Activity Activity Orig Total Early Early Budgeted 2010

FEB MAR APR MAY JUN JUL AUG


ID Description Dur Float Start Finish Cost 0 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7
PRIM CONTRACTOR (DORA CC)
Subtotal 175 20 11FEB10 04AUG10 583,145.00
Milestones
(A)Design and Paper works
MILESTONES

0001A-1 NTP Acknowledged 0 0 11FEB10* 0.00 NTP Acknowledged

0001A-28 Contract Completion 0 20 04AUG10 0.00 Contract Completion


Pre-construction
(A)Design and Paper works
Mobalization

0001A-10 Mobilization 6 21 02APR10 07APR10 8,000.00 Mobilization


PRE-CONSRUCTION SUBMITTALS

0001A-19 Work schedule review By AED 14 43 24FEB10 09MAR10 0.00 Work schedule review By AED

0001A-22 Warranty plan preparation and 12 30 14JUL10 25JUL10 0.00 Warranty plan preparation and review

0001A-3 Area Use plan Preparation and 14 57 11FEB10 24FEB10 0.00 Area Use plan Preparation and review

0001A-34 Work schedule approved by AED 1 43 10MAR10 10MAR10 0.00 Work schedule approved by AED

0001A-4 APP preparation and review 14 57 11FEB10 24FEB10 0.00 APP preparation and review

0001A-5 Security Plan prepartion and 14 57 11FEB10 24FEB10 0.00 Security Plan prepartion and Review

0001A-6 Prepar work schedule 13 43 11FEB10 23FEB10 0.00 Prepar work schedule

0001A-8 QC plan prapartion and review 15 20 11FEB10 25FEB10 0.00 QC plan prapartion and review
SUBMITTALS

0001A-13 Submit Electrical material 15 77 01APR10 15APR10 0.00 Submit Electrical material

0001A-14 Submit architectural materials 10 56 11APR10 20APR10 0.00 Submit architectural materials

0001A-15 Electrical Material review by AED 14 77 16APR10 29APR10 0.00 Electrical Material review by AED

0001A-18 Architectural and Civil Material 14 56 21APR10 04MAY10 0.00 Architectural and Civil Material review by AED

0001A-35 Electrical Material Approved by 1 77 30APR10 30APR10 0.00 Electrical Material Approved by AED

0001A-36 Architectural and Civil Material 1 56 05MAY10 05MAY10 0.00 Architectural and Civil Material approved by AED
DBA INSURANCE

0001E-28 DBA Insurance 1 26 28JUL10 28JUL10 3,095.00 DBA Insurance


Design
(A)Design and Paper works
DESIGN AND ENGINEERING

0001A-11 65% design preparation 10 0 01APR10 10APR10 0.00 65% design preparation

0001A-12 65% design review 14 0 11APR10 24APR10 0.00 65% design review

0001A-16 100% design preparation 3 0 25APR10 27APR10 0.00 100% design preparation

0001A-17 100% design review 14 0 28APR10 11MAY10 0.00 100% design review

0001A-2 Prepare 35% design 14 0 04MAR10 17MAR10 0.00 Prepare 35% design

0001A-29 35 % Design Approved By AED 1 9 01APR10 01APR10 2,000.00 35 % Design Approved By AED

0001A-30 65% Design appoved by AED 1 2 25APR10 25APR10 4,000.00 65% Design appoved by AED

0001A-31 100% Design Approved by AED 1 0 12MAY10 12MAY10 4,050.00 100% Design Approved by AED

0001A-32 Geo technical report review by 14 0 27FEB10 12MAR10 0.00 Geo technical report review by AED

0001A-33 Geo technical approved by AED 1 27 13MAR10 13MAR10 8,000.00 Geo technical approved by AED

0001A-7 Prapare Geo technical Inv Report 16 0 11FEB10 26FEB10 0.00 Prapare Geo technical Inv Report and Submit

0001A-9 35% design review 14 0 18MAR10 31MAR10 0.00 35% design review
Procurement
(A)Design and Paper works
PROCUREMENT

0001A-39 Procurement of Architectural 10 56 06MAY10 15MAY10 0.00 Procurement of Architectural material

0001A-40 Procurement of Eelectrical 10 77 01MAY10 10MAY10 0.00 Procurement of Eelectrical material

0001A-41 Procurement of fabricated doors 10 63 06MAY10 15MAY10 0.00 Procurement of fabricated doors and windows

