You are on page 1of 234

GOVERNMENT OF ANDHRA PRADESH

ANDHRA PRADESH ROAD DEVELOPMENT CORPORATION

ANDHRA PRADESH ROAD SECTOR PROJECT


Feasibility Study, Design and Detailed Engineering

DETAILED PROJECT REPORT


(UPGRADING OF MYDUKUR - JAMMALAMADUGU ROAD)

V
VO UM
OLLU MEE––VVIIII :: E
EN RO
VIIR
NV NM
ON MEEN TA
NT ALL I
IMMP AC
PA TA
CT ASSSSEESSSSM
ME NT
EN T
AN
A DE
ND ENNV VIIR ON
RO NMME NT
EN ALL M
TA MAANNAAGGE ME
EM ENNTTPPLLAANN

Submitted to:

Chief Engineer (R&B) & Managing Director


A.P. Road Development Corporation
Erramanzil, Hyderabad 500 082, A.P., India

Submitted by:

THE Louis Berger Group, Inc.


Engineers • Planners • Scientists • Economists
Plot No. - 41, Sector – 18, Near Maruti Industrial Area,
Gurgaon – 122 015, Haryana, India
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

INDEX

ABBREVIATION

EXECUTIVE SUMMARY

CHAPTER - 1: INTRODUCTION

CHAPTER - 2: DESCRIPTION OF THE PROJECT

CHAPTER - 3: ENVIRONMENT REGULATORY FRAMEWORK

CHAPTER - 4: BASELINE ENVIRONMENT

CHAPTER - 5: STAKEHOLDERS CONSULTATION

CHAPTER - 6: ANALYSIS OF ALTERNATIVES

CHAPTER - 7: PROJECT IMPACTS AND ISSUES

CHAPTER - 8: IMPACT MITIGATION AND ENHANCEMENT

CHAPTER - 9: ENVIRONMENTAL MANAGEMENT PLAN

APPENDICES

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan (i)
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

ABBREVIATIONS

SOS Strategic Option Study


R&B Road & Building Department
APRDC A.P. Road Development Corporation
APRSP Andhra Pradesh Road Sector Project
GOI Government of India
GOAP Government of Andhra Pradesh
SH State Highway
MDR Major District Road
ODR Other District Road
EIA Environmental Impact Assessment
EMP Environmental Management Plan
DoF Department of Forest
MoEF Ministry of Environment and Forest
FHWA Federal Highways Authority
CPCB Central Pollution Control Board
IMD India Meteorological Department
COI Corridor of Impact
PIA Project Influence Area
PD Project District
ROW Right of Way
AAQ Ambient Air Quality
SPM Suspended Particulate Matter
RPM Respirable Particulate Matter
AADT Annual Average Daily Traffic
PUC Pollution under Control Certificate
ASI Archaeological Survey of India.
NOC No Objection Certificates
RH Relative Humidity
PAP Project Affected Person
RAP Resettlement Action Plan
OMC Optimum Moisture Content
CSC Construction Supervision Consultant
EMU Environment Management Unit
EO Environment Officer

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

PIU Project Implementation Unit


PU Package Unit

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

EXECUTIVE SUMMARY

A.1 BACKGROUND
APRDC has planned to improve the State road network by providing better quality and safer roads
to the users in sustainable manner with loan assistance from World Bank. Improved quality of roads,
better institutional operation and management system of APRDC and safe roads are important
features of the project component. In this connection RDC has selected 38 corridors (cumulative
length of 2002 km) of high-density (traffic) roads through Strategic Option Study (SOS) to be
developed in phased manner.
A.2 OBJECTIVES OF THE ASSIGNMENT
The main objective would be to alleviate the current unsafe and congested conditions of the road
network connecting the villages and towns by providing better quality and safe roads to the users in
a sustainable and environment friendly manner. Government of India, GoI through Ministry of
Environment and Forest (MoEF) enforces Environment (Protection) Rules, 1986 for
environmental protection because of intervention of new projects or activities, or on expansion and
modernization of existing projects or activity based on their environmental impacts.
A.3 SCOPE OF ENVIRONMENTAL ASSESSMENT (EA)
The environmental assessment scope includes screening and scoping, environmental assessment and
environmental management plans for the individual project roads as required. The EA process also
envisages to develop a comprehensive environmental management frame work for the entire project
which will adopted as part of the corporate environmental policy for AP Road Development
Corporation.
A.4 DESCRIPTION OF PROJECT ROAD
The Project road, Mydukuru - Jammalmadugu Road is a section of State Highway No.57, located in
Rayalseema Region of Andhra Pradesh. The Project road starts from km 153/000 in Mydukuru
town at the junction with NH-18 in Kadapa district and runs south east direction connecting
Jammalmadugu, Vishwandhapuram, Proddutur, Chanduru and terminates at km 194/000 near
Jammalmadugu R&B Guest House. The Proddutur bypass between km 171/400 and 177/400 is not
included in the project scope. Cumulative length of PR is 35.0km. The project road will improve
connectivity to district town Kadapa, important tourist place, through NH-18 and is widely used by
interstate traffic..
Based on the traffic demand the PR is proposed to be upgraded to 4lane configuration from
Mydukuru to Jammalmadugu, except Proddutur Bypass which is out of the scope of this project.
A.5 KEY ENVIRONMENTAL LAWS AND REGULATIONS
Table 1 presents the environmental regulations and legislations relevant to AP state road project.
Table 1: Environmental Regulations and Legislations
SR. Applicable
Act / Rules Purpose Reason for Applicability Authority
No Yes/ No
As all environmental
MoEF. Gol; DoE,
Environment To protect and improve notifications, rules and
1 Yes State Gov. CPCB;
Protection Act-1986 overall environment schedules, are issued under this
SPCB
act.
To provide environmental
This notification is NOT
Environmental Impact clearance to new
NO applicable to Project road, the
2 Assessment Notification development activities MoEF. EIAA
status of the project road is
14th Sep-2006 following environmental
Major District Road.
impact assessment
Reuse large quantity of fly
ash discharged from
Notification for use of fly Thermal plant within 100km
3 thermal power plant to Yes
ash reaches.
minimize land use for
disposal

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

SR. Applicable
Act / Rules Purpose Reason for Applicability Authority
No Yes/ No
Coastal Regulation
Protection of fragile Road is not located along
4 Zone(CRZ) Notification NO
coastal belt coastal belt
1991 (2002)
National Environment Address Grievances
Grievances if any will be dealt
5 Appellate Authority Act regarding the process of Yes NEAA
with, within this act.
(NEAA) 1997 environmental clearance.
This act will be applicable to as
Set out rule for there will be acquisition of land Revenue
The Land Acquisition
6 acquisition. of land by Yes for widening, geometric Department State
Act 1894 & 1989
government improvements and Government.
realignments.
Moef Circular on
Defining “marginal land’
Marginal Land Superseded by 2006
7 acquisition relating to the NO MoEF
Acquisition and Bypasses Notification
1997 Notification
1999
The Forest
(Conservation) Act 1927 To check deforestation
Forest
The Forest by restricting conversion NO forest area within the
8 NO Department,
(Conservation) Act. 1980 of forested areas into project influence area.
GoAP
forest (conversion ) Rules non- forested areas
1981
MoEF circular (1998) on
linear Plantation on
Protection / planting
roadside, canals and
roadside strip as Roadside tree plantation in
railway lines modifying
9 avenue/strip plantations NO Andhra Pradesh does not comes MoEF
the applicability of
as these are declared under the forest act.
provisions of forest
protected forest areas.
(Conversation) Act, to
linear Plantation
Chief Conservator
To protect wildlife
This act is NOT applicable as Wildlife, Wildlife
Wild Life Protection through certain of
10 NO there is NO points of wildlife Wing, Forest
Act 1972 National Parks and
crossings along project corridor. Department,
Sanctuaries
GoAP.
To control air pollution by This act will also be applicable
& Transport controlling during construction; for
Air (Prevention and
emission of air obtaining NOC for
11 Control of Pollution) Yes SPCB
Department. pollutants as establishment of hot mix plant,
Act, 1981
per the prescribed workers' camp, construction
standards. camp, etc.
To control water
This act will be applicable during
Water Prevention and pollution by controlling
construction for (establishments
12 Control of Pollution) discharge of pollutants as Yes SPCB
of hot mix plant, construction
Act1974 per the prescribed
camp, workers' camp, etc.
standards
This act will be applicable as
The standards for noise for
Noise Pollution vehicular noise, to assess for
day and night have been
13 (Regulation and Yes future years and necessary SPCB
promulgated by the MoEF
Control Act) 1990 protection measure needs to be
for various land uses.
considered in design.
Archaeological Dept
Gol, Indian
Ancient Monuments This act not applicable as
Conservation of cultural Heritage Society and
and Archaeological project road is not close to any
14 and historical remains No Indian National
Sites and Remains Ancient Monument declared
found in India Trust for Art and
Act1958 protected under the act.
Culture Heritage
(INTACH).
Protection form Contractor need to stock
Public Liability and
15 hazardous materials and Yes hazardous material like diesel, SPCB
Insurance Act 1991
accidents. Bitumen, Emulsions etc.
Safe transportation,
For transporting and storing Chief controller
16 Explosive Act 1984 storage and use of Yes
diesel, bitumen etc. of Explosives
explosive material
Minor Mineral and For opening new Regulate use of minor minerals
17 Yes District Collector
concession Rules quarries. like stone, soil, river sand etc.
Central Motor Vehicle These rules will be applicable to
To check vehicular air Motor Vehicle
18 Act 1988 and Central Yes road users and construction
and noise pollution. Department
Motor Vehicle Rules1989 Machinery.
To maintain ecological
National Forest
stability through This policy will NOT be Forest
Policy1952
19 preservation and NO applicable as NO forest area Department, Gol
National Forest
restoration of biological within the CoI. and GoAP
Policy(Revised) 1988
diversity.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

SR. Applicable
Act / Rules Purpose Reason for Applicability Authority
No Yes/ No
The construction of project
The mining act has been road will require aggregates.
Department of
20 The Mining Act(1952) notified for safe and Yes These will be procured through
mining, GoAP
sound mining activity. mining from riverbeds and
quarries

On the basis of data and information collected during field survey and discussion with local expert
and visualise potential associated impact, consultant has categorised this project as category-B,
which requires a lesser level of environmental investigation.
A.6 BASE LINE ENVIRONMENT
Data was collected from secondary sources for the macro-environmental setting like climate,
physiography (Geology and slope), biological and socio-economic environment within Project
Influence Area, PIU/ Project District, PD . First hand information have been collected to record the
micro-environmental features within Corridor of Impact, CoI. Collection of first hand (Primary)
information includes preparation of base maps, extrapolating environmental features on proposed
road design, tree enumeration, location and measurement of socio-cultural features abutting project
road.
A.7 STAKEHOLDER CONSULTATION
Consultative procedure, since the inception of the project, has been continued during pre-feasibility,
feasibility, Environmental Assessment and Management Plan preparation stage. Considering the fact
that involving local communities in the project planning is basis of the participatory planning, often
suggestion and option given by the people improves technical and economic efficiency of the project
and suggested improvements proposals (if adopted by the project) of the people also generates sense
of ownership within communities thus eases implementation process.
A.8 INFORMATION DISSEMINATION
• While conducting tree enumeration and inventory of road side environmental features (hot
spots), the consultant has also conducted information dissemination by one to one campaigning
about proposed improvement,
• Potential project affected families were consulted to inform them about proposed road
improvement program and possible environmental conflict such as tree cutting, relocation of
hand pumps,
• Pictorial Methods were adopted to explain proposed improvement and possible environmental
impacts in the concerned villages,
• Information dissemination through pumhlet / Khadapatralu among the villagers explaining
proposed road improvement.
A.9 ANALYSIS OF ALTERNATIVES
At three location, project road passes through congested areas-
¾ Peddasettipalli Bypass (Km 178.600 - 179.600),
¾ Cudappah Stone Quarry (Km 183.300 - 187.500) and
¾ Dhanvulapadu Bypass (Km 186.100 - 186.900)
Pedasettipalli: Around 1000m length, from km 178/600 to km 179/600, project road passes
through very congested areas of Pedasettypalli village. There are three reverse curves in this segment.
The ROW varies from 8m to 12m. The houses are abutting the roadway and location to prone to
accidents. The entire village is situated on the south of the project road; on the northern side there
are four-five houses in scattered form.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

The approved alignment follows through the left hand side of existing alignment. There is no
apparent advantage to follow this bypass alignment along this road, but is the most suitable option
available, as other options are eliminated/more problematic
Cudappah Stone Quarry (Km 183.300 - 187.500)
The approved alignment follows through the Right hand side of existing alignment. The existing
alignment is straight and in good condition but owing to limited width the proposed new 2 lane will
be following the periphery of the quarry on right hand side of existing alignment. This way the
existing alignment will serve as one way for traffic from Mydukuru to Jammalamadugu and new
proposed realignment will be used by traffic plying from Jammalamadugu to Mydukuru. There is no
apparent advantage to segregate the traffic but land acquisition is a big problem and refilling the site
is not safe.
Dhanvulapadu Bypass (Km 186.100 - 186.900)
Around 800m length, from km 186/100 to km 186/900, project road passes through very
congested areas of Dhanvulapadu village. There are two reverse curves in this segment. The
ROW varies from 10m to 12m. The houses are abutting the roadway and location to prone
to accidents. The approved alignment follows through the left hand side of existing alignment.
There is no apparent advantage to follow this bypass alignment along this road, but is the most
suitable option available, as other options are eliminated/more problematic.

A.10 POTENTIAL IMPACT


Table 2 below presents the general environmental impacts expected due to the proposed upgradation
of the project road. Impacts have been assessed based on the first hand information collected from
the screening & scoping of environmental attributes. The quanta of all the impacts on Natural
Environment are analyzed in detail.
Table 2: General Impacts on Natural Environment
Planning Indirect effects
Project and De- Road Opera- of operation or
Pre-construction Phase Construction Phase
Activity sign tion Induced de-
Phase velopment

Vehicle & Sanitation


Env. com- Removal Removal of Earth works in- Asphalt &
Land ac- Laying of Machine op- & Waste Vehicle
ponent Af- of trees and cluding quarry- crusher
quisition pavement eration & (labour operation
fected Structures vegetation ing plants
maintenance campus)
Reduced
Dust gen- buffering of
Noise, soot,
eration air and noise Asphalt Noise, dust, Odour / Noise, dust,
Air Dust generation odour, dust, other pollution
during dis- pollution, odour pollution smoke pollution
pollution
mantling Hotter, drier
microclimate
Contamina- Contamina- Contami-
Loss of Erosion and Spill from ac-
Generation Erosion and loss tion by fuel tion Com- nation Change in crop-
Land produc- loss of top cidents Depo-
of debris of top soil and lubricants paction of from ping pattern
tive Land soil sition of lead
Compaction soil wastes
Alteration of
drainage Contami- Spill Contami-
Reduction Contamina-
Loss of Siltation Siltation due Break in conti- Contamina- nation nation by fuel, Increased con-
of ground tion by as-
Water water due to to loose nuity of ditches tion by fuel from lubricants and tamination of
water re- phalt leakage
sources loose earth earth Siltation, and lubricants wastes washing of ve- ground water
charge area or fuel
Stagnant water Overuse hicles
pools in quarries.
Noise Pol-
Noise Pol- Noise pollu- Noise Pollu- Noise Pollu-
Noise lution due to Noise Pollution Noise pollution
lution tion tion tion
machinery

Felling Impact of
Loss of Lowered pro- Removal of Lower pro-
Flora trees for pollution on
Biomass ductivity vegetation ductivity
fuel vegetation
Loss of ground Use as fuel
Lowered pro-

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

for vegetation wood ductivity


Toxicity of
vegetation.
Disturbance Collision with Distorted habi-
Fauna Disturbance Disturbance Disturbance Poaching
Habitat loss traffic tat

A.11 AVOIDANCE, MITIGATION & ENHANCEMENT


Prevention or avoidance of impact is better than mitigation of impact. Hence avoidance and
reduction of adverse impacts approaches were adopted during the design stage through continued
interaction between the design and environmental teams. This is reflected in the designs of the
horizontal & vertical alignment, cross sections adopted, construction methods and construction
materials. In-depth site investigations have been carried out so that sensitive environmental
resources are effectively avoided, leading to the environmentally best-fit alignment option. As a
result many of the trees, cultural properties, water bodies etc. have been avoided at the design stage
itself, as presented in Table 3 below.
Table 3: Environmental features saved through Avoidance measure at design stage
Environmental Features Potential Impact Under Direct Impact Saved through alignment design
Trees (nos.) 1163 815 348
Surface Water source 2 0 2
Ground Water source 15 8 7
Cultural Properties 18 7 11
Bus Shelters 10 6 4

A.12 ENVIRONMENTAL MANAGEMENT PLAN


Environmental Management Plan (EMP) deals with the implementation procedure of the guidelines
and measures recommended to avoid, minimize and mitigate environmental impacts of the project.
It also includes management of measures suggested for enhancement of the environmental quality
along the highways.
The institutional arrangement made under project will look into the implementation of project as
well as EMP and the various legal settings applicable to the project are briefly stated in chapter 3.
The avoidance, mitigation & enhancement measures for protection of the environment along
highways have been discussed in detail in previous chapter. Although the social environmental
impacts, its mitigation and management is an essential component of the EMP, this chapter excludes
it for the purpose of clarity and procedural requirements. Social environmental elements have been
separately dealt in separate volume namely, Resettlement and Rehabilitation Action Plan (RAP).
A.13 OBJECTIVE OF EMP
The EMP is a plan of action for mitigation / management / avoidance of the negative impacts of
the project and enhancement of the project corridor. For each measure to be taken, its location,
timeframe, implementation and overseeing / supervision responsibilities are listed. These
components of the EMP have been given in Chapter 9 which explains the environmental issues and
the avoidance/ mitigation/ minimization or enhancement measures adopted and/or to be adopted
during different phases of the project. It also provide the references for the suggested measures,
responsible agency for its implementation/ management as well as its timeframe.
A.14 COST ESTIMATES FOR ENVIRONMENTAL MANAGEMENT
Mitigation measures proposed in the EMP will be implemented by the Contractor. The works to be
undertaken by the Contractor have been quantified and the quantities included in the respective
BOQ items such as earth works, slope protection, noise barriers, road safety features, and shrub
plantation.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Provisional quantities have also been included for additional measures that may be identified during
construction and for silt fencing which will depend on the Contractors work methods and site
locations. Items and quantities have also been included for enhancement measures.
More general environmental management measures to be followed by the contractor have been
included in the specifications and this EMP. These cannot be quantified and are to be included in
the contract rates. A total of Rs. 12.48 million has been allocated for the environmental management
for the Project road.

A.15 ORGANIZATIONAL FRAMEWORK


The proposed project will be implemented by APRDC through its Environmental Management Unit
(EMU). The EMU comprises of officers from Department of Forest, GoAP, and other
environmental Engineers. The EMU will be coordinating with the field level implementing agencies
such as Engineer (Supervision Consultant), Contractor and field level APSHP officials. Role and
responsibilities of important officials is detailed in chapter 9.
ORGANISATIONAL FRAMEWORK OF PIU - APRSP
(Supervision and Monitoring of EMP)

Chief Engineer & Managing Director APRDC

Project Director - APRSP

Environment Management Unit (EMU-APRDC)


Environmental Officer APRDC

ORGANISATION STRUCTURE AT FIELD LEVEL


(R&B), APRDC Environmental
(Supervision and Monitoring of EMP) Engineer,
(CSC)
Executive Engineer of Package Unit. APSHP

Dy. Executive Engineer of Package Unit, APSHP

Environment and Safety Manager of Package Unit,


Contractor

Fig. 1: Organization Framework

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan Page - 6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER 1: INTRODUCTION .....................................................................................................1-2


1.1 BACKGROUND ............................................................................................................................................1-2
1.2 THE PROJECT ...............................................................................................................................................1-2
1.2.1 Project Description ..........................................................................................................................1-2
1.2.2 Objectives of the Assignment ........................................................................................................1-2
1.2.3 Scope of Environmental Assessment (EA)..................................................................................1-3
1.2.4 Project Benefits.................................................................................................................................1-4
1.2.5 Structure of the Report....................................................................................................................1-4

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 1-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER 1: INTRODUCTION

1.1 BACKGROUND
Andhra Pradesh is a progressive state with a population of 76 millions. Around 75% of the total
population is living in the rural areas. Improving infrastructure facilities will promote agricultural and
industrial growth in the state. The Road Policy (2005-15) also aims at providing an efficient, safe and
environmentally sustainable road network in the state. In order to improve the quality of the
corridors, Road and Building Department (RBD) of Government of Andhra Pradesh (GoAP) has
entrusted the responsibility of maintenance and improvement of key State roads (core network) to
Andhra Pradesh Road Development Corporation (APRDC1).
APRDC has planned to improve the State road network by providing better quality and safer roads
to the users in sustainable manner with loan assistance from World Bank. Improved quality of roads,
better institutional operation and management system of APRDC and safe roads are important
features of the project component. In this connection RDC has selected 38 corridors (cumulative
length of 2002 km) of high-density (traffic) roads through Strategic Option Study (SOS) to be
developed in phased manner.
The screening and scoping exercise has been carried out as a part of the feasibility study and to list
out the priority roads in the state. The environmental assessment and analysis has been documented
in this report.
1.2 THE PROJECT
1.2.1 Project Description
Feasibility study was carried out on 38 roads (cumulative length 2002 km) selected through Strategic
Option Study of 10,040km of key road network of state roads. Considering the economic, social and
environmental criteria, 21 roads are selected for implementation in two phases, eight in Phase - I and
thirteen roads in Phase - II. Further these Phase - I corridors have been agreed for implementation
in two years. Four corridors each in year-1 and year-2.
Corridors selected for implementation in Phase–I, year-1 are
1. Kandi-Shadnagar (65.60 Km)
2. Chittoor-Puttur (60.80 Km)
3. Kurnool-Devanakonda (60.60 km)
4. Mydukuru – Jammalamadugu (41 Km)
The present report on Environmental Impact Assessment (EIA) deals with the environmental
analysis of Mydukuru – Jammalamadugu Road in accordance with the World Bank's guidelines on
Environmental Assessment. Figure 1.1 Map showing location & elevation of Mydukuru -
Jammalamadugu Road.
1.2.2 Objectives of the Assignment
The main objective would be to alleviate the current unsafe and congested conditions of the road
network connecting the villages and towns by providing better quality and safe roads to the users in
a sustainable and environment friendly manner. Government of India, GoI through Ministry of
Environment and Forest (MoEF) enforces Environment (Protection) Rules, 1986 for
environmental protection because of intervention of new projects or activities, or on expansion and
modernization of existing projects or activity based on their environmental impacts.
The report in hand is prepared in accordance with the World Bank's operational policies2 guidelines
on Environmental Assessment and to meet the statutory requirement of Ministry of Environmental
1 GoAP is in the process of operatinalizing RDC as per RDC act to manage core network assigned to APRDC (about 10,000km of
roads).
2 Applicable safeguards instruments are prepared based on Bank guidelines like environmental assessment (O.P. 4.01), Natural
Habitat(O.P. 4.04), Forests(O.P. 4.06), Involuntary Resettlement(O.P.4.10) and Indigenous Peoples(O.P. 4.12)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 1-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

and Forest (MoEF), State Pollution Control Board, State Forest Department, etc. The objectives of
this study are stated below:
• To present to decision makers a clear assessment of potential impact associated with the
proposed project intervention,
• To apply a methodology which assesses and predict potential impacts and provides a) the means
for impact prevention and mitigation, b) the enhancement of project benefits, and c) the
minimization of long-term impacts;
• To provide a specific forum in which consultation is systematically undertaken in a manner that
allows stakeholders to have direct input to the environmental management process.
• To assess the analysis of alternatives to bring environmental considerations into the upstream
stages of development planning as well as the later stage of site selection, design and
implementation, and
• To recommend the environmental management measures to reduce adverse impacts.
In order to achieve these objectives, detailed surveys and other studies have been carried out along
the project roads to identify Valued Ecosystem Components (VEC) and corridor specific significant
environmental issues (SEI). For investigation/monitoring purpose the study area has been defined as
under.
o Corridor of Impact, CoI: is the 20m wide strip on either side, beyond Right of Way, RoW.
o Project Influence Area, PIA: is the 10km area on either side along the alignment.
o Project District, PD: is/are the district/districts through which project road is passing.
1.2.3 Scope of Environmental Assessment (EA)
The environmental assessment scope includes screening and scoping, environmental assessment and
environmental management plans for the individual project roads as required. The EA process also
envisages to develop a comprehensive environmental management frame work for the entire project
which will adopted as part of the corporate environmental policy for AP Road Development
Corporation.
Environmental Screening and Scoping
Environmental screening exercise of the project roads were undertaken to facilitate inputs on
environmental considerations, apart from social, economic, and traffic & transport considerations in
selection of project roads out of 2056kms of roads, identified through strategic options study.
Further, this report also provides scoping inputs in determining the major environmental issues and
defines the scope of work for conducting environmental assessment. As per the recommendation of
the Environmental Screening report, detailed Environmental Assessment has been carried out for
the project roads. The scoping exercise defines geographical Boundaries for the project roads for
impact assessment as well as defining the project influence area to assess the impacts due to project
activities.
Environmental Assessment
The EA for selected project roads includes establishing environmental baseline in the study area,
identify the range of environmental impacts, specify the measures to avoid, minimize, and mitigate
negative impacts and maximize positive impacts and integrate possible environmental enhancement
measures. The proposed measures will be formulated in the form of an environmental management
plan with necessary budget and institutional roles for effective implementation. The EMPs for
individual projects and integration of the same in to project implementation agreements, including
construction contract documents.
Environmental Management Framework
An Environmental Management Framework will be designed for the implementation of the project.
The environmental management frame work shall consists of over all framework which will be

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 1-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

developed as a guidance document providing environmental planning and design criteria for of the
current as well as future project roads, generic environmental management measures, institutional
mechanism for implementation, capacity building and training process, and resource material for
RDC to function adequately to mainstream the environmental management.
1.2.4 Project Benefits
The implementation of the project will have the following direct benefits:
(i) Improved quality of life for the population in the project area. Economic boost to the local
population by facilitate easy transportation of materials and having better connectivity for the
commercial centres.
(ii) Provides employment facility for the local population.
1.2.5 Structure of the Report
Chapter-2: Project Description, a brief description of the project corridor is envisaged focusing on
various proposed improvements of corridor with a mention on right of way, roadway
improvements, cross drainage structures, community facilities, traffic projections etc.
Chapter-3: Environment Regulatory Framework, presents the legal and administrative framework
of World Bank, Government of India and Government of Andhra Pradesh. This section underlines
various clearances involved for the project corridor at the State level and at the Central level.
Chapter-4 Baseline Environmental Status, the existing environmental conditions along the corridor
was ascertained by conducting a recognizance survey along with collection of secondary information
pertaining to the corridor. Primary data for various environmental parameters was generated using
suitable monitoring devises. The methodology was strictly adhered to the Central Pollution Control
Board’s stipulated guidelines.
Chapter-5 Public Consultation was carried out in order to know the reactions of local population
and the project affected population. Meetings were held with the stake holders to record their views
on the impacts caused and the suggested remedies to be adopted for the proposed project corridor.
Chapter-6 Analysis of Alternatives was carried out during feasibility study, covered in
Environmental Screening and Scooping report, and the approved alternative is discussed in detail in
this chapter along with the alternatives considered in finalizing the alignment.
Chapter-7 Environmental Impacts, likely impacts caused on various environmental and social
parameters by the various activities proposed for the project corridor was recorded in this chapter.
Chapter-8 Mitigation & Enhancement Measures, various mitigation & enhancement measures were
suggested for the impacts caused due to various activities.
Chapter-9 Based on potential impact and proposed mitigation measure Environmental
Management Plan, is prepared. Organizational framework for execution and monitoring of EMP is
also prepared along with cost estimate for Environment management.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 1-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Fig 1.1: Location Map and Elevation Graph of Mydukuru - Jammalamdugu Road

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 1-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER - 2: DESCRIPTION OF THE PROJECT .........................................................................3


2.1 GENERAL............................................................................................................................................................3
2.2 PRESENT CHARACTERISTICS ....................................................................................................................3
2.2.1 Right of Way (ROW).............................................................................................................................3
2.2.2 Traffic Scenario ......................................................................................................................................4
2.2.3 Road Width.............................................................................................................................................4
2.2.4 Land Use and Roadside Environments..............................................................................................5
2.2.5 Villages and Urban-Built Up Sections ................................................................................................7
2.3 PROPOSED IMPROVEMENTS.....................................................................................................................7
2.3.1 Proposed CW Configuration and Cross Sections.............................................................................7
2.3.2 Identification of Realignment and Bypass Provisions ...................................................................11
2.4 CULVERTS AND BRIDGES .........................................................................................................................11
2.5 IDENTIFICATION OF BORROW AREAS...............................................................................................12
2.6 GEOTECHNICAL INVESTIGATIONS ....................................................................................................12
2.7 HYDRAULIC AND HYDROLOGICAL INVESTIGATIONS .............................................................13
2.8 ROAD SAFETY REVIEW ..............................................................................................................................13
2.9 ROAD CONSTRUCTION STANDARDS, NORMS AND GUIDELINES ........................................18

LIST OF TABLES

Table 2.1: Summary of Right of Way ...............................................................................................................................3


Table 2.2: AADT along Homogeneous segments of Mydukur-Jammalmadugu Road............................................4
Table 2.3: Carriageway Width / lane Configuration along Mydukuru – Jamalmadugu Road .................................4
Table 2.4: Section wise AADT and LOS .........................................................................................................................4
Table 2.5: Summary of Land Use......................................................................................................................................5
Table 2.6: Inhabitation along the Project Road ..............................................................................................................7
Table 2.7 Details the typical cross sections adopted for project road.........................................................................7
Table 2.8: Summary of Proposals for Culverts .............................................................................................................12
Table 2.9: Details of Existing Bridges and Proposal....................................................................................................12
Table 2.10: Realignment sections ....................................................................................................................................13
Table 2.11: Embankment Raising Locations.................................................................................................................14
Table 2.12: Summary of Proposed Horizontal Alignment..........................................................................................14
Table 2.13: Summary of Proposed Minor and Major Junctions ................................................................................14
Table 2.14: Longitudinal Markings Proposed for the Project Road..........................................................................15
Table 2.15: Locations of proposed Crash Barrier.........................................................................................................16

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Table 2.16: Location of Bus Shelters.............................................................................................................................17

LIST OF FIGURES

Fig. 2.1: Land use plan of Mydukur-Jammalmadugu Road...........................................................................................6


Fig 2.2: Typical Cross section for 4-Lane road in Builtup Area and Rural Area (Concentric Widening) .............8
Fig 2.3: Typical Cross section for 4-Lane road in Rural Area (Eccentric Widening and New Formation) ..........9
Fig 2.4: Typical Cross section with use of Fly ash in Embankment..........................................................................10

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER - 2: DESCRIPTION OF THE PROJECT

2.1 GENERAL
Mydukuru - Jammalmadugu Road, the project
road is a section of State Highway No.57,
located in Rayalseema Region of Andhra
Pradesh. The Project road starts from km
153/000 in Mydukuru town at the junction
with NH-18 in Kadapa district and runs south
east direction connecting Jammalmadugu,
Vishwandhapuram, Proddutur, Chanduru and
terminates at km 194/000 near
Jammalmadugu R&B Guest House. The
Proddutur bypass between km 171/400 and
177/400 is not included in the project scope.
Cumulative length of PR is 35.0km. The
project road will improve connectivity to
district town Kadapa, important tourist place,
through NH-18 and is widely used by
interstate traffic.
The ROW varies between 12 to 30m. The land use is predominantly agricultural and barren.
The terrain is plain. The condition of road surface varies between fair to good condition except few
locations where it is in poor condition.
There are three critical locations along the project road, which needs special attention. Around 600m
length, from km 178/200 to km 178/800 (Peddasettipalli village), and 400 m length, from 185/800 to
186/200 (Dhanvalapadu village), the project road passes through very congested areas. And another
location between km 183/000 and km 184/000, there is Kadapa stone quarry located adjacent to the
PR.
Bypass have been proposed at the above three locations, as improvement along the existing is not
possible due to poor geometrics and insufficient ROW.
The two homogenous sections of the project road, “Mydukur – Proddutur” and “Proddutur –
Jammalmadugu” have medium level of interstate commercial traffic and the improved connectivity
will reduce the travel time considerably.
The following sections of this chapter provide details of the present characteristics and proposed
improvements of project road.

2.2 PRESENT CHARACTERISTICS


2.2.1 Right of Way (ROW)
Width of ROW is not uniform along the project road. The following table gives the distribution of
length of Project road and %age length with respect to ROW width.
Table 2.1: Summary of Right of Way
Width of Existing ROW Total
<16m 16m – 20m 20m – 25m 25m – 30m > 30m Length
8.0 12.2 10.8 3.2 0.8 35.0
23% 35% 31% 9% 2% 100%

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

From the above table it has been found that 58% of the PR has insufficient ROW for upgrading of
the road to 4 lane standards and improvement of geometric, if any. This calls for major land
acquisition along the PR.
2.2.2 Traffic Scenario
The vehicle-wise average daily traffic (ADT) figures were estimated by classified count survey. Table
2.2 presents a summary of the vehicle-wise AADT on the project road, for each homogenous section.
Table 2.2: AADT along Homogeneous segments of Mydukur-Jammalmadugu Road
Vehicle Population: AADT (PCUs)
Section Description Count Station Motorized Non-Motorized Total
Vehicle Vehicles Vehicle
MJ-01 Mydukur-Proddutur Km 170/0, Khaderbad 13980 1100 15080
MJ-02 Proddutur-Jammalmadugu Km 178/0, Peddasettipalli 8457 645 9102

Based on the base year traffic as presented above, traffic projections have been done to derive the
traffic demand at horizon years which are important inputs in proposing the improvement options.
Based on the traffic projections and capacity analysis it is concluded to upgrade the existing facility to
4 lane configuration.
2.2.3 Road Width
The carriageway/ roadway width of the project road is not uniform. The following table gives the
distribution of length of Project road and %age length with respect to carriageway width (Single lane,
Intermediate Lane, Double Lane, Double lane with Paved Shoulder).
Table 2.3: Carriageway Width / lane Configuration along Mydukuru – Jamalmadugu Road
Chainage Length
S No. Carriageway Type Remarks
From To ( km )
1 153.0 171.4 18.4 2L BT
2 171.4 177.4 6.0 2L BT Existing Bypass Proddatur town
3 177.4 195.2 17.8 2L BT

From the road inventory it can be summarised that whole of the PR is 2lane with carriageway width
near 6.5m. The width of earth shoulder, in case of two lane road, varies from 1.0m to 1.5m against
the standard width of 2.5m.
Based on the traffic figures and existing lane configurations, the existing Level of Service at which the
sections of project road are experiencing is tabulated in table below:
Table 2.4: Section wise AADT and LOS
Section Description AADT (PCU) Existing CW Configuration Existing LOS
MJ-01 Mydukur-Proddutur 15080 2L D-E
MJ-02 Proddutur-Jammalmadugu 9102 2L C

LOS A: Represents a condition of free flow.


LOS B: Represents a condition of stable flow with restricted freedom for selection of speed.
LOS C: Represents a condition of stable flow with little freedom for selection of speed.
LOS D: Represents a condition of limit of stable flow with condition approaching unstable flow.
LOS E: Represents a condition of unstable flow with volumes close to capacity.
(Refer IRC 106: 1990)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

From the above analysis, the PR has already crossed LOS C/D and reaching E at some critical
locations. Hence the PR needs to be upgraded to have smoother flow of traffic.
2.2.4 Land Use and Roadside Environments
The project road starts from Chittoor and traverses northeast direction to terminate at the outskirt of
Puttur. The following table indicates the distribution of length of Project road and %age Length in
terms of land use and roadside environments. The existing land use within the project influence area is
shown in Fig. 2.1.
Table 2.5: Summary of Land Use
Land Use pattern
Total Length
Urban Built-up Rural Built-up Agricultural Barren
4.0 1.0 28 2.0 35.0
11% 3% 80% 6% 100%

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Fig. 2.1: Land use plan of Mydukur-Jammalmadugu Road

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

2.2.5 Villages and Urban-Built Up Sections


Around 86% length of the project road passes through non-built up area; remaining 14% length
traverses through inhabited area. There are a number of villages and settlements located along the
project road as tabulated below:
Table 2.6: Inhabitation along the Project Road
Chainage Length
S No. Name of Village/Town Remarks
From To ( km )

1 153.0 155.0 2.0 Mydukuru


2 156.0 156.5 0.5 Vishwanadapuram Village
3 163.0 163.5 0.5 Pallavolu Village
4 171.4 178.0 6.6 Prodhutoru Village Existing Bypass
5 178.4 178.6 0.2 Pedasettipalli Village
6 180.0 180.5 0.5 Shankarapalli Village
7 182.0 183.5 1.5 Chauduru Village
8 186.0 186.5 0.5 Salivendula Village

2.3 PROPOSED IMPROVEMENTS


2.3.1 Proposed CW Configuration and Cross Sections
The existing CP road is proposed to be upgraded to 4 lane configuration; the typical cross sections
followed are depicted in Figures 2.2 to 2.4.
Table 2.7 Details the typical cross sections adopted for project road.
Sl
Cross Section Type Description Location / Remarks
No
4-Lane road divided Carriageway 7.25m In major built-up areas. ES area will
4 -Lane road in Built-up
(CW) + 2.5m earthen shoulder (ES) and also be used for utilities. Longitudinal
1 Type-1 Area (Concentric
1.50m Brick Masonry longitudinal drain on drain shall be covered partly wherever
Widening)
both side of 1.2m wide median. required.
4-Lane road divided 7.25m CW + 2.5m ES
4-Lane road in Rural Area Widening on both sides of the
2 Type-2 and trapezoidal unlined drain on both sides
(Concentric Widening) existing CW
of 1.2m median.
4-Lane road divided 7.25m CW + 2.5m ES
4-Lane road in Rural Area Widening on LHS or RHS of the
3 Type-3 and trapezoidal unlined drain on both sides
(Eccentric Widening) existing CW
of 1.2m median.
4-Lane road divided 7.25m CW + 2.5m ES
4-Lane Road in Rural Area New Formation in Realignment
4 Type-4 and trapezoidal unlined drain on both sides
(New Formation) locations.
of 1.2m median.
Embankment Construction Embankment construction with fly ash in Proposed at the sections with
5 Type-5
with Fly ash widening and new formations. embankment height more than 2.0m.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

L AM P PO ST

P RO PO S E D RO W = 2420 0(M in)

BUILT-UP AREA

BUILT-UP AREA
1500 2 500 7 250 1200 7 250 2 500 1500

ES C AR RIAG EW AY C AR RIAG EW AY ES
A NTIG LA RE R AILING
D RA IN U TILITY U TILITY D RA IN
BC 3.0% 2 .5% 2.5% 3.0%
BM D BM

(MIN 1000)

(MIN 1000)
VARYING

VARYING
H FL
P CC X 'X

E XIS TIN G C ARR IA GEW AY


S ELEC TE D SO IL
C BR >10, P I <12
B C 40 mm
S LE CTED S O IL
D B M 50mm W EEP HO LE
W MM E XISTING
B M 75m m (Pa ck age-1) 100M M D IA A T G S B LEVEL
C R U ST B M 65m m (Pa ck age-2)
G SB W MM 2 30m m P C C (M 10)
G SB 150mm
S UB G R ADE S UB G R AD E 500mm
(C B R M IN.7) TY PIC AL C R O SS SECTIO N FOR N O TES :
1 A LL D IM EN SIO N A RE IN MILLIM ETER.
4-LAN E R O AD IN BUILTUP AREA
2 D RA IN S HA LL B E CO VE RE D W H ER E EV ER R EQ UIRED
D ET AIL AT X-X (TY PE -1)

P RO P O SE D RO W =30000

2 0700

2 500 7 250 1 200 7250 2 500

ES C AR RIAG EW AY C AR RIAG EW AY ES
2.5% 2 .5%
3 .0% 3 .0%
2 2

VARYING
(MIN 500)
1 1
1 000

X 'X E XIS TIN G C ARR IA GEW AY


1
B C 40m m 1
BC
D B M 50mm S EL EC TE D SO IL 5 00
D RA IN D BM
B M 75m m (Pa ck age-1) C BR >1 0, P I <12
BM B M 65m m (Pa ck age-2)
60
100 W MM 250mm
1 50
G SB 150m m
W MM
S UB G R AD E 50 0mm T YP IC AL C R O SS SECTION FOR N O TE S:
(C B R M IN. 7) 1. AL L DIM E NS IO N AR E IN M IL LIMETER.
4-LA N E R O AD IN R U R AL A R EA (CO NCENTRIC W IDENING) 2. ES : EA RTHE N SH O U LD ER
(TY PE -2)
D ET AIL AT X-X

Fig 2.2: Typical Cross section for 4-Lane road in Builtup Area and Rural Area (Concentric Widening)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

PROPOSED ROW=30000

20700

2500 7250 1200 7250 2500

ES CARRIAGEWAY CARRIAGEWAY ES
2.5% 2.5%
3.0% 3.0%
2 2

VARYING
(MIN 500)
1 1
1000

EXISTING FORMATION
BC 40mm
500
DRAIN DBM 50mm
BM 75mm (Package-1) NOTES:
BM 65mm (Package-2)
1 ALL DIMENSION ARE IN MILLIMETER.
WMM 250mm 2 ES: EARTHEN SHOULDER
GSB 150mm
SUBGRADE 500mm
(CBR MIN. 7)
TYPICAL CROSS SECTION FOR
4-LANE ROAD IN RURAL AREA (ECCENTRIC WIDENING)

(TYPE-3)

PROPOSED ROW=30000

20700

2500 7250 1200 7250 2500

ES CARRIAGEWAY CARRIAGEWAY ES
2.5% 2.5%
3.0% 3.0%
2 2
1 1

BC 40mm
DBM 50mm SELECTED SOIL
DRAIN DRAIN
BM 75mm (Package-1) CBR>10, PI <12
BM 65mm (Package-2)
WMM 250mm
GSB 150mm
SUBGRADE 500mm
(CBR MIN. 7)
TYPICAL CROSS SECTION FOR

4-LANE ROAD IN RURAL AREA (NEW CONSTRUCTION)

(TYPE-4)

Fig 2.3: Typical Cross section for 4-Lane road in Rural Area (Eccentric Widening and New Formation)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2-9
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

FORMATION WIDTH

ES CARRIAGEWAY CARRIAGEWAY ES
2.5% 2.5%
3.0% 3.0%
2 2
1 1

SELECTED SOIL SUBGRADE 500mm (CBR MIN.7)


CBR>10, PI <12

EXISTING CARRIAGEWAY Fly Ash


BC 40mm Soil Layer
DBM 50mm

200
Fly Ash

1500
BM 75/65mm
WMM 250mm
GSB 230mm
Fly Ash

1500

Selected Earth Cover


as per IRC SP: 58 - 2001

Fig 2.4: Typical Cross section with use of Fly ash in Embankment

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 10
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

2.3.2 Identification of Realignment and Bypass Provisions


There are three locations on the Project Road (PR) which are critical from geometric and land use
point of view. From km 183/00 to 184/00 and from km 185/800 to 186/400 project road passes
through village Dhanvalapadu with sub-standard horizontal geometrics which need improvement.
The details of these locations are discussed below:
Pedasettipalli: Around 600m length, from km 178/200 to km 178/800, project road passes through
very congested area of Peddasettipalli village. There are three reverse curves in this segment. The
ROW varies from 8m to 12m. The houses are abutting the roadway and location is prone to
accidents. The entire village is situated on the south of the project road; on the northern side there
are four-five houses in scattered form.
Consultants have explored the possibility of bypass on left (south) and right (north) of the village.
The take-off and merging points for both alternatives are broadly kept same. Based on the
preliminary examinations of two alternatives and the discussion with the APRDC officials, it was
concluded that Alternative -2, new alignment on RHS (north side of Peddasettipalli village), would be
proposed for the Project.
Kadapa Stone Quarry & Dhanvalapadu village Realignment: The PR road is passing through
Kadapa stone quarry area between km 183/00 to km 184/00. There is deep excavation on both sides
of existing road right, abutting to outer edge of shoulders. The widening of road to four lane,
whether concentric or eccentric, would necessitate construction of retaining wall of more than 15m
height; still it would be a accident prone area. The Consultants explored the possibility to provide
realignment on LHS/RHS of project road. On RHS, realignment is considered more appropriate due
to Penneru River on LHS. This realignment will also bypass the Dhanvalapadu village for Mydukur
bound traffic. A small realignment will be proposed on LHS of Dhanvalapadu village for
Jammalmadugu bound traffic. The proposed realignment is shown in Fig. 2.5.
186100.000
186200.000

186000.000
186300.000

185900.000
186400.000

185800.000
186500.000

185700.000
186600.000

185600.000
186700.000
186800.000

185500.000
186900.000

185400.000
0.000

187000.000

185300.000
187100.000
18770

185200.000
187200.000
.000

185100.000
0.0

187300.000
18700

185000.000
187600

187400.000
187500.000
0.0

0.000
18690

18490

000
.0

800.
800

184
186

0
.00
.0

700
700

184
186

00.0
1866

186200.0
186300.0
186500.0

186400.0

0
.00
0.0

600
18610

184
00.0
1860

00.0

000
1859

500.
184
00.0
1858

00.0
1857

0.000
18440
00.0
1856

00.0
1855

00.0

00
184300.0
1854

00.0
1853

00.0
1852

00
184200.0
00.0
1851

00.0
1850

00
00.0

184100.0
1849

00.0
1848

00.0

00
1847

184000.0
00.0
1846

00.0
1845

00
183900.0
00.0
1844

00.0
1843

00
183800.0
00.0
1842

00.0
1841

0
000.

00
183700.0
184

.0
900
183

.0
800

.000
183600
183

.0
700
183

00
00.0
.0
600

1835
183

.0
500
183

0
.00
400
183
0
400.
183

0
.00
300
183

.000
.0
300

00.0
200
183

1832
183

Fig. 2.5: Realignment at Kadapa Stone Quarry and Dhanvalapadu Village

2.4 CULVERTS AND BRIDGES


The Bridge and culvert inventory was carried out to assess the existing condition and the hydrological
adequacy. The detailed information on all the structural components, HFL, LWL dimensions of all
the components, linear water way, vertical clearances, drainage spouts, handrails etc. are recorded.
There are 107 culverts and 15 bridges on the project road. Some additional culverts have been
proposed depending on the hydrological requirements. A summary of improvement proposals for
cross-drainage structures are given in Table 2.8 and 2.9.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 11
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Table 2.8: Summary of Proposals for Culverts


Type of culverts
Description Total
HP Box Slab
Retained with minor repairs / widening - - 6 6
Reconstruction on Realignment 5 3 - 8
Reconstruction due to poor /dilapidated condition/
27 34 18 79
inadequate waterway
Additional Culverts - - - -
Total 93

Table 2.9: Details of Existing Bridges and Proposal


Existing Arrangement Proposed Arrangement
Sl. No Location Height Proposal Height
Span Span
(ERL-BL) (FRL-BL)
2x3.0+
1 153.420 2.7 Additional -2L 1x8.0 4.5
1x1.5
2 154.450 1x6.0 3.8 Additional -2L 1x6.0 3.8
3 159.350 2x21.0 7.1 Additional -2L 2x21.0 7.1
4 159.980 10x21.6 10.7 Additional -2L 10x21.0 10.7
5 167.665 6x2.0 1.2 Additional -2L 1x12.0 3.2
6 184.205 6x2.0 1.7 Reconstruction-4L 1x12.0 3.5
7 185.020 3x3.6 3.0 Reconstruction-4L 1x15.0 4.6
8 191.290 4x2.0 1.8 Reconstruction-4L 1x15.0 3.1
9 192.135 4x1.5 1.3 Reconstruction-4L 1x15.0 3.6

It is concluded from the above table that 5 out of 9 bridges will be retained as per overall structural
condition. The formation width of new bridges and culverts has been considered as follows:
• For Four lane – 2 x 10.25 m
2.5 IDENTIFICATION OF BORROW AREAS
Extensive survey was conducted to identify borrow areas for locating suitable soil/soil aggregates
mixes to be used in the construction of embankment and sub-grade. Efforts were made to locate
borrow areas near the project road to avoid long haulage of the materials. Similarly, detailed survey
was carried out to identify stone metal quarries of hard stone for use in Granular Sub-base (GSB),
Wet Mix Macadam (WMM), bituminous and cement concrete works.
The following conclusions have been made based on the exploration of potential borrow sources:
• Construction materials are available with in an economical lead;
• Construction materials can be obtained/exploited without any hassles during the implementation
of the project;
• The soil/crushed stone aggregates/ sand etc are exhibiting higher strength properties than
recommended.
• To procure good quality crushed stone aggregate in large quantity, the contractor is required to
install his own crushing plant thus enhancing the quality of the materials; and
2.6 GEOTECHNICAL INVESTIGATIONS
Geotechnical investigations are carried out at proposed bridge locations to explore subsurface
conditions by drilling boreholes to different depths in order to identify the thickness and sequences

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 12
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

of various strata and to ascertain the sub surface profile of soils and bed rock to determine the most
suitable foundation levels of structures.
2.7 HYDRAULIC AND HYDROLOGICAL INVESTIGATIONS
All the hydraulic data for bridges has been collected from the field and it has been analyzed and
studies carried out to determine the adequacy of waterway of the existing bridges proposed to be
retained and new bridges to be constructed as per provisions of IRC:5-1998 and IRC: SP-13. 50 year
return flood was considered.
2.8 ROAD SAFETY REVIEW
The basic aim for road safety review is to identify areas of major concern, including black spots and
accident-prone stretches on project road and to propose measure to be taken for improving the
engineering design with respect to road safety aspects.
Consultants have carried out a detailed reconnaissance along the project roads and identified areas of
major concern, including black spots and accident-prone stretches on each project road. Based on
critical analysis of accident-prone stretches, the observed main causes for accidents are as list below:
1. Inadequate width, of shoulders, varies from 1.0m to 1.5m, which is not sufficient for parking of
disabled vehicles and space for emergency stops for vehicles away from the carriageway.
2. Majority of horizontal curves are not provided with transition curve and do not have sufficient
setback distance and safe stopping distance.
3. The vertical alignment of project roads traverses through plain to hilly terrain and do not have
sufficient safe stopping distance and compatibility between horizontal and vertical alignment is
missing.
4. Lack of segregation of traffic in both direction and lack of access control in built-up area
5. Non-provision of acceleration and deceleration lanes and intersection / junction.
Following measures have been taken up for improve the traffic safety:
1. Geometric Design Aspects
2. Design of Intersections
3. Traffic Control and Road Safety Features
4. Roadside facilities
5. Traffic Calming
A) Geometric Design Aspects
All geometric design elements have been carried out as per Design standards stipulated for Project in
consonance with IRC codal provisions. Comprehensive design standards, which link individual
design elements to best estimates of actual speed have been utilised. The objective is that drivers
must not be presented with the unexpected. The emphasis has been given on maintaining continuity
or giving adequate warning where it could not be made.
Following realignment locations have been identified to improve the horizontal geometrics of the
project road.
Table 2.10: Realignment sections
Realignment Locations Length
Remarks
From To (km)

178.500 179.650 1.150 Peddasettipalli Bypass realignment


183.200 187.550 4.350 Major realignment at Kadapa Stone Quarry
Total(km) 5.500

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 13
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Following embankment raising locations have been identified to improve the vertical geometrics and
submergence locations along the project road.
Table 2.11: Embankment Raising Locations
Sr. Chainage Length of Emb. Height of Emb.
Raising (m) Reason for raising
No. From To Raising (m)
1. 4.100 4.650 550 0.8 Vertical improvement
2. 10.050 10.450 300 0.8 Bridge
3. 11.950 12.300 350 0.8 Vertical improvement
4. 12.650 16.300 3650 1.0 Bypass, viaduct
5. 17.100 17.450 350 1.0 Viaduct
6. 20.500 20.750 250 1.0 Bridge
7. 27.850 28.400 550 1.0 Bridge
8. 29.150 29.400 250 0.7 Vertical improvement
9. 44.100 44.850 750 1.1 Bridges
10. 46.300 46.750 450 1.1 Bridges
11. 47.500 47.750 250 0.7 Vertical improvement
12. 50.500 51.000 500 1.0 Bridge
13. 53.100 53.450 350 0.5 Vertical improvement
14. 63.050 63.350 300 1.1 Bridge
15. 64.100 64.450 350 0.8 Vertical improvement
16. 67.850 68.150 300 0.7 Vertical improvement

Adequate measures have been taken so that the raising if any in settlement areas should be
minimum possible and in no case exceed 0.5m..
The design speed has been kept quite consistent, and speed difference between two consecutive
curves is not exceeded. All horizontal curves are designed for 100 kmph or 80 kmph or the lowest
one is 65kmph, as detailed in table 2.12 below:
Table 2.12: Summary of Proposed Horizontal Alignment
Total No Radius of Curve (m) Design speed (kmph))
of Curves 150-200 200-400 400-800 800 -2000 >2000 65 80 100
70 - 5 12 13 40 - 2 68

All horizontal curves have been designed with proper transition curves and super-elevation runoff.
All vertical curves have been design for minimum stopping sight distance. Due care has been taken to
avoid the raising of profile at urban/builtup locations and in any case the raising has been restricted
to 0.5m.
In built-up areas, the cross-section 1 and 3 (provision of drain and footpath) has been adopted to
segregate the local pedestrians from through motorised traffic.
B) Design of Intersections
Accident data reveals number of accidents at intersection account for almost 30 -40% of all reported
road accidents in India. During the detailed design proposal, all major and minor junctions have been
studied thoroughly with respect to traffic volume and geometric. The important minor junctions
leading to villages and major settlements have been identified and proper junction layouts (including
road markings and traffic signs) have been applied as per IRC-SP: 41-1994. Design of major junctions
has been carried out based on peak hour traffic data. List of major and minor junctions is given
below:
Table 2.13: Summary of Proposed Minor and Major Junctions
Sl. Chainage Type/ Width Road Leads to Type of Remarks

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 14
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

No. Intersection
1 153/000 BT/7 Kurnool/Badwel/ Kadapa + Jn with NH-18
Jammalmadugu/
2 171/400 BT/7 Y Proddutur Bypass take off
Proddutur town
Jammalmadugu/
3 177/400 BT/7 Y Proddutur Bypass end
Proddutur town

C) Traffic Control and Road Safety Features


Traffic control devices and road safety features, comprising of following, plays a key role in
influencing driver behaviour, orientation and information:
• Traffic Signs
• Road Markings
• Delineators
• Road lighting
• Crash Barrier
(i) Traffic Signs
Traffic signs are divided into three broad categories; Warning signs, Regulatory signs and informatory
signs. Warning sign play a crucial role in terms of road safety, in giving advance information about
hazards ahead. Typical examples of warning signs are Curve ahead, Pedestrian crossings, gap in
median etc. Regulatory/ Mandatory signs regulates the side road or through traffic in order to have a
safe movement. STOP, speed limit, NO parking etc, are some of the regulatory traffic signs.
Informatory signs are provided to give information and guidance about the facilities available to the
road users. Village sign boards, Fuel stations, Hospitals etc are some of the information sign boards.
All critical locations were identified after the proposed geometric improvements along the project
road and cross roads, where warning, Regulatory and Informatory signs are required.
Traffic signs have been designed to convey clear and unambiguous messages to road users so that
they can be understood quickly and easily. IRC-67:1977, code for Practice of Road Sign, has been
followed for finalisation of sign installation. On unkerbed roads segments, the extreme edge of the
sign would be 2 to3m from the edge of the carriageway. On kerbed roads it is proposed as not less
than 60cm away from the edge of the kerb.
(ii) Road Markings
Road markings play a very important role in guiding the driver and providing him/ her with the
information necessary to negotiate conflict points on the road network. It is given a high priority for
improving safety. IRC-35: 1997, Code of Practice for Road Markings, provides the recommended
practice for use of road markings. Road markings are lines, words and Symbols attached to the
carriageway or adjacent to the carriageway, for controlling, warning, guiding and informing the users.
Yellow, white and black colours are the standard colours used for marking. Road marking are
classified as longitudinal marking, marking at intersections, marking at hazardous locations, marking
for parking, word messages. The longitudinal marking proposed along the project road as given
below:
Table 2.14: Longitudinal Markings Proposed for the Project Road
Type of line Figure Description
Broken line Broken lines are permissive in character
and may be crossed with discretion, if
traffic permits.

SINGLE BROKEN LINE

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 15
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Type of line Figure Description


Solid lines Solid lines are restrictive in character and
indicate that crossing is not permitted
except for entry or exit from a side road.

SINGLE SOLID LINE


Double solid Double solid lines indicate maximum
lines restrictions and are not to be crossed
except in emergent usage.

PAIR OF SOLID LINES


Combination of In a combination of broken and solid
broken and solid lines, a solid line may be crossed, with
lines discretion, if the broken line is nearer to
the direction of travel. Vehicle from the
opposite directions are not permitted to
cross the solid line.
COMBINATION OF BROKEN & SOILD LINES

Thermoplastic road markings have been proposed considering their long-lasting effect.
(iii) Delineators
The delineators are most likely to be effective on dangerous bends, on approaches to intersections
and on embankments. Though all horizontal curves are design to the IRC standards, delineators have
been proposed for additional guidance and information to the commuter at curves (Radius less that
1000m). Locations along the high embankment have also been provided with delineators. Delineators
with reflectorised panels have been considered.
(iv) Road lighting
Night-time accidents in urban areas can be substantially reduced by the implementation of adequate
street lighting. The stretches of the project road traversing through the built-up/urban areas are
proposed with adequate lighting. Road lighting has also been proposed at all major junctions. One/
Two/ Three arm bracket Sodium vapour lamps have been considered
(v) Crash Barrier
In addition to the adequate provisions of roadway width and roadside design, crash barrier/guard
rails have been proposed to be installed along the roadway edge on either side based on the sections
of the project road having:
• At all the bridge approaches
• Embankment with >3 m height
• Horizontal curves with deflection angle >30 degrees and Radius <=240.
For the embankments upto 3 m height, reasonably flatter side slope of 1 vertical: 3 horizontal or
more would enable erring vehicles to return to the traffic stream. The locations of provision of crash
barrier are given below:
Table 2.15: Locations of proposed Crash Barrier
Sl. No From To Length (m) Remarks
1 178.600 178.800 400 High Embankment
Total (m) 400

D) Roadside Facilities
Following roadside facilities have been provided on Chittoor Puttur road:
• On-street Parking

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 16
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

• Bus Lay-byes and Shelters


(i) On-street Parking
At quite a few locations, project road traverses through built-up areas where small commercial
activities are carried out on both side of the road. The proposed 1.5m paved shoulder may be utilised
for short time parking of the vehicles. This kerbside parking is permitted only if stationary vehicles do
not unduly interfere with free and safe movement of vehicles. Besides, bus laybyes and truck laybyes
are proposed for off-street parking,
(ii) Bus Lay-byes and Shelters
Consultants have identified the location/site for the proposed bus-lay bye for each village or built-up
locations based on the following criteria:
• 18 no.s Bus shelters are proposed near to residences to minimise walking distance and major
intersection/junction should have direct pedestrian links segregated from motorised traffic.
• It should be positioned in straight and level sections of road and should be visible from a long
distance in both directions.
Table 2.16: Location of Bus Shelters
Sl. Location
Description Remarks
No LHS RHS
1 Shelter 153.050 153.100 Mydukuru
2 Shelter 156.350 156.400 Vishwanadapuram Village
3 Shelter 161.100
4 Shelter 162.600 162.650
5 Shelter 168.100 168.150
6 Shelter 170.950 170.900 Prodhutoru Village
7 Shelter 177.800
8 Shelter 177.400
9 Shelter 183.150
10 Shelter 183.350 Chauduru Village
11 Shelter 187.000 187.050 Salivendula Village
12 Shelter 190.650

E) Traffic Calming
Speed is arguably a factor in every accident. Lower speeds reduce both the likelihood of the accident
happening and the severity, if it does occur. Speed reduction benefits have received much attention in
recent years and an international review of speed and accidents concluded that, on an average, each
5km reduction in speed would result in a 22% reduction in fatal accidents.(1 mile leads to 7%)
Traffic calming measures need to be applied in a formal structured manner. All features should only
be constructed where approach speeds are such that all road users can perceive the calming feature
and traverse it safely. They should not be used in isolation but as part of a strategy covering a stretch
of road or an area. Accordingly following two types of Traffic calming measures, i.e Speed humps
and rumble strips have been proposed along the project road.
• Road Humps
• Rumble Strips
(i) Road Humps
Road Humps or Speed breakers are formed by providing a rounded hump of 3.7m width
(17m radius) and 100mm height for the preferred advisory crossing speed of 25kph for general traffic
as per the IRC: 99–1988. The basic material for construction is bituminous concrete formed to
required shape. Road humps have been proposed on minor roads at junctions /intersections with

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 17
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

major roads, School and Hospital zones. Proper signboards and markings are provided to advise the
drivers in advance of the situation. Road humps are extended across carriageway up to the edge of
paved shoulder. Proper signboards and marking are proposed to advise the drivers in advance of the
Road humps.
(ii) Rumble Strips
Rumble Strips are formed by a sequence of transverse strips laid across a carriageway with maximum
permitted height of 20mm. These rumble devices produce audible and vibratory effects to alert
drivers to take greater care and do not normally reduce traffic speeds in themselves. The typical
design details of rumble strips proposed are transverse strips of Pre-mix bituminous concrete 500mm
wide and overall thickness 20mm laid across a carriageway up to the end of paved shoulder. There
will be 6 such transverse strips spaced at 0.5 m c/c. Rumble strips are proposed at:
• Sharp curves with radius less than 170m.
• Transition zones (speed limit zones).
• Village/built-up approaches.
• Sensitive receptors (Schools and hospitals)
Proper signboards and marking are proposed to caution the drivers in advance of the situation.
Photographs of Some of the Activities on Mydukuru - Jammalamadugu Road

2.9 ROAD CONSTRUCTION STANDARDS, NORMS AND GUIDELINES


Following the road construction standards and norms and management procedure has been adopted
to keep the standards and guidelines maintained by the Indian Roads Congress (IRC):
i) Guidelines for Environmental Impact Assessment of Highway Projects, IRC: 104- 1988.
ii) Recommended Practice for Treatment of Embankment slopes for erosion control, IRC: 36-
1974.
iii) Recommended Practice for Borrow pits for Road Embankment for Road manual operation, IRC:
10-1961.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 18
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

iv) Recommended Practice for the construction of Earth Embankments for Road Works, IRC: 36-
1970.
v) Highway Safety Code, IRC, special publication no. 44.
vi) Guidelines on Bulk Bitumen Transportation and Storage Equipment, IRC, special publication 39.
vii) Recommended Practice for Tools Equipment and Appliances for Concrete Pavement
Construction, IRC: 43-1972.
viii) Recommended Practice for use and Upkeep of Equipment, Tools and Appliances for
Bituminous Pavement Construction, IRC: 72-1978.Road Accident Forms A-1 and 4, IRC: 33-
1982.
ix) The factories act 1956 for hygiene and safety requirements of construction workers.
x) Other relevant codes of BIS and National Building Codes.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 2 - 19
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER-3: ENVIRONMENT REGULATORY FRAMEWORK.................................................. 2


3.1 APPLICABLE REGULATIONS ................................................................................................................... 2
3.1.1 Legal Framework.................................................................................................................................. 2
3.1.2 Key Environmental Laws and Regulations...................................................................................... 2
3.1.3 Environmental Requirements of the State ....................................................................................... 3
3.1.4 Other Legislation Applicable to Road Construction Projects ...................................................... 4
3.1.5 World Bank Environmental Requirements...................................................................................... 5
3.1.6 Summary of Clearance Requirements ............................................................................................... 5

LIST OF TABLES

Table 3.1: Environmental Regulations and Legislations ................................................................................ 2


Table 3.2: Applicability of WB Safe Guard Policies .................................................................................... 5

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 3-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER-3: ENVIRONMENT REGULATORY FRAMEWORK

3.1 APPLICABLE REGULATIONS


The chapter presents a review of the existing institutions and legislations relevant to the project at
the National and State level. The various statutory clearances from various state and central
government authorities and the institutional and legal frameworks are discussed in the following
paragraphs.
3.1.1 Legal Framework
The Government of India has laid out various policy guidelines, acts and regulations pertaining to
environment. The Environment (Protection) Act, 1986 provides umbrella legislation for the
protection of environment. As per this Act, the responsibility to administer the legislation has been
jointly entrusted to the Ministry of Environment and Forests (MoEF) and the Central Pollution
Control Board (CPCB)/Andhra Pradesh State Pollution Control Board (APPCB) in the present
context. More details on the legal framework of Government of India and State Government
regulations and clearance procedures are envisaged in the following paragraphs.
3.1.2 Key Environmental Laws and Regulations
Table 3.1 presents the environmental regulations and legislations relevant to AP state road project.
Table 3.1: Environmental Regulations and Legislations
SR. Applicable
Act / Rules Purpose Reason for Applicability Authority
No Yes/ No
As all environmental
MoEF. Gol; DoE,
Environment To protect and improve notifications, rules and
1 Yes State Gov. CPCB;
Protection Act-1986 overall environment schedules, are issued under this
SPCB
act.
To provide environmental
This notification is NOT
Environmental Impact clearance to new
NO applicable to Project road, the
2 Assessment Notification development activities MoEF. EIAA
status of the project road is
14th Sep-2006 following environmental
Major District Road.
impact assessment
Reuse large quantity of fly
ash discharged from
Notification for use of fly Thermal plant within 100km
3 thermal power plant to Yes
ash reaches.
minimize land use for
disposal
Coastal Regulation
Protection of fragile Road is not located along
4 Zone(CRZ) Notification NO
coastal belt coastal belt
1991 (2002)
National Environment Address Grievances
Grievances if any will be dealt
5 Appellate Authority Act regarding the process of Yes NEAA
with, within this act.
(NEAA) 1997 environmental clearance.
This act will be applicable to as
Set out rule for there will be acquisition of land Revenue
The Land Acquisition
6 acquisition. of land by Yes for widening, geometric Department State
Act 1894 & 1989
government improvements and Government.
realignments.
Moef Circular on
Defining “marginal land’
Marginal Land Super seeded by 2006
7 acquisition relating to the NO MoEF
Acquisition and Bypasses notification.
1997 Notification
1999
The Forest
(Conservation) Act 1927 To check deforestation
Forest
The Forest by restricting conversion NO forest area within the
8 NO Department,
(Conservation) Act. 1980 of forested areas into project influence area.
GoAP
forest (conversion ) Rules non- forested areas
1981
MoEF circular (1998) on
linear Plantation on
Protection / planting
roadside, canals and
roadside strip as Roadside tree plantation in
railway lines modifying
9 avenue/strip plantations NO Andhra Pradesh does not comes MoEF
the applicability of
as these are declared under the forest act.
provisions of forest
protected forest areas.
(Conversation) Act, to
linear Plantation

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 3-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

SR. Applicable
Act / Rules Purpose Reason for Applicability Authority
No Yes/ No
Chief Conservator
To protect wildlife
This act is NOT applicable as Wildlife, Wildlife
Wild Life Protection through certain of
10 NO there is NO points of wildlife Wing, Forest
Act 1972 National Parks and
crossings along project corridor. Department,
Sanctuaries
GoAP.
To control air pollution by This act will also be applicable
& Transport controlling during construction; for
Air (Prevention and
emission of air obtaining NOC for
11 Control of Pollution) Yes SPCB
Department. pollutants as establishment of hot mix plant,
Act, 1981
per the prescribed workers' camp, construction
standards. camp, etc.
To control water
This act will be applicable during
Water Prevention and pollution by controlling
construction for (establishments
12 Control of Pollution) discharge of pollutants as Yes SPCB
of hot mix plant, construction
Act1974 per the prescribed
camp, workers' camp, etc.
standards
This act will be applicable as
The standards for noise for
Noise Pollution vehicular noise, to assess for
day and night have been
13 (Regulation and Yes future years and necessary SPCB
promulgated by the MoEF
Control Act) 1990 protection measure needs to be
for various land uses.
considered in design.
Archaeological Dept
Gol, Indian
Ancient Monuments This act not applicable as
Conservation of cultural Heritage Society and
and Archaeological project road is not close to any
14 and historical remains No Indian National
Sites and Remains Ancient Monument declared
found in India Trust for Art and
Act1958 protected under the act.
Culture Heritage
(INTACH).
Protection form Contractor need to stock
Public Liability and
15 hazardous materials and Yes hazardous material like diesel, SPCB
Insurance Act 1991
accidents. Bitumen, Emulsions etc.
Safe transportation,
For transporting and storing Chief controller
16 Explosive Act 1984 storage and use of Yes
diesel, bitumen etc. of Explosives
explosive material
Minor Mineral and For opening new Regulate use of minor minerals
17 Yes District Collector
concession Rules quarries. like stone, soil, river sand etc.
Central Motor Vehicle These rules will be applicable to
To check vehicular air Motor Vehicle
18 Act 1988 and Central Yes road users and construction
and noise pollution. Department
Motor Vehicle Rules1989 Machinery.
To maintain ecological
National Forest
stability through This policy will NOT be Forest
Policy1952
19 preservation and NO applicable as NO forest area Department, Gol
National Forest
restoration of biological within the CoI. and GoAP
Policy(Revised) 1988
diversity.
The construction of project
The mining act has been road will require aggregates.
Department of
20 The Mining Act(1952) notified for safe and Yes These will be procured through
mining, GoAP
sound mining activity. mining from riverbeds and
quarries

3.1.3 Environmental Requirements of the State


Unlike other states, in A.P. the road side plantation within the right of way comes under the
authority of R&B Department. But for felling and transportation of Trees, permission has to be
taken from forest department at DFO level, under A.P. WALTA Act 2002.
Andhra Pradesh Water, Land Trees Act, (WALTA) 2002
The Act came into force on April 19, 2002 with an objective ” to promote water conservation,
and tree cover and regulate the exploitation and use of ground and surface water for
protection and conservation of water sources, land and environment and matters, connected
therewith or incidental thereto”.
SR. Applicable
Act / Rules Purpose Reason for Applicability Authority
No Yes/ No
To promote water Tree cutting and transit
1 WALTA Act 2002 conservation, and tree Yes permission is required from Forest Department.
cover forest department.

