You are on page 1of 4

APTECH ENGINEERING SERVICES, INC.

Calculating True Cost of Cycling


at Combined Cycle Power Plants
BACKGROUND ON CYCLING EFFECTS
During the course of hundreds of engineering GT Exhaust Gas Temp Ramp Rate
900 3000
investigations and analyses, Aptech Engineering 800
2780 Cold 1955 Warm
2500

Services, Inc. (APTECH) has found that

Ramp Rate (deg F/hour)


700
2000

Temp (deg F), MW


1452 Hot
equipment wear and tear due to power plant 600
1500

on/off and load cycling is a very significant 500


1000
400

production cost component. This component 300


500

needs to be unbundled and quantified. 200


0

Furthermore, it has been APTECH’s experience 100


-500

that this component is not well understood or 0 -1000

-100 -1500
accounted for by most power plant owners. This 0 120 240 360 480 600 720 840
Time (min)
960 1080 1200 1320 1440 1560

brochure introduces the general concepts of MW T EXH GAS DIG Ramp Rate

cycling effects and describes how we work with


plant owners to determine the cost-of-cycling.
Figure 1
These costs enable the utility to better optimize
dispatching by taking into account the damage about the same load each time. However, each
and reliability impacts of cycling and ultimately shutdown it is restarted before reaching a cold
increase corporate profits. Such investigations condition, causing different startup ramp rates.
also result in recommendations reducing cycling The initial cold start exhibits a ramp rate of
costs through operational or design changes. 2780°F/hr in exhaust gas temperature transient.
The second (or warm) start exhibits a lower
OPERATIONAL CYCLES LEAD TO DAMAGE ramp rate at 1955°F/hr. The third (hot) start
exhibits a ramp rate of nearly one-half the level
Every time a combined cycle power station is of a cold start at 1452°F/hr. APTECH has found
brought on line, shut down, or used for load such differences in ramp rates between various
following, the gas turbines (GTs), steam cycles are of extreme importance when
turbines, heat recovery steam generators determining the stress level and amount of cyclic
(HRSGs), steam piping, and auxiliary thermal fatigue damage accumulated by both
components go through large thermal and GT and HRSG components.
pressure cycles. Expansion and contraction of
complex GT and HRSG components lead to A similar situation exists in the HRSG when the
thermal and mechanical fatigue damage. Other duct burner is activated, shut off, or the gas
phenomena, such as corrosion fatigue and turbine is dispatched in a load following mode.
water chemistry transients, creep, creep/fatigue Subtle changes in temperature occur among the
interaction, erosion, wear, and vibration also individual tube circuits causing additional
contribute to accelerated life expenditure of thermal/mechanical fatigue cycles. Since HRSG
critical components. components are densely packed and rigidly
supported to optimize the amount of heat
Figure 1 shows three starts executed over a recovered from the GT exhaust, flexing of tube-
24-hour period by a client’s large GT. Exhaust to-header connections and transfer piping
gas temperature, power output, and exhaust nozzles impose huge stresses on connections,
temperature ramp rates are plotted. The ramp ultimately resulting in cracking and tube failures.
rates, expressed as deg F change per hour, are In addition, steaming of water-cooled
important drivers of fatigue and creep/fatigue components and chemical attack of exposed
interaction effects. The GT is dispatched to metal beneath internal deposits can lead to
further damage.

Aptech Engineering Services, Inc.


HOU008-F
-1-
EQUIPMENT SUSCEPTIBILITY IS IMPORTANT critical components, and their historical costs.
The flowchart shown in Figure 2 depicts this
Through APTECH’s many cost-of-cycling combination of methods. For new combined
projects, we have determined that some units cycle units, the Top-Down methods would not
are designed better for cycling than others. apply due to inadequate operating and cost
Some designs are so bad, or the service history. Thus, for these units, APTECH would
duty/ramp rates are so severe, that the HRSGs apply its Bottom-Up methods and industry
experience forced outages within a hundred experience on similar units to derive cycling cost
on/off cycles. Other units can cycle on a daily estimates. The heat rate effects of cycling can
basis without major problems, enduring be determined with only a few months of hourly
thousands of on-off cycles without failure. megawatt and gas consumption data.
Modern power plant designs have tended to
compromise physical robustness to cycling Cost of Cycling Estimation Procedure
stresses for higher efficiencies and lower
installed costs. General Unit Historical Cost
Damage Modeling Analysis

Another factor in cycling susceptibility relates to


NERC_GADS
the method of chemistry control. Some control Statistical/Top-Down Reliability
Cost Model
schemes simply are not good for cycling units, Data

