You are on page 1of 16

g

GER-4205

GE Power Systems

Installation and
Outage Management
Processes and
Technologies

Cynthia Breitkreuz
GE Power Systems
Atlanta, GA
Installation and Outage Management Processes and Technologies

Contents

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Installation Planning and Management. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Pre-Installation Meeting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Installation Processes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Material Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Arrival and Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Inventory Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Case Number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Material Shortages. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Material Shortage Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Installation Coordination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Technical Direction Role . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Installation Change Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Procedural Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Installation Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Progress Meetings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
As Built Construction Prints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Special Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Post-Installation Meeting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Maintenance Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Maintenance Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Post-Outage Review Meeting. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Advanced Review Meeting. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Managing Outage Duration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

GE Power Systems GER-4205 (04/01)


■ ■ i
GE Power Systems GER-4205 ( 04/01)
■ ■ ii
Installation and Outage Management Processes and Technologies

Introduction ning with the simplest form, Technical Direction of


Installation; continuing with complete turnkey
Availability is critical to an equipment owner.
solutions, Centerline Installation Services; and cul-
When equipment is not operable, revenue gen-
minating in plant Performance Testing Services.
eration capability is reduced. Whether an
While technical direction is the most common
owner is installing new units or performing
activity, both performance testing and turnkey
maintenance on its existing fleet, rigorous proj-
centerline installations are increasing.
ect management is key. Most owners will quan-
tify the quality of an installation or outage by a Technical Direction of Installation for the tur-
few critical factors: bine equipment is an active, on-site service pro-
■ On-time completion vided by GEII. It provides engineering and
technical guidance, advice, and counsel to the
■ Equipment performance
customers and their agents, with the objective
■ Quality of workmanship to provide a technically-correct, high-quality,
■ Completion within budget safe installation. Work that is supervised, man-
With over 11,000 units installed worldwide, GE aged, and performed by others is audited,
has developed standard processes for the plan- observed, evaluated, and reported with com-
ning and execution of installations and outages, parisons being made to applicable and up-to-
continually building on experience. This paper date GE specifications, instructions, drawings,
discusses these procedures. recommendations, practices, procedures, and
techniques.
Installation Planning and Management The balance of this section will be arranged in a
An efficient and high quality installation sequential timeline of key events and processes
requires Management, Supervision, and Tech- (refer to Figure 1). Included is a review of the
nical Direction to supplement the materials processes and information transmittal recom-
purchased. General Electric International, Inc. mendations to help in planning any upcoming
(GEII) provides a full range of services begin- installations.

Sample Installation Project Timeline

HRSG Post-
Site Pre-Install Units Receive First 2 X GTG
Preparation Meeting Ship Material & STG COD Install
Fire Operational Operational Meeting

Month 0 5 6 9 11 17 18

Assembly /
Installation

Figure 1. Installation project timeline

GE Power Systems GER-4205 ( 04/01)


■ ■ 1
Installation and Outage Management Processes and Technologies

Pre-Installation Meeting ■ Installation, inspection, and assembly


of the turbines and associated
A pre-installation meeting is normally held
before shipment of the major alignment com- equipment
ponents. ■ Inspection of assembly, clearances,
Pre-installation meetings are held for the pur- alignment and cleanliness
pose of bringing together those people who will ■ Fluid and auxiliary systems flushing
be responsible for the successful installation of and cleaning operations
the GE turbine equipment. ■ Commissioning coordination
The objectives are fourfold: ■ Equipment start-up and initial
1. To discuss the information described operation responsibilities
in the installation plan. ■ Equipment placed into service
2. To establish a mutual understanding ■ Post-installation meeting
of commitments.
3. To describe the General Electric
International, Inc. installation support
Material Control
activities Recent data collected on global installation sites
4. To establish a channel of indicates that 10.8% of all installer delays may
communication during the installation be linked to material receiving, storage and
period. control processes. The importance of creating
proper facilities and procedures for receiving,
Installation Processes cataloguing, and storing material at the job site
The following activities must be considered and cannot be overemphasized. We recommend the
planned as part of a successful installation and following procedures for handling the material
start-up: after it is received. It has been demonstrated
■ Unloading of material that installation efficiency can be maximized
■ Material movement, such as skidding when material is readily available at the
and cribbing of heavy components required time. While identification and accessi-
bility are major factors, the need for quickly
■ Examination of material for loss or
replacing damaged or missing material is prob-
damage
ably more significant in maintaining a sensible
■ Inspection of site storage and work plan. We strongly recommend that the
warehousing facilities methods outlined in this section be given care-
■ Maintenance of adequate storage ful consideration to ensure prompt replace-
records ments or repairs when required.
■ Installation coordination
■ Coordination and administration of Arrival and Inspection
the procurement of tools and All material and equipment should be inspect-
equipment ed upon arrival at the carrier's final delivery
■ Inspection of foundation and setting point. This inspection should include but not
of foundation plates be limited to the following:

