You are on page 1of 2

SPEC F025

January, 2010

DC “HI-POT” Testing Guidelines for MV Cable

DC High Potential (HI-POT) Testing of Medium-Voltage Power Cable

Overview Before performing any DC Hi-Pot Testing Procedures


This procedure is intended to provide over­potential tests: Normally this requires only a few
general guidelines for high potential • All equipment must be discon- seconds unless cable circuits of
DC testing of power cables. nected from the cable circuit, i.e., high capacitance are involved.
taps, motors, circuit breakers, Record leakage current at each
All tests made after cable installation surge arrestors, etc. This will pre- step.
and during the guarantee period shall clude damage to such equipment
be made in accordance with appli- and will prevent test interruptions Maintain the test voltage at the
cable specifications. due to flashovers and/or trip-outs prescribed value for the time
All safety precautions must be resulting from excessive designated in applicable specifi-
observed during testing at leakage current. cations. The following times are
• Establish adequate clearance usually considered adequate: at
high voltage.
between the circuit test ends the end of the test period, set the
Read and understand and follow the and any grounded object, and to test set voltage control to zero,
Operator’s Manual for the particular other equipment not under test
test set being used! allow the residual voltage on the
(about 2.5 feet).
circuit to decay, then ground the
• Ground all circuit conductors not
under test with all cable shields conductor just tested.
Test Equipment including nearby equipment.
Direct current test equip- • Consult termination manufactur- CAUTION
ment is available commercially ers for maximum test voltage It should be recognized that DC
with a wide range of voltages. recommendations and charges on cable can build up to
Accessory equipment necessary time limitations. potentially dangerous levels if grounds
to safely conduct high voltage are removed too quickly. Maintain
tests—such as safety The direct current test voltage solid grounds after the test on the
barriers, rubber gloves and may be applied either continu- cable for at least 4 times the dura-
ously or in predetermined steps
nonconducting hard hats—must tion of the test. On exceptionally long
to the maximum value in
be used; consult appropriate cable lengths, it may be necessary
accordance with applicable
safety officer. specifications. to increase the grounding time. It
is advantageous to maintain these
Test Procedures • Continuous Method – Apply test grounds longer and while reconnect-
voltage at an approximate rise ing circuit components.
See IEEE Standard 400 Article
rate of 1 kV per second or 75% • Acceptance Testing – After
5 Direct Voltage Testing.
of the rated current output of the installation and before the cable is
Acceptable procedures, although equipment, whichever is less. placed in regular service, the speci-
varying slightly in technique, have Some equipment will take longer fied test voltage shall be applied for
more or less been standardized to reach the maximum test volt- 15 consecutive minutes.
as either a “withstand test” or a age because of the amount of • Proof Testing – At any time dur-
“time-leaking current test.” charging current. ing the period of guarantee, the
• Step Method – Apply test volt- cable circuit may be removed from
age slowly in 5 to 7 increments service and tested at a reduced
of equal value to the maximum
voltage (normally 65 percent of the
specified. Allow sufficient time at
each stop for the leakage current original acceptance value) for 5
to stabilize. consecutive minutes.
• Record the leakage current at one
minute intervals for the duration
of the test time involved.

Phone: 888-593-3355
www.generalcable.com
SPEC F025
January, 2010

DC “HI-POT” Testing Guidelines for MV Cable

DC High Potential (HI-POT) Testing of Medium-Voltage Power Cable

Comments Routine periodic DC maintenance Testing Problems


The significance of conducting DC testing of cable for the evaluation
Extra Leakage Current:
high-voltage tests on nonshielded, of the insulation strength is not a
nonmetallic-sheathed cable is common practice. Some power • Failure to guard against corona
dependent upon the environment cable users have adopted a • Failure to clean insulation surface
in which it is installed because the program of testing circuits during • Failure to keep cable ends dry
characteristics of the return circuits planned outages, preferring • Failure to provide adequate
are unknown. The environment possible breakdowns during testing clearance to ground
must be carefully considered or rather than experiencing a service • Improper shield termination
test results may not be significant. outage. It is nearly impossible to
In fact, these tests can result in recommend test voltage values
damage to the cable insulation. for those maintenance tests with Erratic Readings:
the history of the cable circuit. • Fluctuating voltage to test set
Humidity, condensation and actual
precipitation on the surface of a An arbitrary test voltage level • Improper test leads
cable termination can increase could break down a cable circuit
the leakage current by several that would otherwise render long
Environmental Influences:
orders of magnitude. Humidity also trouble-free service at normal
operating AC voltage. • High relative humidity
increases the corona current, which • Dampness, dew, fog
indication is included in the total The main usefulness of DC
high-voltage testing is to detect • Wind, snow
leakage current. Wind prevents the
accumulation of space charges at conducting particles left on the
all bare energized terminals. creepage surface during splicing or Results vs. Cable Life
This results in an increase of termination. To date there is no basis for
corona. It is most desirable to Test equipment should be supplied correlation between DC test
reduce or eliminate corona current from a stable, constant voltage results and cable life expectancy.
at the bare metal extremities of source. Do not use the same
cable or terminations. This may be source that is supplying arc welders
accomplished by covering these or other equipment causing line
areas with plastic envelopes, plastic voltage fluctuations. The output
or glass containers, plastic wrap or voltage of the test
suitable electrical putty. set must be filtered and regulated.
Consider using a portable, motor-
driven alter­nator to energize
test set.
The gradual decrease or non-
increase of leakage current with
respect to time at maximum test
voltage is the acceptance criteria
for DC HI-POT testing.

Phone: 888-593-3355
www.generalcable.com

You might also like