Professional Documents
Culture Documents
TN D-6720
LOAN COPY: RE
AFWL (DO
KIRTLAND AF
by Thomas E. Ohnesorge
..
Manned SpacecrufiCenter
Hozlston, Texas 77058
-\.-" . 1' .
.L.' ...
, < _,i,., .
0333390
". . - . . .. .
.
1.ReportNo. Government
2. Accession No. 3. Recipient's Catalog No.
..i
NASA TN 0-6720 -~
. ~ .
'
~~~
..
A Titla and Subtitle 5. Report Date
APOLLO FXPERIENCE RFFORT
ELFCTRONIC S Y S " S TEST PROGRAM
.~
ACCOMPLISHMENTS
- .- .... .. . ..
~
~
AND RESULTS
7. Author(s) 8. Performing Organization Report No.
" .
Agency
12. Sponsoring AddressName and
-.
Washington, D.C. 20546
15. %-pplementary Notes
- "
~- ~~~
I
1
14. SponsoringAgencyCode
The MSC Director waived the use of the International %Stem Of Units (a) for
this Apollo Experience Report, because, in his judgment, use of SI Units would impair the usefulness
of the report or result in excessive cost.
-- ." . - - ~i
16. Abstract
This document presents a chronological record of the Electronic Systems Test Program from its
conception in May 1963 to December 1969. The original concept of t h e program, which was pri-
marily a spacecraft/Manned Space Flight Network communications system compatibility and per-
formance evaluation, is described. The evolution of these concepts to include various levels of
test detail, as well as systems-level design verification testing, is discussed. Actual implemen-
tation of these concepts is presented, and the facility to support the program is described. Test
r e s u l t s are given, and significant contributions to the lunar landing mission are underlined. Plans
for modifying the facility and the concepts, based on Apollo experience, are proposed.
Apollo Telemetry
. Communications System Ranging
Systems Test
* ' Command
Command Module
* Television
Module
Lunar ' Voice
-- ."
.~~~~
. .,. ""
19. Security Classif. (of this report1 20. Security Classif. (of this page) -1 21. NO. of Pages I 22. Price*
None
- ."
I None
"
75 I $3.00
F o r sale by the National Technical Information Service, Springfield, Virginia 22151
" ~~
CONTENTS
Section Page
SUMMARY ..................................... 1
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
TEST ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Major Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
SpecialTests .................................. 25
SupportTests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
SIGNIFICANT RESULTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
Apollo Lutlar Surface Experiments Package Gross Test (A-7) Results .... 48
iii
Section Page
AntennaStaticTest(B-3)Results ....................... 49
PLANS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
CONCLUDING REMARKS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
APPENDIX A .
TEST PROGRAM OPERATIONS ................ 55
iv
‘TABLES
Table Page
I ELECTRONIC
SYSTEMS
TEST PROGRAM PARTICIPATION ....... 4
I1 BLOCK I-E
PROBLEM ......................
AREAS 12
FI GU RES
Figure Page
2 Generalized
systems
test
configuration . . . . . . . . . . . . . . . . . 7
3 Testactivity of theESTPfrom1964to1969 . . . . . . . . . . . . . . . 10
4 Two-extravehicular-astronaut/LM/MSFN communication
mode . . . . 22
5 Designverificationtest of theEVCS-LM-MSFNsystem ......... 33
6 Extravehicular
astronaut/LM/MSFN/MCC-H
voice
paths ........ 42
B-1 F o r m f o r requesting
ESTL test support . . . . . . . . . . . . . . . . . 59
.
ACRONYMS
AM amplitude modulation
AMQ analog-multiplexer-quantizer
BER b i t e r r o r rate
CM command module
CRO Carnarvon,Australia
vi
CSM command and service module
cv command verification
E1 Engineering Instruction
EKG electrocardiogram
FM frequency modulation
FMFB F M feedback
H . L. hardline
IU instrument unit
vii
LEM lunar ,excursion module
LM lunar module
MCC-H MCC-Houston
PM phase modulation
RC resistor-capacitor
SBER s u b b i t e r r o r rate
viii
SPA signal-processor assembly
TV television
VR verification receiver
WI word intelligibility
ix
APOLLO EXPERIENCE PEPORT
ELECTRON1C SYSTEMS TEST PROGRAM
ACCOMPLISHMENTS AND RESULTS
By Thomas E. Ohnesorge
Manned Spacecraft Center
SUMMARY
The Electronic Systems Test Program described in this document was established
to fulfill a need that developed as manned space-flight communications systems evolved
in complexity and required capability. The combining of all communications functions
into one unified communications system for the Apollo Program, instead of the multiple
communications systems that were used on Project Mercury and the Gemini Program,
necessitated the innovation of a combined systems testing concept. For the first time,
a concept of simultaneous spacecraft/spacecraft/ground conlmunications system testing
w a s established a s a fundamental portion of communications system development and
performance verification. The interaction and combination of all information on one
radio-frequency carrier required compatibility verification and performance evaluation
of the system prior to manned flight. The fact that each type of spacecraft w a s manu-
factured by a different contractor and that the ground communications systemw a s pro-
vided by several different sources intensified this need for combined systems testing.
The test program began with the first system scheduled to fly - that is, the
command and service module Block I (earth-orbital) system - and the Manned Space
Flight Network equipment required to support these missions. The program progressed
to testing of more advanced systems and complex combinations of t h e s e s y s t e m s to
finally arrive at the lunar landing communications system configuration. During this
progression, special testing of critical information channels and channels containing
updated hardware occurred. A few major compatibility problems were detected and
corrective action determined. Many minor problems were noted and solutions recom-
mended. Testing techniques and concepts were developed and evolved as the test pro-
gram progressed.
A s a result, in the spring of 1963, the NASA Manned Spacecraft Center (MSC)
initiated planning and implementation of a program that was subsequently designated
the ESTP. This program was given the specific objectives of verifying spacecraft,
MSFN, and MSC Mission Control Center (MCC) total systems compatibility and of
evaluating the overall performance of the ACS by using operational prototype and pro-
duction hardware. The task was made a joint responsibility of the MSC Ground Sys-
tems Project Office and the MSC Instrumentation and Electronic Systems Division
(later renamed "Space Electronic Systems Division"). In June 1964, an MSC r e o r -
ganization created the Information Systems Division, which was given total responsi-
bility for the ESTP, with support to be provided by other MSC divisions and other
NASA C e n t e r s as required. In August 1969, another MSC reorganization combined
ESTP personnel and spacecraft telecommunications personnel into the same division,
the Telemetry and Communications Systems Division (TCSD).
2
I
During the first 24 months of its existence, five significant events occurred
within the ESTP. First, construction of a facility to house the ESTP at MSC was ap-
proved by NASA Headquarters. This facility was officially designated the Electronic
Systems Compatibility Facility (ESCF). The laboratory area within this facility in
which the actual systems testing takes place was subsequently designated the Electronic
Systems Test Laboratory (ESTL). In the interim, a temporary facility located at MSC
was authorized and subsequently used until the summer of 1966. Second, support and
assistance agreements within MSC and with other NASA Centers were reached. These
agreements, as modified by experience and by changes in functional responsibility, are
summarizedintable I. Third, a decisionwasmadetoeliminatetesting of Gemini
Program communications because the time frame to manned launch was too close
foravailability of properequipment,becausethe rf systemsinvolvedwereessen-
tially the same as thoseforProjectMercury(eventhoughthetelemetryandcom-
mand systems using thesc? links weredifferent),andbecausethetimefordesign
finalization of Apollohardwarewasrapidlyapproaching.Coupledwiththisevent
was a decision to eliminate all plans for testing any vhf or hf s y s t e m s s i n c e t h e s e
s y s t e m s had not changed significantly in several years; however, this decision was
later modified for special instances. Fourth, a Jet Propulsion Laboratory (JPL) Deep
Space Network (a JPL-NASA network for unmanned satellites and probes) unified S-band
(USB) receiver-exciter-ranging (RER) system, modified for Apollo frequencies and
parameters, was made available to the ESTP in September 1964, along with command
and service module (CSM) Block I equipment, so that systems testing could begin in
November 1964. Early testing of t h e s e i t e m s w a s n e c e s s a r y so that any problems en-
countered could be resolved and the necessary modifications couldbe incorporated into
t h e s y s t e m p r i o r t o t h e first manned Apollo flight. (The J P L RER system was replaced
by a production-model MSFN RER system in early 1965. ) Fifth, in January 1965, on
the basis of cost and MCC operation schedules, the plans to incorporate the MCC in the
test loop were dropped at the request ofNASA management. Special tests involving the
MCC have been performed, however; and additional tests will be performed at the
specific request of the MSC Flight Operations Directorate (FOD).
While the initial purpose of the ESTP was, as stated earlier, to provide informa-
tion regarding spacecraft/ground telecommunications system compatibility and per-
formance based on tests with operational equipment, t h i s purpose has been broadened
somewhat to include design verification testing, mission anomaly investigations, pre-
launch problem resolution testing, and exploratory and development tests to improve
systems performance. These and other aspects of the test p r o g r a m are described in
the following sections.
3
TABLE I. - ELECTRONIC SYSTEMS TEST PROGRAM PARTICIPATION
Responsibilities
Chairing all test planning, status review, and final review meetings
4
TABLE I. - ELECTRONIC SYSTEMS TEST PROGRAM PARTICIPATION - Concluded
Responsibilities
5
PROGRAM CONCEPTS AND DEVELOPMENT
The primary objective of the ESTP has been to provide a high level of a s s u r a n c e
that spacecraft, extravehicular? and MSFN telecommunications systems are compatible
and that the overall systems performance levelsare commensurate with project goals
and individual mission requirements. In t h e p r o c e s s of achieving this objective, sev-
eral secondary objectives have been realized. These objectives are the performance
of t e s t s e a r l y enough prior to manned flight to assist in determining overall systems
design requirements and specifications, recommendations for modifications where in-
compatibilities are found to exist o r performance levels are found to be insufficient,
determination of operational constraints, and recommendations for systems
improvements.
0
total systems
were chosen on the assumption that all compatlbllity and
component qualification, as well a s sub- performance
evaluation
systems testing and environmental qualifi-
cation, occurs at the manufacturing o r
prime contractor facilities. The four
testing levels (fig. 1) a r e s u b s y s t e m s Problem area Systems Integration
evaluation tests, systems integration tests, investigation
functlonal checkout
systems compatibility tests, and problem
( ~ensd0oit:O: 1 and
calibration )
resolution tests. A fifth category of test-
ing, "special tests, " is described in sub-
sequentparagraphs.
