Status of Hydro Electric Projects under Execution

As on 30.11.2010
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
A. Projects as per 11th Plan Programme
Central Sector
1 Parbati-II H.P. Civil & HM works: awarded to M/s Patel SEW JV (Dam & part -Slow progress of excavation
NHPC NR HRT) on 11.09.2002, M/s Himachal JV (HRT) on 11.09.2002, of HRT due to poor
12.10.1999/11.09.2002 CS M/s Gammon (I) Ltd. (Power House, Pr. Shaft, Surge Shaft & geological strata especially in
4x200 = 800 MW Execution part HRT) and M/s BJ_Techno-HAS(JV) (Jiwah Nallah) on Face-4. For treatment of
Broad Features : 11.09.2002. strata ahead of face-4 of
Dam – 85m High, 2009-10 Dam- Excavation completed 152155 cum Dam & Inlet structure HRT, work has been awarded
concrete gravity 12th Plan concreting out of 195977 cum completed. to M/s Jager-Bau.
HRT- 6m x 31.52km Head Race Tunnel- 26579 m excavation out of 31525m Treatment of fault zone
S.Shaft-17m x 130m completed ahead of TBM face.
P.Shaft-2 x 3.5m x2133m Total Overt lining: 14045 m excavation out of 31525m Modification of TBM has
P.House- Surface completed been completed.
Turbine- Pelton Feeder Tunnels (Jiwa Nalah): 3270 m exc.out of 4560m done. - Rock busting phenomena in
Switchyard- 400 kV (Manihar-Pancha) 2162 m excavation completed out of 2252m. Face-III in HRT.
Cost: Pressure Shafts- Inclined pressure shaft (left) – Ferrule erection - Ban on use of aggregate by
Original: 3919.59 1266 m out of 1546m completed. Ferrule erection in right H’ble High Court of H.P.
Latest: 4079.44 Pressure Shafts completed. -Slide in Power House area
Power House -Excavation completed and 9413 cum sub in April, 04 June, 06, &
structure and super structure conc. completed out of 60000 cum. Feb, 07.
progress hampered due to PH back slope failure on 20/21st Feb.,
2007.

E&M Works:
Work of power house suspended due to slide of backhill slope
has been resumed and presently concreting is in progress in
service Bay, unit-1 & 2.

HM Works:
Supply of HM components is in progress.

2 Chamera-III H.P. Civil Works: awarded to M/s HCC Ltd. on 21.09.2005. - Labor agitation and stoppage
NHPC NR Diversion Tunnel: Works completed & river diverted on 5.3.07. of works for 3-4 months in
10.10.2003/01.09.2005 CS Dam Area: June, 2006
3x77= 231 MW Execution River bed excavation: 70921 cum completed out of 71000 cum. - Washing away of coffer dam
Broad Features : Dam concreting 142330 cum completed out of 155485 cum. in July, 2007.
Dam –68m High, concrete 2010-11 Head Race Tunnel- Excavation completed and 15391 m overt HRT lining & Dam alongwith
gravity 2010-12 concreting completed out of 15900m. associated HM works are
HRT- 6.5m x 15.9km U-1:03/11 Surge Shaft: excavation completed . critical.
S.Shaft-24m x 110m U-2:04/11 Power House- Excavation completed & concreting nearing
P.House-Uunderground U-3:05/11 completion.
Turbine- V.Francis (Unit-1
Switchyard- 220 kV likely to E&M works:
Cost: slip to Boxing up of Unit-1 completed. Erection of MIV of Unit-1
Original: 1405.63 2011-12) completed. Boxing up of Unit-2 is in progress. Erection of
Latest: 1943.63 MIV,Generator & Turbine of Unit-3 is in progress.

HM works:
Works awarded to M/s Om Metals-SPML(JV) on 26.07.07.
Erection of penstock liner completed. Erection of Intake Gates
Trashrack are in progress.

3 Parbati-III H.P. Civil works: Awarded to M/s Patel – L&T Consortium & M/s -Construction of Sainj By-
NHPC NR Jager – Gammon JV respectively on 15.12.2005. pass road.
12.11.2003/09.11.2005 CS Diversion tunnel: River diverted on 14.03.07. -Poor geology in HRT
4x130 = 520 MW Execution Rockfill Dam: - Delay in award of E&M
Broad Features : Rockfilling above 1300 m: 230700 cum completed out of works due to decision on
Dam – 43m High, Rockfill 2010-11 353000 cum. participation of Chinese
HRT- 7.25m x 7.98km 2011-12 Intake Structure: 10810 cum conc. completed out of companies.
S.Shaft-20m x 114m U-1:07/11 240000 cum.
P.Shaft-2 x 4.5m x345m U-2:08/11 Head Race Tunnel: Excavation completed & 1440 m of overt
P.House- Underground U-3:09/11 lining completed out of 7865 m.

1
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Turbine- V.Francis U-4:10/11 Surge Shaft- 38 m concreting completed out of 133 m.
Switchyard- 400 kV Tail Race Tunnel- 216 m D/S Overt Conc. out of 1094 m
Cost: completed.
Original: 2304.56
Latest: 2095.68 E&M Works:
Design & Engg. works in progress by M/s BHEL. EOT crane
installed in service bay and extended to Unit-I for full capacity.
Draft tube liner erection completed in all Units. Scroll casing
erection in Unit-1 is in progress and in unit-2, stay ring erection
completed. Progress of E&M work has suffered badly due to delay
in re-deployment of erection contrator by M/s BHEL.

HM Works:
D&E works in progress by M/s Om metals-SPML (JV) .
Erection of steel liners for Pressure Shaft in progress in
Horizontal portion.