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 3-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

3.1.4 Other Legislation Applicable to Road Construction Projects


Environmental issues during road construction stage generally involve equity, safety and public
health issues. The road construction agencies require complying with laws of the land, which include
inter alia, the following:
Workmen's Compensaton Act 1923 (the Act provides for compensation in case of injury by
accident arising out of and during the course of employment);
Payment of Gratuity Act, 1972 (gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed 5 years);
Employees PF and Miscellaneous Provision Act 1952 (the Act provides for monthly
contributions by the employer plus workers);
Maternity Benefit Act, 1951 (the Act provides for leave and some other benefits to women
employees in case of confinement or miscarriage, etc.);
Contact Labor (Regulation and Abolitibn) Act, 1970 (the Act provides for certain welfare
measures to be provided by the contractor to contract labour);
Minimum Wages Act, 1948 (the employer is supposed to pay not less than the Minimum
Wages fixed by appropriate Govemment as per provisions of the);
Payment of Wages Ac 1936 (it lays down as to by what date the wages are to be paid, when it
will' be paid and what deductions can be made from the wages of the workers);
Equal Remuneration Act, 1979 (the Act provides for payment of equal wages for work of
equal nature to Male and Female workers and not for making discriminabon against Female
employees);
Payment of Bonus Act, 1965 (the Act provides for payments of annual bonus subject to a
minimum of 83.3% of wages and maximum of 20% of wages);
Industrial Disputes Act, 1947 (the Act lays down the machinery and procedure for resolution
of industrial disputes, in what situations a stike or lock-out becomes illegal and what are the
requirements for laying off or retrenching the employees or closing down the establishment);
Industrial Employment (Standing Orders) Act; 1946 (the Act provides for laying down rules
governing the conditions of employment);
Trade Unions Act, 1926 (the Act lays down the procedure for registation of trade unions of
workers and employers. The trade unions registered under the Act have been given certain
immunities from civil and criminal liabilities);
Child Labour (Prohibition and Regulation) A; 1986 (the Act prohibits employment of
children below 14 years of age in certain occupabons and processes and provides for regulation
of employment of children in all other occupations and processes. Employment of child labour
is prohibited in Building and Construction Industry);
Inter-State Migrant Workmen’s (Regulation of Employment and Conditions of Servlce)
Act, 1979 (the inter-state migrant workers, in an establishment to which this Act becomes
applicable, are required to be provided certain facilities such as housing, medical aid, travelling
expenses from home to the establishment and back, etc.);
The Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and the Cess Act of 1996 (all the establishments who carry
on any building or other construction work and employs 10 or more workers are covered under
this Act; the employer of the establishment is required to provide safety measures at the building
or construction work and other welfare measures, such as canteens, first-aid facilities,
ambulance, housing accommodation for Workers near the workplace, etc.);

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 3-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

The Factories Act, 1948 (the Act lays down the procedure for approval of plans before setting
up a factory, health and safety provisions, welfare provisions, working hours and rendering
information-regarding accidents or dangerous occurrences to designated authorities);
Hazardous Wastes (Management and Handling) Rules, 1989;
Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996.
3.1.5 World Bank Environmental Requirements
The various environmental requirements of World Bank, GOI for the project roads are described
below.
(i) Applicability of various WB safe guard Policies
The World Bank has ten safeguard policies; the details and applicability of the safe guard policies to
the Project road are provided in the Table 3.2.
Environmental requirements of the World Bank are specified in detail in its Operational Policy (OP)
4.01 and other related Operation Policies. In instances in which the procedural and regulatory
requirements differ, the more stringent applies. The World Bank environmental requirements are
based on a three-part classification system.
• Category A-requires a full Environmental Assessment (EA).
• Category B-projects require a lesser level of environmental investigation.
• Category C-projects require no environmental analysis.
On the basis of data and information collected during field survey and discussion with local expert
and visualise potential associated impact, consultant has categorised this project road as category-B,
which require NO Environmental Assessment.
Table 3.2: Applicability of WB Safe Guard Policies
WB Safe Triggered Reason For Mitigation
Subject Category Documentation
Guard Policy Or Not Its Applicability Measures
Environmental All necessary mitigation EIA and EMP
OP 4.01 Triggered Umbrella policy
Assessment measures incorporated. required.
Eco-sensitive-Forestry
OP 4.04 Natural Habitats Not Triggered Not Applicable Not Applicable
and wildlife related issues
OP 4.36 Forestry Not Triggered Not Applicable Not Applicable Not Applicable
OP 4.09 Pest Management Not Triggered Not Applicable Not Applicable Not Applicable
Road widening will lead to
Involuntary
OP 4.30 Not Triggered loss of livelihoods, loss of Not Applicable Not Applicable
Resettlement
land and Buildings etc
No separate Indigenous
OP 4.20 Indigenous people Not Triggered people development Plan Not Applicable Not Applicable
is required for the Project.
A number of temples,
shrines, churches etc are
OP 4.11 (draft) Cultural Property Not Triggered located adjacent to road Not Applicable Not Applicable
ROW. But NO declared
cultural property exists.

3.1.6 Summary of Clearance Requirements


The summary table showing time requirements for agency responsible for obtaining clearance, and a
stage at which clearance will be required is given below:
SI. Time
Type of Clearance Applicability Project Stage Responsibility
No. Required
1 Environmental Clearance from Not Applicable Pre Construction APRDC -
MoEF/SIAA
2 Forest Clearance Not Applicable Pre Construction APRDC -
3 Tree felling permission under For roadside tree cutting Pre construction APRDC 15 days
WALTA Act
4 NOC and consents under Air, For establishment of Construction stage The Contractor 2-3 Months
Water & Environment Act and construction camp. (Prior to initiation of

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 3-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

SI. Time
Type of Clearance Applicability Project Stage Responsibility
No. Required
noise rules from SPCB any work)
5 NOC and consents under Air, For operating Construction stage The Contractor 1-2 Months
Water & Environment Act and construction plant, (Prior to initiation of
noise rules from SPCB crusher, batching plant, any work
Hot Mix Plant etc.
6 Explosive License from Chief for storing fuel oil, Construction stage The Contractor 2-3 Months
Controller of Explosives, lubricants, diesel etc. at (Prior to initiation of
construction camp any work)
7 Permission for storage of Manufacture storage and Construction stage The Contractor 2-3 Months
hazardous chemical from CPCB Import of Hazardous (Prior to initiation of
Chemical any work)
8 Quarry Lease Deed and Quarry Quarry operation (for Construction stage The Contractor 2-3 Months
License from State Department new quarry) (Prior to initiation of
of Mines and Geology any work)
9 Permission for extraction of Extraction of ground Construction stage The Contractor 2-3 Months
ground water for use in road water (Prior to initiation of
construction activities from State any work)
Ground Water board
10 Permission for use of water for Use of surface water for Construction stage The Contractor 2-3 Months
construction purpose from construction (Prior to initiation of
irrigation department any work)
11 Labor license from labor Engagement of Labor Construction stage The Contractor 2-3 Months
commissioner office (Prior to initiation of
any work)

As mentioned in above mentioned table pre -construction regulatory clearance is required only for
tree felling. In Andhra Pradesh tree-felling permission is obtained from District Committee under
WALTA Act 2002. For this project, the designated officer is Divisional Forest Officer, Kadapa. An
application along with list of trees has already been processed and submitted to concern officials.

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 3-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER 4: BASELINE ENVIRONMENT.................................................................................... 3


4.1 BACKGROUND ............................................................................................................................................... 3
4.2 PHYSICAL ENVIRONMENT....................................................................................................................... 3
4.2.1 Air environment................................................................................................................................... 3
4.2.2 Ambient Air Quality ............................................................................................................................ 6
4.3 LAND ENVIRONMENT ............................................................................................................................... 8
4.4 WATER ENVIRONMENT .......................................................................................................................... 11
4.5 AMBIENT NOISE.......................................................................................................................................... 14
4.6 BIO-ENVIRONMENT.................................................................................................................................. 16
4.6.1 Flora ..................................................................................................................................................... 16
4.6.2 Fauna.................................................................................................................................................... 18
4.7 SOCIO -ECONOMIC ENVIRONMENT................................................................................................. 18
4.7.1 Settlements/Villages:......................................................................................................................... 19
4.7.2 Socio-Cultural Properties and Land Acquisition .......................................................................... 19
4.7.3 Cultural Property Resources ............................................................................................................ 19

LIST OF TABLES

Fig. 4.1: Temperature Pattern .......................................................................................................................................... 4


Table 4.1 Important Climatic Component of the project area................................................................................... 4
Fig. 4.2: Extreme Climatic Conditions ........................................................................................................................... 5
Table 4.2: Ambient Air Quality Monitoring Locations ............................................................................................... 7
Table 4.3: Air Quality Monitoring Results..................................................................................................................... 7
Table 4.4 Geological Formations of PIA....................................................................................................................... 8
Fig. 4.3: Physiography ....................................................................................................................................................... 9
Fig. 4.4: Quarry Chart – Sand and Stone Aggregates................................................................................................. 10
Table 4.5: USDA Soil Classification ............................................................................................................................. 10
Table 4.6: Locations of the Soil Sample Analysis ....................................................................................................... 11
Table 4.7: Available Nutrients in the Soil Samples..................................................................................................... 11
Table 4.8: Water Quality Monitoring Locations ......................................................................................................... 12
Table 4.9: CPCB Best Use Classification for Surface Water Bodies ....................................................................... 12
Table 4.10: Monitoring Results for selected Surface Water Bodies......................................................................... 12
Table 4.11: Monitoring Results for selected Ground Water Sources...................................................................... 13
Table 4.12: National Ambient Noise Standards ......................................................................................................... 15
Table 4.13: Equivalent Noise Level Data .................................................................................................................... 15

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Table 4.14: No. of Trees per Km. on Both Sides....................................................................................................... 16


Table 4.15: Social and Economic Indicators of the Project Districts ..................................................................... 19
Table 4.16: Settlement along the Project Road ........................................................................................................... 19
Table 4.17: Type and Number of structures under Impact ...................................................................................... 19
Table 4.18: Total Cultural Property Resources in Project Road .............................................................................. 19

LIST OF FIGURES

Fig. 4.1: Temperature Pattern .......................................................................................................................................... 4


Fig. 4.2: Extreme Climatic Conditions ........................................................................................................................... 5
Fig. 4.3: Physiography ....................................................................................................................................................... 9
Fig. 4.4: Quarry Chart – Sand and Stone Aggregates................................................................................................. 10

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER 4: BASELINE ENVIRONMENT

4.1 BACKGROUND
Previous chapters have highlighted scope of environmental assessment, existing features of the road
and proposed improvement, methodology and regulations applicable to environmental assessment.
In this chapter an attempt has been made to prepare a baseline environmental setting so as
applicability of Government of India (GoI) regulatory requirements as well as environmental
management practices of operational procedure of World Bank could be envisioned. Based on the
existing environmental scenario potential impacts of road improvement will be identified and
accordingly management plan will be proposed in forthcoming sections. The baseline environmental
conditions will help in comparing and to monitor the predicted negative and positive impacts
resulting from the project during construction and operation phases.
Data was collected from secondary sources for the macro-environmental setting like climate,
physiography (Geology and slope), biological and socio-economic environment. First hand
information have been collected to record the micro-environmental features within and adjacent to
the project corridor. Collection of first hand (Primary) information includes preparation of base
maps, extrapolating environmental features on proposed road design, tree inventories, location and
measurement of socio-cultural features abutting proposed road.
Data was also recorded at sites used for extraction of materials for construction but generally outside
the project corridor e.g. borrows areas and quarries. Ambient Air, Noise and water quality samples
were collected at important locations in terms of environment quality to prepare a baseline database.
Consultation was another source of information to explain local conditions like submergence, recent
floods etc. However these consultation results were largely based on short term memories like
information on floods, submergence but still it was helpful in comparing secondary information.
Following section describes the nature, type and characteristics of the physical, biological, cultural
and socioeconomic components along the project roads.
4.2 PHYSICAL ENVIRONMENT
4.2.1 Air environment
Air quality is relatively free from pollution along the project road traversing through agrarian rural
and small semi urban areas. As a part of the Environmental Impact Assessment (EIA), climatic
component has been studied to establish the benchmarks to understand air quality in the project
area.
4.2.1.1 Climate
Among all other physical factors, Climate is the most important factor-influencing environment
because it plays a vital role in determining the evolution of landforms (erosion, soil characteristics),
types of flora and fauna (ecological diversity), the productivity of ecosystems as well it has an
influence on the pollution loads on the environment. Rainfall, temperature, and winds are the
principal climatic components that serve to transport, disperse various forms of pollution into the
atmosphere and on the ground.
The characteristics of these climatic components (temperature, rainfall and winds) are averaged for
comparatively longer period (about 50 years) to establish a general pattern in the project area.
In general, the climate of project influence area (PIA ) of APRSP is classified as tropical(winterless)
but for the purpose of Environmental Assessment, the climate of the PIA has been divided into
following distinct seasons:
1. Rainy – October to Jannuary
2. Summer – March to June (hot and sunny)
3. Summer – End July to September(Hot and cloudy)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

However for the baseline environment of the project, road under study has only two distinct
seasons. (i)Hot season, (ii) Rainy season and. During rainy season the project area is more or less
similar to monsoon and called as (Am), whereas in dry season it is more like savannah (As) with
distinct hot season.
The various climatic factors such as temperature, humidity and rainfall pattern in the project area
have been discussed in detail in the following sections. Following section deals about.
Temperature: May is the hottest month with mean monthly temperature of 40 0C in this area. The
mean daily temperature during summer is as high as 40 0C during March to June (Table 4.1). The
temperature pattern of the project area will be useful as monitoring indicator especially during
construction period near hot mix plants and stone crushers. December and January are
comparatively the coolest months with average mean monthly temperature < 30 0C. But no months,
the mean monthly temperature goes below 18 degree centigrade.

Fig. 4.1: Temperature Pattern

Humidity: The nature and characteristics of the pollutants will vary with change of the humidity in
the atmosphere. Fog provides possibility for suspended particles to coalesce and also enhances
chemical reaction of the gaseous pollutants. The relative humidity is high during North East
monsoon season as well as during south west monsoon season and in remaining period of the year
the air is generally dry (Table 4.1). The relative humidity is the lowest during summers when it
reaches as low as 32% (March) and during monsoon it goes to as high as 71% (Oct).
Table 4.1 Important Climatic Component of the project area
Temperature(0C) Relative Humidity (%) Wind Speed
Month
Max Min 8.30 17.30 M.W.S/km(24 hrs)
January 32.5 18.3 69 42 7
February 36.9 21.5 63 38 7
March 39.5 25.2 66 32 7
April 39.3 26.7 62 43 7
May 40.7 27.8 59 36 7
June 38 25.3 58 42 7
July 34.3 25 65 42 7

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Temperature(0C) Relative Humidity (%) Wind Speed


Month
Max Min 8.30 17.30 M.W.S/km(24 hrs)
August 33.4 2439 69 57 7
September 32.5 24.5 69 63 7
October 30.6 23.7 71 66 7
November 29.8 19.1 68 65 7
December 29.9 18.3 66 66 4

Precipitation: October to January is the rainfall season. During the rainy months, the area receives
almost 70% of the total rainfall. March to June is dry period for the project area. No rainy days is
found during these months. However extreme climatic event like cyclones/depression do form
occasionally. Figure 4.1 has shown value of extreme climatic conditions for the project road.
Annual Rainfall (mm)
Sr.
Description Actual
No. Normal Deviation
2005-06
1 Southwest Monsoon (June to September) 330 394 -16
2 North East Monsoon (October to December) 464 251 85
3 Winter Period (January & February) 0 3 -100
4 Hot Weather Period (March to May) 80 52 54
5 Total (June to May) 874 699 25
6 Annual Average 874 - 25

Fig. 4.2: Extreme Climatic Conditions

The average annual rainfall in the area is 874 mm. Rainfall mainly occurs during the months of SW
monsoon, from July to September. During the rainy months, the area receives almost 90% of the
total rainfall. Rainfall during monsoon is generally caused by depressions from Bay of Bengal. The
rainfall pattern suggests that most of pre-construction activities (mainly earthwork) should be
completed before monsoon season to avoid excessive consumption of water.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Wind: Wind speed and wind direction have a significant role on the dispersion of atmospheric
pollutants and therefore, the air quality of the area. Ground level concentrations for the pollutants
are inversely proportional to the wind speed in the down wind direction, while in upwind direction
no effect will be observed and in cross wind direction partial effect due to the emission sources is
observed.
The wind flow pattern in the project area is governed by continental location of project area, rain
shadow region of western Ghat thus a relatively drier monsoon winds from Arabian Sea. However,
weaker depression from Bay of Bengal also influences wind direction. During October and
November, wind blows from all directions. Summer month’s evidences pre-monsoon winds called
mango showers generally in the month of April and May. Therefore a definite direction of wind like
seasonal reversal of wind pattern (monsoon) is not found in the project area. (See figure 4.2)
Cloud Cover: It can be observed that clear sky will prevail from March to May and more cloud
cover will prevail during the month of July and August without rainfall. Monsoon weather condition
and cloud covers is guided by monsoon winds (retreating monsoon). Cloud in these period do not
prolong for longer period.
4.2.2 Ambient Air Quality
Ambient air quality refers to the background air quality levels in a region, characterised by
concentrations of various pollutants in the atmosphere. The presence of air pollutants and
their concentrations depends on the type of polluting sources, and other factors that influence
their flow and dispersion. In most cases vehicular emissions are the predominant source of air
pollution. Existing ambient air quality data on various sections of the project corridors was
collected to establish a baseline database. The aim was to identify areas that already have high
pollution levels or are expected to experience so, on account of the road project, and to
design adequate mitigation measures, as applicable.
The activities, which generate modify atmospheric air quality, are transportation (i.e., motor
vehicle emissions, which are addressed in this study); industry; domestic and construction.
The principal sources of air pollution due to road projects are hot mix plants and machineries
used during construction phase and the vehicles that ply over it during the operation phase.
The major pollutants of significance to roadside air quality, on account of vehicular emissions,
are suspended particulate matter (SPM), Respirable particulate matter (RPM), sulphur dioxide
(SO2), nitrogen oxides (NOx), hydrocarbons (HC), carbon-monoxide (CO).
Dispersal of pollutants depends upon factors like prevailing wind direction and other weather
conditions, height of the source, and characteristics of roadside plantation and presence of
other sinks along the project corridor.
Ambient air quality standards : GoI Air Pollution Control standards, formulated by MoEF,
were set in 1981. The statutory bodies that regulate these standards at the central and state
levels are the CPCB and the SPCB, respectively. The parameters for which standards have
been formulated are SPM, RPM, SO2, NOx, Pb, and CO. Standards for Hydrocarbons have
not been formulated as yet. Threshold emission limits, for all parameters, have been given for
two time periods of Annual Average and 24 hours threshold limit. Separate limits have also
been set for sensitive, residential/rural and industrial land uses (ReferAppendix 8.15).
* denotes annual arithmetic mean of minimum 104 measurements in a year taken twice a week, 24
hourly at uniform interval. “**” denotes 24 hourly / 8 hourly values which should be met 98% of
the time in a year (on 2% of the time, it may be exceeded for less than two consecutive days). “***”
denotes sensitive areas as mentioned in MOEF notification September 2006.
Monitoring locations: Factors that modify generation of these pollutants are traffic
characteristics (volume, speed, composition and mode), vehicle maintenance levels, road
geometry and areas of congestion. To assess the ambient air quality along the project corridors,
ambient air quality monitoring was carried out at identified locations. The monitoring locations were
selected based on the sensitivity of the receptors to vehicular traffic and to obtain baseline
concentrations of the various representative land uses along the corridors.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

24 hourly continuous air quality monitoring was carried out for pollutants such as Respirable
particulate matter (RPM), suspended particulate matter (SPM), Sulphurdioxide (so2), oxides of
nitrogen (NOx), carbon monoxide (CO) and hydrocarbons. The methodology adopted for the
monitoring of the various pollutant parameters is presented in appendix. Locations of the
monitoring stations are presented in Table 4.2.
Table 4.2: Ambient Air Quality Monitoring Locations
Location Location of Land use along
Chainage Description of Sampling Locations
Code Monitoring Stations the settlement
AQ-1 Jammalamadugu Commercial Km 194/500 on the roof top of shop of Mr. Srinivas

AQ-2 Chauduru Commercial Km 183/800 on the roof top of house of Mr. Subash
on the roof top of house of Mr.
AQ-3 Peddasettipalli Commercial Km 179/200
Rameshwaram
on the roof top of shop cum residence of
AQ-4 Proddatur Residential Km 172/500
Mr.Suresh
on the roof top of house of Mr.
AQ-5 Maidukuru Commercial Km 153/000
Madhusudan Rao

Monitoring results: The results of analysis of air samples are presented in the following tables. In
general for all monitoring stations the RPM values were monitored in the range 120-140 µg/m3
with an average value of 130 µg/m3 . While comparing with the National Ambient Air Quality
(NAAQ) Standard of 100-150 µg/m3 (24-hourly) for Residential, Rural and Industrial Areas
prescribed by Central Pollution Control Board (CPCB), all the monitored RPM values were found to
be very well within the stipulated value for industrial areas but above the limit of rural areas. This is
because of high vehicular location and dryness of the areas. SPM values were ranging from 345-
400µg/m3. While comparing with the NAAQ Standard of 200 and 500 µg/m3 for Residential, Rural
and other Areas, and industrial areas all the monitored SPM values were found to be well within the
limit. Higher concentration of SPM is because of semi arid conditions and loose soil along the
project area.
Table 4.3: Air Quality Monitoring Results

Location Pollutants concentration in µg/m3 mg/m3 PPM


Sr. Name of Date of
Code
No. Location monitoring RPM SPM SO2 NOx Pb CO HC
Jammalamadu
1. gu at junction AQ -1 20.10.2007 142.35 398.14 21.18 30.76 0.47 1.7 52.4
point
2. Chauduru AQ-2 20.10.2007 121.43 349.72 17.23 26.18 0.37 1.5 39.1

3. Peddasettipalli AQ-3 21.10.2007 135.88 389.84 20.14 32.81 0.39 1.6 42.3
Proddatur at
4. AQ-4 21.10.2007 131.34 379.67 19.56 29.45 0.34 1.3 28.6
junction point
Maidukuru at
AQ-5 22.10.2007 134.26 381.37 22.14 31.80 0.42 1.4 34.1
5. junction point

The maximum SO2 and NOx levels monitored were 22.14µg/m3 and 32.81 µg/m3 respectively.
While comparing with the NAAQ Standard (80 µg/m3), the monitoring results were found to be
well within the limits. The maximum CO concentration monitored was 1.7mg/m3 and most of the
CO levels were monitored below the detectable limit of 2 mg/m3. While comparing the NAAQ
Standard -, the monitored CO levels were found to be well within the limit. All HC values were
found to be below the detectable limit of 65 µg/m3.
All Particulate Lead values were found to be above the detectable limit of 0.01 µg/m3 and within the
NAAQ Standard of 1.0 µg/m3 (24-hourly).

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

4.3 LAND ENVIRONMENT


The land environment describes the baseline aspects of the nature and geomorphic features, soil
conditions and quality, borrow and material resources and land use Characteristics. Portion of this
section has analyzed role of these landscape features in road improvement.
Geo-morphological aspects : The landscape falls in the contour of 150-600 meter of peninsular
plateau. The project area is an old pen plain, made of deeply dissected plateau of archaean gnesis and
granite for most of the part with hillocks of small relief’s. Weathering of rocks has has been resulted
into senile topography with dissected plateau and remainant of hillocks. The project road through
out passess at the foothills section in rolling terrain.
Penneru river flows along the project road and Kunderu river crosses the project road near
Chapadu town. The main water course for the project road is from Kurnool - Cuddapah canal
and Eturu canal which crosses the project road near chalivendula.The drainage pattern
suggests that easterly flow of the course of river is micro-managed by local relief of the region
with many rivulets criss-crossing the project area. Since the river passes through dry country
with intense but low rainfall, the fluvial topography is governed by flow of water such as flash
flood kind of thing absent from the project area. (Hydrological aspects have been attached
with this chapter as figure 4.3).
Geology: The project region (PIA of APRSP) contains a wide variety of geological formation
ranging from oldest Dharwar Schiest to the recent alluvium of coastal colluviums. The older rocks
have been subjected to erosion, which resulted in different type of topography in the project area.
Thus these geological formations have undergone process of evolution and are evident from its
footprints in varied topography in the region.
Table 4.4 Geological Formations of PIA
Formations :: Age
The Dharwars :: Lower Pre-cambrian-around 2500 million years.
The Archaean Gneisses :: Lower Pre-cambrian-more than 500 million years.
The Charnockites :: Pre-cambrian-mote than 500 million years.
The Khondalites :: Pre-cambrian-more than 500 million years.
The cuddapahs :: Upper Pre-Cambrian-more than 500 million years.
The Kurnools :: Lower Paleozoic-500 to 300 million years.
The Lower Gondwanas :: Upper Carboniferous-250 to 190 millions years.
The Upper Gondwanas :: Middle Triassic-Lower Cretaceous-170 to 100 million years.
The Deccan Traps :: Mesozoic-Lower Tertiary-150 to 50 million years.
Tertiary Formations :: Miocene-Pliocene-35 to 15 million years.
Laterites :: Pleistocene-1 million to 25000 years.
Alluvium :: Recent-25000 years to the present.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Fig. 4.3: Physiography

As stated earlier, also the partly metamorphosed archaeans or peninsular gneisses dominate the rock
formation in the project area (proposed road). Some of the topopgraphy is of sedimentary
formation also. Most of the length of the road is passing through rolling terrain.
Borrow Areas: All along the project road borrow / material sources have been identified. There are
four borrow areas identified along the proposed project road. The samples were collected from these
sources to carry out the necessary tests to study the adherence to the requirements of the MORTH
specifications and to establish the suitability and availability of borrow areas for embankment, sub
grade and shoulder construction. In addition to these details, the quantum of the materials available
and the lead distances from the project road were also collected which would be useful while arriving
at the detailed rate analysis during the PPR stage. The details of the borrow sources identified is
given in figure below. The location map of borrow areas is shown in Figure 4.4.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-9
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Fig. 4.4: Quarry Chart – Sand and Stone Aggregates

Soil : The project region (PIA of APRSP) has a wide variety of soils, which are broadly classified in
the table below. The soil is dominated by the zonal soil developed on the rocks in-situ, and consists
of Entisols, Inceptisol, Alfisols and Oxisols. Azonal soil is confined to river basin only. (Table 4.5)
Table 4.5: USDA Soil Classification
CLASSIFICATION AS PER THE SEVENTH APPROXIMATION (USDA
Traditional Classification)
Nomenclature
Order Sub-group
Zonal
Association fo Entisols, in-ceptisols,
Red Sandy Soils Ustorthents, Ustochrepts and Rhodustalfs
Alficols
Red Loamy Soils (shallow
Association of Alfisols and Entisols Hapustalfs and Ustrorthents
to moderate)
Alfisols Hapustalfs and Ustrorthents
Laterite Soils Oxisols Hapluorthox
Intra – Zonal
Deep Black Soils Vertisols Chromusterts and Pellusterts
Medium Black Soils Vertisols and Inceptisols Chromusterts and Tropovertepts
Predominantly Chronomusters and
Mixed Red and Black Soils Predominantly Vertisols
Pellusterts
Azonal
Haplaquents, Ustifluvents and
Deltaic Alluvial Soils Entisols and Vertisols
Chromusterts
Coastal Alluvial
Coastal Sandy Entisols Ustipsamments and Quartzipsamments
Skeletal Soils … …

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-10
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

However, the project road is the central part of peninsular plateau, therefore most of the stretches
having zonal and intra –zonal soil. (Table 4.6).
Table 4.6: Locations of the Soil Sample Analysis
Sr.
Location Code Description of the Monitoring location Chainage Type of Land
No.
In the field of Mr. Munni Chilla Reddy at Agricultural land
1. SQ-1 156/200
Vishwanathapuram
2. SQ-2 In the field of Mr Nal Reddy at Pallavolu 163/000 Agricultural land
3. SQ-3 In the field of Mr. Nagaraj Reddy at Lingapuram 168/500 Agricultural land
4. SQ-4 In the field of Mr.Baskar Reddy at Bollavaram 176/800 Agricultural land
5. SQ-5 In the field of Mr. Poeha at Chalivendula 186/100 Agricultural land
(Source: Consultants study, 2007)
The soil analysis results indicate that the soil in the area is brown to light brown in color and red at
few locations. Soil pH plays a very important role in the availability of nutrients. The composition of
the soil microbial community is also dependent on the soil pH. Soil can be classified as alkaline in
one sample location and acidic at remaining three location. Salt concentration is directly proportional
to the osmotic pressure, which governs the process of osmosis in soil – plant system. NPK contents
and Organic Matter was found to be in significant levels.
Table 4.7: Available Nutrients in the Soil Samples
Sr. RESULTS
Parameters
No. SQ-1 SQ-2 SQ-3 SQ-4 SQ-5
1. PH 7.29 7.10 7.17 6.58 8.05
2. Alkalinity meq/100gm 0.45 1.1 0.78 1.0 0.98
Dark Dark Dark
3. Colour Red Brown
Brown Brown Brown
4. Textural Class SL SL SL SL CL
i) Sand % 52 55 51 48 30
ii) Silt % 27 24 28 28 32
iii) Clay % 21 21 21 24 38
5. Nitrogen Av.( Kg/ha) 389.47 411.05 378.18 253.35 251.17
6. Phosphorous Av. (Kg/ha) 47.39 38.65 45.27 32.14 24.63
7. Potassium Av. (Kg/ha) 127.15 145.08 134.55 117.84 109.35
8. Total Organic Carbon % 0.54 0.62 0.55 0.36 0.32
9. Lead (mg/kg) 0.001 0.004 0.002 ND 0.006
10. Arsenic (mg/kg) ND ND ND ND ND
11. Oil & Grease (mg/kg) 0.06 0.08 ND ND ND
(Source: Environmental monitoring, 2007)
The proposed project may cause soil erosion and variant compaction of soil (due to movement of
heavy equipment) during the construction phase. A management plan to minimize the soil erosion
impact and mitigate the problems will be required, given the high NPK and organic content the top
soil protection is also one of the key measures to be considered.
4.4 WATER ENVIRONMENT
As mentioned in earlier section also, Penneru river and Kunderu River near chapadu town and
Kurnool Cuddapah canal and Eturu canal drains the project area. Many groundwater sources such as
wells and hand pumps are located on both sides of the existing road. The proposed project may
contaminate the surface waters during the construction, operation as well as maintenance phases. A
plan for monitoring and mitigation will, therefore, be required to avoid the pollution or deterioration
of the water sources.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-11
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Five locations were selected along the proposed project length for monitoring of existing water
quality in the area. Two of these are surface water bodies and three are ground water sources. The
details of the monitoring points are given in Table 4.8.
Table 4.8: Water Quality Monitoring Locations
Location Code Name of Water body Type of Water Body Chainage
SW1 Chauduru – Penneru River Surface water Km. 183/800
SW2 Chapadu – Kunderu River Surface water Km. 162/500
Jammalamadugu – Hand Pump near
GW1 Ground water Km. 194/500
Panchayat office
Public Tap in front of shop of Mr. Suresh at
GW2 Ground water Km. 172/500
Proddatur
Hand Pump in front of house of Mr.
GW3 Ground water Km 153/000
Srikanth Reddy at Maidukuru
(Source: Environmental monitoring, 2005)
Water Quality Standard
The rivers, nallahs and ponds located along the proposed project road are a source of water for the
local inhabitants, for domestic as well as agricultural uses. An analysis of their present status and the
quality of the water has been done. They have been classified as per the CPCB classification norms
for best use as shown in Table 4.9.
Table 4.9: CPCB Best Use Classification for Surface Water Bodies
Parameters Class A Class B Class C Class D Class E
1. pH 6.5–8.5 6.5–8.5 6.0-9.0 6.5–8.5 6.5–8.5
2. Dissolved oxygen (as O2), mg/l, min 6 5 4 4 -
3. BOD, 5 days at 20° C, max 2 3 3 - -
4. Total coliform organism, MPN/100 ml,
50 500 5000 - -
max
5. Free ammonia (as N), mg/l, max - - - 1.2 -
6. Electrical conductivity, µmhos/cm, max - - - - 2250
7. Sodium absorption ratio, max. - - - - 26
8. Boron (as B), mg/l, max. - - - - 2

Class A: Drinking water source without conventional treatment but after disinfection
Class B: Outdoor bathing (organized)
Class C: Drinking water source after conventional treatment and after disinfections
Class D: Propagation of Wild life and Fisheries
Class E: Irrigation, Industrial Cooling, and Controlled Waste Disposal
Below E: Not meeting A, B, C, D & E Criteria
Water Quality Variation along the Project Road
Surface Water Quality: pH of the surface water was found to be in the range 7.48-7.59 along the
Corridors. Total hardness is found 159 at Penneru River and 154 at Kunderu River. Lead contents
were found to be below the detection limit. In general, surface water quality along the Corridors is
good and complies with CPCB Surface Water Quality norms. Details of water quality features are
mentioned in table below.
Table 4.10: Monitoring Results for selected Surface Water Bodies
Sr. Surface Water Results
Parameters
No. SW -1 SW-2
1. Color (Hazen) 4 2

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-12
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sr. Surface Water Results


Parameters
No. SW -1 SW-2
2. Taste Agreeable Agreeable
3. Odour Odourless Odourless
4. Temperature (0C) 18.5 20.0
5. PH 7.52 7.82
6. Turbidity (NTU) 3.8 1.8
7. Conductivity (µ mhos/cm) 211 487
8. Alkalinity (Ca Co3) (mg/l) 62 65
9. Hardness as(Ca Co3) mg/l 159 154
10. Chlorides( mg/l) 17.4 9.8
11. Fluorides (mg/l) 0.33 0.18
12. Nitrates (mg/l) 1.35 0.88
13. Iron (mgl) 0.15 0.12
14. Coliform (MPN/100ml) 9 17

These monitoring results would form the basis for monitoring the construction & post construction
impacts.
Ground Water
Ground water is a major source of domestic as well as agricultural water supply in the area. The
major groundwater use in this region is for irrigation. Minor irrigation tanks, dry river beds and deep
hand pumps are source of ground water in the project area. The results of analysis of water samples
are presented in Table 4.11.
Table 4.11: Monitoring Results for selected Ground Water Sources
Sr Ground Water Results
Parameters
No. GW-1 GW-2 GW-3
1. Color (Hazen) Colourless Colourless Colour less
2. Taste Agreeable Agreeable Agreeable
3. Odour Odourless Odourless Odourless
4. Temperature (0C) 17.5 18.0 19.5
5. PH 6.98 7.32 7.23
6. Turbidity (NTU) 0.5 1.0 0.2
7. Conductivity(µ mhos/cm) 389 454 428
8. Alkalinity (Ca Co3) (mg/l) 56 58 49
9. Hardness as(Ca Co3) (mg/l) 154 155 131
10. Chlorides( mg/l) 34.52 38.75 42.86
11. Fluorides (mg/l) 0.58 0.67 0.47
12. Nitrates (mg/l) 0.48 0.35 0.25
13. Iron (mgl) 0.015 0.018 0.036
14. Coliform (MPN/100ml) 4 6 3

Ground Water Quality: pH of the ground waters was found to be in the range 6.98-7.32 along the
Corridors. Total alkalinity content was ranging from 49 mg/l (Maidukuru) to 58 mg/l (Proddatur).
Chloride values were analysed in the range 34.52 – 42.86mg/l. The ground water can be used for
drinking after suitable treatment and disinfections.
Flooding / submersible locations:
The submersible sections located in the stretches are mentioned in chapter 2. These submerged
stretches are because of rolling terrain of the project road. These stretches need to be raised above
HFL in accordance with the provisions of IRC – 37, 2001.
List of embankment raising sections

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-13
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sr. Chainage Embankment Raising


Reason for raising
No. From To Length (m)
1. 154.300 154.550 250 Culvert & Bridge
2. 157.750 158050 300 Vertical Improvement
3. 158.200 159.300 1100 Culvert & Bridge
4. 159.400 159.650 250 Vertical Improvement
5. 160.100 160.250 250 Bridge
6. 165.900 166.450 550 Vertical Improvement
7. 166.800 167.200 400 Vertical Improvement
8. 167.400 167.850 450 Bridge
9. 170.950 171.100 150 Vertical Improvement
10. 177.350 177.750 400 Vertical improvement
11. 178.550 179.650 1100 Bypass
12. 180.400 181.450 1050 Vertical improvement
13. 184.050 184.300 250 Bridge
14. 184.850 185.150 300 Bridge
15. 190.050 190.350 300 Culvert
16. 191.100 191.450 250 Bridge
17. 191.750 192.350 600 Bridge
18. 192.900 194.250 1350 Vertical improvement

4.5 AMBIENT NOISE


Road construction results in increase in noise levels due to movement and operation of machinery,
heavy vehicles, loading and unloading of construction materials, apart from high noise levels at the
asphalt plants (90 - 100 dB(A). These activities are intermittent and localised. During the operation
phase, noise is generated from vehicle movement in three ways, namely from the vehicle body parts,
from the tyre-roadway system (also known as the rolling noise) and from the driver behaviour, such
as use of horns.
Noise from the vehicle body parts includes engine, inlet, exhaust, transmission, suspension, gearbox,
cooling fan, during acceleration and chassis, etc. Vehicle condition is very important to this noise
source. The rolling noise/frictional noise (noise from the tyre-roadway system) includes aerodynamic
noise, noise from tyre-road interaction, brakes, etc. The noise level depends upon on the type and
condition of tyres and pavement. At higher speed, these types of noise increase at same rate. At
lower speeds in urban areas, where lower gears are used, noise from the vehicle body parts tends to
be independent of vehicle speed whereas noise from the tyre-roadway system becomes less
important. Driver behaviour contributes to road noise by using vehicle’s horns, sudden breaking on
vehicle speed, depending on the road surface and whether the surface is wet or dry.
The level of noise generated by road traffic depends on the type of vehicle flow, the volume of
traffic, the speed and composition of the traffic, the road gradient and the type of road surface.
Different types of travel patterns indicate the mode of operation of the vehicles. As the flow rate
increases, traffic noise increases to a maximum, thereafter the effect of reducing vehicle speed on
noise predominates. Interrupted traffic flow occurs with lot of interaction between the vehicles and
vehicles are caused to stop or slow down. For decelerating vehicles, the level of noise decreases due
to fall in power output of the vehicle. For accelerating vehicle, initially the noise level increases and
then drops as the speed increases. In the low speed range, noise is independent of vehicle speed.
However in free speed range, i.e., more than 50 km/h a strong relationship prevails between noise
generated and vehicle speeds.
Factors and parameters
The noise from a traffic stream is not constant but varies from moment to moment and it is
necessary to use an index to arrive at a single figure estimate of the overall noise level for
assessment purposes. Variation in traffic volume, vehicle composition and surrounding

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-14
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

commercial and industrial activities are the dominating factors that influence the propagation
of noise. Energy equivalent noise level Leq (in dB(A)) was the primary parameter selected.
Data collection, tabulation and analysis
Noise monitoring along the various corridors of Phase IIB was carried out for 24 hours at
each site selected. At least 40-50 readings were recorded over a measuring period of 5-10
minutes each hour. Noise levels were recorded at all settlements where ambient air monitoring
was carried out. Locations were selected close to the corridor so as to assess the noise
contribution mainly from traffic. In addition, noise levels were also monitored near a stone
crushing unit to assess the noise generated from the crushing operation and to determine
suitable mitigation measures, especially for the workers. Community noise level assessment
was also made due to the contribution from different activities near corridor. The noise levels
are measures as Leq directly using a noise meter.
Leq is defined as the continuous sound level that, were it to exist over the entire period in
question, would give rise to the some total sound energy as the actually varying sound levels.
It thus represents all energy average, not a sound level average.
L10 refers to the sound level, expressed in dB(A), which is exceeding ten percent of the time
period for which monitoring was carried out.
L50 refers to the sound level, expressed in dB(A), which is exceeding fifty percent of the time
period for which monitoring was carried out.
L90 refers to the sound level, expressed in dB(A), which is exceeding ninety percent of the
time period for which monitoring was carried out.
Ambient Noise Standards
Ambient noise standards were established as per the CPCB/MoEF Gazette Notification dated
26th December 1989. It is based on the ‘A’ weighted equivalent noise level, L eq (Refer Table
4.12).
Table 4.12: National Ambient Noise Standards
Day* limits of Leq Night* Limits of Leq
Area Code Category of Zones
(dB(A)) (dB(A))
A Industrial 75 70
B Commercial 65 55
C Residential 55 45
D Silence Zone ** 50 40
Source: GoI, CPCB, 1989

Monitoring locations & results


The noise measurement has been carried out continuously for a period of 24 hours. At each site
2880 data were recorded, each taken at an interval of 30 seconds of which 1800 data recorded at day
time (07:00 AM to 10:00 PM) and 1080 at night time (10:00 PM – 07:00 AM).(Table 4.13)
Table 4.13: Equivalent Noise Level Data
Leq value dB (A)
Sr Location
Location Day time Night time
No. code
Monitoring CPCB Monitoring CPCB
1. Jammalamadugu NQ-1 52.64 65 39.42 55
2. Chauduru NQ-2 60.44 65 45.26 55
3. Peddasettipalli NQ-3 58.56 65 35.38 55
4. Proddaturu NQ-4 62.15 65 46.16 55
5. Chapadu NQ-5 54.32 65 36.25 55

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-15
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Leq value dB (A)


Sr Location
Location Day time Night time
No. code
Monitoring CPCB Monitoring CPCB
6. Maidukuru NQ-6 57.28 65 38.64 55

The monitored noise levels were ranging from 62.15 dB(A) (Proddatur) to 52.64 dB(A)
(Jammalamadugu) While comparing the MoEF Ambient Noise Norms for different categories, Leq
noise levels at all locations during day time & during night time, were found to be on the higher side
but within limit. As the point or monitoring has a mixed environment of commercial and residential
and generally residence a little far away as compared to shops/commercial establishment, hence the
monitoring data is showing the results within limits.
It may be noted that as the noise survey was carried out at sensitive receptors i.e. School Zone and
Hospital Zone respectively, noise standards is found within the limits at almost all the location.
4.6 BIO-ENVIRONMENT
4.6.1 Flora
Andhra Pradesh contains a great diversity of natural ecosystems ranging from desert, semi-arid lands,
mangroves and coral reefs in the west, to dry deciduous forests in the central and southern zone and
moist deciduous and evergreen forests in the north and coastal areas. Irrespective of such diversity,
forest cover in Andhra Pradesh(23%) is not upto ecological standard (33%). To stop rapid depletion
of the residual forests, the GoA has initiated a number of afforestation and conservation
programmes in recent years including community based forest management (World Bank funded).
The tree cover along the project area is dry deciduous interspersed with moist deciduous type near
the water source or near the villages, they normally yield species belonging to the series Neem, Bagi,
Giriship, Tamrind, Kanuga.
Surveys have been carried out to generate an exhaustive inventory of the existing tree species
(Annexure4.1). Giriship, Acacia, Neem, tamarind and thurai etc are the common species growing in
the area of concern. A summary of the tree inventory is given in the Table 4.14.
The names of the different species found along the proposed project road are listed in table 4.15.
The largest numbers of trees are Tamarind – Tamarindus indica, followed by Neem - Azadirecta
indica,, Kanuga – Pongamia pinnata, Teak – Tectona grandis, Bagi, Thurai etc. The trees can be classified as
large/giant or small according to their girth, being greater than 120 cm in diameter.
Table 4.14: No. of Trees per Km. on Both Sides
Starting Ending
LHS RHS TOTAL Important Species
KMS KMS
156 157 40 38 78 Neem,Bagi,Teak
157 158 47 49 96 Neem,Teak, Bagi , Aggipulla
158 159 27 18 45 Neem,Bagi,
159 160 0 11 11 Neem,Bagi,
160 161 44 23 67 Acasia , Bagi , Aggipulla
161 162 25 32 57 Neem, Bagi , Aggipulla
162 163 21 14 35 Neem,Bagi, Giriship
163 164 41 47 88 Kanuga,Bagi, Giriship
164 165 40 41 81 Neem,Bagi,
165 166 38 50 88 Bagi , Aggipulla
166 167 80 82 162 Neem , Bagi , Aggipulla
167 168 40 25 65 Neem , Bagi , Aggipulla
168 169 26 26 52 Kanuga , Neem
169 170 14 12 26 Neem, Giriship
170 171 BY PASS ALIGNMENT
171 172

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-16
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Starting Ending
LHS RHS TOTAL Important Species
KMS KMS
172 173
173 174
174 175 3 1 4 Neem,Bagi,
175 176 4 2 6 Bagi, Giriship
176 177 0 0 0
177 178 3 8 11 Bagi, Giriship
178 179 10 7 17 Neem,Bagi,
179 180 1 0 1 Neem,
180 181 7 8 15 Tamarind , Acasia
181 182 3 0 3 Neem
182 183 26 7 33 Neem, Acasia
183 184 1 18 19 Neem
184 185 1 0 1 Neem,Bagi,
185 186 17 8 25 Neem,Bagi, Thurai
186 187 2 5 7 Neem,Bagi,
187 188 1 0 1 Acasia
188 189 3 3 6 Acasia
189 190 19 1 20 Neem,Bagi, Giriship ,Acasia
190 191 26 13 39 Neem ,Acasia
191 192 3 0 3 Bagi
TOTAL 613 549 1162
FELLING 372 443 815

The roadside trees are continuous throughout the corridor except some stretches where agricultural
land or undulating topography is observed. Environmental impact survey establishes that average
distance of trees from the centerline of road is 8m-10m on each side. The trees are generally having
good canopy. During environmental impact survey such canopy building stretches were identified.
Many of these stretches are very close to present carriageways. While finalizing the alignment
relevant adjustments has been made to minimize the tree felling, however the tree will be felled
within the toe line of the proposed road with a view to enhance road safety as well as to facilitate
construction.
Giant trees: About 151 trees (83 on LHS and 68 RHS) are substantially larger (more than 180 cm
of girth) generally found within RoW (30 meter Corridor). These trees are considered as “giant
trees” and are found often in groups, close to villages near the water bodies. These trees were
planted long before and without the anticipation of future road widening needs. The species mainly
consist of Tamarind, Neem, and Bagi trees. Often these trees are valuable to the local communities
as non-timber resources. List of giant trees are appended as annexure 4.1

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-17
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Green tunnels observed along the road is at only one location (Km 163.070-163.330) as shown in
figure.
Timber resource along the road: the species encountered in the corridor do not have timber value
except in case of limited species. The trees also do not have any specific relevance including religious
importance and community use. The different species of trees that are present along the project road
are presented in annexure 4.1. There are no endangered floral species identified along the Corridor
of Impact.
Avenue Plantation
The surveys have been carried out along the project road to understand the details of avenue
plantation including the total number of each species, the girth size along the project area.
The reconnaissance survey indicated very few old trees along (more than 20 years old) the project
road also.
4.6.2 Fauna
The reconnaissance survey carried out along the entire project road has evidence of Cattle grazing
and domestic animals etc along the project road. There are no wildlife areas along the project
corridor. There are no protected area and bird sanctuary along the corridor. There is general avifauna
such as common Crows, Eagles, and Myna. Except grazing cows, buffalos, goats, numerous birds
have been noticed during the Environmental survey. No endangered wild faunal species have been
noticed. No wildlife sanctuaries have been identified in the PIA.
The grazing animals are an important issue to be considered for the design decision-making as it has
got a direct bearing on road safety, traffic management and accidents as well as cattle crossing.
4.7 SOCIO -ECONOMIC ENVIRONMENT
As mentioned in earlier parts also the project road falls in Kadapa District. Most of the people in the
Districts are dependent on the agricultural activities. The table below indicates that the project area
has poor development indices such as per-capita income, proportion of non workers (55.2%).

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-18
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Literacy rate of the District is also lower than State averages. The socio-cultural indicators suggest
that the project region has low development indices. Female work participation rate is very low
(32.71%).
Table 4.15: Social and Economic Indicators of the Project Districts
Economic Social & Demographic
Project % of land put to
Districts Per capita % Non- Female work Decadal Growth
non agricultural Literacy
Income Workers participation in % Rate
land Use
Kadapa 17682 11.27 55.2 32.71 62.8 14.73

4.7.1 Settlements/Villages:
Following section outlines some of the social indicators of the settlement abutting project road. The
percentage of ST and SC groups is more in Devigudi village (24%) and as low as in Rameswaram
(7%). The non workers percentage is more in Rameswaram (57%). The literacy rate varies from 28%
(chauduru) to 37% (goriganur). The characteristics of settlements are tabulated below in Table 4.17.
Table 4.16: Settlement along the Project Road
Sr Total % Of Non-
Name of the Village % of SC+ST Literacy Rate
No. Population Workers
1 Chapadu 2228 23.115 43.94 35.95
2 Pallavolu 4225 19.314 40.17 35.81
3 Kottapalli 8384 9.697 48.06 37.57
4 Rameswaram 8284 7.122 57.53 31
5 Chauduru 2554 10.572 54.35 28.19
6 Devigudi 2107 24.822 50.74 35.26
7 Goriganur 1912 13.546 45.29 37.97
Source: Consultants surveys, 2007)
4.7.2 Socio-Cultural Properties and Land Acquisition
The proposed project will have impact on residential, commercial as well as other communities
properties. About 1295 sqm of built-up areas (mainly residential and commercial structures) -
required to be relocated. Altogether 118 structures are affected and 31 kiosks need relocation.

Table 4.17: Type and Number of structures under Impact


Features Residential Commercial Resi & Commercial Kiosk
No. of Structures 75 29 14 31
Total Area of Strucuture 6310 947 779 -
Affected Area of structure 897 271 127 -

4.7.3 Cultural Property Resources


There are important community properties and resources along the project road, which has cultural
and sociological importance. As can be seen from table 4.19, these CPRs are mostly away from
proposed CoI thus not having direct impact but there will be conflict because of proposed
improvement. There are about 18 religious structures, 14 hand pump within the 100 m corridor
(Table 4.19). However location of hand pumps are near proposed center line thus needed relocation.
As per provision of RAP these affected community properties will be replaced in close consultation
with the community.
Table 4.18: Cultural Property Resources in Project Road
Sl. No. Chainage Location
Name of Cultural Property Name of Village
(Km.) (Left/Right)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-19
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

1 2 3 4 5
1 153+080 Left Shahi Hospital Mydukuru
2 153+400 Right Sri Bala Sisuvu High School Mydukuru
3 153+460 Left Govt. Hostel for Girls Mydukuru
4 153+580 Left Gram Panchayath Office Mydukuru
5 153+600 Left Veternairy Hospital Mydukuru
6 153+600 Right Water Tank Mydukuru
7 153+800 Right Mosque With Neem Tree Mydukuru
8 155+800 Right Grave Viswanatha Puram
9 156+030 Left Hand Pump Viswanatha Puram
10 156+164 Right Hand Pump Viswanatha Puram
11 156+340 Left Hand Pump Viswanatha Puram
12 156+380 Left Govt School Viswanatha Puram
13 156+463 Left Hand Pump Viswanatha Puram
14 156+463 Left Milk Co operative Society Viswanatha Puram
Hanuman
15 156+510 Right Viswanatha Puram
Temple
16 157+160 Left Hand Pump Badri Palle
17 157+770 Left Bus Shelter Badri Palle
18 157+770 Left Hand Pump Badri Palle
Kasthuriba Gurukula Girls High
19 158+800 Left Alludu Palle
School
20 160+600 Left Chapadu Police Station Chapadu
Hanuman
21 160+840 Left Chapadu
Statue
22 160+840 Left Temple Arch Chapadu
23 161+250 Right Bus Shelter Chapadu
24 161+250 Right Hand Pump Chapadu
25 161+250 Right Veternairy Hospital Chapadu
26 162+375 Left Temple Cum Ashramam Palavolu
27 163+000 Right Hand Pump Palavolu
28 163+200 Left Veternairy Hospital Palavolu
29 164+300 Left Graves Palavolu
30 165+300 Left Water Logged Body Palavolu
31 165+450 Right Kasi Temple Palavolu
32 166+810 Left Bus Shelter V.P.C B.S.1
33 167+350 Left Vinayaka Temple
34 167+450 Right Temple
35 167+725 Left Bus Shelter
36 168+100 Right Govt School Mulavari Gramam
37 168+200 Right Church Mulavari Gramam
38 168+200 Right Hand Pump Mulavari Gramam
39 168+350 Left Hanuman Temple Side Tree Mulavari Gramam
40 168+350 Left Hand Pump Mulavari Gramam
41 168+420 Left Hand Pump Mulavari Gramam
42 168+433 Right Gangamma Stone Mulavari Gramam
43 168+450 Right Mosque With Tree Mulavari Gramam
44 168+830 Right Bus Shelter Mulavari Gramam

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-20
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sl. No. Chainage Location


Name of Cultural Property Name of Village
(Km.) (Left/Right)
1 2 3 4 5
45 168+710 Left Hand Pump M.V.P.H.P.4 Mulavari Gramam
46 168+850 Left V.P.R. College of Education Mulavari Gramam
47 169+350 Right Renuka Ellamma Temple Khadrabad
48 169+430 Right Hand Pump Khadrabad
49 169+500 Right Bus Shelter Khadrabad
Gram Panchayath Office of
50 169+700 Right Kothapalle
Kotha Palle
51 170+040 Left Swamiji Temple Produttur
52 170+920 Left Penta Coastal Church Produttur
53 170+940 Left Dargh Produttur
54 177+910 Left Graves Choutpalle
55 177+930 Right Bus Stop Choutpalle
56 178+250 Right Pond Choutpalle
57 180+955 Right Tombs Choutpalle
58 180+955 Left Bus Shelter Choutpalle
59 181+740 Left Ashramam Choutpalle
60 182+090 Right Church Choutpalle
61 182+449 Right Hand Pump Chowduru
62 182+500 Left Tomb Chowduru
63 187+055 Left Bus Shelter Danlapadu
64 190+205 Left Bus Shelter Jammalamadugu
65 194+200 Right School Jammalamadugu
66 194+200 Left R&B Guest Office Jammalamadugu

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 4-21
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER – 5: STAKEHOLDERS CONSULTATION ................................................................... 2


5.1 INTRODUCTION............................................................................................................................................ 2
5.2 CONSULTATION DURING PRE-FEASIBILITY STAGE ................................................................... 2
5.2.1 Identification of Stakeholders ............................................................................................................ 2
5.2.2 Planning for Consultation................................................................................................................... 2
5.3 CONSULTATION DURING FEASIBILITY STAGE ............................................................................. 3
5.3.1 Information Dissemination ................................................................................................................ 3
5.3.2 Structured Consultation ...................................................................................................................... 4
5.3.3 Role and Responsibilities Identified during Consultation ............................................................. 5
5.4 CONSULTATION DURING DETAILED PROJECT PREPERATION STAGE ............................ 5
5.4.1 Local Level Consultation .................................................................................................................... 6
5.4.2 District Level Consultation................................................................................................................. 7
5.4.3 State Level Consultation...................................................................................................................... 7
5.5 LESSONS LEARNT FROM CONSULTATION AND SUGGESTED FRAMEWORK FOR
ENVIRONMENTAL MANAGEMENT PLAN ........................................................................................ 7
5.5.1 Issues of Tree Cutting ......................................................................................................................... 7
5.5.2 Compensatory Afforestation .............................................................................................................. 7
5.5.3 Implementation Framework............................................................................................................... 8
5.5.4 Monitoring Plan and Training ............................................................................................................ 8
5.5.5 Cultural Properties Resources (CPRs) Enhancement .................................................................... 8

LIST OF TABLES

Table 5.1: Planning and Present Status of Consultation.............................................................................................. 2


Table 5.2: Role and Responsibilities Identified after Consultation for APRSP....................................................... 5
Table 5.3: Issues Raised and Agreement reached during consultation ..................................................................... 6

LIST OF FIGURES

Fig 5.1: Information dissemination through pamphlet Distribution......................................................................... 4

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER – 5: STAKEHOLDERS CONSULTATION

5.1 INTRODUCTION
Consultative procedure since the inception of the project has been continued as part of
environmental screening, environmental assessment and environmental management plan
preparation at various stages of techanical proceedings of the project including pre-feasibility,
feasibility, and detailed project report preparation. Stakeholder consultation involving local
communities in the project planning is basis of the participatory planning. Because, often suggestion
and option given by the people improves technical and economic efficiency of the project and
suggested improvements proposals (if adopted by the project) of the people also generates sense of
ownership within communities thus eases implementation process.
Following section highlights level of consultative procedure adopted at various stages, strategies to
participatory and continued consultation, specific inputs from the stakeholder’s consultation in
project planning.
5.2 CONSULTATION DURING PRE-FEASIBILITY STAGE
5.2.1 Identification of Stakeholders
Identification of important Stakeholders for this project is done taking into consideration of their
expected roles in the planning and implementation of the project. Primary stakeholders are the main
stakeholders with whom the project had direct interaction.
Primary Stakeholders
Potential PAPs, Forest Department and Community Leaders
(Main stakeholders)
Secondary Stakeholders Groups of affected persons;
(Other stakeholders) Village representatives like Sarpanch and members, PRIs, Village level health workers, Patwaris
Tribal groups
Women Groups such as DWACRA groups Officials at Mandal (now Tahsil level)
Local voluntary organizations like CBOs and NGOs;
Field level R&B Engineers, PWD, Government of Andhra Pradesh,
AP State AIDS Control Society representatives,
Commissioner office of Social Welfare, Tribal Development,
Other project stakeholders such as official of line Department

5.2.2 Planning for Consultation


The consultation mechanism has been planned in stages at each level of project preparation. While
village level and Block level consultation was planned during environmental assessment and will be
continued till the operation stage, District level consultation, key informant interview and other
focused consultative procedure was planned during detailed environmental impact assessment stage.
One of the features of present consultation program is to have continued involvement of local
engineers of R&B and APSHP in planning and preparation of environmental management
framework for the implementation of project largely based on input from these concern
stakeholders. The consultation strategies and phases have been discussed below.
Table 5.1: Planning and Present Status of Consultation
Level of
Stakeholders Start Stages Future course
Consultation
PAPs, community,
Pre-feasibility, feasibility
Women groups, Tribal groups, Village Started Contd
and DPR stage
NGOs
APRDC Officials, R&B officials at PIU and Field Pre-feasibility, feasibility
First round completed
Field, Offices and DPR stage
Pre-feasibility, feasibility
RDO, MRO, Forest Official Tahsil/Block Ongoing
and DPR stage
District Officials of line Department,
District DPR stage Continued
such as DRDA, Forest, SLAO

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Level of
Stakeholders Start Stages Future course
Consultation
Pollution Control Board State DPR stage Continued
District and State Forest Officials State DPR stage Continued
5.3 CONSULTATION DURING FEASIBILITY STAGE
At the feasibility stage of the environmental assessment, consultation at individual level, in groups
and focused group discussions at strategic locations such as bypasses, locations of affected
community and other eco-sensitive receptors are conducted. The consultation mechanism devised
to ensure that people are consulted; project related decision/opinions of the people are gathered and
agreement reached on suggestion/ preferences given by the people are shared with the community.
For this purpose, the consultation mechanism was initiated with the information dissemination,
followed by structured consultation and FGDs.

5.3.1 Information Dissemination


• While conducting tree enumeration and inventory of road side other important environmental
features (hot spots), the consultant has conducted information dissemination along the project
route by one to one canvassing about proposed improvement,
• Potential project affected families were consulted to inform them about proposed road
improvement program and possible environmental conflict such as tree cutting, relocation of
hand pumps,
• Pictorial Methods were adopted to explain proposed improvement and possible environmental
impacts in the concerned villages,
• Information dissemination through pumhlet / Khadapatralu among the villagers explaining
proposed road improvement (Fig 5.1)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Fig 5.1: Information dissemination through pamphlet Distribution


• People are requested to gather at common places such as places of panchayat, Gramsabha and
resource person of consultant explaining about the project using board and markers
(Rachabanda).
5.3.2 Structured Consultation
To provide better and qualitative planning options; consultations with specific objectives, agenda
were conducted in structured manner. For this purpose, much advance date and venue of
consultation were fixed in coordination with the PRIs representatives at villages level and Tahsildar,
Forest officials (range official), Mandal Samakhya Group (Velugu) at Mandal level.
Such planned consultation has brought emergent issues of proposed road improvement in the
agenda for discussion, some of the suggestion given by the community really highlighted crux of
local concern of proposed improvement as well as management plan needs to adopted for theses
local concern.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

One of the basic feature of the present consultation strategy to involve local R&B engineers, revenue
administration in project planning so that implementation (particularly options of regulatory
clearance such as Forest, pollution board and utility shifting1 and land acquisition) could be easily
realized.
5.3.3 Role and Responsibilities Identified during Consultation
Based on consultation during feasibility stage of environmental assessment a framework for LA,
R&R and Environmental impact mitigation have been envisaged in the following table along with
responsibilities of officials and expected benefits from the project.
Table 5.2: Role and Responsibilities Identified after Consultation for APRSP
Stakeholders Roles and Responsibility Expected Benefit for the Project
Potential Project • Participate in formal and informal public • Easing implementation.
Affected Persons, meeting, • Incorporation of good practices (From
Project affected groups, • Raise critical issues relevant to the long term memories of the people) of
Project Affected environment, the past in project design.
Communities, • Suggest alternative alignments, • Planning for road safety issues.
Host population environmental impact management, • Community Capacity building and
• Options of widening to save trees and sense of ownership of the project,
other environmental features,
• Methodologies for agreement on
compensation and assistance,
• Suggest methodologies for continued
participation in project cycle
Engineers – APRDC • Land Acquisition • Ease implementation
and PWD, R&B
• Forest Clearance • People oriented planning
• Ensure continued consultation • Ensured public cooperation
• Participate in Block and District Level • Determination of value
Meeting
Forest Official • Enumeration of trees • Faster Forest Clearance for the project
• Identification of eco sensitive hot spots • Transfer of Forest Land is easier
• Scrutiny of application form for forest • Forest regeneration
clearance • Maintenance and growth of sapling at
• Permission for tree cutting nursery
• Salvaging/Auctioning of trees • Transplanting trees along the corridor
• Demarcation of Forest land • Avenue Plantation
GIS and Informatics • Land use classification • To demarcate forest boundaries, major
Department, PWD, irrigation and other structures and
Extent of Forest (Reserved and open),
R&B Government of boundaries
boundaries of sanctuaries and other eco-
AP
sensitive receptors along the project
road
NGOs/CBOs • Ensure public participation in project • Public are informed
Veluru Mandal preparation and implementation, • Opinion and preferences of people are
Samakhya Group, • Assist APRDC and Government for known
Water User Association dovetailing Government schemes for • Easy to develop community capacity
PRIs,ORWs, income generation schemes, development plan.
Community forest • Suggest RDC about afforestation
management groups schemes

5.4 CONSULTATION DURING DETAILED PROJECT PREPERATION STAGE


Consultation during environmental management plan preparation stage has been conducted at local
level during survey stage, District level and State level. Local level consultation has emphasized
1 Implementation Completion report (Report No.29883-IN, 2004) observed that these activities were responsible for delay
completion of APSHP.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

individual level consultation during socio-economic baseline (25%), environmental impact and
Census Survey, consultation with groups of PAFs at pre-decided dates and venue with
representatives of PRIs, tribal groups, velugu groups (DWACRA groups), women groups, and social
forestry organization. District Level Consultation (DLC) was focused to involving stakeholders from
line department such as Forest, irrigation and revenue other than project-affected persons. These
DLC have been framed within the preview of role and responsibilities identified during feasibility
stage as mentioned in the table above. State level consultation is conducted to have policy related
decisions for environmental impact management.

