You are on page 1of 15

OTC 13073

Canyon Express Slugging and Liquids Handling

Bryan K. Wallace, Marathon Oil Company, Ravi Gudimetla and Geir Saether, Intec Engineering Inc.

Copyright 2001, Offshore Technology Conference

This paper was prepared for presentation at the 2001 Offshore Technology Conference held in Introduction
Houston, Texas, 30 April–3 May 2001.
TotalFinaElf, BP, Marathon Oil Company, Pioneer Natural
This paper was selected for presentation by the OTC Program Committee following review of Resources USA, Inc., and Mariner Energy Inc. intend to
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Offshore Technology Conference and are subject to jointly develop three deepwater fields in the Gulf of Mexico
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference or its officers. Electronic reproduction, region. The fields are the Marathon-operated Camden Hills in
distribution, or storage of any part of this paper for commercial purposes without the written
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print
Mississippi Canyon (MC) 348 block, TotalFinaElf-operated
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The Aconcagua in MC305 block, and BP-operated King’s Peak in
abstract must contain conspicuous acknowledgment of where and by whom the paper was
presented. DeSoto Canyon (DC) 133 , DC177, and MC217 blocks. The
production consists primarily of methane gas with varying
volumes of water and condensate. Methanol is to be injected at
Abstract
the wellhead for hydrate inhibition. Maximum production
The Canyon Express development is a three operator
rates from each field range from 100 to 225 MMSCFD with
(TotalFinaElf, BP, and Marathon Oil Company) subsea
approximately 200 to 450 BPD of condensate, 300 to 900
development consisting of the transport of gas-condensate
BPD of water, and 450 to 1400 BPD of methanol.
from deepwater (~7000 feet) subsea reservoirs to a host
The production from the wells will be transported via twin
platform via dual 47-mile 12-inch nominal OD flowlines. The
12-inch nominal O.D. flowlines from the Camden Hills field
three developments are Camden Hills (Marathon, Pioneer
at approximately 7200-foot water depth, to the Aconcagua
Natural Resources USA, Inc., and TotalFinaElf), Aconcagua
field at approximately 7050-foot water depth, then to King’s
(TotalFinaElf, Pioneer Natural Resources USA, Inc., and
Peak field at approximately 6600-foot water depth, and finally
Mariner Energy, Inc.) and King’s Peak (BP). The Canyon
to a host platform fixed structure located on the continental
Express development is unique in that it involves ultra-
shelf. The twin flowlines (East and West) form a piggable
deepwater reservoirs from three individual operators flowing
system via a loop connecting the two flowlines at the flowline
into a common subsea multi-phase gathering system in which
ends. The flowlines are separated by a pigging valve, which
the operating pressure is lowered over time as dictated by
will remain closed during the normal operation of the system.
reservoir decline. The flowline fluid is predominantly methane
Thus, the flowlines will operate independently of the other.
gas along with a liquid phase consisting of condensate,
Analysis of the flowline gas/liquid behavior under various
produced water, and methanol (injected for hydrate
operating scenarios is required to establish and verify
inhibition). To verify the operability of the system it was
operability. The flowline tie-ins of the individual wells are as
necessary to perform transient simulations of the flowline to
follows:
predict the behavior of the fluid in the flowline.
The primary objective behind the transient simulations was
East Flowline
to determine the impact of the liquids in the flowline on the
(2) Camden Hills (MC348-1, MC348-2)
topside facilities and evaluate system performance during both
(1) Aconcagua (MC305-3)
upset and normal conditions. The software used to perform
(1) King’s Peak (DC177-2)
these simulations was Scandpower’s OLGA-2000 version
1.01. Scenarios and time points where potential problems due
West Flowline
to liquids were identified as well as appropriate techniques to
(2) Aconcagua (MC305-1, MC305-2)
control the any associated liquid slugs. The results from this
(3) King’s Peak (MC217-3, MC217-2, DC133-2)
work will form the basis of the operational procedures to be
developed for the Canyon Express flowline system.
The layout is shown schematically in Figure 1.
2 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