4 Kol Dam H.P. Gravity Dam: Excavation in Dam area completed. Excavation in - Clay/earth filling of main
NTPC NR Spillway area 144.64 lac cum out of 169.8 lac cum has been dam.
30.6.2002/Oct.2002 CS completed. - Grouting of dam galleries.
4x200 = 800 MW Execution Coffer Dam Filling: Completed. - Concreting of spillway.
Broad Features : Main Dam: 98.74 lac cum filling completed out of 110 lac cum.
Dam – 163m High, Rock 2008-10 Clay filling – 14.05 lac cum out of 21 lac cum completed.
& Gravell fill 2011-12 Other materials filling – 84.69 lac cum out of 89 lac cum
Penstock Tunnel: 4nos. U-1:03/12 completed.
6.45m dia, 1600m long U-2:03/12 Spillway concreting: 2.27 lac cum concreting completed out of
P.House- Surface U-3:03/12 4.45 lac cum.
Turbine- V. Francis U-4:03/12 Power Intake Concreting: 54865 cum out of 63400 cum has
(With been completed.
Cost: efforts) Power House-: 1.09 lac cum primary conc. out of 1.26 lac cum
Original: 4527.15 and 20740 cum secondary conc. Out of 26500 cum have been
Latest: 4527.15 completed.
Unit-1: Boxed up on 22.10.2009.
Unit-2: Boxed up on 09.08.2010.
Unit-3: Turbine erection completed on 31.05.2010. Stator lowered
on 29.09.10.
Unit-4: Runner lowered on 09.07.2010. Stator assembly in
progress. MIV erection completed.
Penstock : Erection of penstock liners completed.
Erection of Generator Transformer completed for U# 1, U# 3 &
U# 4 and for U# 2 is in progress.
5 Ram Pur (SJVNL) H.P. CCEA clearance obtained on 25.01.2007. Civil works awarded to Slow progress of HRT due to
SJVNL NR Patel Gammon JV on 01.02.2007. LOI for E&M works issued to poor geology.
16.12.2005/25.01.07 CS BHEL on 16.09.08
6x68.67= 412 Execution 10.2 km out of 15.144 km HRT excavation has been completed.
Broad Features: River cut & cover- River has been diverted to the original course.
HRT-10.5m x 15.08Km 2011-12 Main Surge Shaft (149 m): Excavation almost completed and
S.Shaft- 38m x 149m 2013-14 lining to start.
P.House- Surface (09/13) Model test of turbine completed.
Turbine- Francis Service Bay # 1 : Ready for fixing of rails for EOT.
Switchyard – 400 kV Service Bay # 2 : Ready for embedment of sole plates.
Cost:
Original: 2047.03
Latest: 2047.03
6 Uri-II J&K Civil Works: awarded to M/s HCC Ltd., on 21.09.2005. The - Earthquake on 08.10.2005
NHPC NR work has earlier been severely hampered due to devastation by - Flash flood in March, 2007
11.2.2004/1.9.2005 CS earthquake on 08.10.2005. and May, 10d washing away
4x60 = 240 MW Execution Diversion tunnel: River diverted in January, 2007. of coffer dams.
Broad Features : Dam- Concreting completed above RBL. -Massive slide on the right
Dam – 52m High, 2009-10 Open Channel & Desilting Chamber: side of Dam in January, 08.
concrete gravity 2010-12 43903 cum concreting out of 56845 cum completed. -Widening of NH 1A by
HRT- 8.4m x 4.27km U-1:02/11 Head Race Tunnel: BRO.

2
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
S.Shaft-25m x 78m U-2:03/11 Overt lining: 4104 m completed out of 4233 m. Invert lining - Collapse of bridge being
P.House- under.ground U-3:07/11 3572 m completed out of 74235 m. constructed in river Jhelum in
Turbine- V. Francis U-4:08/11 Power House: 18084 cum concreting out of 20160 cum Nov, 2008.
Switchyard – 400 kV (Unit-1 & completed. - HM & E&M works are
Cost: 2 likely to Surge Shaft excavation: Completed. critical.
Original: 1724.79 slip to TRT Excavation: 3609 m heading excavation completed out of - Local disturbance.
Latest: 1704.67 2011-12) 3615 m and 3545 m benching excavation completed out of
3615 m.

E & M works: Erection of draft tubes and Spiral Casing and


lower pit liner for all Units completed. In unit 1, Stator has been
lowered and its centring/ alignment is in progress. Building of
Rotor assembly has also been completed. Erection of Bus duct,
laying of cable tray, installation of fire fighting and drainage &
dewatering pipes are in progress. In Unit 2, erection of distributor
assembly is in progress. Stator assembly for Unit 2 is in progress
in Service Bay. In Unit 3, erection of Turbine Generator is in
progress.

HM works: Erection of Pressure shaft liner/ penstock is in


progress. Erection of second stage embedded parts has been
completed for Head Regulator gates. Erection of Trash Rack for
Head Regulator Gates and HRT Intake has been completed. In
Dam, 1st stage embedded parts has been erected. However due to
floods on 19.05.2010, Coffer Dams got breached as a result of
which all HM works of Dam have been affected. HM works of
Dam is now anticipated to be taken up, after restoration of Coffer
Dams and diversion of River flow through Diversion Tunnel, from
15th Oct’2010.
7 Chutak J&K Civil works: awarded to M/s HCC Ltd. on 23.09.2006. -Extreme cold climate.
NHPC NR River diverted on 22.11.2007. - Delay in award of E&M
23.04.2004/24.08.2006 CS Barrage: Excavation completed. Concreting upto crest level works due to poor
4x11 = 44 MW Execution completed. participation and re-tendering.
Broad Features: HRT: Excavation and overt lining completed. - HM works package award
Barrage- 5 bays, 47.5 long 2010-11 Power House: 5917 cum concreting completed out of 12000 cum. delayed due to abnormal high
HRT- 5.9m x 4.370m 2011-12 Pressure Shaft: 17m vertical concreting of PS-I completed out of price bid.
S. Shaft- 19m x 59m U-1:05/11 30m. 20m vertical excavation of PS-2 completed out of 30m.
P Shaft-3.25m x 37m (2 U-2:06/11
no) U-3:07/11 E&M Works:
P.House- Underground U-4:08/11 Erection of Spiral case of unit 1,2&3 completed. Stator work for
Turbine- V. Francis unit-1 started on 06.08.10. Welding of Spiralcase of unit-4
Switchyard- 33 kV completed. EOT Crane has been commissioned & rails erected
Cost: upto unit-2.
Original: 621.26
Latest: 979.55 HM Works:
Awarded to M/s PES Engineers Private Limited on 28.07.08. 1st
stage embedded parts of Barrage arrived at site. Penstock liner
erection work in unit-1,2,3&4 completed. Further, bifercation
segments of unit-3&4 has been erected. Spillway radial gates
erection in Bay-1 & 2 started. Bay-3 & 4 also handed over to HM
contractor for gate erection.
8 Nimoo Bazgo J&K Civil works: Awarded to M/s HCC Ltd. on 23.09.2006. -Extreme cold climate.
NHPC NR River diverted on 22.11.2007. - Delay in award of E&M
16,03.2006/24.08.2006 CS Dam: works due to poor
3x15 = 45 MW Execution Concreting upto crest level: Completed and Power Dam participation and re-tendering.
Broad Features: concreting 36113 cum completed out of 38280 cum. - HM works package award
Dam –57.5m High, 2010-11 Cellular Wall: Concreting completed. delayed due to abnormal high
concrete gravity 2011-12 Power House: Excavation completed. 13887 cum concreting price bid.
Spillway- 5 x 65m U-1:05/11 completed out of 32000 cum.
Penstock- 3 x 63mx3.3m U-2:06/11
P.House- Surface U-3:07/11 E&M Works:
Turbine- V. Francis Concreting of spiral case of unit-3 in progress. Erection of spiral
Switchyard- 33 kV case of unit-2 completion and handed over to contractor for
Cost: concreting.

3
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Original: 611.01
Latest: 902.27 HM works:
Erection of radial gates of S1 & S3 Bay completed. Tranion beam
of S2 & S3 Bay erected. S3 Bay is yet to handed over to HM
contractor.