5.4.1 Local Level Consultation


Detailed village level consultations were conducted during environmental impact survey stage.
Critical stretches along the proposed corridors were identified and meeting was held. At locations
FGDs were also organized. Following table summarizes highlights of some of the consultation held
along the project road.
Table 5.3: Issues Raised and Agreement reached during consultation
Major
Location Agreement reached Remarks
Issues/concern/suggestion
Chauduru (Km Villagers are against the project
182/130) Proposed road widening if the widening is going be
more than the limits what they
were fixed to.
Safety and proper care for
Sanitary conditions sanitation should be taken
during the project
implementation phase.
Encroachment removal should be The market rate will be
Compensation at the market done after notification much in established by the revenue
value advance and land owners should be department in consultation with
compensated with actual rate of the community.
land.
Peddasettipalli(Km Compensation The villagers are asking for The market rate will be
179/000) compensation by market value established by the revenue
department in consultation with
the community.
Religious structures Religious structures should not Enhancement proposals for
be disturbed. effected structures will be given
in Environmental Management
Avenue plantation should be done Plan.
Tree cutting during widening to build canopy and green tunnels
along the road.
Traffic problems

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Major
Location Agreement reached Remarks
Issues/concern/suggestion
Chapadu (km Asking for less wideing in villages
160/600)
Removal of road side business Removal of road side squatters is The proposed project will
people required and will be resettled as per require safety planning
R&R Policy
Drainage system Proper care should be taken
during the project construction
phase.
Cutting of old trees Tree cutting is a major issue and a
comprehensive afforestation
program and also Avenue
plantation should be done to build
canopy and green tunnels along the
road.

5.4.2 District Level Consultation


The proposed environmental planning envisages District level consultation at two stages.
(i) Consultation with the officials of Revenue, Forests and line Department
(ii) Consultation with the PAPs, elected representatives and other stakeholders
(i) Consultation with the District Officials: Consultation with officials of the District
administration, APSHP as well as RDC key persons2 are organized. Issues discussed in the
meeting are regulatory clearances such as Permission of tree cutting, Land acquisition, issues
related to 4(1) notification under LA act 1894, Utility shifting, planning for relocation site under
APRRP 2005 etc.
(ii) Formal and structured Consultation with PAPs, elected representatives and District
Administration: This consultation is indicative of successfulness of project, intervention
measures required for the environmental management, steps to be followed for consent award
etc. Issues raised during village and Mandal level consultation will be discussed and endorsed,
concerns of the people is given due attention during the meetings, major bottlenecks of the
project will also be addressed to the elected representatives to resolve at the Government level.
5.4.3 State Level Consultation
State level consultation was held at Kurnool involving State Principle Secretary, Collector, Local
R&B Engineers, and APRDC officials along with the consultant. The prime concern of the State
level consultation was to formalize procedure and mechanism of regulatory clearances, utility
shifting, land acquisition etc. various other issues are discussed regularly with state level officers.
5.5 SPECIFIC INPUTS FROM CONSULTATION AND SUGGESTED FRAMEWORK FOR
ENVIRONMENTAL MANAGEMENT PLAN
5.5.1 Issues of Tree Cutting
Mydukuru - Jammalamadugu Road (Part of SH-57) is very typical because of green tunnel and
proddaur town is very congested area. It is proposed to be four lane. While package I has simple
widening has been resulted in less number of tree felling, in Package-II most of trees within RoW are
being cut. While discussing strategies to save trees in these kind of stretches people suggested that
many of trees are very old and 4 laning will have significant impact on roadside trees, thus requires
comprehensive measures. During local level consultation, people also raised concern over tree felling
in bypass stretches.
5.5.2 Compensatory Afforestation
As per provision of Andhra Pradesh Forest WALTA Act compensatory afforestation will be done in
the ratio 1:2. Community during consultation has suggested to plant local species, which provide
shelter to the people (Canopy building trees) and fruit bearing trees.

2
Environment officer, RDO as special LAO for APRSP, are key concern person of RDC.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

5.5.3 Implementation Framework


It is learnt during the consultation that with key stakeholders that general practice of afforestation is
by Department of Forest through contractor involving Engineer. The provision has mixed results.
Recently GoAP has decided not involving contract with the private parties for such practices.
Therefore the project proposes to award afforestation work directly to Department of Forest with
monitoring provision through APRDC. For this purpose Ministry of Works and Ministry of Forest
will initiate MoU to activate operational mechanism of such procedure.
5.5.4 Monitoring Plan and Training
Information collected during environment (air quality, water quality and other parameters) survey
and consultation suggests periodic monitoring plan should be gauged by considering specific but
limited number of environmental parameters. Therefore, Monitoring strategies for the project
should devise a specific plan. Training and capacity building component of environmental team
should be part of consolidated training program of RDC and budgeted in training and institutional
component of the project.
5.5.5 Cultural Properties Resources (CPRs) Enhancement
Regarding cultural properties enhancement, village community is willing to come forward to
cooperate with RDC in the enhancement of religious properties. This is learnt from consultation
that generally CPRs do not receive due attention during construction (as road construction is
primary job of contractor), as a result actual enhancement do not take place. Therefore project
authority should plan for alternative implementation arrangement or strengthen its periodic
monitoring of physical and financial progress of such enhancement.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 5-8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER – 6: ANALYSIS OF ALTERNATIVES .............................................................................2


6.1 GENERAL ........................................................................................................................................................................ 2
6.2 WITH AND WITHOUT PROJECT ALTERNATIVES ................................................................................... 2
6.3 ANALYSIS OF ALTERNATIVE ALIGNMENTS ............................................................................................ 3
6.3.1 Detailed Investigation -Peddasettipalli Bypass (Km 178.600 - 179.600),.....................................6
6.3.2 Detailed Investigation - Cudappah Stone Quarry (Km 183.300 - 187.500).................................6
6.3.3 Detailed Investigation - Dhanvulapadu Bypass (Km 186.100 - 186.900) ....................................8

LIST OF TABLES

Table 6.1: ‘With’ and ‘Without’ Project Scenario............................................................................................................................. 2


Table 6.2: Comparison of Various Alternatives for Bypass ........................................................................................................... 3
Table 6.3: Environmental attributes along the Peddasettipalli bypass alignment........................................................................ 6
Table 6.4: Environmental Attributes presents along the Bypass alignment, Potential Impact & Mitigation Proposed ........ 6
Table 6.5: Environmental attributes along the Cudappah Stone Quarry alignment................................................................... 7
Table 6.6: Environmental attributes under impact......................................................................................................................... 7
Table 6.7: Environmental Attributes presents- Potential Impact & Mitigation Proposed ........................................................ 7
Table 6.8: Environmental attributes along the Peddasettipalli bypass alignment........................................................................ 8
Table 6.9: Environmental attributes under impact......................................................................................................................... 8
Table 6.10: Environmental Attributes presents along the Bypass alignment, Potential Impact & Mitigation Proposed ...... 8

LIST OF FIGURES

Fig. 6.1: Schematic Diagram showing various Bypass Alignments..............................................................................5


Fig. 6.2: Realignment at Kadapa Stone Quarry and Dhanvalapadu Village ...............................................................7

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 6-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER – 6: ANALYSIS OF ALTERNATIVES

6.1 GENERAL
Analysis of alternatives involves a thorough study of the possible future conditions in the
project study of the possible future conditions in the project area in response to a set of
alignment alternatives without the project or status quo condition.
6.2 WITH AND WITHOUT PROJECT ALTERNATIVES
Development of transport infrastructural facilities in the project area will result in increased
revenue generation from the agricultural industry, which will lead to enhanced economic
growth. The project area has a high incidence of road accidents. With the widening of the
road, provision of a median and adoption of traffic calming and road safety measures, the
accident rate may reduce. Keeping in view the site conditions and the scope of development
of the area, the ‘With’ and ‘Without’ project scenarios have been compared as shown in
Table 6.1. By looking at the table it can be concluded that “With” project scenario with
positive/beneficial impacts will vastly improve the environment and enhance social and
economic development of the region compared to the “Without” project scenario, which will
further deteriorate the present environmental setup and quality of life. Hence the “With”
project scenario with minor reversible impacts is an acceptable option than the “Without”
project scenario. The implementation of the project therefore will be definitely advantageous
to achieve the all – round development of the economy and progress of the region.
Impacts on vegetation are expected during construction. Little increase in the pollution levels
of the air is possible. Dust and particulate matter during construction will affect the air quality
on a short-term basis. However, an important benefit which is not represented in this
assessment will be major reduction in the SPM levels from vehicles using a surfaced road
(with project scenario) in the build condition, compared to a continued use of dusty
unsurfaced/tracks (without project scenarios).
The minor impacts due to air, noise, vegetative cover and soil erosion will be remunerated by
adopting appropriate mitigative measures such as roadside plantation, arboriculture &
landscaping, compensatory afforestation, and providing underpasses and noise barriers.
Table 6.1: ‘With’ and ‘Without’ Project Scenario
Component . "With" Project Scenario " Without" Project Scenario
The width of the carriageway of all the sections Two-lane existing highway with poor
Carriageway
will be increased to four-lane divided carriageway geometrics and congested.
The widening of existing highway and
construction of Peddasettipalli Bypass (Km Congestion in, Peddasettipalli
178.600 - 179.600), Cudappah Stone Quarry Cudappah Stone Quarry and
(Km 183.300 - 187.500) and Dhanvulapadu Dhanvulapadu town due to mixing
Traffic of local, pedestrian and through
Bypass (Km 186.100 - 186.900) will greatly
relieve congestion within town as through traffic traffic.
will not enter. Hence, local traffic will get greater
speed within the towns.
Footways has been built on both sides of all the There is high incidence of accidents
urban sections. Traffic calming measures have in all of the sectione of the project
been proposed in major villages and towns. Road Road due to excessive speeds in
Road Safety congested areas and overtaking on
signs and road markings to be provided at
appropriate locations. Zebra crossings have been undivided road sections.
marked at busy crossing points.
Environmental The widening of existing 2lane PR and the Poor due to congestion and high
Quality proposed bypasses will improve environmental emission levels because of slow
quality within the villages and towns due to movement of traffic. A further
lowered pollution levels and relieving of

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 6-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Component . "With" Project Scenario " Without" Project Scenario


congestion. deterioration is expected due to
Short term increase in dust and noise levels increase in traffic volumes and
during construction activities. further congestion within the towns.
Better Lesser time and fuel consumption for easy and
Increased vehicle operating costs
Transportation fast movement through the major towns and
due to reduced speeds
Facilities villages. Better Access to markets
There will be increased access to markets. Local
Economic people will be employed during construction of The economy will remain static.
Development the project road. Better transport facilities will
lead to access to new employment centers.
Higher potential for development in this region Development activities will be
Development
due to improvement in access and consequent greatly hampered by the inadequacy
potentials
increase in connectivity of connectivity.

6.3 ANALYSIS OF ALTERNATIVE ALIGNMENTS


At three location, project road passes through congested areas-
¾ Peddasettipalli Bypass (Km 178.600 - 179.600),
¾ Cudappah Stone Quarry (Km 183.300 - 187.500) and
¾ Dhanvulapadu Bypass (Km 186.100 - 186.900)
Pedasettipalli: Around 1000m length, from km 178/600 to km 179/600, project road
passes through very congested areas of Pedasettypalli village. There are three reverse curves
in this segment. The ROW varies from 8m to 12m. The houses are abutting the roadway and
location to prone to accidents. The entire village is situated on the south of the project road;
on the northern side there are four-five houses in scattered form.
The choice of widening options depend to large extents on site constraint and construction
methodology. It has been endeavour of consultant to propose widening option keeping in
view the following key factors:
• Minimising interference with religious structures such as temples, Mosques, churches,
Crematories, Mazar etc.
• Minimum impact on residential and commercial property abutting the corridor
• Land use and availability of land.
• Optimum utilisation of existing pavement and ROW at location of curve improvement
• Drainage consideration
• Construction problems
• Least disturbance to traffic during construction
• Minimum impact on the environment.
The tabular comparison and schematic diagram of option study for bypass of Pedasettypalli
village is elaborated in Table 6.2 and figure 6.1 respectively.
Table 6.2: Comparison of Various Alternatives for Bypass
Item Alt.- 1 Alt.- 2 Alt.- 3 Remarks
Description of Along the existing New alignment on New alignment on Alt3 is superior to achieve better
alternatives alignment. south (Left) north (Right) technical and road safety aspects.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 6-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Item Alt.- 1 Alt.- 2 Alt.- 3 Remarks


Alt 3 minimise junctions and
Total Length km 1.2 km 3.2km 1.3km
improves geometrics
Alt 3 is most suitable as 90
Built-up mainly Agricultural (70%), Agricultural (10%)
Type of Land % land use along the alignment is
Residential barren 30% and barren (90%)
barren.
No of Cross
Two Two One Alt 3 has least no. of junctions
Road
R&R Issue Significant Minor Minor Alt 1 has high R&R impact.
Future widening will be a problem,
Long Term
Very low High High and air and noise pollution is
Utility
expected.
Not preferred due Preferred as
Public Demanded for
to more land comparatively less Alt 3 is most preferred
consultation Bypass
acquisition land acquisition
Alt 2 civil cost is high compared
Civil Cost Rs. 1.5 Crore Rs. 7.0 Crore Rs. 2.5 Crore
with alt 3.
Prioritization/
3rd priority 2nd priority 1st priority
Conclusion
The above comparison was discussed with Managing Director and other officials of APRDC during site
inspection on 12th May 2007 and it was concluded that Alternative-2, new alignment on RHS (north side of
Pedasettyapalli village), would be proposed for the Project.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 6-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Fig. 6.1: Schematic Diagram showing various Bypass Alignments

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 6-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Based on the preliminary examination, it has been found that Alternative -2, new alignment
on LHS would be the most suitable and long lasting proposal to provide a smooth and
hurdle free movement to the through traffic.
6.3.1 Detailed Investigation -Peddasettipalli Bypass (Km 178.600 - 179.600),
The approved alignment follows through the left hand side of existing alignment. There is no
apparent advantage to follow this bypass alignment along this road, but is the most suitable option
available, as other options are eliminated/more problematic.
The environmental attributes within the corridor of impact (45m wide) is presented below.
Table 6.3: Environmental attributes along the Peddasettipalli bypass alignment
SR.
Description Unit Quantity Remarks
No.
1 Length of alignment m 2000 More than existing alignment by 50m.
2 Land Acquisition ha 9.0 Hectare at 45m wide land width to be acquired.
3 Structures No.s 0 No commercial/residential structure exist..
4 Cemetery Numbers 1 At Km 179.005.

Public consultation has been organised to know the mindset of the people about the bypass
alignment. Details covered in Chapter 5: Stakeholder consultation.
Table 6.4: Environmental Attributes presents along the Bypass alignment, Potential
Impact & Mitigation Proposed
SR.
Description Unit Quantity Mitigation Measures and Budgeting
No.
1 Length of alignment m 2000 More than existing alignment by 50m.
2 Land Acquisition ha 9.0 9 Public Consultation
9 NGO will be hired for information dissemination
9 PAP will be informed 4 month in advance.
3 Structures No.s 0 Utmost care has been given in avoiding any loss to
structures, as many religious structures exists along the
corridor.
4 Cemetery Numbers 1 Km 179.005. RHS under direct impact, will be relocated.

6.3.2 Detailed Investigation - Cudappah Stone Quarry (Km 183.300 - 187.500)


Kadapa Stone Quarry & Dhanvalapadu village Realignment: The PR road is passing through
Kadapa stone quarry area between km 183/500 to km 184/500. There is deep excavation on both
sides of existing road right, abutting to outer edge of shoulders. The widening of road to four lane,
whether concentric or eccentric, would necessitate construction of retaining wall of more than 15m
height; still it would be a accident prone area. The Consultants explored the possibility to provide
realignment on LHS/RHS of project road. On RHS, realignment is considered more appropriate
due to Penneru River on LHS. This realignment will also bypass the Dhanvalapadu village for
Mydukur bound traffic. A small realignment will be proposed on LHS of Dhanvalapadu village for
Jammalmadugu bound traffic. The proposed realignment is shown in Fig. 6.2.

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 6-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

186100.000
186200.000

186000.000
186300.000

185900.000
186400.000

185800.000
186500.000

185700.000
186600.000

185600.000
186700.000
186800.000

185500.000
186900.000

185400.000
0.000

187000.000

185300.000
187100.000
18770

185200.000
187200.000
.000

185100.000
0.0

187300.000
18700

185000.000
187600

187400.000
187500.000
0.0

0.000
18690

18490

000
.0

800.
800

184
186

0
.00
.0

700
700

184
186

00.0
1866

186200.0
186300.0
186500.0

186400.0
0
.00

0.0
600

18610
184

00.0
1860

00.0
000

1859
500.
184

00.0
1858

00.0
1857
0.000
18440

00.0
1856

00.0
1855

00.0
00
184300.0

1854

00.0
1853

00.0
1852
00
184200.0

00.0
1851

00.0
1850
00

00.0
184100.0

1849

00.0
1848

00.0
00

1847
184000.0

00.0
1846

00.0
1845
00
183900.0

00.0
1844

00.0
1843
00
183800.0

00.0
1842

00.0
1841

0
000.
00
183700.0

184

.0
900
183

.0
800
.000
183600

183

.0
700
183
00
00.0

.0
600
1835

183

.0
500
183
0
.00
400
183

0
400.
183

0
.00
300
183

.000
.0
300

00.0
200
183

1832
183
Fig. 6.2: Realignment at Kadapa Stone Quarry and Dhanvalapadu Village
The approved alignment follows through the Right hand side of existing alignment. The existing
alignment is straight and in good condition but owing to limited width the proposed new 2 lane will
be following the periphery of the quarry on right hand side of existing alignment. This way the
existing alignment will serve as one way for traffic from Mydukuru to Jammalamadugu and new
proposed realignment will be used by traffic plying from Jammalamadugu to Mydukuru. There is no
apparent advantage to segregate the traffic but land acquisition is a big problem and refilling the site
is not safe.
The environmental attributes within the corridor of impact (30m wide) is presented below.
Table 6.5: Environmental attributes along the Cudappah Stone Quarry alignment
SR.
Description Unit Quantity Remarks
No.
1 Length of alignment m 4600 More than existing alignment by 700m..
2 Land Acquisition ha 13.80 Hectare at 30m wide land width to be acquired.
3 Structures No.s 0 No commercial/residential structure exist..
No. of trees No.s 3 Details in Table 6.6
4 Electric pole Numbers 2 At Km 183.315 & At km 187.485

Public consultation has been organised to know the mindset of the people about the alignment.
Details covered in Chapter 5: Stakeholder consultation. The environmental features under impact
due to the proposed 2 lane alignment are presented in table below
Table 6.6: Environmental attributes under impact
Dist. From Type of
S.No Chainage Proposed CL Present on Environmental Attributes Impact Mitigation
1 183.315 On CL On CL Electric Pole Direct Will be relocated.

2 183.325 5.9 L.H.S Tree (T1) Avenue plantation

3 183.345 10.2 L.H.S Tree (T2)


4 183.360 13.1 L.H.S Tree (T3)
5 187.485 2.6 L.H.S Electric Pole Direct Will be relocated.

Mitigation measures has been proposed for the impacted features below
Table 6.7: Environmental Attributes presents- Potential Impact & Mitigation
Proposed

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 6-7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

SR.
Description Unit Quantity Mitigation Measures and Budgeting
No.
1 Length of alignment m 4600 More than existing alignment by 700m.
2 Land Acquisition ha 13.80 9 Public Consultation
9 NGO will be hired for information dissemination
9 PAP will be informed 4 month in advance.
3 No. of trees No.s 3 Avenue plantation.
4 Electric pole Numbers 1 Will be relocated as per utility shifting Plan.

6.3.3 Detailed Investigation - Dhanvulapadu Bypass (Km 186.100 - 186.900)


Around 800m length, from km 186/100 to km 186/900, project road passes through very
congested areas of Dhanvulapadu village. There are two reverse curves in this segment. The
ROW varies from 10m to 12m. The houses are abutting the roadway and location to prone
to accidents. The approved alignment follows through the left hand side of existing alignment.
There is no apparent advantage to follow this bypass alignment along this road, but is the most
suitable option available, as other options are eliminated/more problematic.
The environmental attributes within the corridor of impact (45m wide) is presented below.
Table 6.8: Environmental attributes along the Peddasettipalli bypass alignment
SR.
Description Unit Quantity Remarks
No.
1 Length of alignment m 1000 More than existing alignment by 100m..
2 Land Acquisition Ha 3.0 Hectare at 30m wide land width to be acquired.
3 Structures No.s 0 No commercial/residential structure exist..
4 Canal crossings No.s 2 1.from 186.140R.H.S towards 186.075 at L.H.S
2.from 186.800 on R.H.S towards L.H.S at 186.900
5 No. of trees No.s 5 Details in Table
6 Electric pole No.s 2 At Km 183.315 & At km 187.485
7 Pond No.s 1 Km 186.560 to 186.610

Public consultation has been organized to know the mindset of the people about the bypass
alignment. Details covered in Chapter 5: Stakeholder consultation. The environmental features under
impact due to the proposed 4 lane alignment are presented in table below
Table 6.9: Environmental attributes under impact
Dist. From Environmental Type of
S.No Chainage Present on Mitigation
Proposed CL Attribute Impact
Cross Drainage Structure is
7 Canal Crossing (from R.H.S at 186.140 towards L.H.S at 186.075 ) Direct
provided
8 186.110 On CL On CL Tree(T1) Direct Avenue Plantation
9 186.130 3.7 R.H.S Tree(T1) Direct Avenue Plantation
10 186.580 22.400 R.H.S Pond Indirect
Cross Drainage Structure is
11 Canal Crossing (from 186.800 on R.H.S towards L.H.S at 186.900) Direct
provided

Table 6.10: Environmental Attributes presents along the Bypass alignment, Potential Impact
& Mitigation Proposed
SR.
Description Unit Quantity Mitigation Measures and Budgeting
No.
1 Length of alignment m 1000 More than existing alignment by 700m.
2 Land Acquisition Ha 3.0 9 Public Consultation
9 NGO will be hired for information dissemination
9 PAP will be informed 4 month in advance.
Small Canal is crossing at 2 locations, adequate cross
3 Canal Crossing Numbers 2 drainage structures has been provided for minimizing impact
on existing drainage network.
4 No. of trees No.s 3 Avenue plantation.
5 Electric pole Numbers 1 Will be relocated as per utility shifting Plan.
6 Pond No.s 1

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 6-8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Detailed Project Report, Volume-VII:Environmental Impact Assessment & Environmental Management Plan 6-9
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER 7: PROJECT IMPACTS AND ISSUES ............................................................................ 3


7.1 PROJECT IMPACTS AND ISSUES...............................................................................................................3
7.2 PROJECT INTERVENTION .........................................................................................................................4
7.2.1 Land Acquisition ................................................................................................................................. 5
7.2.2 Removal of Pavement & Road Side Structures .............................................................................. 6
7.2.3 Removal of Trees and Vegetation .................................................................................................... 7
7.2.4 Extraction of material for Construction Activity ........................................................................... 7
7.2.5 Machinery and plant for Construction Activity.............................................................................. 8
7.2.6 Manpower for Construction Activity............................................................................................... 8
7.3 AIR ENVIRONMENT- IMPACTS ................................................................................................................9
7.3.1 Meteorological factors and climate................................................................................................... 9
7.3.2 Air quality - emissions......................................................................................................................... 9
7.4 LAND ENVIRONMENT - IMPACTS........................................................................................................10
7.4.1 Impact on Topography..................................................................................................................... 10
7.4.2 Impact on Geology ........................................................................................................................... 10
7.4.3 Impact on Seismology ...................................................................................................................... 11
7.4.4 Impact on Land ................................................................................................................................. 11
7.4.5 Contamination of Soil....................................................................................................................... 12
7.5 WATER ENVIRONMENT –IMPACTS.....................................................................................................13
7.5.1 Loss of Water Bodies........................................................................................................................ 13
7.5.2 Alteration of Cross Drainage........................................................................................................... 15
7.5.3 Run-off and Drainage ....................................................................................................................... 15
7.5.4 Water requirement for project......................................................................................................... 16
7.5.5 Water Quality ..................................................................................................................................... 16
7.6 NOISE ENVIRONMENT - IMPACT.........................................................................................................17
7.7 FLORA AND FAUNA - IMPACT................................................................................................................19
7.7.1 Forest Area ......................................................................................................................................... 19
7.7.2 Wild Life ............................................................................................................................................. 19
7.7.3 Tree Cutting ....................................................................................................................................... 19
7.7.4 Removal of Vegetation ..................................................................................................................... 19
7.7.5 Cattle Grazing .................................................................................................................................... 20
7.8 SOCIO-ECONOMIC ENVIRONMENT-IMPACTS ..............................................................................20
7.8.1 Fear of uncertainties regarding future ............................................................................................ 20
7.8.2 Inducement of Land Prices.............................................................................................................. 21
7.8.3 Inducement of Squatter Influx........................................................................................................ 21
7.8.4 Loss of utilities and amenities ......................................................................................................... 21

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

7.8.5 Public health and safety .................................................................................................................... 21


7.8.6 Resettlement of People..................................................................................................................... 22
7.8.7 Land Use Changes............................................................................................................................. 22
7.8.8 Disturbance to the Road side Services........................................................................................... 22
7.8.9 Removal of encroachments and squatters..................................................................................... 22
7.8.10 Sensitive Cultural Properties............................................................................................................ 23
7.9 BUS SHELTER, BUS BAYS, TRUCK LAY BYES, RESTING PLACE AND SERVICE
ROAD .................................................................................................................................................................25

LIST OF TABLES
Table 7.1 : General Impacts on Natural Environment................................................................................................ 3
Table 7.2: General Impact on Social and Cultural Environment............................................................................... 4
Table 7.4 Land Acquisition Details................................................................................................................................. 5
Table 7.5A: Removal of Structures and Pavement...................................................................................................... 6
Table 7.5B: Removal of Roadside Structures (Residential/Commercial)................................................................ 6
Table 7.6: Clearing and Grubbing & Tree Felling....................................................................................................... 7
Table 7.7: Construction Material Requirement............................................................................................................ 8
Table 7.8: Construction Machinery................................................................................................................................ 8
Table 7.9: Manpower for Construction Activity.......................................................................................................... 8
Table 7.10: List of Embankment Raising Sections..................................................................................................... 10
Table 7.11: Impacts on Water Resources due to Construction Activities .............................................................. 13
Table 7.12A: Impact on surface Water Bodies/Public Utilities ............................................................................... 13
Table 7.12B: Impacts on Ground Water Bodies ........................................................................................................ 13
Table 7.13: Bridges reconstruction................................................................................................................................ 15
Table 7.14: Requirement of Water for Proposed Construction Works .................................................................. 16
Table 7.15: Source of noise pollution ........................................................................................................................... 17
Table 7.16: Sensitive Receptors with respect to Noise Pollution............................................................................. 18
Table 7.17: Impacts on flora & fauna due To Construction Activities................................................................... 19
Table 7.18: Impact on Social and Cultural Environment.......................................................................................... 20
Table 7.19: List of Sensitive Cultural Properties......................................................................................................... 23
Table 7.20: List of Bus shelters...................................................................................................................................... 25

LIST OF FIGURES
Fig 7.1: Seismic Map of Andhra Pradesh..................................................................................................................... 11

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER 7: PROJECT IMPACTS AND ISSUES

7.1 PROJECT IMPACTS AND ISSUES


Previous chapters of this report have dealt about-proposed improvement and existing environmental
condition. Following sections summarizes impact of proposed improvement on existing
environment. As mentioned in earlier section the improvement proposal envisages 2-lane roads with
paved/earthen shoulder as a result direct impact zone up to towline is in the range of 12-16 meters
of corridors and magnitude of indirect impact varies depending upon location of environmental
receptors and type of impact. The planning of proposed project intervention point towards the
impacts in the pre construction, the construction stages and the operation stage. The subsequent
sections deal with the prediction of impacts due to the project on the natural environment and socio
& cultural environment.
Tables 7.1 & 7.2 below presents the general environmental impacts expected due to the proposed
upgradation of the project road. Impacts have been assessed based on the information collected
from the screening & scoping of environmental attributes at feasibility stage. The quanta of all the
impacts on Natural Environment are discussed in details in subsequent paragraphs.
Table 7.1 : General Impacts on Natural Environment
Planning Indirect effects
Project and De- Road Opera- of operation or
Pre-construction Phase Construction Phase
Activity sign tion Induced de-
Phase velopment
Vehicle & Sanitation
Env. com- Removal Removal of Earth works in- Asphalt &
Land ac- Laying of Machine op- & Waste Vehicle
ponent Af- of trees and cluding quarry- crusher
quisition pavement eration & (labour operation
fected Structures vegetation ing plants
maintenance campus)
Reduced
Dust gen- buffering of
Noise, soot,
eration air and noise Asphalt Noise, dust, Odour / Noise, dust,
Air Dust generation odour, dust, other pollution
during dis- pollution, odour pollution smoke pollution
pollution
mantling Hotter, drier
microclimate
Contamina- Contamina- Contami-
Loss of Erosion and Spill from ac-
Generation Erosion and loss tion by fuel tion Com- nation Change in crop-
Land produc- loss of top cidents Depo-
of debris of top soil and lubricants paction of from ping pattern
tive Land soil sition of lead
Compaction soil wastes
Alteration of
drainage Contami- Spill Contami-
Reduction Contamina-
Loss of Siltation Siltation due Break in conti- Contamina- nation nation by fuel, Increased con-
of ground tion by as-
Water water due to to loose nuity of ditches tion by fuel from lubricants and tamination of
water re- phalt leakage
sources loose earth earth Siltation, and lubricants wastes washing of ve- ground water
charge area or fuel
Stagnant water Overuse hicles
pools in quarries.
Noise Pol-
Noise Pol- Noise pollu- Noise Pollu- Noise Pollu-
Noise lution due to Noise Pollution Noise pollution
lution tion tion tion
machinery
Impact of
pollution on
Lowered pro- Lower pro-
Felling vegetation
Loss of ductivity Removal of ductivity
Flora trees for Lowered pro-
Biomass Loss of ground vegetation Use as fuel
fuel ductivity
for vegetation wood
Toxicity of
vegetation.
Disturbance Collision with Distorted habi-
Fauna Disturbance Disturbance Disturbance Poaching
Habitat loss traffic tat

Besides, above-mentioned impact on natural environment there will be socio-economic impacts due
to disruptions on the social and economic interactions of communities. This involves effect on both
the adjacent communities (mostly direct) as well as the nearby communities (mostly indirect). The
various impacts have been detailed as:
• General impacts that apply to the entire Project Influence Area (PIA),

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

• Specific impacts on likely properties and PAPs, within the Corridor of Impact (CoI) of the
Project Road.
For investigation/monitoring purpose the study area has been defined as under.
¾ Corridor of Impact, CoI: is the 20m wide strip on either side, beyond Right of Way, RoW.
¾ Project Influence Area, PIA: is the 10km area on either side along the alignment.
¾ Project District, PD: is/are the district/districts through which project road is passing.

Table 7.2: General Impact on Social and Cultural Environment


Operation
Planning
Project Indirect
and Design Pre Construction Phase Construction Phase
Activity Direct Induced
Phase
development
Design de- Vehicle &
Env. Land Removal of Earth
cisions & machine Asphalt and
Compo- ac- Removal of trees & works in- Laying of Labour Vehicle
Implemen- operation & crusher -
nent quisitio Structures vegetation cluding pavement Camps operation
tation poli- maintenanc plants
Affected n quarrying
cies e
Dust on agri-
Change Loss of land Loss of Loss of Conversion
Agricultural cultural land
- in land economic standing productive - - - - of Agricul-
land reduce n
prices value crops land tural Land
productivity
Loss of
Noise, vi- Noise, vi-
structures, Dust accu- Change in
Buildings bration may bration may
Debri genera- mulation on Vibration building use
and built - - - cause dam- - cause dam- -
tion, building and and noise and charac-
structures age to age to
Noise and Air structure teristics
structures structures
pollution
Loss of
Displacement Noise and
shade & Commu-
of people Air pollu-
community nity Noise
People and Anxiety and Psychological Noise and tion, Colli- Air and noise
trees, Loss Odour and clashes pollution, Induced
Commu- fear among - impact on Air sion with pollution and
of fuel dust with mi- Risk of pollution
nity community people pollution pedestrians discomfort
wood and grant la- accident
loss of liveli- livestock
fodder, Loss bour
hood and vehicles
of income
Noise, vi- Damage
Displacement Damage
bration may from vi-
Cultural loss of Loss of sa- from vibra- Dust accu-
- - cause dam- - - bration & -
Assets structure from cred trees. tion & air mulation
age to air pollu-
RoW pollution
structure tion
Pressure
Utilities Damage to Dust accu-
Interruption on exist-
and - - - - - utility and mulation on -
in supply ing
Amenities amenities water bodies
amenities
Collisions Increase
Increase of Collisions
Labour’s Asphalt with vehi- Impact on in com-
stagnant pedestri-
Health & - - - - odour and cles, pedes- health due to munica- -
water and ans &
Safety dust trians & inhale of dust ble dis-
disease livestock
livestock eases

7.2 PROJECT INTERVENTION


The project intervention necessitate/demand the involvement of following resources, having major
direct and indirect impact
• Land acquisition for widening and geometric improvement.
• Dismantling of few roadside residential and commercial structures (mostly encroachments) for
proposed improvements.
• Clearing and grubbing of vegetation & felling of existing tree for construction activity and road
safety.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

In addition project road upgradation will require 3M i.e. man, material and machinery for execution
of construction Work.
• Construction work involves large number of manpower (both local and migrated, contractor
staff).
• Construction material includes Borrow Earth, coarse and fine aggregated and water.
• Construction machinery includes Crusher Plant, BT plant, Batching Plant and Pavers, Graders,
road rollers and dumpers etc.
The provisional quantification of each of the above mention resources, required for project
intervention, is tabulated in Table 7.3 below.
Table 7.3: Potential Impacts and Requirement of Man, Materials & Machinery
Sr.
Description Unit Quantity Remarks
No.
1 Land Acquisition Ha 44.69 Moderate Impact
Dismantling of
2 Nos. 124 Residential/Commercial/both
Structures
3 Removal of trees Nos. 815 Total Existing trees 1163
4 Removal of vegetation Ha 98
Man, Material and Machinery Requirement for Construction Activity
Total No.s of man days divided by time allotted
5 Labour Nos. 80
for construction activity
Total Machinery working time divided by
6 Operators and drivers Nos. 30
8hours of operator working.
Semi skilled labour-
7 Nos. 10 One mate/supervisor over 8 labours.
mate/ supervisor
8 Officers/incharge Nos. 30
Requirement for embankment, subgrade
9 Borrow Earth cum 184728
shoulder etc
10 Fine Aggregate/Sand cum 76392 Concrete works, screening mayerial and in GSB
11 Coarse Aggregate/Metal cum 432889 WMM, GSB, concrete and BT works
12 Water Kilolitre 174330 All construction activities and for worker use.
Crusher Plant/BT plant/ Based on the project requirement, capacity will
13 Nos. 1each
Batching Plant be judged.
14 Pavers, Grader, Nos. 2 each
15 Dumpers Nos. 30

Consultant during the design process made desperate endeavor to minimize the impact and use of
resources,
7.2.1 Land Acquisition
The proposed project is generally having 30 meter RoW that is sufficient for improvement of the
roads. Only at two locations where geometry is too poor to accommodate four lane road with
minimum design standard LA has been proposed. These LA are to be done from open land and
barren land. No forestland or built-up structure (private) needs to be acquired for the project.
Table7.4 below presents the chainage wise details of land acquisition required for the project road.
Table 7.4 Land Acquisition Details
Bypasses/Realig Widening and Junction Way side amenities
Road Section Total
nments/ Curve improvement & Resettlement site
Mydukuru –
16 24.69 4 44.69
Jammalamadugu

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Since land acquisition is only 6.0 hectares (minimal), hence no major impact due to land acquisition
is envisaged.
Refer Appendix 7.1 for details of settlement/village wise land acquisition.
¾ As far as possible the proposed alignment follows the existing alignment, with concentric
widening.
¾ The land acquisition will be restricted to bare minimum required.
¾ Provision of protection works like retaining/toe wall is kept to confine the embankment with in
RoW /minimizing the width to be acquires.
7.2.2 Removal of Pavement & Road Side Structures
Table 7.5A presents the details of pavement scarification and cross drainage structures to be
removed/ reconstructed for the upgradation of the project road. Strategies have been adopted for
the reuse of these materials so that impact of disposal of these materials could be minimized, as
follows
¾ The excavated bituminous material from the PR will be used in paving of the grave village roads.
¾ The pavement crust excavated (WBM/WMM) will be made to be reuse in the PR crust
formation.
¾ The boulders obtained from dismantling of the masonry work will be dressed to reuse.
¾ Dismantled RCC structure will be crushed to adequate size to be used in village road as gravel.
¾ Hume pipes have limitation of its re-use because of its fixed diameter and suitability to specific
conditions. Also most of the time they are not amendable.
Table 7.5A: Removal of Structures and Pavement

Sr. Quantity Remark


Item Unit
No. PKG I PKG II TOTAL
1 Bituminous Material cum 1136 1185 2321 No significant impact because it will be reused
2 Pavement Crust cum 2723 3849 6572 No significant impact because it will be reused
3 Stone Masonry cum 1984 1653 3637 No significant impact because it will be reused
4 RCC cum 591 827 1418 No significant impact because it will be reused
5 Hume Pipes m 390 230 620 To be safely disposed

Unlike sustainable use of pavement and sub grade materials, roadside dwelling and business unit
would also be impacted and their impacted may not be transformed rather need mitigation measures.
Engineering Design team in consultation with environmental and social team has minimized/
restricted land width in contiguous built-up areas. Even after such engineering efforts some of this
residential and business unit required to be dismantled (partially or fully). Table 7.5 provides total
built-up area and number of structure affected. The impact is not considered very high because these
structures are in the form of katchha, kiosks or semi-permanent. (For detail analysis of impact please
refer Social Assessment Report)
Table 7.5B: Removal of Roadside Structures (Residential/Commercial)

Chainage Total No of Displaced Family


Village From To Res. Com. R&C Kiosk Total
Viswanathapuram 156+030 156+390 5 1 6 12
Pulla Reddy Nagar 157+160 157+345 1 2 3 6
Chapadu 160+600 162+370 2 12 11 25
Pallavolu 162+250 162+900 23 1 2 26
Mulavari palli 168+140 168+975 19 3 3 1 26

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Kadharbath 169+625 169+910 3 9 4 14 30


Lingapuram 170+190 171+545 5 5 2 4 16
Kothapalli 172+000 172+500 1 1
Bojjalavari Palli 177+500 178+000 1 1
Sankarapuram 181+000 182+000 1 1 2
Chowduru 182+130 182+720 15 3 2 1 21
Total 74 22 28 42 166
Note: the assessment is based on preliminary survey, may change in final assessment.
Refer Appendix 7.1 for details of settlement/village wise structures to be removed.
Strategies have been adopted for the reuse of these materials so that impact of disposal of these
materials could be minimized, as follows:
¾ Dismantled RCC structure will be crushed to adequate size to be used in village road as gravel.
¾ Bricks in full will be given/taken by the dwellers or will be paved in footpath and the
broken/fine bricks will be used as screening material in village roads.
7.2.3 Removal of Trees and Vegetation
Tables 7.6 below present the details of trees and vegetation to be removed for the upgradation,
widening and geometric improvement of the project road. Tree up to towline is to be felled. Cases to
case basis felling of trees will be considered for those trees, which are found at the embankment of
slope of carriageway. About 815 (372 LHS and 443 RHS) required to be uprooted because of project
improvement. However to have smooth operation of construction machineries, two plant site and
diversion about 98 ha vegetation to be removed and 5 ha additional temporary LA is to be done.
¾ The road alignment has been adjusted to minimize tree felling.
¾ As part of the effort it is also considered to remove tree up to toe line only.
¾ Alignment has been adjusted to save the Green Tunnel as well.
¾ In case of both side trees not having sufficient clear distance, one side trees has been saved.
¾ Clearing and grubbing restricted to the construction land width and in no case exceeding toe
line.
¾ Providing the embankment slopes with top soil for re-vegetation, immediately after completion
of construction work in that section.
Table 7.6: Clearing and Grubbing & Tree Felling
Sr. Vegetation to be removed (Hectares)
Location Reason for removal of Vegetation
No. PKG I PKG II TOTAL
Clearing and grubbing for construction
1 Along project road 46.0 43.0 89.0
activity
2 Plant site 2.0 2.0 4.0 Construction camp and stock yard
3 Diversion 0.5 0.5 1.0 Diversion
4 Bypass 4.0 0.0 4.0 Bypass Location

7.2.4 Extraction of material for Construction Activity


Table 7.7 below presents the details of construction material required for project road upgradation.
The queries for these aggregates and borrow earth are locally available hence NO significant direct
impact is envisaged, however strict guidelines has been prepared minimize the adverse impact; some
of these guidelines are as follows.
¾ Top soil will be excavated and preserved and reapplied for vegetation growth.
¾ The contractor shall prepare redevelopment plan for the quarry site and get it approved by the
EMU, before the commencement of any quarry activity.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

¾ Contractor will be responsible for adhering to the condition laid by the Director of Geology and
Mining at the time of issue of quarrying permit or quarrying lease.
¾ The contractor shall restore all haul roads to their original state.
¾ Contractor will be responsible for enforcing all safety measures/guidelines detailed time to time
by EMU.
Table 7.7: Construction Material Requirement
Sr. Construction Quantity
Unit Reason
No. Material PKG I PKG II TOTAL
Embankment, Subgrade &
1 Borrow Earth cum 94268 90460 184728
Shoulder
2 Fine Aggregate cum 30405 45987 76392 Screening Material, concreting
WMM, Bituminous work,
3 Coarse Aggregate cum 172293 260596 432889
concrete
4 Water Kilolitre 50290 124040 174330 Civil Works

7.2.5 Machinery and plant for Construction Activity


Table 7.8 below present the quantum of vehicles & machinery required for project intervention and
their influence area. These machineries will have its bearing on surrounding environment especially
on air quality subject to emission level of machinery and Noise Environment, however strict
guideline has been prepared to minimize the adverse impact, some of these guidelines are as follows:
¾ Construction equipment and Machineries deployed for construction will be regularly maintained
and not older than 3 years.
¾ Vehicles/ equipment will be regularly subjected for emission tests and will have valid “Pollution
under Control” certificate.
¾ All vehicles deployed for material haulage will be spill proof.
¾ Water tankers with suitable sprinkling system will be deployed along the haulage road and in the
work site.
Table 7.8: Construction Machinery
Sr. No. Construction Machinery Quantity (no.s) Influence area
1 Dumpers 30 Quarry approach and Project road
2 Excavators 5 Quarry sites & Project Road
3 Road Rollers 6 Project road
4 Graders/ Pavers 2 each Project Road
5 Stone Crusher /BT Plant 1each Plant site

7.2.6 Manpower for Construction Activity


Table 7.9 below presents the number of laborers required for the construction activity.
¾ Contractor will be encouraged for hiring/ engaging more and more local labors.
¾ Contractor is responsible to adhere to the safety measures indicated in the Appendix 8.6 Safety
Measures during Construction activity.
¾ Contractor is responsible to ensure proper medical, hygiene, Sanitation and shelter facilities.
¾ Contractor will encourage/ facilitate HIV/AIDS prevention awareness programs in
construction Camp.
Table 7.9: Manpower for Construction Activity

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sr. Number of labor involved


Construction Activity
No. Local People Contractor’s
1 Quarry 80 10
2 Clearing & Grubbibg 30 12
3 Crusher Plant 5 8
4 BT Plant 10 15
5 Paving 15 15
6 Drivers/Operators 30 50
7 Other Staff 10 30

In total 140no.s of contractor’s staff and labor will be shifted/ deputed on the project corridor.

7.3 AIR ENVIRONMENT- IMPACTS


Motor vehicles have emerged as one of the major sources of air pollution especially in urban areas.
Due to the proposed road improvements aimed at enhancing the efficiency of road transport system
the number of vehicles on these roads will be increased over time, so impacts on ambient air
environment may be significant, which needs detailed analysis.
7.3.1 Meteorological factors and climate
Due to the construction and operation of the project no impacts are expected to contribute to the
micro-climatic and meteorological conditions of the Project affected region. The project will have a
comprehensive afforestation programme and avenue plantation that includes shrub plantation in the
median and RoW edge. This could provide shade and canopy to larger areas. This could reverse if
any minor or negligible impacts do exists due to the widening of the project road.
7.3.2 Air quality - emissions
Preconstruction Stage: The preconstruction stage activities include site clearance, shifting of
utilities, removal of trees present in the corridor of impact, transportation of man and material,
construction of accommodations, construction of stock yards, installation of construction plants and
construction of office buildings. Dust generation during such activities would be the predominant
polluting activity during pre-construction stage and particularly so if pre-construction tasks are
performed during dry weather.
The impacts due to the pre construction activity are temporary and location specific and the width
of the impacts is limited. Impacts at the pre construction stage are temporary as these are lacalised
and fugitive in nature.
Construction Stage: During the construction stage the most predominant air pollutant would be
particulate matter along with various other gaseous pollutants like oxides of nitrogen, carbon
monoxide, sulphur dioxide and carbon based emissions from the hot mix plants.
The air pollution during the construction phase may be considerable locally, particularly near the
working zones, construction plant sites, quarries and from construction machinery and construction
vehicles. The list of activities which generate air pollutants are:
• Dust generation from the construction zone during different stages of the construction such as
clearing and grubbing, materials dumping, drying of materials, brushing of the surface etc.,
• Dust generation from the access roads to the soil borrow-areas, aggregate quarries construction
plants and construction camp sites.
• Operation of the construction plants such as hot mix plants, Crushers, WMM plants and
Concrete Batching Plants.
• Material storage, transportation and handling (loading/ unloading) of different construction
materials such as sand, earth from borrow pits and aggregates.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7-9
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

• Asphalt odor during paving of asphalt layers.


• Odor and smoke from construction labor camp.
Operational Stage: During the operational stage air pollutant will be from vehicular movements on
road.
The severity of impact of gaseous pollutants due to vehicles plying on the highway at any given time
will depend upon the traffic volume, emission rates of auto exhausted pollutants and prevailing
metrological condition within the project corridor. The compliance with future statuary regulatory
requirements with respect to emission limits, auto technology, and vehicular fuel quality would
minimize any negative public health impacts.
7.4 LAND ENVIRONMENT - IMPACTS
7.4.1 Impact on Topography
The design has not suggested any substantial change in the height of the embankments of the road
except to raise in flood prone areas. These are where the bridges have to be raised. The overall
topography of the area is not going to alter due to these minor changes rather there will be some
positive impacts as follows
¾ Raising of embankment leads to NO submergence areas, for round the year connectivity.
¾ More drainage structure will ease/improve the hydrology of the area, relieve the flooding
situation.
¾ Vertical geometrics improvement leads to better sight distance, safer transportation.
¾ Junction design/improvement for better and efficient traffic movement.
List of embankment raising sections is presented in Table 7.10. (embankment raising is >0.5m)
Table 7.10: List of Embankment Raising Sections
Sr. Chainage Length of Emb. Height of Emb.
Raising (m) Reason for raising
No. From To Raising (m)
1. 4.100 4.650 550 0.8 Vertical improvement
2. 10.050 10.450 300 0.8 Bridge
3. 11.950 12.300 350 0.8 Vertical improvement
4. 12.650 16.300 3650 1.0 Bypass, viaduct
5. 17.100 17.450 350 1.0 Viaduct
6. 20.500 20.750 250 1.0 Bridge
7. 27.850 28.400 550 1.0 Bridge
8. 29.150 29.400 250 0.7 Vertical improvement
9. 44.100 44.850 750 1.1 Bridges
10. 46.300 46.750 450 1.1 Bridges
11. 47.500 47.750 250 0.7 Vertical improvement
12. 50.500 51.000 500 1.0 Bridge
13. 53.100 53.450 350 0.5 Vertical improvement
14. 63.050 63.350 300 1.1 Bridge
15. 64.100 64.450 350 0.8 Vertical improvement
16. 67.850 68.150 300 0.7 Vertical improvement
(Height of Raising > 0.5m)
7.4.2 Impact on Geology
Likely impact on the geological resources will occur from the extraction of materials (borrow of
earth, granular sub base and aggregates for base courses and bridges). The boulders will be procured
from the authorized suppliers and prevalent rules will be followed for borrowing of soil, sand and
aggregates. Hence, the impact on general geology of the region is insignificant. At the construction
sites, no blasting is proposed; therefore, there will be no added impact on the geology of the area.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 10
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

7.4.3 Impact on Seismology


The construction and operation of the project road will not lead to any adverse impact on
seismology settings of the regional environment. On the contrary, the seismic events that could
occur on the region could damage the road and structures if not constructed as per the specification
recommended for the seismic zone. Present upgradation will incorporate both, existing structures
will be checked & complied and new structures will be designed earth quake resistant. Project road
falls under ZONE II as per seismic map.

h t ra LEG EN D : -
as
ar
ah
M ADILABAD

Ch M Y D U K U R U - JA M A LM AD U G U
at t a
is g is s
Or
Jagtial
ar AM
h VIJA YA
M UL
D IS T R IC T B O U N D A R Y
NIZAMABAD Peddapalli NAG ARA AK
IK
KARIMNAGAR SR

Toopran
STATE BOUNDARY
WARANGAL
MEDAK VISHAKAPATNAM

Kandi
Bhongir
KHAMMAM
Z O N E II I
Chellvela HYDERABAD
EAST
Karnataka

RANGAREDDY Medisettivrinalem GODAVARI


Kalluru

Shadnagar NALGONDA
WEST
GODAVARI
Kakinada
Rajahmundry
Z O N E II
Nuzvid
Eluru
KRISHNA
MAHBUBNAGAR
Gudivada
GUNTUR
Pedna
MACHILIPATNAM

Kurnool

Devanakonda ONGOLE
Aspari KURNOOL BAY OF BENGAL

Jmmalamadugu

Proddatur Maidukuru
ANANTPUR
NELLORE
KADAPA

Ka
rn a CHITTOOR
ta k Puttar
a
Chittoor

u
ilnad
T am

Fig 7.1: Seismic Map of Andhra Pradesh

7.4.4 Impact on Land


Loss of land: One of the major ‘local’ impacts due to highway project is upon the local land
resources required for widening and improvement of the project road. There are stretches along the
corridors where acquisition of agricultural land has been unavoidable due to non-availability of
sufficient right of way to accommodate the proposed cross-sections. Refer appendix 7.1.
Generation of Debris: The major source of debris generation is dismantling of existing cross
drainage structures and road side residential and commercial structures. Refer Table 7.5A &
Table 7.5B.
Soil Erosion: Erosion of top-soil can be considered a moderate, direct and long-term negative
impact resulting from the construction and maintenance of roads. The potential for soil erosion is
high and pervasive during the construction stage. Starting with clearing and grubbing of trees
vegetation is stripped away, exposing raw soil. The construction of new fill slopes for grading and
bridge-end fills also exposes large areas to erosion, if protection methods are not implemented.
Finally, during the operation or maintenance phase of highway development, erosion can continue
to occur in areas not vegetated. Fills are exposed to long-term exposure to water and wind. Although
soil erosion occurs sporadically on highway corridors, the sites most affected are generally bridge
end fills and over-steep banks.
a) Road Slopes and Spoils
Erosion problems may occur on newly constructed slopes and fills depending on soil type, angle of
slope, height of slope and climatic factors like wind (direction, speed and frequency) and rain
(intensity and duration). Since slope protection methods (re-vegetation or stone pitching) form part
of good engineering practice, and have been incorporated into the detailed design for the roads,
erosion concerns should be minimised. However, failure to maintain soil erosion protection can
reduce the security of high road embankments and add siltation to the rivers during the monsoon
season.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 11
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

b) Construction of New Bridges and Culverts


Along each corridor rehabilitation/reconstruction/widening of a number of major and minor
bridges and culverts is planned. Construction of new bridges involves excavation of river bed and
banks for the construction of the foundation and piers. If the residual spoil is not properly disposed
of, increased sedimentation downstream of the bridge may take place during the monsoon. Also, the
bridge-end fills require armouring to ensure gullying and slumping are minimised. For details of
bridge proposed for reconstruction, refer Table 2.10: Summary of Proposals for Culverts and
Table 2.11: Details of Existing Bridges and Proposal, in chapter 2 of this report.
During the construction period some amount of drainage alteration and downstream
erosion/siltation is anticipated. Some of these alterations may be because of construction of
temporary traffic detours/diversion. Except for these temporary works, in almost all cases there
should be an improvement in the drainage characteristics of the surrounding area due to improved
design and added culvert/ditch capacity. Changes in the drainage pattern due to the raising of the
road profile has not been discussed in specific cases, as the likely impact is not adverse and does not
warrant mitigation (as the road design itself takes care of cross-pavement drainage). New culverts are
being incorporated in the project roads not only to prevent over-topping but also to maintain equal
water distribution on either side of the road. In fact, the bridges and culverts, as designed, are an
automatic enhancement to the local environment (flooding, stagnation, scour, torrent run-off
velocity– all would be reduced as a result of this project).
c) Quarries and Borrow Areas
The excavation of quarries and borrow pits used for obtaining soil and aggregate materials for road
construction can cause direct, and indirect long-term major adverse impacts on the environment.
While loss of productive soil is the most direct negative impact, other significant indirect negative
impacts can also occur.
Since most of the construction materials would be available from existing quarries nearby, relatively
few new borrow areas will be required. Approximate requirement of geo-technical materials to the
project corridors are already presented in Table 7.8.
One of the long-term residual adverse impacts of borrow pits not reclaimed is the spread of malaria.
Mosquitoes breeding and multiplying in stagnant water that collects in these pits can affect humans
in villages and towns close to the features.
7.4.5 Contamination of Soil
Construction Stage: In this project contamination of the soil may take place, from the following
activities at the construction zones, construction labour camps, construction plant sites and other
auxiliary facilities required for the construction. Details of the activities from which the
contamination can occur are presented below;
• Scarified bitumen wastes, over production of bituminous product,
• Debris generation due to dismantling of structures,
• Maintenance of the machinery and operation of the diesel generator sets on site,
• Oil Spill from the operation of the diesel pumps and diesel storage, during transportation and
transfer, parking places, and diesel generator sets,
• Operation of the emulsion sprayer and laying of hot mix,
• Operation of the residential facilities for the labour and officers,
• Storage and stock yards of bitumen and emulsion,
• Excess production of hot mix and rejected materials,
Operation Stage: During the operation stage, soil may get contaminated with similar reasons, as
mentioned above, during routine and periodical maintenance of the project road. The implications
of accidental discharge are potentially disastrous. But, it must be emphasized that the
probability of such an accident is quite low, as one of the objectives of the design is the

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 12
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

enhancement of road safety.


7.5 WATER ENVIRONMENT –IMPACTS
Due to the proposed project there will be some direct and indirect long-term impacts on the water
resources. Table below presents the major adverse impacts on the water resources and the indicators
chosen to assess the impacts for the study.
Table 7.11: Impacts on Water Resources due to Construction Activities
Impacts Due To Construction Indicators
Loss of water bodies Area of water bodies affected
Loss of other water supply sources Number of wells affected
Alteration of drainage, run off, flooding No. of cross drainage channels
Depletion of Ground Water recharge Area rendered impervious
Use of Water Supply for Construction Quantum of water used
Contamination from fuel and lubricants Nature and quantum of contaminators
Contamination from improper sanitation and Area of camp / disposal site and, proximity to water
Waste Disposal in Construction Camps bodies / channels

7.5.1 Loss of Water Bodies


The project road passes through the dry area of Andhra Pradesh with mean annual rainfall of 600-
800mm. Thirty percent length of the project corridor is uncultivated due to non availability of water.
The main produce from cultivated land is ground nut and sunflower, requires less amount of water
comparatively.
Surface Water Bodies
The impact due to acquisition of the tank area or shifting of the community water tanks. Table
below present the details of the existing surface water bodies and possible impacts.
Table 7.12A: Impact on surface Water Bodies/Public Utilities
Chainage 153+600 178+250
Structure ID No Water Tank Pond
Village Name Mydukuru
Side Right Right
(Left/Right)
Length x Breath 12.6x20.0 Bypass
Proposed Eccentric on LHS
Widening (4.6m)
Impact No direct impact No direct
impact

No direct impact is envisaged, of the existing 2 surface water bodies.


Ground water resources
The impacts due to relocation of hand pumps, open wells, Borewells. Table below present
the details of the existing ground water resources and possible impacts
Table 7.12B: Impacts on Ground Water Bodies
Chainage 156+030 156+164
Structure ID No Hand Pump (VNP Hand Pump
0010J21)
Village Name Viswanatha puram Viswanathapuram
Side (Left/Right) Left Right
Distance from ECL 13.8 6.0
Proposed Widening Concentric Concentric
Impact No direct impact Direct impact
Chainage 156+340 156+463
Structure ID No Han d Pump Hand Pump

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 13
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Village Name Viswanatha puram Viswanathapuram


Side (Left/Right) Left Left
Distance from ECL 7 8.2
Proposed Widening Concentric Concentric
Impact No direct impact Direct impact

Chainage 157+160 157+770


Structure ID No Hand Pump Hand Pump
Village Name Badripalle Badripalle
Side (Left/Right) Left Left
Distance from ECL 8.7 8.7
Proposed Widening Concentric Eccentric on RHS
(1.87m)
Impact No direct impact Direct impact

Chainage 161+250 163+000


Structure ID No Hand pump Hand Pump
Village Name Chapadu Palavolu
Side (Left/Right) Right Right
Distance from ECL 11.8 6.0
Proposed Widening Concentric Concentric
Impact Direct impact No direct impact

Chainage 165+300 168+200


Structure ID No Water logged body Hand pump
Village Name Palavolu Mulavarigramam
Side (Left/Right) Left Right
Distance from ECL 12.5 7.0
Proposed Widening Eccentric on LHS Concentric
(4.21m)
Impact Direct impact Direct impact

Chainage 168+350 168+420


Structure ID No Hand pump Hand pump
Village Name Mulavarigramam Mulavarigramam
Side (Left/Right) Left Left
Distance from ECL 5.5 9.0
Proposed Widening Concentric Concentric
Impact Direct impact Direct impact

Chainage 168+710 169+430


Structure ID No Hand pump (MVP Hand Pump
HP 4)
Village Name Mulavarigramam Khadrabad
Side (Left/Right) Left Right
Distance from ECL 11.5 9.5
Proposed Widening Eccentric on RHS Eccentric on RHS
(4.06m) (5.82m)
Impact No Direct Impact No Direct Impact

Chainage 182+449
Structure ID No Hand pump
Village Name Chouduru
Side (Left/Right) Right
Distance from ECL 9.2
Proposed Widening Concentric
Impact Direct impact

Out of the 15 Nos. existing ground water sources 9 Nos. are under direct impact due to the
upgradation of the project corridor.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 14
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

7.5.2 Alteration of Cross Drainage


During the construction period some amount of drainage alteration is anticipated, due to
construction of temporary traffic diversions. Table below elaborates the need of diversion
for the reconstruction and new proposed bridges.
Table 7.13: Bridges reconstruction
Existing Arrangement Proposed Arrangement
Sl.
Location Height Proposal Height
No. Span Span
(ERL-BL) (FRL-BL)
1 153.420 2x3.0 + 1x1.5 2.7 Additional -2L 1x8.0 4.5
2 154.450 1x6.0 3.8 Additional -2L 1x6.0 3.8
3 159.350 2x21.0 7.1 Additional -2L 2x21.0 7.1
4 159.980 10x21.6 10.7 Additional -2L 10x21.0 10.7
5 167.665 6x2.0 1.2 Additional -2L 1x12.0 3.2
6 184.205 6x2.0 1.7 Reconstruction-4L 1x12.0 3.5
7 185.020 3x3.6 3.0 Reconstruction-4L 1x15.0 4.6
8 191.290 4x2.0 1.8 Reconstruction-4L 1x15.0 3.1
9 192.135 4x1.5 1.3 Reconstruction-4L 1x15.0 3.6

With these widening of minor bridges and bridging of existing causeways, there will be an
improvement in the drainage characteristics of the surrounding area and the alteration will be
temporary in nature. All the diversions will be provided with adequate water way for drainage.
7.5.3 Run-off and Drainage
Sediment accumulation in water bodies decreases the storage capacity for road run-off. To worsen
the situation road construction activities can lead to increased run-off both, during the construction
and operational stage. This can be considered a high adverse impact.
Phase of
Sr. No. Reason
Construction
1 Construction phase The removal of vegetation and compaction of soil can lead to increased run-off
during the monsoon
2 Operational phase The area of open ground lost and added impervious black top surface increases the
amount and rate of run-off.
The project involves widening of existing roads within the RoW, with addition of 2x1.5 paved
shoulders to the existing pavement of 7m; provision of2x1m earthen (98 per cent compacted)
shoulders; raising the pavement and as a result widening the embankment. Overall the increase in
the impervious surface would be 6m. During the operation phase increased run-off can be calculated
using the formula:
Increase in runoff per year (m3) = increase in runoff coefficient due to construction * annual rainfall in the area (m) *
area of the constructed surface (m2)
The appropriate run-off coefficients are: 0.95 for asphalt, 0.2 for silty and sandy soil, 0.3 for loamy soil, and 0.55 for
Black cotton soil.
Hence, for Mydukuru – Jammalamdugu Road
Annual average rainfall is equals to 874mm say 0.874m (statistical data book)
The increase in construction surface (BT) equals to 297,500 sqm
Increase in runoff (cum) = (0.95-0.2) X 0.874 X 297.5 X 10^3 = 195.01 x 10^3 cum
Hence additional 1.95 lakh KL of additional storm water will be required to drain off.
Since soil erosion is associated with concentrated flow of water it is imperative to prevent any
increased diversion of run-off into drainage channels.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 15
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

7.5.4 Water requirement for project


The water requirement for construction depends on the climatic conditions, type of equipment, type
of material available, mix design, type of construction plant and number of people working on the
project. With the following assumptions the approximate water quantity required for the Project has
been calculated.
1 8-10% of weight of soil for the embankment construction
2 7-8% of weight of soil for sub grade construction
3 5-6% of weight of GSB materials for GSB and WMM
4 150 liters/ cum for concrete
The water requirement has been assumed based on past project experiences and on the strict quality
control basis. Domestic requirement of 150 liters per worker has been assumed. For this project
about 140 resident workers have been considered. Details of the water requirement assessed for the
project are presented in Table 7.14.
Table 7.14: Requirement of Water for Proposed Construction Works
S. No. Purpose Cum/day
1 Permanent works (Total quantity in cum) 15330 (2years) or 21kl/day
2 Dust Suppression at work zone in (cum/day) 30
3 Curing (cum/day) 10
4 Laboratory (cum/day) 7
5 Haul Roads (cum/day) 15
6 Crusher (cum/day) 10
7 Plant Cleaning and workshop washing in (cum/day) 8
8 Domestic Purpose in (cum/day) 20
Total Requirement(cum/day) 121

Daily water requirement for the permanent works has been calculated assuming the construction
period of 2 years.
7.5.5 Water Quality
Increased Sedimentation
Degradation of water quality due to sediment transport may occur from activities like removal of
trees, removal of grass cover, excavation, stock piling of materials as part of the pre construction and
construction activities. The soil type present along the project corridor consists of the sandy loam to
clay loam.
The impacts due to increased sediment laden run-off will make the water more turbid. This is a
significant negative impact on the water bodies supporting aquatic life. Heavier sediment may
smother the algae growing in the lower strata and could completely alter the nature of the
watercourse. Excessive sediment loads may also mean disruption to areas of fish breeding.
Contamination of Water
Construction Stage: The degradation of the surface and to a much less extent ground water quality
can occur from pavement construction works, bridge construction works, construction plants,
machinery and accommodations of workers. The sources of water pollution from the construction
activities are as follows;
• Water flow from scarified bitumen materials
• From the foundation works of the bridges and culverts such as piling and excavation for open/
well foundations
• Oil spills from the Maintenance of the machinery and operation of the diesel generator sets on

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 16
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

site.
• Oil Spill from the operation of the diesel pumps and diesel storage, transportation and transfer,
parking places, and diesel generators.
• Operation of the emulsion sprayer and laying of hot mix.
• Operation of the residential facilities for the labour and officers and offices
• Storage and stock yards of bitumen and emulsion
Degradation of water quality is also possible due to accidental discharges into watercourses from
drainage of workers camps and from spillages from vehicle parking and/or fuel and lubricant storage
areas.
Operation Stage: During the operation stage, water may get contaminated with similar reasons, as
mentioned above, during routine and periodical maintenance of the project road. The implications
of accidental discharge are potentially disastrous. But, it must be emphasized that the
probability of such an accident is quite low, as one of the objectives of the design is the
enhancement of road safety.
7.6 NOISE ENVIRONMENT - IMPACT
Environmental noise particularly highway traffic noise, is a complex phenomenon because its
intensity and characteristics vary with time depending upon the frequency as well as type of vehicles
on the road.
The impacts of noise due to the project will be of temporary significance locally in the construction
phase and slight increase may occur during the operation stages. Table below present the source of
noise pollution and the impact categorization.
Table 7.15: Source of noise pollution
Sr.
Phase Source of Noise pollution Impact categorization
No.
1 Pre-construction • Man, material & machinery • all activities will last for a short
movements duration and also shall be localized
• establishment of labor camps in nature
onsite offices, stock yards and
construction plants
2 Construction • Plant Site • Plant Site: Impact will be significant
Phase - stone crushing, asphalt production within 500m.
plant and batching plants, diesel • Work zones: Such impacts again will
generators etc be of temporary nature as the
• Work zones construction site will go on changing
with the progress of the works.
- Community residing near to the
work zones
3 Operation Phase • due to increase in traffic (due to • will be compensated with the
improved facility) uninterrupted movement of heavy
and light vehicles till the facility
reaches the level of service C.

Although the baseline day & night time noise levels monitored at various locations along the project
roads are within permissible limits specified by the MoEF for residential and rural areas, still, noise is
a major area of concern, especially since sensitive receptors (schools, colleges and hospitals) have
been located quite close to the road. To assess the noise levels at the various sensitive receptors
located along the roads, consultant carried out the noise survey through noise integrator both at
inside and outside the sensitive receptor. List of the sensitive receptors located along the project
road are presented in Table 7.16.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 17
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Table 7.16: Sensitive Receptors with respect to Noise Pollution


Chainage 153+080 153+400
Structure ID No Shahi Hospital Bala sishu high
school
Village Name Mydukuru Mydukuru
Side (Left/Right) Left Right
Distance from ECL 5.5 7.9
Length x Breath 5.0x14.0 10.3x20.0
Proposed Widening Concentric Concentric
Impact Direct impact Direct impact

Chainage 153+460 153+600


Structure ID No Govt. hostel for girls Veterinary Hospital
Village Name Mydukuru Mydukuru
Side (Left/Right) Left Left
Distance from ECL 7.7 9.0
Length x Breath 60.0x100.0 38.0x50.0
Proposed Widening Eccentric on RHS Eccentric on LHS
(0.73m) (4.6m)
Impact Direct impact Direct impact

Chainage 156+380 158+800


Structure ID No Govt. School Kasturiba gurukula
girls high school
Village Name Viswanatha puram Alludupalle
Side (Left/Right) Left Left
Distance from ECL 10.2 10.1
Length x Breath 16.0x40.0 35.0x100.0
Proposed Widening Concentric Eccentric on RHS
(4.0m)
Impact No direct impact No direct impact

Chainage 161+250 163+200


Structure ID No Veterinary Hospital Veterinary Hospital
Village Name Chapadu Palavolu
Side (Left/Right) Right Left
Distance from ECL 8.3 17.7
Length x Breath 30.0x60.0 20.0x35.0
Proposed Widening Concentric Concentric
Impact No direct impact No direct impact

Chainage 168+100 168+850


Structure ID No Govt. School VPR college of
Education
Village Name Mulavari gramam Mulavari gramam
Side (Left/Right) Right Left
Distance from ECL 10.0 10.0
Length x Breath 22.0x10.0 70.0x200.0
Proposed Widening Eccentric on LHS Eccentric on RHS
(0.88m) (3.96m)
Impact No direct impact No direct impact

Chainage 194+200
Structure ID No School
Village Name Jammalamadugu
Side (Left/Right) Right
Distance from ECL 10.8
Length x Breath 110.0x200.0
Proposed Widening Concentric
Impact No direct impact

Out of the existing 11 sensitive noise Receptors, four are under direct impact. Considering their
sensitivity to noise, measures have been suggested for the mitigation/enhancement of these
locations in next chapter.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 18
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

7.7 FLORA AND FAUNA - IMPACT


The major impact in this project on flora involves the removal of trees to permit construction and to
provide clear zone for safety of the road users. Table below presents the major adverse impacts on
the flora & fauna and the indicators chosen to assess the impacts for this study.
Table 7.17: Impacts on flora & fauna due To Construction Activities
Impacts Due To Construction Indicators
Tree felling No. of trees to be fell
vegetation Area of vegetation loss
Cattle Grazing Ground Area and location of grazing ground.