Start Date 11FEB10 PB15 Sheet 1 Sheet 1 of 6


Early Bar
Finish Date 04AUG10 Progress Bar DORA Construction Co. Date Revision Checked Approved
Data Date 11FEB10 Critical Activity W5J9JE-10-P-0086
Run Date 26JUL10 14:30 Police District 11
Initial Baseline Schedule
© Primavera Systems, Inc.
Activity Activity Orig Total Early Early Budgeted 2010
FEB MAR APR MAY JUN JUL AUG
ID Description Dur Float Start Finish Cost 0 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7
Construction
(C) Primery ECP construction

0001C-1 Drop arm gate installation 2 56 18MAY10 19MAY10 1,000.00 Drop arm gate installation
0001C-2 Installation sliding Gate 4 56 18MAY10 22MAY10 3,000.00 Installation sliding Gate
0001C-3 Pedestrian gate installation 4 62 18MAY10 22MAY10 4,200.00 Pedestrian gate installation
0001C-4 Installatoin of Cable lift gate 4 62 18MAY10 22MAY10 1,950.00 Installatoin of Cable lift gate
(C2) Secondery ECP Construction

0001C2-1 Secondery Vehicle Gate 4 66 20MAY10 23MAY10 5,000.00 Secondery Vehicle Gate
0001C2-11 Secondery Pedestrain Gate 5 66 24MAY10 28MAY10 4,200.00 Secondery Pedestrain Gate installation
(D) Gate House Construction

0001D-1 Lay out of gate house 1 51 08APR10 08APR10 300.00 Lay out of gate house
0001D-10 Curing of Slab conrete 7 56 27APR10 05MAY10 50.00 Curing of Slab conrete
0001D-11 Doors and windows installation 10 51 01MAY10 11MAY10 1,045.00 Doors and windows installation
0001D-12 Plastering inside and outside 10 51 12MAY10 23MAY10 750.00 Plastering inside and outside
0001D-13 Down spouts installation 1 51 27APR10 27APR10 30.00 Down spouts installation
0001D-14 Insolation of roof 1 51 29APR10 29APR10 165.00 Insolation of roof
0001D-15 Painting inside and outside 5 51 24MAY10 29MAY10 560.00 Painting inside and outside
0001D-16 Internal and external conduit 4 59 30MAY10 02JUN10 500.00 Internal and external conduit system
0001D-17 HVAC System installation 1 50 03JUN10 03JUN10 1,500.00 HVAC System installation
0001D-18 Secutiy lights installation 1 50 05JUN10 05JUN10 800.00 Secutiy lights installation
0001D-19 Gravil drainage system 3 55 27MAY10 30MAY10 450.00 Gravil drainage system construction
0001D-2 Excavation for gate house 1 51 10APR10 10APR10 95.00 Excavation for gate house
0001D-23 Pedestrian sidewalk 3 65 24MAY10 26MAY10 600.00 Pedestrian sidewalk
0001D-3 Form and steel work of gate 2 51 11APR10 12APR10 1,200.00 Form and steel work of gate house
0001D-4 Concrete work foundation 1 51 13APR10 13APR10 1,485.00 Concrete work foundation
0001D-5 Fom and stee work of walls 2 51 14APR10 15APR10 860.00 Fom and stee work of walls
0001D-6 Concrete work of walls 1 51 17APR10 17APR10 2,000.00 Concrete work of walls
0001D-7 Curing of Wall concrete 7 51 18APR10 25APR10 50.00 Curing of Wall concrete
0001D-8 Form and steel work of slab 2 56 18APR10 19APR10 215.00 Form and steel work of slab
0001D-9 Concrete work of slab 1 51 26APR10 26APR10 595.00 Concrete work of slab
North East Gurad tower Construction