9 Koteshwar Uttaranch Flash flood occurred on 20/21st September, 2010. Flood water - Delay in Diversion tunnel
THDC al entered the power house . works.
10.04.2000/ NR Civil works:- - Initial R&R problem.
4x100=400 CS Dam and Spillway: Excavation- Completed ( 1293.93 Th.Cum). - Slow progress by Contractor.
Execution Concreting- 511.13 Th.Cum out of 535 Th.Cum completed. - Poor geology, slope failure
Broad Features: Power Intake- Excavation- Completed ( 399 Th.Cum). above Power House & Intake
Dam – 97.5m High, 2005-06 Concreting- 87.59 Th.Cum out of 90 Th.Cum completed. Area affected progress.
concrete gravity 2010-12 Stilling Basin- Excavation- Completed ( 373 Th.Cum). - Breakdown of Rotomec
P.House- Surface U-1:03/10 Concreting- 120.99 Th.Cum out of 122 Th.Cum completed. system affected progress of
Turbine- V. Francis U-2 to 4: Penstocks- Excavation of vertical limbs of penstocks ( Total : 120 works.
Cost: 2011-12 RM)- Completed. - Flash flood occurred on
Original: 1301.56 Excavation of Horizontal limbs of penstocks (Total : 299 RM)- 20/21st September, 2010.
Latest: 2398.39 Completed.
Power House- Excavation- Completed (1319 Th. Cum.
Concreting- 185.82 Th.Cum out of 187 Th.Cum completed.
Access Tunnel to Power House(8m dia D-shaped- total length-
376m)- Completed.
Started on 22.12.06 and heading excavation completed in May-09.
Tail Race Channel-
Excavation of 800.54 Th Cum out of 825 Th. Cum completed.
Switch Yard - Erection of equipment is in progress.
E&M Works:-
Unit Erection:
U-1: Boxed up.
U-2: Stator lowered. Rotor assembly in service bay in progress.
U-3: Spiral casing erected & tested.
U-4: Erection of spiral casing is in progress.
H&M works: Erection of penstocks completed.
Erection of radial gates in all the 4 bays is in progress.
10 Loharinagpala Uttaranch Erection of anchor rages of spillway radial gates completed. Head - Delay in forest clearance for
NTPC al Race Tunnel works awarded in July, 2006 to M/s Patel Engg. approach road to Helgu adit.
11.08.2004/June, 2006 NR Barrage and Desilting arrangement package awarded in July, 2006 - Slow progress due to slide
4x150 = 600 MW CS to M/s HCC, Mumbai. Power House and Penstock works awarded zone in approach road area to
Broad Features : Execution in Sept.,06 to M/s Patel Engg. Hydro-mechanical package Gunagu adit.
Barrage–4 bays of 15m 2011-12 awarded in Aug., 07 to M/s Texmaco Ltd. E&M works awarded to - Work suspended since
HRT- 6m x 13.85km 12th Plan M/s Voith Siemens in January, 2008. 20.02.2009 on directive of
P.Shaft-2x 4m x 500m Work of Barrage & Desilting chamber under progress, River MoP, Govt. of India.
P.House- underground diverted on 14.12.2008 and 2.08 lac cum out of 2.40 lac cum
Turbine- V.Pelton excavation of barrage completed. Excavation of adit, main access
Cost: tunnel in progress. Excavation of adit to TRT completed. Gunagu
Original: 2895.104 adit work 262 m completed. MAT works upto 327 m completed.
Latest: 2895.104 Work in intermediate adit to pressure shaft completed. Excavation
of switchyard 66602 cum completed. 2084 m HRT completed.
Surge shaft excavation 30370 cum completed. Work held up due
to agitation by environmentalists.
11 Tapovan Vishnugad Uttaranch Head Race Tunnel work awarded in Nov., 2006. Barrage & - Delay in HRT work due to
NTPC al Desilting Chamber package awarded in January, 2007. P.H. & late procurement/ deployment
11.08.2004/Nov, 2006 NR penstock package awarded in May, 2007. E&M works awarded to of TBM by civil contractor
4x130 = 520 MW CS M/s BHEL in January, 2008. 400 KV GIS awarded to M/s (about 20 months.)
Broad Features : Execution AREVA T&D Ltd. in July, 2008. - Slow progress of barrage &
Barrage–5 bays of 12m HRT from Intake D/s excavation 1491.5 m out of 3012.30m, U/S desilting chamber.
HRT- 5.4m x 11.97km 2011-12 excavation 226.5 m out of 241.4 m and HRT by TBM 2612.8 m - Surge shaft work slow due to
P.House- underground 12th Plan out of 8618.6 m completed. Excavation of Desilting Chamber poor geology.
Turbine- V.Pelton under progress and 16.58 lakh m3 out of 16.90 lakh m3 completed. - Heavy water ingress in
Cost: Excavation of main access tunnel and Ventilation Tunnel HRT w.e.f. 25.12.2009 and
Original: 2810.84 completed. Power house concreting under progress. In TRT 26835 excavation by TBM is held
Latest: 2978.48 cum out of 45000 cum open exc. & tunnel excavation completed. up.
Concreting 1852/3270 cum done. Adit to surge shaft bottom
completed. Excavation in switchyard is completed.
4
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Surge shaft excavation: Surge shaft full widening 70 m out of
144.3 m completed.
Penstock excavation completed.
12 Teesta Low W.B. Civil works: Awarded to M/s Patel Engg. Ltd. on 28.10.2003. -Delay in forest clearance
Dam-III ER Dam Cellular wall concreting: 63648 cum concreting -Slope failure in Power House
NHPC CS completed out of 67315 cum. and Intake area.
25.06.2002/30.10.2003 Execution. Barrage- Barrage Blocks I to II: 22380cum concreting - Frequent interruption of
4x33 = 132 MW Completed out of 59250 cum. works by local people and
Broad Features : 2006-07 Power House- 95545 cum conc. completed out of 97196 cum. stoppage of works due to GJM
Barrage – 140m Height 2010-11 Tail Race channel: 857576 cum excavation out of 860000 cum agitation.
Penstock-4x 7m x 50m U-1:01/11 completed. - Flash floods in the year 2007
P.House- Surface U-2:01/11 & May, 2009.
Turbine- Kaplan U-3:02/11 E&M Works: -Inadequate labour at site.
Swutchyard – 220 kV U-4:02/11 Unit#1: Erection of generator stator and lowering of rotor - Concreting of barrage bays 1
Cost: (likely to completed. Erection of auxiallaries and unit axis alignment and & 2 and associated HM works
Original: 768.92 slip to box up is in progress. are critical.
Latest: 1398.71 2011-12) Unit#2: Installation of lower bracket assembly in pit and turbine - Law & order problem.
assembly completed. Assembling of rotor in service bay - Works held up at site from
completed. Erection of auxiallaries and generator stator in service 10.05.2010 to 19.07.2010 due
bay is in progress. to local issues.
Unit#3: Installation of turbine assembly and erection of - Breaching of coffer dam
auxiallaries is in progress. during monsoon (July/August,
Unit#4: Erection of Draft tube, Scroll case completed. Erection of 2010) and barrage bays 1&2
auxiallaries is in progress. inundated and flooded.

