1.

create cross dock warehouse level customization

2. mark movement type as cross dock relevant

3. create number range for cross docking

4. define movment type 101


5. define moment type 601
6. define special moment indicator and assign it in the interfaces-> moment types

7. also assign this indicator in the material master -> wm1 view

Then we need to create the CRD process as shown below

1. create sales order


2. create the delivery with reference to the delivery

3. create the Purchase Order

4. create the inbound delivery with reference to the above PO

5. then we need to plan the cross docking through cross docking monitor tool
Here we can see our inbound and outbound deliveries. We need right click the both
deliveries one by one and select the Designate cross docking

6. then we need to pull the both deliveries to the decision tab as shown below:

7. Then create the Transfer for Inbound delivery from VL32n screen. We can
clearly see TO creating from 902 to 916.
8. once we save the TO it will be confirmed automatically in both inbound and
bound delivery documents.

9. then do the PGR and document flow will be as follows:

10. then do the goods issue