0001E-1 Guard towers Layout 1 42 08APR10 08APR10 50.00 Guard towers Layout
0001E-10 Curing of Slab concrete 7 42 05MAY10 12MAY10 50.00 Curing of Slab concrete
0001E-11 Column steel and from work (1st 2 49 03MAY10 04MAY10 600.00 Column steel and from work (1st floor)
0001E-12 Concrete work of columns (1st 1 42 13MAY10 13MAY10 600.00 Concrete work of columns (1st floor)
0001E-13 CMU walls erection 2 46 15MAY10 16MAY10 1,000.00 CMU walls erection
0001E-14 Columns Curing 7 49 17MAY10 23MAY10 50.00 Columns Curing
0001E-15 Form and steel work of slabs (1st 2 46 17MAY10 18MAY10 450.00 Form and steel work of slabs (1st floor)
0001E-16 Concrete work of slabs (1st floor) 1 42 24MAY10 24MAY10 1,600.00 Concrete work of slabs (1st floor)
0001E-17 Curing of Slab Concrete 7 49 25MAY10 31MAY10 50.00 Curing of Slab Concrete
0001E-18 Doors and windows installation 2 46 25MAY10 26MAY10 1,700.00 Doors and windows installation
0001E-19 Plastering 3 42 01JUN10 03JUN10 500.00 Plastering
0001E-2 Excavation for guard towers 2 42 10APR10 11APR10 200.00 Excavation for guard towers
0001E-20 Steel stairs construction 3 52 25MAY10 27MAY10 3,000.00 Steel stairs construction
0001E-21 Insolation of roofs 1 44 05JUN10 05JUN10 500.00 Insolation of roofs
0001E-22 Down spout installation 1 45 06JUN10 06JUN10 100.00 Down spout installation
0001E-23 Painting (inside and outside) 3 43 09JUN10 12JUN10 650.00 Painting (inside and outside)
0001E-24 Steel plates isntallation 3 46 05JUN10 07JUN10 3,750.00 Steel plates isntallation
0001E-25 Installation of communication and 2 44 10JUN10 12JUN10 2,000.00 Installation of communication and data condutes
0001E-26 Sand bags installation 1 43 13JUN10 13JUN10 1,200.00 Sand bags installation

Start Date 11FEB10 PB15 Sheet 2 Sheet 2 of 6


Early Bar
Finish Date 04AUG10 Progress Bar DORA Construction Co. Date Revision Checked Approved
Data Date 11FEB10 Critical Activity W5J9JE-10-P-0086
Run Date 26JUL10 14:30 Police District 11
Initial Baseline Schedule
© Primavera Systems, Inc.
Activity Activity Orig Total Early Early Budgeted 2010
FEB MAR APR MAY JUN JUL AUG
ID Description Dur Float Start Finish Cost 0 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7
0001E-27 External and internal conduit and 3 44 06JUN10 08JUN10 2,700.00 External and internal conduit and wiring
0001E-29 Split pack installation 1 52 09JUN10 09JUN10 1,000.00 Split pack installation
0001E-3 Form and steel work 2 42 12APR10 13APR10 1,150.00 Form and steel work
0001E-30 Search light installation 1 52 09JUN10 09JUN10 6,000.00 Search light installation
0001E-31 Securty lights installation 1 52 09JUN10 09JUN10 2,000.00 Securty lights installation
0001E-33 Exterior insulation 5 50 04JUN10 08JUN10 3,000.00 Exterior insulation
0001E-4 Foundation concrete work 1 42 14APR10 14APR10 1,600.00 Foundation concrete work
0001E-5 Form and steel works of columns 2 42 15APR10 17APR10 600.00 Form and steel works of columns
0001E-6 Concrete work of Columns 2 42 18APR10 19APR10 1,000.00 Concrete work of Columns
0001E-7 Curing of Columns Concrete 7 42 20APR10 27APR10 50.00 Curing of Columns Concrete
0001E-8 Ground floors slabs form and 2 42 29APR10 01MAY10 800.00 Ground floors slabs form and steel works
0001E-9 Concrete work of slab (ground 1 42 02MAY10 02MAY10 2,000.00 Concrete work of slab (ground floor)
North West Guard Tower Constuction

