BROAD STATUS OF THERMAL POWER PROJECTS IN RAJASTHAN

Commissioning Schedule
Sl. Project Details Capacity Original Actual (A) /As Broad Status Critical
No. (MW) now expected Areas
Syn. COD Syn. COD
(Com.) (Com.)
A. PROJECT COMMISSIONED
STATE SECTOR
1 Dholpur CCPP 330
RRVUNL GT-1: Synchronized on 29th Mar’07 and
Distt. Dholpur declared on commercial operation on
GT-1 110 02/07 03/07(A) 09/07(A) 25.09.07
09/07(A)
GT-2* 110 03/07 06/07(A) 10/07(A) GT-2: Synchronized on 16th Jun’07
10/07(A) respectively and declared on commercial
ST* 110 08/07 12/07(A) 03/08(A) operation on 11.10.07 respectively.
03/08(A)
Date of approval by State Cleared State Govt. ST: Synchronized on 27.12.2007 and
Est. approved cost Rs.115500 Lakhs declared on COD on combined mode on
1st March’08.
Completed cost Rs. 108837 Lakhs
Type of fuel LNG
Fuel Linkage 1.5 mmscmd gas from Panna-
Mukta-Tapti basin by ONGC
Date of main plant Order M/s BHEL on 5.6.2004 (BTG) at
Rs. 531.30 Crs.
* Slipped from 10th Plan
2. Kota TPS St.-V 195
RRVUNL (Distt: Kota) a) M/s Desein Pvt. Ltd. Has been appointed
Unit-7 195 11/08 03/09 05/09(A) 9/09 as Consultant.
(2/09) 8/09 (A) b) All BOP packages (except C&I) have
been awarded to M/s Tata Project Ltd.
Est. approved cost Rs. 68000 lakhs c) Unit synchronized on 30.05.2009.
Revised cost (Approved in Rs. 88000 lakhs d) Coal firing done on 4th Aug’09.
02/07) e) Unit commissioned (full load) on 31st
Cumm. Exp. Upto 3/2009 Rs. 75610 lakhs Aug’09.
Exp.During 2009-10 Rs. 5285 Lakhs
(upto 9/09)
Type of fuel Coal
Fuel Linakage .90 MTPA from SECL
Date of main plant Order BTG contract on BHEL on
30.06.2006 at Rs. 362 Crs.
3. Suratgarh TPP St-IV 250 a) M/s DCPL have been appointed as
RRVUNL Consultant.
b) All BOP packages (except C&I) have been
(Distt. Sriganganagar) awarded to M/s Indure Ltd.
U –6 250 09/08 12/08 3/09(A) 09/09 c) DM Plant, PT Plant & FO System: Existing
(11/08) 8/09(A) facility is utilized.
Est. approved cost Rs. 75000 lakhs d) Unit Synchronised on 31.3.09.
e) Coal firing done on 21st Aug’09.
Revised cost Rs. 1,00,000 lakhs f) Unit commissioned (full load) on 29th
Exp. Upto 3/2009 Rs. 95327 lakhs Aug’09.
Exp.During 2009-10 (upto Rs. 4799Lakhs
8/09)
Type of fuel Coal
Fuel Linkage 1.16 MTPA from SECL
Date of main plant Order BTG contract on BHEL on 15.06.2006 at
Rs. 402 Crs.
Power Evacuation System Existing system

