You are on page 1of 131

N68E-22 Cabinet Installation Guide

Issue 01
Date 2008-03-20
Part Number 00407710

Huawei Proprietary and Confidential


Copyright © Huawei Technologies Co., Ltd
Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. For any
assistance, please contact our local office or company headquarters.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website: http://www.huawei.com
Email: support@huawei.com

Copyright © Huawei Technologies Co., Ltd. 2008. All rights reserved.


No part of this document may be reproduced or transmitted in any form or by any means without prior written
consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are the property of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.

Notice
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but the statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Proprietary and Confidential


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide Contents

Contents

About This Document.....................................................................................................................1


1 Safety Information.....................................................................................................................1-1
1.1 Safety Precautions...........................................................................................................................................1-1
1.2 Electricity Safety.............................................................................................................................................1-3
1.3 Inflammable Environment...............................................................................................................................1-5
1.4 Battery.............................................................................................................................................................1-5
1.5 Radiation.........................................................................................................................................................1-7
1.6 Working at Heights.........................................................................................................................................1-9
1.7 Mechanical Safety.........................................................................................................................................1-11
1.8 Others............................................................................................................................................................1-12

2 N68E-22 Cabinet Overview......................................................................................................2-1


3 Preparing for the N68E-22 Cabinet Installation...................................................................3-1
3.1 Unpacking the RNC........................................................................................................................................3-2
3.2 Preparing Tools for N68E-22 Cabinet Installation.........................................................................................3-8

4 Installing the N68E-22 Cabinet................................................................................................4-1


5 Installing the N68E-22 Cabinet on the Concrete Floor.......................................................5-1
5.1 Materials for Installing the N68E-22 Cabinet on the Concrete Floor.............................................................5-2
5.2 Template Files for Installing the N68E-22 Cabinet........................................................................................5-2
5.3 Positioning the N68E-22 Cabinet on the Concrete Floor................................................................................5-4
5.4 Securing the N68E-22 Cabinet on the Concrete Floor....................................................................................5-9
5.5 Testing the Insulation of the N68E-22 Cabinet.............................................................................................5-14
5.6 Combining N68E-22 Cabinets......................................................................................................................5-16

6 Installing the N68E-22 Cabinet on the ESD Floor...............................................................6-1


6.1 Materials for Installing the N68E-22 Cabinet on the ESD Floor....................................................................6-2
6.2 Template Files for Installing the N68E-22 Cabinet........................................................................................6-2
6.3 N6X Series Support Assembly........................................................................................................................6-4
6.4 Positioning the N68E-22 Cabinet on the ESD Floor.......................................................................................6-6
6.5 Assembling the Support and the Guide Rail.................................................................................................6-10
6.6 Fixing the N68E-22 Cabinet on the ESD Floor............................................................................................6-14
6.7 Testing the Insulation of the N68E-22 Cabinet.............................................................................................6-18
6.8 Combining N68E-22 Cabinets......................................................................................................................6-20

Issue 01 (2008-03-20) Huawei Proprietary and Confidential i


Copyright © Huawei Technologies Co., Ltd
Contents N68E-22 Cabinet Installation Guide

6.9 Restoring the ESD Floor...............................................................................................................................6-22

7 Installing Power Cables and PGND Cables for the N68E-22 Cabinet.............................7-1
7.1 RNC Power Cables and PGND Cables to Be Installed...................................................................................7-2
7.1.1 RNC Power Cables.................................................................................................................................7-2
7.1.2 RNC PGND Cables................................................................................................................................7-5
7.2 Connections of RNC Power Cables and PGND Cables................................................................................7-10
7.3 Installation Specifications for RNC Power Cables and PGND Cables.........................................................7-11
7.4 Installing Power Cables and PGND Cables Between the N68E-22 Cabinet and the PDF...........................7-11
7.4.1 Overhead and Underfloor Cabling Modes...........................................................................................7-12
7.4.2 Installing Power Cables and PGND Cables Between the N68E-22 Cabinet and the PDF (Overhead
Cabling).........................................................................................................................................................7-15
7.4.3 Installing Power Cables and PGND Cables Between the N68E-22 Cabinet and the PDF (Underfloor
Cabling).........................................................................................................................................................7-17
7.5 Installing PGND Cables Between the Adjacent N68E-22 Cabinets.............................................................7-20
7.6 Checking the Power-On Status of the RNC Cabinets...................................................................................7-21

8 Installing Accessories for the N68E-22 Cabinet...................................................................8-1


8.1 N68E-22 Cabinet Accessories.........................................................................................................................8-2
8.2 Installing Side Doors of the N68E-22 Cabinet................................................................................................8-2
8.3 Installing Front and Back Doors of N68E-22 Cabinet....................................................................................8-4
8.4 Installing PGND Cables for N68E-22 Cabinet Doors....................................................................................8-5

9 Labeling RNC Cabinets............................................................................................................9-1


10 Labeling Power Cables and PGND Cables of the RNC.................................................10-1
11 Appendix..................................................................................................................................11-1
11.1 Checklist for RNC Cabinet Installation......................................................................................................11-2
11.2 Exploded View of the N68E-22 Cabinet.....................................................................................................11-3
11.3 Layout of Power Switches on the RNC Cabinet.........................................................................................11-6
11.4 Connections of Power Cables and PGND Cables in the RNC Cabinet......................................................11-7

ii Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide Figures

Figures

Figure 1-1 Wearing an ESD wrist strap...............................................................................................................1-5


Figure 1-2 Lifting a weight................................................................................................................................1-10
Figure 1-3 Slant angle........................................................................................................................................1-11
Figure 1-4 One meter higher than the eave........................................................................................................1-11
Figure 2-1 Appearance of the single-door N68E-22 cabinet ...............................................................................2-2
Figure 2-2 Appearance of the double-door N68E-22 cabinet .............................................................................2-3
Figure 3-1 Straightening the tongue.....................................................................................................................3-4
Figure 3-2 Removing the cover from the case.....................................................................................................3-5
Figure 3-3 Removing the side boards...................................................................................................................3-6
Figure 3-4 Unpacking a carton ............................................................................................................................3-7
Figure 5-1 Equipment room layout (unit: mm)....................................................................................................5-3
Figure 5-2 Marking template for installing the N68E-22 cabinet on the concrete floor (unit: mm)....................5-4
Figure 5-3 Marking template for installing the N68E-22 cabinet on the ESD floor (unit: mm)..........................5-4
Figure 5-4 Mounting holes for one cabinet (unit: mm)........................................................................................5-6
Figure 5-5 Mounting holes for a row of cabinets (unit: mm)...............................................................................5-6
Figure 5-6 Digging a pit.......................................................................................................................................5-7
Figure 5-7 Drilling a hole.....................................................................................................................................5-7
Figure 5-8 Expansion bolt assembly....................................................................................................................5-8
Figure 5-9 Installing expansion bolt assembly (1)...............................................................................................5-8
Figure 5-10 Installing expansion bolt assembly (2).............................................................................................5-9
Figure 5-11 Removing the packing accessory....................................................................................................5-10
Figure 5-12 State of the lock of each door.........................................................................................................5-10
Figure 5-13 Removing the short supporting beam.............................................................................................5-11
Figure 5-14 Removing the air filter....................................................................................................................5-12
Figure 5-15 Securing the cabinet........................................................................................................................5-13
Figure 5-16 Leveling the cabinet........................................................................................................................5-13
Figure 5-17 Insulation test..................................................................................................................................5-15
Figure 5-18 Repositioning the air filter..............................................................................................................5-16
Figure 5-19 Connecting the connecting plates...................................................................................................5-17
Figure 5-20 Using a level bar to check the levelness.........................................................................................5-18
Figure 6-1 Equipment room layout (unit: mm)....................................................................................................6-3
Figure 6-2 Marking template for installing the N68E-22 cabinet on the concrete floor (unit: mm)....................6-4
Figure 6-3 Marking template for installing the N68E-22 cabinet on the ESD floor (unit: mm)..........................6-4

Issue 01 (2008-03-20) Huawei Proprietary and Confidential iii


Copyright © Huawei Technologies Co., Ltd
Figures N68E-22 Cabinet Installation Guide

Figure 6-4 N6X series supports............................................................................................................................6-5


Figure 6-5 Guide rail............................................................................................................................................6-6
Figure 6-6 Horizontal pallet.................................................................................................................................6-6
Figure 6-7 Installation holes for one cabinet (unit: mm)......................................................................................6-7
Figure 6-8 Installation holes for a row of cabinets (unit: mm).............................................................................6-8
Figure 6-9 Digging a pit before drilling...............................................................................................................6-8
Figure 6-10 Drilling holes....................................................................................................................................6-9
Figure 6-11 Expansion bolt assembly..................................................................................................................6-9
Figure 6-12 Installing the expansion bolt assembly (I)......................................................................................6-10
Figure 6-13 Installing the expansion bolt assembly (II).....................................................................................6-10
Figure 6-14 Adjusting the height of the support................................................................................................6-11
Figure 6-15 Assembling guide rails...................................................................................................................6-12
Figure 6-16 Fixing the support...........................................................................................................................6-13
Figure 6-17 Insulation plate...............................................................................................................................6-13
Figure 6-18 Installing supports in a row............................................................................................................6-14
Figure 6-19 Removing the wooden packing accessories...................................................................................6-15
Figure 6-20 State of locks on the front and rear doors.......................................................................................6-15
Figure 6-21 Removing the short supporting beam in front of the cabinet.........................................................6-16
Figure 6-22 Removing the air filter....................................................................................................................6-17
Figure 6-23 Installing the cabinet.......................................................................................................................6-17
Figure 6-24 Leveling the cabinet........................................................................................................................6-18
Figure 6-25 Insulation test..................................................................................................................................6-19
Figure 6-26 Repositioning the air filter..............................................................................................................6-20
Figure 6-27 Connecting the connecting plates...................................................................................................6-21
Figure 6-28 Using a level bar to check the levelness.........................................................................................6-22
Figure 6-29 Installing the horizontal pallet........................................................................................................6-23
Figure 6-30 Restoring the ESD floor around the racks......................................................................................6-23
Figure 7-1 -48 V/RTN internal power cable of the RNC.....................................................................................7-4
Figure 7-2 External power cable of the N68E-22 cabinet....................................................................................7-4
Figure 7-3 External power cable of the N68-21-N cabinet..................................................................................7-4
Figure 7-4 External PGND cable of the N68-21-N cabinet...............................................................................7-10
Figure 7-5 External PGND cable of the N68E-22 cabinet.................................................................................7-10
Figure 7-6 Internal RNC PGND cable...............................................................................................................7-10
Figure 7-7 Cable connections.............................................................................................................................7-10
Figure 7-8 Cable holes of the RNC cabinet.......................................................................................................7-13
Figure 7-9 Overhead cabling mode....................................................................................................................7-14
Figure 7-10 Underfloor cabling mode................................................................................................................7-14
Figure 7-11 Installing power cables and PGND cables between the N68E-22 cabinet and the PDF (overhead
cabling)................................................................................................................................................................7-15
Figure 7-12 Installing power cables and PGND cables between the N68E-22 cabinet and the PDF (underfloor
cabling)................................................................................................................................................................7-18
Figure 7-13 PGND cables between adjacent cabinets........................................................................................7-21
Figure 8-1 Installation of a side door for the N68E-22 cabinet............................................................................8-3

iv Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide Figures

Figure 8-2 Installation of a front/back door for the N68E-22 cabinet..................................................................8-4


Figure 8-3 Connecting PGND cables to N68E-22 cabinet doors.........................................................................8-5
Figure 9-1 Row labels..........................................................................................................................................9-1
Figure 9-2 Column labels.....................................................................................................................................9-1
Figure 9-3 Position for attaching the product label .............................................................................................9-2
Figure 11-1 Exploded view of the N68E-22 cabinet..........................................................................................11-4
Figure 11-2 Assignment of power switches on the RSR power distribution box..............................................11-6
Figure 11-3 Layout of power switches on the RBR power distribution box.....................................................11-7
Figure 11-4 Connections of power cables and PGND cables in the N68-21-N cabinet....................................11-8
Figure 11-5 Connections of power cables and PGND cables in the N68E-22 cabinet....................................11-10

Issue 01 (2008-03-20) Huawei Proprietary and Confidential v


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide Tables

Tables

Table 2-1 Technical specifications for the N68E-22 cabinet...............................................................................2-3


Table 3-1 General tools required for N68E-22 cabinet installation.....................................................................3-9
Table 6-1 Materials required for the installation..................................................................................................6-2
Table 6-2 Applicable height range of each support type......................................................................................6-5
Table 7-1 External power cables of the N68-21-N cabinet..................................................................................7-2
Table 7-2 External power cables of the N68E-22 cabinet....................................................................................7-3
Table 7-3 Internal power cables of the RNC........................................................................................................7-3
Table 7-4 PGND cables of the N68-21-N cabinet................................................................................................7-5
Table 7-5 PGND cables of the N68E-22 cabinet.................................................................................................7-7
Table 8-1 N68E-22 cabinet accessories to be installed........................................................................................8-2
Table 11-1 Checked items for RNC cabinet installation....................................................................................11-2
Table 11-2 Parts on the cabinet..........................................................................................................................11-5
Table 11-3 Relation between the switches and subracks....................................................................................11-7
Table 11-4 Connections of power cables and PGND cables in the RNC cabinet (N68-21-N)..........................11-8
Table 11-5 Connections of power cables and PGND cables in the RNC cabinet (N68E-22)..........................11-10

Issue 01 (2008-03-20) Huawei Proprietary and Confidential vii


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide About This Document

About This Document

Purpose
This document describes the N68E-22 cabinet installation. It covers how to install the cabinet,
external power cables, PGND cables, and how to attach engineering labels for RNC power cables
and PGND cables.

Product Version
The following table lists the product versions related to this document.

Product Name Product Version

RNC V200R010

Intended Audience
This document is intended for RNC installers.

Organization

1 Safety Information

2 N68E-22 Cabinet Overview


The N68E-22 cabinet features a modular design. It provides ample space for installing devices
such as subracks, servers, and LAN switches so as to facilitate capacity expansion and
maintenance.
3 Preparing for the N68E-22 Cabinet Installation
Before the installation, you need to unpack the N68E-22 cabinet. Ensure that all tools required
for installing the N68E-22 cabinet are ready.
4 Installing the N68E-22 Cabinet
The N68E-22 cabinet installation involves installing the cabinet, accessories, external power
cables, and PGND cables. In addition, you also need to check the power-on status of the cabinet,
attach engineering labels to the cabinet, and attach engineering labels to the external power
cables and PGND cables.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1


Copyright © Huawei Technologies Co., Ltd
About This Document N68E-22 Cabinet Installation Guide

5 Installing the N68E-22 Cabinet on the Concrete Floor

This describes how to install the N68E-22 cabinet on the concrete floor.

6 Installing the N68E-22 Cabinet on the ESD Floor

This describes how to install the N68E-22 cabinet on the ESD floor. In the equipment room with
ESD floor, you need to install the N68E-22 cabinet on the N6X series supports.

7 Installing Power Cables and PGND Cables for the N68E-22 Cabinet

This describes how to install the power cables and PGND cables between the N68E-22 cabinet
and the Power Distribution Frame (PDF). When the cabinets are combined, you also need to
install the PGND cables between the N68E-22 cabinets.

8 Installing Accessories for the N68E-22 Cabinet

This describes how to install the PGND cables on the side door, front door, and back door of
the N68E-22 cabinet.