GE Power Systems GER-4205 ( 04/01)


■ ■ 2
Installation and Outage Management Processes and Technologies

1. Inspect the protective covering and ■ Weights and dimensions


packing for obvious damage in transit. ■ Package type (case, skid, crate, box)
2. Inspect the “HUMP METERS” and ■ Vendor
blocking of components on the
■ Case number
transport vehicle for shifting during
shipment. Case Number
3. Check the orientation of any The case number is very important. It identifies
components related to gas turbine the material with the following information.
foundation where special orientation The first digit is the unit number designated for
had been requested. this material. The next four alphanumeric char-
4. Check the condition of all equipment acters identify the MLI or model list item num-
and material when received, and ber. The last two digits are assigned sequential-
inventory it. ly for the particular MLI, starting with 01. For
example, the first case (or crate or skid) for the
5. Review the carrier's documentation
Inlet Duct Arrangement, A041, will be assigned
before accepting the delivery for the
case number 1A04101. If there were 16 “cases”
following:
for this shipment, the last case would be
■ Material Safety Data Sheets (MSDS) 1A04116.
for HAZARDOUS material.
When the material is received, the bill of lading
■ A packing list of the equipment should include the case number(s). However, it
being delivered. should be checked against the actual case num-
Carload shipments should be promptly bers to make sure the material was delivered as
unloaded to avoid demurrage charges and intended. Each case should have a packing list,
arranged in an accessible and convenient man- both outside and inside the box.
ner for further inspection and handling. A running tally of the cases received against the
Inventory Control Notification of Shipping Release (NSR) should
be kept. We suggest using a site map using the
The importance of a system for proper invento-
case numbers to identify the locations of the
ry control cannot be overemphasized if an
various boxes. Generally, all the crates for single
effective and efficient installation is to be
items should be received within three weeks
accomplished.
after the NSR is issued.
The process of receiving material shipped
directly from GE suppliers includes the follow-
Material Shortages
ing steps: As materials are received, shortages may appear.
In a broad sense “shortages” are defined as any
Once the proper information is
part needed but not available at the job site.
received, GE issues a Notification of
Shortages fall into one of four categories:
Shipping Release (NSR) to the
supplier. A copy of this notification is 1. Material known to be shipped but not
faxed to your material representative. received at the job site.
The NSR contains the following 2. Material not known to be shipped but
information: known to be needed.

GE Power Systems GER-4205 ( 04/01)


■ ■ 3
Installation and Outage Management Processes and Technologies

3. Material received in insufficient 1. ECNs are limited to the description of


quantity. equipment changes. The principal
4. Material received but damaged in purpose of ECNs is to leverage
shipment or on site, or lost on site. corrective actions that were discovered
in the field on similar units, and
Material Shortage Report implement the corrective action
The Technical Director will issue a Material before the same issue is realized. The
Shortage Report in all cases where: ECN will list the drawings affected,
1. An insufficient quantity of materials is parts required, and the disposition of
received at the site. the affected equipment.
2. Needed materials are not received and 2. TILs are used when a generic-type of
are not known to be shipped. change is involved, especially when a
large distribution is required. TILs are
3. Materials are known to be shipped but
also used as a means to transmit
are not received.
installation recommendations in
A Material Shortage Report, indicating the various areas where drawing changes
required information and reason for the short- are not involved.
age, will serve as an order for the required
materials and initiate shipment of the part(s) to For gas turbine installations, the site Technical
the job site. Direction team will conduct three periodic con-
ference calls with the Product Service and
Installation Coordination Engineering teams. These calls occur three
months prior to first fire, one month prior to
Technical Direction Role first fire, and one week prior to first fire. The
The size and complexity of many turbines pro- intent of this call series is to ensure that the site
hibits full assembly and testing in the factory. To team has received and implemented all TILs
ensure that the equipment is properly installed, and ECNs applicable to your particular unit and
aligned, and checked out before operation, that the team has access to the latest and most
GEII provides Technical Direction during current system documentation.
installation. This service is essential for a prop-
er interpretation of the design criteria, as Procedural Documentation
expressed in the drawings and instruction
GEII uses several other methods of providing
books during installation and start-up.
installation directions to the job site. Many pub-
Installation Change Control lications with identifying series numbers such as
Equipment changes are sometimes required in GEI-86151 (Low Voltage Power Circuit Breaker)
the field for a number of reasons. Additionally, and GEK-39672 (Switchgear) are issued by cog-
GEII continuously evaluates installation meth- nizant engineering functions. Most of these
ods. As new and better methods are developed, publications are included in the instruction
they will be provided. The formal transmittal of books that are distributed at the time the unit
these changes is made through the use of ships. There are a few that are not directly relat-
Engineering Change Notices (ECNs) or ed to specific equipment and are not included
Technical Information Letters (TILs). in the instruction book. These are distributed

