Professional Documents
Culture Documents
15 - 17 OGOS 2006
INSTITUT PEMBANGUNAN KOMPETENSI ,
IPS, KUALA LUMPUR
DISEDIAKAN OLEH
MOHD YAHAYA BIN AHMAD PEng
PRELIMINERIES POND DESIGN CONCEPT
1. SITE SELECTION
structures
Secondary Outlet
(Emergency Spillway)
PLAN
SECTION A-A
Outlet Control
Bypass Flows
Provision should be made in a dry detention basin to bypass low flows through or around the basin. This is
necessary to ensure that the basin floor, particularly if it is grassed, is not inundated by small storms or
continually wetted by dry weather baseflow. The minimum amount of bypass should be one half the
1 month ARI flow.
The sizing of a detention facility requires an inflow hydrograph, a stage-storage curve, and a stage-discharge
curve (sometimes called a rating curve). Inflow hydrographs for a range of design storm durations must be
routed through the basin to determine the maximum storage volume and water level in the basin
corresponding to the maximum allowable outflow rate.
The design storm duration that will produce the maximum storage volume in a basin will vary depending on
catchment, rainfall, and basin outflow characteristics, and is typically somewhere between one and three times
the peak flow time of concentration for the basin catchment. The design storm duration that produces the
maximum storage volume is called the critical duration.
Inflow Hydrographs
Various method can be use such as Time Area Method, Non Linear Resevoir Method, Kinematic Wave Method and Rational
Method Hydrograph Method.
A stage-storage relationship defines the relationship between the depth of water and storage volume in the
storage facility. The volume of storage can be calculated by using simple geometric formulas expressed as a
function of storage depth.
storage (Ip
A stage-discharge curve defines the relationship between the storage water depth and the discharge or oufflow
from a storage facility. A single composite stage-discharge curve should be developed2foreach design storm
outlet arrangement, which requires consideration of the stage and discharge rating relationship for each outlet
component.
0 5 10 15 20 25 30
Discharge (curnec)
Classification
An embankment that raises the water level a specified amount as defined by the appropriate dam safety group
(generally 1.5 m to 3 m or more above the usual mean low water height, when measured along the
downstream toe of the embankment to the emergency spillway crest), is classified as a dam.
The maximum pond depth within the basin should not exceed 3.0 m under normal operating conditions for the
maximum design flow for which the primary outlets have been designed, i.e. the maximum design storm ARI
flow that does not cause the emergency spillway to operate under normal design conditions.
Top Widths
Table 20.1 Minimum Recommended Top Width for Earthen Embankments (USDA, 1982)
Under 3 2.4
3 to 4.5 3.0
Side Slopes
For ease of maintenance, the side slopes of a grassed earthen embankment and basin storage area should not
be steeper than 4(H):l(V). However, to increase public safety and facilitate ease of mowing, side slopes of
6(H): 1(V) (or flatter) are recommended.
Bottom Grades
The floor of the basin shall be designed with a minimum grade of l0/0 to provide positive drainage and minimise
the likelihood of ponding.
Freeboard
The elevation of the top of the settled embankment shall be a minimum of 0.3 m above the water surface in
the detention basin when the emergency spillway is operating at maximum design flow.
Primary outlets are designed for the planned release of water from a detention basin. Basin outlets are
ordinarily uncontrolled (i.e. without gates or valves), and may be a single stage outlet structure or several
outlet structures combined to provide multi-stage outlet control.
Cross-section
(b) Riser Structure
(single and multi-level outlets)
-. ........... ............-
View from Downstream
Orifices
For a single circular orifice, illustrated in Figure 0.5(a), the orifice flow can be determined using Equation 0.1.
where,
Q = the orifice flow rate (m3/s)
Cd = orifice discharge coefficient (0.40 - 0.62)
A, = area of orifice (m2), ~r0 3 4
Do = orifice diameter (rn)
H, = effective head on the orifice measured from the centre of the opening (m)
g = acceleration due to gravity (9.81 m/s2)
4
(a) Free Fall
(c) Multple
Weirs
Typical sharp-crested weirs are illustrated in Figure 20.6. Equation 20.2 provides the discharge relationship for
sharp-crested weirs with no end contractions (illustrated in Figure 20.6(a)).
where,
Q = weir discharge (m3/s)
Cm= 1.81 + 0.22 (HIH,), sharp-crested weir discharge coefficient
B = weir base width (rn)
H = head above weir crest excluding velocity head (m)
(a) No end contractions (b) With end contractions
where,
Q = weirdischarge (m3/s)
CBCW=broad-crested weir coefficient
B = weir base width (m)
H = effective head above weir crest (m)
The discharge through a V-notch weir is shown in Figure 0.7 and can be calculated using:
Q = 1.38 tan :( ) H
where,
Q = weir discharge (m3/s)
6 = angle of V-notch (degrees)
H = head on apex of V-notch (m)
Section A-A
where,
Q = weir discharge (m3/s)
H = head above horizontal sill (m)
Dimensions a, b, x and y are as shown in Figure 20.8.