9 Labeling RNC Cabinets

The labels to be attached to the RNC cabinet are the row labels, column labels, and product
labels.

10 Labeling Power Cables and PGND Cables of the RNC

After the power cables and PGND cables of the RNCs are installed, remove the temporary labels
from the cables and attach engineering labels to these cables.

11 Appendix

This provides the exploded view of the N68E-22 cabinet and an installation checklist.

Conventions
1. Symbol Conventions

The following symbols may be found in this document. They are defined as follows

Symbol Description

Indicates a hazard with a high level of risk that, if not avoided,


will result in death or serious injury.
DANGER

Indicates a hazard with a medium or low level of risk which, if


not avoided, could result in minor or moderate injury.
WARNING

Indicates a potentially hazardous situation that, if not avoided,


could cause equipment damage, data loss, and performance
CAUTION degradation, or unexpected results.

TIP Indicates a tip that may help you solve a problem or save your
time.

2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide About This Document

Symbol Description

NOTE Provides additional information to emphasize or supplement


important points of the main text.

2. General Conventions

Convention Description

Times New Roman Normal paragraphs are in Times New Roman.

Boldface Names of files,directories,folders,and users are in boldface. For


example,log in as user root .

Italic Book titles are in italics.

Courier New Terminal display is in Courier New.

3. Command Conventions

Convention Description

Boldface The keywords of a command line are in boldface.

Italic Command arguments are in italic.

[] Items (keywords or arguments) in square brackets [ ] are optional.

{x | y | ...} Alternative items are grouped in braces and separated by vertical


bars.One is selected.

[ x | y | ... ] Optional alternative items are grouped in square brackets and


separated by vertical bars.One or none is selected.

{ x | y | ... } * Alternative items are grouped in braces and separated by vertical


bars.A minimum of one or a maximum of all can be selected.

[ x | y | ... ] * Alternative items are grouped in braces and separated by vertical


bars.A minimum of zero or a maximum of all can be selected.

4. GUI Conventions

Convention Description

Boldface Buttons,menus,parameters,tabs,window,and dialog titles are in


boldface. For example,click OK.

> Multi-level menus are in boldface and separated by the ">" signs.
For example,choose File > Create > Folder .

5. Keyboard Operation

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 3


Copyright © Huawei Technologies Co., Ltd
About This Document N68E-22 Cabinet Installation Guide

Convention Description

Key Press the key.For example,press Enter and press Tab.

Key1+Key2 Press the keys concurrently.For example,pressing Ctrl+Alt+A


means the three keys should be pressed concurrently.

Key1,Key2 Press the keys in turn.For example,pressing Alt,A means the two
keys should be pressed in turn.

6. Mouse Operation

Action Description

Click Select and release the primary mouse button without moving the
pointer.

Double-click Press the primary mouse button twice continuously and quickly
without moving the pointer.

Drag Press and hold the primary mouse button and move the pointer
to a certain position.

4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

1 Safety Information

1.1 Safety Precautions


This section describes certain safety precautions and helps to choose the measurement device
and testing device. Read and follow these safety precautions before installing, operating, and
maintaining Huawei devices.

Following All Safety Precautions


Before any operation, read the instructions and precautions in this document carefully to
minimize the possibility of accidents.

The Danger, Caution, and Note items in the package of documents do not cover all the safety
precautions that must be followed. They only provide the generic safety precautions for
operations.

Symbols

DANGER
This symbol indicates that casualty or serious accident may occur if you ignore the safety
instruction.

CAUTION
This symbol indicates that serious or major injury may occur if you ignore the safety instruction.

NOTE

This symbol indicates that the operation may be easier if you pay attention to the safety instruction.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-1


Copyright © Huawei Technologies Co., Ltd
1 Safety Information N68E-22 Cabinet Installation Guide

Complying with the Local Safety Regulations


When operating the device, comply with the local safety regulations. The safety precautions
provided in the documents are supplementary. You must comply with the local safety
regulations.

General Installation Requirements


The personnel in charge of installation and maintenance must be trained and master the correct
operating methods and safety precautions before beginning work.

The rules for installing and maintaining the device are as follows:

l Only the trained and qualified personnel can install, operate and maintain the device.
l Only the qualified specialists are allowed to remove the safety facilities, and repair the
device.
l Any replacement of the device or part of the device (including the software) or any change
made to the device must be performed by qualified or authorized personnel of Huawei.
l Any fault or error that might cause safety problems must be reported immediately to the
personnel in charge.

Grounding Requirements
The following requirements are applicable to the device to be grounded:

l Ground the device before installation and remove the ground cable after uninstallation.
l Do not operate the device in the absence of a ground conductor. Do not damage the ground
conductor.
l The unit (or system) must be permanently connected to the protection ground before
operation. Check the electrical connection of the device before operation and ensure that
the device is reliably grounded.

Safety of Personnel
Ensure the following:

l When lightning strikes, do not operate the device and cables.


l When lightning strikes, unplug the AC power connector. Do not use the fixed terminal or
touch the terminal or antenna connector.
NOTE

The previous two requirements are suitable for the wireless fixed terminal.
l To prevent electric shock, do not connect safety extra-low voltage (SELV) circuits to
telecommunication network voltage (TNV) circuits.
l To prevent laser radiation from injuring your eyes, never look into the optical fiber outlet
with unaided eyes.
l To prevent electric shock and burns, wear the electrostatic discharge (ESD) clothing, gloves
and wrist strap, and remove conductors such as jewelry and watch before operation.

1-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

Device Safety
l Before operation, the device must be secured on the floor or other fixed objects, such as
the walls and the mounting racks.
l Do not block ventilation openings while the system is running.
l When installing the panel, tighten the screw with the tool.

1.2 Electricity Safety


High Voltage

DANGER
l The high voltage power supply provides power for running the system. Direct contact with
the high voltage power supply or contact through damp objects may result in fatal danger.
l Non-standard and improper high voltage operations may result in fire and electric shock.

l The personnel who install the AC facility must be qualified to perform operations on high
voltage and AC power supply facilities.
l When installing the AC power supply facility, follow the local safety regulations.
l When operating the AC power supply facility, follow the local safety regulations.
l When operating the high voltage and AC power supply facilities, use the specific tools
instead of common tools.
l When the operation is performed in a damp environment, ensure that water is kept off the
device. If the cabinet is damp or wet, shut down the power supply immediately.

Thunderstorm
The following requirements are suitable only for the wireless base station or the device with an
antenna or GPS antenna.

DANGER
In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or
on a steel tower and mast.

High Electrical Leakage

CAUTION
Ground the device before powering on the device. Otherwise, the personnel and device are in
danger.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-3


Copyright © Huawei Technologies Co., Ltd
1 Safety Information N68E-22 Cabinet Installation Guide

If the "high electrical leakage" flag is stuck to the power terminal of the device, you must ground
the device before powering it on.

Power Cable

CAUTION
Do not install and remove the power cable with a live line. Transient contact between the core
of the power cable and the conductor may generate electric arc or spark, which may cause fire
or eye injury.

l Before installing or removing the power cable, turn off the power switch.
l Before connecting the power cable, ensure that the power cable and label comply with the
requirements of the actual installation.

Fuse

CAUTION
To ensure that the system runs safely, when a fuse blows, replace it with a fuse of the same type
and specifications.

Electrostatic Discharge

CAUTION
The static electricity generated by the human body may damage the electrostatic sensitive
components on the circuit board, such as the large-scale integrated circuit (LIC).

In the following situations, the human body generates a static electromagnetic field:

l Movement of body parts


l Clothes friction
l Friction between shoes and the ground
l Holding plastic in hand

The static electromagnetic field will remain within the human body for a long time.

Before contacting the device, plug boards, circuit boards, and application specific integrated
circuits (ASICs), wear a grounded ESD wrist strap. It can prevent the sensitive components from
being damaged by the static electricity in the human body. If neither the ESD wrist strap nor an
appropriate PGND point is provided, wear the ESD gloves.

Figure 1-1shows how to wear an ESD wrist strap.

1-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

Figure 1-1 Wearing an ESD wrist strap

1.3 Inflammable Environment

DANGER
Do not place the device in the environment that has inflammable and explosive air or fog. Do
not perform any operation in this environment.

Any operation of the electrical device in the inflammable environment causes danger.

1.4 Battery
Storage Battery

DANGER
Before handling the storage battery, read the safety precautions for the handling and connection
of the storage battery.

Incorrect operation of storage batteries may cause danger. During operation, ensure the
following:

l Prevent any short-circuit.


l Prevent the electrolyte from overflowing and leakage.

Electrolyte overflow may damage the device. It will corrode the metal parts and the circuit
boards, and ultimately damage the device and cause short-circuit of the circuit boards.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-5


Copyright © Huawei Technologies Co., Ltd
1 Safety Information N68E-22 Cabinet Installation Guide

General Operations
Before installing and maintaining the storage battery, ensure the following:

l Use special insulation tools.


l Use eye protection devices and operate with care.
l Wear rubber gloves and an apron in case of an electrolyte overflow.
l Always keep the battery upright when moving. Do not place the battery upside down or tilt
it.

Short-Circuit

DANGER
Short-circuit of the battery may cause injury. Although the voltage of a battery is low, high
transient current generated by short-circuit will release a surge of power.

Keep metal objects away from the battery to prevent short circuit. If they have to be used,
disconnect the battery in use before performing any other operation.

Harmful Gas

CAUTION
l Do not use unsealed lead-acid storage batteries, because the gas emitted from it may result
in fire or device corrosion.
l Lay the storage battery horizontally and fix it properly.

The lead-acid storage battery in use will emit flammable gas. Therefore, store it in a place with
good ventilation and take precautions against fire.

High Temperature

CAUTION
High temperature may result in distortion, damage, and electrolyte overflow of the battery.

When the temperature of the battery exceeds 60oC, check whether there is acid overflow. If acid
overflow occurs, handle the acid immediately.

1-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

Acid

CAUTION
If the acid overflows, it should be absorbed and neutralized immediately.

When handling a leaky battery, protect against the possible damage caused by the acid. Use the
following materials to absorb and neutralize acid spills:

l Sodium bicarbonate (baking soda): NaHCO3


l Sodium carbonate (soda): Na2CO3

Antacids must be used according to the instructions provided by the battery manufacturer.

Lithium Battery

CAUTION
There is danger of explosion if the battery is incorrectly replaced.

l Replace the lithium battery with the same or equivalent type recommended by the
manufacturer.
l Dispose of the used battery according to the instructions provided by the manufacturer.
l Do not dispose of the lithium battery in fire.

1.5 Radiation
Electromagnetic Field Exposure

CAUTION
High power radio-frequency signals are harmful to human body.

Before installing or maintaining an antenna on a steel tower or mast with a large number of
transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter
antennas are shut down.

The base transceiver station (BTS) has RF radiation (radiation hazard). Suggestions for the
installation and operation of BTSs are given in the following section. Operators are also required
to comply with the related local regulations on erecting BTSs.

l The antenna should be located in an area that is inaccessible to the public where the RF
radiation exceeds the stipulated value.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-7


Copyright © Huawei Technologies Co., Ltd
1 Safety Information N68E-22 Cabinet Installation Guide

l If the areas where RF radiation exceeds the stipulated value are accessible to workers,
ensure that workers know where these areas are. They can shut down the transmitters before
entering these areas. Such areas may not exist; but if they exist, the areas must be within a
range of less than 10 m around the antennas.
l Each forbidden zone should be indicated by a physical barrier and striking sign to warn the
public or workers.

Laser

CAUTION
When handling optical fibers, do not stand close to, or look into the optical fiber outlet with
unaided eyes.

Laser transceivers or transmitters are used in the optical transmission system and associated test
tools. Because the laser that is transmitted through the optical fiber produces a small beam of
light, it has a very high power density and is invisible to human eyes. If a beam of light enters
the eye, the retina may be damaged.
Normally, staring into the end of an unterminated optical fiber or broken optical fiber with the
unaided eyes from a distance of more than 150 mm [5.91 in.] will not cause eye injury. Eyes
may, however, be damaged if an optical tool such as a microscope, magnifying glass or eye
loupe is used to stare into the bare optical fiber end.
Read the following guidelines to prevent laser radiation:
l Only the trained and authorized personnel can perform the operation.
l Wear a pair of eye-protective glasses when you are handling lasers or optical fibers.
l Ensure that the optical source is switched off before disconnecting optical fiber connectors.
l Never look into the end of an exposed optical fiber or an open connector if you cannot
ensure that the optical source is switched off.
l To ensure that the optical source is switched off, use an optical power meter.
l Before opening the front door of an optical transmission system, ensure that you are not
exposed to laser radiation.
l Never use an optical tool such as a microscope, a magnifying glass, or an eye loupe to look
into the optical fiber connector or end.
Read the following instructions before handling optical fibers:
l Only the trained personnel can cut and splice optical fibers.
l Before cutting or splicing an optical fiber, ensure that the optical fiber is disconnected from
the optical source. After disconnecting the optical fiber, use protecting caps to protect all
the optical connectors.

1-8 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

1.6 Working at Heights

CAUTION
When working at heights, ensure that the objects do not fall.

When working at heights, ensure that the following requirements must be met:
l The personnel who work at heights must be trained.
l The operating machines and tools should be carried and handled safely to prevent them
from falling.
l Safety measures, such as wearing a helmet and a safety belt, should be taken.
l In cold regions, warm clothes should be worn before working at heights.
l Ensure that the lifting appliances are well prepared for working at heights.

Lifting Weights

CAUTION
Do not access the areas under the arm of the crane and the goods in suspension when lifting
weights.

l Ensure that the operators have been trained and qualified.


l Check the weight lifting tools and ensure that they are intact.
l Lift the weight only when the weight lifting tools are firmly mounted onto the weight-
bearing object or the wall.
l Use a concise instruction to prevent incorrect operation.
l The angle between the two cables should be less than or equal to 90o in the lifting of weights
(See Figure 1-2).

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-9


Copyright © Huawei Technologies Co., Ltd
1 Safety Information N68E-22 Cabinet Installation Guide

Figure 1-2 Lifting a weight

Safety Guide on Ladder Use


Checking the Ladder
l Check the ladder before using it. Check the maximum weight that the ladder can support.
l Never overload the ladder.

Placing the Ladder

l The slant angle is preferred to be 75o. The slant can be measured with the angle square or
with arms, as shown in Figure 1-3. When using a ladder, place the wider end of the ladder
on the ground and take protective measures on the base of the ladder against slippage. Place
the ladder on a stable ground.
When climbing the ladder, ensure the following:
l The gravity of the body does not shift from the edge of the ladder.
l Keep balance on the ladder before performing any operation.
l Do not climb higher than the fourth highest step of the ladder.

If you tend to climb to the roof, the length of the ladder should be at least one meter higher than
the eave, as shown in Figure 1-4.

1-10 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

Figure 1-3 Slant angle

Figure 1-4 One meter higher than the eave

1.7 Mechanical Safety


Drilling

CAUTION
Do not drill on the cabinet without permission. Inappropriate drilling on the cabinet may damage
the electromagnetic shielding and internal cables. Metal shavings from the drilling may result
in a short-circuit of the circuit board if they get into the cabinet.

l Before drilling a hole on the cabinet, remove the cables from the cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-11


Copyright © Huawei Technologies Co., Ltd
1 Safety Information N68E-22 Cabinet Installation Guide

l During the drilling, wear blinkers to protect your eyes.


l During the drilling, wear the protective gloves.
l Prevent the metal shavings from getting into the cabinet. After drilling, clean the metal
shavings in time.