Subsystems evaluation
The subsystems evaluation tests a r e
subsystems performance
designed to check each subsystem (or ( verification and updating)
"black box") individually to verify per- A
formance according to speci.fication and
Subsystems from
to obtain important calibration data for prlme contractor
following tests. These subsystems evalua-
confused
qualifi-
with
be to(not
tests
tion equipment)
ground I
lspacecraft and
6
The subsystems and systems evaluation tests are repeated whenever a major
change occurs in the ESTL and are periodically repeated (between major test phases)
to supplement daily maintenance checks and to verify o r detect changes to subsystems
and systems calibration. Abbreviated versions of these tests, called brief systems
t e s t s , are run more frequently to provide verificationof important parameter values.
simulstor
thattheprimaryobjective of theESTP is monitor
realized. A generalized systems test con-
figuration is shown in figure 2. These
tests are designed not only t o a s c e r t a i n
total systems compatibility but also to
determine the performance levels and
limitations of the system for each com- Comparison f
munications mode. During these tests, system MSFN
USB system
the performance characteristics of each equipment )
(evaluation
information channel are determined and
documented.Theinformationchannel
t e s t s c o v e r not only transmitters and re- Data for systems
c e i v e r s but subcarrier
also equipment
and -1 performance
evaluation
initial modulation and processing equip-
ment(pulsecodemodulation (PCM) telem-Figure 2. - Generalizedsystemstest
equipment,
equipment,
center
etry
audio
configuration.
updata buffer (UDB), etc. ). T h e s e t e s t s
are performed on one channel at a time
(voice, television (TV), telemetry, ranging, and updata) under various combinations of
up-link and down-link modulation. Each channel is tested over the full range of rf levels
and Doppler conditions expected during operational missions. In fact, a phase of testing
in which the rf levels and the Doppler-shift effects are varied in a t i m e f r a m e s i m u l a -
ting that expected duringan actual flight can be performed. The following are examples
of measurements taken during systems compatibility tests. (The number sequence
does not indicate relative significance, )
2. Subcarrierdemodulatorthreshold
3. Ranging subsystemthreshold
7. Voiceintelligibility
8. Televisionpicturequality
The fourth level of testing, the problem resolution tests, is conducted in more
detail but on r e s t r i c t e d p o r t i o n s of the overall system to explore problems detected
during the systems compatibility tests. It is this level of testing, primarily, which
enables realization of the secondary ESTP objectives discussed earlier. The problem
resolution tests a r e often run concurrently with compatibility tests on simulated space-
craft and ground equipment; only when a resolution is found are the ongoing compatibil-
ity tests interrupted to verify the solution on the operational equipment. Problem
resolution testing is also conducted when theoretical analyses indicate potential prob-
lems and when anomalies are detected during a mission.
A similar but less directly related level of testing, designated simply a s special
t e s t s , is performed (upon request) todevelop systems improvements in the case of
marginal performance, to verify new designs in the conceptual stage of hardware de-
velopment, o r to see if the existing system can accommodate new information transfer
o r relay requirements. This level of testing also includes verification of certain NASA
Goddard Space Flight Center (GSFC)-engineered modifications to the MSFN equipment
p r i o r t o release to all MSFN sites, astronaut demonstrations where voice-conferencing
capabilities and procedure tests are conducted with astronaut participation, andhigh-
gain antenna tracking tests with varying up-link transmission modes. Special support
to the MCC a l s o is included here by incorporating a t e m p o r a r y hookup to the MCC o r
simply by making appropriate tape recordings to be replayed in the MCC o r over the
MSFN to the MCC.
Both the problem resolution tests and the special tests, as separate categories,
are relatively late developments in the ESTP. It was found that to stop and reconfigure
for testing covered by these categories in the middle of, o r between, regularly sched-
uled systems compatibility tests often jeopardized schedules to the point that data either
could not be made available in time to be useful (spacecraft development too advanced),
o r the data taken were no longer applicable because of systems changes. Therefore,
the separate categories were established, and testing was scheduled during off-shift
periods, on simulated equipment, o r i n s e p a r a t e l a b o r a t o r i e s (the MSC Audio Tech-
niques and Evaluation Laboratory and the MSC Communications Systems Engineering
Laboratory) organizationally and electrically connected with the ESTL. However, be-
cause of p r i o r i t i e s o r possible consequences, the mainstream tests often have been de-
layed so that problem resolution tests o r s p e c i a l t e s t s took priority. On each such
occurrence, the test personnel worked closely with the requesting organization and es-
tablished procedures and schedules acceptable to all concerned. In many of these in-
stances, however, the data analysis and final reporting have been left to the requesting
organization so that other testing may proceed. In essence, then, the original testing
concept of the ESTP has been modified to provide flexible and rapid response to urgent
requirements that affect system design, requirement implementation, o r crew safety.
Also, future program support, where simple exploratory testing can clarify systems
capabilities and allow firming up of concepts, has been employed.
A further refinement in the original planof the ESTP occurred rather early in
the program. In many instances at that time, only early breadboard-type equipment
was available for testing and only f o r a short period of time; the prototype o r opera-
tional equipment on a more permanent basis was not available until several months
8
later. Consequently, systems compatibility testing was divided into two types - g r o s s
compatibility testing and detailed compatibility and performance evaluation testing.
The gross compatibility tests were designed to obtain maximum information about the
equipment in a s h o r t t i m e - usually 4 to 6 weeks. Only two major conditions were
tested: nominal parameter and range values and combined worst-case values. This
testing allowed detection of major incompatibilities, but tended to bypass minor prob-
lems. The detailed compatibility tests, which cover all expected conditions, come
later and usually last 3 months; Here, minor problems are ferreted out, special
testing is inserted upon request, and complete documentation on the operational system
is obtained.
Test techniques are continually being developed for the ESTP. Such items as
speech-to-noise ratio measurement, frame-synchronization loss-rate measurement,
noise-figure measurement, and others have been developed to yield greater accuracy
and to reduce test time where possible. A study is now underway on ESTP accuracies
based on measurement tolerances and interactions; the down-link telemetry channel
portion of the study is complete and the down-link normal voice channel portion is
nearly so.
Strict configuration control of the ESTL equipment used for the ESTP is main-
tained. A detailed description of the ESTL equipment. sample test plans, signal flow,
and quality and configuration control procedures are contained in a five-volume report
prepared by MSC. A l l v o l u m e s a r e updated periodically to reflect changes in proce-
d u r e s and equipment. Test program operations and ESTL equipment and support capa-
bility a r es u m m a r i z e d inappendixes A and B, respectively.Similarcontrol is
maintained over the Audio Techniques and Evaluation Laboratory and the Communica-
tions Systems Engineering Laboratory whenever these laboratories perform tests di-
rectly related to the ESTP. A brief description of laboratory capabilities available is
given in appendix B. The original program plan and sequence of testing, as proposed
in the five-volume report, have been adhered to except for two major causes. One
cause, the largest perturbing factor, w a s that additional tests (extravehicular astro-
naut demonstration tests, rf t r a c k e r t e s t s , Apollo lunar surface experiments package
(ALSEP) tests, Apollo range instrumented aircraft (ARIA) performance evaluation tests,
etc.) were implemented and completed. The total time added by this cause w a s over
1-1/2 years. The second cause (of less significance) was that increased test scope,
including special testing, took more time than originally forecast. The time increase
for the latter cause was approximately 6 months. The total increase in time was, then,
approximately 2 years. A s a result of this additional testing, many significant contri-
butions - important in design, in development, and ultimately in mission operations -
were made by each of the previously listed program phases.
The ESTP has made the following significant contributions to the ACS. (The
numbering sequence does not indicate relative significance. )
2. Determination of o v e r a l l s y s t e m s p e r f o r m a n c e l e v e l s a n d c a p a b i l i t i e s
9
4. Verification of analyses and predictions
The ESTP has resulted in a complete and thorough documentation of the per-
formance capabilities and the limitations of the ACS and can provide similar results
f o r any communications system used for manned space flight.
TEST ACTIVITIES
Testing activities under the ESTP were begun in September 1964, in temporary
facilitiesat MSC, andhavecontinuedwithoutinterruption,exceptforbriefrecon-
figurationsandupdateperiods(includingrelocationtothepermanentfacility),until
thepresenttime.Thespecifictestsconducted are describedinthissection. For
convenienceandemphasis,they a r e groupedintothreecategories:majortests
(totalspacecraft/groundtests),specialtests(partialspacecraft/groundtests),and
support tests (special problems of lesser manpowersignificancethanthespecial
tests). A schedulewhichillustratesthetimesequenceandrelationship of t h e s e
t e s t s is shown in figure 3. Significant outputs from the tests are discussed in the sec-
tion entitled "Significant Results. I'
10
Major Tests
Major tests (designated "A") are aimed at verifying overall communications sys-
tems compatibility and performance for overall program support and do not, as such,
cover such special testing as determining systems capabilities to fulfill individual mis-
sion objectives where they differ from flight to flight. However, the major tests do
establish basic performance criteria and capability and information from which specific
mission capabilities can be derived.
Two major classifications of tests were accomplished. The first of these was to
determine the compatibility and performance of the overall system. These tests de-
t e r m i n e d s u c h c h a r a c t e r i s t i c s a s PCM data quality, voice intelligibility. updata link
(UDL) quality. ranging accuracy, and acquisition time, all at various rf received signal
levels and carrier thresholds. The second classification of tests included investigation
of problem areas detected in the compatibility and performance tests and also included
TV demodulation tests, emergency-key demodulation tests, and low-frequency inciden-
tal amplitude modulation (IAM) and incidental phase modulation (IPM) tests designed to
answer special questions that arose regarding spacecraft (particularly the lunar mod-
ule (LM)) high-gain antenna pointing accuracy and stability effects on data quality. This
s e r i e s of tests proved the basic compatibility of the Block I ACS. However, as noted
previously, several problems that had to be solved prior to a lunar mission were un-
covered. At the time of these tests, the Block I ACS was no longer intended for use at
lunar distances; some of the problems detected, however, were common to both the
Block I and the Block I1 systems. Other problems were not serious enough to demand
major hardware rework but did require systems or operational constraints. Some
problenls indicated the need for detailed specifications, primarily in regard to systems
11
performances and interfaces. The major problems in each category are presented in
table 11. Based on r e s u l t s of this test series, the problems were corrected by hard-
ware, documentation. or procedure changes. In many instances, further testing w a s
needed prior to making any definite corrections to the problems. Some of the addi-
tional testing performed is discussed in later sections of this report.
Problem Resolution
~~ ~.
