HUDA Regulation

HYDERABAD URBN DEVELOPMENT AUTHORITRY

ABSTRACT

Municipal Corportions; Municipalities and other areas falling in Urban Development Authority areas –
Rationalisation of floor Area Ratio (F.A.R.) and other Standards of Building Requirements – Orders –
Issued.

---------------------------------------------------------------------------------------------------------------------------------

MUNICIPAL ADMINISTRATION AND URBAN DEVELOPMENT (M1) DEPARTMENT

ABRIDGED VERSION OF G.O.Ms.No. 423, M.A. Dated 31st July, 1998.

O R D E R:

Government after careful examination of the matter in detail issue the following orders:

1. PROCEDURE FOR OBGTAINING BUILDING PERMIT:

1.1. No person shall carry out any development or building construction activigty without obtaining
permit from the Authority, except in the following cases and unless exempted by State or Central
Acts/Rules/Orders:-

(a) No prior sanction of building applications are necessary for the construction of individual residential
buildings in plots upto 100 Sq.mtrs. and height restricted to 10 Mtrs. I.e. Ground + 2 Upper Floors
(without stilts) subject to the following conditions:

i. such plot should be less than or equal to 100 Sq.mtrs. as per the following:
a. Part of an approved layout or sub-division.
b. Allotted by or purchased from a public agency like Housing Board,Housing Corporation
etc.
c. Covered byb pattas issued by Revenue Department.
d. T.S. Record or Registered Sale Deed of Date prior to the date of these Orders.
ii. the construction shall be carried out, strictly in accordance with the MasterPlan/Z.D.P., Zoning
Regulations, Building Bye-laws/Rules etc.
iii. the owner shall file with the local authority, copies of drawings of proposedbuilding along with
necessary fee/charges as fixed by the local authoritiestogether with attested copies of ownership
documents and layout plan beforeundertaking the construction.
iv. the owner shall file with the local authority an undertaking starting that he shall leave and
surrender land for road widening, if any, free of cost and he will not violate any rules, building

HUDA-BUILDING BYE LAWS Page 1


bye-laws, and that in case of violations the local authority would be at liberty to summarily remove
such deviations without prior notice and at owners cost.
v. such application filed with the local authority shall be valid for a period of 3 years for completion of
building and it would be mandatory to file building completion certificate with the concerned local
authorities.

(b) In respect of construction of individual Residential buildings in plots upto 300 Sq.mtrs. and height
upto 10 mtrs. I.e., Ground + two Upper floors (without stilts) no prior approval from the local
authority/Urban Development Authority is necessary, provided: that such type of individual residential
buildings are got approved from empanelled licensed personnel i.e., qualified Architects, Engineers,
Town Planners and Surveyors; and it shall be ensured by the licensed technical personnel that the
construction is undertaken and carried out as per the approved building plans. Such plots should from
part of an layout or sub-division approved by the competent Authority. Further,

i. The licenced technical personnel shall be completely and solely responsible for ensuring that such
residential buildings conforms to all regulations, bye-laws, other stipulations in force.
ii. The construction shall be commenced by the owner only after filing with the local authority a copy of
the building drawings approved by the licensed technical personnel along with prescribed fee/charges
as fixed by the local authority together with attested ownership documents, copy of layout/sub-division
etc., in the prescribed format.
iii. The owners shall file an undertaking stating that he shall leave & surrender the land affected in road
widening if any, fee of cost and that, he shall not violate any Regulations, bye-laws or the approved
drawings signed by the licensed technical personnel and in case of any violations, the local authority
would be at liberty to summarily remove the same without prior notice at the owners cost.
iv. Such building drawings approved by the licenced technical personnel shall be valid for three years
from the date of filing a copy of approved building drawing with the local authority, Building completion
Certificate shall be filed by the owner with the local authority through the licenced technical personnel
within this period.
v. If it comes to the notice of the local authority that the approval of building drawings are in violation of
rules or if the facts have been mis-represented in the following cases, the licensed technical personnel
will be held solely responsible and his license will e liable for cancellation, disqualification, etc.
a. If the building proposal is approved in a plot forming part of unauthorized Layout, or sub-
division.
b. If the building proposal is approved in violation of Zoning Regulations, Bye-laws, Master
Plan/Zonal Development Plan etc.
c. If the building proposal is approved in a plot of 300 Sq. mtrs. Or less but the same is
actually having an extent more than 300 sq. mtrs. on ground.
d. Where the dimensions of the plot are not tallying with documentary plan, ground situation
to that of sanction plan by licensed technical personnel.
e. if the site details are wrongly represented in the drawings.

