You are on page 1of 9

Koç University Graduate School of Business

EMBA Program Today’s Agenda


ƒ Wrap-up: How to manage processes effectively
to improve flow rate?
ƒ Quiz 1
OPSM 901: Operations Management ƒ How does variability impact processes flow rate
andd flflow titime?
?
– Multi-stage processes: process time variability
Session 4:
– Single stage process arrival and process time
-The role of Variability variability
-Lean Principles - Lean Principles
- Turkish Airlines Case
2
OPSM901 Operations Management OPSM901 Operations Management

Wrap-Up:
Multi-Product Process Analysis & Apps Bottleneck
ƒ Manage better with the three key operational measures and an inter- ƒ Bottleneck:The factor which limits production
functional macro process view of the organization
ƒ Process measures:
ƒ (Internal)Theoretical bottleneck is the resource
– Flow time → manage critical activities with minimum theoretical capacity
– Capacity → manage bottleneck resources
ƒ Levers for improving
– Flow time → manage critical activities Effect of product mix on the bottleneck:
– Capacity & Throughput Part A
R1:Cutting R2:Finishing
ƒ Process capacity depends on a zillion things
– Effect of product mix decisions on process capacity 3 min/part 2 min/part
• marginal contribution per unit of bottleneck capacity used
Part B Unit Load calculations can
– Bottleneck may shift on adding capacity
Account for the product mix–
Î diminishing returns to capacity investment
50% A-50% B product mix, unit loads: i.e. How much a resource is
R1: 1.5 min/part (3x0.5) needed affects the Bottleneck
R2: 2 min/part bottleneck!

4
OPSM901 Operations Management OPSM901 Operations Management

Bottlenecks: Buffers and Inspection Theory of Constraints: from “The Goal”

Five steps for effective process management:


Station #1 Station #2 Station #4 Station #5

3.5 /hr 3.5 /hr 1 /hr 3.5 /hr 3.5 /hr


ƒ Step 1: Identify the constraint
ƒ Step 2: Exploit the system’s
system s constraints
ƒ How would you release Raw Material into
station #1?
ƒ Step 3: Subordinate everything else
ƒ Where should you place buffer inventory? ƒ Step 4: Elevate the constraint
Why? ƒ Step 5: if new constraint go to Step 1-2
ƒ Where would you place inspection
equipment?

5 6
OPSM901 Operations Management OPSM901 Operations Management

1
Things that influence flow time

ƒ Process control
– What we illustrated with Gantt charts
Protecting the bottleneck: – Schedule resources to synchronize flows with the
bottleneck
effective scheduling and effective lot-sizing
ƒ Lotsize
– Before I move from one product run to another,
how much will I produce
• Physical constraints
• Customer order size
• Managerial decisions
ƒ Set-up time/production time
8
OPSM901 Operations Management OPSM901 Operations Management

High-Inventory Manufacturing Low-Inventory Manufacturing


Batch Batch
size=1000 3.64 months (24 hrs a day, 7 days a week) Order : size=200 1.91 months Order :
1000 units Move batches of 200 1000 units
Release materials according
A : 1/2 hr/unit 1 2 3 4 5 A : 1/2 hr/unit
inventory to the bottleneck

B : 1/10 hr/unit 1 2 3 4 5 B : 1/10 hr/unit

avg. C : 1 hr/unit C : 1 hr/unit


inventory
inventory
B : 1/10 hr/unit 1 2 3 4 5 avg. B : 1/10 hr/unit
inventory
D : 3/4 hr/unit 1 2 3 4 5 D : 3/4 hr/unit
750 850 1000 1850 2000 2450 9
Time (hours) 1000 1290 2000 Time (hours) 10
Wait for the bottleneck
OPSM901 Operations Management OPSM901 Operations Management

Comparison: Large batches or Small batches?


Lotsize decision

A ƒ When do you detect


Small batches
(low-ınventory)
ƒ Three products: P1, P2, P3
Large batches (high-inventory) quality problems?
ƒ Produce 100 units of each
B ƒHow do you
incorporate
ƒ Alternatives
engineering changes? – 100 P1 100 P2 100P3
C ƒDue-date – 1P1 1P2 1P3 1P1 1P2 1P3
performance? • 100 times set-up
B ƒMargins? (lead time) ƒ Set-up time
ƒForecast accuracy? – Cutting tools, cleaning, calibration, loading programs,
D
etc.