~
.-.iL.~_
When the transponder was in the ranging Block I - The up-link modulation indices
mode, up-link data were turned were reduced.
around and remodulated onto the
down link, severely degrading the Block I1 - The problem was minimized
51.2-kbps telemetry data. by transponder design.
Incorrect range tally read-outs for cer- Personnel at JPL corrected the problem.
tain range-code delays were caused
by d e s i g n e r r o r in the ranging
subsystem.
Quality of updata did not correspond to Block I - The quality was adequate.
predictions as a r e s u l t of poor detec-
tor design. Block I1 - A design correction was
incorporated.
400-Hz power to the transponder con- Block I - A much improved inverter was
tained AM as a r e s u l t of load changes: designed by the contractor.
this condition caused undesired PM
on the down link, which degraded re- Block I1 - The transponder design in-
ceived data. cluded dc regulation.
- ~- _ _ ~-
=- " _.__
TABLE 11. - BLOCK I-E PROBLEM AREAS - Continued
~ . . . ~
.~ - . ~~ -~ .. .. ..
..
Problem Resolution
...- . -, .. - " - .~ ~ ~ ~~
I _ _ .
Very weak up-link signals caused noise Tests to determine the point atwhich
modulation on the transponder voltage- this condition affects PCM data quality
controlled oscillator (VCO). were performed.
Design of the audio center was such that Block I1 specifications were changed to
upvoice was fed back into the down- improve this condition.
voice channel, thereby limiting maxi-
mum obtainable voice intelligibility.
Detected UDL subbits could be inverted Po1arit.y at each point in the system had
if one of many interfaces was not to be specified and closely observed.
properly interfaced.
13
, ,..
~~~
Problem
~
I Resolution
I
..
~~
- ~~
"" -~ ~~ .
Long s t r i n g s of '(1's'' o r "O1s" in the The PCM bit and word formats had to be
PCM data stream could possibly cause specified in such a manner that long
loss of lock by the bit-rate clock on series of " 1's" o r ''O1s" w e r e not
the ground. present in the format.
primary objective of the CSM Block I1 (sj.mulatea compatibility test series was to ver-
i f y the compatibility and performance of the intended CSM Block I1 design by using sim-
ulated CSM communications equipment and operational ground equipment. (The ground
USB system used for the Block I-E t e s t s w a s r e p l a c e d with an operational system spe-
cifically designed for the Apollo Program. ) The subcarrier demodulators were simu-
lated; that is, they were not the planned operational units. Simulated CSM equipment
had to be used because the Block I1 design had not been finalized. The Block I1 equip-
ment was simulated by the Block I "E-5" transponder modified for Block I1 p a r a m e t e r s
and by a "Universal" (or adjustable) spacecraft communications system which was pro-
vided for this test and is now assigned to the problem resolution phase of the ESTP.
Consequently. this test series a l s o s e r v e d as a design verification test for the CSM
Block I1 communications system. Furthermore, problem areas could be resolved
more readily since the design was not f i r m .
The types of tests performed were very similar to those done for the Block I-E
model (A-l), except that some mission profile tests, in which a dynamic Doppler sim-
ulator was used to simulate spacecraft velocity and range changes, were performed.
Also, the number of data points taken for each channel was somewhat reduced because
of the limited time available.
Again, the test series verified the basic compatibility of the communications s y s -
tem design, this time for Block 11. Also, as before, some problems were uncovered
which had to be resolved. These problems can be categorized as before, and the major
ones are presented in table ID. A l l necessary corrective action h a s been taken. This
action has occurred. however, often as a r e s u l t of further testing, some of which is
described in later sections of this report.
14
TABLE 111. - BLOCK 11 SIMULATED SYSTEM PROBLEM AREAS
~~~~ .. __
" ..
Problem
..
. ~
For low spacecraft transmit power and GSFC personnel redesigned the filter-
omnidirectional antenna configura- demodulator subsystem for detection
tion, the total ground-received signal of emergency key.
power from lunar distance was 1.8 dB
below that required for 80-percent
copying accuracy of keyed tones.
Plus-Doppler offsets caused slight deg- The problem is a function of rate and
radation of voice and UDL channel magnitude of Doppler and must be
performance; negative offsets caused accounted for in circuit margin
improvement of similar magnitude. calculations.
This was caused by phase shifts re-
sulting from the transponder carrier
loop static-phase error and was most
noticeable at weak signal levels.
Telemetry BER using the DSE w a s some- The problem must be accounted for in
what degraded for the real-time case. circuit margin calculations.
Also, f o r 32: 1 playback, the best
BER achievable was 1 X 10- '.
15
TABLE 111. - BLOCK 11 SIMULATED SYSTEM PROBLEM AREAS - Concluded
_______~
~
~
". -~
Problem Resolution
_"-
_________~~
Best telemetry BER of 1 X lo-' for the The specification was changed to reflect
DSE conflicted with performance and equipment limitations.
interface specifications.
Problem Resolution
~~ ~~
~~~
Telemetry channel performance was de- The MSFC personnel were advised of the
graded by up-link modulation in the problem and reduced the turnaround
transponder ranging channel. channel gain constant.
Down-link false lock was caused by the The MSFC personnel were advised of the
transponder switching power supply, problem and took corrective action.
which generated spurious signals at
37 dB below the carrier wave. The
MSFN r e c e i v e r would lock onto the
spurious signals.
16
Command and service module Block I-D/MSFN USB compatibility tests (A-4). -
The CSM. Block -1-D.model USB- equipment andT h e MSFN .RER-Kbsystemswent into
t e s t i n g n e a r t h e f i r s t of May 1966, and the testing was concluded in mid-June 1966.
The results of the tests were compared to the system specifications and to expected
performance. This comparison indicated that audio center crosstalk and the presence
of excessive noise in the crewmembers' headsets (when the crew audio switch was on
with the 30-kilohertz up-link subcarrier off) created problems. Also, the results of
antenna switching indicated that the automatic switch affected the USB equipment
carrier-acquisition threshold and that conditions existed in which the antenna switch
could go into oscillation. This automatic switch was not incorporated into the final
Block I1 design.
-~-~- . - -
I
~ " ".i ~ ~ -. " . ~" I___
Problem Resolution
-".. . . "
.". ." . - . . .. L . "
System degradation was caused by poor F o r both Block I and Block 11, a much
regulation of the 400-Hz power supply, improved inverter system (effective
causing AM and PM in the modulator, on Apollo-Saturn 202) was designed by
the VCO, and the power amplifier. the contractor. Block I1 s y s t e m s a l s o
have regulated dc power supply.
17
TABLE V. - COMMAND AND SERVICE MODULE BLOCK I/MSFN
" .- . ~ - ~ ~ . - -~
Problem Resolution
-~- " . . - . .. . -
The signal margin was inadequate for the Personnel at GSFC redesigned the filter-
emergency key (assuming failure of demodulator system to achieve ac-
the power amplifiers and the high- ceptable performance.
gain antenna).
Degradation of UDL was caused by IAM Reduced up- link modulation indices mini-
of the ground SCO. mized this effect. Personnel at GSFC
initiated development of improved SCO.
Data signal polarities were reversed Total system polarities were specified to
(PCM,UDL, T V , andPRN). all concerned; some MSFN hardware
wiring changes were also required.
(A-5). - The CSM communications equipment, including the USB equipment and the
MSFN RER subsystems, entered testing in mid-June 1966, and the tests were com-
pleted in mid-July 1966. These tests were performed to determine whether any prob-
lem detected during the earlier tests (A-2) remained in the prototype equipment. The
test results revealed two m a j o r p r o b l e m s . F i r s t , t h e s p e c i f i e d b i t e r r o r r a t e ( B E R )
of 1 x could not be achieved when the MSFN receiver was tuned to the700-hertz
18
loop bandwidth, and the backup voice was phase modulated on t h e c a r r i e r with 1. 6-kbps
telemetry imposed on a 1.024-megahertz subcarrier. The specified BER could be
achieved when the receiver was tuned to the 50-hertz loop bandwidth.
Secondly, when the up-link carrier was phase modulated with the pseudorandom
noise (PRN) range code at 1.34 radians, the power in the received range code at the
MSFN site was s o strong that the correct ranging procedure could not be followed un-
less additional attenuation was incorporated into the MSFN ranging receiver design.
The available attenuation in the ranging receiver was 12 decibels, and test results in-
dicated that an additional 5-decibel attenuation was required. These problems are
summarized in table VI.
Problem Resolution
Block I1 PCM performance w a s degraded The specified BER could only be achieved
in the back-up voice mode with the when the 50-Hz receiver loop w a s
MSFN receiver tuned to the 700-Hz used.
loop bandwidth.
Lunar module/MSFN USB gross compatibility tests (A-6). - The LM/MSFN USB
-
t e s t s began in mid-October 1966, and were completed during the first week of Decem-
b e r 1966. The tests were necessary to verify that the LM transceiver and the MSFN
RER subsystems were compatible with the system specification and with mission re-
quirements. Performance characteristics such a s BER, probability of c o r r e c t a c -
quisition, range-code acquisition time, TV picture quality, and voice quality were
observed and recorded. Several major anomalies were observed. These problems
are summarized in table VII. Many of the listed recommendations resulted in further
t e s t s , s o m e of which are discussed later in this report.
19
TABLE VII. - LUNAR MODULE/MSFN USB GROSS TEST PROBLEM AREAS
Problem Resolution
Down-link voice quality (gross WI) t e s t s Selected redesign of the LM voice channe
indicated serious deficiency in the was accomplished to improve time
maximum downvoice intelligibility constants and linear dynamic range.
obtainable when space-suit noise was
simulated.Suspectedcauseswere
audio center automatic volume control
amplifier stages emphasizing the in-
put noise and high clipping levels in
the backup voice mode ( 2 4 dB
specified).
The ranging modulation index of 1. 34 ra- Attenuation in the MSFN range receiver
dians required an i . f . attenuation of was increased. New up-linkmodula-
16 dB in the MSFN range receiver. tion indices for PRN ranging modes
The existing systems capability was werespecified.Also, MGC capability
a maximum of 12 dB. in the MSFN receiver was added.
20
4
Apollo lunar surface experiments package/MSFN USB gross compatibility tests
(A-7).-5e-ATEP?mmGnTCaWeTuipFeiif anhii'symiiated M-SFN receiver-exciter
entered testing on December 1, 1966, and the work was completed December 22, 1966.
Because the MSFN USB system had not been implemented to transmit and receive
ALSEP frequencies, a USB system simulator (USBSS) designed to transmit and receive
CSM and LM frequencies was modified to transmit and receive the ALSEP frequencies.
