Professional Documents
Culture Documents
APCPDCL has a vast infrastructure facility in its operating area with 1,338 Nos.
of 33/11 KV substations, 2,039 Nos. of power transformers, 720 Nos. of 33 KV feeders,
5,257 Nos. of 11 KV feeders and around 2,46,426 Nos. of distribution transformers of
various capacities.
A number of new initiatives for improving the quality supply of power were introduced
by APCPDCL such as:
Having electrified 6,489 villages, 5,600 general hamlets, 2,059 tribal hamlets, 12,105
Dalit wadas and 5,806 weaker sections colonies, APCPDCL is looking forward to meet
many challenges with promise to deliver quality customer services through innovative
programmes. The philosophy of APCPDCL is to continually striving to enhance its
performance and emerge stronger by the day to offer its customers the best and value for
money.
The company is managed by a Board of Directors consisting of the following members:
Chairman and Managing Director: Mr. M.T. Krishna Babu,IAS
Director (IPC,RAC ): Mr. B. Ravindra Reddy B.E.
Director (P & MM): Mr. KH. Ghulam Ahmed, B.E.
Director (Commercial & Customer Services): Mr. A. Srinivasa Rao, B.E.
Director (Finance): Mr. P. Rajagopal Reddy
Director (Operation - Rural): Mr. B. Veera Reddy
Director (Projects & IT ): Mr. G.Raghuma Reddy
Director (HRD & IR, Operations -Greater Hyderabad ): Mr. K.Venkata Narayana.
ABSTRACT
In India the losses in low voltages network constitute about 30% of total
energy, these losses occur in commercial, domestic, Industrial and agricultural sectors.
Among these agricultural sectors plays a prominent role. The existing distribution system is
low voltage distribution system. The characteristics of the system are installation of 3-
This is an agricultural demand side management project that may reduce the
technical and commercial losses by enhancing the distribution system efficiency using high
voltage distribution system i.e., high voltage line is taken as near the load
possible
as and
distribution transformer of appropriate capacity (16/25KV A) are installed to feed one or small
B y this project in agricultural dem and side area the line losses can be reduce up to
10% to 12% than the losses present in existing system . There are m any advantages in
im plem enting H V D S system such as failures of distribution transform er, m inim ization of
interruptions etc. H VD S is the solution for the reduction of pow er losses by utilizing the sam e pole
CHAPTER-1
INTRODUCTION
1.1 GENERAL:
The pump loads consume nearly 30 to 40% of the total Electrical Energy
production and are growing rapidly. At the same time, the agricultural tariffs do not
provide sufficient revenue to cover the cost of production. The studies on end use
efficiency of pump sets have also indicated that the overall efficiency of the pump sets is
as low as 20% against achievable efficiency of 60% one of the main contributing factor
for low efficiency of the pump sets is the prevailing Low voltages(as low as 70% of rated
voltage) at the pump sets terminals. The low voltages have also resulted in high technical
loses in low voltage network (about 10%).Another menace of Distribution network is
rampant taping from long LV lines and extracting energy illegally. An agricultural
Demand side management program comprising enhancing Distribution system efficiency
by using 11KV High voltage Distribution System (HVDS).HVDS envisages installation
of small capacity Distribution Transformers to feed 2 or 3 pump sets with a view to
minimize LV loss extending HV lines near the load as possible by the method of clusters.
The loads in Rural distributions are widely dispersed and to fetch a small load
of 4 KW (5 HP) LT lines are run for long distances. For a 400 KVA load, the amperage
at 11 KV is 5 Amperes, whereas at LT it is 140 Amps. Prior to introduction of HVDS, 11
KV, 3-phase lines are run up to large sized 3-phase transformers 11KV / 433V from
which lengthy 3-phase LT Lines are run. Such a system is found not suitable for Indian
conditions, especially Rural, as voltage profiles is poor, losses are high and outages in
supply are also high.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 02
CHAPTER II
2.1 INTRODUCTION:
The long LV lines of small conductor size cause high line losses. The low voltage
network energy losses alone are estimated to be 8% to 10% of total energy handled in
other words, the LV network contributes to about 30% of total energy losses. The
international norm for energy loss in low voltage network is 1% to 2%.Thus the energy
losses of LV network are 5 to 6 international norms.
The voltage drop in LVDS is very high as the lines are long and conductor sizes are
small. The sample studies made in Andhra Pradesh distribution system indicated the 50% of
LV feeders have more than 10% voltage drop and another 25% have 5 -10% voltage drop . The
maximum permissible voltage drop on LV feeders is 6% in accordance with IE rules - Rule 56.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 04
The present failure rate of 3-phase distribution transformers is 19.91%. The major
contributing factors for this high failure rate are LT line faults and indiscriminate loading of
transformers over and about its capacity. The lengthy LT lines LVDS coupled with poor
construction standards are the cause work for large number of LT faults. Further the fault
current due to a fault at tail end of lengthy feeders may not be adequate enough to cause
protective device operation and it reflects as load on the network. Thus these faults cause
frequent failure of transformers. The overloading of transformers could not be effectively
checked, as it serves large number of consumers spread over a wide area.