Culverts
Pipe or box culverts are often used as outlet structures for detention facilities. The design of these outlets can
be for either single or multi-stage discharges
Erosion Protection
The purpose of a secondary outlet (emergency spillway) is to provide a controlled overflow for flows in excess
of the maximum design storm ARI for the storage facility.
Overflow Weir
The most common type of emergency spillway used is a broad-crested overflow weir cut through original
ground next to the embankment. The transverse cross-section of the weir cut is typically trapezoidal in shape
for ease of construction.
Q = ,C B H;.' (20.6)
Where,
Q = emergency spillway discharge (m3/s)
CSp= spillway discharge coefficient
B = emergency spillway base width (m)
Hp = effective head on the spillway crest (m)
The discharge coefficient CSp in Equation 20.6 varies as a function of spillway base width and effective head.
Design values for CSpare provided in Design Chart 20.2.
7. PUBLIC SAFETY
Retarding basins should be provided with signs that clearly indicate their purpose and their potential
danger during storms. Signs should be located such that they are clearly visible at public access points
and at entrances and exits to outlet structures.. Gratings or trash racks may be used to help prevent this
happening. A pipe rail fence should be provided on steep or vertical drops such as headwalls and
wingwalls at the inlet and outlet to a primary outlet structure to discourage public access.
8. LANDSCAPING
Aesthetics of the finished facility is therefore extremely important. Wherever possible, designs should
incorporate naturally shaped basins with landscaped banks, footpaths, and selective planting of
vegetation to help enrich the area and provide a focal point for surrounding development.
Consultation
Planned Maintenance and Inspection
Effect of Design on Maintenance Costs
Grassed Areas and Embankments
Waterways
Primary Outlets
Sediment Removal
Structural Repairs and Replacement
STORM PAY
Version 1.0
Feb 2006
The user must always start the storm pay and come back to main window after data input using a
input box on colour and view a result using a output box by click &?%.
Main window
The user can refer Urban Stormwater Management Manual, MSMA (2000) for further detail
and description when using a Storm Pay.
At How to use worksheet, create a new project by moving a mouse to a button box under
Input in General information at Catchment as shown below.
Enter a "project title", "state", "nearest hydrology station" and "area of development" in
General Information at I n ~ u worksheet
t as shown below.
t
ProJect tile.
---
State :
--- - I
1 Perak 1
POND 1
I
I t
Calculating a Precipitation
Time of concentration
At How to use worksheet, before calculated a precipitation at selected duration, td, the
user must calculated tc pre and tc post by moving a mouse to a button box under Input in
Time of concentrati~onat Precipitation as shown below.
Enter a "length", "slope", "n manning", "area" and "wetted parameter" in Time of
Concentration at Input worksheet as shown below.
-
to,min
Length, m I 840 I
-Slope,
- %
n manning
P
-- M, min
Length, m
---V-- -
I
Slope, W
P -- IS
n
-- manning -----. -- 6.011
Area,
---.--
A (m2] 2
Wetted parameter, P (ml I 1 6
Either tc pre or tc post, to view the output, moving a mouse to a button box under Output
in time of concentration at Precipitation as shown below.
At How to use worksheet, to calculated a intensity at selected duration, td, for selected
system, the user can moving a mouse to a button box under Input in Intensity at
Precipitation as shown below.
Enter a "Fd", "AN at selected system", "a, b, c & d", and/ or "deduction factor" in
Intensity at Input worksheet as shown below.
The output as shown in rfall insity minorari, rfall insity majorari and rfall insity
emergency worksheet.
Selection of intensity
At How to use worksheet, the user can moving a mouse to a button box under Input in
Intensity and temporal pattern at Selection of Intensity as shown below.
At Intenct temp petrn worksheet, for selection of intensity, the user must related to tc
post. The selection of intensity must start from 0.5 tc post to 3 tc post. The value for
selected tc and intensity for selected system must gain from rfall insity minorari, rfall
insity majorari and rfall insity emergency worksheet. For values and referred table for
temporal pattern, the user must refer to MSMA. Make sure the values represented
selected tc (0.5 tc post to 3 tc post) as shown on Tables below.
Table 13.81 -
emo oral patterns west coast of pemwxr m w i a I I i I i
The method used in calculating Loss and excess rainfall is Loss Method. At How to use
worksheet, either for pre-development or post-development, at selected ART, the user can
calculated loss and excess rainfall by moving a mouse to a button box under Input in Loss
and excess rainfall at Precipitation as shown below.