Since the MSFN modification was not completely defined a t t h e t i m e t h eUSBSS was
modified, some assumptions were made to allow for the early implementation of the
ALSEP modification. The ALSEP equipment was also not operational but was a
"brassboard" model, electrically similar to the design concept.
The polarity inversion problem could be resolved by inverting the polarity of the
transmitted ground signal; this solution, however, had to be implemented so as not to
make the ground signal incompatible with the LM and the CSM UDL. Therefore, the
GSFC personnel decided to utilize inverted PSK data to modulate the ALSEP up-link
carrier. Also, the ALSEP manufacturer has accepted a specification requirement that
each of the production ALSEP receivers provides the same polarity output signal for a
given input signal polarity. This modification does not. however, solve the noise-
figure problem, which is still being evaluated.
phase I (quick-look) compatibility tests were performed during February 1967. The
purpose of this test phase was to provide an early indicationof the level of compatibil-
ity and performance of a dual extravehicular astronaut communications system by using
the space-suit communicator (SSC)/LM/MSFN/CSM system in support of dual extra-
vehicular astronaut activity.
21
The original Apollo Program requirement for lunar surface operations was for
one astronaut to explore the surface while the other stayed in the LM. The SSC s y s t e m
was developed to provide the communications capability for this original mode of opera-
tion. The SSC system provided for duplex voice between the extravehicular astronaut
and the LM a n d f o r the transmission of extravehicular mobility unit (EMU) biomedical
and status data to the LM. The LM system provided voice conference (among the ex-
travehicular astronaut, the LM crewman, and the MSFN) and provided the relay of
EMU data to the MSFN; the MSFN system could extend the voice conference to the
CSM through S-band. In February 1967, the operational plans began to evolve to the
"two extravehicular astronaut" procedure which was finally adopted. Because of this
change in the lunar surface operational procedure, this quick-look series of communi-
cations system tests was performed.
/ /
Monitor
and
record
/ /
Monitor
and
record ,/ Wnltor
"
LM and
S-band / record /
MHz 2282.5 1 + S-band
Signal cornblnallon 7
FMIPM mice 2101.8 MHz
FMIPM blomedlcal Slgnal combination 2
EMU - PCM'Phl'PM 1.6 kbps FMIPM mice
TM
, -- ---
,
-
,'I
f"""+
II
I
csh,,
L"""l.'
I
I
1
-~-------~
"
J
)
""""
r"""""""
1
"""""- + MSFN Voice
/ 'I /
Monitor Note: System designed for only one
and channel B ltransmissiord at
record
/ any one time
22
communications. Also, voice conference was not possible if either extravehicular as-
tronaut transmitted E M U data, because this condition prohibited the other extravehicu-
lar astronaut from '?breakingin. ''
The tests and the demonstration proved that the ACS could not support the new
two-extravehicular-astronaut requirement. Because this was a major problem, equip-
ment redesign and modification were initiated. (See description of t e s t B-6. ) This
effort led to the implementation of a voice subcarrier squelch for the LM S-band equip-
ment and to the development of the extravehicular communications system (EVCS) to
replace the SSC.
23
Command and service ~ - module/ARIA
. ._ . compatibility
-t-e s. t-s -(A- 10). - The CSM/ARIA
communications compatibility and performance evaluation tests were performed in
February and March 1968. Tests were performed jointly by representatives of MSC,
U. S. Air Force Eastern Test Range (ETR), and GSFC, using an ARIA a i r c r a f t on the
ground at Ellington Air Force Base connected to CM and simulated S-IVB communica-
tions equipment set up in temporary quarters adjacent to the aircraft. The purposes of
t h e s e t e s t s w e r e t o v e r i f yARIA/CSM USB compatibility and to evaluate the performance
levels and circuit margins for the CSM/ARIA USB communications system prior to
scheduled ARIA mission support. This test program also included tests to determine
S-IVB/ARIA telemetry link performance and to determine if any interference between
the S-IVB and CSM occurred at the ARIA receiver. The test program consisted of
voice tests (ARIA-to-CM and CM-to-ARIA), telemetry tests (CM-to-ARIA and S-IVB-
to-ARIA), and data-dump tests (recorded down-link information relayed to the MSFN
f r o m t h e ARIA after completion of active spacecraft coverage).
In general, the test results verified that systems compatibility and performance
were commensurate with mission communications support requirements. During data-
dump tests, however, the reconstructed PCM data from the ARIA r e c o r d e r w e r e
severely degraded when received at the MSFN. A different modulation technique, using
a subcarrier available from the tape recorder, improved the quality and was subse-
quently adopted. Other minor problems, such as phase-lock loop instability caused by
ARIA receiver crystal oven on-off cycling, were also resolved.
The original schedule called for test initiation in December 1968 (calibration
tests) and completion of all t e s t s by July 1969. Several other priority tests associated
with the Apollo 11 and 12 missions. however, caused the schedule for the phase I11
test series to be extended through December 1969. These priority tests are discussed
in later paragraphs. All mission critical modes were nevertheless tested prior to the
Apollo 10 mission.
The phase I11 test series was divided into eight segments consisting of calibration
t e s t s ; UDL tests: PCM telemetry tests; voice performance tests; an EVCS electro-
cardiogram (EKG), EVCS pulse amplitude modulation (PAM), and LM hardline (H. L. )
biomedical tests; TV t e s t s ; a ranging test: and rf-acquisition tests. Calibration tests
a r e a continuing item, a portion being performed for each segment. The UDL, PCM
telemetry, voice performance, ranging, rf-acquisition, and EVCSPAM t e s t s a r e com-
plete. Television tests are complete, based on the new color TV system for the LM.
The UDL t e s t s , r u n f r o m D e c e m b e r 16,1968, to January 10, 1969, showed that the LM
UDL system performed within specifications and that performance was comparable to
the Block I1CM UDL system. Special investigation of the backup upvoice, however,
revealed some problems that were related to theLM commander microphone and side-
tone circuitry in the LM signal-processor assembly (SPA). The voice output level from
24
the 10-kilohertz channel was too low; therefore, the signal was routed through the LM
commander's microphone amplifier. This routing caused the backup upvoice to be
turned around and transmitted on the LM down-link wave channel, producing an echo
effect at MCC. Operational and hardware solutions were explored and several were
found acceptable; because of the delivery and launch schedules, however, operational
solutions (ground and spacecraft operator procedures) were recommended.
The telemetry tests were initiated on January 17, 1969, and, after several pri-
ority test interruptions, were completed on F e b r u a r y 29,1969. Results showed posi-
tive circuit margins in all cases except the baseband modes. Tests also showed that
the LM telemetry subcarrier amplitude is reduced somewhat (8 percent) when modulated
by the high-bit-rate data when it had a ''1-0" transition density; this in turn affects the
carrier modulation index and degrades overall performance by approximately 0.5 deci-
bel. Other activity is aimed at correcting these problems.
Voice performance tests were begun on March 5 and were completed in mid-
March 1969. Upvoice test results indicated positive lunar-distance performance mar-
gins for all voice up-link combinations for the omnidirectional antenna and the MSFN
85-foot-diameter antenna; however, onboard squelch operated at a total received power
that was 7 to 10 decibels stronger than the worst-case specified total received power.
indicating the possibility of p r e m a t u r e loss of up-link voice under certain conditions.
The squelch circuit can be switch deactivated, however. Down-link test results showed
negative performance margins with the LM steerable antenna for certain signal combi-
nations. The down-link relay voice test showed good performance for all modes of in-
t e r e s t . T h e EVCS receiver tests showed good performance except for the case of
EVCS- 1 to EVCS-2 where only 70 percent W 1 was noted, quite possibly caused by
EVCS-1 s u b c a r r i e r i n t e r f e r e n c e . T h e vhf signal received at the LM was satisfactory.
Down-link emergency-key tests also run at this time indicated satisfactory per-
formance for this communications mode. A 15-decibel discrepancy between predicied
and measured AM-key demodulator predetection signal-to-noise ratio was observed.
Investigation indicated that spurious response in the predetection filter. coupled with
a larger than specified noise bandwidth. raised the effective predetection noise power.
The EVCS EKG, EVCS PAM, and LM H. L. biomedical tests were performed
from April 1 to June 6, 1969. Results using flight-type hardware showed that system
performance was satisfactory and that all worst-case performance margins were
positive except for certain instances where the EKG and PAM a r e on down-link signal
combination 10 with the LM steerable antenna and MSFN 85-foot-diameter antenna in
use; these negative margins can be overcome, however, by u s e of the erectable an-
tenna or the MSFN 210-foot-diameter antenna.
Special Tests
The major special tests (designated "BfV) are aimed at verifying particular
channel compatibility and performance; at resolving real o r potential major problems
25
,
Additional S-band tests (B- 1).- The spacecraft equipment that underwent the ini-
tial Block I t e s t s ( s e r i e s A-1) entered roughly 5 weeks of additional testing in Septem-
b e r 1965. The primary purpose of these tests was to investigate several questions
identified from the results of the Block I-E USB tests and from specific analytical
studies performed by the MSC Communications System Analysis Branch. In general,
the equipment used during these tests was the Block I-E spacecraft system and an up-
dated MSFN RER s y s t e m ( s e r i a l n u m b e r 14). In some instances, the modified E-5
transponder which simulated a Block I1 unit (and which was used in the simulated
Block I1 tests, A-2) and three different 70-kilohertz UDL discriminators were used.
The specific questions which were to be answered by these tests, and the results of
t h e s e t e s t s , a r e s u m m a r i z e d i n t a b l e VIII.
-._. -.- - -- .
-
Test
UDL
Purpose
26
TABLE VIII. - ADDITIONAL S-BAND TESTS - Continued
UDL Perform S-band tests with worst- The effect of high IAM on link per-
case and best-case IAM up-link formancewasnoticeable.Lower
subcarrier oscillators, using a modulation indices, however,
GSFC-supplied 5-percent AM minimized the problem for
70-kHz SCO. Block I.
. ". ~- ." .
~~
27
I1
" ~ ~~
Special Establish PCM performance range The IPM effects on BER increased
as a function of IPM. as the modulating frequency de-
creased.Thisdegradationbe-
came significant ( 2 dB) at P M
r a t e s of 50 Hz f o r a peak phase
deviation of 38".It also was
significant for PM rates of
2000 Hz a t a peak phase devia-
tion of 4 5 " . Bandlimited voice
degradation increased more
rapidly with increasing rms
phasedeviation.Theconclu-
sions drawn were that IPM in
e x c e s s of 28" r m s s h a p e d as
either a sine wave o r Gaussian
bandlimited noise significantly
degraded the 5 1.2-kbps
telemetry.