11 12
OPSM901 Operations Management OPSM901 Operations Management

2
How increase capacity?Summary of Typical Actions
Set-up times ¾ Key action = optimize only bottleneck management
ƒ Decrease the work content of bottleneck activities
– Never unnecessarily idle (“starve”) bottlenecks = eliminate bottleneck waits:
ƒ Set-up time does not depend on lotsize and is • Reduce variability if it leads to bottleneck waiting
• Synchronize flows to and from the bottleneck: sync when resources start an
the same for all lotsizes. activity
– work smarter:
• Reduce & externalize setups/changeover times, streamline + eliminate non-
ƒ Production time depends on lotsize value added work
– do it right the first time: eliminate rework/corrections
– Not always
y ((baking,
g heat treat)) – work faster

ƒ Long set-up times large lotsizes ƒ Move work content from bottlenecks to non-bottlenecks
– create flexibility to offload tasks originally assigned to bottleneck to non-critical
ƒ Reduce set-up time to produce in small lotsizes resource or to third party
• Can we offload tasks to cross-trained staff members?

ƒ Increase Net Availability of Process


– work longer: increase scheduled availability
– increase scale of process: invest in more human and capital resources
– eliminate unscheduled downtimes/breakdowns
• Preventive maintenance, backups, etc.

ƒ Note that the bottleneck may shift after improvement


13
OPSM901 Operations Management OPSM901 Operations Management

Variability = Actual - Expected

Average value

Range of observed values

Fluctuations in values
THE ROLE OF VARIABILITY
Variance (or Standard deviation) of
the values

15 16
OPSM901 Operations Management OPSM901 Operations Management

Key Points:
Variability in task times
The role of variability
Note there is no buffer between stages:
ƒ if task times are similar will have a balanced line
Capacity/hr: Capacity/hr:

6units/hr 6units/hr 6/hr


6units/hr 6units/hr 6/hr
ƒ in the absence of variability (deterministic task
4 or 8/hr 4 or 8/hr 5/hr
times) complete synchronization is possible,
idleness is minimized
2 or 10 2 or 10 4/hr

ƒ In the presence of variability full 0 or 12 0 or 12 3/hr


synchronization cannot be achieved
As variability increases, throughput (rate) decreases
17 18
OPSM901 Operations Management OPSM901 Operations Management

3
Compounding effect of variability and unbalanced
Resource interaction effects
task times
In a serial process downstream resources depend on upstream
resources: can have temporary starvation (idleness)

6/hr 6/hr 6/hr 6/hr 6/hr 6/hr 4/hr 4/hr

6/hr 4 or 8/hr 4 or 8/hr 4 or 8/hr 4.5/hr 4 or 8/hr 2 or 6/hr 3 5/h


3.5/hr

6/hr 2 or 10 2 or 10 2 or 10 3/hr 2 or 10 0 or 8 2.5/hr

6/hr 0 or 12 0 or 12 0 or 12 1.5/hr

As variability increases, the impact of resource interaction increases


19 20
OPSM901 Operations Management OPSM901 Operations Management

Want to reduce resource interference in your


processes: how?

–Dependent Events: Products require more


than one step ƒ smaller lotsizes (smaller batches)
–Statistical Fluctuations: Machine and human ƒ better balanced line
variations; errors; raw material quality ƒ by speeding-up bottleneck (adding staff, changing
problems; procedure, different incentives, change
technology)
Dependent Events + Statistical Fluctuations
ƒ through cross-training
Reduced Production ƒ eliminate steps
ƒ buffers
Whenever we have dependent events, their ƒ integrate work (pooling)
fluctuations don’t average out; they accumulate

21 22
OPSM901 Operations Management OPSM901 Operations Management

Want to eliminate as much variability as


possible from your processes: how? Process management
ƒ Strategic positioning-establish product capabilities
ƒ specialization in tasks can reduce task time variability ƒ Determine appropriate process capabilities: time, quality,
ƒ standardization of offer can reduce job type variability cost, flexibility
ƒ Process design, appropriate selection of resources
ƒ automation of certain tasks
ƒ Process documentation: flowchart
ƒ IT support: templates, prompts, etc.
ƒ Analyze at macro level
ƒ Incentives – Where is the bottleneck?
ƒ Scheduled arrivals to reduce demand variability – Is capacity enough?
ƒ Initiatives to smoothen arrivals – How is time performance?
– Where do quality problems occur?
ƒ Analyze at micro level
– Scheduling: focus on the bottleneck
– Set-up times, lotsize
– Reduce variability
23 24
OPSM901 Operations Management OPSM901 Operations Management

4
Framework for Process Flow Management

Flow Chart Process

Identify Bottlenecks Identify Critical Path

Maximal Flow Rate Minimal Flow Time VARIABILITY DRIVES WAITING:


mean Macro Average No Process
Competitive?

