Professional Documents
Culture Documents
GUE S. S.
Gue & Partners Sdn. Bhd., Malaysia
ABSTRACT: Soil nailing is an in-situ ground improvement method which has gained increasing
acceptance in this region, but is not generally recommended for clayey and organic soils. This restriction
is empirically based, and little information exists on the performance of soil nails when the method is
applied in these soil conditions. To address this gap, a deep excavation for the construction of a 3/12
storey deep basement carried out using a novel technique, which combines Contiguous Bored Piles and
Jack-in pipe reinforcements, was instrumented to monitor its performance. This paper will highlight
briefly the instrumentation program, which was set up mainly as a safety control and to monitor the
interaction of this retaining system with the surrounding soft soil. In addition, numerical analyses were
conducted to study the soil-structure interaction of this new construction technique. Data from the field
monitoring and FEM analyses will be presented with regard to the effectiveness this system particularly
the jacked-in pipes in supporting the deep excavation. It follows from this comparison that the field
instrumentation and numerical analyses have proved to be valuable tools in assessing the deformations to
be expected at critical stages of the excavation. The project shows that jacked-in pipe in soft clayey soils
is possible, at least for short term and can be effectively used as temporary support in deep excavation.
1.0 INTRODUCTION soil nailing partly stems from the Reinforced Earth
techniques, rock bolting and multi-anchorages
Deep basement construction is becoming systems (Recommendations Clouterre 1993). Soil
increasingly expensive, nullifying the justification nailing has been primarily used for temporary
for overconservative designs. One of the ways in retaining structures for basement excavation and
which construction cost can be reduced is by permanent cut-slope stabilisation. Jacked-in pipe
employing fast and cost-effective deep basement retaining system, which is similar to soil nailed
construction techniques. This paper will highlight system is not common. This technique has gained
the use of Jacked-in Pipe Reinforcement in support momentum in Malaysia mainly for the ease and
of Contiguous Bored Pile walls. speed of installation and it is also very cost
The field instrumentation has proven to be a effective.
valuable tool in assessing the validity of the initial However, with the advent of numerous research
design assumptions The Observational method programs (Schlosser, 1986; Elias and Juran, 1990),
(Peck, 1969) was practised whereby field results increase in the state-of-understanding and
obtained from the adequately instrumented soil experience, both abroad (Schlosser, 1982;Bruce
nailed retaining system were used in the back and Jewell, 1986, Bruce and Jewell 1987, Juran et
analysis of design parameters. The back calculated al., 1990;) and local (Tan, et al., 1998; Luo et al.,
parameters were implemented in the Finite 1998; Tan et al., 1999) will promote the use of this
Element Analyses to predict deformations in the technique, both as a temporary and permanent
subsequent construction phases. structure.
Soil nailing is an in-situ soil reinforcement
technique, which in the last three decades has been 2.0 DESCRIPTION OF PROJECT
successfully used in France, United Kingdom, The condominium project which is located at UEP
United States and Southeast Asia. The origins of Subang Jaya of Malaysia consists of three
1
condominium towers of 33 storey and a single 20
SPT 'N' VS DEPTH ( m ) PLOT
storey office tower. Due to the huge demand for 0 10 20
'N'
30 40 50 60
0
parking space, an approximately three storey deep SPT 'N' GREATER THAN 50
DEPTH ( m )
condition and the fast track requirement of the 20
BH / DA 7 BH / DA 8 BH / DA 10 BH / DA 6
BH / DA 11 BH / DA 2 BH / DA 3 BH / DA 4
BH / DA 5 BH / DA 9 BH / DA 12 BH / DA 13
BH / DA 14 BH / DA 1
Firm Reddish
0
5
0
Firm Reddish
0
9
underlain soft clayey material, the registered SPT
Brown Yellowish
Final Water
Table 5
clayey SILT 7 Final Water
Table
5
Brown Yellowish
clayey SILT
Loose to Medium
2 ‘N’ values were zero and Vane Shear strength
5.8mbgl 8 5 4
10
to Coarse SAND
0
10
4.8
11.8
10 0
7
0
6.8
36 Very Soft Dark
Grey Silty CLAY
1
0
layers, namely Granular material and Cohesive
Very Soft Dark 40.5 with Fine Sand
15
Grey Silty CLAY
with Fine Sand 15
0
15
21.5
30.5 15
and decay roots
15
0 material.
