Professional Documents
Culture Documents
All installed medium voltage cables 2000 volts and above including
stress cones and splices shall successfully pass the following field acceptance test. Field
acceptance testing of cables must be done before cables are energized to ensure that no damage
has occurred during installation and that the cables are satisfactory for operation. Two types of
tests must be performed: "Insulation Resistance (Megger) tests" and "High D.C. Potential
(Hi-Pot) tests".
(b) 100 KV Dielector D.C. test set with test cables, safety barriers, etc.
(Biddle “Dielectric Test Set” Catalog No. 221100, 2-50 KV modules or equal)
(g) Test report sheets (Biddle "Dielectric Absorption Test Data Report"
sheets No. 951-3 for power cable, or equal)
Page 6 of 16
AGE-6 (11/03)
b) Post "Danger" High Voltage signs at each end of cable run and
have a man stationed at exposed connections.
e) After test and before turning cables over to workmen, ground all
cables for at least one hour to drain off all residual energy.
f) Start the "megger" and record the resistance readings at the end
of two minutes. If a reading is just above a definite scale value, record the
reading as that value "plus" (+) megohms.
Page 7 of 16
AGE-6 (11/03)
j) Caution. After all three phases have been tested, ground all three
conductors for at least one hour to drain all energy obtained from the test
instrument.
Each cable shall be tested between conductor and ground and between
other conductors in same conduit or duct. Cable shield must be connected to the same ground.
Refer to Figure B for typical connections.
(15-Minute Test)
NOTE: Maximum proof test voltage for non-shielded medium voltage cable shall not
exceed 3 times the cables rated insulation level. (5KV cable shall be tested to 15KV.)
Page 8 of 16
AGE-6 (11/03)
The high voltage terminal of the test set shall be connected to the conductor of
one phase. The return terminal shall be connected to the insulation shielding of that phase and
also to the conductors of the other two phases. Connect the ground terminal of the test set and
the insulation shielding of the other two phases to the switchgear or substation ground bus. To
eliminate leakage during test, a polyethylene bag may be placed over each end (terminal lug) of
the conductor being tested. First fill the bag with air by waving it in the air, then place over the
cable lug or conductor. The bag should not touch lug or conductor. The end of bag is then
taped securely to the insulation.
Page 9 of 16
AGE-6 (11/03)
h) After voltage is decreased to zero, the test set is turned off and
the cable shall be discharged through the test set discharge resistor.
Page 10 of 16