Verify effects of updata phase Tests confirmed that, when a
reversal. 180" phase change was made,
all messages were rejected.
~ ~-~ ~ " ." - - "
Special FM tests (B-2). - The special FM channel tests were conducted jointly
with GSFC from March 7 to 21, 1966, to investigate possible problem areas in the L M
and the Block I1 CM FM transmission links. The primary area of concern was that the
LM TV channel was ac-coupled; and, for a very-low-frequency video waveform, the
information was greatly distorted. Also, when the video was completely differentiated,
the transmitter peak-frequency deviation essentially doubled. Other areas of concern
included effects of frequency offset caused by oscillator drift and Doppler effects and
determination of the optimum FM demodulator configuration for critical FM modes.
Both LM and Block I1 CM FM operational modes were tested. The FM transmitter
used for this test was the transmitter associated with theUSB t e s t s e t ; t h e F M t r a n s -
mitter, which is a direct-coupled device, was used to simulate the LM t r a n s m i t t e r by
the incorporation of an external ac network.
28
TABLE M. - FREQUENCY MODULATION TEST RESULTS
29
TABLE M. - FREQUENCY MODULATION TEST RESULTS - Concluded
~ -~ ~ ~
30
s u b c a r r i e r o s c i l l a t o r s (SCO) with reduced IAM improved tracker performance to within
specification; similar improvement was obtained by reduction of up-link c a r r i e r modu-
lation indices. Subcarrier deviation changes had no significant effects on t r a c k e r e r r o r
performance.
Frequency
~ - . .modulation
. . . demodulator
. . . .~~ threshold-extension
" . - . . ." tests - Study of
(B-4).
a n a l y s i s a n d t e s t i n g r e s d t s u pto the summer-of 1967 indicated conclusively that per-
formance of the Apollo CM communications system in the FM mode would be seriously
degraded under certain operational modes at lunar distances. Particularly, playback
telemetry and voice, as well as TV information, were expected to be poor. The iden-
tified reasons were the following:
1. The signal level arriving at the MSFN receiver was below the "threshold" of
the FM receiver-demodulator combination.
Further effort during the ensuing 1 2 months resulted in tests during Septem-
b e r 1968 of five FM demodulators and of a refined click eliminator. The four demodu-
l a t o r s w e r e (1) the MSC MSFN demodulator, ( 2 ) a retuned and realined (by the Applied
Physics Laboratory (APL) at Johns Hopkins University) MSFN demodulator furnished
by GSFC, ( 3 ) a n MSFN demodulator modified by GSFC (to improve alinement proce-
dures), (4) a conventional demodulator furnished by GSFC, and (5) a modified (for
Apollo modes) Lunar Orbiter FMFB discriminator provided by MSC. T h e t e s t s w e r e
witnessed by GSFC personnel. None of the MSFN o r MSFN-type demodulators per-
formed as expected, with the possible exception of the APL-retuned unit. The conven-
tional unit also was disappointing. The FMFB demodulator showed significant
31
improvement but, in its existing state, was difficult to interface with the MSFN re-
ceiver. The click eliminator worked quite well.
Further effort by GSFC resulted in their contracting for new MSFN FM demodu-
lators. A prototype unit was brought to MSCby GSFC in early December 1968, along
with the APL-realined unit, to compare performance of these units with the MSC MSFN
demodulator for the specific purpose of determining the optimum unit to use on the
85-foot-diameter antenna sites for the Apollo 8 mission. The results of t h e s e t e s t s
clearly indicated that the new GSFC prototype unit was the best, and the unit was sub-
sequently used on the Apollo 8 mission. The MSC personnel supplied six click elimi-
nators (built in-house) to the three 85-foot-diameter antenna sites (one prime and one
backup) for the Apollo 8 mission, and these were installed and operational on one site
i n t i m e f o r t h e Apollo 8 mission with generally satisfactory results. During the last
week of March 1969, a production version of the new demodulator was loaned to the
ESTL for a series of tests involving the LM in a lunar surface (relay) FM configuration
and the CSM in various FM configurations. These tests used the Communications Sys-
tems Engineering Laboratory breadboard EVCS system throughout the program. In
general, the new demodulator showed significant improvement (4 to 6 decibels) in per-
f o r m a n c e f o r CSM voice-dump modes and increased performance for CSM slow-scan
TV. The LM signal combination 10 performance was deemed adequate to support the
lunar mission but was not significantly improved over the original demodulator system.
It should also be noted that good picture quality for the commercial TV signal format
was expected to require use of the JPL 210-foot-diameter antenna system. Because of
somewhat different characteristics of the new GSFC demodulator, the click-eliminator
effort is being continued to optimize its performance with these units.
Tests were performed to analyze both NRZ-L and split-phase PCM channel per-
formance using the existing LM SPA configuration and also using a simulated LM SPA
with the output bandwidth modified (widened) for split-phase operation. Results of
t e s t s with the existing SPA configuration indicated that split-phase performance was
poorer than NRZ-L performance by about 2 decibels and that the split-phase encoding
was more sensitive to ranging signal interference. The test results obtained by using
the modified SPA indicated that split phase performed slightly better than NRZ-L, prob-
ably as a r e s u l t of a more stable clock reference. An interesting result was that the
NRZ-L also performed better with the wider output bandwidth, indicating that the
32
existing SPA design was not optimized. Nevertheless, because of time and cost im-
pacts, the changes to split-phase encoding for the PCM channel were not approved, and
increased monitoring of channel loading for each LM was effected.
Major changes made to achieve the dual-EVCS system were (1) implementation
of an FM transmit link from EVCS-2 to EVCS- 1 f o r r e l a y of EVCS-2 voice and data to
the LM through EVCS- 1 in the primary mode of operation and ( 2 ) reduction of the num-
b e r of subcarriers (seven for the old case) to a total of four for dual-EVCS operation.
As a r e s u l t of the short period of time available for development and qualification of
the new system, major emphasis was placed on performing end-to-end rf system (dual
EVCS/LM/MSFN) design verification and performance evaluation tests. Of major con-
cern at the time (and also the specific objective of the test program) was the experi-
mental determination of minimum performance requirements f o r (1)the EVCS
subcarrier levels to be modulated onto the 1.25-megahertz subcarrier (the LM SPA
had been designed for seven subcarriers) and (2) the deviationof the 1.25-megahertz
s u b c a r r i e r on the S-band carrier. (Analysis of vendor acceptance test procedure (ATP)
data showed that, although within specification limits, all signal-processor assemblies
were performing at o r near the minimum (worst-case) deviation level. )
5-band
I iBh
,,lIl
frequency t
ableandthatthisminimumspecifiedper- ,"~~:a",brtqnlr~~~-links,gnal A
formance could
be
improved to
an combinations IO and 7
acceptable level, as shown by test data, Baseband mice - down-link
signal
and
by increasing either the EVCS s u b c a r r i e r
Data display
levels o r the 1.25-megahertz subcarrier
deviation on t h e c a r r i e r .
Figure 5. - Design verification test of the
EVCS-LM-MSFN system.
33
In an effort to prevent the necessity for modifications to the SPA,a review of
vendor ATP data related to the S-band modulator sensitivity was initiated. It w a s found
that, for most cases, the modulator sensitivity was near the "high" limit of the speci-
fication, a factor that compensates for the minimum 1.25-megahertz level output of the
SPA. Test results and related information presented to the CCB on June 14, 1968, re-
sulted in the decision "not to modify" the SPA, but to monitor ATP data to ensure that
a worst-case system would not be assembled (i. e . , a system which had three simul-
taneous conditions of (1)minimum deviation of the EVCS s u b c a r r i e r s onto the
1. 25-megahertz subcarrier, (2) minimum 1. 25-megahertz output from the SPA, and
( 3 ) minimum S-band modulator sensitivity).
In addition to performing EVCS design verification tests during this time period,
an attempt was made to resolve the problem of low-bit-rate telemetry BER degradation
caused by baseband voice interference with the telemetry channel (occurs for signal
combinations 4 and 8). Test results were presented to the June 14 CCB, resulting in
the decision to accept momentary telemetry data dropouts during speech periods.
Special
~ - "" - - . .8-mission
Apollo .- - .
""
tests
.- - . .
(B-8). - A s e r i e s of special tests was performed to
. - . . .. .. -
verify certain operational modes {including a nonstandard signal combination having
backup voice. low-bit-rate telemetry subcarrier. and ranging on the carrier) and pro-
cedures planned for the Apollo 8 mission. These tests were performed in November
and early December 1968. and involved evaluation of proposed MSFN ranging and ac-
quisition procedures and of performance of PM down-link mode 8 under expected
34
mission conditions. Test results indicated that the GSFC-proposed ranging and ac-
quisition procedures were acceptable, that down-link emergency-key channel perform-
ance was acceptable, but that up-link automatic gain control (AGC) key (not a normal
mode but evaluated at the request of the MSC Flight Support Division) copying was
limited to three words per minuteas a r e s u l t of slow onboard AGC and meter response.
Voice and telemetry tests indicated telemetry channel performance degradationof ap-
proximately 2 decibels when ranging was also on the carrier, indicating, as was ex-
pected, a n e e d f o r m o r e s t r i n g e n t c o n t r o lof omnidirectional antenna switching when
ranging was to be used. The baseband voice channel performance was affected very
little by the ranging code o r clock.
It was also determined that the sequential color TV deviation could be increased
to a maximum of 1 . 6 megahertz with the telemetry, voice, EKG, and PAM channel
performance remaining approximately ( 1 decibel or less) equal to the case using slow-
scan black-and-white TV. Preemphasis was not recommended for the LM because of
additional degradation ( 1 to 2 decibels) to the EKG and PAM channels.
Tests also showed that the rf power margins for good-quality sequential color TV
are such that the MSFN 210-foot-diameter receiving antenna would be required if the
spacecraft steerable antenna was to be used. With the erectable antenna, an MSFN
85-foot-diameter antenna receiving station would provide adequate performance
margins.
Apollo
~.. .. .-
lunar
"_ - surface
. . -. -
experiments package
.
command ..anomaly
. .. ~. . ."
~
tests (B- 10). - The
" ~ ""
objective of the ALSEP command anomaly tests, which were performed in August 1969,
w a s to determine, by experimental means, the performance of the ALSEP command
channel under different MSFN-to-ALSEP up-link conditions. Of particular interest was
a determination a s to whether previously experienced problems could be repeated and
explained.
