Professional Documents
Culture Documents
( Reaffirmed 2004 )
Indian Standard
POWERTRANSFORMERS
PART 5 TRANSFORMER/REACTOR BUSHINGS - MINIMUM EXTERNAL
CLEARANCE IN AIR - SPECIFICATION
Q BIS 1994
FOREWORD
This Ir,dian Standard was adopted by the Bureau of Indian Standards, after the draft finalized by the
Transformers Sectional Committee had been approved by the Electrotechnical Division Council.
In the preparation of this standard considerable assistance has been derived from IEC Pub 76-3-l
( 1987 ) ‘Power Transformer : Part 3 lnsulation levels and dielectric tests External clearances in air’
issued by the International Electrotechninal Commission ( IEC ).
For the purpose of deciding whether a particular requirement of this standard is complied wilh, the final
value, observed or calculated, expressing the result of a test or analvsis shall be rounded off in accordance
with IS 2 : 1960 ‘Rules for rounding off numerical values ( revised )‘. The number of significant places
retained in the rounded off value shall be the same as that of the specified value in this standard.
IS 2026 ( Part 5 ) : 1994
Indian Standard
POWERTRANSFORMERS
PART 5 TRANSFORMER/REACTOR BUSHINGS-MINIMUM EXTERNAL
CLEARANCE IN AIR - SPECIFICATION
1
IS 2026 ( Part 5 ) : i994
on the transformer itself. Recommended test the standard voltages which appear in Table 2
procedures for such cases are given. of IS 2026 ( Part 3 ) : 1981.
3.8 If the transformer is specified for operation If a type test on a reduced clearance is to be
at an altitude higher than 1000 m, the clearance conducted this shall be lightning impulse test,
requirements have to be increased by 1 percent dry with positive impulse, three shots, with the
for every 100 m by which the altitude exceeds test voltage according to Table 1.
1 000 m. Requirements are given for the follow-
ing clearances: 4.2 Windings with CT, 3 300 kV - Transformer
- clearance phase-to-earth and phase-to- Specified According to Method 1
neutral;
For equipment with U, in this range, IS 2165
- clearance *phase-to-phase between phases ( Part 2 ) : 1977 specifies different requirements
of the same winding; and for phase-to-earth and phase-to-phase insulation.
- Air insulation clearances are referred to
clearance between a line terminal of the switching impulse conditions. Transformers
high voltage winding and a line terminal which are specified according to Method 1 in
of a lower voltage winding. IS 2026 (Part 3 ) : 1981 have, however, no
3.9 It follows from the above that the rated switching impulse withstand level.
‘recommended’ values are in effect <minimum’ The recommended minimum distances in
values. The design clearances shall be stated on Table 2 have been chosen, directly on the basis
the outline drawing. These are nominal values of U, values, from the selection of standard
subject to normal manufacturing tolerances and clearances appearing in Table 3. This is because
they have to be selected so that the actual it is assumed that the requirements for external
clearances will be at least equal to the specified insulation should be the same, irrespective of
values. These statements shall be taken as proof the use of Method 1 or Method 2 as described
that the transformer complies with the in IS 2026 ( Part 3 ) : 1981 for the tests on the
recommendations of the standard, or with the internal insulation.
modified values which may have been agreed for
the particular contract. The phase-to-earth clearances in Table 2 also
apply for clearances towards the terminals of a
4 BUSHING CLEARANCE REQUIREMENTS lower voltage winding. ( An unusual voltage
AS DETERMINED BY TRANSFORMER ratio or connection may, however, require
INSULATION WITHSTAND VOLTAGES special consideration of the clearances. )
4.0 The requirements are formulated as descri-
bed below, depending on the U, voltage value 4.2.1 Type Test Procedure
of the winding, and on the method of specifying If a type test on a reduced clearance is to be
the transformer insulation. conducted this shall be carried out as described
Indian Standards IS 2165 ( Part 1 ) : 1977 deals in 4.3.3. The test voltage is selected as follows:
with phase-to-earth insulation co-ordination - determine the standard clearance value;
and IS 2165 ( Part 2) : 1983 deals with phase-to-
phase insulation co-ordination, principles and - by reference to the appropriate curve of
rules. The above two Indian Standards make Fig. 1 or Fig. 2, establish the switchmg
use of different reference withstand voltage for impulse voltage correspondjng to this
different ranges of Urn voltages. In the ranges standard clearance. This is the test
,4 and B ( U, ( 300 kV ) the reference voltages voltage to be used.
are power frequency voltage and lightining
impulse voltage. In range C ( U, > 300 kV ) 4.3 Windings with [lnr > 300 kV - Transformer
the reference voltage for external CiearanCe iS Specified According to Method 2
a switching impulse voltage. For further details,
see 3. The conversion from rated with- Transformers specified according to Method 2
stand voltages to clearances in this standard is have a rated switching impulse withstand
generally along the lines of 1’S2165 ( Part 1 ) : voltage assigned to the highest voltage winding.