The operation of the Canyon Express production system the lowest flowline production rate, at which the system can
will consist of a gradual reduction in topside pressure over operate without the creation of slugs whose size is greater than
time (Early Life Host Platform Arrival Pressure of 2000 psig the capacity of the topside facilities.
through to Late Life Arrival Pressure of 500 psig) to maximize
recovery from the wells. As the gas rate and reservoir pressure System Shutdown and Restart. This is indicative of
decline over time, liquid loading in the wells and flowlines situations where all wells on a flowline are shutdown for an
will increase. As the liquid loading in the flowlines increase, extended period and subsequently restarted. During the
various production problems due to liquid slugging may occur shutdown, liquids are expected to settle at low spots in the line
during both normal production and transient situations (system due to gravity. Upon restart of the wells, these liquids will be
restarts, flow increases, etc.) if liquids are not properly transported out of the flowline in the form of temporary higher
managed. Thus, the handling and management of temporary liquid flowrates. The analysis was centered on evaluating the
increased liquid flowrate and volume is a significant aspect in increased liquid volume and to determine if these slugs are in
determining the operability of the Canyon Express system. excess of the liquid handling capacity of the topside facilities.
The objective of this paper is to describe the dynamic
simulations, using OLGA 2000 version 1.01, performed to: Increase of Gas Flow. This is indicative of bringing a well
• Determine the approximate range and duration of on-line or increasing the flowrate from a well. For a constant
increased liquid flow expected over the field life for host platform arrival pressure, the higher the gas flow, the
different production scenarios, lower the steady-state liquid holdup in the flowline. As the gas
• Summarize the range of liquid volume computed flow from the wells is increased the flowline liquid content is
• Identify specific scenarios during the field life where reduced from the steady-state volume of the lower flow. As
liquid management problems arise. with the shutdown and restart case, during the period in which
the higher liquid content is being displaced there is a
Studied Scenarios temporary increase in liquid flow to the topsides. The more
With input from the various Canyon Express partners, specific rapid the gas flow increase, the higher the liquid rate to the
steady-state and non-steady-state scenarios were identified for topsides facilities. Therefore, an increase in gas flowrate must
dynamic modeling to predict slug volumes (if any) that could be limited to a rate that results in manageable liquid volumes.
be present with each specific scenario. The scenarios were
simulated for early (2000 psig arrival), mid (1000 psig arrival) Increase of Liquid Flow. An increase of associated liquids
and late (500 psig arrival) field life conditions to show the from one or more wells (e.g. increased water flowrate due to
effect of increased liquid loading due to decreased flowline breakthrough) will result in a higher steady-state liquid
pressure and water production. These pressures were used to flowrate to the topsides facilities. If the liquid flow is in
differentiate between the times in the field life are shown in excess of the topsides capacity then the high liquid cut wells
the Design Data and Assumptions section of this paper. In would need choked back as the slug tank is designed and
addition, all simulations were performed for the East flowline intended for transient liquid flow increases and not continual
only as this line is expected to have lower gas flowrates, high liquid flows.
higher water rates, and lower pressure which results in a
greater potential for liquids management problems. Pigging and Rapid Flowline Depressurization. Although
The scenarios where significant variations in liquid pigging and flowline depressurization were considered and
flowrate may occur are as follows: evaluated in the design and are important factors in
determining adequate topside facility capacity for liquids
Steady-State Operation (Low Flow). For normal operation management, neither topic is discussed in this paper.
where the gas flowrate is too low to maintain steady flow,
liquid and pressure builds up in the flowline until the flowline Design Data and Assumptions
pressure is high enough to push the liquid slug out of the
flowline and onto the platform topsides facilities. For this Flowline Fluid Composition. Canyon Express hydrocarbon
scenario, the liquid rate to the topsides would fluctuate due to fluid is predominantly methane (~99 mol%) with a liquid
the cyclical loading and unloading of flowline liquid content. condensate in the quantity of 2 Bbls/MMSCF at stock tank
As long as the HP Separator can adequately handle the liquid conditions. Additional liquids in the flowline include produced
fluctuations, the operation could tolerate "slight slugging" but water and methanol injected upstream of the choke at each
not require any slug tank capacity. If the periodic slugs were wellhead for hydrate inhibition.
in excess of topsides liquid handling capability then the slug
tank must be sized such that the predicted periodic slug Flowline Route Profiles and Properties. The East flowline
volume could be contained thus allowing for continued route profile, shown in Figure 2, was obtained directly from
operation at the design gas flowrate. Modeling this scenario flowline alignment sheets. The flowline and riser outside
also helped to evaluate the “operating envelope” of the diameter is 12.75-inches. The flowline wall thickness varied
production system. The “operating envelope” involves finding based on mechanical requirements and codes.
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 3