0001F-1 Layout 1 37 08APR10 08APR10 50.00 Layout


0001F-10 Curing of Slab concrete 7 37 20APR10 27APR10 50.00 Curing of Slab concrete
0001F-11 Column steel and from work (1st 2 37 29APR10 01MAY10 600.00 Column steel and from work (1st floor)
0001F-12 Concrete work of columns (1st 1 37 02MAY10 02MAY10 600.00 Concrete work of columns (1st floor)
0001F-13 CMU walls erection 2 37 11MAY10 12MAY10 1,000.00 CMU walls erection
0001F-14 Form and steel work of slabs (1st 2 37 13MAY10 15MAY10 450.00 Form and steel work of slabs (1st floor)
0001F-15 Concrete work of slabs (1st floor) 1 37 16MAY10 16MAY10 1,600.00 Concrete work of slabs (1st floor)
0001F-16 Curing of Slab Concrete 7 37 17MAY10 24MAY10 50.00 Curing of Slab Concrete
0001F-17 Doors and windows installation 2 37 25MAY10 26MAY10 1,700.00 Doors and windows installation
0001F-18 Plastering 3 37 27MAY10 30MAY10 500.00 Plastering
0001F-19 Steel stairs construction 3 37 31MAY10 02JUN10 3,000.00 Steel stairs construction
0001F-2 Excavation for guard towers 2 37 10APR10 11APR10 200.00 Excavation for guard towers
0001F-20 Insolation of roofs 1 37 03JUN10 03JUN10 500.00 Insolation of roofs
0001F-21 Down spout installation 1 37 05JUN10 05JUN10 100.00 Down spout installation
0001F-22 Painting (inside and outside) 3 37 06JUN10 08JUN10 650.00 Painting (inside and outside)
0001F-23 Steel plates isntallation 3 41 09JUN10 12JUN10 3,750.00 Steel plates isntallation
0001F-24 Installation of communication and 2 41 13JUN10 14JUN10 2,000.00 Installation of communication and data condutes
0001F-25 Sand bags installation 1 41 15JUN10 15JUN10 1,200.00 Sand bags installation
0001F-26 External and internal conduit and 3 44 09JUN10 12JUN10 2,700.00 External and internal conduit and wiring
0001F-27 Curing of columns 7 37 03MAY10 10MAY10 50.00 Curing of columns
0001F-28 Security lights installation 1 46 09JUN10 09JUN10 2,000.00 Security lights installation
0001F-29 split pack installation 1 46 09JUN10 09JUN10 2,000.00 split pack installation
0001F-3 Form and steel work for 1 37 12APR10 12APR10 1,150.00 Form and steel work for foundation
0001F-30 Search lights installation 1 46 09JUN10 09JUN10 6,000.00 Search lights installation
0001F-31 external insolation 10 37 09JUN10 20JUN10 3,600.00 external insolation
0001F-4 Foundation concrete work 1 37 13APR10 13APR10 1,600.00 Foundation concrete work
0001F-5 Form and steel works of columns 1 37 14APR10 14APR10 600.00 Form and steel works of columns
0001F-6 concrete work of Columns 1 37 15APR10 15APR10 1,000.00 concrete work of Columns
0001F-7 Curing of Columns Concrete 1 37 17APR10 17APR10 50.00 Curing of Columns Concrete
0001F-8 Ground floors slabs form and 1 37 18APR10 18APR10 800.00 Ground floors slabs form and steel works
0001F-9 Concrete work of slab (ground 1 37 19APR10 19APR10 2,000.00 Concrete work of slab (ground floor)
Northern Middle Guard Tower Construction

0001G-1 Guard towers Layout 1 31 08APR10 08APR10 50.00 Guard towers Layout
0001G-10 Curing of Slab concrete 7 31 02MAY10 09MAY10 50.00 Curing of Slab concrete
0001G-11 Column steel and from work (1st 2 31 10MAY10 11MAY10 600.00 Column steel and from work (1st floor)
0001G-12 Concrete work of columns (1st 1 31 12MAY10 12MAY10 600.00 Concrete work of columns (1st floor)
0001G-13 Columns Curing 7 31 13MAY10 20MAY10 50.00 Columns Curing
0001G-14 CMU walls erection 2 31 22MAY10 23MAY10 1,000.00 CMU walls erection
0001G-15 Form and steel work of slabs (1st 2 31 24MAY10 25MAY10 450.00 Form and steel work of slabs (1st floor)
0001G-16 Concrete work of slabs (1st floor) 1 31 26MAY10 26MAY10 1,600.00 Concrete work of slabs (1st floor)