vi) If it come to the notice of the local authority that the owner after obtaining sanction of building by the
licenced technical person takes up the construction in violation of Rules, Regulations etc., and against
sanctioned plan, action will be taken against such construction as per rules including demolition by the
local authority.

HUDA-BUILDING BYE LAWS Page 2


vii) The local authority shall also monitor the construction of above buildings and take necessary action
against unauthorised constructions/deviations as per rules.

1.2 However, any person can also apply to the concerned local authority for sanction in respect of
buildings in plots upto and including 300 Sq.mtrs.

1.3 For all other types of residential and non-residential buildings prior written permission of the local
authority/Urban Development Authority is necessary.

2. TIME LIMIT FOR GRANT OR REFUSAL OF BUILDING APPLICATION

2.1The time limit for disposal of building applications is as follows:

a) Individual Residential Buildings .. 15 days


b) Other Buildings .. 30 days

2.2. If within the specified time period mentioned above the authority fails to intimate in writing to the
person or body who has submitted the application for building sanction its decision of refusal or
sanction, such applications together with plans and statements shall be deemed to have been
sanctioned, provided the deemed sanction shall not be construed as authorising any such person or
body to carryout the construction or works in contravention of or against any regulations bye-laws or any
other law in force.

3. REVIEW OF REJECTIN OF BUILDING APPLICATIONS:

3.1 After rejection of building applications on technical grounds and within seven days Of such refusal
the architect/Licenced Technical personnel and owner may represent the case to the local body on any
working day between 3.00 p.m. to 5.00 p.m.After hearing, the concerned Authority shall communicate its
decision on the representation within ten days of such hearing.

3.2. If the architect or owner or both are not satisfied with the decision on their representation then he
may file a review petition along with 25% of permit fee together with reasons and grounds for reviewing
earlier decisions. The Review Petition shall be referred to a SELECT COMMITTEE whose decisions
shall be final.

The SELECT COMMITTEE shall consist of the following:

a. Two Practising Architects.


b. One Retired Town Planner not below the rank of Joint Director At the time of Retirement.
c. Chief City Planner/City Planner of concerned local authority or Chief
PlanningOfficer/Planning Officer of concerned Urban Development Authority who shall be
the conveners of the Committee for the cases of their jurisdiction.

3.3 The Select Committee shall meet with in seven days from the date of review Petition filed and
communicate its decision within ten days of its meeting.

HUDA-BUILDING BYE LAWS Page 3


4. SITE AND BUILDINGS REQUIREMENTS:

1. For Residential, Commercial, Institutional and other non Industrial buildings, andFor
different areas are as follows:

TABLE FOR F.A.R.

Statement Plot size Proposed Road width as per Notified Master Plan/Zonal
Development Plan.

Below 12 12 to 18 18 Mts. & Maximum Height


Mts. Mtrs. above. in Mts.

(A) Below 200 1.00 1.25 1.25 10 (no stilt).