197; and IS 2165 ( Part 2 ) : 1983. This value, which applies bttween phase and
earth, is also used as a reference for the external
. . .
4.1 Wmdlags with U, < 300 kV insulation. The internal insulation is verified b\
a test with negative test voltage on the tested
The same distance shall apply for clearances phase, and with I.5 times test voltage between
phase-to-earth, phase-to-neutral, phase-to- the phases on three-phase transformers.
phase, and towards terminals of a lower Voltage
winding. The recommended minimum clea- For thk external insulation the phase-to-phahe
rances are given in Table 1 with reference to withstand voltage is defined differently according
2
IS 2026 ( Part 5 ) : 1994
Table 1 Recommeded Minimum Clearances from Bushing Live Parts on Power Transformers
Having Windings witb Highest Voltage for Equipment U, <’ 300 kV
( Altitude Up to 1 000 m )
( Clause 4.1 )
Highest Voltage Rated Short Rated Lighthing Impulse Withstand Minimum Clearance
for Equipment Duration Voltage r_--_---_- h_-- _-__ __~
Power Fre- ( peak ) With Reference Wit:oRgr$ernce
Crms ) quency With- r---- ----_h_--_--_.-_ to Distribution
stand Voltage Distribution Other Trans- Transformers Transformers
( rms ) Transformers formers
(1) (2) (3) (4) (5) (6)
kV kV kV kV mm mm
< 1’1 3 - - - -
3’6 10 20 40 - 60
7’2 20 40 60 60 90
12 28 60 75 90 125
650 1 250
275
750 1 450
325
245
850 1 600
360
Table 2 Recommended Minimum Clearances from Bushing Live Parts on Power Transformers
Having Windings with Highest Voltage for Equipment U, > 300 kV, Specified
According to Method 1 ( Altitude Up to 1 000 m )
( Clauses 4.1 and 4.2 )
Highest Voltage Rated Short Dura- Rated Lightn- Minimum Clearance
for EF;pment tion Power Fre- ing Impulse r------- h-_-----~
quency Withstand Withstand Phase-to- Phase-to-
( rms ) Voltage Voltage Earth Earth
( rms )
(1) (2) (p3) (4) (5)
kV kV . kV mm mm
9.50 1 900 2 250
3
IS 2025 ( Part 5 ) : 1994
Table 3 Recommended Minimum Clearances from Bushing Live Parts on Power Transformers
Having Windings with Highest Voltage for Equipment iJ, > 300 kV, Specified
According to Method 2 ( Altitude Up to 1 000 m )
( Clauses 4.3, 4.3.1.3.~ and-4.3.2 )
Highest Voltage Rated Switching Rated Lightning LMinimum Clearance
for Eq;i;ment Impulse Withstand Impulse With- ~---_-----_----h ---------7
Voltage stand Voltage Phase-to-Earth, Phase-to-Phase, To Other
(rms) ( peak ) ( peak 1 Based on Swit- Based on Swit- Winding,
thing Impulse thing Impulse Based on
Withstand Withstand Lightning
Vojtage Voltage Impulse
Withstand
Voltage
(1) (2) (3) (4) (5) (6)
kV kV kV mm mm mm
650 1600
750
300
1 900 2 250
950 1 750
650
362 2 300 2 650
1050 1 950
950
420
2 700 3 100
1175 2200
1300 2400
1050
3 100 3 5co
525 1425 2 650
1175
3 700 4 200
1550 2 850
5 000 5 800
765
1800 3 300
5 800 6700
1950 3 600
Dm
1
I i i i i i i i kV
Om
FIG. 2 CLEARANCE
PHASE-TO-PHASEBASEDON SWITCHING IMPULSEVOLTAGE APPEARING
BETWEENPHASE
to IS 2165 ( Part 2 ) : 1983 ( see Table 4 ). An between the two terminals under consideration
appropriate test procedure involves positive during the switching impulse test [ see 14 of
polarity impulses for a configuration phase-to- IS 2026 ( Part 3 ) : 1981 ] according to the turns
earth, and opposite polarity impulses for phase- ratio between the windings. This voltage.value
to-phase clearances ( see 4.3.3 ). This has been gives the clearance which is required with regard
considered for the clearance values given in to the switching impulse condition. Fig. 2 is
Table 3. used to find the recommended clearance if the
terminals receive opposite polarity voltages and
4.3.1 Clearance Phase-to-Earth, Phase-to-Neutral the ratio between their voltage amplitudes is 2
and Phase-to-Phase Between Phases of the Same or less. In other cases, Fig. 1 applies.