Demand
Performance Re-Design EVEN IN SINGLE STAGE
Pattern
Micro Variability
Yes
No Demand &
PROCESSES
Competitive?
Performance Supply Mgt
variability
Yes Continuous
Improvement
25
OPSM901 Operations Management OPSM901 Operations Management

Consider service processes Why do queues form? Why is there waiting?


Call #
10
ƒ This could be a call center or a restaurant or a shared 9

service center
ƒ High utilization: 8
7
6
– throughput/capacity 5
ƒ Customers or customer jobs arrive to the process; their 4
3
arrival times are not known in advance – High inflow rate 2
1
ƒ Customers are processed.
processed Processing rates have some – Low processing rate 0
0 20 40 60 80 100

ƒ variability:
TIME
variability.
ƒ The combined variability results in queues and waiting. Inventory (# of calls in system)
– arrival times 5

ƒ We need to build some safety capacity in order to – service times 4

reduce waiting due to variability – processor availability


3

2
Stability condition:
1
average system capacity > average demand=throughput
0
0 20 40 60 80 100
27 TIME 28
OPSM901 Operations Management OPSM901 Operations Management

Why is there waiting? A measure of variability

ƒ the perpetual queue: insufficient capacity ƒ Needs to be unitless


ƒ the predictable queue: peaks and rush-hours ƒ Only variance is not enough
ƒ the stochastic queue: whenever customers come faster
than they are served
ƒ Use the coefficient of variation
ƒ CV= σ/µ (standard deviation/mean)
In presence of variability we need to build
safety capacity in system to have a stable system:
(i.e. average system capacity > average demand=throughput)

29 30
OPSM901 Operations Management OPSM901 Operations Management

5
Example: CV=1
Histogram of exponential distribution:
Interpreting the variability measures interarrival times at an outpatient clinic

CVi = coefficient of variation of inter-arrival times

i) constant or deterministic arrivals CVi = 0

ii) completely random or independent arrivals CVi =1

iii) scheduled or negatively correlated arrivals CVi < 1

iv) bursty or positively correlated arrivals CVi > 1

31 32
OPSM901 Operations Management OPSM901 Operations Management

Generalized Throughput-Delay Curve In words:

Average ƒ In high utilization case: small decrease in


Flow
Time T utilization yields large improvement in response
Variability
Increases time
ƒ This marginal
g improvement
p decreases as the
slack in the system increases
ƒ Reducing the utilization of bottleneck stage
results in the highest response time reduction
Tp

Utilization (ρ)= arrival rate/service rate 100% ρ


33 34
OPSM901 Operations Management OPSM901 Operations Management

Performance Improvement Levers


Check a simulation:
ƒ Capacity Utilization / Safety Capacity
ƒ Waiting Line Simulation – Demand Management (arrival rate)
• Peak load pricing
– Increase Capacity (processing rate)
ƒ http://archive.ite.journal.informs.org/Vol7No1/DobsonShumsky/security_simulation.php
• Number of Servers (scale)
• Processing Rate (speed)
ƒ You can check the effect of CV and utilization (arrival rate/service rate) on
waiting ƒ Variability Reduction
– Arrival times
• Scheduling, Reservations, Appointments
– Processing times
• Standardization, Specialization, Training
ƒ Synchronization
– Matching capacity with demand

35 36
OPSM901 Operations Management OPSM901 Operations Management

6
Effect of Pooling (Resources)
The impact of task integration (pooling)
Ri/2 ƒ balances utilization...
Server 1
Ri Queue 1 ƒ reduces resource interference...
ƒ ...therefore reduces the impact of temporary
Ri/2 bottlenecks
Server 2
Queue 2 ƒ there is more benefit from pooling in a high utilization
and high variability process
ƒ pooling is beneficial as long as
Server 1 • it does not introduce excessive variability in a low variability
Ri system
Queue • the benefits exceed the task time reductions due to
Server 2 specialization

37 38
OPSM901 Operations Management OPSM901 Operations Management

Summary of fundamental process principles

ƒ identify and eliminate bottlenecks


ƒ reduce as much variability as possible
ƒ eliminate handoffs, improve communication to
minimize resource interference MANAGING VARIABILITY IN
ƒ for high utilization processes build-in more slack
OUTPUT PERFORMANCE:
QUALITY MANAGEMENT &
LEAN PRINCIPLES

39 40
OPSM901 Operations Management OPSM901 Operations Management

Elements of Lean Thinking (TPS)


The Ideal: Synchronization and Efficiency : Just the right part in the right Process Control Chart
quantity at the right time in the right place, at minimum cost

