Professional Documents
Culture Documents
Seattle, WA
Demolition Overview
Overview
This document describes the demolition plan for The McGuire apartment building and attached
parking structure including methods, durations, work hours, crew size, truck rate and mitigating
potential negative impacts to the neighborhood.
The McGuire will be demolished in fourteen to eighteen months over the following four phases.
Note that due to the dense urban location and lack of basement to contain debris, neither the
tower nor the parking structure will be demolished by use of explosives.
1. The parking structure will be demolished to the top of the first floor slab by Mass
Demolition. (See the next section for a description of each demolition method.)
2. Next, the tower will be demolished from the top down to approximately level six by
Floor-by-Floor Demolition.
3. The remaining floors of the tower will be demolished by Mass Demolition.
4. Finally, the below-grade foundations and substructures of the parking structure and tower
will be demolished with hydraulic excavators and the ~5’ deep excavated hole will be
filled in with gravel.
Noise: The hydraulic excavators generally work by “munching” instead of impact and thus
produce less noise and vibration than other demolition methods, such as hammering.
Page 1 of 6
The McGuire
Seattle, WA
Demolition Overview
Dust: Misting water at the point of concrete disturbance is the best way
to reduce dust. The hydraulic excavators will be fitted with a water
hose at the mouth of the “muncher” and hand-held water hoses will be
used at truck loading.
Page 2 of 6
The McGuire
Seattle, WA
Demolition Overview
through to the ground below. Mesh will also be installed on the outside of the scaffolding at the
working floor and two floors below to further minimize the potential for escaping debris and
dust.
Noise: Floor-by-Floor demolition will not exceed the allowable noise levels in the City’s Noise
Ordinance. The project will further reduce the noise disturbance to the neighborhood by:
1. Installing plywood on the deck and outside of the scaffold at the floor of work.
2. Installing mesh on the outside of the scaffold at the floor of work and two floors below.
3. Installing solid perimeter site fencing.
4. Moving debris from each floor to the ground level within chutes inside the building.
5. Lining the sides and base of the debris chutes with sound-absorptive materials.
6. Large elements such as the interior columns and perimeter moment frame will be
processed at the ground level inside the solid perimeter site fencing.
Page 3 of 6
The McGuire
Seattle, WA
Demolition Overview
7. Debris will be down-sized or rubblized with
the use of “muncher” attachments to limit the
use of noisy demolition hammers. Demolition
hammers use will be limited to oversized
materials or where down-sizing is impractical
by other means.
8. Planning circular truck routes to minimize the
use of back-up alarms.
9. During loading of trucks, care will be taken
not to drop rubble in the truck beds. Rather,
rubble will be lowered and spread into the
beds, front-to-back, minimizing surface-to- Mini-excavators will rubblize the upper floors of the
surface contact during loading. tower and push debris down interior chutes, containing
dust and noise during Floor-by-Floor demolition
Dust: Misting water at the point of concrete disturbance is the best way to reduce dust. Hand-
held water hoses will be used at all demolition points and truck loading. In addition, the beds of
the trucks will be wetted prior to loading to prevent dust transmission during travel and wheels
will be washed and streets swept as needed. The need is expected to be minimal as lay-down area
and truck loading will occur on the concrete slab of the former parking structure, which allows
for a clean site with minimal dust and mud. Similar to the noise discussion above, the plywood
and mesh on the scaffold, solid perimeter site fencing and interior debris chutes will minimize
dust.
Traffic: Extended traffic lane closures are not expected to be required for the demolition of the
McGuire. However, it is likely that parking will be closed in the alley and that sidewalks around
the building will be closed throughout demolition and the parking lanes and alley may be closed
periodically, if needed. Flag-persons will be employed to control traffic flow in and around the
jobsite.
Foundation Demolition will be by excavators with hydraulic breakers to break the foundations
into pieces and bucket attachments to dig up the foundations. Broken pieces will be loaded into
the trucks or crushed to gravel-size for backfill of the ~5’ deep excavated hole. This method of
foundation demolition appropriately addresses the following neighborhood concerns:
Safety: Foundation demolition by excavators with hydraulic breakers and buckets is the safest
and industry standard method for demolition foundations. The demolition will be limited to the
maximum extent possible without requiring perimeter shoring, thus mitigating the safety risk of
undermining the surround sidewalks and streets.
Page 4 of 6
The McGuire
Seattle, WA
Demolition Overview
Noise: Breaking up 5’ thick pieces of concrete is noisy. However, this phase of the demolition is
relatively short and the noise will be contained to the greatest extent possible by the solid
perimeter site fencing.
Dust: Misting at the point of demolition and truck loading will continue to be utilized throughout
foundation demolition. The solid perimeter site fencing and street sweeping as needed will
further contain the dust.
Traffic: No street or sidewalk closures are expected during this phase. Flag-persons will continue
to maintain safe and efficient traffic flow in around the jobsite.
General Comments
Working hours will be within the allowable working hours by the City of Seattle’s noise
ordinance. Regular work hours are presently planned for 7am to 5pm on weekdays, extending to
7pm on weekdays and Saturdays from 9am to 7pm when necessary, such as during critical
operations or to maintain schedule. Work hours and the noise plan will be coordinated with
DPD.
Crew size will vary from ten to forty individuals on site per day, depending on the phase of
demolition. Mass Demolition of the parking structure and lower tower levels and Foundation
Demolition will require ten to twenty individuals. Floor-by-Floor Demolition will require
twenty to forty individuals. Some parking for workers will be provided inside the construction
boundary after demolition of the parking structure. Additional parking for workers will be
provided using local pay lots and/or use of mass transit.
Truck Rate will vary from twenty to forty trucks per day, depending on the phase of demolition.
Mass Demolition of the parking structure and lower tower levels will produce higher daily loads.
Floor-by-Floor Demolition of the upper tower will produce lower daily loads. Truck rates will
not be constant and there will be many days where no truck trips occur, while debris is
accumulating or being prepared (downsized) for shipment. Truck rates, haul routes and the
overall traffic and pedestrian plan will be coordinated with SDOT.
Page 5 of 6
The McGuire
Seattle, WA
Demolition Overview
Closing
This demolition plan for The McGuire focuses on safety and mitigating impacts to the
environment and neighborhood, our top concerns.
Katie Henry
Project Manager
Lease Crutcher Lewis
(206) 622-0500
katie.henry@lewisbuilds.com
Page 6 of 6