Professional Documents
Culture Documents
MANAGEMENT
Topic : Diagnosis of KESC
Faculty: Maryam Siyal
Program: BBA(H)
Course: Principles of management
• History of KESC
• Who they are?
• What they do?
• KESC’s vision.
• Strategic planning.
• Turnaround strategy.
• Working environment.
members.
• Problems faced by KESC.
generation capacity.
• Sources and links.
KARACHI ELECTRIC
SUPPLY COMPANY
HISTORY OF KESC
KESC is one of the oldest companies in Karachi and was established in
the city even before the creation of Pakistan in 1947. Incorporated on
September 13, 1913, under the Indian Companies Act of 1882, the
company was nationalized in 1952 but was re-privatized on November
29, 2005. KESC came under new management in September, 2008; a
significant number of professional managers with experience in
running utility and other large companies have joined under this
management and will be running it until the company is turned into a
best practice utility.
WHAT THEY DO
They currently provide electricity to over 2.1million consumers, not
only in Karachi but also in the towns of Dhabeji and Gharo in the
province of Sindh and Hub, Uthal, Vindhar and Bela in the adjacent
province of Baluchistan.
KESC’s VISSION
Our vision is to be a value-driven and service integrated company,
with innovative ideas, where the core set of values is shared amongst
everyone.
• Thought Leadership
• Knowledge Based Learning
• Values
• Social Responsibility
STRATEGIC PLANNING
Strategic plan with implementation mechanism was
prepared for rehabilitation of out dated and
dilapidated transmission and distribution network
which has been under execution in a phased and
prioritised manner.
A number of critically important projects have been commissioned or
are in the final stage of completion, which has improved network
reliability and increased transmission & distribution capacity.
Establishment of a computerized system for management of
generation, transmission and distribution known as SCADA is being
executed as one of the prioritized projects. The commissioning of this
critically important project would significantly improve efficiency of
power system control & monitoring, facilitate timely operational
decisions & economic dispatch of power and would minimise outages
and technical losses.
Turnaround Strategy
The new owners, in partnership with KESC management and Siemens,
have come up with a three-tier turnaround strategy:
Dist Capacity
4328 MVA
FACTS & FIGURES
KESC is an integrated power utility with exclusive franchise rights to
serve Karachi and its surrounding areas, with a licensed network area
spanning 6,000 square kilometers.
Employees: Around 17,000(52% permanent, 48% contract, 89% staff, 11% officers)
Key Status Overview Key Status Overview
Grid Stations 59 • Transmits Transformers • Distributes
electricity electricity to 2
Transformers from Pole 13,414 million
generation to mounted customers.
220 KV/ 132 12 distribution at Feeders 1,020
KV high voltage. • Bulk
132 KV/ 11 105 Power Lines customers get
KV • Only 11 supply from
Total 117 customers on 11 KV 7,096 km 11 KV lines.
the
Power Lines 0.4 KV 11,718 km
transmission • All other
network. consumer has
12 220 KV 223 connections
Lines km • Grid stations from the 0.4
56 x 132 KV 617 step-down KV circuit.
km electricity.
5 x 66 KV 149
km
Total 989 Total 18,814
km
KESC
ORGANIZATION STRUCTURE
KESC Board of Directors
Chief Executive
Generation
Chief Legal Adviser IT Department Head
Transmission
• There is a simple connection of kunda and there are also planned connections.
• Media presents just the consumers problems and does not show problems faced
by them
• Their biggest threats are the kunda system and the public.
• Those employees that are not corrupt are very sincere in their work showing up
for work during severe load shedding days though they know that their building
can be attacked by angry mob.
2. Capacity Addition:
Capacity addition of 780 MW through two new combined-cycle power
generation plants is planned under this component. The plants will
have a dependable capacity of approximately 745 MW. The first plant
of 220 MW will be built on surplus land within the boundary of Korangi
Thermal Power Station and will cost PRs11.0 billion ($174 million).
• http://www.kesc.com.pk/en
• http://docs.google.com/gview?
a=v&q=cache:_Vdfkg0C0lsJ:www.adb.
org/Documents/RRPs/PAK/40943-PAK-
RRP.pdf+KESC+mission+statement&hl
=en&gl=pk&pid=bl&srcid=ADGEEShuJ
kRiPhq-
szu718ZTeIl6KwewFfkj50TiPpxHANTNI
4nlTIltmkuu7z5_izEfSJlXLZvz33nR3RS
VzIMTj-poa-
QkcthPApnkTiOZfdJGhoM2uWfKDudgU
e_wFpt6QLdCvYZ2&sig=AFQjCNEbUCti
hyWo-gM9-dyaTzA1bMf4hg.