0 0
and decay roots 20
31
0 0
31
20
Very Soft Grey
Silty Clayey Fine 20
0
3 20 20
Very Soft Grey
Silty Clayey Fine 20
6
9
4.0 THE JACKED-IN PIPES AND
SAND
Medium Dense
Grey Fine to
18
20
SAND
Medium Dense
15
13
CONTIGUOUS BORED PILE SYSTEM
Coarse Grey Fine to
27 14
25 SAND 25 25 25 Coarse 25
Very Stiff to SAND
Hard Whitish
Grey Brown
29
50
16
38
Jacked-in Pipes Reinforcement
30
Clayey SILT
30
50
50 30 30
Very Stiff to
Hard Whitish 30
47
44
Mild steel pipes which functions as soil nails are
Grey Brown
End of B/H Clayey SILT 37
installed by hydraulic jacking. This method has
39
35 35 35 35
Very Dense
Whitish Grey 35 40 proven to be an efficient and effective technique
Brown Fine
to Coarse SAND
End of Borehole 50
for excavation support, where conventional soil
40 40 40 40 40 nails and ground anchors have little success in such
Typical Subsoil Profile
difficult soft soil conditions. Such conditions are
sandy collapsible soil, high water table and in very
soft clayey soils where there is a lack of short-term
Fig. 1:Typical Subsoil Profile pullout resistance.
2
In view of the close proximity of commercial of this paper, construction has only reached the 4th
buildings to the deep excavation, a very stiff level of excavation):
retaining system is required to ensure minimal
ground movements the retained side of the Stage 0 Installation of Contiguous Bored Pile
excavation. Contiguous Bored Piles which acts as Wall
Stage 1 Excavation 1: Excavation to 2.7m below
an earth retaining wall during the excavation works
ground level
were installed along the perimeter of the Stage 2 Jacked-in pipe: Level 1 at 1.7m below ground
excavation and supported by Jack-in pipes. level.
In the initial design of the retaining system, Stage 3 Excavation 2. Excavation to 4.5m below
conventional ground anchors were proposed, but ground level.
the jacked-in pipes were accepted as an alternative Stage 4 Jacked-in pipe: Level 2 at 3.5m below ground
level.
to ground anchors due to speed and cost-
Stage 5 Excavation 3: Excavation to 6m below ground
effectiveness of the system. Relatively, larger level.
movements are required to mobilised the tensile Stage 6 Jacked-in pipe: Level 3 at 5m below ground
and passive resistance of the jacked-in pipes when level
compared to ground anchors. However it was Stage 7 Excavation 4: Excavation to 7.5m below
anticipated that the ground settlement at the ground level
retained side and maximum lateral displacement of Stage 8 Jacked-in pipe: Level 4 at 6.5m below ground
level
the wall using this system would still be within the
required tolerance after engineering assessment.
6.0 GEOTECHNICAL INSTRUMENTATION
INSTALLATION OF SOIL NAILS
In view of this relatively new excavation support
technique, in-situ soft soil conditions and the close
proximity of the commercial buildings to the deep
excavation, a performance monitoring program
was provided. Firstly, as a safety control. Second,
TEMPORARY BOLT
to refine the numerical analysis using field
CONTIGUOUS BORED PILE WALL
measurements obtained at the early stages of
JACKING PLATFORM
construction and third, to provide an insight into
SOIL NAIL (1 5 0 m m
the possible working mechanisms of the system.
D I A M E T E R S T E E L T U B E)
The geotechnical instrumentation program
HYDRAULIC JACK consists of 18 vertical inclinometer tubes located
REACTION PLATE
strategically along the perimeter of the Contiguous
Bored Pile wall and 30 optical survey makers
(surface settlement points) near the vicinity of the
commercial buildings. This instrumentation would
RIG NO.1 RIG NO.2 provide sufficient readings to monitor the
Fig. 3: Schematic of Jack-in Soil Nails performance of the excavation system.