HM works:
Design/Drawings and Fabrication of various Components is in
progress. Erection of Penstocks is completed. Erection of intake
service gate 1&2 completed. 21% Erection of Intake stoplog gate
1&2 completed.ET&C of spillway stoplog Bay S-5, S-6 & S-7
completed. Erection of Radial gate in Bay No. IV & V completed.
13 Teesta Low W.B.. Civil works: awarded to M/s HCC on 19.01.2006. -Delay in forest clearance
Dam-IV ER st - Frequent interruption of
1 stage river diversion achieved on 30.01.2007.
NHPC CS works by local people and
23.12.2003/30.09.2005 Execution Excavation of Dam Spillway: 912098 cum completed out of stoppage of works due to GJM
4x40 = 160 MW 922047 cum. agitation.
Broad Features : 2009-10 Concreting in spillway glacis and piers: 128493 cum completed - Flash floods in the year
Dam –45m High, concrete 2011-12 out of 135754 cum. 2007, May, 2009 and
gravity U-1:07/11 Power House: 87929 cum concreting completed out of July/August. 2010..
Penstock-4x7m x45m U-2:08/11 141614cum. - Works held up at site from
P.House- Surface U-3:09/11 10.05.2010 to 19.07.2010 due
Turbine- Kaplan U-4:10/11 E&M Works: to local issues.
Swutchyard – 220 kV Design/Engineering in progress by M/s BHEL. 97% of erection of - 2nd stage river diversion
Cost: EOT crane completed in service Bay. Erection of Draft Tube planned during November, 11.
Original: 1061.38 Liner in unit#1 completed and 92%,82%& 80% erection of draft The project may slip to 2012-
Latest: 1462.09 tube liner in Unit-2, 3 & 4 completed. Erection of Spiral case in 13.
U#1 is in progress.

HM works:
Design/Engineering in progress by M/s OM METALS. 32%
erection of Penstock Liner completed. 27% erection of Radial gate
in Bay 1 to 7 completed. 19% erection of silt flushing gate
completed.

14 Subansiri Lower Ar.P/Assa Civil works: awarded to M/s BGS-SGS-Soma JV (Dam/Barrage - Signing of MoU with State
NHPC m and HRT) on 19.12.2003 and M/s L&T Ltd. (Power House & Government of Assam.
07.06.2001/09.09.03 NER Tail Race works) on 19.12.2003. - Washing away of coffer dam
8x250= 2000 MW CS Diversion tunnel: River diverted on 25.12.2007. in the year 2008.
Broad Features : Execution Inlet Structure- Excavation completed. - Slope failure of power house
Dam –116m High, Dam in January, 2008.
concrete gravity 2010-11 Foundation excavation: 161691 cum completed out of 173000 - Change of surge shaft to
HRT- 8 x 9.5m x 1145m 12th Plan cum. surge tunnels.
P.Shaft-8x 9.7m x2153m Dam concreting upto EL 108m: 251385 cum completed out of - Law & Order problem.
P.House- Surface 1350000 cum. - Damage to bridge at
Turbine- Francis Reconstruction of U/S and D/S coffer dam and dykes: Ranganadi river.
5
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Switchyard – 400 kV Completed. - Cut-off wall issue.
Cost: Intake Structure: 129062 cum concreting completed out of - Local issues.
Original: 6285.33 260000 cum.
Latest: 8155.01 Head Race Tunnel (I- VIII): 5350 m heading excavation
completed out of 7124 m.
Surge Tunnels (8 nos.): Surge Chamber has been modified to
8 nos. surge tunnel. Adit excavation is in progress.
Pressure Shaft-
Horizontal Pressure Shaft: 1410 RM excavation out of 1429 RM
completed.
Surface Power House:
Concreting: 68857 cum out of 360000 cum completed.

E&M Works:
1no. 200/30/10 T EOT crane, 2 nos.340/40/10 T EOT Crane-I and
1 no 100 T EOT Crane in service way commissioned. Parts of
upper & lower pit liner all units, draft tube elbow unit-1 to unit-8,
Guide Vanes Unit-1 to Unit-8, Stay Ring all units MIV power
pack all units and Bus duct & Accessories of all Units have
reached at Project. Supply of other parts is in progress. Erection
and welding of DT-Liner-1 done. Erection of DT liner in Unit-2 is
in progress.