Enter a "initial losses", "% pervious", "& impervious7', and "% propotional loss" in loss
& excess rainfall Input worksheet as shown below.
Propotionctlloss. % I 20 I I o I
Impervious,
-.--- X . - .- -
---- 0 I "---- \ so 'I
Propotional toss. % I 20 0 I
mlMhod llreo for pre dm., ma keo for port dew., mZ
lime kea Method 0.5 tc tc 0.5 1, t, 2k 3t,
A1 3461 S 3461 .5 3461.5 3461.5 3461.5 71923.0
A2 1 3461 .S 3461.5 3461.5 3461.5 3461.5 126730.0
85
I
135
tinergency
---. -- ---- --- - tp [min) 25 25 40 60
I
--- Qo [m3/s] 8.251
--------- - - -- ------- --- --
Max. vol. estimated (m3] 8627
F
pond parameter 1 I 1 I 1
----- Stalt detention level 0.0 m
Start invert level i 31.00 m
- i -
--- Max. bund high 32.50 m
/ Max. high when reach max. volume 32.10 m I
number 20
cliameter 150 rnM
0.02
Area mmz 17673.75
diameter 0.15 m
0.075 m
H Ho Q m3/s (basis)
0.00 0.000 0.000
0.10 0.025 0.153
0.20 0.125 0 343
0.30 0.225 0.4mf
I Time lndcx I Inflow l 1 Inflow l 1 Inflow l 1
APPENDIX
Polynomial expressions in the form of Equation 0.1 have been fitted to the published IDF curves for
the 35 main citiesltowns in Malaysia.
= a + b ln(t) + c(ln(t,l,I2 + d ( l t ~ ( t ) ) ~ (0.1)
where,
R4 = the average rainfall intensity (mm/hr) for ARI and duration t
R = average return interval (yti3n)
t = duration (minutes)
a to d are fmng constants dependent on ARI.
The design rainfall depth Pdfor a short duration d (minutes) is given by,
pd =&I -F~(P60 - 5 0 ) (0.2)
where Pso, PbOare the 30-minute and 60-minute duration rainfall depths respectively, obtained from
the published design curves. FD is the adjustment factor for storm duration
Equation 0.2 should be used for durations less than 30 minutes. For durations between 15 and 30
minutes, the results should be checked against the published IDF curves. The relationship is valid for
any ARI within the range of 2 to 100 years.
Note that Equation 0.2 is in terms of rainfall depth, not intensity. If intensity is required, such as for
roof drainage, the depth Pd (mm) is converted to an intensity I (mm/hr)'by dividing by the duration d
in hours:
I, Pd (0.3)
d
~uratio
n
(minutes)
1 ,
Table 0.1 Values of FDfor Equation 0.2
P24h
West Coast
120 150
(,mm) I East Coast
All
The following preliminary equations are recommended for calculating the 1,3,6-month and 1 year
ARI rainfall intensities in the design storm, for all durations:
where, 0.083ID ,0.25ID ,0.5ID and ' I ~are the required 1,3,6-month and 1-year ARI rainfall intensities for
any duration D, and 2 ~ is D the 2-year ARI rainfall intensity for the same duration D, obtained from IDF
curves.
where,
to = overland sheet flow travel time (minutes)
L = overland sheet flow path length (m)
n = Manning's roughness value for the surface
S = slope of overland surface (Yo)
Note : Values for Manning's 'n ' are given in Table 0.2.
Some texts recommend an alternative equation, the Kinematic Wave Equation. However this
theoretical equation is only ,valid for uniform planar homogeneous flow. It is not recommended for
practical application.
* From Crawford and Linsley (1966) - obtained by calibration of Stanford Watershed Model.
** From Engman (1986) by Kinematic wave and storage analysis of measured rainfall runoff data.
However, it is incorrect to simply add the values of to for each segment as Equation 0.1 is based on the
assumption that segments are independent of each other, i.e. flow does not enter a segment fiom
upstream.
Utilising Equation 0.1, the following method (Australian Rainfall & Runoff, 1998) for estimating the
total overiand flow travel time for segments in series is recommended. For two segments, termed A
and B (Figure 0.1):
) ~ B ( L ~ + L-
t ~ o t a l= t ~ ( b + B )t ~ ( ~ ) (0.6a)
where,
LA = length of flow for Segment A
LB = length of flow for Segment 6
~AW) = time of flow calculated for Segment A over
length LA
tBL..) =time for Segment B over the lengths indicated
For each additional segment, the following time value should be added:
t~ = ~ ~ ( L T ~-I )ti(Lrota1 - 4 ) (0.6b)
where,
tadd = time increment for additional segment
LTotal = total length of flow, including the current segment i
Lj = length of flow for segment i
t,( ...) = time for the segment i over the lengths indicated
Segment
Segment
B
\ \ \ \ \ \ \
Travel
Time
This procedure must be applied iteratively because the travel time is itself a function of rainfall
intensity.