The locations of these instruments are detailed
5.0 SEQUENCE OF CONSTRUCTION in Fig. 4 for the inclinometers and Fig. 5 for the
optical survey points. Vertical inclinometer
The layout of Contiguous Bored Pile retaining wall readings were taken once weekly and the surface
as detailed in Fig. 3 forms the basement wall of the settlement readings were taken once every two
substructure. The retaining wall system consists of weeks. However when critical stages were
closely spaced 1000mm diameter bored piles near involved, the frequency of the readings was
the commercial buildings and 800mm diameter for increased both as a safety control and to provide
area away from the commercial buildings. To sufficient field data for numerical modelling.
facilitate the Top-Down excavation of the deep Fig. 6 illustrates the trend of horizontal
basement, roller pipes of 150mm diameter were displacement of the wall as measured through
jacked in sub-horizontally after each excavation inclinometers installed at the site.
stage. The phases of the basement construction are
described as follows (currently during the writing
3
1 2 3 4 5 6 7
1
8
PROPOSED UNDERGROUND CARPARK
18
9
CONTIGUOUS BORED PILE WALLS
17 16 15 10
14
13 11
VERTICAL INCLINOMETERS
12
30 30 30
30
- INCLINOMETER 2 - - INCLINOMETER 8 - -INCLINOMETER 9- - INCLINOMETER 10 -
25 25 25 25
20 20 20
20
Depth (m)
15
15 15 15
10
10 10 10
5
5 5
5
0
-0.02 0 0.02 0.04 0.06 0.08 0 0
-0.02 0 0.02 0.04 0.06 0.08
0
0 0.02 0.04 0.06 0.08 0.1 0 0.02 0.04 0.06 0.08 0.1
Horizontal Displacement (m) Horizontal Displacement (m)
Horizontal Displacement (m) Horizontal Displacement (m)
30 30 30
30
-INCLINOMETER 11- -INCLINOMETER 12- -INCLINOMETER 15-
INCLINOMETER -16
25 25 25 25
20 20 20 20
15 15 15 15
10 10 10 10
AFTER STAGE
6(NAIL LEVEL
5 3,5m BGL) 5 5 5
AFTER STAGE
5(EXCAVATION
NO.3,6mBGL)
AFTER STAGE
7(EXCAVATION
0 NO 4,7.5mBGL) 0 0 0
0 0.02 0.04 0.06 0.08 0.1 0 0.02 0.04 0.06 0.08 0.1 0 0.02 0.04 0.06 0.08 0.1 -0.08 -0.06 -0.04 -0.02 0
Horizontal Displacement (m) Horizontal Displacement (m) Horizontal Displacement (m) Horizontal Displacement (m)
Fig. 6: Measured Horizontal Displacements of Contiguous Bored Pile Walls supported by Jacked-in Soil Nails
4
COMMERCIAL BUILDINGS
3
2
3
2
Design methods recommended at the present time is
3
2
3
2
3
2
RETAINED SIDE
1 1
still based on classical limit equilibrium methods,
1 1 1
EXCAVATED SIDE
which only evaluate the stability of the structure.
ROW E ROW D
However when constructing deep excavations in
ROW C ROW B ROW A
Fig. 5: Layout of Settlement Markers 3-D numerical problem. This can be seen from the
results of the instrumentation as indicated in Fig. 6
where deformations are restrained at the corners due
to edge effect (inclinometer 8) and the maximum
occurring approximately at the centre of the wall
(Inclinometer 9 & 10).