HM Works:
Supply of Penstock liner plates - 50%, Draft tube gate & EP and
Gantry crane - 94%, HRT Intake trash rack & EP - 97%, HRT
Intake bulkhead Gate & gantry crane - 48%, Hoist bridge
structure - 08 nos., Diversion tunnel gates 70%, Fabrication of
43% of Pressure Shaft Liner at site workshop has been completed.
Erection of 1st stage embeded parts of Intake gate 1,2,5,6,7 and 8
are in progress. Out of total 1593m, 69m pressure shaft steel liner
erected. Erection of 1st stage EP of draft tube gates are in
progress.
15 Kameng Ar. Bichom Dam: Excavation (including intake) (R) 485528/611546 - Change in Crest level from
NEEPCO Pradesh cum and Concreting 6803.18/ 360000 cum completed. EL 755m to EL 735m, length
02 12 2004 NER Tenga Dam: Excavation 90870/147075 cum and of dam increased from 247.3m
/4x150 = 600 MW CS Concreting 86205/88260 cum completed. to 264.15m. Also, Diversion
Broad Features: Execution HRT: Excavation: 8425.80/14477.50m completed. Face- arrangement modified.
Dam :Bichom-75m High, II, III, VI & VII critical, work slow due to bad Geology. - Subsequently delay in
247.3m long. 2009-10 construction drawings from
Surge Shaft: Open excavation and boring completed,
Tenga – 25.0 High, 103m 12th Plan consultant i.e. SMEC.
long. Lining: 2817/6281 m completed. - Slow progress in Dam &
HRT- 6.7m dia, HPT: Boring completed & excavation works in progress. HRT due to various reasons
14.477km. Power House & TRT: Excavation 1050430/1214865 cum ie. Bad geology, heavy
High Pressure Tunnel completed. Concreting 15422/75600 cum completed. seepage, in adequate
(HPT)Total length 3.64 HM Works & Penstock: Fabrication & erection of machinery at site etc.
km Surge Shaft: 25m dia, penstock steel liner and HM works are in progress. - Work suffered due to flash
70m H Electro-mechanical works: BHEL mobilized at site & D/T flood in Oct. 08.
Penstock- 2x 4m liner received at site. Laying of earth-mat in Unit area in - Contractual issues.
P.House- semi-U/G
progress. E&M equipment and material are reaching site
Turbine- Francis
Cost: progressively.
Original: 2496.90
Latest: 2496.90
State Sector
16 Uhl-III, H.P. Neri Khad works (Trench weir, Intake Structures, Water Slow progress of civil works,
Beas Valley Power NR conductor system upto Khuddar Reservoir): 43089 cum particularly HRT (which is
Corporation Ltd. (HPSEB) SS excavation and 985.5 cum concreting completed by previous critical) due to poor geology,
19.09.02 / Execution contractor. Work rescinded on 21.05.08. Fresh award given to difficult area, inadequate
(TEC -2x50 MW) M/s CCPL on 25.10.2008. New contractor has started the work. mobilization by contractor,
3x33.3 =100 MW 2006-07 40701 cum out of 45203 cum excavation and 11325 cum out of etc. Contract for Package-I &
(Revised vide HPSEB 12th Plan 14483 cum concreting completed. Package-V cancelled and
letter dt. 19.01.07. Rana Khad Works (Trench weir, Intake Structures, Water fresh awards placed.
Broad Features: conductor system upto Khuddar Reservoir): 90540 cum out of
HRT-4.15m x 8.47 km 96248 cum excavation and 15392 cum out of 20011 cum
6
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
S.Shaft- 13m x 57m concreting completed.
Penstock- 3.4m x 1860m Aqueduct over Rand Khad: 18583 cum out of 18650 cum
P.House- Surface excavation and 2562 cum out of 2900 cum concreting completed.
Turbine- V. Francis Out of 651 MT steel, 541 MT has been erected.
Cost: Storage Reservoir: 44690 cum out of 60145 cum excavation and
Original: 431.56 24650 cum out of 37596 cum concreting completed.
Latest: 431.56 HRT: 6856.5 m out of 9258.5 m excavation completed by
previous contractor. Contract was cancelled due to slow progress.
Fresh award given to M/s CCPL on 30.09.2008. 1044 m out of
2402 m excavation completed and balance is 1358 m.
Penstock: U/G excavation completed and open excavation
(149469 cum out of 155000 cum) is in progress. 25114 cum out of
31622 cum concreting completed.
Power House and Tail Race: 26267 out of 31500 cum excavation
completed and 5740 cum out of 10105 cum concreting completed.
Award for E&M equipments placed on 15.02.2007 to BHEL.
17 Swara Kuddu H.P. Package –I (Diversion structure, intake and desilting chambers) – Slow progress of HRT due to
H.P. Power Corpn. Ltd. NR Awarded to M/s Patel Engg. Ltd., Mumbai, on 25.08.2009. poor geology.
HPSEB Clearance: SS HRT works (Package–II) awarded in June, 07. The stipulated period for
10.11.2004 Execution 4139 m out of 11145 m excavation of HRT completed. Lining completion of Package-III is
3x37= 111 MW 2010-11 from Face # 3 & # 4 has been started. 39 months i.e. completion by
Broad Features: 12th Plan Excavation of all the Adits completed. May, 2012.
Diversion Structure: Package – III (Power House Complex) awarded in February, The stipulated period for
10.45m high Piano Key 2009. Excavation of MAT, cable tunnel cum constt adit to PH, completion of Package-IV is
Weir. valve chamber and pilot hole to top of PH cavern has been 38 months i.e. completion by
HRT- D-Shaped, 5m dia, completed. Excavation of Power house and transformer cavern is April, 2012.
11.145Km long. in progress.
Power House- Under Award of contract for E&M Package (Package-IV) has been
ground signed on 27.2.2009 with JV of M/s VA Tech Hydro India Pvt
Turbine- 500 rpm vertical Ltd & M/s VA Tech EMF Pvt Ltd with effective date as
francis. 13.3.2009. Stipulated period for completion is 38 months i.e.
Switchyard: 220 Kv. completion by May, 2012.
Cost:
Original: 558.53 (03/03)
Latest: 721.71 (02/08)
18 Priyadarshini Jurala A.P. Power House - Power House concreting in progress. - Units commissioning
APGENCO SR Unit #1- Commissioned on 28.03.2008. COD on 18.08.2008. delayed due to single shift
24 07 02 SS Unit #2- Commissioned on 31.08.2008. COD on 11.09.2008. working by Chinese personnel
6x39= 234 Execution Unit #3- Commissioned on 27.06.2009. COD on 07.08.2009. and Visa renewable problem
Broad Features : Unit #4- Commissioned on 28.08.2010. of Chinese working personnel
Barrage – 27.8m Height 2006-07 Unit #5 – Commissioned on 9.11.2010. at site.
P.House- Surface 2007-11 Unit #6- Fixing & alignment of stator is in progress. - Commissioning of Unit# 5 &
Turbine- Bulb U-4: & 5- #6 was delayed due to
Cost: Comnd. rectification of stator design
Original: 547 U-6:03/11 problem.
Latest: 547 (Unit-6
likely to slip
to 2011-12)
19 Nagarujana Sagar TR A.P. Civil works awarded on 9.5.2005. E&M works awarded to M/s - Slow progress in
APGENCO SR BHEL on 3.5.2006. Construction of dam.and
17 01 05 SS Main Dam: Excavation at dam area is completed and associated HM works.
2x25=50 Execution 333807/489000 (68%) cum concreting completed. - Delay in Award of HM
Broad Features: P.H. Civil works: Excavation completed in PH area and works.
Dam –29.5m High 2008-09 33250/37500 cum concreting completed. - unprecedented floods on
Spillway- 21nos gate 2010-12 Penstocks: 17/25 ferrules erected for Unit-1. 01.10.2009
Penstock- 2x 5.35m U-1:03/11 EOT Crane: EOT crane commissioned.
P.House- Surface U-2:06/11 Unit Erection:
Turbine- V. Kaplan (Unit-1 Unit-1- Lowering & alignment of stay ring completed.
Cost: likely to Unit-2- Lowering of stay ring completed.
Original: 357.63 slip to H&M works re-awarded to GTV-PES Jt. venture on 11.5.2009.
Latest: 464.70 2011-12) Fabrication of 11 radial gates out of total 20 gates completed.