Start Date 11FEB10 PB15 Sheet 3 Sheet 3 of 6


Early Bar
Finish Date 04AUG10 Progress Bar DORA Construction Co. Date Revision Checked Approved
Data Date 11FEB10 Critical Activity W5J9JE-10-P-0086
Run Date 26JUL10 14:30 Police District 11
Initial Baseline Schedule
© Primavera Systems, Inc.
Activity Activity Orig Total Early Early Budgeted 2010
FEB MAR APR MAY JUN JUL AUG
ID Description Dur Float Start Finish Cost 0 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7
0001G-17 Curing of Slab Concrete 7 31 27MAY10 03JUN10 50.00 Curing of Slab Concrete
0001G-18 Doors and windows installation 2 31 05JUN10 06JUN10 1,700.00 Doors and windows installation
0001G-19 Plastering 3 31 07JUN10 09JUN10 500.00 Plastering
0001G-2 Excavation for guard towers 2 31 10APR10 11APR10 200.00 Excavation for guard towers
0001G-20 Steel stairs construction 3 31 10JUN10 13JUN10 3,000.00 Steel stairs construction
0001G-21 Insolation of roofs 1 31 14JUN10 14JUN10 500.00 Insolation of roofs
0001G-22 Down spout installation 1 31 15JUN10 15JUN10 100.00 Down spout installation
0001G-23 Painting (inside and outside) 3 32 16JUN10 19JUN10 650.00 Painting (inside and outside)
0001G-24 Steel plates isntallation 3 32 20JUN10 22JUN10 3,750.00 Steel plates isntallation
0001G-25 Installation of communication and 2 32 23JUN10 24JUN10 2,000.00 Installation of communication and data condutes
0001G-26 Sand bags installation 1 32 26JUN10 26JUN10 1,200.00 Sand bags installation
0001G-27 External and internal conduit 3 35 20JUN10 22JUN10 2,700.00 External and internal conduit system
0001G-28 Secutiy lights installation 1 37 20JUN10 20JUN10 2,000.00 Secutiy lights installation
0001G-29 Split pack installation 1 37 20JUN10 20JUN10 2,000.00 Split pack installation
0001G-3 Form and steel work 2 31 12APR10 13APR10 1,150.00 Form and steel work
0001G-30 Search light installation 1 37 20JUN10 20JUN10 6,000.00 Search light installation
0001G-31 External insulation 10 31 16JUN10 27JUN10 3,600.00 External insulation
0001G-4 Foundation concrete work 1 31 14APR10 14APR10 1,600.00 Foundation concrete work
0001G-5 Form and steel works of columns 2 31 15APR10 17APR10 600.00 Form and steel works of columns
0001G-6 Concrete work of Columns 1 31 18APR10 18APR10 1,000.00 Concrete work of Columns
0001G-7 Curing of Columns Concrete 7 31 19APR10 26APR10 50.00 Curing of Columns Concrete
0001G-8 Ground floors slabs form and 2 31 27APR10 29APR10 800.00 Ground floors slabs form and steel works
0001G-9 Concrete work of slab (ground 1 31 01MAY10 01MAY10 2,000.00 Concrete work of slab (ground floor)
Sout East Guard Tower Construction

0001H-1 Guard tower Layout 1 29 08APR10 08APR10 50.00 Guard tower Layout
0001H-10 Curing of Slab concrete 7 29 02MAY10 09MAY10 50.00 Curing of Slab concrete
0001H-11 Column steel and from work (1st 2 29 10MAY10 11MAY10 600.00 Column steel and from work (1st floor)
0001H-12 Concrete work of columns (1st 1 29 12MAY10 12MAY10 600.00 Concrete work of columns (1st floor)
0001H-13 Columns Curing 7 29 13MAY10 20MAY10 50.00 Columns Curing
0001H-14 CMU walls erection 2 29 22MAY10 23MAY10 1,000.00 CMU walls erection
0001H-15 Form and steel work of slabs (1st 2 29 24MAY10 25MAY10 450.00 Form and steel work of slabs (1st floor)
0001H-16 Concrete work of slabs (1st floor) 1 29 26MAY10 26MAY10 1,600.00 Concrete work of slabs (1st floor)
0001H-17 Curing of Slab Concrete 7 29 27MAY10 03JUN10 50.00 Curing of Slab Concrete
0001H-18 Doors and windows installation 2 29 05JUN10 06JUN10 1,700.00 Doors and windows installation
0001H-19 Plastering 3 29 07JUN10 09JUN10 500.00 Plastering
0001H-2 Excavation for guard towers 2 29 10APR10 11APR10 200.00 Excavation for guard towers
0001H-20 Steel stairs construction 3 29 10JUN10 13JUN10 3,000.00 Steel stairs construction
0001H-21 Insolation of roofs 1 29 14JUN10 14JUN10 500.00 Insolation of roofs
0001H-22 Down spout installation 1 29 15JUN10 15JUN10 100.00 Down spout installation
0001H-23 Painting (inside and outside) 3 29 16JUN10 19JUN10 650.00 Painting (inside and outside)
0001H-24 Steel plates isntallation 3 29 20JUN10 22JUN10 3,750.00 Steel plates isntallation
0001H-25 Installation of communication and 2 29 23JUN10 24JUN10 2,000.00 Installation of communication and data condutes
0001H-26 Sand bags installation 1 29 26JUN10 26JUN10 1,200.00 Sand bags installation
0001H-27 External and internal conduite 3 29 27JUN10 29JUN10 2,700.00 External and internal conduite system
0001H-28 Security lights installation 1 37 20JUN10 20JUN10 2,000.00 Security lights installation
0001H-29 Split pack installation 1 37 20JUN10 20JUN10 2,000.00 Split pack installation
0001H-3 Form and steel work 2 29 12APR10 13APR10 1,150.00 Form and steel work
0001H-30 Search light installation 1 37 20JUN10 20JUN10 6,000.00 Search light installation
0001H-31 External isolation 3 35 20JUN10 22JUN10 3,600.00 External isolation
0001H-4 Foundation concrete work 1 29 14APR10 14APR10 1,600.00 Foundation concrete work
0001H-5 Form and steel works of columns 2 29 15APR10 17APR10 600.00 Form and steel works of columns
0001H-6 Concrete work of Columns 1 29 18APR10 18APR10 1,000.00 Concrete work of Columns
0001H-7 Curing of Columns Concrete 7 29 19APR10 26APR10 50.00 Curing of Columns Concrete
0001H-8 Ground floors slabs form and 2 29 27APR10 29APR10 800.00 Ground floors slabs form and steel works
0001H-9 Concrete work of slab (ground 1 29 01MAY10 01MAY10 2,000.00 Concrete work of slab (ground floor)