Reservoir Data. Each field operator in the Canyon Express an emergency dump (slug tank). The OLGA modeling of the
system has independently modeled their respective reservoirs. inlet separation did not permit application of a constraint on
For this work the specific reservoir data was compiled and the emergency dump liquid flowrate. Conformance to any
used as the basis for input to the transient simulations and for identified liquid flow constraints to the slug tank were
evaluation of the results. Due to confidentiality issues, the confirmed and adhered to via iteration of the simulations. The
reservoir data are not stated in this paper. The parameters used topside basis assumed for separator simulation is as follows:
for input and evaluation include: water production per zone • A normal liquid level was defined for the two-phase HP
over time, production rate over time, and corresponding Separator. A level of 1.25 feet above the normal level in
reservoir pressure over time. the HP separator results in liquid flow to the emergency
dump (slug tank). A 4" liquid level control valve on the
Flowline Fluid Rates. The basis for the transient simulations liquid outlet line was modeled and tuned to maintain the
cover conditions representing early life, mid life, and late life normal liquid level setpoint. The emergency dump closes
flowline operation as outlined in Table 1. This covers an initial when the HP separator liquid level reaches 0.05 feet below
host platform arrival pressure of 2000 psig, end of life arrival the defined normal level.
pressure of 500 psig, and includes an intermediate operation • A maximum outlet liquid flow constraint from the HP
with an arrival pressure of 1000 psig. The liquid flow from the Separator was used to simulate the liquid handling
individual wells assumed in the flowline during these periods limitation of downstream facilities for liquid from the East
are consistent with the liquid predicted in the reservoir models flowline. Any flow above this value would result in the
and steady-state flowline simulations : liquid level rising in the HP separator. This flowrate
• The liquid flow values used in the simulations were constraint differed for the three periods modeled as the
obtained from the steady-state simulations and the downstream facilities service both flowlines and the West
reservoir performance predictions provided from each line liquid flow varies over time. The total liquid flow
Canyon Express partner. constraint value used was consistent with the capacity of
• The host platform arrival pressures and predicted gas the downstream liquid handling facilities.
flowrates for each case were obtained from the steady-state • The flow of liquid from the HP Separator to the slug tank
simulations. via the emergency dump is limited by a fixed choke
(installed to limit gas blowby) in the line. Constraint to this
Host Platform Topside Facilities. Included in the OLGA flowrate on the emergency dump liquid within the model
dynamic simulation of the flowline was modeling of the HP was not possible as this is not an OLGA capability. This
Separator operation and its respective outlet liquid flows. value was manually adhered to by verification from the
Figure 3 shows the flow schematic diagram of the topside inlet simulation output and modifying as necessary.
facilities for one of the two flowlines. The process flow path
of the production is summarized as follows: System Modeling and Analysis Summary
• The multi-phase flow from the Canyon Express The transient simulations for the Canyon Express system were
flowlines is routed to its respective inlet HP Separator. performed using OLGA 2000 version 1.01. Data generated
• The gas phase from the HP separators is compressed from steady-state modeling was used as the initial input into
and dehydrated. the transient model and the OLGA model was then run to a
• During normal operation, the separated liquid steady-state condition. Flowline operation was manipulated to
production flows from the Canyon Express two-phase simulate both steady-state operation and the various non-
HP Separators to further liquid processing facilities. steady-state scenarios described above to determine the
This includes separation facilities for the water, ultimate effect of operational changes on flowline liquid
methanol, and condensate. loading and host platform topside facilities.
• Any liquid from the flowline that flows into the HP The following sections briefly summarize the simulation
Separator in excess of its normal processing capacity is procedure and results for each of the scenarios. Critical cases
routed to a 2400 barrel slug tank on the topsides. where significant slug volumes occur for a specific scenario
The dynamic modeling performed with OLGA 2000 are discussed in more detail within the respective section.
included simulation of the HP Separator operation and its
respective liquid outlet flows. This provided a prediction of Steady-State Operation Procedure and Summary
the effect and response of the host platform inlet separator and
its resultant normal flow to the downstream liquid facilities Simulation Procedure. The objective of these simulations
and emergency flow to the slug tank. The topside modeling was as follows :
portion of the flowline simulation, illustrated in Figure 3, • Determine if flow instabilities due to slugging occur
included the HP inlet separator only. To adequately represent during the normal steady-state operation of the
the normal liquid flow from the separator the normal outlet flowlines for various flowrates across the range of
flow was constrained to the capacity of the downstream potential operating conditions.
equipment. Any flow in excess of this constraint was routed to
4 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