20 Lower Jurala AP Works for construction of weirs was awarded to M/s Patel Engg. - Delay in award of E&M
APGENCO, A.P. SR and the work commenced in November, 2008. About 60 % (Total works.
TEC in July 2007 SS qty.- 157000 cum) concreting completed. - Slow progress of civil
7
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
6x40=240 (120 MW likely Execution Excavation works for approach channel, intake pool, power house works.
to slip) pit, tail race pool and channel was awarded to M/s Ramakrishna
Broad Features: 2011-12 Reddy, Hyderabad in November, 2007. Excavation completed.
Intake: 18 vents (3 vents 12th Plan Works for construction of power house civil works including
for each unit) 4.7m width, switchyard, gates etc was awarded on 04.07.2009. Concreting of
P.House- Surface, intake raft for Unit 1,2 & 3, downstream draft tube cone
Turbine- Bulb concreting completed.
Design Head- 20m LOA for E&M works earlier placed on M/s CMEC, China is
SWYD- 220 kV January, 2008 was cancelled and re-awarded to M/s Alsthom
Cost: Project India Ltd. on 09.06.2008..
Original: 908.34 Erection of 70/10 T EOT crane at unloading bay completed.
Latest: 908.34
21 Pulichintala A.P. Dam is under construction by Irrigation Department, Govt. of A.P. - Slow progress of Dam.
APGENCO SR The works for dam construction were awarded to M/s SCL- - E&M works need to be
120 MW (4x30 MW) SS CR18G JV. Dam concreting works are in progress and about 50% expedited.
25.04.2007 Execution concreting is completed. - unprecedented flood on
Broad Features: The excavation of power house completed. 02.10.2009.
Design Head: 24 M 2010-11 The E&M works have been awarded to M/s BHEL in May, 2007.
Power House: Surface 2010-12 Materials are being received progressively at site.
Turbine : V. Kaplan U-1:03/11 Erection of Draft tube of unit-2 is completed & released for
Annual Energy: 220 MU U-2:06/11 concreting. Erection of draft tube liner for Unit-1 is in progress.
Cost: U-3:09/11
Original: 380 Crs.(PL 06- U-4:12/11
07) (Unit-1
Latest: 380 Crs.(PL-06- likely to
07) slip to
2011-12)
22 Pallivasal Kerala Contract has been awarded for construction of the project on turn- - Works are getting affected
KSEB SR key basis to consortium of M/s ESSAR – DEC – CPPL. due to poor maintenance of
2x30= 60 MW SS Progress/Total Qty: machineries by contractor.
Broad Features: Execution Intake structure excavation – 28398/33492 cum. - Land acquisition problem for
HRT: 3.50m X 3396m HRT excavation –2669/3396 m. penstock.
Surge Shaft: 7.0m X 49m 2010-11 Surge Tank/Forebay excavation – 3260/3710 cum & concreting - Slow progress of civil
Pressure Shaft: 2.50m X 12th plan 226/768 cum. works.
1019.20m TRT/Channel Excavation – 6280/7384 cum. - Change in alignment of Adit
Penstock: Pressure Shaft excavation : 712/1062 m. to HRT.
2.00mX1161.20m Surface penstock excavation –74238/122600 cum.
Power House: Surface Concreting – 4700/11375 cum.
Turbine : Pelton Fabrication & supply –1968/2057 m.
S.Yard: 220kV – Single Erection & testing – 703/2057 m.
bus P.H. excavation : 53350/64408 cum.
Cost: Tail race Channel: 6280/7384 cum.
Original: 242.95 + US$ Switchyard excavation & leveling – 13240/16610 cum.
57M
23 Bhawani Kattalai Tamil Civil & HM works: About 90% of barrage works are completed.
Barrage-II Nadu Civil works in 14 spans (18 barrage spans & 2 Intake spans) out of
11.6.99 SR 20 spans have beencompleted. Balance work is likely to be
2x15 = 30 SS completed by November, 2010. 10 out of 18 barrage gates have
Broad Features: Execution been commissioned and erection of balance gates will be taken up
Barrage –22 gates after completion of civil works. Power House civil works are
P.House- Surface almost completed.
Turbine- Bulb 2006-07 E&M works: Erection of stay ring for both the units has been
Cost: 2011-12 completed. Erection of auxiliaries system is almost completed.
Original: 99.15 U-1:07/11 Cabling works are in progress.
Latest: 400.59 U-2:08/11
24 Bhawani Kattalai Tamil Civil & HM works: About 75% of barrage works are completed.
Barrage-III Nadu Civil works of barrage are being done in three phases. For Phase-
27.03.02 SR I, all civil works are completed and for Phase-II & III, piers and
2x15 = 30 SS weirs have been completed. Erection of 5, out of 16 barrage gates
Broad Features: Execution have been completed. All the barrage works are programmed to
Barrage –22 gates be completed by August, 2011. In Power House, about 95% civil
P.House- Surface 2006-07 works are completed.
Turbine- Bulb 2011-12 E&M works: Erection of stay ring are in progress. Erection of
Cost: U-1:01/12 auxiliaries would be taken up after completion of power house
Original: 99.75 U-2:02/12 civil works in November, 2010.
8
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Latest: 398.60
25 Myntdu, Meghalaya Flash flood on 20.5.10 caused damage to already erected electrical Delay in commissioning due
MeSEB NER equipment. to flash flood occurred on
20.09.99/ SS Main Dam: Excavation completed and 331163 out of 332311 20.5.10.
2x42+1x42 = 126 Execution cum concreting completed.
Broad Features: HRT & HPT: Completed.
Dam –63m High 2006-07 Surge Shaft: Works completed.
HRT- 3316.46mx3.4m dia 2010-11 Surface Penstock: Excavation completed. 27078 cum out of
Power House- Surface U-1:2011-12 27385 cum concreting completed. Fabrication completed.
Turbine- V. Francis U-2:2011-12 Erection 3000.52 m out of 3129m completed.
Cost: U-3:2011-12 Power House: Excavation completed. 19590/20362 cum
Original: 363.08 substructure and 2705/4050 cum super structure concreting
Latest: 965.93 completed.
Tail Race: Excavation completed & lining 15525/20000 cum
completed.
E&M: Rectification of damaged equipment is under progress.
HM works: Erection of Radial gates is underway and 3nos out of
7 gates erected.

26 New Umtru Meghalay Civil works awarded to M/s ITD Cementation (India) Ltd. in Dec. Extremely slow progress of
MeSEB, a NER 2007. Work resumed 5th Dec. 2008. civil works.
2x20=40 Order for HM works has been placed to M/s SEW Texmaco in
Broad Features: 2011-12 January, 2009. E&M works awarded to VA Tech Hydro
Diversion Structur-Gated 2011-12 (ANDRITZ) in Feb. 2009.
structure (FRL-130.1m, U-1:11/11 Surge shaft: Open excavation completed and balance boring work
MDDL-123.3m) U-2:12/11 of surge shaft 6800 cum yet to be taken.
HRT- 5m dia, 750m long
P.House- Deep Set
SWYD- 132 kV
Cost: 194.3 Cr.
194.3 Cr.
Private
27 Karcham Wangtoo H.P. Financial closure achieved on 30.3.2006.
Jaypee Karcham Hydro NR Design, engineering, procurement & construction contract
Corporation Ltd. PS awarded to M/s JAL on 09.07.2003. LOI for E&M works issued
31.03.2003/30.3.2006 Execution on 30.10.2007 in favour of Voith-Siemens – Adritz VA Tech
(FC) Hydro Karcham Wangtoo Consortium.
4x250=1000 2008-09 River diversion completed on 11.04.2007.
Broad Features : 2011-12 Main Dam: Excavation completed and 526118 cum concreting
Dam – 98m Height U-1:08/11 out of 541000 cum completed.
HRT- 10.48m x 17.2km U-2:09/11 Intake: Excavation and overt concreting of intake tunnel
P.Shaft-4x 4.7m x291m U-3:10/11 completed.
P.House- underground U-4:11/11 HRT: Heading excavation completed and 16875 m benching,
Turbine- Francis 16911.5 m overt lining & 13905 m invert lining out of 16925m
Cost: HRT completed.
Original: 5909.59 Power House: Both the EOT cranes are in operation and unit
Latest: 5909.59 erection is in progress.
TRT: Excavation completed and 1203 m out of 1273 m Overt
lining and 719m invert lining has been done.

28 Budhil H.P. Financial closure achieved in March, 2006. HRT lining & E&M works
Lanco Green Power Pvt NR All works awarded and are under progress are critical.
Ltd PS River diversion works completed.
1.06.2005/ Jan, 06 (FC) Execution Dam : Concreting of 39108 cum out of 44595 cum completed.
2x35=70 MW HRT: 6270 m excavation completed and 3077 m concreting has
Broad Features: 2008-09 also been completed.
Dam-58m High 2010-11 Power House: Excavation completed. EOT crane is in operation.
HRT-4m x U-1:03/11 Stator & rotor formation is in progress.
6028m\.House- U-2:03/11 E&M Works: Works awarded to M/s Dongfong Electric
underground Corporation Limited, China. 80% supply completed.
Turbine- V. Francis
Cost:
Original: 418.80
Latest: 418.80