Handling Sharp Objects

CAUTION
When carrying the device by hand, wear the protective gloves to prevent injury by sharp objects.

Handling Fans
l When replacing a component, place the component, screw, and tool at a safe place to prevent
them from falling into the running fan.
l When replacing the ambient equipment around the fan, do not place the finger or board
into the running fan until the fan is switched off and stops running.

Moving Heavy Objects


Wear the protective gloves when moving heavy objects.

CAUTION
l Be careful when moving heavy objects.
l When moving the chassis outwards, be aware about the unfixed or heavy objects on the
chassis to prevent injury.

l Two persons should be available to move a chassis; one person must not move a heavy
chassis. When moving a chassis, keep your back straight and move stably to prevent a
sprain.
l When moving or lifting a chassis, hold the handle or bottom of the chassis. Do not hold the
handle of the installed modules in the chassis, such as the power module, fan module, or
board.

1.8 Others
Inserting and Removing a Board

CAUTION
When inserting a board, wear the ESD wrist strap or gloves. Insert the board gently to prevent
any bent pins on the backplane.

1-12 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 1 Safety Information

l Insert the board along the guide rail.


l Avoid contact of one board with another to prevent short-circuit or damage.
l Do not remove the active board before powering off.
l When holding a board in hand, do not touch the board circuit, components, connectors, or
connection slots.

Bundling Signal Cables

CAUTION
Bundle the signal cables separately from the strong current cables or high voltage cables.

Cabling Requirements
At a very low temperature, movement of the cable may damage the plastic skin of the cable. To
ensure the construction safety, comply with the following requirements:

l When installing cables, ensure that the environment temperature is above 0oC.
l If cables are stored in the place below 0oC, move the cables into a place at a room
temperature and store the cables for more than 24 hours before installation.
l Move the cables with care, especially at a low temperature. Do not drop the cables directly
from the vehicle.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 1-13


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 2 N68E-22 Cabinet Overview

2 N68E-22 Cabinet Overview

The N68E-22 cabinet features a modular design. It provides ample space for installing devices
such as subracks, servers, and LAN switches so as to facilitate capacity expansion and
maintenance.

Appearance of the N68E-22 Cabinet


The color of the N68E-22 cabinet surface is purple and gray. The N68E-22 cabinet can be
categorized into two types: the single-door cabinet and the double-door cabinet. Figure 2-1
shows the single-door N68E-22 cabinet. Figure 2-2 shows the double-door N68E-22 cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 2-1


Copyright © Huawei Technologies Co., Ltd
2 N68E-22 Cabinet Overview N68E-22 Cabinet Installation Guide

Figure 2-1 Appearance of the single-door N68E-22 cabinet

2-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 2 N68E-22 Cabinet Overview

Figure 2-2 Appearance of the double-door N68E-22 cabinet

Technical Specifications for the N68E-22 Cabinet


Table 2-1 describes all technical specifications for the N68E-22 cabinet.

Table 2-1 Technical specifications for the N68E-22 cabinet

Measurement Item Specification

Dimensions (H x W x D) 2,200 mm (H) x 600 mm (W) x 800 mm (D)

Available space height 46 U

Weight Rack: ≤ 59 kg; Empty cabinet: ≤ 100 kg;


Cabinet in full configuration: ≤ 350 kg

Power supply Four -48 V DC inputs

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 2-3


Copyright © Huawei Technologies Co., Ltd
2 N68E-22 Cabinet Overview N68E-22 Cabinet Installation Guide

Measurement Item Specification

EMC l ETSI EN300 386


l Council directive 89/336/EEC

2-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 3 Preparing for the N68E-22 Cabinet Installation

3 Preparing for the N68E-22 Cabinet


Installation

About This Chapter

Before the installation, you need to unpack the N68E-22 cabinet. Ensure that all tools required
for installing the N68E-22 cabinet are ready.

3.1 Unpacking the RNC


When the packing cases that contain the RNC cabinets and components are delivered to the site,
unpack the cases and check the equipment quality so as to facilitate the smooth installation.
3.2 Preparing Tools for N68E-22 Cabinet Installation
The tools required for the N68E-22 cabinet installation are: measuring tools, marking tools,
drilling tools, fastening tools, pliers, auxiliary tools, meters, and some special tools.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 3-1


Copyright © Huawei Technologies Co., Ltd
3 Preparing for the N68E-22 Cabinet Installation N68E-22 Cabinet Installation Guide

3.1 Unpacking the RNC


When the packing cases that contain the RNC cabinets and components are delivered to the site,
unpack the cases and check the equipment quality so as to facilitate the smooth installation.

Prerequisite
l Site preparation for the RNC installation is complete.
l The packing cases that contain the cabinets and components are ready on site.

Context

CAUTION
Electronic devices such as boards and Application Specific Integrated Circuit (ASIC) are ESD-
prone. When operate with these devices, correctly put on an ESD wrist strap. Ensure that the
ESD wrist strap is properly connected to the ESD connector on the cabinet. If neither the ESD
wrist strap nor an appropriate PGND point is provided, wear the ESD gloves.

l When moving the equipment, prevent the equipment from colliding with objects such as
doors, walls, or shelves.
l Do not touch the unpainted metal surface of the equipment or its components with sweat-
soaked or dirty gloves.

Procedure
Step 1 Unload the packing cases.

CAUTION
Arrange the packing cases in sequence and the labels in the same direction to facilitate the check.

Step 2 When unloading the equipment, check whether the quantity of the packing cases on the site
matches with the Packing List. Ensure that the place of delivery is the correct installation place.

If... Then...

The quantity of the packing cases on site matches with the Packing List. Go to Step 4.

The quantity of the packing cases on site does not match with the Packing Go to Step 3.
List.

3-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 3 Preparing for the N68E-22 Cabinet Installation

Step 3 In case of any error, the installation supervisor must stop the unpacking immediately and send
the Article Problem Feedback Form to the order management engineer in the local Huawei office
within three days. Note that this form must be signed by the customer.
Step 4 Check whether the packing cases are intact and the equipment is placed upright in transit.

If... Then...

Any packing case is damaged or soaked. Go to Step 5.

The packing cases are intact. Go to Step 6.

Step 5 Stop the unpacking immediately, make investigations to find the cause, and contact the order
management engineer in the local Huawei office for further treatment.

CAUTION
To protect the equipment and find out the causes, perform the following steps: Move the
unpacked equipment indoor for proper storage, take photos of the storage environment and of
the rusted or corroded equipment, packing cases, and packing materials. Keep these photos for
later verification. Store the packing cases and materials in a proper place.

Step 6 Unpack the wooden cases.

CAUTION
l Before the unpacking, move the wooden cases into or close to the equipment room if there
is enough space. This prevents damage to the cabinets in transit.
l You can find articles rapidly according to the names, codes, locations, and quantities of the
articles on the Packing List.
l Here shows an example of a wooden case that contains the cabinet. The methods for
unpacking other types of wooden cases are similar.

1. Place the wooden case on the ground. Ensure that the side with the wooden frame faces the
bottom.
2. Use a wrench, a straight screwdriver, or a claw hammer to straighten the tongue.
Refer to Figure 3-1.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 3-3


Copyright © Huawei Technologies Co., Ltd
3 Preparing for the N68E-22 Cabinet Installation N68E-22 Cabinet Installation Guide

Figure 3-1 Straightening the tongue

3. Remove the cover. If the wooden case contains a carton, take out the carton and then open
it according to Step 7. If the wooden case contains a cabinet, go to the next step. Refer to
Figure 3-2.

3-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 3 Preparing for the N68E-22 Cabinet Installation

Figure 3-2 Removing the cover from the case

4. Remove the side boards of the wooden case in the same way as described previously. Refer
to Figure 3-3.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 3-5


Copyright © Huawei Technologies Co., Ltd
3 Preparing for the N68E-22 Cabinet Installation N68E-22 Cabinet Installation Guide

Figure 3-3 Removing the side boards

5. Erect the cabinet with the BOTTOM side down.

CAUTION
If the cabinet falls during the erection, it may cause personnel injury. Therefore, this
operation requires three to five installers to work together.

6. Remove the base of the case, that is, the side with the wooden frame.
7. Remove the foamed wrap angles.
8. Remove the vacuum plastic bag.
Step 7 Unpack the carton, as shown in Figure 3-4.

3-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 3 Preparing for the N68E-22 Cabinet Installation

Figure 3-4 Unpacking a carton

(1) Carton label (2) Strap (3) Pressure-sensitive adhesive tape


(4) Foam block (5) Board label (6) Board

1. Check the types and quantities of the articles in the carton according to the label on the
carton.
2. Cut the straps using the diagonal pliers.
3. Rip the adhesive tape along the joint seams using the paper knife. Do not insert the knife
too deep, otherwise the articles may be damaged.
4. Unpack the carton and take out the articles.
Step 8 Unpack boards.

CAUTION
l Electronic components are extremely sensitive to static electricity. Therefore, properly wear
an ESD wrist strap or glove when unpacking the boards.
l The ESD bag contains the desiccant to keep the bag dry. When taking the board from a cold
dry place to a hot damp place, wait at least 30 minutes before unpacking the board. Otherwise,
moisture condensed on the board surface may damage the board.

1. Check that there is no evident damage on the board packages.


2. Open the packages and check that the boards are in good condition. For any problem,
contact the order management engineer at the local Huawei office.
Step 9 Check whether the unpacked boards need to be installed immediately, and proceed accordingly.

If... Then...

The board needs to be installed Place the board on an ESD surface and
immediately. discharge the static electricity.

The board does not need to be installed Pack the board with the original materials and
immediately. place them at a cool dry place away from direct
sunlight or strong electromagnetic radiation.

Step 10 Check the articles one by one according to the name, type, and quantity of each article stated on
the Packing List.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 3-7


Copyright © Huawei Technologies Co., Ltd
3 Preparing for the N68E-22 Cabinet Installation N68E-22 Cabinet Installation Guide

The checking of the articles covers the following aspects:


l Appearance: Check that there are no defects on the appearance of the cabinet; there is no
looseness, distortion, or damage; the identification is legible; all nameplates and decorating
plates are available and meet the requirements.
l Integrity: Check that all the parts and accessories required for the installation of cabinets are
available.
l Computer terminal: Check that the monitor, keyboard, and mouse are all available and in
good condition.
l Boards: Check that the type and quantity of the boards are consistent with the Packing List;
no printed circuit board is broken; no component is detached from the board.
NOTE

The installation supervisor should be responsible for the inspection of the electrically sensitive equipment
and components.

If... Then...

The item saying "Outstanding articles" is The installation supervisor informs the order
stated on the Packing List. management engineer at the local Huawei
office for further treatment. At the same time,
both parties sign the Packing List.

There is any absent, wrong, or extra Note the following points: Representatives of
shipment, or any damaged articles. Huawei and the customer both sign the
Unpacking Inspection Memo and Packing
List. The installation supervisor must fill in the
Article Problem Feedback Form and sends it
back to the order management engineer at the
local office within three days. The installation
supervisor must keep the problematic articles
together with the inner and outer packing intact
for future investigation and verification.

All the products are intact. Place the inspected articles by the type. Then,
both parties sign the Packing List.

----End

3.2 Preparing Tools for N68E-22 Cabinet Installation


The tools required for the N68E-22 cabinet installation are: measuring tools, marking tools,
drilling tools, fastening tools, pliers, auxiliary tools, meters, and some special tools.

General Tools
The general tools required for the N68E-22 cabinet installation are listed in Table 3-1.

3-8 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 3 Preparing for the N68E-22 Cabinet Installation

Table 3-1 General tools required for N68E-22 cabinet installation


Types Tools

Measurement Long tape, 50 m ribbon tape, 5 m measuring tape, 400 mm level bar, and
tools level instrument

Marking tools Marking pen, pencil

Drilling tools Percussion drill with matching bits of Ф6, Ф8, Ф10, Ф12, Ф14, and Ф16,
and vacuum cleaner

Fastening tools Straight screwdrivers (M3 to M6)


Cross screwdrivers (M3 to M6)
Adjustable wrench
Socket wrenches (M6, M8, M10, M12, M14, M17, M19)
Double offset ring wrenches (M6, M8, M10, M12, M14, M17, M19)
Combination wrenches (M17 and M19)
Long-arm wrench

Pliers Sharp nose pliers, diagonal pliers, pincer pliers, electric hand drill, file,
hacksaw, crowbar, rubber hammer, and nail hammer

Auxiliary tools Paper knife, bellows, plumb, fork, ladder, heat blower, and insulating tape

Special Tools
The special tools required for the N68E-22 cabinet installation are: Earth resistance meter, ESD
wrist strap, ESD glove, cable peeler, clamping pliers, safety knife, multi-purpose crimping pliers.

Meters
The meters required for the N68E-22 cabinet installation are: multimeter, 500 V megohm meter
(for testing insulation resistance).

NOTE

The meters must be checked and certified.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 3-9


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 4 Installing the N68E-22 Cabinet

4 Installing the N68E-22 Cabinet

The N68E-22 cabinet installation involves installing the cabinet, accessories, external power
cables, and PGND cables. In addition, you also need to check the power-on status of the cabinet,
attach engineering labels to the cabinet, and attach engineering labels to the external power
cables and PGND cables.

Prerequisite
l The RNC equipment has been unpacked and accepted.
l The equipment is delivered to the site.
l The tools required for the installation are all ready.

Procedure
Step 1 Install the N68E-22 cabinet.

If... Then...

Installing the N68E-22 cabinet on the ESD Refer to 6 Installing the N68E-22 Cabinet on
floor, the ESD Floor.

Installing the N68E-22 cabinet on the Refer to 5 Installing the N68E-22 Cabinet on
concrete floor, the Concrete Floor.

Installing the N68E-22 cabinet on other Contact Huawei engineers for technical
types of floor, support.

Step 2 Install power cables and PGND cables for the N68E-22 cabinet. Refer to 7 Installing Power
Cables and PGND Cables for the N68E-22 Cabinet.

Step 3 Install accessories for the N68E-22 cabinet. Refer to 8 Installing Accessories for the N68E-22
Cabinet.

Step 4 Attach engineering labels to the N68E-22 cabinet. Refer to 9 Labeling RNC Cabinets.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 4-1


Copyright © Huawei Technologies Co., Ltd
4 Installing the N68E-22 Cabinet N68E-22 Cabinet Installation Guide

Step 5 Attach engineering labels to external power cables and PGND cables. Refer to 10 Labeling
Power Cables and PGND Cables of the RNC.

----End

4-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

5 Installing the N68E-22 Cabinet on the


Concrete Floor

About This Chapter

This describes how to install the N68E-22 cabinet on the concrete floor.

Prerequisite
The materials required for installing the N68E-22 cabinet are available, as specified in 5.1
Materials for Installing the N68E-22 Cabinet on the Concrete Floor.
1. 5.3 Positioning the N68E-22 Cabinet on the Concrete Floor
The positioning of the N68E-22 cabinet on the concrete floor includes the following steps:
determining cabinet positions, marking the positions, drilling holes, and installing
expansion bolt assemblies.
2. 5.4 Securing the N68E-22 Cabinet on the Concrete Floor
This describes how to secure the N68E-22 cabinet on the concrete floor.
3. 5.5 Testing the Insulation of the N68E-22 Cabinet
This describes how to test the insulation of the N68E-22 cabinet to ensure that the cabinet
is insulated from the ground.
4. 5.6 Combining N68E-22 Cabinets
This describes how to use connecting plates to install two or more cabinets side by side.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-1


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

5.1 Materials for Installing the N68E-22 Cabinet on the


Concrete Floor
For the installation of the N68E-22 cabinet on the concrete floor, you need only the N68E-22
cabinet, and the quantity depends on the actual site plan.