Winding
NOTE;If Fig. 1and Fig. 2 are compared, it appenrs
The clearance from the high voltage bushing that a phase-to-phase clearance withstands a higher
top to earth ( tank, conservator, cooling equip- voltage difference than the same.distance would do
in a phase-to-earth configuration. The reason is that
ment, switchyard structures ) or to the neutral in the phase-to-phase configuration the two terminals
terminal is determined from column 4 of are supposed to have opposite polarity, and the
Table 3. The clearance between bushing caps of maximum dielectric gradient at either of them ( which
difference phases is determined from column 5 is largely determined by the voltage to earth ) is
relatively lower.
of Table 3.
It is assumed also that the electrodes have a
4.3.2 Clearance Between Terminals of Different
rounded shape. The clearance however,
shall,
Windings also fulfil the lightning impulse withstand
The clearance between terminals of different requirement, which presupposes that the lower
windings of the transformer shall be checked voltage winding terminal is at earth potential
with regard to both switching, impulse and when rated lightning impulse withstand voltage is
lightning impulse conditions. The switching applied to the high voltage terminal. The dis-
impulse withstand requirement is based on the tance requirement in column 6 of Table 3 and
precalculated difference voltage which appears Fig. 3 corresponding to this rated lightning
5
----
impulse voltage, has therefore, to be fulfilled test voltage, positive, on one line terminal, the
between the two terminals. The higher of the other half, negative on another line terminal,
two clearance estimates shall apply. The and the third terminal earth [ see 10, 12 and 14
s\\,itching impulse test on the transformer will of IS 2165 ( Part 2 ) : 1983 ] The combinations
induce voltages between phases of other star- of phase-to-earth and phase-to-phase test volt-
connected windings as well. It shall be checked ages, according to IS 2165 ( Part 2 ) : 1983 are
wliether this condition requires a larger phase- reproduced in Table 4. The values for
to-phase clearance in such a winding than as U, = 525 kV and 800 kV are subject to
prescribed for this \vinding alone such as in 4.1. review.
4.3.3 Type Test Procedure
If a tape test on a reduce clearance is to be When the outer phases are placed symmetrically
conducted, the test procedure shall be as with respect to the middle phase, it is sufficient
foilows: to make two separate tests, one with positive
polarity on the middle phase, and the other
A test on a configuration phase-to-earth or with positive polarity on an outer phase, the
phase-to-netural, or towards a terminal of a middle phase having negative polarity. If the
lower voltage winding shall consist of a line terminal arrangement is asymmetrical, it
switching impulse test, dry, with positive may be necessary to perform more than two
polarity on the line terminal of the winding tests.
( the higher voltage winding ). The counter
electrode shall be earthed. If the tested
terminal belongs to a three-phase winding, Each test shall consist of 15 applications of
the other line terminals shall also be impulse voltage with wave shape 250/2 500 in
earthed. accordance with IS 2071 ( Part 1 ) : 1993.
NOTE - This test ih not generally feasible on
complete three-phase transformers and may, thcre- NOTE - The above test procedure for phase-to-
for-e, have to be conducted on ;I model simulating the phase external clearances, which follows IS 2165
actual configuration of the transformer. ( Part 2 ) : 1983 differs in several’ respects from the
Tests on the phase-to-phase clearances of a switching impulse test procedure specified for the
internal insulation of the transformer in 14 of
three-phase transformer shall consist of switch- IS 2165 ( Part 2 ) . 1983. The two test procedures do
ing impulse tests, dry, with half of the specified not replace each other.
6
IS 2026 ( Part 5 ) : 1994
1 300
1 300
1 425
I 425
1800
2 400
2 550
ANNEX A
( Clause 2 )
7
Burenti of Indian Standards
BIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promote
harmonious development of the activities of standardization, marking and quality certification of goods and
attending to connected matters in the country.
Copyright
BIS has the copyright of all its publications. No part of these publications may be reproduced in any form
without the prior permission in writing of BPS. This does not preclude the free use, in the course of
implementing the standard, of necessary details, such as symbols and sizes, type or grade designations.
Enquiries relating to copyright be addressed to the Director (Publication), BIS.
Amendments are issued to standards as the need arises on the basis of comments. Standards are also reviewed
periodically; a standard along with amendments is reaffirmed when such review indicates that no changes are
needed; if the review indicates that changes are needed, it is taken up for revision. Users of Indian Standards
should ascertain that they are in possession of the latest amendments or edition by referring to the latest issue
of ‘BIS Handbook’ and ‘Standards Monthly Additions’.
This Indian Standard has been developed from Dot: No. ETD 16 ( 3486 J