For Hyd. & VSP 200 to below 1000 1.00 1.25 1.33 15 *

Mpl. Corpns. & Gaddiannaram Gram Panchayat. 1000 to below 2000. 1.25 1.33 1.50 **

2000 & above. 1.25 1.50 1.75 **

(B) Below 200 1.00 1.25 1.30 10 (no stilt)

For other MPL. 200. to below 1.10 1.30 1.40 15 *


1000
Corporations. 1.25 1.40 1.60 **
1000 to below 2000
1.25 1.50 1.75 **
2000 & above

© Below 200 1.00 1.25 1.33 10 (no stilt)

For mpltys., within UDA areas of HUDA, TUDA, KUDA, 200 to below 1000 1.25 1.33 1.50 15 *
VUDA, VGTUDA, SSSUDA.
1000 to below 2000 1.33 1.40 1.60 **

2000 & above 1.40 1.50 1.75 **

(D) Below 200 1.25 1.25 1.33 10 (no stilt)

For Gram Panchayats falling within UDA areas of HUDA, 200 to below 1000 1.40 1.50 1.60 15 *
TUDA, KUDA, VUDA, VGTUDA, SSUDA.
1000 to below 2000 1.50 1.60 1.70 **

2000 & above 1.75 1.85 2.00 **

* Individual residential buildings upto 300 sq.mtrs. Max. height 10 mtrs.

* Individual Residential buildings in plots larger than 300 Sqm. Max. height 13 metrs. No stilt.

For Group Housing/Apartments in plots of 450 Sqmtrs. Max. height 18 mtrs. Including and
above. stilt.

HUDA-BUILDING BYE LAWS Page 4


** No height restriction subject to setbacks as per rules and clearances from Fire Services &
Airport Authority & as per the stipulations of Multi-storied Building Regulations.

In case of individual residential building 15% of permissible F.A.R. shall be added for
calculation of gross FAR for areas such as garage, servant room, balconies, staircase, and
portico.

The common areas shall be included in the calculation of gross FAR by adding 30% of
prescribed FAR in the case of Group Housing/Apartment.

In the case of Commercial/Institutional Buildings the Gross FAR shall be calculated by adding
35% of the prescribed FAR.

Common areas shall include:

a. Air-conditioning plant room, electrical transformer cabin, pump, - house.


b. Watchman booth, garbage shaft.
c. Corridors, Staircase, Lift blocks.
d. Balconies.

The width of the balcony shall not be more than 1.2 mtrs. if the building setback is 4.00 mtrs.

If the building setback is 5.00 mtrs. and above the maximum width of the balcony can

be 1.5 mtrs.

4.3 FOR EXAMPLE: In a plot proposed for Apartment complex/Group Housing Scheme, if the
prescribed permissible FAR is 1.50 then the gross FAR shall be 1.50 + 30% of 1.50 = 1.95
which shall include all common areas & structures (excluding parking areas to be provided)
and as illustrated below:

Building Plot Prescribed Gross FAR (inclusive of common/ Total buildable area including common areas (except
Occupancy size FAR parking area in sq.mtrs.).
Areas structures excepting

Parking areas.

Residential 1000 1.5 1.5 + 30% of 1.5 = 1.95 1950

Non-Residential. 1000 1.5 1.5 + 35% of 1.5 = 2.025 2025

HUDA-BUILDING BYE LAWS Page 5


9. RESIDENTIAL BUILDINGS:

Row Housing:

i) Minimum site area for permitting Row Housing Development. … 1000 Sq.mtrs.
ii) Maximum Plot size. … 125 Sq.mtr. Minim plot size. … 50 Sq.mtr.
iii) Minimum width of plot … 4.5 to 8.0 Mtr.
iv) Minimum width of internal road … 9.00 Mtr.
v) Maximum No. of Plot permissible in a row. 8
vi) Minimum space between two blocks/row … 6 mtrs.
vii) Building set backs .. Front. … 3.00 mtrs. .. Rear. … 1.50 mtrs.
viii) Maximum height of the building … 6.00 mtrs. i.e.(Ground=One Upper floor)
ix) Minimum Open space (park) in plots .. 10% ,,2000 Sq.mtrs. & above.
x) Corner plots shall be splayed with 3 mtrs.
A. Individual Residential Buildings:
1. Maximum permissible F.A.R. : Refer relevant statement
2. Maximum Plot coverage:
Plot area in Sq.mtrs. Maximum permissible coverage.

a. Below 500 As per min. building setbacks (as per items No.3).
b. 500 & below 2000 50%
c. 2000 & above 1000 Sq.mtrs. or 40% of the plot area whichever is higher.