5.2 Template Files for Installing the N68E-22 Cabinet


The template files for installing the N68E-22 cabinet consist of the equipment room floor plan
and the marking template. The equipment room floor plan is used to determine the installation
position of the N68E-22 cabinet in the equipment room. The marking template is used to
determine the drilling positions. The equipment room floor plan can be used both when the
N68E-22 cabinet is installed on the concrete floor and when the N68E-22 cabinet is installed on
the ESD floor, but the marking template varies with the installation position.

Equipment Room Layout


The Equipment Room Layout is provided by the customer or the site survey personnel. Figure
5-1 is an example of the Equipment Room Layout.

5-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

Figure 5-1 Equipment room layout (unit: mm)

NOTE

See Figure 5-1. The requirements for the installation position of the N68E-22 cabinet are as follows:
l The horizontal distance between two rows of cabinets should be at least 1,000 mm.
l The distance between the wall and the side of cabinet that is the closest to the wall is at least 800
mm.
l The distance between the wall and the front/back of cabinet that is the closest to the wall is at least
800 mm for double-door N68E-22 cabinet, and it is at least 1,000 mm for single-door N68E-22
cabinet.
l The width of the passages in the equipment room is at least 1,000 mm.

Marking Template
The marking template is delivered with the cabinet. The marking template for installing the
N68E-22 cabinet on the concrete floor is different from the marking template for installing the
N68E-22 cabinet on the ESD floor. See Figure 5-2 and Figure 5-3.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-3


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

Figure 5-2 Marking template for installing the N68E-22 cabinet on the concrete floor (unit: mm)

Figure 5-3 Marking template for installing the N68E-22 cabinet on the ESD floor (unit: mm)

5.3 Positioning the N68E-22 Cabinet on the Concrete Floor


The positioning of the N68E-22 cabinet on the concrete floor includes the following steps:
determining cabinet positions, marking the positions, drilling holes, and installing expansion
bolt assemblies.

Prerequisite
l The parts required for the installation are available. The required parts are the M12x60
expansion bolt assemblies.
l The materials required for the installation are available. The required materials are the
marking template and Equipment Room Layout.
l The tools required for the installation are available. The required tools are tape measure,
marking pen, percussion drill with the Ф16 drill bit, vacuum cleaner, and hammer (such as
claw hammer).

Context
l Marking cabinet positions and drilling holes are the primary tasks of installation. Therefore,
the accuracy of these tasks should be ensured; otherwise, the following tasks will incur
great inconvenience.

5-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

l Before marking cabinet positions and drilling holes, check the installation position of the
equipment, such as cable racks, in the equipment room for easy cabling.
l The Equipment Room Layout is provided by the customer or the site survey personnel.

Procedure
Step 1 Check that the Equipment Room Layout is in accordance with the requirements for installing the
N68E-22 cabinet by referring to 5.2 Template Files for Installing the N68E-22 Cabinet.

Step 2 Use a tape measure to determine the cabinet positions based on the dimensions specified in the
Equipment Room Layout.

Step 3 Determine the positions of the holes for the expansion bolt assemblies on the concrete floor
based on the installation position of the cabinet.
You can use the marking template or tape measure to determine the positions of the holes for
the expansion bolt assemblies on the concrete floor. The marking template is made of paper and
is prone to deformation. Before using the marking template, check whether it is deformed based
on the dimensions of marking template specified in 5.2 Template Files for Installing the
N68E-22 Cabinet.

If... Then...

The marking template is one of the Use the marking plate to determine the
accessories delivered on site and is not positions of the holes for the expansion bolt
deformed, assemblies and then go to Step 4.

Other, Use the tape measure to determine the


positions of the holes for the expansion bolt
assemblies and then go to Step 5.

Step 4 Use the marking plate to determine the positions of the holes for the expansion bolt assemblies.
1. As shown in Figure 5-4 or Figure 5-5, use measuring and marking instruments to measure
and mark the start points for the front of a row of cabinets. From each start point, mark the
benchmark lines in the cabinet arrangement direction.
2. Place the marking template on the floor. Ensure that the semicircle notch of the template
indicates the front of the cabinet and the edges of the template align with the benchmark
lines.
3. Mark the positions of the holes (four holes for each cabinet) for expansion bolts on the floor
by using the template.
4. After all the hole positions are marked, measure the holes again to ensure that the
dimensions of the holes are correct.
5. Go to Step 6.

Step 5 If the marking template cannot be used on site, use the tape measure to determine the positions
of the holes for the expansion bolt assemblies.
1. As shown in Figure 5-4 or Figure 5-5, use measuring and marking instruments to measure
and mark two straight lines with 687 mm wide spacing, and ensure that the lines are parallel
with the front of the cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-5


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

Figure 5-4 Mounting holes for one cabinet (unit: mm)

Figure 5-5 Mounting holes for a row of cabinets (unit: mm)

2. As shown in Figure 5-4 or Figure 5-5, determine the position of hole for the first expansion
bolt assembly on each of the straight lines. Taking the hole as the benchmark point, mark
the mounting holes for other expansion bolt assemblies in succession.
3. After all the hole positions are marked, measure the holes again to ensure that the
dimensions of the holes are correct.
Step 6 Drill the holes.

5-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

CAUTION
l The concrete floor should not be penetrated. Therefore, you should confirm the thickness of
the concrete floor before the drilling. For some types of concrete floors on which the drilling
is not suitable, you should consult the architectural engineers and get their permission before
drilling holes.
l Before drilling holes, you should take dustproof measures on the electronic equipment in the
equipment room. While drilling holes, you should clean the dust with a vacuum cleaner.
Before removing the dustproof cover from the electronic equipment, you should clean the
pieces of concrete which accumulate during the drilling.
l You must wear safety goggles during the drilling to protect your eyes from the harm of dust.
l While drilling holes, you must hold the drill stock firmly. You must keep the drilling bit
vertical to the floor lest the floor be damaged or the holes be slanting.

1. Dig a pit by using a chisel to help hold the drill bit to the floor, as shown in Figure 5-6.

Figure 5-6 Digging a pit

2. Use a percussion drill to drill holes at the marked places on the concrete floor. The depth
of each hole must range from 52 mm to 60 mm. All the holes must have the same depth.
Select a Ф16 drill bit in appropriate length. See Figure 5-7.

Figure 5-7 Drilling a hole

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-7


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

3. Check that the depth of each hole ranges from 52 mm to 60 mm and that the holes are not
slanting. If the depth of the hole is not appropriate or if the hole is slanting, re-drill the hole.
If the slanting hole cannot be corrected, discard the hole.
4. Clean the dust inside and outside the holes by using a vacuum cleaner.

Step 7 Install the expansion bolt assemblies.


Figure 5-8 shows an expansion bolt assembly.

Figure 5-8 Expansion bolt assembly

(1) Bolt (2) Spring washer (3) Flat washer (4) Expansion tube

(5) Nut (6) Guiding slot (7) Guiding rib

1. Measure the distance between the holes. If the distance does not meet the specifications,
reposition and drill new holes.
2. Insert the guiding rib on the nut into the guiding slot on the expansion tube and then screw
the bolt slightly to ensure that the guiding rib does not move out from the guiding slot. See
Figure 5-9 ①.
3. Insert the expansion tube and the nut into the hole vertically, and then use a rubber hammer
to strike the expansion tube until it is completely buried in the hole, as shown in Figure
5-9 ②.

Figure 5-9 Installing expansion bolt assembly (1)

4. Pretighten the expansion bolt clockwise so that the nut and the expansion tube do not get
loose easily. See Figure 5-10 ①.

5-8 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

5. Screw off the expansion bolt counterclockwise and then remove the spring washer and flat
washer. Keep them for future use. See Figure 5-10 ②.

Figure 5-10 Installing expansion bolt assembly (2)

----End

5.4 Securing the N68E-22 Cabinet on the Concrete Floor


This describes how to secure the N68E-22 cabinet on the concrete floor.

Prerequisite
l The equipment to be installed is available. The equipment to be installed is the N68E-22
cabinet.
l The materials required for the installation are available. The required materials are
insulating pads, flat washers 12, spring washers 12, adjusting pads (optional), and M12x60
expansion bolt assemblies.
l The tools required for the installation are available. The required tools are the forklift, level
bar, torque wrench, socket wrench, and cross screwdriver.

Context

CAUTION
The gravity center of the N68E-22 cabinet is high, so you must not lift or push the cabinet alone.
To avoid personal injury or the damage to the cabinet, you must ensure that you have at least
one assistant and that you can use the forklift appropriately before moving the cabinet.

Procedure
Step 1 Remove the wooden protection boards from the front and the rear of the cabinet.
Step 2 Remove the four wooden protection boards from both the left and right parts of the rack. Pull
down the hook pin at the upper part of both the front and rear doors of the cabinet, and then
remove both doors. Lay the doors appropriately. See Figure 5-11.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-9


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

Figure 5-11 Removing the packing accessory

NOTE

When laying the doors, you should ensure that the lock of each door is unlocked. Therefore, the lock rod
at the lower part of each door does not protrude and is not deformed because of pressure. See Figure
5-12.

Figure 5-12 State of the lock of each door

Step 3 Remove the two short supporting beams on the left and right of the cabinet front. Figure 5-13
shows how to remove the short supporting beam.

5-10 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

Figure 5-13 Removing the short supporting beam

Step 4 Screw off the two M6x12 screws from the air filter, as shown in Figure 5-14 ①. Remove the
air filter, as shown in Figure 5-14 ②.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-11


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

Figure 5-14 Removing the air filter

Step 5 Place the cabinet in the specified position. Align the mounting holes in the cabinet with the holes
on the floor.
Step 6 Add the spring washer, flat washer, and insulating tube to each of the four expansion bolts. Then,
insert each expansion bolt into the expansion tube and pretighten the expansion tube and the nut.
See Figure 5-15.
Step 7 Below the cabinet, push two insulating plates from both the front and rear sides. Ensure that the
notch faces the inner side and is wedged in the expansion bolt. Align the mounting holes of each
insulating plate with the corresponding expansion bolt holes. See Figure 5-15.

5-12 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

Figure 5-15 Securing the cabinet

(1) M12x60 bolt (2) Washer 12 (3) Flat washer


(4) Insulating tube (5) Insulating plate

Step 8 Level the cabinet. Use the level bar to check the levelness of the cabinet. If the cabinet is not
level, use the socket wrench to adjust the leveling foot (adjustable range: 0-10 mm) of the cabinet
and ensure that the cabinet is level. See Figure 5-16.

Figure 5-16 Leveling the cabinet

(1) Leveling foot (2) Fixing bolt

Step 9 After the cabinet is level, use the torque wrench to fix the four fixing bolts and tighten them to
45 N·m.

----End

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-13


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

5.5 Testing the Insulation of the N68E-22 Cabinet


This describes how to test the insulation of the N68E-22 cabinet to ensure that the cabinet is
insulated from the ground.

Prerequisite
The multimeter required for the insulation test is available.

Procedure
Step 1 Set the multimeter to the megohm position.
Step 2 Measure the resistance between the M12x60 expansion bolt and the cabinet.

If... Then...

The resistance is equal to or greater than five Go to Step 7.


megohms,

The resistance is smaller than five megohms, You can infer that the cabinet is not insulated
from the ground and then go to Step 3.

5-14 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

Figure 5-17 Insulation test

Step 3 Remove all the installation parts between the N68E-22 cabinet and the ground.
Step 4 Check that the insulation parts are not missing or damaged.
Step 5 Fix the cabinet again.
Step 6 Go back to Step 1 to test the insulation again.
Step 7 Use two M6x12 screws to fix the air filter and ensure that it is in the original position. See Figure
5-18.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-15


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

Figure 5-18 Repositioning the air filter

----End

5.6 Combining N68E-22 Cabinets


This describes how to use connecting plates to install two or more cabinets side by side.

Prerequisite
The required tools such as wrench and climbing ladder are available.

Context
The connecting plates are installed on top of and are delivered with the cabinets.

Procedure
Step 1 Remove the connecting plates from the column inside the cabinet, rotate each of them by 180
degrees, and then reinstall them. Use M8x30 bolts to connect the connecting plates of the adjacent
cabinets together. See Figure 5-19 ①.

5-16 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 5 Installing the N68E-22 Cabinet on the Concrete Floor

Figure 5-19 Connecting the connecting plates

Step 2 Remove the two connecting plates from the front and rear doorheads of the adjacent cabinets.
Then, reinstall the connecting plates, as shown in Figure 5-19 ②.
Step 3 At the bottom of the combined cabinets and in front of the column, use a level bar to check
whether the levelness and vertical deviation of the row of cabinets meet the specifications, as
shown in Figure 5-20. If the cabinet is not level, use a socket wrench to adjust the leveling foot.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 5-17


Copyright © Huawei Technologies Co., Ltd
5 Installing the N68E-22 Cabinet on the Concrete Floor N68E-22 Cabinet Installation Guide

Figure 5-20 Using a level bar to check the levelness

----End

5-18 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

6 Installing the N68E-22 Cabinet on the ESD


Floor

About This Chapter

This describes how to install the N68E-22 cabinet on the ESD floor. In the equipment room with
ESD floor, you need to install the N68E-22 cabinet on the N6X series supports.

Prerequisite
The materials required for the installation are available. For details, refer to 6.1 Materials for
Installing the N68E-22 Cabinet on the ESD Floor.
1. 6.4 Positioning the N68E-22 Cabinet on the ESD Floor
This describes how to position the N68E-22 cabinet on the ESD floor, including positioning
the cabinet, drawing lines, drilling holes, and installing expansion bolt assembly.
2. 6.5 Assembling the Support and the Guide Rail
This describes how to assemble the N6X series supports and guide rails, and how to fix
them on the concrete floor.
3. 6.6 Fixing the N68E-22 Cabinet on the ESD Floor
This describes how to fix the N68E-22 cabinet on the ESD floor. The front and rear doors
of the cabinet are installed before delivery. You need to remove the front and rear doors,
and then fix the N68E-22 cabinet on the N6X series supports.
4. 6.7 Testing the Insulation of the N68E-22 Cabinet
This describes how to test the insulation of the N68E-22 cabinet to ensure that the cabinet
is insulated from the ground.
5. 6.8 Combining N68E-22 Cabinets
This describes how to use connecting plates to install two or more cabinets side by side.
6. 6.9 Restoring the ESD Floor
This describe how to restore the ESD floor. After the N68E-22 cabinet is installed on the
ESD floor, you need to install the horizontal pallet and restore the ESD floor around the
cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-1


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

6.1 Materials for Installing the N68E-22 Cabinet on the ESD


Floor
The materials for installing the N68E-22 cabinet on the ESD floor are N68E-22 cabinet and N6X
series support assembly.
Table 6-1 lists the materials required for the installation.

Table 6-1 Materials required for the installation


Name Type Quantity

N68E-22 cabinet - Determined based on the


requirements on site

N6X series support assembly Support 2 x Number of the cabinets

Guide rail 2 x Number of the cabinets

Horizontal pallet 2 x Number of the cabinets

6.2 Template Files for Installing the N68E-22 Cabinet


The template files for installing the N68E-22 cabinet consist of the equipment room floor plan
and the marking template. The equipment room floor plan is used to determine the installation
position of the N68E-22 cabinet in the equipment room. The marking template is used to
determine the drilling positions. The equipment room floor plan can be used both when the
N68E-22 cabinet is installed on the concrete floor and when the N68E-22 cabinet is installed on
the ESD floor, but the marking template varies with the installation position.