The flow normally varies along the length of a kerbed gutter due to lateral surface inflows. Therefore,
the flow velocity will also vary along the length of a gutter. As the amount of gutter flow is not
known for the initial analysis of a sub-catchment, the flow velocity and hence the flow time cannot be
calculated directly. An initial assessment of the kerbed gutter flow time must be made.
An approximate kerbed gutter flow time can be estimated from Design Chart O.Error! Bookmark not
defined. or by the following empirical equation:
where,
t, = kerbed gutter flow time (minutes)
L = length of kerbed gutter b w (m)
S = longitudinal grade of the kerbed gutter (%)
Equation 0.2 should only be used for L < 100 metres. Kerbed gutter flow time is generally only a
small portion of the time of concentration for a catchment. The errors introduced by these
approximate methods of calculation of the flow time result in only small errors in the time of
concentration for a catchment, and hence high accuracy is not required.
From which,
n.L ~
t,, = - 2 1 ~3 1 / 2 (0.8b)
60
where,
V = average velocity (m/s)
n = Manning's roughness coefficient
R = hydraulic radius (m)
S = friction slope (m/m)
L = length of reach (m)
tch = travel time in the channel (minutes)
Where an open channel has varying roughness or depth across its width it may be necessary to
sectorise the flow and determine the average velocity of the flow, to determine the flow time.
For natural/landscaped catchments and mixed flow paths the time of concentration can be found by
use of the Bransby-Williams' Equation 0.10 (AR&R, 1987). In these cases the times for overland flow
and channel or stream flow are included in the time calculated.
Here the overland flow time including the travel time in natural channels is expressed as:
where,
t, = the time of concentration (minute)
, = a conversion factor, 58.5 when area A is in km2,
F
or 92.5 when area is in ha
L = length of flow path from catchment divide to outlet (km)
A = catchment area (km2 or ha)
S = slope of stream flow path (m/km)
The Rational Formula is one of the most frequently used urban hydrology methods in Malaysia. It
gives satisfactory results for small catchments only.
The formula is:
where,
Q, = yyear ARI peak flow (m3/s)
C = dimensionless runoff coefficient
''1, = yyear ARI average rainfall intensity over time of concentration, tc,(mm/hr)
A = drainage area (ha)
Table 4.3 Design Storm ARIs for Urban Stormwater Systems
Note: Hydrological Soil Group corresponds to the classification given by the U.S. Soil Conservation
Service. Well drained sandy soils are "A"; poorly drained clayey soils are "D". The texture of the
layer of least hydraulic conductivity in the soil profile should be considered. Caution should be used in
applying values from the above table to sandy soils (Group A). Source: XP-SWMM Manual (WP-
Software, 1995).
Table O.Al Coefficients for the IDF Equations for the Different Major Cities and Towns in Malaysia
(30 5 t 5 1000 min)
I / Highland
Pahang Kuantan
I
Terengganu
I Kuala
Terengganu
APPENDIX 0.A DESIGN TEMPORAL PATTERNS
Table O.B1 Temporal Patterns -West Coast of Peninsular Malaysia
No. of
Duration Time Fraction of Rainfall in Each Time Period
(min) Periods
10 2 0.570 0.430 -
15 3 0.320 0.500 0.180 -
30 6 0.160 0.250 0,330 0.090 0.110 0.060 -
60 12 0.039 0.070 0.168 0.120 0.232 0.101 0.089 0.057 0.048 0.031 0.028 0.017
120 8 0.030 0.119 0.310 0.208 0.090 0.119 0.094 0.030 -
180 6 0.060 0.220 0.340 0.220 0.120 0.040 -
360 6 0.320 0.410 0.110 0.080 0.050 0.030 -
n, 10 min Duration
Time Period
1 2
Time Period
3
I 1 2 lim
1 e Per~od
4
1 2 3 4 5 6 7 8 9 1 0 1 1 I 2 1 2 3 4 5 6 7 8
Time Period Time Per~od
1 2 3 4
Time Period
5
1 I 1 2 3
lime Period
4 5 6
Table 0.B2 Temporal Patterns - East Coast of Peninsular Malaysia '
No. of
Fraction of Rainfall in Each Time Period
(min) Periods
120
180
360
1 2 3 4 5 6
I 2 1 2 3
Time Jer~od Time Period
Time Period
60 minute Durat~on
0.3 1
1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 2 3 4 5 6 7 8
Time Period Time Per~od
1 2 3 4 5 6 1 2 3 4 6
Time Period lime Period
(# these patterns can also be used in Sabah and ak, until local studies are carried out)
CULVERT:
Outkt Control Nomograph- Concrete Pipe Culvert Rowing Full with 27-30
n = 0.012
-
15 - 17 OGOS 2006
INSTITUT PEMBANGUNAN KOMPETENSI ,
IPS, KUALA LUMPUR
DISEDIAKAN OLEH
MOHD YAHAYA BIN AHMAD PEng
'RELIMINERIES POND DESIGN CONCEPT
1. SITE SELECTION
PLAN
SECTION A-A
Outlet Control
Bypass Flows
Provision should be made in a dry detention basin to bypass low flows through or around the basin. This is
necessary to ensure that the basin floor, particularly if it is grassed, is not inundated by small storms or
continually wetted by dry weather baseflow. The minimum amount of bypass shouid be one half the
1month ARI flow.