3. Building setback Requirements:


i) For buildings upto 300 Sq.mtrs. plot area and upto 10 mtrs. height:
Plot size in Sq.mtrs. Setbacks in Mtrs.

Front Rear Sides

Upto 50 0.75 -- --

50 and upto 75 1.00 1.00 0.50

75 and upto 100 1.25 1.00 0.50

100 and upto 150 1.50 2.00 1.00

150 and upto 200 2.00 2.00 1.25

200 and upto 300 3.00 2.00 1.50

ii) For buildings above 300 Sq.mtrs. of plot area and height upto 10.0 mtrs. minimum building setbacks:

Front (Mtrs.) Rear (Mtrs.) Sides (Mtrs.)

Upto 12.0 Road. 3.00 a. 1/4th of plot width with 1.5 Mtr. On one side.
12.0 and upto 3,00 OR
18.0 Road. 4.00 b) Where 1/4th of side setback is more than 6.0 mtrs. minimum of 3.0
Above 18.0 Road. 3.00 Mtrs. in each side.

HUDA-BUILDING BYE LAWS Page 6


For buildings above 300 Sq.mtrs. of plot area maximum height shall be 13 mtrs., i.e., Ground + 3 Floors
including height of the plinth.

For this additional 3.00 mtrs. heights there shall be increase of 1.0 mtr. To the setbacks Prescribed for
buildings in area more than 300 Sq.mtrs. and upto 10 mtrs. height.

4. OTHERS

A. A Garage not exceeding 3 x 6 mtrs. in size with a maximum height of 2.50 mtrs. will be allowed
abutting rear and side boundary only in case of plots of 300 Sq.mtrs. and above.
B. A servant room not exceeding 9.0 Sq.mtrs. with a latrine of 2.00 Sq.mtrs. in area with a maximum
height of 2.75 mtrs. will be permitted in the rear open yard only in case of plots having an area of
500 Sq.mtrs. and above.
C. In case, if the site conditions or the design demands a 10% of relaxation of setbacks (except
F.A.R) can be availed automatically by the individual in plots upto 300 Sq.mtrs. this relaxation can
not be availed in respect of FAR and height of the building.
D. No stilt Floor shall be allowed in individual residential buildings. If a portion of the ground floor is
used for parking it will be counter in FAR.
E. The individual residential buildings shall be permitted with 15% of permissible fAR towards
garrage, servant room, balconies, staircase and portico.

C. GROUP HOUSING / APARTMENTS SCHEMES:

1. Group Housing Schemes means the development of buildings having FIVE or more multiple dwelling
units and common services on a given site or plot in single or multiple Blocks, with-out customery sub-
division of land by way of individual plots.

2. Minimum Plot Area : 450 Sq.mtrs.

3. Minimum Abutting Road width :

Group Housing shall be permitted on 12 mtrs. wide roads. However, Group Housing shall Also be
permitted on 9 mtr. Wide road subject to handing over of 3 mtrs. wide strip of land on the frontage of
plot to the local authority free of cost, subject to the conditions that the Remaining plot shall be 450
Sq.mtr. or more.

The local authority shall pay the area and utlise it for public purposes. Construction of compound wall
will be permitted after leaving 3 mtr. Wide strip.

4. Maximum plot coverage : 40%

Maximum permissible F.A.R. : Refer relevant statement

HUDA-BUILDING BYE LAWS Page 7


5. Building set-back requirements :

The following are the minimum setbacks to bde left around the building:

Plot size in Sq.mtrs. For building height

12.0 mtr. Or stilt + three floors. Above 12.0 mtrs. and upto 18 mtrs. i.e., stilt + five floors.