Equipment Room Layout


The Equipment Room Layout is provided by the customer or the site survey personnel. Figure
6-1 is an example of the Equipment Room Layout.

6-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-1 Equipment room layout (unit: mm)

NOTE

See Figure 6-1. The requirements for the installation position of the N68E-22 cabinet are as follows:
l The horizontal distance between two rows of cabinets should be at least 1,000 mm.
l The distance between the wall and the side of cabinet that is the closest to the wall is at least 800
mm.
l The distance between the wall and the front/back of cabinet that is the closest to the wall is at least
800 mm for double-door N68E-22 cabinet, and it is at least 1,000 mm for single-door N68E-22
cabinet.
l The width of the passages in the equipment room is at least 1,000 mm.

Marking Template
The marking template is delivered with the cabinet. The marking template for installing the
N68E-22 cabinet on the concrete floor is different from the marking template for installing the
N68E-22 cabinet on the ESD floor. See Figure 6-2 and Figure 6-3.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-3


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-2 Marking template for installing the N68E-22 cabinet on the concrete floor (unit: mm)

Figure 6-3 Marking template for installing the N68E-22 cabinet on the ESD floor (unit: mm)

6.3 N6X Series Support Assembly


The N6X series support assembly consists of the N6X series supports, guide rail, and horizontal
pallet. The cabinet, guide rail, and supports are fixed by bolts, and the ESD floor is supported
by the horizontal pallet.

N6X Series Supports


Supports are used to lift the cabinet for the convenience of cabling. Figure 6-4 shows the N6X
series supports.

6-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-4 N6X series supports

(1) Half support (2) Expansion lever (3) M8 screw assembly

(4) Connection holes for the support (5) Connection holes for the support (6) Height mark of the ESD floor
and the guide rail and the horizontal pallet

(7) Height locking bolt (8) Installation hole to the ground

The N6X series supports are adjustable. You can adjust the length of the expansion lever by
adjusting the M8 screw assembly and the supports.
The N6X series supports feature two models. One model has a fixed height and the other has
adjustable heights. Table 6-2 lists applicable height range of each support type.

Table 6-2 Applicable height range of each support type


Type Applicable Height of the ESD Remarks
Floor

I Support with 296 mm to 465 mm l The supports can be adjusted to


adjustable any height within the range.
heights l The height of the ESD floor is the
distance between the upper
surface of the ESD floor and the
concrete floor.

II Support with Customized based on the height of The supports are suitable for
fix height the ESD floor. extremely high or low applications.
The lowest applicable floor height
is 100 mm.

Guide rail
The guide rail connects the cabinet and the support. Figure 6-5 shows the guide rail.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-5


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-5 Guide rail

(1) Connection holes for the cabinet (2) Connection holes for the support

Horizontal Pallet
The horizontal pallet supports the floor in front of and at the rear of the cabinet. Figure 6-6
shows the horizontal pallet.

Figure 6-6 Horizontal pallet

(1) Connection holes for the support

6.4 Positioning the N68E-22 Cabinet on the ESD Floor


This describes how to position the N68E-22 cabinet on the ESD floor, including positioning the
cabinet, drawing lines, drilling holes, and installing expansion bolt assembly.

Prerequisite
l The materials required for the installation are available. They are the M12x60 expansion
bolt assemblies.
l The materials required for the installation are available. They are the line drawing template
and the Equipment Room Layout.
l The tools required for the installation are available. They are a tape, panel lifter, electric
saw, ink fountain, marking pen, percussion drill (with φ16 drill bits), cleaner, safety
goggles, dustproof coverings for electronic equipment, and rubber hammer.

Procedure
Step 1 Check and ensure that the Equipment Room Layout can meet the requirements for installing the
N68E-22 cabinet by referring to 6.2 Template Files for Installing the N68E-22 Cabinet.
Step 2 According to the dimensions specified in the Equipment Room Layout, use the tape to measure
and determine the position of the cabinet.

6-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Step 3 Remove the ESD floor in the installation area by using a panel lifter.
Step 4 Remove the supporting pieces of the ESD floor.
Step 5 Clean the installation area.
Step 6 Determine the method for locating the holes for the expansion bolt assemblies on the concrete
floor.
You can locate the holes using the line drawing template or the tape. Before using the line
drawing template, you need to check whether it is intact by measuring the dimensions of the
paper line drawing template. For details, refer to 6.2 Template Files for Installing the N68E-22
Cabinet.

If ... Then ...

The line drawing template is shipped with Locate the holes for the expansion bolt
the product and is intact, assemblies using the line drawing template. Go
to Step 7.

Other, Locate the holes for the expansion bolt


assemblies using the tape. Go to Step 8.

Step 7 Locate the holes for the expansion bolt assemblies using the line drawing template.
1. Based on Figure 6-7 or Figure 6-8, measure and draw several marking points using
measuring and marking tools, and then draw the base lines.
2. Place the line drawing template on the floor. Ensure that the half-circle gap on the template
indicates the face of the cabinet, and that the border line are in alignment with the base line.
3. Mark the positions for expansion bolts on the floor using the template. Mark four bolt
positions for each cabinet.
4. Measure the hole location line carefully, and ensure that the dimensions are accurate.
5. Go to Step 9.
Step 8 Locate the holes for the expansion bolt assemblies using the tape.
1. Based on Figure 6-7 and Figure 6-8, draw two straight lines by using the measuring and
marking tools. The two lines must be parallel to the front of the cabinet, and the spacing
between them must be 704 mm.

Figure 6-7 Installation holes for one cabinet (unit: mm)

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-7


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-8 Installation holes for a row of cabinets (unit: mm)

2. Based on Figure 6-7 or Figure 6-8, determine the position of the first expansion bolt
assembly on the lines as datum marks, and then mark positions of the other ones.
3. Measure the hole location line carefully, and ensure that the dimensions are accurate.
Step 9 Drill holes.

CAUTION
l Check the thickness of the concrete floor, and ensure that the drill bit does not penetrate
through the concrete floor. Before drilling holes in some concrete floors, you must consult
the architect.
l Before drilling holes, protect the electronics by using the dust-proof cover. When drilling
holes, use a vacuum cleaner to clear the dust. Clear the dust before removing the dust-proof
cover.
l When drilling holes, wear safety goggles to protect your eyes.
l Keep the drilling bit vertical to the ground and hold the drill stock tightly to drill holes.

1. Use a chisel to dig a pit before drilling, as shown in Figure 6-9.

Figure 6-9 Digging a pit before drilling

2. Mark the positions of the expansion bolts on the concrete floor using a chisel. Ensure that
the hole depth are the same, ranging from 52 mm to 60 mm, as shown in Figure 6-10.

6-8 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-10 Drilling holes

3. Ensure that the depth of the holes is within the range of 52 mm to 60 mm and the holes are
vertical. If the depth of the hole is not appropriate or if the hole is lopsided, re-drill the hole.
4. Use a vacuum cleaner to clear the dust inside and around the holes.
Step 10 Install the expansion bolt assemblies.
Figure 6-11 shows the expansion bolt assembly.

Figure 6-11 Expansion bolt assembly

(1) Bolt (2) Spring washer (3) Flat washer (4) Expansion tube

(5) Expansion nut (6) Guiding slot (7) Guiding rib

1. Use a vacuum cleaner to clear the dust inside and around the holes. Measure the spacing
between holes. If the spacing between holes is not proper, reposition the hole and re-drill
before installing the expansion bolt assembly.
2. Put the guiding rib of expansion nut in the guiding slot of the tube, screw the bolt until the
guiding slot cannot fall out of the guiding rib, as shown in ① of Figure 6-12.
3. Place the expansion bolt assembly into the hole vertically, and then use the nail hammer to
drive the entire expansion tube into the hole, as shown in ② of Figure 6-12.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-9


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-12 Installing the expansion bolt assembly (I)

4. Screw the expansion bolts in the clockwise direction. Ensure that the expansion nut and
the expansion tube are tightened, as shown in ① of Figure 6-13.
5. Screw off the expansion bolt in the anti-clockwise direction, remove the spring washer and
the flat washer, and store them properly for later use, as shown in ② of Figure 6-13.

Figure 6-13 Installing the expansion bolt assembly (II)

----End

6.5 Assembling the Support and the Guide Rail


This describes how to assemble the N6X series supports and guide rails, and how to fix them
on the concrete floor.

Prerequisite
l The materials required for the installation are available. They are supports, the guide rail,
M12x35 bolt assembly, and M12x60 bolt assembly.
l The materials required for the installation are available. They are spring washers 12, flat
washers 12, and big flat washers.
l The tools required for the installation are available. They are a torque wrench and a
horizontal ruler.

6-10 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Procedure
Step 1 Adjust the height of the support. Adjust the two half supports, and ensure that the end of the
supports are in alignment with the silkscreen 800 on the expansion lever. Then screw the six
M8x20 bolt assembly, as shown in Figure 6-14.

Figure 6-14 Adjusting the height of the support

(1) Half support (2) M8 bolt assembly

(3) Expansion lever (4) Height locking bolt

Step 2 Adjust the height of the support.


1. Loosen the height locking bolts. Figure 6-14 shows positions of the height locking bolts.
2. Adjust the height of the support. Ensure that the height indicator on the support is on the
same level as the ESD floor.

CAUTION
l The height of the ESD floor is provided in the engineering survey report.
l Ensure that the height silkscreen value of each support is the same as the measurement
height of the ESD floor. Otherwise, in the case of capacity expansion, the heights of the
cabinets in the same row might be inconsistent.

3. Fasten the two height locking bolts in the middle, and then the four height locking bolts on
both sides using a torque wrench to 45N·m.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-11


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Step 3 Figure 6-15 shows how to assemble the guide rails.

Figure 6-15 Assembling guide rails

(1) Support (2) Guide rail (3) M12x35 bolt

(4) Spring washer (5) Flat washer

1. Place the guide rail on the support, and then align the installation holes on the guide rail
with the that on the support.
2. Assemble the support with guide rails using the M12x35 bolt assembly, spring washers,
and flat washers.
3. Adjust the position of the support to ensure that the diagonal lines of the two guide rails
are equal in length, with a deviation of 2 mm.
4. Fasten the bolts in a cross way.
Step 4 Adjust and fix the support.
1. Align the installation holes on the support with the holes on the ground, and then place the
support on the ground.
2. Fit the spring washer and flat washers on the M12x60 bolts, and then insert the bolts through
the holes on the support into the four holes on the ground vertically, as shown in Figure
6-16.

6-12 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-16 Fixing the support

(1) Support (2) Guide rail (3) M12x60 bolt

(4) Spring washer (5) Big flat washer (6) Adjusting pad

(7) Expansion tube (8) Expansion nut (9) Horizontal ruler

3. Place the horizontal ruler on the support to check the levelness. If the support is not level,
add adjusting pads until the support is level in both directions.
4. Then fasten the four bolts diagonally to 45 N·m.
Step 5 In combined cabinet installation, install the supports side by side.
To facilitate later installation, use insulation plate to help determine distance between two
adjacent supports. Figure 6-17 shows the insulation plate.

Figure 6-17 Insulation plate

(1) Location hole (2) Installation hole

1. Place the insulation plate on the guide rails of two adjacent supports, with the half-circle
gaps facing the installation holes on guide rails. Then locate the supports using M12x35
bolt assembly, as shown in Figure 6-18. Adjust the distance between adjacent supports
using the insulation plate by following the same steps.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-13


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-18 Installing supports in a row

(1) Insulation plate (2) M12x35 bolt

2. Check the levelness of the supports using a horizontal ruler. If the supports are not level,
adjust the supports using adjusting pads, as shown in Figure 6-18.
3. Fasten the height locking bolts using a wretch.
4. Remove the M12x35 bolt assembly and the insulation plates, and store them properly for
fixing the cabinet.

----End

6.6 Fixing the N68E-22 Cabinet on the ESD Floor


This describes how to fix the N68E-22 cabinet on the ESD floor. The front and rear doors of the
cabinet are installed before delivery. You need to remove the front and rear doors, and then fix
the N68E-22 cabinet on the N6X series supports.

Prerequisite
l The materials required for the installation are available. They are the cabinet and M12x35
bolts.
l The materials required for the installation are available. They are insulation plate, flat
washers 12, and spring washers 12.
l The tools required for the installation are available. They are a horizontal ruler, torque
wrench, socket wrench, and cross screwdriver.

Context

CAUTION
The gravity center of the cabinet lies in the upper part. Therefore, do not lift or push the cabinet
alone. To move a cabinet, at least two persons are required and use a forklift to ensure personal
safety and to avoid damage to the cabinet.

6-14 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Procedure
Step 1 Remove the protection boards in front of and at the rear of the cabinet.

Step 2 Remove the four wooden packing accessories at the left and right of the rack, pull down the
hook pin on the front and rear doors, and then remove the front and rear doors and place them
properly, as shown in Figure 6-19.

Figure 6-19 Removing the wooden packing accessories

NOTE

When placing the doors of the cabinet, ensure that the locks are open to prevent distortion of the levers at
the lower part of the door, as shown in Figure 6-20.

Figure 6-20 State of locks on the front and rear doors

Step 3 Remove the short supporting beams in front of the cabinet, as shown in Figure 6-21.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-15


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-21 Removing the short supporting beam in front of the cabinet

Step 4 Remove the two M6x12 screws on the air filter, as shown in ① of Figure 6-22. Remove the air
filter, as shown in ② of Figure 6-22, and store it properly for later use.

6-16 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-22 Removing the air filter

Step 5 Determine the front of the cabinet, and then lift the cabinet onto the guide rail. Ensure that the
four installation holes at the bottom of the cabinet are in alignment with that on the guide rails.

Step 6 Fit the spring washers, flat washers, and insulation coverings on the four expansion bolts, insert
the expansion tube, and then screw the expansion nuts, as shown in Figure 6-23.

Step 7 From the front and rear of the cabinet, install two insulation plates at the lower part of the cabinet.
Ensure that the nicks face inside and the installation holes on the insulation plates are in alignment
with that for the expansion bolts, as shown in Figure 6-23.

Figure 6-23 Installing the cabinet

(1) N68E-22 cabinet (2) Guide rail (3) Support

(4) Insulation plate (5) Insulation covering (6) Flat washer

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-17


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

(7) Spring washer (8) Bolt

Step 8 Level the cabinet. Check the levelness of the cabinet using a horizontal ruler. If the cabinet is
not level, adjust the pad (adjusting range: 0–10 mm) using a socket wrench, as shown in Figure
6-24.

Figure 6-24 Leveling the cabinet

(1) Adjusting pad (2) Fixing bolt

Step 9 Screw the four fixing bolts to 45 N·m by using a torque wrench.

----End

6.7 Testing the Insulation of the N68E-22 Cabinet


This describes how to test the insulation of the N68E-22 cabinet to ensure that the cabinet is
insulated from the ground.

Prerequisite
The multimeter required for the insulation test is available.

Procedure
Step 1 Set the multimeter to the megohm position.

Step 2 Measure the resistance between the M12x60 expansion bolt and the cabinet.

If... Then...

The resistance is equal to or greater than five Go to Step 7.


megohms,

6-18 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

If... Then...

The resistance is smaller than five megohms, You can infer that the cabinet is not insulated
from the ground and then go to Step 3.

Figure 6-25 Insulation test

Step 3 Remove all the installation parts between the N68E-22 cabinet and the ground.

Step 4 Check that the insulation parts are not missing or damaged.