GE Power Systems GER-4205 ( 04/01)


■ ■ 4
Installation and Outage Management Processes and Technologies

by the local GEII office when they are applica- tions, applicable parts lists, and a few detailed
ble to the installation. machine drawings. These prints, which repre-
sent the “as built” condition of the gas turbines,
Installation Schedule
are provided to the technical director to assist
A basic requirement for a successful installation him in his consulting capacity. Any drawings in
plan is the installation schedule. This schedule the sets that are changed during the installation
can take various forms from a bar chart to a period are replaced with the updated drawing.
complex logic network programmed with provi- When the installation is complete, the
sions for resource allocations. The bar chart Technical Director will provide the customer
allows you to list your work activities in sequen- with a set of the construction prints less the
tial order, plan your job duration, determine parts lists (PLs) and machine drawings. This set
your labor and material requirements, and will describe the “as built” condition of the gas
track the job. The logic network, when proper- turbine.
ly programmed, allows all of the above plus crit-
ical-path planning, periodic job tracking with Special Tools
compensation for manpower and material defi- GE will supply a variety of special tools for the
ciencies, and job-cost tracking. The installation gas turbines and generators that are not nor-
schedule that you use on the turbine installa- mally furnished by the installation contractor. A
tion should be designed to meet your needs and list of special tools provided by GE is included
provide the optimum installation cycle. with the construction print list under “Tool
While responsibility for schedule creation, List” or “Installation Device.” The special tools
maintenance, and adherence remain with the shown on these lists are part of the turbine and
installer, it is critical that the installer and GEII generator packages and are turned over and
Technical Direction team review the schedule documented at the completion of the turbine
tasks in concert, to ensure that all work tasks are installation. It is important that these devices be
provided for and to fully leverage the past expe- carefully stored and protected for future main-
riences of both parties. tenance on the machine.

Certain interfaces between the turbines and Post-Installation Meeting


other equipment on-site will take place during In addition to the pre-installation meeting,
the installation. Prior to interface activities, additional job-site meetings will be scheduled
depending on the operation involved, a meet- on an as needed basis. The last meeting that
ing should be held to discuss dates, problems, GEII will schedule as part of turbine installation
specifications, and any special requirements is the post-installation meeting. The post-instal-
that may be involved. lation meeting is the formal conclusion of all
Progress Meetings installation activities and includes the presenta-
tion and review of installation data, tools, and
Periodic reviews of the installation and commis-
construction prints. The post-installation meet-
sioning activities are of major importance if the
ing is normally held one month after the com-
commercial operating date is to be achieved.
mercial operating date.
As Built Construction Prints
The Construction Print List contains all the pri- Maintenance Management
mary and secondary drawings, process instruc- Turbine maintenance has been viewed tradi-

GE Power Systems GER-4205 ( 04/01)


■ ■ 5
Installation and Outage Management Processes and Technologies

tionally as an activity that takes place at standard Asset Performance requires looking at post-out-
intervals during a scheduled outage. That view age reports and evaluating the plan for the
is changing. While turbine maintenance often equipment at the time of the post-outage meet-
takes place according to established plant ing. Evaluation of equipment performance and
schedules (for example, during a nuclear refu- long-term maintenance planning is therefore a
eling) the approach has evolved to one of man- continual process beginning at the end of one
aging Asset Performance. Equipment owners are outage (refer to Figure 2). Alternatives for
evaluating their overall fleet and analyzing the improving performance, whether in output,
most effective way to maximize the revenue gen- efficiency, emissions, reliability, or availability
erated. This could include extending intervals often require more time to evaluate, procure,
between maintenance cycles, or it could mean and implement than the 6-month to 1-year win-
taking an outage earlier than usual in order to dow allows. Many companies have budgeting
install a performance enhancement package. cycles that make it difficult to support a major
The increasingly macro view of turbine equip- maintenance or capital expenditure not identi-
ment compels a need for even more rigorous fied well in advance. Thus it becomes critical to
planning and analysis. In the past, Owners and view this planning as a continuous process,
Service Providers considered the planning for rather than a discrete event.
maintenance as an activity that began about 6
months to a year in advance of an outage. It Maintenance Planning
would begin with an Advanced Review Meeting A maintenance plan is a continuous process of
and end with a Post-Outage Review Meeting, review, recommendation, and implementation.
where the final inspection report and future Service providers can develop a pro-active plan
recommendations would be reviewed. Some with the customer to support the inspection
actions were taken, but often the report would and repair of the equipment involved. It is crit-
not be filed until the next planning cycle. ical that a plan tailored to the specific outage