Upto 1000 3.00 mtrs. 4.00 mtrs.

Above 1000 & upto 2000 4.00 mtrs. 5.00 mtrs.

Above 2000 5.00 mtrs. 6.00 mtrs.

Note: i) In case of front setback it will be as per building line i.e., 3.00 mts. upto12.0 Mtrs. 4.00 Mtrs. for
12.0 to 18.0 Mtrs. and 6.0 Mtrs. above 18.0Mtrs. road width or setback prescribed above whichever is
higher.

i. The distance between two blocks shall not be less than half of the heightof the talleeer
block or building.
ii. It is permitted to transfer one metre of setback from one side to the other side which need
not be uniform and at any given point such transfer should not be more than one metre
subject to maintaining of minimum building line in the front.

6. Ventilating spaces for water closets and bathrooms if not open to front, sides or rear open spaces
shall open to a ventilation shaft or size not less than 4.00 Sqmtrs. with a minimum of width of 1.5 mtrs.

RECREATIONAL OPEN SPACE (TOT-LOT)

a) Plot upto 2000 Sq.mtrs. : 5% of plot area

b) Plots above 2000 mtrs. : 10%

The area left towards totlot shall be open to sky and should be provided on Ground
Level.In the case of group housing being developed with more than one block, the
Recreational open Space may be provided with the mandatory open space between the
two blocks after 3 metres wide circulation space is left along the building. The totlot shall
be provided at ground level andShall be open to sky.

1. PARKING REQUIREMENTS

The standards of parking requirements for Group Housing/Apartments are modified asDetailed below:
A. CAR PARKING:

Authority Area Area of Flat Parking Requirement (One car Parking space equal to 20 Sq.mtrs.)

1. Municipal Corporation Area. a. Below 100 Sqm. 1 Car/Every two flats


b. Above 100 Sqm. 1 Car/Every one flat

2. Other Areas of Urban Dev. a. Upto 40 Sqm. 1 Car/Every 4 flats


Areas excluding Mpl. Corpn. b. 40-60 Sqm 1 Car/Every 3 flats
Areas. c. 60-100 Sqm 1 Car/Every 2 flats
d. Above 100 Sqm. 1 Car/Every one flat

3. Visitors Parking 1 Car/Every 10 flats.

HUDA-BUILDING BYE LAWS Page 8


A. SCOOTER PARKING:

For all areas


(a) Upto 40 Sqm. 5 Scooters/every six flats.
(b) 40-60 Sqm. 3 Scooters/Every four flats.
(c) 60-100 Sqm. 1 Scooter/Every two flats.

2. Visitors parking 1 Scooter/Every five flats.

i. The parking shall be provided only on stilt floors.


ii. In plots of 1000 Sq.mtrs. and above, where residential apartments are taken up two stit parking
will also be permitted if necessary. To facilitate this developments, height restriction for construc-
tion on plots of above 1000 Sq.mtrs. is relaxed. However, such constructions should adhere to
theMulti-storied building regulations.
iii. In plots of 2000 Sq.mtrs. and above parking will be allowed in basement and on stilt floor. The
basement will be allowed from the building line on the front side, on remaining sides it will be
permitted after leaving 1.5 mtrs. from boundary wall.
iv. One set of Toilet of 1.2 M x 2 M separately for ladies and gents shall be provided in the Stilt Floor.
This shall not be included in F.A.R.
v. Parking requirements shall be deemed to have been fulfilled in a residential Group Housing
Complex which is built within the maximum permissible F.A.R. if the entire stilt floor and/or
basement wherever permitted is used for parking except the portion used for the stair case & lift.