Step 5 Fix the cabinet again.

Step 6 Go back to Step 1 to test the insulation again.

Step 7 Use two M6x12 screws to fix the air filter and ensure that it is in the original position. See Figure
6-26.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-19


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-26 Repositioning the air filter

----End

6.8 Combining N68E-22 Cabinets


This describes how to use connecting plates to install two or more cabinets side by side.

Prerequisite
The required tools such as wrench and climbing ladder are available.

Context
The connecting plates are installed on top of and are delivered with the cabinets.

Procedure
Step 1 Remove the connecting plates from the column inside the cabinet, rotate each of them by 180
degrees, and then reinstall them. Use M8x30 bolts to connect the connecting plates of the adjacent
cabinets together. See Figure 6-27 ①.

6-20 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-27 Connecting the connecting plates

Step 2 Remove the two connecting plates from the front and rear doorheads of the adjacent cabinets.
Then, reinstall the connecting plates, as shown in Figure 6-27 ②.
Step 3 At the bottom of the combined cabinets and in front of the column, use a level bar to check
whether the levelness and vertical deviation of the row of cabinets meet the specifications, as
shown in Figure 6-28. If the cabinet is not level, use a socket wrench to adjust the leveling foot.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-21


Copyright © Huawei Technologies Co., Ltd
6 Installing the N68E-22 Cabinet on the ESD Floor N68E-22 Cabinet Installation Guide

Figure 6-28 Using a level bar to check the levelness

----End

6.9 Restoring the ESD Floor


This describe how to restore the ESD floor. After the N68E-22 cabinet is installed on the ESD
floor, you need to install the horizontal pallet and restore the ESD floor around the cabinet.

Prerequisite
l The materials required for the installation are available. They are the horizontal pallet and
M12x30 bolt assembly.
l The materials required for the installation are available. They are spring washers 12 and
flat washers 12.
l The tools required for the installation are available. They are a wrench and a hand saw.

Procedure
Step 1 Fix the horizontal pallet to the support using M12x30 bolt assembly, as shown inFigure 6-29.

6-22 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 6 Installing the N68E-22 Cabinet on the ESD Floor

Figure 6-29 Installing the horizontal pallet

Step 2 Adjust the height of the horizontal pallet to ensure that the horizontal pallet securely contact the
ESD floor.
Step 3 Cut and restore the ESD floor around the racks based on actual requirements, as shown in Figure
6-30.

Figure 6-30 Restoring the ESD floor around the racks

----End

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 6-23


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

7 Installing Power Cables and PGND Cables


for the N68E-22 Cabinet

About This Chapter

This describes how to install the power cables and PGND cables between the N68E-22 cabinet
and the Power Distribution Frame (PDF). When the cabinets are combined, you also need to
install the PGND cables between the N68E-22 cabinets.

Prerequisite
l The N68E-22 cabinet is installed.
l The power cables and PGND cables required for installing the N68E-22 are ready.

1. 7.4 Installing Power Cables and PGND Cables Between the N68E-22 Cabinet and the PDF
This describes how to install the power cables and PGND cables between the N68E-22
cabinet and the PDF. The installation methods include two types: overhead cabling and
underfloor cabling. Select either of them according to the actual scenario.
2. 7.5 Installing PGND Cables Between the Adjacent N68E-22 Cabinets
When the N68E-22 cabinets are combined, link the three equipotential PGND cables on
the mounting bars at the back of the cabinet between the adjacent N68E-22 cabinets.
3. 7.6 Checking the Power-On Status of the RNC Cabinets
This describes how to check the power supplies to the RNC. After the checking, ensure
that the power supplies to the subracks, fan box, and boards are all working properly.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-1


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

7.1 RNC Power Cables and PGND Cables to Be Installed


The power cables and PGND cables required to be installed on site are the external RNC power
cables, external RNC PGND cables, and PGND cables for interconnecting RNC cabinets.

7.1.1 RNC Power Cables


The RNC power cables provide DC power for the cabinet and its internal modules. The RNC
power cables are of two categories: external power cables and internal power cables. The cables
are mandatory.
7.1.2 RNC PGND Cables
The PGND cables are used to ground the RNC cabinet and its internal modules. They are
mandatory.

7.1.1 RNC Power Cables


The RNC power cables provide DC power for the cabinet and its internal modules. The RNC
power cables are of two categories: external power cables and internal power cables. The cables
are mandatory.

Description of RNC Power Cables


The RNC external power cables are used to connect the Power Distribution Frame (PDF) to the
RNC power distribution box. The connectors of the external power cables need to be made on
site.
Table 7-1 shows the external power cables of the N68-21-N cabinet. Table 7-2 shows the
external power cables of the N68E-22 cabinet.

Table 7-1 External power cables of the N68-21-N cabinet


Cable Color Cross- Type and Type and Quantity
Name Sectional Installation Installation
Area Position of Position of
Connector 1 Connector 2

Externa Blue 25 mm2/35 2-hole JG Based on the 4 per cabinet


l -48 V mm2 terminal/-48 V DC actual site
DC input port on the measurement/-
power power distribution 48 V DC output
cable box port

Externa Black 25 mm2/35 2-hole JG terminal/ Based on the 4 per cabinet


l RTN mm2 RTN input port on actual site
power the power measurement/
cable distribution box RTN output
port

7-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Table 7-2 External power cables of the N68E-22 cabinet


Cable Color Cross- Type and Type and Quantity
Name Sectional Installation Installation
Area Position of Position of
Connector 1 Connector 2

Externa Blue 25 mm2/35 OT terminal/-48 V Based on the 4 per cabinet


l -48 V mm2 DC input port on the actual site
DC power distribution measurement/-
power box 48 V DC output
cable port

Externa Black 25 mm2/35 OT terminal/RTN Based on the 4 per cabinet


l RTN mm2 input port on the actual site
power power distribution measurement/
cable box RTN output
port

NOTE

The colors of the external power cables listed here are just for reference. The colors must be in accordance
with the special field requirements if any.

The internal power cables connect the power distribution boxes to the modules inside the RNC
cabinet and thus supply the multiple outputs of the power distribution box to the modules. The
internal power cables are installed before the RNC cabinet is delivered.
The connectors of the power cables of the N68E-22 cabinet are the same as those of the N68-21-
N cabinet. Table 7-3 shows the internal power cables of the RNC.

Table 7-3 Internal power cables of the RNC


Cable Color Cross- Type and Connector Quantity
Name Sectional Installation Type 2/
Area Position of Installation
Connector 1 Position 2

Internal Blue 8 mm2 OT terminal/–48 V OT terminal/ 2 per


–48 V DC output port on DC input port subrack
power the power on the subrack
cable distribution box For details, see
For details, see lines lines 1, 3, 5, 7,
1, 3, 5, 7, 9, 11 in 9, 11 in 11.4
11.4 Connections of Connections of
Power Cables and Power Cables
PGND Cables in and PGND
the RNC Cabinet. Cables in the
RNC Cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-3


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Cable Color Cross- Type and Connector Quantity


Name Sectional Installation Type 2/
Area Position of Installation
Connector 1 Position 2

Internal Black 8 mm2 OT terminal/–48 V OT terminal/ 2 per


RTN DC output port on DC input port subrack
power the power on the subrack
cable distribution box For details, see
For details, see lines lines 2, 4, 6, 8,
2, 4, 6, 8, 10, 12 in 10, 12 in 11.4
11.4 Connections of Connections of
Power Cables and Power Cables
PGND Cables in and PGND
the RNC Cabinet. Cables in the
RNC Cabinet.

Appearance
Figure 7-1 shows the internal power cable of the RNC.

Figure 7-1 -48 V/RTN internal power cable of the RNC

(1) OT terminal

Figure 7-2 shows the external power cable of the N68E-22 cabinet.

Figure 7-2 External power cable of the N68E-22 cabinet

(1) OT terminal

Figure 7-3 shows the external power cable of the N68-21-N cabinet.

Figure 7-3 External power cable of the N68-21-N cabinet

(1) OT terminal (2) 2-hole JG terminal

7-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

7.1.2 RNC PGND Cables


The PGND cables are used to ground the RNC cabinet and its internal modules. They are
mandatory.

Description of RNC PGND Cables


The external PGND cable is mandatory for the RNC cabinet. Each RNC cabinet is configured
with one external PGND cable. When the cabinets are combined, three interconnection PGND
cables must be installed between every two adjacent cabinets. Other PGND cables are already
installed in the cabinet before delivery.
Table 7-4 describes the PGND cables of the N68-21-N cabinet.

Table 7-4 PGND cables of the N68-21-N cabinet


Cable Color Cross- Connector Connector Quantity
Name Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2

External Green and 25 mm2/35 2-hole JG Based on the 1 per


PGND yellow mm2 terminal/ site survey/ cabinet
cable Grounding PGND output
bolt at the top port
back of each
cabinet

Interconne Green and 6 mm2 OT terminal/ OT terminal/ 3 per


ction yellow PGND Busbar PGND Busbar couple of
PGND of each RNC of each RNC adjacent
cable cabinet cabinet cabinets
For details, For details, see
see lines 24 to lines 24 to 26 in
26 in Connections of
Connections the power
of the power cables and
cables and PGND cables
PGND cables in the N68-21-
in the N cabinet.
N68-21-N
cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-5


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Cable Color Cross- Connector Connector Quantity


Name Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2

PGND Green and 10 mm2 OT terminal/ OT terminal/ 2 per


cable of the yellow PGND Busbar PGND wiring cabinet
cabinet of each RNC post on the
Busbar cabinet cabinet top
For details, For details, see
see lines 20 to lines 20 to 21 in
21 in Connections of
Connections the power
of the power cables and
cables and PGND cables
PGND cables in the N68-21-
in the N cabinet.
N68-21-N
cabinet.

PGND Green and 6 mm2 OT terminal/ OT terminal/ 1 per


cable of the yellow PGND Busbar port for PGND cabinet
power of each RNC cable on the
distribution cabinet power
box For details, distribution box
see line 13 in For details, see
Connections line 13 in
of the power Connections of
cables and the power
PGND cables cables and
in the PGND cables
N68-21-N in the N68-21-
cabinet. N cabinet.

PGND Green and 6 mm2 OT terminal/ OT terminal/ 2 per


cable of the yellow PGND Busbar port for PGND subrack
subrack of each RNC cable on the
cabinet subrack
For details, For details, see
see lines 14 to lines 14 to 19 in
19 in Connections of
Connections the power
of the power cables and
cables and PGND cables
PGND cables in the N68-21-
in the N cabinet.
N68-21-N
cabinet.

7-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Cable Color Cross- Connector Connector Quantity


Name Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2

PGND Green and 6 mm2 OT terminal/ OT terminal/ 8 per


cable of the yellow grounding grounding bolt cabinet
cabinet bolt on the on each door
door base For details, see
For details, lines 50 to 57 in
see lines 50 to Connections of
57 in the power
Connections cables and
of the power PGND cables
cables and in the N68-21-
PGND cables N cabinet.
in the
N68-21-N
cabinet.

Table 7-5 shows the PGND cables of the N68E-22 cabinet.

Table 7-5 PGND cables of the N68E-22 cabinet


Cable Color Cross- Connector Connector Quantity
Name Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2

External Green and 25 mm2/35 OT terminal/ Determine the 1 per


PGND yellow mm2 grounding terminal type cabinet
cable bolt at the top based on the site
back of each survey/output
cabinet terminal of the
PGND cable

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-7


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Cable Color Cross- Connector Connector Quantity


Name Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2

Interconne Green and 6 mm2 OT terminal/ OT terminal/ 3 between


ction yellow grounding grounding hole adjacent
PGND hole of the in the mounting cabinets
cable mounting bar bar of the RNC
of the RNC cabinet
cabinet For details, see
For details, lines 24 to 26 in
see lines 24 to Connections of
26 in the power
Connections cables and
of the power PGND cables
cables and in the N68E-22
PGND cables cabinet.
in the
N68E-22
cabinet.

PGND Green and 6 mm2 OT terminal/ OT terminal/ 1 per


cable of the yellow grounding terminal for the cabinet
power hole in the PGND cable on
distribution mounting bar the power
box of the RNC distribution box
cabinet For details, see
For details, line 13 in
see line 13 in Connections of
Connections the power
of the power cables and
cables and PGND cables
PGND cables in the N68E-22
in the cabinet.
N68E-22
cabinet.

7-8 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Cable Color Cross- Connector Connector Quantity


Name Sectional Type 1/ Type 2/
Area Installation Installation
Position 1 Position 2

PGND Green and 6 mm2 OT terminal/ OT terminal/ 2 per


cable of the yellow grounding port for the subrack
subrack hole in the PGND cable on
mounting bar the subrack
of the RNC For details, see
cabinet lines 14 to 19 in
For details, Connections of
see lines 14 to the power
19 in cables and
Connections PGND cables
of the power in the N68E-22
cables and cabinet.
PGND cables
in the
N68E-22
cabinet.

PGND Green and 6 mm2 OT terminal/ OT terminal/ 8 per


cables of yellow grounding grounding bolt cabinet
cabinet hole in the on each door
doors column of the For details, see
RNC cabinet lines 50 to 57 in
For details, Connections of
see lines 50 to the power
57 in cables and
Connections PGND cables
of the power in the N68E-22
cables and cabinet.
PGND cables
in the
N68E-22
cabinet.

NOTE

l The minimum bending radius of the RNC external PGND cable is 30 mm.
l The colors of the PGND cables listed here are just for reference. For special requirements, the colors
can be changed accordingly.

Appearance
Figure 7-4 shows the external PGND cable of the N68-21-N cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-9


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Figure 7-4 External PGND cable of the N68-21-N cabinet

(1) OT terminal (2) 2-hole JG terminal

Figure 7-5 shows the external PGND cable of the N68E-22 cabinet.

Figure 7-5 External PGND cable of the N68E-22 cabinet

(1) OT terminal

Figure 7-6 shows the internal RNC PGND cable.

Figure 7-6 Internal RNC PGND cable

(1) OT terminal

7.2 Connections of RNC Power Cables and PGND Cables


This describes how the power cables and the PGND cables connect the RNC to the power
distribution frame (PDF) and how the PGND cables interconnect the RNC cabinets.

Figure 7-7 shows the connections of the power cables and PGND cables.

Figure 7-7 Cable connections

7-10 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

NOTE

l Each RNC cabinet is configured with nine cables, that is four -48 V power cables, four RTN power
cables, and one PGND cable.
l It is recommended that the PGND cables of the RNC cabinets be connected to the closest grounding
bar. When the PDF is far from the RNC cabinets, for example, the PDF is not in the same equipment
room as the RNC cabinets, connect the PGND cables of the RNC cabinets to the closest grounding
bar co-grounded with the PDF rather than connect the PGND cables directly with the PDF.

7.3 Installation Specifications for RNC Power Cables and


PGND Cables
When installing the RNC power cables and PGND cables, ensure that the requirements for
routing and binding the cables are met.

Requirements for Routing Cables


l Before routing the cables, wrap the connectors by using the insulating tapes to prevent the
connectors from contacting the terminals connected to the PDF.
l While routing cables, take the capacity expansion into consideration.
l Separate the power cables and PGND cables from the signal cables.
l When power cables or PGND cables are laid parallel to signal cables, leave at least 10 mm
between the power cables or PGND cables and the signal cables inside the cabinet and at
least 100 mm between them outside the cabinet.
l Ensure that the bend radius of the power cables and PGND cables is five times longer than
the diameter of the cable.
l In the underfloor cabling mode, reserve extra length of the power cables outside the cable
holes of the power distribution box on top of the cabinet. The purpose is to help plug in
and pull out the cables. In addition, flush the cables at the top of the cabinet.
l When connecting power cables to the terminals of the power distribution box, route them
in a straight manner and ensure that The cables are routed smoothly without any tangling.