During checkout of the ALSEP at the manufacturer's facility, at the NASA John F.
Kennedy Space Center (KSC), and during the Apollo 11 mission (early Apollo scientific
experiments package (EASEP) operation), conditions which required special investigation
35
were experienced. One of the conditions was a command verification (CV) problem.
When the ALSEP received a valid up-link command, it sent a down-link verification of
the received command followed by an extraneous verificationof a 177 command (ap-
proximately one time for eight valid up-link commands). However, because the 177
command is not an allowable command, it was not executed by the ALSEP and caused
no harm. Cursory circuit analysis indicated that the CV- 177 condition discussed will
always produce a verified but unexecuted command. Another unexpected condition was
the receipt of a CV without an up-link carrier. The EASEP, left on the lunar surface
by the Apollo 11 crew, sent false verifications of nontransmitted commands at the rate
of approximately three per hour during periods when no up-link signal was present. In
addition, because ground testing performed with more than one up-link rf c a r r i e r
showed that false command verifications occurred, additional data concerning the ef-
fects of two simultaneous up-link rf carriers with several possible combinations of
modulation were needed. Therefore, tests to measure performance characteristics -
such as received carrier power, commands sent, commands verified, and commands
executed - were initiated.
For a single up link, operating near command threshold with all " 1's'' modulated
on t h e c a r r i e r , a random CV was received on the average of one each 1.7 seconds.
None of these commands w a s executed; but, given enough time, it is likely that an
execute would have occurred. F o r a single up link near command threshold with a
1-kilohertz sine wave modulated onto the carrier, random commands were executed
an average of one each 1.3 minutes, and an average of 1.4 random command verifica-
tions were received each second. The latter condition could result i f the 2-kilohertz
component of the PSK signal failed at a s i t e . If this were to happen and up-link modu-
lation were not removed quickly, several undesirable commands could be executed.
False verifications of 177 commands occurred after proper execution and verifi-
cation of a valid command, and the frequency of t h e s e o c c u r r e n c e s was approximately
one time in eight commands for normal down-link telemetry bit rate and one time in
16 commands for low bit rate. Even though this is an anomaly, it was not considered
a serious problem. For dual up link, the ALSEP was jammed for signal levels within
0.5 decibel of each other. It was found that there must be at least a 3-decibel differ-
ence in total received power between the two up-link signals to ensure execution of
commands sent on the stronger up link. For most dual-up-link conditions tested, it
was possible to have random commands executed. The rate at which this occurred
depended on relative PSK phasing and relative power levels. On the average for all
dual-up-link tests conducted, one random command was executed each 7 minutes.
With no up-link c a r r i e r , a test was run for a 10.5-hour period; and 23 random
command verifications were received. This was an average of one CV each 27 minutes
and agreed with the results obtained from the EASEP left on the lunar surface during
the Apollo 11 mission. None of these commands was executed; but t h e r e is unity
probability that, in some finite time, a random command would be executed. The time
required has been calculated to be approximately 1000 years per command execute.
Test results showed that real-time data modulation of the scientific data sub-
c a r r i e r s ( 9 5 k i l o h e r t z , 125 kilohertz, and 165 kilohertz) w a s possible only when the
S-band transmission contained only the scientific data subcarriers: that is. the S-band
transmission excluded telemetry ( 1 . 024-megahertz subcarrier) and baseband voice.
The recorded data modulation of the scientific data subcarriers was apparently limited
(by DSE electronics) to a level which did not provide a frequency deviation of z 7. 5 p e r -
cent of the subcarrier center frequencies. Positive scientific subcarrier predetection
signal-to-noise margins were indicated for the real-time and tape modes.
Since the characteristics of the scientific data information were not fully known
a t t h e t i m e of t h e s e t e s t s , a conclusive performance test could not be performed on the
scientific subcarriers. The results of the tests performed in the ESTL, however, do
indicate that adequate performance can be expected for the usual typeof data
encountered.
Additional Apollo lunar mission systems tests were performed in the ESTL with
a simulated spacecraft 113 system configuration. The results indicated that the signal
performance was not adequate to support mission requirements. Based on t h e r e s u l t s
of these tests, the signal design has been changed to improve channel performance.
37
Support Tests
The primary purpose of the support tests (designated 'lC1l) was,for the most
part, to obtain more information on specific problem areas identified o r suspected
within a channel, as opposed to overall channel o r overall systems performance eval-
uation. Some of the tests preceded major special tests or major test phases and were
intended to evaluate fixes to problems or to gain critical informationas soon as possi-
ble in the test series. Several of the support tests are discussed briefly, in chrono-
logical order, in the following paragraphs.
The problem first appeared when the Univac 1218 computer was utilized to de-
termine BER as a check on the serial bit error detector (SBED) used in previous tests.
The Univac 1218 print-out indicated more errors than the SBED f o r a simultaneous
run. It thus became apparent that the data. which should have been inhibited from the
computer when frame synchronization was lost. were not being inhibited and that they
w e r e not being decommutated into the proper &bit groupings. Additional tests indi-
cated that the frame synchronizer was not losing lock even though circuit tests indi-
cated that correlation was occurring at the wrong time in the data. By further testing,
it was found that the improper lock was caused by an overlap of approximately 20 to
30 nanoseconds of control and timing pulses at the digital-to-analog control gate in the
decommutator. This condition was apparent when the bit-rate clock (as a result of
noise on the input to the signal conditioner) became a 1-bit period behind in phase with
38
the data. The GSFC personnel were notified of the problem and took corrective action
on the MSFTP-1. Transition density tests were inconclusive, as the SBED r e s u l t s
showed very little degradation caused by lack of transition for up to 54 bits, but effects
on the decommutation process were masked by the improper lock problem. (Later
tests on an MSFTP-2 PCM processor indicated no effects for lack of transitions of up
t o 200 bits. )
Goddard Space Flight Center aircraft transponder test (C-3). - On June 20 and 21,
1966, YheESTL, -at the-reqiiesf of GSFC personne1,"performedploratory t e s t s on a
CSM Block I-D model USB equipment package from one of the GSFC flyby a i r c r a f t . In
brief, the tests pointed out that one of the transponders performed within specification
when specified nominal power voltages were used in the ESTL and that the other trans-
ponder performed within specifications when nominal power was applied, except that the
turnaround ratio (TAR) for the PRN range code was too high. When applied power volt-
age was reduced to attainlow test-point voltage outputs (13. 5 volts dc) as experienced
in the aircraft, circuit margins and thresholds were adversely affected on both units.
The high-TAR transponder, in UDL tests, leveled off a t a PCM subbit e r r o r r a t e
(SBER) of 5 x whichcouldnotbeimproved. An inspectionandcheck of the air-
craft 400-hertz power supply indicated a problem in filtering of the three-phase power.
Shorting one of these filters raised the voltage at transponder 15-volt test points to
within specification. Normal transponder operation, except for t h e high TAR on one
unit, was then experienced in the aircraft environment.
Apollo UDB performance tests (C-4). - Special Apollo UDL quick-look tests were
perfornyed in-the-ES-TTtoLiniestigateUDB output distortion relative to the DRUL and
digital command system output (1- and 2-kilohertz composite). Representatives from
GSFC had reported the existence of this distortion and had indicated that the UDL p e r -
formance might be below the expected performance.
The specification for the UDB modulator (PSK) output was the same as for the
DRUL. The PSK waveform for all r t l c ~ ' 'and all r 7 0 7 ~wra's t h e s a m e a s f o r both the
UDB and the DRUL; however. the P S K waveforms were not the same for data transi-
tions. The UDB PSK signal was amplitude distorted when a "0" to ' I 1" transition
occurred. The SBER tests were performed as a function of received power with the
Block I1 UDL decoder to determine if UDL channel performance was degraded by this
distorted PSK signal. The specific tests performed were (1) SBER as a function of r e -
ceived power, (2) comparison of UDB and DRUL waveforms, and (3) comparison of UDB
and DRUL modulator alinement methods.
The unsymmetrical 2-kilohertz sine wave of the UDB appeared to be the result of
crosstalk from the l-kilohertz sine wave at the PSK summing point. Better isolation
in the summing network was judged capable of preventing this distortion of the
39
2-kilohertz sine wave. Thii would also improve the accuracy of the amplitude setting
and the zero-crossing alinement of the UDB modulator.
The UDB alinement method was not easily understood, but basically, the desig-
nated alinement procedure was to obtain the best PSK signal under steady-state condi-
tions (no transitions) with little concern for the independent relative amplitude and phase
relationship of the 1- and 2-kilohertz sine waves. The zero crossings of the DRUL s i n e
waves occur at the same point and were positive slopes as defined for a DRUL ' I 1'' bit.
The zero crossings of the UDB sine waves for a positive slope 2-kilohertz sine wave
and a negative slope l-kilohertz sine wave occurred approximately 100 microseconds
a p a r t . It appeared that the most desirable method for modulator alinement would be
with a scope presentation of both sine waves and not with one shorted to ground. It a l s o
appeared that the 1- and 2-kilohertz sine waves were enough out of phase that, when the
transition from "0" to " 1" occurred (180" phase shift), the transition occurred at some
point other than 180"; and this produced the distorted waveform.
While more extensive testing of the UDB was considered necessary, the basic
purpose of t h i s s e r i e s of t e s t s w a s satisfied; that is, the UDB performed satisfactorily
with the Block I1 UDL decoder, and the distorted PSK waveform did not degrade the
UDL channel performance. A s a r e s u l t of these and subsequent tests, GSFC personnel
issued changes to the UDB modulator to correct the situations noted previously.
40
Apollo 4 (AS-501) countdown demonstration test support (C-9). - During the
Apollo-4. C'ountdown-Dem%ns%ration.Test-(CDDT>n October 1967, the Merritt Island
Launch Area (MILA) S-band station and several other receiving sites at KSC experi-
enced fluctuating signals and asymmetrical sidebands, resulting in degraded PCM
telemetry at various times in the count. These stations were in a relatively poor area
of the spacecraft antenna pattern (between the two radiating elements). Since the JPL
station (number 71) was almost directly in the major lobe of one element, this station
was requested to examine the signal during the final terminal count. The report was
that the signal appeared excellent at all times. This tends to confirm that the problems
a t MILA and the other stations were caused by interfering signals radiating from both
antenna elements and reflections from other objects (multipath). An intensive investi-
gation was initiated to determine if any phase and amplitude differences between the two
radiating elements could cause telemetry degradation in flight (other than that indicated
in the composite antenna patterns).
Tests in the ESTL confirmed that the variations in signal spectrum could be
caused by the interferometer phenomena associated with radiation fromtwo s o u r c e s .
