You are on page 1of 3

SYDN EY Arena

Wins
GOLD Medal
by Carl Yaeger

T
he world’s greatest athletes, dards for the building’s construc- construction and plays the key role
many of who spent a lifetime tion and operation. Accessibility in achieving the character envi-
preparing for the moment, considerations were paramount be- sioned by the designers. Steel’s ver-
gathered last fall in Sydney, Aus- cause the SuperDome was also satility has been demonstrated by
tralia for the Olympic Games. The used for international Paralympic the design of this unique structure.
Sydney Olympic Committee events for the disabled, which took Various simple and complex
wanted nothing less than a world- place only weeks after the arch structures and folded plate
class facility to serve as the stage Olympics ended. structures were investigated early
for this athletic and cultural specta- Construction of major projects on but discarded in favor of a truss
cle. also pose a unique challenge on the system. During the concept design
The result was the $200 million island continent, which has no a number of alternative truss sys-
Sydney SuperDome, built for the glass manufacturing capability and tems were examined, including a
games but destined to be a key ele- is home to only two construction fully trussed roof, a braced arch
ment of Sydney’s cultural fabric for cranes capable of handling such a roof and a roof with and without
decades to come. The grand arena, project. the stepped center hub. The alter-
seating 15,000 for gymnastics and The goal was to create a new natives included investigation of
18,000 for basketball, was designed benchmark in the design of acces- both wood and steel truss systems.
by an international consortium led sible and “green” public assembly The final design evolved in re-
by Devine deFlon Yaeger, a Kansas facilities. To meet that goal and de- sponse to the weight of the struc-
City based architectural and engi- liver the building on time and on ture, erection requirements and
neering firm. budget, the planners decided early environmental analysis.
The challenges were many and in the process to depend heavily on Devine deFlon Yaeger employed
varied. The Sydney Olympic Com- structural steel. Steel is the domi- sustainable design techniques
mittee set high environmental stan- nant material in the SuperDome’s throughout the project and per-

Modern Steel Construction / February 2001


formed in-depth analysis of se- that are tied back to the perimeter ted by ring action in a reinforced
lected building materials, looking columns. concrete plant room slab.
at the ecology rating of each. For In the center of the main roof is a The roof has strict acoustical re-
every decision, the questions asked raised section measuring 40 by quirements and was constructed
were: “Is it recyclable? Is it local? Is 70 m, which consists of trussed with a layering of elements. This
it transferable? Is it cost-efficient?” space frames about 5 m deep. consisted of a top metal deck, two
The goal was nothing less than to These frames consist mainly of 250 levels of purlins, insulation and
create the “greenest” arena facility and 310 universal column sections. plywood. In all, the weight of the
in the world. Radiating from the raised space roof system is 55 kg per sq. m.
The building boasts a self-con- frame in the center are 36 trusses at The main roof weight, including
tained system to maximize the use 20 m centers that span 30 m to the the masts, columns, cables and the
of recycled water. With this “gray” perimeter of the building. These 800 deep steel rakers, is 880 tons.
water system, roof runoff and hand trusses typically consist of 219 by This does not include the 25 km of
water are then used for toilets, etc. 6.4 CHS (G350) bottom chords and steel purlins in the roof. More than
The SuperDome also incorporates 250 UC 73 and 250 UC 89 top 26,000 sq. m of steel roof sheeting
the country’s grandest solar struc- chords. The top and bottom chords was used.
ture and energy-efficient lighting were bent to the radius. Between The outer “donut’’ section of the
system and largely used local labor the radiating trusses is a parallel roof was partially constructed in
and indigenous materials. beam (250 UB 25), which is sup- pie-shaped segments on the
One percent of total seating ca- ported on ring trusses spanning be- ground, which included the roof
pacity was designated for specta- tween the radiating trusses, sheeting system. These were then
tors with disabilities and their allowing for the purlin spacing to lifted into place on six temporary
companions. Patrons with disabili- be cut down to 10 m. towers. The infill sections beside
ties benefit from enhanced sight Around the perimeter of the roof these elements were then com-
lines and easy access to everything is a horizontal truss that distributes pleted in the air. The raised center
from concessions to telephones. the thrust from the radial trusses roof was placed in erected position.
Transmitter headphones are avail- into the bases of the columns. When all the framing elements
able for the hearing impaired. The These forces are generated by a were in position, including the ca-
most difficult accessibility issue is combination of arching action of bles, jacking down the outer cables
moving vertically with elevators, the roof and the horizontal compo- tensioned the structure. Finally, the
so more handicapped parking was nents of the restraining cable temporary towers were lowered,
allowed for on each garage level. forces. These forces are then resis- allowing the roof structure to take
But the SuperDome is more than all the dead loads.
just a functional triumph. It is a
stunning addition to the Sydney
skyline, with its distinctive
“crown” appearance created by 18
roof-support masts and their asso-
ciated cables projecting into the air
above the roofline.
During construction, managers
needed to carefully analyze and
monitor the erection sequence of
the roof, because the forces gener-
ated by the method of construction
can significantly affect the final de-
sign forces in the members.
The span of the main roof is 140
m by 100 m, with an area of 12,500
sq. m. There are 18 perimeter 600
by 400 steel box columns at about
20 m centers but this spacing in-
creases to 32 m around the corners
of the roof. The columns extend 12
m above the roof level, allowing
the roof to be supported by cables Exterior of Sydney SuperDome.

February 2001 / Modern Steel Construction


The structure has been designed
to support substantial rigging Owner/developer:
loads of up to 70 tons, in addition AbiGroup
to self weight, live and wind loads.
A 30-ton gondola is suspended Structural engineer:
from the center of the roof, sup- Taylor Thomson and Whiting
porting an array of large video Architect:
screens and scoreboards, giving the Devine deFlon Yaeger
operators great versatility for set-
ting up various show configura- Associate Architect:
tions. Cox Richardson
There is a wide veranda and Construction:
colonnade wrapped around the AbiGroup
building that, together with the ex-
tensive use of steel, echoes Aus- Environmental Consultant:
tralian vernacular traditions. The Manidis Roberts
elliptical dome over the building Software:
footprint is extended by the vary- AutoCAD; Spacegass for struc-
ing veranda depth, with a maxi- tural analysis.
mum of 30 m, giving added
interest to the façade.
The roof of the foyer structure
consists of triangular trusses, span-
ning up to 30 m, strutted off the
main concrete structure. Two plane
trusses were joined together to
form the triangular trusses.
The columns supporting the
foyer trusses are linked with the
colonnade columns into a triangu-
lar vertical truss. These vertical
trusses are extended into a tree
structure to support the edge of the
veranda roof. The façade system is
completed by horizontal trusses at
each floor level, which turn the ve-
randa colonnade into a large space
frame.
The result is a network of highly
inter-related lightweight members,
each serving several functions, pro-
ducing the appearance of a lacy
veil of fine steelwork. The web
wraps around the façade, creating
a spider-web effect from the inside.

Carl Yaeger, AIA, is a principal of


Kansas City, MO-based Devine deFlon
Yaeger, and served as the firm’s princi-
pal-in-charge on the Sydney Super-
Dome.

You might also like