Name of Work: Widening the existing SH-132 Commencing From Ch: 1+500 to Ch:10+000 4-Lane CW and Ch: 10+000

to Ch: 27+170
2-Lane CW from Bellary City to Karnataka/AP Border on DBFOT Annuity Frame Work

S.No Item Deacription Unit Qty SEW Rate Amount RK RateVariation Remarks

Clearing and grubbing road land including removal of


appurtenances complete as per drawings and Technical
1.01 Specifications Clause 201 with all leads and lifts and as per the
Ha 1.82 26148 47600 26344 196 0.75%
instructions of Employer's Representative.

Dismantling pavement including disposal of unsuitable material


and stacking of serviceable material l and / or salvaging useful
1.02 materials complete with all lead and lifts as per Technical
Specifications Clause 202 and as per the instruction of
Employer's Representative.
a) Bituminous Pavement courses Cum 105 105 0 Ok
b) Granular material Cum 78 79 1 1.28%

1.03
a) Plain cement concrete Cum 889 896 7 0.78%
b) Reinforced concrete Cum 889 896 7 0.78%
c) Stone / brick structures Cum 209 211 2 0.96%
d) Guide Rails / Fencing / Kerb / Gutters / Pipes Lm 314 316 2 0.64%
e) Dismantling of Causeways pipe Lm 1046 1054 8 0.76%
f) Km stones / 5 km stone / Hectometer stone /Utility Services Nr 209 211 2 0.96%
g) site preparatory works and pre-construction activities Ls 1 10000000 ###

2.01
(a) All types of soil/ Soft Rock Cum ### 54 297820 55 1 1.85%
(c) Hard Rock without blastering Cum 513 516 3 0.58%

Construction of embankment with approved material from borrow


2.02 areas complete as per drawings and Technical Specifications Cum ### 195 ### 190 -5 2.63%
Clause 305 with all leads and lifts and as per the instructions of
Employer's Representative.
Name of Work: Widening the existing SH-132 Commencing From Ch: 1+500 to Ch:10+000 4-Lane CW and Ch: 10+000 to Ch: 27+170
2-Lane CW from Bellary City to Karnataka/AP Border on DBFOT Annuity Frame Work

S.No Item Deacription Unit Qty SEW Rate Amount RK RateVariation Remarks
Construction of subgrade/shoulder for Main Carriageway
including bus/ Truck bye, Service Road, Approaches to
Underpass with approved materials from borrowpits satisfying
2.03 four days soaked CBR value of not less than 8 % complete as Cum 217 211 -6 2.84%
per drawing and Technical Specification Clause 305& 407 with
all leads lifts and as per instructions of Employer's
representative.

Construction of earthen shoulder with approved material


complete as per drawing and Technical Specifications Clause
2.06 407 & 401 with all leads and lifts and as per the instructions of
Cum 209 211 2 0.95%
Employer's Representative.

Filling of median/island and compaction to 95% MDD and as per


2.07 drawings and Technical Specifications Clause 407 with all leads Cum 188 190 2 1.06%
and lifts and as per the instructions of Employer's
Representative.