9. SPECIAL REGULATIONS:

1. The following are the Special Regulations to maintain special characterstics of Banjara Hills and
Jubilee Hills areas covered by Block No.1 & 2 of Municipal Corporation of Hyderabad, Ward No.8 and
Part of Block No.3 of Municipal Corporation of Hyderabad Ward No.8 comprising.

a) Areas covered by part of the Jubilee Hills Cooperative Housing Society’s Layout.
b) Areas covered by NISIET and Yousufguda Police Lines which fall within Zonal Development
Plans for the Planning Divisions IV and V.
i. Maximum FAR for Residential Buildings .. 1.00
ii. Maximum FAR for Notified Commercial Areas .. 1.50
iii. Minimum road width for commercial complexes subject to land use as per Master
Plan/ZDP .. 18.00 Mtrs.
iv. Maximum permissible height for Residential Buildings … 10.00 Mtrs.

2. Building Line for plots abutting certain important Roads in Hyderabad.

For certain important roads like Inner Ring Road, National High-ways etc., to be notified from time to
time and as given hereunder, a minimum building line of 6 mtrs. is prescribed for all, types of
Residential, Institutional, Educational and Industrial Buildings.

For commercial complexes and mixed occupancies like shopping on Ground floor and other uses on
upper floors a minimum building line of 8 mtrs., is prescribed. However, the Upper floors are allowed
with front setback of 6 metres.
HUDA-BUILDING BYE LAWS Page 9
However, if the front setback to be provided as per stipulation is more than the building line mentioned
above, the same shall be provided.

a. Inner Ring Road.


b. Portions of National Highways passing through HUDA Areas.
c. Road linking Ameerpet Cross Roads with Greenlands.
d. Road between Lakdikapool to the souther and of public gardens.
e. Punjagutta junction to Lakdikapool viz Khairtabad
f. Liberty Junction to Narayanaguda Junction via Himayathnagar.
g. Liberty Junction to Nayapool via Abids and Mojamjahi market.

FEES AND CHARGES LEVIABLE FOR BUILDING & LAYOUT APPLICATIONS:

A. Development Charges (under Section 27 & 28 of the AP Urban Areas (Development) Act, 1975
– Rates as given in G.O.Ms No. 51, MA, Dated: 5-2-1996.

B. Processing Charges: Building Applications @ Rs. 5/- per sq. mt of proposed built up area;
Layout applications and Sub-Division applications @ Rs 2/- per sq. mt of land

C. Stationery & Publication Charges: Rs. 5000/- per application

D. In case of plots/sites in unapproved layouts or not forming part of any layout – 10%
proportionate open space charges and layout charges.

E. HUDA Board charges (applicable in Appeal/ NOC Cases)

At the time of application only 10% of Processing Charges are collected. HUDA intimates the rest of the
charges and fees after the technical approval.

HUDA-BUILDING BYE LAWS Page 10


TIME-LIMIT FOR DISPOSAL OF APPLICATIONS IN HUDA:
1. Building Applications: 30 days
Scrutiny and approval & intimation of balance fees & Charges: 20 days
Payment of Fees & Charges & release of Plan to local body: 10 days
Total: 30 days

2. Layout Application: 60 days


Scrutiny and approval & intimation of balance fees & Charges:30 days
Payment of Fees & Charges & release of Plan to local body: 10 days
Completion of layout demarcation, fencing of mortgaged 10 days
Release of layout after compliance of mortgage deed, submission of Non Encumbrance
Certificate 10 days
Total : 60 Days
Final Layout Release:
Scrutiny of application & approval for Final Layout: 10 days
Handing over of open spaces & roads to local body
& submission of their Report 15 days
Release of Final Layout to local Body & Relinquishment deed:10 days

3. NOC Cases:
(A) B Normal permissible cases: 30 days
Scrutiny and approval & intimation of balance fees & Charges:20 days
Payment of Fees & Charges & release of Plan to local body: 10 days
Total : 30 days
B)B Under Appeal Clause by HUDA Board: After approval by HUDA Board:
intimation of fees & Charges: 10 days
Payment of Fees & Charges & release of NOC : 10 days

4. Land Use Certificates 2 days in respect of Non-MCH Area


3 days in respect of MCH Area

HUDA-BUILDING BYE LAWS Page 11