The sizing of a detention facility requires an inflow hydrograph, a stage-storage curve, and a stage-discharge
curve (sometimes called a rating curve). Inflow hydrographs for a range of design storm durations must be
routed through the basin to determine the maximum storage volume and water level in the basin
corresponding to the maximum allowable outflow rate.
The design storm duration that will produce the maximum storage volume in a basin will vary depending on
catchment, rainfall, and basin oufflow characteristics, and is typically mewh here between one and three times
the peak flow time of concentration for the basin catchment. The design storm duration that produces the
maximum storage volume is called the critical duration.
Inflow Hydrographs
Various method can be use such as Time Area Method, Non Linear Resevoir Method, Kinematic Wave Method and Rational
Method Hydrograph Method.
A stage-storage relationship defines the relationship between the depth of water and storage volume in the
storage facility. The volume of storage can be calculated by using simple geometric formulas expressed as a
function of storage depth.
=rase (*
A stage-discharge curve defines the relationship between the storage water depth and the discharge or oufflow
from a storage facility. A single composite stage-discharge curve should be developed,for each design storm
outlet arrangement, which requires consideration of the stage and discharge rating relationship for each outlet
component.
Classification
An embankment that raises the water level a specified amount as defined by the appropriate dam safety group
(generally 1.5 m to 3 m or more above the usual mean low water height, when measured along the
downstream toe of the embankment to the emergency spillway crest), is classified as a dam.
The maximum pond depth within the basin should not exceed 3.0 m under normal operating conditions for the
maximum design flow for which the primary outlets have been designed, i.e. the maximum design storm ARI
flow that does not cause the emergency spillway to operate under normal design conditions.
Top Widths
Table 20.1 Minimum Recommended Top Width for Earthen Embankments (USDA, 1982)
Under 3
Side Slopes
For ease of maintenance, the side slopes of a grassed earthen embankment and basin storage area should not
be steeper than 4(H):l(V). However, to increase public safety and facilitate ease of mowing, side slopes of
6(H): 1(V) (or flatter) are recommended.
Bottom Grades
The floor of the basin shall be designed with a minimum grade of 1% to provide positive drainage and rninimise
the likelihood of ponding.
Freeboard
The elevation of the top of the settled embankment shall be a minimum of 0.3 m above the water surface in
the detention basin when the emergency spillway is operating at maximum design flow.
Primary outlets are designed for the planned release of water from a detention basin. Basin outlets are
ordinarily uncontrolled (i.e. without gates or valves), and may be a single stage outlet structure or several
outlet structures combined to provide multi-stage outlet control.
Cross-section
(b) Riser Structure
(single and multi-level outlets)
-. .
........- . :______.._..-
Orifices
For a single circular orifice, illustrated in Figure O.S(a), the orifice flow can be determined using Equation 0.1.
where,
Q = the orifice flow rate (m3/s)
Cd = orifice discharge coefficient (0.40 - 0.62)
A, = area of orifice (m2), n 0 8 4
Do = orifice diameter (m)
H, = effective head on the orifice measured from the centre of the opening (m)
g = acceleration due to gravity (9.81 m/s2)
(c) Multple
Weirs
Typical sharp-crested weirs are illustrated in Figure 20.6. Equation 20.2 provides the discharge relationship for
sharp-crested weirs with no end contractions (illustrated in Figure 20.6(a)).
where,
Q = weir discharge (m3/s)
CScw= 1.81 + 0.22 (H/H,), sharp-crested weir discharge coefficient
B = weir base width (m)
H = head above weir crest excluding velocity head (m)
(a) No end contractions (b) With end contractions
Q =c- B (20.3)
where,
Q = weir discharge (m3/s)
CBCW=broad-crested weir coefficient
B = weir base width (m)
H = effective head above weir crest (rn)
The discharge through a V-notch weir is shown in Figure 0.7 and can be calculated using:
Q = 1.38 tan ;( ) H
where,
Q = weir discharge (m3/s)
B = angle of V-notch (degrees)
H = head on apex of V-notch (rn)
Section A-A
where,
Q = weir discharge (m3/s)
H = head above horizontal sill (m)
Dimensions a, b, x and y are as shown in Figure 20.8.