If slugging were present at design production rates, then • The transition point between higher flowrates and lower
flowline diameter, gas rates, and operating pressure would flowrates (as illustrated by the inflection) can be seen
need to be modified. The simulation procedure was to run at on the early life curve at 150 MMSCFD. This is where
various flowrates for a specific arrival pressure. Each the flowline pressure drop moves from gas flow
simulation continued until a steady-state condition was dominant to liquid content dominant.
reached. A steady-state condition was defined as when the Figures 4 and 5 illustrate that lower gas flowrates do not
liquid content in the flowline remained constant or when necessarily result in lower flowline pressure drop as the
steady cyclic fluctuations were observed in the liquid content resultant increase in liquid content at lower gas rates
and exit liquid rates as shown in Figure 6. The former is significantly increases the pressure at the end of the flowline.
indicative of higher flowrate conditions where liquids are As ascertained from these graphs, flow instability (e.g.
swept out of the line at constant rates due to the higher gas sudden liquid increase at the platform over time), is likely to
sweeping velocity. The latter is indicative of increased liquids occur at low flowrates which might occur anytime during field
production due to an increase in water production combined life. Thus analysis was performed to determine the liquid
with lower gas sweeping velocities. slugging potential and system operability for a range of gas
Summary of Steady-State Operation Results. flowrates. A summary of this analysis per time is as follows:
The initial analysis concerning transient modeling was to − Early Life. The liquid flowrate was constant at the higher
determine the flowline liquid content and flowrate for various gas flowrates. Slight liquid fluctuations were observed at a
gas flowrates and pressures in the range of flowline operation. low gas flowrate of 20 MMSCFD but no liquid volume in
Liquid management problems are generally observed at lower excess of HP Separator capability was predicted.
gas velocities and higher liquid content resulting in higher − Mid Life. The liquid flowrate was constant at the higher
pressures at the wellheads and fluctuations in liquid rates at gas flowrates. Slight liquid fluctuations were also observed
the topsides. Figures 4 and 5 illustrate the resulting liquid at low gas flowrate of 20 MMSCFD but no liquid volume
loading and wellhead pressure at different flowline outlet in excess of HP Separator capability was predicted.
pressures and produced water content. − Late Life. The liquid flowrate was constant at the higher
Figure 4 shows the predicted liquid content in the flowline gas flowrates. Slight liquid fluctuations were observed at
for various gas flowrates in the Canyon Express operating the low gas flowrates of 20 MMSCFD and 40 MMSCFD
envelope. The graph illustrates the following: but no liquid volume in excess of HP Separator capability
• Liquid content increases as the flow rates for each case was predicted.
decrease as shown in the top graph.
• Higher liquid contents are observed for the higher For the low gas flowrates, liquid fluctuation occurs when
pressure cases compared to the lower pressure cases at the large total liquid content in the flowline begins to block
similar rates as there is less velocity in the flowline. flow at the flowline low spots. When the appropriate pressure
(e.g. 100 MMSCFD at 2000 psig arrival shows a 7000 build up behind the liquid occurs, these liquid slugs are pushed
barrel liquid content versus 5000 barrels for the 100 further down the flowline eventually reaching the topside
MMSCFD at 1000 psig case). separator. This process is cyclic as the liquid buildup volume
• Operation at 20 MMSCFD for all three cases shows a in the flowline fluctuates when the liquid slugs exit the
liquid content of approximately 20,000 barrels. flowline. This operation would continue as long as sufficient
Figure 5 shows the predicted wellhead pressure (end of reservoir pressure exists to move the slugs of liquid.
the flowline) for various gas flowrates in the Canyon Express Liquid slugging during steady-state operation was seen to
operating envelope. In general, a change in gas flow rate occur for the late life, low flowrate case from the OLGA
affects the pressure at the end of the flowline. For dry gas, a simulator results. Most notable, as shown in Figures 6 and 7,
decrease in gas flowrate should result in a decrease in pressure for the late life, low flowrate case, are fluctuations in total
drop across the flowline. The graph illustrates the following: liquid flowrate, total flowline liquid content, and HP separator
• For the Canyon Express multiphase flow a decrease in liquid level.
gas flowrate results in an increase in liquid content. Figure 6 shows liquid flowrate at the flowline outlet pipe
This additional liquid effectively reduces the cross- section prior to the separator and also the total flowline liquid
sectional area of the flowline and creates pockets of content. The graph illustrates the following:
liquid and hydrostatic head that the gas must overcome. • The fluctuations observed for liquid flowrate indicate
• At higher gas flowrates the pressure drop across the that some degree of slugging is present. If no slugging
flowline decreases as gas flow through the flowline is were present, the plotted line would be level upon
reduced. This is due to the relatively insignificant reaching steady-state conditions.
change in flowline liquid content at these flowrates. • Although the liquid flowrate varies between 0 and 3500
• At lower gas flowrates the pressure drop across the BPD, the flowline liquid content only between 14,900
flowline actually increases as gas flow through the and 15,000 bbls. The liquid content differential of 100
flowline decreases. This is due to a significant increase bbls between the high and low values indicate that the
in flowline liquid content at the lower gas flowrates. slugging conditions are very slight.
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 5