7.7.1 Forest Area


No forest area exists within the corridor of impact.
7.7.2 Wild Life
NO wild life crossing is found along the project corridor.
7.7.3 Tree Cutting
Trees located within the toe line (bottom of formation) need to be removed for efficient
construction workmanship and more importantly to prevent collision with the trees, in case of
accident. Roadside trees with strong and rigid stems can pose safety hazards. Some trees obstruct
clear sight distances. Others have a propensity to overturn when old and are potential safety hazards
depending upon age and decay condition. All such trees that are safety hazards need to be cleared.
There will be a significant, direct impact on cutting of the roadside trees, it includes
• The loss of shade
• Loss of tree products.
• Removal of roadside trees will also reduce comfort levels for slow moving traffic and
pedestrians.
• The removal of trees would leads to erosion and contributes to the loss of the micro-ecosystems
developed on the roadside.
• Besides this trees act as noise barrier, dust absorption, air purifier etc.
A detailed tree inventory was carried out of all the existing trees within the corridor of impact, due
care had been given in alignment design to reduce/minimize the loss of flora and green tunnels. As a
result a total of about 815 trees out of a total 1163 existing trees are required to be cut for the
proposed project. About 372 trees on the left side and 443 trees on the right side are being affected
due to the proposed widening. The major trees affected are Thumma,Neem, kangua,Agipulla, Raavi,
Giriship, Tamarand etc.
No tree will be cut beyond the proposed toe line. Cutting of trees for fuel by workers, especially near
their camps is of major concern. Therefore adequate training of the workers and availability of their
fuel requirements are to be ensured by the Contractor.
7.7.4 Removal of Vegetation
Clearing and grubbing of the area is the foremost requirement to start the construction activities in
accordance with MoRTH specifications. The impact due to removal of vegetation includes
• Dust generation during windy atmosphere
• Loss of productive top soil
• Soil erosion during rainy season, may lead to water contamination.
Measures have been taken in reducing and curtailing the clearing and grubbing of excess land. Refer
Table 7.6 for the item wise quantitative requirement of clearing and grubbing.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 19
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

7.7.5 Cattle Grazing


No cattle grazing grounds have been found along the corridor of Impact.
7.8 SOCIO-ECONOMIC ENVIRONMENT-IMPACTS
Adverse socio-economic impacts include all disruptions on the social and economic interactions of
communities due to the road intervention (Table 7.18). This involves effect on both the adjacent
communities (mostly direct) as well as the nearby communities (mostly indirect). The various
impacts have been detailed as:
• General impacts that apply to the entire project Influence Area,
• Specific impacts on likely properties and PAPs, within the Corridor of Impact.

Table 7.18: Impact on Social and Cultural Environment


Operation
Planning
Project Indirect In-
and Design Pre Construction Phase Construction Phase
Activity Direct duced de-
Phase
velopment
Design
Vehicle &
Env. decisions Removal of Earth Laying Asphalt
Land machine op-
Compo- & Imple- Removal of trees & works in- of and Labour Vehicle
acquisit eration & -
nent menta- Structures vegetation cluding pavemen crusher Camps operation
ion maintenanc
Affected tion quarrying t plants
e
policies
Dust on
Agricul- Change Loss of land Loss of Loss of Conversion
agricultural
tural - in land economic standing produc- - - - - of Agricul-
land reduce
land prices value crops tive land tural Land
productivity
Loss of
Building Noise, vi- Dust ac-
structures, Noise, vibra- Change in
s and bration cumulation
Debri gen- tion may Vibration building use
built - - - may cause - on building -
eration, cause damage and noise and charac-
structure damage to and struc-
Noise and Air to structures teristics
s structures ture
pollution
Displacement Loss of shade Noise and
Commu
of people & community Air pollution, Air and
People Anxiety nity Noise
Psychological trees, Loss ofNoise and Collision noise
and and fear Odour clashes pollution, Induced
- impact on fuel wood Air with pollution
Commu- among and dust with Risk of pollution
people and fodder, pollution pedestrians and
nity community migrant accident
loss of liveli- Loss of in- livestock and discomfort
labour
hood come vehicles
Noise, Damage
Displacement Damage
vibration Dust from
Cultural loss of Loss of from
- - may cause - accumulati - vibration & -
Assets structure sacred trees. vibration &
damage to on air
from RoW air pollution
structure pollution
Dust Pressure
Utilities
Damage to accumulati on
and Interruption
- - - - - utility and on on existing -
Ameniti in supply
amenities water amenitie
es
bodies s
Increase
Increase of Collisions Impact on Collisions
Labour’s Asphalt in
stagnant with vehicles, health due pedestrian
Health - - - - odour communi -
water and pedestrians & to inhale of s&
& Safety and dust cable
disease livestock dust livestock
diseases

General Impacts
Engineering, environmental and socio-economic surveys, conducted during the design phase, for the
generation of the baseline information, give indications of several adverse impacts in the vicinity of
the alignment, which are related to common human psychology and general in nature.
7.8.1 Fear of uncertainties regarding future
These normally become long lived, given the length of time, which elapses between initial surveys
and commencement of construction.
Land and property owners are subjected to sufferings regarding uncertainties of the extent of loss

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 20
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

and the nature of compensation. These involve:


• uncertainty of the amount of land/property to be acquired,
• time of acquisition and evacuation,
• extent and amount compensation,
• Provision of alternative land or job, etc.
7.8.2 Inducement of Land Prices
Once the project becomes common knowledge, there may be an incidence of unscrupulous
speculators moving in to purchase land at what might seem to be advantageous prices, prior to the
commencement of the official procedures. Such impact is more likely to occur in the case of urban
fringe areas during the design and pre-construction phase.
7.8.3 Inducement of Squatter Influx
Squatters may attempt to occupy land along and adjacent to the proposed alignments, in the hope of
receiving compensation or some other inducements to leave when construction commences. Such
squatters could cause undue pressure on local resources such as water and firewood, which could
result in conflicts with those who are harvesting the resources presently.
7.8.4 Loss of utilities and amenities
Site clearance involves removal of various assets, utilities and amenities that are:
• Natural (trees, bushes and grasslands), and
• Physical structures (public or private assets and utilities).
• Relocation of utilities like electricity, water and telephone lines
For people dependent on the above, this constitutes economic loss for some time before these are
restored to their previous status. These have been further discussed in the RAP.
7.8.5 Public health and safety
a) Impacts on Public health and safety may arise during the phases of pre-construction,
construction and operation phases. During the pre-construction and construction phases,
dismantling of the structures for CoI clearance and road construction activities may result in the
following health hazards:
• Dismantling of properties has psychological impacts on their owners and others associated
with them.
• Debris generated on account of the above mentioned activities.
b) Labour Camps during construction period can bring the following problems.
• In the case of non-local labour (if so is arranged by the contractor), labour camps are set up
at one or more sites adjacent to the alignment, and at some ancillary sites, like aggregate
quarries. These labourers hired from outside can have clashes with the local population on
account of cultural and religious differences. The influx of a large work force to an area,
already hard pressed for basic services (medical services, power, water supply, etc.), can
impose additional stress on these facilities.
• if alternative fuels are not made available to the workforce, there is a likelihood that trees
will be cut down for cooking or heating purposes.
• In sanitary conditions in the labour camps might also result in impact on health of labourers
as well as the local population. Transmission of diseases is also facilitated by the migration
of people. During the construction phase work, crews and their dependants may bring with
them a multitude of communicable diseases including sexually transmitted diseases (STDs)
like AIDS. This is more so if the nature of the project requires more male-workers, who
have migrated from other parts of the state or country.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 21
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

c) Allied activities during construction period may cause local disruption.


• During road construction allied activities like quarrying and crushing operations, traffic
diversions, etc., may cause disruption of social and economic life of the local population of
the nearby areas.
• Dust and noise generated in crushing and blasting operations may cause nuisance to the
nearby communities.
• Traffic jams and congestion, loss of access and other road accident risks, as a result of
diversion of traffic and construction work on road.
• There will be some impact on land during construction, limited mainly to temporary
acquisition to cater to road diversion or traffic detours and establishment of labour camps.
d) Accidents and Safety
• Although the design speeds have been kept lower in the major settlement areas, some
amount of severance is expected in the rural areas. Especially where the residential area is on
one side and their agricultural land and other facilities are on the other side of the highway.
School children and ladies carrying pots full of water from the water sources (ponds/wells)
also get exposed to this risk. In rural areas it was seen that cattle also cross the highways
near the settlement.
7.8.6 Resettlement of People
People, displaced from their homes and agricultural lands on account of the project, shall induce
additional pressures to the local resource base. These include pressure on:
• water resources in areas where availability is low,
• grazing lands and fuel-wood,
• Public services such as schools and medical facilities.
• This is critical since number of displaced persons being squatters is larger than legal
landholders formally displaced.
7.8.7 Land Use Changes
Land use changes along the road corridors are anticipated. These shall bring about a change in the
characteristics of the adjacent lands. There would be succession of land uses and higher return uses
would displace the lower return uses. This phenomenon will occur at major intersections and in
settlement areas along the project corridors. The urban fringe areas along the project roads will be
subjected to ribbon development.
7.8.8 Disturbance to the Road side Services
Along the highway, near settlements, small shops get attracted to serve the local people as well as the
highway users. A composite socio-economically inter-dependent has been developed as a
consequence. The shops serve dual purpose by providing income and employment to locals as well
as service to the road users. It is likely that due to implementation of the project some of the shops
may get displaced. This would cause negative impact on the livelihood of people as well as loss of
service to the local people and road users.
7.8.9 Removal of encroachments and squatters
In order to reduce the number of PAPs, land clearing shall be restricted to within the Corridor of
Impact (CoI) which principally lies within the RoW. Width of the CoI varies according to the design
and is narrower in the settlement areas, where the numbers of PAPs are likely to be more. However,
some amount of land clearing will be essential in several of these stretches.
The potential impacts likely to arise from clearance of encroached residential areas (especially in
settlements along the project corridors) may involve loss of valuable residential space to the
residents. In the case of squatter settlements, displacement might lead to loss of shelter if adequate
measures are not taken for their resettlement. Compensation may not be enough for the effected

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 22
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

persons to gain access to shelter. Other impacts include disturbance to family and community life
and increased distance from their workplace. In such cases the displaced persons may again resort to
squatting.
The extent of loss in the case of encroached agricultural lands shall be relatively less, in comparison
with residential and commercial properties. This because, the encroached lands form only a small
part of the total cropped land of the farmers.
Specific Impact
Other socio-economic impacts involve the presence of sensitive community facilities within the
Corridor of Impact such as worship places and cultural properties.
7.8.10 Sensitive Cultural Properties
Utmost care has been taken in finalising the horizontal and vertical alignment so that the impact on
cultural properties could be better avoided than mitigated as a result, out of the 18 nos. cultural
properties existing within the Corridor of Impact only 7 nos. are in direct impact, i.e. lying within the
formation width of the proposed widening/upgradation. The total list of cultural properties
identified within CoI that will have experience positive or negative impact is provided in the Table
7.19 below.
Table 7.19: List of Sensitive Cultural Properties
Chainage 153+800 156+510
Structure ID No Mosque with tree Anjaneya swamy
temple
Village Name Mydukuru Viswanathapuram
Side (Left/Right) Right Right
Distance from ECL 7.7 6.5
Length x Breadth 5.0x4.0 9.0/8.0x15.00
Proposed Widening Eccentric on Concentric
LHS(3.88m)
Impact No Direct Impact Direct Impact

Chainage 160+840 160+840


Structure ID No Hanuman statue Temple Arch
Village Name Chapadu Chapadu
Side (Left/Right) Left Left
Distance from ECL 7.5 12.5
Length x Breadth 4.0x4.0 4.0 x 4.0
Proposed Widening Eccentric On Eccentric On
RHS(4.54m) RHS(4.54m)
Impact No Dire3ct Impact No Dire3ct Impact

Chainage 162+375 165+450


Structure ID No Temple cum Kasi Naina Temple
Ashramam cum chowltry /
hand pump
Village Name Palavolu Palavolu
Side (Left/Right) Left Right
Distance from ECL 7.5 8.9
Length x Breadth 30.0x60.0 12.0x30.0
Proposed Widening Eccentric On Eccentric On
RHS(3.51m) LHS(5.24m)
Impact No Dire3ct Impact No Dire3ct Impact

Chainage 167+350 167+450


Structure ID No Vinayaka temple Temple
Village Name
Side (Left/Right) Left Right
Distance from ECL 9.7 7.5
Length x Breadth 22.0x50.0 12.0x14.0
Proposed Widening Eccentric On RHS Eccentric On
(4.17m) RHS(4.64m)
Impact No Direct Impact Direct Impact

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 23
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Chainage 168+200 168+350


Structure ID No Church Ha numan temple
with tree
Village Name Mulavarigramam Mulavarigramam
Side (Left/Right) Right Left
Distance from ECL 8.5 5.5
Length x Breadth 20.0x15.0 5.0x3.0
Proposed Widening Concentric Concentric
Impact Direct Impact Direct Impact

Chainage 168+433 168+450


Structure ID No Gangamma stone Mosque with tree
inside
Village Name Mulavarigramam Mulavarigramam
Side (Left/Right) Right Right
Distance from ECL 6.5 7.00
Length x Breadth 1.5 x 1.5 6.0x5.3
Proposed Widening Concentric Concentric
Impact Direct Impact Direct Impact

Chainage 169+350 170+040


Structure ID No Renuka Ellamma gudi Swamiji Temple
with tree
Village Name Khadrabad Khadrabad
Side (Left/Right) Right Left
Distance from ECL 5.1 14.5
Length x Breadth 2.5x2.5 6.0x14.0
Proposed Widening Eccentric On Eccentric On
RHS(5.84m) RHS(2.01m)
Impact Direct Impact No Direct Impact

Chainage 170+920 170+940


Structure ID No Penthacostanl church Dargha
Village Name Proddutur Proddutur
Side (Left/Right) Left Left
Distance from ECL 11.5 11.5
Length x Breadth 12.0x100.0 25.0x100.0
Proposed Widening Eccentric On RHS Eccentric On
(0.85m) RHS(0.85m)
Impact No Direct Impact No Direct Impact

Chainage 181+740 182+090


Structure ID No Ashramam Church
Village Name Chouduru Chouduru
Side (Left/Right) Left Right
Distance from ECL 7.5 16.5
Length x Breadth 16.0x40.0
Proposed Widening Eccentric ON Concentric
RHS(3.87m)
Impact No Direct Impact No Direct Impact

Out of the existing 18 religious structures along the project corridor, seven are under direct impact.
However three are very small setup with no shed. Other four are comparatively medium sized
structures. Besides direct impact, there are many possible indirect impacts due to construction
activities, as follows.
• Access to religious places would be difficult during the construction period due to the presence
of working areas, consequent traffic management issues, presence of heavy equipment,
machineries and numerous workers and controlled sign boards.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 24
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

• Many existing signs boards and information boards will be removed for the construction
work. This will make it more complicated for identifying the pilgrimage location, routes and
landmarks.
• Safety issues and accidents could go high during the construction period.
7.9 BUS SHELTER, BUS BAYS, TRUCK LAY BYES, RESTING PLACE AND SERVICE
ROAD
Concentric widening is proposed in built-up sections of the project road so as to minimize the
negative impact due to upgradation/ widening of the project road. The Table 2.1 of Chapter 2
describes the settlements locations along the proposed project road. Out of the total of 10 existing
pucca bus waiting sheds, 6 will be relocated, as these bus shelters are falling within the formation
width.
Table 7.20: List of Bus shelters
Chainage 157+770 161+250
Structure ID No Bus shelter Bus shelter
Village Name Badripalli Chapadu
Side (Left/Right) Left Right
Distance from ECL 14.5 8.1
Length x Breath 6.0x8.0 4.0x4.0
Proposed Widening Eccentric on RHS Concentric
(1.87m)
Impact No direct impact Direct impact

Chainage 166+810 167+725


Structure ID No Bus shelter Bus shelter
Village Name
Side (Left/Right) Left Left
Distance from ECL 10.5 8.6
Length x Breath 7.0x6.0 6.0x4.0
Proposed Widening Eccentric on RHS Eccentric on RHS
(4.09m) (4.86m)
Impact No direct impact No direct impact

Chainage 168+830 169+500


Structure ID No Bus shelter Bus shelter
Village Name Mulavari Gramam Khadrabad
Side (Left/Right) Right Right
Distance from ECL 8.5 6.5
Length x Breath 6.0x3.0 5.0 x 3.0
Proposed Widening Eccentric on RHS Eccentric on RHS
(4.00m) (6.46m)
Impact Direct impact Direct impact

Chainage 177+930 180+955


Structure ID No Bus shelter Bus shelter
Village Name Choutpalle Choutpalle
Side (Left/Right) Right Left
Distance from ECL 11.5 8.6
Length x Breath 4.4x4.0
Proposed Widening Concentric Eccentric on LHS
(5.63m)
Impact No direct impact Direct impact

Chainage 187+055 190+205


Structure ID No Bus shelter Bus shelter
Village Name Danlapadu Jammalamadugu
Side (Left/Right) Left Left
Distance from ECL 8.0 5.3
Length x Breath 6.0x10.0 7.8x7.0
Proposed Widening Eccentric on LHS Eccentric on LHS
(4.67m) (4.21m)
Impact Direct impact Direct impact

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 25
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 7 - 26
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER 8: IMPACT MITIGATION AND ENHANCEMENT .................................................... 3


8.1 MITIGATION, AVOIDANCE AND ENHANCEMENT.......................................................................3
8.2 AIR ENVIRONMENT – MITIGATION.....................................................................................................3
8.2.3 Meteorological Factors and Climate - mitigation............................................................................. 4
8.2.4 Air Quality Emissions - mitigation..................................................................................................... 4
8.2.5 Air Quality Monitoring - mitigation................................................................................................... 5
8.3 LAND ENVIRONMENT- MITIGATION MEASURES.........................................................................5
8.3.1 Change in Topography - mitigation................................................................................................... 6
8.3.2 Change in Geology- mitigation........................................................................................................... 6
8.3.3 Change in Seismology - mitigation..................................................................................................... 6
8.3.4 Change in Land Environment – Mitigation ..................................................................................... 6
8.3.5 Contamination of soil: Mitigation ...................................................................................................... 7
8.3.6 Soil Quality Monitoring - mitigation.................................................................................................. 8
8.4 WATER ENVIRONMENT-MITIGATION MEASURES .......................................................................9
8.4.1 Loss of Water Bodies-Mitigation......................................................................................................10
8.4.1.1 Surface Water Bodies .........................................................................................................................10
8.4.1.2 Ground water resources.....................................................................................................................10
8.4.2 Alteration of cross drainage ..............................................................................................................11
8.4.3 Runoff and drainage ...........................................................................................................................12
8.4.4 Water Requirement for Project.........................................................................................................12
8.4.5 Water Quality.......................................................................................................................................12
8.4.6 Water Quality Monitoring - mitigation............................................................................................13
8.5 NOISE ENVIRONMENT-MITIGATION MEASURES.......................................................................14
8.5.1 Sensitive Receptors – mitigation ......................................................................................................14
8.5.2 Noise Pollution - Mitigation..............................................................................................................15
8.5.3 Noise Pollution Monitoring - mitigation.........................................................................................16
8.6 FLORA & FAUNA - MITIGATION...........................................................................................................16
8.6.1 Forest Area – Mitigation....................................................................................................................16
8.6.2 Wild Life - Mitigation.........................................................................................................................16
8.6.3 Trees – Mitigation...............................................................................................................................16
8.6.4 Vegetation - Mitigation ......................................................................................................................18
8.6.5 Cattle Grazing - Mitigation................................................................................................................18
8.7 SOCIO-ECONOMIC ENVIRONMENT - MITIGATION...................................................................18
8.7.1 General Impacts - Mitigation ............................................................................................................18
8.7.2 Specific Impacts – Mitigation ...........................................................................................................23

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

8.8 BUS SHELTER, BUS BAYS, TRUCK LAY BYES, RESTING PLACE AND SERVICE
ROAD .................................................................................................................................................................24
8.9 AVOIDANCE OF DISRUPTION AND SAFETY RISKS DURING THE
CONSTRUCTION STAGE ...........................................................................................................................25
8.9.1 Disruption to the Community ..........................................................................................................25
8.9.2 Safety of the Workers.........................................................................................................................26

LIST OF TABLES

Table 8.1: Environmental features saved through Avoidance measure at design stage ......................................... 3
Table 8.2: Surface Water Bodies-Mitigation ................................................................................................................ 10
Table 8.3: Ground water Sources-mitigation............................................................................................................... 10
Table 8.5 List of silt fencing locations.......................................................................................................................... 12
Table 8.6 List of sensitive receptor ............................................................................................................................... 14
Table 8.7 List of Sensitive Cultural Properties............................................................................................................ 23
Table 8.8 List of Existing Bus Shelters......................................................................................................................... 24
Table 8.9 List of Proposed Bus Shelters ...................................................................................................................... 24

LIST OF DRAWINGS

Drawing No. 8.1: Conceptual plan of Oil Interceptor ................................................................................................ 8


Drawing No. 8.2 : Conceptual plan of Soak Pit for Hand Pump ............................................................................ 11
Drawing No. 8.3: Conceptual Plan of Diversion at Bridge Location...................................................................... 12
Drawing No. 8.5: Conceptual plan of silt fencing. ..................................................................................................... 13
Drawing No. 8.6: Conceptual Drawing for Noise Barrier ........................................................................................ 15
Drawing No. 8.7: Conceptual Plan for Avenue Plantation....................................................................................... 17
Drawing No. 8.8: Conceptual Plan for Tree Guard................................................................................................... 18
Drawing No. 8.9: Conceptual Plan for Bus shelter .................................................................................................... 25
Drawing No. 8.10: Conceptual Plan for traffic Diversion ........................................................................................ 26

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER 8: IMPACT MITIGATION AND ENHANCEMENT

8.1 MITIGATION, AVOIDANCE AND ENHANCEMENT


Prevention or avoidance of impact is better than mitigation of impact. Hence avoidance and
reduction of adverse impacts approaches were adopted during the design stage through continued
interaction between the design and environmental teams. This is reflected in the designs of the
horizontal & vertical alignment, cross sections adopted, construction methods and construction
materials. In-depth site investigations have been carried out so that sensitive environmental
resources are effectively avoided, leading to the environmentally best-fit alignment option. As a
result many of the trees, cultural properties, water bodies etc. have been avoided at the design stage
itself, as presented in Table 8.1 below.
Table 8.1: Environmental features saved through Avoidance measure at design stage
Saved through
Environmental Features Potential Impact Under Direct Impact
alignment design
Trees (nos.) 1163 815 348
Surface Water source 2 0 2
Ground Water source 15 8 7
Cultural Properties 18 7 11
Bus Shelters 10 6 4

8.2 AIR ENVIRONMENT – MITIGATION


Motor vehicles have emerged as one of the major sources of air pollution especially in urban areas.
Due to the proposed road improvements aimed at enhancing the efficiency of road transport system
the number of vehicles on these roads will be increased over time. Summary of potential impact and
mitigation measures proposed is mentioned below:
Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
1 Meteorological Marginal Due to production and 9 comprehensive afforestation
factors and impact laying of hot bituminous 9 avenue plantation
climate mix.
9 shrub plantation in the
median/island
9 RoW hedge
2a Air quality - temporary shifting of utilities, Sprinkling of Water
emissions and location removal of trees &
specific vegetation,
Pre- transportation of material Fine materials to be completely
construction (Dust covered, during transport & stocking.
stage Generation) installation of construction Plant to be installed in Downwind
plants direction from nearby settlement.
2b Air quality - Moderate clearing and grubbing Air pollution Norms will be enforced,
emissions impact materials dumping Laborers will be provided mask.
brushing of the surface Local people will be educated on safety
Construction (Gaseous access roads to borrow- and precaution.
Stage pollutants & areas on access roads, newly constructed
Dust hot mix plants, Crushers embankment etc.
generation)
paving of asphalt layers
Labour Camps
2c Air quality - Moderate air pollutants from traffic compliance with future statuary
emissions impact regulatory requirements
auto-technology, vehicular fuel quality-

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
Operation (Gaseous dust emission from tyres improvement
Stage pollutants)
3 Air quality - -- Effectiveness / shortfall (if Measures will be revised & improved to
monitoring any) mitigate/ enhance environment due to
Any unforeseen impact. any unforeseen impact.

Emissions from the vehicles are potentially disastrous. But, it must be emphasized that the air
pollution from vehicle emission will reduce on completion, as one of the objectives of the
design is enhancement of facility to cater traffic requirement, till it reach level of service ‘C’.
For existing level of service refer table 2.3
8.2.3 Meteorological Factors and Climate - mitigation
As indicated in previous chapter, there will not be any micro-climatic effect/impact due to increased
traffic emission on the project road during construction and operation phase, if any minor impact
do exists due to widening will be counter by compensatory and additional afforestation plan and
avenue plantation.
8.2.4 Air Quality Emissions - mitigation
Pre-construction Stage: As indicated in previous chapter, the dust generation due to pre-
construction activities is very temporary and localized, and will be efficiently countered by sprinkling
of water.
Construction Stage: During the construction stage, there are two major sources: the first one is
construction activities at working zones, which cause primarily dust emission and second are from
operation of the construction plant, equipments and machinery, which causes gaseous pollutants.
The specific measures include:
• Locating Plant at a significant distance from nearest human settlement in the predominant down
wind direction.
• Vehicles delivering fine materials like soil and fine aggregates shall be covered to reduce spills on
existing roads.
• Water will be sprayed on earthworks, temporary haulage and diversions on a regular basis.
• Batch type hot mix plants fitted with the bag filter / cyclone and scrubber will be installed for
the reduction of the air pollution.
• Pollution control systems like water sprinkling and dust extractors and cover on conveyors will
be installed for the crushers.
• All vehicles, equipment and machinery used for construction will be regularly maintained to
ensure that the emission levels conform to the SPCB/CPCB norms.
• Air pollution monitoring plan has been delineated for construction phase separately for checking
the effectiveness of the mitigation measures adopted during the construction phase of the
Contract.
Operation Stage: As indicated in previous chapter, the air pollutant will be from vehicular
movement on road and dust emission by tyres. As such the nation and international bodies are quite
active in controlling the air pollution through emission limit, auto technology and fuel quality which
will counter the increase in air pollution due to increase in traffic during operation phase. Additional
measures/proposed are below:
• Pollution resistant species, which can grow in high pollutant concentrations or even absorb
pollutants, can be planted along the roadside.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

• Monitoring of air pollution levels at sensitive locations shall be carried out all through the
operation stage to check that the pollution levels are within standards prescribed by CPCB. A
monitoring plan to this effect has been prepared for all roads separately and is presented in the
individual EMPs.
• Other measures such as the reduction of vehicular emissions, ensuring vehicular maintenance
and up-keep, educating drivers about driving behavior / methods that will reduce emissions are
beyond the scope of the Project but will be far more effective in reducing the pollutant levels.
8.2.5 Air Quality Monitoring - mitigation
Apart from provision of the mitigation measures, their effectiveness and further improvement in
designs to reduce the air pollution with increase in traffic shall be monitored. The monitoring plan
shall be functional in construction as well as in operation stages. The frequency, duration and
responsibility will be as per the APPENDIX # 8.15: ENVIRONMENTAL MONITORING
PLAN. For location refer table 4.3: Ambient Air Quality Monitoring Locations including one at Hot
mix plant site. And standard/acceptable values are given in table 4.2: National Ambient Air Quality
Standards. Any value/result not within acceptable limits will be reported to engineer, for remedial
measures.
8.3 LAND ENVIRONMENT- MITIGATION MEASURES
Land Acquisition, soil erosion and contamination of soil have emerged as major sources of land
impact especially in urban areas and near by watercourses. Due to the proposed road improvements
aimed at enhancing the efficiency of road transport system, which will result in economic growth in
the region over time.
Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
1 Change in Topography Marginal impact Due to embankment raising. Embankment rising to relieve water logging.

2 Change in Geology Direct , long Extraction of materials (borrow no blasting is envisaged


term, negative earth, coarse & fine aggregates). quarry redevelopment plan need to be enforced
impact
3 Change in Seismology No Negative Cross drainage structures are checked and
Impact complied with the seismological settings of the
region. (Zone)
4 Change in Land
environment
a Loss of land Direct, long- Land Acquisition Land acquisition to be minimized with
term negative Change in land use pattern provision of Retaining walls.
impact
b Generation of Debris Negative Impact May contaminate air, water and disposed properly to avoid contamination
land, if not disposed properly.
c Soil Erosion Moderate, direct, Road slopes and spoils Embankment protection.
long-term For Emb. ht. >3m Stone pitching,
negative impact Emb. ht .<3m Turfing.
Construction of new bridges Residual spoil need to be disposed properly.
and culverts Silt Fencing need to be provided.
Quarry and Borrow areas Quarries need to be reclaimed
5 Contamination of Soil Direct, long term Scarified bitumen wastes Hazardous Wastes (Management and
negative impact Handling) Rules, 1989 to be enforced.
Oil & diesel Spills Oil Interceptor will be provided for accidental
Emulsion sprayer and laying of spill of oil and diesel.
hot mix
Production of hot mix and
Rejected material will be layed in village roads
rejected materials
or as directed by engineer.
Residential facilities for the
labor and officers Septic tank will be construction for waste
Routine and periodical disposal.
maintenance
6 Soil quality - Effectiveness / shortfall (if any) Measures will be revised & improved to
monitoring Any unforeseen impact mitigate/ enhance environment due to any
unforeseen impact.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

The implications of accidental discharge are potentially disastrous. But, it must be


emphasized that the probability of such an accident is quite low, as one of the objectives of
the design is the enhancement of road safety.
8.3.1 Change in Topography - mitigation
As indicated in previous chapter, there is not much change in the embankment of the project road
(refer Table 2.13 Embankment raising sections) hence no appreciable change in topography.
Pavement height will be raised only to accommodate structural layers over the existing pavement.
The raising due to submergence and profile improvement is positive impacts on the local
environment. The raised sections are located away from habitations. Adequate measures have
been taken so that the raising if any in settlement areas should be minimum possible and in
no case exceed 0.5 m.
8.3.2 Change in Geology- mitigation
As part of the Project preparation, the sources of quarries for the fine and coarse aggregates have
been identified for use in road works and structural works, details of the quarries have been
presented in Chapter 4 Baseline Environment. No new quarry has been proposed for the Project
requirements. Only existing, live, licensed quarries will be used as sources of coarse and fine
aggregates. It will be ensured the aggregates procured during construction stage will be from the
authorized or licensed suppliers only. In case of use of any new quarry by contractor, the
instructions/procedure as detailed in APPENDIX # 8.1: AGGREGATE QUARRY
MANAGEMENT will be applicable.
Selected soil borrow areas have been identified during the design stage of the Project. Most of these
borrow areas are local borrow areas, and agricultural fields not in productive use, and where farmers
want to lower the level of the land (reduction of energy requirement for the watering and reduce loss
of water, nutrients, and fertilizer through the seepage). The detailed list of the borrow areas is given
in Chapter 4 Baseline Environment. In case of taking earth from any of these borrow areas the
instructions / procedure as detailed in APPENDIX # 8.2: BORROW AREA MANAGEMENT,
will be applicable.
8.3.3 Change in Seismology - mitigation
As indicated in previous chapter, there will be NO impact on the seismological setting of the region.
Rather, as part of the project all the existing structures will be checked and constructed as per the
seismological requirements of the region in conformity to the IRC 6, 2000 guidelines. Refer Fig 6.1
Seismology map of Andhra Pradesh.
8.3.4 Change in Land Environment – Mitigation
Loss of Land: As far as possible the land acquisition has been kept to the minimum, by restricting
the geometric improvement within the existing right of way. The same can be seen as only 44.69
hectare land is required for project road upgradation. However the land acquisition will be done at
sections having width, insufficient to accommodate the approved cross-sections & geometric
improvements. For Land acquisition sections refer Table 7.2 Land Acquisition Details.
Debris Generation: Due to the removal of structures (Residential and commercial), pavement
scarification and cross drainage structures lot of debris will generate, which need to be disposed
properly to avoid contamination of land and water. For safe and environmental friendly disposal of
waste debris the instruction/procedure specified in APPENDIX # 8.3: DEBRIS DISPOSAL
SITES, will be applicable.
Soil Erosion: could cause sever negative impact if not dealt with, in time, as this harms the
environment in two ways, firstly it erodes the top soil and secondly it spoils the resource where it
settles, mostly water course. Hence soil erosion cause loss of top-soil and contamination of water
bodies/sources/channels.
A comprehensive instruction/procedure is prepared in APPENDIX # 8.4: SITE CLEARANCE
AND TREE FELLING

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

a) Road slopes and spoils


Adequate measures have been devised for control of the soil erosion from the embankments, the
slopes have been restricted to 1 vertical: 2 horizontal for most of the sections. Soil erosion through
embankments is prevented and controlled by following methods.
Alt 1. Grassing of slopes: (for emb. ht. < 3.0m). For this purpose it is best to use locally growing
grasses and bushes, as these are best adapted to the local soil, temperature and rainfall conditions.
Plantation is best done just after the first pre-monsoon showers, which gives a time of 2-3 weeks for
the grass to take root before the onset of monsoon. Normally, no watering of the grassed slopes is
done following the planting. However, watering of the slopes may be provided if the planting is
done in the non-monsoon season, or to respond to dry conditions following planting. The above
methods of providing vegetation cover on embankment slopes follow provisions in IRC-56-1974,
“Recommended Practice for Treatment of Embankment Slopes for Erosion Control”.
Alt 2. Use of Pitching to Control Erosion: (for emb. ht. >= 3.0m). Stones or bricks are hand laid
on the surface and lightly tamped. The interstices between the stones are filled up with soil. Grasses
may be dibbled into the soil filled spaces. As the grass grows, it develops a good binding effect on
the pitching. List of stone pitching sections is provided in previous chapter.
b) Construction of new bridges and culverts
Contractor will be responsible of removing all the debris/ earth generated due to dismantling of
existing structure and excavation of the foundation of cross drainage works, form the water course
before the onset of monsoon.
c) Quarries and borrow areas
A comprehensive management plan for restoring of quarry and borrow area is prepared. Refer
APPENDIX # 8.1: AGGREGATE QUARRY MANAGEMENT & APPENDIX # 8.2:
BORROW AREA MANAGEMENT.
Prior to the start of the relevant construction, the Contractor shall submit to the Engineer for
approval, his schedules for carrying out temporary and permanent erosion/sedimentation control
works as are applicable for the items of clearing and grubbing, roadway and drainage excavation,
embankment/sub-grade construction, bridges and other structures across water courses, pavement
courses and shoulders. He shall also submit for approval his proposed method of
erosion/sedimentation control on service road and borrow pits and his plan for disposal of waste
materials. No construction activity will start prior to approval by engineer, of the measures
and method to be adopted by contractor.
8.3.5 Contamination of soil: Mitigation
Contamination of soil can spoil the soil and can also contaminate the surface as well as ground water
sources. Details of the activities from which the contamination can occur are presented below;
Potential Impact Mitigation/Enhancement
Scarified bitumen wastes, Excess production Scarified waste and excess/rejected hot mix, with the
of hot mix and rejected materials. consent of village authority, will be used in village roads
construction.
Debris generated from dismantling of A comprehensive list of instructions/procedures has been
structures. suggested in APPENDIX # 8.3: DEBRIS DISPOSAL
SITES, for contractor to adhere to for safe and
environmental friendly disposal of debris.
Maintenance of the machinery and operation The base of all machinery, generators will be paved and all
of the diesel generator sets on site the waste/spill will be drained to oil interceptor before
Oil Spill from the operation of the diesel discharging.
pumps and diesel storage, during Figure of oil interceptor is presented below.
transportation and transfer, parking places,
and diesel generator sets
Operation of the emulsion sprayer and Proper demarcation of the surface to be sprayed /paved will

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Potential Impact Mitigation/Enhancement


laying of hot mix be done to minimize the excessive spread of emulsion/hot
mix.
Operation of the residential facilities for the The residential facilities will be provided with proper
labour and officers sanitation, and planed setup of construction camp. A
comprehensive plan of construction camp is prepared in
APPENDIX # 5: SITING & LAYOUT OF
CONSTRUCTION CAMP
Storage and stock yards of bitumen and The base of bitumen/emulsion stock yard will be paved and
emulsion all the waste/spill will be drained to oil interceptor before
discharging.
Figure of oil interceptor is presented below

Oil interceptor: Oil and grease from polluting run-off is another major concern. During
construction, discharge of Oil and Grease is most likely from work shops, oil and waste oil storage
areas, diesel oil pumps, vehicle parking areas from the construction camps. Vehicle/machinery and
equipment maintenance and refuelling will be carried out so that spillage of fuels and lubricants do
not contaminate the soil. The source is well defined and restricted. An “oil interceptor” will be
provided for wash down and refuelling areas. Fuel storage will be in proper bunded areas. All spills
and collected petroleum products will be disposed off in accordance with MoEF and SPCB
guidelines. Fuel storage and fuelling areas will be located at least 300m from all cross drainage
structures and significant water bodies. Drawing 8.1 provides the details of the arrangement for the
oil interceptor for the removal of oil and grease.

Drawing No. 8.1: Conceptual plan of Oil Interceptor

8.3.6 Soil Quality Monitoring - mitigation


Apart from provision of the mitigation measures, their effectiveness and further improvement in
designs to reduce the concentration of pollutants in the soil due to construction activity shall be
monitored, as contamination of soil is directly linked with contamination of water. The monitoring
plan shall be functional in construction as well as in operation stages. The frequency, duration and
responsibility will be as per the APPENDIX # 8.15: ENVIRONMENTAL MONITORING

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

PLAN. For location refer table 4.11: Ambient soil Quality Monitoring Locations including one at
Hot mix plant site. And standard/acceptable values are given in Table 4.12 : National Ambient soil
Quality Standards. Any value/result not within acceptable limits will be reported to engineer, for
remedial measures.
8.4 WATER ENVIRONMENT-MITIGATION MEASURES
Due to the proposed project there will be some direct and indirect long term impacts on the water
resources. Table below presents the major adverse impacts on the water resources and the mitigation
measures taken.
Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
1 Loss of water Major, direct Part or complete Land acquisition to be minimized with
Bodies impact acquisition of source of provision of Retaining walls.
water Relocation of ground/surface water
sources.
2 Alteration of Very Low One major bridge over widening of minor bridges and bridging
Cross Drainage Impact existing causeway. of existing causeways, there will be an
Widening of minor improvement in the drainage
bridges and culverts. characteristics of the project area
3 Runoff and Direct Siltation of water bodies Silt fencing to be provided.
drainage Impact Reduction in ground Recharge well to be provided to
recharge. compensate the loss of pervious
surface.
Increased drainage Continuous drain is provided, unlined
discharge in rural area and lined in urban areas.
4 Water Direct Water requirement for Contractor needs to obtain approvals
requirement for Impact construction activity. for taking adequate quantities of water
project Water requirement of from surface and ground water
labour. sources. This is required to avoid
depletion of water resources
5 Water Quality
a Increased Direct increased sediment laden Silt fencing to be provided.
sedimentation impact run-off
alter the nature & Instructions given in Appendix 8.9:
capacity of the sediment control to be enforced.
watercourse
b Contamination of Direct • Scarified bitumen Hazardous Wastes (Management and
Water adverse wastes Handling) Rules, 1989 to be enforced.
impact • Oil & diesel Spills Oil Interceptor will be provided for
accidental spill of oil and diesel.
• Emulsion sprayer and
laying of hot mix
Rejected material will be layed in village
• Production of hot mix
roads or as directed by engineer.
and rejected materials
• Residential facilities for
Septic tank will be construction for
the labor and officers
waste disposal.
• Routine and periodical
maintenance
6 Water quality - Effectiveness / shortfall Measures will be revised & improved to
monitoring (if any) mitigate/ enhance environment due to
Any unforeseen impact any unforeseen impact.

The implications of accidental discharge are potentially disastrous. But, it must be

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8-9
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

emphasized that the probability of such an accident is quite low, as one of the objectives of
the design is the enhancement of road safety.
8.4.1 Loss of Water Bodies-Mitigation
8.4.1.1 Surface Water Bodies
Two Surface water bodies located along the corridor, Table 8.2 presenting the total no of surface
water bodies along the project road and enhancement measure proposed.
Table 8.2: Surface Water Bodies-Mitigation
Name of Location Distance
Sl. Chainage
Common (Left / from PCL Impact Mitigation/Enhancement
No. (Km.)
Property Right) (in mts)
Right No Direct Repair of tank platform
1 153+600 Water Tank 9.6
Impact Proper drainage with soak pit
No Direct No impact/ bypassed
2 165/300 Water Body Left 11.2
Impact

8.4.1.2 Ground water resources


Loss of other water supply sources includes; removal of private and community ground water
sources like bore wells, tube wells and open wells. These losses have been covered under the utility
relocation process in the pre-construction phase of the EMAP. Compensatory water supply sources
will be set up before the start of construction activities. Impacted Ground water resources present
along the project road and its mitigation measure present in the Table 8.3.
Table 8.3: Ground water Sources-mitigation
Name of Location Distance Mitigation/Enhancement
Sl. Chainage
Common (Left / for PCL Impact
No. (Km.)
Property Right) (in mts)
1 156/030 Hand Pump Left No Direct Impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
2 156/164 Hand Pump Right 6.4 Direct impact Drain and soak pit as per Drawing 8.2
3 41/300 Hand Pump Left 7.3 No Direct Impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
4 156/463 Hand Pump Left 8 Direct impact Drain and soak pit as per Drawing 8.2
5 157/160 Hand Pump Left No Direct Impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
6 157/770 Hand Pump Left 10.6 Direct impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
7 161/250 Hand Pump Right 11.7 Direct impact Drain and soak pit as per Drawing 8.2
8 163/000 Hand Pump Right 5.8 No Direct Impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
9 168/200 Hand Pump Right 7 Direct impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
10 168/350 Hand Pump Left 5 Direct impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
11 168/420 Hand Pump Left 9 Direct impact Drain and soak pit as per Drawing 8.2
Hand Pump
12 168/710 Left 2.8 No Direct Impact Drain and soak pit as per Drawing 8.2
M.V.P.H.P.4
Will be relocated to the nearest place
13 169/430 Hand Pump Right 3.7 Direct impact Drain and soak pit as per Drawing 8.2
Will be relocated to the nearest place
14 182/449 Hand Pump Right 9 Direct impact Drain and soak pit as per Drawing 8.2

Any source of community water (potable or otherwise) such as open wells, ponds, tube-wells and
bore wells, accidentally lost will be replaced immediately. The location and siting of the replaced
source of water will be as close as possible to the original source.
The project road passes through the dry region of Andhra Pradesh, loss of water has sever impact,
hence soak pits are provided for the waste water from the hand pump to recharge the ground water,

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 10
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

which otherwise would have lost by evaporation. The typical layout of the soak pit is presented
below in Drawing No. 8.2

Drawing No. 8.2 : Conceptual plan of Soak Pit for Hand Pump

8.4.2 Alteration of cross drainage


• All cross drainage structures have been designed to handle a 50-year peak flood level. A detailed
hydrological study had been carried to calculate the design discharge.
• Pipe drainages will be provided for diversion roads constructed for the construction of new
bridges and culverts. (refer drawing 8.3)
• Storm water from all longitudinal and Cross drainage works will be connected to the natural
drainage courses.
• The contractor will remove obstructions that may cause temporary flooding of local drainage
channels, during the construction phase.
• Contractor will be responsible for removal of debris generated due to the dismantling of
structure and earth generated due to the excavation of foundation, from the water course before
the onset of monsoon. For list of bridge under reconstruction/new proposed bridges (refer
Table 6.11)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 11
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Drawing No. 8.3: Conceptual Plan of Diversion at Bridge Location

8.4.3 Runoff and drainage


• Continuous Drain (lined/unlined) is provided throughout the project road for efficient drainage
of storm water.
• Lined drain is provided at builtup sections for quick drainage of storm water.
• The increased runoff due to increased impervious (Bituminous Top) surface will be countered
with increased pervious surface area through soak pits, at hand pump locations.
• The local bodies need to discourage/stop the filling of private water bodies, ponds etc to
develop commercial places and shops due to the improved roads and improved connectivity
8.4.4 Water Requirement for Project
Acquisition and management of water for construction is an issue that must be addressed by the
contractor. The Contractor is expected to obtain water for construction purposes that is of a high
water quality.
• Contractor needs to obtain approvals for taking adequate quantities of water from surface and
ground water sources. This is required to avoid depletion of water resources.
• Contractor is required to minimise wastage of water.
• Water conservation methods to be adopted during construction process to make optimum use
of water, as limited water sources are available along the PR.
8.4.5 Water Quality
a) Increased sedimentation
• Silt fencing will be provided
• Desilting will be done for the existing ponds/Tanks
• Desilting of the waste water will be ensured before the discharge of drain water into natural
stream
• Instructions given in APPENDIX 8.9: SEDIMENT CONTROL to be enforced
Table 8.5 List of silt fencing locations
Sl. No. Location Length (approximate) Remark
1 Top soil storage 300m Around the periphery of dumping yard
2 Borrow area site 100m Along the length of borrow area in down slope direction
3 Surface Water bodies 200m Equals to diameter/length or as instructed by engineer.
4 Plant Site 100m In down slope direction of fine material

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 12
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Drawing No. 8.5: Conceptual plan of silt fencing.


b) Contamination of water.
• Oil interceptor will be provided at plant site and truck lay byes.
• Construction work close to the streams or water bodies will be avoided during monsoon.
• The discharge standards promulgated under the Environmental Protection Act, 1986 will be
strictly adhered to. All wastes arising from the project will be disposed off in a manner that
is acceptable to the State Pollution Control Board (SPCB).
• All relevant provisions of the Factories Act, 1948 and the Building and other Construction
Workers (regulation of Employment and Conditions of Service) Act, 1996 will be adhered
to.
• Construction labourers’ camps will be located at least 1000m away from the nearest
habitation.
• Unless otherwise authorised by the local sanitary authority, arrangements for proper
disposal of excreta by incineration at the workplace suitably approved by the local medical
health or municipal authorities will be made.
• All approach roads to rivers and other surface water bodies need to be closed permanently
to avoid vehicle washing and to avoid major pollution sources. This applicable to all areas
including the secondary construction sites.
• Automotive service centres will be discouraged from establishing along the corridors with
out installing preventive measures against petroleum and oil contamination.
8.4.6 Water Quality Monitoring - mitigation
Apart from provision of the mitigation measures, their effectiveness and further improvement in
designs to reduce the concentration of pollutants in the soil due to construction activity shall be
monitored, as contamination of soil is directly linked with contamination of water. The monitoring
plan shall be functional in construction as well as in operation stages. The frequency, duration and
responsibility will be as per the APPENDIX # 8.15: ENVIRONMENTAL MONITORING

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 13
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

PLAN. For location refer table 4.11: Ambient Water Quality Monitoring Locations including one at
Hot mix plant site. And standard/acceptable values are given in table 4.12: National Ambient Water
Quality Standards. Any value/result not within acceptable limits will be reported to engineer, for
remedial measures.
8.5 NOISE ENVIRONMENT-MITIGATION MEASURES
Environmental noise particularly highway traffic noise, is a complex phenomenon because its
intensity and characteristics vary with time depending upon the frequency as well as type of vehicles
on the road.
Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
Noise barrier to be provided
Sensitive Direct
1 Increase in noise pollution Traffic calming devises to be used.
receptors impact
NO Horn Zone sign Post.
Man, material & machinery
Noise movements Area specific and for short duration
Pollution Direct Machinery to be checked & complied
2a (Pre- impact, short Establishment of labor with noise pollution regulations.
Construction duration camps onsite offices, stock Camps to be setup away from the
Stage) yards and construction settlements, in the down wind direction.
plants
stone crushing, asphalt Camps to be setup away from the
production plant and settlements, in the down wind direction.
Noise
batching plants, diesel Noise pollution regulation to be
Pollution Marginal
2b generators etc monitored and enforced.
(Construction Impact
Temporary as the work zones will be
Stage)
Community residing near changing with completion of
to the work zones construction
Noise will be compensated with the
due to increase in traffic
Pollution Marginal uninterrupted movement of heavy and
2c (due to improved facility)
(Operation Impact light vehicles till the facility reaches the
Stage) level of service C.
Noise Effectiveness / shortfall (if Measures will be revised & improved to
3 Pollution any) mitigate/ enhance environment due to
Monitoring Any unforeseen impact any unforeseen impact.

8.5.1 Sensitive Receptors – mitigation


All schools, hospitals and cultural properties have been identified and those that are close to the
project roads ie with in 100 m distance will require noise barrier to accommodate the long term
impact of the improved road. List of sensitive receptors along the project corridor is presented in
table 8.6 below
Table 8.6 List of sensitive receptor
Name of Location Distance Distance Dimensions
Sl. Chainage
Common (Left / from ECL for PCL Impact Mitigation/Enhancement
No. (Km.) Length Breadth
Property Right) (in mts) (in mts)
Shahi Direct
1 153+080 Left 5.5 5.53 5.00 14.00
Hospital Impact
Will be relocated to the
Sri Bala nearest possible place.
Direct
2 41/300 Sisuvu High Right 7.9 7.8 10.30 200.00
Impact
School
Govt.
Direct
3 153+460 Hostel for Left 7.7 8.4 60.00 100.00 Boundary wall will be shifted.
Impact
Girls Noise barrier will be
Veternairy Direct provided (refer dwg:8.6)
4 153+600 Left 9 38.00 50.00
Hospital impact
No Direct Noise barrier will be
5 156+380 Govt School Left 11.2 11.3 16.00 40.00
Impact provided (refer dwg:8.6)

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 14
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Name of Location Distance Distance Dimensions


Sl. Chainage
Common (Left / from ECL for PCL Impact Mitigation/Enhancement
No. (Km.) Length Breadth
Property Right) (in mts) (in mts)
Kasthuriba
Gurukula No Direct Noise barrier will be
6 158+800 Left 10.1 14.1 35.00 100.00
Girls High Impact provided (refer dwg:8.6)
School
Veternairy No Direct
7 161+250 Right 8.1 8.0 20.00 60.00
Hospital Impact Noise barrier will be
Veternairy No Direct provided (refer dwg:8.6)
8 163+200 Left 17.7 18.2 20.00 35.00
Hospital Impact
No Direct
9 168+100 Govt School Right 10 10.9 22.00 10.00
Impact
V.P.R. Noise barrier will be
No Direct
10 168+850 College of Left 10 14.0 70.00 200.00 provided (refer dwg:8.6)
Impact
Education
No Direct
11 194+200 School Right 10.8 10.9 110 200.00
Impact
1000

230
200
2500

2500
150

300 25
345
600

460

575
100

750

Drawing No. 8.6: Conceptual Drawing for Noise Barrier

8.5.2 Noise Pollution - Mitigation


• Noise standards will be strictly enforced for all vehicles, plants, equipment, and construction
machinery. All construction equipment used for an 8-hour shift will conform to a standard of
less than 90dB(A). If required, high noise producing generators such as concrete mixers,
generators, graders, etc. must be provided with noise shields.
• Machinery and vehicles will be maintained regularly, with particular attention to silencers and
mufflers, to keep construction noise levels to minimum.
• Workers in the vicinity of high noise levels will be provided earplugs, helmets and will be
engaged in diversified activities to prevent prolonged exposure to noise levels of more than
90dB(A) per 8 hour shift.
• During construction vibratory compactors will be used sparingly within the urban areas. In case
of complaints from roadside residents, the engineer will ask the site engineer to take suitable
steps of restricting the work hours even further or use an alternative roller.
• Proposed tree and shrub plantations planned for avenue plantation especially close to
settlements, may form an effective sound buffer during the operation stage.
• People will be convinced / educated to prevent sensitive land uses from developing up adjacent
to the project corridors.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 15
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

8.5.3 Noise Pollution Monitoring - mitigation


Apart from provision of the mitigation measures, their effectiveness and further improvement in
designs to reduce the concentration of pollutants in the soil due to construction activity shall be
monitored, as contamination of soil is directly linked with contamination of water. The monitoring
plan shall be functional in construction as well as in operation stages. The frequency, duration and
responsibility will be as per the APPENDIX # 8.15: ENVIRONMENTAL MONITORING
PLAN. For location refer table 4.11: Ambient Water Quality Monitoring Locations including one at
Hot mix plant site. And standard/acceptable values are given in table 4.12: National Ambient Water
Quality Standards. Any value/result not within acceptable limits will be reported to engineer, for
remedial measures.
8.6 FLORA & FAUNA - MITIGATION
The major impact in this project on flora involves the removal of trees to permit construction and to
provide clear zone for safety of the road users. There is NO recorded wild life habitat in near vicinity
of the project corridor.
Trees located within the clear zone need to be removed to prevent collision with the trees, in case of
accident. Roadside trees with strong and rigid stems can pose safety hazards. Some trees obstruct
clear sight distances. Others have a propensity to overturn when old and are potential safety hazards
depending upon age and decay condition. All such trees that are safety hazards need to be cleared.
Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
1 Forest area NO Impact No forest area Nil
2 Wild Life NO Impact No wild life habitat Nil
Maximum deviation in alignment design
to save the road side trees.
Increase in soil erosion,
Compulsory tree plantation in the ratio
silting of water bodies,
of 1:2, i.e. for each tree cut, two saplings
Dust & noise pollution.
3 Trees Cutting Direct impact will be enforced However Avenue
plantation along corridor is also
loss of shade & loss of tree
proposed.
products
Endangered Tree species will be
transplanted.
Clearing and grubbing will be minimized,
and sprinkled with water to reduce dust
Increase in soil erosion, pollution.
silting of water bodies, Exposed surface like embankment slopes
4 Vegetation Direct Impact
noise pollution. Dust will be protected with stone pitching and
Pollution turfing.
Open land in and around plant will be
vegetated.
5 Cattle Grazing No Impact No cattle grazing found Nil

8.6.1 Forest Area – Mitigation


No forest area within the corridor of impact.
8.6.2 Wild Life - Mitigation
No wild life habitat/wild life crossing within the corridor of impact.
8.6.3 Trees – Mitigation
The mitigation and enhancement measures taken along the project corridor includes,
a) Compensatory Afforestation: to compensate the felling of trees.
b) Avenue Plantation
c) Plantation at enhancement sites

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 16
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

d) Landscaping at Junctions and realignment locations etc.


Compensatory Afforestation: Compensatory afforestation will be taken up as per the Forest
(Conservation) Act, 1980. For each tree felled, two trees will be planted. The R&BD will bear the
cost of such afforestation. Refer APPENDIX 8.10: ARRANGEMENT WITH FOREST
DEPARTMENT
• To minimise loss of trees, clearance of only those trees identified from the design will be
removed. The felling of trees has been minimised as much as possible by having the centreline
adjusted so as to necessitate felling of trees from only one side, in case of green tunnel.
• Endangered species, if found during construction, will be transplanted as per the APPENDIX
8.13: TRANSPLANTATION OF TREES.
• No tree will be removed in the zone of construction without the prior approval of the DoF,
through the supervising engineer.
• A total of 1163 trees need to be uprooted along the alignment because of project intervention.
Avenue Plantation: In addition to the compensatory afforestation, trees shall be planted along the
project corridors by the APRDC through Department of Forest for this purpose RDC should sign a
MOU with Department of Forest. Such plantations will be initiated once the construction is
complete. The objective behind such plantation is to cover/ re-vegetate the areas within the RoW
that are at presently barren. To maintain the present character of strip plantation, similar indigenous
trees should be planted. Refer APPENDIX 8.11: SELECTION OF TREE SPECIES.
• Considering the combined compensatory afforestation by DoF and the plantation by the
APRDC, a total of 6,000 saplings will be planted along the corridor in single, 300 no. of trees in
each package.
• Costing has been done as per forest schedule of rate, including the plantation and maintenance
cost for 3 years.

Drawing No. 8.7: Conceptual Plan for Avenue Plantation

Landscaping at Junctions and medians etc: No trees are planted up to 50m before the
intersections so as to achieve clear sight distances For intersections, shrubs will be planted at 1.5m
c/c as per the design shown in the Figure 8.8. Beyond this point only dwarf shrubs are planted.
The height of these shrubs should be such that they do not obstruct the view of traffic coming from
the intersecting road. The plants recommended for intersections are Celodendron inerme, Antirhinnum,

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 17
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Browallia. The intersections where landscaping is proposed is presented in the individual EMPs. The
supervision consultant shall ascertain availability of space in the junctions mentioned below and
plantation shall be done in the available space. Refer APPENDIX 8.11: SELECTION OF TREE
SPECIES.