Due to the complex soil-pipe, soil-wall and pipe-
wall interaction, a global soil arch will be formed
(Schlosser et al., 1997;Benhamida et al, 1997). In
addition to this, local arching will develop between
the pipes, and therefore creating concentration of
stresses. With good engineering judgement and
SURFACE SETTLEMENT OF RETAINED GROUND
A. 3-DIMENSIONAL PLOT & B.CONTOUR PLOT
Fig. 7: Variation of vertical settlement from field practise a 3-D problem can still be effectively
performance modelled as a 2-D plane strain problem. The
PLANE STRAIN ANALYSIS CONDITION
numerical analyses were performed using “Plaxis”
(Brinkgreve and Vermeer, 1998) a Finite Element
Method computer program under plain strain
condition (Fig. 8). The Contiguous Bored Pile wall
and hollow steel pipes were modelled using a linear
elastic model and its material properties converted
to the equivalent 2D parameters through area ratio
factors (Al-Hussaini & Johnson, 1978). The model
pipes were elastic and pinned to the Contiguous
Bored Pile wall. An elastic -perfectly plastic model
Fig. 8: Plane Strain Analysis (Plaxis V 7.11) was used to model the behaviour of the soil-pipe
Stiffness G vs Working Strain interface. The model, which uses the Coulomb
criteria, distinguishes between the elastic behaviour,
where small displacements can occur within the
TYPICAL STRAIN RANGES
FOUNDATIONS
Shear Strain %
0.1 1 10
5
stiffness obtained from these tests is several
magnitudes lower than the in-situ soil stiffness.
HORIZONTAL DISPLACEMENT : NUMERICAL MODELLING
AND MEASURED The undrained soil modulus for the Soft Peaty
Excavation Lvl 3
Clays were assumed to be Eu = 700 Su (Gue,
105 1997(b); Gue, 1998) for all stages of excavation.
The soil modulus for the fill soils (Sands) were
Lo?se Sandy SILT
Excavation Lvl 1
100
assumed to be E’ = 3500N based on Stroud and
Excavation Lvl 2 Butler (1975), where the N Standard Penetration
Excavation Lvl 3 95
Loose Silty
SAND
Test Value. For the Clayey Silt, Eu = 700 Su and Su
Dark Soft 90 = 5.5N was adopted. In addition to this, the soil is
DEPTH (m)
SILT
Excavate Lvl 1
Excavate Lvl 2
have influenced the predicted deformation profile,
Exacavte Lvl 3
Excavate Lvl 4
95
notably small strain behaviour, where at very small
Loose Silty SAND
CLAY
Final Excavation Level (Jardine et al 1985; Burland, 1989) and therefore the
85 soil tends to deform less.
Medium Dense
Grey Fine -
80
Coarse SAND
An analysis was performed without the nail
Very Stiff-Hard Brownish SILT
75
inclusions, where the retaining wall was modelled as
a cantilever wall. Fig. 11 compares the deflection
-0.1 -0.08 -0.06 -0.04 -0.02
70
0 0.02 0.04 0.06 0.08 0.1
profile between the cantilevered wall and
HORIZONTAL DISPLACEMENT ( m)
‘improved’ wall at 7.5m deep of excavation. It
Inclinometer 21/6/99 Excavate-4 Nail-3 shows a distinct restraint offered by the jacked-in
pipe inclusions. The influences of pipe bending on
the reinforcement mechanism and has been a subject
of great debating (Bridle & Barr, 1990; Jewell &
Pedley; 1990; Schlosser, 1991; Jewell & Pedley,
Fig. 10b 1991). Fig. 12 compares the deflection profile of
retaining wall where the jacked-in pipes were
Fig. 10: Measured Field Performance and Finite modelled using;
Element Analysis for; a) Nail Level 2 & Excavation
Level 3, b) Nail Level 3 & Excavation Level 4
6
(geotextile element in Plaxis) with only the axial
HORIZONTAL DISPLACEMENT OF CONTIGUOUS BORED
stiffness. Fig. 12 shows that bending stiffness has an
PILE WALL WITH AND WITHOUT SOIL NAIL INCLUSIONS influence in the reinforcement mechanism, where
105
jacked-in pipes modelled using the beam elements
show a smaller displacement compared to the
100
geotextile elements in all of the numerical stages. A
large-scale experimentation in soft clays conducted
95
by Oral et al (1998) has indicated that due to lack of
nail-pullout, nail bending played a major role in the
90
reinforcement mechanism. A similar behaviour was
DEPTH (m)
-0.01
-0.02
-0.03
Finite Element Analysis
100 Measured -0.04
-0.05
-45 -35 -25 -15 -5
Distance from Wall (Retained Side) m
95
Fig. 13: Surface Settlement: Measured Field
Performance and Prediction from Finite Element
Depth of wall (m)
90 Analysis
85
8.0 CONCLUSION