Start Date 11FEB10 PB15 Sheet 4 Sheet 4 of 6


Early Bar
Finish Date 04AUG10 Progress Bar DORA Construction Co. Date Revision Checked Approved
Data Date 11FEB10 Critical Activity W5J9JE-10-P-0086
Run Date 26JUL10 14:30 Police District 11
Initial Baseline Schedule
© Primavera Systems, Inc.
Activity Activity Orig Total Early Early Budgeted 2010
FEB MAR APR MAY JUN JUL AUG
ID Description Dur Float Start Finish Cost 0 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7
South West Guard Tower construction

0001I-1 Guard tower Layout 1 29 08APR10 08APR10 50.00 Guard tower Layout
0001I-10 Curing of Slab concrete 7 29 02MAY10 09MAY10 50.00 Curing of Slab concrete
0001I-11 Column steel and from work (1st 2 29 10MAY10 11MAY10 600.00 Column steel and from work (1st floor)
0001I-12 Concrete work of columns (1st 1 29 12MAY10 12MAY10 600.00 Concrete work of columns (1st floor)
0001I-13 Columns Curing 7 29 13MAY10 20MAY10 50.00 Columns Curing
0001I-14 CMU walls erection 2 29 22MAY10 23MAY10 1,000.00 CMU walls erection
0001I-15 Form and steel work of slabs (1st 2 29 24MAY10 25MAY10 450.00 Form and steel work of slabs (1st floor)
0001I-16 Concrete work of slabs (1st floor) 1 29 26MAY10 26MAY10 1,600.00 Concrete work of slabs (1st floor)
0001I-17 Curing of Slab Concrete 7 29 27MAY10 03JUN10 50.00 Curing of Slab Concrete
0001I-18 Doors and windows installation 2 29 05JUN10 06JUN10 1,700.00 Doors and windows installation
0001I-19 Plastering 2 29 07JUN10 08JUN10 500.00 Plastering
0001I-2 Excavation for guard towers 2 29 10APR10 11APR10 200.00 Excavation for guard towers
0001I-20 Steel stairs construction 3 29 09JUN10 12JUN10 3,000.00 Steel stairs construction
0001I-21 Insolation of roofs 1 29 13JUN10 13JUN10 500.00 Insolation of roofs
0001I-22 Down spout installation 1 29 14JUN10 14JUN10 100.00 Down spout installation
0001I-23 Painting (inside and outside) 3 29 15JUN10 17JUN10 650.00 Painting (inside and outside)
0001I-24 Steel plates isntallation 3 29 19JUN10 21JUN10 3,750.00 Steel plates isntallation
0001I-25 Installation of communication and 2 29 22JUN10 23JUN10 2,000.00 Installation of communication and data condutes
0001I-26 Sand bags installation 1 29 24JUN10 24JUN10 1,200.00 Sand bags installation
0001I-27 External and Internal conduit 3 29 26JUN10 28JUN10 2,700.00 External and Internal conduit system
0001I-28 Security lights installation 1 29 29JUN10 29JUN10 2,000.00 Security lights installation
0001I-29 Split pack installation 1 29 29JUN10 29JUN10 2,000.00 Split pack installation
0001I-3 Form and steel work 2 29 12APR10 13APR10 1,150.00 Form and steel work
0001I-30 Search light installation 1 29 29JUN10 29JUN10 6,000.00 Search light installation
0001I-31 External insolation 1 38 19JUN10 19JUN10 3,600.00 External insolation
0001I-4 Foundation concrete work 1 29 14APR10 14APR10 1,600.00 Foundation concrete work
0001I-5 Form and steel works of columns 2 29 15APR10 17APR10 600.00 Form and steel works of columns
0001I-6 Concrete work of Columns 1 29 18APR10 18APR10 1,000.00 Concrete work of Columns
0001I-7 Curing of Columns Concrete 7 29 19APR10 26APR10 50.00 Curing of Columns Concrete
0001I-8 Ground floors slabs form and 2 29 27APR10 29APR10 800.00 Ground floors slabs form and steel works
0001I-9 Concrete work of slab (ground 1 29 01MAY10 01MAY10 2,000.00 Concrete work of slab (ground floor)
NORTHERN BOUNDARY WALL CONSTRUCTION