flowrate, flowline content, HP separator level fluctuation, and


The operability at the low flowrate is evident in Figure 7 slug tank accumulated liquid volume were reviewed. These
which shows the liquid level in the separator for this case. The graphs are shown in Figures 8 thru 10 for the late life case.
graph illustrates the following: Figure 8 shows the liquid volume flow at the last pipe
• Although fluctuations in liquid are present, the inlet section upstream of the separator and the total liquid content
separator can adequately handle the liquid flow to the in the flowline. The graph illustrates the following:
topsides at the normal liquid level setpoint with only • The wells flow into the flowline is shutdown at hour 24.
slight oscillations in the separator level • The wells remain closed for 24 hours to allow the liquid
holdup in the line to settle.
Shut-In / Start-Up Simulation Procedure and Summary. • After the wells are restarted at hour 48, the liquid
content in the flowline rises to almost 8000 bbls as
Simulation Procedure. For early, mid, and late life cases, a additional liquid from the restarted wells is introduced
simulation of steady-state operation, followed by a total line into the flowline. This increase occurs as the gas flows
shut-in and subsequent full restart was performed to determine are low and the liquid in the line present before the
instantaneous slug volumes during startup scenarios. The shutdown is yet to be displaced.
objectives of these analyses were as follows: • After liquid flow to the host facility recommences at
• Determine increased liquid volume using a ramp-up hour 60, the instantaneous flow to the inlet separator
rate (time period in which gas rate goes from zero to increases to a maximum of nearly 5500 BPD which is
operating rate with a linear increase in flow rate) per above the capacity of the liquid flow from the inlet
well typical to a field start-up. separator to the downstream liquid processing facilities.
• Verify that the predicted slug volume is within the Figure 9 shows the separator level and portrays the relative
liquid handling capabilities of the host platform topside level between the oil phase and water/methanol phase for the
facilities. The host platform topsides capability was liquid in the separator. The graph illustrates the following:
assumed to be adequate if the accumulated slug volume • The relative volume of water/methanol decreases as the
was less than the slug tank capacity. liquid first arrives at the platform following the startup.
• Determine pressure requirements at the wells at restart This higher flow of oil in the initial return of the flow is
considering liquid holdup for each time point. due to the separation of the oil and water phases in the
The simulation procedure for each case was as follows : liquid holdup of the flowline during the shut-in period.
• Run simulation with the four wells until a steady-state • The high volume of water/methanol in the flowline
condition is reached. liquid content results in a high flow of water/methanol
• Shut-in all four wells for 24 hours to allow liquid approximately 6 hours after the re-establishment of
content in the flowline to settle to the lowest points. liquid flow. The water/methanol and oil in the separator
• Start-up the wells one at a time starting with the furthest varies until steady-state operation is re-established.
well and working forward up the flowline. Each well is • The level in the separator cannot be maintained at the
ramped to full rate over a six hour period. The start-up normal liquid level and eventually reaches the high-
of a next well is three hours after the previous start-up. high level which activates flow into the emergency
Summary of Shut-Down and Startup Results dump (flow to the slug tank).
− Early Life. Liquid flowrate to the host platform eventually Figure 10 shows the accumulated volume of liquids that
increases above normal liquid rates due to the displacement flowed to the slug tank over the transient period. As the
of the liquid volume which gravity flowed to the end of the simulation predicted liquid flow through the emergency dump,
flowline during the shut-in period. The transient higher it was vital to determine whether the topside slug tank was of
liquid flow did not result in a problem for the separator. adequate size to receive the liquid slug volume predicted for
− Mid Life. Similar to early life results. The increased liquid this case. The graph illustrates the following:
flow slightly increased the HP separator level above • The 450 bbl accumulation predicted is well below the
normal but never reached the high-high level. capacity of the 2400 bbl slug tank. In addition, a longer
− Late Life. Liquid flowrate to the host platform increases start-up period may greatly reduce the 450 bbl value.
significantly during the transient period after restart. This • The great majority of the liquid volume flowing into the
is due to the displacement of the liquid which settles in the slug tank is the water / methanol phase. This is due to
flowline during the shut-in period. The increased liquid the separation of the oil phase from the water /
flow (for this staggered start-up scenario simulated) was in methanol phase for the liquids which were resident in
excess of the HP separator capability and thus required the the flowline during the shutdown period. The initial
use of the slug tank (450 barrels accumulated). This liquids into the separator after restart are predominantly
volume is within the capacity of the slug tank. oil phase and arrive at a manageable flowrate as the gas
Whether or not a slugging problem exists for the cases rate is still low. The subsequent liquid is predominantly
described above was determined from examining several water / methanol and flowing at a higher rate due to the
outputs from the OLGA simulation. Most notably, the liquid higher gas rates as the wells reach full flow.
6 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