Original 3ph 100KVA Dist. Transformer replaced 3ph 15KVA Dist. Transformer erected
with 11KV.CTPT set. under HVDS to cater 2 to 3 services
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 05
Due to high drop on LV lines the consumers are subjected to wide voltage
fluctuations with variation of load. All the modem electrical and electronic equipment are
sensitive to voltage variations and the consumers are forced to use stabilizers to provide
stable supply. The voltage stabilizers draw reactive power from the system causing
associated reactive power management problems on the upstream side of the power
system.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 06
2.3 RELIABILITY:
The project area selected is Thipparthy mandal in Nalgonda district of Andhra Pradesh
that comes under APCPDCL where the agricultural loads are concentrated more under
which 4 feeders of distribution transformers are considered which are
1. A. D. Pally feeder
2. Velugupally feeder
3. Vempati feeder
4. Thungathurthy Rural
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 07
Here we have selected A.D.Pally feeder with implementation of HVDS has done
fully. Under the A.D.Pally feeder consisting 05 Nos of 63KVA and 24Nos, of 100 KVA
transformers and 662 Nos, of agricultural services with the connected load of 2760 HP
and it having a length of LT and HT lines are 56.5 Km and 13.2 Km's. The crap pattern
under this feeder mainly consists of paddy and part of land is cultivated with horticulture.
• Voltage drop at the consumer end as such the lines are lengthy High I2R losses as
such lines are in LVDS.
• Frequent motor burn outs due to low voltage and consequent expenditure on
repairs.
• Transformer failures- expenditure towards repairs and Inconvenience to the
consumers. Damage to standing crops, due Lo delay in replacement of failed
distribution transformers.
• Fluctuations in voltages due to more number of consumers connected under this
transformer (say 25 to 30 consumers).
• Nobody owns the transformer since everybody thinks that others will take care of
the transformer.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 09
CHAPTER 3
TABLE 3.1 Characteristics of the HVDS and LVDS system for distribution of some
quantum of power.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 10
Current 11.0
The HV line is taken as near the load as possible and a LV service cable is run
to feed loads. Thus the losses in LV network are negligible. The voltage drop for
Distribution of quantum of power is less than 1% as against that in LVDS and this ensures
proper voltage profile at all customer points. The length of the LT lines are minimum.
Further the AB cables are used for LT lines as current ratings are low. Thus the
failure of transformers due to LV line faults is eliminated. Consumer, whom it serves, as
its failures will affect their supply, will effectively prevent the loading of transformers
over above its capacity. The LT lines are virtually eliminated and even the short LT lines
required would be AB cable. This makes direct tapping of lines of a very difficult task. Each
transformer caters to 2 or 3 consumers and they can be made responsible to prevent any
unauthorized connection on the transformer.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 11
The voltage drop for distribution of same amount of power is less than 1% as against that
in LVDS and this ensures proper voltage profile at all customer premises can be
maintained satisfactorily. This will avoid burning of motors. The LT line network is
replaced with HT network by substituting transformers of 16KVA and 25KVA supplying
3 to 4 nearest loads making LT lines as small as possible.
The voltage drop on the LT line is negligible. The additional drop due to
extension of HV line of consumer premises is also negligible. Thus the voltage profile is
very stable and there will be no need to use voltage stabilizer. Further, any voltage
fluctuations occurring can be remedied by installation of automatic voltage. Summing up
it can be stated that HVDS is technically superior and provides ready solution to the
problem of distribution system.
• Connection of existing pump sets from the newly erected 15KVA distribution
transformers with air bunched cable (ABC).
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 14
The main concept of HVDS is to reduce the losses occurring in the distribution system.
Losses in the distribution system can be identified as
• Technical losses
• Commercial losses
• Copper losses come under technical losses. As the name itself indicates, these
losses depend on current (I) and resistance (R).
R= L/A
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 15
Here, and L cannot be altered as they are not under our control. The only
alternative is to increase the size of the conductor used.
A study has been made in our project by increasing the size of the
conductor from 30sq.mm to 55sq.mm the loss reduction was significant. The losses have
come down from 5.3% to 3.75%. Now let us think about reducing I, i.e. current
We all know very well that for a given load, the current is determined by the formula,
I = Load / 3 V cos
V = voltage Is In Volts
Load in Watts.
Hence, the other alternative is to increase the denominator. That means we have
to increase V or increase cos0 (power factor). The existing power factor of almost all 11
KV feeders is in the range of 0.9 to 0.95 i.e. nearly unity. Hence, the other alternative is
only to increase the voltage.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 16
We can call this system as "LT less system" or "HT system" or HVDS.
• The registered customer will feel ownership and take responsibility and not
allow to meddle the LT network.
• Prevention of unauthorized loads by the customers themselves since the
distribution transformer may fail if loaded beyond its capacity.
• Failure will be minimal because of no over loading and no meddling of LT
lines.
