Professional Documents
Culture Documents
Estimate to complete - How much more the project would cost from this
point onwards?
PERT = (O + 4ML + P) / 6
STD. DEV. OF TASK = P – O / 6
TASK VAR. = [(P - O)/6 ] squared = Std. Dev ^ 2
CP STD. DEV. = √ σ² + σ² + σ²
SIGMA
1 = 68.26
2 = 95.46
3 = 99.73
6 = 99.99
Channels of Communication =(n (n – 1)) / 2
Project Selection
Payback Period Less is better Net Investment / Avg. Annual cash flow
Class of Estimates
Definitive +10-10%
Order of Magnitude > + 50/-50%)
Contract Incentives
Savings = Target Cost – Actual Cost
Bonus = Savings x Percentage
Contract Cost = Bonus + Fees
Total Cost = Actual Cost + Contract Cost
Point of Total Assumption (PTA) ((Ceiling Price - Target Price) / buyer's Share
Ratio)+ Target Cost