Flow Increase Simulation Procedure and Result Summary. instantaneous start-up of MC305-3 the increased liquid
flow was in excess of the HP separator liquids handling
Simulation Procedure. The objective of these cases was as and slug tank capacity. Ramp-up periods of 24, 48, and 96
follows : hours were also evaluated and found to be too short to
• Determine for early, mid and late field life, the effect on manage a predicted volume of liquid within the slug tank
the topside liquids handling of bringing a well on line capacity. A minimum ramp-up period of 120 hours was
(no flow to full flow) with the other wells on the required to adequately process the additional liquid volume
flowline already flowing. within the topside facilities capacity. A volume of 1960
The increase in gas rate also results in a subsequent barrels at the slug tank was predicted for this case.
increase in liquid rate as represented by the gas / liquid ratios Increasing the ramp-up time to 144 hours only slightly
listed in Table 1. This scenario required thorough study as it lowered the slug tank accumulated volume to 1770 bbls.
will be a standard operation with a significant potential for Although the gas flowrate increases from 40
liquid slugging. For each case, the well to be brought on-line MMSCFD to 75 MMSCFD the predicted wellhead
was MC305-3 as this is the highest flowrate well. Higher gas pressure at the MC348-1 well actually decreases from
flow will cause the higher liquid content to be displaced from 2200 psig to 1750 psig. This illustrates the effect that the
the line at a higher rate than the start-up of the other wells. 7500 bbls of additional liquid content at the lower
Using this well is a conservative case for this scenario. The flowrate has on the predicted pressure drop in the
effect of the higher gas flowrates on liquid content is flowline. The additional gas flowrate is beneficial as it
illustrated in Figure 4 which was previously described. The increases the gas velocity thus sweeping out liquids. This
simulation procedure for each point was as follows : ultimately has a positive effect on the pressure drop as
• Run simulation with three wells on-line (MC305-3 generically shown in Figure 5.
shutdown) until a steady-state condition is reached. As with the startup and shutdown , the key graphs to examine
• Start-up well MC305-3 at various ramp-up speeds for this scenario were the total liquid volume and content,
(instantaneous through up to seven days) to determine separator level fluctuation, and accumulated liquid in the slug
the ramp-up achievable for each case that does not tank. Figures 11 through 13 show these graphs for the mid life
overwhelm the liquid handling at the host platform. and Figure 14 is for a late life case.
Summary of Results Figure 11 shows the liquid volume flow for instantaneous,
- Early Life. The liquid rate to the host platform from the 12, 48 and 60 hour ramp-up start-up of MC305-3 (mid life
flowline is increased for a short period as the higher gas conditions). The graph illustrates the following:
velocity displaces the additional liquid content (600 • For the instantaneous ramp-up case, the instantaneous
barrels) associated with lower flow. The instantaneous flowrate to the inlet separator increases to a maximum
(immediate increase from no flow to full flow) ramp-up of nearly 13,000 BPD which is above both the capacity
case caused a small volume (<20 bbls) to flow to the slug of the topsides liquid processing facilities and the
tank. For a 12-hour ramp-up rate the liquid level in the overall liquid handling capacity of the separator. The
separator remained normal increased liquid flowrate is due to the sudden higher
− Mid Life. As with the early case, the liquid flowrate from gas velocity in the flowline from the gas flow increase.
the flowline to the host platform increases with the higher • For the other ramp-up cases (12, 48, and 60 hours) , the
gas flowrate while the liquid content decreases. The total liquid flow is spread out over a longer period of time
liquid differential to be displaced with the increase in gas which results in a lower maximum liquid flow.
volume and velocity is 3300 barrels. For an instantaneous • The steady-state condition returns approximately 24-72
start-up of MC305-3 the increased liquid flow was in hours (depending on the ramp-up speed) after the
excess of the HP separator and slug tank capability. To startup of MC305-3. This results in approximately
alleviate this problem, the well, (MC305-3) must be 1200 BPD of liquid (steady-state) from the flowline
ramped-up to full production over a longer period of time after MC305-3 is startup.
to limit the rate and volume of liquid received at the Figure 12 shows the inlet separator liquid level for the
topsides. A minimum ramp-up of 12 hours was required to instantaneous, 48 and 60 hour ramp-up cases (mid life). The
adequately contain the additional liquid volume. A volume graph illustrates the following:
of 2230 bbls at the slug tank was predicted for this case • The steady-state normal liquid level is maintained in the
which is at the slug tank volume limit. A ramp-up of 48 separator during steady-state operation but cannot be
hours resulted in 950 bbls to the slug tank which is within maintained during non-steady-state operation.
the slug tank capacity. • For all cases, the liquid level in the separator exceeds
− Late Life. As with the early case, the liquid flowrate to the normal level and reaches the high-high level upon
the host platform from the flowline increases with the receipt of liquid from the flowline at the topsides
higher flowrate while the liquid content decreases. The facilities. This activates the emergency dump valve
total liquid differential to be displaced with the increase in (flow to the slug tank). High-high levels show a lesser
gas volume and velocity is 7500 barrels. For an occurrence for the longer ramp-up periods.
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 7

Figure 13 shows the accumulated liquid into the slug tank excess liquids for this case with no flow to the slug tank.
over time for the instantaneous, 12, 48, and 60 hour ramp-up The pressure at MC348-1 increases with higher flowline
periods. The graph illustrates the following: liquid content.
• For the instantaneous cases, predicted accumulated − 50 BBL/MMSCF: This water rate increase resulted in a
volume is greater than the slug tank capacity. flow increase of 2100 BPD of liquid (water/methanol).
• For the 12 hour case, the total predicted accumulated Total liquid flow increased to 2540 BPD. The excess
volume is just below the capacity of the slug tank. liquid exceeded slug tank volume in 2.75 days following
• For the 48 and 60 hour cases, the total predicted arrival at host platform. The pressure at MC348-1
accumulated volume is well less than the capacity of increases with higher flowline liquid content.
the slug tank. − 100 BBL/MMSCF: This water rate increase resulted in a
For the late life case, longer ramp-up times are required flow increase of 4600 BPD of liquid (water/methanol).
due to the large liquid holdup present in the line. The specific Total liquid flow increased to 5040 BPD. The excess
ramp-up period identified where the accumulated volume did liquid exceeded the slug tank volume in 1 day following
not exceed the slug tank volume was 120 hours. Figure 14 arrival at host platform. The pressure at MC348-1
shows the accumulated liquid volumes in the slug tank for the increases significantly with higher flowline liquid content.
instantaneous, 48, 96, and 120 hour cases. The graph
illustrates the following: Figure 15 illustrates the results outlined above.
• For the instantaneous, 48, and 96 hour cases, predicted
accumulated volume is greater than slug tank capacity. Conclusions
• For the 120 hour case, the total predicted accumulated − No steady-state operation scenarios were identified in
volume is below the capacity of the slug tank. which liquid slug volumes were present in excess of the
HP Separator liquid handling capability. For the great
Liquid Flow Increase Simulation Procedure and Result majority of cases investigated there was no liquid slugging
Summary. predicted.
− Non-steady-state scenarios were identified which result in
Simulation Procedure. The objective of these cases was as increased liquid flow in excess of topside capacity.
follows : However, there are cases where slug volumes could be
• Determine if a significantly increased liquid rate results operationally mitigated via procedures in which the liquid
in slugging which overwhelms the topside liquid inlet flow rates were reduced by controlling the flowline
handling facilities. gas rate (e.g. slower ramp-up of well).
These simulations were performed only for the late life flow − Operation with a reduced slug tank volume (<2400 bbls)
conditions as this is the worst case scenario for significant may be possible as liquid inlet rates can be operationally
impact on the topsides liquids handling. For the liquid controlled but not necessarily eliminated. There were
volume associated with the late life flow of 75 MMSCFD, the cases identified during the late life where the minimum
water production (and associated methanol dosing) of one well slug tank size predicted was approximately 1700 barrels.
was increased to simulate an instantaneous increase in liquid However, control of liquid rate by reducing gas rate will
rate in the flowline. This would be indicative of water require longer ramp up times during increases in flow to
breakthrough in a single well and illustrates the resultant reduce liquid inlet rate.
impact on the host platform liquid handling facilities. The
simulation procedure for this analysis was as follows. Acknowledgments
• Run simulation with all four wells operating at the late The authors would like to thank the management of Canyon
life flowrate until a steady-state condition is reached. Express field owners TotalFinaElf, BP, Marathon Oil
• Increase the water production ratio at MC348-1 to Company, Mariner Energy, Inc., and Pioneer Natural
simulate a sudden increase in liquid rate in the Resources USA, Inc., for permission to publish this paper. We
flowline. The ratios for MC348-1 were increased would like to thank Dick Shea of Scandpower and Norm
from 8 bbls / MMSCF to 25, 50, and 100 bbls / McMullen of B.P. for their valuable assistance and modeling
MMSCF respectively. The gas flowrate for MC348-1 suggestions with the OLGA 2000 simulator.
in the late life case is 20 MMSCFD. The methanol
flowrate ratio of 1.5 times the water rate is held
constant.