Culverts
Pipe or box culverts are often used as outlet structures for detention facilities. The design of these outlets can
be for either single or multi-stage discharges
Erosion Protection
The purpose of a secondary outlet (emergency spillway) is to provide a controlled ovefflow for flows in excess
of the maximum design storm ARI for the storage facility.
Overflow Weir
The most common type of emergency spillway used is a broad-crested overflow weir cut through original
ground next to the embankment. The transverse cross-section of the weir cut is typically trapezoidal in shape
for ease of construction.
The discharge coefficient CSp in Equation 20.6 varies as a function of spillway base width and effective head.
Design values for CSp are provided in Design Chart 20.2.
7. PUBLIC SAFETY
Retarding basins should be provided with signs that clearly indicate their purpose and their potential
danger during storms. Signs should be located such that they are clearly visible at public access points
and at entrances and exits to outlet structures.. Gratings or trash racks may be used to help prevent this
happening. A pipe rail fence should be provided on steep or vertical drops such as headwalls and
wingwalls at the inlet and outlet to a primary outlet structure to discourage public access.
8. LANDSCAPING
Aesthetics of the finished facility is therefore extremely important. Wherever possible, designs should
incorporate naturally shaped basins with landscaped banks, footpaths, and selective planting of
vegetation to help enrich the area and provide a focal point for surrounding development.
Consultation
Planned Maintenance and Inspection
Effect of Design on Maintenance Costs
Grassed Areas and Embankments
Waterways
Primary Outlets
Sediment Removal
Structural Repairs and Replacement
STORM PAY
Version 1.0
Feb 2006
The user must always start the storm pay and come back to main window after data input using a
input box on colour and view a result using a output box by click -1,
Main window
The user can refer Urban Stormwater Management Manual, MSMA (2000) for further detail
and description when using a Storm Pay.
At How to use worksheet, create a new project by moving a mouse to a button box under
Input in General information at Catchment as shown below.
Enter a "project title", "state", "nearest hydrology station" and "area of development" in
General Information at Input worksheet as shown below.
Calculating a Precipitation
Time of concentration
At How to use worlcsheet, before calculated a precipitation at selected duration, td, the
user must calculated tc pre and tc post by moving a mouse to a button box under Input in
Time of concentration at Precipitation as shown below.
Enter a "length", "slope7', "n manning", "area" and "wetted parameter" in Time of
Concentration at Input worksheet as shown below.
n manning
Slope, X
n manning I I I 0.011 I
--Area, A (m')
Either tc pre or tc post, to view the output, moving a mouse to a button box under Output
in time of concentration at Precipitation as shown below.
At How to use worksheet, to calculated a intensity at selected duration, td, for selected
system, the user can moving a mouse to a button box under Input in Intensity at
Precipitation as shown below.
Enter a "Fd", "ARI at selected system", "a, b, c & d", and/ or "deduction factors' in
Intensity at Input worksheet as shown below.
Selection of intensity
At How to use worksheet, the user can moving a mouse to a button box under Input in
Intensity and temporal pattern at Selection of Intensity as shown below.
---5
F:bubUc domain storm pay-new proposal.xk - ' i i c t temp petrn'
At Intenct temp petrn worksheet, for selection of intensity, the user must related to tc
post. The selection of intensity must start from 0.5 tc post to 3 tc post. The value for
selected tc and intensity for selected system must gain from rfall insity minorari, rfall
insity majorari and rfall insity emergency worksheet. For values and referred table for
temporal pattern, the user must refer to MSMA. Make sure the values represented
selected tc (0.5 tc post to 3 tc post) as shown on Tables below.
-
T a b k 13.B1 Temporal patterns West Coast of Pensvlclr Malaysia
1 1 1 1 I 11 1 1
b c t i o n o f Rdmfall in Each lime Period
The method used in calculating Loss and excess rainfall is Loss Method. At How to use
worksheet, either for pre-development or post-development, at selected A N , the user can
calculated loss and excess rainfall by moving a mouse to a button box under Input in Loss
and excess rainfall at Precipitation as shown below.
Enter a "initial losses", "% pervious", "& impervious", and "% propotional loss" in loss
& excess rainfall Input worksheet as shown below.