9
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
29 Malana-II H.P. Financial closure on 03.08.2006. HRT works slow due to poor
Everest Power Pvt. Ltd. NR Dam: Excavation of dam completed and 83917/89000 cum geology.
15.10.2004 by HP Govt./ PS concreting done.
2x50=100 MW Execution HRT: Excavation completed and 3006 m lining out of 4952m has
Broad Features: been done
Dam –45.5m High 2008-09 Power House: All major civil works for both the units is
HRT- 3m x 4.874 km 2010-11 complete.
S. Shaft- 6m x 90m U-1:01/11 Pressure Shaft: 196/198 m Horizontal pressure shaft completed.
P. Shaft- 2.5m x 666m U-2:02/11 E&M Works: Both the units are boxed up and dry test is in
P.House- underground progress.
Turbine- Pelton
Cost:
Original: 598.00
Latest: 598.00
30 Sorang H.P. Financial closure achieved in June, 2007. Difficult area, accessibility
Himachal Sorang Power NR Civil & HM works awarded to NCC – Maytas – SSJV consortium and availability of working
corporation Ltd. PS in June, 2007. period.
June, 2006/ Execution E &M works awarded to M/s Voith Siemens in June, 2007.
2x50= 100 MW All infrastructure works including bridge completed.
2012-13 Excavation of Power house is completed.
2011-12 Boring of main access tunnel, Adit to HRT and excavation of PH
U-1:09/11 cavern has been completed. 86% excavation of transformer cavern
U-2:10/11 completed.
56% boring of HRT has been completed
Land – Forest & Pvt. Land acquisition is in progress.
31 Shrinagar Uttarakha - Order for civil works awarded to M/s NCC-GVKPL consortium - Concreting of dam is
GVK Industries Ltd. nd on 11.06.07. critical.
14/06/2000/ FC NR - LOA for E&M works issued to M/s BHEL in April,2007. - E&M equipment delievery
4x82.5=330 PS - HM works awarded to M/s Precision Infratech Limited. to be co-ordinated with
Broad Features: Execution - Financial closure achieved on 3.8.2007. BHEL.
Dam –66.5m High, Progress/Total Quantity of various Activities:
concrete gravity 2005-06 - Diversion tunnel and NH-54 Road realignment completed.
HRT- 13m x 889m 2011-12 - Construction of coffer dam near Power House completed.
Penstock-4x 5.6m x 114m U-1:12/11 - Dam excavation (100%) completed. Concreting 31% done.
P.House- Surface U-2:01/12 - HRT excavation completed and lining 23% completed.
Turbine- Francis U-3:02/12 - Power Channel excavation 79% & concreting 29% completed.
Cost: U-4:03/12 Surface penstocks: Excavation completed. Concreting 7%
Original: 1699.12 completed. Penstocks 87.5 % completed.
Latest: 2069.00 - Power House excavation completed and concreting in progress..
Unit Erection:
Unit # 1; Erection of spiral casing is in progress.
Unit #2: Draft tube erected.
Unit #3: Draft tube erection in progress.
Unit #4: Pit liner erection in progress. Earth mate works
completed.
32 Maheshwar, M. P. CIVIL & HM WORKS: R&R issues.
SMHPCL WR All major civil works related to dam and intake are completed. Permission of competent
30 12 96/ 29.9.2006 (FC) PS Civil works in power house area is progressing as per the schedule authority for erection of
10x40= 400 Execution of erection of various units. . balance 5 nos. radial gates.
Broad Features: Erection of 22 nos. , out of total 27 nos. of radial gates is Supply of equipment by
Dam-35m High, concrete 2001-02 completed in all respect. The erection of balance 5 nos. radial BHEL in sequential manner.
gravity 2011-12 gates is held up for want of clearance from competent authority.
P.Shaft-10x7.82m x 52m U-1:06/11 It was informed by concerned engineer that the erection of balance
P.House- Surface U-2:07/11 5 nos. radial gates would be completed in one and half months
Turbine- Kaplan U-3:08/11 time once the clearance is obtained.
Cost: U-4:09/11 Erection of intake service gates for 12 nos. vents i.e for four units
Original: 1569.27 U-5:10/11 was completed. Erection of balance intake service gates is
Latest: 2449.20 U-6:11/11 programmed for completion by Nov., 2010. The erection of draft
U-7:12/11 tube gates is programmed to be completed by Dec, 2010.
U-8:01/12 E&M WORKS: Electro-mechanical contract with BHEL made
U-9:02/12 effective on 25.06.2007.
U-10:03/12 Unit #10 is nearing boxing up and stator for
(U-6 to 10 unit #8 has been lowered and rotor is ready in service bay.
with Erection of three units is in various stages.
efforts) The works regarding erection / inter-connection / testing &
10
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
commissioning of unit Auxiliaries and Station Service system is in
progress.