Summary of Results
− 25 BBL/MMSCF: This water rate increase resulted in an
increased flow of 850 BPD per day (water/methanol).
Total liquid flow increased to 1290 BPD. The liquid
handling facilities as modeled are capable of handling the
8 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

CANYON EXPRESS DEVELOPMENT


FLOWLINE SCHEMATIC
TRANSIENT STUDY BASIS

CAMDEN ACONCAGUA KINGS


HILLS PEAK

HOST
MARATHON TOTALFINAELF BP PLATFORM
GAS EXPORT

MC MC MC MC DC
305-1 305-2 217-3 217-2 133-2
WEST

EAST

DUAL 12"
MC MC MC DC
PIPELINES
348-1 348-2 305-3 177-2

4 miles 11 miles 32 miles

Figure 1- Schematic Model of Canyon Express Production System

CANYON EXPRESS DEVELOPMENT


EAST FLOWLINE ROUTE PROFILE
TRANSIENT STUDY BASIS

1000

HOST PLATFORM
0

-1000

-2000
Elevation (ft)

-3000

-4000

-5000

-6000

-7000
177-2
305-3
348-2
348-1

-8000
0 20 40 60 80 100 120 140 160 180 200 220 240 260
Distance (1000 ft)

Figure 2: East Flowline Route Profile used in OLGA Simulations


OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 9

Case Î Early Mid Late

Water Rate (bbls/mmscf) 0.7 2.5 8.0


Methanol Rate (bbls/bbl
1.5 1.5 1.5
water)
Condensate Rate (bbls/mmscf) 2.0 2.0 2.0
Host Arrival Pressure (psig) 2000 1000 500
Host Separator Pressure (psig) 1750 750 486

East Line Wells Flow (mmscfd)

MC348-1 50 31 20
MC348-2 50 50 10
MC305-3 60 55 35
DC177-2 50 14 10
Total 210 150 75

Table 1: Basis for Transient Simulations

CANYON EXPRESS DEVELOPMENT


TRANSIENT STUDY HP SEPARATOR BASIS

INLET
CANYON CHOKE
EXPRESS
MULTIPHASE INLET HP SEPARATOR
FLOW
HLL 3 ft - 93inft - 9 in
HLL LC
60"

NLL NLL
2 ft - 62inft - 6 in LC
EMERGENCY

NORMAL
FLOW
DUMP

FC

CONSTRAINT
2600 to 2800 BPD

TO
SLUG TANK
Figure 3- HP Separator Model Used in OLGA 2000
10 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

Liquid Content East Flowline


Early = 2000 psia, 0.7 H2O, Mid = 1000 psia, 2.5 H2O, Late = 500 psia, 8 H2O

25000

20000
Liquid content (bbls)

Early life
15000
Mid life
Late life

10000

5000

0
0 50 100 150 200 250
Gas Flowrate (mmscf/d)

Figure 4 - Flowline Liquid Content at Various Gas Flowrates

Subsea Inlet Pressure East Flow line


Early = 2000 psia, 0.7 H2O, Mid = 1000 psia, 2.5 H2O, Late = 500 psia, 8 H2O

4500

4000

3500
Pressure at Camden Hills (psia)

3000

2500 Early life


Mid life
2000
Late life

1500

1000

500

0
0 50 100 150 200 250
Gas Flow rate (m m scf/d)