Advanced
Advanced Pre-Outage
Pre-Outage
Review
Review Meeting
Meeting
Meeting
Meeting

Efficiency
Efficiency
Reliability/Availability
Reliability/Availability
Emissions
Emissions Improvements
Improvements
Preventative
Preventative Maintenance
Maintenance

Post-Outage
Post-Outage Outage
Outage
Meeting
Meeting Execution
Execution

Continuous Evaluation of Performance Enhancements


Figure 2. Outage management cycle

GE Power Systems GER-4205 ( 04/01)


■ ■ 6
Installation and Outage Management Processes and Technologies

scope is developed so that participants under- ■ Lube oil system inspection (if
stand their responsibilities and the impact that applicable)
outage planning has on its successful comple- ■ Coupling inspection (if applicable)
tion. This plan must include all work activities,
■ Enclosures (if applicable)
as well as the schedule, parts lists, tooling and
equipment requirements, and repair services ■ Alignment and clearance overview (if
expected. Service providers can assist in devel- applicable)
oping recommendations for parts, and can ■ Start Up comments
track and expedite as needed. Additionally, they
Advanced Review Meeting
can review repair requirements and can assist in
planning the workscope with the selected repair The current condition of the equipment is
facility. It is key to the outage schedule that all reviewed to determine recommendations for
repairs are coordinated. Utilizing a Three operational and outage planning. Parts, materi-
Meeting Concept is an effective process to use for al, technical and procedural issues are
developing maintenance plans. The purpose of addressed to ensure that actions are imple-
each meeting is described below. mented as required to support the scheduled
maintenance program. These meetings are
Post-Outage Review Meeting held 6-to-8 months in advance of all scheduled
This meeting is the end point of one outage outages. The following activities take place at
and the start point for the next. It is held fol- this session.
lowing the completion of an outage. Its purpose ■ Review previous inspection report
is to review the outage report, performance,
■ Review unit history since last
and findings, as well as to identify problems,
inspection and identify additional
determine best practices, and discuss recom-
work scope
mendations. A performance review, for which
criteria should be established at the pre-outage - This includes operational trending
meeting, should take place. In addition, parts data
recommendations can be made and a prelimi- - Forced outage occurrences
nary plan for the next scheduled outage can be - Operational issues, which require
outlined. The final outage report should maintenance activity at a scheduled
include: inspection (such as lube oil leaks,
■ Job summary faulty instrumentation, etc.)
■ Inspection summary - Specific fleet issues, which may
affect reliability of the unit
■ Recommendations
■ Review parts inventory for unit
■ Parts used and recommended
■ Review all parts orders and associated
■ TIL/ECN activity
delivery dates
■ Combustion section data
■ Review TIL list for unit for additional
■ Compressor section data (if workscope and parts requirements
applicable) ■ Review status of parts being
■ Turbine section data (if applicable) refurbished

GE Power Systems GER-4205 ( 04/01)


■ ■ 7
Installation and Outage Management Processes and Technologies

■ Review completion / ship dates Critical Path Management - Any given outage is
■ Review inspection reports / findings likely to have unexpected work that can impact
the schedule. Data shows that 39% of outage
■ Review changes in safety regulations,
delays are due to emergent or unplanned work.
which require implementation during
GEII approaches Critical Path Management
the next inspection
with standard processes developed through
Managing Outage Duration years of project experience, coupled with the
Many factors affect the length of an outage. use of custom-designed software developed
Two of them are a well-defined workscope and specifically for this application. The software
the appropriate combination of skilled people. enables the incorporation of emergent work
Workscope and responsibilities of all parties are into the schedule. Resource loading can be eval-
discussed during the pre-outage meeting. uated and shifted as required. Incoming parts,
Access to skilled engineers and technicians repairs, and other work, which can affect the
should be considered when scheduling the timeliness of task completion, are tracked with
work. As the U.S. industry moves from per- alternatives developed in advance to the fur-
forming maintenance in spring or fall to having thest extent possible. The project baseline
outages primarily in the spring (refer to Figure schedule is developed utilizing task level data,
3), one must consider the impact on the avail- best practices, and lessons learned from past
ability of trained craft labor, technicians, and and current outages.
specialists. With more operations moving Once the schedule is finalized, the work on crit-
toward outsourcing versus in-house mainte- ical path is identified. GEII personnel then use
nance crews, this concern is magnified. a Failure Modes and Effects Analysis (FMEA) to
To effectively manage the outage and minimize identify the areas of greatest risk and develop
the impact of the unexpected, it is important to contingency plans to mitigate that risk (refer to
consider several elements. Figure 4). The FMEA is a systematic approach