Drawing No. 8.8: Conceptual Plan for Tree Guard

8.6.4 Vegetation - Mitigation


• High embankment will be re-vegetated with local shrubs and grasses to prevent soil erosion
from the bare earth, prior to the monsoon.
8.6.5 Cattle Grazing - Mitigation
No cattle grazing seen along the corridor.
8.7 SOCIO-ECONOMIC ENVIRONMENT - MITIGATION
Adverse socio-economic impacts include all disruptions on the social and economic interactions of
communities due to the road project. This involves effect on both the adjacent communities (mostly
direct) as well as the nearby communities (mostly indirect). The various impacts have been detailed
as:
• General impacts that apply to the entire corridor,
• Specific impacts on likely properties and PAPs, within the Corridor of Impact (CoI) of the
project corridor.
8.7.1 General Impacts - Mitigation
Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
1 Fear of Direct, long Land and property owners are Public participation sessions
uncertainties Impact subjected to sufferings regarding were/will be conducted in
regarding future uncertainties of the extent of loss different stages of project.
and the nature of compensation
2 Inducement of Direst impact danger of unscrupulous Market Value Assessment
land prices speculators moving in to purchase Committee will decide the actual

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 18
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
land cost of land
3 Inducement of Direct impact Squatters may attempt to occupy The dates of base-line socio-
squatter influx adjacent land in the hope of economic survey have been
receiving compensation undue considered as cut off date for
pressure on local resources identification of project affected
people PAP.
4 Loss of utilities Direct Natural (trees, bushes and Relocation of utilities will be
and amenities Impact grasslands), and Physical completed prior to start of
structures (public or private project work.
assets and utilities). These have been further
discussed in details in RAP
5a Public Health High direct Psychological impacts on their Advance notice as per RAP(4
and Safety adverse owners and others associated months before commencement
impact with them. of work) will be given to the
owners of the affected
Debris generated properties.
Debris, so generated will be
disposed to the satisfaction of
Engineer. Refer Appendix 8.3:
Debris Disposal Site.
Monitoring of air , water ,noise
and land during construction
and operation phase. Refer
Appendix 8.15: Monitoring
Plan.
Refer Appendix 8.7:
Environment Friendly
construction Methodology.
5b Labour Camps Direct can have clashes with the local All contractors will be
Impact population encouraged to recruit the local
Pressure on basic facilities like people as labourer at least for
medical services, power, water unskilled and semi-skilled jobs.
supply, etc.
Transmission of communicable Hygiene and basic facilities will
diseases including aids. be ensured at labour camp to
sanitary conditions in the labour prevent the spread of disease.
camps Refer Appendix 8.5 sitting and
layout of construction Camps,
and Appendix 8.6 Workers
Safety during construction
5c Allied activities Indirect Social and economic life of the Detailed traffic control plans
Impact local population due to quarrying shall be prepared and submitted
and crushing operations, traffic to the engineer for approval 5
diversions, etc. days prior to commencement of
traffic jams and congestion, loss work on any section of road.
of access and other road accident
risks temporary land acquisition
5d Accidents and Direct School children The contractor will provide,
Safety Impact ladies carrying pots full of water erect and maintain barricades,
including signs marking flags
lights and flagmen as required
by the Engineer.
6 Resettlement of In direct Pressure on civil amenities, water A comprehensive resettlement
People impact sources, grazing lands, fuel wood, action plan has been prepared
medical facilities etc. to improve the standard of
living of the affected population

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 19
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Sr.
Item Impact Impact (Reason) Mitigation/Enhancement
No.
7 Land Use Indirect Succession of land uses and Project is widening of existing
Changes impact higher return uses would displace of pavement, hence no major
the lower return uses at major change in land use pattern is
intersections and in settlement envisaged along the project
areas. road.
Urban fringe areas will be
subjected to ribbon development.
8 Disturbance to Indirect Some Shops may be shifted, no The cleaning of such informal
road side Impact income from highway users establishment will be carried
services hence loss of service to the local out as phase-wise resettlement
people Programme
9 Removal of Indirect loss of shelter disturbance to Impact will be avoided by
encroachments impact family and community life implementation of phase-wise
and squatters resettlement action Programme
Notice will be served 4 months in
advance.
10 Sensitive Indirect Loss of community facilities or Discussed in detail in following
community impact institutions paragraphs.
facilities
11 Host Indirect Displaced, resettled families will special provision has been
Community Impact put pressure on the existing made in the comprehensive
scarce infrastructure and resettlement action plan for the
amenities available with the host host community
community

8.7.1.1 Fear of uncertainties regarding future


The Project is only of widening and strengthening of the existing road, and within the confines of
the existing RoW, the fear of uncertainties is most likely limited to the people squatting and
encroaching in the RoW. At places where the community utilities are to be affected a certain amount
of anxiety will be among the people in that particular community.
To remove such fear from the people, public participation sessions were/will be conducted in
different stages of project, viz. pre-design, design, pre-construction and construction.
In the pre-design stage, a comprehensive socio-economic survey was conducted to prepare base line
status of the households squatting or encroached upon the RoW. During the survey each
households were contacted/interviewed and they were explained about the purpose of the survey,
need of the project and benefits associated with the project etc.
The second stage of public participation was in the form of village meetings, focus group discussion,
individual interviews, voluntary and academic institution consultation.
The third stage of participation session will start before pre-construction. The EMU will verify and
consult the individual EPs with the help of an NGO for distribution of ID card. At this stage the
EPs will be explained about their entitlement and R&R framework.
All people likely to be displaced will be informed in advance through NGO by a time bound
Programme about resettlement to remove fear of uncertainty.
During the construction stage the consultation process will continue to avoid any inconvenience to
the community at any point of time.
8.7.1.2 Inducement of Land Prices
As the project becomes common knowledge, the land prices along the corridor will increase. For
realignment and geometric improvement of highway, extra additional land may be required; Market
Value Assessment Committee will decide the actual cost of such land. The actual cost of land may
be different from induced land cost. The MVAC have time bound Programme to calculate the

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 20
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

actual cost of land. In calculating the actual land cost individual project affected person (PAP) &
NGOs will be involved.
8.7.1.3 Inducement of Squatter Influx
Once the project becomes common knowledge, people may attempt to occupy the land along the
corridor in anticipation of compensation. To avoid such, the dates of base-line socio-economic
survey have been considered as cut off date for identification of project affected people, who are
eligible for compensation. The cut off dates will be used to establish whether a person located in the
right way qualifies as a PAP for the disbursement of compensation. All the PAPs recorded during
socio-economic baseline survey are eligible for compensation after verification by EMU.
8.7.1.4 Loss of utilities and amenities
The site clearance for construction of road may result in loss or relocation of certain utilities and
amenities, viz. electricity, water and telephone line etc. People dependent upon these utilities and
amenities may experience inconvenience and economic loss. Though such impacts are unavoidable
keeping in mind the scale of work, but every care will be taken in co-ordination with concerned
departments, to restore the facility within shortest possible time to avoid any prolonged hardship or
inconvenience to the community. Similarly other utilities like water source, cattle trough etc. will be
constructed or replaced at appropriate place with the consent of community prior to dismantling the
existing one.
8.7.1.5 Public Health and Safety
a) During the Pre-construction and Construction Phases dismantling of the structures for CoI
clearance and road construction may result in health hazards. To minimise this potential negative
impact the following recommendations should be adopted:
• To avoid the psychological impacts due to the demolition of properties on the owners and other
tenants. The advance notice as per RAP will be given to the owners of the affected properties.
An advance notice will be served at least four months before construction commences. For
squatters needing relocation, all R&R activities will be undertaken and entitlements will be
completed before construction starts.
• Debris generated from the demolition of properties will be properly disposed of to avoid the
health problems in the safeties. Earth material, if required will be dumped in borrow areas as
approved by the engineer. Borrow areas will be filled to avoid health hazards from stagnant
water collecting in these areas. The contractor will make all arrangements for dismantling and
cleaning up of debris. Implementation will be as per the approval and direction of the engineer.
• Instructions as given in APPENDIX 8.7: ENVIRONMENT FRIENDLY CONSTRUCTION
METHODOLOGY, to be enforced
b) During the construction period the potential negative community impacts arising from imported
labour in the labour camps will be avoided as per following: -
All contractors will be encouraged to recruit the local people as labourer at least for unskilled
and semi-skilled jobs. This would automatically reduce the magnitude of impact expected due to
outside labour. Wherever the local labourers are not available the contractor should ensure the
following provision for imported labour.
• The additional stress on the facilities like medical services, power, water supply due to a
labour camp in a local area will be avoided by the contractor providing these facilities for the
labourers as per the direction of the Engineer
• In areas where wildlife resources are abundant, construction workers shall be instructed how
to protect natural resources, fauna, flora and aquatic life. In such areas hunting and
unauthorised fishing are prohibited.
• In the labour comps, all temporary accommodation must be constructed and maintained in
such a fashion that uncontaminated water is available for drinking, cooking and washing.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 21
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

The sewage system for the camp will be properly designed built and operated so that no
health hazard occurs. Garbage bins will be provided in the camp and regularly emptied. The
collected garbage will be disposed off in a hygienic and approved manner.
• Instructions as given in APPENDIX 8.5: SITTING AND LAYOUT OF
CONSTRUCTION CAMPS, to be enforced.
• Instructions as given in APPENDIX 8.6: WORKERS SAFETY DURING
CONSTRUCTION, to be enforced.
• Instructions as given in APPENDIX 8.8: STORAGE, HANDLING USE AND
EMERGENCY DURING CONSTRUCTION, to be enforced.
c) Allied activities during construction period may cause local disruption:
In the construction phase, there may be inconvenience to the local people as well as the highway
passengers due to traffic jams and congestion, loss of access and other road accident risk as a
result of construction. Detailed traffic control plans shall be prepared and submitted to the
engineer for approval 5 days prior to commencement of work on any section of road. In the
preparation of the traffic control plan special consideration shall be given to the safety of
pedestrians and workers at night.
d) Accidents and Safety
To avoid the accidents during construction phase, contractor shall take all necessary measures to
ensure traffic safety. The contractor will provide, erect and maintain barricades, including signs
marking flags lights and flagmen as required by the Engineer.
In the operation phase, traffic control measures such as speed breakers and sign boards
(including speed limits) will be provided and strictly enforced in residential areas, near schools
and water bodies like ponds and wells.
8.7.1.6 Resettlement of People
People displaced from their home and livelihood on account of the proposed activity will be taken
care in the project. A comprehensive resettlement action plan has been prepared to improve the
standard of living of the affected population if not at least restore their livelihood and regaining their
former standard of living (Refer Resettlement Action Plan Report).
8.7.1.7 Land Use Changes
As regards land use changes, it is likely that the impact would be very minimal. Since the project is
widening of road within the existing ROW, the possibility of major land acquisition is not envisaged.
In design stage utmost care has been taken to keep the land acquisition at minimal for road
realignment and geometric purpose. The probable impact on road-side business and trees within
ROW has been reduced and avoided through design.
8.7.1.8 Disturbance to Roadside Service
Along the highway, near settlements, small shops serve the local people as well as highway users.
Some of these shops are within the RoW. To avoid any impact on livelihood of people dependent
on roadside business, the cleaning of such informal establishment will be carried out as phase-wise
resettlement Programme. Loss of livelihood of the displaced shop owners will be compensated as
per assistance or entitlements in Entitlement Framework of Andhra Pradesh.
8.7.1.9 Removal of Encroachments and Squatters
The impact due to removal of encroachments and squatters will be avoided by implementation of
phase-wise resettlement action Programme. To avoid the severance of impact, advance notice will be
given to the encroachers and squatters. The notice will be given four months prior to construction
phase starts. Relocation of all such impacted persons will be as per R&R schedule.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 22
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

8.7.1.10 Sensitive Community Facilities


The impacts due to project on the sensitive community facilities or institution along the project
corridor such as education institution, health facilities, a number of recreational facilities and others
like ponds and cultural community assets avoided in the design phase of the project. These are
discussed in detail in subsequent paragraphs.
8.7.1.11 Host Community
Families displaced due to the project will be resettled at suitable place. This may put pressure on the
existing scarce infrastructure and amenities available with the host community. To avoid such
pressure on already scarce resources, viz. water, grazing land, fuel woods, and medical facility etc.
special provision has been made in the comprehensive resettlement action plan for the host
community. This will be applicable where the total number of resettled people exceeds 200 or 10
percent of the host community whichever is less (Refer: Resettlement Action Plan Report).
8.7.2 Specific Impacts – Mitigation
8.7.2.1 Sensitive Cultural Properties (CPR)
A no. of sensitive communal assets exists along the project corridor. Table below presents the
impact and mitigation/enhancement proposed at each location. (Refer APPENDIX 8.14:
MITIGATION/ENHANCEMENT OF CULTURAL PROPERTIES.)
Table 8.7 List of Sensitive Cultural Properties
Dimensions Mitigation/
Name of Location Distance Distance
Sl. Chainage Enhancement
Cultural (Left / from ECL for PCL Impact
No. (Km.) ( As per Appendix 8.14)
Property Right) (in mts) (in mts) Length Breadth
Mosque With No Direct
1 153/800 Right 7.7 11.6 5.00 4.00 ……….
Neem Tree Impact
Hanuman Direct
2 41/300 Right 6.5 6.6 9.00/8.00 15.00 Will be relocated
Temple Impact
Hanuman No Direct
3 160/840 Left 7.5 12.0 4.00 4.00
Statue Impact
No Direct
4 160/840 Temple Arch Left 12.5
Impact
Temple Cum No Direct
5 162/375 Left 7.5 11.0 30.00 60.00
Ashramam Impact
Kasi No Direct
6 165/450 Right 8.9 14.1 12.00 30.00
Temple Impact
Vinayaka No Direct
7 167/350 Left 9.7 13.9 22.00 55.00
Temple Impact
Direct
8 167/450 Temple Right 7.5 2.9 12.00 14.00 Will be relocated
Impact
Direct
9 168/200 Church Right 8.5 8.5 20.00 15.00 Will be relocated
Impact
Hanuman
Direct
10 168/350 Temple Side Left 6.5 6.0 5.00 3.00 Will be relocated
Impact
Tree
Gangamma Direct
11 168/433 Right 6.5 6.3 1.50 1.50 Will be relocated
Stone Impact
Mosque With Direct
12 168/450 Right 7 6.7 6.00 5.50 Will be relocated
Tree Impact
Renuka
Direct
13 169/350 Ellamma Right 5.1 -0.7 2.50 2.50 Will be relocated
Impact
Temple
No Direct
14 170/040 Swamiji Temple Left 14.5 16.5 6.00 14.00
Impact
Penta Coastal No Direct
15 170/920 Left 11.5 12.4 12.00 100.00
Church Impact
No Direct
16 170/940 Dargh Left 11.5 12.3 13.00 100.00
Impact
No Direct
17 181/740 Ashramam Left 7.5 11.4 16.00 40.00
Impact
18 182/090 Church Right 16.5 16.1 No Direct

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 23
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Impact

Besides mitigation & enhancement, following measures will be taken for safety of the locals:
• Local people will be informed about the schedule of construction activity, so that the local
people remain prepared in advance.
• The existing sign boards will not be removed but shifted to appropriate place during
construction, so that people don’t find problem in identifying the tourist/religious place.
• During construction proper demarcation and sign board, indicators and flag man will be
deputed for safe traffic movement. (Refer drawing 8.10)
8.8 BUS SHELTER, BUS BAYS, TRUCK LAY BYES, RESTING PLACE AND SERVICE
ROAD
As a part of road improvement, bus shelters will be constructed/repaired at all built up locations.
The table below presents the impact and mitigation proposed for each of the existing bus shelters.
Table 8.8 List of Existing Bus Shelters
Location Distance Impact
Sl. Name of Chainage (Left / for PCL Mitigation and
No. Property (Km.) Right) (in mts) Enhancement
1 Bus Shelter 157/770 Left 16.4 No Direct Impact
2 Bus Shelter 161/250 Right 8.1 Direct impact Will be Relocated
3 Bus Shelter 166/810 Left 2.6 No Direct Impact
4 Bus Shelter 167/725 Left 13.5 No Direct Impact
5 Bus Shelter 168/830 Right 4.5 Direct impact Will be Relocated
6 Bus Shelter 169/500 Right 0.0 Direct impact Will be Relocated
7 Bus Shelter 177/930 Right 11.5 No Direct Impact
8 Bus Shelter 180/955 Left 3.0 Direct impact Will be Relocated
9 Bus Shelter 187/055 Left 3.3 Direct impact Will be Relocated
10 Bus Shelter 190/205 Left 1.1 Direct impact Will be Relocated
(Refer Drawing No 8.9)
Besides the reconstruction/relocation of 5 bus shelters and repair & rehabilitation of all existing bus
shelters, 18 nos. of new bus shelter/bus laybyes are proposed, tabulated below.
Table 8.9 List of Proposed Bus Shelters
Sl. Location
Description Remarks
No LHS RHS
1 Shelter 153.050 153.100 Mydukuru
2 Shelter 156.350 156.400 Vishwanadapuram Village
3 Shelter 161.100
4 Shelter 162.600 162.650
5 Shelter 168.100 168.150
6 Shelter 170.950 170.900 Prodhutoru Village
7 Shelter 177.800
8 Shelter 177.400
9 Shelter 183.150
10 Shelter 183.350 Chauduru Village
11 Shelter 187.000 187.050 Salivendula Village
12 Shelter 190.650
For dimensions, plan and layout refer drawing no 8.9: Conceptual plan of Bus shelter.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 24
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Drawing No. 8.9: Conceptual Plan for Bus shelter

8.9 AVOIDANCE OF DISRUPTION AND SAFETY RISKS DURING THE


CONSTRUCTION STAGE
8.9.1 Disruption to the Community
8.9.1.1 Loss of Access
At all times, the Contractor will provide safe and convenient passage for vehicles, pedestrians and
livestock to and from side roads and property accesses connecting the project road. Work that
affects the use of side roads and existing accesses will not be undertaken without providing adequate
provisions.
The works will not interfere unnecessarily or improperly with the convenience of public or the
access to, use and occupation of public or private roads, railways and any other access footpaths to
or of properties whether public or private.
8.9.1.2 Traffic Jams, Congestion and Safety
Detailed Traffic Control Plans will be prepared prior to commencement of works on any section of
road. The traffic control plans will contain details of temporary diversions, details of arrangements
for construction under traffic and details of traffic arrangement after cessation of work each day.
Temporary diversion (including scheme of temporary and acquisition) will be constructed with the
approval of the Engineer and the EMU. Special consideration will be given in the preparation of the
traffic control plan to the safety of pedestrians and workers at night.
The Contractor will ensure that the running surface is always properly maintained, particularly during
the monsoon so that no disruption to the traffic flow occurs. The temporary traffic detours will be
kept free of dust by frequent application of water, if necessary.
The Contractor will take all necessary measures for the safety of traffic during construction and
provide, erect and maintain such barricades, including signs, markings, flags, lights and flagmen as
may be required by the Engineer for the information and protection of traffic approaching or
passing through the section of the highway under improvement.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 25
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Drawing No. 8.10: Conceptual Plan for traffic Diversion

8.9.2 Safety of the Workers


• Refer Appendix 8.5: Sitting And Layout Of Construction Camp.
• Refer Appendix 8.6: Workers Safety During Construction.
• Refer Appendix 8.7: Environment Friendly Construction Methodology.
• Refer Appendix 8.6: Storage, Handling Use And Emergency.
8.9.2.1 Risk from Operations
The Contractor is required to comply with all the precautions as required for the safety of the
workmen as per the International Labour Organisation (ILO) Convention No. 62 as far as those are
applicable to this contract. The contractor will supply all necessary safety appliances such as safety
goggles, helmets, masks, etc., to the workers and staff. The contractor has to comply with all
regulation regarding safe scaffolding, ladders, working platforms, gangway, stairwells, excavations,
trenches and safe means of entry and egress.
8.9.2.2 Risk from Electrical Equipment
Adequate precautions will be taken to prevent danger from electrical equipment. No material or any
of the sites will be so stacked or placed as to cause danger or inconvenience to any person or the
public. All necessary fencing and lights will be provided to protect the public. All machines to be
used in the construction will conform to the relevant Indian Standards (IS) codes, will be free from
patent defect, will be kept in good working order, will be regularly inspected and properly
maintained as per IS provisions and to the satisfaction of the Engineer.
8.9.2.3 Risk at Hazardous Activity
All workers employed on mixing asphaltic material, cement, lime mortars, concrete etc., will be
provided with protective footwear and protective goggles. Workers, who are engaged in welding
works would be provided with welder’s protective eye-shields. Stone-breakers will be provided with
protective goggles and clothing and will be seated at sufficiently safe intervals.
The use of any herbicide or other toxic chemical will be strictly in accordance with the
manufacturer’s instructions. The Engineer will be given at least 6 working days notice of the
proposed use of any herbicide or toxic chemical. A register of all herbicides and other toxic
chemicals delivered to the site will be kept and maintained up to date by the Contractor. The register
will include the trade name, physical properties and characteristics, chemical ingredients, health and
safety hazard information, safe handling and storage procedures, and emergency and first aid
procedures for the product.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 26
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

8.9.2.4 Risk of Lead Pollution


No man below the age of 18 years and no woman will be employed on the work of painting with
products containing lead in any form. No paint containing lead or lead products will be used except
in the form of paste or readymade paint. Face masks will be supplied for use by the workers when
paint is applied in the form of spray or a surface having lead paint dry rubbed and scrapped.
8.9.2.5 Risk Caused by Force Majure
All reasonable precaution will be taken to prevent danger of the workers and the public from fire,
flood, drowning, etc. All necessary steps will be taken for prompt first aid treatment of all injuries
likely to be sustained during the course of work.
8.9.2.6 Risk from Explosives
Except as may be provided in the contract or ordered or authorised by the Engineer, the Contractor
will not use explosives. Where the use of explosives is so provided or ordered or authorised, the
Contractor will comply with the requirements of the following Sub-Clauses of this Clause besides
the law of the land as applicable: (also refer Appendix 8.8: Storage, Handling use and emergency.)
• The Contractor will at all times take every possible precaution and will comply with appropriate
laws and regulations relating to the importation, handling, transportation, storage and use of
explosives and will, at all times when engaged in blasting operations, post sufficient warning
flagmen, to the full satisfaction of the Engineer.
• The Contractor will at all times make full liaison with and inform well in advance and obtain
such permission as is required from all Government Authorities, public bodies and private
parties whatsoever concerned or affected or likely to be concerned or affected by blasting
operations.
8.9.2.7 Malarial Risk
The Contractor will, at his own expense, conform to all anti-malarial instructions given to him by the
Engineer, including filling up any borrow pits which may have been dug by him.
Gravid, blood laden mosquitoes can not fly very far, so they generally bite within a kilometre or so
of their breeding place. Thus borrow pits and any other water bodies created during the construction
process will be situated 1 to 2km away from the human settlements. Pits dug up closer than these
will be adequately drained to prevent water logging.
Similarly compensatory measures for filling up part of the water bodies situated adjacent to the
project corridors will be directed towards deepening of the water bodies concerned. This way the
capacity of the water body remains the same, while water surface available for breeding of
mosquitoes is reduced. This will have an additional advantage of decreased evaporation losses, which
will be important in water-scarce corridors such as 02, 23 and 28.
8.9.2.8 First Aid
At every workplace, a readily available first aid unit including an adequate supply of sterilised
dressing material and appliances will be provided as per the Factory Rules. Workplaces remote and
far away from regular hospitals will have indoor heath units with one bed for every 250 workers.
Suitable transport will be provided to facilitate take injured or ill person(s) to the nearest applicable
hospital. At every workplace an ambulance room containing the prescribed equipment and nursing
staff will be provided as prescribed.
8.9.2.9 Potable Water
In every workplace at suitable and easily accessible places a sufficient supply of cold potable water
(as per IS) will be provided and maintained. If the drinking water is obtained from an intermittent
public water supply then, storage tanks will be provided. All water supply storage will be at a distance
of not less than 15m from any latrine, drain or other source of pollution. Where water has to be
drawn from an existing well, which is within such proximity of any latrine, drain or any other source
of pollution, the well will be properly chlorinated before water is drawn from it for drinking water.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 27
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

All such wells will be entirely closed in and be provided with a trap door, which will be dust proof
and waterproof. A reliable pump will be fitted to each covered well. The trap door will be kept
locked and opened only for cleaning or inspection, which will be done at least once a month.
8.9.2.10 Hygiene
The Contractor during the progress of work will provide, erect and maintain necessary (temporary)
living accommodation and ancillary facilities for labour to standards and scales approved by the
resident engineer. Refer Appendix 8.5: Sitting and layout of construction Camp.
There will be provided within the precincts of every workplace, latrines and urinals in an accessible
place, and the accommodation, separately for each for these, as per standards set by the Building and
other Construction Workers (regulation of Employment and Conditions of Service) Act, 1996.
Except in workplaces provided with water-flushed latrines connected with a water borne sewage
system, all latrines will be provided with dry-earth system (receptacles) which will be cleaned at least
four times daily and at least twice during working hours and kept in a strict sanitary condition.
Receptacles will be tarred inside and outside at least once a year. If women are employed, separate
latrines and urinals, screened from those for men and marked in the vernacular will be provided.
There will be adequate supply of water, close to latrines and urinals.
All temporary accommodation must be constructed and maintained in such a fashion that
uncontaminated water is available for drinking, cooking and washing. The sewage system for the
camp must be properly designed, built and operated so that no health hazard occurs and no
pollution to the air, ground or adjacent watercourses takes place. Compliance with the relevant
legislation must be strictly adhered to. Garbage bins must be provided in the camp and regularly
emptied and the garbage disposed off in a hygienic manner. Construction camps are to be sited away
from vulnerable people and adequate health care is to be provided for the work force.
Unless otherwise arranged for by the local sanitary authority, arrangement for proper disposal of
excreta by incineration at the workplace will be made by means of a suitable incinerator approved by
the local medical health or municipal authorities. Alternatively, excreta may be disposed off by
putting a layer of night soils at the bottom of a permanent tank prepared for the purpose and
covering it with 15 cm layer of waste or refuse and then covering it with a layer of earth for a
fortnight (by then it will turn into manure).
On completion of the works, the whole of such temporary structures will be cleared away, all
rubbish burnt, excreta or other disposal pits or trenches filled in and effectively sealed off and the
whole of the site left clean and tidy, at the Contractor’s expense, to the entire satisfaction of the
Engineer.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 8 - 28
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

TABLE OF CONTENTS

CHAPTER - 9: ENVIRONMENTAL MANAGEMENT PLAN ....................................................... 2


9.1 OBJECTIVE OF EMP ..................................................................................................................................... 2
9.2 ORGANIZATIONAL FRAMEWORK ..................................................................................................... 18
9.3 COST ESTIMATES FOR ENVIRONMENTAL MANAGEMENT ................................................... 20
9.4 BASIS OF COSTING ..................................................................................................................................... 23

LIST OF TABLES

Table 9.1: The Environmental Management Plan (EMP)........................................................................................... 3


Table 9.2: Roles and Responsibilities of Officers ....................................................................................................... 18
Table 9.3: Cost Estimates for Environmental Management..................................................................................... 20

LIST OF FIGURES

Fig. 9.1: Organisation Framework of PIU - APRSP .................................................................................................. 20

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 1
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

CHAPTER - 9: ENVIRONMENTAL MANAGEMENT PLAN


Environmental Management Plan (EMP) deals with the implementation procedure of the guidelines
and measures recommended to avoid, minimize and mitigate environmental impacts of the project.
It also includes management of measures suggested for enhancement of the environmental quality
along the highways.

The institutional arrangement made under project will look into the implementation of project as
well as EMP and the various legal settings applicable to the project are briefly stated in chapter 3.
The avoidance, mitigation & enhancement measures for protection of the environment along
highways have been discussed in detail in previous chapter. Although the social environmental
impacts, its mitigation and management is an essential component of the EMP, this chapter excludes
it for the purpose of clarity and procedural requirements. Social environmental elements have been
separately dealt in separate volume namely, Resettlement and Rehabilitation Action Plan (RAP).
9.1 OBJECTIVE OF EMP
The EMP is a plan of action for mitigation / management / avoidance of the negative impacts of
the project and enhancement of the project corridor. For each measure to be taken, its location,
timeframe, implementation and overseeing / supervision responsibilities are listed. These
components of the EMP have been given in Table 9.1 which explains the environmental issues and
the avoidance/ mitigation/ minimization or enhancement measures adopted and/or to be adopted
during different phases of the project. It also provides the references for the suggested measures,
responsible agency for its implementation/ management as well as its timeframe.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 2
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Table 9.1: The Environmental Management Plan (EMP)


Environmental Implementing Responsible Reference/Contrac
Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
DESIGN PHASE
General consideration Standard cross section alternatives were used for the Project During Design PIU – APRDC Design Consultant Chapter-14:
of Cross section road design depending on the traffic requirement and economic Economic Analysis,
Alternatives indicators like EIRR & NPV. FSR
Geometric Design The proposed alignment is selected/adjusted (within During PIU – APRDC Design Consultant Chapter-3:
IRC/MoRTH specifications) alignment design Geometric Design,
- to minimise land disturbance Main Report, Draft
- to avoid culturally & environmentally sensitive areas – cultural D.P.R.
properties, water bodies etc.
Issues from Various issues raised were examined & suitably incorporated During Design PIU - APRDC Design Chapter5:
stakeholder based on merit & other road safety measures. Consultants Stakeholder
Consultations Consultation
Avoidance of Cultural - Cultural properties along the alignment were identified. During PIU – APRDC PIU – EMU, (Refer clause
Properties - Religious Structures were avoided by adjustment of alignment. alignment design Design 8.7.1.2 chapter-8,
- There is no religious structure to be relocated. Consultants of this report.)
Preservation of tree More than 25% of the existing trees have been saved during During APRDC, PIU – EMU, MoRTH clause
alignment design.( Table:8.1) alignment design Department of Design 201.5 (Page42)
No trees to be cut beyond toe line. Forest, A.P. Consultants
Detailed Avenue plantation scheme is prepared, for plantation all Clause
along the project corridor, cost is considered in Budget. 8.6.3,chapter 8
Design Discharge & Bridges have been designed for the 50-year flood frequency. All During Design APRDC Design Vol-3 Hydrology
Drainage design culverts have been designed for 25 years flood frequency. The Consultants report)
fill height has been designed for 50-year flood.
Monitoring at critical The monitoring of Air, land, water and Noise has been carried During Design APRDC Design Table 4.2, 4.7, 4.8
locations out at critical locations along the project corridor. This will serve Consultants and 4.12 of
as a benchmark for monitoring during construction and Chapter 4: Baseline
operational phases. (Appendix 8.15: Monitoring Plan) Environment
Orientation of A comprehensive tanning/orientation schedule has been During Design APRDC Design Appendix:
Implementing Agency prepared at different stages for APRDC. Consultants Training Schedule

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 3
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
External Influence of Location and basic facilities at site are suggested in a way to During Design APRDC Design Appendix 8.5
construction camp cause minimum interference with the local system, for details Consultants
refer Appendix 8.5: Guidelines for siting & layout of
construction camp
Road safety issue due Geometric improvement has been incorporated as per IRC During PIU - APRDC Design Not Applicable
to poor geometrics. codes and MoRTH specifications. alignment design Consultants
Diversion of Traffic Appropriate diversion of traffic schemes to ensure smooth During Design PIU - APRDC Design Clause no 8.9.1.2
traffic flow, minimize accidents during construction, design of Consultants (chapter-8)
diversionary signage
Accident black spot Improved road surface with improved road geometry, Pedestrian During design PIU - APRDC Design Not Applicable
facilities and Bus shelters is planned. Lining and signing is given Stage. Traffic Police Consultants
a high priority for all road junctions. Safety Audits completed on Traffic Police
the final design drawing and corrective measures undertaken.
PRE-CONSTRUCTION PHASE
Permissions/ Tree felling permission has been obtained from DoF, under After centerline APRDC, PIU – EMU, MoRTH clause
Approvals WALTA Act of Andhra Pradesh. marking at site. Department of Design 201.5 (Page42)
Forest, A.P. Consultants
Land Acquisition The land acquisition has been done as per “The Land After proposed APRDC, PIU, Land
Acquisition Act, 1894”. centreline Revenue Acquisition Volume: VIII
marking at site Department Officer (LAO- Resettlement
APRDC) Action Plan, Draft
CSC D.P.R
Property Acquisition - Compensation has been paid to Project Affected Peoples based Post design to APRDC, PIU
on the Resettlement Action Plan. Pre- Revenue R&R Officer
Volume: VIII
construction. Department, (APRDC), CSC
Resettlement
NGOs Action Plan, Draft
recommended in D.P.R
RAP
Relocation of Utilities All community underground and over head utilities are to be Post design to APRDC, Design PIU – R&R
shifted as per utility shifting plan, prior permission should be Pre-construction Consultant officer, CSC Volume: VIII
obtained from regional offices of Electricity, Contractor Resettlement

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 4
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
Telecommunications, OFC, Water works etc. Action Plan, Draft
D.P.R
Loss of drinking Private drinking water source replaced according to RAP and Post design to APRDC PIU, Refer RAP
water source (surface public water sources replaced according to EMP. Pre- surface Water CSC, Contractor
water) construction. Board /PHED Clause 8.4.1,
No surface water body is imacted. (refer Clause 8.4.1.1 of this Chapter 8 of this
report) report
Loss of drinking Private drinking water source replaced according to RAP and Post design to APRDC PIU, Refer RAP
water source (Ground public water sources replaced according to EMP. Pre- Ground Water CSC, Contractor
water) construction. Board /PHED Clause 8.4.1,
Eight ground water sources are to be relocated. (refer Clause Chapter 8 of this
8.4.1.2 of this report) report
Tree Felling A total of 815 trees are to be fell, 372 on LHS and 443 on RHS Post design to APRDC, PIU – EMU, CSC MoRTH clause
(Refer Appendix 4.1) Permission has been obtained from forest Pre- Department of Contractor 201.5 (Page42)
department. construction. Forest, A.P.
In case of any Endangered species found, it should be Clause
transplanted as per Appendix 8.13 8.6.3,chapter 8
Cultural Properties Seven sensitive cultural properties will be relocated. Pre PIU – APRDC CSC, Contractor (Refer clause
Construction PIU – EMU, 8.7.1.2 chapter-8,
41/300 Hanuman Temple of this report.)
167/450 Temple
168/200 Church
168/350 Hanuman Temple Side Tree
168/433 Gangamma Stone
168/450 Mosque With Tree
169/350 Renuka Ellamma Temple

(Refer Clause 8.7.2 of this report)


Loss of existing bus Six existing bus shelters are to be relocated. (Refer Clause 8.8 of During design PIU – APRDC Design Not Applicable
stops and Waiting this report) stage. Consultants Refer :clause 8.8
shed facilities (Chapter 7)
CONSTRUCTION PHASE

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 5
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
Clearances, Approvals List of clearance Required prior to start of construction Activity Construction APRDC, SPCB, The Contractor General
and Permits Type of Clearance Applicability stage (Prior to CPCB, Chief Conditions of
NOC and consents under Air, For establishment of initiation of any Controller of Contract
Water & Environment Act and construction camp. work Explosives,
noise rules from SPCB District Collector
Time period in State department
NOC and consents under Air, For operating constructi- getting the of Mines and
Water & Environment Act and on plant, crusher, permission is 2-3 Geology,
noise rules from SPCB batching plant etc. months. State Ground
Explosive License from Chief For storing fuel oil, Water Board,
Controller of Explosives, lubricants, diesel etc. State Irrigation
Permission for storage of Manufacture storage Department,
hazardous chemical from and Import of Labour
CPCB Hazardous Chemical commissioner
Borrow Area, approval from Borrow area for officer Clause 111.3,
district collector, Concent letter, excavation of earth MoRTH
lease aggrement with the owner
of land.
Quarry Lease Deed and Quarry Quarry operation (for
License from State Department new quarry)
of Mines and Geology
Permission for extraction of Extraction of ground
ground water for use in road water
construction activities from
State Ground Water board
Permission for use of water for Use of surface water for
construction purpose from construction
irrigation department
Labor license from labor Engagement of Labor
commissioner office

Provide a copy of all necessary clearances to the CSC / EMU

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 6
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
9 Adhere to all clearance terms and conditions
9 Obtain written permission from private landholders to
conduct construction activities on their land prior to
commencing works.
Environmental Monitoring is to be carried out regularly as per the frequency and During and after SPCB, PIU - Contractor As a Project
Management locations mentioned in Appendix 8.15. construction APRDC specific action this
And Monitoring (Five Years) will have to be
Facility Equipment incorporated.
for EMP (Meters,
Vehicles and
Buildings)
Asphalting Asphalt mixing plants should be sited over 1000 m (refer During PIU- APRDC, Contractor MORTH
CPCB/SPCB, No Objection Certificate) from any communities. Construction CSC, Specification 111,
Mixing equipment should be well sealed, and be equipped with a SPCB 111.5
dust-removal device.
Operators should wear dust masks, ear protection and hard hats.
AIR
Gaseous Emissions Vehicles and machinery are to be maintained so that emissions Beginning with PIU - APRDC, Contractor MORTH
conform to National Ambient air quality standards. & throughout SPCB Specification 111.1,
All vehicles and machineries should obtain Pollution Under construction 111.5
Control Certificates
Dust Generation 9 Vehicles delivering materials should be covered to reduce Beginning with PIU – APRDC, Contractor MORTH
spills and dust blowing off the load. & throughout EMU – APRDC Specification 111.1,
9 Clearing and grubbing to be done, just before the start of construction CSC 111.5,
next activity on that site. In case of time gap, water should until asphalting 111.8,
be sprinkled regularly till the start of next activity. is completed and 111.9,
9 Water to be sprayed during the construction phase, at mixing side slopes are 111.10
sites, approach roads & temporary roads. covered.
9 In laying sub-base, water spraying is needed to aid
compaction of the material. After the compaction, water
spraying should be carried out at regular intervals to prevent

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 7
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
dust generation.
9 Road surface should be cleaned with air compressor and
vacuum cleaners prior to the construction works. Manual
labour using brooms should be avoided, if used labour to be
provided masks.
9 Embankment slopes to be covered with turfing/stone
pitching immediately after completion
Equipment Selection Construction plant and equipment will meet recognised During PIU – APRDC, Contractor MORTH Spec
maintenance and international standards for emissions and will be maintained and construction EMU – APRDC, 106, IRC: 72-1978;
operation operated in a manner that ensures that relevant air, noise, and CSC IRC: 90-1985,
discharge regulations are met 111.5, 111.9,
111.10, 201.3
LAND
Soil Erosion and Main reason of soil erosion is rains/monsoon, contractor should Upon PIU – APRDC, Contractor MORTH
completion of EMU – APRDC,
Sedimentation control plan the activities so that NO bare/ loose earth surface is left out Specification 306,
before the onset of monsoon, for minimising the soil erosion construction CSC 307, 308
following preventive measures to be taken such as activities at these
sites.
9 Embankment slopes to be covered, soon after completion
During
9 Next layer/activity to be planned, soon after completion of,
construction
clearing and grubbing, laying of embankment layer, sub
grade layer, subbase layer, scarification etc.
9 Top soil from borrow area, Debris disposal sites; borrow
area, construction site to be protected/covered for soil
erosion.
9 Debris due to excavation of foundation, dismantling of
existing cross drainage structure will be removed from the
water course immediately.
9 Diversions for bridges, will be removed from the water
course before the onset of monsoon.
Loss of agricultural All areas of cutting and all areas to be permanently covered will During PIU – APRDC Contractor MORTH
topsoil be stripped to a depth of 150mm and stored in stockpile. construction EMU –APRDC, Specification

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 8
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
Top soil will be safeguard from erosion and will be reused as CSC 301.3.2, 305.3.3
follows.
9 Covering all borrow areas after excavation is over.
9 Dressing of slopes of road embankment
9 Agricultural field, acquired temporarily.
Compaction of Soil Construction vehicles should operate within the Corridor of During PIU – APRDC Contractor MORTH
and Damage to Impact avoiding damage to soil and vegetation. construction EMU –APRDC, Specification 201.2
Vegetation Diversions, access road used will be redeveloped by contractor, CSC
to the satisfaction of the owner/villagers.
Contamination of soil Guidelines of “Hazardous waste (management and handling) During PIU – APRDC Contractor Clause 8.3.5,
rules, 1989 will be enforced. Construction EMU –APRDC, Chapter-8 of this
9 Plant to be setup 500m away from surface water body. CSC report.
9 Oil interceptor will be installed at construction site.
9 Septic tank will be constructed for safe disposal of waste.
Borrow pits NO borrow pit will be opened without the permission of During PIU – APRDC Contractor IRC: 10 1961
supervision consultant. Construction EMU –APRDC, MORTH Spec.
9 Written approval from owner to be submitted to EMU. CSC 111.2, 305.2.2
9 Borrow pits have been identified outside the ROW. Before Appendix 8.2:
opening additional borrow pits, operating pits shall be borrow area
closed according to IRC specification. management

1) Quarrying 1. Quarrying will be carried out at approved and licensed During PIU – APRDC Contractor MORTH
quarries only. Copy of licenses to be submitted to the EMU. Construction EMU –APRDC, Specification 111.3,
2) Material sources 2. As far as possible contractor will use the material from the CSC 302, 305.2.2
Material sources as shown Chapter 4 – Baseline Studies
In case on new quarry the instruction of Appendix 8.1:
Aggregate Quarry Management will be applicable.

WATER
Loss of water bodies 9 NO excavation from the bund of the water bodies. During PIU – APRDC Contractor MORTH
(Surface/Ground) 9 NO debris disposal near, any water body. Construction EMU –APRDC, Specification 111.4,

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 9
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
9 Prior written permission from authorities for use of water CSC 201.2, 301, 304,
for construction activity should be submitted to EMU. 306
9 Construction labours should be restricted from polluting
the source or misusing the source.
9 Shifting of source to be completed prior to disruption of Table 8.2 and 8.3
the actual source. list of water bodies
and their
9 Source to be replaced immediately, in case of accidental mitigations.
loss.
9 Alternate measures to be taken/ensured during disrupted
period.
Alteration of drainage 9 Diversions should be constructed during dry season, with Whenever PIU – APRDC Contractor MORTH
adequate drainage facility, and will be completely removed encountered EMU –APRDC, Specification
before the onset of monsoon. during CSC 201.2,301, 304,
9 Debris generated due to the excavation of foundation or construction. Irrigation Dept. 306, 312
due to the dismantling of existing structure should be
removed from the water course. Clause 8.4.2,
9 Silt fencing has to be provided on the mouth of discharge chapter 8 of this
into natural streams. report.
9 Continuous drain (lined/unlined) is provided, obstruction if
any, to be removed immediately.

Runoff and drainage 9 Throughout continuous drain is provided. During PIU – APRDC Contractor
9 Lined drain is provided at builtup locations for quick Construction EMU –APRDC,
drainage. CSC
9 Increased runoff due to increased impervious surface is
countered through increased pervious surface area through
soak pits.
Water requirement 9 Contractor has to provide list of sources (surface/ground) During PIU – APRDC Contractor
for project for approval from EMU. Construction EMU –APRDC,
9 Prior to use of source contractor should obtain the written CSC

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 10
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
permission from authority, to use the water in construction
activity, and submit a copy to EMU.
9 During construction only permitted quantity (permission
taken) from approved sources should be used in
construction activity.
9 Contractor to ensure optimum use of water; discourage
labour from wastage of water.
Silting/sedimentation 9 Measures suggested under “Soil Erosion and Sedimentation Throughout PIU – APRDC, Contractor MORTH
control” has to be enforced. construction EMU –APRDC, Specification 111.4,
9 Silt fencing should be provided around water bodies. period. CSC 306
9 Construction activities should be stopped near water bodies Irrigation Dept.,
during monsoon. Forest Dept.

Contamination of 9 Measures suggested under “Contamination of soil” has to Throughout PIU – APRDC, Contractor MORTH
water be enforced. construction EMU –APRDC, Specification
9 Construction work close to water bodies should be avoided period. CSC, SPCB, 111.1, 111.4, 111.9,
during monsoon. Irrigation Dept 111.13, 122, 201.2,
9 Labour camps are to be located away from water bodies. 201.4, 301.1.3.10,
304.3.3, 306
9 Car washing/workshops near water bodies are to be
avoided.
NOISE
Noise 9 Noise standard at processing sites, e.g. aggregate crushing Beginning PIU – APRDC Contractor MORTH
plants, batching plant, hot mix plant are to be strictly and EMU –APRDC, Specification 111,
monitored to prevent exceeding of GOI noise standards. throughout CSC , SPCB 111.5
9 Workers in the vicinity of strong noise to wear protectors construction
and their working time should be limited as a safety
measure. Table 8.6 list of
9 In construction sites within 150 m of sensitive receptors sensitive receptor
construction to be stopped from 22:00 to 06:00. and their
9 Machinery and vehicles should be maintained to keep their mitigations.
noise to a minimum.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 11
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
9 Noise barrier to be constructed at noise sensitive locations.
(refer Clause 8.5.1 of this report)
FLORA & FAUNA
Loss of trees and 9 Avenue plantation has to be taken up soon after After PIU – APRDC Contractor EMU MORTH
Avenue Planting completion of civil works. (Refer clause 8.6.3 of this report) completion of EMU –APRDC, Specification, 111,
9 Cultural property has to be enhanced with plantation. (refer construction CSC, 111.5, 201.5, 306,
clause 8.6.3 of this report) activities Forest Dept. 308
9 Contractor has to make sure that no trees/branches to be
fell by labourer for fuel, warmth during winter. Enough
provision of fuel to be ensured.
Vegetation clearance 9 Clearing and grubbing should be avoided beyond that During cleaning PIU – APRDC Contractor MORTH
which is directly required for construction activities. operations EMU –APRDC, Specification 201.2
9 Next activity to be planned/started immediately, to avoid During CSC,
dust generation and soil erosion during monsoon. construction Forest Dept.
9 Turfing / re-vegetation to be started soon after completion
of embankment.
Fauna 9 Construction workers must protect natural resources & During PIU – APRDC Contractor MORTH
wild animals. construction EMU –APRDC, Specification 111.1,
9 Hunting will be prohibited. CSC, 111.6
9 Nesting grounds & migratory paths will be protected. Forest Dept
SOCIO-ECONOMIC ENVIRONMENT
General Issues During PIU – APRDC Contractor MORTH
Fear of Public participation sessions were/will be conducted in Construction EMU –APRDC, Specification
uncertainties different stages of project construction. CSC 111, 111.5, 111.6,
regarding future 112, 201.2, 201.3 &
Public Health and Debris, so generated will be disposed to the satisfaction 201, 302, 306
Safety of Engineer.
Monitoring of air, water, noise and land during
construction and operation phase.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 12
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
Labour Camps Contractors should recruit the local people as laborers at
least for unskilled and semi-skilled jobs.
Hygiene and basic facilities should be ensured at labour
camp to prevent the spread of disease.
Allied activities Detailed traffic control plans shall be prepared and
submitted to the engineer for approval 5 days prior to
commencement of work on any section of road.
Accidents and The contractor should provide, erect and maintain
Safety barricades, including signs marking flags lights and
flagmen as required by the Engineer.

Sensitive Community 9 A comprehensive mitigation/enhancement plan is prepared During PIU – APRDC Contractor Plate # CP01
Structures for each of the existing community properties along the construction EMU –APRDC, through Plate #
project corridor.(refer clause 8.7.2 of this report) CSC CP11
9 Precautions should be taken during construction, for
accidental loss/damage of any communal property.
9 Any loss during construction will be the solo responsibility
of contractor and the damage will be repaired immediately
up to the satisfaction of people, at contractor’s own cost.
9 Through access/identification should be maintained during
construction.
Road side amenities 9 Bus shelter will be proposed at all builtup locations, in case During PIU – APRDC Contractor
already existing; the same will be repaired and rehabilitated. construction EMU –APRDC,
9 Pedestrian crossing is provided at major pedestrian CSC
crossings, providing zebra crossing, sign posts and speed
breakers.
ROAD SAFETY
Accident with COMPLIANCE with “Rules” as defined in Environmental During APRDC, State Contractor, local EMP
hazardous materials (Protection) Act, 1986, including: Construction Police & Fire bodies
9 For delivery of hazardous substances, three certificates Station, SPCB,
issued by transportation department are required permit EMU

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 13
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
license, driving license, and guarding license.
9 Vehicles delivering hazardous substances will be printed
with standard signs.
9 Public security, transportation and fire fighting departments
will designate a special route for these vehicles.
9 These vehicles can only be parked at designated parking
lots.
9 In case of spill of hazardous materials, relevant departments
will be informed at once & dealt with it in accordance with
spill contingency plan.
OPERATIONAL PHASE
AIR
Dust Generation 9 Dust generation due to vehicle wheel will be reduced due to After Forest dept. Maintenance unit- EMP
increased/widened paved surface. completion of EMU APRDC
9 Avenue plantation to be maintained, casualties to be construction Forest Dept
replaced. activity
9 Avenue plantation includes species having dust absorption
characteristic.
9 Community properties and realignment locations has been
proposed for peripheral plantation and landscaping.
9 Maintenance of roads to be ensured.
Air Pollution 9 With the reduction in journey time, idle engine running time After EMU, SPCB Maintenance unit- Environmental
air pollution will reduce. completion of Forest Dept, APRDC Management Plan
9 Avenues plantation is proposed throughout the corridor, construction State Transport Forest Dept (EMP)
casualties to be replaced. activity Dept., Police
9 Avenue plantation includes species having air purifying
characteristic.
9 Enforce Pollution Under Control (PUC) Programs. The
public will be informed about the regulations on air
pollution of vehicles.
9 Air pollution monitoring program has been devised for

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 14
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
checking pollution level and suggesting remedial measures.
LAND
Temporary land 9 Borrow area redevelopment plan to be completed/ After EMU, SPCB, Maintenance unit- EMP
acquisition enforced. completion of APRDC
9 All temporary acquired land for construction of diversion, construction
transportation of material etc should be redeveloped to the
satisfaction of owner.
9 Affected productive area to be poured with top soil.
Soil erosion 9 Embankment slopes to be re-vegetated, casualties to be After EMU, SPCB, Maintenance unit- EMP
replaced. completion of APRDC
9 Residual spoils to be disposed properly. construction
Soil Contamination 9 Accidental spills are potentially disastrous, but its probability After EMU, SPCB, Maintenance unit- EMP
is quite low as one of the objectives of this project is to completion of State Police, State APRDC
enhance road safety. construction Transport Dept.
9 The public should be informed about the regulations on land
pollution.
9 Monitoring of Land pollution to be done regularly as per
frequency and location mentioned in Appendix 8.15 and
suggesting remedial measures.
WATER
Silting/sedimentation 9 Measures suggested under “soil erosion” to be enforced. After EMU, SPCB Maintenance unit- EMP
9 De-silting of existing water bodies to be takenup. completion of APRDC
9 Silt fencing to be provided. construction
Contamination of 9 Accidental spills are potentially disastrous, but its probability After EMU, SPCB, Maintenance unit- EMP
water is quite low as one of the objective of this project is to completion of State Police, State APRDC
enhance road safety. construction Transport Dept.
9 Discouraging local people from establishing workshops and respective
car wash near public drinking water source. Municipal Agency
9 The public to be informed about the regulations on water
pollution.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 15
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
9 Monitoring of water pollution to be done regularly as per
frequency and location mentioned in Appendix 8.15 and
suggesting remedial measures.
Maintenance of Storm 9 The urban drainage systems should be maintained to Especially at the EMU, respective Local municipal EMP
Water Drainage accommodate storm water flow. start & end of Municipal Agency corporation
System 9 Cleaning/removing of spoils should be ensured rains
before/during the monsoon rains.
NOISE
Noise 9 HORN PROHIBITED sign post will be enforced. After SPCB, State Maintenance unit- EMP
9 Maintenance of noise barriers. completion of Police, Traffic APRDC
9 Discouraging local people from establishing sensitive construction Police, State Forest Dept
receptor near the road. Transport Dept.
9 The public to be informed about the regulations on noise
pollution.
9 Monitoring of noise pollution to be done regularly as per
frequency and location mentioned in Appendix 8.15 and
suggesting remedial measures.
FLORA & FAUNA
Loss of trees and 9 The avenue plantation should be completed, maintained and After
Avenue Planting casualties to be replaced. completion of
9 Discouraging local peoples from cutting tree/branches for construction
fuel, cattle food etc.
9 Educating people about the usefulness of trees.
SOCIO-ECONOMIC ENVIRONMENT
General issues 9 Public consultation to be organized after completion of Operation phase APRDC, EMU Maintenance unit
construction to access the people opinion/grievances from
the project intervention.
9 Remedial measures to mitigate the impact due to project
intervention to be incorporated in the operation phase.
Sensitive Communal 9 The mitigation/enhancement measures to be completed, and

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 16
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Environmental Implementing Responsible Reference/Contrac


Mitigation/Enhancement measures Time frame
Impact & Issues Organisation Organisation tual Clause
Structures trees to be maintained and casualties to be replaced.
ROAD SAFETY
Protection of high 9 Stabilization of altered (especially high emb.) embankments. Immediately APRDC EMU Design standard
road embankments 9 Although stone pitching is provided, vigilance to be after requirement
maintained. construction

Safety and noise 9 New buildings are prohibited within 50 m of the edge of Throughout and Local Bodies Local Bodies IRC 35-1971
disturbance carriageway. after project IRC 79-1981
9 No new schools and hospitals are allowed within 200 m of development IRC 93-1995
carriageway. Wherever required appropriate noise barrier period
should be constructed.
Accident black spot 9 Road surface to be maintained, pot holes to be filled During PIU – EMU, PIU EMP
immediately. Operational Local Bodies
9 Regular maintenance of sign post, painting/removal of bills. stage.
9 Road marking to be maintained.
9 People to be educated about the safety in following traffic
rules.
9 Speed limit to be enforced at sensitive locations.
9 Lighting of major junctions near settlements.
9 Mitigative /preventive measures for accident black spots,
like traffic calming devises.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 17
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

9.2 ORGANIZATIONAL FRAMEWORK


The proposed project will be implemented by APRDC through its Environmental Management Unit
(EMU). The EMU comprises of officers from Department of Forest, GoAP, and other
environmental Engineers. The EMU will be coordinating with the field level implementing agencies
such as Engineer (Supervision Consultant), Contractor and field level APSHP officials. Role and
responsibilities of important officials is mentioned below.
Table 9.2: Roles and Responsibilities of Officers
Officer Responsibility
Chief Engineer & • Overview of the project implementation
Managing
Director • Ensure timely budget for the EMP.
• Coordination with different state level committee, to obtain regulatory
clearances.
• Participate in state level meetings
• Monthly review of the progress.
Project Director • Overall responsible for EMP implementation
APRSP
• Reporting to various stakeholders (World Bank, Regulatory bodies) on status
of EMP implementation
• Coordination with PIU Staff (EMU & APSHP).
• Responsible for obtaining regulatory Clearances
• Review of the progress made by contractors
• Ensure that BOQ items mentioned in EMP are executed as per Contract
provisions.
Environmental • Assisting Project Director in overall implementation of EMP
Officer (PIU)
• Review of periodic reports on EMP implementation and advising Project
Director in taking corrective measure.
• Conducting periodic field inspection of EMP implementation
• Assisting Project Director to reporting various stakeholders (World Bank,
Regulatory bodies) on status of EMP implementation
• Preparing environmental training program and conducting the same for field
officers and engineers of contractor.
Engineer • Act as an “Engineer” for supervising EMP implementation
(Supervision
Consultant) • Responsible for maintaining quality of EMP envisioned in detail Project
Report
• Maintaining progress reports on EMP implementation
• Periodic reporting to PIU-APRSP about the status of EMP implementation
• Work in close coordination with Executive Engineer (package unit) and
contractor.
Executive • Conducting need-based site inspection and preparing compliance reports and
Engineer forwarding the same to the Environmental Management Unit (EMU)
• Programming necessary training program on environmental issues.
Deputy Executive • Working as site-representative of Executive Engineer (APSHP)
Engineer
• Conducting regular site inspection to all onsite and offsite works

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 18
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Officer Responsibility
• Maintaining records of all necessary statutory compliance, to be obtained
from contractor.
• Maintaining records of EMP implementation including photographic records
• Attending environmental and social training programs
• Preparing periodic reports on EMP implementation and forwarding to EE
Environment & • As detailed below
Safety Manager
of Contractor

For ensuring that EMP is implemented as per provision in the document, Contractor shall
nominate a qualified and experienced Manager from the commencement to completion of the
project.
The responsibilities of Environment & Safety Manager of Contractor will include the
following:
¾ Directly reporting to the Project Manager of the Contractor;
¾ Discussing various environmental/social issues and environmental/social mitigation,
enhancement and monitoring actions with all concerned directly or indirectly;
¾ Prepare Contractor’s Checklist, traffic management plan and safety plan as part of their Work
Program;
¾ Ensure Contractor’s compliance with the ESMF stipulations and conditions of statutory bodies;
¾ Assisting his project manager to ensure social and environmentally sound and safe construction
practices;
¾ Conducting periodic environmental and safety training for contractor’s engineers, supervisors
and workers along with sensitization on social issues that may be arising during the construction
stage of the project;
¾ Preparing a registers for material sources, labour, pollution monitoring results (if required by
APSPCB), public complaint/grievance redressal and as may be directed by the Engineer;
¾ Assisting the R&B on various environmental monitoring and control activities including
pollution monitoring; and
¾ Preparing and submitting monthly/bio-monthly reports to R&B on status of implementation
safeguard measures.
¾ Will be responsible for getting and maintaining the approvals or clearance for varioud
departments and Environmental officer as per formats attached in Appendix: 9.2

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 19
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

ORGANISATIONAL FRAMEWORK OF PIU - APRSP


(Supervision and Monitoring of EMP)

Chief Engineer & Managing Director APRDC

Project Director - APRSP

Environment Management Unit (EMU-APRDC)


Environmental Officer APRDC

ORGANISATION STRUCTURE AT FIELD LEVEL


(R&B), APRDC Environmental
(Supervision and Monitoring of EMP) Engineer,
(CSC)
Executive Engineer of Package Unit. APSHP

Dy. Executive Engineer of Package Unit, APSHP

Environment & Safety Manager of Package Unit,


Contractor

Fig. 9.1: Organisation Framework of PIU - APRSP

9.3 COST ESTIMATES FOR ENVIRONMENTAL MANAGEMENT


Mitigation measures proposed in the EMP will be implemented by the Contractor. The works to be
undertaken by the Contractor have been quantified and the quantities included in the respective
BOQ items such as earth works, slope protection, noise barriers, road safety features, and shrub
plantation.
Provisional quantities have also been included for additional measures that may be identified during
construction and for silt fencing which will depend on the Contractors work methods and site
locations. Items and quantities have also been included for enhancement measures.
More general environmental management measures to be followed by the contractor have been
included in the specifications and this EMP. These cannot be quantified and are to be included in the
contract rates.
The budgetary provisions for the implementation of the environmental management plan of the
Project are presented in Table 9.3.
Table 9.3: Cost Estimates for Environmental Management
Cost (in
S. No. Item Unit Rate (in INR) Quantity INR) Remarks
A PRE CONSTRUCTION
PHASE
16,300 Trees to be
1 Tree Felling Permission Number 20 815 cut
Covered under
regulatory
2 Utility Shifting clearance,

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 20
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Cost (in
S. No. Item Unit Rate (in INR) Quantity INR) Remarks
Engineering
cost.
Total Cost
B CONSTRUCTION
PHASE
1
1.1 Oil Interceptors Number 5,000 2 10,000 Clause 8.3.5
1.2 Silt Fencing Length, m 850 700 595,000 Clause 8.4.5
1.3 Soak pits for Hand Number 5000 15 75,000 Clause 8.4.1
Pump/Wells
1.4 Relocation of Hand Pumps Numbers 75,000 9 675,000
1.5 Relocation of Cultural Numbers 200,000 4 800,000
Properties
1.6 Desilting/Deepning of Number 100,000 1 100,000 Along Bypass
Ponds
2
2.1

2.1.1 Plantation & maintenance Number 1000 6,000 6,000,000


of Saplings for 3 years
Tree Guards
2.1.2 Brush Wood Fence Numbers 180 3600 648,000 As separate
Contract
2.1.3 Half Brick circular Tree Numbers 974 1800 1,753,200
Guard
2.1.4 Iron Tree Guard Numbers 1497 600 898,200
3 Landscaping
3.1 At Junction location Numbers 50 500 25,000 At 1.5m for
50m
4

4.1 Air Quality


4.1.1 Monitoring of Air Quality Per 5,000 12 60,000 Three season
near Hot mix plants Samples in a year for 2
years
4.1.2 Monitoring of Air Quality Per 5,000 24 120,000 Three season
at Critical Locations Samples in a year for 2
years
4.2 Noise Levels
4.2.1 Monitoring of Noise Level Per 4,000 6 24,000 Three season
at Equipment Yards Samples in a year for 2
years
4.2.2 Monitoring of Noise Levels Per 4,000 24 96,000 Three season
at Critical Locations Samples in a year for 2
years
4.3 Water Quality
4.3.1 Monitoring of Water Per 5,000 40 200,000 Four season
Quality Samples in a year for 2
years
4.4 Soil Quality
4.4.1 Monitoring of Soil Quality Per 6,000 32 192,000 Four season
Samples in a year for 2
years
4.4.2 Additional Soil Monitoring Per 6,000 6 36,000
during Spills Samples

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 21
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Cost (in
S. No. Item Unit Rate (in INR) Quantity INR) Remarks
5 Orientation of Per - - - Deemed to be
Implementing agency Session included in
staff Consultancy
fee.
6 Mitigation/Enhancement Measures
6.1
6.1.1 Cultural Properties Numbers 3,000 18 54,000
Resources as per list
6.3 Surface Water Numbers 3,000 1 3,000
Bodies/incidental
6.4 For Incidental spaces Numbers 10,000 10 100,000
C GOOD ENGINEERING PRACTICES

1 Dust Suppression Covered under Engineering Costs


2 Erosion Control Measures
(Turfing / Pitching /
Seeding & Mulching)
3 Provision of Cross drainage
& side drainage structures
4 General Borrow area
management and
maintenance of haul roads
related to borrow areas
5 Air/noise pollution control
measures in construction
equipments
6 Management and disposal
of scarified waste
bituminous material
7 Provision of Informatory
Signs
8 Busshelters
9 Construction of Speed
Humps
10 Cattle Crossings
11 Management of quarries Deemed to be included in Contractor’s quoted rates
12 Redevelopment of Borrow
Areas
13 Construction Camp Will form part of the contractor’s cost
Mangement Costs
14 Safety measures for workers
D ITEMS COVERED UNDER THE RAP BUDGET

1 Relocation of private Covered under RAP Budget


Properties
2 Relocation of private Water
points (wells, tanks, water
taps and hand pumps)
3 Relocation of graveyards,
statues, motor sheds
4 Relocation of Other
Community Assets (private)

E OPERATION PHASE

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 22
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Cost (in
S. No. Item Unit Rate (in INR) Quantity INR) Remarks
1 Monitoring of
Environmental Attributes
during Operation Phase
1.1 Monitoring of Air Quality Per 24 Two season in
at Critical Locations Sample a year for 3
years
1.2 Monitoring of Noise Levels Per 36 Three season
at Critical Locations Sample in a year for 3
years
1.3 Monitoring of Water Per 60 Four season
Quality Sample in a year for 3
years
1.4 Monitoring of Soil Quality Per 48 Four season
Sample in a year for 3
years
1.5 Additional Soil Monitoring Per 6 Throughout
during Spills Sample operation
phase.
1.6 Noise mitigation measures Sq. m 2000
in form of noise barrier at
sensitive receptors*
2 Information - - - - Covered
Dissemination under RAP
Sub Total INR 12,480,700 Say
GRAND TOTAL US$ @ US$ 312,100
INR 40.00/$
* The provision made shall be utilised in construction phase also if necessary

9.4 BASIS OF COSTING


(A) COSTS DURING PRE-CONSTRUCTION STAGE
ITEM 1.0 TREE FELLING PERMISSION
Tree felling permission will be obtained from Forest Department of Andhra Pradesh under
WALTA ACT 2002, a fee of Rs 20 per felling tree is charged from the agency, in this case
APRDC, and for tree felling cost is considered in Engineering cost.
ITEM 2.0 UTILITY SHIFTING
The cost of existing utility shifting is taken separately in engineering costing, under the Non
civil cost Head.
(B) COSTS DURING CONSTRUCTION PHASE
ITEM 1.0 MITIGATION MEASURES OTHER THAN GOOD
ENGINEERING PRACTICES
This section includes the costs for the mitigation measures during the construction other
than those included in the Engineering Budget. It covers the following items:
Item 1.1 Oil Interceptors
The unit cost of Single Chamber Gravity Separation Type Oil & Grease Interceptors
(Influent handling capacity 20 L/hr) as per prevalent market rates is Rs 5,000.
Item 1.2 Silt Fencing
The per unit length cost of silt fencing as per market rate is Rs 850.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 23
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Item 1.3 Soak pits for hand pumps and wells.


The unit cost of soak pit of 1.5m diameter and 1.0m deep made of brick
masonry/concrete rings, filled with brick bats and pables, as per market rate of Rs
5,000.
Item 1.4 Relocation of ground water bodies
The unit cost of relocation of ground water sources has bee considered as per market rate of
Rs75,000/source.
Item 1.5 Relocation of Cultural Properties
The unit cost of relocation of cultural properties- Religious structures has bee considered as
per existing structure evaluation and cost of land at Rs200,000/source.
Item 1.6 Pond deepening/desilting
A lump sum cost of Rs.100,000/- has been provided for deepening/desilting of pond. The
unit rates for earthwork excavation from ponds have been obtained from the Schedule of
Rates as Rs.62/- per cum.

ITEM 2.0 TREE PLANTATION AND PROTECTION


Item 2.1 Avenue plantation including Compensatory afforestation
The afforestation wil be done by APRDC through Forest department. The MoU will be
signed between APRDC and Forest Department.

ITEM 3.0 LANDSCAPING AND HEDGING


It includes the costs involved in landscaping apart from tree plantation. It is proposed to
plant dwarf shrubs along the T-Junctions, realignment location and hedging along Right of
Way.
Item 3.1 Along junction
It has been estimated that the number of shrubs required, Considering 100no.s of shrubs at
each major junction, planting at 1.5 m c/c. The unit cost of shrubs is Rs 50.
ITEM 4.0 MONITORING OF ENVIRONMENTAL ATTRIBUTES
DURING CONSTRUCTION ACTIVITY
Item 4.1 Air Quality
The cost for continuous 24 hour monitoring for SPM, RPM, SO2, NOx, CO & Pb as per
prevalent market rates is Rs 5,000/sample. (For locations and frequency refer Appendix
8.15 Monitoring plan)
Item 4.2 Noise Level
The cost for noise level monitoring on dB(A) scale (readings to be taken at 15 second
interval for 15 minutes every hour for a total period of 24 hours) as per prevalent market
rates is Rs 4,000/sample. (For locations and frequency refer Appendix 8.15 Monitoring
plan)
Item 4.3 Water Quality
Water quality will be monitored for the following parameters:
• pH, BOD, COD, TDS, Pb, Oil & Grease and Detergents for surface water
• pH, TDS, Total Hardness, Sulphate, Chloride, Fe, Pb and Coliform count for ground
water

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 24
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

Cost for one time monitoring of water quality as per prevalent market rates is Rs
5,000/sample. (For locations and frequency refer Appendix 8.15 Monitoring plan)
Item 4.4 Soil Quality
Cost for one time monitoring of soil quality for Pb, Sodium Absorption Ratio & Oil &
Grease as per prevalent market rates is Rs 6,000/sample. (For locations and frequency refer
Appendix 8.15 Monitoring plan) Provisions have also been included in the budget to
monitor the soil quality in event of any major accident/spillage during bulk transport of
hazardous material. Costs are incorporated for monitoring at such locations.
ITEM 5.0 ORIENTATION OF IMPLEMENTING AGENCY STAFF
This item includes the costs to be incurred for training sessions involving the PIU staff. The
training programme will be attended by EMU staff –APRDC, Engineer – Supervision
Consultant and Contractor representative. The cost is included in the consulting fee of
Engineers.
ITEM 6.0 ENHANCEMENT MEASURES
The costs have been calculated for each cultural property within the corridor of impact
generic enhancement has been proposed. For generic enhancements of cultural properties,
water bodies and incidental spaces adequate provisions have been made in the budget.

(E) COSTS DURING OPERATION STAGE


ITEM 1.0 MONITORING OF ENVIRONMENTAL ATTRIBUTES
DURING OPERATION PHASE
The rates for monitoring of quality are same as those mentioned for the construction stage.
Provisions have been made in the budget to monitor each year upto 3 years from
completion of construction.
ITEM 2.0 INFORMATION DISSEMINATION
This item includes the costs to be incurred for information dissemination during the
implementation stage. Cost of information dissemination has been included in RAP
towards the cost of NGO.

