
CB all poles are connected to the timer kit and also the Trip, Close coil was
energized and de-energized by means of the timer kit and the timing was noted.
Using the relay test kit the current was injected directly into the relay instead of CT
current, and the tripping time was noted.
Functional checkup, Fault simulation checkup was done in these types of relays
Current Transformer
50% and 100% of Rated current was injected in the CT primary and the sec. current
was measured at the secondary terminal as well as in the metering circuit.
Megger test was carried out between primary to earth (5 KV), Primary to sec. (5 KV),
sec. to earth (1 KV)
Polarity Test
By applying the small amount of DC voltage (9 V) in the primary (P1 & P2) the
deflection was measured in the secondary by means of Galvanometer.
Potential Transformer
Ratio Test
415V 3 phase supply was applied to the primary of the PT and the secondary
voltage was measured in the secondary terminals and also in the metering circuit.
And by means of that the ratio was calculated and checked.
Megger test was carried out between primary to earth (5 KV), Primary to sec. (5 KV),
sec. to earth (1 KV)
Polarity Test
Bus Bar
Torque Test
By means of torque wrench the tightness of the bus bar was checked.
Megger test was carried out between phases, between phase and earth. The test
was carried out for 60 sec.
Operational Checkup:
By providing the control voltage to the HT panels the electrical ON & OFF was
checked and the interlock scheme is also checked.
Transformer
Magnetic Balance Test
Example: R was cutoff the value between YB, RY, BR was measured and it must
satisfied YB= RY + BR
Primary of the transformer was energized by means of 3 phase supply (415V) and
the no load current taken by the transformer was measured.
Vector group test
Primary of the transformer was energized by means of 3 phase supply (415V) and
depends upon the vector Group mentioned in the Drawing the test was carried out.
Ratio Test
Primary of the transformer was energized by means of 3 phase supply (415V), the
voltage was measured at the secondary of the transformer and depends upon the
tap position the ratio error was calculated.
Megger test was carried out between primary to earth, primary to secondary (both
5 KV), Secondary to earth (1 KV).
Using Micro ohm meter the winding resistance value was measured in the primary
and secondary windings.
Operational checkup
Operational was done for the OLTC and functional checkup was done for the
protection system in transformer.
Bus Duct
Megger test and torque test was done, If required the winding resistance test may
also conducted at joints.
NOTE: All the above test was done at normal tapping expect Ratio
test.
LT Panels
LT Switchgear:
Megger test was carried out between the phases (CB close), between phase and
earth (CB close), Across Contacts (CB open) with 1KV.
Functional Checkup
By providing the control voltage to the LT panels the electrical ON & OFF was
checked and the interlock scheme is also checked
Bus Bar
Megger test was done between phases, between phases to neutral, between phases
to earth with 1 KV.