Requirements for Binding Cables


l Bind the power cables and PGND cables separately from the signal cables.
l Bind the power cables and PGND cables every 200 mm.
l Determine the types of cable ties (100 mm, 150 mm, 300 mm, or 295 mm) based on the
number of cables.
l Orient the cable ties to the same direction.
l Bind the cables tightly. Then cut off the surplus parts completely for indoor cable ties and
leave 3 mm to 5 mm for outdoor cable ties. Trim the tails of the cable ties.

7.4 Installing Power Cables and PGND Cables Between the


N68E-22 Cabinet and the PDF
This describes how to install the power cables and PGND cables between the N68E-22 cabinet
and the PDF. The installation methods include two types: overhead cabling and underfloor
cabling. Select either of them according to the actual scenario.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-11


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

7.4.2 Installing Power Cables and PGND Cables Between the N68E-22 Cabinet and the PDF
(Overhead Cabling)
This describes how to install power cables and PGND cables between the N68E-22 cabinet and
the PDF by overhead cabling.
7.4.3 Installing Power Cables and PGND Cables Between the N68E-22 Cabinet and the PDF
(Underfloor Cabling)
This describes how to install power cables and PGND cables between the N68E-22 cabinet and
the PDF by underfloor cabling.

7.4.1 Overhead and Underfloor Cabling Modes


The cables can be connected to the RNC cabinet in either overhead cabling mode or underfloor
cabling mode.
Based on actual scenarios, the cabling can be of either overhead or underfloor cabling mode.
For overhead cabling mode, the cables are led upward out of the cabinet through the upper cable
hole or other channels; for underfloor cabling mode, the cables are led downward out of the
cabinet through the lower cable hole or other channels. Here shows an example of overhead/
underfloor cabling mode through the upper/lower cable hole.
External cables can be connected to the RNC cabinet either through the upper cable hole or the
lower cable hole. Each corner on the top and the bottom of the cabinet provides a rectangular
cabling hole, as shown in Figure 7-8.

7-12 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Figure 7-8 Cable holes of the RNC cabinet

If the cable hole is covered with the rodent-proof cover, you need to remove the cover before
the cabling. Then, lead the cables through the cable hole and bind the cables. Replace the rodent-
proof cover on the cable hole, and mark the area to be cut based on the cross section of the bound
cables. Then, use the scissors to cut the area. At last, replace the rodent-proof cover. Ensure that
the bound cables fit in well with the cover, that is, the cables are fully engaged and no side
clearance is left.

Overhead Cabling
The cables are fixed through the cable holes of the two sides at the top of the cabinet. Route the
cables along both sides of the cabinet in the downward way to the related devices. The overhead
cabling mode is suitable for the equipment room with the cement floor, as shown in Figure
7-9.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-13


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Figure 7-9 Overhead cabling mode

Underfloor Cabling
The cables are fixed through the cable holes of the two sides at the bottom of the cabinet. Lay
the cables along the both sides of the cabinet in the upward way to the related devices. The
underfloor cabling mode is suitable for the equipment room with the ESD floor, as shown in
Figure 7-10. When the underfloor cabling mode is applied, ensure that the height of the piled
cables cannot exceed the 3/4 height of the space under the ESD floor.

Figure 7-10 Underfloor cabling mode

7-14 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

7.4.2 Installing Power Cables and PGND Cables Between the


N68E-22 Cabinet and the PDF (Overhead Cabling)
This describes how to install power cables and PGND cables between the N68E-22 cabinet and
the PDF by overhead cabling.

Prerequisite
l The N68E-22 cabinet to be connected with power cables and PGND cables is installed.
l The output power switches on the PDF are set to OFF.
l All switches on the power distribution box of the N68E-22 cabinet are set to OFF.
l The parts to be installed are all ready. The parts for the installation are: power cable and
PGND cable.
l The materials required for the installation are ready. The materials required refer to cable
ties.
l The tools required for the installation are all ready. The tools for the installation are:
diagonal pliers, handsaw, cable cutter, wrench, and cross screwdriver.

Context
The following takes the PDF shipped with the RNC as an example to describe how to install the
cables within the PDF. For details, refer to the documents shipped with the PDF. If other types
of DC power distribution cabinets are used on site, refer to the relevant documents for the cable
installation.

Figure 7-11 shows how to install power cables and PGND cables between the N68E-22 cabinet
and the PDF by overhead cabling.

Figure 7-11 Installing power cables and PGND cables between the N68E-22 cabinet and the
PDF (overhead cabling)

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-15


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Procedure
Step 1 Determine the length of each power cable and PGND cable by referring to the relevant
engineering design document or according to the actual site survey.
Step 2 Lay out the power cables and PGND cables on site, and determine the length of the cables using
the tape measure or other measuring tools. Then , use the handsaw (teeth space: 0.8 mm) or cable
cutter (KT35) to cut the cable of the length a little longer than necessity.

CAUTION
If a cable is not long enough, replace it with a longer one. Do not join another cable to the short
one by adding a connector or welding.

Step 3 Attach temporary labels to both ends of the cables. The contents on the temporary labels are not
restricted because they are only for distinguishing the cables after the layout.
Step 4 Lay the power cables and PGND cables according to the requirements for routing cables and
the engineering requirements.
1. Lead the power cables and PGND cable out of the PDF through the upper cable hole in the
PDF.

CAUTION
l If the distance between the cable rack and the top of the cabinet exceeds 800 mm, use
a ladder for leading the cables down to the cabinet.
l Ensure that the bend radius is five times longer than the diameter of the cable.

2. Lead the cables to the cable rack.


3. Lead the cables to the top of each N68E-22 cabinet along the cable rack.
Step 5 Connect the power cables and PGND cable to the N68E-22 cabinet.
1. Make OT terminals for the power cables and PGND cable at the N68E-22 cabinet. Refer
to Assembling the OT Terminal and the Power Cable.
2. Fix the wiring terminal of the PGND cable to the grounding bolt at the top back of the
cabinet. The grounding bolt is labeled .
3. Remove the plastic cover plates off the cable holes on the top of the cabinet, and prepare
the cover plates and screws for future use.
4. Lead the RTN and -48 V power cables through the upper cable hole into the cabinet until
they reach the input terminals of the power distribution box. Link the RTN cables to the
wiring terminal labeled +, and the -48 V cables to the wiring terminal labeled -. Then, fasten
the screws.

7-16 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

CAUTION
Input power is not allowed at the 2(+)2(-) input terminals. Thus, link the RTN and -48 V
power cables respectively to input terminals 1(+), 1(-), and 3(+), 3(-).

5. Cut an appropriate cross section of the plastic cover plate after the layout, and then cover
the cable hole with the cut plastic cover plate. Fasten the screws.

Step 6 Link the other end of the power cable to the PDF, and link the other end of the PGND cable to
the PDF or close to the PGND bar.
1. Remove the insulating tapes from the connectors of the cables. Determine the length of the
cables according to their installation positions, and then cut off the redundant parts.
2. Determine the type of connectors for the power and PGND cables at the PDF according to
the cable connection principle of the PDF and the engineering requirements. Then, make
the connectors as required.
3. Connect the PGND cable, the RTN, and the -48 V power cables to the corresponding wiring
posts on the PDF. Fasten all screws.

----End

Postrequisite
Record the operation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

7.4.3 Installing Power Cables and PGND Cables Between the


N68E-22 Cabinet and the PDF (Underfloor Cabling)
This describes how to install power cables and PGND cables between the N68E-22 cabinet and
the PDF by underfloor cabling.

Prerequisite
l The N68E-22 cabinet to be connected with power cables and PGND cables is installed.
l The output power switches on the PDF are set to OFF.
l All switches on the power distribution box of the N68E-22 cabinet are set to OFF.
l The parts to be installed are all ready. The parts for the installation are: power cable and
PGND cable.
l The materials required for the installation are ready. The materials required refer to cable
ties.
l The tools required for the installation are all ready. The tools for the installation are:
diagonal pliers, cable cutter, wrench, cross screwdriver, and lifting rope.

Context
This document takes the PDF shipped with the RNC as an example to describe how to install
the cables within the PDF. For details, refer to the documents shipped with the PDF. If other
types of DC power distribution cabinets are used on site, refer to the relevant documents for the
cable installation.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-17


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Figure 7-12 shows how to install power cables and PGND cables between the N68E-22 cabinet
and the PDF by underfloor cabling.

Figure 7-12 Installing power cables and PGND cables between the N68E-22 cabinet and the
PDF (underfloor cabling)

Procedure
Step 1 Determine the length of each power cable and PGND cable by referring to the relevant
engineering design document or according to the actual site survey.

Step 2 Lay out the roll of power cables and PGND cable on site, and determine the length of the cables
using the tape measure or other measuring tools. Then , use the handsaw (teeth space: 0.8 mm)
or cable cutter (KT35) to cut off the cable of the length a little longer than necessity.

CAUTION
If a cable is not long enough, replace it with a longer one. Do not join another cable to the short
one by adding a connector or by welding.

7-18 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Step 3 Attach temporary labels to both ends of the cables. The contents on the temporary labels are not
restricted because they are only for distinguishing the cables after the layout.

Step 4 Lay the power cables and PGND cable according to the requirements for routing cables and
engineering requirements.
1. Lead four pairs of power cables and one PGND cable through the lower cable hole of the
PDF along under the ESD floor to below the N68E-22 cabinet.
2. Divide the four pairs of power cables into two groups, each of which involves two pairs.
Bind one of the two groups and the PGND cable with the cable tie, and then use the cable
tie to bind the other group separately. Route the two groups of cables to the central columns
at both sides of the N68E-22 cabinet.
3. Route one end of the lifting rope through the central column of the cabinet until it reaches
the bottom of the cabinet, and then bind the lifting rope with the power and PGND cables
below the central column.
4. Pull the end of the lifting rope at the top of the central column until the power cables and
PGND cable reach the top of the central column.
5. Remove the temporary cable ties off the lifting rope, the power cables and PGND cable.

Step 5 Connect the power cables and PGND cable to the N68E-22 cabinet.
1. Make OT terminals for the power cables and PGND cable at the N68E-22 cabinet. Refer
to Assembling the OT Terminal and the Power Cable.
2. Fix the wiring terminal of the PGND cable to the grounding bolt at the top back of the
cabinet. The grounding bolt is labeled .
3. Remove the plastic cover plates off the cable holes on the top of the cabinet, and prepare
the cover plates and screws for future use.
4. Lead the RTN and -48 V power cables through the upper cable hole into the cabinet until
they reach the input terminals of the power distribution box. Link the RTN cables to the
wiring terminal labeled +, and the -48 V cables to the wiring terminal labeled -. Then, fasten
the screws.

CAUTION
Input power is not allowed in the 2(+)2(-) input terminals. Thus, link the RTN and -48 V
power cables respectively to input terminals 1(+), 1(-), and 3(+), 3(-).

5. Cut an appropriate cross section of the plastic cover plate after the layout, and then cover
the cable hole with the cut plastic cover plate. Fasten the screws.

Step 6 Connect the power cables to output terminals of the PDF.


1. Remove the insulating tapes from the connectors of the cables. Determine the length of the
cables according to their installation positions, and then cut off the extra parts.
2. Determine the type of connectors for the power and PGND cables at the PDF according to
the cable connection principle of the PDF and the engineering requirements. Then, the
connectors are made as required.
3. Connect these cables including the PGND cable, the RTN, and the -48 V power cables to
the corresponding wiring posts on the PDF.

----End

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-19


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

Postrequisite
Record the operation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

7.5 Installing PGND Cables Between the Adjacent N68E-22


Cabinets
When the N68E-22 cabinets are combined, link the three equipotential PGND cables on the
mounting bars at the back of the cabinet between the adjacent N68E-22 cabinets.

Prerequisite
l The N68E-22 cabinets to be connected with the PGND cables are installed.
l All switches on the power distribution boxes of the N68E-22 cabinets are set to OFF.
l All the related power distribution switches on the PDF are set to OFF.

Context
Each end of the three equipotential cables is respectively fixed to the mounting bar on the right
back of the cabinet.

Procedure
Step 1 Position the three equipotential cables on the mounting bar at the back of the cabinet.
Step 2 Link the three equipotential cables between the combined cabinets, as shown in Figure 7-13.

7-20 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Figure 7-13 PGND cables between adjacent cabinets

----End

Postrequisite
Record the installation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

7.6 Checking the Power-On Status of the RNC Cabinets


This describes how to check the power supplies to the RNC. After the checking, ensure that the
power supplies to the subracks, fan box, and boards are all working properly.

Prerequisite
l The RNC cabinet is connected to the PDF by power cables and PGND cables.
l All the internal power cables and PGND cables are installed.
l All subracks within the cabinet, the fan box within the subrack, and boards are installed.
l The multimeter is ready.

Context
The RNC cabinet uses the DC power supply. For the requirements of the cabinet power supply,
refer to Technical Specifications for the RNC Power Distribution Box.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-21


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
Cabinet N68E-22 Cabinet Installation Guide

CAUTION
Correctly put on the ESD wrist strap and ensure that the ESD wrist strap is properly connected
to the ESD connector on the cabinet.

Procedure
Step 1 On the PDF, set the status of the corresponding output switch to be OFF.On the power
distribution box of the RNC cabinet, set the status of the corresponding output switch to be
OFF.

Step 2 Set the multimeter to the state of resistance measurement. Use the multimeter to measure the
output terminal on the PDF and the input and output terminals of the power distribution box on
the RNC cabinet. Check that no short circuit exists between the working power supply of
-48V and the working location RTN or between the working power supply of -48V and the
PGND.

Step 3 On the PDF, set the status of the corresponding output switch to be ON. On the power distribution
box of the RNC cabinet, set the status of the corresponding output switch to be OFF.
At this time, the power distribution box turns to the self-test mode. The RUN and ALM LEDs
are on at the same time and the buzzer buzzes. After the self-test is complete, the power
distribution box requests the SCUa board for registry until the registry succeeds. During the
request process, the RUN LED on the power distribution box blinks at 2 Hz. When the request
for registry succeeds, the RUN LED blinks at 0.5 Hz. For the description about the LED status
on the power distribution box, refer to LEDs on the Front Panel of the RNC Power
Distribution Box.

Step 4 Set the multimeter to the state of voltage measurement. Use the multimeter to measure the output
voltage of the PDF or the input voltage of the power distribution box within the cabinet. Ensure
that the voltage ranges from -57 V to -40 V before you proceed the next test item.

Step 5 Take a subrack as a unit and set the corresponding switch of the power distribution box within
the RNC cabinet to ON.

Step 6 Set the multimeter to the state of voltage measurement. Use the multimeter to measure the voltage
range. Check whether the output power range of the subrack is within the allowed voltage range,
that is, from -57 V to -40 V. At the same time, check whether the fan box within the subrack
and the power supply of the boards within the subrack can work properly.
l After the subrack is powered on, the green STATUS LED on the panel of the fan box blinks.
In case of abnormality, turn off the corresponding switch of the power distribution box
immediately, turn off the switch of the PDF, and check whether the output voltage of the
power distribution box is abnormal and whether the power cables are wrongly installed. For
the description about the LED status of the fan box, refer to LED on the Fan Box.
l After the subrack is powered on, the RUN LED on the panel of the board is on steady or
blinks. If none of the LEDs for a board is on after the subrack is powered on, the slot or the
board itself might be faulty. Then, contact Huawei for technical support. For the description
about the LEDs on boards, refer to RNC LEDs.
l In case of abnormality, that is, when all of the LEDs for all boards within a subrack is off,
turn off the corresponding switch of the power distribution box immediately, and then turn
off the switch of the PDF. Check whether the output voltage of the power distribution box
is abnormal and whether the power cables are wrongly installed.