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan 9- 25
Andhra Pradesh Road Sector Project
The Louis Berger Group, Inc. Feasibility Study, Design and Detailed Engineering

LIST OF APPENDICES

APPENDIX 4.1: TREE ENUMERATION : PROJECT ROAD

APPENDIX 8.1: GUIDELINES FOR AGGREGATE QUARRY MANAGEMENT


APPENDIX 8.2: GUIDELINE FOR BORROW AREAS MANAGEMENT
APPENDIX 8.3: GUIDELINE FOR DEBRIS DISPOSAL SITES AND
MANAGEMENT
APPENDIX 8.4: GUIDELINES FOR SITE CLEARANCE AND TREE FELLING
APPENDIX 8.5: GUIDELINE FOR SITING & LAYOUT OF CONSTRUCTION
CAMP
APPENDIX 8.6: WORKERS SAFETY DURING CONSTRUCTION ACTIVITIES
APPENDIX 8.7: GUIDELINE FOR ENVIRONMENT FRIENDLY
CONSTRUCTION METHODOLOGY
APPENDIX 8.8: STORAGE, HANDLING, USE AND EMERGENCY RESPONSE
FOR HAZARDOUS CHEMICALS
APPENDIX 8.9: SOIL EROSION AND SEDIMENTATION CONTROL
APPENDIX 8.10: ARRANGEMENT WITH FOREST DEPARTMENT
APPENDIX 8.11: GUIDELINES FOR SELECTION OF TREE SPECIES
APPENDIX 8.12: GUIDELINE FOR AVENUE PLANTATION
APPENDIX 8.13: GUIDELINES FOR TRANSPLANTATION OF FULL-GROWN
TREES
APPENDIX 8.14: MITIGATION ENHANCEMENT OF CULTURAL PROPERTIES
APPENDIX 8.15: GUIDELINES FOR MONITORING PROGRAM
APPENDIX 8.16: TRAINING PROGRAMME ON ENVIRONMENTAL ASPECTS

APPENDIX 9.1: MODIFICATIONS TO MORTH CLAUSE 111, MEASURES FOR


SAFEGUARDING ENVIRONMENT

Detailed Project Report, Environmental Impact Assessment & Environmental Management Plan A-1
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
1 156.010 6.7 Thumma 140 10 T4 To be Fell
2 156.025 8.01 Neem 45 10 T1 To be Fell
3 156.030 8.15 Neem 75 11 T2 To be Fell
4 156.030 7.8 Kanuga 50 12 T1 To be Fell
1 156.060 7.2 Bagi 155 15 T4 To be fell 5 156.060 6.3 Giriship 135 11 T4 To be Fell
6 156.080 7.55 Thumma 140 13 T4 To be Fell
2 156.090 7.7 Neem 125 35 T4 To be fell
7 156.100 7.63 Giriship 220 14 T4 To be Fell
8 156.100 7.65 Giriship 223 15 T4 To be Fell
3 156.115 7.9 Neem 130 30 T4 To be fell
9 156.120 7.35 Aggipulla 95 16 T3 To be Fell
4 156.127 9.1 Giriship 150 10 T4 To be fell
10 156.150 11.7 Neem 140 13 T4
5 156.152 12 Neem 160 25 T4
11 156.160 7.05 Giriship 170 14 T4 To be Fell
12 156.180 7.05 Neem 160 12 T4 To be Fell
6 156.185 9.9 Neem 100 30 T3 To be fell
13 156.202 9.35 Raavi 85 11 T2 To be Fell
14 156.202 7.35 Raavi 190 12 T4 To be Fell
7 156.204 9.1 Neem 50 10 T1 To be fell
8 156.206 10.3 Neem 39 8 T1 To be fell
15 156.212 7 Neem 140 13 T4 To be Fell
16 156.225 7.1 Neem 125 11 T4 To be Fell
9 156.236 10 Neem 35 6 T1 To be fell
17 156.240 8.3 Neem 140 12 T4 To be Fell
10 156.248 8.2 Kanuga 73 10 T2 To be fell
11 156.255 8.4 Bagi 135 30 T4 To be fell
18 156.260 13.15 Neem 150 11 T4
19 156.270 9.75 Neem 62 10 T2 To be Fell
12 156.272 10.5 Neem 63 20 T2 To be fell
20 156.275 6.1 Giriship 150 13 T4 To be Fell
21 156.285 8.05 Giriship 140 12 T4 To be Fell
13 156.288 7.8 Thurai 155 15 T4 To be fell
22 156.295 10 Konda Patti 50 9 T1
14 156.300 10.7 Aggipulla 40 10 T1 To be fell
15 156.305 12 Neem 55 8 T1 23 156.305 10.15 Konda Patti 62 8 T2
24 156.315 10.12 Konda Patti 61 9 T2
25 156.335 7.3 Neem 100 10 T3 To be Fell
16 156.340 8.2 Bagi 157 25 T4 To be fell 26 156.340 7.25 Neem 80 9 T2 To be Fell
27 156.350 7.35 Giriship 150 11 T4 To be Fell
17 156.355 14.5 Neem 185 25 T4
28 156.360 7.85 Raavi 210 12 T4 To be Fell
29 156.380 13.2 Neem 144 12 T4
30 156.390 13.15 Giriship 110 10 T3
18 156.395 5.9 Bagi 276 40 T4 To be fell 31 156.395 13.1 Tamarind 90 11 T2
32 156.400 7.15 Neem 120 12 T3 To be Fell
33 156.420 6.7 Giriship 280 13 T4 To be Fell
19 156.430 8.4 Thurai 53 8 T1 To be fell
20 156.440 6.2 Bagi 150 20 T4 To be fell
21 156.443 12 Teak 50 12 T1
22 156.447 6.4 Bagi 133 8 T4 To be fell
23 156.479 6.6 Neem 96 12 T3 To be fell
24 156.479 7 Raavi 73 12 T2 To be fell
25 156.590 6.2 Bagi 256 40 T4 To be fell
26 156.608 6.2 Bagi 130 35 T4 To be fell
34 156.620 6.3 Baggi 180 11 T4 To be Fell
27 156.698 6.5 Bagi 160 30 T4 To be fell
28 156.769 7.1 Thumma 110 15 T3 To be fell
29 156.769 11.4 Thumma 93 16 T3
30 156.804 6.5 180 15 T4 To be fell
35 156.820 6.2 Sunkesula 170 13 T4 To be Fell
31 156.840 11 Bagi 85 30 T2
32 156.850 6.5 Bagi 210 50 T4 To be fell 36 156.850 6.35 Giriship 200 14 T4 To be Fell
33 156.854 8.1 Bagi 60 10 T1 To be fell
34 156.857 8.3 153 20 T4
35 156.858 6.8 Bagi 215 45 T4 To be fell
36 156.866 6.5 Bagi 160 45 T4 To be fell
37 156.869 10.7 85 25 T2 To be fell
37 156.880 6.25 Giriship 315 12 T4 To be Fell
38 156.890 6.3 Giriship 249 11 T4 To be Fell
39 156.900 6.1 Giriship 165 12 T4 To be Fell
38 156.935 6.5 Bagi 150 40 T4 To be fell
40 156.980 6.4 Giriship 100 11 T3 To be Fell
41 157.010 7.05 Giriship 180 12 T4 To be Fell
39 157.015 7 Thurai 135 15 T4 To be fell
42 157.040 7.3 Giriship 290 13 T4 To be Fell
40 157.045 6.8 Bagi 295 40 T4 To be fell
43 157.060 7.05 Sunkesula 75 12 T2 To be Fell
44 157.170 7.3 Banyan 295 13 T4 To be Fell
41 157.075 6.5 Bagi 340 40 T4 To be fell
42 157.143 5.5 Kanuga 125 12 T4 To be fell
45 157.180 7.35 Neem 120 12 T3 To be Fell
43 157.185 10.7 Bagi 126 20 T4 To be fell
46 157.190 7.05 Giriship 250 13 T4 To be Fell
47 157.195 6.95 Giriship 270 12 T4 To be Fell
44 157.197 6.1 Bagi 162 35 T4 To be fell
45 157.206 5.5 Bagi 210 25 T4 To be fell
48 157.210 7 Giriship 260 13 T4 To be Fell
46 157.218 6.1 Bagi 255 40 T4 To be fell
49 157.220 7.05 Giriship 245 12 T4 To be Fell
47 157.224 10.2 Chigara 120 30 T3 To be fell
48 157.230 6.2 Bagi 146 45 T4 To be fell
49 157.239 6.3 Neem 120 30 T3 To be fell
50 157.250 7.15 Giriship 300 13 T4 To be Fell
50 157.251 9.5 Giriship 43 9 T1 To be fell
51 157.252 9.6 63 12 T2 To be fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
52 157.254 5.3 Bagi 255 45 T4 To be fell
53 157.256 9.8 Giriship 73 15 T2 To be fell
51 157.260 10.3 Kanuga 140 12 T4
54 157.261 10.1 Giriship 54 10 T1 To be fell
55 157.267 4.9 Bagi 283 50 T4 To be fell
56 157.269 9.8 Giriship 35 3 T1 To be fell
52 157.270 7.05 Sunkesula 250 11 T4 To be Fell
57 157.271 9.8 Giriship 52 6 T1 To be fell
58 157.276 9.9 Giriship 63 5 T2 To be fell
53 157.280 11.05 Sunkesula 60 12 T1
59 157.286 5.4 Kanuga 125 25 T4 To be fell
60 157.286 10.2 Kanuga 155 12 T4 To be fell
54 157.290 8.05 Sunkesula 120 11 T3 To be Fell
61 157.294 10.4 Neem 170 25 T4 To be fell
55 157.300 9.05 Sunkesula 92 12 T3 To be Fell
62 157.306 9.5 Giriship 55 18 T1 To be fell
63 157.310 9.5 Kanuga 50 10 T1 To be fell 56 157.310 9.15 Sunkesula 36 9 T1 To be Fell
64 157.311 9.4 Giriship 48 15 T1 To be fell
57 157.315 10.75 Banka 41 6 T1
65 157.317 9.6 Giriship 60 20 T1 To be fell
66 157.319 9.6 Giriship 75 25 T2 To be fell
67 157.320 5.7 Neem 193 25 T4 To be fell
68 157.330 9.2 Giriship 65 20 T2 To be fell
69 157.333 6.3 Bagi 165 20 T4 To be fell
70 157.340 8.3 Bagi 155 35 T4 To be fell
58 157.345 11.55 Neem 208 12 T4
59 157.360 7 Neem 120 11 T3 To be Fell
60 157.370 7.05 Giriship 240 12 T4 To be Fell
71 157.396 7.3 Bagi 182 25 T4 To be fell
72 157.408 6.9 Bagi 141 30 T4 To be fell
73 157.430 10.5 Neem 120 25 T3 To be fell
74 157.435 7.2 Bagi 163 30 T4 To be fell
75 157.440 7.4 Thumma 120 22 T3 To be fell
76 157.455 8.3 Bagi 176 30 T4 To be fell
77 157.490 7.5 Bagi 187 25 T4 To be fell
78 157.498 6.4 Aggipulla 108 20 T3 To be fell
79 157.509 6.6 Bagi 167 30 T4 To be fell
80 157.519 6.8 Thurai 176 18 T4 To be fell
81 157.562 6.3 Bagi 200 40 T4 To be fell
82 157.572 12.7 Bagi 95 12 T3 To be fell
61 157.580 6.5 Aggipulla 140 10 T4 To be Fell
62 157.610 6.52 Aggipulla 110 12 T3 To be Fell
63 157.612 7.05 Aggipulla 155 13 T4 To be Fell
64 157.620 12.5 Giriship 90 12 T2
65 157.625 6.95 Kanuga 160 13 T4 To be Fell
66 157.635 6.1 Sunkesula 180 12 T4 To be Fell
67 157.640 12.5 Sunkesula 70 11 T2
68 157.650 6.1 Giriship 220 13 T4 To be Fell
69 157.655 12.8 Subabul 60 12 T1
70 157.656 12.78 Subabul 80 11 T2
83 157.658 13.1 Raavi 268 22 T4
84 157.668 6.6 Kanuga 76 8 T2 To be fell
85 157.693 5.3 Bagi 142 20 T4 To be fell
71 157.700 12.65 Kanuga 120 12 T3
72 157.710 11.35 Kanuga 90 11 T2
73 157.720 7.95 Kanuga 110 12 T3 To be Fell
74 157.725 10.75 Kanuga 68 11 T2 To be Fell
86 157.728 6.3 Bagi 273 35 T4 To be fell
75 157.730 10.72 Kanuga 150 12 T4 To be Fell
87 157.740 5.6 Bagi 203 30 T4 To be fell 76 157.740 10.65 Kanuga 100 11 T3 To be Fell
77 157.750 7.02 Kanuga 66 10 T2 To be Fell
78 157.760 7.05 Sunkesula 100 11 T3 To be Fell
79 157.770 7.1 Giriship 201 16 T4 To be Fell
80 157.780 7.65 Kanuga 75 9 T2 To be Fell
81 157.785 12.95 Giriship 42 7 T1
82 157.795 8.85 Banyan 210 13 T4 To be Fell
83 157.800 7.3 Kanuga 50 12 T1 To be Fell
84 157.810 8.85 Giriship 250 14 T4 To be Fell
85 157.860 8.95 Giriship 190 13 T4
86 157.880 7.3 Aggipulla 100 12 T3 To be Fell
87 157.910 8.75 Thumma 110 13 T3
88 158.010 5.65 Aggipulla 110 12 T3 To be Fell
89 158.040 6 Giriship 290 11 T4 To be Fell
90 158.080 6.4 Giriship 260 12 T4 To be Fell
88 158.099 4.1 Aggipulla 145 20 T4 To be fell
89 158.285 4.3 Aggipulla 170 20 T4 To be fell
91 158.380 7.15 Aggipulla 220 11 T4
92 158.390 7.1 Aggipulla 150 12 T4 To be Fell
90 158.396 5.6 Aggipulla 145 22 T4 To be fell
93 158.420 6.05 Giriship 210 11 T4 To be Fell
94 158.435 6.04 Aggipulla 150 12 T4
91 158.448 7.3 Kanuga 73 5 T2 To be fell
92 158.462 7.5 Bagi 228 25 T4 To be fell
93 158.482 10.3 Bagi 132 8 T4 To be fell
94 158.500 8.9 Thumma 125 10 T4 To be fell
95 158.506 7 Bagi 182 25 T4 To be fell
95 158.515 6.3 Giriship 121 12 T4
96 158.517 6.9 Thumma 152 15 T4 To be fell
97 158.530 6.9 Aggipulla 133 20 T4 To be fell
98 158.544 6.9 Bagi 153 30 T4 To be fell
99 158.555 6.8 Bagi 152 20 T4 To be fell 96 158.555 6.67 Giriship 180 13 T4
100 158.594 6.9 Bagi 184 25 T4 To be fell
101 158.603 7.1 Bagi 152 15 T4 To be fell
97 158.625 7.15 Giriship 165 12 T4 To be Fell
98 158.650 7.86 Giriship 220 13 T4 To be Fell
102 158.673 7.5 Aggipulla 112 13 T3 To be fell
99 158.680 7.95 Thumma 160 13 T4 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
100 158.700 9.05 Giriship 150 12 T4 To be Fell
103 158.703 8.1 Bagi 178 20 T4 To be fell
101 158.750 6.5 Giriship 175 11 T4 To be Fell
102 158.757 14.1 Giriship 120 12 T3 To be Fell
103 158.757 6.35 Giriship 90 13 T2 To be Fell
104 158.760 12.95 Giriship 175 14 T4
105 158.765 6.67 Neem 80 11 T2 To be Fell
106 158.770 12.96 Giriship 52 12 T1
107 158.775 6.37 Giriship 63 11 T2 To be Fell
108 158.780 12.95 Giriship 130 14 T4
104 158.787 7.6 Bagi 175 18 T4 To be fell
109 158.790 6.52 Neem 180 14 T4 To be Fell
110 158.794 12.65 Giriship 130 13 T4
111 158.796 12.63 Giriship 62 10 T2
112 158.798 12.65 Giriship 86 11 T2
113 158.800 12.65 Giriship 78 12 T2
105 158.808 12.2 Neem 184 17 T4 To be fell
114 158.810 6.45 Thumma 170 11 T4 To be Fell

106 159.035 6.2 Bagi 72 8 T2 To be fell


107 159.065 8.4 Neem 58 10 T1 To be fell
108 159.105 8.3 Neem 65 15 T2 To be fell
109 159.173 8.2 Neem 92 18 T3 To be fell
110 159.180 10.4 Neem 103 17 T3 To be fell
111 159.210 10.9 Neem 110 20 T3 To be fell
112 159.216 10.1 Neem 75 20 T2 To be fell
113 159.216 12.5 Neem 80 23 T2 To be fell
114 159.246 10.2 Neem 72 22 T2 To be fell
115 159.445 9 Neem 112 20 T3 To be fell
116 159.465 8.9 Neem 105 15 T3 To be fell
115 160.020 5.52 Kanuga 68 11 T2 To be Fell
116 160.030 6.85 Neem 150 12 T4
117 160.095 6.3 Aggipulla 82 12 T2 To be fell
117 160.100 6.05 Aggipulla 120 10 T3
118 160.110 6.95 Neem 130 12 T4
119 160.170 12.94 Giriship 177 13 T4
120 160.200 13.3 Giriship 355 16 T4
121 160.210 5.95 Giriship 100 12 T3
122 160.225 11.65 Tamarind 165 13 T4
123 160.270 6.6 Seema Tanged 75 11 T2
124 160.280 6.95 Aggipulla 105 12 T3
125 160.290 11.67 Neem 160 11 T4
126 160.305 12.05 Neem 165 12 T4
127 160.310 13.5 Neem 130 14 T4
118 160.335 10.6 Bagi 270 30 T4 To be fell
128 160.350 9.65 Neem 165 13 T4
129 160.380 8.95 Aggipulla 72 11 T2
130 160.385 9.05 Aggipulla 146 12 T4
131 160.410 Deep Curve
132 160.410 11.05 Neem 235 13 T4
133 160.430 11.52 Neem 260 14 T4
119 160.442 7.7 Aggipulla 72 10 T2 To be fell
120 160.482 9.8 Bagi 126 15 T4 To be fell
134 160.500 10.05 Thumma 120 13 T3
121 160.515 8.2 Bagi 172 32 T4 To be fell
135 160.520 8.65 Aggipulla 60 12 T1
136 160.530 8.95 Giriship 210 13 T4
122 160.538 8 Bagi 183 25 T4 To be fell
137 160.540 13.05 Neem 78 11 T2
138 160.550 12.05 Neredu 88 12 T2
139 160.565 12.15 Badam 68 8 T2
123 160.578 7.8 Aggipulla 97 18 T3 To be fell
140 160.580 10.25 Neem 76 12 T2
124 160.585 9.4 Thumma 123 22 T4 To be fell
141 160.590 12.35 Banyan 78 13 T2
125 160.598 7.2 Aggipulla 135 20 T4 To be fell
126 160.604 8.3 Thumma 152 23 T4 To be fell
142 160.610 12.05 Neem 68 12 T2
143 160.610 6.7 Giriship 210 14 T4
127 160.614 7.7 Thumma 112 16 T3 To be fell
144 160.615 12.06 Badam 52 11 T1
128 160.627 7.6 Bagi 234 20 T4 To be fell
145 160.630 6.4 Neem 755 19 T4 To be Fell
129 160.660 7.1 Neem 110 22 T3 To be fell
130 160.664 7.4 Bagi 205 20 T4 To be fell
131 160.676 7.2 Aggipulla 65 8 T2 To be fell
146 160.695 7 Aggipulla 100 12 T3 To be Fell
132 160.730 6.7 Bagi 190 30 T4 To be fell
133 160.815 7 Bagi 165 15 T4 To be fell
147 160.820 8.05 Neem 130 16 T4
148 160.830 7.05 Giriship 140 15 T4
149 160.840 7.06 Giriship 220 16 T4
134 160.850 6.2 Bagi 250 32 T4 To be fell 150 160.850 7.05 Giriship 195 15 T4 To be Fell
151 160.880 7.65 Giriship 275 12 T4
135 160.885 6.4 Bagi 73 12 T2 To be fell
152 160.900 7.05 Giriship 120 13 T3 To be Fell
153 160.910 7.65 Giriship 140 14 T4 To be Fell
136 160.920 10.3 Neem 183 25 T4 154 160.920 7.65 Giriship 142 13 T4 To be Fell
155 160.930 7.45 Aggipulla 184 12 T4 To be Fell
137 160.959 9.6 Neem 202 30 T4
156 160.970 7.65 Giriship 290 13 T4 To be Fell
157 160.980 5.92 Rappal 76 10 T2 To be Fell
158 160.980 7.45 Tangedi 120 14 T3 To be Fell
138 160.985 6.2 Bagi 115 15 T3 To be fell
139 160.997 11.4 Neem 125 25 T4
159 161.405 5.8 Giriship 240 12 T4 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
140 161.406 5.7 Aggipulla 130 25 T4
141 161.418 5.6 Aggipulla 115 20 T3 To be fell
160 161.420 5.95 Aggipulla 120 11 T3 To be Fell
161 161.440 5.92 Giriship 270 12 T4 To be Fell
142 161.448 7.4 Neem 100 20 T3 To be fell
162 161.450 5.95 Aggipulla 90 13 T2 To be Fell
143 161.460 7.6 JeediMamid 150 20 T4 To be fell
144 161.470 9.6 Giriship 120 22 T3 163 161.470 7.23 Banyan 225 16 T4 To be Fell
145 161.470 10.3 Bagi 130 25 T4
164 161.510 11.5 Seema Tanged 95 12 T3
165 161.520 8.53 Seema Tanged 80 9 T2 To be Fell
166 161.530 5.7 Giriship 254 12 T4 To be Fell
146 161.570 12.1 Giriship 60 10 T1
167 161.580 6.5 Aggipulla 95 11 T3 To be Fell
147 161.583 12.2 Neem 62 10 T2
148 161.593 9.5 Bagi 45 6 T1
168 161.595 6.66 Tangedi 85 12 T2 To be Fell
169 161.600 8.75 Thumma 125 13 T4 To be Fell
149 161.605 12.3 Neem 180 20 T4
150 161.617 12.1 Neem 85 18 T2
170 161.620 8.25 Giriship 255 12 T4 To be Fell
151 161.630 12.4 Giriship 95 25 T3 171 161.630 7.95 Aggipulla 150 13 T4 To be Fell
152 161.662 10.5 Neem 45 5 T1
172 161.670 6.85 Aggipulla 130 14 T4 To be Fell
153 161.676 10.7 Thumma 165 18 T4
173 161.680 6.65 Aggipulla 100 12 T3 To be Fell
154 161.686 10.6 Thumma 145 25 T4
174 161.690 6.1 Giriship 250 13 T4 To be Fell
175 161.720 6.55 Giriship 210 14 T4 To be Fell
176 161.730 6.44 Neem 140 11 T4 To be Fell
155 161.746 6.4 Neem 120 25 T3 To be fell
156 161.750 6.5 Giriship 100 22 T3 To be fell
157 161.756 6.4 Bagi 150 15 T4 To be fell
158 161.785 6.8 Bagi 240 30 T4 To be fell
177 161.795 7.8 Giriship 220 12 T4 To be Fell
159 161.810 6.5 Kanuga 85 5 T2 To be fell 178 161.810 7.65 Aggipulla 95 13 T3 To be Fell
160 161.823 7.3 Bagi 210 25 T4 To be fell
161 161.853 7.6 Bagi 155 20 T4 To be fell
162 161.862 6.3 Bagi 120 12 T3 To be fell
163 161.875 5.7 Bagi 170 20 T4 To be fell
164 161.882 5.9 Aggipulla 70 8 T2 To be fell
179 161.900 6.5 Aggipulla 96 10 T3 To be Fell
180 161.910 6.67 Giriship 155 12 T4 To be Fell
181 161.920 6.68 Tangedi 90 10 T2 To be Fell
182 161.930 6.32 Aggipulla 82 9 T2 To be Fell
165 161.936 6.1 Aggipulla 65 12 T2 To be fell
166 161.946 6.1 Bagi 195 25 T4 To be fell
183 161.950 5.65 Giriship 188 14 T4 To be Fell
167 161.966 7 Aggipulla 95 9 T3 To be fell
168 161.976 6.1 Bagi 65 8 T2 To be fell
169 161.986 6.2 Bagi 170 22 T4 To be fell
184 161.990 7.9 Giriship 142 12 T4 To be Fell
170 161.995 6.4 Bagi 85 10 T2 To be fell
171 161.999 5.3 Bagi 85 12 T2 To be fell
172 162.007 5.5 Bagi 170 22 T4 To be fell
185 162.010 8.9 Giriship 135 12 T4
173 162.045 5.4 Aggipulla 110 18 T3 To be fell
174 162.056 5.8 Bagi 225 30 T4 To be fell
175 162.067 6.4 Bagi 110 12 T3 To be fell
176 162.098 6.9 Bagi 200 30 T4 To be fell
186 162.110 8.45 Raavi 315 18 T4
187 162.120 7.8 Neem 150 13 T4
188 162.130 12.3 Neem 93 14 T3
189 162.140 8.8 Tamarind 240 16 T4
177 162.195 9.3 Bagi 190 32 T4 To be fell
178 162.260 7.5 Bagi 100 8 T3 To be fell 190 162.260 9.6 Neem 105 13 T3
191 162.265 8.9 Thumma 80 12 T2
192 162.275 8.96 Kanuga 65 13 T2
193 162.280 8.05 Giriship 110 12 T3
194 162.330 6.7 Aggipulla 75 10 T2 To be Fell
195 162.340 6.4 Patti 60 12 T1 To be Fell
196 162.345 6.37 Neredu 118 13 T3 To be Fell
197 162.360 7.05 K.patti 75 12 T2
198 162.370 8.6 Neem 55 13 T1
199 162.375 8.72 Neem 60 14 T1
179 162.385 7.5 Bagi 120 20 T3 To be fell
180 162.825 6.2 Bagi 100 10 T3 To be fell
181 162.832 6.6 Neem 65 8 T2 To be fell
182 162.835 7.7 Thurai 40 6 T1
183 162.860 7.8 Bagi 60 6 T1
200 162.880 5.7 Neem 170 12 T4 To be Fell
184 162.900 7 Neem 65 10 T2 To be fell
201 162.920 13 Neem 260 14 T4
202 162.925 8.15 Giriship 47 13 T1 To be Fell
203 162.960 10.15 Neem 110 12 T3
185 162.970 8.9 Giriship 45 12 T1 204 162.970 8.05 Neem 110 13 T3 To be Fell
205 162.990 8.5 Sunkesula 80 11 T2 To be Fell
206 163.020 9.05 Neem 90 11 T2 To be Fell
186 163.042 7.4 Neem 65 9 T2
207 163.050 8.3 Neem 40 9 T1 To be Fell
187 163.055 10.2 JeediMamid 80 6 T2 To be fell
188 163.059 10.3 Neem 220 20 T4 To be fell
189 163.070 9.7 Tamarind 300 30 T4 To be fell 208 163.070 7.65 Neem 55 7 T1 To be Fell
190 163.077 9.8 Neem 75 12 T2 To be fell
191 163.080 9.9 Raavi 110 10 T3 To be fell 209 163.080 7.55 Neem 75 9 T2 To be Fell
192 163.087 7.2 Kanuga 70 8 T2 To be fell
210 163.090 7.45 Sunkesula 75 10 T2 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
211 163.092 7.45 Giriship 105 11 T3 To be Fell
193 163.095 11.1 Neem 150 15 T4 To be fell
194 163.980 7.9 Bagi 45 8 T1 To be fell
195 163.108 7.6 Neem 150 18 T4 To be fell
212 163.110 7.45 Neem 115 12 T3 To be Fell
196 163.119 7.1 Bagi 135 10 T4 To be fell
197 163.132 8.1 Neem 60 8 T1 To be fell
198 163.142 7.5 Neem 85 12 T2 To be fell
199 163.153 10.6 Neem 130 18 T4 To be fell
213 163.160 7.6 Kanuga 70 13 T2 To be Fell
200 163.165 10.7 Neem 65 4 T2 To be fell
201 163.177 6.4 Bagi 130 18 T4 To be fell
214 163.180 6.3 Giriship 85 11 T2 To be Fell
202 163.185 6.5 Bagi 125 15 T4 To be fell
215 163.190 6.5 Neem 125 12 T4 To be Fell
203 163.195 6.6 Bagi 126 20 T4 To be fell GT 216 163.195 14.7 Neem 70 13 T2
204 163.199 7.1 Bagi 125 14 T4 To be fell GT 217 163.197 14.61 Neem 73 12 T2
205 163.212 7 Bagi 180 22 T4 To be fell GT 218 163.215 6.5 Giriship 82 13 T2 To be Fell
GT
206 163.230 6.9 Bagi 140 16 T4 To be fell GT 219 163.230 6.67 Giriship 80 12 T2 To be Fell
207 163.250 6.9 Bagi 168 20 T4 To be fell GT 220 163.250 5.95 Neem 60 11 T1 To be Fell
GT 221 163.260 7.3 Kanuga 42 12 T1 To be Fell
208 163.265 7.6 Bagi 100 10 T3 To be fell GT
209 163.278 7.5 Bagi 125 20 T4 To be fell GT
GT 222 163.280 7.65 Giriship 125 11 T4 To be Fell
210 163.292 7.3 Bagi 125 20 T4 To be fell GT
211 163.300 6.7 Bagi 130 20 T4 To be fell GT 223 163.300 7.7 Neem 58 10 T1 To be Fell
212 163.310 6.2 Kanuga 50 5 T1 To be fell GT 224 163.310 5.85 Giriship 95 11 T3 To be Fell
225 163.320 5.95 Giriship 160 12 T4 To be Fell
213 163.325 6.5 Seema Chin 45 5 T1 To be fell
214 163.330 6.5 Bagi 120 20 T3 To be fell 226 163.330 6.35 Giriship 140 13 T4 To be Fell
227 163.340 6.33 Giriship 190 14 T4 To be Fell
215 163.343 5.6 Bagi 170 15 T4 To be fell
228 163.355 7.15 Giriship 160 12 T4 To be Fell
216 163.387 7.5 Bagi 200 25 T4 To be fell
229 163.390 7.25 Giriship 175 11 T4 To be Fell
230 163.405 7.32 Giriship 160 13 T4 To be Fell
231 163.425 7.05 Giriship 198 12 T4 To be Fell
232 163.440 7.15 Giriship 175 13 T4 To be Fell
233 163.450 7.15 Giriship 120 14 T3 To be Fell
234 163.460 7.14 Giriship 50 11 T1 To be Fell
235 163.475 7.15 Giriship 140 12 T4 To be Fell
236 163.530 7.82 Giriship 75 13 T2 To be Fell
217 163.533 6 Bagi 160 20 T4 To be fell
237 163.550 7.05 Giriship 45 12 T1 To be Fell
218 163.575 6.4 Bagi 50 8 T1 To be fell
219 163.630 6.5 Bagi 39 4 T1 To be fell
220 163.645 6.5 Bagi 55 7 T1 To be fell
221 163.700 6 Kanuga 85 6 T2 To be fell
222 163.748 7.4 Bagi 240 35 T4 To be fell
223 163.760 6.3 100 15 T3 To be fell
224 163.760 6.3 Giriship 90 10 T2 To be fell
225 163.768 6.2 Bagi 110 15 T3 To be fell
238 163.770 8 Seema Tanged 82 13 T2 To be Fell
226 163.776 6.3 Bagi 55 7 T1 To be fell
239 163.790 7.9 Aggipulla 110 12 T3 To be Fell
227 163.812 6 Bagi 190 25 T4 To be fell
228 163.828 6.4 Bagi 155 20 T4 To be fell
240 163.830 6.85 Giriship 85 11 T2 To be Fell
229 163.843 6.7 Bagi 185 22 T4 To be fell
241 163.850 6.65 Kanuga 38 7 T1 To be Fell
230 163.855 6.8 Kanuga 90 8 T2 To be fell
231 163.859 6.8 Bagi 45 6 T1 To be fell
242 163.870 6.67 Giriship 100 10 T3 To be Fell
243 163.890 6.65 Giriship 65 9 T2 To be Fell
244 163.940 9.1 Aggipulla 175 12 T4
232 163.950 7.3 Giriship 50 7 T1 To be fell 245 163.950 7.1 Giriship 135 7 T4 To be Fell
246 163.995 8.55 Giriship 52 8 T1
247 164.005 6.45 Giriship 50 10 T1 To be Fell
248 164.010 6.7 Giriship 120 11 T3 To be Fell
233 164.045 6.3 Bagi 100 12 T3 To be fell
249 164.060 6.85 Neem 75 7 T2 To be Fell
250 164.080 6.75 Tangedi 55 8 T1 To be Fell
234 164.100 7 Bagi 40 8 T1 To be fell 251 164.100 8.05 Giriship 165 10 T4
235 164.110 7.1 Bagi 95 12 T3 To be fell
252 164.160 6.55 Giriship 70 7 T2 To be Fell
253 164.175 6.25 Giriship 78 8 T2 To be Fell
254 164.195 6.56 Giriship 120 9 T3 To be Fell
236 164.203 6.3 Bagi 150 22 T4 To be fell
255 164.240 6.15 Giriship 90 11 T2 To be Fell
256 164.250 7.6 Giriship 70 12 T2 To be Fell
237 164.255 7.4 Bagi 155 25 T4 To be fell
257 164.260 6.9 Giriship 90 13 T2 To be Fell
258 164.270 6.95 Giriship 80 10 T2 To be Fell
238 164.298 7 Bagi 130 20 T4 To be fell
239 164.299 5.9 Aggipulla 50 10 T1 To be fell
259 164.320 13.4 Neem 100 13 T3
260 164.322 13.95 Kanuga 150 14 T4
240 164.323 6.7 Bagi 190 35 T4 To be fell
261 164.326 11.45 pula 70 13 T2
262 164.330 13.96 Neradu 175 14 T4
263 164.335 11.65 Neradu 150 15 T4
241 164.342 6.9 Bagi 140 22 T4 To be fell
242 164.354 7.3 Bagi 72 10 T2 To be fell
243 164.358 7.5 Bagi 85 18 T2 To be fell
264 164.360 13.97 Kanuga 122 16 T4
265 164.365 5.65 Giriship 130 11 T4 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
266 164.370 5.45 Aggipulla 70 14 T2 To be Fell
244 164.378 7.1 Bagi 85 15 T2 To be fell
267 164.380 6.25 Giriship 110 11 T3 To be Fell
245 164.384 7.3 Bagi 160 22 T4 To be fell
246 164.393 8.1 Bagi 190 25 T4 To be fell
247 164.403 7.8 Bagi 120 28 T3 To be fell
248 164.407 7.5 Bagi 210 30 T4 To be fell
268 164.410 5.6 Giriship 165 12 T4 To be Fell
249 164.419 7.5 Kanuga 75 8 T2 To be fell
269 164.420 5.7 Aggipulla 93 10 T3 To be Fell
270 164.460 5.5 Giriship 125 12 T4 To be Fell
250 164.469 7.7 Bagi 160 20 T4 To be fell
271 164.470 5.65 Tangedi 65 10 T2 To be Fell
251 164.484 7.5 Bagi 135 25 T4 To be fell
272 164.485 5.75 Kanuga 59 6 T1 To be Fell
273 164.495 10.4 Sunkesula 73 12 T2
252 164.501 7.6 Aggipulla 90 10 T2 To be fell
253 164.513 7.7 Bagi 160 25 T4 To be fell
254 164.527 6.3 Bagi 165 20 T4 To be fell
274 164.540 6 Giriship 120 13 T3 To be Fell
255 164.550 8.4 Bagi 180 30 T4 To be fell 275 164.550 6.05 Giriship 160 12 T4 To be Fell
276 164.580 6.45 Giriship 90 11 T2 To be Fell
256 164.594 7.4 Bagi 155 26 T4 To be fell
257 164.598 6 Bagi 165 30 T4 To be fell
277 164.600 6.85 Giriship 105 10 T3 To be Fell
258 164.606 6.6 Kanuga 90 8 T2 To be fell
259 164.620 7.5 Bagi 220 30 T4 To be fell
260 164.631 7.3 Giriship 65 8 T2 To be fell
261 164.632 7.5 Bagi 115 12 T3 To be fell
262 164.654 8.3 Aggipulla 80 13 T2 To be fell
263 164.676 8.7 Bagi 190 25 T4 To be fell
264 164.688 8.9 Neem 120 20 T3 To be fell
278 164.690 6.65 Giriship 170 11 T4 To be Fell
265 164.702 10.2 Aggipulla 80 8 T2 To be fell
266 164.712 7.3 Bagi 60 10 T1 To be fell
279 164.720 6.25 Tangedi 75 7 T2 To be Fell
269 164.728 6.5 Bagi 200 25 T4 To be fell
267 164.733 7.8 Bagi 140 20 T4 To be fell
280 164.740 6.05 Giriship 120 11 T3 To be Fell
281 164.750 6.5 Kanuga 94 11 T3 To be Fell
268 164.755 9 Kanuga 45 6 T1 To be fell
282 164.810 5.95 Giriship 240 12 T4
270 164.845 7.4 Bagi 180 22 T4 To be fell
283 164.860 6.8 Giriship 95 12 T3
271 164.880 7.4 Bagi 175 20 T4 To be fell
284 164.920 6.65 Giriship 100 13 T3 To be Fell
285 164.950 6.5 Kanuga 52 6 T1 To be Fell
286 164.970 6.75 Aggipulla 90 9 T2 To be Fell
272 164.985 7 Giriship 90 10 T2 To be fell
273 164.995 8.1 Bagi 125 22 T4 To be fell
274 165.005 6.7 Bagi 200 30 T4 To be fell
275 165.040 6.3 Aggipulla 50 7 T1 To be fell
276 165.050 6.7 Kanuga 65 6 T2 To be fell
277 165.065 5.7 Bagi 160 20 T4 To be fell
278 165.074 8 Bagi 125 20 T4
287 165.085 6.1 Aggipulla 95 10 T3 To be Fell
279 165.132 7.1 Bagi 160 18 T4 To be fell
288 165.135 7.1 Giriship 80 8 T2 To be Fell
289 165.145 7.95 Giriship 130 9 T4 To be Fell
280 165.197 6.9 Bagi 155 20 T4 To be fell
290 165.310 7.4 Giriship 205 10 T4 To be Fell
281 165.328 6.5 Bagi 190 22 T4 To be fell
291 165.330 7.35 Giriship 140 12 T4 To be Fell
292 165.350 7.25 Giriship 115 13 T3 To be Fell
282 165.353 6.1 Bagi 130 16 T4
293 165.360 7.35 Giriship 185 11 T4 To be Fell
294 165.390 6.8 Aggipulla 90 10 T2 To be Fell
283 165.394 6.5 Bagi 85 10 T2
284 165.406 7.3 Bagi 175 25 T4
285 165.420 11.6 Neredu 220 20 T4
286 165.421 8.9 Bagi 210 25 T4
287 165.424 12.1 Marri 195 22 T4
288 165.429 9.4 Neredu 190 20 T4
289 165.430 12.1 JeediMamid 100 10 T3
290 165.434 11.6 Neem 140 25 T4
291 165.439 12.7 102 20 T3
295 165.440 6.1 Aggipulla 70 11 T2 To be Fell
292 165.443 6.9 Bagi 190 35 T4
293 165.448 8.4 Neem 140 18 T4
294 165.478 5.8 Bagi 180 23 T4 To be fell
296 165.490 6.2 K.patti 77 9 T2 To be Fell
297 165.500 6.15 Tangedi 14 11 T1 To be Fell
298 165.510 6.35 Giriship 110 12 T3 To be Fell
295 165.543 6.6 Bagi 150 20 T4 To be fell
299 165.570 6.3 Tangedi 60 8 T1 To be Fell
300 165.585 7.65 Giriship 130 9 T4 To be Fell
296 165.601 7.8 Bagi 155 25 T4 To be fell
301 165.605 7.8 Tangedi 52 7 T1 To be Fell
297 165.622 7.7 Aggipulla 90 13 T2 To be fell
302 165.630 6.85 Giriship 120 10 T3 To be Fell
298 165.635 8 Bagi 170 22 T4 To be fell
303 165.650 6.95 Kanuga 110 9 T3 To be Fell
299 165.656 6.9 Bagi 180 20 T4 To be fell
300 165.695 7.8 Bagi 145 22 T4 To be fell
301 165.706 7.3 Neem 45 10 T1 To be fell
302 165.709 7.2 Kanuga 90 8 T2 To be fell
304 165.745 7.05 Giriship 120 11 T3 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
303 165.753 6.3 Aggipulla 68 12 T2 To be fell
304 165.759 6.5 Kanuga 50 7 T1 To be fell
305 165.766 5.9 Aggipulla 130 15 T4 To be fell
305 165.780 5.75 Giriship 150 10 T4 To be Fell
306 165.790 6.15 Tangedi 70 8 T2 To be Fell
306 165.794 6.2 Bagi 100 10 T3 To be fell
307 165.803 6.1 Bagi 85 9 T2 To be fell
307 165.825 6.15 Tangedi 125 7 T4 To be Fell
308 165.840 6.75 Aggipulla 85 10 T2 To be Fell
308 165.845 6.2 Aggipulla 95 15 T3 To be fell
309 165.850 6.85 Tangedi 110 11 T3 To be Fell
310 165.860 6.97 Tangedi 110 9 T3 To be Fell
311 165.870 7.15 Tangedi 50 8 T1
309 165.870 6 Bagi 190 20 T4 To be fell
310 165.877 6.2 Aggipulla 115 18 T3 To be fell
312 165.880 7.05 Aggipulla 132 10 T4 To be Fell
313 165.890 7.7 Aggipulla 100 11 T3
311 165.894 5.9 Aggipulla 120 15 T3 To be fell
312 165.898 6.7 Aggipulla 55 10 T1 To be fell
313 165.902 6.1 Aggipulla 90 12 T2 To be fell
314 165.910 7.1 Aggipulla 70 10 T2
314 165.913 6.3 Aggipulla 110 15 T3 To be fell
315 165.920 7.1 Aggipulla 70 11 T2
315 165.923 6.5 Aggipulla 112 13 T3 To be fell
316 165.930 6.8 Aggipulla 65 12 T2 To be fell 316 165.930 7.65 Giriship 110 12 T3
317 165.938 6.2 Aggipulla 120 20 T3 To be fell
317 165.940 7.67 Giriship 135 13 T4
318 165.950 7.65 Aggipulla 100 12 T3
318 165.953 6.3 Aggipulla 110 15 T3 To be fell
319 165.960 7.6 Aggipulla 51 9 T1
319 165.963 6.3 Aggipulla 112 18 T3 To be fell
320 165.965 7.65 Giriship 85 10 T2
321 165.970 6.05 Aggipulla 60 7 T1 To be Fell
320 165.971 6.2 Aggipulla 105 15 T3 To be fell
321 165.978 6.3 Bagi 190 25 T4 To be fell
322 165.980 7.65 Aggipulla 55 7 T1
322 165.988 6.3 Aggipulla 90 14 T2 To be fell
323 165.990 7.05 Aggipulla 70 9 T2
323 165.995 6.5 Aggipulla 130 20 T4 To be fell
324 165.998 7.65 Aggipulla 115 12 T3
324 166.009 6.4 Bagi 210 35 T4 To be fell
325 166.010 7.1 Giriship 185 13 T4 To be Fell
325 166.016 7.7 Bagi 140 20 T4 To be fell
326 166.020 7 Giriship 160 14 T4
326 166.026 7.8 Bagi 165 25 T4 To be fell
327 166.030 6.72 Giriship 170 15 T4 To be Fell
328 166.040 6.85 Giriship 183 14 T4 To be Fell
328 166.048 7.6 Bagi 170 25 T4 To be fell
329 166.050 6.1 Giriship 215 15 T4 To be Fell
329 166.060 7 Bagi 195 30 T4 To be fell 330 166.060 6.8 Giriship 180 16 T4 To be Fell
330 166.069 5.5 Bagi 170 40 T4 To be fell
331 166.070 6.65 Giriship 182 13 T4 To be Fell
331 166.073 10.3 Tamarind 220 30 T4 To be fell
332 166.080 6.45 Giriship 170 15 T4 To be Fell
332 166.086 5.1 Aggipulla 60 9 T1 To be fell
333 166.090 6.3 Giriship 185 14 T4 To be Fell
333 166.094 6.4 Aggipulla 75 10 T2 To be fell
334 166.100 6.65 Aggipulla 100 13 T3
334 166.110 6 Bagi 170 22 T4 To be fell 335 166.110 7.05 Aggipulla 55 9 T1
336 166.115 6.35 Aggipulla 80 7 T2 To be Fell
335 166.121 7 Bagi 160 25 T4 To be fell
336 166.126 7 Bagi 135 25 T4 To be fell
337 166.129 6.8 Bagi 125 22 T4 To be fell
337 166.130 6.65 Giriship 200 12 T4
338 166.139 7.5 Bagi 180 25 T4 To be fell
338 166.140 6.75 Giriship 210 14 T4
339 166.151 7.2 Bagi 151 22 T4 To be fell
339 166.160 5.9 Giriship 160 14 T4 To be Fell
340 166.161 5.9 Bagi 190 25 T4 To be fell
340 166.170 6.05 Giriship 170 15 T4 To be Fell
341 166.171 6.5 Bagi 120 24 T3 To be fell
341 166.180 5.85 Aggipulla 75 9 T2 To be Fell
342 166.181 6.9 Bagi 170 28 T4 To be fell
343 166.187 8.7 Neem 60 12 T1 To be fell
342 166.190 6.65 Aggipulla 70 8 T2 To be Fell
344 166.191 6.3 Bagi 72 12 T2 To be fell
345 166.194 6.3 Bagi 150 30 T4 To be fell
346 166.200 6.7 Aggipulla 70 12 T2 To be fell 343 166.200 5.8 Giriship 150 10 T4 To be Fell
344 166.210 5.9 Tangedi 65 9 T2 To be Fell
347 166.211 9.1 Neem 60 10 T1 To be fell
345 166.220 6.55 Giriship 120 10 T3
348 166.215 8.7 Aggipulla 50 7 T1 To be fell
349 166.224 8.9 Bagi 120 30 T3 To be fell
346 166.230 6.65 Aggipulla 90 12 T2
347 166.240 6.75 Aggipulla 65 9 T2
348 166.250 6.35 Aggipulla 115 10 T3 To be Fell
350 166.258 7.8 Aggipulla 80 13 T2 To be fell
349 166.260 6.05 Tangedi 60 9 T1 To be Fell
351 166.267 8.6 Bagi 200 25 T4 To be fell
350 166.270 6.15 Tangedi 60 10 T1 To be Fell
352 166.278 8.9 Bagi 175 26 T4 To be fell
351 166.280 5.95 Giriship 165 11 T4 To be Fell
353 166.289 9.1 Bagi 180 25 T4 To be fell
352 166.290 6.05 Giriship 170 10 T4 To be Fell
354 166.300 7.2 Bagi 140 25 T4 To be fell 353 166.300 6.75 Aggipulla 60 9 T1 To be Fell
355 166.301 7.1 Bagi 80 24 T2 To be fell
354 166.310 6.05 Aggipulla 95 10 T3 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
356 166.311 7 Bagi 190 25 T4 To be fell
355 166.320 6.15 Giriship 140 11 T4 To be Fell
357 166.322 7 Bagi 80 12 T2 To be fell
356 166.330 5.95 Giriship 225 13 T4 To be Fell
358 166.340 8.2 Bagi 180 28 T4 To be fell
359 166.350 8.4 Bagi 170 28 T4 To be fell 357 166.350 6.15 Giriship 200 15 T4 To be Fell
358 166.360 6.25 Giriship 210 14 T4 To be Fell
327 166.370 7.7 Bagi 180 30 T4 To be fell 359 166.370 7.2 Giriship 190 15 T4
360 166.380 7.9 Aggipulla 185 16 T4
360 166.383 8.6 Bagi 110 20 T3 To be fell
361 166.390 7.1 Aggipulla 100 12 T3 To be Fell
361 166.393 8.3 Aggipulla 110 18 T3 To be fell
362 166.399 8.1 Neem 60 9 T1 To be fell
362 166.400 6.5 Aggipulla 130 13 T4 To be Fell
363 166.407 7.2 Aggipulla 70 10 T2 To be fell
363 166.410 6.9 Aggipulla 110 12 T3
364 166.417 8.9 Aggipulla 92 12 T3 To be fell
364 166.425 6.75 Aggipulla 130 11 T4
365 166.428 7.1 Aggipulla 100 15 T3 To be fell
366 166.430 7.1 Aggipulla 60 12 T1 To be fell
367 166.431 7.2 Aggipulla 55 10 T1 To be fell
365 166.435 6.85 Aggipulla 80 12 T2
366 166.445 6.65 Thumma 95 11 T3
370 166.450 6.6 Aggipulla 125 15 T4 To be fell
368 166.452 5.8 Aggipulla 90 15 T2 To be fell
371 166.458 6.8 Aggipulla 100 17 T3 To be fell
367 166.460 6.5 Aggipulla 90 12 T2
372 166.462 6.8 Aggipulla 80 15 T2 To be fell
369 166.463 6.6 Aggipulla 130 15 T4 To be fell
373 166.472 7.2 Aggipulla 90 14 T2 To be fell
374 166.482 6.8 Giriship 85 13 T2 To be fell
375 166.485 6.8 Aggipulla 90 14 T2 To be fell
368 166.490 6.45 Aggipulla 110 11 T3
376 166.497 6.7 Aggipulla 115 20 T3 To be fell
377 166.508 7.1 Aggipulla 150 18 T4 To be fell
369 166.510 6.15 Aggipulla 135 12 T4 To be Fell
378 166.518 7.5 Aggipulla 110 18 T3 To be fell
379 166.530 7.6 Aggipulla 115 20 T3 To be fell 370 166.530 6.05 Aggipulla 150 13 T4 To be Fell
380 166.543 7.4 Aggipulla 120 18 T3 To be fell
371 166.550 7.65 Aggipulla 55 9 T1
372 166.555 7.67 Aggipulla 70 6 T2
381 166.557 7.4 Aggipulla 100 15 T3 To be fell
373 166.560 7.5 Aggipulla 72 9 T2
382 166.568 7.4 Aggipulla 110 20 T3 To be fell
374 166.570 7.5 Aggipulla 77 10 T2
383 166.582 7.6 Aggipulla 75 12 T2 To be fell
375 166.585 7.65 Aggipulla 180 9 T4
384 166.597 7.5 Aggipulla 155 20 T4 To be fell
376 166.600 7.25 Aggipulla 117 8 T3
385 166.609 7.3 Thumma 138 18 T4 To be fell
377 166.610 7.45 Aggipulla 120 10 T3
386 166.615 7.7 Aggipulla 99 20 T3 To be fell
378 166.620 7.35 Aggipulla 130 11 T4
387 166.625 7.5 Aggipulla 105 17 T3 To be fell
379 166.630 7.25 Aggipulla 75 10 T2 To be Fell
388 166.655 7.2 Aggipulla 98 12 T3 To be fell
380 166.660 7.85 Aggipulla 65 9 T2 To be Fell
381 166.665 7.8 Aggipulla 67 10 T2 To be Fell
389 166.666 6.2 Aggipulla 176 20 T4 To be fell
382 166.675 6.95 Aggipulla 120 11 T3 To be Fell
390 166.676 6.9 Aggipulla 103 15 T3 To be fell
391 166.677 6.8 Aggipulla 45 10 T1 To be fell
392 166.687 6.9 Aggipulla 115 18 T3 To be fell
383 166.695 6.05 Aggipulla 75 9 T2 To be Fell
393 166.698 6.5 Aggipulla 92 12 T3 To be fell
384 166.700 6.25 Aggipulla 60 8 T1 To be Fell
394 166.707 6.9 Aggipulla 123 20 T4 To be fell
385 166.710 6.45 Aggipulla 65 7 T2 To be Fell
395 166.718 6.7 Aggipulla 130 17 T4 To be fell
386 166.720 6.55 Aggipulla 63 6 T2 To be Fell
396 166.738 6.4 Aggipulla 120 20 T3 To be fell
397 166.745 6.1 Aggipulla 130 18 T4 To be fell 387 166.745 7.9 Aggipulla 65 7 T2
388 166.750 8.45 Aggipulla 70 9 T2
398 166.755 6.5 Aggipulla 110 18 T3 To be fell 389 166.755 7.95 Aggipulla 50 7 T1
390 166.760 8.05 Aggipulla 70 9 T2
399 166.765 6.3 Aggipulla 90 12 T2 To be fell
400 166.765 6.2 Giriship 110 15 T3 To be fell
391 166.770 7.95 Aggipulla 53 10 T1
401 166.780 7.1 Aggipulla 50 12 T1 To be fell 392 166.780 6.85 Aggipulla 105 11 T3 To be Fell
393 166.790 6.7 Aggipulla 115 12 T3 To be Fell
402 166.795 6.8 Aggipulla 60 12 T1 To be fell
394 166.800 6.65 Aggipulla 105 13 T3 To be Fell
395 166.810 5.95 Giriship 115 14 T3 To be Fell
396 166.820 7.5 Aggipulla 55 9 T1
397 166.825 7.6 Aggipulla 65 6 T2
398 166.830 8.15 Aggipulla 50 8 T1
399 166.835 8.54 Aggipulla 55 7 T1
400 166.850 9.2 Seema Tanged 120 9 T3
401 166.860 9 Aggipulla 110 10 T3
402 166.870 11.85 Aggipulla 100 9 T3
403 166.895 9.5 Bagi 140 22 T4 To be fell
404 166.975 9.4 Aggipulla 150 25 T4 To be fell 403 166.975 11 Giriship 162 10 T4
404 166.990 13.3 Neem 140 12 T4
405 166.995 6.8 Aggipulla 75 13 T2 To be fell
405 167.005 7.5 Giriship 100 9 T3
406 167.013 6.3 Bagi 100 17 T3 To be fell
406 167.020 7.05 Seema Tanged 120 10 T3
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
407 167.040 7.85 Giriship 137 11 T4
408 167.050 10.45 Neem 150 11 T4
409 167.110 8.2 Aggipulla 67 10 T2
407 167.120 10.4 Neem 75 20 T2 To be fell 410 167.120 14.65 Neem 88 11 T2
408 167.121 10.5 Neem 80 18 T2 To be fell
409 167.124 9.8 Neredu 41 12 T1 To be fell
411 167.130 8.45 Neem 110 12 T3
410 167.142 10.2 65 25 T2 To be fell
411 167.143 5.9 Bagi 165 26 T4 To be fell
412 167.148 13.2 Neem 80 22 T2 To be fell
413 167.151 12.9 51 21 T1 To be fell
414 167.155 7.3 Aggipulla 80 18 T2 To be fell
412 167.160 7.4 Giriship 130 14 T4 To be Fell
413 167.161 7.35 Tangedi 128 15 T4 To be Fell
415 167.167 7.1 Bagi 150 15 T4 To be fell
414 167.170 7.65 Tangedi 80 12 T2
416 167.180 7.7 Bagi 90 12 T2 To be fell 415 167.180 10.45 Neem 90 10 T2
416 167.187 6.85 Aggipulla 70 11 T2 To be Fell
417 167.190 7.05 Aggipulla 65 12 T2 To be Fell
417 167.194 7.6 Bagi 100 13 T3 To be fell
418 167.195 6.95 Aggipulla 44 7 T1 To be Fell
418 167.199 8.5 Aggipulla 70 10 T2 To be fell
419 167.200 7.55 Tangedi 110 10 T3 To be Fell
419 167.202 7.9 Aggipulla 75 10 T2 To be fell
420 167.205 7.45 Tangedi 120 7 T3 To be Fell
421 167.215 7.15 Tangedi 90 9 T2 To be Fell
420 167.222 8.3 Neem 180 20 T4 To be fell
421 167.230 8.5 Neem 80 15 T2 To be fell 422 167.230 6.8 Giriship 150 10 T4 To be Fell
423 167.235 11 Neem 103 11 T3
422 167.236 10 Neem 95 14 T3 To be fell
423 167.246 8.7 Aggipulla 85 15 T2 To be fell
424 167.255 11.95 Neem 100 11 T3
425 167.260 8.05 Tangedi 110 10 T3
426 167.270 8.15 Tangedi 45 11 T1
427 167.280 8.65 Tangedi 90 9 T2
428 167.290 8.4 Aggipulla 86 8 T2
429 167.300 8.25 Aggipulla 86 11 T2
424 167.303 7.8 Neem 140 18 T4 To be fell
430 167.310 8.45 Aggipulla 40 7 T1
425 167.320 12.3 Neem 100 20 T3 To be fell 431 167.320 8.65 Tangedi 85 10 T2
432 167.330 8.55 Giriship 185 12 T4
433 167.335 8.25 Aggipulla 38 6 T1
434 167.340 12.35 Neem 145 11 T4
435 167.350 8.35 Aggipulla 70 9 T2
436 167.365 8.05 Raavi 56 6 T1
437 167.375 9.15 Thumma 55 9 T1
438 167.420 7.95 Aggipulla 74 7 T2
426 167.435 6.2 Bagi 50 5 T1 To be fell
427 167.438 8.2 Neem 47 5 T1 To be fell
428 167.470 6.7 Bagi 65 10 T2 To be fell
439 167.700 12.05 Neem 52 10 T1
429 167.720 8 Aggipulla 90 17 T2 To be fell
440 167.730 9.65 Giriship 126 7 T4
441 167.780 8.85 Neem 72 9 T2
442 167.860 8.15 Eucalyptus 100 11 T3 To be Fell
443 167.890 8.05 Eucalyptus 77 12 T2 To be Fell
444 167.900 7.95 Giriship 123 13 T4 To be Fell
430 167.997 10 Raavi 40 4 T1 To be fell
431 168.004 10.1 Raavi 45 5 T1 To be fell
445 168.130 9.55 Neem 38 7 T1 To be Fell
432 168.155 12.2 Giriship 95 18 T3
433 168.158 12.4 Giriship 75 18 T2
446 168.160 10.35 Neem 72 9 T2 To be Fell
434 168.162 9.1 Kanuga 100 20 T3 To be fell
435 168.174 13.8 Neem 170 25 T4
447 168.180 6.4 Giriship 53 7 T1 To be Fell
436 168.186 6.9 Neem 70 13 T2 To be fell
448 168.195 9.1 Neem 160 13 T4 To be Fell
437 168.198 6.7 Kanuga 130 15 T4 To be fell
438 168.203 6.6 Giriship 40 7 T1 To be fell
449 168.215 6.75 Neem 45 4 T1 To be Fell
439 168.217 6.7 Neem 90 15 T2 To be fell
450 168.220 6.7 Neem 46 7 T1 To be Fell
451 168.225 6.66 Neem 35 6 T1 To be Fell
452 168.235 6.75 Kanuga 75 9 T2 To be Fell
453 168.250 11.6 Neem 230 12 T4
454 168.280 7.6 Subabul 140 11 T4 To be Fell
455 168.290 7.75 Subabul 120 12 T3 To be Fell
456 168.300 7.85 Subabul 260 13 T4 To be Fell
440 168.315 7.3 Bagi 92 12 T3 To be fell
457 168.330 9.55 Neem 130 12 T4 To be Fell
458 168.360 7.95 Neem 225 14 T4 To be Fell
459 168.360 8.4 Neem 40 7 T1 To be Fell
460 168.425 11.75 Neem 190 16 T4
441 168.427 8.7 Giriship 55 6 T1 To be fell
442 168.427 8.7 Neem 42 5 T1 To be fell
443 168.460 6 Bagi 110 25 T3 To be fell
444 168.467 5.5 Bagi 230 30 T4 To be fell
461 168.470 6.53 Neem 202 15 T4 To be Fell
445 168.495 9.7 Giriship 75 15 T2 To be fell
446 168.505 8 Neem 210 25 T4 To be fell
447 168.535 11.5 Giriship 45 10 T1
448 168.542 10.7 Neem 45 8 T1 To be fell
449 168.550 11.4 Neem 46 8 T1
462 168.590 11.25 Neem 195 16 T4
463 168.650 8.85 Neem 180 12 T4
450 168.665 8.9 Neem 120 14 T3 To be fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
464 168.675 10.84 Neem 300 14 T4
465 168.700 12.34 Neem 245 12 T4
466 168.730 7.5 Neem 65 13 T2
451 168.756 10.9 90 10 T2 To be fell
452 168.805 12.3 Neem 80 10 T2 To be fell
467 168.840 11.05 Neem 100 13 T3
453 168.870 12.8 Giriship 107 12 T3 To be fell
454 168.890 8.2 Neem 235 25 T4 To be fell
455 168.900 12.5 Giriship 130 25 T4 To be fell
468 168.910 10.9 Neem 175 14 T4
456 168.913 8.1 Aggipulla 75 12 T2 To be fell
469 168.950 12.05 Neem 110 13 T3
470 168.960 12.15 Neem 200 14 T4
471 169.030 7.85 Neem 105 13 T3
457 169.072 8.1 Neem 180 25 T4 To be fell
472 169.105 6.55 Neem 230 14 T4
473 169.230 8.9 Giriship 105 12 T3
458 169.260 11.9 Neem 175 25 T4 To be fell
459 169.296 10.6 Neem 70 12 T2 To be fell
474 169.300 13.05 Neem 130 13 T4
460 169.306 7.9 Neem 85 10 T2 To be fell
461 169.309 5 Kanuga 60 10 T1 To be fell
462 169.312 8.5 Neem 85 12 T2 To be fell
475 169.360 14.75 Neem 137 14 T4
476 169.400 14.88 Neem 110 13 T3
477 169.475 15 Kanuga 90 14 T2
463 169.520 9.1 Turaka Nee 80 8 T2 To be fell
478 169.590 8.05 Neem 135 13 T4
464 169.600 9.5 Neem 220 12 T4 To be fell
465 169.615 9.4 Neem 40 8 T1 To be fell
466 169.624 12 Giriship 110 12 T3 To be fell
467 169.626 9.5 Giriship 80 11 T2 To be fell
479 169.640 7.35 Neem 65 9 T2
480 169.690 6.9 konda Neem 180 10 T4
481 169.750 6.75 Neem 206 12 T4
482 169.825 6.85 Neem 190 13 T4
483 169.840 6.85 Neem 232 12 T4
484 169.880 6.75 Neem 210 13 T4
468 169.945 9.3 Neem 290 35 T4 To be fell
469 174.140 11.9 Neem 65 8 T2
485 174.430 13.72 Kanuga 55 7 T1
486 174.435 11.16 Sunkesula 25 6 T1
487 174.960 9.45 Giriship 85 8 T2
470 175.012 7.8 Bagi 92 25 T3
471 175.059 8.1 Giriship 100 20 T3
488 175.280 7.3 Bagi 130 10 T4
489 175.300 7.69 Bagi 140 9 T4
490 175.340 8.95 Bagi 150 10 T4
491 175.350 9.65 Bagi 5.5 7 T1
472 177.605 10.5 Giriship 45 9 T1
473 177.615 10.2 Giriship 40 9 T1
474 177.645 10.2 Giriship 40 6 T1
475 177.657 10.3 Giriship 45 7 T1
476 177.677 9.9 Bagi 48 10 T1
477 177.697 10.1 Giriship 40 7 T1
478 177.720 11.7 Giriship 55 6 T1 492 177.720 14.5 Neem 72 8 T2
493 177.830 8.75 Giriship 45 7 T1
494 177.840 9.1 Giriship 37 8 T1
479 177.988 9 Giriship 50 8 T1
495 178.660 6.88 Neredu 40 7 T1
496 178.740 9.7 Sunkesula 42 6 T1
497 178.755 12.7 Neem 60 7 T1
498 178.770 8.45 Neem 60 9 T1
499 178.790 6.55 Neem 63 9 T2
480 178.795 9.9 Neem 120 13 T3
500 178.805 5.9 Neem 42 11 T1
481 178.815 5.8 Giriship 100 15 T3 501 178.815 5.15 Neem 100 12 T3
482 178.832 8.3 Neem 90 18 T2
483 178.833 5.8 Neem 55 15 T1
502 178.840 10.45 Neem 38 9 T1
484 178.843 7.8 Chigara 55 12 T1
485 178.855 11.6 Chigara 51 17 T1
486 178.870 6.8 Chigara 65 12 T2
503 178.890 6.55 Tamarind 57 8 T1
504 178.940 5.7 Sunkesula 40 10 T1
505 179.790 10.2 Neem 55 T1 To be Fell
487 180.007 8.1 Neem 90 20 T2
488 180.024 9.4 Neem 83 10 T2
506 180.030 8.8 Tamarind 92 7 T3 To be Fell
507 180.040 7.6 Tamarind 42 6 T1 To be Fell
489 180.070 7.6 Thumma 135 18 T4
508 180.090 7 Tamarind 75 7 T2 To be Fell
509 180.120 7.05 Tamarind 65 6 T2 To be Fell
510 180.140 7.15 Tamarind 80 9 T2 To be Fell
490 180.220 9.8 Bagi 50 10 T1
491 180.270 8.6 Tamarind 75 10 T2
511 180.380 6.5 Tamarind 53 6 T1 To be Fell
492 180.452 8 Thumma 93 13 T3
493 180.470 7.2 Neem 60 7 T1
494 180.530 8.2 Thumma 107 22 T3
512 180.570 8.7 Tamarind 60 7 T1 To be Fell
513 181.035 10.3 Neem 90 9 T2 To be Fell
514 181.750 6.3 Neem 92 7 T3 To be Fell
515 181.755 6.45 Neem 60 8 T1 To be Fell
495 182.040 14.1 Neem 110 15 T3
516 182.150 13.2 Kanuga 42 9 T1
517 182.170 8.6 Neem 72 7 T2 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
518 182.180 8.7 Neem 42 8 T1 To be Fell
519 182.185 8.5 Neem 50 7 T1 To be Fell
520 182.200 10 Neem 175 12 T4 To be Fell
521 182.205 10.25 Neem 90 13 T2 To be Fell
522 182.220 6.3 Kanuga 52 7 T1 To be Fell
523 182.240 6.05 Sunkesula 95 10 T3 To be Fell
524 182.250 8.75 Neem 103 10 T3 To be Fell
525 182.255 6.4 Kanuga 94 11 T3 To be Fell
526 182.260 11.4 Kanuga 102 10 T3
527 182.300 7.6 Neem 70 9 T2 To be Fell
498 182.342 11.8 Thumma 120 20 T3
528 182.350 7.6 Sunkesula 75 7 T2 To be Fell
496 182.375 9.9 Neem 95 12 T3 To be fell
529 182.380 8.3 Neem 90 9 T2 To be Fell
530 182.381 8.35 Raavi 70 8 T2 To be Fell
531 182.405 5.4 Neem 76 6 T2 To be Fell
532 182.430 6.3 Neem 60 7 T1 To be Fell
497 182.630 9.8 Neem 55 8 T1 To be fell 533 182.630 8 Neem 54 9 T1 To be Fell
534 182.650 11.2 Neem 115 10 T3
535 182.670 11.1 Neem 75 8 T2
536 182.675 7.2 Neem 70 7 T2 To be Fell
537 182.700 8.8 Neem 137 8 T4 To be Fell
538 182.710 7.59 Neem 110 9 T3 To be Fell
539 182.820 13.25 Neem 68 8 T2
540 182.825 13.35 Sunkesula 100 9 T3
499 182.904 7.5 Neem 45 10 T1 To be fell
500 182.919 7.2 Neem 87 5 T2 To be fell
501 182.936 9.6 Neem 100 15 T3
541 182.975 14.2 Neem 130 9 T4
542 183.175 9.9 Neem 75 8 T2
502 183.223 13.4 Neem 52 10 T1
503 183.373 11.4 Neem 85 15 T2
504 183.655 9.2 Neem 52 12 T1
543 184.760 8 Neem 100 7 T3
505 185.535 9.2 Bagi 160 22 T4
544 185.550 6.7 konda Neem 88 8 T2
506 185.555 6.8 Neem 77 15 T2 To be fell
545 185.570 6.2 Giriship 66 9 T2
546 185.660 6.6 Thurai 40 6 T1 To be Fell
547 185.700 6.85 Thurai 47 7 T1 To be Fell
548 185.720 6.75 Thurai 43 6 T1 To be Fell
549 185.740 6.6 Thurai 50 7 T1
550 185.745 6.95 Thurai 57 6 T1
551 185.750 6.99 Thurai 48 7 T1
552 185.755 7.05 Thurai 50 6 T1
553 185.760 7.1 Thurai 57 7 T1
554 185.765 7.15 Thurai 40 6 T1
555 185.770 7.2 Thurai 47 6 T1
556 185.780 7.25 Thurai 43 7 T1
557 185.790 7.35 Thurai 60 7 T1
507 185.841 10.5 Neem 80 15 T2
508 185.842 10.5 Neem 112 20 T3
509 185.865 9.4 Neem 47 5 T1
510 185.870 6.6 Konda Nee 100 8 T3
511 185.905 9.9 Giriship 115 13 T3 558 185.905 11.3 Neem 53 9 T1
559 185.920 8.85 Neem 40 6 T1
560 185.940 8.3 Neem 53 7 T1
512 185.960 6.3 60 8 T1
513 186.075 7.7 Neem 70 10 T2
514 186.094 13.1 Neem 135 15 T4
561 186.130 8.95 Bagi 103 10 T3
562 186.140 9.15 Neem 40 7 T1
515 186.672 12.5 Jammi 62 8 T2
516 186.848 14.5 Neem 105 20 T3
517 186.922 13.2 Neem 80 15 T2
563 187.805 7 Thumma 85 9 T2 To be Fell
518 188.020 8.6 Thumma 125 23 T4
564 188.515 9.7 Thumma 70 10 T2 To be Fell
519 188.720 10 Thumma 80 15 T2
565 188.730 9.5 Thumma 67 9 T2 To be Fell
520 188.965 8.8 Thumma 113 12 T3 566 188.905 6.8 Kanuga 43 6 T1 To be Fell
521 189.201 7.15 Thumma 75 15 T2
522 189.365 6.3 Bagi 49 8 T1 To be fell
567 189.440 6.9 Sunkesula 86 9 T2 To be Fell
523 189.462 7 Bagi 124 15 T4
524 189.469 7.7 Giriship 54 13 T1
568 189.470 7 Giriship 120 10 T3 To be Fell
525 189.474 7.4 Giriship 99 12 T3
569 189.475 7.15 Tangedi 50 6 T1 To be Fell
570 189.480 7 Giriship 105 7 T3 To be Fell
571 189.490 6.8 Giriship 100 8 T3 To be Fell
526 189.502 6.8 Bagi 134 15 T4
572 189.505 6.75 Giriship 65 7 T2 To be Fell
573 189.525 6.5 Giriship 100 9 T3 To be Fell
527 189.545 6.6 Bagi 88 18 T2 To be fell
528 189.551 6.7 Giriship 61 10 T2 To be fell
574 189.560 7 Aggipulla 80 7 T2 To be Fell
529 189.561 6.6 Bagi 76 12 T2 To be fell
530 189.567 6.4 Bagi 88 13 T2 To be fell
531 189.573 6.6 Bagi 90 12 T2 To be fell
532 189.577 6.6 Bagi 88 15 T2 To be fell
575 189.580 6.7 Giriship 140 8 T4 To be Fell
576 189.595 6.6 Giriship 120 9 T3 To be Fell
577 189.630 7 Giriship 90 7 T2 To be Fell
578 189.640 6.7 Giriship 150 10 T4 To be Fell
579 189.660 6.6 Giriship 130 9 T4 To be Fell
580 189.670 6.5 Giriship 80 7 T2 To be Fell
ammalamadugu - Maidukuru Tree Inventory (R.H.S Jammalamadugu - Maidukuru Tree Inventory ( L.H.S )
S.No Chainage Dist. Name of Girth Height Mo Remarks Green S.No Chainage Dist. Name of the Girth cm Height MoRT Remarks
CL th T RT T l ECL T HT
581 189.680 6.75 Giriship 90 8 T2 To be Fell
582 189.690 11.05 Giriship 43 6 T1 To be Fell
583 189.700 6.4 Giriship 140 7 T4 To be Fell
533 189.707 7.7 Thumma 73 6 T2
534 189.804 8.6 Bagi 38 6 T1
535 189.871 8.2 Neem 71 13 T2
536 189.880 6.5 Bagi 168 20 T4
584 189.895 6.7 Tangedi 162 6 T4 To be Fell
585 189.910 6.85 Tangedi 135 9 T4 To be Fell
586 190.035 6.6 Tangedi 44 6 T1 To be Fell
537 190.089 6 Bagi 73 8 T2 To be fell
587 190.130 6.1 Giriship 100 5 T3 To be Fell
588 190.135 6.15 Giriship 56 6 T1 To be Fell
538 190.145 6.1 Bagi 49 8 T1 To be fell
539 190.151 6.1 Bagi 40 8 T1 To be fell
540 190.162 6.3 Bagi 46 7 T1 To be fell
589 190.170 6.7 Giriship 97 9 T3 To be Fell
541 190.185 6.1 Bagi 73 12 T2 To be fell
590 190.195 6.75 Tangedi 110 8 T3 To be Fell
591 190.230 7.95 Tangedi 100 9 T3 To be Fell
542 190.240 7.7 Thumma 136 20 T4
592 190.250 8.5 Neem 70 8 T2 To be Fell
593 190.300 13.8 Neem 66 7 T2 To be Fell
543 190.306 10.4 Neem 84 15 T2
544 190.310 10.5 Neem 48 7 T1
545 190.313 13 Neem 42 8 T1
594 190.330 9.3 Neem 110 6 T3 To be Fell
595 190.390 7.05 Neem 100 7 T3 To be Fell
596 190.400 8.65 Thumma 123 9 T4 To be Fell
597 190.420 5.6 Giriship 80 8 T2 To be Fell
598 190.430 7.75 Neem 74 7 T2 To be Fell
546 190.443 6.8 Neem 92 15 T3 To be fell
599 190.450 7.45 Tangedi 130 9 T4 To be Fell
600 190.460 7.4 Tangedi 60 8 T1 To be Fell
601 190.465 6.8 Giriship 140 9 T4 To be Fell
602 190.470 7.5 Neem 40 6 T1 To be Fell
603 190.480 6.3 Giriship 90 8 T2 To be Fell
604 190.490 6.5 Giriship 110 9 T3 To be Fell
547 190.495 6.2 Bagi 80 12 T2 To be fell 605 190.495 6.6 Tangedi 77 8 T2 To be Fell
548 190.517 6.8 Bagi 160 8 T4
549 190.568 5.9 Rela 40 5 T1 To be fell

606 190.585 6.4 Giriship 65 7 T2 To be Fell


607 190.595 6.3 Giriship 90 9 T2 To be Fell
608 190.600 8 Neem 75 8 T2 To be Fell
609 190.860 6.6 Neem 90 10 T2 To be Fell
610 190.910 6.7 Giriship 80 7 T2 To be Fell
611 190.950 6.6 Giriship 87 10 T2 To be Fell
612 191.150 7.9 Thurai 40 6 T1 To be Fell
613 191.510 8.5 Giriship 61 8 T2 To be Fell
614 191.545 7.5 Bagi 60 9 T1 To be Fell
APPENDIX 8.1: GUIDELINES FOR AGGREGATE QUARRY MANAGEMENT

The Contractor will finalize the locations from the list given by DPR Consultant’s for procuring materials. The
Contractor shall establish a new quarry only with the prior consent of the EO only in cases when: (i) Lead from existing
quarries is uneconomical and (ii) Alternative material sources are not available. The Contractor shall prepare a
Redevelopment Plan for the quarry site and get it approved by the EO/Supervision Consultant.
The construction schedule and operations plans to be submitted to the EO prior to commencement of work shall
contain a detailed work plan for procuring materials that includes procurement, transportation and storage of quarry
materials.