• In the event of equipment failure only 2 or 3 customers will get affected
instead of 25 to 30 customers in original system.
• High quality of supply since there Is practically no voltage drop.
• Less burn out of motors because of good voltage and less fluctuations.
• Considerable reduction in line losses and consequent savings in power
purchase cost.
• Since losses are reduced considerably, power can be supplied to additional
loads without any further investment or infrastructure.
• No additional generation capacity needed for giving new loads due to
reduction in power drawls.
• Accidents due to touching of snapped conductors reduced due to the fact that
the breaker trips at substation since the line is a 11 KV potential.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 17
• The motors are drawing lesser currents and hence life span of motor is increased.
The rate of motor burn outs is also reduced.
• The motors running smoothly without hissing noise.
• The transformer failures are almost avoided.
• Theft of energy eliminated since the consumers will not allow others to pilfer from
their distribution transformer.
• Interruptions have been minimized and quality of supply is assured,
• Due to reliability of supply, 2 crops can be raised and can increase the
productivity.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 18
CHAPTER-IV
The LT lines are short and insulated, avoiding all LT faults. The reliability of
HV system can easily be improved by providing sectionalizes or autoreclosures on the
line. The failure of transformer will affect a very small number of consumers served by it.
Thus the reliability of power supply is very high in HVDS.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 19
The high voltage drops in the LV network results in low voltages at customer
premises particularly agricultural pump sets. This resulted in large scale burning of pump set
motors the efficiency of motors is lower than rated voltage. Thus the end use equipment efficiency is
low resulting in wastage of energy in LVDS.
The voltage drop for distribution of same amount of power is less than 1% that of
LVDS and thus the voltages at the consumer premises can be maintained satisfactorily. This
will avoid burning of motors. Thus the end use equipment efficiency is very high in LVDS.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 20
The major factors involved in the failure of DTRS in LVDS are LT line faults and
indiscriminate loading of transformers over and above its capacity. The over loading of
transformers could not be alternatively checked, as It serves large number of consumers spread
over a wide area. The following figure shows distribution transformer.
The length of LT lines is minimum, Further the AB cables are used for LT lines, as the
current ratings are low and as AB cable is cheaper than bare conductor at low current ratings.
Thus the failure of transformers due to UV line faults is eliminated. The loading of
transformer over and above its capacity will be effectively prevented by consumers
whom it serves, as its failure will affect their supply in HVDS.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 21
Theft of energy by direct tapping in agricultural and urban areas became a serious
problem. It is estimated that the number of direct tapping for pump sets is estimated to be as
high as 25% of total number of services connected. These unauthorized tapping are mainly
responsible for over loading of the system ant consequential failure by using LVDS.
The LT lines are virtually eliminated and even the short LT lines required will be AB
cable. This makes direct tapping of lines a very difficult task and the eliminating
unauthorized connections by using HVDS.
In LVDS, the long LV lines of small conductor size cause high line losses.
The international norm for energy loss in low voltage network is 1% to 2%. Thus the
energy loss of LV network of LVDS is 5 to 6 times the international norms. The HV line
is taken as near the load as possible and the LV service cable is used to feed loads. Thus
the LV networks are negligible in HVDS.
The voltage drop in LVDS system is very high as the lines are long and
conductor sizes are small. The voltage drop for distribution of same quantum of power is
less than 1% as against that in LVDS and this ensures proper voltage profiles at all
customer points.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 22
A study has been made by the CPDCL after implementing the HVDS
scheme in Nalgonda district. The study has resulted in the following benefits of HVDS
over LVDS.
The following details show the result of total benefits in the revenue form.
2907 25 72675
908 16 14528
Total 87023KVA
87.203MVA
Financial benefit due to avoiding the unauthorized Connections - Rs. 214.54 Lakhs
All the LT lines under Rainigudem sub-station A.D.Pally feeder of all 100KVA,63KVA
and 50KVA distribution transformers are replaced with high voltage distribution system
with a 185 numbers of 16KVA and 97 Nos, of 25KVA transformers are energized at the
load centers scattered all over the entire line.
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 26
The total energy input at the Raigiri feeder is 4, 72,000 units according to the energy
recordings.
HT LO SS IN RAIG IRI
FEEDER:
Total no of units drawn = (no. of 16KVA DTR's Avg. no. of units drawn) + (no. of
25KVA DTR's Avg. no. of units drawn)
= (185*1,290) + (97*1,815)
= 4, 14,705 units
= ((4,72,000 – 4,14,705)/4,72,000)*100
= 12.13%
L T L IN E L O S SE S IN R A IG IR I F E E D E R :
= 60,180 units
H IG H V O L T A G E D IST R IB U T IO N SY ST E M 28
= 3, 25,350 units
=3 , 85,530 units
= 4.15%
HIGH VOLTAGE DISTRIBUTION SYSTEM 29
COMPARISION OF LOSSES:
erected
erected
3 No. of days 30
6 Losses 16733.85
HVDS implemented
LVDS
losses