You are on page 1of 4

Substation Automation System – Value Additions in Condition Monitoring

This paper discusses the value for Bus CVTs, it is implemented in


additions made by automation system BCUs supplied for measuring Bus
in the area of condition monitoring of CVTs. Logics for Bus CVT become
CVT, imbalance bay/feeder currents difficult for the station without SAS.
which shows the intactness of primary For such stations, alternatives may be
circuit and monitoring of measuring explored for the availability of spare
system. analog channels in any numerical
relay available in the station.
CVT Condition Monitoring
The logic implemented in the BCU has
One of the best methods of been shown in Fig.1.
monitoring the healthiness of CVT is
by monitoring drift between phase R-N VOLT
Abs
1
2
Sub
Y
Abs I/P SET UP
LIMIT
Y

secondary voltages. As per


POWERGRID O&M guidelines, drift I/P SET UP
Abs Sub Abs Alarm to HMI
Y-N VOLT 1
Y or BO of the
Y
2 LIMIT

between CVT secondary Ph-E voltages


should not be more than 2V. B-N VOLT Abs
1
2
Sub
Y
Abs I/P SET UP

LIMIT
Y

Accordingly, there was schedule of


monitoring the same quarterly. Now a Fig.1 Logic for measuring CVT
days, numerical relays/BCUs have Secondary Drift.
facility of logics to be implemented on
real time conditions. This opportunity Equivalent threshold value of 2V can
has been grabbed and logics be set in Set Upper Limit gate (This
implemented at Kalivanthapattu SS gate is available in Siemens supplied
as a sample basis. The concept IEDs – equivalent gate available may
considered to implement this be used incase of other suppliers).
monitoring is as follows:
The logics were implemented at
Only one core per CVT is considered Kalivanthapattu SS for all the CVT
for monitoring of secondary, metering cores and tested
preferably metering core due to higher successfully at HMI and Remote HMI
accuracy. Hence logics are written alarm for the set drift limits.
onto respective BCU (metering core
always connected to BCU) that was Unlike knowing the drift in monthly or
supplied along with SAS. The stations, quarterly measurement, the drift
where BCUs are not available (ie., violation is known instantaneously at
stations without SAS) logics can be HMI and Remote HMI. This will help in
built in numerical relays ie., on preventing sudden failure/blasting of
protection core of CVT and CVTs and hence reducing line outage
annunciation may be wired to RTU due to such unwarranted occurrences.
through a binary output of numerical This information speeds up taking
relay.

Logics for feeder CVTs, are decisions for the replacement of faulty
implemented in main bay BCUs and CVTs and hence the replacement.
Current Imbalance Monitoring
Monitoring 230kV Bus Coupler and Transfer Bus
Coupler.
Current in EHV circuit is generally
balanced one with small variation. Except for 400kV tie bays, metering
Imbalance in primary circuit may core CTs are available to BCUs for all
happen due to the following reasons the aforementioned cases. For Tie bay
measurement, the logic is built in LBB
• Mis – alignment of isolators relay ie., on protection core CT. And
• Loosely connected jumpers Tie LBB relay is not connected to LAN
and terminal connectors of as there is no LAN port available on
primary circuit. the relay. The logic built on LBB relay
• Carbonization of terminal initiates its Binary output and is wired
connectors of primary circuit. to near IED and from IED, event is
routed to HMI.
Why Current Imbalance Monitoring
I-R PH I/P
Abs
1
Sub Abs I/P SET UP
Y
Y
2 LIMIT

When imbalance current due to the Abs Sub Abs I/P SET UP Alarm to HMI
I-Y PH I/P 1

aforementioned reasons left 2


Y
LIMIT
Y
or BO of the

unnoticed for a longer durations, it Abs Sub Abs I/P SET UP

may cause disastrous consequences


I-B PH I/P 1
Y
Y
2 LIMIT

particularly, when one of the parallel Fig.2 Logic for measuring Current
paths, is under shutdown. Further, Imbalance.
with this remote operation/SCADA
concepts, unlike manual recording, Equivalent threshold value can be set
analog data is being logged into soft based on the experience of the feeder
records automatically. Due to lesser past history. Generally this value
manual intervention, there is high ranges from 4% – 8% of the rated
chance for unnoticing of such current ie., 40 to 80A for a 1000/1A
incidences for longer durations. These CT.
conditions cause the need of
monitoring current imbalance in the As discussed earlier, this is most
bays/elements of switchyard, important parameter to be monitored
particularly in remote stations. especially for remote operated
stations. The event of imbalance
Concept current for the said bays/elements
has been routed to local HMI at
Logic concept is same as used in CVT Kalivanthapattu SS and remote HMI
secondary drift measurement. at Sriperumbudur SS.
Metering core of the CTs preferred
wherever feasible due to more
accuracy. The concept at
Kalivanthapattu Substation uses,
Measurement Monitoring System -
feeder current imbalance (both 400kV MW Balance Measurement
and 230kV), ICT current imbalance
(both HV & IV) and 400kV Tie bays,
For a substation MW of incoming and values are derived from different IEDs,
outgoing feeders are balanced. MW logic has to be written in station level
derived from in elements and out devices ie., at gateway/PAS. SICAM
elements can be verified for the PAS is a powerful tool that is supplied
balance condition. Imbalance by M/s. Siemens at Kalivanthapattu to
condition may arise due to following read all the station data from all IEDs
reasons. and switches and sending them to
HMI/RHMI/RLDC. Logics can also be
• Unhealthy CT secondary circuit written at station level ie., at SICAM-
• Unhealthy CVT secondary PAS. All analog values are available at
circuit including Fuse failure PAS, which can be tagged to logics
and non switching over CVT and logic output to be sent to HMI as
circuits during Bus-shut downs. alarm.
• Faulty Measurement Units or
errors in configuration Solutions for day to day problems can
be easily arrived at automated
Incidentally, there is no substations. This proves cost
supervision/monitoring system effectiveness of automated substation
available for such occurrences unless in O&M era and thus it always adds
it is detected by the manual value to the existing system without
intervention or else during SEM data
uploading etc.,

Concept

The real time MW of incoming and


outgoing feeders are routed to logics
and compared for more than 3% error.
Incase difference between in and out
MWs becomes more than 3%,
corresponding event will be sent to
HMI and RHMI also. Two ways of MW
balance modes are being
implemented at Kalivanthapattu SS.

• MW balance of incoming and


outgoing feeders
• MW balance of HV and IV
circuits of ICTs

With this entire measurement system


comes under monitoring.

The logic implementation is done


using different available gates similar
to CVT drift measurement and Current
imbalance measurement. As analog

You might also like