Professional Documents
Culture Documents
Definitions
FOR THE PURPOSE OF THIS MANUAL, A QUALIFIED PERSON IS FAMILIAR WITH THE
INSTALLATION, CONSTRUCTION AND OPERATION OF THE EQUIPMENT AND THE
HAZARDS INVOLVED.
The person is trained in the proper care and use of protective equipment such as
rubber gloves, hard hat, safety glasses or face shields, flash clothing, etc., in
accordance with established safety practices.
DANGER
DANGER LABEL INDICATES AN IMMINENTLY HAZARDOUS SITUATION WHICH, IF NOT
AVOIDED, WILL RESULT IN DEATH OR SERIOUS INJURY.
WARNING
WARNING LABEL INDICATES A POTENTIALLY HAZARDOUS SITUATION WHICH,
IF NOT AVOIDED, COULD RESULT IN DEATH OR SERIOUS INJURY.
CAUTION
CAUTION LABEL INDICATES A POTENTIALLY HAZARDOUS SITUATION WHICH,
IF NOT AVOIDED, COULD RESULT IN DEATH OR SERIOUS INJURY.
Storage instruction
As soon as the busway arrive at the site, Inspect each busway piece for
possible damage or contamination.
Contact surfaces must be clean. However, do not attempt to polish
tarnished contact surfaces.
If there is no damage, restore the packing to its original condition to
prepare for job site storage.
Do not lay the busway directly on the ground. Always place pieces of wood
under the busway and stack up firmly as shown. Never put it upright in
storage or during installation.
X X
WARNING
Lifting busway without the proper Lifting devices may result in busway
damage, serious injury or death.
Phase sequence
G
A
B
C
N
3Phase, 4Wire
+Housing Ground,
+50%, 100% Ground bus
Typical bus bar phase sequence is G-A-B-C-N top to bottom when internal (or
isolated) ground and neutral are provided. Joint supports on the ends of each
busway section include an arrow that points “up” to the "ground side" of the
busway. The rating nameplate is placed on the “neutral side”.
WARNING
WARNING: The embossed arrows on the Joint Covers must point in the
same direction as arrows on the Joint Supports.
Installation of busway
1. Minimum clearance
A phase
B phase
C phase
N phase
Typical bus bar phase sequence is G-A-B-C-N top to bottom when internal
ground and neutral are provided. Joint supports on the ends of each busway
section include an arrow that points “up” to the "ground side" of the busway. The
rating nameplate is placed on the “neutral side”.
The item number sequence identified on these installation drawings must be
followed exactly to insure proper installation.
CAUTION
Housing end ramps provide ground continuity as well as sealing surfaces
on water resistive ratings. Do not damage these housing end ramps prior
to or during installation.
Water resistive ratings may be jeopardized if the end ramps are
damaged.
WARNING
Ensure that the bus bars and housing end ramps engage properly
between the joint stack and insulator plates as shown in Figure.
Joint assembly instruction
1
Check the contact surface has no
damage and contamination.
Inspect the busway run for
straightness in all planes
Insert the “bar ends” to joint kit
slowly.
Bar end
Joint kit
2
Using the torque wrench,
tighten the outer bolt head of
joint bolt until break off (shear
torque =800kgf·cm)
3
Plug in Box
R T
S N
Plug in Feeder
Support
16/31
설치
17/31
Horizontal support
1. Trapeze Hangers Installation
Trapeze Hangers, and single drop rod hangers are used to support
horizontal busway runs on maximum(3m) centers.(desired regular interval
= 1500mm)
Ø12mm steel drop rods and hardware are to be furnished by the installer.
Avoid positioning hangers at busway joints and plug-in openings, where
possible. Maintain good alignment along the busway run.
Second H
adjusting
nut
Base channel
Jam nut
Spring hanger
Rigid hanger
Spring Hangers are used to support vertical (riser) busway. Note that no joint may be
installed less than 500 mm above the floor. No joint component should fall within the
floor penetration.
After installing the busway section through the floor, perform the following procedure :
1. Loosen the hanger bolt.
2. Assemble the hangers to each side of the busway.
3. Position the hangers on the busway so that the base channel rests on the floor or
other support. A floor flange may be placed under the hanger, but it will not support the
busway weight.
4. Fit the hanger clamps to the busway housing and hand tighten the hanger
bolts.
5. Anchor the base channels to their supports.
6. Tighten the hanger bolts.
7. Install the next length and make the joint assembly
8. If springs are furnished, they must be adjusted as shown picture. Determine
the required dimension H of the hanger springs, found on the layout drawing.
Using the Second adjusting nuts , set the springs on the hangers to the
dimension H. With the springs adjusted, hold First adjusting nut in position and
tighten jam nut against First adjusting nut to retain the spring setting.
Tighten all jam nuts using this procedure.
Actual measurement
L + 42
Case 1.
21 21
L + 250
Case 2.
L - 250
Maintenance and checking
1. External appearance
Checking to see whether there is deformation, damage, dirt, etc. throughout the
whole length of the busway and whether there is dislocation bending and other
abnormality of the connecting covers, hanger and plug-in appliances.
2. load condition
WARNING
After completing installation, recheck all joint bolts with a torque wrench
for 800kg-cm torque. A Joint Bolt without a red tag may still not be tight.
The bolt may have been loosened to adjust or test the busway.
Busway installation checklist
11. Did you check for proper clearances for the bus at floors, walls,
ceilings, other bus, and trades? (Never use cement to seal between the Yes/No
bus and floors or walls.)
12. Have all shipping screws been removed from expansion lengths? Yes/No
13. Was all foreign material removed from the installed bus? Yes/No
14. Was a final megohm test performed when all bus was installed? Yes/No