as they lead to a high probability of chemistry


Cost-of-Cycling
upsets and off normal conditions during cycling Estimation
that cause considerable damage. Maintenance Bottom-Up
Signature Engineering
Data Recurring Capital
Accounting
We use our extensive experience in analyzing Analysis EFOR/Replacement of Costs
Power
failures, including the use of calibrated damage
Heat Rate/Efficiency
and life expenditure models, to assess how Long-Term Capacity Plant
susceptible an HRSG or GT is to cycling Damage
Start-Up Fuel &Aux. Inspection
Modeling of
damage. Critical
Power & Chemicals and
Interviews
Components Cycle Types:
• Hot, Warm, Cold Starts
CYCLING INCREASES HEAT RATES Industry • Load Follow to Various Plant
Comparisons Load Levels Surveys
Another added cost that is not fully accounted of Similar
• Trip and Shutdowns
Units
for by plant owners is the extra fuel needed (i.e.,
higher heat rate) due to cycling. Most people
use incremental heat rate data based on static Figure 2
tests at specified set points to determine the
heat rate at a certain load level. This does not The following is a list of tasks APTECH would
account for the loss of efficiency due to variable typically undertake to determine cycling costs of
load operation—impacting heat rate 2 to 20%. a combined-cycle:
APTECH determines the overall heat rate
effects of each type of cycle (hot starts, warm Tasks Task Description
starts, cold starts, and load follows under 1 Project Kickoff and Data Gathering
varying load levels and ramp rates.) 2 Review of Plant Signature Data
3 Engineering Assessment and
HOW DOES APTECH ESTIMATE Operations Review
CYCLING COSTS? 4 Survey of Selected Plant Personnel
5 Damage Modeling
APTECH has developed and used a
6 Statistical Regression
methodology that employs a combination of
7 Component Life Expenditure/Cost
“Top Down” models and “Bottom-Up” methods.
8 Heat Rate Impact Modeling
Our Top-Down models are based on the use of
9 Total Cost Estimation
past histories of operations, forced outages, and
10 Evaluate Measures to Mitigate Cycling
costs. We have successfully used this method
Costs
on hundreds of generation units throughout the
11 Report and Optional Training
world. Bottom-Up methods rely on calculations
of operational stresses (e.g., temperature,
pressure, and chemistry), life-expenditure of

Aptech Engineering Services, Inc.


-2-
Figure 3 shows the results, breaking down
cycling costs for hot, warm, and cold starts, and
low-load follow for a typical unit.

Cycling Cost Breakdown

120 MegaWatt
Startup Fuel, Aux Power, Generation
100
etc. Cost
80 Low & Variable Load Extra
Fuel Cost
K$

60
Forced Outage Cost
40 Replacement Power Cost Total
20 Maintenance, Operation &
Capital Cost
0 Cost
Cold Start Warm Hot Start Load Hourly
Start Follow

Figure 3

HOW CAN THE RESULTS OF APTECH’S


Figure 4
WORK BE USED?
Once cycling costs are determined, the
Past clients have used APTECH’s cycling cost CyclingvAdvisor is used on a generation
results in the following ways. system level to optimize dispatch schedules of
the plants. It is unique in the industry because of
¾ Proper unbundling of variable costs to its rigorous accounting of damage costs as well
better: as fuel costs. It can also include emission costs
ƒ Negotiate long-term contracts in order to minimize total production costs of an
ƒ Bid into power markets entire Utility system.
ƒ Recover costs of ancillary services (e.g.,
AGC)
¾ Better Information for maintenance
budgeting
¾ Least cost system dispatch (including
APTECH’s CyclingvAdvisorTM)
¾ Improved cycling operations (including
APTECH’s COSTCOM®)

Clients have saved millions of dollars annually in


reduced overall production costs, with increased
profits. APTECH’s Technical Paper TP-054 can Phone, fax, or email us for more
be requested for more information. information!
WHAT IS CYCLINGvADVISOR AND Ph: 832-593-0550
COSTCOM? Fx: 832-593-0551
These software products were developed by
APTECH to allow plant owners to use the cost of Email: costofcycling@aptechpower.com
cycling results in real-time. COSTCOM uses Website: www.aptechpower.com
plant data to track cycling costs. COSTCOM can
be used as a training tool for operators to better
control damage costs related to cycling. It
provides actual unit damage costs as the unit is
running, as shown in Figure 4. It can include fuel
costs, dynamic heat rate effects, and emissions
credits/costs, thus giving total unit production
costs in real time.

Aptech Engineering Services, Inc.


-3-
OTHER COMBINED CYCLE SUPPORT SERVICES
APTECH is committed to OFFERED BY APTECH
assisting our clients with the APTECH also provides the following services to our clients:
operation and maintenance of
their power plant equipment. ¾ Acceptance testing
APTECH will help you run your ¾ Performance testing, prediction, and improvement
equipment as long as practical ¾ Failure investigation, metallurgical examination, root
cause analysis
and
¾ Inspection and maintenance planning (strategic and fast
track turn around)
” Safely ¾ Condition monitoring and trend analysis
” Reliably ¾ Emissions system evaluation
” Economically ¾ EP&C contract drafting, review, and monitoring as
Owner’s Engineer or Financing Institution Engineer
¾ Applications engineering for power plant modifications
APTECH’s goal is to work
and scope of supply
with our clients to ¾ O&M audit of complete combined cycle systems
¾ Asset valuation and due diligence evaluation
REDUCE POWER ¾ Operating and engineering staff training
PRODUCTION COSTS ¾ Litigation and expert witness support, including warranty
issues

Engineering Services, Inc.


16100 Cairnway Drive, Ste 310
Houston, TX 77084

ADDRESS SERVICES REQUESTED

TO:

You might also like