Operation & redevelopment plan (if a new quarry is opened)…..

• Photograph of the quarry site prior to commencement


• The quarry boundaries as well as location of the materials deposits, working equipments, stockpiling, access
roads and final shape of the pit.
• Drainage and erosion control measures at site.
• Safety Measures during quarry operation.
• Design for redevelopment of exhaust site.
Option-A: Revegetating the quarry to merge with surrounding landscape: This is done by conserving and reapplying the topsoil
for the vegetative growth.
Option-B: Developing exhausted quarries as water bodies: The pit shall be reshaped and developed into pond, for harvesting
rainwater. This option shall only be considered where the location of quarry is at the lowest point, i.e. surrounding
areas/natural drainage slopes towards it.

CONSTRUCTION STAGE
Development of site: To minimize the adverse impact during excavation of material following measures are need to be
undertaken:
i) Adequate drainage system shall be provided to prevent the flooding of the excavated area
ii) At the stockpiling locations, the Contractor shall construct sediment barriers to prevent the erosion of excavated
material due to runoff
iii) Construction of offices, laboratory, workshop and rest places shall be done in the up-wind of the plant to minimize
the adverse impact due to dust and noise.
iv) The access road to the plant shall be constructed taking into consideration location of units and also slope of the
ground to regulate the vehicle movement within the plant.
v) Incase of storage of blasting material, all precautions shall be taken as per The Explosive Rules, 1983.
QUARRY OPERATIONS INCLUDING SAFETY
i) Overburden shall be removed and disposed inline with Guidelines for Debris Disposal Site and management giving
in Annexure-8.3
ii) During excavation, slopes shall be flatter than 20 degrees to prevent their sliding. Incases where quarry strata are
good and where chances of sliding are less this restriction can be ignored.
iii) Incase of blasting, procedure and safety measures shall be taken as per The Explosive Rules, 1983
iv) The contractor shall ensure that all workers related safety measures shall be done as per guidelines for Workers and
Safety attached as Annexure-8.8
v) The Contractor shall ensure maintenance of crushers regularly as per manufacturer’s recommendation.

Page 1 of 5
Topsoil will be excavated and preserved during transportation of the material measures shall be taken to minimize the
generation of dust and prevent accidents.
The EO and the Supervision Consultant shall review the quarry site for the management measures during quarry
operation, including the compliance to pollution norms.
POST CONSTRUCTION STAGE
The Contractor shall restore all haul roads constructed for transporting the material from the quarries to construction
site to their original state.
The EO and the Supervision Consultant shall be entrusted the responsibility of reviewing the quarry site for the
progress of implementation of Redevelopment Plan. These shall include the following two cases;
• Redevelopment of quarries opened by the Contractor for the project
• Redevelopment of existing quarries operated by other agencies
In the first case, the Contractor shall be responsible for the Redevelopment Plan prior to completion after five years,
during the defect liability period. The EO shall be responsible for reviewing this case of redevelopment prior to the
issuing the defect liability certificate.
In the second case, the redevelopment of exhaust quarry shall be the responsibility of the agency providing the permit
to ensure the implementation of Redevelopment Plan.

Page 2 of 5
Case I- For each aggregate-cum-quarry sand source, the plan should contain a separate section. If the quarry is an
existing one and is managed directly by the Contractor, the plan should contain the following:
Sr. Remarks by
Item Unit Details
No. SC/EO, if any
1. Name / identity of the location
2. Nearest project road chainage.
3. Name of the owner
4. Area involved Cum
5. Arrangement with the owner (agreement with land owner
should be attached as an Annexure)
6. Quantity of material to be withdrawn vis-à-vis the material Cum
available
7. Machinery & equipment to be used
8. Copy of the consents to establish and operate should be
attached as an Annexure.
9. Copy of the licence from Mining & Geology, Police & Fire
dept.
10. Conditions laid down in the clearances / licences and plans
to ensure compliance
11. Photographs of the quarry prior to commencing
operations.
12. Access roads condition and proposed maintenance
13. Tree-cutting required, if any, along with compensation No.s
measures
14. Information on whether or not the quarry will be closed
under this project. If yes, the proposed closure &
restoration plan.
15. Sketch of the layout of the quarry
16. Description of the operating practices to be adopted.

Attach Photograph of Proposed Site, Location Map, and Agreement with land owner

REMARKS

SUBMITTED CHECKED APPROVED


SIGNATURE ……………… SIGNATURE ………………….. SIGNATURE …………………
NAME …………………. NAME ……………………… NAME ……………………..
DESIGNATION …………..
CONTRACTOR CONSTRUCTION SUPERVISION EXECUTIVE ENGINEER
CONSULTANT

Page 3 of 5
Case II -If the quarry is an existing one and is managed directly by a sub-contractor from whom the Contractor is
sourcing the materials, the plan should contain the following:

Sr. Remarks by
Item Unit Details
No. SC/EO, if any
1. Name / identity of the location
2. Nearest project road chainage.
3. Name of the owner
4. Area involved
5. Arrangement with the owner
6. Arrangement with the sub-contractor (agreement with sub-
contractor should be attached as an Annexure and should
necessarily require the adoption of good quarry management
practices – a description of the requirements should be
included)
7. Quantity of material to be withdrawn vis-à-vis the material
available
8. Machinery & equipment to be used
9. Drainage plans
10. Top soil management
11. Description of the operating practices
12. Health facilities
13. Safety provisions made including fire protection systems and
the availability of different personal protective equipment
such as helmets, ear plugs / muffs and face masks
14. Copy of the sub-contractor licences from PCB, Mining &
Geology, Police & Fire Dept.
15. Conditions laid down in the clearances / licences
16. Monitoring plans for air quality
17. Information on whether or not the quarry will be closed
under this project. If yes, the proposed closure & restoration
plan.
18. Sketch of the layout of the quarry
19. Photographs of the quarry before material sourcing for the
project
Attach Photograph of Proposed Site, Location Map, and Agreement with land owner

REMARKS

SUBMITTED CHECKED APPROVED


SIGNATURE ……………… SIGNATURE ………………….. SIGNATURE …………………
NAME …………………. NAME ……………………… NAME ……………………..
DESIGNATION …………..
CONTRACTOR CONSTRUCTION SUPERVISION EXECUTIVE ENGINEER
CONSULTANT

Page 4 of 5
Case III - If the quarry is a new one and is managed directly by the Contractor from whom the contractor is sourcing
the materials, the plan should contain the following:

Remarks by
Sr.
Item Unit Details SC/EO, if
No.
any
1. Name / identity of the location
2. Nearest project road chainage.
3. Name of the owner
4. Area involved Sqm
5. Existing land use (verification required from land records with
revenue department)
6. Land use of the area surrounding the proposed site including a map
7. Access roads – existing conditions, proposed development and
maintenance
8. Tree-cutting and vegetation clearance required, if any, along with No.s
compensation measures
9. Arrangement with the owner (Agreement should necessarily include
commitment of the contractor to adopt good quarry management
practices – a description of the requirements should be included -
and should indicate proposed restoration plans)
10. Quantity of material to be withdrawn vis-à-vis the material available Cum
11. Particular areas to be quarried should be clearly identified
12. Pre-establishment activities, e.g. purchase / lease of nearby
properties
13. Machinery & equipment to be used
14. Drainage plans
15. Top soil management
16. Description of the operating practices
17. Health facilities
18. Safety provisions made including fire protection systems and the
availability of different personal protective equipment such as
helmets, ear plugs / muffs and face masks
19. Monitoring plans for air quality
20. Copy of the sub-contractor licenses from PCB, Mining & Geology,
Police & Fire dept.
21. Conditions laid down in the clearances / licences
22. Information on whether or not the quarry will be closed under this
project. If yes, the proposed closure & restoration plan.
23. Sketch of the layout of the quarry
24. Concerns of the local people living in the immediate / near vicinity
should be identified and appropriates measures should be reflected
25. Tree-cutting required, if any, along with compensation measures
26. Photographs of the quarry before the project
Attach Photograph of Proposed Site, Location Map, and Agreement with land owner

REMARK

SUBMITTED CHECKED APPROVED


SIGNATURE …………… SIGNATURE ………………….. SIGNATURE
…………………
NAME …………………. NAME ……………………… NAME ………………..
DESIGNATION ………
CONTRACTOR CONSTRUCTION SUPERVISION CONSULTANT EXECUTIVE
ENGINEER

Page 5 of 5
APPENDIX 8.2: GUIDELINE FOR BORROW AREAS MANAGEMENT

Borrow areas will be finalized either form the list of locations recommended by DPR consultants or new areas identified
by contractor. The finalization of locations identified by DPR consultant or identified by contractor depends upon the
formal agreement between landowners and contractor and its suitability from civil engineering as well as environmental
consideration. Meeting the guidelines/notifications as stipulated from time to time by the Ministry of Environment and
Forests, Government of India, and local bodies, as applicable shall be the sole responsibility of the contractor.
Besides this certain precautions have to be taken to restrict unauthorized borrowing by the contractor. No borrow area
shall be opened without permission of the Engineer/EO. The engineer in addition to the established practices, rules and
regulation will also consider following criteria before approving the Borrow areas.
(1) The borrow area should not be located in cultivable land unless unavoidable i.e. no suitable uncultivable land in the
vicinity for borrowing or private landowners are willing to allow borrowing in their fields.
(2) Along the roadside, borrow pits should be located 5m away from the toe line.
(3) The loss of productive and agriculture soil should be minimum.
(4) The loss of vegetation is almost nil or minimum.
(5) Sufficient quality of soil is available.
(6) The Contractor will ensure that suitable earth is available.
After identification of borrow areas based on guidelines. Contractor will fill reporting format as under and submit the
same for approval to the “Engineer” Once approved the contractor will adhere to the recommendation for borrow area
to the satisfaction of Engineer.
(1) In no case the depth of borrow area should exceed 2m from the existing ground level.
(2) Borrow pits slope should be maintained, no steeper than 1 Vertical: 4 Horizontal.
(3) In case of cultivable land, top soil (15cm) should be preserved and stockpiled.
(4) Ridges of not less than 8m width should be left at intervals not exceeding 300m. Small drains to be cut through the
ridges to facilitate drainage
(5) Water pooling to be avoided/managed so that no disease spread due to water stagnation.
(6) Borrow pits should be located at least 1000m away from settlements.
(7) Precautionary measures as the covering of vehicles will be taken to avoid spillage during transportation of borrow
area.
(8) The unpaved surfaces used for the haulage of borrow materials should be maintained properly for dust
suppression.
(9) Haulage of material to embankments or other areas of fill shall proceed only when sufficient spreading and
compaction fascility is operating at the place of deposition, to minimize dust pollution.
(10) Borrow pits located near settlements will be re-developed immediately after borrowing is completed. If spoils are
dumped, that will be covered with a layers of stockpiled topsoil in accordance with compliance requirements with
respect MOEF/SPCB guidelines
(11) Redevelopment of the borrow areas to mitigate the impact will be the responsibility of the contractor. The
contractor shall evolve site-specific redevelopment plans for each borrow area locations, which shall be
implemented after the approval of the Engineer.
(12) Borrow area near to any surface water body will be at least at a distance of 15m from the toe of the bank or high
flood level, whichever is maximum.

Page 1 of 4
(13) During rains appropriate measures to be taken to minimize soil erosion, silt fencing to be provided as directed by
Engineer/EO.
(14) Borrow areas might be used for aquaculture in case landowner wants such development. In that case, such borrow
area will be photographed after their post use restoration and Environment Expert of Supervision Consultant will
certify the post use redevelopment.
The Contractor will keep record of photographs of various stages i.e., before using materials from the location (pre-
project), for the period borrowing activities (construction Phase) and after rehabilitation (post development), to
ascertain the pre and post borrowing status of the area.

Page 2 of 4
Format EM1: Reporting for Borrow Areas

(To be Submitted by Contractor for taking consent for opening of Borrow area)

Construction Stage Report: Date ____ Month________ Year_________


Site Layout of Borrow Area and Proposed Borrow Area Redevelopment Plan to be attached with format
Format to be submitted before target date as (decided by PIU) for establishing Borrow Areas
Borrow Area No. BA
Location of Borrow Area (Km______ Package ______)

Sl. Remarks by
Item Unit Details
No SC/EO, if any
1 Details of Borrow Area
a Date of Borrow Area becoming operational dd/mm/yy
b Current Landuse
c Distance from Nearest Settlement Km
d No of settlements within 200m of Haul Road No.
e No of settlements within 500m of Borrow Area No.
f Total Capacity cum
g No of Trees with girth more than 0.3 m No.
h Length of Haul Road km
i Width of Haul road m
j Type of Haul Road metal/dirt
k Size of Borrow Area sqkm
l Area of Borrow Area km x km
m Quantity Available cum
n Distance of Nearest Water Source Type/Size/Capacity/Present
Use/Ownership
o Quantity of top soil removed cum
p Detail of storage of topsoil
q Daily/occasional use of the Borrow Area by the -
community, if any
r Probable reuse of Borrow pit-ask community -
s Drainage channels/slope/characteristics of the area -
2 Enhancement Elements
a Quantity of top soil removed sq.m
b Detail of storage of topsoil sq.m
c Adjoining land use/Natural elements
d Near by catchment for storing water
e Erosion Control Programme
f Preventive measures for
i Leaching
ii Mosquito Breeding
iii Water run-off/contamination
iv Any other environmental degradation
3 Details of workforce
a Total No of Labourers No.
b Total no of Male Workers No.
c No of Male Workers below 18 years of age No.

Page 3 of 4
Sl. Remarks by
Item Unit Details
No SC/EO, if any
d Total No of Female Workers No.
e No of Female workers below 18 years of age No.
4 Details of redevelopment, Plan to be enclosed

Certified that the furnished information is correct the quality of work is as per good practice and all
relevant information as required is attached

Project Engineer
(Supervision Consultant) (Contractor)

Attach Photograph of Proposed Site, Location Map, and Agreement with land owner

REHABILITATION PLAN MEASURES


LOCATION 1: 4:
LOCATION 2: 5:
LOCATION 3: 6:

REMARKS

SUBMITTED CHECKED APPROVED

SIGNATURE ……………… SIGNATURE ………………….. SIGNATURE …………………

NAME …………………. NAME ……………………… NAME ……………………..

DESIGNATION …………..

CONTRACTOR CONSTRUCTION SUPERVISION EXECUTIVE ENGINEER


CONSULTANT

Page 4 of 4
APPENDIX 8.3: GUIDELINE FOR DEBRIS DISPOSAL SITES AND MANAGEMENT

The locations of Disposal sites have to be selected such that:


• Productive land to be avoided and available wasteland to be given preference.
• Disposal sites to be located at least 1000m away from sensitive locations like Settlements, Water body, notified
forest areas, Sanctuaries or any other sensitive locations.
• Should be located in the downwind side of nearest settlement locations.
• Disposal sites do not contaminate any water sources, rivers etc for this, site should be located away from water
body, disposal site should be lined properly to prevent infiltration of water.
• Public perception about the location of debris disposal site has to be obtained before finalizing the location.
• Permission from the Villager/local community is to be obtained in writing by contractor for finalising the disposal
site identified.
• The Plan must be approved by EO/Supervision Consultant and PIU- APRDC.
PRECAUTIONS TO BE ADOPTED DURING DISPOSAL OF DEBRIS / WASTE MATERIAL
The contractor shall take the following precautions while disposing off the waste material
• During the site clearance and disposal of debris, the contractor will take full care to ensure that public or private
properties are not damaged/affected, there is no dwellings below the dumpsite and that the traffic is not
interrupted.
• Contractor will dispose off debris only to the identified places or at other places only with prior permission of
Engineer/EO.
• In the event of any spoil or debris from the sites being deposited on any adjacent land, the contractor will
immediately remove all such spoil debris and restore the affected area to its original state to the satisfaction of the
Engineer/EO.
• The contractor will at all times ensure that the entire existing drains within and adjacent to the site are kept safe and
free from any debris.
• Contractor will utilize effective water sprays during the delivery and handling of materials when dust is likely to be
created and to dampen stored materials during dry and windy weather.
• Materials having the potential to produce dust will not the loaded to a level higher than the side and tail boards and
will be covered with a tarpaulin in good condition.
• Care should always be taken to maintain the hydrological flow in the area.
REHABILITATION OF DISPOSAL SITES
The dumpsites filled only upto the ground level could be rehabilitated as per guidelines below and to be decided by the
engineer and the supervision consultant
• The dumpsites have to be suitably rehabilitated by planting local species of shrubs and other plants. Local species
of trees has also to be planted so that the landscape is coherent and is in harmony with its various components.
• In cases where a dumpsite is near to the local village community settlements, it could be converted into a play field
by spreading the dump material evenly on the ground. Such playground could be made coherent with the
landscape by planting trees all along the periphery of the playground.
• Material excavated for foundation of bridge works should not be dumped in the water course; if same has to be
refilled then precaution has to be taken so that the excavated material should not be carried away by flowing/rainy
water, thereby silting the water course.
• Care should always be taken to maintain the hydrological flow in the area.

Page 1 of 2
Format EM1: Selection of dump site locations
From ________ To _____
(Give chainage and nearest settlements from both ends)

Criteria on which information for each site is to be collected Site 1 Site 2 Site 3 Site 4
Area covered (m2)
Total Material that can be dumped within the site (m3)
Depth to which dumping is feasible (m)
Distance of nearest watercourse (m)
Nearest Settlement (m)
Date/s of Community Consultation/s
Whether the community is agreeable to siting of dumping site (Y/N)
Date of Permission from Village Council President(VCP)
Proposed future use of the Site

Selected Site (tick any one column only)


Certified that the above information is correct to the best of my knowledge and belief.

(Contractor)
Verified: Date:

Recommendation on the suitability of the site

Signed: Date:

Name & Designation:

Decision Taken (tick one): Approved/Not Approved

Signed: Date:

Name and Designation of Deciding Authority

Enclosures
(Tick as appropriate)
1 Maps of each location
2 Photographs
a Each dumping location
b Each community consultation
3 Photocopies of permissions from VCPs

Name and Designation of Verifier:

Page 2 of 2
APPENDIX 8.4: GUIDELINES FOR SITE CLEARANCE AND TREE FELLING

1. VEGETATION CLEARANCE
Vegetation clearance shall comprise uprooting of vegetation, grass, brushwood, shrubs, stumps, trees and
saplings of girth upto 30 cm. measured at a height of one meter above the ground level. Where only clearance
of grass is involved it shall be measured and paid for separately. The procedure/ steps involved for uprooting,
skating and felling trees are described below.
1.1 Uprooting of Vegetation
• The roots of trees and saplings shall be removed to a depth of 60 cm. Below ground level or 30 cm. below
formation level or 15 cm below sub grade level, whichever is lower.
• All holes or hollows formed due to removal of roots shall be filled up with earth rammed and levelled.
• Trees, shrubs, poles, fences, signs, monuments, pipe lines, cables etc. within or adjacent to the area, which
are not required to be disturbed during vegetation clearance shall be properly protected by the contractor
at his own cost.
Staking and Disposal
• All useful materials obtained from clearing and grubbing operation shall be staked in the manner as
directed by the Engineer.
• Trunks and branches of trees shall be cleared of limbs and tops stacked properly at the places indicated by
the Engineer- in – charge. These materials shall be the property of the Government.
• All unserviceable materials are disposed off in such a manner that there is no livelihood of getting mixed
up with the materials meant for construction.
Felling Trees
• Marking of tress: Trees, above 30 cm. Girth (measured at a height of one meter above ground level) to be
cut, shall be approved by the Engineer-in-charge and then marked at the site.
• Felling of trees: Felling of trees shall include taking out roots up to 60 cm. below ground level or 30 cm.
below formation level or 15 cm. below sub-grade level, whichever is lower.
• Filling: All excavations below general ground level arising out of removal of trees, stumps etc. shall be
filled with suitable material in 20 cm. layers and compacted thoroughly so that the surface at these points
conform to the surrounding area.
• Sizing: The trunks and branches of trees shall be cleared of limbs and tops and cut into suitable pieces as
directed by the Engineer-in-charge.
• Staking: The serviceable materials shall be staked in the manner as directed by the Environmental specialist
of Supervision Consultants/Engineer-in-charge.
• Disposal: The material, which cannot be used or auctioned shall be removed from the area and disposed
off as per the directions of the Engineer-in-charge. Unsuitable waste materials should not get mixed with
construction material during disposal.
Format EM4: Tree Felling
Physical Target Completion Target
S.
Links Target % of task Target Date of Completion Reason for
No Total Target
Achieved completed Date if task completed Delay if any
Unit
1 nos
2 nos
3 nos
4 nos

(Signed)

Assistant Conservator of Forests

Page 1 of 1
APPENDIX 8.5: GUIDELINE FOR SITING & LAYOUT OF CONSTRUCTION CAMP

(A) SITING
The contractor based on the following guidelines shall identify the location of the construction site. The
construction site shall be located:
• The construction camps will be located at least 1000m away from major settlements in downwind
direction. The living accommodation and ancillary facilities for labour shall be erected and maintained to
standards and scales approved by the resident engineer.
• A minimum 500m away from surface water course or body.
• A minimum 1000m away from Wild life Sanctuary/Ecologically sensitive areas.
• Should not be located in cultivable land unless unavoidable.
• All sites used for camps must be adequately drained.
• The camps must be located such that the drainage from and through the camps will not endanger any
domestic or public water supply.
• All sites must be graded, ditched and rendered free from depressions such that water may get stagnant and
become a nuisance.

(B) LAYOUT
A conceptual layout of a typical construction site has been presented in Figure below. The Contractor during
the progress of work will provide, erect and maintain necessary (temporary) living accommodation and
ancillary facilities for labour to standards and scales approved by the engineer. All temporary accommodation
must be constructed and maintained in such a fashion that uncontaminated water is available for drinking,
cooking and washing. Safe drinking water should be provided to the dwellers of the construction camps.
Adequate washing and bathing places shall be provided, and kept in clean and drained condition. Construction
camps are to be sited away from vulnerable people and adequate health care is to be provided for the work
force.
Sanitation Facilities: Construction camps shall be provided sanitary latrines and urinals. Sewerage drains
should be provided for the flow of used water outside the camp. Drains and ditches should be treated with
bleaching powder on a regular basis. The sewage system for the camp must be properly designed, built and
operated so that no health hazard occurs and no pollution to the air, ground or adjacent watercourses takes
place. Compliance with the relevant legislation must be strictly adhered to. Garbage bins must be provided in
the camp and regularly emptied and the garbage disposed off in a hygienic manner
Shelter at Workplace: At every workplace, there shall be provided free of cost, four suitable shelters, two for
meals and two others for rest, separately for use of men and women labourers. The height of shelter shall not
be less than 3m from floor level to lowest part of the roof. Sheds shall be kept clean and the space provided
shall be on the basis of at least 0.5m2 per head.
Canteen Facilities: A cooked food canteen on a moderate scale shall be provided for the benefit of workers
wherever it is considered necessary. The contractor shall conform generally to sanitary requirements of local
medical, health and municipal authorities and at all times adopt such precautions as may be necessary to
prevent soil pollution of the site.
First aid facilities: At every workplace, a readily available first-aid unit including an adequate supply of
sterilized dressing materials and appliances will be provided. Workplaces remote and far away from regular
hospitals will have indoor health units with two bed fascility. Suitable transport will be provided to facilitate
taking injured and ill persons to the nearest hospital. At construction camp an ambulance room containing the
prescribed equipment and nursing staff will be provided.
Health Care Facilities: Health problems of the workers should be taken care of by providing basic health
care facilities through health centres temporarily set up for the construction camp. The health centre should
have at least a doctor, nurses, duty staff, medicines and minimum medical facilities to tackle first-aid
requirements or minor accidental cases, linkage with nearest higher order hospital to refer patients of major
illnesses or critical cases.
The health centre should have MCW (Mother and Child Welfare) units for treating mothers and children in
the camp. Apart from this, the health centre should provide with regular vaccinations required for children.

Page 1 of 3
Day Crèche Facilities: At every construction site, provision of a day crèche shall be worked out so as to
enable women to leave behind their children. At construction sites where 20 or more women are ordinarily
employed, there shall be provided at least a hut for use of children under the age of 6 years belonging to such
women. Huts shall not be constructed to a standard lower than that of thatched roof, mud walls and floor with
wooden planks spread over mud floor and covered with matting. Huts shall be provided with suitable and
sufficient openings for light and ventilation. There shall be adequate provision of sweepers to keep the places
clean. There shall be two maidservants (or aayas) in the satisfaction of local medical, health, municipal or
cantonment authorities. Where the number of women workers is more than 25 but less than 50, the contractor
shall provide with at least one hut and one maidservant to look after the children of women workers. Size of
crèches shall vary according to the number of women workers employed.

Page 2 of 3
Figure-1: Typical Layout of Construction Camp

Page 3 of 3
APPENDIX 8.6: WORKERS SAFETY DURING CONSTRUCTION ACTIVITIES

SAFE LAYOUT IN THE CONSTRUCTION PLANT, CAMP AND QUARRY AREAS


1. Arrange border to perimeter fencing
2. Ensure good visibility and safe access at site entrances
3. Provide adequate warning signs at the entrance and exit where necessary
4. Provide adequate space/area for loading and unloading, storage of materials, plant and machinery
5. Display emergency procedure and statutory notices at conspicuous location
6. Consider welfare facilities required
7. Provide areas for dumping garbage and other waste materials, and also arrange for their regular clearance.
8. Arrange storage, transport and use of fuel, other flammable materials and explosives in line with the license
requirements to be obtained from appropriate authorities
9. Plan emergency assembly points, fire escape routes and locate fire-fighting equipment
10. Provide access roads and plant movement areas within the site.
11. Ensure the availability of first aid facilities and display notices at the various works to show the location of these
facilities
12. Provide proper drainage and sewage & drainage facilities
HOUSE KEEPING PRACTICES
1. Maintain washrooms and canteens clean
2. Keep all walkways clear and unobstructed at all times
3. Ensure that spillages of oil and greasy
4. Stack raw materials and finished products clear of walkways or inside roads
5. Do not leave tools on the floor or in any location where they can be easily dislodged
6. Keep windows and light fitting clean
7. Maintain the workplace floors dry and in a non-slippery condition
8. Provide and maintain proper drainage system to prevent water ponding
9. Use metal bins for oily and greasy rags and store all flammable materials in appropriate bins, racks or cabinets.
Ensure that the meal bins for storing oily and grease rags should be covered with lids.
10. Ensure that protruding nails in boards or walls are moved or bent over so that they do not constitute a hazard to
people
11. Make sure that hazardous/dangerous chemicals are kept in the goods stores with the appropriate labeling, display
of the material-safety-data-sheet (MSDS) and other precautionary measures
12. Display ‘no smoking’ signs in areas with high fire risks, e.g. paint stores, wood working area and others
TREE FELLING
• Use hard hats during tree felling
• Ensure tools such as the axes are in good condition
• Determine proper foot and body position when using the axe. Do not cut above your head
• Wear appropriate foot protection
• Carry a first aid kit to the site
• Determine possible hazards in the area, e.g. electrical or telephone or other utility lines
• Prior to felling, determine the safest direction for the fall
• Determine the proper hinge size before directing the tree fall.

Page 1 of 11
NOISE HAZARDS AND ITS CONTROL
1. Note that indications of noise levels are:
• You have to shout to be heard;
• Your hearing is dulled just after work;
• You get head noises or ringing in the ears after work;
• You have difficulty hearing people while others are talking
2. Use sound level meters to measure. If the sound level exceeds 85 dB(A), then preventive measures should be taken
3. Make personnel aware of noisy areas by using suitable warning signs and insisting that ear protectors should
necessarily be worn.
4. Reduce noise at source by improved maintenance, replacing noisy machines, screening with noise absorbing
material, making changes to the process/equipment, controlling machine speeds, ensuring that two noise-
generating machines are not running at the same time, using cutting oils and hydraulic breakers.
5. Appoint a competent person to carryout a detailed noise assessment of the site, designate ear protection zone, and
give instructions on the necessary precautionary measures to be observed by site personnel, including the use of
suitable type of ear protections.
6. Wear and maintain ear muffs and ear plugs as required
7. In construction or repair work, noise should be kept to a low-level bearing in mind the disturbance to local
residents.
ROAD WORKS
1. The use of signage is most important to caution the road users of possible unsafe conditions due to the road works.
2. Use the appropriate signage devices as required by the site conditions/situation. The devices include regulatory
signs, delineators, barricades, cones, pavement markings, lanterns and traffic control lights.
3. In using signs, make sure that they are (i) simple, easy-to-understand and convey only one message, (ii) luminescent
and with reflective properties, and )iii) broad, prominent and of appropriate size.
4. In using barricades, make sure that you keep traffic away from work areas and you guide the drivers to keep along a
safe, alternative path.
5. Ensure that proper personal protective equipment (PPE) is provided to all the workers.
6. Cover existing road signs and install new ones at appropriate locations taking into account the distances that would
be required and reaction times.
7. Plan layout and traffic management so that hazard are not created.
8. Deploy flagmen, who control traffic at the work areas. The flag should be 600mm x 600mm fastened to a 1m
length staff.
9. Flagmen should wear reflective safety vests along with hard hats
10. If required, use wireless devices for flagmen to co-ordinate from either ends of the road, where works are being
carried out.
ELECTRICAL HAZARDS IN CONSTRUCTION AREAS
1. Treat all wires as live wires
2. Never touch dangling wires, but report them to your manager
3. Unless you are a qualified electrician, do not attempt electrical repairs
4. Never use electrical equipment if you hands are wet or you are standing in water
5. If electrical equipment is sparking or smoking, turn the power off and report the condition to your supervisor
6. Never use electrical wires that have physical damage
7. Never allow equipment or traffic to run over electrical wires.

Page 2 of 11
USE AND STORAGE OF GAS/LPG
1. Store filled gas/LPG cylinder in the open area, i.e. outside of the building
2. Transport, store, use and secure cylinders in upright position
3. Ensure proper ventilation at the ground level in locations where gas/LPG is in use
4. Avoid physical damage to the cylinders
5. Never weld or cut on or near the cylinders
6. Store empty cylinders secured and upright
7. Make sure that the cylinder is closed immediately after use
8. Investigate immediately if there is the smell of LPG or gas
9. Never use destenched gas/LPG on site.
10. Make sure that there is no other unrelated fire in the vicinity of the cylinder
OPERATION OF EXCAVATORS
1. Ensure that excavators are operated by authorized persons who have been adequately trained.
2. Prevent unauthorized movement or use of the excavators
3. Check regularly and maintain the machine thoroughly
4. Ensure that all relevant information, including those related to instruction, training, supervision and safe system of
work are provided to the operators.
5. Ensure that the operation and maintenance manuals, manufacturer’s specifications, inspection and maintenance log
books are provided for the use of the mechanics, service engineers or other safety personnel during periodic
maintenance, inspection and examination.
6. During tipping or running alongside the trenches, excavators must be provided with stop blocks.
7. Excavators must be rested on firm ground during operation
8. Avoid operating the machine too close to an overhang, deep ditch or hope and be alter to potential carving edges,
falling rocks and slides, rough terrain and obstacles.
9. Locate and identify underground services by checking with all utility companies before excavations.
10. Ensure that all excavations are supervised by experienced and competent persons.
11. When reversing or in caste the operator’s view is restricted, adequate supervision and signaling should be provided.
12. Ensure that the type and capacity of the excavator are properly chosen for the intended purposes and site
conditions. Never use a machine for any purposes other than it is designed for.
13. Check and report for excessive wear and any breakage of the bucket, blade, edge, tooth and other working tools of
the excavator.
14. Check that all linkages/hinges are properly lubricated and ensure that the linkage pins are secured. Never use
improper linkage pins.
15. Never dismount or mount a moving machine
16. Work only with adequate ventilation and lighting
17. Ensure that the protective front screen of the driving cabin is fixed in position during excavations to avoid eye
injury to the operator.
18. Ensure switch-off of the unattended vehicle.
OPERATION OF TRUCKS AND DUMPERS
1. Ensure that only trained, authorized and licensed drivers operate the vehicles
2. Enlist the help of another worker before reversing the vehicle
3. Switch-off the engine of an unattended vehicle
4. Lower the tipping bodies when the machine is unattended, but if it is necessary to leave them in the raised position
they should be blocked to prevent their fall.

Page 3 of 11
5. Wear safety boots or shoes to avoid injuries during loading and unloading.
6. Carryout periodic servicing to the manufacturer’s requirements. All records of maintenance and repairs should be
in writing or kept on site.
7. Keep the vehicle tidy and the cabin free from tools and material, which might obstruct the controls.
8. Keep to speed limits.
9. No passenger should be carried on a dumper except the driver
10. Never drive the vehicle across a slope
11. Provide stop blocks when the vehicle is tipping into or running alongside excavations
12. Do not overload the vehicle.
13. Carry only well secured loads
14. Park only on level ground, in neutral with the parking brake applied
15. Never mount of dismount from a moving vehicle
GAS WELDING
1. Use the following personal protective equipment during welding
• Face or hand shield fitted with filters
• Goggles, particularly when chipping slag
• Gloves long enough to protect wrists and forearms against heats, sparks, molten metal and radiation
• High-top boots to prevent sparks from entering footwear.
2. Screen of the work area with sturdy opaque or translucent materials because glare can cause eye injury.
3. Key for opening the acetylene cylinder valve must be one the valve stem while the cylinder is in use so that the
cylinder valve may be immediately shut-off in an emergency.
4. Ventilate the workplace using air blowers and exhaust fans to remove poisonous fumes and gases that are given off
during welding
5. Take precautions against flying sparks and hot slag where welding is beign done near flammable materials and
check the area before leaving.
6. Do not weld material degreased with solvents until completely dry.
7. Do not use gas cylinders for supporting work or as rollers
8. Do not use oil grease on oxygen cylinder fittings
9. Do not use cylinders with damaged valves.
10. Do not use too much force if valves are stuck.
11. Replace valve caps after use
12. Search for leaks in equipment by using a solution of soapy water.
13. Shut the cylinder valve if acetylene from a cylinder catches fire at the valve or regulator due to leakage at a
connection.
14. Treat all gas cylinders as “full” unless you are sure otherwise.
15. Never attempt to transfer acetylene from one cylinder to another or attempt to refill an acetylene cylinder.
16. Place portable fire extinguishers near the welding area
17. Secure all cylinders against accidental displacement.
18. Always lift gas cylinders. Do not slide them along the ground or drop them from trucks.
19. Keep gas cylinders in vertical position both in storage and when in use
20. Keep the work place dry, secure, free from combustible materials and obstruction.
21. Store the acetylene and oxygen cylinders separately, and in a proper store.
22. Keep the gas cylinders from source of heat, flammable materials, corrosive chemicals and fumes.

Page 4 of 11
MANUAL HANDLING AND LIFTING
1. Use mechanical equipment in lace of manual handling as far as possible.
2. Assess the manpower required to handle or life the load safety and arrange the manpower accordingly.
3. In handling hazardous materials, the workers shall be informed of the hazards and safety precautions.
4. All relevant persons shall be trained in the proper methods of lifting and carrying.
5. Where team work is required, select the persons whose ages and physical builds are compatible for teaming up.
Coordinate the actions of the team members by giving necessary instructions.
6. Always lighten or suitably shape the load for manual handling as far as possible Keep a look out for splinters, sharp
edges, loose banding and nails.
7. Clear path or obstruction and tripping hazards.
8. Stack and secure goods safety on trucks, otherwise they fall off and injure passers-by.
9. Use personal protective equipment such as gloves, safety shoes, etc.
10. Adopt the following procedure when you lift a load:
11. Stand close to the object. Have a firm footing with feet spread on either side of the road.
12. Bend the knees and keep your back as straight as you can
13. Grasp object firmly. Be sure grip will not slip
14. Breath in and throw the shoulder back wards.
15. Straighten the legs, continuing to keep the back as straight as you can.
16. Hold object firmly close to the body
17. Always lift smoothly. Avoid jerky motions. Turn with feet instead of twisting the back.
HANDLING CHEMICALS AND HAZARDOUS SUBSTANCES
1. Always substitute hazardous chemicals with harmless or less hazardous ones wherever possible.
2. Enclose the process using chemicals or provide other engineering controls such as local exhaust ventilation, a fume
cupboard or a safety cabinet.
3. Exercise great care in the storage and use of chemicals because they may be explosive, poisonous, corrosive or
combustible.
4. Separate different chemicals physically
5. Store chemicals classified as dangerous goods in a properly constructed and approved goods store. Keep proper
records of all chemicals and hazardous substances delivered, stored and used on site.
6. Consider unknown substances and liquids as dangerous until proven otherwise.
7. All containers should be clearly labeled to indicate contents. Never use a wrongly labeled container for chemicals.
8. Prohibit smoking in the vicinity of dangerous chemicals
9. Ensure that you are wearing the correct personal protective equipment before you handle chemicals
10. Maintain the Material Safety Data Sheet of all chemicals for reference on safety precautions to be taken and the use
of suitable PPE.
11. When opening containers, hold a rag over the cap or lid, as some volatile liquids tend to spurt up when released.
12. Wash before you eat and do not eat at the work place.
13. If the skin is splashed with a chemical, rinse it immediately with plenty of clean water. Eye should be flushed
thoroughly with water followed by immediate medical attention.
14. Eye fountain, emergency shower and breathing apparatus should be available in the vicinity of the workplace.
15. Safety instructions for handling emergency situations should be displayed prominently at both the storage and use
locations.
FIRST AID
1. Provide first aid boxes at every site

Page 5 of 11
2. Ensure that training on the use of the first aid box is provided to a handful of staff working in the site.
3. Display the list of persons who are trained on providing first aid.
4. Ensure that every first aid box is marked plainly “First Aid” in English and local language.
5. The responsible person or first aider should replenish the contents of the first aid box as necessary.
PERSONAL PROTECTIVE EQUIPMENT
General
1. Consider the provision of personal protective equipment only after all measures for removing or controlling safety
hazards have been provided reasonably impractical.
2. Ensure that sufficient personal protective equipment are provided and that they are readily available for every
person who may need to use them.
3. The management should ensure that all persons make full and proper use of the personal protective equipment
provided.
4. Provide instruction and training in the proper use and care of any specific protective equipment where necessary
5. Do not willfully misuse, interfere with or ill-treat any protective clothing and equipment provided.
6. Ensure that the personal protective equipment are in good condition. Report immediately any damage to the
management for replacement. Always keep the personal protective equipment as clean as possible.
Eye protection
1. Issue eye protection equipment where there is a foreseeable risk of eye injury
2. Ensure an adequate supply of goggles/shields is available.
3. Keep the goggles clean and make sure they are good fit.
4. Do not watch welding operations unless your eyes are protected from the damaging effect of flash.
Head Protection
1. No person shall enter a construction site unless he is wearing a suitable safety helmet
2. Wear a safety helmet:
• When there is the risk of being hit by falling objects
• While on or near a construction site
• During adverse weather conditions
• When in any area designated as a “hard hat” area.
3. Provide identification labels to all helmets in some way to prevent random exchange among wearers, with one
helmet exclusive to each person.
4. Inspect helmets for cracks of sign of impact or rough treatment before each usage. Destroy, remove and replace all
worn, defective or damaged helmets.
Hearing Protection
1. Provide ear plugs or ear muffs as required. Use re-usable ear plugs when the reduction required (15-25 dBA) is not
excessive. Use ear muffs where a large attenuation of upto 40 dBA is demanded.
2. Do not use dry cotton wool for hearing protection because it cannot provide any.
3. Provide disposable ear plugs for infrequent visitors and ensure that they are never re-used.
4. Provide re-usable ear plugs for those who need to work continuously for a long period in a high noise area.
5. Use ear muffs with replaceable ear cushions because they deteriorate with age or may be damaged in use.
6. Avoid wearing spectacles with ear muffs.
7. Use soap and water or the recommended solvent for cleaning ear muffs.
8. Provide ear muffs for those who may need to get in and out of a high noise area frequently.

Page 6 of 11
RESPIRATORY PROTECTIVE EQUIPMENT
1. Wear suitable respirable for protection when there is a potential for small particles entering the lungs, e.g. emptying
of cement bags.
2. Ensure that he explanators can provide adequate protection.
3. Provide training to all persons using the respirators for their correct fitting, use, limitations and symptoms of
exposure.
4. Clean and inspect all respirators before and after use.
5. Store respirators properly when not in use.
Safety Footwear
1. Wear suitable footwear for work
2. Use safety footwear on site or in other dangerous areas
3. Wear suitable safety shoes or ankle boots when working anywhere where there is high risk of foot injuries from
slippery or uneven ground, sharp objects, falling objects, etc.
4. All safety footwear, including safety shoes, ankle boots and rubber boots, should be fitted with steel toecaps.
5. Avoid wearing flip flops, high heeled shoes, slippers, light sport shoes in situations where there is a risk of foot
injury.
6. Keep shoe lace knots tight.
Hand Protection
1. Wear suitable gloves for selected activities such as welding & cutting and manual handling of materials &
equipment.
2. Do not wear gloves where there is a risk of them becoming entangled in moving parts of machinery
3. wash hands properly with disinfectant soap and clean water before drinking, eating or smoking. Wash hands
immediately after each operation on site when the situation warrants.
FIRE PREVENTION, FIGHTING AND EQUIPMENT
Before fire breaks cut
1. Store flammable material in proper areas having adequate fire protection systems.
2. Display sufficient warning signs.
3. Train selected personnel to use these fire extinguishers
4. Inspect fire extinguishers regularly and replace as necessary
5. Fire escape route should be kept clear at all times and clearly indicated.
6. Know the escape route and assembly point.
7. Display escape route maps prominently on each floor
8. Carryout fire drill regularly. Designate fire officers
9. Install fire alarm wherever required and test regularly.
10. Provide sufficient exit signs at prominent locations for directing people to the escape staircases and routes.
When fire breaks out.
1. Alert all persons
2. Put off the fire with appropriate fire extinguishers only when you are sure that you are safe to do so.
3. Escape if you are in danger through the fire escape route to assembly point
4. Fire officers to carryout head count at the assembly point.
Incident and accident investigations
1. Carryout the investigation as quickly as possible.
2. Conduct interviews with as many witnesses as necessary

Page 7 of 11
3. Do not rely on any one sole source of evidence
4. Use the following tools:
Checklists for obtaining basic and typical information for accidents
• Notebook
• Tape records
• Camera
• Measuring tape
• Special equipment for the particular investigation
5. Obtain answers to the following questions:
• When did the accident occur?
• Where did it occur?
• Who was injured and what was damaged?
• What caused the accident?
• Why did it occur?
• How could it have been prevented?
• How can a recurrence be prevented?
6. Prepare a short but sufficient investigation report that contains the following:
• A summary of what had happened
• A summary of events prior to the accident
• Information gathered during the investigation
• Details of witnesses
• Information on injury or loss sustained
• Conclusions and possible causes of the accident
• Recommendations to prevent recurrence
• Supporting materials (photos, diagrams, etc.)
WORKERS SAFETY DURING CONSTRUCTION
Sl Stage and Nature of Construction Hazard Safety measures expected to be taken by the Contractors
No. and Site Engineers
1 Excavation in soft loose & slushy soil above The Excavation beyond 1.5 m to 2.00 m to be done in steps of
2.00 m depth sliding of earth or collapsing of minimum 500 mm offsets as shown in Clause 2.18.2(b) and
sides. also planking and strutting should be done as in Clause 2.19.1.
2 Excavation in slippery area (water logged) – Try to dewater the area and spread minimum 150 mm thick
The labour may fall or machinery on site may sand layer to avoid slipping
slip.
3 Excavation in Rock where chiseling is For hammer work, only experienced and skilled labour should
involved – The fall of hammer may injure the be employed. Chisel should not be allowed to be held by hand,
hand, small rock pieces may injure the eyes while hammering but chisel holding clamp should be provided.
and legs. The labour should be provided with goggles and leg cover to
protect eyes and legs, from injuries due to small rock pieces.
4 Excavation in Rock where blasting is The work of blasting should be entrusted to only experienced
involved - Careless handling may lead to persons. Provide sufficient length of fuse to give ample margin
injury to main worker or a passer by. of time from the time of lighting to the time of explosion. A
danger zone at least 180m diameter is to be flagged off 10
minutes before actual firing. All workmen should be sent away
from danger zone except the firing man, who should be pro-

Page 8 of 11
Sl Stage and Nature of Construction Hazard Safety measures expected to be taken by the Contractors
No. and Site Engineers
vided with a whistle.
5 Excavation for drain across road or manhole The area should be well barricaded & a red lamp provided at
adjacent to a road – chances of a passer by night. A watchman should be deputed to prevent any move-
falling into the excavated portion ment of persons, or vehicles.
6 During Excavation or some times even while In places where the movement of snakes are more the con-
concreting – Snake bites or Scorpion stings – tractor should provide the labour with gum boots, gloves etc.
and also make snake antidotes available on site. A particular
care that has to be taken on such site is to always keep a
vehicle available on site to rush the patient to a doctor. This
applies to snake stinged patients as well.
7 Centring (form-work) and scaffolding – Many a times ballies joined together give way due to weak
Form-work collapse while concreting or just joint. Hence the use of joined ballies should be restricted. Only
before concreting especially when wooden 2 joined ballies out of 8 ballies should be allowed. In case of
ballies are used. double staging for a Slab at a height, utmost care should be
taken to see that the top balli rests on the bottom balli. A
particular care that should be taken during each concreting
operating of slabs and beams is that, one carpenter and two
helpers with spare ballies, nails etc. should be deputed below
the slab/beam that is being concreted to watch any distur-
bance in the supports of the form-work below during concret-
ing and in case of any doubt the concreting should be stopped
immediately and the form work strengthened. Never allow
bricks below a balli to make up the required height. This is
most dangerous.
8 Form-work for beams and slabs: The bottom This case is noticed when slender ballies are used without
of beam collapses and many a times brings bracing. In fact, no concreting should be allowed without
down the slab as well, injuring the labour and bracing at 300 mm above ground, and at mid way, in normal
supervision staff. beams & slabs. The bracings should be for the support of
beams as well as slabs.
9 Form-work for sides of a slab–The labour This is noticed when the carpenter fixes the side shuttering of
just rests his foot on the plank and looses a slab with a plank just tied by binding wire to the steel
balance and falls resulting a fatal accident. reinforcements and by wooden pieces nailed in wall and plank.
This is so weak a portion that with little pressure the plank
gives way.
Hence side shuttering should be done with a direct balli
support from ground or floor, and the practice of tying planks
with binding wire to the steel reinforcement should be totally
avoided. A temporary railing along the periphery of slab will
guard the life of labour and supervision staff.
10 Form-work for beams and slabs–Opening In fact, this is a most dangerous work. One should be very
the form- work–Accident due to fall of careful while form-work is removed. Only trained carpenters
materials during removing the forms. should be deputed for the work. A safe resting place outside
the area of slab as a temporary measure should be constructed
from where the Slab can be removed safely. Removal of form-
work during night should not be permitted under any
circumstances.
11 Scaffolding–Fall of work-man, Supervision This is a very common negligence on the part of labour who
Staff, Standing on Chalis not tied properly or do scaffolding work. The Chalis on which they work either
tied only at one end. span over it's complete length or is tied loosely and many a
(Chalis mainly made of Bamboos). times at one end only. Hence, care must be taken that the
Chali do not span over the full length but some middle
support should be provided and also the same is tied properly
on both ends.
12 Ladders–Balli or bamboo ladders – The The ladders should be strong enough to bear the weight of a
horizontal member breaks and the person labour with materials on head. As far as possible a hand rail

Page 9 of 11
Sl Stage and Nature of Construction Hazard Safety measures expected to be taken by the Contractors
No. and Site Engineers
falls. Some times the top face just rests on should be provided at one end. The horizontal member should
wall and the whole ladder tilts causing an be preferably fixed with. bolt & nuts or strong nails. When the
accident. ladder is placed across a wall the top portion should be tied
firmly to a strong support so that the ladder does not move
laterally.
13 Column Reinforcements–Column The tendency of bar-benders is to tie the vertical steel with
reinforcements mainly in independent coir rope or 8 mm steel rods as ties on all four sides of the
footings collapses – Injury to persons column reinforcement. This method of supporting the column
working nearby. reinforcements results in a weak support. Hence, the column
reinforcements should be supported by strong ballies on all
four sides of reinforcements and as far as possible a combined
platform should be constructed out of ballies over which the
reinforcements can be supported.
14 Concreting chajjas – When chajjas are While concreting chajjas care must be taken that the labour do
concreted with out care and on opening the not stand on the reinforcement and disturb the position.
form-work the chajja would collapse, causing Separate scaffolding must be tied over which the labour can
injury to labour on top or bottom of chajja. stand and work without disturbing the reinforcements. The
main reason is in chajja the steel is placed on top face but if
the labour stands on the steel, it will bend and come to bottom
face and hence the chajja will fall when form-work is removed,
thus, causing injury to labour working on top, or bottom.
15 Dismantling–Dismantled materials may fall When work of demolition is to be taken up the area should be
on passer by or the person engaged in closed for all outsiders. No one should be allowed up to 50 m.
dismantling work may fall due to slipping. from the place of demolition. The workers engaged in
The dismantled materials may fall on persons demolition should be asked to wear safety belts. Helmets must
working below. be worn by all the workers engaged in dismantling work. The
place should be strictly guarded at night with red lights at
prominent places, and watchman should be posted.
16 Electric-Connections/Cables etc. –High The work in such places, should not be allowed to the workers
tension/L.T. Electric wire passing near the themselves, but in such position the work must be executed
slab structure- while bending, lifting or tying under the strict supervision of a responsible Foreman or a
reinforcements the bar benders may sustain Supervisor.
the Electric Shock, causing fatal injury.

17 Electric Connections/Cables etc. –Cables Before taking up the work all available drawings should be
below ground may get punctured during studied, local enquiry to be made to know the position of
excavation & thus electrocute the labour cables and work in such area should be got executed under
working. Similarly when concreting is in strict supervision of an experienced Foreman or a Supervisor.
progress the punctured cable may prone to
be fatal to the labour.
18 Electric Connections/Cables etc. – The Electric wires should be maintained by an electrician who
Temporary Electric lines near damp walls, should regularly check up the insulation of wires especially
near joinery stretched on a considerable placed near steel items & damp areas.
length – There is every chance that the wire
The temporary wiring should be supported properly.
may get cut due to usage and may develop
short circuits/leakages etc. and may As far as possible a good quality wire should be used which
electrocute the person touching the wire may not get damaged easily.
accidentally.
19 Electric and gas welding work – Drilling, All wiring works to be inspected by experienced electrician. All
polishing work – Done by temporary cables wires to be properly insulated and fixed at height on temporary
used on a number of works – Due to the fact poles. No welding work should be permitted near damp area.
that the wires are old & when they come in The welders to be provided with welder's goggles & gloves. As
contact with water even in the process of far as possible machine in good condition should be used.
curing the surrounding area may get affected
due to leakage in the electric current thus
causing damage to the workers & supervision

Page 10 of 11
Sl Stage and Nature of Construction Hazard Safety measures expected to be taken by the Contractors
No. and Site Engineers
staff.
20 Construction Machinery & Lifts – Concrete The Mixers with hopper should be operated by an experienced
Mixers – Safety precautions. A mixer with mixer operator and such mixers should not be allowed to be
hopper tried to be operated by an helper handled by a helper or a labour.
could not release brake in time thus causing
injury to the person near hopper- some times
fatal one.
21 Construction Machinery & Lifts - Lifts - (1) A brick protection wall of minimum 1.00 m height should
Safety precautions. be constructed around the Lift Pit, thus, preventing the
children going near the pit. A special care should be taken to
(1) The lift pit if left unguarded the children
see that the children are not allowed to come near the
of workers may fall in the pit resulting in fatal
machinery.
accident
(2) The manually operated brakes of the lift (2) The condition of the lift must be maintained properly. The
failed or the communication between lift operator should be well trained. The labour receiving the
the labour at the top and the liftman bucket at top should be smart and active enough to convey the
failed and thus, the lift was not message of stopping & releasing the lift-to-lift operator
controlled and resulted in fatal accident. properly.
22 Water Storage Tank for general use & curing The water tanks constructed on site should be protected by at
- chances of children of workers falling in the least 1.00 m high walls on four sides, so that the children do
tank with fatal accident. not fall.
23 Misuse of lift by labour and some times No person should be allowed to go to upper floors by lifts that
supervision staff The lifts that are meant for are mainly meant for conveying the building materials. Fatal
lifting materials used by labour to go to accidents have taken place due to above action of workers.
upper floors – The labour thus traveling
many a times get injured.
24 Site Cleaning–Cleaning top floors of This dangerous practice should not be allowed at all. The
buildings – Upper portion of any structure – materials should be brought to the ground with the help of lift
Throwing waste materials broken concrete or the use of rope over pully with a bucket, thus bringing
pieces, brick bats, sand etc. straightway from down materials safely.
top to ground injuring person below or even
a passerby.
25 Bar bending work-Helpers of bar benders to This is a very bad practice. The helpers should bring the rods
follow short cut method, throw surplus steel to ground with the help of lift or rope & pulley.
pieces from top floors to ground and may
cause fatal injuries.

Page 11 of 11
APPENDIX 8.7: GUIDELINE FOR ENVIRONMENT FRIENDLY CONSTRUCTION METHODOLOGY

The contractor shall be deemed to have acquainted himself with the requirements of all the current statutes, ordinances,
by-laws, rules and regulations or their instruments having the force of law including without limitation those relating to
protection of the environment, health and safety, importation of labour, demolition of houses, protection of
environment and procurement, transportation, storage and use of explosives, etc.
1. PROTECTION OF ENVIRONMENT
(i) The contractor will take all necessary measures and precautions and ensure that the execution of the works
and all associated operations on site or offsite are carried out in conformity with statutory and regulatory
environmental requirements including those prescribed in EMP.
(ii) The contractor will take all measures and precautions to avoid any nuisance or disturbance to inhabitants
arising from the execution of works.
(iii) All liquid waste products arising on the sites will be collected and disposed of at a location on or off the sites
and in a manner that will not cause either nuisance or pollution.
(iv) The contractor will at all times ensure that all existing water courses and drains within and adjacent to the
site are kept safe and free from any contamination.
(v) The contractor will submit details of his temporary drainage work system (including all surface channels,
sediment traps, washing basins and discharge pits) to the Project Implementation Unit –APRDC /
Environment Officer for approval prior to commencing work on its construction.
(vi) The contractor will arrange all the equipment in good condition to minimize dust, gaseous or other air-
borne emissions and carry out the works in such a manner as to minimize adverse impact on air.
(vii) Any vehicle with an open load-carrying area used for transporting potentially dust-producing material will
have properly fitted side and tailboards. Materials having the potential to produce dust will not be loaded to
a level higher than the side and tail boards and will be covered with a clean tarpaulin in good condition.
(viii) The contractor will take all necessary measures to ensure that the operation of all mechanical equipment and
condition processes on and off the site will not cause any unnecessary or excessive noise, taking into
account applicable environmental requirements.
(ix) The contractor will take necessary measures to maintain all plant and equipment in good condition.
(x) Where the execution of the works requires temporary closure of road to traffic, the contractor will provide
and maintain temporary traffic diversions subject to the approval of the EO/Engineer.
(xi) Where the execution of the works requires single-lane operation on public road the contractor will provide
and maintain all necessary barriers, warning signs and traffic control signals to the satisfaction of the
EO/Engineer.
(xii) Wherever traffic diversions, warning signs, traffic control signals, barriers and the like are required, the
contractor will install them to the satisfaction of EO/Engineer prior to commencing the work, in that area.
(xiii) Contractor will install asphalt plants and other machineries away from the populated areas as per laid down
regulations.
(xiv) Permit for felling of trees will be obtained from the forest department before the execution of any work.
(xv) Trees and plants going to be uprooted will be duly compensated and maintained up to 3 years.
(xvi) Mist sprays should be provided at appropriate places for preventing dust pollution during handling and
stockpiling of stones and loose earth.
(xvii) Over Burden (OB) waste dumps shall be sprayed with water, as they are the major source of air borne
particulate matter.
(xviii) OB waste dumps shall be reclaimed / afforested to bind the loose soil and to prevent soil erosion. The
frequency of sprinkling should be fixed as per the seasonal requirement and in consultation with engineer.
(xix) Regular water spraying on haulage roads during transportation of construction material by water sprinklers.
The frequency of sprinkling should be fixed as per the seasonal requirements in consultation with engineer.
(xx) Transfer point for transporting construction material shall be provided with appropriate hoods/ chutes to
prevent dust emissions.

Page 1 of 4
(xxi) Dumping of construction material should be from an optimum height (preferably not too high), so as to
reduce the dust blow.
(xxii) Innovative approaches of using improvised machinery designs, with in-built mechanism to reduce sound
emission.
(xxiii) Procurement of drill loaders, dumbers and other equipment with noise proof system in operator’s cabin.
(xxiv) Confining the equipment with heavy noise emissions in soundproof cabins, so that noise is not transmitted
to other areas.
(xxv) Regular and proper maintenance of noise generating machinery including the transport vehicles to maintain
noise levels.
(xxvi) Provisions should be made for noise absorbing pads at foundations of vibrating equipments to reduce noise
emissions.
2. QUARRY OPERATIONS
The Contractor shall obtain materials from quarries only after the consent of the Forest Department or other
concerned authorities and in consultation with the EO/Engineer. The quarry operations shall be undertaken within
the purview of the rules and regulations in force and instructions as mentioned in Appendix 8.1: Guidelines for
Quarry Management and Appendix 8.2: Guidelines for Borrow Area Management.
3. PREVENTION OF WATER COURSES FROM SOIL EROSION AND SEDIMENTATION
SILTATION
The Contractor shall apply following mitigation measures to prevent sedimentation and pollution of watercourses.
• To prevent increased siltation, if need be existing bridges maybe widened downstream side of the water body;
• Cement and coal ash should be stacked together, fenced by bricks or earth wall, and kept away from water, to
prevent leachate formation and contamination of surface and ground water;
• If need be, slope of the embankments leading to water bodies should be modified and rechannelised to
prevent entry of contaminants into the water body;
• During construction silt fencing (consists of geo-textile with extremely small size supported by wire-mish
mounted on a panel made up of angle frame) could be used along the road at all canals and rivers to prevent
sediments from the construction site to enter into the watercourses.
4. POLLUTION FROM HOT-MIX PLANTS AND BATCHING PLANTS
Bituminous hot-mix plants and concrete batching plants shall be located sufficiently away from habitation,
agricultural operations. The Contractor shall take every precaution to reduce the levels of noise, vibration, dust and
emissions from his plants and shall be fully responsible for any claims for damages caused to the owners of
property, fields and residents in the vicinity.
5. ARRANGEMENT FOR TRAFFIC DURING CONSTRUCTION
The Contractor shall at all times carry out work on the road in a manner creating least interference to the flow of
traffic with the satisfactory execution. For all works involving improvements to the existing state highway, the
Contractor shall, in accordance with the directives of the SE, provide and maintain, during execution of the work, a
passage for traffic either along a part of the existing carriageway under improvement, or along a temporary
diversion constructed close to the state highway. The Contractor shall take prior approval of the SE regarding
traffic arrangements during construction.
6. TRAFFIC SAFETY AND CONTROL
(i) Where subject to the approval of the Engineer the execution of the works requires temporary closure of road
to traffic use, the Contractor shall provide and maintain temporary traffic diversions. The diversion shall
generally consist of 200 mm thickness of gravel 4.5 meters wide laid directly upon natural ground and where
any additional earthworks are required for this purpose that will be provided under the appropriate payment
items.
(ii) Where the execution of the works requires single-lane operation on public road, the Contractor shall provide
and maintain all necessary barriers, warning signs and traffic control signals to the approval of the Engineer.
(iii) With the exception of temporary traffic arrangements or diversions required within the first 4 weeks of the
Contract, the Contractor shall submit details of his proposals to the Engineer for approval not less than 4
weeks prior to the temporary arrangement or diversion being required. Details of temporary arrangements or
diversions for approval as soon as possible after the date of the Letter of Acceptance.

Page 2 of 4
(iv) The color, configuration, size and location of all traffic signs shall be in accordance with the code of practice
for road sign. In the absence of any detail or for any missing details, the signs shall be provided as directed by
the Supervising Engineer (SE).
(v) The Contractor shall take all necessary measures for the safety of traffic during construction and provide, erect
and maintain such barricades, including signs, marking, flags, lights and flagmen as may be required by the
Engineer for the information and protection of traffic approaching or passing through the section of the road
under improvement. Before taking up any construction, an agreed phased programme for the diversion of
traffic or closer of traffic on the road shall be drawn up in consultation with the SE.
(vi) At the points where traffic is to deviate from its normal path (whether on temporary diversion or part width of
the carriageway) the lane width path for traffic shall be clearly marked with the aid of pavement markings,
painted drums or a similar device to the directions of the SE. At night, the passage shall be delineated with
lanterns or other suitable light source.
(vii) One-way traffic operation shall be established whenever the traffic is to be passed over part of the carriageway
inadequate for two-lane traffic. This shall be done with the help of temporary traffic signals or flagmen kept
positioned on opposite sides during all hours. For regulation of traffic, the flagmen shall be equipped with red
and green flags and lanterns / lights.
(viii) On both sides, suitable regulatory / warnings signs as approved by the PIU-APRDC shall be installed for the
guidance of road users. On each approach, at least two signs shall be put up, one close to the point where
transition of carriageway begins and the other 120 m away. The signs shall be of design and of reflectory type,
if so directed by the Engineer.
(ix) Upon completion of the works for which the temporary traffic arrangements or diversions have been made,
the Contractor shall remove all temporary installations and signs and reinstate all affected roads and other
structures or installations to the conditions that existed before the work started, as directed by the Engineer.
7. HEALTH AND SAFETY
The contractor shall take all measures and precautions necessary to ensure the health, safety and welfare of all
persons entitled to be on the site. Such precautions shall include those that, in the opinion of the Engineer, are
reasonable to prevent unauthorized entry upon the site and to protect members of the public from any activities
under the control of the contractor. The contractor’s responsibilities shall include but not be limited to:
(i) The provision and maintenance of the Contractor’s Equipment in a safe working condition and the adoption
of methods of work that are safe and without risks to the health of any person entitled to be on the site.
(ii) The execution of suitable arrangements for ensuring safety and absence of risks to health in connection with
the use, handling, storage, transport and disposal of articles and substances,
(iii) The provision of lighting, including standby facilities in the event of failure that, in the opinion of the
Engineer, is adequate to ensure the safe execution of any works that are to be carried out at right.
(iv) The provision of protective clothing and safety equipment, with such personnel and equipment and such
information, instruction, training and supervision as are necessary to ensure the health and safety at work of all
persons employed on or entering on the site in connection with the works, including the Engineer’s
supervisory staff, all in accordance with the laws.
(v) Near towns, villages and all frequented places, trenches and foundation pits shall be securely fenced provided
with proper caution signs and marked with lights at night to avoid accidents. Contractor shall take adequate
protective measures to see that the excavation operations do not affect or damage adjoining structures.
(vi) The contractor shall not use or generate any materials in the works, which are hazardous to the health of
persons, animals or vegetation. Where it is necessary to use some substances, which can cause injury to the
health of workers, the Contractor shall provide protective clothing or appliances to his workers.
(vii) The contractor will take all measures necessary to safeguard the health; safety and welfare of all persons
entitled to be on site and will ensure that works are carried out in a safe and efficient manner.
(viii) The contractor will provide, and ensure the utilization of appropriate safety equipment for all workmen and
staff employed directly or indirectly by the contractor. Such safety equipment will include but not be limited to
the safety helmets, goggles and other eye protectors, hearing protectors, safety harnesses, safety equipment for
working over water, rescue equipment, fire extinguishers and first-aid equipment. The personnel working at
vulnerable locations at site will wear safety helmets and strong footwear.
(ix) The contractor will provide an adequate number of latrines and other sanitary arrangements at areas of the site
where work is in progress and ensure that they are regularly cleaned and maintained in a hygienic condition.

Page 3 of 4
8. FIRST AID
(i) The provision and maintenance of suitably equipped and staffed first aid stations throughout the extent of the
works to the satisfaction of the Engineer. The contractor shall allow in his prices and the responsible for the
costs of all such site welfare arrangements and requirements.
(ii) Injuries might occur during the construction period. It is therefore pertinent to provide first aid facilities for
all the construction workers. At construction camps and at all workplaces first aid equipment and nursing staff
must be provided. Since many of the workplaces may be far away from regular hospitals, an indoor health unit
having one bed facility every 150 workers needs to be provided.
(iii) Adequate transport facilities for moving the injured persons to the nearest hospital must also be provided in
ready to move condition.
(iv) The first-aid units apart from an adequate supply of sterilized dressing material should contain other necessary
appliances as per the factory rules.
9. MAINTENANCE
(i) All buildings, rooms and equipment and the grounds surrounding them shall be maintained in a clean and
operable condition and be protected from rubbish accumulation.
(ii) Each structure made available for occupancy shall be of sound construction, shall assure adequate protection
against weather, and shall include essential facilities to permit maintenance in a clean and operable condition.
Comfort and safety of occupants shall be provided for by adequate heating, lighting, ventilation or insulation
when necessary to reduce excessive heat.
(iii) Each structure made available for occupancy shall comply with the requirements of the Uniform Building
Code. This shall not apply to tent camps.
10. MAINTENANCE OF DIVERSIONS AND TRAFFIC CONTROL DEVICES
Signs, lights, barriers and other traffic control devices, as well as the riding surface of diversion shall be maintained
in a satisfactory condition till such time they are required as directed by the EO/Engineer. The temporary traveled
way shall be kept free of dust by frequent applications of water, if necessary.

Page 4 of 4
APPENDIX 8.8: STORAGE, HANDLING, USE AND EMERGENCY RESPONSE FOR HAZARDOUS
CHEMICALS

A1. REFUELING/MAINTENANCE PROCEDURE


• Truck or suitable containers will bring in all fuel and fluids. There will be no storage of fuel, oil or fluids
within 100m (or 50m) of the permanent water line.
• Prior to re-fueling or maintenance, drip pans and containment pans will be placed under the equipment.
Absorbent blankets may also be required to be placed under the equipment and hoses where there is a
possibility of spillage to occur.
• All used oils or fluids will be properly contained and transported to appropriately licensed (authorized) disposal
facilities;
• Following re-fueling and maintenance, the absorbent blankets (if any) and spill pans will be picked up and the
fuel truck or container moved outside of the 100m (or 50m) wide area.
Emergency Spill Procedure
Should a spill occur, either though spillage or equipment failure, the applicable emergency spill procedure outlined
in sections A-2 to A-4 must followed.
A2. SPILL PROCEDURE (INSIDE THE STREAM)
In the case of a spill, overflow or release fluid into the stream waterway (whether water is flowing during the spill or
not), do what is practical and safely possible to control the situation, then get help.
• Stop the flow
o Stop the release into the stream waterway
o Shutdown equipment
o Close valves and pumps
o Plug hoses
• Remove Ignition Sources
o Shut off vehicles and other engines
o Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire
extinguisher on hand but keep it a safe distance away from the potential ignition source (if a fire starts, the
extinguisher must be easily accessible).
• Contract the environmental Officer and initiate Emergency Response
o Notify the site supervisor and the Contractor’s Environmental Officer as soon as possible
o The Environmental Officer will review the situation and decide if Emergency Services like Fire Brigade
are required
o Appropriate parties to be notified of the spill are
• The contractor’s Project Manager
• The Engineer through his designated Environmental Officer
• The Client
• Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable.
• Site Safety Officer
• Cleanup and Disposal
o Emergency Services will be engaged for the containment, cleanup and disposal of contamination release
into the environment
• Reporting
o The contractor’s Environmental Officer will document the event and submit reports to the EO/Engineer,
the Client and appropriate regulatory agencies like the Pollution Control Board (s).

