FORM CP-1 SERIAL NO.

Ex/ Conc/ 092

UPPER KOTMALE HYDROPOWER PROJECT Kotmale Switchyard Expansion Works


APPLICATION
FOR
COMMENCEMENT OF CONCRETE PLACEMENT
Fill out first by the Contractor as per clauses 11.3.8 and 12.3.6 in Technical specifications
Working Area Concrete Volume Expected Job Start Pour
Location Block No. Lift No. Class (m3) Date Time
kothmale Expansiton F08b, F03a,
S/Y (phase -02) F05a
- B 6.252 03/12/2010 11.00

detail of Section / Area of placement :


* In case of tunnel works, entry station nos: Base concrete - Equipment foundation F08b, F03a, F05a (phase-02 /Bay-06)

Site Preparation shall be checked by the Contractor in advance and counter checked by the Engineer. Accepted Not applicable Not accepted

CHECK ITEM Contractor Engineer CHECK ITEM Contractor Engineer


A. ROCK SURFACE E. REINFORCEMENT BAR
1 Geological conditions and mapping - 1 Diameters O
2 Surface trimming and scaling - 2 Pitches O
3 Dewatering condition - 3 Splicings O
4 Surface cleaning and moistening - 4 Stiffening O
B. LIFT SURFACE 5 Spacers & min. concrete coverage O
1 Green-cutting (Removal of laitance) - 6 Cleaning condition O
2 Crack (Report to the Engineer if any.) - 7 Quality of re-bars: rust, etc. O
3 Loose surface to be removed - F. ITEMS TO BE EMBEDDED (Q'ty, Location, Type, Stiffening)
4 Dewatering conditions - 1 Water stop -
5 Cleaning and moistening conditions - 2 Grout pipes -
C. STRUCTURAL JOINTS 3 Other pipes -
1 Joint coating quality - 4 Cables, Grounging wires, etc. -
2 Setting and quality of joint filler - 5 Anchor metals -
3 Cleaning condition - G. EQUIPMENT & TOOLS (Condition, Capacity, Q'ty, etc.)
D. FORM WORK / SETTING-OUT 1 Stock: cement and aggregates
1 Setting levels and dimensions O 2 Batching plant preparation
2 Quality of form materials O 3 Transportation equipment
3 Form stability and deformation O 4 Crane / Backhoe / Concrete bucket
4 Blockouts: Location, dimension, etc. O 5 Concrete pump or placer, pipelines
5 Support and stiffening condition O 6 Concrete chuteway, if permitted
6 Form oil sheathing and quality O 7 Vibrator including stand-by units
7 Cleaning conditoon O 8 Hand shovel, buckets, etc.
9 Tools for spot drain
10 Tools for green cutting
11 Curing water and mats
12 Stand-by generator
13 Concrete molds and slump cone

Engineer's Comment

FOR COMMENCEMENT OF CONCRETE PLACEMENT


Requested by the Contractor Approved by the Engineer

Name: Ruwan perera Name:

Signature: Date: 02-Dec-10 Signature: Date: