Professional Documents
Culture Documents
In determining whether to accept or Finally, recall that NPV figures calculated for projects with
different lives are not comparable and, therefore, we need to
reject a particular project using NPV restate the NPVs of the two alternatives in a way that will allow
analysis, we apply the NPV decision direct comparison. We learnt in FINM1001 that one way to do
this is to compare the equivalent annual values (“EAV”) of the
rule. This rule can be summarized as two projects, calculated as below, and the decision rule is to
follows: accept the project with the highest EAV (NB: In FINM1001, we
called this the annual equivalent approach, however, to ensure
{Accept a project if its NPV>0; consistency with the FINM2001 textbook, we will herein refer
to it as EAV).
{Reject a project if its NPV<0; and,
NPV
{Indifferent to a project if NPV=0. EAV =
1 − (1 + k ) − n
k
{The potential that projects will have working capital Where te = tc(1-γ) and γ is the proportion of the tax collected from a
requirements. company that is paid out to shareholders and recovered through tax
credits associated with franked dividends. Further, given the
importance of consistency, we would use a post effective tax discount
We will now consider each of these in turn, and rate in calculating the NPV of these cash flows, the calculation of which
subsequently illustrate how they are accounted for we will consider in Lecture 8 (NB: In the interim, you will be given these
discount rates).
by way of an example.
Example I Example II
The use of different methods of calculating depreciation
and working capital is best evidenced by way of an Based on the preceding information:
example. Suppose Bettman Limited, which operates in a {Depreciation p.a. = $1 million * 7.5% = $75,000;
classical tax system, is considering the introduction of a {Post-tax net cash flows = $400,000(1-0.40) + $75,000 *
new project and has asked you whether they should 0.40 = $270,000 p.a.;
proceed. Information is as follows: {Calculate gain / loss on sale of equipment after 10
{ Initial cost of capital equipment is $1 million; years:
{ The equipment has an expected economic life of 10 years; z Book value of machine at end of life = $1,000,000 –
{ Annual net cash flows before tax are $400,000; $75,000 * 10 = $250,000;
{ The tax allowable depreciation rate is 7.5% prime cost; z Salvage value = $100,000; and,
z Therefore, loss on sale = $250,000 – $100,000 =
{ The working capital requirement is $200,000; $150,000.
{ Salvage value of equipment is $100,000;
{Tax deduction on loss on sale = 0.40 * $150,000 =
{ The post-tax required rate of return is 8% p.a.; and, $60,000
{ The tax rate is 40%.
IRR = 0.04
= 4% This project has multiple IRRs, as discount rates of 2% and
3% will both make the NPV equal to zero.
If all variables are correctly specified, the There are numerous methods that can be
present value of any future cash flow must be employed in assessing the viability of projects.
However, the NPV method is recommended for
the same under both the risk-adjusted discount investment evaluation as it is not only consistent
rate method or the certainty-equivalent method, with the goal of maximising shareholder wealth,
and therefore: but also has fewer problems than approaches
such as IRR.
E (Ct ) α t E (Ct )
=
(1 + k )t (1 + R f )t Further, in practice, other valuation methods such
(1 + R f )t as the accounting rate of return, payback period
∴α t = and economic value added are used in conjunction
(1 + k )t
with NPV.
Next Lecture….
Given the strength of NPV, we now focus on it and its use
in making complex investment decisions, covering:
{ The principles employed in estimating project cash flows;
{ How to choose between mutually exclusive projects with
different lives. In doing this, we will introduce new methods of
adjusting for life differences not considered in FINM1001,
namely the lowest common multiple method and the constant
chain of replacement in perpetuity method;
{ How to determine when to retire (abandon) or replace
equipment;
{ How to employ sensitivity analysis and break-even analysis to
analyze project risk; and,
{ The role of qualitative factors and resource constraints on project
selection.