These tests also showed that telemetry reception could be degraded if the signal re-
ceived from one of the two s o u r c e s w a s not at least 6 decibels greater than the signal
received from the other source. A s a result, the JPL station w a s asked to support the
final countdown and launch phases.
Application of the test results to the high-apogee portion of the Apollo 4 mission
showed that the USB telemetry might be degraded near the end of the Carnarvon, Aus-
tralia (CRO), pass and for portions of the Guam pass as the antenna patterns were not
favorable at these times. Analysis was done to show that vhf telemetry coverage of the
final service propulsion system burn over the Guam station would be adequate during
those times when USB was expected to be poor.
Lunar
"." - module
- - . .- . . UDL verification
~ _I__ ""
tests (C-10). - A test w a s performed in the Com-
. .- . -
munications Systems Engineering Laboratory in January 1968 to verify, under condi-
tions of no thermal noise degradation, that the newly designed LM updata PSK
demodulator operation w a s compatible with the MSFN-remote-site- transmitted 1- and
2-kilohertz UDL signals. This was accomplished by using tapes especially recorded by
the MSFN remote sites (Bermuda, Texas, Hawaii, and CRO) for this test. and the L M
breadboard PSK demodulator. The tapes of updata transmissions were made in the
same manner as during an actual mission. As an additional check, two of the tapes
used were also decoded with a payload module decoder (PMD) similar to the CSM com-
mander decoder. Also, an additional tape, one of the AS-501 mission tapes from CRO,
was used.
All the tapes were successfully demodulated and decoded. The CRO test tape.
however, contained inverted data which were successfully demodulated when the inter-
face lines to the demodulator were inverted. It was concluded from this test that no
inherent compatibility problems between the MSFN-transmitted UDL signals and the
LM PSK demodulator would be encountered.
41
Extravehicular astronaut/LM/
MSFN/MCC-H voice demons3rationtest
(C-11). - At t h e r e q z t - o f F O D , a test to
exercise
from
link
voice
entire
the a sim- Simulated
ulated lunar distance to the MCC-H was
conducted in May 1968 to verify that ac-
ceptable voice communications could be
received at the MCC-H when an astronaut
had traveled one-half mile from the LM ____ -.\
on the lunar surface. The MSFN equip-
ment output recordings of downvoice w e r e
made in the ESTL with suited astronauts
talking into the SSC (old extravehicular
astronaut) equipment through the LM to
the MSFN. Selected portions of these
MSFN-recorded voice tapes were for-
warded to the MSFN site a t CRO and re-
layed from CRO to the MCC-H by way of
a communications satellite and commer- Earth
cial land lines (fig. 6).
The resultant voice signals re-
ceived at the MCC-H and monitored on the
intercommunicationsloopswerevery .
good.Subsequent analysis indicated that
the voice intelligibility through the com- Figure 6 . - Extravehicular astronaut/LM/
plete
systemfrom
the
extravehicular1 MSFN/MCC-H voice paths.
astronaut to theMCC-H w a s i n e x c e s s of
90 percent. This was achieved with a minimum down-link received carrier power of
-99.8 dBm (85-foot-diameter dish antenna configuration).
Simulated voice spectrum (C- 13).- During May 1968, calibrations were made on
the relationship of USB modulation index caused by voice to the modulation index
caused by a sine-wave input. The calculations agreed with test results for signal com-
bination 8 but fell down for signal combination 4, indicating that precise LM processing
characteristics had to be known. The calculations were thus abandoned, and a simu-
lated voice spectrum was developed by the Audio Techniques and Evaluation Laboratory
42
f o r poss!.':la application in setting and measuring the mode indices. The spectrum was
produced 'by using a noise source and band-pass filters. The peak-to-rms ratio of the
simulated spectrum was measured and comparedwith the peak-to-rms ratio of the
t h r e e s e p a r a t e s p e a k e r s on the "top dog" WI test tapes. The peak-to-rms ratio
(15.2 decibels) compared favorably (within 0.133 decibel) with the average of the three
speakers.
Goddard Space Flight Center linear phase detector tests (C-14). - T e s t s with a
GSFC linearphase ~&<cto~-w~e initiated-on-July-23r19-68,
in an effort to improve the
down-link modes (both LM and CM) that have 1.6-kbps telemetry on the 1.024-megahertz
subcarrier and backup voice at baseband on the carrier. Previous test results showed
that the telemetry data were severely degraded when voice was present. The tests were
terminated on July 25, 1968. Test results indicated that the GSFC linear phase detec-
t o r was performing approximately 7 to 8 decibels worse than the normal MSFN
coriixGratioii aacl also experienced similar telemetry channel degradation when the
carrier was modulated with baseband voice.
Apollo 7 prelaunch test support (C- 15). - During prelaunch testing of Apollo 7
equipment at KSC? problems with MSFN-received vhf voice quality and with spurs on
the S-band down link (causing false receiver lock) were noted. An intensive series of
tests was performed in the ESTL in cooperation with GSFC to investigate these prob-
lems. It was found that the MSFN-received vhf voice-quality problem was probably
caused by improper alinement and tuning of the vhf receivers. The S-band down-link
spur problem w a s found to be resolvable by limiting the sweep amplitude of the ground
station to + 37 kilohertz to avoid acquiring the spurs. Both solutions were coordinated
with GSFC, which issued appropriate instructions to the MSFN.
Command and service module S-band up-link squelch control tests (C-18). - T e s t s
on the L M up-link voice squelch were performed in August 1968 to providedata t.hat
43
could be related to a CM squelch proposal. Preliminary evaluation of earlier test re-
sults indicated that the squelch was not as sensitive as required. Tests showed, how-
ever, that the squelch circuit did not degrade signal performance. These tests
indicated that WI was on t h e o r d e r of 95 percent at squelch threshold and thatWI re-
duced to about 80 p e r c e n t a t 3 decibels below threshold. The squelch action exhibited
a gradual decrease in output noise level with decreasing received signal strength after
squelch operation, rather than exhibiting an instantaneous squelch of noise. The
squelch point had very little hysteresis; that is, the squelch point remained essentially
the same whether approached from strong signal (above threshold) or weak signal
(below threshold). Preliminary evaluation indicated that the squelch is, in general,
acceptable. October 1968 tests on actual CSM squelch circuitry indicated operation as
desired; however, the rf level at which the squelch operated did not appear optimized.
A squelch-disable switch is available, however, to avoid premature loss of the voice
signal.
As a r e s u l t of the previous findings and because of still less than optimum per-
formance during the Apollo 10 mission, a task was initiated in the Audio Techniques
and Evaluation Laboratory to develop modifications that would eliminate or reduce the
undesirable VOGAA operating characteristics. A s a r e s u l t of this task, a 560-hertz
center-frequency (standard telemetry) filter with a 3-decibel band pass of 84 h e r t z was
installed at the input to the detector circuit. Also, the maximum release time of the
VOGAA w a s increased from 750 to 1190 milliseconds.
44
After these modifications were made. the VOGAA was subjected to all of the
tests previously performed on the unmodified VOGAA. These tests indicated that the
modified VOGAA had less word dropouts for speech-to-noise ratios less than 6 deci-
bels, that it was not subject to tones outside its 500- to 600-hertz detector band pass,
and that it minimized the "crashing" effects produced by the VOGAA when i t t r i g g e r s
011 receiver impulse noise.
It should be noted that the band-pass filter caused certain words to be lost if
good-quality laboratory speech was used a s a n input. However, the VOGAA modifica-
tions were designed for optimum performance with Apollo speech. The speech proc-
essing of the Apollo microphones and communications system ensures - based on
power spectral density analysis - that sufficient speech power will be available in the
f i l t e r band pass. In tests, word dropouts were not a problem when MSFN-recorded
Apollo down-link voice was used a s an input. These changes to the VOGAA have not
been implemented 011 the MSFN; however. further development is expected.
Apollo 10 color TV tests (C-21). - A test was accomplished May 9, 1969, in the
ESTL by-iIshgtlie fisTit-coi& TV camera working through the CSM./MSFN system, in-
cluding both the old FM demodulator and the new demodulator. The test was quite suc-
cessful, with no evidence of the clipping of white-level signals which had been evident
on a KSC-MILA test on May 6. 1969. A simulated TV signal (color bar). originating
at the Goldstone 210-foot-diameter antenna station, was observed at MSC on May 13.
1969. and appeared to be satisfactory at approximately the expected signal levels.
SIGNIFICANT RESULTS
A s evidenced by the foregoing. there have been many significant results from the
ESTP in t e r m s of "revelations" regarding system performance. While not wholly unex-
pected based on systems analysis, these results pointed out some deficiencies in prior
theoretical work and. empirically, defined these deficiencies in a quantitative manner,
often providing information for updating system mathematical models. In particular.
the effects of intermodulation. cross modulation, incidental modulation ( A M and P M ) .
and noise-figure constants (and other phenomena and parameters) were determined on
a s y s t e m b a s i s . A s the systems investigated were among the first to utilize coherent
up l i ~ l k sand down links with several modulation components 011 each. the significance
of s o m e of the findings cannot be overemphasized in t e r m s of gaining an understanding
of all the interrelationships involved. For example, the content of the up-link modula-
tion was expected to have some effect on the down link; the full effect was, however,
not apparent until tests were run under various system configurations. A few specific
examples will be discussed in this section. Perhaps of prime significance, however,
i n t e r m s of ESTP results, was the developnlent of a test team and a laboratory which
a r e unexcelled anywhere in the country. This team and laboratory represent a highly
responsive test capability for the resolution of anomalies which develop during count-
downs o r missions. for demonstration (to management, to the mission operations team,
and to the flight crew) of the actual performance to be expected of the communications
system during any mission, and for verification, experimentally. of design modifica-
tions prior to finalization of change decisions. These developments are significant be-
cause, in the process of creating a capability for and an understanding of the state of
the art, the state of t h e a r t of communications testing has been advanced. The
45
techniques and knowledge developed are applicable not only to the Apollo Program and
to future manned space-flight programs, but to any communications system of the
present or future. Because of the extensive effort put into each test to ensure that all
systems performance requirements were met, even results indicating "no problems''
can be considered significant (e. g . , a large amount of data to verify analysis, empiri-
cal data to complement analysis, intimate knowledge of systems capability and limita-
tions, and an extensive store of information on data quality capability). A discussion
of significant results based on t h e s e c r i t e r i a would then, necessarily, be a repeat of
the previous section. Therefore, for purposes of this section, significant results are
defined as those having direct and long-range (lunar mission) effect on overall system
design or those which resolved an immediate problem related to continuance of a count-
down o r a mission. With these criteria in mind, the following discussion presents the
most, not necessarily all, significant results of the ESTP.