- 43 -
Commissioning Schedule
Sl. Project Details Capacity Original Actual (A) /As Broad Status Critical
No. (MW) now expected Areas
Syn. COD Syn. COD
(Com.) (Com.)
4. Giral Lignite TPS 125 a) Unit synchronized on 26.12.08. - Lignite
Stage-II, b) Lignite firing completed on 10th Feb’09. handling
RRVUNL Unit is running at 80-90 MW with 400 system
Distt. Barmer PPM. BHEL and RRVUNL gradually - Excessive
U-2 125 6/08 09/08 12/08(A) 09/09 increased a load of 125 M on 28.6.09. emission
(8/08) 11/09(A) c) To reduce SOx level from 3800 ppm to of Sox.
Date of approval by State Govt. 05.01.2006 300 ppm at full load of 125 MW, efforts Level.
Original Est. cost Rs. 61800 Lakhs were continued for increasing lime
Latest Est. Cost Rs. 65000 lakhs dosing as per norms fixed by BHEL.
d) Unit achieved full load on 6.11.2009
Exp. Upto 3/2009 Rs. 70388 Lakhs
with 280 ppm Sox level.
Exp. During 2009-10(upto 8/09) Rs. 3094 Lakhs
Type of fuel Lignite
Fuel Linkage
Date of main plant order 30.11.2005 on BHEL (BTG) at Rs.
531.30 Crs.
Power Evacuation system 220 KV Giral TPS- Barmer-
Dhorimanna- Bhinmal S/C, LILO of
Mada
5. Chhabra TPP 500 a) M/s Tata Consultancy Engineers have been
RRVUNL (Distt. Baran) appointed as Consultant.
b) CHP: Order has been awarded on M/s Techpro Readiness of
U-1 09/08 12/08 4/09(A) 12/09 System Ltd., Chennai on 1.11.06. bunker floor
250 (11/08) 10/09(A) c) DM Plant: Order has been awarded on M/s & inter
Thermax, Pune on 26.04.07. connection
U-2 250 12/08 03/09 03/10(A) 06/10 d) Cooling Tower: Order has been awarded to M/s
(2/09) 5/10(A) between
PCT. 8 cells of Induced Draft cooling tower has Unit-1&2
Date of approval by State Cleared been completed.
Original Est. cost Rs. 175000 lakhs e) AHP: Bottom ash hopper is in progress. Dry ash
Readiness
Latest Est. cost Rs. 235000 lakhs collection system is nearing completion.
Unit-1 of bottom
Exp. Upto 3/2009 Rs. 217188 lakhs ash hopper.
Exp.During 2009-10 (upto 08/09) Rs. 14209 Lakhs a) Unit synchronised on 16.4.09
b) Coal firing completed in Oct’09 and Unit
Type of fuel Coal
commissioned on 30th Oct’09.
Fuel Linkage 2.31 MTPA from SECL Unit-2
Date of main plant Order: 03.03. 2006 on BHEL (BTG) at Rs. a) Boiler erection started on 21.04.07, drum lifted
780 Crs on 26th Nov’07, hydraulic test conducted on 21st
Power evacuation system 400KV Dahra-Bhilwara S/C, Apr’09 and light up completed on 31st Dec’09.
Chhabra-Hinduan S/C, Chhabra b) Unit synchronized on 31.03.2010.
c) Unit comm. on 04.05.10

- 44 -
Commissioning Schedule
Sl. Project Details Capacity
Original Actual (A) /As Broad Status Critical
No. (MW) now expected Areas
Syn. COD Syn. COD
(Com.) (Com.)
B. PROJECT UNDER CONSTRUCTION
STATE SECTOR
1. Kalisindh TPP 1200 a) LOA Placed on M/s BGR on 09.07.2008 to
RRVUNL execute the project on EPC basis.
(Distt. Jhalawar) b) Zero date of the project is 9th July’ 08.
U –1 600 09/11 01/12 09/11 1/12 c) Coal handling plant is awarded to M/s
(12/11) (12/11) TRF.
d) Ash handling plant is awarded to M/s
U-2 600 12/11 04/12 12/11 4/12 Macawber Beekay.
(3/12) (3/12) e) DM/PT plant awarded to M/s BGRESL.
f) Chimney: 191 out of 275 mtrs. RCC shell
Org. Est. cost Rs. 490006 lakhs
completed.
Latest Est. cost Rs. 490006 lakhs Unit-1:
Exp. Upto 3/2009 Rs. 62675 lakhs a) Boiler erection started on 7th Dec 09.
Exp.During 2009-10 Rs. 37557 Lakhs b) Boiler drum is lifted on 19th May’10.
(upto 8/09) Boiler erection is in progress, 460 MT out
Type of fuel Coal of 5440 MT pressure part erection
Fual Linkage Captive- “Parsa East and Kanta completed. 1448/27531 joints completed.
Basin” c) ESP erection is in progress.
Date of main plant Order M/s BGR on 09.07.2008 (EPC) Unit-2:
a) Boiler erection started on 26th Mar 10.
(Supplier of TG, SG & Aux. – M/s
b) Boiler structure erection is in progress,
DEC) 2330MT out of a total 5900 MT structure
Power evacuation system steel erection completed.
2. Chhabra TPP Extn. 500 a) LOA Placed on M/s BHEL. An advance of
RRVUNL Rs.7421.25 lacs paid to BHEL.
(Distt. Baran ) b) Order for all BOPs except (C&I), has been
U-3 250 09/11 - 01/12 05/12 placed on M/s Indure.
(12/11) 04//12 c) C&I order has been placed on M/s IL Kota.
d) Order for Cooling Tower placed on M/s
U-4 250 10/11 - 04/12 08/12 Paharpur Cooling Tower.
(3/12) 07/12 e) Order for chimney also placed.
Org. Est. cost Rs. 220000 lakhs f) Order for Switchyard equipment, 6.6kV
Latest Est. cost Rs. 220000 lakhs switch gear, Generator Transformer,
Exp. Upto 3/2009 Rs. 21367 lakhs Station Transformer etc. placed on M/s
ABB.
Exp.During 2009-10 Rs. 90231 Lakhs
g) Excavation for boiler foundation
Exp.During 2010-11 Rs. 7771 Lakhs completed. PCC work is in progress.
Type of fuel Coal h) Order for main plant civil works for both
Fuel linkage Captive- “Parsa East and Kanta units placed.
Basin”
Date of main plant Order M/s BHEL on 20.08.2008
Power evacuation system
3 Ramgarh CCPP Extn.- 160
III, RRVUNL a) Main Plant order placed on M/s BHEL on
Distt. Jaisalmer 14.07.2009.
GT-1 110 11/11 11/11 b) Gas supply and transmission agreement
executed with GAIL on 7.8.09 for supply
ST 50 03/12 03/12 of 0.95 MMSCMD gas out of which 0.75
Date of approval by State Cleared State Govt. MMSCMD will be used for expansion
Est. approved cost Rs. 64000 Lakhs project and remaining gas will be used for
existing units.
Expenditure till Rs. Lakhs
Type of fuel LNG
Fuel Linkage 0.95 mmscmd gas
Date of main plant Order M/s BHEL on 14.07.09 (BTG)