7-22 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
7 Installing Power Cables and PGND Cables for the N68E-22
N68E-22 Cabinet Installation Guide Cabinet

Step 7 Repeat Step 5 through Step 6 until the tests for the power-on status of the three subracks within
one RNC cabinet are complete.
Step 8 Repeat Step 1 through Step 7 to measure the power supply for other RNC cabinets.

----End

Postrequisite
Record the test results in the checklist as shown in Data Sheets of RNC Hardware
Installation.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 7-23


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 8 Installing Accessories for the N68E-22 Cabinet

8 Installing Accessories for the N68E-22


Cabinet

About This Chapter

This describes how to install the PGND cables on the side door, front door, and back door of
the N68E-22 cabinet.

Prerequisite
l The cabinet is installed.
l Accessories of the cabinet are delivered to the site.

1. 8.2 Installing Side Doors of the N68E-22 Cabinet


A single N68E-22 cabinet has four side doors. When multiple N68E-22 cabinets are
combined in a row, install four side doors between the ends of the cabinet row and the walls.
When the N68E-22 cabinet is combined with other types of cabinets, you need to install
the side doors where the cabinets are combined.
2. 8.3 Installing Front and Back Doors of N68E-22 Cabinet
There are two types of cabinets: single-door cabinet and double-door cabinet. The
installation methods of the front/back door for either type of cabinets are the same. Here
shows an example of front/back door installation of a single-door cabinet.
3. 8.4 Installing PGND Cables for N68E-22 Cabinet Doors
Each door of the cabinet needs to be installed with a PGND cable.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 8-1


Copyright © Huawei Technologies Co., Ltd
8 Installing Accessories for the N68E-22 Cabinet N68E-22 Cabinet Installation Guide

8.1 N68E-22 Cabinet Accessories


The accessories include the front, back, and side doors, and their PGND cables.
Table 8-1 lists N68E-22 cabinet accessories to be installed.

Table 8-1 N68E-22 cabinet accessories to be installed


Name Installation Position Remarks

Side door Refer to 11.2 Exploded View of the Four side doors need to be
N68E-22 Cabinet. installed for the combined
cabinets. That is, two side doors
need to be installed on the
leftmost side and another two
side doors on the rightmost side
of the cabinet.

Front/back door The methods for installing the


single-door and the double-door
cabinets are identical.

PGND cables The PGND cables refer to those


connected to the between the front/back/side door
cabinet doors and the cabinet base.

8.2 Installing Side Doors of the N68E-22 Cabinet


A single N68E-22 cabinet has four side doors. When multiple N68E-22 cabinets are combined
in a row, install four side doors between the ends of the cabinet row and the walls. When the
N68E-22 cabinet is combined with other types of cabinets, you need to install the side doors
where the cabinets are combined.

Prerequisite
l The parts to be installed are all ready. The parts refer to the side doors to be installed and
the sunk screws M6 x 12.
l The tools required for the installation are all ready. The tool refers to the cross screwdriver
with a long handle.

Context
Figure 8-1 shows the installation of a side door for the N68E-22 cabinet.

8-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 8 Installing Accessories for the N68E-22 Cabinet

Figure 8-1 Installation of a side door for the N68E-22 cabinet

Procedure
Step 1 Remove the connecting plate from the top of the cabinet , as shown in ① of Figure 8-1.
Step 2 Link the PGND cable on the rack to the grounding bolt on the side door, as shown in ② of
Figure 8-1.
Step 3 Place the side door properly, align the eight M6 x 12 screws with the installation holes, and then
fasten the screws, as shown in ③ of Figure 8-1.

----End

Postrequisite
Record the installation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 8-3


Copyright © Huawei Technologies Co., Ltd
8 Installing Accessories for the N68E-22 Cabinet N68E-22 Cabinet Installation Guide

8.3 Installing Front and Back Doors of N68E-22 Cabinet


There are two types of cabinets: single-door cabinet and double-door cabinet. The installation
methods of the front/back door for either type of cabinets are the same. Here shows an example
of front/back door installation of a single-door cabinet.

Prerequisite
l To facilitate the operation, install the front door and the back door after installing the other
hardware.
l The front door and the back door to be installed are ready.

Context
Figure 8-2 shows the installation of a front/back door for the RNC cabinet.

Figure 8-2 Installation of a front/back door for the N68E-22 cabinet

Procedure
Step 1 Insert the pivot pin of the door into the hole in the lower lintel of the cabinet, as shown in ① of
Figure 8-2.
Step 2 Pull down the latch, align the latch with the pivot hole in the upper lintel of the cabinet, and then
release the latch so as to fix the door onto the cabinet, as shown in ② of Figure 8-2.

----End

8-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 8 Installing Accessories for the N68E-22 Cabinet

Postrequisite
Record the installation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

8.4 Installing PGND Cables for N68E-22 Cabinet Doors


Each door of the cabinet needs to be installed with a PGND cable.

Prerequisite
l The PGND cables to be installed are ready.
l The tools required for the installation are all ready. The tools refer to cross screwdriver and
wrench.

Context
Figure 8-3 shows the installation positions of the PGND cables on N68E-22 cabinet doors.

Figure 8-3 Connecting PGND cables to N68E-22 cabinet doors

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 8-5


Copyright © Huawei Technologies Co., Ltd
8 Installing Accessories for the N68E-22 Cabinet N68E-22 Cabinet Installation Guide

Procedure
Step 1 As shown in ① of Figure 8-3, install the PGND cable of the side door.
NOTE
For a row of combined cabinets, only the PGND cables of the side doors at the ends of the cabinet row
need to be installed.

Step 2 As shown in ② of Figure 8-3, install the PGND cable of the front/back door.

----End

8-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 9 Labeling RNC Cabinets

9 Labeling RNC Cabinets

The labels to be attached to the RNC cabinet are the row labels, column labels, and product
labels.

Context
Figure 9-1 shows the row labels.

Figure 9-1 Row labels

Figure 9-2 shows the column labels.

Figure 9-2 Column labels

The product label is an oblong one and identifies the RNC product. Figure 9-3 shows where the
product label shall be attached.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 9-1


Copyright © Huawei Technologies Co., Ltd
9 Labeling RNC Cabinets N68E-22 Cabinet Installation Guide

Figure 9-3 Position for attaching the product label

Procedure
Step 1 Attach row labels.
Attach row labels to the side doors on the two ends of each cabinet row.
When there is more than one row of cabinets, attach the label A to the side doors at the two ends
of the cabinet row which is closest to the door of the equipment room, the label B to the second
row, the label C to the third row, and so on.
Step 2 Attach column labels.
The column label is attached on the doorhead of the cabinet front. Attach the label 00 to the first
cabinet near the main aisle, 01 to the second one, 02 to the third one, and so on.
Step 3 Check that product labels are available on the front/back doors of the cabinet. Otherwise, obtain
the product labels from delivered accessories and attach them to the top left of each front/back
door of the cabinet. Refer to Figure 9-3.

----End

Postrequisite
Record the operation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

9-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 10 Labeling Power Cables and PGND Cables of the RNC

10 Labeling Power Cables and PGND


Cables of the RNC

After the power cables and PGND cables of the RNCs are installed, remove the temporary labels
from the cables and attach engineering labels to these cables.

Prerequisite
l All the power cables and PGND cables are installed.
l The materials are all ready. The materials refer to the ball pen and the label paper.

Procedure
Step 1 Remove the temporary labels from the power cables.
Step 2 For how to make the engineering labels for the power cables and the PGND cables, refer to
Labeling Power Cables.

----End

Postrequisite
Record the operation results in the checklist, as shown in Data Sheets of RNC Hardware
Installation.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 10-1


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 11 Appendix

11 Appendix

About This Chapter

This provides the exploded view of the N68E-22 cabinet and an installation checklist.

11.1 Checklist for RNC Cabinet Installation


This describes the items and specifications for checking the installation of the RNC cabinet.
11.2 Exploded View of the N68E-22 Cabinet
This shows the components of the N68E-22 cabinet and parts on the cabinet.
11.3 Layout of Power Switches on the RNC Cabinet
The power distribution box of the RNC cabinet provides 20 (10 x 2) power outputs. The 6 (3 x
2) power outputs of RNC the power distribution box provide power for specific internal
components in the RNC cabinet.
11.4 Connections of Power Cables and PGND Cables in the RNC Cabinet
The power cables and PGND cables in the RSR cabinet are connected the same way as those in
the RBR cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 11-1


Copyright © Huawei Technologies Co., Ltd
11 Appendix N68E-22 Cabinet Installation Guide

11.1 Checklist for RNC Cabinet Installation


This describes the items and specifications for checking the installation of the RNC cabinet.
Table 11-1 lists the items and specifications for checking the installation of the RNC cabinet.

Table 11-1 Checked items for RNC cabinet installation


No. Checked Item

1 The cabinets are arranged in accordance with the engineering design.

2 The supports are positioned and spaced in accordance with the drawing of the
installation holes. (This item applies to the cabinet installation on the ESD floor.)

3 All supports are fixed to the floor correctly. (This item applies to the cabinet
installation on the ESD floor.)

4 All components of the supports are installed correctly. (This item applies to the
cabinet installation on the ESD floor.)

5 All floor holders are installed at the same height. (This item applies to the cabinet
installation on the ESD floor supported by floor holders.)

6 Each cabinet is well insulated from the support or the floor.

7 All plastic boards are installed on the top and bottom of the cabinets.

8 All cabinet accessories are installed, including front door, back door, and side doors.

9 The row labels, column labels, and product labels are attached to the specified
positions.

10 The ESD wrist strap is connected to the ESD bonding point on the cabinet.

11 All connecting plates are installed for combining cabinets.

12 Insulation is performed for shockproof parts between multiple rows of cabinets.

13 All bolts are fixed with flat washers and spring washers in a correct order.

14 The cabinets are stable and orderly.

15 All the adjacent cabinets stand side by side in a straight line.

16 The vertical deviation of cabinet installation is less than 3 mm.

17 All cabinet side doors facing the aisle are aligned with the error less than 5 mm.

18 The surfaces of the cabinets are clean without any fingerprint or smudge. There is
no dust, excessive cable tie ends or other sundries either inside or outside each
cabinet.

19 All kinds of labels are correct, legible and intact.

20 The front and back doors of the cabinets are easy to open or close.

11-2 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 11 Appendix

No. Checked Item

21 The modules in one cabinet are aligned from the top down.

22 All the filler panels are installed.

23 All boards are installed in proper positions, and their DIP switches are properly set.

24 No parts on the cabinets are damaged or detached. No cables are damaged or


snapped.

25 No paint is detached. No distortion exists.

11.2 Exploded View of the N68E-22 Cabinet


This shows the components of the N68E-22 cabinet and parts on the cabinet.
Figure 11-1 shows the exploded view of the N68E-22 cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 11-3


Copyright © Huawei Technologies Co., Ltd
11 Appendix N68E-22 Cabinet Installation Guide

Figure 11-1 Exploded view of the N68E-22 cabinet

1 Rack 2 Side door 3 Front/back door

Figure 11-1 shows the parts alphabetically sequenced in Table 11-2.

11-4 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 11 Appendix

Table 11-2 Parts on the cabinet


No. Description No. Description

a b

1 Product label 1 Huawei logo

c d

1 Connecting plate for combining


RNC cabinets (1) Central column

e f

1 Plastic cover plate (for the power 1 Grounding position of the cabinet
cable hole)
2 Power cable hole

g h

1 Wire bushing
1 Latch

i j

1 Grounding screw 1 Adjusting anchor bolt

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 11-5


Copyright © Huawei Technologies Co., Ltd
11 Appendix N68E-22 Cabinet Installation Guide

No. Description No. Description

k l

1 Pin hole

1 Pivot pin on the lower part of the


front door

11.3 Layout of Power Switches on the RNC Cabinet


The power distribution box of the RNC cabinet provides 20 (10 x 2) power outputs. The 6 (3 x
2) power outputs of RNC the power distribution box provide power for specific internal
components in the RNC cabinet.
The power distribution box of the RNC cabinet provides 6 (3 x 2) power outputs for the subracks.
The power supply is divided into two groups: A and B. The switches are A8 to A10 and B8 to
B10. Figure 11-2 and Figure 11-3 show the assignment of power switches on the power
distribution box. Table 11-3 describes the relation between the switches and subracks.

Figure 11-2 Assignment of power switches on the RSR power distribution box

11-6 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 11 Appendix

Figure 11-3 Layout of power switches on the RBR power distribution box

Table 11-3 Relation between the switches and subracks


RNC Subracks Power Switches

Subrack 2, subrack 5 A8, B8

Subrack 1, subrack 4 A9, B9

Subrack 0, subrack 3 A10, B10

11.4 Connections of Power Cables and PGND Cables in the


RNC Cabinet
The power cables and PGND cables in the RSR cabinet are connected the same way as those in
the RBR cabinet.
Figure 11-4 shows the connections of the power cables and the PGND cables in the N68-21-N
cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 11-7


Copyright © Huawei Technologies Co., Ltd
11 Appendix N68E-22 Cabinet Installation Guide

Figure 11-4 Connections of power cables and PGND cables in the N68-21-N cabinet

Table 11-4 describes connections of the power cables and PGND cables in the RNC cabinet.

Table 11-4 Connections of power cables and PGND cables in the RNC cabinet (N68-21-N)
Number Description

5, 6; 11, 12 Power cables of the lowest subrack

3, 4; 9, 10 Power cables of the middle subrack

1, 2; 7, 8 Power cables of the highest subrack

11-8 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 11 Appendix

Number Description

13 PGND cable connecting the power distribution box and


the busbar

14, 15, 16; 17, 18, 19 PGND cables connecting subracks to busbars

20, 21 PGND cables of the cabinet busbar

24, 25, 26 PGND cables connecting the adjacent cabinets

50 to 57 PGND cables of cabinet doors

Figure 11-5 shows the connections of the power cables and the PGND cables in the N68E-22
cabinet.

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 11-9


Copyright © Huawei Technologies Co., Ltd
11 Appendix N68E-22 Cabinet Installation Guide

Figure 11-5 Connections of power cables and PGND cables in the N68E-22 cabinet

Table 11-5 describes connections of the power cables and PGND cables in the RNC cabinet.

Table 11-5 Connections of power cables and PGND cables in the RNC cabinet (N68E-22)
Number Description

5, 6; 11, 12 Power cable of the lowest subrack

3, 4; 9, 10 Power cable of the middle subrack

1, 2; 7, 8 Power cable of the highest subrack

11-10 Huawei Proprietary and Confidential Issue 01 (2008-03-20)


Copyright © Huawei Technologies Co., Ltd
N68E-22 Cabinet Installation Guide 11 Appendix

Number Description

13 PGND cable connecting the power distribution box and


the mounting bar

14, 15, 16; 17, 18, 19 PGND cables connecting the subracks and the mounting
bar

24, 25, 26 PGND cables connecting the adjacent cabinets

50 to 57 PGND cables of cabinet doors

Issue 01 (2008-03-20) Huawei Proprietary and Confidential 11-11


Copyright © Huawei Technologies Co., Ltd

You might also like