Width, W 181.82
I 1
number
Polynomial expressions in the form of Equation 0.1 have been fitted to the published IDF curves for
the 35 main citieshowns in Malaysia.
ln(qt) = a + b ln(t) + c(ln(tjy2 + d(ln(t)13 (0.1)
where,
R& = the average rainfall intensity (mmfhr) for ARI and duration t
R = average return interval (years)
t = duration (minutes)
a to d are fitting constants dependent on ARI.
The design rainfall depth Pd for a short duration d (minutes) is given by,
' d =40- F~(P60 - 4 0 ) (0.2)
where P30, P60 are the 30-minute and 60-minute duration rainfall depths respectively, obtained from
the published design curves. FD is the adjustment factor for storm duration
Equation 0.2 should be used for durations less than 30 minutes. For durations between 15 and 30
minutes, the results should be checked against the published IDF curves. The relationship is valid for
any ARI within the range of 2 to 100 years.
Note that Equation 0.2 is in terms of rainfall depth, not intensity. If intensity is required, such as for
roof drainage, the depth Pd (mm) is converted to an intensity I (mm1hr)'by dividing by the duration d
in hours:
P24h (mm)
West Coast East Coast
100 180
The following preliminary equations are recommended for calculating the 1,3,6-month and 1 year
ARI rainfall intensities in the design storm, for all durations:
where, 0.083Z ,0.25I' ,0.5IDand 'ZD are the required 1, 3, dmonth and 1-year ARI rainfall intensities for
any duration D, and 2~~ is the 2-year ARI rainfall intensity for the same duration D, obtained from IDF
curves.
where,
to = overland sheet flow travel time (minutes)
L = overland sheet flow path length (rn)
n = Manning's roughness value for the surface
S = slope of overland surface (YO)
* From Crawford and Linsley (1966) - obtained by calibration of Stanford Watershed Model.
** From Engman (1986) by Kinematic wave and storage analysis of measured rainfall runoff data.
However, it is incorrect to simply add the values of to for each segment as Equation 0.1 is based on the
assumption that segments are independent of each other, i.e. flow does not enter a segment from
upstream.
Utilising Equation 0.1, the following method (Australian Rainfall & Runoff, 1998) for estimating the
total overland flow travel time for segments in series is recommended. For two segments, termed A
and B (Figure 0.1):
~ )~ B ( L ~ -+ f ~B(LA)
trofd~= ~ A ( L + ) (0.6a)
where,
LA = length of flow for Segment A
LB = length of flow for Segment 6
tNU) = time of flow calculated for Segment A over
length LA
tBc..)=time for Segment 6 over the lengths indicated
For each additional segment, the following time value should be added:
tadd = t i ( L w ) - t i ( L , ~ a ,- 4 ) (0.6b)
where,
Segment
Segment
B
b-~,+~l -l
\ \ \ \ \ \ \
Length
Travel
Time
This procedure must be applied iteratively because the travel time is itself a function of rainfall
intensity.
The flow normally varies along the length of a kerbed gutter due to lateral surface inflows. Therefore,
the flow velocity will also vary along the length of a gutter. As the amount of gutter flow is not
known for the initial analysis of a sub-catchment, the flow velocity and hence the flow time cannot be
calculated directly. An initial assessment of the kerbed gutter flow time must be made.
An approximate kerbed gutter flow time can be estimated from Design Chart O.Error! Bookmark not
d e f i n d or by the following empirical equation:
where,
t, = kerbed gutter flow time (minutes)
L = length of kerbed gutter flow (m)
S = longitudinal grade of the kerbed gutter (%)
Equation 0.2 should only be used for L < 100 metres. Kerbed gutter flow time is generally only a
small portion of the time of concentration for a catchment. The errors introduced by these
approximate methods of calculation of the flow time result in only small errors in the time of
concentration for a catchment, and hence high accuracy is not required.
From which,
t - "'L ~ s
2 1 3 'I2
* -60
where,
V = average velocity (mls)
n = Manning's roughness coefficient
R = hydraulic radius (m)
S = friction slope (m/m)
L = length of reach (m)
td, = travel time in the channef (minutes)
Where an open channel has varying roughness or depth across its width it may be necessary to
sectorise the flow and determine the average velocity of the flow, to determine the flow time.
where,
L = pipe length (m)
V = average pipe velocity (mls)
0.0.2 Time of Concentrationfor Natural Catchment
For natural/landscaped catchments and mixed flow paths the time of concentration can be found by
use of the Bransby-Williams' Equation 0.10 (AR&R, 1987). In these cases the times for overland flow
and channel or stream flow are included in the time calculated.
Here the overland flow time including the travel time in natural channels is expressed as:
where,
tc = the time of concentration (minute)
F, = a conversion factor, 58.5 when area A is in krn2,
or 92.5 when area is in ha
L = length of flow path from catchment divide to outlet (krn)
A = catchment area (km2or ha)
S = slope of stream flow path (m/km)
The Rational Formula is one of the most frequently used urban hydrology methods in Malaysia. It
gives satisfactory results for small catchments only.