0001BA-1 Demolition Of Parameter wall 2 51 08APR10 10APR10 5,000.00 Demolition Of Parameter wall
0001BA-10 Coping of bounary wall 3 51 17MAY10 19MAY10 1,500.00 Coping of bounary wall
0001BA-11 Ston veneer construction 5 51 20MAY10 25MAY10 2,500.00 Ston veneer construction
0001BA-12 Sand toned stucco of bound 10 51 20MAY10 31MAY10 1,500.00 Sand toned stucco of bound boudary wall
0001BA-13 Concertina installation 3 51 01JUN10 03JUN10 1,750.00 Concertina installation
0001BA-2 Boundary wall layout 1 51 11APR10 11APR10 200.00 Boundary wall layout
0001BA-3 Boundary wall excavation 4 51 12APR10 15APR10 1,200.00 Boundary wall excavation
0001BA-4 Foundation Form and steel work 5 51 17APR10 21APR10 13,000.00 Foundation Form and steel work
0001BA-5 Foundation concrete work 3 51 22APR10 25APR10 15,000.00 Foundation concrete work
0001BA-6 Demolition of a portion of existing 2 61 08APR10 10APR10 1,500.00 Demolition of a portion of existing building
0001BA-7 Form work for wall 8 51 26APR10 05MAY10 15,000.00 Form work for wall
0001BA-8 Steel work of Wall 10 51 06MAY10 17MAY10 12,450.00 Steel work of Wall
0001BA-9 Concrete work of wall 5 51 12MAY10 17MAY10 10,150.00 Concrete work of wall
SOUTHERN BOUDARY WALL CONSTRUCTION

0001BB-1 Demolition Of Parameter wall 2 17 08APR10 10APR10 6,000.00 Demolition Of Parameter wall
0001BB-10 Coping of bounary wall 4 17 13JUN10 16JUN10 4,500.00 Coping of bounary wall
0001BB-11 Ston veneer construction 7 17 17JUN10 24JUN10 1,700.00 Ston veneer construction
0001BB-12 Sand toned stucco of bound 11 17 26JUN10 07JUL10 1,000.00 Sand toned stucco of bound boudary wall

Start Date 11FEB10 PB15 Sheet 5 Sheet 5 of 6


Early Bar
Finish Date 04AUG10 Progress Bar DORA Construction Co. Date Revision Checked Approved
Data Date 11FEB10 Critical Activity W5J9JE-10-P-0086
Run Date 26JUL10 14:30 Police District 11
Initial Baseline Schedule
© Primavera Systems, Inc.
Activity Activity Orig Total Early Early Budgeted 2010
FEB MAR APR MAY JUN JUL AUG
ID Description Dur Float Start Finish Cost 0 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7
0001BB-13 Concertina installation 5 17 08JUL10 13JUL10 1,750.00 Concertina installation
0001BB-2 Boundary wall layout 1 17 11APR10 11APR10 200.00 Boundary wall layout
0001BB-3 Boundary wall excavation 6 17 12APR10 18APR10 1,200.00 Boundary wall excavation
0001BB-4 Foundation Form and steel work 7 17 19APR10 26APR10 12,500.00 Foundation Form and steel work
0001BB-5 Foundation concrete work 5 17 27APR10 03MAY10 15,000.00 Foundation concrete work
0001BB-6 Demolition of a portion of existing 3 17 08APR10 11APR10 1,950.00 Demolition of a portion of existing Ecp building
0001BB-7 Form work for wall 15 17 04MAY10 20MAY10 15,000.00 Form work for wall
0001BB-8 Steel work of Wall 12 17 22MAY10 03JUN10 12,000.00 Steel work of Wall
0001BB-9 Concrete work of wall 7 17 05JUN10 12JUN10 10,550.00 Concrete work of wall
EASTERN BOUNDARY WALL CONSTRUCTION