33 Chujachen Sikkim Financial closure achieved on 14.03.2007 - Flash flood on 16.04.2009


Gati Infrastructure Ltd, ER Civil works: awarded to M/s SEW & PRASAD (JV) Hyderabad washing away Rangpo coffer
Secunderabad PS on 09.03.2006. dam.
30.11.2004 (State Govt.)/ Execution Rongli Dam: All excavation & concreting works completed. - Very slow progress in HRT
2x49.5= 99 MW Rongli Intake excavation and concreting completed. lining works.
Broad Features: 2009-10
Dam – 2010-11 Rangpo Dam Excavation about 1,00,000/1,08,000 cum
Rampo- 48.5m High U-1: 02/11 completed and concreting of 56033/76000 cum completed. Intake
Rongli- 41m High U-2: 03/11 excavation completed and concreting 5123/6000 cum completed.
HRT- Surge Tank: Excavation completed & concreting 1724/2600 cum
Rampo-3.3m x 2578m completed.
Rongli-3.5m x 2256m HRT: 7753/7926 m excavation completed. Invert concreting
Common-5.2m x 3225m 485m completed. Overt concreting 480.4 m completed.
S. Shaft-12m x 104m BF Valve: Excavation completed and concreting 616.5/900 cum
P.House- Surface completed.
Turbine- V. Francis Pressure Shaft: Excavation almost completed. .Erection of steel
Cost: liners completed. Concreting & Grouting 10465/11315m
Original: 448.76 completed.
Latest: 651.50 H&M works: awarded to M/s PES Engineers Pvt. Ltd on
11.12.07.
Erection works in various phases of completion.
TRT – Excavation 7050/7300 cum & lining 4978/5400 cum
completed.
Units: Both units boxed up.
Switchyard 11/132 kV: Completed.
34 Teesta-III Sikkim State clearance to the project accorded on 18th July 2005. TEC As per contract, the
Teesta Urja Ltd. (TUL) ER from CEA accorded on 12.05.2006. Environment and Forest commissioning of three units
12.05.2006 PS clearance have been obtained. Private and Forest land acquisition is in 2011-12 and other three
6x200=1200MW Execution has been completed. LOA for turnkey execution of the project units in 2012-13.
Broad Features: placed on the EPC consortium led by M/s Navayuga Engineering
Dam-Concrete with chute 2011-12 Company, Hyderabad and AIPL on 18.04.2007 and contract Project authorities have
spillway 60m high. 2011-12 agreement signed on 12.09.2007. intimated that all the six units
HRT- 7.5m dia, U-1: 12/11 Flushing Tunnel heading excavation has been completed. would be commissioned
13.325Km long. U-2: 01/12 HRT: 11.3/13.816 km excavation completed. 1.66 km lining during 11th plan (from August,
Press. Shaft- 3nos. 3.8m U-3: 02/12 completed. 2011 to January, 2012.)
dia. U-4: 03/12 Excavation of all the access tunnels to the Machine Hall, GIS hall Considering the present pace
Power House- Under U-5: 03/12 & TRI completed. of civil works & mobilization
ground U-6: 03/12 TRT: 94% excavation completed. done at site, it is possible to
Turbine- Pelton The electro-mechanical works have been awarded to consortium commission the units as per
Cost: led by M/s VA tech Hydro and the contract has been signed on the revised schedule,
Original: 5705.55 Crs. 18.10.2007. indicated by the project
Latest: 5705.55 Crs. Diversion tunnel: Excavation completed. authorities provided no major
Adits: Inlet Adit to Diversion Tunnel, Intermediate Adit to geological surprises /
Diversion Tunnel, Zero Adit to Intake, Adit to flushing tunnel, bottlenecks are encountered
Adit to desilting basin, Adit to Power House top, Adit 2,3,4 & 5 to and completion of E&M
HRT completed. works is done for all the units
Pressure shaft: Inclined portion PS-1 577/588 and PS-2 well in time..
496/571 m completed.
Power House: MAT completed.
B. Projects likely to give benefits beyond 11th Plan
Central
35 Kishanganga J&K Infrastructure works are under progress. Disturbance in Kashmir valley
(NHPC), J&K NR Revised CCEA approval accorded in December, 2008. affected the progress of
20.07.07 CS Turnkey execution of the project awarded to M/s Kishanganga works.
3x110 Execution Consortium with HCC ld. As lead partner, M/s Halcow group ltd.,
330 2016-17 UK as partner and M/s SELI SJZA Italy, M/s BHEL, M/s DSD
Cost: 2016-17 NOELL Gmbll Germany & M/s PES engineers Pvt. Ltd. As sub-
Original: 3642.04 contractor on 22.01.2009
Latest: 3642.04 Diversion Work: 225 m benching excavation completed out of
569m.
HRT : 614 m excavation completed out of 8630 m.
11
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
36 Pare Ar. P Civil works awarded to M/s HCC ltd. on 12.10.2009.
M/s NEEPCO NER Infrastructure & Pre-construction activities are in progress.
2x55 = 110 MW CS
Execution
12th Plan
State
37 Baglihar-II J&K Some works already taken up with Baglihar-I.
JKPDC NR Works have been allotted but yet to start.
3x150= 450 MW SS
Execution
2014-15
2014-15
38 Kashang-I H.P. Civil & HM works awarded to M/s HCC Ltd. in February, 2009
H.P. Power Corpn. Ltd. NR and effective date for commencement of works is 09.04.2009.
31.07.08 SS E&M works awarded to M/s Andritz India on 29.04.2010.
65 MW Execution Excavation of Adits, Power house, pressure shaft, Transformer
12th Plan hall, TRT etc. are in progress.
12th Plan
39 Thottiyar Kerala Civil Works:
KSEB SR Weir: 1989 cum excavation out of total 5850 cum completed.
1x30 + 1x10= 40 MW SS Approach Channel & Intake: 2749 cum out of 9100 cum done.
Cost: Execution Power House, switchyard & allied works: 12715 cum excavation
Original: 14400 lakhs out of 44500 cum done.
Latest: 14400 lakhs 12th Plan
12th Plan
Private
40 Tidong-I H.P. Civil works awarded in November, 2008.
M/s Nuziveedu Seeds NR Infrastructure & Pre-construction activities are in progress.
100 MW PS
Execution
12th Plan
12th Plan
41 Phata Byung Uttarakhand Work awarded on 14.02.2008 as EPC contract to M/s Lanco
M/s Lanco NR Infratech Ltd. With a construction period of 36 months.
06.10.2008 PS Approach roads to Dam U/S, D/S , Adit-II, Adit-III, surge shaft
2x38 MW = 76 MW Execution Top,,Power House and Gabni Gad completed and approach road
Broad Features: to vertical pressure shaft is in progress.
12th Plan Diversion Tunnel Excavation and concreting completed.
Dam – 26m high 12th Plan Dam concreting are in progress.
HRT- 3.2 m dia & P.H.: Heading excavation in progress.
9.38 km length
Pressure Shaft: 2.5m
dia, 662.25 m length
Turbine – Frances

42 Singoli Bhatwari Uttarakhand Civil works awarded on 6.5.2008.


M/s L&T NR River diversion – Excavation & concreting of diversion tunnel in
11.07.2008 PS progress.
3x33 MW = 99 MW Execution HRT &HRC: Excavation 1175.5/11255 m completed.
Broad Features: Pressure Shaft: Excavation 221/485 m completed.
2013-14
2013-14
43 Teesta-VI Sikkim Infrastructure works such as roads and bridges are in progress.
LANCO ER Land acquisition is in process. Excavation works of Adits
27.12.2006 PS (1+2+3+4+4A+HRT-2) 356786/2447447 completed.
4x125= 500 MW Execution Surge Tank Excavation 69054/278183 completed.
Cost: Pressure Shaft: 8457/18456 cum. completed.
Original: 3283.08 2012-13 In power house complex Excavation of Main access Tunnel,
Latest : 3283.08 12th Plan ventilation Tunnel, Adit to Transformer cavern, cable tunnel and
Broad Features: Adit to BFV chamber completed.
Barrage: 34.27m high TRT: 30275/354714 cum completed.
HRT- 2nos,13.7km long
Pressure shaft: 4nos. 5.4m
dia. 130m av length,
12
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
13.325Km long.
TRT: 4nos 250m av
length, 8.5m dia.
Power House- Under
ground
Turbine- Francis
44 Rangit-IV Sikkim Work for construction of Head Race Tunnel is awarded to
Jal Power corp. Ltd. ER M/s Coastal Projects Pvt. Ltd. on 22.11.2007. Dam & Intake work
06.07.2007 PS has been awarded on 01.02.08. E&M work under process of
3x40= 120 MW Execution award.
Cost: Dam & Intake works: Excavation 49000/156000 cum completed.
Original: 726.17 Crs. 2012-13 Excavation of road diversion tunnel has been completed.
12th Plan HRT: Adit-1 & Adit 2 excavation completed and HRT excavation
Latest : 726.17 Crs. in progress and 959m/6488 m completed. Construction Power and
Broad Features: infrastructure works such as roads are in progress.
Dam: Concrte gravity 44m Power House: Civil works awarded on 23.05.2008. The work of
high .HRT :6.5km long approach road to power house in progress.
6.4m dia E&M Works: LOI placed on 28.08.09 to M/S ANDRITZ &
Power House : Surface Balance of Plant (E&M) has been issued on 14.08.2009. Bids
Turbine: Francis were received/opened on 27.11.2009. Bids have been received
HRT- 2nos,13.7km long from bidders and same are under evaluation.
Pressure shaft: 4nos. 5.4m
dia. 130m av length,
13.325Km long.
TRT: 4nos 250m av
length, 8.5m dia.
Power House- Under
ground
Turbine- Francis
45 Jorethang Loop Sikkim Civil & E&M works awarded.
M/s DANS Energy ER LOI issues by Govt. of Sikkim on 01.03.2005. Entire civil and
96 MW PS HM works awarded to M/s SEW Construction Ltd on 2nd March,
2x48 = 96 MW Execution 2008. E&M works awarded to M/s Alstom Project India Ltd. on
26th May, 2008.
12th Plan Tunneling construction work is in progress at adit, Barrage and
12th Plan power house area.

46 Bhasmey Sikkim Forest clearance under process. Commencement of land


Gati Infrastructure ER acquisition started. MOA of the project earlier cancelled by the
3x17= 51 MW PS State Government was restored. Environment clearance obtained
Execution on 15.05.2007. Civil works awarded in Dec. 2009.

2012-13
2012-13

13