Figure 5 - Pressure at End of Flowline at Various Gas Flowrates


OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 11

4000 15250

LIQUID CONTENT
3500 15000

3000 14750
Liquid Flowrate at Separator (BPD)

LIQUID FLOWRATE

Flowline Liquid Content (Bbls)


2500 14500

2000 14250

1500 14000

1000 13750

500 13500

0 13250
0 12 24 36 48 60 72 84 96 108 120 132 144
Time (Hrs)
Figure 6 - Late Life
Steady-State Operation at 40 MMSCFD
Liquid Flowrate at Separator and Flowline Liquid Content

4.00
High-High Liquid
Level
3.75

3.50
Separator Liquid Level (ft)

3.25

3.00

2.75

Actual Liquid Level


2.50

2.25

2.00
0 12 24 36 48 60 72 84 96 108 120 132 144
Time (Hrs)

Figure 7 - Late Life


Steady-State Operation at 40 MMSCFD
Host Platform HP Separator Liquid Level
12 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

6000 8500

5500 8250

5000 8000

4500 7750
Liquid Flowrate at Separator (BPD)

LIQUID CONTENT

Flowline Liquid Content (Bbls)


4000 7500

3500 7250
SHUTDOWN

RESTART
3000 7000

2500 6750

2000 6500
LIQUID FLOWRATE
1500 6250

1000 6000

500 5750

0 5500
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)

Figure 8: Late Life


Full Flow / Shutdown / Re-Start (75-0-75 MMSCFD):
Liquid Flowrate at Separator and Total Liquid Content

4.00
High-High Liquid
Level
3.75

3.50
Separator Liquid Level (Ft)

3.25
SHUTDOWN

RESTART

3.00

2.75
Actual Liquid Level
2.50

2.25

2.00
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)

Figure 9: Late Life


Full Flow / Shutdown / Re-Start (75-0-75 MMSCFD):
Host Platform HP Separator Liquid Level
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 13

2800

SLUG TANK CAPACITY


2400
Accumulated Volume per Phase (Bbls)

2000
SHUTDOWN

1600

RESTART
1200

800

400
WATER / METHANOL

OIL
0
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)

Figure 10 - Late Life


Full Flow / Shutdown / Re-Start (75-0-75 MMSCFD)
Liquid Accumulation at Slug Tank

14000

12000
INSTANTANEOUS RAMP-UP
Liquid Flowrate at Separator (BPD)

10000
RESTART WELL

8000
12 HOUR RAMP-UP

6000

48 HOUR RAMP-UP
4000

60 HOUR RAMP-UP

2000

0
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)

Figure 11 - Mid Life


Gas Flow Increase (95 MMSCFD to 150 MMSCFD)
Flow Rate at HP Separator for Various Ramp-up Times
14 B. WALLACE, R. GUDIMETLA, G. SAETHER OTC 13073

4.00

High-High Liquid Level

3.75

3.50 INSTANTANEOUS
RAMP-UP
Separator Liquid Level (Ft)

3.25
RESTART WELL

60 HOUR RAMP-UP

3.00

48 HOUR RAMP-UP
2.75

Normal Liquid Level

2.50

2.25

2.00
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)

Figure 12 - Mid Life


Gas Flow Increase (95 MMSCFD to 150 MMSCFD)
Host Platform HP Separator Liquid Level

3000

SLUG TANK
0 HOUR RAMPUP
CAPACITY
2400
Accumulated Liquid Volume (Bbls)

12 HOUR RAMPUP
RESTART WELL

1800

1200

48 HR RAMPUP

600
60 HR RAMPUP

0
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)

Figure 13 - Mid Life


Gas Flow Increase (95 MMSCFD to 150 MMSCFD)
Liquid Accumulation at Slug Tank at Various Ramp-up Times
OTC 13073 CANYON EXPRESS SLUGGING AND LIQUIDS HANDLING 15

7200
0 HR RAMPUP

6400

5600
Accumulated Liquid Volume (Bbls)

4800
RESTART WELL

48 HR RAMPUP
4000

3200
SLUG TANK
96 HR RAMPUP
CAPACITY
2400

1600

800 120 HR RAMPUP

0
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
Time (Hrs)
Figure 14 - Late Life
Gas Flow Increase (95 MMSCFD to 150 MMSCFD)
Liquid Accumulation at Slug Tank for Various Ramp-up Times

7200
WATER RATIO LIQUID
6400
RATE
25 BBL / MMSCF 2,500 BPD
5600 50 BBL / MMSCF 4,000 BPD
Accumulated Liquid Volume (Bbls)

100 BBL / MMSCF


100 BBL / MMSCF 6,500 BPD
INCREASE LIQUID

4800

4000

3200
SLUG TANK CAPACITY 50 BBL / MMSCF

2400

1600

800
25 BBL / MMSCF

0
0 12 24 36 48 60 72 84 96 108 120
Time (Hrs)
Figure 15 - Late Life
Liquid Flow Increase
Liquid Accumulation at Slug Tank for Various Liquid Ratios

You might also like