Page 1 of 3
• Procedure Review
o The Engineer will review the report, determine if changes are required to procedures and recommend
implementation of all required changes….
A3. SPILL PROCEDURE (ON LAND)
In the case of a spill, overflow or release fluid onto land, do what is practical and safety possible to control the
situation, then get help.
• Stop the flow
o Stop the release into the water body
o Shut down equipment
o Close valves and pumps
o Plug hoses
• Remove Ignition Sources
o Shut off vehicles and other engines
o Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire
extinguisher on hand but keep it a safe distance away from the potential ignition sources (if a fire starts
the extinguisher must be easily accessible).
• Contain the Spill
o Dike around the spill to contain the material
o Spread absorbent or place a spill blanket on the spill
o Enlist the help of personnel on site
o Notify your supervisor as soon as possible
• Notification
o Appropriate parties to be notified of the spill are:
• The Contractor’s Project Manager
• The Engineer through his designated Environmental Officer
• The Client
• Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable
• Site Safety Coordinator
• Cleanup and Disposal
o The Engineer’s Environmental Officer will ensure that a proper cleanup and disposal method is
determined.
• Reporting
o The Contractor’s Environmental Officer will document the event and submit reports to the Engineer, the
Client and appropriate regulatory agencies like the Pollution Control Board (s).
• Procedure Review
o The Engineer will review the report, determine if changes are required to procedures are recommend
implementation of all required changes.
A4. SPILL PROCEDURE (WITHIN PONDS)
In the case of a spill, overflow or release fluid due to equipment or hose failure, do what is practical and safely
possible to control the situation, then get help
• Stop the flow
o Stop the release
o Shut down equipment

Page 2 of 3
o Close valves and pumps
o Plug hoses
• Remove Ignition Sources
o Shut off vehicles and other engines
o Do not allow tiger torches, vehicles, smoking or other sources of ignition near the area. Keep a fire
extinguisher on hand but keep it a safe distance away from the potential ignition sources (if a fire starts
the extinguisher must be easily accessible).
• Contain the Spill
o Stop any pumps that may be moving the water from the area where the spill occurred
o Enlist the help of personnel on site
o Notify your supervisor as soon as possible
• Notification
o Appropriate parties to be notified or the spill are:
• The Contractor’s Project Manager
• The Engineer through his designated Environmental Officer
• The Client
• Regulatory Agencies like Pollution Control Board, Municipal Authorities, as applicable
• Site Safety Coordinator
• Cleanup and Disposal
o The Engineer’s Environmental Officer will ensure that a proper cleanup and disposal method is
determined. Absorbent pads will soak up the spilled material. The pads will be contained and removed
from site for disposal at a licensed (authorized) facility.
• Reporting
o The Contractor’s Environmental Officer will document the event and submit reports to the Engineer, the
Client and appropriate regulatory agencies like the Pollution Control Board (s)
• Procedure Review
o The Engineer will review the report, determine if changes are required to procedures ad recommend
implementation of all required changes.

Page 3 of 3
APPENDIX 8.9: SOIL EROSION AND SEDIMENTATION CONTROL

All materials shall meet commercial grade standards and shall be approved by the Engineer before being used in the
work.
CONSTRUCTION STAGE
Prior to the start of the relevant construction, the Contractor shall submit to the Engineer for approval, his schedules
for carrying out temporary and permanent erosion/sedimentation control works as are applicable for the items of
clearing and grubbing, roadway and drainage excavation, embankment/sub-grade construction, bridges and other struc-
tures across water courses, pavement courses and shoulders. He shall also submit for approval his proposed method of
erosion/sedimentation control on service road and borrow pits and his plan for disposal of waste materials. Work shall
not be started until the erosion/sedimentation control schedules and methods of operations for the applicable
construction have been approved by the Engineer.
The surface area of erodible earth material exposed by clearing and grubbing, excavation, borrow and fill operations
shall be limited to the extent practicable. The Contractor may be directed to provide immediate control measures to
prevent soil erosion and sedimentation that will adversely affect construction operations, damage adjacent properties, or
cause contamination of nearby streams or other watercourses. Such work may involve the construction of temporary
berms, dikes, sediment basins, slope drains and use of temporary mulches, fabrics, mats, seeding, or other control
devices or methods as necessary to control erosion and sedimentation.
The Contractor shall be required to incorporate all permanent erosion and sedimentation control features into the
project at the earliest practicable time as outlined in his accepted schedule to minimize the need for temporary erosion
and sedimentation control measures.
Temporary erosion/sedimentation and pollution control measures will be used to control the phenomenon of erosion,
sedimentation and pollution that may develop during normal construction practices, but may neither be foreseen during
design stage nor associated with permanent control features on the Project.
Where erosion or sedimentation is likely to be a problem, clearing and grubbing operations should be so scheduled and
performed that grading operations and permanent erosion or sedimentation control features can follow immediately
thereafter if the project conditions permit; otherwise temporary erosion or sedimentation control measures may be
required between successive construction stages. Under no conditions shall a large surface area of credible earth material
be exposed at one time by clearing and grubbing or excavation without prior approval of the EO/Engineer.
The Engineer may limit the area of excavation, borrow and embankment operations in progress, commensurate with
the Contractor's capability and progress in keeping the finish grading, mulching, seeding and other such permanent
erosion, sedimentation and pollution control measures, in accordance with the accepted schedule.
Temporary erosion is sometimes caused due to the Contractor's negligence, carelessness or failure to install permanent
controls. Sedimentation and pollution control measures then become necessary as a part of the work as scheduled or
ordered by the Engineer, and these shall be carried out at the Contractor's own expense. Temporary erosion,
sedimentation and pollution control work required, which is not attributed to the Contractor's negligence, carelessness
or failure to install permanent controls, will be performed as ordered by the EO/Engineer.
Temporary erosion, sedimentation and pollution control may include construction work outside the right of way where
such work is necessary as a result of road construction such as borrow pit operations, service roads and equipment
storage sites.
The temporary erosion, sedimentation and pollution control features installed by the Contractor shall be maintained by
him till these are needed, unless otherwise agreed by the Engineer.

Page 1 of 1
APPENDIX 8.10: ARRANGEMENT WITH FOREST DEPARTMENT

REGULATORY FRAMEWORK
• The APRDC under the provisions of the Forest (Conservation) Act, 1980 will submit a diversion proposal in the
prescribed format through the State Forest Department to the concerned Regional Office of the Ministry of
Environment and Forests, of the Govt. of India. The Regional Office is the competent authority to dispose of such
proposal irrespective of the area involved. While issuing such approval, the Regional Office may stipulate a
condition that for every tree cut at least two trees have to be planted.
• Forest Department of the Government of AP after having identified the lands on the embankment and toes of the
road will delineate the proposed area of compensatory afforestation on a suitable map. The Department of Forest
will thereafter prepare an afforestation scheme providing therein the details of work schedule, the cost structure
and proposed monitoring mechanism.
FUNDING MECHANISM
• The Ministry of Environment and Forests under their order dt. the 24th, April, 2004 have constituted an authority
known as Compensatory Afforestation Fund Management and Planning Authority, CAMPA for the purpose
of management of money received from user agencies for compensatory afforestation. The APRCD being the user
agency in this project will be required to deposit the money as estimated by the State Forest Department to the
CAMPA .
• CAMPA shall release funds to the State in predetermined installments through the State Level Management
Committee as per the Annual Plan of Operations drawn by the State Forest Department
SELECTION OF TREE SPECIES
• Trees to be selected for planting should be site-specific taking into account the type of soil, features of the planting
site e.g for saline and alkaline soils and water logged area will require special attention.
• Browse hardiness, good growth rate, resistance to insects/pests disease and biotic interference etc should be given
appropriate weightage in selection of species.
• Evergreen / semi-evergreen species should be preferred to deciduous species.
• In urban /semi-urban stretches of road, flowering trees should be preferred to add to aesthetics of the surround.
• Trees having large tomentose leaves may be included in stretches where particulates are likely to be high.
• In the matter of selection of species for planting, stakeholders need be consulted and their views accommodated
keeping view the site- specifics.
PLANTING PATTERN
• Monoculture planting should be avoided. Mixed culture of shade-giving, flowering and fruit-bearing species should
be preferred.
• The first row may be composed of a mix of species of flowering trees; such mix may consist of trees coming into
flowers in different seasons.
• The second row may have representation of middle-sized evergreen and fruit-bearing species.
• The third row wherever feasible should be of broad-leaved evergreen species; the species should be so chosen as to
make sure that they grow taller than tress planted in the first and second rows.
MANAGEMENT AND MONITORING
• Strip plantations should be properly fenced to prevent damages by biotic interference.
• Wherever possible live- hedges may be provided; in such stretches live-hedges need be grown a year ahead of actual
planting; such hedges may be reinforced by weaving with split bamboos.
• It may also be explored as to whether communities along the roads can be involved in protection and maintenance
of such plantations through a mechanism of sharing of usufructs.
• Local voluntary organisations, sports/youth clubs may also be encouraged for protection of such plantations
through provision of incentives.

Page 1 of 1
APPENDIX 8.11: GUIDELINES FOR SELECTION OF TREE SPECIES

Highway-side plantation may be of various species, some of which are not appropriate. In many places in
Andhra Predesh, one may find giant trees with strong stems and horizontally spreading roots. Some trees
branch out early and have short stems. Some trees without deep roots system overturn when old in rain or
wind.
1. TREES TO BE AVOIDED: On all account, the following trees should be avoided along the roadside:
S
Trees Name Characteristics
No.
1 Eucalyptus (all species), All these tree species have very weak wood and consequently
Millenglonia Hortensis, break easily in windstorm. After a heavy storm, roads become
Eugenia jambolana, Albizzia blocked and traffic is stopped for a considerable length of time.
lebbek, During a storm, these trees are threats to vehicles plying and
pedestrians on the road. Besides the eucalyptus has a few other
Cassia siamca and
negative environmental impacts.
Ficus (all species).
2 Acacia arabica, Acacia They are thorny trees to be avoided close to urban stretches. Their
Modesta and Zizyphus thorns are nuisances for the pneumatic tyres of small vehicles.
Jujuba, etc
3 Ficus bengalensis The Ficus species are of tap root system but flowing type (average
depth of root system is 1.5m). Therefore, these, when mature, may
overturn in strong-wind, storm, etc. Even the existing trees may be
recommended for removal from safety points of view

2. TREES TO BE SELECTED: On the other hand, some trees are appropriate for highway landscaping.
These include trees, which have thiner stem but dense foliage; that absorb/retain dust and other atmospheric
pollutants; those, which erosion resistant species, etc. These species should be preferred for replanting. These
trees include
S
Trees Name Characteristics
No.
1 Azardiracta indica (Neem) The leaves, barks are used for medicinal purposes, and the seeds
yield valuable oil. It can grow on alkaline usar soil
2 Maduca indica (Mahua) The fruit is edible and seeds yields oil. It is also ornamental
3 Tamarindus indica (Imli) A beautiful tree, which stands the dust of roads very well. Its fruit
and timber are also valuable; suitable for dry area
4 Dalbergia sisoo (Shisham) Yields excellent timber
5 Mangifera indica (Mango) Yield valuable fruit
6 Safed siris A quick growing beautiful tree. Because of the light yellow colour
of the trunk, it reflects even weak light. This is an excellent
roadside tree.

3. DUST RESISTANCE: Many of the species resists pollution. Almost all trees have capability to absorb dust.
Available data (from CPCB) shows that different species have different dust collection efficiency, although
dust collection depends on the total leaf area.
S Dust Collection Total leaf Area Mean Dust
Species
No. Efficiency (g/m2-d) (m2/tree) Collection (g/tree-d)
1 Ficus bengalensis 3.59 107-125 416.44
2 Ficus religiosa 4.15 55-62 242.76
3 Magnifera indica 1.05 60-76 275.40
4 Anthocephalus 3.57 42-48 160.65

Page 1 of 3
S Dust Collection Total leaf Area Mean Dust
Species
No. Efficiency (g/m2-d) (m2/tree) Collection (g/tree-d)
5 Lagerstroemia 4.04 28-32 121.20
6 Polyalthia longifolia 4.56 8-12 45.60
7 Tectona grandis 5.35 35-38 195.26
8 Terminalia arjuna 4.49 48-52 224.50
9 Bauhinea variegata 3.90 23-28 99.45

4. POLLUTION RESISTANCE: Similarly, available data from CPCB shows different species have different
capacities of absorbing gases. Data for particular gases were not available. However, some plants are known to
absorb CO and CO2 (white dwarf Oleander), SO2 (Betula verrucosa, Fagus sylvestris, carpinus betula), etc.
S No. Species Absorbance Index
1 Albizzia lebbek 62
2 Cassia Fistula 54
3 Ficus glomerata 32
4 Anthocephalus indicus 24
5 Polyalthis longifolia 19
6 Eucalyptus sp. 15

5. CHARACTERISTICS OF TREE SPECIES FOUND ALONG PROJECT CORRIDOR


No. of % no. of
S
Species Characteristics Existing existing
No.
trees trees
1 Azadirachta Category of wood is E. It is dust resistant, gas absorbent. 249 22%
indica- Neem Controls erosion, is drought resistant and supports
wildlife. Seeds yield margosa oil, which has medicinal
properties including being extremely effective in
treatment of leprosy and skin diseases.
2 - Giriship 243 21%
3 Samania Saman Category of wood is E. Planted as avenue tree. It is dust 227 20%
Bagi resistant, gas absorbent. Controls erosion, is drought
resistant and supports wildlife. The pod fed to cows is
believed to increase the quantity of milk.
4 Delonix regia - Category of wood is E. Ornamental plant. It is dust 197 17%
Aggi Pulla resistant, gas absorbent. Controls erosion, is drought
resistant and supports wildlife. Flowers and buds are
often used as pot-herbs.
5 Pongamia Category of wood is E. Dust resistant, gas resistant. 52 5%
pinnata – Controls erosion. Drought resistant. Seeds are effective
Karanj in treating bronchitis. Seeds/oil have
antiseptic/antiparasitic properties
6 Tamarindus Category of wood is E. Seed yields fellose, which is used 14 1%
indica – as a sizing agent. It is dust resistant, gas absorbent.
tamarind Controls erosion, is drought resistant and supports
wildlife.

7 Sysygium Category of wood is E. Vinegar is prepared from the juice. 8 1%


cumini – Jamun It is dust resistant, gas absorbent. Controls erosion, is
drought resistant and supports wildlife. Bark of the tree is
used for tanning of leather. Fruits are very nourishing for
diabetic patients.

Page 2 of 3
6. USE CHARACTERISTICS OF TREE SPECIES FOUND ALONG PROJECT CORRIDOR
The following table lists the predominant species found along project corridor along with the use
characteristics.

as manure
Beverages

Repellent
Religious

Medicine
Tanning
Yielding
Fruits &

Oil cake
Brushes
Thatch
Fodder

Hedge

Others
Plants

Plants
Insect
Tooth
Seeds

Oil
TREE SPECIES

Azardirachta indica 9 9 9 9 9
Samania samon 9
Delonix regia 9
Pongamia pinnata 9 9
Tamarindica indica 9 9
Syzgium cumini 9 9 9 9

7. RECOMMENDED SPECIES FOR PLANTATION ALONG PROJECT CORRIDOR


Based on the above findings about the use and characteristics of the predominant tree species found along the
project corridor. The order of priority of species to be planted is

as manure
Religious

Medicine
Tanning
Yielding
Fruits &

Oil cake
Brushes

Others
Tooth
Seeds
Oil
TREE SPECIES Usefulness Recommendation

Azardirachta indica 1 30% 9 9 9 9 9


Syzgium cumini 2 20% 9 9 9 9
Pongamia pinnata 3 15% 9 9
Tamarindica indica 3 15% 9 9
Samania samon 5 10% 9
Delonix regia 5 10% 9

Page 3 of 3
APPENDIX 8.12: GUIDELINE FOR AVENUE PLANTATION

1 GENERAL DESCRIPTION
1.1 Avenue plantation is suggested all along the rural stretches of the project corridor.
1.2 The selections of species agreeing with the general landscaping of the area are suggested/recommended in
APPENDIX 8.11: GUIDELINES FOR THE SELECTION OF TREE SPECIES.
1.3 Planting should generally be done at the height of the monsoons in the month of July.
1.4 It is felt that a weighted emphasis should be paid to protection, maintenance and safety of the planted trees.
Suitable full-timers should be employed for this purpose.
1.5 The species to be planted would be to enhance the visual experience of the road corridor. One/ two / three
rows of trees are recommended in accordance to the varying width available of different sections. Tree spacing
in case of broad canopy should not be less than 10m, and in case of medium canopy should not be less than
7m. (Refer Figure below)

ROW = 30.00m
ROW > 30.00m
3.00 1.50 2.00 2.50 7.00 2.50 2.00 1.50 3.00 2.50 7.00 2.50
2.50 2.50 3.00 3.00 3.00 1.50 2.50 2.50 1.50 3.00 3.00 3.00 3.00
ROW

ROW

ROW

ROW
10.00 10.00 10.00

10.00
CARRIAGEWAY

CARRIAGEWAY
EMBANKMENT

EMBANKMENT
CENTER LINE

CENTER LINE
SHOULDER

SHOULDER
DRAIN

DRAIN
ROW

ROW

ROW

ROW
10.00 10.00 10.00

10.00
ROW

ROW

ROW

ROW
10.00 10.00 10.00

Conceptual Plan for Avenue Plantation


1.6 The plants will be at spacing of 10 meters and size of the pits for planting will be 0.6m /0.75m dia and deep.
Therefore, total no. of plants per km will be 200 in case where single row is proposed and 400 in case of two
row.
1.7 The species recommended for avenue plantation should be able to withstand extreme temperature and climate
conditions and also has low requirements of water. These species have been proposed considering the climatic
conditions, requirements of water and future management. However other species may also be used, after
approval from EO/Engineer.
1.8 The surface for the avenue plantation should be well prepared. The masses of loose debris and any convexities
will be removed and similarly and concavities are to be filled by good soil. The surface should have sufficient
layer of good quality of soil so as to have a better growth and survival of trees, grasses and saplings.
1.9 The height of the plants will not be less than 1.5m. and need to be in polythene bags until the planting.
1.10 All plants supplied must be planted within three days of removal from the nursery.
1.11 The contractor/agency hired will be required to water the area in case of sufficient rains water after planting.
1.12 Size of the pits for planting saplings - 75x75x75 cm
1.13 No. of Plant per km - 200
1.14 Use of compost of manure - 1/3 of volume of pit mixed with soil, and refilled

Page 1 of 7
1.15 The total no. tree saplings to be planted along the corridor
S.No. Description No. of sapling Required Area for Landscaping (sqm)
1 Avenue Plantation Nil
2 Realignment Sections
3 Cultural Properties

1.16 Table-1: Activities schedule for Plantation along the Road

Year Month Sl No. Activities to be done

1st Year Jan to Mar 1 Surveying & Clearing of the area


2 Digging of Pits
3 Procurement of Angles Iron and Barbed wire (or other fencing
material), and erecting the fence
2nd Year April to June 1 Purchase of Farm yard manure
2 Brick/Iron etc. guard for 1st row
3. Plantation along the road
4 Filling up of pits with Farm yard manure and soil
July to August 1 Transportation of Plants
2 Planting of Sapling
3 Watering
4 Weeding and Hoeing
Sept to Nov 1 Weeding of Hoeing
2 Watering 4 times a month
Dec to Feb 1 Weeding of Hoeing
2 Maintenance
March 1 Watering 4 times a month
3rd Years April to June 1 Watering 6 times a month
July to August 1 Casualty Replacement (20% of the total plants)
2 Weeding
3 Maintenance by Mali
Sep to Nov 1 Watering 2 times a month
2 Maintenance by Mali
Dec to Feb 1 Maintenance by Mali
March 1 Watering 4 times a month
2 Maintenance by Mali
4th Year April to March 1 Watering
2 Casualty Replacement (10% of the total plants)
3 Maintenance by Mali

2 PLANTATION
Scope

Page 2 of 7
Contractor/ agency hired to furnish all materials, labor and related items necessary to complete the work
indicated on drawing and specified herein.
2.1 Materials
Saplings
• Saplings/Seedlings shall be well-formed and free from defects such as knots, sun-scaled, windburn,
injuries, abrasion or disfigurement. All saplings shall be healthy, sound, free from plant diseases, insect’s
pests, of their egg and well-developed root systems.
• No plant will be accepted, if branches are damaged or broken. All the plant material must be protected
from the sun and weather until planted.
• Any nursery stock shall have been inspected and approved by the EO-APRDC.
• All saplings will be delivered with legible identification labels.
• The root system shall be conducive to successful transplantation. While necessary, the root-ball shall be
preserved by suitable material. On soils where retention of a good ball is not possible, the roots should be
suitably protected in some other way, which should cause any damage to roots.
Topsoil/Good Earth
• Topsoil or good earth shall be a friable loam, typical of cultivated topsoil of the locality containing at least
2% of decayed organic matter (humus).
• Stored topsoil will be used for plantation at median and also for roadside plantation. Otherwise it could be
taken from a well-drained arable site.
• It shall be free of subsoil, stones, earth skids, sticks, roots or any other objectionable extraneous matter or
debris.
• It shall contain no toxic material.
• No topsoil shall be delivered in a muddy condition.
Manure
• Only organic manure will be used for plantation. Composts from municipal solid wastes and distillery
waste may be used.
• Manure shall be free from extraneous matter, harmful bacteria insects or chemicals (Subjected to safety
norms).
General Condition
• Saplings shall be substantially free from pests and diseases, and shall be materially undamaged. Torn or
lacerated roots shall be pruned before dispatch.
• No roots shall be subjected to adverse conditions such as prolonged exposure to drying winds or
subjection to water logging, between lifting and delivery.
Supply and Substitution
Upon submission of evidence that certain materials including plant materials are not available at time of
contract, the contractor shall be permitted to substitute other and plants, with an equitable adjustment of price.
All substitutions shall be of the nearest equivalent species and variety to the original specified and shall be
subjected to the approval of the Landscape Architect. Packaging shall be adequate for the protection of the
plants and such as to avoid heating or drying out.
Each specimen of tree, or each bundle, shall be legibly labeled with the following particulars:
• Its name (Both common and Scientific)
• The name of the supplier, unless otherwise agreed.
• The date of dispatch from the nursery.

Page 3 of 7
2.2 Planting
Plants and Saplings
All saplings should be supplied with adequate protection as approved. After delivery, if planting is not to be
carried out immediately, balled plants should be placed and the ball covered with sand to prevent drying out.
Bare rooted plants can be heeled in by placing the roots in prepared trench and covering them with earth,
which should be watered into, avoid air pockets round the roots. Saplings shall be planted as suggested by
Environment officer.
Digging of Pits
• Tree pits shall be dug a minimum of three weeks prior to backfilling.
• The pits shall be 60 to 90cms in diameter and 90 to 120cms deep.
• While digging the pits, the topsoil upto a depth of 30cms may be kept aside, if found good (depending
upon site conditions), and mixed with the rest of the soil.
• If the soil is normal it shall be mixed with manure.
• The bottom of the pit shall be forked to break up the subsoil.
Back Filling
The soil back filled watered through end gently pressed down, a day previous to planting, to make sure that it
may not further settle down after planting. The soil shall be pressed down firmly by treading it down, leaving a
shallow depression all round for watering.
Planting
• No pits shall be dug until final position has been pegged out for approval.
• Care shall be taken that the plant sapling when planted is not be buried deeper than in the nursery, or in
the pot.
• Planting should not be carried out in waterlogged soil.
• Plant saplings at the original soil depth; soil marks on the stem is an indication of this and should be
maintained on the finished level, allowing for setting of the soil after planting.
• All plastic and other imperishable containers should be removed before planting.
• Any broken or damage roots should be cut back to sound for healthy growth.
• The bottom of the planting pit should be covered with 50mm to 75mm of soil.
• Bare roots should be spread evenly in the planting pit; and small mound in the center of the pits on which
the roots are well aid on and evenly spread.
• Soil should be placed around the roots, gently shaking the saplings to allow the soil particles to shift into
the root system to ensure close contact with all roots and prevent air pockets.
• Back fill soil should be firmed as filling proceeds, layer by layer, care being taken to avoid damaging the
roots.
Staking
Newly planted saplings must be held firmly although not rigidly by staking to prevent a pocket forming around
the stem and newly formed fibrous roots being broken by mechanical pulling as the tree rocks.
Methods:
The main methods of staking shall be:
• A single vertical shake, 900mm longer than the clear stem of the saplings driven 600mm to 900mm into
the soil.
• Two stakes as above driven firmly on either side of the saplings with a cross bar to which the stem is
attached. Suitable for bare- rooted or Ball material.
• A single stake driven in at an angle at 45 degrees and leaning towards the prevailing wind, the stem just
below the lowest branch being attached to the stake. Suitable for small bare- rooted or Ball material

Page 4 of 7
• For plant material 3m to 4.5m high with a single stem a three- wire adjustable guy system may be used in
exposed situations.
The end of stake should be pointed and the lower 1m to 1.2m should be coated with a non-injurious wood
preservative allowing at least 150mm above ground leveI.
Tying
Each saplings should be firmly secured to the stake so as to prevent excessive movement. Abrasion must be
avoided by using a buffer, rubber or Hessian, between the saplings and stake. The saplings should be secured
at a point just below its lowest branch, and also just above ground level; normally two ties should be used for
saplings. These should be adjusted or replaced to allow for growth.
Watering
The Landscape Contractor should allow for the adequate watering in of all newly planted trees and saplings
immediately after planting and during the growing season, keep the plant material well watered.
Manure/Fertilizer usage
The fertilizers/manure usage should be such that the turn of all the fertilizers comes after, every 15 days from
the beginning of the monsoon till the end of winter:
Organic well-rotted dry farm yard manure: 0.05 cum or tussle.
1. Urea 25gm.
2. Ammonium sulphate 25gm.
3. Potassium sulphate 25gm.
All saplings, which are supplied pot grown, shall be well soaked prior to planting.
Watering in and subsequent frequent watering of summer planted container- grown plants is essential.
Application of inorganic manure should as for possible be avoided. Form yard manure as biofertilizer with for
better option.
4. COMPLETION
On completion, the ground shall be formed over and left tidy.
Special Conditions and Particular Specifications:
1. Wherever applicable, work shall be done according to C.P.W.D. specifications
2. At the time of invitation of tender.
3. Water shall be made available, near the tube well at one point. Contractors shall make their own
arrangement for drawing water from there. Water charges as per the value of work done shall be deducted
from the contractors Bills.
4. If electricity is required for the works, the same shall be made available at one point within the site of
works, for which recovery at the prevailing rate per unit shall be deducted from the contractors’ bill.
5. The work mentioned in the schedule of Quantities include grassing as well as planting of trees and
saplings. 'Contractors' quoted rates shall include execution of these works at different levels. No extra cost
shall be paid for any item, for working at these levels.
6. The Contractor shall provide all facilities to subcontractor (plantation) / Environment Officer / or his
authorized representatives to make frequent inspection of their Nursery and ascertain the process /
quality of various categories of trees/plants etc., grown by them.
7. The safe custody and up-keep of various categories of plants brought to site is the sole responsibility of
the contractor and he shall employ sufficient supervisory personnel to ensure the safety of these items.
8. The site of work may be handed over to the contractors for execution of work in phases, as soon as the
same are available. Nothing extra shall be payable for such phased execution of work.
9. While excavating / executing the work the contractors shall ensure that existing cables / pipe lines /
structures / fittings are not damaged.
10. The Contractor shall co-ordinate his work with other agencies employed by the Clients and ensures that
the work of other agencies is not hampered in any way during the duration of contract.

Page 5 of 7
11. The Contractor shall keep the site of works neat and clean during the execution of the work. Any debris
found at or near the site of work shall be rescued immediately as and when so required by the Contractor.
12. On completion of the work, the site of work shall be thoroughly cleaned and all debris removed before
the work is handed over satisfactorily.
13. The Contractors shall, without any additional charge to the clients, renew or replace any dead or defective
plants/grass and shall fully maintain the whole landscape for a period of 12 months after the certified date
of completion.
14. Saplings/small tree shall be of minimum length straight and symmetrical with a crown and having a
persistent main stem. The size of crown shall be in good over all proportion to the height of the tree.
15. Small trees and saplings shall be well formed with the crown typical of the species or variety.
16. General Requirements of Plants:
• Plants shall be typical of their species and variety, well-developed branches, and well foliated with
fibrous root system. Plants shall be free from defects and injuries. Plants shall not be pruned before
planting.
• Plants shall be free from defects and injuries.
• Plants shall not be pruned before planting.
• Plants shall not be freshly dug and nursery grown.
• Nursery grown plants shall have been at least once transplanted.
• Bark shall be free from abrasion.
• All trees, soon after planting, shall be properly supported with bamboo stocks to ensure their safety
against winds or any other factor, which may affect it adversely.

Page 6 of 7
Format for the monitoring of the tree plantation and landscaping is given below.

Format EM7: Tree Plantation and Landscaping

Construction Stage: Quarterly Report -Date____ Month______ Year______

All landscape works to be as per Landscape Plan

Physical Target Financial Target Completion Target


Target
Date of Reason
(tree/saplings to
Target % of task Total Budget % Target Completion for
be planted in
Sl. Achieved completed (lakhs) Spent used Date /% Delay
Activity Package) for this
No completed if any
Quarter
No. Survival
unit of Rate
Trees (%)
Tree
1 Plantation km-km
along roadside
Landscaping
2 of Road Nos.
Junctions
Plantation at
3 Incidental Nos.
Spaces
Plantation at
Locations
4 Nos.
identified for
enhancement
Turfing on
5 km-km
Embankment
Saplings on
6 km-km
Embankment

Certified that the above information is correct

Assistant Conservator of Forests

Page 7 of 7
APPENDIX 8.13: GUIDELINES FOR TRANSPLANTATION OF FULL-GROWN TREES

If trees are not very old they can be transplanted easily. The percentage of survival can be hundred per cent if the work
is done properly and during the rainy season. The following steps are involved:
1. The sites where the trees are to be shifted should be selected first. The sites should be free of overhead telephone
or power lines. Large pits should be dug at these sites to comfortably accommodate the ‘tree roots’ ball of earth.
2. Distance between pits depends on the variety. In case of short varieties with a small spread, the distance should be
10 ft. to 15 ft. For tall varieties with spreads of between 15 ft. and 20 ft. on either side, the distance should not be
less than 30 feet.
3. When pits are dug at the selected sites, their sizes would depend on the dimensions/age of the tree. For trees of
medium size the pit size will be around 8 feet in diameter and 5 feet deep. The actual pit size for different trees can
be adjusted with experience. The point to be kept sight of is that ‘trees roots’ ball of earth should fit in comfortably
with at least 6 to 12 inches clearance all around. Usually the pit size in feet should be directly proportional to the
girth of the trees in inches.
4. Adequate quantity of soil and manure mixture @ 4:1 is necessary for each pit. A little bone meal can also be added.
To start with only about 60cm soil mixture is to be filled in each pit and watered well to form a puddle before the
actual transplantation. The total quantity of soil and manure required for all the pits should be mixed and arrange
before the start of the actual operation.
5. Before transplantation, the trees should be ‘extensively pruned’. That is, the foliage should be completely removed
and all the branches should be cut off with a pruning saw. No other implement should be used. The cut surfaces
should be painted with non-synthetic white paint to anaesthesise these portions. ‘Extensive pruning ‘ helps in easier
‘replanting balance’ and handling, thereby reducing the shock effect. This also aids the plant roots in recovering and
adhering to the new soil and reduces transpiration and/or loss of moisture.
6. The trees are now ready for lifting or uprooting. A deep trench of at least up to 5 feet in depth is to be dug around
the base of the tree at least 2 to 3 feet away from the trunk in the case of trees with a girth of up to 60cm. The
depth of the trench and its distance from the trunk would therefore vary with the size of the tree. The trench
should be dug to gradually converge towards the base of the tree so that ‘tree roots’ ball of earth can ultimately be
ditached from the ground.
7. The trees are then to be lifted with the help of a crane of suitable size. Before lifting, a piece of guny should be
wound round the trunk, with a few wooden batons secured around the gunny pack on the outside by a steel wire
rope. This will facilitate lifting without injuring the bark. Immediately the ‘trees roots’ ball should be sprayed with
potassium phosphate solution and then wrapped and tied with a piece of very wet gunny.
8. Before replanting, the soil at the base of the pit should be watered heavily after which the uprooted tree along with
the ‘tree roots’ ball should be lowered carefully into the new pit with the help of the crane.
9. The empty space in this pit is to be filled with the previous prepared mixture of soil, bone meal and manure and
thoroughly rammed in tightly, so that no air gaps are left inside the soil. Air gaps could result in fungal infection to
the roots. Sand can also be added which will fill up the air gaps when watered.
10. The trunk can now be sprayed with Blytox, a copper sulphate compound whose action is anti-fungicidal in nature.
11. The transplanted tree should be watered heavily at the base.
12. Guy ropes, angle iron or bamboos should be used for a few days to secure the tree till the soil hardens around the
transplanted tree to hold it erect.
13. Four to five days after transplantation the trunk can be sprayed with potassium nitrate solution for facilitating the
initiation of new shoots.
14. If rains are inadequate watering should continue for three months.
The heavily pruned transplanted tree is not a pretty sight, but this should not deter the optimist, as the chances of
survival are maximum without the branches and foliage.

Page 1 of 1
Appendix 8.14

List of Sensitive Cultural Properties

Location
Sl. Chainag Name of Cultural Mitigation/ Enhancement
(Left / Impact
No. e (Km.) Property
Right)
Mosque With Neem Specific Enhancement as
1 153/800 Right No Direct Impact
Tree per LBG/APRDC/CP/01
Hanuman
2 41/300 Right Direct Impact Will be relocated
Temple
Hanuman Specific Enhancement as
3 160/840 Left No Direct Impact
Statue per LBG/APRDC/CP/02
Generic Enhancement
4 160/840 Temple Arch Left No Direct Impact
Generic Enhancement
5 162/375 Temple Cum Ashramam Left No Direct Impact
Kasi Generic Enhancement
6 165/450 Right No Direct Impact
Temple
Specific Enhancement as
7 167/350 Vinayaka Temple Left No Direct Impact
per LBG/APRDC/CP/03
8 167/450 Temple Right Direct Impact Will be relocated

9 168/200 Church Right Direct Impact Will be relocated


Hanuman Temple Side
10 168/350 Left Direct Impact Will be relocated
Tree
11 168/433 Gangamma Stone Right Direct Impact Will be relocated

12 168/450 Mosque With Tree Right Direct Impact Will be relocated

13 169/350 Renuka Ellamma Temple Right Direct Impact Will be relocated


Specific Enhancement as
14 170/040 Swamiji Temple Left No Direct Impact
per LBG/APRDC/CP/04
15 170/920 Penta Coastal Church Left No Direct Impact Generic Enhancement
Specific Enhancement as
16 170/940 Dargh Left No Direct Impact
per LBG/APRDC/CP/05
Generic Enhancement
17 181/740 Ashramam Left No Direct Impact
Generic Enhancement
18 182/090 Church Right No Direct Impact
Chainage 153+800
Structure ID No Mosque with Neem tree
Village Name Mydukuru
Side (Left/Right) Right
Distance from ECL 7.7
Length x Breadth 5.0x4.0
Proposed Widening Eccentric on LHS (3.88m)
Impact No direct impact
DWG No LBG/APRDC/CP/01

Chainage 160+840

Structure ID No Hanuman Statue


Village Name Chapadu
Side (Left/Right) Left
Distance from ECL 7.5
Length x Breadth 4.0x4.0
Proposed Widening Eccentric on RHS (4.54m)
Impact No direct impact
DWG No LBG/APRDC/CP/02

Chainage 167+350
Structure ID No Vinayaka temple
Village Name
Side (Left/Right) Left
Distance from ECL 9.7
Length x Breadth 22.0x55.0
Proposed Widening Eccentric on RHS (4.17m)

Impact No direct impact


DWG No LBG/APRDC/CP/03

Chainage 170+040
Structure ID No Swamiji Temple
Village Name Proddutur
Side (Left/Right) Left
Distance from ECL 14.5
Length x Breadth
Proposed Widening Eccentric on RHS (2.0m)
Impact No direct impact
DWG No LBG/APRDC/CP/04
170+920
Chainage
Structure ID No Pentacostal church
Village Name Proddutur
Side (Left/Right) Left
Distance from ECL 11.5
Length x Breadth

Proposed Widening Eccentric on RHS (0.85m)


Impact No direct impact
DWG No LBG/APRDC/CP/05
APPENDIX 8.15: GUIDELINES FOR MONITORING PROGRAM

1.1 Environmental Monitoring Plan


The monitoring programme is devised to ensure that the envisaged purpose of the project is achieved and results in
the desired benefit to the target population. To ensure the effective implementation of the EMP, it is essential that
an effective monitoring programme be designed and carried out. Broad objectives of the monitoring programme
are:
• To evaluate the performance of mitigation measures proposed in the EMP
• To suggest improvements in the management plans, if required
• To satisfy the statutory and community obligations
The monitoring programme contains monitoring plan for all performance indicators, reporting formats and
necessary budgetary provisions. Monitoring plan for performance indicators and reporting system is presented in
the following sections.
1.1.1 Performance Indicators
Physical, biological and environmental management components identified as of particular significance in affecting
the environment at critical locations have been suggested as Performance Indicators (PIs). The Performance
Indicators shall be evaluated under three heads as:
• Environmental condition indicators to determine efficacy of environmental management measures in
control of air, noise, water and soil pollution;
• Environmental management indicators to determine compliance with the suggested environmental
management measures
• Operational performance indicators have also been devised to determine efficacy and utility of the
mitigation/enhancement designs proposed
The Performance Indicators and monitoring plans prepared for Project Implementation are presented in Table 1.1.
Table 1.1: Performance Indicators for Project Implementation
Sl.
Indicator Details Stage Responsibility
No.
A Environmental Condition Indicators and Monitoring Plan
Pre Construction PU through approved
monitoring agency
1 Air Quality Construction
R&B through approved
Operation
monitoring agency
Pre Construction PU through approved
monitoring agency
2 Noise Levels Construction
The parameters to be monitored, frequency and R&B through approved
Operation
duration of monitoring as well as the locations to monitoring agency
be monitored will be as per the Monitoring Plan Pre Construction PU through approved
prepared (Refer Table 1.2) monitoring agency
3 Water Quality Construction
R&B through approved
Operation
monitoring agency
Pre Construction PU through approved
monitoring agency.
4 Soil Quality Construction
R&B through approved
Operation
monitoring agency

Page 1 of 8
Sl.
Indicator Details Stage Responsibility
No.
B Environmental Management Indicators and Monitoring Plan
Location of construction camps have to be
Construction
1 identified and parameters indicative of Pre-construction PU
Camps
environment in the area has to be reported
Location of borrow areas have to be identified
and parameters indicative of environment in the
2 Borrow Areas area has to be reported. Refer Guidelines 7.2 Pre-construction PU
(Guidelines for Borrow Areas Management) for the
identified Borrow Areas.
Progress of tree removal marked for cutting is to
3 Tree Cutting Pre-construction Forest Department to PU
be reported
Progress of measures suggested as part of the
4 Tree Plantation Construction Forest Department
Strategy is to be reported
C Management & Operational Performance Indicators
1 Survival Rate of The number of trees surviving during each visit Forest Department/ R&B
Trees will be compared with the number of saplings Operation
planted
2 Status Regarding The PU will undertake site visits to determine how The R&B/APRDC will be
Rehabilitation of many borrow areas have been rehabilitated in line responsible for a period of
Operation
Borrow Areas with the landowner’s request and to their full three years.
satisfaction.
3 Soil Erosion Visual monitoring and operation inspection of The R&B/APRDC will
embankments will be carried out once in three Operation be responsible for a
months. period of three years.
1.1.2 Monitoring Parameters and Standards
The Environmental monitoring of the parameters involved and the threshold limits specified are discussed below:
Ambient Air Quality Monitoring (AAQM)
The air quality parameters viz: Sulphur Dioxide (SO2), Oxides of Nitrogen (NOX), Carbon Monoxide (CO), Hydro-
Carbons (HC), Suspended Particulate Matter (SPM), and Respirable Particulate Matter (RPM) shall be regularly
monitored at identified locations from the start of the construction activity. The air quality parameters shall be
monitored in accordance with the National Ambient Air Quality Standards as given in Table 1.2A. The duration
and the pollution parameters to be monitored and the responsible institutional arrangements are detailed out in the
Environmental Monitoring Plan Table 1.3 and specific details in chapter on baseline environment.
Table 1.2A National Standard of Air
Time Residential,
Sensitive Industrial
Pollutant Weighted Rural & Method of Measurement
Area Area
Average Other Areas
Annual* 15 µg/m³ 80 µg/m³ 60 µg/m³ Improved West and Gaeke
Sulphur Dioxide
Method
(SO2) 24 hours** 30 µg/m³ 120 µg/m³ 80 µg/m³ Ultraviolet Fluorescence
Jacob & Hochheiser Modified
Oxides of Nitrogen Annual* 15 µg/m³ 80 µg/m³ 60 µg/m³ method
Gas phase Chemiluminescence
(NOX) 24 hours** 30 µg/m³ 120 µg/m³ 80 µg/m³

Suspended Annual* 70 µg/m³ 360 µg/m³ 140 µg/m³ High Volume Sampler (Average
Particulate Matter flow rate not less than 1.1
(SPM) 24 hours** 100 µg/m³ 500 µg/m³ 200 µg/m³ m³/minute)
Respirable Respirable Particulate Matter
Particulate Matter Annual* 50 µg/m³ 120 µg/m³ 60 µg/m³ Sampler
(RPM) 24 hours** 75 µg/m³ 150 µg/m³ 100 µg/m³
Size < 10µm

Page 2 of 8
Time Residential,
Sensitive Industrial
Pollutant Weighted Rural & Method of Measurement
Area Area
Average Other Areas
AAS Method after sampling
Lead Annual* 0.50 µg/m³ 1.0 µg/m³ 0.75 µg/m³ using
(Pb) 24 hours** 0.75 µg/m³ 1.5 µg/m³ 1.00 µg/m³ EPM 2000 or equivalent filter
paper
Carbon Monoxide 8 hours** 1.0 mg/m³ 5.0 mg/m³ 2.0 mg/m³ Non-dispersive infrared
(CO) 1 hour 2.0 mg/m³ 10.0 mg/m³ 4.0 mg/m³ Spectroscopy
* Annual arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform interval
**24 hourly/8 hourly values should be met 98% of the time in a year. However, 2% of the time, it may exceed but
not on two consecutive days.
Source: Central Pollution Control Board, 1997 Gazette Notification dated 4/94, Part II Sec 3 (ii)

Noise Quality Monitoring


The noise levels shall be monitored at already designated locations in accordance with the Ambient Noise Quality
standards given in Table 1.2B. The duration and the noise pollution parameters to be monitored and the
responsible institutional arrangements are detailed in the Environmental Monitoring Plan Table 1.3 and specific
details in chapter on baseline environment.
Table 1.2B National Standard of Noise
Area Code Category of Zones Limits of Leq in dB(A) Day* Night*
A Industrial 75 70
B Commercial 65 55
C Residential 55 45
D Silence Zone ** 50 40

* Daytime shall mean from 6.00am to 10.00 pm and Night shall mean from 10.00 pm to 6.00 am
** Silence zone is defined as area up to 100 meters around premises of hospitals, educational institutions and
courts. Use of vehicles horns, loud speakers and bursting of cracking are banned in these zones.
Water Quality Monitoring
Water quality parameters such as pH, BOD, COD, DO coliform count, total suspended solids, total dissolved
solids, Iron, etc. shall be monitored at all identified locations during the construction stage as per standards
prescribed by Central Pollution Control Board and Indian Standard Drinking water specifications IS 10500, 1991,
presented in Table 1.2C. The duration and the pollution parameters to be monitored and the responsible
institutional arrangements are detailed out in the Environmental Monitoring Plan Table 1.3 and specific details in
chapter on baseline environment.
Table 1.2C: National Standard of Water
Sr. IS:2296
Parameters IS:10500 Method Adopted
No (Class C)
1 PH 6.5-8.5 6.5-8.5 pH meter
2 BOD (3 days 270C) 3.0 NS DO-Azide modification of Wrinkler’s method
3 Temperature ( C) NS NS Thermometer
4 Dissolved oxygen 4 NS Azide Modification of Wrinkler’s method
5 Color (Hazen) 300 NS Visual Comparison method
6 Fluorides (F) 1.5 1.0 (1.5) SPANDS method
7 Chlorides (Cl) 600 250(1000) Argentometric Titration
8 Total Dissolved Solids 1500 500 (2000) Gravimetric Analysis
9 Sulphates (SO4) 400 200 (400) Barium Chloride method
10 Iron (Fe) 50 0.3 (1.0) Phenanthrolin method
11 Oil and Grease 0.1 NS Partition – Gravimetric method
12 Nitrates 50 45 (100) Chromotropic acid

Page 3 of 8
Sr. IS:2296
Parameters IS:10500 Method Adopted
No (Class C)
13 Chromium (Cr6+) 0.05 0.05 Atomic Absorption Spectrophotometry
14 Cadmium (Cd) 0.01 0.01 Atomic Absorption Spectrophotometry
15 Lead (Pb) 0.1 0.05 Atomic Absorption Spectrophotometry
16 Copper (Cu) 1.5 0.05 (1.5) Atomic Absorption Spectrophotometry
17 Cyanide (CN) 0.05 0.05 Chloramine-T-method
18 Selenium (Se) 0.05 0.01 Atomic Absorption Spectrophotometry
19 Arsenic (As) 0.2 0.05 Atomic Absorption Spectrophotometry
20 Phenols 0.005 0.001(0.002) Spectrophotometer
21 Detergents 1.0 0.2 (1.0) Spectrophotometer
22 DDT Absent Absent Spectrophotometer
Total Coliform Multiple Tube
23 5000 NS
(MPN/100 ml) Fermentation Technique
NS: Not specified; Brackets ([ ]) indicates extended limits. All the values in mg/l if otherwise mentioned

1.1.3 Monitoring Plans for Environment Condition


For each of the environmental components, the monitoring plan specifies the parameters to be monitored; location
of the monitoring sites; frequency and duration of monitoring. The monitoring plan also specifies the applicable
standards, implementation and supervising responsibilities. The monitoring plan for the various environmental
condition indicators of the project in construction and operation stages is presented in Table 1.3.
Monitoring plan does not include the requirement of arising out of Regulation Provision such as obtaining NOC/
consent for plant site operation.

Page 4 of 8
Table 1.3: Environmental Monitoring Plan

Attribute Project Stage Parameter Special Guidance Standards Frequency Duration Location Implementation
High volume sampler Along the road
to be located 50 m Three seasons per (refer table no 4.2)
Construction Air (prevention and 24 hours
Air CO, NOx, SPM, from the plant in the year Hot mix / batching EMU-APRSP
Control of Pollution) Sampling
RPM, and SO2 downwind direction. plant
Rules, CPCB, 1994
Use method specified Two seasons in a Along the road (refer
Operation
by CPCB for analysis year for three years table no 4.3) EMU-APRSP
All essential Along the road EMU-APRSP
Four seasons per
Construction characteristics and Grab sample collected (refer table no 4.8)
Indian Standards for year
some of desirable from source and
Inland Surface Waters
characteristics as analyse as per Standard Grab
Water (IS: 2296, 1982) and
decided by the Methods for Sampling
for Drinking Water (IS four seasons for Surface water sources
Operation Environmental Examination of Water
: 10500 - 1991) three years Table 4.8
Specialist of the and Wastewater EMU-APRSP
CSC and APRDC
Equivalent noise levels Along the road
using an integrated Three seasons per (refer table no 4.12) EMU-APRSP
Construction
noise level meter kept year Leq in Hot mix / batching
at a distance of 15 from dB(A) of plant
Noise levels on dB MoEF Noise Rules,
edge of pavement day time
(A) scale 2000
Noise Equivalent noise levels and night
Three seasons per Along the road
using an integrated time
Operation year for three (refer table no 4.12)
noise level meter kept EMU-APRSP
years.
at a distance of 15 from
edge of pavement
Along the road
Threshold for each
Sample of soil collected Four seasons per (refer table no 4.6)
Construction contaminant set by
Monitoring of Pb, to acidified and year Grab Hot mix / batching EMU-APRSP
Soil IRIS database of
SAR and Oil & analysed using Sampling plant
USEPA until national
Grease absorption Along the road
standards are four seasons for
Operation spectrophotometer (refer table no 4.6)
promulgated three years EMU-APRSP
Borrow
Construction As per Guidelines Visual Observation - Once in a month - Borrow area location Contractor
area
Areas where
Tree Operation As per
Quarterly - plantation is being EMU-APRSP
plantation stage Rehabilitation Plan
done

Page 5 of 8
ENVIRONMENTAL MONITORING LOCATIONS
In addition of the critical locations selected during design stage, the environmental monitoring will also be done at
the construction camp site and any other plant site during construction stage. List of critical locations for caring out
monitoring is presented in chapter 4: Baseline environment.

REPORTING PROCEDURES
Mitigation and enhancement measures adopted in the final design have been identified in the contract documents
and Bill of quantities so that performance and completion is effective. The periodic site visits of the
EO/Engineer/EE of the PU will keep a record of progress as well as the site-specific EMP implementation
records. The frequent meeting of the EO/Engineer with the Contractors will ensure any information and
communication gap with regard to the Construction phase environmental management at construction site; labour
and construction camps quarry and borrow areas etc. It is necessary that the EO/Engineer should visit the sites for
evolving a concept for the Environmental Management with regard to the siting of various construction
requirements. The various reporting guidelines and arrangements are presented in TABLE 1.4. DESIRED
MONITORING AND REPORTING PROCESS AND RESPONSIBILITIES.

Page 6 of 8
Table 1.4: Desired Monitoring and Reporting Process and Responsibilities
Contractor CSC Consultant PIU-APRDC Reporting from
Format Implementation and Oversee Field APRDC to World
Item Stage Reporting to Reporting to
No. Reporting to TA Supervision Compliance Bank)
CU, APRSP EMU, APRSP
Consultant Monitoring
P1 Identification for disposal locations Pre -construction One Time One Time One Time One Time One Time One Time
P2 Setting up of Construction Camp Pre- construction One Time One Time One Time One Time One Time One Time
P3 Establishment of Borrow areas Pre- construction Monthly Monthly Quarterly Quarterly Quarterly Quarterly
Before start of
P4 Establishment of HMP/ BMP One Time One Time One Time One Time One Time One Time
construction
P5 Road Safety and Traffic Management Pre- construction Monthly Monthly Monthly Monthly Quarterly Quarterly
P6 Arrangement for Temporary Land Pre- Construction Monthly Monthly Monthly Quarterly Quarterly Quarterly
Immediately on
During
P7 Pollution Monitoring Pre- Construction Quarterly receipt of Quarterly Quarterly Quarterly
Monitoring
results
During construction
P8 Tree cutting/Stump Removal Monthly Monthly Monthly Quarterly Quarterly Quarterly
period
Identification of Source of water for
P9 Pre- construction One Time One Time One Time One Time OneTime One Time
Construction
During Construction
C1 Details of earth work Monthly Monthly Monthly Quarterly Quarterly Quarterly
period
During Construction
C2 Details of Hot Mix Plant Monthly Monthly Monthly Quarterly Quarterly Quarterly
period
During Construction
C3 Details of landfill locations/ Monthly Monthly Monthly Quarterly Quarterly Quarterly
period
During Construction
C4 Details of Machinery in Operations Monthly Monthly Monthly Quarterly Quarterly Quarterly
period
During construction
C5 Redevelopment of borrow areas Monthly Monthly Monthly Quarterly Half Yearly Quarterly
period
During construction
C6 Safety Check List Monthly Monthly Monthly Quarterly Half Yearly Quarterly
period
Immediately on
During construction After
C7 Accident Report After Accident receipt of Quarterly Half Yearly Quarterly
period Accident
report
During construction During
C8 Pollution Monitoring Quarterly Quarterly Quarterly Quarterly Quarterly
period Monitoring
C9 Enhancement Measures During Construction Monthly Monthly Monthly Quarterly Quarterly Quarterly
Restoration of Construction Sites Immediate after
C10 One Time One Time One Time One Time One Time Quarterly
Construction
O1 Pollution Monitoring During Operation - - - Quarterly Quarterly Quarterly
Page 7 of 8
Contractor CSC Consultant PIU-APRDC Reporting from
Format Implementation and Oversee Field APRDC to World
Item Stage Reporting to Reporting to
No. Reporting to TA Supervision Compliance Bank)
CU, APRSP EMU, APRSP
Consultant Monitoring
Twice a year Twice a year
Monitoring of culvert opening and
O2 During Operation - - - Pre and Post Pre and Post -
longitudinal drains
monsoon monsoon
FORMS TO BE FILLED BY PU/CSC
Form for keeping records of Consent
PU1 obtained by contractor (To be filled by Construction Quarterly Quarterly Quarterly Half Yearly -
Supervision Consultant)
PU2 Checklist for Environment Inspection - - - - - -
PU3 Summary Sheet (To be filled by PU) Construction - - Quarterly Half Yearly -

The reporting formats are presented in the end of the EMP Document

Page 8 of 8
APPENDIX 8.16: TRAINING PROGRAMME ON ENVIRONMENTAL ASPECTS

A comprehensive training programme has been planned for the project by PCC & PIU intended to address all
components of the project. The programme has been intended for all Contractors, Suprevision Consultants and the
Package Unit -APSHP. As and when found necessary PIU in consultation with PCC will select appropriate modules for
the training of contractors and for the training of engineers responsible for supervision and maintenance work. List of
appropriate training modules and their time frames is discussed in subsequent paragraphs..
Training Module Details
The training components may be broadly divided into the following categories:
• Principles and policies for (natural and social) environmental mitigation in development projects;
• Legal and institutional aspects; project mandates;
• Probable (natural and social) environmental impacts and losses in road strengthening and widening projects;
• The EMAP in APSHP consisting of
i) the construction stage environmental concerns;
ii) the environmental designs and implementation plans;
iii) the project entitlement framework;
iv) types and aspects of vulnerability of the EPs;
v) counselling and grievance redressal methods and mechanisms and
vi) financial control mechanisms;
• Monitoring, evaluation and reporting methods and mechanisms and,
• Inter-sectoral and inter-agency collaboration, etc.
Table 1.1 - Training Programme for the EMU
Training Training Components
Sessions
Module I • Principles and policies for (natural and social) environmental mitigation in development projects;
Initiation
• Legal and institutional aspects; project mandates including the WB operational guidelines;
• Introduction to the designs, implementation schedule for APSHP.
Module II • Probable (natural and social) environmental impacts and losses in road strengthening and
Project widening projects;
Specifics
• Basic features of the EMAP and the RAP in APSHP.
Module III • Construction stage environmental concerns including hot-spot mitigation matrices
EMAP
• Environmental designs and implementation plans; Location-wise and class-wise;
• Project entitlement framework including group, individual or community entitlements; the
verification procedure; conditions/circumstances under which additional persons may be
considered affected/entitled;
• Vulnerability of the EPs; special measures or additional supports proposed in the entitlement
framework to assist vulnerable groups to protect their livelihood;
• Counselling for each category of entitled persons, households or groups; method and scope of
counselling; Completion and distribution of entitlement photo identity cards;
• grievance redressal methods and mechanisms; market value assessment method and mechanisms
proposed in APSHP;
• Financial control mechanisms including disbursement of compensation/assistance payments in a
transparent method.
Module IV • Laws and other statutes associated with the proposed project such as the Labour Laws, the

Page 1 of 2
Training Training Components
Sessions
Construction various pollution control acts, Environmental (Protection) Act, Mining Act, Hazardous Materials
stage issues (Handling) Act, Forest (Conservation) Act, Land Acquisition Act, Draft National Rehabilitation
Policy, etc;
• Efficient construction activity monitoring; compliance monitoring;
• Environmental clauses in APSHP contract documents and their implications.
Module V • Monitoring requirements; monitoring techniques;
Operation
stage issues • Environmental evaluation techniques;
• Reporting requirements and mechanisms for APSHP.
Module VI • environmental surveys including ambient air, noise, biological and water quality surveys;
Long term
• social surveys, survey questionnaire design, sampling techniques;
issues
• data storage, analysis and retrieval;
• contract documents and incorporation of environmental clauses;
• community consultation and participatory technology generation methods;
• legal or statutory requirements for environmental, social and forestry clearance of road projects
and,
• contingency planning and management, etc.
The above are the major areas of training and discussion and is not an exclusive list. The additional areas of training, in
order to develop long term capacity in the EMU will also be arranged, as desired/planed.

Page 2 of 2
APPENDIX 9.1: MODIFICATIONS TO MORTH CLAUSE 111, MEASURES FOR
SAFEGUARDING ENVIRONMENT

The Contractor shall abide by the regulation and other stipulations made by the MoEF and PCB at the time
of according Environmental Clearance of the Project for implementing purpose.

Sub-Clause 111.1 General

Delete the second sentence of the first paragraph.


Add the following after the first paragraph:
“The Environmental Management Plan (EMP) has been prepared by Independent Review Consultant for the
Employer to provide the Contractor with measures to be taken to manage environmental matters during the
Contract period. The enhancement measures are given in the drawings under Chapter 8: Mitigation &
Enhancement of EMP (Part A: Main Report). The issuance of the Environmental Management Plan
does not relieve the Contractor of the responsibility to ensure total compliance with current laws, rules and
regulations in force governing pollution and environmental protection applicable to the State of Andhra
Pradesh or where the Works are situated. This total compliance is required during the construction phase for
construction related activities. The Contractor must carry out the requirements of the EMP and as listed
under Sub-Clause 111.15.

In all situations where the Contractor is required to obtain approval or a license, from Statutory Authorities
or Landowners independent of the Employer, for any activity associated with the Works to be executed
under the contract, evidence of the approval or license must be provided to the Engineer for his consent
prior to commencement of any operation associated with the work which necessitated this approval or
license.

All costs associated with environmental protection during the construction phase (for construction related
activities only) including obtaining the necessary approvals and licenses, shall be deemed to be included in
the rates for items of work included in the Bill of Quantities. The items mentioned in Bill No. 1(b), which
have been covered in MoRT&H specifications or Section VI of Bid document (Technical Specifications) will
not be paid separately.

The Contractor shall preserve existing trees, plants, and other vegetation that are to remain within or adjacent
to the Works and shall take all precautions necessary to prevent damage or injury thereto. Any accidental
clearance shall be replanted to the satisfaction of the Engineer and at the cost of the Contractor.

On completion of the Works, all areas disturbed by the Contractor’s construction activities (such as areas of
compounds, material storage, access and haul roads) shall have been restored to their original condition, and
agreed as having been restored by the relevant property owner or as may be acceptable to the Engineer.
Restoration of an area shall include clearing excess material, scarifying the surface, top soiling, seeding and
planting. The cost of this work shall be deemed to be included in the rates generally.

The Contractor’s on-site establishment shall include a nominated environmental representative, available at
any time, who will be responsible for all environmental matters associated with the Works. The nominated
person shall have a working knowledge of National and State current laws, rules and regulations in force that
relate to the protection of the environment with respect to the Works to be undertaken as part of this
Contract.

If requested by the Engineer, the Contractor shall on two weeks notice, nominate and make available site
staff of foreman level and above for training in the environmental aspects of road construction. The staff to
be included in the training shall be chosen by the Engineer. The costs of providing personnel for the
environmental training are deemed to be included in the rates generally.”

Sub-Clause 111.2 Borrow Pits for Embankment Construction.

Add the following after the first sentence:

Page 1 of 5
“Where borrow material (including subgrade and sub-base) is required to complete the Works, details of the
location and extraction methods of the borrow sites shall be submitted by the Contractor to the Engineer for
his consent. The submission to the Engineer shall include the required approvals, licences, terms and
conditions for extracting the material from the relevant Statutory Authorities, and landowners, responsible
for the area in which the proposed borrow area is to be located. The edges of borrow sites shall be no closer
than 3 metres from any fence line or boundary. Adequate clearance shall be provided for the construction
catch drains. Borrow sites shall have adequate drainage outlets unless the relevant landowner has agreed that
the borrow area is to create a permanent tank or dam.

Cut batter slopes shall not be steeper than 3 to 1 and shall be left by the Contractor in a tidy and safe
condition to the satisfaction of the landowner and the Engineer.

Written clearance from the landowner/village head shall be obtained before leaving a site from which
borrow material has been extracted. Copies of such clearances shall be provided to the Engineer prior to
issuance of the Taking-Over Certificate.

Site preparation for borrow areas shall be in accordance with Section 201, Clearing and Grubbing, of this
specification. Topsoil is to be stripped and stockpiled in accordance with Sub-Clause 301.3.2. Where it is
required to replace the topsoil as part of the reinstatement of borrow areas, the topsoil will be replaced and
seeded in accordance with Sub-Clause 308.3, immediately after the area is no longer required for borrow.

Access roads and tracks to borrow areas shall be maintained during use and left in good condition after
closing down the borrow areas.

The guidelines Borrow Areas Management are given in Appendix 8.2 of EMP. The cost of maintaining and
reinstating/redevelopment of borrow areas in accordance with the requirements of this Clause shall be
deemed to be included in the rates for the borrow material.”

Sub-Clause 111.3 Quarry Operations.

Add the following after the first paragraph:


“Where the Contractor intends to operate his own quarries, whether it be for obtaining naturally occurring
materials or manufacturing product, it will be the responsibility of the contractor to obtain the necessary
approvals and licenses from the relevant Authorities and subsequent operations will be in accordance with
the requirements of these Authorities.

The costs associated with setting-up and maintaining a quarrying operation is deemed to be included in the
rates for the supply of material.”

Sub-Clause 111.5 Pollution from Hot Mix Plants and Batching Plants.

Add the following after the first paragraph:


“Siting and operation of Hot Mix and Batching Plants shall be undertaken in accordance with all current
rules and regulations for protection of the environment. The Contractor will be responsible for obtaining
relevant approval from the Authorities responsible for administering the environmental rules and
regulations.”

Sub-Clause 111.6 Substances Hazardous to Health.

Add the following after the first paragraph:


“The use of any herbicide or other toxic chemical shall be subject to the approval of the relevant Authorities
and strictly in accordance with the manufacturer’s instructions. The Engineer will be given at least six (6)
working days notice of the proposed use of any herbicide or toxic chemical.

A register of all herbicides and other toxic chemicals delivered to the site, shall be kept and maintained up to
date by the Contractor. The register shall include the trade name, physical properties and characteristics,

Page 2 of 5
chemical ingredients, health and safety information, safe handling and storage procedures, and emergency
and first aid procedures for the product.”

Sub-Clause 111.8

Add the following after the first sentence:


“At the direction of the Engineer, the Contractor shall provide for laying of dust palliative on, or watering of,
the works and of roads, and other areas immediately adjacent to the Works. The materials and methods used
for dust control will be subject to approval of the Engineer.”

Sub-Clause 111.11

Delete and replace with the following:


“Any structural damage caused to public or private property attributable to the Contractor’s construction
equipment or method of working, shall be made good without delay and to the acceptance of the affected
party without any extra cost.”

Sub-Clause 111.12

Delete and replace with the following:


“Compliance with the sub-clause 111.11 will not relieve the Contractor of any responsibility for complying
with the requirements of any Public or Statutory Authority in respect to use of their property or services. The
costs of compliance with Clause 111 shall be deemed to be included in the rates for items included in the Bill
of Quantities.”

Sub-Clause 111.13.

Add new Sub-Clause:

“The Contractor’s attention is drawn to the Discharge Standard promulgated under the Environment
Protection Act, 1986, and the Contractor’s responsibility to adhere to these limits. All waste arising from the
project is to be disposed of in a manner which is acceptable to the State Pollution Control Board and the
Engineer.”

Sub-Clause 111.14

Add new Sub-Clause:

“The Contractor shall plan and execute the work so as to minimize the possibility of pollution of areas
adjoining the construction work sites or any area utilized by the Contractor for the project, from
contaminants such as petroleum products, trade waste, garbage and other noxious substances. Impervious
bunds shall be constructed around all fuel, oil and liquid material storage areas large enough to contain at
least 120% of the total storage volume.

Drainage of these bunded areas shall be provided with lockable gate valves. The gate valves shall remain
closed and locked at all times except during the controlled removal of storm water from the bunded area.
The valves shall be manned at all times when they are unlocked or open.”

Sub-Clause 111.15

Add new Sub-Clause:

“The Contractor must carry out the following as part of the Works. The cost of carrying out these works
must be contained in the rates submitted by the Contractor in the bills of quantities.

Sub-Clause 111.15.1 Flora and Fauna Management

Page 3 of 5
Action during construction
Potential impact Action Timing
Unnecessary Provide a clearing programme for Engineer’s Prior to start of
clearance of trees approval. The clearing programme will include: construction.
and vegetation
Schedule of activities,
Assignment of responsibilities,
Training of Contractor’s personnel,
Field maps or survey drawings at a scale of not less than
1:2000 delineating areas to be cleared.
Identify and mark road construction boundaries on- For duration of
site with the Engineer and advise construction construction activities.
workers.
Delineate limits of access tracks, stockpiles and Prior to start of
borrow pits, so as to minimize the impacts on construction
vegetation.
Transplant trees in cleared area where practical. Prior to construction.

Accidental Review design for each road section and construction For duration of
clearance camp. construction activities.

Should excessive clearing inadvertently occur, replace Without delay.


topsoil, replant with appropriate local species,
undertake any other practical reinstatement, and
fence to limit further incursion.

Sub-Clause 111.15.2 Water resources, Drainage, Flood control and Sediment control

Action during construction


Potential impact Action Timing
Haulage of material to embankments or other areas At all times
of fill shall proceed only when sufficient spreading
and compaction plant is operating at the place of
deposition

Sub-Clause 111.15.3 Waste Management

Action during construction


Potential
Action Timing
impact
Accidental Clean up any accidental spillages of Pollutants Immediately on
Spillages occurrence
Ensure the required dispersants and persons trained in At all times
the use of the materials are available on site to clean up
any accidental spillages.
Ensure that the wastes generated from the clean up of Immediately on
spillages are disposed of in an approved way. occurrence
Clean and maintain all silt traps. Regularly (frequently
during wet season)
Environmental All employees shall be obliged to maintain a clean work
nuisance and site and an inspection made at the end of each work
visual intrusion day to ensure that the work site is left tidy and rubbish-
free.

Sub-Clause 111.15.4 Air Quality Management

Page 4 of 5
Action During Construction

Potential impact Action Timing


Air Pollution Cleared vegetation, timber and other combustible waste
material shall not be burned.
Dispose of waste materials other than by burning At all times

Sub-Clause 111.15.5 Noise Control


Action during construction

Potential impact Action Timing


Increased ambient All work shall be carried out without unreasonable At all times
noise levels noise and disturbance.

Increased ambient Limit construction and equipment operation near Duration of


noise levels dwellings and sensitive areas such as schools and construction
hospitals to the hours that the Contract specifies.
Refer to Sub-Clause 45.2 of Section 5 Part II –
Conditions of Particular Application.

Page 5 of 5

You might also like