While not directly significant to lunar missions under the ground rules established
previously, the detection and resultant correction of the receiver degradation caused by
power amplifier harmonics did allow successful performance of the communications
system during the early development flights which used Block I equipment.
46
f
.i
'
the system. Also, poor emergency-key performance was noted and, as a result, the
detection circuitry for this signal was redesigned at GSFCand was thereby made ac-
ceptable for all operational conditions expected.
47
The theoretical required numbers of word samples and listeners were determined
to achieve an accuracy of at least 90 percent (with 95-percent confidence) for intelligi-
bility ratings. Also, high-quality tape recordings were made by using acoustical isola-
tion for the speaker and balanced audio cabling. Other problems noted were similar to
those detected during CSM Block I and Block I1 tests and were significant in that they
demonstrated the repeatability of the test approach and also the wide applicability of
results to similar systems.
48
! portions of an overall communications system. In addition, the data and resulting anal-
ysis provided more detailed information on the ARIA communications support capability
than had been obtained before o r after these tests. The successful and cooperative
tests were significant in that ARIA communications capabilities and limitations were
defined for the use of all parties involved.
49
Frequency Modulation Demodulator Threshold-Extension
Test (B-4)Results
Besides being significantk t e r m s of long-term inter-Center cooperative effort
to resolve an operational problem and in terms of actual impact on coverage of the
lunar missions, the FM demodulator threshold-extension tests were significant in that
they contributed greatly to extension of the state of the art of FM demodulation. The
click eliminator, a new operational demodulator, and other devices tested in various
states of design finalization are distinct advances for which the ESTP is in p a r t
responsible.
50
Lunar Module Color TV Test (B-9) Results
The extensive, and often hectic, series of tests of the LM color TV provided
management with quantitative and timely information enzbling the decision to include
color TV on the LM f o r Apollo 12. All possible contingencies were tested andall
doubts and objections overcome by the thorough evaluation of the color TV signal ef-
f e c t s on the LM down-link FM communications channel.
51
PLANS
While these activities are expected to consume the major portion of available test
time for the remainder of calendar year 1970 (and perhaps beyond, depending on devel-
opments of the Apollo Program), a serious effort is underway to evaluate the experi-
ences and the operations of the ESTP during the past 6 y e a r s . In particular, during the
ACS phase 111 t e s t s , a concurrent study has been in process to compare measured and
predicted data by using probability and statistical techniques to try to understand in de-
tail the effects of various instrument inaccuracies and human errors on the end results
of the tests. On a limited basis, this had been done very early in the test program but
only t o the extent necessary to assure the test personnel that nothing was grossly wrong
with the test configurations and that reasonable caution in test setupwould assure mean-
ingful results. This study is also envisioned as the basis f o r a much more extensive
review of test techniques, performance criteria, and specification criteria.
52
specifications become more complex, which in turn increases the complexity of the
testing required to verify the hardware against requirements. Meanwhile, as discussed
previously, the existing specification criteria, such as WI and BER as a function of
signal-to-noise ratio, and so forth, are inadequate to fully define system performance.
Also, the test methods available remain limited to one channelat a time, one signal-
to-noise ratio at a time, and so forth, with all other variables held constant (a very
time-consuming method). An effort to improve the performance criteria as well as the
techniques for measuring the p a r a m e t e r s a s s o c i a t e d with these criteria will beof g r e a t
value to all future communications systems in that an accurate and rapid determination
of requirements and actual performance could be achieved early in the development
phases of t h e s e s y s t e m s , at a minimum cost in time and dollars.
The first phase of the effort will be a study directed toward the refinement or
development (or both) of communications systems performance criteria that are both
significant and reasonable. Samples of ACS performance criteria; of basic require-
ments for future communications systems; of test plans, procedures, data packages,
and reports; and of ESTL accuracy study reports now in preparation will be used.
Communications and measurement theory will be applied, and measurement technique
developments, including availability of new instruments, will be investigated to arrive
a t a s e t of realistic communications systems criteria coveringall phases of telecom-
munications systems performance that can easily, accurately, and economically be
measured in the ESTL and associated laboratories.
The second phase of the effort will be a study making use of the phase I r e s u l t s
to develop a plan for upgrading the ESTL to accurately measure the performance cri-
t e r i a p a r a m e t e r s d e t e r m i n e d f r o m p h a s e I. This plan will include alternate methods
of automating the testing wherever practicable by making use of limited programable
devices, including any existing o r adaptable equipment available at the time. New
measurement hardware development may be indicated. The study will also include
evaluation of the approach of using a "universal breadboard'' communications system,
comprised of commercially available hardware and existing spacecraft hardware, for
the purpose of concept and design verification testing of advanced communications sys-
tems prior to availability of flight breadboards. If the evaluation is favorable, compo-
nents to assemble such a breadboard, based on minimum new buys for each new s y s t e m
proposed, will be recommended.
The third phase of the effort will be dependent on the results of phases I and I1
and will be concerned with implementing the results of phase II.
This phase will con-
sist of an in-house effort to assemble and integrate existing equipment and commer-
cially available hardware according to the resultsof phase I and the plan developed in
phase II. Development of new instruments, if any, recommended by phase I1 r e s u l t s
will be contracted out and integrated into the appropriate laboratories as an in-house
effort. A final phase, to demonstrate on a s y s t e m s basis the results of phases I, 11,
and I€I, will complete this effort.
53
5
In summary, the ultimate end product of the effort is the ability to make the best
measurements as easily, quickly, and economically as possible with concurrent accu-
racy and repeatability. Phases' I and II will have comprehensive study reports as prod-
ucts. Phase I11 will have as its end product a test laboratory equipped to implement the
r e s u l t s of this effort. Phase IV will work out imperfections and prove the concepts de-
veloped. Figure 7 shows a preliminary schedule for the planned effort.
CONCLUD I NG REMARKS
The Electronic Systems Test Program has contributed significantly to the devel-
opment, implementation, and operation of the Apollo communications system. In addi-
tion to the achievement of a high confidence level in systems performance prior to the
first manned lunar landing, the test program has effected many cost savings in that
early detection of problems requiring hardware changes, including determination of the
scope of these changes and the optimum point in the system to effect them, has been
achieved and verified. A unique but flexible test concept and capability has been devel-
oped where none existed previously. Test techniques and methods have been derived
and implemented. Improvements in these concepts and techniques, based on experience
with the Apollo P r o g r a m , are now being investigated. The Electronic Systems Test
Program concept, along with the associated facilities, personnel, and techniques, is
considered a success. This program stands ready to support the remaining Apollo
Program missions as required and can easily adapt to the supportof future space-flight
programs, manned or unmanned.
54
APPENDIX A
TEST PROGRAM OPERATIONS
The procedure and the sequence of operations for test p r o g r a m s and clarification
of areas of support generally required to accomplish test objectives are briefly dis-
cussed herein.
I!
I
I
I
paragraphs. I'
I Testplan
Channel I
"
I
II final review test
gredictions meeting
I
I
I
I' I
""""""""""
2=""""- 1
usuallyheld at MSC. Participants in this 1 ! ,
review are representatives of MSC, ap-
propriaterepresentatives of otheragen- I
I-H H I
I ,
II Final reporl su: ; ; ; ;
I
The purposes of this review are to discuss
in detail the planned tests and to ensure Figure A-1. - Test program operations
that all the test requirements necessary to flow chart.
achieve the primary objectives of the test
program are adequately identified in the
test plan.
TEST PROCEDURES
The formal test procedures are provided by TCSD through an MSC laboratory-
contractor effort. Test procedures can be modified at any time during the test program;
however, all changes in the scope of the testing must be approved by the MSC Test
Director.
Channel performance predictions are provided by TCSD. The test predictions are
based on measured systems parameters, except in cases w h e r e m e a s u r e d p a r a m e t e r s
are not available. Specified parameters will be used in these cases.
55
Ill 1111 I1111111
TEST OPERATIONS
The test operation requires participation of TCSD and appropriate MSC laboratory
and manufacturing contractor personnel. Manufacturing contractor participation con-
sists of the following:
1. Systems engineer (provide quick response to contractor management for prob-
lem resolution and quick response from contractor engineering relative to design and
test changes)
2. Test engineer (participate in detailed test planning and conduction)
During the test program, a coordination meeting is held at the ESCF at 8:45 a.m.
each working day. The purpose of this meeting is to discuss the test results of the
previous day, tests planned for the current day, test procedure modifications, and any
problems associated with the test program operation.
DATA PACKAGEREVIEW
Approximately 10 working days after completion of the tests, the laboratory con-
tractor provides, at a review meeting, copies of all raw and reduced data along with an
updated test procedure.
Interim test reports covering all t e s t r e s u l t s are prepared by the laboratory con-
tractor and submitted to TCSD. These documents are given limited distribution approx-
imately 30 working days after completion of the test program.
56
APPENDIX B
TELEMETRY AND COMMUNICATIONS SYSTEMS DIVISION,
COMMUNICATIONS SYSTEMS ENGINEERING AND TEST BRANCH LABORATORY,
ESTP SUPPORT CAPABILITY
The following is a brief summary of the laboratory capability available from the
ESTP.
57
TABLE B-I. - ESTL GROUND EQUIPMENT - Continued
__-
Equipment Designation Remarks
58
TABLE B-I. - ESTL GROUND EQUIPMENT - Concluded
I
I"-~~-
Equipment Designation
~-
Remarks
b. Status:TheESTLisopera-
ESCL TEST REPIJEST
............
tional.
c.SupportRequests:TheESCL
Test Request (MSC F o r m 745, dated
April 1971) is used to request support.
See figure B- 1.
2. Audio TechniquesandEvaluation
Laboratory
...........
a. Capability:
7-he
laboratory
is capable of analysis of voice tapes -.....,
......................................
(speech- to-noise ratio? spectrum), limited
tape dubbing, preparation of audio tapes,
audio tape library, and testing/analysiF
of audio circuits/components/systems.
This includes the capability of discrimina-
.......................................................................................
tion of Apollo USB voice subcarriers and
limited TV testing/analysis capability. .......................................................
.,IY<,I
b. Status:Thelaboratory is
qerational.
59
c. Support Requests: The ESCL Test Request (fig. B-1) is used to request
support.
3. CommunicationsSystemsEngineeringLaboratory
b.Status:Thelaboratory is operational.
c. Support Requests: The ESCL Test Request (fig. B-1) is used to request
support .