The formula is:
where,
Note: Hydrological Soil Group corresponds to the classification given by the U.S. Soil Conservation
Service. Well drained sandy soils are "A"; poorly drained clayey soils are "D". The texture of the
layer of least hydraulic conductivity in the soil profile should be considered. Caution should be used in
applying values from the above table to sandy soils (Group A). Source: XP-SWMM Manual (WP-
Software, 1995).
Table O.Al Coefficients for the IDF Equations for the Different Major Cities and Towns in Malaysia
(30 I t < 1000 min)
Pahang
Kaub
Cameron
Highland
Temerloh
Terengganu Kuala
Terengganu
APPENDIX 0.A DESIGN TEMPORAL PATTERNS
Table O.B1 Temporal Patterns - West Coast of Peninsular Malaysia ,
No. of
Duration
Time Fraction of Rainfall in Each Time Period
(min) Periods
10 2 0.570 0.430 -
15 3 0.320 0.500 0.180 -
30 6 0.160 0.250 0.330 0.090 0.110 0.060 -
60 12 0.039 0.070 0.168 0.120 0.232 0.101 0.089 0.057 0.048 0.031 0.028 0.017
120 8 0.030 0.119 0.310 0.208 0.090 0.119 0.094 0.030 -
180 6 0.060 0.220 0.340 0.220 0.120 0.040 -
360 6 0.320 0.410 0.110 0.080 0.050 0.030 -
0.4
1 L 1 2 3 4 5 6
- -
1 2 3 4 5 6 7 8 9 1 0 1 1 1 2 1 2 3 4 5 6 7 8
Time Period Time Pertod
-
1 2 3
Trne Period
4 5
1 1 2 3
Tiwe Period
4 5 6
Table 0.B2 Temporal Patterns - East Coast of Peninsular Malaysia '
No. of
Duration Time Fraction of Rainfall in Each Time Period
(min) Periods
10 2 0.570 0.430 -
15 3 0.320 0.500 0.180 -
30 6 0.160 0.250 0.330 0.090 0.110 0.060 -
60 12 0.039 0.070 0.168 0.120 0.232 0.101 0.089 0.057 0.048 0.031 0.028 0.017
120 8 0.030 0.119 0310 0.208 0.090 0.119 0.094 0.030 -
180 6 0.190 0.230 0.190 0.160 0.130 0.100 -
360 6 0.290 0.200 0.160 0.120 0.140 0.090 -
Time Perrod
1 2 3 4 5 6 7 8 9 1 0 1 1 1 2
1 2 3 4 5 6 7 8
Time Period Time Period
1 2 3 4 5 6 1 2 3 4 5 6
Time Period Time Period
(# these patterns can also be used in Sabah and Sarawak, until local studies are carried out)
CULVERT:
-
Ir~letWef Nomograph Cormgated Metal Pipe (OIP) Culvert 27-25
I 27.7 1 -- - -
1
Oitical Depth in a Rectangular (Box) Section
1
27.9 27-29
27.10 Outlet Cmtrd Nomograph -Corn& Pipe CUMflowing Full with 27-30
n = 0.012
i
k.Chin Cbong Wing
Penganh
i P S Wayah Perukutwn
Banfir Di Kg. C h e m
b w , Sun@ Kenyong
p d a a uur row
LOKASI PROJEK
r 5.rr .=A I
DESIGN PEAK FLOW
FLOOD HYDROGRAPH
- Doenion n o r k
flood r l o r l g paad
Pond iolct and oullrl w o r k s
Outlet channel
Other ancillary works
Outlet Channel Works @ I
Bed level 30 50 rn
- .- < - 18 m
500 m m drop
---pa ~ ~ - ~ -
-..---.--
-
14 m Constriction across Sg Kcrajong in Reference Design Plan -
50m L e n g t h W e i r across Diversion C a n a l Section
r
*
Test Series Carried Out
Study Objectives
I Physical Hyddraulie Model Study
I
To determine effectiveness of reltrence (original)
design in diverting the requisite proportion of
inflow to detention pond
Based on test findings on reference design, to
recommend design modifications where necessary
for further testing
To determine final dimensions of inlet
configuration to achieve the desired diversion
To study the effects of a nearby DBKL drain, and
a log boom, on the flood diversion
Modified Design 1
I
FINDINGS
Modified Design I1
POND DESIGN
CH ZOOB - CH350B
PELBAGAI ISU LAIN I
I -
POND Relocation Of Trees
I.
Prov. Sum
UTILITIES 4LLOCATION
PENGAUHANSETXNGGAN
,-
DESIGN PEAK FLOW