ƒ All processes in control and capable


ƒ Level production (Heijunka)
– Smooth production runs
Prrocess Measure

– Connect the production system to the customers-produce as


they want (“pull”)
– Minimize changeover times
ƒ Eliminate Waste (Muda)
Every task/activity/function must add value
Time
– Defect, inventory,waiting, movement are non-value adding
ƒ Expose sources of waste (Jidoka)
ƒ Information: Monitor process variability over time
Problems are natural and are opportunities to learn
ƒ Control Limits: Average + z Normal Variability
– Problem visibility, fast feedback, correction
– Management by sight ƒ Decision Rule: Ignore variability within limits as “normal”
ƒ Continuous improvement (Kaizen) Investigate variation outside as “abnormal”
ƒ Errors: Type I - False alarm (unnecessary investigation)
– Buffer reduction and employee involvement Type II - Missed signal (to identify and correct)
– Management by stress 41 42
OPSM901 Operations Management OPSM901 Operations Management

7
Process Capability:
Process Control and Improvement Ability to Meet Customer Requirements
Process output
Customer Requirements(Specs): (LS,US)=(75,85)

ƒ Proportion of Output Within


Specs: Given a Process in control
Out of Control In Control Improved with µ = 82.5 psi and σ = 4.2 psi
P(Meet Specs) = 0.699
LS µ US
UCL
ƒ Shifting µ to 80 yields P(Meet
Specs) = 0.766
µ
ƒ Reducing σ to 2.5 yields P(Meet
Specs) = 0.9544
LCL

43 44
OPSM901 Operations Management OPSM901 Operations Management
LS µ US

Synchronize to reduce waste: Synchronize to reduce waste:


customer demand pulls product Quality at the Source

PUSH: Inputs availability triggers execution ƒ Quality at source also improves time and
throughput performance
Supplier Process Customer ƒ Fool-proof/Fail-safe design (Poka-Yoke)
inputs outputs
ƒ Inspection
– Self
– Automated (Jidoka)

PULL: Outputs need triggers execution ƒ Line-stopping empowerment (Andon)


ƒ Human infrastructure
Supplier Process Customer
inputs outputs

45 46
OPSM901 Operations Management OPSM901 Operations Management

Synchronize to reduce waste: Reducing waste: Increase Problem Visibility


Just-In-Time operations The River Analogy:Lower the Water to Expose the Rocks

JIT = have exactly what is needed, in the quantity


it is needed, when it is needed, where it is
needed.
ƒ Reduce transfer batches
ƒ Level load production
ƒ Pull rather than push work Defects
Inventory

ƒ Quality at source Defective Materials Machine Breakdowns Long Set ups

ƒ Set up cells Long Lead times Unsuitable Equipment Uneven Schedules

Unreliable Suppliers Inefficient Layouts Absenteeism


47
Rigid Work Rules
48
OPSM901 Operations Management OPSM901 Operations Management

8
Ongoing objectives Process Improvement
ƒ Improve process flows
– Efficient plant layout
ƒ Measurement
– Fast and accurate flow of material and information
– External and Internal
ƒ Increase process flexibility
ƒ Analysis
– Reduce changeover times
– Analyze Variation P D
– Cross
Cross-training
training
ƒ Control C A
ƒ Decrease process variability Improve
– Adjust Process
– Flow rates
– Processing times
ƒ Improvement Innovate

– Quality – Reduce Variation P D

ƒ Minimize processing costs ƒ Innovation C A


Improve
– Eliminate transportation, inspection, rework – Redesign Product/Process Control

49 50
OPSM901 Operations Management OPSM901 Operations Management

Services: customers introduce variability Customer assessment of service quality


external
ƒ Arrival variability Dimensions of
service quality
word of mouth personal needs past experience communication

ƒ Request variability
ƒ Capability variability • tangibles
• reliability
ƒ Effort variability • responsiveness
• competence
ƒ Subjective preference variability • courtesy
• credibility expected service
• security Perceived
• access service
• communication quality
• understanding
the customer perceived service

51
OPSM901 Operations Management OPSM901 Operations Management

Identifying quality shortfalls


Next Time
Reference:A. Parasuraman, VA Zeitham and LL Berry, Journal of Marketing, 1985

word-of-mouth personal needs past experience ƒ Quiz 2: Chapters 4,5 and today’s lecture notes
expected service
ƒ Study questions: Exercises from the book
Gap 5 ƒ Individual Assignment
perceived service ƒ Please read the beer game handout and be
Customer
Provider
prepared to play the game
service
delivery ƒ Barilla Case-a quick read will be enough
Gap 3:
Gap 1: quality of conformance quality
design Gap 4 external
service quality communications
Gap 2: specifications to customer
quality function
deployment
management
54
perceptions
OPSM901 Operations Management OPSM901 Operations Management

You might also like