Professional Documents
Culture Documents
Deliverable-Oriented and
Schedule-Driven Project
Execution
By Dong Choi, PMP
Activity Duration and Critical Path Calculation The overall scope of work in this project consists of
• P&ID duration = 200 x 100 / (100 x 40) = 5 wks seven activities. The seven activities are sequenced in the
• Piping dwg duration = 4500 x 4 / (25 x 40) = 18 wks Precedence Diagram Method in Figure 2. The preparation of
• Pipe install duration = 335,000 / (100 x 6 x 15) = 37 P&IDs, for instance, should be completed prior to the start
wks of the preparation of the piping drawings and equipment
�������� ��������
����� ����
������� �����
��� ����
������ ������
���� �������
procurement. After activity sequencing, the duration of each The activity of Equip Proc or Equip Install may cause
activity was calculated dividing unitized work volume (e.g., a delay of up to 16 weeks, which still does not delay overall
20,000 man-hours required for preparing 200 P&IDs) by project schedule. The 16 weeks of the activity is called the
unitized resource requirements (4,000 hours per week can be “float.”
worked off by 10 engineers). The numbers of weeks for the
duration of Figure
activities2:
areActivity
shown onsequencing—Precedence
the Precedence Diagram Primavera
diagramming Outputs
method.
Method in Figure 2. Primavera is a universal scheduling tool for large, project-
There are two paths in the project schedule: P&ID → intensive industries, including EPC.
Piping Dwg → Pipe Proc → Pipe Install → Hydro & Precom Figure 3 shows the print-outs of Primavera run of the
(Path 1) and P&ID → Equip Proc → Equip Install → Pipe sample scheduling problem.
Install → Hydro & Precom (Path 2). To find a critical path 1. The Gantt chart in Figure 3 is a typical presentation of
and overall duration of the project, the durations of individual the schedules. From the Gantt chart, one can see that
activities were added. Path 1 takes 126 weeks while Path 2 equipment procurement is planned to:
takes 110 weeks. Therefore, Path 1 is a critical path (the path Take 44 weeks
with the longest duration) whose duration of 126 weeks is the Start 2 October 2006
project duration in the problem. Complete 5 August 2007
PROJECT Nov/15/2009
ACT ID Work Description Resp Plan Start Plan Comp Act Start Act Comp Dev. Progress Remark
Links to: Action Log,
Best Practice, Lessons
Learned, Scope Change,
Risk Register
OKGP06010 Project Procedure for Commissioning - IFR
OKGP07020 Project Procedure for Training - IFC
OKEP06030 A/G Isometrics Dwg (<3") - IFC
OKEP13030 A/G B/M Take Off - Final
OKEE09020 Relay Coordination Study - IFC
OKEE18020 Communication Plan - IFC
OKEN12020 Location Plan of Instrument by Area - IFC
OKEV32020 FDN Dwg for Safety Shower Chiller - IFC
OKEV33020 FDN Dwg for UV Light Control Package - IFC
OKEV34020 FDN Dwg for Chemical Injection Unit - IFC
OKEV35020 FDN Dwg for Local Support - IFC
OKEB08020 Chemical Storage Architecture Dwg - IFC
OKET21010 Shop Dwg for Local Support
OKEH03020 HVAC Dwg for Analyzer House - IFC
OKPS06040 Tray & Packing (Tower-1) - Manufacture (60%)
OKPS07040 Tray & Packing (Tower-2) - Manufacture (60%)
OKPS08040 Vessel-1 - Manufacture (60%)
OKPS09050 Vessel-2 - Manufacture & Ex-work (1st)
OKPS09055 Vessel-2 - Manufacture & Ex-work (1st)
OKPS10040 H/ex.-1 - Manufacture (60%)
OKPS11040 H/ex.-2 - Manufacture (60%)
OKPS14040 Plate H/ex. - Manufacture (60%)
OKPS20050 Ejector - Manufacture & Ex-work
OKPS21050 Eductor - Manufacture & Ex-work
OKPS22060 Desuperheater - Delivery to Site
OKPR08040 Cycle Water Treat'g Unit - Manufacture (60%)
OKPR09040 Incinerator Package - Manufacture (60%)
OKPR10050 Oil Mist Generator - Manufacture & Ex-work
OKPR13040 Chemical Injection Unit - Manufacture (60%)