0001BC-1 Demolition Of Parameter wall 2 40 08APR10 10APR10 5,000.00 Demolition Of Parameter wall
0001BC-10 Ston veneer construction 5 40 27MAY10 01JUN10 1,600.00 Ston veneer construction
0001BC-11 Sand toned stucco of bound 10 40 02JUN10 13JUN10 1,700.00 Sand toned stucco of bound boudary wall
0001BC-12 Concertina installation 3 40 14JUN10 16JUN10 1,000.00 Concertina installation
0001BC-2 Boundary wall layout 1 40 11APR10 11APR10 1,750.00 Boundary wall layout
0001BC-3 Boundary wall excavation 4 40 12APR10 15APR10 500.00 Boundary wall excavation
0001BC-4 Foundation Form and steel work 5 40 17APR10 21APR10 12,000.00 Foundation Form and steel work
0001BC-5 Foundation concrete work 3 40 22APR10 25APR10 15,000.00 Foundation concrete work
0001BC-6 Form work for wall 8 40 26APR10 05MAY10 1,500.00 Form work for wall
0001BC-7 Steel work of Wall 10 40 06MAY10 17MAY10 13,500.00 Steel work of Wall
0001BC-8 Concrete work of wall 5 40 18MAY10 23MAY10 11,300.00 Concrete work of wall
0001BC-9 Coping of bounary wall 3 40 24MAY10 26MAY10 2,500.00 Coping of bounary wall
WESTERN BOUNDARY WALL CONSTRUCTION

0001BD-1 Boundary wall layout 1 44 08APR10 08APR10 200.00 Boundary wall layout
0001BD-10 Ston veneer construction 5 44 23MAY10 27MAY10 1,000.00 Ston veneer construction
0001BD-11 Sand toned stucco of bound 10 44 29MAY10 08JUN10 1,000.00 Sand toned stucco of bound boudary wall
0001BD-12 Concertina installation 3 44 09JUN10 12JUN10 1,750.00 Concertina installation
0001BD-2 Boundary wall excavation 4 44 10APR10 13APR10 500.00 Boundary wall excavation
0001BD-3 Foundation Form and steel work 5 44 14APR10 19APR10 12,000.00 Foundation Form and steel work
0001BD-4 Foundation concrete work 3 44 20APR10 22APR10 15,000.00 Foundation concrete work
0001BD-5 Demolition of a portion Of old 2 62 08APR10 10APR10 1,500.00 Demolition of a portion Of old room
0001BD-6 Form work for wall 7 44 24APR10 02MAY10 13,000.00 Form work for wall
0001BD-7 Steel work of Wall 9 44 03MAY10 12MAY10 10,000.00 Steel work of Wall
0001BD-8 Concrete work of wall 5 44 13MAY10 18MAY10 10,550.00 Concrete work of wall
0001BD-9 Coping of bounary wall 3 44 19MAY10 22MAY10 2,300.00 Coping of bounary wall
ELECTRICAL DISTRIBUTION SYSTEM
Electrical Distribution system

0001E-32 Under gr Ele distr system for all 20 37 07JUN10 26JUN10 5,000.00 Under gr Ele distr system for all buildings
0001E-42 Transformer installation 2 55 07JUN10 08JUN10 5,000.00 Transformer installation
Contract Closeout
(A)Design and Paper works
CONTRACT CLOSEOUT

0001A-20 Punch list correction 15 22 14JUL10 28JUL10 0.00 Punch list correction
0001A-21 As built drawings review by AED 14 20 14JUL10 27JUL10 0.00 As built drawings review by AED
0001A-23 Finish work in location 2 22 29JUL10 30JUL10 0.00 Finish work in location
0001A-24 prefinal inspection 15 20 14JUL10 28JUL10 0.00 prefinal inspection
0001A-25 Demobilization 5 20 28JUL10 01AUG10 1,500.00 Demobilization
0001A-26 Final enspiction and Hand over 3 20 02AUG10 04AUG10 0.00 Final enspiction and Hand over
0001A-27 site clean up 2 20 31JUL10 01AUG10 0.00 site clean up
0001A-38 As build drawings approved by 1 26 29JUL10 29JUL10 3,500.00 As build drawings approved by AED

Start Date 11FEB10 PB15 Sheet 6 Sheet 6 of 6


Early Bar
Finish Date 04AUG10 Progress Bar DORA Construction Co. Date Revision Checked Approved
Data Date 11FEB10 Critical Activity W5J9JE-10-P-0086
Run Date 26JUL10 14:30 Police District 11
Initial Baseline Schedule