Figure 3. U.S. maintenance shift

GE Power Systems GER-4205 ( 04/01)


■ ■ 8
Installation and Outage Management Processes and Technologies

that has proven powerful in this application. It communications infrastructure. A dedicated


involves identifying the manner in which a phone line allows the Technical Adviser to
process could fail to meet requirements, the interface with experts via computer to obtain
failure’s effect, potential causes of the failure, faster response to questions, as well as access to
current controls in place, and recommended drawings and technical documents. This also
actions. By rating the severity, the likelihood of facilitates ordering and status of emergent work

Proce ss Pote ntia l Pote ntia l S O D R


Ste p/Pa rt Fa ilure Fa ilure E Pote ntia l C Curre nt E P
Num be r Mode Effe cts V Ca use s C Controls T N
Install Galling of Stuck Nut Dirty Stud Visual
8 3 4 96
Nuts Threads Inspection
Damaged Visual
8 4 7 224
Thread Inspection
Extensio- Improper Leaky Incorrect Duplicate
meter Stretch Joint Measurement/ Measurement
9 5 6 270
Measure- on Stud Under- Process
ment Stretched Stud
Broken Incorrect Duplicate
Stud Measurement/ Measurement
10 3 6 180
Over-Stretched Process
Stud

Figure 4. Contingency planning – risk analysis

occurrence, and the ability to detect the cause items and communication of the status of off-
or failure mode, a risk priority number (RPN) site work, such as repairs. GEII is also develop-
can be calculated. This assists the Project ing on-line collaboration tools that will allow
Manager to determine which area needs risk faster exchange of information among outage
mitigation efforts first. Another tool utilized is participants. All of this can make communica-
the Cause and Effect Diagram (also referred to tion more efficient, but it can happen only if
as a Fishbone Diagram). Traditionally used by the infrastructure to enable it exists.
engineers in Root Cause Analysis, this tool has
been leveraged for pro-active applications in Summary
contingency planning (refer to Figure 5). The Experience shows that the quantity and quality
Cause and Effect Diagram provides an organ- of advanced preparation heavily influence the
ized visual method of displaying all possible successful execution of an installation or
causes of a problem and is helpful in consider- maintenance outage. GEII will continue to
ing all reasons for occurrence. develop better and faster ways to plan and
Information Management – With information implement equipment service. Through
technology playing an increasingly larger role development of new tools, communication and
in daily activity, it is necessary to consider the planning will become faster and more flexible.

GE Power Systems GER-4205 (04/01)


■ ■ 9
Installation and Outage Management Processes and Technologies

Site Layout Customer Issues Environmental

3 2
No Electrical Hook-Ups Not enough Extension Cords

Bolt Heaters in Disrepair

Failure to
complete
3 Bolting
2 Inconsistent Extensiometer Shell ‘On-
Incorrect Layoff Calculated Measurements
Time’
3 2 Incorrect Replacement
Not enough Bolt Heaters Layoff Marked Incorrectly Nuts Shipped 4

2
Nuts Stick during Installation Impact
High Low

Easy 1 2
Project Management Craft Labor Issues Supplier issues Implement

3 4
Hard

Figure 5. Contingency planning – cause and effect

Ongoing programs in technology will enhance work on site. These advances, coupled with the
the capability of GEII service personnel to unique skills of Customer/GEII teams, will help
communicate with experts globally, improving set new standards of service well into the
both responsiveness time and the quality of future.

GE Power Systems GER-4205 (04/01)


■ ■ 10
Installation and Outage Management Processes and Technologies

List of Figures
Figure 1. Installation project timeline
Figure 2. Outage management cycle
Figure 3. U.S. maintenance shift
Figure 4. Contingency planning – risk analysis
Figure 5. Contingency planning – cause and effect

GE Power Systems GER-4205 (04/01)


■ ■ 11
Installation and Outage Management Processes and Technologies

GE Power Systems GER-4205 (04/01)


■ ■ 12

You might also like