- 45 -
Commissioning Schedule
Sl. Project Details Capacity Original Actual (A) /As Broad Status Critical
No. (MW) now expected Areas
Syn. COD Syn. COD
(Com.) (Com.)
C Private Sector
1 Jallipa Kapurdi TPP 1080 BOPs
Raj West power ltd. a) 6.6kV/440V two dry type transformers
(Distt. Barmer) and turbine MCC charged
U –1 135 09/09 10/09 08/09(A) 11/09 b) 183 km of RW pipeline laid.
Unit-1
(10/09) 10/09(A) (A) Unit synchronized on 17.08.09,
commissioned on 16.10.09 and COD
U-2 135 10/09 11/09 6/10(A) 08/10 achieved on 26th Nov. 09.
(11/09) 7/10(A) Unit-2
Unit synchronized on 16th June’10 and
U-3 135 12/09 01/10 08/10 10/10 achieved full load on 8.7.10.
(01/10) (09/10) Unit-3
a) Boiler drum lifted on 19.3.08. Boiler
structure 89% completed.. APH99% and
U-4 135 02/10 03/10 09/10 11/10 pressure parts erection 93% completed.
(03/10) (10/10) b) Common chimney for Unit- 3&4 shell
casting completed.
U-5 135 05/10 07/10 11/10 01/11 c) ESP erection 99% completed. Collecting
(07/10) (12/10) plate alignment is in progress.
d) Boiler H/T completed on 12th Jun’10 and
U-6 135 07/10 08/10 01/11 03/11 BLU is expected in Aug’10.
(08/10) (02/11) e) Unit synchronization is expected in 08/10.
Unit-4
a) Drum lifting completed on 2.6.08. Boiler
U-7 135 08/10 09/10 02/11 04/11 structure erection 90% completed. APH
(09/10) (03/11) 98% and pressure part erection 97%
completed.
U-8 135 11/10 12/10 05/11 07/11 b) ESP erection 93% completed. Collecting
(12/10) (06/11) plate alignment is in progress.
Unit-5
Est. approved cost Rs. 507500 lakhs a) Boiler drum lifted on 4.8.08, boiler
structure work 86% completed. APH
Revised cost Rs. 507500 lakhs erection 89% and pressure part erection
Exp. During 2007-08 Rs. 105496 lakhs 54% completed.
Exp. During 2008-09 Rs. 236408 lakhs b) Common chimney for Unit- 5&6 shell
Exp. Upto 2009-10(upto 9/09) Rs. 48862 lakhs casting completed.
c) ESP erection 92% completed.
Exp.During 2010-11 Rs. -- Lakhs Unit-6
Type of fuel Lignite a) Boiler structure work 82% completed.
Fuel Linkage Captive coal mines from Jallipa & b) ESP structure work 87% completed. APH
Kapurdi, 40,000 MT coal from erection 81% completed and pressure part
erection 56% completed.
Indonesia.
c) Chimney for Unit 5&6 completed.
Date of main plant Order Unit-7&8
3/07 on M/s Dongfang a) Boiler structure work for Unit 7&8 is 27%
Power evacuation system 400 KV Jhodpur - 1nos. and Barmer &30% completed respectively.
b) ESP for U-7 77% completed & U-8 7%
– 2 nos.
completed.
200KV, Dohrimanna – 2 nos. & c) Common chimney for Unit-7&8
Barmer – 1nos. completed.
d) Ash cooler, startup burners, ignition &
fuel oil system shipped from China.

- 46 -